WO2019080824A1 - 一种城市轨道交通工程新型铺轨机及其施工方法 - Google Patents

一种城市轨道交通工程新型铺轨机及其施工方法

Info

Publication number
WO2019080824A1
WO2019080824A1 PCT/CN2018/111341 CN2018111341W WO2019080824A1 WO 2019080824 A1 WO2019080824 A1 WO 2019080824A1 CN 2018111341 W CN2018111341 W CN 2018111341W WO 2019080824 A1 WO2019080824 A1 WO 2019080824A1
Authority
WO
WIPO (PCT)
Prior art keywords
track
trolley
laying machine
lifting
new
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Ceased
Application number
PCT/CN2018/111341
Other languages
English (en)
French (fr)
Inventor
郑康海
黄新
韩建东
刘习生
孙军溪
赵文君
徐明发
陈付平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Civil Engineering Co Ltd of CREC
Huahai Engineering Co Ltd of Shanghai Civil Engineering Co Ltd of CREC
Original Assignee
Shanghai Civil Engineering Co Ltd of CREC
Huahai Engineering Co Ltd of Shanghai Civil Engineering Co Ltd of CREC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Civil Engineering Co Ltd of CREC, Huahai Engineering Co Ltd of Shanghai Civil Engineering Co Ltd of CREC filed Critical Shanghai Civil Engineering Co Ltd of CREC
Priority to DE212018000090.5U priority Critical patent/DE212018000090U1/de
Priority to US16/333,991 priority patent/US20210332533A1/en
Publication of WO2019080824A1 publication Critical patent/WO2019080824A1/zh
Anticipated expiration legal-status Critical
Ceased legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B29/00Laying, rebuilding, or taking-up tracks; Tools or machines therefor
    • E01B29/16Transporting, laying, removing, or replacing rails; Moving rails placed on sleepers in the track

