WO2022119209A1 - 고로의 송풍 또는 재송풍 공정 및 이를 위한 고로 설비 - Google Patents

고로의 송풍 또는 재송풍 공정 및 이를 위한 고로 설비 Download PDF

Info

Publication number
WO2022119209A1
WO2022119209A1 PCT/KR2021/017217 KR2021017217W WO2022119209A1 WO 2022119209 A1 WO2022119209 A1 WO 2022119209A1 KR 2021017217 W KR2021017217 W KR 2021017217W WO 2022119209 A1 WO2022119209 A1 WO 2022119209A1
Authority
WO
WIPO (PCT)
Prior art keywords
blast furnace
gas
blowing
clean gas
clean
Prior art date
Application number
PCT/KR2021/017217
Other languages
English (en)
French (fr)
Inventor
안동일
박종성
김희원
조한진
김영현
자코부스반 라르 레이노드
이호영
Original Assignee
청원금속 주식회사
현대제철 주식회사
다니엘리 코루스 베뷔
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 청원금속 주식회사, 현대제철 주식회사, 다니엘리 코루스 베뷔 filed Critical 청원금속 주식회사
Publication of WO2022119209A1 publication Critical patent/WO2022119209A1/ko

Links

Images

Classifications

    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21BMANUFACTURE OF IRON OR STEEL
    • C21B7/00Blast furnaces
    • C21B7/007Controlling or regulating of the top pressure
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21BMANUFACTURE OF IRON OR STEEL
    • C21B7/00Blast furnaces
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21BMANUFACTURE OF IRON OR STEEL
    • C21B7/00Blast furnaces
    • C21B7/16Tuyéres
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21BMANUFACTURE OF IRON OR STEEL
    • C21B9/00Stoves for heating the blast in blast furnaces
    • C21B9/10Other details, e.g. blast mains
    • C21B9/12Hot-blast valves or slides for blast furnaces
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F27FURNACES; KILNS; OVENS; RETORTS
    • F27DDETAILS OR ACCESSORIES OF FURNACES, KILNS, OVENS, OR RETORTS, IN SO FAR AS THEY ARE OF KINDS OCCURRING IN MORE THAN ONE KIND OF FURNACE
    • F27D17/00Arrangements for using waste heat; Arrangements for using, or disposing of, waste gases
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F27FURNACES; KILNS; OVENS; RETORTS
    • F27DDETAILS OR ACCESSORIES OF FURNACES, KILNS, OVENS, OR RETORTS, IN SO FAR AS THEY ARE OF KINDS OCCURRING IN MORE THAN ONE KIND OF FURNACE
    • F27D17/00Arrangements for using waste heat; Arrangements for using, or disposing of, waste gases
    • F27D2017/009Cyclone for separating fines from gas

