WO2019151656A1 - Procédé et dispositif de distribution de sorties d'ess - Google Patents

Procédé et dispositif de distribution de sorties d'ess Download PDF

Info

Publication number
WO2019151656A1
WO2019151656A1 PCT/KR2018/016755 KR2018016755W WO2019151656A1 WO 2019151656 A1 WO2019151656 A1 WO 2019151656A1 KR 2018016755 W KR2018016755 W KR 2018016755W WO 2019151656 A1 WO2019151656 A1 WO 2019151656A1
Authority
WO
WIPO (PCT)
Prior art keywords
discharge
ess
unit
maximum
power
Prior art date
Application number
PCT/KR2018/016755
Other languages
English (en)
Korean (ko)
Inventor
김영욱
진보건
Original Assignee
효성중공업 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 효성중공업 주식회사 filed Critical 효성중공업 주식회사
Publication of WO2019151656A1 publication Critical patent/WO2019151656A1/fr

Links

Images

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/28Arrangements for balancing of the load in a network by storage of energy
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/38Arrangements for parallely feeding a single network by two or more generators, converters or transformers
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/12Monitoring or controlling equipment for energy generation units, e.g. distributed energy generation [DER] or load-side generation
    • Y04S10/123Monitoring or controlling equipment for energy generation units, e.g. distributed energy generation [DER] or load-side generation the energy generation units being or involving renewable energy sources
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/14Energy storage units

