一种大跨度不等高双向曲面网架的累积提升方法Cumulative lifting method for large-span unequal height bidirectional curved surface grid
技术领域Technical field
本发明涉及网架施工技术领域,具体涉及一种大跨度不等高双向曲面网架的累积提升方法。The invention relates to the technical field of grid construction, in particular to a cumulative lifting method for a large-span unequal height bidirectional curved surface grid.
背景技术Background technique
随着大跨度、大面积网架结构的不断涌现,大面积网架的施工高度及跨度不断的增加,传统的施工方法不仅使施工成本增加、施工周期加长,且施工安全性降低。因此,寻求安全快捷、成本低廉的施工方法为当前大面积大跨度网架施工研究的重点之一。With the continuous emergence of large-span and large-area grid structures, the construction height and span of large-area grids continue to increase. Traditional construction methods not only increase the construction cost and lengthen the construction period, but also reduce the construction safety. Therefore, seeking a safe, fast, and low-cost construction method is one of the focuses of the current research on large-area and large-span grid construction.
超高度拱形网架结构是一种以焊接球节点为主的网架结构形式,其适合于空间结构跨度大、轻型、受力合理的柱状或拱形结构形式。此类结构在飞艇库、干煤棚、建筑水泥材料反应堆等建筑物中应用较多。The ultra-high arched grid structure is a grid structure with welded spherical nodes as the main form, which is suitable for columnar or arched structures with large span, light weight and reasonable stress. This type of structure is widely used in buildings such as airship depots, dry coal sheds, and building cement material reactors.
国内某飞艇库项目结构形式为曲面网架,跨度140米,长266米,最高点标高116米。结构64.237米标高以上为拱形网壳,以下为平板网架(平板网架倾斜8°),均采用正方四角锥结构形式。结构24米标高以上为焊接空心球节点,以下为相贯节点。整体结构支撑在下部混凝土独立基础上,支撑柱脚为插入式。The structure of a domestic airship warehouse project is a curved grid with a span of 140 meters, a length of 266 meters, and an elevation of 116 meters at the highest point. The structure above the 64.237 meters elevation is an arched net shell, and the following is a flat net frame (the flat net frame is inclined 8°), all of which are in the form of a square quadrangular pyramid. The structure above the elevation of 24 meters is welded hollow sphere joints, and the following are intersecting joints. The overall structure is supported on the lower concrete independent foundation, and the supporting column feet are inserted.
目前大跨度大面积网架结构施工常用方法有:(1)滑架法,(2)结构累积滑移法,(3)折叠展开提升法,(4)悬挑法。而针对屋面为弧形网壳、立面为倾斜平板网架的大跨度、超高度网架结构,以上几种施工方案不管从施工成本、施工质量以及施工安全各方面均有所欠缺,不尽完美。At present, the commonly used methods of large-span and large-area grid structure construction are: (1) sliding frame method, (2) structure cumulative slip method, (3) folding and unfolding lifting method, (4) cantilevering method. Regarding the large-span and super-height grid structure with an arc-shaped reticulated shell on the roof and an inclined flat-plate grid on the facade, the above-mentioned construction schemes are lacking in terms of construction cost, construction quality, and construction safety. perfect.
目前,超高度拱形网架结构设计与施工在我国乃至世界上都还处于探索研究阶段,目前竣工验收的案例还没有。基于这种状况,国内外许多科研单位、高校及施工单位均在积极地进行模型试验研究,理论计算。At present, the design and construction of the ultra-high arched grid structure is still in the stage of exploration and research in my country and even in the world, and there are no cases of completion acceptance. Based on this situation, many research institutes, universities and construction units at home and abroad are actively conducting model test research and theoretical calculations.
发明内容Summary of the invention
因此,本发明要解决的技术问题在于克服现有技术中针对大跨度空间双向曲面网架常采用的施工方法存在投入的支撑措施多,施工效率慢,施工成本高的缺陷,从而提供一种大跨度不等高双向曲面网架的累积提升方法。Therefore, the technical problem to be solved by the present invention is to overcome the disadvantages of large-span space bidirectional curved surface grid construction methods in the prior art, such as large investment support measures, slow construction efficiency, and high construction costs, thereby providing a large-scale construction method. Cumulative lifting method for two-way curved surface grids with unequal spans.