Definitions

  • the invention relates to engineering technology science, in particular to a new rail laying machine for urban rail transit engineering and a construction method thereof.
  • the track laying machine equipment mainly has three types: assembling fixed door type structure, manual and hydraulic fixed distance variable span type structure and automatic retrieval electric stepless variable cross door type structure.
  • the three types of track laying machines need to lay temporary running rails for the track laying machine.
  • Temporary walking rails are pre-layed on the side walls of the tunnel or structural floor on both sides of the main line.
  • the gauges are generally 2800mm, 3000mm, 3100mm, 3800mm, etc.
  • the temporary running rails are fixed on the tunnel side by special steel structural buttresses. On the wall or structural floor. Due to the narrow space of the underground tunnel of the urban rail transit project, the installation of temporary running rails allows the narrow space to reduce the working space.
  • the laying of the rails during the construction of the track requires the support of the lateral support to ensure the track state, the lateral support and the temporary travel track. Conflicts have occurred, which has reduced the construction space of the main track rails.
  • the structure of the temporary travel rail is different for different tunnel structures (the circular tunnel is installed on the side wall, the horseshoe tunnel and the rectangular tunnel are installed on the structural bottom plate, and some structures need to be installed on one side of the side wall and one side on the side.
  • the concrete construction of the track bed is changed from one completion to two constructions (first casting the integrated track bed, then pouring the road bed gutter), resulting in the formation of the concrete track bed and the ditch.
  • Structural joints as the laying of the main track continues to advance forward, a large number of temporary running rails are used in reverse circulation, which makes the construction of the main track both spatially and temporally; at the same time, the installation of temporary running rails needs to be in the building.
  • Perforated fixed walking track buttress on the structure affects the appearance and performance of the structure to a certain extent; when encountering special sections such as stations and civil defense doors, the temporary running track is caused by the change of the temporary running track gauge due to the limitation of the structural boundary.
  • Construction work occupying the effective time and space of the track construction to varying degrees; due to the need to lay temporary running track, the operation process is added to the positive track construction, the construction investment is increased, and the construction cost and personnel labor intensity are increased.
  • the existing track construction track laying machine is widely used in practical applications, but it brings many constraints and influences to the construction of the main line.
  • the structure of plate track bed and prefabricated assembly structure will become the mainstream.
  • the adaptability, full-featured and flexible requirements of the track-laying equipment have higher requirements, and it is an inevitable trend to provide more working space and effective working time for the track laying. Therefore, it is possible to develop an energy-saving and environment-friendly hoisting and transshipment of materials such as track materials, prefabricated products, and assembled structures in the tunnel without the need to lay temporary traveling rails, and the rapid transition of the whole machine without disintegration and simple separation can realize long-distance transportation transfer.
  • the new type of track laying machine has become an inevitable trend and a top priority.
  • the object of the present invention is to solve the problem that the current track construction must lay the temporary running track on both sides of the main line, and at the same time improve the transportation efficiency and safety, and design a new rail tracker for urban rail transit engineering and its construction method.
  • the device comprises a lifting walking work trolley, a connecting truss beam, a crawler running mechanism and a supporting structure.
  • the new track laying machine is composed of two lifting walking working trolleys and connecting truss beams connecting two lifting traveling trolleys, and lifting the walking operation trolley by A walking frame trolley, a horizontal frame beam for longitudinal movement, and a support structure capable of horizontally extending to the sides of the main rail and having a vertical lifting walking trolley at the front and rear ends of the horizontal frame beam, the trolley is driven by the trolley
  • the support structure for a vertical lifting machine transitions laying new track in the positive and non-positive line of the linear track.
  • the outer side of the horizontal frame beam is provided with a bolt hook for connecting the new track laying machine and the tractor.
  • the upper reinforcing structure frame of the horizontal frame beam is provided with a hydraulic pumping station and a power cable reel for the hydraulic operation of the lifting work trolley, and the truss beam is connected.
  • Two lifting trolleys are connected to form a complete machine, and a lifting hoisting trolley for hoisting materials is installed on the connecting truss beam. The lifting hoisting trolley is pulled by the hoisting machine to walk along the truss beam to achieve precise lifting of the track material and In place.
  • the horizontal frame beam is composed of a plurality of longitudinal beams, a plurality of beams and an upper reinforcing structure.
  • the longitudinal beam is both a structural beam of a horizontal frame beam and a guide column of a moving carriage moving forward and backward.
  • the beam is both a structural beam of a horizontal frame beam and a lifting traveling trolley.
  • the vertical support structure realizes horizontal horizontally retractable guide sleeve structure, and a reinforcing structure is installed on the upper part of the horizontal frame beam to ensure the longitudinal and lateral rigidity of the horizontal frame beam, and a horizontal expansion mechanism perpendicular to the line direction is installed in the beam, and the horizontal expansion mechanism is
  • the guide post and the vertical guide sleeve are composed.
  • the horizontal telescopic mechanism is matched by the guide column and the guide sleeve structure, and the horizontal lateral expansion and contraction is realized by the hydraulic drive cylinder, and the vertical support structure is installed in the guide sleeve, and the vertical support structure is composed of the second guide post, the first guide post and the first drive
  • the hydraulic cylinder is composed of a second guide post or a guide sleeve of the first guide post, and the vertical support structure is realized by driving the first guide post and the second guide post to extend step by step through the first hydraulic drive cylinder.
  • the walking trolley consists of a frame structure, a track running wheel and a crawler running mechanism installed in the center of the plane frame structure of the running trolley.
  • the frame structure is composed of two guiding sleeves and a track running wheel and a connecting structural member, and the walking trolley passes the guiding sleeve set in the lifting walk.
  • On the horizontal frame beam of the trolley the forward and backward movement of the trolley along the horizontal frame beam is realized by the second hydraulic drive cylinder.
  • the running trolley track is driven by the motor to walk on the positive track, and is installed at the center of the upper plane of the trolley.
  • There is a crawler running mechanism and the crawler running mechanism is fixed on the lower structural bottom plate of the running trolley through the rotating disc.
  • the crawler running mechanism realizes up and down expansion and contraction through the guide sleeve guide pillar device, and the telescopic guide sleeve is fixed on the rotary disc, and the steering is mounted on the rotary disc.
  • the ball pin is driven, and the up-and-down telescopic movement of the guide post is realized by the third hydraulic drive cylinder, and the crawler running mechanism is connected by the pin shaft and the guide post, and the crawler running mechanism is composed of a chassis, a drive wheel, a guide wheel, a roller, a pulley and a crawler.
  • the hydraulic drive motor is composed of a wraparound motor on the upper plane of the trolley. Rotating the turntable center line of the car, the turntable by rollers revolving about the center of the car, there are cutter mounted on the loading base, and is connected by a hinge pin connected to joist.
  • the connecting truss beam is composed of steel pipe welding, which is divided into three sections.
  • the section is "chair" type, which is arranged symmetrically in two sides.
  • Each section is connected by a connecting pin, and a track for hoisting trolley is installed on the connecting truss beam.
  • a hoist and a pulley block are installed at both ends of the connecting truss beam for pulling the hoisting trolley to move forward and backward along the track, and hydraulically driven hydraulic pumping stations and cable winding wires are installed on the upper reinforcing structure of the horizontal frame beam of the lifting traveling trolley.
  • the disc is used to provide hydraulic and electrical power to the new track laying machine.
  • the construction method using the track laying machine is as follows: when the new track laying machine removes the rail row from the rail transport vehicle, the first horizontal lifting and vertical support structure of the lifting traveling trolley lifts the new rail laying machine to the lifting rail as a whole. The height of the material is pushed to the new track-laying machine to the underside of the truss beam, and the hoisting trolley is used to lift the track material away from the flatbed transporter and the material support. The flat transporter exits the new track-laying machine.
  • the vertical support structure of the lifting trolley is operated to lower the new track laying machine together with the track material, so that the new track laying machine travels smoothly onto the main track to complete the unloading; the new track laying machine moves in the positive track to the installation position, currently When the side lifts the walking trolley to reach the end of the main track, the vertical support structure of the lifting trolley moves the traveling trolley out of the track, and the longitudinal movement control device that operates the lifting trolley moves the trolley out of the main track.
  • the operation track control device lowers the track running mechanism on the structural floor and restores the lifting mechanism Shrink the initial position, continue to let the new track laying machine move forward to reach the rail row design and installation position, remove the rail material, connect the rail, install the rail row, temporarily support and fix the new installation rail row, reverse operation, new railing machine lifting, mechanism conversion, vertical
  • the mobile control device returns the new track laying machine to the positive track, and continues to walk to the unloading position again to carry out the lifting and arranging the next cycle.
  • Synchronous reverse operation 1.
  • the vertical support structure with horizontal expansion and contraction of the traveling trolley is used to recover the vertical support upwards.
  • the 1st and 2nd lifting trolleys are connected with the truss beam and the suspended track material.
  • Slowly descending, and slowly descending on the positive track continue to reverse operation 1.
  • the 2nd and 2nd lifted walking trolleys have a horizontally telescopic vertical support structure to recover the vertical support and return to the new track laying machine. , locking operation, adjusting the vertical support structure with horizontal expansion and contraction of the traveling trolley of No.1 and No.2, so that the distance of the vertical support section of the unified horizontal section is greater than the width of the track material;
  • Operation of the new track laying machine running device control system enables the new track laying machine hoisting track material to travel along the positive track to the design and installation position.
  • the new track laying machine hoisting track material is completed by concrete pouring, uncast concrete section, and rail alignment adjustment. And the fixed section reaches the end of the positive track;
  • Synchronous operation lifting hoisting trolley slowly descends the rail row to the design and installation height, and moves a small lifting hoisting trolley before and after, and stops the operation after the alignment of the newly installed rail row and the installed rail row is completed;
  • Synchronous operation 1, 2 lifted the trolley track travel control device, so that the new track laying machine returns to receive the newly transported rail row location, ready for another rail lifting operation;
  • step A-step C Repeat all the actions of step A-step C to complete the re-hoisting and transportation of the rail row, installation and new rail-laying machine in place, and so on.
  • the specific construction method is as follows: the new track laying machine working surface transition operation, when there is a need to transfer to the new working surface after the completion of one working surface of the track construction, there are several situations: one is the working position of another construction line in the same direction, and the other is The operation position of the other two construction lines in the opposite direction, the new track-laying machine transition is realized by the traction of the orbital tractor through the paved first ballast and the second ballast, and the transfer of the work surface is carried out according to the following steps. :
  • On-site operation position Retract the horizontal expansion device of the vertical support structure of the new type of track-laying machine and the vertical support structure of the traveling trolley to the travel transfer position, and retract the vertical support structure to the upper limit.
  • the position shifting position is locked, the power supply of the new track laying machine is removed, the cable is wound up into the cable reel, and the connection between the new track laying track wheel and the running drive reducer is removed, so that it is in a neutral state, and the new track laying machine
  • the rail tractor is connected by connecting the towing bar, and the rail tractor is started, so that the rail tractor pulls the new track laying machine and slowly drives to the second ballast position.
  • the rail tractor pulls the new track laying machine through the second track, when the new track laying machine
  • the tail stops moving, and the first track and the second open channel are moved to the side track, and the track tractor is started, so that the track tractor pushes the new track laying machine into the second pass, and the first turn enters the positive track.
  • Line arrive at the new work surface, complete the transfer operation;
  • the first track and the second channel open the side track, and the track tractor is started, so that the track tractor pushes the new track machine through the second turn and the first turn to enter the main line.
  • the vehicle returns to the side of the road.
  • the tail of the orbital tractor reaches the position of the first road, the vehicle stops, the first track is pulled to resume the forward passage, and the new track laying machine is driven to the working surface.
  • the invention has the advantages of:
  • the new type of track laying machine adopts a combination of symmetrical structure type, and the structure can be assembled and disassembled by the assembly module, which is convenient for operation, driving, transshipment and transfer transportation;
  • the new track laying machine uses electric drive and track construction to share power with other operations, saving energy, the total vehicle quantity is light, and the environmental protection advantage is more prominent;
  • the new type of track-laying machine uses the main track to travel, and it is not necessary to lay the auxiliary temporary track to work more efficiently.
  • the track is used for a wider range of adaptation;
  • the new track laying machine cancels the temporary auxiliary track, reduces the construction process, reduces the construction input and construction cost, and reduces the construction safety hazard;
  • the new track laying machine adopts the positive track walking, completely cancels the temporary running track laying, avoids occupying the structural space of the track bed, realizes the construction of the track bed concrete once, improves the concrete construction quality, and solves the phenomenon of water seepage in the construction bed of the track bed;
  • the new track laying machine walks on the positive track, is not affected by the structural section, and is suitable for various working conditions of the track laying. Due to the hoisting of the truss beam, the working space is large and the lifting capacity is large.
  • the lifting walking trolley adopts a horizontally retractable structure design, and the ultra-wide material such as the pre-spelling ballast can be hoisted, and has wide applicability and strong versatility.
  • Figure 1 is a front elevational view of a novel track laying machine in accordance with an embodiment of the present invention.
  • Figure 2 is a side elevational view of a novel track laying machine in accordance with an embodiment of the present invention.
  • FIG. 3 is a schematic view of a connecting truss truss beam in an embodiment of the present invention.
  • FIG. 4 is a schematic view of a connecting truss truss beam in an embodiment of the present invention.
  • Figure 5 is a schematic view of a track running trolley in an embodiment of the present invention.
  • Figure 6 is a side elevational view of the track running trolley in the embodiment of the present invention.
  • Figure 7 is a schematic view of a crawler running mechanism in an embodiment of the present invention.
  • Figure 8 is a side elevational view of the track running mechanism in accordance with an embodiment of the present invention.
  • Figure 9 is a plan view of the crawler running mechanism in the embodiment of the present invention.
  • Fig. 10 is a schematic view showing the horizontal frame beam of the traveling trolley in the embodiment of the present invention.
  • Figure 11 is a side elevational view of the horizontal frame beam of the lifting trolley in the embodiment of the present invention.
  • Figure 12 is a schematic view showing the vertical support horizontal expansion structure in the embodiment of the present invention.
  • FIG. 13 is a schematic structural view of a vertical support telescopic guide sleeve guide post according to an embodiment of the present invention.
  • Figure 14 is a side elevational view showing the structure of the vertically supported telescopic guide sleeve guide post in the embodiment of the present invention.
  • Figure 15 is a schematic view showing the guide bush of the vertical support guide post in the embodiment of the present invention.
  • Figure 16 is a schematic view of a vertical telescopic guide column mechanism in an embodiment of the present invention.
  • Figure 17 is a schematic view showing the assembly of a horizontal telescopic guide post and a horizontal frame beam in the embodiment of the present invention.
  • Figure 18 is a schematic view showing the structure of a hoisting trolley in the embodiment of the present invention.
  • Figure 19 is a schematic view showing the installation of a cable reel and a hydraulic pump station in an embodiment of the present invention.
  • Figure 20 is a schematic view showing the arrival of a new type of rail-laying machine to the working surface of the track tractor in the embodiment of the present invention.
  • Figure 21 is a schematic view showing the rail track of the rail tractor in the embodiment of the present invention.
  • Figure 22 is a schematic view of the waiting for the feeding rail after the new track laying machine is lifted to the upper working point in the embodiment of the present invention.
  • Figure 23 is a side elevational view of the new rail laying machine waiting for the feeding rail after it is raised to the upper working point in the embodiment of the present invention.
  • Fig. 24 is a schematic view showing the feeding operation of the rail tractor pushing the rail and delivering the vehicle in the embodiment of the present invention.
  • Figure 25 is a schematic view showing the feeding operation of the rail row completely entering the lower part of the new track laying machine in the embodiment of the present invention.
  • Figure 26 is a side elevational view of the feeding operation in the embodiment of the present invention in which the rail row completely enters the lower portion of the new track laying machine.
  • Figure 27 is a schematic view showing the operation of lifting the rails of the lifting and hoisting trolley of the new type of track laying machine in the embodiment of the present invention.
  • Figure 28 is a side elevational view of the lifting operation of the new type of track laying machine lifting and hoisting trolley in the embodiment of the present invention.
  • Figure 29 is a schematic view of the underside of the new type of track laying machine for the traction flatbed of the rail vehicle in the embodiment of the present invention.
  • Figure 30 is a schematic view showing the overall traveling track of the new track laying machine landing on the main track in the embodiment of the present invention.
  • Figure 31 is a schematic view showing the walking of the lifting rail of the new track laying machine in the design and installation position in the embodiment of the present invention.
  • Figure 32 is a side elevational view showing the walking direction of the lifting rail of the new track laying machine in the embodiment of the present invention.
  • Figure 33 is a side elevational view of the temporary support section of the rail-laying hoisting rail of the new type of rail-laying machine through the rail row in the embodiment of the present invention.
  • Figure 34 is a schematic view of a new type of track laying machine hoisting prefabricated track plate in an embodiment of the present invention.
  • Figure 35 is a side elevational view of a new type of track laying machine hoisting prefabricated track panel in accordance with an embodiment of the present invention.
  • Fig. 36 is a schematic view showing the long-distance transfer of the trolley of the traveling trolley after the decomposition of the new type of track laying machine module in the embodiment of the present invention.
  • Figure 37 is a schematic view showing the long-distance transfer of the continuous lifting truss beam loading after the decomposition of the new track laying machine module in the embodiment of the present invention.
