WO2020237154A1 - Recovering hydrocarbons in multi-layer reservoirs with coiled tubing - Google Patents
Recovering hydrocarbons in multi-layer reservoirs with coiled tubing Download PDFInfo
- Publication number
- WO2020237154A1 WO2020237154A1 PCT/US2020/034221 US2020034221W WO2020237154A1 WO 2020237154 A1 WO2020237154 A1 WO 2020237154A1 US 2020034221 W US2020034221 W US 2020034221W WO 2020237154 A1 WO2020237154 A1 WO 2020237154A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- layer
- horizontal section
- coiled tubing
- wellbore
- reservoir
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Ceased
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B43/00—Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
- E21B43/11—Perforators; Permeators
- E21B43/116—Gun or shaped-charge perforators
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B43/00—Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
- E21B43/14—Obtaining from a multiple-zone well
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B23/00—Apparatus for displacing, setting, locking, releasing or removing tools, packers or the like in boreholes or wells
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B23/00—Apparatus for displacing, setting, locking, releasing or removing tools, packers or the like in boreholes or wells
- E21B23/14—Apparatus for displacing, setting, locking, releasing or removing tools, packers or the like in boreholes or wells for displacing a cable or a cable-operated tool, e.g. for logging or perforating operations in deviated wells
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B33/00—Sealing or packing boreholes or wells
- E21B33/10—Sealing or packing boreholes or wells in the borehole
- E21B33/12—Packers; Plugs
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B33/00—Sealing or packing boreholes or wells
- E21B33/10—Sealing or packing boreholes or wells in the borehole
- E21B33/13—Methods or devices for cementing, for plugging holes, crevices or the like
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B43/00—Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
Definitions
- This disclosure relates to hydrocarbon production.
- target reservoirs which usually include different geological layers. All the reservoir layers can be produced simultaneously during the life time of the well, resulting in more production from dominant layers while production from the less prolific layers.
- casings can be run across the wellbore with sequential perforations starting from the deepest layers to ensure better sweep efficiency across all layers; however, this is not applicable in horizontal wells.
- the wells are connected to a topside facility where it the hydrocarbons can be processed for transportation and refinement. In some instances, the wells could be re-completed to target unswept reservoir zones or abandoned after a period of time when its drainage area is depleted.
- This disclosure describes technologies relating to depleting reservoirs with coiled tubing.
- An example implementation of the subject matter described within this disclosure is a method of producing from a multi-layered reservoir.
- the method has the following features.
- a first layer of the multi-layered reservoir is produced through a coiled tubing production string.
- the coiled tubing production string is located within a wellbore that includes a first horizontal section within the first layer.
- the coiled tubing production string includes a packer at a downhole end of the coiled tubing production string.
- the packer seals an annulus that is defined by an outer surface of the coiled tubing production string and an inner surface of the wellbore.
- the annulus is sealed from the first layer.
- the coiled tubing is retracted from the first layer of the multi-layered reservoir to a second layer of the multi-layered reservoir.
- the second layer is uphole of the first layer.
- the first layer is sealed from the second layer.
- the second layer produced through the coiled tubing production string.
- the coiled tubing production string is located
- the packer is unsealed prior to retracting the coiled tubing from the first layer to the second layer.
- the packer is retracted with the coiled tubing.
- the packer is retrieved from the wellbore.
- a second packer is installed and resealed after retracting the coiled tubing from the first layer to the second layer.
- the second packer seals the annulus from the second layer.
- aspects of the example method which can be combined with the example method alone or in combination, include the following.
- the coiled tubing is retracted from the second layer of the multi-layered reservoir to a third layer of the multi-layered reservoir.
- the third layer is uphole of the second layer.
- the second layer is sealed from the third layer.
- the third layer is produced from through the coiled tubing production string.
- Retracting the coiled tubing includes using a coiled tubing truck.
- aspects of the example method which can be combined with the example method alone or in combination, include the following.
- Sealing the first layer from the second layer includes installing a plug.
- the plug includes a cement plug or an expandable plug.
- the first horizontal section includes an open-hole completion.
- the second horizontal section includes an open-hole completion after retracting the coiled tubing to the second layer.
- a wellbore is formed in a layered reservoir.
