WO2018013777A1 - Riser deflection mitigation - Google Patents

Riser deflection mitigation Download PDF

Info

Publication number
WO2018013777A1
WO2018013777A1 PCT/US2017/041882 US2017041882W WO2018013777A1 WO 2018013777 A1 WO2018013777 A1 WO 2018013777A1 US 2017041882 W US2017041882 W US 2017041882W WO 2018013777 A1 WO2018013777 A1 WO 2018013777A1
Authority
WO
WIPO (PCT)
Prior art keywords
riser
tether
restraint device
segment
ratcheting
Prior art date
Application number
PCT/US2017/041882
Other languages
French (fr)
Inventor
Wenzhi Li
Original Assignee
Ensco International Incorporated
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ensco International Incorporated filed Critical Ensco International Incorporated
Priority to EP17828444.4A priority Critical patent/EP3485131A4/en
Publication of WO2018013777A1 publication Critical patent/WO2018013777A1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B17/00Drilling rods or pipes; Flexible drill strings; Kellies; Drill collars; Sucker rods; Cables; Casings; Tubings
    • E21B17/01Risers
    • E21B17/017Bend restrictors for limiting stress on risers
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B19/00Handling rods, casings, tubes or the like outside the borehole, e.g. in the derrick; Apparatus for feeding the rods or cables
    • E21B19/002Handling rods, casings, tubes or the like outside the borehole, e.g. in the derrick; Apparatus for feeding the rods or cables specially adapted for underwater drilling
    • E21B19/004Handling rods, casings, tubes or the like outside the borehole, e.g. in the derrick; Apparatus for feeding the rods or cables specially adapted for underwater drilling supporting a riser from a drilling or production platform

