WO2012112759A2 - Method and system for collecting and analyzing operational information from a network of components associated with a liquid energy commodity - Google Patents
Method and system for collecting and analyzing operational information from a network of components associated with a liquid energy commodity Download PDFInfo
- Publication number
- WO2012112759A2 WO2012112759A2 PCT/US2012/025418 US2012025418W WO2012112759A2 WO 2012112759 A2 WO2012112759 A2 WO 2012112759A2 US 2012025418 W US2012025418 W US 2012025418W WO 2012112759 A2 WO2012112759 A2 WO 2012112759A2
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- database
- network
- crude oil
- processing facility
- liquid energy
- Prior art date
Links
- 239000007788 liquid Substances 0.000 title claims abstract description 69
- 238000000034 method Methods 0.000 title claims abstract description 66
- 238000003860 storage Methods 0.000 claims abstract description 93
- 238000012545 processing Methods 0.000 claims abstract description 80
- 238000005259 measurement Methods 0.000 claims abstract description 45
- 239000010779 crude oil Substances 0.000 claims description 121
- 238000005086 pumping Methods 0.000 claims description 73
- 238000004458 analytical method Methods 0.000 claims description 25
- 238000012806 monitoring device Methods 0.000 claims description 24
- 238000001931 thermography Methods 0.000 claims description 22
- 230000004907 flux Effects 0.000 claims description 14
- 238000012544 monitoring process Methods 0.000 claims description 12
- 238000004519 manufacturing process Methods 0.000 claims description 8
- 238000004891 communication Methods 0.000 claims description 5
- 230000002596 correlated effect Effects 0.000 claims description 5
- 238000007689 inspection Methods 0.000 claims description 3
- VNWKTOKETHGBQD-UHFFFAOYSA-N methane Chemical compound C VNWKTOKETHGBQD-UHFFFAOYSA-N 0.000 description 20
- 239000003921 oil Substances 0.000 description 20
- 239000000306 component Substances 0.000 description 13
- 238000007667 floating Methods 0.000 description 13
- 239000003345 natural gas Substances 0.000 description 10
- 238000003708 edge detection Methods 0.000 description 9
- 239000000047 product Substances 0.000 description 9
- 230000008859 change Effects 0.000 description 8
- 239000003502 gasoline Substances 0.000 description 7
- ATUOYWHBWRKTHZ-UHFFFAOYSA-N Propane Chemical compound CCC ATUOYWHBWRKTHZ-UHFFFAOYSA-N 0.000 description 6
- 238000010438 heat treatment Methods 0.000 description 6
- 230000000737 periodic effect Effects 0.000 description 6
- 239000003209 petroleum derivative Substances 0.000 description 6
- 238000005194 fractionation Methods 0.000 description 5
- 238000004088 simulation Methods 0.000 description 5
- 239000007789 gas Substances 0.000 description 4
- OTMSDBZUPAUEDD-UHFFFAOYSA-N Ethane Chemical compound CC OTMSDBZUPAUEDD-UHFFFAOYSA-N 0.000 description 3
- 238000000342 Monte Carlo simulation Methods 0.000 description 3
- 230000002159 abnormal effect Effects 0.000 description 3
- 235000013844 butane Nutrition 0.000 description 3
- 230000006870 function Effects 0.000 description 3
- 238000010191 image analysis Methods 0.000 description 3
- 230000006698 induction Effects 0.000 description 3
- IJDNQMDRQITEOD-UHFFFAOYSA-N n-butane Chemical compound CCCC IJDNQMDRQITEOD-UHFFFAOYSA-N 0.000 description 3
- 230000008569 process Effects 0.000 description 3
- 239000001294 propane Substances 0.000 description 3
- VGGSQFUCUMXWEO-UHFFFAOYSA-N Ethene Chemical compound C=C VGGSQFUCUMXWEO-UHFFFAOYSA-N 0.000 description 2
- 239000005977 Ethylene Substances 0.000 description 2
- 239000008186 active pharmaceutical agent Substances 0.000 description 2
- 239000001273 butane Substances 0.000 description 2
- 239000006227 byproduct Substances 0.000 description 2
- 238000004364 calculation method Methods 0.000 description 2
- 238000004590 computer program Methods 0.000 description 2
- 238000010276 construction Methods 0.000 description 2
- 238000001816 cooling Methods 0.000 description 2
- 239000008358 core component Substances 0.000 description 2
- 238000005336 cracking Methods 0.000 description 2
- 230000003247 decreasing effect Effects 0.000 description 2
- 238000001514 detection method Methods 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- -1 ethylene, propylene Chemical group 0.000 description 2
- 238000004231 fluid catalytic cracking Methods 0.000 description 2
- OFBQJSOFQDEBGM-UHFFFAOYSA-N n-pentane Natural products CCCCC OFBQJSOFQDEBGM-UHFFFAOYSA-N 0.000 description 2
- 239000003208 petroleum Substances 0.000 description 2
- 238000007670 refining Methods 0.000 description 2
- 239000000126 substance Substances 0.000 description 2
- 238000012546 transfer Methods 0.000 description 2
- 238000009827 uniform distribution Methods 0.000 description 2
- 238000001429 visible spectrum Methods 0.000 description 2
- 230000000007 visual effect Effects 0.000 description 2
- 238000011179 visual inspection Methods 0.000 description 2
- 241000196324 Embryophyta Species 0.000 description 1
- 238000013459 approach Methods 0.000 description 1
- 230000008901 benefit Effects 0.000 description 1
- 230000005540 biological transmission Effects 0.000 description 1
- 230000003139 buffering effect Effects 0.000 description 1
- 230000000875 corresponding effect Effects 0.000 description 1
- 230000007123 defense Effects 0.000 description 1
- 230000003111 delayed effect Effects 0.000 description 1
- 230000001419 dependent effect Effects 0.000 description 1
- 238000004141 dimensional analysis Methods 0.000 description 1
- 238000009826 distribution Methods 0.000 description 1
- 239000000428 dust Substances 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 239000002803 fossil fuel Substances 0.000 description 1
- 239000000446 fuel Substances 0.000 description 1
- 230000005484 gravity Effects 0.000 description 1
- 238000003384 imaging method Methods 0.000 description 1
- 230000008676 import Effects 0.000 description 1
- 230000007257 malfunction Effects 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000005065 mining Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000000053 physical method Methods 0.000 description 1
- 238000010248 power generation Methods 0.000 description 1
- 239000012716 precipitator Substances 0.000 description 1
- 230000009467 reduction Effects 0.000 description 1
- 150000003839 salts Chemical class 0.000 description 1
- 210000003813 thumb Anatomy 0.000 description 1
- 230000009466 transformation Effects 0.000 description 1
- 238000000844 transformation Methods 0.000 description 1
- 230000003442 weekly effect Effects 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F17—STORING OR DISTRIBUTING GASES OR LIQUIDS
- F17D—PIPE-LINE SYSTEMS; PIPE-LINES
- F17D1/00—Pipe-line systems
- F17D1/08—Pipe-line systems for liquids or viscous products
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F17—STORING OR DISTRIBUTING GASES OR LIQUIDS
- F17D—PIPE-LINE SYSTEMS; PIPE-LINES
- F17D3/00—Arrangements for supervising or controlling working operations
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F17—STORING OR DISTRIBUTING GASES OR LIQUIDS
- F17D—PIPE-LINE SYSTEMS; PIPE-LINES
- F17D3/00—Arrangements for supervising or controlling working operations
- F17D3/01—Arrangements for supervising or controlling working operations for controlling, signalling, or supervising the conveyance of a product
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F17—STORING OR DISTRIBUTING GASES OR LIQUIDS
- F17D—PIPE-LINE SYSTEMS; PIPE-LINES
- F17D3/00—Arrangements for supervising or controlling working operations
- F17D3/18—Arrangements for supervising or controlling working operations for measuring the quantity of conveyed product
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01F—MEASURING VOLUME, VOLUME FLOW, MASS FLOW OR LIQUID LEVEL; METERING BY VOLUME
- G01F23/00—Indicating or measuring liquid level or level of fluent solid material, e.g. indicating in terms of volume or indicating by means of an alarm
- G01F23/22—Indicating or measuring liquid level or level of fluent solid material, e.g. indicating in terms of volume or indicating by means of an alarm by measuring physical variables, other than linear dimensions, pressure or weight, dependent on the level to be measured, e.g. by difference of heat transfer of steam or water