  • FIG. 28 Walking trolley guide sleeve 29. Walking trolley running axle 30. Walking trolley structure reinforcing rib plate 31. Stranded seat 32. Guide post 33. Track towing pulley 34. Track travel guide wheel 35. Track running roller 36. Track running drive wheel 37. Horizontal frame beam reinforcement structure 38. Vertical support horizontal extension Device hydraulic drive cylinder 39. Second guide post 40. Vertical guide sleeve 41. Vertical support device drives hydraulic cylinder 42. Vertical support device 1 stage guide column drives hydraulic cylinder 43. Vertical support device 2 guide column 44. Vertical Guide column to support device 45. Tracking machine traction connection hook 46. Power supply cable reel 47. Winding machine 48. Pulley unit 49. Hydraulic pump station 50. Travel drive motor 51. Track travel drive motor 52. Rail support device 53. Drive ball pin.
  • the main technical scheme of the invention is that the new track laying machine is designed with two truss beams connected to the front and rear lifting trolleys with lifting function.
  • the new track laying machine is arranged symmetrically in front and rear, and the new track laying machine in the positive track area is walking in the positive direction.
  • the new track laying machine in the non-positive track section walks on the structural bottom plate, and the lifting traveling trolley has horizontal expansion and vertical lifting support structure, which is needed for the loading and unloading of track material and running mechanism of the new track laying machine, and the function of connecting the truss beam
  • the two lifting trolleys are connected together to form a complete machine, and the second is to install a lifting hoisting trolley for hoisting rails and the like on the connecting truss beam.
  • the lifting hoisting trolley is pulled by the hoist to walk along the truss beam.
  • the first horizontal lifting and vertical support control device for lifting the traveling trolley lifts the new rail laying machine to the lifting and unloading
  • the height of the track material is used to push the flat car of the track material such as the rails to the new type of track laying machine under the truss beam.
  • the heavy lifting trolley lifts the track material such as the rails away from the flatbed transporter and the material support cushions.
  • the flatbed truck exits the new track laying machine, and the vertical support control device that lifts the traveling trolley lowers the new track laying machine together with the rails and other materials.
  • the new type of track-laying machine travels smoothly on the main track to complete the unloading.
  • the new track-laying machine runs on the main track to the vicinity of the installation position.
  • the operation lifts the traveling trolley.
  • the vertical support control device causes the traveling trolley to be off track, and the longitudinal movement control device for operating the lifting trolley moves the trolley away from the main track, and the operation track control device lowers the crawler running mechanism on the structural floor, and the lifting mechanism Return to the contraction “0” position, continue to let the new track laying machine move forward to reach the rail row design and installation position, and remove the rail material such as the rail row.
  • a new type of rail-laying machine for urban rail transit engineering including lifting walking work trolley, connecting truss beam (8), crawler running mechanism (2) and supporting structure
  • the new track laying machine consists of two lifting walking platforms
  • the vehicle is composed of a connecting truss beam (8) connecting two lifting traveling trolleys
  • the lifting walking working trolley is composed of a running trolley (5) and a horizontal frame beam (4) for longitudinal movement of the traveling trolley, in a horizontal frame beam ( 4)
  • the front and rear ends are installed with support structures that can be horizontally extended to both sides of the main line rail and have a vertical lifting walking work trolley.
  • the traveling trolley is composed of a frame structure, a track running wheel (6) and a plane frame structure mounted on the traveling trolley.
  • the center crawler running mechanism (22) is composed.
  • the new track laying machine walks on the main track by the track running wheel.
  • the new track laying machine walks on the structural bottom plate through the track running mechanism,
  • the horizontally telescopic and vertically raised support structures are used for the conversion of the new track laying machine in the positive track and the non-positive track.
  • the outer side of the horizontal frame beam (4) is equipped with a bolt hook for connecting the new track laying machine and the tractor, and the upper reinforcing structure frame (3) of the horizontal frame beam is mounted with hydraulic pressure for the hydraulic operation of the lifting work trolley.
  • the pumping station (49) and the power supply cable reel (46) are connected to the truss beam (8) to connect the two lifting traveling trolleys together to form a complete machine, and a lifting hoisting trolley for lifting materials is mounted on the connecting truss beam ( 9) The lifting and hoisting trolley is pulled by the hoist to walk along the truss beam to achieve precise lifting and positioning of the track material.
  • the horizontal frame beam (4) is composed of a number of longitudinal beams, a plurality of beams and an upper reinforcing structure (3).
  • the longitudinal beam is both a structural beam of the horizontal frame beam and a guide column of the moving carriage moving forward and backward.
  • the beam is both
  • the structural beam of the horizontal frame beam is a guide sleeve structure for lifting the vertical support structure of the traveling trolley to realize horizontal horizontal expansion and contraction.
  • a reinforcing structure is installed on the upper part of the horizontal frame beam to ensure the longitudinal and lateral rigidity of the horizontal frame beam, and the vertical direction is installed in the beam.
  • the horizontal telescopic mechanism in the direction of the line, the horizontal telescopic mechanism is composed of a guide post (39) and a vertical guide sleeve (40), and the horizontal telescopic mechanism is matched by the structure of the guide post (39) and the guide sleeve (25), and horizontally horizontally telescopically passes through the hydraulic pressure.
  • the driving cylinder is realized, and a vertical supporting structure is installed in the guiding sleeve (40).
  • the vertical supporting structure is composed of a second guiding column, a first guiding column and a first driving hydraulic cylinder, and the second guiding column is also a guide of the first guiding column
  • the sleeve, the vertical support structure is realized by the first hydraulic drive cylinder (41) driving the first guide post and the second guide post to extend step by step.
  • the walking trolley consists of a frame structure, a track running wheel and a track running mechanism installed in the center of the plane frame structure of the running trolley.
  • the frame structure consists of two guiding sleeves and a track running wheel and a connecting structure, and the traveling trolley passes
  • the guide sleeve is set on the horizontal frame beam of the lifting trolley, and the forward and backward movement of the trolley along the horizontal frame beam is realized by the second hydraulic driving cylinder (7), and the walking trolley track is driven by the motor to walk on the positive track.
  • a crawler running mechanism is installed at a center of the upper plane of the walking trolley, and the crawler running mechanism is fixed on the lower structural bottom plate of the running trolley through the rotating disc, and the crawler running mechanism realizes the vertical expansion and contraction through the telescopic guide sleeve (24) guide pillar (32) device.
  • the telescopic guide sleeve (24) is fixed on the rotary disc (23), and the steering drive ball pin is mounted on the rotary disc (23), and the upper and lower telescopic expansion of the guide post (32) is realized by the third hydraulic drive cylinder (18), and the crawler belt travels.
  • the mechanism is connected by a pin and a guide column, and the crawler running mechanism is composed of a chassis, a drive wheel, a guide wheel, a roller, a pulley and a crawler, and a hydraulic drive motor group.
  • a turntable (27) rotatable around the center of the trolley is mounted on the upper plane of the trolley, and the turntable is rotated around the center of the trolley through the roller, and a hinge seat (31) is mounted on the turntable (27) through the hinge pin and
  • the connecting truss beams (8) are connected.
  • the connecting truss beam (8) consists of steel pipe welded, divided into three sections, the section is "chair” shaped, arranged symmetrically in two sides, each section is connected by a connecting pin, and the truss beam is connected
  • a track for the hoisting trolley (9) is mounted thereon, and a hoisting machine (47) and a pulley block (48) are installed at both ends of the connecting truss beam for pulling the hoisting trolley to move forward and backward along the track, and lifting the horizontal frame beam of the traveling trolley
  • the upper reinforced structure is provided with a hydraulically driven hydraulic pump station (49) and a cable reel (46) for providing hydraulic and electrical power to the new track laying machine.
  • Example 1 New track laying machine construction preparation, rail lifting and installation work
  • the new type of track laying machine is changed from the running state to the rail lifting state.
  • the new track laying machine is composed of two lifting traveling trolleys and connecting lifting truss beams.
  • the lifting traveling trolley is composed of a horizontal frame beam and a running trolley
  • the horizontal frame beam is composed of two longitudinal beams, four beams and an upper reinforcing structure (37).
  • the two longitudinal beams are not only the structural beam of the horizontal frame beam but also the guide column of the moving frame of the moving frame.
  • the four beams are both the structural beam of the horizontal frame beam and the vertical support device of the lifting traveling trolley to realize horizontal horizontal expansion and contraction.
  • a reinforcing structure (37) is mounted on the upper portion of the horizontal frame structure to ensure the longitudinal and lateral stiffness of the horizontal frame beam.
  • a horizontal telescopic mechanism perpendicular to the line direction is installed in the beam, and the horizontal telescopic mechanism is composed of a guide post (39) and a vertical guide sleeve (40), and the horizontal telescopic mechanism is matched by the structure of the guide post (39) and the guide sleeve (25).
  • the horizontal lateral expansion is achieved by a hydraulically driven cylinder, and a vertical support device is installed in the guide sleeve (40).
  • the vertical support device consists of a 2-stage guide post (43), a 1-stage guide post (44) and a first drive hydraulic cylinder (41).
  • the composition, the 2-stage guide post is also the guide sleeve of the 1-stage guide post.
  • the vertical support is realized by a hydraulically driven cylinder driving the first stage guide post and the second stage guide post step by step.
  • the walking trolley consists of a frame structure, a track running wheel and a crawler running mechanism installed in the center of the traveling frame plane frame structure.
  • the frame mechanism is composed of two guide sleeves and a track running wheel 6 and a connecting structural member, and the traveling trolley is set on the horizontal frame beam (4) of the lifting traveling trolley through the guide sleeve (28), and the traveling trolley is along the horizontal frame beam (4).
  • the forward and backward movement is realized by the second hydraulic drive cylinder (7), and the running track of the trolley track is 1508 mm, which is driven by the motor to run on the positive track.
  • a crawler running device (22) is installed at the center of the upper plane of the walking trolley, and the crawler running device (22) is fixed on the lower structural bottom plate of the traveling trolley (5) through the rotating disc (23), and the crawler running device (22) passes through the guide
  • the guide post (32) device realizes up-and-down telescopic, the telescopic guide sleeve is fixed on the rotary disc (23), and the steering drive ball pin (53) is mounted on the rotary disc (23), and the guide post (32) is telescoped up and down.
  • the two hydraulic drive cylinders (18) are realized, the crawler running device (22) is connected by the pin shaft and the guide post (32), and the crawler running device (22) has a chassis, a crawler running drive wheel (36), and a crawler guide wheel (34).
  • the crawler roller (35), the crawler pulley (33) and the crawler drive motor (51) are arranged on the upper plane of the trolley (5) with a turntable (27) that can be rotated around the center of the trolley. ), the turntable is rotated around the center of the trolley by the roller, and the grounding seat (31) is mounted on the loading plate (27), and is connected by the hinge pin and the connecting truss beam (8).
  • the new track-laying machine is operated to prepare for the unloading position, and the hydraulic drive cylinders of the lifting trolley are respectively operated to extend the horizontal telescopic guide column of the vertical support device to both sides of the line, and when the same section protrudes The internal space is stopped and locked when it meets the transport flatbed and rail width requirements.
  • the hydraulic drive cylinders respectively operating the vertical support device drive the guide columns downwardly to support them smoothly on the concrete track bed surface (if the position of the track bed surface is not suitable, the horizontal expansion and contraction are adjusted to meet the appropriate position, and the ground unevenness is used for the support pad.
  • the vertical support device of the 1st and 2nd lifting trolleys is extended downward due to the restriction of the bed surface, so that the new track laying machine is lifted upwards, when the new track laying machine is raised to meet
  • it stops lifting partially adjusts the stress state of the eight supporting legs of the new railing machine, so that it is evenly stressed, and the new rail laying machine belongs to the horizontal state, and stops and locks after completion.
  • the traveling traction winch of the hoisting trolley is operated, so that the hoisting trolley travels to the hoisting position of the hoisting truss beam, and the lifting hoisting device adjusts the height of the lifting sling to meet the feeding of the rail transporter.
  • the command rail tractor pulls the flatbed slowly out of the new track laying machine, and when it is completely out of the new track laying machine, accelerates the orbital tractor to return to the base to reload the rails;
  • the synchronous track-operating track-driving drive motor of the new type of track-laying machine 1 and 2 lifts the walking trolley to make the new rail-laying hoisting rail row walk along the positive track to the rail-row design and installation position;
  • the vertical support control system of the No. 2 lifted walking trolley enables the support feet of the vertical support to be smoothly supported on the floor of the section structure (the pad is not used), and the operation is continued to make the trolley 5 Lifting off a certain height from the positive track tread (higher than the height of the gear) to stop the operation;
  • the vertical support control device for the 2nd lift walking trolley is used to make the vertical support slowly retract from the bottom plate to a certain height (without affecting the new track laying machine) and then stop the operation;
  • the synchronous operation No. 1 lifts the traveling trolley running control device and the No. 2 lifting traveling trolley crawling control device to drive the new track laying machine to the direction without the forward track.
  • the new track laying machine No. 1 is lifted.
  • the walking trolley walks on the main track, and the No. 2 lifted walking trolley walks on the structural floor. Adjusting the walking direction by operating the crawler steering control device 53 of the No. 2 trolley when the operation is in the curved section;
  • the synchronous operation No. 1 lifts the traveling trolley running vehicle control device and the No. 2 lifting traveling trolley vertical support horizontal frame beam longitudinal movement control device to move the new track laying machine in the direction of the positive track.
  • the horizontal projection of the No. 2 lifting walking trolley traveling trolley 5 all enters the end of the newly installed rail row rail, the operation is stopped;
  • Operation No. 2 lifts the vertical support control device of the traveling trolley to lower the lifting trolley, and the trolley slowly landed on the front surface of the rail of the main track. Continue operation to stop the vertical support after retracting to the top dead center position;
  • the running control device of the traveling carriage 5 of the traveling trolley of the synchronous operation No. 1 and No. 2 raises the new track laying machine to the position of the original unloading rail along the positive track, and stops when it reaches the position of the unloading rail.
  • Example 2 Lifting and installation of prefabricated track panels for new track laying machine
  • the construction of the urban rail transit channel bed is generally carried out after the construction of the section track bed cushion.
  • the track bed is a precast concrete board, the length is generally 5800mm (normal version), and the length of the curve adjustment board is generally 4500mm-5000mm, in order to facilitate the prefabricated board.
  • Transportation generally laying 25m-50m track plate and installing rail fasteners in time to form transportation channel. When the track plate is laid for more than 100m, the track plate and track state are adjusted, and the self-compacting concrete or other mortar material is poured under the track plate. The track plate and the track state are fixed to form a track line. Therefore, laying track panels is a key process.
  • the track board is unloaded, hoisted, moved and seated.
  • a. New type of rail-laying machine lifting See Figure 10-38, the new track-laying machine is operated to the position where the unloading position is to be stopped (the new track-laying machine No. 1 lifting the traveling trolley is at the position where the rail plate has been installed and formed at the end of the rail of the main-track rail 5 meters)
  • the No. 2 lift walking trolley is at the position of the cushion where the track plate is not installed).
  • the hydraulic drive cylinders 38 for respectively operating the lifting carriages of No. 1 and No. 2 respectively extend the horizontal telescopic guide posts 39 of the vertical supporting device to both sides of the line, and when the internal space extending from the same section meets the requirements for transporting the flatbed and the width of the rails Stop and lock.
  • the vertical support device of the lifting trolley of the 2nd and 2nd lifts protrudes downward, and the downward direction of the cushion layer is restricted.
  • the traveling traction hoist 47 of the lifting and hoisting trolley 9 is respectively adjusted to adjust the lifting point position of the lifting and hoisting trolley 9, and the operation is stopped after error-free;
  • the command rail tractor will temporarily transport the main line to the new track laying machine
  • the synchronous lifting hoisting trolley 9 lifts the rail and moves it longitudinally to the installation position of the rail plate, and slowly lowers the rail to be placed smoothly on the rail groove plate of the rail plate;
  • Synchronous operation 1.
  • the vertical support control device for lifting the walking trolley enables the supporting foot to be stably supported on the cushion level, and continues to operate to lift the new railing machine as a whole to the position of the lifting rail plate, and stop the new type.
  • the track laying machine makes the new track laying machine in a horizontal state, and checks whether the support of the eight supporting feet of the new track laying machine is stable and reliable, and the locking operation is performed after all errors are correct;
  • the track construction is generally centered on the track-laying base, and the upper and lower lines are constructed in both directions.
  • the key equipment for turnaround as a track is to carry out construction in advance.
  • the transfer of the new track laying machine is realized by using the completed ballast and single crossing line. There are three kinds of positions for the working surface transfer. On the way, the new working surface 1, the new working surface 2 and the new working surface 3:
  • the horizontal telescopic device of the vertical support device of the traveling trolley of No. 1 and No. 2 of the new track laying machine is retracted to the travel transfer position, and the vertical support device is retracted to the upper limit position and the travel position is locked.
  • the new track laying machine and the rail tractor are connected by a connecting bar. Start the orbital tractor and let the orbital tractor pull the new track-laying machine slowly to the position of the ballast 2.
  • the track tractor pulls the new track-laying machine through the switch 2, when the tail of the new track-laying machine reaches the position of the switch 2, it stops moving, and the switch 1 and the switch 2 open the channel to the side track, start the track tractor, and let the track tractor Pushing the new track laying machine into the aisle 2, the turnout 1 enters the positive line 1, reaches the new working surface 1, and completes the transition operation;
  • the horizontal telescopic device of the vertical support device of the traveling trolley of No. 1 and No. 2 of the new type of track laying machine is retracted to the travel transfer position, and the vertical support device is retracted to the upper limit position and the travel position is locked.
  • the new track laying machine and the rail tractor are connected by a connecting bar. Start the orbital tractor and let the orbital tractor pull the new track-laying machine slowly to the position of the ballast 2.
  • the track tractor pulls the new track-laying machine through the switch 2, when the tail of the new track-laying machine reaches the position of the switch signal, it stops moving, and the turn-by-turn track is opened by the switch 1 and the switch 2 to start the track tractor, so that the track tractor can be pushed.
  • the new track laying machine enters the aisle ⁇ 2
  • the turnout 1 enters the positive line 1, and stops when the tail of the track tractor arrives at the signal position of the switch 1, removes the connection between the new track laying machine and the track tractor, and starts the lateral return of the track tractor. Stop when the tail of the orbital tractor reaches the alarm position of the switch 1.
  • the horizontal telescopic device of the vertical support device of the traveling trolley of No. 1 and No. 2 of the new type of track laying machine is retracted to the running transfer position, and the vertical supporting device is retracted to the upper limit position and the traveling position is locked.
  • the new track laying machine and the rail tractor are connected by a connecting bar. Start the orbital tractor and let the orbital tractor pull the new track-laying machine slowly to the position of the ballast 2.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Machines For Laying And Maintaining Railways (AREA)