Definitions

  • the present invention relates to a blowing or re-blowing process for starting or restarting a blast furnace and a blast furnace facility therefor.
  • a blowing or re-blowing process for starting or restarting a blast furnace and a blast furnace facility therefor.
  • stop wind for the repair of the blast furnace
  • the breather valve is closed to blow the clean gas to the gas holder without discharging the blast furnace gas through the breather valve.
  • it relates to a re-blowing process and a blast furnace facility therefor.
  • the blast furnace may be shut down for intensive repair or maintenance in addition to the shutdown for regular maintenance, so-called reduction operation.
  • regular maintenance the furnace level (vertical height) of the charge in the blast furnace is maintained, but in the case of reducing maintenance, the charge in the blast furnace is lowered to the tuyere level.
  • the blast furnace and gas cleaning section should be purged to restart the blast furnace so that the composition of the mixed gas including the generated blast furnace gas is out of the explosive range.
  • the purged gas is discharged through the breather valve.
  • the air blown from the blast furnace blower is converted into hot air of 1200°C or higher through the hot stove and is fed into the blast furnace, and the blast furnace gas generated through the reaction inside the blast furnace is discharged through the breather valve.
  • the level of non-explosiveness that is, when the oxygen concentration in the gas cleaning facility/after gas pipe is ⁇ 1%.
  • the gas released through one or more breather valves during the blowing or re-blowing process of the blast furnace causes the emission of dust as well as harmful gas components.
  • Some blast furnaces use one or more additional breather valves, for example between subsequent stages of a gas cleaning plant or at the top of a downstream scrubber. These so-called semi-clean gas breather valves emit semi-clean gas with a low dust content, but the released gas is still polluted.
  • the patented invention removes dust from the top bleeder valve when the blast furnace plant is shut down, and collects harmful gases through clean BFG (blast furnace gas) piping. Gases containing oxygen are dust
  • BFG Blast Furnace Gas
  • the patented invention has a configuration in which harmful components are removed by burning with a fire stack while discharging the blast furnace gas to a breather valve during restart, but more equipment is required for burning, and there is a risk that harmful components may remain after burning.
  • the present invention is to solve the problems of the prior art, and it is an object of the present invention to blow or re-blow (restart) the blast furnace with little impact on the environment because there is no emission of blast furnace gas through the breather valve when the blast furnace is restarted after the shutdown. It is to provide a process and a blast furnace facility for the same.
  • a first aspect of the present invention is a blowing or re-blowing process of a blast furnace facility including a gas cleaning section for purifying a blast furnace and blast furnace gas,
  • a blowing or re-blowing process of a blast furnace in which clean gas is discharged through a clean gas vent line downstream of the gas cleaning section is provided.
  • a blowing or re-blowing process of a blast furnace is proposed, in which the blast furnace and gas cleaning equipment are purged with steam and nitrogen to generate a flow from the tuyere of the blast furnace to the clean gas vent line in a state in which the breather valve of the blast furnace is closed.
  • a blast furnace facility comprising a blast furnace having at least one breather valve, a gas cleaning section, and a clean gas transport line to a gas holder for additional transport of the clean gas,
  • the clean gas transport line to the gas holder is a clean gas discharge line that discharges the blast furnace gas purified in the gas cleaning section and residual air in the pipe with the breather valve closed before the blast furnace is restarted in the blowing or re-blowing process
  • a blast furnace facility comprising
  • the breather valve is closed before the blast furnace is restarted, the blast furnace gas in the blast furnace is purified through the gas cleaning section, and then the clean gas is discharged through a clean gas vent line. It has the effect of preventing the blast furnace gas containing dust and harmful components from being discharged to the outside through the breather valve.
  • FIG. 1 is a schematic configuration diagram of an embodiment of a blast furnace facility of the present invention.
  • a blowing or re-blowing process of a blast furnace including a blast furnace and a gas cleaning section for purifying gas from the blast furnace, the breather valve is closed, and nitrogen and steam are supplied to the blast furnace and the gas cleaning section purging to create a flow to the clean gas vent line provided downstream of the gas cleaning section for the air remaining in the uptake, downcomer, and clean gas delivery line of the blast furnace
  • the gas is purified to a clean gas state through the gas cleaning section and discharged to the clean gas vent line.
  • the clean gas shutoff valve is opened for the clean gas transported to the gas holder through the clean gas transport line, and the clean gas vent line is closed.
  • FIG. 1 is a schematic configuration diagram of an embodiment of a blast furnace facility of the present invention.
  • the blast furnace facility 1 of the present invention includes a blast furnace 2 and an off-gas system implemented as an uptake 3 on the upper portion of the blast furnace 2 .
  • the illustrated embodiment has a plurality of uptakes 3 schematically represented by one line in the figure, but blast furnaces without uptakes or having only one uptake may also be used. Most modern blast furnaces include a configuration in which multiple uptakes engage each other at their upper ends.
  • uptake (3) is a breather valve (4).
  • Most blast furnaces have multiple breather valves on a breather platform above the junction of multiple uptakes.
  • a downcomer 5 carries the blast furnace gas from the top of the uptake 3 to the gas cleaning section 6 .
  • the gas cleaning section 6 may have any suitable arrangement of dust removal systems, but typically includes a gravity or cyclone dust catcher 7 followed by usually a wet scrubber 8 or bag filter station or electrostatic precipitator goes on
  • a cone capable of regulating the upper pressure and the rear end pressure of the blast furnace is installed inside the scrubber 8, and the opening rate is managed to contribute to the stable operation of the facility from fluctuations in the blast furnace gas pressure.
  • the blast furnace plant also generally has a demister 9 downstream of the gas cleaning section 6 for separating the scrubber liquid. All gas cleaning equipment 7, 8 and demister 9 may have associated purging gas supplies, for example at locations 7A, 8A, 9A.
  • the embodiment of the blast furnace facility of the present invention further includes a clean gas vent line 11 for generating a flow of clean gas from the gas cleaning section 6 of the blast furnace gas when the blast furnace is operated or restarted.
  • a clean gas delivery line 10 carries the clean gas from the gas clean section 6 to, for example, a gas holder 27 .
  • the clean gas vent line 11 is branched from the clean gas delivery line 10 .
  • the clean gas vent line 11 may be closed by the discharge valve 12 .
  • a clean gas shutoff valve (13) is located downstream of the clean gas vent line (11).
  • the blast furnace 2 On the inlet side, the blast furnace 2 includes tuyeres 14 that form a hot air inlet to the blast furnace.
  • the tuyeres 14 are generally uniformly distributed around the circumference of the blast furnace through a bustle main.
  • a blower 15 blows compressed air through a supply line, the supply line being a first branch 16A having a hot stove 17 for heating the air at a predetermined distance downstream of the blower 15 and this hot air It is divided into a second branch 16B having no rows.
  • Each of the stoves 17 includes its own valve 19 .
  • the two branches 16A, 16B are coupled together at a downstream point to form a blast mixing circuit.
  • the valves 18 , 19 can be used to meter and mix the flows of the two branches 16A, 16B to create a blast of a desired temperature entering the blast furnace 2 at a given hot air pressure.
  • additional oxygen and/or moisture and/or fuels such as pulverized coal, natural gas, hydrogen or oil and/or other components may be added to the hot air air.
  • the supplied air flows through the line 20 to the tuyeres 14 of the blast furnace 2 .
  • the line 20 may have a backdraft stack 21 that is closable by a valve 22 . Opening the valve 22 facilitates the evacuation of the gaseous product from the blast furnace 2 after shutdown.
  • the blast furnace plant 1 may not have such a backdraft stack 21 .
  • Some blast furnace facilities may have a hot air main isolation valve immediately upstream of the bustle main of the tuyeres 14 or immediately upstream of the backdraft stack 21 when the backdraft stack 21 is present.
  • it may include a nitrogen supply line 23 for purging nitrogen, etc. in the hot air mixed into the tuyere 14.
  • the blast furnace 2 includes purging gas supply units 24 and 26 .
  • Typical purging gases are nitrogen and/or steam.
  • Hot air air at about 1200° C. is optionally supplied to the blast furnace 2 via tuyeres 14 along with additional oxygen and/or moisture and/or fuel such as pulverized coal, natural gas, hydrogen or oil.
  • the hot air gasifies the coke and injected fuel, and heats, reduces and melts the iron load to form liquid hot metal, slag and blast furnace gas.
  • the pressure in the blast furnace is typically about 2-5 bar.
  • the blast furnace gas is collected in the uptake section (3) and conveyed through the downcomer (5) to the gas cleaning section (6), where most of the dust content is removed and the pressure is reduced to the pressure of the gas holder (27), typically about approx. reduced to 40-100 mbar.
  • the clean gas is conveyed to the gas holder (27) through the clean gas delivery line (10).
  • the collected clean gas can be used as fuel for heating, such as for the production of steam furnaces 28 or steam.
  • the nitrogen supply line 23 does not exist in the configuration of the hot air supply lines 16A and 16B.
  • the clean gas vent line 11 has an ejector 30 to increase the pressure drop and promote flow by suction.
  • the clean gas vent line 11 is divided into a first branch 11A without an ejector 30 and a second branch 11B with an ejector 30 . Downstream of the ejector 30 , the two lines 11A, 11B are again combined as a single exhaust port.
  • the discharge valves 12 and 32 are used to close one of the lines after opening the other, so the clean gas vent line 11 can be selectively used with or without the ejector 30 . have.
  • the ejector 30 is connected to a supply 33 of an inert power gas such as steam or nitrogen.
  • the purging gas supply units 24 and 26 for the blast furnace 2 are open. Then, the valve 12 of the clean gas vent line 11A bypassing the ejector 30 is opened, and the clean gas shutoff valve 13 of the clean gas delivery line 10 to the gas holder 27 is closed. . In the next step, the ejector 30 is opened while the clean gas vent line 11A bypassing the ejector 30 is closed. The pressure in the system is controlled by the suction generated by the ejector 30 . After a set period, the breather valves 4 above the uptakes 3 are opened, and then the ejector 30 and the clean gas vent line 11 are closed.
  • the breather valves 4 and 25 are opened from after shutdown of the blast furnace 2 to before restarting.
  • the valves of the purge supply unit 24 and 26 at the top of the blast furnace and the valves of the purge supply unit of the gas cleaning section 6 are opened to discharge the air in the pipe through the breather valve 4 to release the air in the pipe. make it not This is to eliminate the risk of explosion due to the gas generated in the blast furnace and oxygen in the air that may remain in the pipe after restarting.
  • the semi-clean gas breather valve 25 is closed and the breather valve 4 is opened, and the hot stove valve is opened to start the operation again.
  • the clean gas shutoff valve 13 is opened to transfer the blast furnace gas to the gas holder 27 . While the clean gas shutoff valve 13 is opened, the breather valve 4 is closed.
  • the blast furnace gas is discharged to the outside through the breather valve (4) without going through the gas cleaning section (6) until the breather valve (4) is closed. Therefore, in the process of restarting the blast furnace, the blast furnace gas is discharged to the atmosphere through the breather valve (4).
  • An embodiment of the blowing or re-blowing process of the blast furnace of the present invention will be described.
  • An embodiment of the present invention is characterized in that the blast furnace gas generated during operation or restart of the blast furnace contains dust and harmful components and is not discharged to the outside through the breather valve.
  • a configuration is proposed in which the breather valves 4 and 25 are closed before the re-operation of the blast furnace and the blast furnace gas is discharged as clean gas after passing through the gas cleaning section 6 after the re-operation.
  • steam and nitrogen are purged in the blast furnace 2 and the gas cleaning section 6 with the breather valves 4 and 25 closed to uptake (3) and a process of generating a flow of air in the downcomer 5 and the clean gas delivery line 10 to the clean gas vent line 11 .
  • Oxygen measurement is carried out in the clean gas delivery line 10 after the demister 9, but when the breather valves 4 and 25 are open, the pressure is low, so it is difficult to measure oxygen.
  • the pressure increase inside the clean gas delivery line 10 can be achieved by adjusting the gas flow passage inside the scrubber 8, alternatively by first closing the breather valve 25 and secondarily by closing the breather valve 4 A gradual closure is also possible.
  • breather valves 4 and 25 When the breather valves 4 and 25 are closed, pressure fluctuations caused by blast furnace gas generated inside the blast furnace or steam purge at the top of the blast furnace may occur, so that the gas inside the blast furnace may flow back to the tuyere 14 . In order to prevent this, it can be improved by opening the valve 23 before closing the breather valves 4 and 25 and injecting nitrogen.
  • the blast furnace After closing the breather valves (4) and (25) and confirming that the nitrogen and steam being purged in the upper part of the blast furnace (2) and the gas cleaning section (6) flow into the clean gas vent line (11), the blast furnace can be restarted. do.
  • the valve 23 After opening the hot blast furnace valve 19 to introduce hot air into the blast furnace, the valve 23 may be closed to stop nitrogen injected into the blast furnace tuyere.
  • the blast furnace gas generated by operation or re-operation of the blast furnace becomes a clean gas state through the gas cleaning section 6 , and the clean gas is discharged to the clean gas vent line 11 .
  • the oxygen component is measured in the clean gas transport line 10 to prevent explosion, and when the concentration is checked within 1%, the standard for mixed gas is sufficient.
  • the clean gas shutoff valve 13 may be opened when the pressure of the clean gas transport line 10 becomes at a level similar to that of the gas holder 27 .
  • the hot air entering the tuyere 14 is increased stepwise by the blowing amount or blowing pressure. In general, a capacity of 2000 to 2500 Nm3 / min will be sufficient. This is different for each content volume of each blast furnace.
  • the clean gas shutoff valve 13 When the conditions for transfer to the gas holder 27 are satisfied, the clean gas shutoff valve 13 is opened to guide the flow of clean gas to the gas holder 27, and the discharge valve 12 of the clean gas vent line 11 is blocked. Induce gas flow to normal operating conditions.
  • the present invention can be used in industries that prevent air pollution caused by blast furnaces, such as the iron making industry.