本发明的上述技术目的是通过以下技术方案得以实现的:The above-mentioned technical objectives of the present invention are achieved through the following technical solutions:
一种大跨度不等高双向曲面网架的累积提升方法,包括以下步骤:A method for accumulative lifting of large-span unequal-height two-way curved surface grids includes the following steps:
S1、施工前计算分析:利用计算软件对施工全过程进行计算分析,确保施工过程中网架结构本身及提升系统能满足相关力学及构造要求,确保施工过程安全可控;S1. Calculation and analysis before construction: use calculation software to calculate and analyze the whole construction process to ensure that the grid structure itself and the lifting system can meet the relevant mechanical and structural requirements during the construction process, and ensure that the construction process is safe and controllable;
S2、施工中计算控制:液压提升施工同步控制性要求高,施工过程中采用计算机同步控制系统,并加强提升过程中的检测;S2. Computational control during construction: high requirements for synchronous control of hydraulic lifting construction, computer synchronous control system is used during construction, and detection during lifting is strengthened;
S3、立面支撑网架安装:采取格构式支撑架、揽风绳的措施对立面支撑部分的网架进行临时固定;S3. Installation of the vertical support grid frame: adopt the measures of lattice type support frame and wind rope to temporarily fix the grid frame of the vertical support part;
S4、双向曲面网架拼装:将大跨度不等高的双向曲面网架部分在其投影的正下方的拼装胎架上进行拼装;S4. Assembling of two-way curved net frame: Assemble the two-way curved net frame with large span and unequal height on the assembled tire frame directly below the projection;
S5、设置提升点:在立面支撑网架结构上安装提升支架和液压提升器,且在保证施工要求的前提下,减少提升点的数量;S5. Set up lifting points: install lifting brackets and hydraulic lifters on the vertical support grid structure, and reduce the number of lifting points under the premise of ensuring construction requirements;
S6、累积提升:将步骤S4中的双向曲面网架部分划分为几个提升分区,并在立面支撑网架结构的拼装胎架底部安装千斤顶,由高到低,依次提升各个分区,且与后续分区逐步连接,逐步提升,形成整体造型后提升就位;S6. Cumulative lifting: Divide the two-way curved network frame in step S4 into several lifting zones, and install jacks at the bottom of the assembled tire frame that supports the grid structure on the facade, and lift each zone in turn from high to low. Subsequent partitions are gradually connected and gradually improved to form an overall shape and then lifted into place;
S7、配件安装:提升结束后,增加杆件进行组装,组装完成后进行加固处 理。S7. Accessories installation: After the lifting is completed, add rods for assembly, and perform reinforcement treatment after the assembly is completed.
可选地,所述步骤S2中,于主要受力部分设置应力感应片,监控其内部应力变化情况,提升过程中杆件的应力比控制在0.85以内,结构整体的变形控制在L/250,L为相邻提升点的间距。Optionally, in the step S2, a stress sensing sheet is set in the main stressed part to monitor the change of its internal stress, the stress ratio of the rod during the lifting process is controlled within 0.85, and the overall deformation of the structure is controlled at L/250, L is the distance between adjacent lifting points.
可选地,所述支撑架的间距为20-45m,所述揽风绳拉设在立面支撑部分的2/3高度处,所述揽风绳与地面的夹角为30-45°,所述立面支撑部分的高度为50-75m。Optionally, the distance between the support frames is 20-45m, the wind rope is pulled at 2/3 of the height of the vertical support part, and the angle between the wind rope and the ground is 30-45°, The height of the façade supporting part is 50-75m.
可选地,所述步骤S5中,所述提升支架设置于网架的球节点上,采用计算机软件进行仿真验算,根据验算结果对支撑区域网架杆件进行加固,使得所述提升支架的高度比提升点的高度高0.5-1m,并且所述液压提升器的型号根据提升点的提升反力确定,以此设置钢绞线,所述钢绞线的安全系数控制在2-4倍的范围内。Optionally, in the step S5, the lifting bracket is set on the ball node of the grid, and computer software is used to perform a simulation check. According to the check calculation result, the support area grid member is reinforced to make the height of the lifting bracket It is 0.5-1m higher than the height of the lifting point, and the model of the hydraulic lifter is determined according to the lifting reaction force of the lifting point, so as to set the steel strand, the safety factor of the steel strand is controlled in the range of 2-4 times Inside.