Definitions

  • a riser string or riser may be used to transport drill pipe, casing, drilling mud, production materials or hydrocarbons between the offshore platform or floating vessel and a wellhead.
  • the riser is suspended between the offshore platform or floating vessel and the wellhead, and may experience forces, such as underwater currents, that cause deflection (e.g., bending or movement) in the riser.
  • Acceptable deflection can be measured by the deflection along the riser, and also at, for example, select points along the riser. These points may be located, for example, at the offshore platform or floating vessel and at the wellhead. If the deflection resulting from underwater current is too great, drilling must cease and the drilling location or reservoir may not be accessible due to such technological constraints.
  • FIG. 1 illustrates an example of an offshore platform having a riser.
  • FIG. 2 illustrates an example of the offshore platform of FIG. 1 having a riser experiencing deflection.
  • FIG. 3 illustrates a first embodiment of a system to mitigate the deflection of the riser of FIG. 2.
  • FIG. 4 illustrates a top and a side view of a riser restraint device of FIG. 3.
  • FIG. 5 illustrates a second top view of the riser restraint device 44 of FIG. 3.
  • a riser e.g., a riser string
  • offshore platform such as a drillship, a semi-submersible platform, a floating production system, or the like
  • a line is anchored to the riser via an anchor point.
  • the line may also be tethered to one or more winches on the offshore platform and through controlled deployment and retraction of the line via the one or more winches, the deflection of the riser may be adjusted. In this manner, through control of the amount of length of the line disposed between the anchor point and the one or more winches, deflections of the riser may be reduced.
  • FIG. 1 illustrates an offshore platform comprising a offshore vessel 10.
  • an offshore vessel 10 is a drillship (e.g., a ship equipped with a drill rig and engaged in offshore oil and gas exploration and/or well maintenance or completion work including, but not limited to, casing and tubing installation, subsea tree installations, and well capping), other offshore platforms such as a semi- submersible platform, a floating production system, or the like may be substituted for the drillship.
  • a drillship e.g., a ship equipped with a drill rig and engaged in offshore oil and gas exploration and/or well maintenance or completion work including, but not limited to, casing and tubing installation, subsea tree installations, and well capping
  • other offshore platforms such as a semi- submersible platform, a floating production system, or the like may be substituted for the drillship.
  • the techniques and systems described below are described in conjunction with a drillship, the techniques and systems are intended to cover at least the additional offshore platforms described above.
  • the offshore vessel 10 includes, having a derrick 11 thereon, includes a riser 12 extending therefrom.
  • the riser 12 may include a pipe or a series of pipes (e.g., riser segments) that connect the offshore vessel 10 to the seafloor 14 via, for example, blow out preventer (BOP) 16 that is coupled to a wellhead 18 on the seafloor 14.
  • BOP blow out preventer
  • the riser 12 may transport produced hydrocarbons and/or production materials between the offshore vessel 10 and the wellhead 18, while the BOP 16 may include at least one valve with a sealing element to control wellbore fluid flows.
  • the riser 12 may pass through an opening (e.g., a moonpool) in the offshore vessel 10 and may be coupled to drilling equipment of the offshore vessel 10. As illustrated in FIG. 1, it may be desirable to have the riser 12 positioned in a vertical orientation between the wellhead 18 and the offshore vessel 10. However, external factors (e.g., environmental factors such as currents) may disturb the vertical orientation of the riser 12.
  • an opening e.g., a moonpool
  • external factors e.g., environmental factors such as currents
  • the riser 12 may experience deflection, for example, from currents 20. These currents 20 may apply forces on the riser 12, which causes deflection (e.g., motion, bending, or the like) in riser 12.
  • deflection e.g., motion, bending, or the like
  • the riser 12 will have significant horizontal deflection due to the drag loads applied along the riser 12.
  • the angle 24 between the vertical axis 26 (e.g., an axis of 90° between the seafloor 14 and the surface of the sea 28) of the riser bottom flex joint 30 may exceed tolerance levels for the performance of, for example, drilling operations.
  • This angle 24 may be modified through the dynamic positioning of the offshore vessel 10. That is, through the movement of the offshore vessel 10 in response to the currents 20, the static angle 24 of the bottom flex joint 30 may be reduced and/or eliminated to meet any operational requirements associated with, for example, the blow out preventer 16, the wellhead 18, and/or the riser 12.
  • adjustment of the position of the offshore vessel 10 to reduce and/or eliminate the static angle 24 of the bottom flex joint 30 may also increase the angle 32 of top flex joint 34 beneath drill floor 36 with respect to the vertical axis 26. This may cause the portion of the riser 12 beneath the drill floor as it passes through the moonpool 38 to interfere with the hull 40 of the offshore vessel 10. This interference between the riser 12 and the hull 40 is to be avoided.
  • FIG. 3 illustrates a system to mitigate the deflection of the riser 12.
  • measurements may be made relating to the angle 24 of the riser 12 with respect to the BOP 16 and the angle 32 of the riser 12 with respect to a rig on the offshore vessel 10.
  • Deflection of the riser 12 should be reduced to maintain these angles 24, 32 in a predetermined range, for example, within approximately 10° of the vertical axis 26 for angle 24 and/or within approximately 15° of the vertical axis 26 for angle 32.
  • a tension system may be employed.
  • one or more tethers 42 may be coupled to a specialized riser segment 22, for example, to a riser restraint device 44 of the riser segment.
  • This riser restraint device 44 may be a ring, cylinder, or similar device that may circumscribe a particular riser segment 22.
  • the riser restraint device 44 may be permanently affixed (e.g., welded to) the riser segment 22 or the riser restraint device 44 may be detachable from the riser segment 22 via one or more fasteners (bolts, or the like). In some embodiments, the riser segment 22 and/or the riser restraint device 44 coupled thereto may be positioned at a predetermined depth below the bottom of the hull 40.
  • one or more tethers 42 may be coupled to the riser restraint device 44.
  • Each tether 42 may be composed of metal or of another minimally deformable material to control the horizontal position of the riser restraint device 44 about point 46 when coupled to ratcheting system 48.