- G01F23/28—Indicating or measuring liquid level or level of fluent solid material, e.g. indicating in terms of volume or indicating by means of an alarm by measuring physical variables, other than linear dimensions, pressure or weight, dependent on the level to be measured, e.g. by difference of heat transfer of steam or water by measuring the variations of parameters of electromagnetic or acoustic waves applied directly to the liquid or fluent solid material
- G01F23/284—Electromagnetic waves
- G01F23/292—Light, e.g. infrared or ultraviolet
- G01F23/2921—Light, e.g. infrared or ultraviolet for discrete levels
- G01F23/2922—Light, e.g. infrared or ultraviolet for discrete levels with light-conducting sensing elements, e.g. prisms
- G01F23/2925—Light, e.g. infrared or ultraviolet for discrete levels with light-conducting sensing elements, e.g. prisms using electrical detecting means
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01F—MEASURING VOLUME, VOLUME FLOW, MASS FLOW OR LIQUID LEVEL; METERING BY VOLUME
- G01F1/00—Measuring the volume flow or mass flow of fluid or fluent solid material wherein the fluid passes through a meter in a continuous flow
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01F—MEASURING VOLUME, VOLUME FLOW, MASS FLOW OR LIQUID LEVEL; METERING BY VOLUME
- G01F15/00—Details of, or accessories for, apparatus of groups G01F1/00 - G01F13/00 insofar as such details or appliances are not adapted to particular types of such apparatus
- G01F15/06—Indicating or recording devices
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01F—MEASURING VOLUME, VOLUME FLOW, MASS FLOW OR LIQUID LEVEL; METERING BY VOLUME
- G01F23/00—Indicating or measuring liquid level or level of fluent solid material, e.g. indicating in terms of volume or indicating by means of an alarm
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/80—Management or planning
- Y02P90/82—Energy audits or management systems therefor
Definitions
- the present invention is a method and system for collecting and analyzing operational information from a network of components associated with a liquid energy commodity, such as crude oil or natural gas liquid (NGL).
- a liquid energy commodity such as crude oil or natural gas liquid (NGL).
- Liquid energy commodities such as crude oil
- NNL natural gas liquid
- Liquid energy commodities such as crude oil
- NNL natural gas liquid
- These commodities are bought and sold by many parties, and as with any traded market, information about the traded commodities is very valuable to market participants.
- the operations of the various components and facilities of the production, transportation, storage, and distribution systems for each of these commodities can have significant impacts on the price and availability of these commodities, making information about said operations valuable.
- such information generally is not disclosed publicly by the various component owners or operators, and access to said information is therefore limited.
- EIA Information Administration
- the present invention is a method and system for collecting and analyzing operational information from a network of components associated with a liquid energy commodity, such as crude oil or natural gas liquid ( GL).
- a liquid energy commodity such as crude oil or natural gas liquid ( GL).
- sensors or measurement devices are deployed at various points in a network to collect data.
- the method then generally comprises the steps of: (a) measuring an amount of the liquid energy commodity in storage at one or more storage facilities in the network, and storing that measurement data in a first database at a central data processing facility; (b) determining a flow rate of the liquid energy commodity in one or more selected pipelines in the network, and storing that flow rate data in a second database at the central data processing facility; (c) ascertaining an operational status of one or more processing facilities in the network, and storing that operational status information in a third database at the central data processing facility; (d) analyzing the measurement data, the flow rate data, and the operational status information to determine a balance of the liquid energy commodity in the network or a selected portion thereof at a given time; and (e) communicating information about the balance of the liquid energy commodity to a third -party market participant.
- each selected storage facility in a particular network there is a measurement of the amount of crude oil or other liquid energy commodity in storage.
- most crude oil is stored in large, above-ground tanks that either have: a floating roof, which is known as an External Floating Roof (EFR); or a fixed roof with a floating roof internal to the tank, which is known as an Internal Floating Roof (IFR).
- EFR External Floating Roof
- IFR Internal Floating Roof
- an inspection of each tank at the particular location is conducted that includes the collection of one or more photographic images (i.e., visible spectrum) or video of each tank, and/or the collection of infrared images or video of each tank.
- the collected photographic images and the collected infrared images of each tank are then transmitted to a central processing facility for analysis to obtain a measurement of the amount of crude oil or other liquid energy commodity in storage.
- pumping stations are positioned along pipelines.
- the pumps used at each of these pumping stations are typically electrically driven induction motors.
- one preferred form of analysis is based on monitoring the real-time electric power consumption of some number of pumping stations along a selected pipeline.
- a monitoring device is deployed and used to monitor one or more power lines supplying electric power to each selected pumping station.
- the monitoring device is primarily comprised of sensing elements responsive to electric potential and the magnetic flux densities associated with the one or more power lines, therefore allowing for periodic or continuous measurements of the electric potential and magnetic flux densities associated with the one or more power lines, and thus a determination of power.
- Data from such monitoring devices is then transmitted to the central data processing facility.
- a model of the pipelines and the pumping stations in the particular network is developed that includes computations of the elevation gain or loss between any monitored pumping station and the next pumping station downstream using standard geographical elevation data.
- the pressure differential between the output or discharge side of any particular monitored pumping station and the input side of the next station downstream is then estimated.
- a range of possible flow rates for the pipeline from minimum possible flow to maximum possible flow for the pipeline is plotted versus the equivalent expected power consumption at the monitored pumping station.
- FIG. 1 is a schematic view of an exemplary network associated with crude oil production
- FIG. 2 is a schematic view of an exemplary network associated with crude oil transport and processing
- FIG. 3 is an exemplary image in which the outline of three tanks has been found and marked on the image using the Sobel edge detection method
- FIG. 4 is an exemplary image with the outline of three tanks from FIG. 3 overlaid on a subsequent collected image;
- FIG. 5 is a graph that illustrates the one-dimensional shape of an edge in an image
- FIG. 6 includes a pair of 3x3 convolution masks used in a Sobel edge detection method
- FIG. 7 illustrates how a convolution mask in a Sobel edge detection method is applied to an input image
- FIG. 8 is a plot of flow rate (barrels per day) against expected power consumption (MW) for an exemplary pumping station;
- FIGS. 9(a)-(d) are a series of thermal images illustrating the ramp-down of a fluid catalytic cracking unit at a refinery
- FIG. 10 illustrates a storage hub that is connected to three pipelines
- FIG. 1 1 is a plot illustrating how directly measured data is fitted using a standard mathematical regression model to historic data
- FIG. 12 is a schematic view of another exemplary network associated with crude oil production
- FIG. 13 is a flow chart depicting the general functionality of an implementation of the method and system of the present invention in connection with the exemplary network of FIG. 12;
- FIG. 14 is a schematic representation of the core components in an exemplary implementation of the method and system of the present invention.