- the wellbore includes a first horizontal section within a first layer of the reservoir and a second horizontal section within a second layer of the reservoir.
- the second horizontal section is uphole of the first horizontal section.
- a length of coiled tubing extends through the wellbore from a topside facility to the first horizontal section.
- An annular packer is positioned at a downhole end of the length of coiled tubing. The annular packer seals an annulus defined by an outer surface of the length of coiled tubing and an inner surface of the wellbore. The annular packer seals the annulus from the first horizontal section.
- the wellbore further includes a third horizontal section within a third layer of the reservoir.
- the third horizontal section is uphole from the second horizontal section.
- the first layer is stratigraphically lower than the second layer
- the second layer is stratigraphically lower than the third layer.
- the second horizontal section and the third horizontal section are connected by a vertical section or a deviated section.
- the annular packer is a retrievable annular packer.
- aspects of the example system which can be combined with the example system alone or in combination, include the following.
- the first horizontal section and the second horizontal section are connected by a vertical section or a deviated section.
- the first horizontal section includes an open-hole completion.
- An example implementation of the subject matter described within this disclosure is a method of completing a well within a multilayered reservoir.
- the method include the following features.
- a wellbore is formed.
- the wellbore includes a first horizontal section within a first layer of the reservoir and a second horizontal section within a second layer of the reservoir.
- the second horizontal section is uphole of the first horizontal section.
- a coiled tubing string is inserted such that a downhole end is within the first horizontal section.
- a packer is seated at a downhole end of the coiled tubing string.
- the packer seals an annulus defined by an outer surface of the coiled tubing string and an inner surface of the wellbore.
- the packer seals the annulus from the first horizontal section.
- the first horizontal section and the second horizontal section are connected by a vertical section or a deviated section.
- the first horizontal section is completed with an open-hole completion.
- Forming the wellbore further includes forming a third horizontal section within a third layer of the reservoir.
- the third horizontal section is uphole from the second horizontal section.
- the second horizontal section and the third horizontal section are connected by a vertical section or a deviated section.
- the first layer is stratigraphically lower than the second layer
- the second layer is stratigraphically lower than the third layer.
- Forming the wellbore includes using a drilling rig.
- Completing the wellbore in the second layer does not require using a drilling rig.
- FIG. 1 is a schematic diagram of an example well production system at a first stage of production of a multi-layered reservoir with adjacent production layers.
- FIG. 2 is a schematic diagram of an example well production system at a second stage of production of a multi-layered reservoir with adjacent production layers.
- FIG. 3 is a schematic diagram of an example well production system at a third stage of production of a multi-layered reservoir with adjacent production layers.
- FIG. 4 is a schematic diagram of an example well production system at a first stage of production of a multi-layered reservoir without adjacent production layers.
- FIG. 5 is a flowchart of an example method that can be used with aspects of this disclosure.
- FIG. 6 is a flowchart of an example method that can be used with aspects of this disclosure.
- a goal of developing a production plan for a given hydrocarbon reservoir involves determining how to extract as much hydrocarbon out of the reservoir. Often times this is referred to as the “recovery factor” of the reservoir. The goal is generally to have the recovery factor be as high as is feasible.
- This disclosure relates to a method of producing a multilayered reservoir with coiled tubing.
- One horizontal well is drilled step wisely (stair-way) through many overlying production layers.
- the horizontal is a continuity of horizontal sections drilled at the top of each producing layer simultaneously crossing vertically or slanted from one layer to the next one forming a step design single wellbore.
- the well might be drilled with a coiled tubing drilling stringer or with regular drilling pipe.
- the length of coiled tubing is extended through the wellbore to the bottom layer, where the annulus between the coiled tubing and the wall of the wellbore is sealed with a packer.
- the lower level is produced until the water-cut is too substantial, then the coiled tubing is retracted to the next layer. The packer is then re-seated, and the lower layer is abandoned. The process is repeated for each subsequent layer. Such a process allows a greater total hydrocarbon recovery from the reservoir by reducing the effect of more prolific production layers.
- FIG. 1 is a schematic diagram of an example well production system 100 at a first stage of production.
- the well production system 100 includes a wellbore 102 formed in a layered reservoir 104.