  • each tether 42 may be composed of, for example, steel rope, nylon rope or a similar material and may operate similarly to control the horizontal position of the riser restraint device 44 when coupled to the ratcheting system 48.
  • the ratcheting system 48 may operate to control the horizontal position of the riser restraint device 44 about point 46 and, thus, the bottom angle 24, top angle 32 and moonpool 38 interface to meet respective operational requirements.
  • each tether 42 may be adjustable in length.
  • the ratcheting system 48 may include an extension and retraction mechanism 50 that may operate to extend or retract each tether 42 in response to external forces, such as currents 20 and/or in response to control commands.
  • This extension and retraction mechanism 50 may be, for example, a constant tension winch, a hydraulic device similar to a riser tensioner, or another type of winch. The use extension and retraction mechanism 50 may allow for specified tension to be applied to the tethers 42.
  • the one or more tethers 42 may be coupled to a single ratcheting system 48 or each tether 42 may be coupled to respective single ratcheting system 48.
  • the tethers 42 may pass through one or more fairleads 52 that operate to guide the tethers 42 while reducing and/or restricting lateral movement of the tethers 42.
  • the one or more fairleads 52 may include a mechanical device, such as a ring, a hook, or the like or the one or more fairleads 52 may be an aperture in the hull 40 of the offshore vessel 10.
  • the ratcheting system 48 may operate in response to measured changes in the environment, including weather changes, and may readjust tension of the one or more tethers 42 in response to the measured changes. Furthermore, during conditions (e.g., adverse weather conditions) that may require removal of the riser 12, the ratcheting system 48 may generally release the tension in the tethers 42 to provide slack for disconnection of the tethers 42 either in the sea 28 (e.g., via a remotely operated vehicle, via acoustic or other wireless signals, via a hardwired connection, or the like) or as the riser segment 22 is being broken out on the offshore vessel 10.
  • conditions e.g., adverse weather conditions
  • the ratcheting system 48 may generally release the tension in the tethers 42 to provide slack for disconnection of the tethers 42 either in the sea 28 (e.g., via a remotely operated vehicle, via acoustic or other wireless signals, via a hardwired connection, or the like) or as the riser
  • FIG. 4 illustrates a side view 54 and a top view 56 of the riser segment 22 having the riser restraint device 44.
  • the riser segment 22 of FIG. 4 may be a particular riser joint that is physically distinct from the remaining riser segments 22 of FIGS. 2 and 3.
  • the riser segment 22 may be shaped in a manner that reduces and/or eliminates possible stress
  • the middle portion 53 of the riser segment 22 may be thicker in circumference or otherwise reinforced relative to the portions of the riser segment 22 not adjacent to the riser restraint device 44 (e.g., the upper portion 58 and the lower portion 60 of the riser segment 22).
  • the riser segment 22 may have a tapered main body along upper portion 58 and lower portion 60 versus middle portion 53 (e.g., the riser segment 22 may be tapered in regions not adjacent to the riser restraint device 44) in contrast to other portions of the riser 12, which may have non-tapered vertical lengths.
  • the riser restraint device 44 may include an upper stopper 62 and a lower stopper 64 (e.g., flanges), which may operate to prevent the one or more tethers 42 from sliding vertically along riser segment 22 beyond each of the upper stopper 62 and the lower stopper 64.
  • the riser restraint device 44 may also include one or more steel or other metallic bars 59 that operate to protect auxiliary lines 61 by preventing contact between the auxiliary line 61 and the one or more tethers 42.
  • the riser restraint device 44 may also be a load ring that allows for free rotation in a circumferential direction about the riser segment 22 when the one or more tethers 42 are attached thereto.
  • a cable 66 may be disposed about the riser restraint device 44, whereby the cable 66 includes two loops 68 that may be connected to the tethers 42.
  • the cable 66 of FIG. 5 may operate as a load ring, as it is able to rotate freely around the riser restraint device 44 and, thus, the riser segment 22.
  • offshore vessels 10 in currents 20 typically are positioned directly into currents 20 in order to stay in position, but the offshore vessel 10 may, on occasion, be positioned at certain angle with respect to currents 20.
  • the ratcheting system 48 can compensate with the angle of the offshore vessel 10 by adjusting the pulling force of each respective tether 42.
  • multiple locations of the ratcheting system 48 can be utilized. For example, one or more single ratcheting systems 48 may be at the bow, stern, port, or starboard portion of the offshore vessel 10.
  • two ratcheting systems 48 each tethered to the riser restraint device 44 may be positioned at the bow, stern, port, or starboard portion of the offshore vessel 10.
  • One ratcheting system 48 may be at the bow portion while another ratcheting system 48 is at the stern portion of the offshore vessel 10 or one ratcheting system 48 may be at the port portion while another ratcheting system 48 is at the starboard portion of the offshore vessel 10 (where each of the two disposed ratcheting systems 48 controls one or two tethers 42).
  • four or more ratcheting systems 48 may be disposed about the offshore vessel 10 and may be used in conjunction or separate from one another based upon the currents 20 encountered.
  • the dimensions of the tapered riser joint 22 may be determined and generated based its specific application. Likewise, the location of riser joint 22, the tension, and/or the length of the tether 42 may be determined based on the specific application in which the offshore vessel 10 is to be deployed. The disclosed embodiments operate to mitigate riser deflection due to, for example, static current, which may, therefore, allow for the removal of or discontinued use of a dynamic control system for the offshore vessel 10. Additionally, manual adjustment of tension and/or length of tether 42 may be required in response of current 20 speed change, which may be monitored via a monitoring system of bottom angle 22 and top angle 24 equipped on the offshore vessel 10.
  • the proposed system for riser 12 deflection mitigation can be easily disarmed by slacking the tether 42.
  • the tether 42 in response emergency disconnection of the riser system, can be locked (fixed in length) or slacked, whichever is benefit to the riser 12 system.
  • Each of these operations, as well as the tensioning and/or adjustment of the length of the tether 42 provided can be controlled via a control panel or remote control system of device 50 and can operate so as to not influence a procedure of emergency disconnection of riser 12.