- the present invention is a method and system for collecting and analyzing operational information from a network of components associated with a liquid energy commodity, such as crude oil or natural gas liquid (NGL).
- a liquid energy commodity such as crude oil or natural gas liquid (NGL).
- crude oil is a fossil fuel, it is typically drilled or mined at locations where there are naturally occurring deposits or reservoirs. Once collected at such a location (for example, from a well), the crude oil is typically pumped directly into a pipeline or stored in above-ground storage (e.g., tanks) or underground storage (e.g., salt dome caverns). From such storage facilities, it can then be transported via pipelines to refineries or other processing facilities for processing.
- above-ground storage e.g., tanks
- underground storage e.g., salt dome caverns
- natural gas is extracted at locations where there are naturally occurring reservoirs.
- the extracted natural gas is then processed into "dry” natural gas or “wet” natural gas at processing plants, the latter of which is termed natural gas liquid (NGL).
- NGL natural gas liquid
- the NGL is then transported using NGL pipelines and stored at NGL storage sites.
- the NGL may then be separated into at what are termed "purity" products such as ethane, propane, and butane.
- purity products such as ethane, propane, and butane.
- These NGL products can then be processed at ethylene cracking facilities which take NGL products in and process them into petrochemical industry feedstocks such as ethylene, propylene, etc.
- sensors or measurement devices are deployed at various points in a network to collect data.
- the method then generally comprises the steps of: (a) measuring an amount of the liquid energy commodity in storage at one or more storage facilities in the network, and storing that measurement data in a first database at a central data processing facility; (b) determining a flow rate of the liquid energy commodity in one or more selected pipelines in the network, and storing that flow rate data in a second database at the central data processing facility; (c) ascertaining an operational status of one or more processing facilities in the network, and storing that operational status information in a third database at the central data processing facility; (d) analyzing the measurement data, the flow rate data, and the operational status information to determine a balance of the liquid energy commodity in the network or a selected portion thereof at a given time; and (e) communicating information about the balance of the liquid energy commodity to a third -party market participant.
- a "network" for crude oil can thus be characterized as having three fundamental components: (i) crude oil storage facilities; (ii) crude oil pipelines; and (iii) crude oil refineries or other processing facilities.
- the amount of crude oil stored in tanks located at either terminals, storage hubs, or oil refineries is of the order of 340 million barrels. 55,000 miles of pipelines transport crude oil from American production wells (notably in the states of Texas, Louisiana, Oklahoma, and Wyoming), import terminals (notably seaports in the Gulf of Mexico), or overland across the border from Canada to various regional markets. These markets are divided into five large regions in the U.S. known as Petroleum Administration for Defense (PAD) Districts. Crude oil pipelines typically vary in diameter from eight to thirty inches. Larger interregional pipelines, which service refineries or storage hubs, are generally more relevant to overall market dynamics than smaller intra-regional pipelines.
- Crude oil stored at refineries is available for refining at any particular point in time into gasoline and/or other petroleum products.
- Crude oil stored at major oil storage hubs may be indicative of the amount of crude oil being stored by financial speculators or by suppliers to refineries downstream of the storage hub.
- Other tank storage may be primarily used to maintain appropriate pressures and volumes in order to successfully operate the required flow dynamics on a particular pipeline.
- each selected storage facility in a particular network there is a measurement of the amount of crude oil or other liquid energy commodity in storage.
- a measurement of the amount of crude oil or other liquid energy commodity in storage For instance, one preferred method for measuring the amount of crude oil being stored in a particular tank is described in commonly owned and co-pending U. S. Patent Application Serial No. 13/089,674 entitled “Method and System for Determining an Amount of Crude Oil Stored in a Particular Location," which is incorporated herein by reference.
- an inspection of each tank at the particular location is conducted that includes the collection of one or more photographic images (i.e., visible spectrum) or video of each tank, and/or the collection of infrared images or video of each tank.
- photographic images i.e., visible spectrum
- video of each tank can be collected by aerial means, through use of ground-placed, fixed cameras, or via satellite imaging.
- aerial image acquisition such as a helicopter flyover
- the helicopter preferably flies a defined and repeatable flight route and adheres to a pre-defined sequence for image acquisition, which facilitates the subsequent analysis.
- fixed thermal imaging cameras may take infrared images at predetermined intervals.
- the collected photographic images and the collected infrared images of each tank are then transmitted to a central processing facility for analysis.
- tank levels can be measured by drawing two vertical lines, such as LI and L2.
- LI line is drawn on the inside of the tank from the top of the tank down to the top of the lid and approximates the height the roof has been lowered.
- L2 line is drawn on the outside of the tank from the top of the tank down to the bottom of the tank and approximates the height of the tank.
- the respective lengths of the L 1 and L2 lines are then measured.
- Such measurement is optimized, for example, by ensuring an appropriate camera angle and distance from the tank, using high-resolution equipment for image acquisition, and/or ensuring consistent and proper placement of the LI and L2 lines on the image.
- the amount of crude oil in the tank can be calculated. For example, if the roof is at the halfway point, i.e., at a 50% height relative to the top of a 200,000-barrel tank, and the tank has a typical cylindrical construction with a constant diameter from the base to the top, it is calculated that 100,000 barrels of crude oil are in the tank. Stated another way, tank level percent of capacity can be calculated by 1 - (D1/D2), where Dl and D2 are the respective measured lengths of LI and L2 in image pixels. Tank level percent of capacity is then multiplied by the tank capacity to calculate the number of barrels of crude oil in the tank.
- the top, roof, and the base of a tank are identified in either a photographic image or infrared image.
- Automated elliptical form fitting or detection algorithms employing mathematical transformations, such as a Hough transform, can then be used to fit an elliptical plane on each of the top, roof, and the base of the tank.
- the amount of crude oil in the tank can again be calculated.
- the liquid level within a selected tank can be ascertained from the collected infrared images, as the temperature of the stored oil is different than that of the gas above it in the tank.
- One preferred form of analysis to determine the height of the liquid level in the tank is to measure the pixel distance from the liquid-gas boundary to the base of the tank. Based on the ascertained liquid level within the tank and the stored volume capacity information and/or the stored physical dimensions of the selected tank, the amount of crude oil in the tank can again be calculated.
- infrared images are collected for each tank of interest at selected intervals (e.g., every five minutes) and transmitted to the central data processing facility for analysis.
- the camera that collects the infrared images is preferably fixed in position, it is acknowledged that there is often some minor movement of the camera.
- feature detection is used to find the tank location in each infrared image, thus ensuring an accurate calculation of the amount of crude oil in the tank.
- Edges in images are areas with strong intensity contrasts, i.e., a significant change in intensity from one pixel to the next.
- There are various methods and techniques for detecting edges in an image which can be generally grouped into two categories: gradient and
- a gradient method detects the edges by looking for the maximum and minimum in the first derivative of the image.