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Manufacturing & Machinery (AREA)
  • Materials Engineering (AREA)
  • Metallurgy (AREA)
  • Organic Chemistry (AREA)
  • Environmental & Geological Engineering (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Waste-Gas Treatment And Other Accessory Devices For Furnaces (AREA)
  • Blast Furnaces (AREA)

Abstract

본 발명은 고로의 송풍 또는 재송풍 공정 및 이를 위한 고로설비에 관한 것이다. 본 발명에서는, 고로 및 고로로부터 가스를 정화하기 위한 가스청정섹션을 포함하는 고로의 송풍 또는 재송풍 공정으로서, 브리더밸브를 폐쇄하고, 고로 및 가스청정섹션에 질소 및 스팀을 퍼지하여 고로의 업테이크, 다운코머, 청정가스운반라인에 잔존하는 공기에 대해서 상기 가스청정섹션의 하류에 구비된 청정가스벤트라인으로의 흐름을 생성하고, 고로의 가동 또는 재가동으로 발생하는 고로가스는 가스청정섹션을 거쳐 청정가스 상태로 정화되어 상기 청정가스벤트라인으로 배출되도록 하고, 청정가스가 청정가스벤트라인으로 배출되면서 청정가스운반라인의 압력이 가스홀더의 압력을 초과하는 경우, 상기 청정가스차단밸브는 상기 청정가스운반라인을 통해 상기 가스홀더로 운반되는 청정가스에 대해 개방되고, 상기 청정가스벤트라인은 폐쇄되는 것을 특징으로 하는 고로의 송풍 또는 재송풍 공정 및 이를 위한 고로설비가 제시된다.