Definitions

  • the present invention relates to a method and apparatus for operating an ESS, and more particularly, to a method and apparatus for distributing power with optimum efficiency in a large-scale ESS having two or more unit ESSs.
  • Smart grid technology that combines IT technology with the existing power grid is emerging to form a smart power grid through efficient power management of electric power facilities, industrial facilities, and private facilities.
  • the smart grid environment is a hybrid network that combines various devices and combines wired and wireless.
  • the smart grid communication network construction method uses broadband wireless communication (Wimax) for trunk lines and high-speed power line communication (PLC) for subscriber networks. Management, electric vehicles, solar equipment monitoring, etc.) is being improved.
  • Wimax broadband wireless communication
  • PLC high-speed power line communication
  • the smart grid system aims to save power, and generally uses a method of turning on / off a specific device as shown in Korean Patent Laid-Open No. 2012-0097551 for power saving.
  • existing smart grid systems do not provide an appropriate way of distributing energy to efficiently use the supplied energy.
  • Energy storage system can play a key role in linking smart grid after converting renewable energy sources, which are being actively developed, into high quality power. In particular, it is necessary to link wind power generation and solar power generation systems with high output variability to the grid.
  • the principle of energy storage is to receive electrical energy from the power system, store it as ionization, kinetic energy, physical compression and chemical energy, convert it into electrical energy when needed, and supply it to the power system.
  • Medium and large energy storage devices can be classified into various types.
  • Lithium ion battery is a representative secondary battery, there is a separator and an electrolyte between the positive electrode and the negative electrode to store and discharge energy as lithium ions move.
  • it is still economically disadvantageous, its output characteristics and efficiency are good, and its range of application has recently been widened.
  • a plurality of unit BESSs having a battery pack composed of lithium ion batteries are provided for a single target site. In this way, the disadvantages of economics and the lifespan of lithium ion battery life are compensated for.
  • the charge / discharge power distribution of the entire ESS including a plurality of unit BESS requires a different method from the ESS having a single battery pack.
  • FR frequency regulation
  • An object of the present invention is to provide an efficient ESS output distribution method and apparatus when a plurality of unit ESSs are provided.
  • An object of the present invention is to provide a method and apparatus for distributing an ESS output capable of maximally maintaining a maximum output duration for a plurality of ESSs having different discharge rates and output limits.
  • An ESS output distribution method includes calculating a maximum discharge holding time of each unit ESS based on state of charge information of each unit ESS; Determining a first discharge sharing in accordance with the maximum discharge holding time; Determining a final discharge share as the maximum power that can be supplied for a unit ESS whose discharge power according to the determined first discharge sharing exceeds a maximum power that can be supplied; And when the unit ESS in which the final discharge sharing is determined exists, determining the second discharge sharing according to the maximum discharge holding time with respect to the remaining portions other than the corresponding unit ESS.
  • the method may further include determining a power demand of the grid or a load connected to the grid.
  • the second discharge sharing may be determined with respect to the power obtained by subtracting the sharing power of the unit ESSs in which the final discharge sharing is determined from the power demand.
  • the current remaining charge is calculated by applying the current SOC to the battery maximum capacity of each unit ESS, and the maximum power available for supplying each unit ESS to the current remaining charge is calculated.
  • the maximum discharge holding time can be calculated by applying.
  • the step of determining the final discharge sharing as the maximum power available for the unit ESSs that are the determination target of the second discharge sharing, and as a result, the If there is a unit ESS in which the final discharge sharing is determined to be the maximum power that can be supplied, the third discharge sharing may be determined according to the maximum discharge holding time with respect to the rest other than the corresponding unit ESS.
  • An ESS output distribution device for determining the discharge sharing of each unit ESS in a structure in which a plurality of unit ESS is connected to the system, for the power demand of the system and the unit ESS
  • An information obtaining unit obtaining the charging state information
  • a storage unit in which charge state information and maximum supply power of the unit ESSs are recorded
  • Based on the charging state information of each unit ESS the maximum discharge holding time of each unit ESS is calculated, the discharge sharing for determining the discharge power of the respective unit ESS, based on the calculated maximum discharge holding time of each unit ESS Decision unit;
  • a controller for instructing output to the determined discharge powers for each unit ESS and scheduling a next output distribution.
  • the process of determining respective discharge powers may include: determining a first discharge share according to the maximum discharge sustain time; Determining a final discharge sharing as the maximum power that can be supplied, when the discharge power according to the determined first discharge sharing exceeds the maximum power that can be supplied; And determining a second discharge sharing in accordance with the maximum discharge holding time for the remaining devices except for the device for which the discharge power is determined as the maximum power that can be supplied.
  • the maximum power maintainable time of N batteries can be maintained equally, thereby increasing the overall utilization of the battery, and consequently, the overall utilization of the ESS from the perspective of the ESS user. There is an advantage to increase.
  • the ESS output distribution method and apparatus of the present invention have the advantage that the entire ESS can be operated all at once with the maximum output in case of emergency while faithfully following the low load operation command value at all times, which is advantageous in terms of responsiveness. .
  • FIG. 1 is a block diagram showing the overall structure of a large-scale ESS in which the ESS output distribution method according to the spirit of the present invention can be performed.
  • FIG. 2 is a block diagram illustrating an ESS output distribution apparatus for performing an ESS output distribution method according to the inventive concept in the large-scale ESS of FIG. 1.
  • FIG. 3 is a flowchart illustrating a method of distributing ESS output according to an embodiment of the present invention.
  • FIG. 4 is a conceptual diagram illustrating a process of distributing an output based on SOC and maximum charging capacity of each unit ESS according to the spirit of the present invention, that is, a method of operating the ESS maximum duration according to the spirit of the present invention.