- a Laplacian method searches for zero crossings in the second derivative of the image to find edges. Referring now to FIG. 5, an edge has the one-dimensional shape of a ramp.
- the derivative of the one-dimensional shape thus shows a maximum located at the center of the edge.
- the theory can be carried over to two dimensions as long as there is an accurate approximation to calculate the derivative of a two-dimensional image.
- a Sobel operator is used to perform a two-dimensional spatial gradient measurement on a particular infrared image in order to find the approximate absolute gradient magnitude at each point in the infrared image. See R. Gonzalez and R. Woods, Digital Image Processing, Addison Wesley (1992), pp. 414- 428.
- the Sobel edge detection method uses a pair of 3x3 convolution masks (FIG.
- FIG. 7 illustrates how a convolution mask in a Sobel edge detection method is applied to an input image, with the mask being applied over the top left portion of the input image and equation (1) below being used to calculate a particular pixel in the output image.
- the center of the mask is placed over the pixel that is being manipulated in the image; for example, pixel (a 22 ) is converted to pixel (b 22 ) by:
- b 2 2 (an * mil) + (ai 2 * mi 2 ) + (ai 3 * m ) + (a 2 i * m 2 i) + (a 22 * m 22 ) +
- a Sobel edge detection image is computed for each collected infrared image. Then, for each edge detection image, the tank location is found by determining the best fit to one or more features. Each feature is a set of pixel locations where the Sobel edge detection image should contain an edge and have a black color.
- FIG. 3 is an exemplary image in which the outline of three tanks has been found and marked on the image using the Sobel edge detection method, and FIG. 4 shows how this outline of three tanks can be overlaid on a subsequent collected image.
- the tank level is computed based on a vertical line starting at the bottom of each tank, as also shown in FIG. 4. Each vertical line is searched upward from the bottom of the tank for the next edge location, which is the oil level location.
- the number of pixels between the bottom of the tank and the oil level location is used to compute the tank percent full as follows:
- Percent Full 100 * (pixel_height) / (total pixel height of tank)
- the flow rate with respect to a certain tank can be calculated by the rate of change of the storage levels within the tank:
- the objective again is to obtain a measurement of the amount of crude oil in storage in the particular network, which is stored at the central data processing facility.
- NGL products such as ethane, propane, and butane
- similar image collection and analysis on the vertical and horizontal tanks commonly used to store such products can be carried out in order to obtain a measurement of the amount of the NGL product in storage in the particular network.
- Crude oil pipeline flow data in real-time is generally only known to the owners, operators, and shippers on the pipeline.
- one preferred form of analysis is based on monitoring the real-time electric power consumption of some number of pumping stations along a selected pipeline.
- a monitoring device is deployed and used to monitor one or more power lines supplying electric power to each selected pumping station.
- the monitoring device (also referred to herein as “power monitoring device”) is primarily comprised of sensing elements responsive to electric potential and the magnetic flux densities associated with the one or more power lines, therefore allowing for periodic or continuous measurements of the electric potential and magnetic flux densities associated with the one or more power lines, and thus a determination of power.
- the construction and use of such monitoring devices is described in commonly owned U. S. Patent No. 6,771,058 entitled “Apparatus and Method for the Measurement and Monitoring of Electrical Power Generation and Transmission,” and U.S. Patent No. 6,714,000 entitled “Apparatus and Method for Monitoring Power and Current Flow,” each of which is incorporated herein by reference.
- Data from such monitoring devices is then transmitted to a central data processing facility.
- a model of the pipelines and the pumping stations in the particular network is developed that includes computations of the elevation gain or loss between any monitored pumping station and the next pumping station downstream using standard geographical elevation data.
- the pressure differential between the output or discharge side of any particular monitored pumping station and the input side of the next station downstream is then estimated.
- the pressure change calculations also take typical minimum and maximum pressures for the pipeline into account for use as reasonable computation boundary values.
- a preferred flow model takes into account the pipeline length and elevation change between a monitored pumping station and the next pumping station downstream.
- the pipeline length, elevation change, and power usage are used to estimate the pressure differential between the output side of the first pumping station and the input side of the next pumping station downstream.
- the frictional pressure differential or head loss (HeadLoss (H) in feet) between any two pumping stations on a selected pipeline can be calculated from the variables set forth below. See Pipeline Rules of Thumb
- the flow rate (Q) values range from zero to the maximum flow rate of the pipeline.
- centiStokes (cSt) value is based on an assumption of API and temperature, and then is converted into units of (ft 2 1 sec) : (c3 ⁇ 4) * i0.0763910
- Fanning's equation is then used to compute the frictional pressure drop (HeadLoss) between pumping stations for a given flow rate (Q), pipeline segment length (L) and elevation profile.
- Fanning's equation for expressing the frictional pressure drop of oil flowing in a pipeline is a function of a frictional loss (j) derived from the Reynolds number (Re).
- the pump efficiency (E) is estimated to range between 0.25 and 0.40.
- the power consumed by any particular pump can then be computed directly from pump horsepower using a horsepower to power unit conversion factor c, which is equal to 0.000746.
- D the diameter of the pipeline
- Q gallons/minute
- the kinematic viscosity v 0.004 centiStokes.
- the elevation difference between pumping station x and pumping station y 353 feet.
- the resultant head loss (HeadLoss) is 181.1 feet.
- FIG. 8 A plot of flow rate (barrels per day) against expected power consumption (MW) is shown in FIG. 8.
- one preferred method of deriving total pipeline flow is to compute an average of the estimated flow rates at several pumping stations to determine the flow rate on the pipeline as a whole.
- the approach is often used when fewer than half the pumping stations are monitored on a given pipeline.
- Another preferred method of deriving total pipeline flow uses Monte Carlo simulations to model power usage at all pumping stations along a given pipeline and is used when half or more than half of the pumping stations are monitored.
- the simulations use inputs from the monitored pumping stations, as well as predictions of power usage at pumping stations along the pipeline which are not monitored.
- the power usage at the unmonitored pumping stations is modeled with a uniform distribution from zero to a maximum power usage based on the number of pumps and the type of pumps at each pumping station.
- each Monte Carlo simulation uses the same observed power usage for the monitored pumping stations and performs a random sample of the power usage uniform distributions for the unmonitored pumping stations. Equations (6) to (13) are used to simulate pressure head profile along the entire pipeline.
- the pipeline flow regime zero barrels per day to capacity, is divided in a finite number of intervals. For each flow value at the center of each flow interval, a large number of Monte Carlo simulations are performed and the number of valid simulations is recorded. An overall pipeline flow is computed using the following expected value:
- v_i is the number of valid simulations for J
- a thermal imaging camera may be used to assess the on/off condition of one or more pumping stations.
- electrically-driven induction motors are commonly used at pumping stations, some pumps may be driven by gas or diesel-powered motors. Such motors typically exhaust through one or more stacks, so the operation and operational levels (including number of pumps on or off) of the pumping station can also be assessed using a thermal imaging camera directed at the stacks or ancillary equipment.
- Crude oil invariably enters an oil refinery at some point in the network to be processed into gasoline and/or other petroleum products, such as diesels, jet fuels, heating oil, etc.
- the ability of the various units at the refinery to utilize the incoming crude oil is dependent on the proper functioning of such units.