可选地,所述步骤S5中,在提升之前,用钢拉索对网架结构本身施加预应力,预应力的大小为500-1000KN,用于抵抗提升反力。Optionally, in the step S5, before lifting, a steel cable is used to prestress the grid structure itself, the magnitude of the prestress is 500-1000 KN, which is used to resist the lifting reaction force.
可选地,所述步骤S6中,所述液压提升器的配置系数一致,且通过控制端统一指挥开动提升,以200mm行程分段控制。Optionally, in the step S6, the configuration coefficients of the hydraulic lifts are the same, and the lifting is uniformly commanded by the control terminal, and the lift is controlled in sections with a 200mm stroke.
可选地,所述步骤S6中,在所述钢绞线上做好刻度标记,间距为1m,提升前记录各千斤顶上夹片到最近刻度的距离,作为同步控制的基准;提升过程中,观测各提升点的钢筋刻度,控制各吊点的不同步差在允许范围内。Optionally, in the step S6, make scale marks on the steel strand with an interval of 1 m, and record the distance from the clip on each jack to the nearest scale before lifting, as a reference for synchronization control; during the lifting process, Observe the steel bar scale of each lifting point, and control the asynchronous difference of each lifting point within the allowable range.
可选地,所述步骤S6中,夹具的回缩量因千斤顶而异,在提升一定数量的缸数后,测量夹片到刻度的距离,依据提升前的记录分析各提升点的同步性,对存在偏差的提升点进行个别调整。Optionally, in the step S6, the amount of retraction of the clamp varies from jack to jack. After lifting a certain number of cylinders, measure the distance from the clip to the scale, and analyze the synchronization of each lifting point based on the record before lifting. Individual adjustments are made to deviations in the lifting points.
本发明技术方案,具有如下优点:The technical scheme of the present invention has the following advantages:
1.机械设备要求低。本发明专利由于采用累积提升提升的施工方法,所用到的机械设备除了液压提升器、液压泵源系统、同步控制系统等之外,仅需安排几台小型地面拼装机械,对曲面网架液压提升部分进行地面拼装即可满足施工要求;与其它施工方案相比,其具有施工机械费用低、施工机械设备资源丰富等优势。1. Low requirements for mechanical equipment. Due to the construction method of accumulative lifting and lifting in the patent of the invention, the mechanical equipment used in addition to the hydraulic lifter, hydraulic pump source system, synchronous control system, etc., only need to arrange a few small ground assembly machinery to hydraulically lift the curved net frame Part of the ground assembly can meet the construction requirements; compared with other construction schemes, it has the advantages of low construction machinery cost and abundant construction machinery equipment resources.
2.施工工效高。双向曲面网架先在地面拼装成若干个小单元,然后采用吊装机械将拼装完成的单元吊装至拼装胎架上,以拼装成整体提升单元,施工设备及措施安装简单,施工过程便捷,施工效率高。2. High construction efficiency. The two-way curved surface grid is first assembled into several small units on the ground, and then the assembled unit is hoisted to the assembled tire frame by hoisting machinery to assemble into an overall lifting unit. The installation of construction equipment and measures is simple, the construction process is convenient, and the construction efficiency high.
3.施工成本低。网架在地面操作平台上拼装,搭设拼装平台的措施量小,所用到的机械均为常见的小型机械和设备,租赁方便且费用低廉,相比高空散装、分块吊装等方案施工成本大大降低。3. Low construction cost. The grid frame is assembled on the ground operation platform, and the amount of measures to set up the assembly platform is small. The machinery used is common small machinery and equipment, which is convenient and cheap to rent. Compared with the high-altitude bulk and block hoisting schemes, the construction cost is greatly reduced. .