Abstract

一种城市轨道交通工程新型铺轨机及其施工方法,装置包括抬升行走作业台车、连接桁架梁(8)、履带走行机构(2)和支撑结构,首先操作抬升行走台车的水平伸缩和竖向支撑结构将新型铺轨机整体抬升到吊卸轨道材料的高度,用起重吊装小车(9)把轨道材料吊起离开平板运输车及材料支垫物;继续让新型铺轨机向前行走到达轨排设计安装位置,卸下轨道材料,连接钢轨、安装轨排临时支撑固定新安装轨排,继续向再一次吊装轨排位置行走到达卸车地点进行排吊装下一个循坏。本装置结构简单、操作方便、成本低,同时也确保了作业过程中的安全和提高了效率。

Description

一种城市轨道交通工程新型铺轨机及其施工方法 [技术领域]
本发明涉及工程技术科学,具体是一种城市轨道交通工程新型铺轨机及其施工方法。
[背景技术]
目前我国城市轨道交通工程轨道施工中,采用的铺轨机设备主要有拼装固定门型结构、人工及液压定距变跨门型结构和自动检索电动无极变跨门型结构三种型式。三种结构形式的铺轨机都需要铺设临时走行轨供铺轨机走行。临时走行轨是预先铺设在正线两侧的隧道侧壁或结构底板上,轨距一般为2800mm、3000mm、3100mm、3800mm等几种,由特制的钢结构支墩把临时走行轨固定在隧道侧壁或结构底板上。由于城市轨道交通工程地下线隧道结构空间狭小,安装临时走行轨让狭小的空间减小了作业空间,轨道施工时铺排铺设需借助于侧向支撑来保证轨道状态,侧向支撑经常和临时走行轨发生冲突,使得正线轨道轨排铺设施工空间减小。隧道结构的不同,临时走行轨安装位置也不同(圆形隧道安装在侧壁上,马蹄形隧道和矩形隧道安装在结构底板上,有的结构就需要一侧安装在侧壁上、一侧安装在结构底板上),无论何种安装方式都占用道床结构位置空间,使得道床混凝土施工由一次完成变成两次施工(先浇筑整体道床,再浇筑道床水沟),导致整体道床与水沟形成混凝土结构缝;随着正线轨道的铺设不断地向前循环推进,大量的临时走行轨循环倒运使用,使得正线轨道施工无论是空间上还是时间上都产生影响;同时安装临时走行轨需要在建筑结构物上打孔固定走行轨支墩,一定程度上影响结构的外观和性能;当遇到车站、人防门等特殊地段时,由于结构边界的限制使得临时走行轨轨距变化造成临时走行轨的不连续,既占用正线轨道的安装位置,还由于铺轨机变跨要求而中断正线轨道施工作业,不同程度地占用轨道施工有效时间和空间;由于需要铺设临时走行轨道,给正线轨道施工增加了作业工序,增加了施工投入,加大了施工成本和人员劳动强度。
综上所述,现有的轨道施工铺轨机在实际应用中虽然广泛采用,但给正线施工带来诸多制约和影响。在现代轨道交通工程铺设施工技术飞速发展时期,板式道床、预制拼装结构等结构将成为主流。为满足铺轨施工效率的更高需求,铺轨设备的自适应性、全功能型、灵活性都有更高的要求,为正线铺轨提供更大的作业空间和有效作业时间等成为必然的趋势,因此开发一种不需要铺设临时走行轨就能实现隧道内轨道材料、预制品、拼装结构等材料的吊装、转运以及整机免解体快速转场、简单分拆可实现长途运输转移的节能环保的新型铺轨机成为必然的趋势、当务之急。
[发明内容]
本发明的目的就是为了解决目前轨道施工必须在正线两侧铺设临时走行轨道这一辅助工序的问题,同时提高运输效率和安全,而设计一种城市轨道交通工程新型铺轨机及其施工方法,装置包括抬升行走作业台车、连接桁架梁、履带走行机构和支撑结构,新型铺轨机由两台抬升行走作业台车和连接两台抬升行走台车的连接桁架梁组成,抬升行走作业台车由走行小车、供走行小车实现纵向移动的水平框架横梁组成,在水平框架横梁的前后端安装能向正线轨道两侧水平伸出的并具有竖向抬升行走作业台车的支撑结构,走行小车由框架结构、轨道走行轮和安装在走行小车平面框架结构中心的履带走行机构组成,在有正线轨道地段新型铺轨机通过轨道走行轮行走在正线轨道上,在无正线轨道地段新型铺轨机通过履带走行机构行走在结构底板上,具有水平伸缩和竖向抬升的支撑结构用于新型铺轨机在正线轨道和无正线轨道转换。
水平框架横梁的外侧安装有供新型铺轨机和牵引车连接的插销挂钩,水平框架横梁的上部加强结构框架上安装供抬升作业台车液压作业的液压泵站和供电电缆卷盘,连接桁架梁把两台抬升行走台车连接在一起形成整机,在连接桁架横梁上安装有供吊装材料的起重吊装小车,起重吊装小车由卷扬机牵引可沿桁架梁前后行走以实现轨道材料的精确吊装和就位。
水平框架横梁由若干纵梁、若干横梁和上部加强结构组成,纵梁既是水平框架横梁的结构梁又是走行小车的前后移动的导柱,横梁既是水平框架横梁的结构梁又是抬升行走台车竖向支撑结构实现水平横向伸缩的导套结构,在水平框架横梁的上部安装加强结构以保证水平框架横梁的纵向、横向刚度,在横梁内安装垂直于线路方向的水平伸缩机构,水平伸缩机构由导柱和竖向导套组成。水平伸缩机构通过导柱、导套结构进行配合,水平横向伸缩通过液压驱动油缸实现,在导套内安装竖向支撑结构,竖向支撑结构由第二导柱、第一导柱和第一驱动液压油缸组成,第二导柱还是第一导柱的导套,竖向支撑结构通过第一液压驱动油缸驱动第一导柱和第二导柱逐级伸出来实现。
走行小车由框架结构、轨道走行轮和安装在走行小车平面框架结构中心的履带走行机构组成,框架结构由两根导套和轨道走行轮以及连接结构件组成,走行小车通过导套套装在抬升行走台车水平框架横梁上,走行小车沿水平框架横梁的前后移动是通过第二液压驱动油缸来实现,走行小车轨道走行轮由电机驱动行走在正线轨道上,在走行小车的上平面中心位置安装有履带走行机构,履带走行机构通过回转盘固定在走行小车的下结构底板上,履带走行机构通过导套导柱装置实现上下伸缩,伸缩导套固定在回转盘上,在回转盘上平面安装转向驱动球销,导柱的上下伸缩通过第三液压驱动油缸实现,履带走行机构通过销轴和导柱连接,履带走行机构由底盘、驱动轮、引导轮、支重轮、托带轮和履带、液压驱动马达组成,在走行小车的上平面上还安装有可绕走行小车中心回转的转盘,转盘通过滚柱绕小车中心回转,在装盘上安装有绞座,通过铰销和连接桁架梁相连。
连接桁架梁由钢管焊接组成,分为三节,断面为“椅”字型,分左右两榀对称布置,每节之间通过连接销进行连接,在连接桁架梁上安装有供吊装小车行走的轨道,在连接桁架梁的两端安装有卷扬机和滑轮组,用于牵引吊装小车沿轨道前后移动,在抬升行走台车水平框架横梁的上加强结构上,安装供液压驱动的液压泵站和电缆卷线盘,用于给新型铺轨机提供液压和电力。
采用所述铺轨机的施工方法如下:新型铺轨机从轨排运输车上卸下轨排时,首现操作抬升行走台车的水平伸缩和竖向支撑结构将新型铺轨机整体抬升到吊卸轨道材料的高度,将运输轨道材料的平板运输车推送到新型铺轨机连接桁架梁下,用起重吊装小车把轨道材料吊起离开平板运输车及材料支垫物,平板运输车退出新型铺轨机下方,操作抬升行走台车的竖向支撑结构将新型铺轨机连同轨道材料下降使新型铺轨机走行小车平稳地降落在正线轨道上完成卸车;新型铺轨机在正线轨道走行至安装位置附近,当前方抬升行走台车到达正线轨道端头车档时,操作抬升行走台车的竖向支撑结构使走行小车脱离轨道,操作抬升行走台车的纵向移动控制装置将走行小车移出正线轨道外,操作履带走行控制装置将履带走行机构下降支撑在结构地板上,将抬升机构恢复到收缩初始位,继续让新型铺轨机向前行走到达轨排设计安装位置,卸下轨道材料,连接钢轨、安装轨排临时支撑固定新安装轨排,反向操作新型铺轨机抬升、机构转换、纵向移动控制装置将新型铺轨机回位到正线轨道上,继续向再一次吊装轨排位置行走到达卸车地点进行排吊装下一个循坏。
具体施工方法如下:
A.轨排搭接吊装、运输工作
(1)操作新型铺轨机到达轨排卸车位置,分别操作1、2号抬升行走台车的带水平伸缩的竖向支撑结构使竖向支撑向线路两侧伸出,伸出距离满足轨排运输平板车和所装载材料的宽度加安全距离的要求,确认安全后锁闭操作;
(2)分别操作1、2号抬升行走台车的带水平伸缩的竖向支撑结构使竖向支撑向下伸出,竖向支撑下支撑脚盘平稳地支撑在已达到强度的道床上面或结构底板上面,并确认均匀受力,同步继续操作1、2号抬升行走台车的带水平伸缩的竖向支撑结构使竖向支撑继续向下伸出,由于底板的支撑反作用使得1、2号抬升行走台车以及连接吊装桁架梁缓缓向上抬升,当到达吊装高度后停止操作,再次检查抬升行走台车的竖向支撑结构稳固支撑和均匀受力后锁闭;
(3)指挥轨道牵引车推送运输轨道材料的平板运输车缓缓驶入新型铺轨机下方,当轨排全场范围完全进入连接吊装桁架梁下时停止推送,驻车制动;
(4)分别操作新型铺轨机连接桁架梁横梁上的起重小车,使其对准轨道材料吊装的吊点位置,降下吊装扁担将挂钩和轨排连接,分别操作起重小车使吊点受力,再次检查新型铺轨机的竖向支撑脚确认牢固,同步操作起重小车缓缓吊起轨道材料,当轨道材料完全脱离平板运输车上的转向架支撑结构上支点加安全距离后停止起升,锁闭操作,启动轨道牵引车使其牵引平板车缓缓驶离新型铺轨机下方一定距离停车或返回基地运输下一个轨排;
(5)同步反向操作1、2号抬升行走台车的带水平伸缩的竖向支撑结构使竖向支撑向上回收,此时1、2号抬升行走台车连同连接桁架梁、所吊轨道材料缓缓下降,并缓慢地下降在正线轨道上,继续反向操作1、2号抬升行走台车的带水平伸缩的竖向支撑结构使竖向支撑向上回收,回位到新型铺轨机转运状态,锁闭操作,调整1、2号抬升行走台车的带水平伸缩的竖向支撑结构,使统一横的断面竖向支撑支撑脚的距离大于轨道材料的宽度即可;
(6)操作新型铺轨机走行装置控制系统使新型铺轨机吊装轨道材料沿正线轨道向设计安装位置走行,新型铺轨机吊装轨道材料通过混凝土浇筑完成地段、未浇筑混凝土地段、以及轨排调整完成并固定地段到达正线轨道端头;
(7)当新型铺轨机2号抬升行走台车的走行小车到达正线轨道端头车档位置时停止走行;
B.新型铺轨机走行机构转换、移动、轨排就位工作
(1)当新型铺轨机2号抬升行走台车的走行小车走行轮到达正线轨道端头车档位置时停止走行,操作2号抬升行走台车走行小车纵移控制装置,使抬升行走台车水平框架结构相对于走行小车向无正线轨道方向移动到达纵移止点位置停止操作;
(2)操作2号抬升行走台车的带水平伸缩的竖向支撑结构向下伸出,带水平伸缩的竖向支撑结构下支撑脚盘平稳地支撑在结构底板上面,并确认均匀受力,继续操作使2号抬升行走台车走行小车向上抬升离开正线轨道踏面并高于车档高度后停止抬升操作并锁闭;
(3)同步操作1号抬升行走台车的走行小车走行驱动和2号抬升行走台车走行小车纵移控制装置,使1号抬升行走台车、连接桁架梁、轨道材料、2号抬升行走台车的走行小车向无正线轨道方向移动,到达2号抬升行走台车走行小车纵移止点位置停止操作,锁闭,此时走行小车水平投影完全脱离正线轨道;
(4)操作2号抬升行走台车走行小车内的履带走行机构升降装置,使履带走行机构慢慢下降,且平稳地支撑在结构地板上并受力;
(5)操作2号抬升行走台车的带水平伸缩的竖向支撑结构,使带水平伸缩的竖向支撑结构完全脱离结构底板一定高度停止操作并锁闭;
(6)同步操作1号抬升行走台车走行小车走行控制装置和2号抬升行走台车履带走行控制装置,使新型铺轨机向无正线轨道方向走行,操作2号行走太车上的履带走行方向控制装置调整2号台车走行方向,保证2号台车行走在轨道中心线上,当1号抬升行走台车接近正线轨道端头时停止走行,检查轨排水平投影位置和已安装轨排端头相连位置,如位置有少量偏差则通过移动起重吊装小车完成对位,如偏差较大则移动新型铺轨机完成对位;
(7)同步操作起重吊装小车将轨排缓缓下降至设计安装高度,前后少量移动起重吊装小车,完成新安装轨排和已安装轨排的对位后停止操作;
(8)用钢轨夹板把钢轨接头进行连接固定,在轨排上按设定位置安装临时支撑或轨道状态调整架并拧紧调整螺母固定新安装轨排的空间位置;
(9)操作起重吊装控制装置,摘除吊装扁担和轨排的连接,提升吊装扁担到上限位位置停止操作;
C.新型铺轨机走行机构转换返回搭接吊装位置作业
(1)操作新型铺轨机向有正线轨道方向走行,当走行履带端面靠近新安装轨排端头时停止走行;
(2)操作2号抬升行走台车的走行小车纵移控制装置,使抬升行走台车水平框架结构相对于走行小车向有正线轨道方向移动到达纵移止点位置停止操作;
(3)操作2号抬升行走台车的带水平伸缩的竖向支撑结构使竖向支撑向下伸出,带水平伸缩的竖向支撑结构下支撑脚盘平稳地支撑在结构底板上面,并确认均匀受力,继续操作使2号抬升行走台车的走行小车向上抬升高于车档高度后停止抬升操作并锁闭;
(4)操作2号抬升行走台车走行小车内的履带走行机构升降装置,使履带走行机构慢慢抬升,且平稳地收缩在走行小车内部的上限位位置停止操作并锁闭;
(5)同步操作1号抬升行走台车的走行小车走行驱动和2号抬升行走台车走行小车纵移控制装置,使1号抬升行走台车、连接桁架梁、2号抬升行走台车的走行小车向有正线轨道方向移动,到达2号抬升行走台车的走行小车纵移止点位置停止操作,锁闭,此时走行小车水平投影完全进入正线轨道上方;
(6)操作2号抬升行走台车的带水平伸缩的竖向支撑结构,使带水平伸缩的竖向支撑结构回缩,2号抬升行走台车的走行小车平稳地降落在正线轨道上车档内侧,继续操作2号抬升行走台车的带水平伸缩的竖向支撑结构,使带水平伸缩的竖向支撑结构完全回缩到上止点位置后停止操作并锁闭;
(7)同步操作1、2号抬升行走台车轨道走行控制装置,使新型铺轨机返回到接收新运输到的轨排地点,准备再一次的轨排吊装作业;
D.新型铺轨机再次吊装轨排、运输、安装作业
重复所述步骤A-步骤C的全部动作,完成轨排的再次吊装运输、安装和新型铺轨机就位,以此类推完成轨道施工作业。
具体施工方法如下:新型铺轨机作业面转场作业,当轨道施工一个作业面完成后需要转场至新作业面时有这样几种情况:一是同方向的另一条施工线作业位置,二是反方向的另两条施工线作业位置,新型铺轨机转场是在轨道牵引车的牵引下通过已铺好的第一道岔、第二道岔实现转场作业,完成作业面转移按下述步骤进行:
(1)转移到同方向另一条线路施工现场作业位置:将新型铺轨机的1、2号抬升行走台车竖向支撑结构的水平伸缩装置收回到走行转移位置,将竖向支撑结构收回到上限位转移走行位置锁闭,拆除新型铺轨机供电电源,将电缆收卷到电缆卷线盘内,拆除新型铺轨机轨道走行轮与走行驱动减速器的连接,使其处于空挡状态,将新型铺轨机和轨道牵引车用连接拖杠进行连接,启动轨道牵引车,让轨道牵引车牵引新型铺轨机缓缓驶向第二道岔位置,首先轨道牵引车牵引新型铺轨机通过第二道岔,当新型铺轨机尾部到达道岔信号机位置时停止走行,扳动第一道岔和第二道岔开通道岔侧向通行轨道,启动轨道牵引车,让轨道牵引车推送新型铺轨机进过第二道岔、第一道岔进入正线,到达新作业面,完成转场作业;