  • first and second may be used to describe various components, but the components may not be limited by the terms. The terms are only for the purpose of distinguishing one component from another.
  • first component may be referred to as the second component, and similarly, the second component may also be referred to as the first component.
  • a component When a component is referred to as being connected or connected to another component, it may be understood that the component may be directly connected to or connected to the other component, but there may be other components in between. .
  • the idea of the present invention is to distribute two or more individual ESSs for the optimal charging power for the power system.
  • the two or more individual ESSs are called a large-scale ESS, and each individual ESS is called a unit ESS. I'll call it.
  • it is suitable for each unit ESS to have its own PCS in the application of the idea of the present invention.
  • the large-scale ESS is not called a large-scale because the absolute scale is above a certain limit, but means that the large-scale ESS is larger than each unit ESS.
  • the large-scale ESS may simply be referred to simply as the ESS.
  • the ESS output distribution device is a strategy (algorithm) according to the spirit of the present invention, and is a device (server, etc.) for controlling the output of each PCS of each unit ESS.
  • the ESS output distribution device is an output control server for the large-scale ESS, and may transmit an output command for discharge to the PCS of each unit ESS included in the large-scale ESS.
  • the ESS output distribution device may be integrated with the PCS of the master unit ESS of the large-scale ESS, and may transmit an output command for discharge to the PCS of the slave unit ESS of the large-scale ESS.
  • FIG. 1 shows the overall structure of a large-scale ESS in which the ESS output distribution method according to the spirit of the present invention can be performed.
  • a real-time output distribution calculation of N parallel connected power conversion systems (PCSs) is performed by a power management system (PMS) of a large-scale ESS instead of a master PCS.
  • PMS power management system
  • the illustrated PMS is an ESS output distribution device that is different from the spirit of the present invention.
  • the illustrated large-scale ESS is composed of a plurality of unit ESSs 100 connected in parallel, and each unit ESS 110 is a PCS 110 and a battery management system (BMS) connected to the PCS 110. 120 and the battery 140 may be implemented. In addition, each PCS 110 may be controlled using a PMS 150.
  • BMS battery management system
  • the BMS 120 may be included in the battery module.
  • the BMS 120 may control the operation of the battery by acquiring basic data for checking the state of the battery 140.
  • the voltage, current, and temperature of the battery 140 may be sensed to transmit information to an upper device through communication. These functions are the information needed to safely operate the energy storage device.
  • the host device PCS 110 or PMS 150 can use this information to check the operating state and malfunction of the battery, and protect the battery module from abnormal conditions through a circuit that protects overvoltage, overcurrent and overtemperature. have.
  • the PCS 110 may be implemented to perform power supply to a load using a commercial power source.
  • a generator not shown
  • power is stored (charged) in a lithium-polymer (lithium-ion) battery storage device through a bidirectional power converter. can do.
  • the battery module may be a concept including the BMS 120 and the battery 140.
  • the battery module is constructed using a lithium-polymer (lithium-ion) battery that has high efficiency, long life, and instant charging and discharging characteristics.
  • the energy storage system has been remarkably developed due to the improvement of instantaneous charge and discharge characteristics of lithium-polymer batteries and the large capacity of the batteries.
  • the PMS 150 can increase the overall utilization of the battery by equally maintaining the maximum output maintainable time of the N batteries by using the output distribution method, and consequently, the ESS user's viewpoint. Can increase the overall utilization of the ESS.
  • the PMS 150 may be implemented to communicate information necessary for energy charge and discharge control to the PCS 110 through communication with the PCS 110.
  • the PMS 150 receives various information about the energy state of the PCS 110 and the BMS 120, battery cell voltage, current, and temperature, and determines a protection function for overvoltage, overcurrent, and overtemperature. Can be protected from abnormal conditions.
  • the charging or discharging on / off signal of the battery module may be transmitted to the PCS 110 to command the charging or discharging of the battery module.
  • the PMS 150 When the PMS 150 normally distributes the output command, the PMS 150 distributes the output command in a direction that maximizes the time at which the large-scale ESS can perform the maximum output operation in consideration of the output of the current SOC and PCS of each unit ESS.
  • a PMS for a large ESS is not provided, and the master PCS can perform real-time output distribution calculations of PCSs (ie those for each unit ESS) connected in parallel to the system of the large ESS.
  • the master PCS is a PCS provided in one of the unit ESSs provided in the large-scale ESS.
  • FIG. 2 illustrates an example of a detailed structure of an ESS output distribution apparatus, that is, a PMS 150 that performs an ESS output distribution method according to the inventive concept in the large-scale ESS of FIG. 1.
  • the illustrated ESS output distribution device 150 includes: an information acquisition unit 152 for acquiring power demand (consumption state information) of the system to which power is supplied and charging state information for unit ESSs (100 of FIG. 1); A storage unit 154 in which charge state information (SOC and maximum charge capacity) and maximum supply power of the unit ESSs 100 are recorded; Based on the state of charge information of each of the unit ESS 100, calculate the maximum discharge holding time of each unit ESS 100, based on the calculated maximum discharge holding time of each unit ESS (100) A discharge sharing determiner 156 that determines discharge powers of the unit ESSs 100; And a controller 158 for instructing each of the unit ESSs 100 to output the determined discharge powers and scheduling a next output distribution.
  • the information acquisition unit 152 monitors the electrical characteristics (voltage / current, etc.) of the PCS 110 input / output terminals of the unit ESS 100 to calculate charging state information of the unit ESSs, or the units Charge status information may be received from the BMS 120 of the ESS 100.
  • the charge state information may include a state of charge (SOC) and a maximum charge capacity, and may further include a state of health (SoH).
  • the information acquisition unit 152 calculates electrical characteristics (voltage, current, etc.) detected at points on a power supply line to a grid or a load, and thus information on power demand of a load connected to the grid, that is, power consumption. Information about the state can be calculated.
  • the storage unit 154 may store SOCs and maximum charging capacities of each unit ESS 100 measured at predetermined cycles (monitoring time intervals) as the charging state information.