Description

고로의 송풍 또는 재송풍 공정 및 이를 위한 고로 설비
본 발명은 고로의 가동 또는 재가동을 위한 송풍 또는 재송풍 공정 및 이를 위한 고로 설비에 관한 것이다. 더 상세하게는 고로의 가동을 위한 송풍 공정 및 고로의 보수를 위한 조업정지(휴풍)를 통해 보수가 완료된 후 고로의 재가동시에 먼지의 방출이 없고 환경에 미치는 영향이 적은 고로의 재송풍(재가동)공정을 제공하는 것으로, 고로, 열풍로, 가스청정설비를 포함하는 고로설비에 열풍을 재공급하기 전 브리더밸브를 폐쇄하여 브리더밸브를 통한 고로가스의 배출없이 청정가스를 가스홀더로 보내는 고로의 송풍 또는 재송풍 공정 및 이를 위한 고로 설비에 관한 것이다.
고로는 정기적인 보수를 위한 조업정지(휴풍)외에도 고로의 집중적인 수리 또는 유지보수를 위해 소위 감척조업으로 휴풍을 진행할 수 있다. 정기보수시에는 고로내 장입물의 노내 레벨(수직높이)이 유지되나 감척보수시에는 고로내 장입물을 풍구레벨까지 낮춘다.
보수가 완료된 후 고로 재가동을 위해 고로 및 가스청정섹션내 퍼지를 실시하여 발생된 고로가스를 포함한 혼합가스의 조성이 폭발범위 밖으로 되도록 하여야 한다. 이때 퍼지된 가스는 브리더밸브를 통하여 배출되게 된다. 고로 블로어로부터 송풍된 공기는 열풍로를 통해 1200℃ 이상의 열풍으로 변환되어 고로로 투입되며 고로 내부에서 반응을 통해 발생된 고로가스는 브리더밸브를 통해 배출된다.
이후 고로가스가 가스홀더로 이송되기 위해, 고로가스가 가스청정섹션내 가스와 혼합가스를 형성하였을 때 폭발성이 없는 수준, 즉 가스청정설비/후단가스배관내 산소농도가 ≤1%가 되었을 때 또한 후단가스배관 압력이 가스홀더와 동일한 압력이 되었을 때 후단가스배관과 가스홀더를 차단하고 있던 클린가스차단밸브(또는 수봉변)의 개방을 실시하며 그 후 브리더밸브를 폐쇄하게 된다.
고로의 송풍 또는 재송풍 공정중 하나 이상의 브리더밸브를 통해 방출되는 가스는 유해가스 성분뿐만 아니라 분진 방출을 유발한다. 일부 고로에서는, 예를 들어 가스청정설비중 후속단계 사이 또는 다운스트림 스크러버의 상단부에서 하나 이상의 추가 브리더밸브를 이용하기도 한다. 이러한 소위 반청정가스 브리더밸브는 먼지함량이 낮은 반청정가스를 방출하지만 방출된 가스는 여전히 오염상태이다.
고로의 휴풍 및 재가동시 방출되는 가스의 오염을 저감시키기 위한 발명으로, 대한민국 특허번호 제10-2037032호(등록일: 2019년10월21일)의 고로공장의 탑블리더밸브 공해방지 및 저감을 위한 가스 처리장치 및 방법의 발명이 공개되어 있다.
상기 특허발명은, 고로공장 휴지시에는 탑블리더밸브로부터 발생하는 먼지(Dust)는 제거하고 유해한 가스는 청정 BFG(고로가스) 배관으로 회수하고, 고로공장 재가동시에는 탑블리더밸브로 방출되는 다소의 산소가 함유된 가스는 먼지
(Dust)를 제거하고 BFG(고로가스)는 대기로 일부 방출 또는 화이어 스택(Fire Stack)에서 태워 인체에 해로운 요소를 제거하는 구성의 발명이다.
상기 특허발명은 재가동시에 고로가스를 브리더밸브로 배출하면서 화이어스택으로 태워 유해성분을 제거하는 구성이나, 태우기 위한 설비가 더 필요하고 태운 후에도 유해성분이 잔존할 우려가 있다.
따라서, 고로의 재가동시에 브리더밸브를 통한 고로가스의 방출이 없어 환경에 미치는 영향이 적은 고로의 송풍 또는 재송풍(재가동)공정 및 이를 위한 고로 설비에 관한 발명이 요망된다.
본 발명은 상기 종래기술의 문제점을 해결하기 위한 것으로서, 본 발명의 목적은 고로의 휴풍 후 재가동시에 브리더밸브를 통한 고로가스의 방출이 없어 환경에 미치는 영향이 적은 고로의 송풍 또는 재송풍(재가동)공정 및 이를 위한 고로 설비를 제공함에 있다.
본 발명의 목적을 달성하기 위한 기술적 해결 수단으로, 본 발명의 제1 관점은, 고로 및 고로가스를 정화하기 위한 가스청정섹션을 포함하는 고로설비의 송풍 또는 재송풍 공정으로서,
청정가스가 상기 가스청정섹션의 하류에서 청정가스벤트라인을 통해 배출되는 고로의 송풍 또는 재송풍 공정이 제시된다.
또한, 본 발명의 제2 관점으로, 고로 및 고로가스를 정화하기 위한 가스청정섹션을 포함하는 고로의 송풍 또는 재송풍 공정으로서,
상기 고로의 브리더밸브를 폐쇄한 상태에서, 고로 및 가스청정설비에 스팀 및 질소 등을 퍼지하여 고로의 풍구에서 상기 청정가스벤트라인으로의 흐름을 생성하는 고로의 송풍 또는 재송풍 공정이 제시된다.
또한, 본 발명의 제3 관점으로, 적어도 하나의 브리더밸브를 구비한 고로, 가스청정섹션, 및 청정된 가스의 추가적인 운반을 위한 가스홀더로의 청정가스운반라인을 포함하는 고로 설비로서,
상기 가스홀더로의 상기 청정가스운반라인은 송풍 또는 재송풍 공정에서 고로의 재가동 전 상기 브리더밸브를 폐쇄한 상태에서 상기 가스청정섹션에서 정화된 고로가스와 배관내의 잔존 공기를 배출하는 청정가스배출라인을 포함하는 고로 설비가 제시된다.
본 발명에 의하면, 고로의 재가동 전에 브리더밸브를 폐쇄하고 고로내의 고로가스를 가스청정섹션을 거쳐 정화시킨 후 그 청정가스를 청정가스벤트라인을 통해 배출하게 함으로써, 고로의 재가동시에 발생되는 고로가스 중의 더스트 및 유해성분이 포함된 고로가스가 브리더밸브를 통해 외부로 배출되는 것을 방지할 수 있는 효과가 있다.
도 1은 본 발명의 고로설비의 실시예에 관한 개략적인 구성도이다.
본 발명의 실시를 위한 최선의 형태로서, 고로 및 고로로부터 가스를 정화하기 위한 가스청정섹션을 포함하는 고로의 송풍 또는 재송풍 공정으로서, 브리더밸브를 폐쇄하고, 고로 및 가스청정섹션에 질소 및 스팀을 퍼지하여 고로의 업테이크, 다운코머, 청정가스운반라인에 잔존하는 공기에 대해서 상기 가스청정섹션의 하류에 구비된 청정가스벤트라인으로의 흐름을 생성하고, 고로의 가동 또는 재가동으로 발생하는 고로가스는 가스청정섹션을 거쳐 청정가스 상태로 정화되어 상기 청정가스벤트라인으로 배출되도록 하고, 청정가스가 청정가스벤트라인으로 배출되면서 청정가스운반라인의 압력이 가스홀더의 압력을 초과하는 경우, 상기 청정가스차단밸브는 상기 청정가스운반라인을 통해 상기 가스홀더로 운반되는 청정가스에 대해 개방되고, 상기 청정가스벤트라인은 폐쇄되는 것을 특징으로 하는 고로의 송풍 또는 재송풍 공정 및 이를 위한 고로설비가 제시된다.