(2)转移到反方向新作业面:将新型铺轨机的1、2号抬升行走台车竖向支撑结构的水平伸缩装置收回到走行转移位置,将竖向支撑结构收回到上限位转移走行位置锁闭,拆除新型铺轨机供电电源,将电缆收卷到电缆卷线盘内,拆除新型铺轨机轨道走行轮与走行驱动减速器的连接,使其处于空挡状态,将新型铺轨机和轨道牵引车用连接拖杠进行连接,启动轨道牵引车,让轨道牵引车牵引新型铺轨机缓缓驶向第二道岔位置,首先轨道牵引车牵引新型铺轨机通过第二道岔,当新型铺轨机尾部到达道岔信号机位置时停止走行,扳动第一道岔和第二道岔开通道岔侧向通行轨道,启动轨道牵引车,让轨道牵引车推送新型铺轨机经过第二道岔、第一道岔进入正线,当轨道牵引车尾部到达第一道岔的信号机位置时停车,拆除新型铺轨机和轨道牵引车的连接,启动轨道牵引车侧向通行返回,当轨道牵引车尾部到达第一道岔的警冲标位置时停车,扳动第一道岔恢复正向通行,启动新型铺轨机向作业面方向行驶,当新型铺轨机的尾部经过第一道岔到达第一道岔的警冲标位置时停止,扳动第一道岔开通侧向通行,启动轨道牵引车向正线行驶,当轨道牵引车尾部到达第一道岔的信号机位置时停车,扳动第一道岔恢复正向通行,启动轨道牵引车缓缓经过第一道岔向新型铺轨机靠近,到达第一道岔的警冲标位置附近时停车,用连接拖杠连接轨道牵引车和新型铺轨机,连接无误后启动轨道牵引车将新型铺轨机推送到新作业面,完成作业转场;
(3)转移到反方向新作业面:将新型铺轨机的1、2号抬升行走台车竖向支撑结构的水平伸缩装置收回到走行转移位置,将竖向支撑结构收回到上限位转移走行位置锁闭,拆除新型铺轨机供电电源,将电缆收卷到电缆卷线盘内,拆除新型铺轨机轨道走行轮与走行驱动减速器的连接,使其处于空挡状态,将新型铺轨机和轨道牵引车用连接拖杠进行连接,启动轨道牵引车,让轨道牵引车牵引新型铺轨机缓缓驶向第二道岔位置,当新型铺轨机头部到达第二道岔的警冲标位置时停车,拆除新型铺轨机和轨道牵引车的连接,启动轨道牵引车继续向前行驶,当轨道牵引车尾部到达到达第二道岔的信号机位置时停车,扳动第二道岔开通侧向通行,启动轨道牵引车反向行驶,当轨道牵引车尾部到达第二道岔的警冲标位置时停车,扳动第二道岔恢复正向通行,开动新型铺轨机向新作业面方向行驶,当新型铺轨机尾部到达第二道岔的信号机位置时停止,扳动第二道岔,恢复侧向通行,启动轨道牵引车缓缓靠近新型铺轨机后停止,用连接拖杠连接轨道牵引车和新型铺轨机,连接无误后启动轨道牵引车将新型铺轨机推送到另一新作业面,完成作业转场。
本发明同现有技术相比,其优点在于:
1、新型铺轨机采用组合对称结构型式,结构可以总成模块组装拆卸,方便作业、行驶、转运和转场运输;
2、新型铺轨机采用电力驱动和轨道施工其他作业共用电力,节约能源,整车总量轻便,环保优势更加突出;
3、新型铺轨机利用正线轨道走行,不需铺设辅助临时轨道工作效率更高,在无正线轨道地段采用履带走行适应范围更广;
4、新型铺轨机取消了临时辅助轨道,减少了施工工序,降低了施工投入和施工成本,减少了施工安全隐患;
5、新型铺轨机采用了正线轨道行走,完全取消了临时走行轨道铺设,避免了占用道床结构空间使得道床混凝土一次施工得以实现,提高了混凝土施工质量,解决了道床施工缝渗水的现象;
6、新型铺轨机行走在正线轨道上,不受结构断面的影响,适合于铺轨的各种工况作业。由于采用桁架梁进行吊装,作业空间大、起重量大。抬升行走台车采用可水平伸缩结构设计,预拼道岔等超宽材料可以吊装,适用性广、通用性强。
[附图说明]
图1是本发明实施例中新型铺轨机主视图。
图2是本发明实施例中新型铺轨机侧视图。
图3是本发明实施例中连接吊装桁架梁示意图。
图4是本发明实施例中连接吊装桁架梁示意图。
图5是本发明实施例中轨道走行小车示意图。
图6是本发明实施例中轨道走行小车侧视图。
图7是本发明实施例中履带走行机构示意图。
图8是本发明实施例中履带走行机构侧视图。
图9是本发明实施例中履带走行机构俯视图。
图10是本发明实施例中抬升行走台车水平框架横梁示意图。
图11是本发明实施例中抬升行走台车水平框架横梁侧视图。
图12是本发明实施例中竖向支撑水平伸缩结构示意图。
图13是本发明实施例中竖向支撑伸缩导套导柱结构示意图。
图14是本发明实施例中竖向支撑伸缩导套导柱结构侧视图。
图15是本发明实施例中竖向支撑导柱导套示意图。
图16是本发明实施例中竖向伸缩导柱机构示意图。
图17是本发明实施例中水平伸缩导柱与水平框架横梁组装示意图。
图18是本发明实施例中吊装小车结构示意图。
图19是本发明实施例中电缆卷线盘、液压泵站安装示意图。
图20是本发明实施例中轨道牵引车推送新型铺轨机到达作业面示意图。
图21是本发明实施例中轨道牵引车运送轨排示意图。
图22是本发明实施例中新型铺轨机抬升到上作业点后等待喂送轨排示意图。
图23是本发明实施例中新型铺轨机抬升到上作业点后等待喂送轨排侧视图。
图24是本发明实施例中轨道牵引车推送轨排与送车进行喂料作业示意图。
图25是本发明实施例中轨排完全进入新型铺轨机下方完成喂料作业示意图。
图26是本发明实施例中轨排完全进入新型铺轨机下方完成喂料作业侧视图。
图27是本发明实施例中新型铺轨机起重吊装小车吊起轨排作业示意图。
图28是本发明实施例中新型铺轨机起重吊装小车吊起轨排作业侧视图。
图29是本发明实施例中轨道牵引车牵引平板车撤离新型铺轨机下方示意图。
图30是本发明实施例中新型铺轨机整体下降轨道走行小车降落在正线轨道上示意图。
图31是本发明实施例中新型铺轨机吊装轨排向设计安装位置行走示意图。
图32是本发明实施例中新型铺轨机吊装轨排向设计安装位置行走侧视图。
图33是本发明实施例中新型铺轨机吊装轨排通过轨排临时支撑地段侧视图。
图34是本发明实施例中新型铺轨机吊装预制轨道板示意图。
图35是本发明实施例中新型铺轨机吊装预制轨道板侧视图。
图36是本发明实施例中新型铺轨机模块分解后抬升行走台车装车长途转运示意图。
图37是本发明实施例中新型铺轨机模块分解后连续吊装桁架梁装车长途转运示意图。
如图所示,图中:1.行走台车竖向支撑结构 2.履带走行机构 3.水平框架横梁上加强结构 4.水平框架横梁 5.走行小车 6.轨道走行轮 7.第二液压驱动油缸 8.连接桁架梁 9.吊装小车 10.滑动滚柱 11.行走台车竖向支撑装置 12.行走小车与连接桁架梁铰连接装置 13.走行小车纵向滑移导套装置 14.履带走行升降装置 15.竖向支撑导柱结构 16.连接横梁单棍 17.起重小车电动葫芦 18.第三驱动液压油缸 19.吊装小车走行轮 20.竖向支撑液压驱动油缸 21.走行小车走行驱动链轮 22.履带走行机构 23.回转盘 24.伸缩机固定装置 25.伸缩导套 26.吊装小车导套 27.转盘 28.走行小车导套 29.走行小车走行轮轴 30.走行小车结构加强筋板 31.绞座 32.导柱 33.履带拖带轮 34.履带走行引导轮 35.履带走行支重轮 36.履带走行驱动轮 37.水平框架横梁上加强结构 38.竖向支撑水平伸缩装置液压驱动油缸 39.第二导柱 40.竖向导套 41.竖向支撑装置驱动液压油缸 42.竖向支撑装置1级导柱驱动液压油缸 43.竖向支撑装置2级导柱 44.竖向支撑装置导柱 45.铺轨机牵引连接挂钩 46.供电电缆卷盘 47.卷扬机 48.滑轮组 49.液压泵站 50.走行驱动电机 51.履带走行驱动马达 52.轨排支撑装置 53.驱动球销。
[具体实施方式]
下面结合附图对本发明作进一步说明,这种装置的结构和原理对本专业的人来说是非常清楚的。应当理解,此处所描述的具体实施例仅仅用以解释本发明,并不用于限定本发明。
本发明的主要技术方案是新型铺轨机整机设计用连接桁架梁连接前后两台具有抬升功能的抬升行走台车,新型铺轨机为前后对称布置,在有正线轨道地段新型铺轨机行走在正线轨道上,无正线轨道地段新型铺轨机行走在结构底板上,抬升行走台车具有水平伸缩和竖向抬升支撑结构,供新型铺轨机装卸轨道材料和走行机构转换需要,连接桁架梁的功能是把两台抬升行走台车连接在一起形成整机,其次是在连接桁架横梁上安装有供吊装轨排等材料的起重吊装小车,起重吊装小车由卷扬机牵引可沿桁架梁前后行走以实现轨道材料的精确吊装和就位,新型铺轨机从轨排运输车上卸下轨排时,首现操作抬升行走台车的水平伸缩和竖向支撑控制装置将新型铺轨机整体抬升到吊卸轨道材料的高度,将运输轨排等轨道材料的平车推送到新型铺轨机连接桁架梁下,用起重吊装小车把轨排等轨道材料吊起离开平板运输车及材料支垫物,平板车退出新型铺轨机下方,操作抬升行走台车的竖向支撑控制装置将新型铺轨机连同轨排等材料下降使新型铺轨机走行小车平稳地降落在正线轨道上完成卸车,新型铺轨机然正线轨道走行至安装位置附近,当前方抬升行走台车到达正线轨道端头车档时,操作抬升行走台车的竖向支撑控制装置使走行小车脱离轨道,操作抬升行走台车的纵向移动控制装置将走行小车移出正线轨道外,操作履带走行控制装置将履带走行机构下降支撑在结构地板上,将抬升机构恢复到收缩“0”位,继续让新型铺轨机向前行走到达轨排设计安装位置,卸 下轨排等轨道材料。连接钢轨、安装轨排临时支撑固定新安装轨排,反向操作新型铺轨机抬升、机构转换、纵向移动等控制装置将新型铺轨机回位到正线轨道上,继续向再一次吊装轨排位置行走到达卸车地点进行排吊装下一个循坏。
参见图1-37,一种城市轨道交通工程新型铺轨机,包括抬升行走作业台车、连接桁架梁(8)、履带走行机构(2)和支撑结构,新型铺轨机由两台抬升行走作业台车和连接两台抬升行走台车的连接桁架梁(8)组成,抬升行走作业台车由走行小车(5)、供走行小车实现纵向移动的水平框架横梁(4)组成,在水平框架横梁(4)的前后端安装能向正线轨道两侧水平伸出的并具有竖向抬升行走作业台车的支撑结构,走行小车由框架结构、轨道走行轮(6)和安装在走行小车平面框架结构中心的履带走行机构(22)组成,在有正线轨道地段新型铺轨机通过轨道走行轮行走在正线轨道上,在无正线轨道地段新型铺轨机通过履带走行机构行走在结构底板上,具有水平伸缩和竖向抬升的支撑结构用于新型铺轨机在正线轨道和无正线轨道转换。
参见图1-37,水平框架横梁(4)的外侧安装有供新型铺轨机和牵引车连接的插销挂钩,水平框架横梁的上部加强结构框架(3)上安装供抬升作业台车液压作业的液压泵站(49)和供电电缆卷盘(46),连接桁架梁(8)把两台抬升行走台车连接在一起形成整机,在连接桁架横梁上安装有供吊装材料的起重吊装小车(9),起重吊装小车由卷扬机牵引可沿桁架梁前后行走以实现轨道材料的精确吊装和就位。
参见图1-37,水平框架横梁(4)由若干纵梁、若干横梁和上部加强结构(3)组成,纵梁既是水平框架横梁的结构梁又是走行小车的前后移动的导柱,横梁既是水平框架横梁的结构梁又是抬升行走台车竖向支撑结构实现水平横向伸缩的导套结构,在水平框架横梁的上部安装加强结构以保证水平框架横梁的纵向、横向刚度,在横梁内安装垂直于线路方向的水平伸缩机构,水平伸缩机构由导柱(39)和竖向导套(40)组成,水平伸缩机构通过导柱(39)、导套(25)结构进行配合,水平横向伸缩通过液压驱动油缸实现,在导套(40)内安装竖向支撑结构,竖向支撑结构由第二导柱、第一导柱和第一驱动液压油缸组成,第二导柱还是第一导柱的导套,竖向支撑结构通过第一液压驱动油缸(41)驱动第一导柱和第二导柱逐级伸出来实现。
参见图1-37,走行小车由框架结构、轨道走行轮和安装在走行小车平面框架结构中心的履带走行机构组成,框架结构由两根导套和轨道走行轮以及连接结构件组成,走行小车通过导套套装在抬升行走台车水平框架横梁上,走行小车沿水平框架横梁的前后移动是通过第二液压驱动油缸(7)来实现,走行小车轨道走行轮由电机驱动行走在正线轨道上,在走行小车的上平面中心位置安装有履带走行机构,履带走行机构通过回转盘固定在走行小车的下结构底板上,履带走行机构通过伸缩导套(24)导柱(32)装置实现上下伸缩,伸缩导套(24)固定在回转盘(23)上,在回转盘(23)上平面安装转向驱动球销,导柱(32)的上下伸缩通过第三液压驱动油缸(18)实现,履带走行机构通过销轴和导柱连接,履带走行机构由底盘、驱动轮、引导轮、支重轮、托带轮和履带、液压驱动马达组成,在走行小车的上平面上还安装有可绕走行小车中心回转的转盘(27),转盘通过滚柱绕小车中心回转,在转盘(27)上安装有绞座(31),通过铰销和连接桁架梁(8)相连。
参见图1-37,连接桁架梁(8)由钢管焊接组成,分为三节,断面为“椅”字型,分左右两榀对称布置,每节之间通过连接销进行连接,在连接桁架梁上安装有供吊装小车(9)行走的轨道,在连接桁架梁的两端安装有卷扬机(47)和滑轮组(48),用于牵引吊装小车沿轨道前后移动,在抬升行走台车水平框架横梁的上加强结构上,安装供液压驱动的液压泵站(49)和电缆卷线盘(46),用于给新型铺轨机提供液压和电力。
以下结合附图及具体实施例对本实用新型中的施工技术方案进行进一步说明。
实例一:新型铺轨机施工准备、轨排吊运及安装作业
1、新型铺轨机由走行状态装转变为轨排吊装状态
参见图1-6,本发明主要结构设计:新型铺轨机由2台抬升行走台车和连接吊装桁架梁组成。
参见图5-20,抬升行走台车由水平框架横梁和走行小车组成,水平框架横梁由2根纵梁、4根横梁和上部加强结构(37)组成。2根纵梁既是水平框架梁的结构梁又是走行小车的前后移动的导柱,4根横梁既是水平框架梁的结构梁又是抬升行走台车竖向支撑装置实现水平横向伸缩的导套结构。在水平框架结构的上部安装加强结构(37)以保证水平框架横梁的纵向、横向刚度。在横梁内安装垂直于线路方向的水平伸缩机构,水平伸缩机构由导柱(39)和竖向导套(40)组成,水平伸缩机构通过导柱(39)、导套(25)结构进行配合,水平横向伸缩通过液压驱动油缸实现,在导套(40)内安装竖向支撑装置,竖向支撑装置由2级导柱(43)、1级导柱(44)和第一驱动液压油缸(41)组成,2级导柱还是1级导柱的导套。竖向支撑通过液压驱动油缸驱动1级导柱和2级导柱逐级伸出来实现。走行小车由框架结构、轨道走行轮和安装在走行小车平面框架结构中心的履带走行机构组成。框架机构由两根导套和轨道走行轮6以及连接结构件组成,走行小车通过导套(28)套装在抬升行走台车水平框架横梁(4)上,走行小车沿水平框架横梁(4)的前后移动是通过第二液压驱动油缸(7)来实现,走行小车轨道走行轮轮距为1508mm,由电机驱动行走在正线轨道上。在走行小车的上平面中心位置安装有履带走行装置(22),履带走行装置(22)通过回转盘(23)固定在走行小车(5)的下结构底板上,履带走行装置(22)通过导套导柱(32)装置实现上下伸缩,伸缩导套固定在回转盘(23)上,在回转盘(23)上平面安装转向驱动球销(53),导柱(32)的上下伸缩通过第二液压驱动油缸(18)实现,履带走行装置(22)通过销轴和导柱(32)连接,履带走行装置(22)有底盘、履带走行驱动轮(36)、履带走行引导轮(34)、履带走行支重轮(35)、履带托带轮(33)和履带走行驱动马达(51)组成,在走行小车(5)的上平面上还安装有可绕走行小车中心回转的转盘(27),转盘通过滚柱绕小车中心回转,在装盘(27)上安装有绞座(31),通过铰销和连接桁架梁(8)相连。