- Refineries are highly complex facilities which generally are designed and intended to function year-round on a 24 hour-a-day, 7 day- a- week schedule. However, disruptions and malfunctions of equipment at these facilities occurs on a relatively frequent basis and can have immediate impact on market dynamics. Specifically, if particular units at one or more refineries are off-line, there is a decreased demand for crude oil at the affected refineries and a decreased supply of gasoline and other refined products in markets supplied by affected refineries. So-called refinery unit ramp- downs and ramp-ups are of particular market interest, but, in addition, there is also an interest in the flow rates of crude oil into each refinery and the amount of crude oil in storage at each refinery at any given time.
- processing facilities this term is also intended to include any facility in a network in which there is some handling of the liquid energy commodity that can be monitored, even if there is no material change to the liquid energy commodity, such as buffering, transfer, or surge overflow facilities.
- one preferred method for monitoring the operation of processing facilities is by using fixed thermal imaging cameras.
- a thermal imaging camera can acquire thermal data and record images of emissions and heat signatures of various key units that can be used to ascertain whether the processing facility is functioning as expected or not.
- FIGS. 9(a)-(d) are a series of thermal images illustrating the ramp-down of a fluid catalytic cracking unit (FCCU) at a refinery.
- each primary unit at a refinery typically has one or more exhaust stacks associated with it, which generally function as exhausts for heating devices, such as furnaces, heat exchangers, etc., or exhausts for emission control devices, such as wet gas scrubbers, electrostatic dust precipitators, etc.
- a characteristic level of heating is observed on a thermal image of the stack.
- a characteristic emission via a plume emanating from the top of the stack is also present and visible.
- the heating and emissions from such stacks are seen to be either absent completely or display some abnormal characteristics (e.g., excess heating or excess emissions).
- a characteristic level of heating can be observed on the thermal images for many other of types of equipment associated with a unit, including, but not limited to, vessels, piping, duct work, heat exchangers, furnaces, and/or ancillary equipment.
- the FCCU is in far right of the image, as illustrated by the arrow.
- the FCCU is shown in normal operating mode.
- the FCCU As shown in FIG. 9(b), during the start of ramp-down, emissions are seen from a stack in the middle of the FCCU, and the FCCU itself shows relative cooling with respect to neighboring units.
- the body of the FCCU shows continuing cooling; the emitting stacks remains hot, but emissions from it are reduced.
- both FCCU and the stack have completely cooled down, and ramp-down of the FCCU is complete.
- Each primary unit at a refinery also has emergency control devices, such as flares, blowdown stacks, and other devices which can burn off or dissipate inline streams of feedstocks, processing chemicals, and associated by-products in the case where the units need to be shut-down rapidly.
- emergency control devices can also be used in the normal operation of such units to control the amounts of feedstocks, processing chemicals, and associated by-products in the process streams.
- These emergency control devices can also be observed by a thermal imaging camera as operating at characteristically levels (typically low or off) when the associated units are operating normally and at abnormal levels (typically emitting at abnormal and elevated levels) when the associated units are experiencing issues, are being started up, or being shut down.
- thermal images such as those shown in FIGS. 9(a)-(d) can be analyzed visually or by using automated image analysis to ascertain the operational status of the primary units of a refinery.
- image analysis techniques that may be utilized, reference is made to commonly assigned and co-pending U.S. Patent Application Serial No. 13/269,833 entitled "Method and System for Providing Information to Market Participants About One or More Power Generating Units Based on Thermal Image Data," which is a continuation of U. S. Patent Application Serial No. 12/053,139. Each of these patent applications is incorporated herein by reference.
- monitoring technology is also applicable to such processing facilities as: (a) fractionation facilities, where NGLs are separated from the crude oil for subsequent processing into such products as ethane, propane, and butanes; (b) upgrading facilities (or upgraders), which process raw crude oils after mining and prepare the crude oils for delivery to and subsequent refining at crude oil refineries; (c) ethylene cracking facilities, where NGL products and/or petroleum liquids (such as naphtha) are processed into petrochemical industry feedstocks such as ethylene, propylene, etc.; and (d) natural gas processing facilities, which produce NGL from natural gas.
- fractionation facilities where NGLs are separated from the crude oil for subsequent processing into such products as ethane, propane, and butanes
- upgrading facilities or upgraders
- ethylene cracking facilities where NGL products and/or petroleum liquids (such as naphtha) are processed into petrochemical industry feedstocks such as ethylene, propylene, etc.
- natural gas processing facilities which produce NGL from natural gas.
- the combined data from the monitoring of these three fundamental components can be used to estimate physical balances of interest.
- FIG. 10 illustrates a storage hub (i.e., a collection of storage tanks) 100 that is connected to three pipelines: Pipeline A, Pipeline B, and Pipeline C.
- a storage hub i.e., a collection of storage tanks
- measurement of the amount of crude oil in each storage tank is made, and then a sum of all such measurements yields the collective amount in storage at the storage hub 100 at a given time.
- a determination of the real-time inflows and outflows of oil into the storage hub 100 can be made on a periodic basis from the data collected from the monitoring devices for the power lines supplying electric power to selected pumping stations along each of the three pipelines. For example, if Pipeline A and Pipeline B are incoming, and Pipeline C is outgoing, a net inflow into the storage hub 100 can be computed from a summation of the inflows less any outflows:
- NetlnflowIntoHub (Pipeline A FLOW + PipelineB FLOW ) - Pipeline C FLOW ⁇
- a substantially real-time determination can be made as to the amount of crude oil in storage at the storage hub 100 at a given time.
- additional modeling may then be possible to determine operational parameters, such as the effect on storage levels at the storage hub 100 for various operational conditions of the incoming and outgoing pipelines, the use of certain storage tanks to contain crude oil from certain pipelines, what crude oil is in transit through the storage hub 100 and what crude oil stays at the storage hub 100.
- data collected from the monitoring devices for the power lines supplying electric power to selected pumping stations (PSl, PS2, PS3, PS4, PS5) along each of the pipelines can be combined with information obtained from the analysis of thermal images of a refinery (not shown) connected to the pipelines to determine the balances of crude oil in transit to the refinery, in storage at the refinery, and being processed at the refinery at any given time.
- data can also be obtained from third-party and publicly available data sources, such as that provided by the United States Energy Information Administration (“EIA”), to deliver estimations and predictions of parameters of market interest related to commodity supply, demand, and storage.
- EIA United States Energy Information Administration
- one such parameter of interest is the total volume of crude oil in storage in the PAD 2 market region at any given time.
- EIA publishes an amount for this value weekly, typically on Wednesday morning at 10:30 AM EST.
- Directly measured data and EIA data can be effectively combined using a standard mathematical regression model. Specifically, the standard mathematical regression model is used to fit the directly measured data to the historic PAD 2 crude oil storage inventory data published by EIA.
- the determined PAD 2 crude oil inventories are then estimated going forward using the resultant model.
- directly measured data is obtained using the techniques described above for: (i) the storage levels at a major PAD 2 storage hub; (ii) the crude oil flow rates into PAD 2 (collected from six pipelines entering the PAD 2 region from PAD 3); and (iii) refinery unit operational data (collected from nine PAD 2 refineries).
- This directly measured data is then fitted using a standard mathematical regression model to historic PAD 2 crude oil storage inventory data published by EIA.
- the determined crude oil inventories based on the model output (“Model" line in FIG. 1 1) can then be compared to actual PAD 2 crude oil inventory data ("PAD 2" line in FIG. 1 1), and PAD 2 crude oil inventories can then be estimated going forward using the resultant model.