- the layered reservoir 104 in this example includes 3 horizontal production layers: a first horizontal layer 104a, a second horizontal layer 104b, and a third horizontal layer 104c.
- the first horizontal layer 104a is stratigraphically lower than the second horizontal layer 104b.
- the second layer 104b is stratigraphically lower than the third layer 104c.
- the wellbore 102 passes through the first layer 104a, the second layer 104b, and the third layer 104c.
- the wellbore 102 includes a first horizontal section 102a within a first layer 104a of the reservoir 104.
- a second horizontal section 102b is located within a second layer 104b of the reservoir 104.
- the second horizontal section 102b is uphole of the first horizontal section 102a.
- the second horizontal section 102b is connected to the first horizontal section 102a by a first deviated or vertical section 102d.
- the first deviated or vertical section 102d connects a downhole end of the second horizontal section 102b to an uphole end of the first horizontal section 102a.
- the wellbore 102 includes a third horizontal section 102c within a third layer 104c of the reservoir 104.
- the third horizontal section 102c is uphole of the second horizontal section 102b.
- the third horizontal section 102c is connected to the second horizontal section 102b by a second deviated or vertical section 102e.
- the second deviated or horizontal section 102e connects a downhole end of the third horizontal section 102c to an uphole end of the second horizontal section 102b.
- the wellbore 102 forms a step pattern through the various layers of the layered reservoir 104, and the wellbore 102 includes a horizontal section within each layer.
- a serpentine pattern can be used to similar effect without departing from this disclosure.
- a serpentine pattern can be combined with a step pattern depending on the topology of the individual reservoir. While the reservoir 104 and wellbore 102 are described within this disclosure as having three layers with three horizontal sections, greater or fewer layers and subsequent horizontal sections can be used without departing from this disclosure.
- a topside facility 106 is positioned to receive production fluid from the wellbore.
- the topside facility can include separators, pumps, compressors, amine units, glycol units, storage tanks, or any other equipment to assist in hydrocarbon production, hydrocarbon processing, or both.
- Extending into the wellbore 102 from the topside facility is a length of coiled tubing 108.
- the length of coiled tubing 108 extends though the wellbore 102 into the first horizontal section 102a.
- the length of coiled tubing 108 fluidically connects the first horizontal section 102a to the topside facility for production.
- annular packer 110 is positioned at a downhole end of the length of coiled tubing 108.
- the annular packer seals an annulus 112 defined by an outer surface of the length of coiled tubing 108 and an inner surface of the wellbore 102.
- the annular packer 110 seals the annulus 112 from the first horizontal layer 104a.
- “Seal” in the context of this disclosure refers to completely blocking fluid flow or partly blocking fluid flow.
- the annular packer 110 is a retrievable annular packer.
- the illustrated implementation shows an open-hole completion within the first horizontal section 102a. Other well completions can be used depending on wellbore stability, production zone length, production rate, well economics, any combination of these reasons, or any other reason.
- the first layer 104a of the multi-layered reservoir 104 is produced through the coiled tubing length 108. That is, the coiled tubing length 108 acts as a production string.
- the terms“coiled tubing length” and“production string” may be used interchangeably.
- Producing from the first horizontal section 102a refers to directing production fluid from the first horizontal layer 104a, through the first horizontal section 102a, and up the length of coiled tubing 108 to the topside facility 106.
- Production fluid can include liquid hydrocarbons, water, gaseous hydrocarbons, or any combination and ratio of these.
- Production from the first horizontal section 102a continues until the ratio of hydrocarbons to other production fluids, such as water, decreases to be less than a specified threshold. Once the water cut becomes too great (hydrocarbon ratio becomes too small), an operator may move on to a second stage of production.
- FIG. 2 is a schematic diagram of the example well production system 100 at the second stage of production. Once the water cut in the first production layer
- the packer 110 is unseated (unsealed), and the coiled tubing 108 is retracted from the first horizontal section 102a in the first layer 104a of the multi-layered reservoir 104 to the second horizontal section 102b in the second layer 104b of the multi-layered reservoir 104.
- Retracting and the coiled tubing 108 can be done using a coiled tubing truck or boat and does not require a drill rig.