이하에서 본 발명의 실시예를 첨부한 도면을 참조하면서 상세히 설명하기로 한다. 이하의 본 발명의 실시예들에 관한 설명, 설명에 사용된 용어 및 표현 등은 본 발명의 범위를 한정하지 않는다.
도 1은 본 발명의 고로설비의 실시예에 관한 개략적인 구성도이다.
도 1에 도시한 바와 같이 본 발명의 고로설비(1)는, 고로(2) 및 고로(2)의 상부에 업테이크(uptake)(3)로서 구현되는 오프-가스 시스템을 포함한다. 도시된 실시예는 도면에 하나의 라인으로 개략적으로 표현된 다수의 업테이크(3)를 갖지만, 업테이크를 갖지 않거나 하나의 업테이크만을 갖는 고로들도 사용될 수 있다. 현대의 고로들은 대부분 다수의 업테이크가 그들의 상단부들에서 서로 결합하는 구성을 포함한다.
업테이크(3)의 상부에는 브리더밸브(4)가 있다. 대부분의 고로들은 다수의 업테이크의 접합부 위의 브리더 플랫폼 상에 다수의 브리더밸브를 갖는다.
다운코머(downcomer)(5)가 업테이크(3)의 상부로부터 가스청정섹션(6)으로 고로가스를 운반한다. 가스청정섹션(6)은 임의의 적절한 배열의 먼지 제거 시스템들을 가질 수 있지만, 통상적으로 중력 또는 사이클론 더스트 캐처(7)를 포함하고, 그 뒤에 는 보통 습식 스크러버(8) 또는 백필터스테이션 또는 정전기 집진기가 이어진다.
상기 스크러버(8) 내부에는 고로 상부 압력 및 후단부 압력조절이 가능한 콘이 설치되어 있으며 개방율을 관리하여 고로가스 압력변동으로부터 설비의 안정적 운영에 기여할 수 있도록 한 구성이다.
습식 스크러버가 사용되는 경우, 고로 설비는 일반적으로 스크러버 액체를 분리하기 위해 가스청정섹션(6)의 하류에 디미스터(Demister)(9)를 또한 구비한다. 모든 가스청정장비(7, 8) 및 디미스터(9)는 관련된 퍼징가스공급부들을 예를 들어 위치들(7A, 8A, 9A)에 가질 수 있다.
본 발명의 고로설비의 실시예는 고로의 가동 또는 재가동시 고로가스의 가스청정섹션(6)으로부터 청정가스의 흐름을 생성하는 청정가스벤트라인(11)을 더 포함한다.
청정가스운반라인(10)이 가스청정섹션(6)으로부터 예를 들어 가스홀더(27)로 청정가스를 운반한다. 상기 청정가스벤트라인(11)이 청정가스운반라인(10)으로부터 분기된다. 청정가스밴트라인(11)은 배출밸브(12)에 의해 폐쇄될 수 있다. 청정가스차단밸브(13)가 청정가스벤트라인(11)의 하류에 위치된다.
입구 측에서, 고로(2)는 고로에의 열풍 입구를 형성하는 송풍구들(14)을 포함한다. 송풍구들(14)은 일반적으로 버슬 메인(bustle main)을 통해 고로의 원주 주위에 균일하게 분포된다.
블로어(15)가 공급라인을 통해 압축된 공기를 송풍하며, 공급라인은 블로어(15)의 하류의 소정 거리에서 공기를 가열하기 위한 열풍로(17)를 갖는 제1 분기(16A) 및 이러한 열풍로들을 갖지 않는 제2 분기(16B)로 분할된다. 열풍로(17) 각각은 그 자신의 밸브(19)를 포함한다. 2개의 분기(16A, 16B)는 블라스트 혼합 회로를 형성하기 위해 하류 지점에서 서로 결합된다. 밸브들(18, 19)은 2개의 분기(16A, 16B)의 흐름을 계량하고 혼합하여 주어진 열풍 압력으로 고로(2)에 들어가는 원하는 온도의 블라스트를 생성하는 데 사용될 수 있다. 원하는 경우, 추가적인 산소 및/또는 수분 및/또는 미분탄, 천연 가스, 수소 또는 오일과 같은 연료들 및/또는 다른 성분들이 열풍 공기에 추가될 수 있다.
공급된 공기는 라인(20)을 통해 고로(2)의 송풍구들(14)로 흐른다. 도시된 실시예에서, 상기 라인(20)은 밸브(22)에 의해 폐쇄 가능한 백드래프트스택(21)을 구비할 수 있다. 상기 밸브(22)를 개방하는 것은 셧다운 후에 고로(2)로부터의 가스 생성물의 배출을 용이하게 한다. 대안으로서, 고로 설비(1)는 이러한 백드래프트스택(21)을 갖지 않을 수 있다.
일부 고로 설비들은 송풍구들(14)의 버슬 메인의 바로 상류에 또는 백드래프트스택(21)이 존재하는 경우에는 백드래프트스택(21)의 바로 상류에 열풍 메인격리밸브를 가질 수 있다.
또한, 송풍구(14)로 혼입되는 열풍에 질소 등을 퍼지하기 위한 질소공급라인(23)을 포함할 수 있다.
고로(2)는 퍼징가스공급부들(24)(26)을 구비한다. 통상적인 퍼징가스들은 질소 및/또는 증기이다.
습식 스크러버(8)의 상부에는 반청정가스 브리더밸브(25)로의 라인이 있다.
고로설비(1)의 정상 동작 동안, 철 적하물(광석) 및 코크가 고로(2)의 상부 섹션까지 개별 층들에 적하된다. 약 1200℃의 열풍 공기가 옵션으로서 추가적인 산소 및/또는 수분 및/또는 미분탄, 천연 가스, 수소 또는 오일과 같은 연료와 함께 송풍구들(14)을 통해 고로(2)에 공급된다. 열풍은 코크 및 주입된 연료를 가스화하고, 철 적하물을 가열, 환원 및 용융시켜 액체 고온 금속, 슬래그 및 고로가스를 형성한다. 정상 동작 동안, 고로 내의 압력은 통상적으로 약 2-5 bar이다. 고로가스는 업테이크 섹션(3)에 수집되고 다운코머(5)를 통해 가스청정섹션(6)으로 운반되며, 여기서 대부분의 먼지 함량이 제거되고 압력이 가스홀더(27)의 압력, 통상적으로 약 40-100 mbar로 감소된다. 가스청정섹션(6)을 통과한 후, 청정가스는 청정가스운반라인(10)을 통해 가스홀더(27)로 운반된다. 수집된 청정가스는 가열을 위한, 예컨대 열풍로(28)들 또는 증기의 생성을 위한 연료로서 사용될 수 있다.
본 발명의 고로설비의 다른 실시예로서, 열풍공급라인(16A, 16B)의 구성에는 질소공급라인(23)이 존재하지 않는다. 대신에, 청정가스벤트라인(11)은 압력 강하를 증가시키고 흡입에 의해 흐름을 촉진하기 위한 이젝터(30)를 구비한다. 청정가스벤트라인(11)은 이젝터(30)가 없는 제1 분기(11A) 및 이젝터(30)가 있는 제2 분기(11B)로 분할된다. 이젝터(30)의 하류에서, 2개의 라인(11A, 11B)은 단일 배기구로서 다시 결합된다. 배출밸브들(12, 32)은 라인들 중 하나를 개방한 후에 다른 하나의 라인을 폐쇄하기 위해 사용되며, 따라서 청정가스벤트라인(11)은 이젝터(30)와 함께 또는 이젝터 없이 선택적으로 사용될 수 있다. 이젝터(30)는 증기 또는 질소와 같은 불활성 동력 가스의 공급부(33)에 연결된다.