4.施工安全高。采用计算机软件进行仿真验算,根据验算结果对支撑区域网架杆件进行加固,使得提升支架的高度比提升点的高度高0.5m,并且液压提升器的型号根据提升点的提升反力确定,以此设置钢绞线,钢绞线的安全系数控制在2-4倍的范围内,并且凭借应力感应片,在提升过程中控制杆件的应力比在0.85以内,结构整体的变形控制在L/250,L为相邻提升点的间距。4. High construction safety. Computer software is used for simulation and calculation, and the support area grid members are reinforced according to the results of the calculation, so that the height of the lifting bracket is 0.5m higher than the height of the lifting point, and the model of the hydraulic lifter is determined according to the lifting reaction force of the lifting point. With this setting of the steel strand, the safety factor of the steel strand is controlled within the range of 2-4 times, and by virtue of the stress sensing sheet, the stress ratio of the rod is controlled to be within 0.85 during the lifting process, and the deformation of the structure as a whole is controlled at L/ 250, L is the distance between adjacent lifting points.
5.施工质量容易保证。液压提升器的配置系数一致,且通过控制端统一指挥开动提升,以200mm行程分段控制;在钢绞线上做好刻度标记,间距为1m,提升前记录各千斤顶上夹片到最近刻度的距离,作为同步控制的基准;提升过程中,观测各提升点的钢筋刻度,控制各吊点的不同步差在允许范围内;夹具的回缩量因千斤顶而异,在提升一定数量的缸数后,测量夹片到刻度的距离,依据提升前的记录分析各提升点的同步性,对存在偏差的提升点进行个别调整。5. The construction quality is easy to guarantee. The configuration coefficient of the hydraulic lifter is the same, and the lifting is uniformly commanded by the control terminal, and is controlled in sections with a 200mm stroke; mark the scale on the steel strand with a spacing of 1m, and record the clip on each jack to the nearest scale before lifting The distance is used as the benchmark for synchronous control; during the lifting process, observe the rebar scale of each lifting point, and control the asynchronous difference of each lifting point to be within the allowable range; the retraction amount of the fixture varies with the jack, and a certain number of cylinders are being lifted After that, measure the distance from the clip to the scale, analyze the synchronization of each lifting point based on the records before lifting, and make individual adjustments to the lifting points with deviations.
具体实施方式Detailed ways
为了使本发明的目的、技术方案及优点更加清楚明白,以下结合实施例,对本发明进行进一步详细说明。应当理解,此处所描述的具体实施例仅仅用以解释本发明,并不用于限定本发明。In order to make the objectives, technical solutions, and advantages of the present invention clearer, the present invention will be further described in detail below in conjunction with embodiments. It should be understood that the specific embodiments described here are only used to explain the present invention, but not used to limit the present invention.
实施例1:Example 1:
一种大跨度不等高双向曲面网架的累积提升方法,包括以下步骤:A method for accumulative lifting of large-span unequal-height two-way curved surface grids includes the following steps:
S1、施工前计算分析:利用计算软件对施工全过程进行计算分析,确保施工过程中网架结构本身及提升系统能满足相关力学及构造要求,确保施工过程安全可控;S1. Calculation and analysis before construction: use calculation software to calculate and analyze the whole construction process to ensure that the grid structure itself and the lifting system can meet the relevant mechanical and structural requirements during the construction process, and ensure that the construction process is safe and controllable;
S2、施工中计算控制:液压提升施工同步控制性要求高,施工过程中采用计算机同步控制系统,并加强提升过程中的检测;S2. Computational control during construction: high requirements for synchronous control of hydraulic lifting construction, computer synchronous control system is used during construction, and detection during lifting is strengthened;