- the packer 110 is unsealing prior to retracting the coiled tubing 108 from the first layer 104a to the second layer 104b. In some implementations, the packer 110 is retracted with the coiled tubing 108. In some implementations, the packer 110 is retrieved from the wellbore 102, and a second packer is installed and resealed at a downhole end of the coiled tubing 108 after retracting the coiled tubing from the first layer 104a to the second layer 104b. In some implementations, the same packer 110 can be refurbished and reused. In some implementations, the original packer is not retrieved, and is instead abandoned within the wellbore 102. The newly seated packer 110 seals the annulus 112 from the second layer 104b.
- a plug 202 is installed between the first horizontal section 102a and the second horizontal section 102b. As illustrated, the plug 202 is installed within the first vertical section 102d, but can be installed anywhere along the wellbore 102 such that the first layer 104a is fluidically isolated from the second layer 104b.
- the plug 202 can include an expandable plug, a cement plug, or any other plug appropriate for abandoning a section of a well.
- the second layer 104b is isolated from the first layer 104a, production is flowed from the second layer 104b.
- Producing from the second layer 104b is substantially similar to producing from the first layer 104a with the exception of any differences described within this disclosure.
- the second layer 104b is produced through the coiled tubing 108 until the ratio of hydrocarbons to other production fluids, such as water, decreases to a value less than a specified threshold. Once the water cut becomes too great (hydrocarbon ratio becomes too small), an operator may move on to a third stage of production.
- FIG. 3 is a schematic diagram of the example well production system 100 at the third stage of production.
- the transition from the second stage of production to the third stage of production is substantially similar to the transition from the first stage of production to the second stage of production with the exception of any exceptions described herein.
- producing from the third layer 104c is substantially similar to producing from the first layer 104a and the second layer 104b with the exception of any differences described herein.
- the transition from the second stage of production to the first stage of production includes retracting the coiled tubing from the second layer 104b of the multi-layered reservoir 104 to a third layer 104c of the multi-layered reservoir 104.
- the second layer 104b is sealed from the third layer 104c by a packer 110.
- the third layer is produced through the coiled tubing production string 108.
- a plug 204 is installed between the second horizontal section 102b and the third horizontal section 102c. As illustrated, the plug 204 is installed within the first vertical section 102e, but can be installed anywhere along the wellbore 102 such that the second layer 104b is fluidically isolated from the third layer 104c.
- the plug 204 can include an expandable plug, a cement plug, or any other plug appropriate for abandoning a section of a well.
- the third layer 104c is produced through the coiled tubing 108 until the ratio of hydrocarbons to other production fluids, such as water, decreases to a value less than a specified threshold. Once the water cut becomes too great (hydrocarbon ratio becomes too small), an operator may move on to a fourth stage of production (not illustrated).
- the fourth stage of production includes abandonment. Once the wellbore is abandoned according to local guidelines (plugging, cementing, etc.), the coiled tubing 108 can be moved to another production location and installed into a new wellbore.
- a sidetrack can be formed within the original wellbore and production can continue in a different section of the reservoir 104. While described in the context of three production layers, greater or fewer production layers can be included in each individual reservoir.
- multiple wellbores can radiate from a single, central, or vertical wellbore to produce multiple sections of a reservoir simultaneously. In such an implementation, flows can be comingled from different sections of the reservoir, or they can be fluidically isolated prior to processing at the topside facility 106. Aspects of this disclosure are applicable to both onshore and offshore production.
- FIG. 4 is a schematic diagram of an example well production system 400 at a first stage of production.
- FIG. 4 is substantially similar to FIG. 1 with the exception of any differences described herein.
- each production zone is isolated by a non-producing layer between each production layer.
- the first production layer 104a is separated from the second production layer 104b by a first non-production layer 402a.
- a non-production layer has low permeability and less or no hydrocarbon reserves within the rock formation than the production layers.
- the second production layer 104b is isolated from the third production layer 104c by a second non-production layer 402b.
- Producing with the example, well production system 400 is substantially similar to producing with the well production system 100.
- FIG. 5 is a flowchart of an example method 500 that can be used with aspects of this disclosure.
- fluid is produced from a first layer of the multi layered reservoir through a coiled tubing production string.
- the coiled tubing production string is located within a wellbore with a first horizontal section within the first layer.
- the coiled tubing production sting includes a packer at a downhole end of the coiled tubing production string.