- FIG. 12 is a schematic view of another exemplary network associated with crude oil production.
- crude oil originating from an oil platform 200 (or other production source) is delivered to a pipeline 210.
- the pipeline 210 is then connected and delivers the crude oil to a fractionation facility 212, which is monitored by a sensor S5, as also described below in Table 2.
- a sensor S5 as also described below in Table 2.
- a storage facility 214 which is monitored by sensor(s) S6, as also described below in Table 2.
- S7 there is an additional data input, as represented in FIG. 12 by S7.
- This additional data input, S7 is used to further verify the collected data and results of the various computational analyses.
- crude oil in the storage facility 214 is delivered to one or more ships at a sea terminal for export.
- Much data about ships that transfer crude oil is publicly known and available, including ship capacity and ship location via Automatic Identification System (AIS) ship tracking services.
- AIS Automatic Identification System
- a visual camera or an infrared camera can be used to estimate flow rate of oil delivered to the particular ship by measuring the change in ship draft (i.e., the change in ship position relative to the waterline) over time. That delivery of oil should be equal to the reduction in oil level in the storage facility 214.
- AIS Automatic Identification System
- the outputs from S I, S2, S3, and S4 are used to determine power changes at each pumping station along the pipeline 210, which can then be used to determine flow rate of the crude oil through the pipeline 210, as indicated by block 300 of FIG. 13, and that flow rate data is stored in a database at a central data processing facility.
- the output from S5 is used to determine the operational status of the fractionation facility 212, as indicated by block 302 of FIG. 13, and that operational status information in also stored in database at the central data processing facility.
- the output from S6 is used to measure an amount of the crude oil in storage at the storage facility 214, as indicated by block 304 of FIG. 13, and that measurement data is also stored in a database at the central data processing facility.
- an analysis is performed on the flow rate data, the operational status information, and the measurement data to determine total "balances" of the crude oil in different functional parts of the network, as indicated by block 310 of FIG.
- balances of interest to market participants would include, but are not limited to: the amount of crude oil flowing into the network at a given time, the amount of crude oil in storage in the network at a given time; and/or the amount of crude oil flowing out of the network at a given time.
- information about the balance of the crude oil in the network can be communicated to market participants and other interested parties, i.e., third parties who would not ordinarily have ready access to such information, as indicated by block 320. It is contemplated and preferred that such communication to third-party market participants could be achieved through electronic mail delivery and/or through export of the data to an access-controlled Internet web site, which third-party market participants can access through a common Internet browser program, such as Microsoft Internet Explorer®. Of course, communication of information and data to third- party market participants may also be accomplished through a wide variety of other known communications media without departing from the spirit and scope of the present invention.
- FIG. 14 is a schematic representation of the core components in an exemplary implementation of the method and system of the present invention.
- the central data processing facility 10 includes a first database 20, a second database 22, and a third database 24.
- these databases 20, 22, 24 could be integrated into a single database at the central data processing facility 10.
- the central data processing facility 10 hosts a digital computer program, i.e., computer-readable instructions stored and executed by a computer, that includes appropriate modules for executing the requisite routines and subroutines for performing the operational steps of the present invention.
- an exemplary system for determining an amount of a liquid energy commodity stored in a tank includes: (a) a storage measurement module 40 for receiving and analyzing collected images of one or more storage facilities to measure an amount of the liquid energy commodity in storage at each of the one or more storage facilities, and storing that measurement data in a first database 20; (b) a flow rate determination module 42 for receiving and processing measurements of the electric potential and magnetic flux densities associated with power lines for pumping stations on a pipeline to determine a flow rate of the liquid energy commodity in each selected pipeline, and storing that flow rate data in a second database 22; (c) an operational status module 44 for receiving and processing information about an operational status of a processing facility and storing that operational status information in a third database 24; (d) an analysis module 50 for querying the databases 20, 22, 24 and analyzing the measurement data, the flow rate data, and the operational status information to determine a balance of the liquid energy commodity in the network or a selected portion thereof at a given time; and (e) a communications module
Landscapes
- Engineering & Computer Science (AREA)
- Business, Economics & Management (AREA)
- Physics & Mathematics (AREA)
- Human Resources & Organizations (AREA)
- Mechanical Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Economics (AREA)
- Strategic Management (AREA)
- Entrepreneurship & Innovation (AREA)
- General Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Game Theory and Decision Science (AREA)
- General Business, Economics & Management (AREA)
- Development Economics (AREA)
- Theoretical Computer Science (AREA)
- Educational Administration (AREA)
- Marketing (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Tourism & Hospitality (AREA)
- Thermal Sciences (AREA)
- Fluid Mechanics (AREA)
- Health & Medical Sciences (AREA)
- Public Health (AREA)
- Water Supply & Treatment (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
- Arrangements For Transmission Of Measured Signals (AREA)
- Pipeline Systems (AREA)
Abstract
Description
Claims
Priority Applications (9)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
EP18186703.7A EP3432249B1 (en) | 2011-02-16 | 2012-02-16 | Method and system for collecting and analysing operational information from a network of components associated with a liquid energy commodity |
MX2013009414A MX2013009414A (en) | 2011-02-16 | 2012-02-16 | Method and system for collecting and analyzing operational information from a network of components associated with a liquid energy commodity. |
CN201280009294.3A CN103477359B (en) | 2011-02-16 | 2012-02-16 | For collecting the method and system of the operation information of the network with analysis element |
BR112013021047-8A BR112013021047B1 (en) | 2011-02-16 | 2012-02-16 | METHOD AND SYSTEM FOR COLLECTING AND ANALYZING OPERATIONAL INFORMATION FROM A NETWORK OF COMPONENTS ASSOCIATED WITH A NET ENERGY COMMODITIES AND METHOD FOR MONITORING RAW OIL TRANSPORT IN A NETWORK |
CA2827314A CA2827314C (en) | 2011-02-16 | 2012-02-16 | Method and system for collecting and analyzing operational information from a network of components associated with a liquid energy commodity |