具体地,提前在网架的主要受力部分贴设应力感应片,以监控其内部应力变化情况;Specifically, a stress sensing sheet is attached to the main stressed part of the grid in advance to monitor its internal stress changes;
S3、立面支撑网架安装:采取格构式支撑架、揽风绳的措施对立面支撑部分的网架进行临时固定,在本发明此实施例中,将揽风绳拉设在立面支撑部分的2/3高度处,揽风绳与地面的夹角为45°,支撑架的间距为20m,立面支撑部分的高度为50m;S3. Installation of the vertical support grid: the grid type support frame and the wind rope are adopted to temporarily fix the grid of the vertical support part. In this embodiment of the present invention, the wind rope is pulled on the vertical support part. At 2/3 of the height, the angle between the wind rope and the ground is 45°, the distance between the support frames is 20m, and the height of the vertical support part is 50m;
S4、双向曲面网架拼装:将大跨度不等高的双向曲面网架部分在其投影的正下方的拼装胎架上进行拼装,从而双向曲面网架先在地面拼装成若干个小单元,然后采用吊装机械将拼装完成的单元吊装至拼装胎架上,以拼装成整体提升单元;S4. Assembling of two-way curved net frame: Assemble the two-way curved net frame with large span and unequal height on the assembled tire frame directly below its projection, so that the two-way curved net frame is first assembled into several small units on the ground, and then Use hoisting machinery to hoist the assembled unit to the assembled tire frame to assemble into an integral lifting unit;
S5、设置提升点:在立面支撑网架结构上安装提升支架和液压提升器,且在保证施工要求的前提下,减少提升点的数量,从而凭借应力感应片,在提升过程中控制杆件的应力比在0.85以内,结构整体的变形控制在L/250,L为相 邻提升点的间距;S5. Set up lifting points: install lifting brackets and hydraulic lifters on the vertical support grid structure, and reduce the number of lifting points under the premise of ensuring construction requirements, so as to control the rods during the lifting process by virtue of the stress sensing sheet The stress ratio is within 0.85, and the overall deformation of the structure is controlled at L/250, where L is the distance between adjacent lifting points;
具体地,提升支架设置于网架的球节点上,采用计算机软件进行仿真验算,根据验算结果对支撑区域网架杆件进行加固,使得提升支架的高度比提升点的高度高0.5m,并且液压提升器的型号根据提升点的提升反力确定,以此设置钢绞线,钢绞线的安全系数控制在2-4倍的范围内;Specifically, the lifting bracket is set on the ball node of the grid, and computer software is used for simulation and calculation. According to the verification results, the support area grid member is reinforced, so that the height of the lifting bracket is 0.5m higher than the height of the lifting point, and the hydraulic The type of the lifter is determined according to the lifting reaction force of the lifting point, and the steel strand is set accordingly, and the safety factor of the steel strand is controlled within the range of 2-4 times;
另外,需要在提升位置设置临时杆件和临时球,作为提升下吊点,每个提升点设置3根临时杆件,限定临时杆件不能与结构杆件冲突,下吊点采用焊接球,焊接球的直径控制在500-800mm,焊接球内加设十字加劲板;In addition, it is necessary to set temporary rods and temporary balls at the lifting position as the lower lifting point. Each lifting point is set with 3 temporary rods to limit the temporary rods from conflicting with the structural members. The lower lifting points are welded balls and welded. The diameter of the ball is controlled at 500-800mm, and a cross stiffening plate is added in the welding ball;
S6、累积提升:将步骤S4中的双向曲面网架部分划分为几个提升分区,并在立面支撑网架结构的拼装胎架底部安装千斤顶,由高到低,依次提升各个分区,且与后续分区逐步连接,逐步提升,形成整体造型后提升就位;S6. Cumulative lifting: Divide the two-way curved network frame in step S4 into several lifting zones, and install jacks at the bottom of the assembled tire frame that supports the grid structure on the facade, and lift each zone in turn from high to low. Subsequent partitions are gradually connected and gradually improved to form an overall shape and then lifted into place;