고로(2)를 위한 퍼징가스공급부들(24)(26)이 개방된다. 그 다음, 이젝터(30)를 우회하는 청정가스벤트라인(11A)의 밸브(12)가 개방되고, 가스홀더(27)로의 청정가스운반라인(10)의 청정가스차단밸브(13)가 폐쇄된다. 다음 단계에서, 이젝터(30)가 개방되는 반면, 이젝터(30)를 우회하는 청정가스벤트라인(11A)이 폐쇄된다. 시스템 내의 압력은 이젝터(30)에 의해 생성되는 흡입에 의해 제어된다. 설정 기간 후에, 업테이크들(3) 상부의 브리더밸브들(4)이 개방되고, 이어서 이젝터(30) 및 청정가스벤트라인(11)이 폐쇄된다.
종래의 고로의 재가동 공정에서는, 고로(2)의 셧 다운 이후부터 재가동 전까지 브리더밸브(4, 25)는 개방되어 있다. 고로의 재가동 전에 고로 상부의 퍼지공급부(24)(26)의 밸브와 가스청정섹션(6)의 퍼지공급부의 밸브들을 개방하여 배관 내부에 있는 공기를 브리더밸브(4)를 통해 배출하여 배관 내 공기가 없게 한다. 이는 재가동 후 고로에서 발생하는 가스와 배관 내에 잔존할 수 있는 공기 중 산소에 의한 폭발 발생의 위험성을 제거하기 위함이다.
고로 재가동 전에 반청정가스 브리더밸브(25)는 닫고 브리더밸브(4)는 개방된 상태에서 열풍로밸브를 개방하여 재가동을 시작한다. 고로 재가동 후 청정가스운반라인(10) 내부 산소 성분을 측정하여 1% 이내가 되면 청정가스차단밸브(13)를 개방하여 고로가스를 가스홀더(27)로 이송하게 된다. 청정가스차단밸브(13)를 개방하면서 브리더 밸브(4)는 폐쇄시킨다. 재가동 이후 브리더밸브(4)를 닫기 전까지 고로가스는 가스청정섹션(6)을 거치지 않고 브리더밸브(4)를 통해 외부로 배출된다. 따라서 고로의 재가동 공정에서 고로가스가 브리더밸브(4)를 통하여 대기중으로 배출된다.
본 발명의 고로의 송풍 또는 재송풍 공정의 실시예를 설명하기로 한다. 본 발명의 실시예는 고로의 가동 또는 재가동시 발생되는 고로가스 중에 더스트 및 유해성분이 포함된 상태로 브리더밸브를 통해 외부로 배출되지 않게 하는 것에 특징이 있다. 이를 위하여 고로의 재가동 전에 브리더밸브(4)(25)를 폐쇄하고 재가동 이후에는 고로가스가 가스청정섹션(6)을 거친 이후 청정가스로 배출되도록 하는 구성이 제시된다.
본 발명의 고로의 가동 또는 재가동 공정의 실시예에서는 브리더밸브(4)(25)를 폐쇄한 상태에서 고로(2) 및 가스청정섹션(6)에 스팀 및 질소 등을 퍼지하여 업테이크(3) 및 다운코머(5), 청정가스운반라인(10)에 있는 공기를 청정가스벤트라인(11)으로의 흐름을 생성하는 공정을 포함한다.
고로(2)가 가동 또는 재가동하기 전에도 고로 내부에 있는 철광석과 코크스가 반응하여 고로가스가 발생하게 되는데 브리더밸브(4)를 폐쇄하고 청정가스벤트라인(11)으로 흐름을 바꾸는 경우 가스청정섹션(6) 및 청정가스운반라인(10)에 잔류하는 산소와의 혼합가스를 만들어 폭발할 수 있는 위험성이 있다. 따라서 브리더밸브(4)의 폐쇄 전에 청정가스운반라인(10) 내부의 산소 농도는 폭발점 미만으로, 2% 보다 작게 관리한다.
산소 측정은 디미스터(9) 이후의 청정가스운반라인(10)에서 실시하게 되는데 브리더밸브(4)(25)가 개방된 상태에서는 압력이 낮아 산소측정이 어렵다. 청정가스운반라인(10) 내부의 압력 증대는 스크러버(8) 내부에 가스 흐름 통로를 조정함으로써 달성할 수 있으며, 대안으로는 1차로 브리더밸브(25)를 닫고, 2차로 브리더밸브(4)를 단계적으로 폐쇄하는 방안도 가능하다.
브리더밸브(4)(25)를 폐쇄할 때 고로 내부에서 발생되는 고로가스 또는 고로 상부 스팀퍼지 등에 의한 압력 변동이 발생하여 고로 내부 가스가 송풍구(14)로 역류할 수 있다. 이를 방지하기 위하여 브리더 밸브(4)(25)를 폐쇄하기 전에 밸브(23)를 개방하여 질소를 주입함으로써 이를 통하여 개선할 수 있다.
브리더밸브(4)(25)를 폐쇄하고 고로(2) 상부 및 가스청정섹션(6)에 퍼지되고 있는 질소와 스팀이 청정가스벤트라인(11)으로 흐름이 형성된 것을 확인한 이후에 고로 재가동이 가능하다. 열풍로 밸브(19)를 개방하여 고로에 열풍을 넣어준 이후 밸브(23)를 닫아 고로 송풍구로 주입되는 질소는 중지 할 수 있다.
고로 가동 또는 재가동으로 발생되는 고로가스는 가스청정섹션(6)을 거쳐 청정가스 상태가 되고, 상기 청정가스는 청정가스벤트라인(11)으로 배출되게 된다.
청정가스를 가스홀더(27)로 이송 시 폭발 방지를 위하여 청정가스운반라인(10)에서 산소 성분을 측정하여 1% 이내 농도 확인 시 혼합가스로의 기준은 충분하다.
가스홀더(27)로 청정가스를 이송하기 위하여 청정가스운반라인(10)의 압력이 가스홀더(27)와 유사한 수준이 될 때 청정가스차단밸브(13)를 개방할 수 있다. 청정가스운반라인(10)의 압력을 높여주기 위하여 송풍구(14)로 들어가는 열풍을 송풍량 또는 송풍압으로 단계적으로 증대하게 되는데 일반적으로 2000~2500 Nm3 / min의 용량이면 충분할 것이다. 이는 각 고로의 내용적마다 상이하다.
가스홀더(27)로의 이송 조건이 만족할 경우 청정가스차단밸브(13)를 개방하여 청정가스의 흐름을 가스홀더(27)로 유도하며 청정가스벤트라인(11)의 배출밸브(12)를 차단하여 정상조업 상태로 가스흐름을 유도한다.
이상에서 설명한 본 발명의 실시예는 본 발명의 다양한 실시예 중 일부에 불과하다, 본 발명의 고로의 송풍 또는 재송풍 공정에서 고로가스에 대해서 브리더밸브를 폐쇄시키고, 가스청정섹션에서 청정가스벤트라인으로의 흐름을 생성시키는 기술적사상에 포함되는 다양한 실시예가 본 발명의 보호범위에 포함되는 것은 당연하다.
본 발명은 제철 산업 등의 고로로 인해 발생되는 대기 오염을 방지하는 산업에 이용할 수 있다.