- the packer seals an annulus defined by an outer surface of the coiled tubing production sting and an inner surface of the wellbore. The annulus is sealed from the first layer.
- the packer is unsealed. In some implementations, the packer is retracted with the coiled tubing. In some implementations, the packer is retrieved from the wellbore.
- the coiled tubing is retracted from the first layer of the multi-layered reservoir to a second layer of the multi-layered reservoir.
- a second packer is installed and sealed. The same packer used in the previous layer can be refurbished and reused, or a new packer can be installed.
- the first layer is sealed from the second layer. That is, the second packer seals the annulus from the second layer.
- fluid is produced from the second layer through the coiled tubing production string.
- more than two production layers are present in the reservoir.
- subsequent layers can be produced.
- the coiled tubing is retracted from the second layer of the multi-layered reservoir to a third layer of the multi-layered reservoir.
- the third layer is uphole of the second layer. The second layer is then sealed from the third layer, and the third layer is produced through the coiled tubing production string.
- retracting the coiled tubing includes using a coiled tubing truck.
- a drill rig can be used to retract the coiled tubing.
- sealing the first layer from the second layer comprises installing a plug, for example, a cement plug.
- other sealing systems can be used, for example, a permanently installed packer.
- the first horizontal section and the second horizontal section each include open-hole completions. While primarily described as using open-hole completions, other completion methods can be used in any section of the wellbore without departing from this disclosure.
- FIG. 6 is a flowchart of an example method 600 of completing a well within a multilayered reservoir that can be used with aspects of this disclosure.
- a wellbore is formed.
- the wellbore can be formed using a drilling rig, coiled tubing drilling, or any other drilling method suitable for the desired wellbore trajectory.
- the wellbore includes a first horizontal section within a first layer of the reservoir and a second horizontal section within a second layer of the reservoir.
- the second horizontal section is uphole of the first horizontal section.
- the first horizontal section and the second horizontal section are connected by a vertical section or a deviated section.
- the first horizontal section is completed with an open-hole completion.
- the wellbore includes a third horizontal section within a third layer of the reservoir.
- the third horizontal section is uphole from the second horizontal section.
- the first layer is stratigraphically lower than the second layer and the second layer is stratigraphically lower than the third layer, but the methods and systems described herein can be applied to other reservoir topologies having greater of fewer layers, with different arrangements, without departing from this disclosure.
- a coiled tubing string is inserted into the wellbore such that a downhole end is within the first horizontal section.
- a packer is seated at a downhole end of the coiled tubing string. The packer is positioned such that it seals an annulus defined by an outer surface of the coiled tubing string and an inner surface of the wellbore. The packer seals the annulus from the first horizontal section. After the annulus is sealed, fluid is produced through the coiled tubing from the first horizontal section.
Landscapes
- Life Sciences & Earth Sciences (AREA)
- Engineering & Computer Science (AREA)
- Geology (AREA)
- Mining & Mineral Resources (AREA)
- Physics & Mathematics (AREA)
- Environmental & Geological Engineering (AREA)
- Fluid Mechanics (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Earth Drilling (AREA)
- Extraction Or Liquid Replacement (AREA)
Abstract
Description
Claims
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| SA521430926A SA521430926B1 (en) | 2019-05-23 | 2021-11-22 | Recovering hydrocarbons in multi-layer reservoirs with coiled tubing |