A.新型铺轨机抬升:
参见图3-10,将新型铺轨机运行到准备卸车位置停车,分别操作抬升行走台车的液压驱动油缸使竖向支撑装置的水平伸缩导柱向线路两侧伸出,当同一断面伸出的内部空间满足运输平板车和轨排宽度要求时停止并锁闭。分别操作竖向支撑装置的液压驱动油缸驱动导柱向下伸出,使其平稳地支撑在混凝土道床上面(如果道床面位置不合适则向外调整水平伸缩满足合适位置,地面不平进行支垫),确认稳妥后同步操作1、2号抬升行走台车的竖向支撑装置向下伸出由于道床面的制约向下伸出使得新型铺轨机产生向上抬升的状态,当新型铺轨机抬升到满足吊装平板车上的轨排材料高度后停止抬升,局部调整新型铺轨机8个支撑脚的受力状态,使其均匀受力,并使新型铺轨机属于水平状态,完成后停止操作并锁闭。
B.调整吊装小车的位置和吊装扁担的高度:
参见图20-30,操作吊装小车的走行牵引卷扬机,使吊装走行小车行驶到计划在吊装桁架梁的吊装位置,起升吊装装置调整吊装扁担高度,满足轨排运输车的喂料通行。
2、轨排喂料、新型铺轨机起吊、新型铺轨机下降至正线轨道上
a、参见图10-37,指挥轨道牵引车推送轨排运输平车缓缓进入新型铺轨机下;
b、参见图10-37,当轨排完全进入新型铺轨机下方时停止推送,制动;
c、参见图10-37,分别操作起重吊装小车的走行牵引卷扬机对起重吊装小车的吊点位置进行调整,无误后停止操作;
d、分别操作小车放下吊装扁担,使扁担挂钩和轨排牢固连接;
e、参见图10-37,一切确认无误后,解除平板车上的轨排约束,同步操作起重吊装小车使吊装小车缓缓将平板车上的轨排吊起,当轨排完全脱离平板车及其支垫轨排的转向架支座后停止操作。检查轨排及其钢筋笼是否脱离支垫,是否高出支垫物而影响走行,个别调整高度,一切无误后锁闭操作;
f、参见图10-37,指挥轨道牵引车牵引平板车缓缓退出新型铺轨机下方,当完全脱离新型铺轨机下方时加速使轨道牵引车驶回基地再次装载轨排;
g、参见图10-37,同步操作新型铺轨机1、2号抬升行走台车的竖向支撑装置的液压驱动油缸驱动导柱向回收缩使新型铺轨机缓缓下降,将新型铺轨机1、2号抬升行走台车的走行小车的轨道走行轮平稳地停放在正线轨道上。继续回缩液压油缸使8个支撑脚脱离混凝土道床面上升到上止点位置停止操作并锁闭。
3、新型铺轨机前行、走行装置转换、轨排安装就位:
a、分别操作起重吊装小车9调整轨排离正线轨道的高度,以免影响新型铺轨机的正常行驶;
b、参见图10-37,同步操作新型铺轨机1、2号抬升行走台车的轨道走行驱动电机使新型铺轨机吊装轨排沿正线轨道向轨排设计安装位置行走;
c、参见图10-37,当新型铺轨机2号抬升行走台车到达正线轨道端头车档位置时停止操作。操作2号抬升行走台车的竖向支撑水平框架横梁纵向移动驱动液压油缸7,使竖向支撑水平框架横梁整体向无正线轨道方向移动(相对于走行小车5),当移动到止点位置时停止操作;
d、参见图10-37,操作2号抬升行走台车的竖向支撑控制系统使竖向支撑下支撑脚平稳地支撑在区间结构底板上(不平时进行支垫),继续操作使走行小车5抬离正线轨道踏面一定高度(高于车档高度)停止操作;
e、参见图10-37,同步操作2号抬升行走台车的竖向支撑水平框架横梁纵向移动液压油缸7和1号抬升行走台车的走行装置使新型铺轨机吊装轨排向无正线轨道方向移动,当2号抬升行走台车的走行小车5全部移出正线轨道后停止操作;
f、参见图10-37,操作隐藏在2号抬升行走台车走行小车5中间的履带走行装置升降控制装置,使履带走行装置22缓缓下降平稳地支撑在结构底板上并受力,停止操作;
g、参见图10-37,操作2号抬升行走台车的竖向支撑控制装置使竖向支撑缓缓向上回缩脱离底板到一定高度(不影响新型铺轨机走行)后停止操作;
h、参见图10-37,同步操作1号抬升行走台车走行控制装置和2号抬升行走台车履带走行控制装置使新型铺轨机向无正向轨道方向行驶,此时新型铺轨机1号抬升行走台车行走在正线轨道上,2号抬升行走台车行走在结构底板上。当该作业在曲线地段时通过操作2号台车的履带走行转向控制装置53来调整行走方向;
i、参见图10-37,当新型铺轨机所吊装轨排的末端(靠近1号抬升行走台车端)其水平投影位置目测正好和已安装轨排端头相对齐时停止走行。同步操作起重吊装小车9将轨排下降(如接头对位有偏差时,纵向移动吊装小车使轨排准确对位),使轨排钢轨踏面基本处于设计安装高度;
j、参见图10-37,用接头夹板连接新安装轨排钢轨和原安装轨排接头,在新安装轨排上按设计要求间距安装临时支撑或轨道状态调整支架,对轨排进行固定。轨排固定完成后降下吊装小车9的吊钩,摘除轨排扁担,并将轨排吊装扁担抬升到最高点停止操作。
4、新型铺轨机走行机构转换、返回原轨排卸车点:
a、同步操作1号抬升行走台车走行装置控制装置和2号抬升行走台车履带走行装置控制装置使新型铺轨机向有正线轨道方向行走,当履带走行面靠近新安装轨排端头时停止走行;
b、参见图10-37,操作2号抬升行走台车竖向支撑水平框架梁的纵向移动液压油缸7使水平框架横梁向正线轨道方向移动,到止点位置时停止;
c、参见图10-37,操作2号抬升行走台车的竖向支撑控制装置,使竖向支撑支撑在结构底板上,继续操作通过目测使走行小车5的轨道走行轮下踏面高于新安装轨排钢轨上踏面后停止操作;
d、参见图10-37,操作2号抬升行走台车的履带升降控制装置,使履带走行装置22向上回缩到走行小车5的内部上止点停止操作,并锁闭;
e、参见图10-37,同步操作1号抬升行走台车走行小车控制装置和2号抬升行走台车竖向支撑水平框架横梁纵向移动控制装置使新型铺轨机向有正线轨道方向移动。当2号抬升行走台车走行小车5的水平投影全部进入新安装轨排轨道端头内时停止操作;
f、参见图10-37,操作2号抬升行走台车竖向支撑控制装置使抬升行走台车下降,走行小车平稳地降落在正线轨道钢轨他面上。继续操作使竖向支撑回缩到上止点位置后停止操作;
g、参见图10-37,同步操作1、2号抬升行走台车的走行小车5的走行控制装置使新型铺轨机沿正线轨道向原卸轨排位置行走,到达卸轨排位置后停止走行。
5、重新吊卸新轨排:
重复上述1、2、3、4中的所有步骤,完成新轨排的卸车和安装。这样不断地重复上述步骤完成轨道的铺设作业。
实例二:新型铺轨机预制轨道板吊运及安装施工
城市轨道交通道床板铺设施工一般是在区间道床板垫层施工完毕后进行,道床板为预制混凝土板,长度一般为5800mm(普通版),曲线调整板长度一般为4500mm—5000mm,为了便于预制板运输,一般铺设25m—50m道床板后及时安装钢轨扣件形成运输通道,当轨道板铺设达100m以上时,对轨道板和轨道状态进行调整,在轨道板下灌注自密实混凝土或其他砂浆材料对轨道板及轨道状态进行固定,形成轨道线路。因此铺设轨道板是关键工序。
1、轨道板卸车载、吊装、移动和就位
a、新型铺轨机抬升:参见图10-38,将新型铺轨机运行到准备卸车位置停车(新型铺轨机1号抬升行走台车处在已安装轨道板并形成正线轨道钢轨端部5米位置,2号抬升行走台车处在未安装轨道板的垫层位置上)。分别操作1、2号抬升行走台车的液压驱动油缸38使竖向支撑装置的水平伸缩导柱39向线路两侧伸出,当同一断面伸出的内部空间满足运输平板车和轨排宽度要求时停止并锁闭。分别操作1、2号抬升行走台车的竖向支撑装置的液压驱动油缸41、42驱动导柱43、44向下伸出,使其平稳地支撑在垫层面(如果垫层面位置不合适则向外调整水平伸缩满足合适位置,地面不平时进行支垫),确认稳妥后继续同步操作1、2号抬升行走台车的竖向支撑装置向下伸出,由于垫层面的制约向下伸出使得新型铺轨机产生向上抬升的状态,当新型铺轨机抬升到满足吊装平板车上的轨道板高度后停止抬升,分别调整新型铺轨机8个支撑脚的受力状态,使其均匀受力,并使新型铺轨机属于水平状态,完成后停止操作并锁闭;
b、调整吊装小车9的位置和吊装扁担的高度:参见图10-38,操作吊装小车9的走行牵引卷扬机47,使吊装走行小车9行驶到计划在吊装桁架梁的吊装位置,起升吊装装置调整吊装扁担高度,满足轨排运输车的喂料通行。
2、轨道板喂料、轨道板起吊、移动、安装:
a、参见图10-37,指挥轨道牵引车推送轨道板运输平车缓缓进入新型铺轨机下;
b、参见图10-37,当轨道板完全进入新型铺轨机下方时停止推送,制动;
c、参见图10-37,分别操作起重吊装小车9的走行牵引卷扬机47对起重吊装小车9的吊点位置进行调整,无误后停止操作;
d、分别操作小车9放下吊装扁担,使扁担挂钩和轨道板牢固连接;
e、参见图10-37,一切确认无误后,解除平板车上的轨道板约束,同步操作起重吊装小车9使吊装小车缓缓将平板车上的轨道板吊起,当轨道板完全脱离平板车及其支垫轨道板的垫木后停止操作。检查轨道板是否脱离支垫,是否高出支垫物而影响走行?个别调整高度,一切无误后锁闭操作;
f、参见图10-37,同步操作起重吊装小车移动控制装置使吊装小车吊装轨道板沿连接桁架梁向安装方向移动(见图54),当到达安装位置上方时停止移动,操作吊装小车吊装控制将轨道板缓缓下降,平稳地摆放在安装位置,此时可通过移动吊装小车使轨道精确就位;
g、参见图10-37,轨道板摆放完成后拆除吊装扁担与轨道板的连接,同步提升吊装扁担至上限位高度,同步移动吊装小车到运输平板车轨道板位置继续吊装下一块轨道板;
h、重复操作上述c、d、e、f、g步骤完成第二块、第三块等轨道板的吊装;
i、当新型铺轨机下方空间轨道板全部安装完成后,停止操作;
j、参见图10-37,指挥轨道牵引车把正线临时用钢轨运送到新型铺轨机下;
k、参见图10-37,同步操作起重吊装小车9吊起钢轨并纵向移动到轨道板的安装位置,缓缓降下钢轨平稳地摆放在轨道板的承轨槽垫板上;
l、参见图10-37,按规定要求用扣件扣紧钢轨,使正线钢轨形成通道。
3、新型铺轨机前移、抬升,准备新位置吊装:
a、参见图10-37,同步操作新型铺轨机1、2号抬升行走台车的竖向支撑装置的液压驱动油缸41、42驱动导柱43、44向回收缩,使新型铺轨机缓缓下降,将新型铺轨机1号抬升行走台车的走行小车5的轨道走行轮平稳地停放在正线轨道上停止操作。操作2号抬升行走台车的履带走行机构,使其下降平稳地支撑在垫层面上,继续操作1、2号抬升行走台车的竖向支撑控制装置使8个支撑脚脱离垫层面回缩到上止点位置停止操作并锁闭;
b、同步操作新型铺轨机走行控制装置使新型铺轨机向无轨道板方向走行,当1号抬升行走台车走行小车距离正线轨道钢轨端头5米时停止走行;
c、同步操作1、2号抬升行走台车的竖向支撑控制装置使支撑脚平稳地支撑在垫层面上,继续操作使新型铺轨机整体抬升到吊装轨道板的位置停止操作,调平新型铺轨机使新型铺轨机处于水平状态,检查新型铺轨机8个支撑脚支撑是否稳固可靠,一切无误后锁闭操作;
d、重复上述一、二、三各步骤完成再次轨道板吊装作业和钢轨安装作业。最后完成轨道板的铺装作业。
实例三:新型铺轨机作业面转场
参见图20-37,轨道施工一般是以铺轨基地为中心,上、下行线双向进行施工。道岔作为轨道转向的关键设备是提前进行施工的。新型铺轨机作业面转移就是利用已铺设完成的道岔和单渡线实现的,作业面转移有3种位置,途中新作业面1、新作业面2和新作业面3:
1、将新型铺轨机的1、2号抬升行走台车竖向支撑装置的水平伸缩装置收回到走行转移位置,将竖向支撑装置收回到上限位转移走行位置锁闭。拆除新型铺轨机供电电源,将电缆收卷到电缆卷线盘内。拆除新型铺轨机轨道走行轮与走行驱动减速器的连接,使其处于空挡状态。将新型铺轨机和轨道牵引车用连接拖杠进行连接。启动轨道牵引车,让轨道牵引车牵引新型铺轨机缓缓驶向道岔2位置。首先轨道牵引车牵引新型铺轨机通过道岔2,当新型铺轨机尾部到达道岔2信号机位置时停止走行,扳动道岔1和道岔2开通道岔侧向通行轨道,启动轨道牵引车,让轨道牵引车推送新型铺轨机进过道岔2、道岔1进入正线1,到达新作业面1,完成转场作业;
2、参见图20-37,将新型铺轨机的1、2号抬升行走台车竖向支撑装置的水平伸缩装置收回到走行转移位置,将竖向支撑装置收回到上限位转移走行位置锁闭。拆除新型铺轨机供电电源,将电缆收卷到电缆卷线盘内。拆除新型铺轨机轨道走行轮与走行驱动减速器的连接,使其处于空挡状态。将新型铺轨机和轨道牵引车用连接拖杠进行连接。启动轨道牵引车,让轨道牵引车牵引新型铺轨机缓缓驶向道岔2位置。首先轨道牵引车牵引新型铺轨机通过道岔2,当新型铺轨机尾部到达道岔信号机位置时停止走行,扳动道岔1和道岔2开通道岔侧向通 行轨道,启动轨道牵引车,让轨道牵引车推送新型铺轨机进过道岔2、道岔1进入正线1,当轨道牵引车尾部到达道岔1的信号机位置时停车,拆除新型铺轨机和轨道牵引车的连接,启动轨道牵引车侧向通行返回,当轨道牵引车尾部到达道岔1的警冲标位置时停车。扳动道岔1恢复正向通行,通电使新型铺轨机向作业面方向行驶,当新型铺轨机的尾部经过道岔1到达道岔1的警冲标位置时停止。扳动道岔1开通侧向通行,启动轨道牵引车向正线1行驶,当轨道牵引车尾部到达道岔1的信号机位置时停车,扳动道岔1恢复正向通行。启动轨道牵引车缓缓经过道岔1向新型铺轨机靠近,到达道岔1的警冲标位置附近时停车,用连接拖杠连接轨道牵引车和新型铺轨机,连接无误后启动轨道牵引车将新型铺轨机推送到新作业面2,完成作业转场;
3、参见图20-37,将新型铺轨机的1、2号抬升行走台车竖向支撑装置的水平伸缩装置收回到走行转移位置,将竖向支撑装置收回到上限位转移走行位置锁闭。拆除新型铺轨机供电电源,将电缆收卷到电缆卷线盘内。拆除新型铺轨机轨道走行轮与走行驱动减速器的连接,使其处于空挡状态。将新型铺轨机和轨道牵引车用连接拖杠进行连接。启动轨道牵引车,让轨道牵引车牵引新型铺轨机缓缓驶向道岔2位置。当新型铺轨机头部到达道岔2的警冲标位置时停车,拆除新型铺轨机和轨道牵引车的连接,启动轨道牵引车继续向前行驶,当轨道牵引车尾部到达到达道岔2的信号机位置时停车。扳动道岔2开通侧向通行,启动轨道牵引车反向行驶,当轨道牵引车尾部到达道岔2的警冲标位置时停车。扳动道岔2恢复正向通行,开动新型铺轨机向新作业面4方向行驶,当新型铺轨机尾部到达道岔2的信号机位置时停止。扳动道岔2,恢复侧向通行,启动轨道牵引车缓缓靠近新型铺轨机后停止,用连接拖杠连接轨道牵引车和新型铺轨机,连接无误后启动轨道牵引车将新型铺轨机推送到新作业面3,完成作业转场。