JP2013554598A JP5767344B2 (en) | 2011-02-16 | 2012-02-16 | Method and system for collecting and analyzing operational information from a network of component requirements related to liquid energy products |
SG2013062229A SG192799A1 (en) | 2011-02-16 | 2012-02-16 | Method and system for collecting and analyzing operational information from a network of components associated with a liquid energy commodity |
AU2012217632A AU2012217632B2 (en) | 2011-02-16 | 2012-02-16 | Method and system for collecting and analyzing operational information from a network of components associated with a liquid energy commodity |
EP12747594.5A EP2676232B1 (en) | 2011-02-16 | 2012-02-16 | Method and system for collecting and analyzing operational information from a network of components associated with a liquid energy commodity |
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US201161443510P | 2011-02-16 | 2011-02-16 | |
US61/443,510 | 2011-02-16 |
Publications (2)
Publication Number | Publication Date |
---|---|
WO2012112759A2 true WO2012112759A2 (en) | 2012-08-23 |
WO2012112759A3 WO2012112759A3 (en) | 2012-11-08 |
Family
ID=46636624
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
PCT/US2012/025418 WO2012112759A2 (en) | 2011-02-16 | 2012-02-16 | Method and system for collecting and analyzing operational information from a network of components associated with a liquid energy commodity |
Country Status (11)
Country | Link |
---|---|
US (3) | US8717434B2 (en) |
EP (2) | EP3432249B1 (en) |
JP (1) | JP5767344B2 (en) |
CN (1) | CN103477359B (en) |
AU (1) | AU2012217632B2 (en) |
BR (1) | BR112013021047B1 (en) |
CA (1) | CA2827314C (en) |
MX (1) | MX2013009414A (en) |
MY (1) | MY164743A (en) |
SG (1) | SG192799A1 (en) |
WO (1) | WO2012112759A2 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US9934591B2 (en) | 2016-04-08 | 2018-04-03 | Orbital Insight, Inc. | Remote determination of quantity stored in containers in geographical region |
US10217236B2 (en) | 2016-04-08 | 2019-02-26 | Orbital Insight, Inc. | Remote determination of containers in geographical region |
Families Citing this family (18)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20130127908A1 (en) * | 2011-11-22 | 2013-05-23 | General Instrument Corporation | Method and apparatus for dynamic placement of a graphics display window within an image |
US11836332B1 (en) * | 2012-03-29 | 2023-12-05 | Edward J. Wiegele | Representation of remote assets system and method |
CA2830402A1 (en) * | 2012-10-23 | 2014-04-23 | Syscor Controls & Automation Inc | Visual monitoring system for covered storage tanks |
WO2016011158A1 (en) * | 2014-07-15 | 2016-01-21 | Genscape Intangible Holding, Inc. | Method and system for monitoring a production facility for a renewable fuel |
US9669850B2 (en) | 2014-09-08 | 2017-06-06 | Genscape Intangible Holding, Inc. | Method and system for monitoring rail operations and transport of commodities via rail |
US20160343124A1 (en) * | 2015-05-19 | 2016-11-24 | Genscape Intangible Holding, Inc. | Method and system for determining a status of one or more tanks in a particular location |
US9957959B2 (en) * | 2015-09-20 | 2018-05-01 | Macau University Of Science And Technology | Linear programming-based approach to scheduling of crude oil operations in refinery for energy efficiency optimization |
US9334722B1 (en) | 2015-11-18 | 2016-05-10 | Mubarak Shater M. Taher | Dynamic oil and natural gas grid production system |
CN106525121B (en) * | 2016-11-01 | 2019-03-05 | 北京师范大学 | A kind of the energy safety of supply evaluation system |
US11029185B2 (en) * | 2017-11-30 | 2021-06-08 | Rampart Strong, Llc | Tank gauge |
US11655823B2 (en) * | 2017-12-20 | 2023-05-23 | Siemens Energy Global GmbH & Co. KG | Predictive pump station and pipeline advanced control system |
EP3756135A4 (en) * | 2018-02-21 | 2021-12-01 | Genscape Intangible Holding, Inc. | Method and system for estimating an operating state of a facility via imaging of electromagnetic radiation |
CN109238381B (en) * | 2018-09-14 | 2020-07-07 | 北京市公用事业科学研究所 | Method for monitoring flow of user gas equipment |
WO2020060694A1 (en) | 2018-09-21 | 2020-03-26 | Ecolab Usa Inc. | Portable fluid level monitoring device and method |
JP7426391B2 (en) * | 2018-12-03 | 2024-02-01 | バイオ-ラッド ラボラトリーズ インコーポレーティッド | Liquid level determination method |
CN111156419B (en) * | 2020-01-07 | 2021-09-17 | 南京富岛信息工程有限公司 | Variable speed scheduling method and system for long-distance pipeline crude oil mixed transportation |
WO2021181675A1 (en) * | 2020-03-13 | 2021-09-16 | コニカミノルタ株式会社 | Gas inspection management system, gas inspection management method, and program |
CN115456451B (en) * | 2022-09-28 | 2023-10-31 | 中远海运科技股份有限公司 | AIS-based ship oil consumption estimation method and system |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO1984003488A1 (en) | 1983-03-07 | 1984-09-13 | Cypher Systems | Oil field lease management and security system and method therefor |
Family Cites Families (22)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5313908A (en) | 1990-10-05 | 1994-05-24 | Kunz Daniel W | Car topable catamaran with collapsible frame and universal tiller/rudder-mast daggerboard mounting constructions |
US5757664A (en) * | 1996-06-04 | 1998-05-26 | Warren Rogers Associates, Inc. | Method and apparatus for monitoring operational performance of fluid storage systems |
JPH08339400A (en) * | 1995-06-13 | 1996-12-24 | Idemitsu Kosan Co Ltd | Integrated control system of oil factory |
JP2970647B2 (en) * | 1998-04-01 | 1999-11-02 | 横河電機株式会社 | Fuel gas supply system |
US6714000B2 (en) | 1999-06-14 | 2004-03-30 | Genscape, Inc. | Method for monitoring power and current flow |
JP2001265125A (en) * | 2000-03-16 | 2001-09-28 | Nec Niigata Ltd | Liquid developing machine and image forming device using the same |
AU2001253541A1 (en) * | 2000-04-13 | 2001-10-30 | Genscape, Inc. | Apparatus and method for the measurement and monitoring of electrical power generation and transmission |
US20020035551A1 (en) * | 2000-09-20 | 2002-03-21 | Sherwin Rodney D. | Method and system for oil and gas production information and management |
US6722207B1 (en) * | 2002-03-19 | 2004-04-20 | Murray F. Feller | Electro-magnetic flow transducer with insulating scroll |
US6957586B2 (en) | 2003-08-15 | 2005-10-25 | Saudi Arabian Oil Company | System to measure density, specific gravity, and flow rate of fluids, meter, and related methods |
US7359931B2 (en) | 2003-08-15 | 2008-04-15 | Saudi Arabian Oil Company | System to facilitate pipeline management, software, and related methods |
US7376522B2 (en) * | 2003-10-20 | 2008-05-20 | Genscape Intangible Holding, Inc. | Method and system for determining the direction of fluid flow |
US7274996B2 (en) | 2003-10-20 | 2007-09-25 | Genscape Intangible Holding, Inc. | Method and system for monitoring fluid flow |
EP1682947A4 (en) | 2003-10-23 | 2008-01-23 | Clearsight Systems Inc | Method and system for optimization of general symbolically expressed problems, for continuous repair of state-functions, including state functions derived from solutions to computational optimization, for generalized control of computational processes, and for hierarchical meta-control and construct |
JP2005291830A (en) * | 2004-03-31 | 2005-10-20 | Shinko Engineering & Maintenance Co Ltd | Image measurement apparatus and image measurement method for liquid level |
US7177780B2 (en) * | 2005-01-14 | 2007-02-13 | Flying J, Inc. | Methods and systems for measuring physical volume |