在本发明此实施例中,网架结构在立面上分为四个单元网架,每个单元网架通过多组提升系统与前单元网架累积提升就位,即第一单元网架在拼装胎架上拼装成整体,在单元网架两侧设置多组提升系统,将第一单元网架同步提升到一定高度,随后采用大型履带吊吊装分块单元网架,完成第二单元网架组装,此时第一、第二单元网架的拼装胎架写在,并在立面支撑网架部分落位,然后拆除第一单元网架的提升系统,并转移至第二单元网架处,将第一、第二单元网架一起同步提升至一定高度,从而以此类推,完成后续单元网架的安装;In this embodiment of the present invention, the grid structure is divided into four unit grids on the facade, and each unit grid is cumulatively lifted into place through multiple sets of lifting systems and the front unit grid, that is, the first unit grid is in place. The assembled tire frame is assembled into a whole, and multiple sets of lifting systems are set on both sides of the unit grid to raise the first unit grid to a certain height simultaneously, and then use a large crawler crane to hoist the block unit grid to complete the second unit grid Assemble. At this time, the assembled tire frames of the first and second unit grids are written in, and part of the grid is supported on the vertical surface. Then the lifting system of the first unit grid is removed and transferred to the second unit grid , Raise the first and second unit grids to a certain height simultaneously, and so on to complete the installation of the subsequent unit grids;
在网架提升过程中,为了防止提升反力对网架结构本身造成破坏,在提升之前,用钢拉索给网架结构本身施加预应力,预应力的大小为500-1000KN,用于抵抗提升反力;During the lifting process of the grid, in order to prevent the lifting reaction force from damaging the grid structure itself, steel cables are used to prestress the grid structure itself before lifting. The prestress is 500-1000KN to resist the lifting. Reaction force;
在分级累积提升过程中,不同分级间的合拢是精度和变形控制的重点,相对于传统整体提升方法的不同在于,分级累积提升合拢时,不同级间处于不同的应力状态下:在这种情况下将两级提升分区合拢后,由于应力状态的不同, 形成整体提升后,由于应力的释放,会对网架造成变形影响。为解决这一问题,液压提升器的配置系数一致,且通过控制端统一指挥开动提升,以200mm行程分段控制;在钢绞线上做好刻度标记,间距为1m,提升前记录各千斤顶上夹片到最近刻度的距离,作为同步控制的基准;提升过程中,观测各提升点的钢筋刻度,控制各吊点的不同步差在允许范围内;夹具的回缩量因千斤顶而异,在提升一定数量的缸数后,测量夹片到刻度的距离,依据提升前的记录分析各提升点的同步性,对存在偏差的提升点进行个别调整;In the process of grading and accumulative lifting, the closing of different classes is the focus of accuracy and deformation control. Compared with the traditional overall lifting method, the difference is that when the grading and accumulative lifting are closed, different levels are in different stress states: in this case After the two-level lifting partitions are closed together, due to the different stress states, after forming an overall lifting, due to the release of stress, it will cause deformation of the grid. In order to solve this problem, the configuration coefficient of the hydraulic lifter is the same, and the lifting is uniformly commanded by the control terminal, and the 200mm stroke is controlled in sections; the scale marks are made on the steel strand with a distance of 1m, and the jacks are recorded before lifting. The distance from the clamp to the nearest scale is used as the benchmark for synchronization control; during the lifting process, observe the rebar scale of each lifting point to control the asynchronous difference of each lifting point within the allowable range; the retraction amount of the clamp varies with the jack. After lifting a certain number of cylinders, measure the distance from the clip to the scale, analyze the synchronization of each lifting point based on the records before lifting, and make individual adjustments to the lifting points with deviations;
S7、配件安装:提升结束后,增加杆件进行组装,组装完成后进行加固处理。S7. Accessories installation: After the lifting is completed, add rods for assembly, and perform reinforcement treatment after the assembly is completed.