Claims (15)

  1. 고로 및 고로로부터 가스를 정화하기 위한 가스청정섹션을 포함하는 고로의 송풍 또는 재송풍 공정으로서,
    청정가스가 상기 가스청정섹션의 하류에서 청정가스벤트라인을 통해 대기로 배출되는 고로의 송풍 또는 재송풍 공정.
  2. 고로 및 고로로부터 가스를 정화하기 위한 가스청정섹션을 포함하는 고로의 송풍 또는 재송풍 공정으로서,
    상기 가스청정섹션으로부터 청정가스벤트라인으로의 흐름을 생성시키는 고로의 송풍 또는 재송풍 공정.
  3. 고로 및 고로로부터 가스를 정화하기 위한 가스청정섹션을 포함하는 고로의 송풍 또는 재송풍 공정으로서,
    상기 고로 및 가스청정설비에 스팀 및 질소 등을 퍼지하여 고로 또는 고로 송풍구에서 청정가스벤트라인으로의 흐름을 생성하는 고로의 송풍 또는 재송풍 공정.
  4. 청구항 1 내지 청구항 3 중 어느 한 항에 있어서,
    상기 고로의 브리더밸브들은 폐쇄된 상태인 것을 특징으로 하는 고로의 송풍 또는 재송풍 공정.
  5. 고로 및 고로로부터 가스를 정화하기 위한 가스청정섹션을 포함하는 고로의 송풍 또는 재송풍 공정으로서,
    브리더밸브를 폐쇄하고, 고로 및 가스청정섹션에 질소 및 스팀을 퍼지하여 고로의 업테이크, 다운코머, 청정가스운반라인에 잔존하는 공기를 제거하기 위해서 상기 가스청정섹션의 하류에 구비된 청정가스벤트라인으로의 흐름을 생성하는 고로의 송풍 또는 재송풍 공정.
  6. 청구항 5에 있어서,
    상기 브리더밸브들을 폐쇄하기 전 상기 청정가스운반라인의 내부 산소 농도는 2% 보다 낮게 유지하는 것을 특징으로 하는 고로의 송풍 또는 재송풍 공정.
  7. 청구항 6에 있어서,
    상기 청정가스운반라인 내부의 산소 측정을 위해, 상기 청정가스운반라인의 내부 압력을 증가시키는 것을 특징으로 하는 고로의 송풍 또는 재송풍 공정.
  8. 청구항 7에 있어서,
    상기 청정가스운반라인의 내부압력의 증가를 위해, 반청정가스 브리더밸브를 폐쇄시킨 후 이어서 브리더밸브들을 단계적으로 폐쇄시키는 것을 특징으로 하는 고로의 송풍 또는 재송풍 공정.
  9. 청구항 7에 있어서,
    상기 청정가스운반라인의 내부압력의 증가를 위해, 스크러버 내부의 콘을 조정하는 것을 특징으로 하는 고로의 송풍 또는 재송풍 공정.
  10. 청구항 4에 있어서,
    상기 브리더밸브를 폐쇄하기 전 질소공급밸브를 개방하는 것을 특징으로 하는 고로의 송풍 또는 재송풍 공정.
  11. 청구항 5에 있어서,
    상기 브리더밸브를 폐쇄하기 전 질소공급밸브를 개방하는 것을 특징으로 하는 고로의 송풍 또는 재송풍 공정.
  12. 청구항 11에 있어서,
    상기 청정가스벤트라인으로의 흐름이 생성된 후, 송풍구를 통해 열풍을 주입한 후 상기 질소공급밸브를 폐쇄시키고 고로에의 송품 및 재송풍을 수행하는 것을 특징으로 하는 고로의 송풍 또는 재송풍 공정.
  13. 청구항 12에 있어서,
    고로의 재가동으로 발생하는 고로가스는 가스청정섹션을 거쳐 청정가스 상태로 정화되어 상기 청정가스벤트라인으로 배출되는 것을 특징으로 하는 고로의 송풍 또는 재송풍 공정.
  14. 청구항 13에 있어서,
    청정가스가 청정가스벤트라인으로 배출되면서 청정가스운반라인의 압력이 가스홀더의 압력을 초과하는 경우, 상기 청정가스차단밸브는 상기 청정가스운반라인을 통해 상기 가스홀더로 운반되는 청정가스에 대해 개방되고, 상기 청정가스벤트라인은 폐쇄되는 것을 특징으로 하는 고로의 송풍 또는 재송풍 공정.
  15. 적어도 하나의 브리더밸브를 구비한 고로, 가스청정섹션, 및 상기 가스정화섹션에서 정화된 가스의 운반을 위한 가스홀더로의 청정가스운반라인을 포함하는 고로 설비로서,
    상기 가스홀더로의 상기 청정가스운반라인은 송풍 또는 재송풍 공정에서 고로의 재가동 전 상기 브리더밸브를 폐쇄한 상태에서 상기 가스청정섹션에서 정화된 고로가스와 배관내의 잔존 공기를 배출하는 청정가스벤트라인을 포함하는 고로 설비.
PCT/KR2021/017217 2020-12-04 2021-11-23 고로의 송풍 또는 재송풍 공정 및 이를 위한 고로 설비 WO2022119209A1 (ko)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
KR10-2020-0168840 2020-12-04
KR1020200168840A KR20220079251A (ko) 2020-12-04 2020-12-04 고로의 송풍 또는 재송풍 공정 및 이를 위한 고로 설비