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Mechanical Engineering (AREA)
  • Earth Drilling (AREA)

Abstract

Techniques and systems to reduce deflection of a riser extending from an offshore platform. A system may include a riser restraint device configured to be coupled to riser of an offshore platform. The system may also include a tether configured to be coupled to the riser restraint device. The system may further include a ratcheting system configured to be coupled to the tether, wherein the riser restraint device is configured to resist movement of the riser via selective retraction and extension of the tether from the ratcheting system.

Description

RISER DEFLECTION MITIGATION
BACKGROUND
[0001] This section is intended to introduce the reader to various aspects of art that may be related to various aspects of the present disclosure, which are described and/or claimed below. This discussion is believed to be helpful in providing the reader with background information to facilitate a better understanding of the various aspects of the present disclosure. Accordingly, it should be understood that these statements are to be read in this light, and not as admissions of prior art.
[0002] Advances in the petroleum industry have allowed access to oil and gas drilling locations and reservoirs that were previously inaccessible due to technological limitations. For example, technological advances have allowed drilling of offshore wells at increasing water depths and in increasingly harsh environments, permitting oil and gas resource owners to successfully drill for otherwise inaccessible energy resources. To drill for oil and gas offshore, it is desirable to have stable offshore platforms and/or floating vessels from which to drill and recover the energy resources. Techniques to stabilize the offshore platforms and floating vessels include, for example, the use of mooring systems and/or dynamic positioning systems.
However, these systems may not always adequately stabilize components descending from the offshore platforms and floating vessels to the seafloor wellhead.
[0003] For example, a riser string or riser (e.g., a pipe or series of pipes that connects the offshore platforms or floating vessels to the floor of the sea) may be used to transport drill pipe, casing, drilling mud, production materials or hydrocarbons between the offshore platform or floating vessel and a wellhead. The riser is suspended between the offshore platform or floating vessel and the wellhead, and may experience forces, such as underwater currents, that cause deflection (e.g., bending or movement) in the riser. Acceptable deflection can be measured by the deflection along the riser, and also at, for example, select points along the riser. These points may be located, for example, at the offshore platform or floating vessel and at the wellhead. If the deflection resulting from underwater current is too great, drilling must cease and the drilling location or reservoir may not be accessible due to such technological constraints.
BRIEF DESCRIPTION OF DRAWINGS
[0004] FIG. 1 illustrates an example of an offshore platform having a riser.
[0005] FIG. 2 illustrates an example of the offshore platform of FIG. 1 having a riser experiencing deflection.
[0006] FIG. 3 illustrates a first embodiment of a system to mitigate the deflection of the riser of FIG. 2.
[0007] FIG. 4 illustrates a top and a side view of a riser restraint device of FIG. 3.
[0008] FIG. 5 illustrates a second top view of the riser restraint device 44 of FIG. 3.
DETAILED DESCRIPTION
[0009] One or more specific embodiments will be described below. In an effort to provide a concise description of these embodiments, all features of an actual implementation may not be described in the specification. It should be appreciated that in the development of any such actual implementation, as in any engineering or design project, numerous
implementation-specific decisions must be made to achieve the developers' specific goals, such as compliance with system-related and business-related constraints, which may vary from one implementation to another. Moreover, it should be appreciated that such a development effort might be complex and time consuming, but would nevertheless be a routine undertaking of design, fabrication, and manufacture for those of ordinary skill having the benefit of this disclosure.
[0010] When introducing elements of various embodiments, the articles "a," "an," "the," and "said" are intended to mean that there are one or more of the elements. The terms "comprising," "including," and "having" are intended to be inclusive and mean that there may be additional elements other than the listed elements.
[0011] Systems and techniques for stabilizing a riser (e.g., a riser string) extending from offshore platform, such as a drillship, a semi-submersible platform, a floating production system, or the like, are set forth below. In one embodiment, a line is anchored to the riser via an anchor point. The line may also be tethered to one or more winches on the offshore platform and through controlled deployment and retraction of the line via the one or more winches, the deflection of the riser may be adjusted. In this manner, through control of the amount of length of the line disposed between the anchor point and the one or more winches, deflections of the riser may be reduced.
[0012] With the foregoing in mind, FIG. 1 illustrates an offshore platform comprising a offshore vessel 10. Although the presently illustrated embodiment of an offshore vessel 10 is a drillship (e.g., a ship equipped with a drill rig and engaged in offshore oil and gas exploration and/or well maintenance or completion work including, but not limited to, casing and tubing installation, subsea tree installations, and well capping), other offshore platforms such as a semi- submersible platform, a floating production system, or the like may be substituted for the drillship. Indeed, while the techniques and systems described below are described in conjunction with a drillship, the techniques and systems are intended to cover at least the additional offshore platforms described above.