Applications Claiming Priority (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| US16/421,185 US10927654B2 (en) | 2019-05-23 | 2019-05-23 | Recovering hydrocarbons in multi-layer reservoirs with coiled tubing |
| US16/421,185 | 2019-05-23 |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| WO2020237154A1 true WO2020237154A1 (en) | 2020-11-26 |
Family
ID=71094817
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| PCT/US2020/034221 Ceased WO2020237154A1 (en) | 2019-05-23 | 2020-05-22 | Recovering hydrocarbons in multi-layer reservoirs with coiled tubing |
Country Status (3)
| Country | Link |
|---|---|
| US (1) | US10927654B2 (en) |
| SA (1) | SA521430926B1 (en) |
| WO (1) | WO2020237154A1 (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US11125026B2 (en) | 2018-10-24 | 2021-09-21 | Saudi Arabian Oil Company | Completing slim-hole horizontal wellbores |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US2986214A (en) * | 1956-12-26 | 1961-05-30 | Jr Ben W Wiseman | Apparatus for perforating and treating zones of production in a well |
| EP0796980A2 (en) * | 1996-03-20 | 1997-09-24 | Schlumberger Limited | Zonal isolation methods and apparatus |
| WO2001061146A1 (en) * | 2000-02-15 | 2001-08-23 | Exxonmobil Upstream Research Company | Method and apparatus for stimulation of multiple formation intervals |
| US20110048743A1 (en) * | 2004-05-28 | 2011-03-03 | Schlumberger Technology Corporation | Dissolvable bridge plug |
Family Cites Families (46)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US2738013A (en) | 1952-09-05 | 1956-03-13 | Oil Recovery Corp | Oil well tool |
| US3333635A (en) | 1964-04-20 | 1967-08-01 | Continental Oil Co | Method and apparatus for completing wells |
| US3527298A (en) | 1969-02-11 | 1970-09-08 | Drill Stem Testing & Coring Lt | Bottom hole sampler |
| US4498543A (en) | 1983-04-25 | 1985-02-12 | Union Oil Company Of California | Method for placing a liner in a pressurized well |
| US5287741A (en) | 1992-08-31 | 1994-02-22 | Halliburton Company | Methods of perforating and testing wells using coiled tubing |
| US5664628A (en) | 1993-05-25 | 1997-09-09 | Pall Corporation | Filter for subterranean wells |
| US5427177A (en) | 1993-06-10 | 1995-06-27 | Baker Hughes Incorporated | Multi-lateral selective re-entry tool |
| GB9313081D0 (en) | 1993-06-25 | 1993-08-11 | Pumptech Nv | Selective zonal isolation of oil wells |
| US5411082A (en) | 1994-01-26 | 1995-05-02 | Baker Hughes Incorporated | Scoophead running tool |
| US5449039A (en) | 1994-02-07 | 1995-09-12 | Canadian Occidental Petroleum, Ltd. | Apparatus and method for horizontal well fracture stimulation |
| NO325157B1 (en) | 1995-02-09 | 2008-02-11 | Baker Hughes Inc | Device for downhole control of well tools in a production well |
| EP0839255B1 (en) | 1995-07-25 | 2003-09-10 | Nowsco Well Service, Inc. | Safeguarded method and apparatus for fluid communication using coiled tubing, with application to drill stem testing |
| US5671809A (en) | 1996-01-25 | 1997-09-30 | Texaco Inc. | Method to achieve low cost zonal isolation in an open hole completion |
| US5730221A (en) | 1996-07-15 | 1998-03-24 | Halliburton Energy Services, Inc | Methods of completing a subterranean well |
| US6082454A (en) | 1998-04-21 | 2000-07-04 | Baker Hughes Incorporated | Spooled coiled tubing strings for use in wellbores |
| US6446727B1 (en) | 1998-11-12 | 2002-09-10 | Sclumberger Technology Corporation | Process for hydraulically fracturing oil and gas wells |
| AU3592800A (en) | 1999-02-09 | 2000-08-29 | Schlumberger Technology Corporation | Completion equipment having a plurality of fluid paths for use in a well |
| US6394184B2 (en) | 2000-02-15 | 2002-05-28 | Exxonmobil Upstream Research Company | Method and apparatus for stimulation of multiple formation intervals |
| US6615920B1 (en) | 2000-03-17 | 2003-09-09 | Marathon Oil Company | Template and system of templates for drilling and completing offset well bores |
| US6745834B2 (en) | 2001-04-26 | 2004-06-08 | Schlumberger Technology Corporation | Complete trip system |