Claims (8)

  1. 一种城市轨道交通工程新型铺轨机,包括抬升行走作业台车、连接桁架梁、履带走行机构和支撑结构,其特征在于新型铺轨机由两台抬升行走作业台车和连接两台抬升行走台车的连接桁架梁组成,抬升行走作业台车由走行小车、供走行小车实现纵向移动的水平框架横梁组成,在水平框架横梁的前后端安装能向正线轨道两侧水平伸出的并具有竖向抬升行走作业台车的支撑结构,走行小车由框架结构、轨道走行轮和安装在走行小车平面框架结构中心的履带走行机构组成,在有正线轨道地段新型铺轨机通过轨道走行轮行走在正线轨道上,在无正线轨道地段新型铺轨机通过履带走行机构行走在结构底板上,具有水平伸缩和竖向抬升的支撑结构用于新型铺轨机在正线轨道和无正线轨道转换。
  2. 如权利要求1所述的一种城市轨道交通工程新型铺轨机,其特征在于水平框架横梁的外侧安装有供新型铺轨机和牵引车连接的插销挂钩,水平框架横梁的上部加强结构框架上安装供抬升作业台车液压作业的液压泵站和供电电缆卷盘,连接桁架梁把两台抬升行走台车连接在一起形成整机,在连接桁架横梁上安装有供吊装材料的起重吊装小车,起重吊装小车由卷扬机牵引可沿桁架梁前后行走以实现轨道材料的精确吊装和就位。
  3. 如权利要求1所述的一种城市轨道交通工程新型铺轨机,其特征在于水平框架横梁由若干纵梁、若干横梁和上部加强结构组成,纵梁既是水平框架横梁的结构梁又是走行小车的前后移动的导柱,横梁既是水平框架横梁的结构梁又是抬升行走台车竖向支撑结构实现水平横向伸缩的导套结构,在水平框架横梁的上部安装加强结构以保证水平框架横梁的纵向、横向刚度,在横梁内安装垂直于线路方向的水平伸缩机构,水平伸缩机构由导柱和竖向导套组成,水平伸缩机构通过导柱、导套结构进行配合,水平横向伸缩通过液压驱动油缸实现,在导套内安装竖向支撑结构,竖向支撑结构由第二导柱、第一导柱和第一驱动液压油缸组成,第二导柱还是第一导柱的导套,竖向支撑结构通过第一液压驱动油缸驱动第一导柱和第二导柱逐级伸出来实现。
  4. 如权利要求1所述的一种城市轨道交通工程新型铺轨机,其特征在于走行小车由框架结构、轨道走行轮和安装在走行小车平面框架结构中心的履带走行机构组成,框架结构由两根导套和轨道走行轮以及连接结构件组成,走行小车通过导套套装在抬升行走台车水平框架横梁上,走行小车沿水平框架横梁的前后移动是通过第二液压驱动油缸来实现,走行小车轨道走行轮由电机驱动行走在正线轨道上,在走行小车的上平面中心位置安装有履带走行机构,履带走行机构通过回转盘固定在走行小车的下结构底板上,履带走行机构通过导套导柱装置实现上下伸缩,伸缩导套固定在回转盘上,在回转盘上平面安装转向驱动球销,导柱的上下伸缩通过第三液压驱动油缸实现,履带走行机构通过销轴和导柱连接,履带走行机构由底盘、驱动轮、引导轮、支重轮、托带轮和履带、液压驱动马达组成,在走行小车的上平面上还安装有可绕走行小车中心回转的转盘,转盘通过滚柱绕小车中心回转,在转盘上安装有绞座,通过铰销和连接桁架梁相连。
  5. 如权利要求1所述的一种城市轨道交通工程新型铺轨机,其特征在于连接桁架梁由钢管焊接组成,分为三节,断面为“椅”字型,分左右两榀对称布置,每节之间通过连接销进行连接,在连接桁架梁上安装有供吊装小车行走的轨道,在连接桁架梁的两端安装有卷扬机和滑轮组,用于牵引吊装小车沿轨道前后移动,在抬升行走台车水平框架横梁的上加强结构上,安装供液压驱动的液压泵站和电缆卷线盘,用于给新型铺轨机提供液压和电力。
  6. 一种采用如权利要求1-5所述城市轨道交通工程新型铺轨机的施工方法,其特征在于所述施工方法如下:新型铺轨机从轨排运输车上卸下轨排时,首现操作抬升行走台车的水 平伸缩和竖向支撑结构将新型铺轨机整体抬升到吊卸轨道材料的高度,将运输轨道材料的平板运输车推送到新型铺轨机连接桁架梁下,用起重吊装小车把轨道材料吊起离开平板运输车及材料支垫物,平板运输车退出新型铺轨机下方,操作抬升行走台车的竖向支撑结构将新型铺轨机连同轨道材料下降使新型铺轨机走行小车平稳地降落在正线轨道上完成卸车;新型铺轨机在正线轨道走行至安装位置附近,当前方抬升行走台车到达正线轨道端头车档时,操作抬升行走台车的竖向支撑结构使走行小车脱离轨道,操作抬升行走台车的纵向移动控制装置将走行小车移出正线轨道外,操作履带走行控制装置将履带走行机构下降支撑在结构地板上,将抬升机构恢复到收缩初始位,继续让新型铺轨机向前行走到达轨排设计安装位置,卸下轨道材料,连接钢轨、安装轨排临时支撑固定新安装轨排,反向操作新型铺轨机抬升、机构转换、纵向移动控制装置将新型铺轨机回位到正线轨道上,继续向再一次吊装轨排位置行走到达卸车地点进行排吊装下一个循坏。
  7. 如权利要求6所述的一种城市轨道交通工程新型铺轨机施工方法,其特征在于具体施工方法如下:
    A.轨排搭接吊装、运输工作
    (1)操作新型铺轨机到达轨排卸车位置,分别操作1、2号抬升行走台车的带水平伸缩的竖向支撑结构使竖向支撑向线路两侧伸出,伸出距离满足轨排运输平板车和所装载材料的宽度加安全距离的要求,确认安全后锁闭操作;
    (2)分别操作1、2号抬升行走台车的带水平伸缩的竖向支撑结构使竖向支撑向下伸出,竖向支撑下支撑脚盘平稳地支撑在已达到强度的道床上面或结构底板上面,并确认均匀受力,同步继续操作1、2号抬升行走台车的带水平伸缩的竖向支撑结构使竖向支撑继续向下伸出,由于底板的支撑反作用使得1、2号抬升行走台车以及连接吊装桁架梁缓缓向上抬升,当到达吊装高度后停止操作,再次检查抬升行走台车的竖向支撑结构稳固支撑和均匀受力后锁闭;
    (3)指挥轨道牵引车推送运输轨道材料的平板运输车缓缓驶入新型铺轨机下方,当轨排全场范围完全进入连接吊装桁架梁下时停止推送,驻车制动;
    (4)分别操作新型铺轨机连接桁架梁横梁上的起重小车,使其对准轨道材料吊装的吊点位置,降下吊装扁担将挂钩和轨排连接,分别操作起重小车使吊点受力,再次检查新型铺轨机的竖向支撑脚确认牢固,同步操作起重小车缓缓吊起轨道材料,当轨道材料完全脱离平板运输车上的转向架支撑结构上支点加安全距离后停止起升,锁闭操作,启动轨道牵引车使其牵引平板车缓缓驶离新型铺轨机下方一定距离停车或返回基地运输下一个轨排;
    (5)同步反向操作1、2号抬升行走台车的带水平伸缩的竖向支撑结构使竖向支撑向上回收,此时1、2号抬升行走台车连同连接桁架梁、所吊轨道材料缓缓下降,并缓慢地下降在正线轨道上,继续反向操作1、2号抬升行走台车的带水平伸缩的竖向支撑结构使竖向支撑向上回收,回位到新型铺轨机转运状态,锁闭操作,调整1、2号抬升行走台车的带水平伸缩的竖向支撑结构,使统一横的断面竖向支撑支撑脚的距离大于轨道材料的宽度即可;
    (6)操作新型铺轨机走行装置控制系统使新型铺轨机吊装轨道材料沿正线轨道向设计安装位置走行,新型铺轨机吊装轨道材料通过混凝土浇筑完成地段、未浇筑混凝土地段、以及轨排调整完成并固定地段到达正线轨道端头;
    (7)当新型铺轨机2号抬升行走台车的走行小车到达正线轨道端头车档位置时停止走行;
    B.新型铺轨机走行机构转换、移动、轨排就位工作
    (1)当新型铺轨机2号抬升行走台车的走行小车走行轮到达正线轨道端头车档位置时停止走行,操作2号抬升行走台车走行小车纵移控制装置,使抬升行走台车水平框架结构相对于走行小车向无正线轨道方向移动到达纵移止点位置停止操作;
    (2)操作2号抬升行走台车的带水平伸缩的竖向支撑结构向下伸出,带水平伸缩的竖向支撑结构下支撑脚盘平稳地支撑在结构底板上面,并确认均匀受力,继续操作使2号抬升行走台车走行小车向上抬升离开正线轨道踏面并高于车档高度后停止抬升操作并锁闭;
    (3)同步操作1号抬升行走台车的走行小车走行驱动和2号抬升行走台车走行小车纵移控制装置,使1号抬升行走台车、连接桁架梁、轨道材料、2号抬升行走台车的走行小车向无正线轨道方向移动,到达2号抬升行走台车走行小车纵移止点位置停止操作,锁闭,此时走行小车水平投影完全脱离正线轨道;
    (4)操作2号抬升行走台车走行小车内的履带走行机构升降装置,使履带走行机构慢慢下降,且平稳地支撑在结构地板上并受力;
    (5)操作2号抬升行走台车的带水平伸缩的竖向支撑结构,使带水平伸缩的竖向支撑结构完全脱离结构底板一定高度停止操作并锁闭;
    (6)同步操作1号抬升行走台车走行小车走行控制装置和2号抬升行走台车履带走行控制装置,使新型铺轨机向无正线轨道方向走行,操作2号行走太车上的履带走行方向控制装置调整2号台车走行方向,保证2号台车行走在轨道中心线上,当1号抬升行走台车接近正线轨道端头时停止走行,检查轨排水平投影位置和已安装轨排端头相连位置,如位置有少量偏差则通过移动起重吊装小车完成对位,如偏差较大则移动新型铺轨机完成对位;
    (7)同步操作起重吊装小车将轨排缓缓下降至设计安装高度,前后少量移动起重吊装小车,完成新安装轨排和已安装轨排的对位后停止操作;
    (8)用钢轨夹板把钢轨接头进行连接固定,在轨排上按设定位置安装临时支撑或轨道状态调整架并拧紧调整螺母固定新安装轨排的空间位置;
    (9)操作起重吊装控制装置,摘除吊装扁担和轨排的连接,提升吊装扁担到上限位位置停止操作;
    C.新型铺轨机走行机构转换返回搭接吊装位置作业
    (1)操作新型铺轨机向有正线轨道方向走行,当走行履带端面靠近新安装轨排端头时停止走行;
    (2)操作2号抬升行走台车的走行小车纵移控制装置,使抬升行走台车水平框架结构相对于走行小车向有正线轨道方向移动到达纵移止点位置停止操作;
    (3)操作2号抬升行走台车的带水平伸缩的竖向支撑结构使竖向支撑向下伸出,带水平伸缩的竖向支撑结构下支撑脚盘平稳地支撑在结构底板上面,并确认均匀受力,继续操作使2号抬升行走台车的走行小车向上抬升高于车档高度后停止抬升操作并锁闭;
    (4)操作2号抬升行走台车走行小车内的履带走行机构升降装置,使履带走行机构慢慢抬升,且平稳地收缩在走行小车内部的上限位位置停止操作并锁闭;
    (5)同步操作1号抬升行走台车的走行小车走行驱动和2号抬升行走台车走行小车纵移控制装置,使1号抬升行走台车、连接桁架梁、2号抬升行走台车的走行小车向有正线轨道方向移动,到达2号抬升行走台车的走行小车纵移止点位置停止操作,锁闭,此时走行小车水平投影完全进入正线轨道上方;
    (6)操作2号抬升行走台车的带水平伸缩的竖向支撑结构,使带水平伸缩的竖向支撑结构回缩,2号抬升行走台车的走行小车平稳地降落在正线轨道上车档内侧,继续操作2号抬升行走台车的带水平伸缩的竖向支撑结构,使带水平伸缩的竖向支撑结构完全回缩到上止点位置后停止操作并锁闭;
    (7)同步操作1、2号抬升行走台车轨道走行控制装置,使新型铺轨机返回到接收新运输到的轨排地点,准备再一次的轨排吊装作业;
    D.新型铺轨机再次吊装轨排、运输、安装作业
    重复所述步骤A-步骤C的全部动作,完成轨排的再次吊装运输、安装和新型铺轨机就位,以此类推完成轨道施工作业。
  8. 如权利要求6所述的一种城市轨道交通工程新型铺轨机施工方法,其特征在于具体施工方法如下:新型铺轨机作业面转场作业,当轨道施工一个作业面完成后需要转场至新作业面时有这样几种情况:一是同方向的另一条施工线作业位置,二是反方向的另两条施工线作业位置,新型铺轨机转场是在轨道牵引车的牵引下通过已铺好的第一道岔、第二道岔实现转场作业,完成作业面转移按下述步骤进行:
    (1)转移到同方向另一条线路施工现场作业位置:将新型铺轨机的1、2号抬升行走台车竖向支撑结构的水平伸缩装置收回到走行转移位置,将竖向支撑结构收回到上限位转移走行位置锁闭,拆除新型铺轨机供电电源,将电缆收卷到电缆卷线盘内,拆除新型铺轨机轨道走行轮与走行驱动减速器的连接,使其处于空挡状态,将新型铺轨机和轨道牵引车用连接拖杠进行连接,启动轨道牵引车,让轨道牵引车牵引新型铺轨机缓缓驶向第二道岔位置,首先轨道牵引车牵引新型铺轨机通过第二道岔,当新型铺轨机尾部到达道岔信号机位置时停止走行,扳动第一道岔和第二道岔开通道岔侧向通行轨道,启动轨道牵引车,让轨道牵引车推送新型铺轨机进过第二道岔、第一道岔进入正线,到达新作业面,完成转场作业;
    (2)转移到反方向新作业面:将新型铺轨机的1、2号抬升行走台车竖向支撑结构的水平伸缩装置收回到走行转移位置,将竖向支撑结构收回到上限位转移走行位置锁闭,拆除新型铺轨机供电电源,将电缆收卷到电缆卷线盘内,拆除新型铺轨机轨道走行轮与走行驱动减速器的连接,使其处于空挡状态,将新型铺轨机和轨道牵引车用连接拖杠进行连接,启动轨道牵引车,让轨道牵引车牵引新型铺轨机缓缓驶向第二道岔位置,首先轨道牵引车牵引新型铺轨机通过第二道岔,当新型铺轨机尾部到达道岔信号机位置时停止走行,扳动第一道岔和第二道岔开通道岔侧向通行轨道,启动轨道牵引车,让轨道牵引车推送新型铺轨机经过第二道岔、第一道岔进入正线,当轨道牵引车尾部到达第一道岔的信号机位置时停车,拆除新型铺轨机和轨道牵引车的连接,启动轨道牵引车侧向通行返回,当轨道牵引车尾部到达第一道岔的警冲标位置时停车,扳动第一道岔恢复正向通行,启动新型铺轨机向作业面方向行驶,当新型铺轨机的尾部经过第一道岔到达第一道岔的警冲标位置时停止,扳动第一道岔开通侧向通行,启动轨道牵引车向正线行驶,当轨道牵引车尾部到达第一道岔的信号机位置时停车,扳动第一道岔恢复正向通行,启动轨道牵引车缓缓经过第一道岔向新型铺轨机靠近,到达第一道岔的警冲标位置附近时停车,用连接拖杠连接轨道牵引车和新型铺轨机,连接无误后启动轨道牵引车将新型铺轨机推送到新作业面,完成作业转场;
    (3)转移到反方向新作业面:将新型铺轨机的1、2号抬升行走台车竖向支撑结构的水平伸缩装置收回到走行转移位置,将竖向支撑结构收回到上限位转移走行位置锁闭,拆除新型铺轨机供电电源,将电缆收卷到电缆卷线盘内,拆除新型铺轨机轨道走行轮与走行驱动减速器的连接,使其处于空挡状态,将新型铺轨机和轨道牵引车用连接拖杠进行连接,启动轨道牵引车,让轨道牵引车牵引新型铺轨机缓缓驶向第二道岔位置,当新型铺轨机头部到达第二道岔的警冲标位置时停车,拆除新型铺轨机和轨道牵引车的连接,启动轨道牵引车继续向前行驶,当轨道牵引车尾部到达到达第二道岔的信号机位置时停车,扳动第二道岔开通侧向通行,启动轨道牵引车反向行驶,当轨道牵引车尾部到达第二道岔的警冲标位置时停车,扳动第二道岔恢复正向通行,开动新型铺轨机向新作业面方向行驶,当新型铺轨机尾部到达第二道岔的信号机位置时停止,扳动第二道岔,恢复侧向通行,启动轨道牵引车缓缓靠近新型铺轨机后停止,用连接拖杠连接轨道牵引车和新型铺轨机,连接无误后启动轨道牵引车将新型铺轨机推送到另一新作业面,完成作业转场。
PCT/CN2018/111341 2017-10-26 2018-10-23 一种城市轨道交通工程新型铺轨机及其施工方法 Ceased WO2019080824A1 (zh)