[0013] As illustrated in FIG. 1, the offshore vessel 10 includes, having a derrick 11 thereon, includes a riser 12 extending therefrom. The riser 12 may include a pipe or a series of pipes (e.g., riser segments) that connect the offshore vessel 10 to the seafloor 14 via, for example, blow out preventer (BOP) 16 that is coupled to a wellhead 18 on the seafloor 14. In some embodiments, the riser 12 may transport produced hydrocarbons and/or production materials between the offshore vessel 10 and the wellhead 18, while the BOP 16 may include at least one valve with a sealing element to control wellbore fluid flows. In some embodiments, the riser 12 may pass through an opening (e.g., a moonpool) in the offshore vessel 10 and may be coupled to drilling equipment of the offshore vessel 10. As illustrated in FIG. 1, it may be desirable to have the riser 12 positioned in a vertical orientation between the wellhead 18 and the offshore vessel 10. However, external factors (e.g., environmental factors such as currents) may disturb the vertical orientation of the riser 12.
[0014] As illustrated in FIG. 2, the riser 12 may experience deflection, for example, from currents 20. These currents 20 may apply forces on the riser 12, which causes deflection (e.g., motion, bending, or the like) in riser 12. Thus, when the offshore vessel 10 works under the existence of strong currents 20, the riser 12 will have significant horizontal deflection due to the drag loads applied along the riser 12. As a result, the angle 24 between the vertical axis 26 (e.g., an axis of 90° between the seafloor 14 and the surface of the sea 28) of the riser bottom flex joint 30 may exceed tolerance levels for the performance of, for example, drilling operations.
[0015] This angle 24 may be modified through the dynamic positioning of the offshore vessel 10. That is, through the movement of the offshore vessel 10 in response to the currents 20, the static angle 24 of the bottom flex joint 30 may be reduced and/or eliminated to meet any operational requirements associated with, for example, the blow out preventer 16, the wellhead 18, and/or the riser 12. However, adjustment of the position of the offshore vessel 10 to reduce and/or eliminate the static angle 24 of the bottom flex joint 30 may also increase the the angle 32 of top flex joint 34 beneath drill floor 36 with respect to the vertical axis 26. This may cause the portion of the riser 12 beneath the drill floor as it passes through the moonpool 38 to interfere with the hull 40 of the offshore vessel 10. This interference between the riser 12 and the hull 40 is to be avoided.
[0016] Thus, force applied to the riser 12 from the currents 20 (or other environmental forces) other may cause the riser 12 to stress the BOP 16 or cause key seating, as the angle 24 that the riser 12 contacts the BOP 16 may be affected via the deflection of the riser 12. Likewise, the currents 20 and/or efforts to mitigate the force of the currents 20 (e.g., dynamic positioning of the offshore vessel) may cause the riser 12 to contact the edge of the moonpool 38 of the offshore vessel 10. To reduce the deflection of the riser 12, and to reduce the chances of occurrence of the aforementioned problems caused by riser 12 deflection, additional systems and techniques may be employed.
[0017] FIG. 3 illustrates a system to mitigate the deflection of the riser 12. In some embodiments, measurements may be made relating to the angle 24 of the riser 12 with respect to the BOP 16 and the angle 32 of the riser 12 with respect to a rig on the offshore vessel 10.
Deflection of the riser 12 should be reduced to maintain these angles 24, 32 in a predetermined range, for example, within approximately 10° of the vertical axis 26 for angle 24 and/or within approximately 15° of the vertical axis 26 for angle 32. To help reduce the deflection, and to maintain the aforementioned angles 24, 32 in a predetermined range, a tension system may be employed. For example, one or more tethers 42 may be coupled to a specialized riser segment 22, for example, to a riser restraint device 44 of the riser segment. This riser restraint device 44 may be a ring, cylinder, or similar device that may circumscribe a particular riser segment 22. The riser restraint device 44 may be permanently affixed (e.g., welded to) the riser segment 22 or the riser restraint device 44 may be detachable from the riser segment 22 via one or more fasteners (bolts, or the like). In some embodiments, the riser segment 22 and/or the riser restraint device 44 coupled thereto may be positioned at a predetermined depth below the bottom of the hull 40.
[0018] As previously noted, one or more tethers 42 may be coupled to the riser restraint device 44. Each tether 42 may be composed of metal or of another minimally deformable material to control the horizontal position of the riser restraint device 44 about point 46 when coupled to ratcheting system 48. Likewise, each tether 42 may be composed of, for example, steel rope, nylon rope or a similar material and may operate similarly to control the horizontal position of the riser restraint device 44 when coupled to the ratcheting system 48. In some embodiments, the ratcheting system 48 may operate to control the horizontal position of the riser restraint device 44 about point 46 and, thus, the bottom angle 24, top angle 32 and moonpool 38 interface to meet respective operational requirements.
[0019] In this manner, the riser restraint device 44 may serve as a resistance point for the riser segment 22 and, thus, the riser 12, thereby limiting downstream deflections (e.g., limiting the deflection of the riser 12 to the predetermined amount of movement of the riser restraint device 44). In some embodiments, each tether 42 may be adjustable in length. For example, the ratcheting system 48 may include an extension and retraction mechanism 50 that may operate to extend or retract each tether 42 in response to external forces, such as currents 20 and/or in response to control commands. This extension and retraction mechanism 50 may be, for example, a constant tension winch, a hydraulic device similar to a riser tensioner, or another type of winch. The use extension and retraction mechanism 50 may allow for specified tension to be applied to the tethers 42.
[0020] The one or more tethers 42 may be coupled to a single ratcheting system 48 or each tether 42 may be coupled to respective single ratcheting system 48. The tethers 42 may pass through one or more fairleads 52 that operate to guide the tethers 42 while reducing and/or restricting lateral movement of the tethers 42. The one or more fairleads 52 may include a mechanical device, such as a ring, a hook, or the like or the one or more fairleads 52 may be an aperture in the hull 40 of the offshore vessel 10. In some embodiments, the ratcheting system 48 may operate in response to measured changes in the environment, including weather changes, and may readjust tension of the one or more tethers 42 in response to the measured changes. Furthermore, during conditions (e.g., adverse weather conditions) that may require removal of the riser 12, the ratcheting system 48 may generally release the tension in the tethers 42 to provide slack for disconnection of the tethers 42 either in the sea 28 (e.g., via a remotely operated vehicle, via acoustic or other wireless signals, via a hardwired connection, or the like) or as the riser segment 22 is being broken out on the offshore vessel 10.