  • the controller 158 may maintain a previous output instruction according to the monitoring time interval (that is, hold the change to the next time) or change the output instruction to output the discharge powers determined by the discharge sharing determiner 156. . According to an implementation, the controller 158 may not only output distribution between the unit ESSs 100 according to the spirit of the present invention, but also power input / output of each unit ESS 100 according to power demand / supply expectation of a system or a load. You can schedule the output.
  • the discharge sharing determiner 156 may determine a power demand of a grid or loads connected to the grid at the next monitoring time interval.
  • the discharge sharing determiner 156 may determine the discharge powers (final discharge sharing) of each unit ESS 100 according to the flowchart of FIG. 3 described later according to the monitoring time interval. At this time, the final discharge share of each unit ESS 100 is determined for the determined power demand in the monitoring time interval.
  • FIG. 3 is a flowchart illustrating a method of distributing ESS output according to an embodiment of the present invention.
  • the illustrated ESS output distribution method may include determining a power demand of a grid or a load connected to the grid (S10); Calculating maximum discharge holding times of each unit ESS based on the state of charge information of each unit ESS (S110); Determining a first discharge sharing in accordance with the maximum discharge holding time (S120); Determining a final discharge share as the maximum power that can be supplied to the unit ESS whose discharge power according to the determined first discharge burden exceeds the maximum power that can be supplied (S130); If there is a unit ESS in which the final discharge share is determined (the discharge power is determined by the maximum power that can be supplied) (S190), determining the second discharge share according to the maximum discharge holding time for the remaining units except for the unit ESS ( S200) may be included.
  • FIG. 4 is a conceptual diagram illustrating a process of distributing an output based on SOC and maximum charging capacity of each unit ESS according to the spirit of the present invention, that is, a method of operating the ESS maximum duration according to the spirit of the present invention.
  • the maximum operating time (MW) of each ESS converter and the SOC (MWh) of the battery are used to calculate the time that can be operated at the current maximum output, respectively, and the output using the reciprocal of this time as the priority. Allocate Next, if this allocation exceeds the maximum output of the ESS PCS (inverter or converter), the maximum output is determined as the limit discharge as the final discharge share of the ESS, and redistributed using the remaining allocation minus the final discharge share. If the above distribution is continued, it is always possible to maintain a state in which the maximum number of times that a plurality of ESSs can operate at the maximum output.
  • ESS PCS inverter or converter
  • the power demand of the grid or loads connected to the grid may be determined at the above-described predetermined monitoring time interval.
  • the power consumption pattern of each load is derived, and the derived power consumption pattern is applied to the upcoming monitoring time interval, so as to adjust the power demand of the load. Forecast and accumulate the power demand forecasts for all loads to yield the system's power demand (expected).
  • the power demand in an upcoming monitoring time interval may be determined from a separate external server that plans the power demand of the system or predicts the power demand of the system.
  • a current amount of charge is applied by applying a current SOC to a battery maximum capacity of each unit ESS, and the current remaining amount is calculated.
  • the maximum discharge holding time can be calculated by applying the maximum output of the PCS (ie, inverter) of each unit ESS to the amount of charge.
  • the current remaining charge is calculated by multiplying the maximum capacity of the battery of each unit ESS by the current SOC (%), and the current remaining charge is the maximum of the PCS of the unit ESS (that is, the interversor).
  • the time for discharging to the output (that is, the maximum discharge holding time) is calculated.
  • the maximum capacity of 5 MWh of the battery is multiplied by 50% as the current SOC, and 2.5 MWh is calculated from the remaining charge, and 2.5 MWh is 1 MW, the maximum output of the inverter.
  • 2.5 hours that is, 150 minutes
  • the discharge time can be calculated as the maximum discharge holding time (the discharge time at the current maximum output).
  • a synthesized output target value for determining the power demand of the grid or the loads connected to the grid determined in the step S10 is determined, and the combined output target value is determined solely for each unit ESS.
  • the combined output target value of 8MW is distributed according to the ratio of the maximum discharge holding time (currently dischargeable time at the maximum output) of all the unit ESSs, and ⁇ 4.597701, 1.83908, 0.91954, 0.45977, 0.183908 ⁇ .
  • the discharge share of was determined.
  • next discharge sharing determination procedure means the second discharge sharing determination step (S200).
  • step S130 When the maximum power is not exceeded in step S130, the unit ESS is not taken for the corresponding unit ESS, and the process proceeds to the next unit ESS (S148).
  • each unit ESS is represented by n
  • the total number of unit ESSs is represented by N (that is, N is 5 in FIG. 4).
  • the first discharge sharing for the first unit ESS is 4.597701MW, which is greater than the inverter output of 1MW for the first unit ESS, and according to steps S140 and S145, the final discharge sharing for the first unit ESS is the maximum output of 1MW. Confirmed.
  • the second discharge sharing is determined only for the remaining unit ESSs except for the unit ESSs in which the final discharge sharing is determined.
  • the second discharge sharing is determined for the power obtained by subtracting the sharing power of the unit ESSs whose final discharge sharing is determined from the power demand.
  • the second discharge sharing is determined for 7MW minus the final discharge sharing 1MW of the first unit ESS (INV # 1) where the final discharge sharing is determined from 8MW of power demand (synthetic output target value), but the first unit ESS (INV) is determined.
  • the second discharge share of ⁇ 3.783784, 1.891892, 0.945946, 0.378378 ⁇ was determined by determining the ratio of the maximum discharge holding times of units 2 to 5 except for # 1) ⁇ 60: 30: 15: 6 ⁇ .
  • step S200 of determining the second discharge sharing that is, after performing the step S200
  • S128 shown in FIG. 3. S130, S140, S145, S148, and S190 may be repeated.
  • the final maximum supplyable power of the unit ESS PCS is determined for the unit ESS. It is decided by discharge sharing.
  • the final discharge sharing of the second unit ESS (INV # 2) among the four unit ESSs in which the second discharge sharing is determined is determined to be 2MW of the maximum power that can be supplied by the corresponding ESS PCS (inverter).
  • step of determining the third discharge sharing in the same process is performed on the remaining unit ESSs. Can be. Determining this next discharge share is performed until there are no unit ESSs whose final discharge share has not been determined.
  • unit ESS 150 ESS output distribution device
  • the present invention relates to a method and apparatus for operating an ESS, and can be used in the field of ESS.