| US7828068B2 (en) * | 2002-09-23 | 2010-11-09 | Halliburton Energy Services, Inc. | System and method for thermal change compensation in an annular isolator |
| US7267172B2 (en) | 2005-03-15 | 2007-09-11 | Peak Completion Technologies, Inc. | Cemented open hole selective fracing system |
| GB0911672D0 (en) | 2009-07-06 | 2009-08-12 | Tunget Bruce A | Through tubing cable rotary system |
| US20100319928A1 (en) | 2009-06-22 | 2010-12-23 | Baker Hughes Incorporated | Through tubing intelligent completion and method |
| US8220547B2 (en) | 2009-07-31 | 2012-07-17 | Schlumberger Technology Corporation | Method and apparatus for multilateral multistage stimulation of a well |
| WO2011034547A1 (en) * | 2009-09-21 | 2011-03-24 | Schlumberger Canada Limited | Multilateral system with rapidtrip intervention sleeve and technique for use in a well |
| US8555978B2 (en) | 2009-12-02 | 2013-10-15 | Technology Commercialization Corp. | Dual pathway riser and its use for production of petroleum products in multi-phase fluid pipelines |
| US20110192596A1 (en) | 2010-02-07 | 2011-08-11 | Schlumberger Technology Corporation | Through tubing intelligent completion system and method with connection |
| WO2012074614A1 (en) | 2010-12-03 | 2012-06-07 | Exxonmobil Upstream Research Company | Double hydraulic fracturing methods |
| US9513055B1 (en) | 2011-04-28 | 2016-12-06 | Differential Engineering Inc. | Systems and methods for changing the chemistry in heaps, piles, dumps and components |
| CA2749437C (en) * | 2011-08-17 | 2018-11-27 | Imperial Oil Resources Limited | Harvesting resource from variable pay intervals |
| US9249559B2 (en) * | 2011-10-04 | 2016-02-02 | Schlumberger Technology Corporation | Providing equipment in lateral branches of a well |
| MX353730B (en) | 2011-12-15 | 2018-01-25 | Raise Production Inc | Horizontal and vertical well fluid pumping system. |
| US9016391B1 (en) | 2012-08-29 | 2015-04-28 | Team Oil Tools, L.P. | Swellable packer with internal backup ring |
| WO2014089490A1 (en) | 2012-12-07 | 2014-06-12 | Halliburton Energy Services Inc. | Drilling parallel wells for sagd and relief |
| US9140119B2 (en) | 2012-12-10 | 2015-09-22 | Halliburton Energy Services, Inc. | Wellbore servicing fluids and methods of making and using same |
| CN106460491B (en) | 2014-05-29 | 2019-07-26 | 哈利伯顿能源服务公司 | Methods of Forming Multilateral Wells |
| AU2015268790B2 (en) | 2014-06-04 | 2017-11-09 | Halliburton Energy Services, Inc. | Whipstock and deflector assembly for multilateral wellbores |
| US9416638B2 (en) | 2014-06-24 | 2016-08-16 | Saudi Arabian Oil Company | Multi-lateral well system |
| US20160333680A1 (en) | 2015-05-12 | 2016-11-17 | Schlumberger Technology Corporation | Well re-fracturing method |
| US9493993B1 (en) | 2015-06-10 | 2016-11-15 | Ptech Drilling Tubulars Llc | Work string and method of completing long lateral well bores |
| US9644463B2 (en) | 2015-08-17 | 2017-05-09 | Lloyd Murray Dallas | Method of completing and producing long lateral wellbores |
| US10422220B2 (en) | 2016-05-03 | 2019-09-24 | Schlumberger Technology Corporation | Method and systems for analysis of hydraulically-fractured reservoirs |
| US20180119533A1 (en) * | 2016-10-28 | 2018-05-03 | Saudi Arabian Oil Company | Wellbore System With Lateral Wells |
| US10584556B2 (en) | 2016-12-06 | 2020-03-10 | Saudi Arabian Oil Company | Thru-tubing subsurface completion unit employing detachable anchoring seals |
| US10443379B2 (en) | 2017-06-15 | 2019-10-15 | Pursuit Techmologies Ltd. | Apparatus and method for testing an oil and/or gas well with a multiple-stage completion |
-
2019
- 2019-05-23 US US16/421,185 patent/US10927654B2/en active Active
-
2020
- 2020-05-22 WO PCT/US2020/034221 patent/WO2020237154A1/en not_active Ceased
-
2021
- 2021-11-22 SA SA521430926A patent/SA521430926B1/en unknown
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US2986214A (en) * | 1956-12-26 | 1961-05-30 | Jr Ben W Wiseman | Apparatus for perforating and treating zones of production in a well |