[0021] FIG. 4 illustrates a side view 54 and a top view 56 of the riser segment 22 having the riser restraint device 44. The riser segment 22 of FIG. 4 may be a particular riser joint that is physically distinct from the remaining riser segments 22 of FIGS. 2 and 3. For example, the riser segment 22 may be shaped in a manner that reduces and/or eliminates possible stress
concentrations due to pulling loads. For example, the middle portion 53 of the riser segment 22 (e.g., the portion adjacent the riser restraint device 44) may be thicker in circumference or otherwise reinforced relative to the portions of the riser segment 22 not adjacent to the riser restraint device 44 (e.g., the upper portion 58 and the lower portion 60 of the riser segment 22). In this manner, the riser segment 22 may have a tapered main body along upper portion 58 and lower portion 60 versus middle portion 53 (e.g., the riser segment 22 may be tapered in regions not adjacent to the riser restraint device 44) in contrast to other portions of the riser 12, which may have non-tapered vertical lengths. Additionally, the upper portion 58 of the riser segment 22 may include a connector 55, such as a box connector, while the lower portion 60 of the riser segment 22 may include a connector 57, such as a pin connector. [0022] As illustrated, the riser restraint device 44 may include an upper stopper 62 and a lower stopper 64 (e.g., flanges), which may operate to prevent the one or more tethers 42 from sliding vertically along riser segment 22 beyond each of the upper stopper 62 and the lower stopper 64. The riser restraint device 44 may also include one or more steel or other metallic bars 59 that operate to protect auxiliary lines 61 by preventing contact between the auxiliary line 61 and the one or more tethers 42. The riser restraint device 44 may also be a load ring that allows for free rotation in a circumferential direction about the riser segment 22 when the one or more tethers 42 are attached thereto. Alternatively, as illustrated in FIG. 5, a cable 66 may be disposed about the riser restraint device 44, whereby the cable 66 includes two loops 68 that may be connected to the tethers 42. The cable 66 of FIG. 5 may operate as a load ring, as it is able to rotate freely around the riser restraint device 44 and, thus, the riser segment 22.
[0023] Additionally, offshore vessels 10 in currents 20 typically are positioned directly into currents 20 in order to stay in position, but the offshore vessel 10 may, on occasion, be positioned at certain angle with respect to currents 20. Through the use of separate tethers 42, the ratcheting system 48 can compensate with the angle of the offshore vessel 10 by adjusting the pulling force of each respective tether 42. Moreover, it is envisioned that multiple locations of the ratcheting system 48 can be utilized. For example, one or more single ratcheting systems 48 may be at the bow, stern, port, or starboard portion of the offshore vessel 10. Likewise, two ratcheting systems 48, each tethered to the riser restraint device 44 may be positioned at the bow, stern, port, or starboard portion of the offshore vessel 10. One ratcheting system 48 may be at the bow portion while another ratcheting system 48 is at the stern portion of the offshore vessel 10 or one ratcheting system 48 may be at the port portion while another ratcheting system 48 is at the starboard portion of the offshore vessel 10 (where each of the two disposed ratcheting systems 48 controls one or two tethers 42). Similarly, four or more ratcheting systems 48 may be disposed about the offshore vessel 10 and may be used in conjunction or separate from one another based upon the currents 20 encountered.
[0024] The dimensions of the tapered riser joint 22 may be determined and generated based its specific application. Likewise, the location of riser joint 22, the tension, and/or the length of the tether 42 may be determined based on the specific application in which the offshore vessel 10 is to be deployed. The disclosed embodiments operate to mitigate riser deflection due to, for example, static current, which may, therefore, allow for the removal of or discontinued use of a dynamic control system for the offshore vessel 10. Additionally, manual adjustment of tension and/or length of tether 42 may be required in response of current 20 speed change, which may be monitored via a monitoring system of bottom angle 22 and top angle 24 equipped on the offshore vessel 10. Furthermore, as previously discussed, the proposed system for riser 12 deflection mitigation can be easily disarmed by slacking the tether 42. For example, in response emergency disconnection of the riser system, the tether 42 can be locked (fixed in length) or slacked, whichever is benefit to the riser 12 system. Each of these operations, as well as the tensioning and/or adjustment of the length of the tether 42 provided can be controlled via a control panel or remote control system of device 50 and can operate so as to not influence a procedure of emergency disconnection of riser 12.
[0025] This written description uses examples to disclose the above description, including the best mode, and also to enable any person skilled in the art to practice the disclosure, including making and using any devices or systems and performing any incorporated methods. The patentable scope of the disclosure is defined by the claims, and may include other examples that occur to those skilled in the art. Such other examples are intended to be within the scope of the claims if they have structural elements that do not differ from the literal language of the claims, or if they include equivalent structural elements with insubstantial differences from the literal languages of the claims. Accordingly, while the above disclosed embodiments may be susceptible to various modifications and alternative forms, specific embodiments have been shown by way of example in the drawings and have been described in detail herein. However, it should be understood that the embodiments are not intended to be limited to the particular forms disclosed. Rather, the disclosed embodiment are to cover all modifications, equivalents, and alternatives falling within the spirit and scope of the embodiments as defined by the following appended claims.