Priority Applications (2)

Application Number Priority Date Filing Date Title
DE212018000090.5U DE212018000090U1 (de) 2017-10-26 2018-10-23 Neue Schienenverlegmaschine für die städtische Schienenverkehrtechnik
US16/333,991 US20210332533A1 (en) 2017-10-26 2018-10-23 Novel track layer for urban track traffic engineering and its construction method

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201711011324.5 2017-10-26
CN201711011324.5A CN107642012B (zh) 2017-10-26 2017-10-26 一种城市轨道交通工程新型铺轨机及其施工方法

Publications (1)

Publication Number Publication Date
WO2019080824A1 true WO2019080824A1 (zh) 2019-05-02

Family

ID=61123568

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2018/111341 Ceased WO2019080824A1 (zh) 2017-10-26 2018-10-23 一种城市轨道交通工程新型铺轨机及其施工方法

Country Status (4)

Country Link
US (1) US20210332533A1 (zh)
CN (1) CN107642012B (zh)
DE (1) DE212018000090U1 (zh)
WO (1) WO2019080824A1 (zh)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110725215A (zh) * 2019-11-06 2020-01-24 郑州市市政工程总公司 现有桥梁上新建上层桥梁的运梁结构和利用现有桥梁的运梁方法
CN111441195A (zh) * 2020-04-22 2020-07-24 中铁上海工程局集团有限公司 一种铺轨机行进变跨引导装置及其使用方法
CN114311249A (zh) * 2021-11-23 2022-04-12 中交第三航务工程局有限公司宁波分公司 一种凿毛机凿毛的控制方法
CN114776952A (zh) * 2021-06-23 2022-07-22 重庆电子工程职业学院 一种可变轮距的滑轨车
CN115595836A (zh) * 2022-11-08 2023-01-13 中铁五局集团第六工程有限责任公司(Cn) 一种地下铁预制轨道板道床分区段工序的施工方法
CN117026699A (zh) * 2023-08-07 2023-11-10 中国铁建高新装备股份有限公司 一种道岔焊轨作业车

Families Citing this family (35)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107642012B (zh) * 2017-10-26 2024-08-02 中铁上海工程局集团有限公司 一种城市轨道交通工程新型铺轨机及其施工方法
CN109706960B (zh) * 2018-12-26 2024-08-02 中国建筑土木建设有限公司 一种架廊台车
CN109624623A (zh) * 2019-01-16 2019-04-16 中铁上海工程局集团有限公司 一种走行钢轮和履带可切换式走行装置及使用方法
CN109914166B (zh) * 2019-03-15 2024-08-02 中铁上海工程局集团有限公司 一种城市轨道散铺法机械化施工设备及其施工方法
CN110053634B (zh) * 2019-05-05 2024-05-28 中铁上海工程局集团有限公司 一种跨座式轨道梁搬运机及其使用方法
CN112252099B (zh) * 2019-07-22 2025-07-18 中国铁建高新装备股份有限公司 一种用于铁路道岔铺换的作业车及其作业方法
CN110541347B (zh) * 2019-09-17 2024-12-24 中铁工程装备集团隧道设备制造有限公司 大跨度全液压轮胎步履式隧道仰拱栈桥及施工方法
JP7138812B2 (ja) * 2019-11-18 2022-09-16 広州地鉄設計研究院股▲分▼有限公司 多機能磁気浮上列車レールのレール搬送敷設機
CN111038940B (zh) * 2019-12-02 2024-11-29 上海市政工程设计研究总院(集团)有限公司 一种轨道式用于吊装运输的牵引系统
CN110939383B (zh) * 2019-12-26 2025-07-25 中铁四局集团电气化工程有限公司 一种新型多用途隧道打孔机
CN111719358A (zh) * 2020-06-28 2020-09-29 中铁上海工程局集团有限公司 一种城市轨道交通工程公铁两用铺轨机及其使用方法
CN212388270U (zh) * 2020-06-28 2021-01-22 中铁上海工程局集团有限公司 一种城市轨道交通工程公铁两用铺轨机
FR3112352B1 (fr) * 2020-07-08 2023-10-27 Matisa Materiel Ind Sa Procédé de renouvellement de rails d’une voie ferrée par des longs rails nouveaux, et train de travaux associé
EP4196826B1 (en) * 2020-08-12 2024-06-26 Selskabet Af 6. April 2010 ApS Suspension of electromagnetic receiver coil
CN112408190B (zh) * 2020-12-03 2024-12-10 中船第九设计研究院工程有限公司 一种平面分段流水线
CN113152299B (zh) * 2021-04-23 2023-07-04 中交第二航务工程局有限公司 一种斜拉桥钢梁节段荡移装置及吊装方法
CN114060056B (zh) * 2021-11-15 2024-06-11 中铁长安重工有限公司 一种隧道纵向钢筋和环向钢筋作业设备
CN114320361B (zh) * 2021-12-16 2023-10-20 中铁十局集团青岛工程有限公司 一种衬砌带模注浆系统
CN114394513B (zh) * 2022-01-11 2026-02-03 中铁第四勘察设计院集团有限公司 一种适用于高速磁浮的轨道梁起吊设备
CN114045711B (zh) * 2022-01-13 2022-04-08 唐山中铁实业集团有限公司 轨排铺设机组及铺设方法
DE202022002760U1 (de) 2022-05-18 2023-08-21 Martin Buck Vorrichtung zur Fixierung von Laufschienen eines Hochregallagergestells
DE102022112480A1 (de) 2022-05-18 2023-11-23 Martin Buck Vorrichtung und Verfahren zur Fixierung von Laufschienen eines Hochregallagergestells
CN114955421B (zh) * 2022-05-20 2023-03-14 山东农业大学 网格式吊挂运输系统及控制方法
CN114892541B (zh) * 2022-06-16 2024-08-16 湖南科技大学 一种行走吊装一体的跨座式单轨架桥机
CN115559162A (zh) * 2022-10-25 2023-01-03 中铁一局集团有限公司 一种盾构隧道临时轨道拆除装置
CN115653316B (zh) * 2022-11-15 2023-03-31 中铁九局集团有限公司 一种钢筋网绑扎机器人及其绑扎方法
CN115788074B (zh) * 2022-11-30 2025-08-05 中国一冶集团有限公司 一种叠合板快速精准安装装置及其施工方法
CN115748328B (zh) * 2022-12-06 2026-02-27 宝鸡中车时代工程机械有限公司 一种八轮道岔转运装置
CN116163168A (zh) * 2023-03-09 2023-05-26 重庆单轨交通工程有限责任公司 一种跨座式单轨轨道梁梁体抬升防倾覆装置
CN117513078A (zh) * 2023-10-31 2024-02-06 中国水利电力对外有限公司 一种多功能轨道转运铺设方法
CN117905277A (zh) * 2024-03-02 2024-04-19 湖南省第六工程有限公司 一种用于保温层施工的铺贴系统及方法
CN118273172B (zh) * 2024-05-09 2025-01-21 中铁二十三局集团有限公司 磁浮轨道梁架梁运输装置及架梁方法
CN119021044B (zh) * 2024-08-26 2026-02-03 中铁一局集团有限公司 一种轨道施工预制板调整机器人及其作业方法
CN119190100A (zh) * 2024-10-14 2024-12-27 第同管理(东莞)有限公司 轨道检测装置
CN120749600B (zh) * 2025-08-25 2025-11-11 长缆科技集团股份有限公司 一种可伸缩式线缆展放装置及电缆展放方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4637314A (en) * 1985-06-20 1987-01-20 Gower David I Railroad spike resinstallation apparatus
CA2277359A1 (fr) * 1998-07-10 2000-01-10 Fassetta Mecanique Procede et dispositif de pose d'element de voie par les lorries a chenilles
CN104179092A (zh) * 2014-09-04 2014-12-03 常州市瑞泰工程机械有限公司 拆取、运输、铺设道岔钢轨组件的机械
CN104727194A (zh) * 2015-04-01 2015-06-24 武桥重工集团股份有限公司 一种可带载横移跨线的铁路铺轨机
CN107642012A (zh) * 2017-10-26 2018-01-30 中铁上海工程局集团有限公司 一种城市轨道交通工程新型铺轨机及其施工方法
CN207498754U (zh) * 2017-10-26 2018-06-15 中铁上海工程局集团有限公司 一种城市轨道交通工程新型铺轨机

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0056497A1 (de) * 1981-01-15 1982-07-28 Les Fils D'auguste Scheuchzer S.A. Rahmenwagen in einem Gleisbauzug zur Untergrundsanierung von Eisenbahngleisen
AT400340B (de) * 1989-10-12 1995-12-27 Plasser Bahnbaumasch Franz Einrichtung zum verlegen von schwellen
CN201010842Y (zh) * 2007-03-22 2008-01-23 中铁一局集团有限公司新运工程公司 轮胎式可变跨多功能轨道铺设机
CN101718063A (zh) * 2009-04-16 2010-06-02 上海彭浦机器厂有限公司 铁路铺轨机用履带式牵引机构
CN102102317B (zh) * 2009-12-22 2012-03-07 中铁科工集团有限公司 客货共线无缝线路铺架工法及用于架设铁路t梁的架桥机
CN103938508B (zh) * 2014-02-26 2016-08-31 中铁上海工程局集团有限公司 一种铺轨机整机长途运输装卸方法
CN106638185B (zh) * 2016-10-10 2019-01-11 中铁上海工程局集团有限公司 一种行进过程自动变跨铺轨机及使用方法
CN106894338B (zh) * 2017-02-13 2019-03-05 北京恒力铁科技术开发有限公司 一种桥梁梁底检查车轨道的铺设设备

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4637314A (en) * 1985-06-20 1987-01-20 Gower David I Railroad spike resinstallation apparatus
CA2277359A1 (fr) * 1998-07-10 2000-01-10 Fassetta Mecanique Procede et dispositif de pose d'element de voie par les lorries a chenilles
CN104179092A (zh) * 2014-09-04 2014-12-03 常州市瑞泰工程机械有限公司 拆取、运输、铺设道岔钢轨组件的机械
CN104727194A (zh) * 2015-04-01 2015-06-24 武桥重工集团股份有限公司 一种可带载横移跨线的铁路铺轨机
CN107642012A (zh) * 2017-10-26 2018-01-30 中铁上海工程局集团有限公司 一种城市轨道交通工程新型铺轨机及其施工方法
CN207498754U (zh) * 2017-10-26 2018-06-15 中铁上海工程局集团有限公司 一种城市轨道交通工程新型铺轨机

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110725215A (zh) * 2019-11-06 2020-01-24 郑州市市政工程总公司 现有桥梁上新建上层桥梁的运梁结构和利用现有桥梁的运梁方法
CN111441195A (zh) * 2020-04-22 2020-07-24 中铁上海工程局集团有限公司 一种铺轨机行进变跨引导装置及其使用方法
CN114776952A (zh) * 2021-06-23 2022-07-22 重庆电子工程职业学院 一种可变轮距的滑轨车
CN114776952B (zh) * 2021-06-23 2023-07-07 青岛东唐影视科技有限公司 一种可变轮距的滑轨车
CN114311249A (zh) * 2021-11-23 2022-04-12 中交第三航务工程局有限公司宁波分公司 一种凿毛机凿毛的控制方法
CN115595836A (zh) * 2022-11-08 2023-01-13 中铁五局集团第六工程有限责任公司(Cn) 一种地下铁预制轨道板道床分区段工序的施工方法
CN115595836B (zh) * 2022-11-08 2024-04-30 中铁五局集团第六工程有限责任公司 一种地下铁预制轨道板道床分区段工序的施工方法
CN117026699A (zh) * 2023-08-07 2023-11-10 中国铁建高新装备股份有限公司 一种道岔焊轨作业车

Also Published As

Publication number Publication date
DE212018000090U1 (de) 2019-06-24
CN107642012A (zh) 2018-01-30
CN107642012B (zh) 2024-08-02
US20210332533A1 (en) 2021-10-28

Similar Documents

Publication Publication Date Title
WO2019080824A1 (zh) 一种城市轨道交通工程新型铺轨机及其施工方法
CN207498755U (zh) 一种带有水平伸缩和竖向支撑调节的走行小车
CN212388270U (zh) 一种城市轨道交通工程公铁两用铺轨机
CN207498754U (zh) 一种城市轨道交通工程新型铺轨机
CN111038940B (zh) 一种轨道式用于吊装运输的牵引系统
CN101818480A (zh) 一种箱梁转运平台及其移梁和装梁工序
CN114715797A (zh) 一种轨道板更换装置及系统
CN107513907A (zh) 一种地铁整体道床混凝土浇筑输送机及其使用方法
CN213328698U (zh) 一种高速铁路桥面系预制件安装设备
CN209444345U (zh) 一种隧道拱部预制管片施工装置
CN112252099B (zh) 一种用于铁路道岔铺换的作业车及其作业方法
CN114320364B (zh) 一种隧道喷锚辅助台车
CN114370006A (zh) 一种运梁车驮运架桥机转场的施工方法
CN111719358A (zh) 一种城市轨道交通工程公铁两用铺轨机及其使用方法
CN102071641B (zh) 水泥梁驮运桥机布支腿式运架一体架桥机及其架桥工法
CN114319145A (zh) 利用架桥机的桥梁架设方法
CN109487646A (zh) 盾构区间与站台区间运行轨道行进过程自动变跨方法
CN110777681B (zh) 一种整孔梁换架设备
CN110747757B (zh) 整孔梁换架设备
CN108130862A (zh) 过隧运梁车
CN113479787B (zh) 侧喂架廊机及管廊施工工艺
CN217325000U (zh) 架桥机的中托支架系统
CN109355983B (zh) 一种城市轨道的无轨施工方法
CN210439082U (zh) 一种复杂地段磁浮轨排铺设系统
CN110565458B (zh) 一种用于铺设u型梁轨道的铺设台车及方法

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 18870092

Country of ref document: EP

Kind code of ref document: A1

122 Ep: pct application non-entry in european phase

Ref document number: 18870092

Country of ref document: EP

Kind code of ref document: A1