| EP0796980A2 (en) * | 1996-03-20 | 1997-09-24 | Schlumberger Limited | Zonal isolation methods and apparatus |
| WO2001061146A1 (en) * | 2000-02-15 | 2001-08-23 | Exxonmobil Upstream Research Company | Method and apparatus for stimulation of multiple formation intervals |
| US20110048743A1 (en) * | 2004-05-28 | 2011-03-03 | Schlumberger Technology Corporation | Dissolvable bridge plug |
Non-Patent Citations (2)
| Title |
|---|
| NASSER AL-ARIAMI ET AL: "Striving the Coil Tubing Limit Intervention on a Snake" Long Horizontal" Complex Gas Well", SPE, 31 March 2007 (2007-03-31), pages 20 - 21, XP055719281 * |
| R.E. COOPER ET AL: "Coiled Tubing in Horizontal Wells", INTERNATIONAL MEETING ON PETROLEUM ENGINEERING, 4 November 1988 (1988-11-04), XP055719364, DOI: 10.2118/17581-MS * |
Also Published As
| Publication number | Publication date |
|---|---|
| US10927654B2 (en) | 2021-02-23 |
| SA521430926B1 (en) | 2024-08-21 |
| US20200370401A1 (en) | 2020-11-26 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| AU2009210651B2 (en) | Apparatus, assembly and process for injecting fluid into a subterranean well | |
| AU2004234548B2 (en) | Method of creating a borehole in an earth formation | |
| US8413726B2 (en) | Apparatus, assembly and process for injecting fluid into a subterranean well | |
| US20160053597A1 (en) | Hydraulic fracturing while drilling and/or tripping | |
| US20190383127A1 (en) | Systems and Apparatuses for Separating Wellbore Fluids and Solids During Production | |
| US20180023375A1 (en) | Vertical drilling and fracturing methodology | |
| US10415361B1 (en) | Separating gas and liquid in a wellbore | |
| US10563486B2 (en) | Screen assembly for a resource exploration system | |
| US20230313636A1 (en) | Repairing wellbores with fluid movement behind casing | |
| US9714558B2 (en) | Open hole expandable junction | |
| US10927654B2 (en) | Recovering hydrocarbons in multi-layer reservoirs with coiled tubing | |
| US10392904B2 (en) | Lateral junction for use in a well | |
| Cales | The development and applications of solid expandable tubular technology | |
| CN112313392B (en) | Well construction and completion method | |
| CN103380262B (en) | The method keeping sufficient hydrostatic pressure in multiple intervals of the well in soft formation | |
| US20240287876A1 (en) | Performing a wellbore tieback operation | |
| US20240060400A1 (en) | Performing a wellbore tieback operation | |
| US20200095833A1 (en) | Screen assembly and method of forming a screen assembly | |
| US11619109B2 (en) | Methods of sealing polished bore receptacles by localized sealant injection | |
| US10450843B2 (en) | Screen assembly for a resource exploration system | |
| US20220235628A1 (en) | Controlling fluid flow through a wellbore tubular | |
| US12000247B2 (en) | Expandable tubulars to isolate production casing | |
| US12607091B2 (en) | Curing casing leak tool | |
| US11091979B2 (en) | Method and apparatus for setting an integrated hanger and annular seal before cementing | |
| US11927079B2 (en) | Gravel pack systems, methods to flow fluid out of a gravel pack system, and methods to provide fluid flow during a gravel packing operation |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| 121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 20733094 Country of ref document: EP Kind code of ref document: A1 |
|
| NENP | Non-entry into the national phase |
Ref country code: DE |
|
| 32PN | Ep: public notification in the ep bulletin as address of the adressee cannot be established |
Free format text: NOTING OF LOSS OF RIGHTS PURSUANT TO RULE 112(1) EPC (EPO FORM 1205A DATED 30/03/2022) |
|
| 122 | Ep: pct application non-entry in european phase |
Ref document number: 20733094 Country of ref document: EP Kind code of ref document: A1 |
|
| WWE | Wipo information: entry into national phase |
Ref document number: 521430926 Country of ref document: SA |
|
| WWE | Wipo information: entry into national phase |
Ref document number: 521430926 Country of ref document: SA |
|
| WWG | Wipo information: grant in national office |
Ref document number: 521430926 Country of ref document: SA |