Claims

1. A system, comprising:
a riser restraint device configured to be coupled to riser of an offshore platform;
a tether configured to be coupled to the riser restraint device; and
a ratcheting system configured to be coupled to the tether, wherein the riser restraint device is configured to resist movement of the riser via selective retraction and extension of the tether by the ratcheting system.
2. The system of claim 1, comprising a riser segment as a portion of the riser, wherein the riser segment comprises the riser restraint device.
3. The system of claim 1, wherein the riser restraint device comprises an upper stopper configured to prevent the tether from sliding vertically beyond the upper stopper and a lower stopper configured to prevent the tether from sliding vertically beyond the lower stopper.
4. The system of claim 3, wherein the tether is configured to be coupled to the riser restraint device between the upper stopper and the lower stopper.
5. The system of claim 3, comprising a cable disposed between the upper stopper and the lower stopper.
6. The system of claim 5, wherein the cable comprises a loop configured to be coupled to the tether to couple the tether to the riser restraint device.
7. The system of claim 1, wherein the riser restraint device comprises a load ring configured to rotate in a circumferential direction about the riser.
8. The system of claim 1, wherein the ratcheting system is configured to selectively retract and extend the tether based on a measurement of an angle of the riser with respect to a vertical axis.
9. The system of claim 1, wherein the ratcheting system comprises a winch.
10. A method, comprising:
disposing a riser segment onto a riser of an offshore platform, wherein the riser segment comprises a riser restraint device;
coupling one end of a tether to the riser restraint device, wherein the tether is additionally coupled to a ratcheting system; and
positioning the riser segment at a predetermined depth below the offshore platform.
11. The method of claim 10, comprising activating the ratcheting system to retract a portion of the tether into the ratcheting system to generate a predetermined tension between the tether and the riser segment.
12. The method of claim 11, comprising reactivating the ratcheting system to extend the portion of the tether from the ratcheting system to reduce the predetermined tension between the tether and the riser segment.
13. The method of claim 12, comprising activating the ratcheting system or reactivating the ratcheting system in response to a notification of an emergency disconnection of the riser from a wellhead or a blow-out preventer.
14. The method of claim 10, comprising monitoring an angle of the riser with respect to a vertical axis.
15. The method of claim 14, comprising activating the ratcheting system to retract a portion of the tether into the ratcheting system to maintain a predetermined tension between the tether and the riser segment based on the monitored angle.
16. The method of claim 14, comprising activating the ratcheting system to extend a portion of the tether from the ratcheting system to maintain a predetermined tension between the tether and the riser segment based on the monitored angle.
17. A riser segment of a riser of an offshore platform, comprising:
an upper portion;
a lower portion;
a middle portion disposed between the upper portion and the lower portion, wherein the middle portion is thicker in circumference than both of the upper portion and the lower portion; and
a riser restraint device configured to receive a tether, wherein the riser restraint device is configured to operate in conjunction with the tether to resist movement of the riser segment in response to a current.
18. The riser segment of claim 17, wherein the riser restraint device is disposed in the middle portion.
19. The riser segment of claim 17, comprising a connector configured to couple the riser segment to a second riser segment having non-tapered vertical length.
20. The riser segment of claim 17, wherein the riser restraint device comprises a bar disposed between the tether and an auxiliary line disposed vertically along the riser segment, wherein the bar is configured to prevent contact between the auxiliary line and the tether.
PCT/US2017/041882 2016-07-13 2017-07-13 Riser deflection mitigation WO2018013777A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
EP17828444.4A EP3485131A4 (en) 2016-07-13 2017-07-13 Riser deflection mitigation

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
US15/209,146 US9739101B1 (en) 2016-07-13 2016-07-13 Riser deflection mitigation
US15/209,146 2016-07-13

Publications (1)

Publication Number Publication Date
WO2018013777A1 true WO2018013777A1 (en) 2018-01-18

Family

ID=59581252

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/US2017/041882 WO2018013777A1 (en) 2016-07-13 2017-07-13 Riser deflection mitigation

Country Status (3)

Country Link
US (1) US9739101B1 (en)
EP (1) EP3485131A4 (en)
WO (1) WO2018013777A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110588877A (en) * 2019-09-30 2019-12-20 广州黄船海洋工程有限公司 Diving moon pool installation process

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US10294729B2 (en) * 2017-10-17 2019-05-21 Ensco International Incorporated Riser and subsea equipment guidance

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4576516A (en) * 1984-11-28 1986-03-18 Shell Oil Company Riser angle control apparatus and method
US20030230409A1 (en) * 2002-06-13 2003-12-18 Jean Guesnon Instrumentation assembly for an offshore riser
US20130092387A1 (en) * 2008-02-11 2013-04-18 Vetco Gray Inc. Riser Lifecycle Management System, Computer Readable Medium and Program Code
US20130139415A1 (en) * 2010-08-13 2013-06-06 Deep Reach Technology Inc. Subsea Excavation Systems and Methods
US20130319680A1 (en) * 2012-05-31 2013-12-05 Transocean Sedco Forex Ventures Limited Drilling Riser Retrieval in High Current