Publications (1)

Publication Number Publication Date
WO2022119209A1 true WO2022119209A1 (ko) 2022-06-09

Family

ID=81854169

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/KR2021/017217 WO2022119209A1 (ko) 2020-12-04 2021-11-23 고로의 송풍 또는 재송풍 공정 및 이를 위한 고로 설비

Country Status (2)

Country Link
KR (1) KR20220079251A (ko)
WO (1) WO2022119209A1 (ko)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57155305A (en) * 1981-03-19 1982-09-25 Kawasaki Steel Corp Treatment of gas generated from blast furnace at time of vacant furnace blowing
KR20020051629A (ko) * 2000-12-23 2002-06-29 이구택 고로 휴풍시 배출관 유지장치 및 방법
KR20050023886A (ko) * 2003-09-03 2005-03-10 주식회사 포스코 고로의 휴,송풍작업시 분진제거 장치
KR20110120443A (ko) * 2010-04-29 2011-11-04 현대제철 주식회사 고로 설비의 휴풍 제어 방법
KR102037032B1 (ko) * 2019-06-27 2019-10-25 용운중공업 주식회사 고로공장의 탑블리더밸브 공해방지 및 저감을 위한 가스 처리장치 및 방법

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57155305A (en) * 1981-03-19 1982-09-25 Kawasaki Steel Corp Treatment of gas generated from blast furnace at time of vacant furnace blowing
KR20020051629A (ko) * 2000-12-23 2002-06-29 이구택 고로 휴풍시 배출관 유지장치 및 방법
KR20050023886A (ko) * 2003-09-03 2005-03-10 주식회사 포스코 고로의 휴,송풍작업시 분진제거 장치
KR20110120443A (ko) * 2010-04-29 2011-11-04 현대제철 주식회사 고로 설비의 휴풍 제어 방법
KR102037032B1 (ko) * 2019-06-27 2019-10-25 용운중공업 주식회사 고로공장의 탑블리더밸브 공해방지 및 저감을 위한 가스 처리장치 및 방법

Also Published As

Publication number Publication date
KR20220079251A (ko) 2022-06-13

Similar Documents

Publication Publication Date Title
CN103890197A (zh) 操作鼓风炉设备中的回热加热器的方法
CN102425940A (zh) 石灰回转窑煤粉制备与输送装置及其方法
CN100471960C (zh) 用于直接熔炼工艺的固体供给材料的供给方法和设备
WO2010120046A2 (ko) 가연성 불순물이 혼합된 배출가스로부터 이산화탄소를 회수하기 위한 이산화탄소 고순도화 장치 및 이를 이용하여 고순도의 이산화탄소를 회수하는 방법
WO2022119209A1 (ko) 고로의 송풍 또는 재송풍 공정 및 이를 위한 고로 설비
KR101186277B1 (ko) 슬래그 입상화 방법 및 시스템
KR20210081242A (ko) 고로 설비 및 셧다운 프로세스
US3084039A (en) Recovery of combustible gases in ferro-metallurgical processes
US4356063A (en) Pre-heated coal supply system for a coking oven battery
KR101557776B1 (ko) 용광로에 장입물을 공급하는 장치
RU2448144C2 (ru) Установка сухого тушения кокса
KR100584735B1 (ko) 콜 더스트 취입장치를 갖는 코렉스 용융로
JP5626860B2 (ja) 廃棄物溶融炉の廃棄物及び副資材装入装置
CN113122290B (zh) 一种干熄焦炉常用放散气的处理方法
JP4537602B2 (ja) 廃棄物溶融炉における可燃性ダスト吹き込み方法
CN116943406B (zh) 一种烟气净化系统脱硫剂在线置换方法及系统
CN108827013A (zh) 连续加料电弧炉炉内烟气净化系统及方法
JP3877443B2 (ja) 溶解装置
JP4100509B2 (ja) 廃棄物の処理システム
JP2009213973A (ja) バグ・フィルタ式集塵装置
EA047612B1 (ru) Способ эксплуатации доменного цеха
Trovant et al. A Novel Dry-Based System for Safe, Hygienic Energy Recovery from Ferroalloy Furnace Exhaust
CN116761974A (zh) 运行高炉设备的方法
CN111174096A (zh) 一种用于沥青烟气的输送系统
JPH0257624A (ja) 高炉々内ガスの空気置換方法

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 21900897

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 21900897

Country of ref document: EP

Kind code of ref document: A1