JP5186773B2 (en) * | 2006-05-25 | 2013-04-24 | 株式会社リコー | Waste liquid tank, liquid discharge device, image forming device |
US7953587B2 (en) * | 2006-06-15 | 2011-05-31 | Schlumberger Technology Corp | Method for designing and optimizing drilling and completion operations in hydrocarbon reservoirs |
US7668688B2 (en) | 2008-06-17 | 2010-02-23 | Saudi Arabian Oil Company | System, program product, and related methods for estimating and managing crude gravity in real-time |
US20100042527A1 (en) * | 2008-07-10 | 2010-02-18 | Weather Insight, Lp | Storm Commodity Forecast System and Method |
US8452046B2 (en) * | 2008-10-07 | 2013-05-28 | Honeywell International Inc. | Method and apparatus for automatic sediment or sludge detection, monitoring, and inspection in oil storage and other facilities |
US8193967B2 (en) * | 2008-12-10 | 2012-06-05 | The United States Of America As Represented By The Secretary Of The Army | Method and system for forming very low noise imagery using pixel classification |
-
2012
- 2012-02-16 EP EP18186703.7A patent/EP3432249B1/en active Active
- 2012-02-16 CA CA2827314A patent/CA2827314C/en active Active
- 2012-02-16 WO PCT/US2012/025418 patent/WO2012112759A2/en active Application Filing
- 2012-02-16 US US13/398,268 patent/US8717434B2/en active Active
- 2012-02-16 BR BR112013021047-8A patent/BR112013021047B1/en active IP Right Grant
- 2012-02-16 EP EP12747594.5A patent/EP2676232B1/en active Active
- 2012-02-16 CN CN201280009294.3A patent/CN103477359B/en active Active
- 2012-02-16 AU AU2012217632A patent/AU2012217632B2/en active Active
- 2012-02-16 MY MYPI2013003007A patent/MY164743A/en unknown
- 2012-02-16 SG SG2013062229A patent/SG192799A1/en unknown
- 2012-02-16 JP JP2013554598A patent/JP5767344B2/en active Active
- 2012-02-16 MX MX2013009414A patent/MX2013009414A/en active IP Right Grant
-
2014
- 2014-03-17 US US14/215,384 patent/US9886673B2/en active Active
-
2017
- 2017-12-13 US US15/840,603 patent/US10692022B2/en active Active
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO1984003488A1 (en) | 1983-03-07 | 1984-09-13 | Cypher Systems | Oil field lease management and security system and method therefor |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US9934591B2 (en) | 2016-04-08 | 2018-04-03 | Orbital Insight, Inc. | Remote determination of quantity stored in containers in geographical region |
US10192323B2 (en) | 2016-04-08 | 2019-01-29 | Orbital Insight, Inc. | Remote determination of containers in geographical region |
US10217236B2 (en) | 2016-04-08 | 2019-02-26 | Orbital Insight, Inc. | Remote determination of containers in geographical region |
US10319107B2 (en) | 2016-04-08 | 2019-06-11 | Orbital Insight, Inc. | Remote determination of quantity stored in containers in geographical region |
US10607362B2 (en) | 2016-04-08 | 2020-03-31 | Orbital Insight, Inc. | Remote determination of containers in geographical region |
Also Published As
Publication number | Publication date |
---|---|
EP3432249A1 (en) | 2019-01-23 |
EP2676232A2 (en) | 2013-12-25 |
US10692022B2 (en) | 2020-06-23 |
AU2012217632B2 (en) | 2015-07-02 |
CN103477359B (en) | 2016-11-16 |
MY164743A (en) | 2018-01-30 |
SG192799A1 (en) | 2013-09-30 |
US9886673B2 (en) | 2018-02-06 |
US20120206595A1 (en) | 2012-08-16 |
CA2827314C (en) | 2018-06-26 |
CA2827314A1 (en) | 2012-08-23 |
WO2012112759A3 (en) | 2012-11-08 |
US20140200936A1 (en) | 2014-07-17 |
BR112013021047A2 (en) | 2016-10-18 |
BR112013021047B1 (en) | 2021-03-30 |
JP2014511527A (en) | 2014-05-15 |
MX2013009414A (en) | 2014-01-24 |
EP3432249B1 (en) | 2020-04-08 |
CN103477359A (en) | 2013-12-25 |
JP5767344B2 (en) | 2015-08-19 |
US8717434B2 (en) | 2014-05-06 |
EP2676232B1 (en) | 2018-09-05 |
AU2012217632A1 (en) | 2013-09-05 |
EP2676232A4 (en) | 2016-10-12 |
US20180101796A1 (en) | 2018-04-12 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US10692022B2 (en) | Method and system for collecting and analyzing operational information from a network of components associated with a liquid energy commodity | |
US8842874B1 (en) | Method and system for determining an amount of a liquid energy commodity stored in a particular location | |
Azadeh et al. | Evolutionary multi-objective optimization of environmental indicators of integrated crude oil supply chain under uncertainty | |
AU2020392228A1 (en) | Intelligent vibration digital twin systems and methods for industrial environments | |
EP4066073A1 (en) | Intelligent vibration digital twin systems and methods for industrial environments | |
WO2020227429A1 (en) | Platform for facilitating development of intelligence in an industrial internet of things system | |
EP3966695A1 (en) | Platform for facilitating development of intelligence in an industrial internet of things system | |
US8275719B1 (en) | Electronic settlement of petroleum and gas distributions | |
US20160019482A1 (en) | Method and system for monitoring a production facility for a renewable fuel | |
Kaiser | An integrated systems framework for service vessel forecasting in the Gulf of Mexico | |
CA2992088A1 (en) | Method and system for estimating production of an energy commodity by a selected producer | |
EP3942271A1 (en) | Method and device for operating a distribution network | |
Limpanachaipornkul et al. | Revisiting GBS CO2 Removal Optimization–First Step to NET ZERO | |
Kamojjala | World Environmental and Water Resources Congress 2018: Hydraulics and Waterways, Water Distribution Systems Analysis, and Smart Water | |
Melo et al. | A framework for the probabilistic integrity and risk assessment of unpiggable pipelines | |
Zelentsov et al. | The Concept of Autonomous Oil and Gas-Condensate Field of Gazpromneft-Yamal | |
Oyokunyi et al. | The Cost of Gas Production Optimization Using Linear Programing on Reverse Fishbone Diagram: A Case Study | |
Gonzalez et al. | Production Data Management System to Enhance Collaboration and Production Surveillance, Large Steam Thermal Pilot North LSTPN KOC-Heavy Oil Field | |
Rippon et al. | Failure modes and effect analysis of a sour corrosion control system | |
Foroushani et al. | LDS Concept Based on Remote Sensing Petroleum Pipeline Seeps Detection in Deep | |
Risa | Norwegian pipeline gas from an asset management perspective: present and future | |
D'Alessandria | Design of a self-contained fixed offshore oil production platform for the shores of Venezuela. | |
Kozman et al. | Intelligent Platforms to Manage Offshore Assets | |
Enerstvedt | VRD plant performance testing project |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 12747594 Country of ref document: EP Kind code of ref document: A2 |
|
ENP | Entry into the national phase |
Ref document number: 2827314 Country of ref document: CA |
|
WWE | Wipo information: entry into national phase |
Ref document number: MX/A/2013/009414 Country of ref document: MX |
|
ENP | Entry into the national phase |
Ref document number: 2013554598 Country of ref document: JP Kind code of ref document: A |
|
NENP | Non-entry into the national phase |
Ref country code: DE |
|
ENP | Entry into the national phase |
Ref document number: 2012217632 Country of ref document: AU Date of ref document: 20120216 Kind code of ref document: A |
|
WWE | Wipo information: entry into national phase |
Ref document number: 2012747594 Country of ref document: EP |
|
REG | Reference to national code |
Ref country code: BR Ref legal event code: B01A Ref document number: 112013021047 Country of ref document: BR |
|
ENP | Entry into the national phase |
Ref document number: 112013021047 Country of ref document: BR Kind code of ref document: A2 Effective date: 20130816 |