Family Cites Families (29)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3010214A (en) * 1958-12-24 1961-11-28 California Research Corp Ship positioning means and method
US3142343A (en) * 1960-12-14 1964-07-28 Shell Oil Co Method and apparatus for drilling underwater wells
US3265130A (en) * 1962-05-23 1966-08-09 Shell Oil Co Method and apparatus for drilling underwater wells
US3983706A (en) * 1975-07-10 1976-10-05 Texaco Inc. Marine structure with hydraulic tensioner
US4244663A (en) * 1978-12-26 1981-01-13 Marathon Manufacturing Company Apparatus for restricting pipe motion
US4436451A (en) * 1980-02-20 1984-03-13 Anderson Harold E Self-standing marine riser
US4317174A (en) * 1980-02-28 1982-02-23 The Offshore Company Riser angle positioning system and process
US4708525A (en) * 1982-02-25 1987-11-24 Amoco Corporation Multiterminators for riser pipes
US4473323A (en) * 1983-04-14 1984-09-25 Exxon Production Research Co. Buoyant arm for maintaining tension on a drilling riser
GB2170240B (en) * 1985-01-25 1988-01-27 Shell Int Research Riser tensioning system
US4616707A (en) * 1985-04-08 1986-10-14 Shell Oil Company Riser braking clamp apparatus
US4617998A (en) * 1985-04-08 1986-10-21 Shell Oil Company Drilling riser braking apparatus and method
US5479990A (en) * 1992-09-28 1996-01-02 Shell Oil Company Rising centralizing spider
US5447392A (en) * 1993-05-03 1995-09-05 Shell Oil Company Backspan stress joint
US5950737A (en) * 1997-07-08 1999-09-14 Abb Vetco Gray Inc. Drilling riser centralizer
US5978739A (en) * 1997-10-14 1999-11-02 Stockton; Thomas R. Disconnect information and monitoring system for dynamically positioned offshore drilling rigs
GB2334048B (en) * 1998-02-06 1999-12-29 Philip Head Riser system for sub sea wells and method of operation
FR2782342B1 (en) * 1998-08-11 2000-11-10 Technip Geoproduction METHOD OF ESTABLISHING AN OPERATING FACILITY
US7416025B2 (en) * 2005-08-30 2008-08-26 Kellogg Brown & Root Llc Subsea well communications apparatus and method using variable tension large offset risers
US20090056936A1 (en) * 2007-07-17 2009-03-05 Mccoy Jr Richard W Subsea Structure Load Monitoring and Control System
US20090212092A1 (en) * 2008-02-21 2009-08-27 Israel Stol Method for forming friction welded compression based tubular structures
US8439109B2 (en) * 2008-05-23 2013-05-14 Schlumberger Technology Corporation System and method for depth measurement and correction during subsea intervention operations
WO2011150363A1 (en) * 2010-05-28 2011-12-01 Weatherford/Lamb, Inc. Deepwater completion installation and intervention system
US20140374117A1 (en) * 2012-05-17 2014-12-25 Geir Aune Methods and Means for Installing, Maintaining and Controlling a Self-Standing Riser System
BR112016002576A2 (en) * 2013-08-13 2017-08-01 Propocean As stabilization of a rising column tube
WO2015168432A1 (en) * 2014-04-30 2015-11-05 Seahorse Equipment Corp Bundled, articulated riser system for fpso vessel
FR3030667B1 (en) * 2014-12-18 2016-12-23 Dietswell CLAMPING DEVICE FOR AN OMBILICAL CONDUIT USEABLE DURING DEEP WATER DRILLING.
WO2016137718A1 (en) * 2015-02-26 2016-09-01 Exxonmobil Upstream Research Company Drilling riser with distributed buoyancy
WO2016164573A1 (en) * 2015-04-07 2016-10-13 Ensco International Incorporated Riser deflection mitigation

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4576516A (en) * 1984-11-28 1986-03-18 Shell Oil Company Riser angle control apparatus and method
US20030230409A1 (en) * 2002-06-13 2003-12-18 Jean Guesnon Instrumentation assembly for an offshore riser
US20130092387A1 (en) * 2008-02-11 2013-04-18 Vetco Gray Inc. Riser Lifecycle Management System, Computer Readable Medium and Program Code
US20130139415A1 (en) * 2010-08-13 2013-06-06 Deep Reach Technology Inc. Subsea Excavation Systems and Methods
US20130319680A1 (en) * 2012-05-31 2013-12-05 Transocean Sedco Forex Ventures Limited Drilling Riser Retrieval in High Current

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
See also references of EP3485131A4 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110588877A (en) * 2019-09-30 2019-12-20 广州黄船海洋工程有限公司 Diving moon pool installation process
CN110588877B (en) * 2019-09-30 2021-04-27 广州黄船海洋工程有限公司 Diving moon pool installation process

Also Published As

Publication number Publication date
EP3485131A4 (en) 2020-02-26
EP3485131A1 (en) 2019-05-22
US9739101B1 (en) 2017-08-22

Similar Documents

Publication Publication Date Title
US10072467B2 (en) Method and apparatus for elevating the tapered stress joint or flex joint of an SCR above the water
US5439321A (en) Interruptive mobile production system
US7628206B2 (en) Dry tree subsea well communications apparatus using variable tension large offset risers
CN105283380B (en) Riser tensioners conductor for dry tree semi-submersible
US20100326667A1 (en) Production of hydrocarbons
US10513888B2 (en) Weathervaning riser joint
US4386659A (en) Guides for forming connections
US20100047024A1 (en) Riser tensioner restraint device
US10151151B2 (en) Riser deflection mitigation
RU2672362C2 (en) Mounting and dismounting of flexible line
US20170191334A1 (en) Systems and methods for engaging subsea equipment
US4354446A (en) Temporary mooring of tension leg platforms
US9739101B1 (en) Riser deflection mitigation
US8430171B2 (en) Method and arrangement for sealing a subsea oil wellhead
US10294729B2 (en) Riser and subsea equipment guidance
US9903509B2 (en) Riser deflection mitigation
EP0045653B1 (en) Mooring of floating structures
US11028663B1 (en) Process and apparatus for installing a payload onto a subsea structure
US9759350B2 (en) Riser deflection mitigation
Huber et al. The ‘British Argyll’DSV Wirelining System
WO2008070245A2 (en) Subsea actuation systems and methods
WO2022191714A1 (en) Linear rope tensioner
Bensimon et al. Deepwater Installation of a Large Capacity FPSO with Large Number of Risers in the Marlim Field
WO1999014462A1 (en) Riser installation method and riser system

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 17828444

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

ENP Entry into the national phase

Ref document number: 2017828444