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Supply And Distribution Of Alternating Current (AREA)
  • Charge And Discharge Circuits For Batteries Or The Like (AREA)

Abstract

La présente invention concerne un procédé de distribution de sorties d'ESS pour déterminer une part de décharge d'ESS unitaires respectifs dans une structure dans laquelle une pluralité de systèmes de stockage d'énergie (ESS) unitaires sont connectés à un système, qui peut comprendre les étapes consistant à : calculer le temps de décharge maximal d'ESS unitaires respectifs sur la base d'informations d'état de charge d'ESS unitaires respectifs ; déterminer une première part de décharge en fonction du temps de décharge durable maximal ; confirmer, comme puissance maximale pouvant être fournie, une part de décharge finale pour un ESS unitaire dont la puissance de décharge, conformément à la première part de décharge déterminée, dépasse la puissance maximale pouvant être fournie ; et déterminer une deuxième part de décharge en fonction du temps de décharge durable maximal pour le reste à l'exclusion de l'ESS unitaire correspondant, si l'ESS unitaire pour lequel la part de décharge finale a été confirmée existe.
PCT/KR2018/016755 2018-01-31 2018-12-27 Procédé et dispositif de distribution de sorties d'ess WO2019151656A1 (fr)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
KR10-2018-0012467 2018-01-31
KR1020180012467A KR20190093034A (ko) 2018-01-31 2018-01-31 Ess 출력 분배 방법 및 장치

Publications (1)

Publication Number Publication Date
WO2019151656A1 true WO2019151656A1 (fr) 2019-08-08

Family

ID=67479826

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/KR2018/016755 WO2019151656A1 (fr) 2018-01-31 2018-12-27 Procédé et dispositif de distribution de sorties d'ess

Country Status (2)