实施例1:Example 1:
一种大跨度不等高双向曲面网架的累积提升方法,包括以下步骤:A method for accumulative lifting of large-span unequal-height two-way curved surface grids includes the following steps:
S1、施工前计算分析:利用计算软件对施工全过程进行计算分析,确保施工过程中网架结构本身及提升系统能满足相关力学及构造要求,确保施工过程安全可控;S1. Calculation and analysis before construction: use calculation software to calculate and analyze the whole construction process to ensure that the grid structure itself and the lifting system can meet the relevant mechanical and structural requirements during the construction process, and ensure that the construction process is safe and controllable;
S2、施工中计算控制:液压提升施工同步控制性要求高,施工过程中采用计算机同步控制系统,并加强提升过程中的检测;S2. Computational control during construction: high requirements for synchronous control of hydraulic lifting construction, computer synchronous control system is used during construction, and detection during lifting is strengthened;
具体地,提前在网架的主要受力部分贴设应力感应片,以监控其内部应力变化情况;Specifically, a stress sensing sheet is attached to the main stressed part of the grid in advance to monitor its internal stress changes;
S3、立面支撑网架安装:采取格构式支撑架、揽风绳的措施对立面支撑部分的网架进行临时固定,在本发明此实施例中,将揽风绳拉设在立面支撑部分的2/3高度处,揽风绳与地面的夹角为30°,支撑架的间距为45m,立面支撑部分的高度为75m;S3. Installation of the vertical support grid: the grid type support frame and the wind rope are adopted to temporarily fix the grid of the vertical support part. In this embodiment of the present invention, the wind rope is pulled on the vertical support part. At 2/3 of the height, the angle between the wind rope and the ground is 30°, the distance between the support frames is 45m, and the height of the vertical support part is 75m;
S4、双向曲面网架拼装:将大跨度不等高的双向曲面网架部分在其投影的 正下方的拼装胎架上进行拼装,从而双向曲面网架先在地面拼装成若干个小单元,然后采用吊装机械将拼装完成的单元吊装至拼装胎架上,以拼装成整体提升单元;S4. Assembling of two-way curved net frame: Assemble the two-way curved net frame with large span and unequal height on the assembled tire frame directly below its projection, so that the two-way curved net frame is first assembled into several small units on the ground, and then Use hoisting machinery to hoist the assembled unit to the assembled tire frame to assemble into an integral lifting unit;
S5、设置提升点:在立面支撑网架结构上安装提升支架和液压提升器,且在保证施工要求的前提下,减少提升点的数量,从而凭借应力感应片,在提升过程中控制杆件的应力比在0.85以内,结构整体的变形控制在L/250,L为相邻提升点的间距;S5. Set up lifting points: install lifting brackets and hydraulic lifters on the vertical support grid structure, and reduce the number of lifting points under the premise of ensuring construction requirements, so as to control the rods during the lifting process by virtue of the stress sensing sheet The stress ratio is within 0.85, and the overall deformation of the structure is controlled at L/250, where L is the distance between adjacent lifting points;
具体地,提升支架设置于网架的球节点上,采用计算机软件进行仿真验算,根据验算结果对支撑区域网架杆件进行加固,使得提升支架的高度比提升点的高度高1m,并且液压提升器的型号根据提升点的提升反力确定,以此设置钢绞线,钢绞线的安全系数控制在2-4倍的范围内;Specifically, the lifting bracket is set on the ball node of the grid, and computer software is used for simulation and calculation. According to the results of the verification, the support area grid member is reinforced, so that the height of the lifting bracket is 1m higher than the height of the lifting point, and the hydraulic lifting The model of the device is determined according to the lifting reaction force of the lifting point, and the steel strand is set accordingly, and the safety factor of the steel strand is controlled within the range of 2-4 times;
另外,需要在提升位置设置临时杆件和临时球,作为提升下吊点,每个提升点设置3根临时杆件,限定临时杆件不能与结构杆件冲突,下吊点采用焊接球,焊接球的直径控制在500-800mm,焊接球内加设十字加劲板;In addition, it is necessary to set temporary rods and temporary balls at the lifting position as the lower lifting point. Each lifting point is set with 3 temporary rods to limit the temporary rods from conflicting with the structural members. The lower lifting points are welded balls and welded. The diameter of the ball is controlled at 500-800mm, and a cross stiffening plate is added in the welding ball;
S6、累积提升:将步骤S4中的双向曲面网架部分划分为几个提升分区,并在立面支撑网架结构的拼装胎架底部安装千斤顶,由高到低,依次提升各个分区,且与后续分区逐步连接,逐步提升,形成整体造型后提升就位;S6. Cumulative lifting: Divide the two-way curved network frame in step S4 into several lifting zones, and install jacks at the bottom of the assembled tire frame that supports the grid structure on the facade, and lift each zone in turn from high to low. Subsequent partitions are gradually connected and gradually improved to form an overall shape and then lifted into place;
在本发明此实施例中,网架结构在立面上分为七个单元网架,每个单元网架通过多组提升系统与前单元网架累积提升就位,即第一单元网架在拼装胎架上拼装成整体,在单元网架两侧设置多组提升系统,将第一单元网架同步提升到一定高度,随后采用大型履带吊吊装分块单元网架,完成第二单元网架组装,此时第一、第二单元网架的拼装胎架写在,并在立面支撑网架部分落位,然后拆除第一单元网架的提升系统,并转移至第二单元网架处,将第一、第二单元网架一起同步提升至一定高度,从而以此类推,完成后续单元网架的安装;In this embodiment of the present invention, the grid structure is divided into seven unit grids on the facade, and each unit grid is cumulatively lifted into position with the front unit grid through multiple sets of lifting systems, that is, the first unit grid is in place. The assembled tire frame is assembled into a whole, and multiple sets of lifting systems are set on both sides of the unit grid to raise the first unit grid to a certain height simultaneously, and then use a large crawler crane to hoist the block unit grid to complete the second unit grid Assemble. At this time, the assembled tire frames of the first and second unit grids are written in, and part of the grid is supported on the vertical surface. Then the lifting system of the first unit grid is removed and transferred to the second unit grid , Raise the first and second unit grids to a certain height simultaneously, and so on to complete the installation of the subsequent unit grids;
在网架提升过程中,为了防止提升反力对网架结构本身造成破坏,在提升之前,用钢拉索给网架结构本身施加预应力,预应力的大小为500-1000KN,用于抵抗提升反力;During the lifting process of the grid, in order to prevent the lifting reaction force from damaging the grid structure itself, steel cables are used to prestress the grid structure itself before lifting. The prestress is 500-1000KN to resist the lifting. Reaction force;
在分级累积提升过程中,不同分级间的合拢是精度和变形控制的重点,相对于传统整体提升方法的不同在于,分级累积提升合拢时,不同级间处于不同的应力状态下:在这种情况下将两级提升分区合拢后,由于应力状态的不同,形成整体提升后,由于应力的释放,会对网架造成变形影响。为解决这一问题,液压提升器的配置系数一致,且通过控制端统一指挥开动提升,以200mm行程分段控制;在钢绞线上做好刻度标记,间距为1m,提升前记录各千斤顶上夹片到最近刻度的距离,作为同步控制的基准;提升过程中,观测各提升点的钢筋刻度,控制各吊点的不同步差在允许范围内;夹具的回缩量因千斤顶而异,在提升一定数量的缸数后,测量夹片到刻度的距离,依据提升前的记录分析各提升点的同步性,对存在偏差的提升点进行个别调整;In the process of grading and accumulative lifting, the closing of different classes is the focus of accuracy and deformation control. Compared with the traditional overall lifting method, the difference is that when the grading and accumulative lifting are closed, different levels are in different stress states: in this case After the two-level lifting zones are closed together, due to the different stress states, after forming an overall lifting, due to the release of stress, it will have a deformation effect on the grid. In order to solve this problem, the configuration coefficient of the hydraulic lifter is the same, and the lifting is uniformly commanded by the control terminal, and the 200mm stroke is controlled in sections; the scale marks are made on the steel strand with a distance of 1m, and the jacks are recorded before lifting. The distance from the clamp to the nearest scale is used as the benchmark for synchronization control; during the lifting process, observe the rebar scale of each lifting point to control the asynchronous difference of each lifting point within the allowable range; the retraction amount of the clamp varies with the jack. After lifting a certain number of cylinders, measure the distance from the clip to the scale, analyze the synchronization of each lifting point based on the records before lifting, and make individual adjustments to the lifting points with deviations;
S7、配件安装:提升结束后,增加杆件进行组装,组装完成后进行加固处理。S7. Accessories installation: After the lifting is completed, add rods for assembly, and perform reinforcement treatment after the assembly is completed.
显然,上述实施例仅仅是为清楚地说明所作的举例,而并非对实施方式的限定。对于所属领域的普通技术人员来说,在上述说明的基础上还可以做出其它不同形式的变化或变动。这里无需也无法对所有的实施方式予以穷举。而由此所引伸出的显而易见的变化或变动仍处于本发明创造的保护范围之中。Obviously, the above-mentioned embodiments are merely examples for clear description, and are not intended to limit the implementation manners. For those of ordinary skill in the art, other changes or modifications in different forms can be made on the basis of the above description. It is unnecessary and impossible to list all the implementation methods here. The obvious changes or changes derived from this are still within the protection scope created by the present invention.