Country Link
KR (1) KR20190093034A (fr)
WO (1) WO2019151656A1 (fr)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102165619B1 (ko) * 2020-03-02 2020-10-15 한국과학기술정보연구원 최적의 전력효율을 유지하는 전력 관리 시스템 및 이의 운용 방법
KR102450205B1 (ko) * 2020-05-14 2022-10-04 효성중공업 주식회사 전력 공급 시스템의 출력 분배 방법
CN117254494B (zh) * 2023-09-27 2024-03-22 南方电网调峰调频(广东)储能科技有限公司 多站点协同储能集控调度系统及方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1032936A (ja) * 1996-07-12 1998-02-03 Tokyo R & D:Kk 電源装置の制御システムおよび制御方法
KR20160094228A (ko) * 2015-01-30 2016-08-09 삼성에스디아이 주식회사 배터리 시스템 및 이를 포함하는 에너지 저장 시스템
JP2016152718A (ja) * 2015-02-18 2016-08-22 三菱重工業株式会社 充放電制御装置、移動体及び電力分担量決定方法
KR20170073939A (ko) * 2015-12-21 2017-06-29 삼성전자주식회사 배터리 제어 방법, 배터리 제어 장치, 및 배터리 팩
KR20170110885A (ko) * 2016-03-24 2017-10-12 주식회사 비긴스 배터리 방전 제어 방법 및 장치

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101237787B1 (ko) 2011-02-25 2013-02-28 컨스핀솔루션(주) 인터넷과 연동하는 스마트그리드 제어장치 및 방법

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1032936A (ja) * 1996-07-12 1998-02-03 Tokyo R & D:Kk 電源装置の制御システムおよび制御方法
KR20160094228A (ko) * 2015-01-30 2016-08-09 삼성에스디아이 주식회사 배터리 시스템 및 이를 포함하는 에너지 저장 시스템
JP2016152718A (ja) * 2015-02-18 2016-08-22 三菱重工業株式会社 充放電制御装置、移動体及び電力分担量決定方法
KR20170073939A (ko) * 2015-12-21 2017-06-29 삼성전자주식회사 배터리 제어 방법, 배터리 제어 장치, 및 배터리 팩
KR20170110885A (ko) * 2016-03-24 2017-10-12 주식회사 비긴스 배터리 방전 제어 방법 및 장치

Also Published As

Publication number Publication date
KR20190093034A (ko) 2019-08-08

Similar Documents

Publication Publication Date Title
WO2015102396A1 (fr) Procédé et appareil de distribution électrique dans un système de stockage d'énergie
KR20160143092A (ko) 배터리 제어 시스템 및 방법
WO2012033254A1 (fr) Système de stockage d'énergie et procédé de commande associé
KR101375330B1 (ko) 배터리 시스템, 이의 제어방법 및 배터리 시스템을 포함하는 에너지 저장 시스템
EP2658027A1 (fr) Système d'alimentation électrique
WO2018016735A1 (fr) Système de batteries
WO2019151656A1 (fr) Procédé et dispositif de distribution de sorties d'ess
WO2020040350A1 (fr) Nouveau système de production d'énergie hybride à énergie renouvelable et son procédé de production d'énergie
KR20110084754A (ko) 센싱보드가 내장된 배터리팩과 그것을 채용한 전력저장시스템
WO2013133592A1 (fr) Système et procédé de commande de fréquence
KR20170019971A (ko) 배터리 팩 및 이를 포함하는 에너지 저장 시스템
WO2020013614A1 (fr) Procédé d'opération de charge et de décharge de sse
CN112467769A (zh) 一种模块化预安装储能系统
CN217642739U (zh) 一种储能电池系统及储能设备
WO2018230831A1 (fr) Système de stockage d'énergie
CN111555321A (zh) 储能联合火电调频中pcs的功率分配方法及装置
WO2019221361A1 (fr) Système de gestion d'énergie
WO2022196846A1 (fr) Système de gestion hiérarchique de système de stockage d'énergie
CN202888913U (zh) 一种分布式新能源电力系统的蓄能控制装置
WO2018135716A1 (fr) Dispositif de stockage d'énergie et système de stockage d'énergie le comprenant
CN110445162B (zh) 储能装置
CN215772577U (zh) 供电系统
WO2023039888A1 (fr) Procédé de charge, dispositif de charge et système de charge pour batterie d'alimentation
WO2021230607A1 (fr) Procédé de distribution de sortie d'un système d'alimentation électrique
CN114938066A (zh) 一种数据中心供电系统及方法

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 18903482

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase