WO2011153063A2 - Power distribution system having priority load control - Google Patents
Power distribution system having priority load control Download PDFInfo
- Publication number
- WO2011153063A2 WO2011153063A2 PCT/US2011/038113 US2011038113W WO2011153063A2 WO 2011153063 A2 WO2011153063 A2 WO 2011153063A2 US 2011038113 W US2011038113 W US 2011038113W WO 2011153063 A2 WO2011153063 A2 WO 2011153063A2
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- load
- generator
- interruption device
- distribution system
- fault condition
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Ceased
Links
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02H—EMERGENCY PROTECTIVE CIRCUIT ARRANGEMENTS
- H02H7/00—Emergency protective circuit arrangements specially adapted for specific types of electric machines or apparatus or for sectionalised protection of cable or line systems, and effecting automatic switching in the event of an undesired change from normal working conditions
- H02H7/26—Sectionalised protection of cable or line systems, e.g. for disconnecting a section on which a short-circuit, earth fault, or arc discharge has occured
- H02H7/30—Staggered disconnection
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02H—EMERGENCY PROTECTIVE CIRCUIT ARRANGEMENTS
- H02H7/00—Emergency protective circuit arrangements specially adapted for specific types of electric machines or apparatus or for sectionalised protection of cable or line systems, and effecting automatic switching in the event of an undesired change from normal working conditions
- H02H7/06—Emergency protective circuit arrangements specially adapted for specific types of electric machines or apparatus or for sectionalised protection of cable or line systems, and effecting automatic switching in the event of an undesired change from normal working conditions for dynamo-electric generators; for synchronous capacitors
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—ELECTRIC POWER NETWORKS; CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for AC mains or AC distribution networks
- H02J3/12—Arrangements for adjusting voltage in AC networks by changing a characteristic of the network load
- H02J3/14—Arrangements for adjusting voltage in AC networks by changing a characteristic of the network load by switching loads on to, or off from, the networks, e.g. progressively balanced loading
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—ELECTRIC POWER NETWORKS; CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J9/00—Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting
- H02J9/04—Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source
- H02J9/06—Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source with automatic change-over, e.g. UPS systems
- H02J9/066—Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source with automatic change-over, e.g. UPS systems characterised by the use of dynamo-electric machines
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02P—CONTROL OR REGULATION OF ELECTRIC MOTORS, ELECTRIC GENERATORS OR DYNAMO-ELECTRIC CONVERTERS; CONTROLLING TRANSFORMERS, REACTORS OR CHOKE COILS
- H02P9/00—Arrangements for controlling electric generators for the purpose of obtaining a desired output
- H02P9/006—Means for protecting the generator by using control
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02H—EMERGENCY PROTECTIVE CIRCUIT ARRANGEMENTS
- H02H3/00—Emergency protective circuit arrangements for automatic disconnection directly responsive to an undesired change from normal electric working condition with or without subsequent reconnection ; integrated protection
- H02H3/08—Emergency protective circuit arrangements for automatic disconnection directly responsive to an undesired change from normal electric working condition with or without subsequent reconnection ; integrated protection responsive to excess current
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02H—EMERGENCY PROTECTIVE CIRCUIT ARRANGEMENTS
- H02H3/00—Emergency protective circuit arrangements for automatic disconnection directly responsive to an undesired change from normal electric working condition with or without subsequent reconnection ; integrated protection
- H02H3/24—Emergency protective circuit arrangements for automatic disconnection directly responsive to an undesired change from normal electric working condition with or without subsequent reconnection ; integrated protection responsive to undervoltage or no-voltage
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—ELECTRIC POWER NETWORKS; CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J2105/00—Networks for supplying or distributing electric power characterised by their spatial reach or by the load
- H02J2105/50—Networks for supplying or distributing electric power characterised by their spatial reach or by the load for selectively controlling the operation of the loads
- H02J2105/51—Networks for supplying or distributing electric power characterised by their spatial reach or by the load for selectively controlling the operation of the loads according to a condition being electrical
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02B—CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
- Y02B70/00—Technologies for an efficient end-user side electric power management and consumption
- Y02B70/30—Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02B—CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
- Y02B70/00—Technologies for an efficient end-user side electric power management and consumption
- Y02B70/30—Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
- Y02B70/3225—Demand response systems, e.g. load shedding, peak shaving
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P80/00—Climate change mitigation technologies for sector-wide applications
- Y02P80/10—Efficient use of energy, e.g. using compressed air or pressurized fluid as energy carrier
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S20/00—Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
- Y04S20/20—End-user application control systems
- Y04S20/222—Demand response systems, e.g. load shedding, peak shaving
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S20/00—Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
- Y04S20/20—End-user application control systems
- Y04S20/248—UPS systems or standby or emergency generators
Definitions
- the present disclosure relates generally to a power distribution system, and more particularly, to a power distribution system having priority load control.
- Mobile power units are self-contained power modules that can be permanently or temporarily connected to an offboard facility, for example to a home, a hospital, or a factory, to provide primary, supplemental, and emergency backup power.
- Cables extend from a distribution grid of the facility to the mobile power units and are selectively connected to the mobile power units by way of load interruption devices, for example generator breakers. Additional load breakers are commonly associated with different components and/or branches of the facility's distribution grid.
- fault conditions can occur that should be isolated to minimize damage to the facility and to the mobile power units.
- These fault conditions can include over-current conditions and over- or under- voltage conditions caused by open-circuits and short-circuits.
- all breakers including the generator breaker and the load breakers, trip to disconnect the mobile power units from the branches and components of the facility, thereby isolating the open- or short-circuits.
- the '741 publication discloses an electrical protection arrangement for a distribution network that is provided between a power source and multiple electric loads.
- the arrangement comprises multiple fault current flow detectors set in a hierarchy of levels, and a controller configured to actively trip a circuit breaker associated with each fault current flow detector.
- the controller determines, by sequential movement along a fault path, at which level in the hierarchy of levels the circuit breaker should be tripped to isolate parts of the electrical distribution network. Generally, the lowest level within the hierarchy of levels is tripped first to isolate a minimum amount of the electrical distribution network, leaving the remainder of the network operational.
- the electrical protection arrangement of the '741 publication may still be problematic.
- the arrangement of the '741 publication may require specialized and dedicated detectors and controllers that increase a cost of the arrangement.
- the arrangement of the '741 publication may not be applicable and/or provide little benefit to networks that include mobile power units.
- the disclosed power distribution system is directed to overcoming one or more of the problems set forth above and/or other problems of the prior art. Summary
- the power distribution system may include a generator, a first load interruption device associated with the generator, and a load powered by the generator.
- the power distribution system may also include a second load interruption device associated with the load, and a generator controller.
- the generator controller may be configured to control the generator, to determine existence of a fault condition associated with electric service between the generator and the load, and to selectively activate the second load interruption device based on the determination.
- the generator controller may be further configured to determine if activation of the second load interruption device isolated the fault condition, and to selectively activate the first load interruption device when activation of the second load interruption device fails to isolate the fault condition.
- the present disclosure is directed to a generator set.
- the generator set may include an engine and a generator driven by the engine to generate electric power.
- the generator set may also include a generator interruption device, and a connector configured to electrically connect an output of the generator to an external load via a load interruption device.
- the generator set may further include a generator controller in communication with the engine, the generator, the generator interruption device, and the load interruption device.
- the generator controller may be configured to regulate operation of the engine and generator, to determine existence of a fault condition associated with electric service passing through the connector, and to selectively activate the load interruption device based on the determination.
- the generator controller may also be configured to determine if activation of the load interruption device isolated the fault condition, and to selectively activate the generator interruption device when activation of the load interruption device fails to isolate the fault condition.
- the present disclosure is directed to a mobile power unit.
- the mobile power unit may include a frame, an engine connected to the frame, and a generator connected to the frame and driven by the engine.
- the mobile power unit may also include an onboard generator interruption device, a connector configured to connect an output of the generator to an offboard facility load, and a controller connected to the frame and in communication with the engine, the generator, the onboard generator interruption device, and an offboard load interruption device associated with the offboard facility load.
- the controller may be configured to regulate operation of the mobile power unit, to determine existence of a fault condition associated with electric service passing through the connector, and to selectively activate the offboard load interruption device based on the determination.
- the controller may also be configured to determine if activation of the offboard load interruption device isolated the fault condition, and to selectively activate the onboard generator interruption device when activation of the offboard load interruption device fails to isolate the fault condition.
- Fig. 1 is a diagrammatic illustration of an exemplary power distribution system
- Fig. 2 is a flowchart illustrating an exemplary disclosed method for operating the power distribution system of Fig. 1.
- Fig. 1 illustrates an exemplary power distribution system 10 consistent with certain disclosed embodiments.
- Power distribution system 10 may be configured to provide power to a facility 12, for example to a home, a hospital, or a factory.
- power distribution system 10 may provide emergency backup power to one or more loads 14, 16, 18 at facility 12 when power supplied from a utility power grid 20 is interrupted.
- power distribution system 10 may be configured to provide primary power or temporary supplemental power, if desired.
- power distribution system 10 may include a mobile power unit 22 connected to loads 14-18 by way of a power transmission network 24 and a connector 26.
- Loads 14-18 may include any type of power consuming system or device at facility 12 that is located external to and offboard of mobile power unit 22. Loads 14-18 may be arranged in series to receive electric power supplied by utility power grid 20 and mobile power unit 22 and to utilize the electric power to perform specialized tasks. Loads 14-18 may include, for example, lights, motors, heating elements, electronic circuitry, refrigeration devices, air conditioning units, computer servers, industrial machines, etc. In one exemplary embodiment, one or more of loads 14-18 may be more critical than one or more other loads 14- 18 at facility 12. For example, a first load 14 may be more critical than a downstream second load 16, which in turn may be more critical than a third load 18 located at a distal end of transmission network 24.
- Exemplary loads 14 that require or benefit from uninterrupted power may include those found in life-support systems, traffic controllers, computer servers, telecommunication installations, and industrial applications.
- a load interruption device may be associated with each of loads 14-18.
- a first load interruption device 28 may be associated with first load 14; a second load interruption device 30 may be associated with second load 16; and a third load interruption device 32 may be associated with third load 18.
- Each of load interruption devices 28-32 may embody facility interruption devices that are located external to and offboard of mobile power unit 22, and be configured to selectively disconnect their associated loads 14-18 from
- each of load interruption devices 28-32 may embody a mechanical switch or a solid state device such as a breaker that is tripped or opened to disconnect its associated load 14-18 from transmission network 24, and is reset or closed to connects its load 14-18 to transmission network 24. Because of the series arrangement of loads 14-18, tripping of a load interruption device 28-32 located further downstream on transmission network 24 and away from mobile power unit 22 may not substantially affect electric service to loads 14-18 located further upstream on transmission network 24. In contrast, tripping of a load interruption device 28-32 located further upstream on transmission network 24 may disconnect electric service from all of loads 14-18 located further downstream on transmission network 24.
- Transmission network 24 may embody any electric transmission system for distributing electric power generated by utility power grid 20 and mobile power unit 22 to loads 14-18.
- transmission network 24 may include a system of transmission lines, connection equipment (e.g., switch gears, transformers, power relays, and the like), and other suitable devices for distributing electric power across a power grid.
- connection equipment e.g., switch gears, transformers, power relays, and the like
- portions of transmission network 24 may be buried underground and/or run overhead via transmission towers.
- Connector 26 may include any type of device capable of coupling together one or more of mobile power unit 22, utility power grid 20, transmission network 24, and/or loads 14-18 of facility 12.
- connector 26 may include various transfer switches, junction boxes, fuses, or any other components that may be suitable for electrically interconnecting one or more systems.
- Connector 26 may also or alternatively include a voltage transformer configured to reduce or otherwise condition the voltage of power provided by mobile power unit 22 and/or utility power grid 20 to a suitable level for use by conventional consumer devices.
- Mobile power unit 22 may embody a frame-mounted generator set (genset) having components that interact to generate electric power.
- generator set generator set
- mobile power unit 22 may comprise a frame 34, a prime mover 36 mounted to frame 34, and a generator 38 mounted to frame 34 and mechanically coupled to rotate with an output of prime mover 36.
- prime mover 36 is depicted and described as a heat engine, for example, a combustion engine that combusts a mixture of fuel and air to produce the rotating mechanical output.
- prime mover 36 may be any type of combustion engine such as a diesel engine, a gasoline engine, or a gaseous fuel-powered engine.
- Generator 38 may be, for example, an AC induction generator, a permanent-magnet generator, an AC synchronous generator, or a switched-reluctance generator.
- generator 38 may include multiple pairings of poles (not shown), each pairing having three phases arranged on a circumference of a stator (not shown) to produce an alternating current with a frequency of 50 or 60 Hz.
- Electric power produced by generator 38 may be directed offboard mobile power unit 22 to facility 12 by way of transmission network 24 and connector 26.
- a generator interruption device 40 may be associated with generator 38 to selectively disconnect generator 38 from transmission network 24.
- generator interruption device 40 may embody a mechanical switch or a solid state device such as a breaker that is included within and mounted onboard mobile power unit 22.
- Generator interruption device 40 may selectively trip or open to disconnect generator 38 from transmission network 24, and reset or close to connect generator 38 to transmission network 24.
- Mobile power unit 22 may include additional components that facilitate electric power generation in a mobile configuration.
- mobile power unit 22 may include an onboard fuel tank 42 and a cooling system 44.
- Fuel tank 42 may be connected to a lower side of frame 34 and form a portion of a mounting platform for prime mover 36 and generator 38.
- fuel tank 42 may be mounted between side rails (not shown) of frame 34. Fuel tank 42 may hold a supply of fuel for use by prime mover 36.
- Cooling system 44 may also be mounted to frame 34 and include components, for example a radiator, a fan, and associated coolant lines, that direct chilled coolant through prime mover 36 and/or generator 38. These components and others may allow mobile power unit 22 to be moved from one facility 12 to another without significant external support and preparations at each facility 12.
- Mobile power unit 22 may also include a terminal box 46 mounted to frame 34 and housing a controller 48 that is in communication with prime mover 36, generator 38, and load interruption devices 28-32 and 40.
- Controller 48 may embody a single or multiple microprocessors, field programmable gate arrays (FPGAs), digital signal processors (DSPs), etc. that include a means for controlling operations of prime mover 36, generator 38, and load interruption devices 28-32 and 40 in response to various input. Numerous commercially available microprocessors can be configured to perform the functions of controller 48. It should be appreciated that controller 48 could readily embody a microprocessor separate from those that control functions of facility 12, and that controller 48 may communicate with facility microprocessors via datalinks or other methods.
- controller 48 Various other known circuits may be associated with controller 48, including power supply circuitry, signal-conditioning circuitry, actuator driver circuitry (i.e., circuitry powering solenoids, motors, or piezo actuators), communication circuitry, and other appropriate circuitry.
- actuator driver circuitry i.e., circuitry powering solenoids, motors, or piezo actuators
- controller 48 may be configured to monitor performance of power distribution system 10 and responsively regulate operations of load interruption devices 28-32 and 40. For example, controller 48 may monitor a current, a frequency, and/or a voltage characteristic of the electric power provided by mobile power unit 22 through connector 26 to offboard loads 14-18. In response to a quality deviation of supplied power (i.e., a fault condition associated with the current, frequency, and/or voltage of power passing through transmission network 24), controller 48 may selectively trip or reset interruption devices 28-32 and 40 to isolate a cause of the quality deviation.
- a quality deviation of supplied power i.e., a fault condition associated with the current, frequency, and/or voltage of power passing through transmission network 24
- Controller 48 may monitor performance of power distribution system 10 by way of one or more sensors 50, for example current transformers, that are strategically located along portions of transmission network 24. Each sensor 50 may be configured to monitor the current, frequency, and/or voltage of power generated by mobile power unit 22 and directed to offboard loads 14-18, and to generate corresponding signals directed to controller 48.
- sensors 50 for example current transformers, that are strategically located along portions of transmission network 24.
- Each sensor 50 may be configured to monitor the current, frequency, and/or voltage of power generated by mobile power unit 22 and directed to offboard loads 14-18, and to generate corresponding signals directed to controller 48.
- Fig. 2 may illustrate an exemplary operation of power distribution system 10. Fig. 2 will be discussed in more detail in the following section to further illustrate the disclosed concepts.
- the disclosed power distribution system may help to direct electric power having consistent quality from a mobile power unit to offboard loads of a facility in an efficient and cost-effective manner.
- the disclosed power distribution system may monitor quality characteristics of the electric power produced by the mobile power unit and, in response to deviations from desired power characteristics, selectively isolate a cause of the deviations without shutting down the entire power distribution system. By isolating just the cause of the deviations, without shutting down the entire power distribution system, critical loads of the power distribution system may remain operational and less time and resources may be required to correct the cause of the deviations.
- Fig. 2 will be now be discussed in detail.
- prime mover 36 of mobile power unit 22 may be activated to drive generator 38 and produce electric power.
- prime mover 36 may draw and combust fuel from tank 42 to generate a rotational output that drives generator 38 to produce electric power in an amount based on a demand of facility 12.
- the electric power may be directed through generator interruption device 40 to transmission network 24 and loads 14-18 located offboard of mobile power unit 22 (Step 100).
- the electric power from mobile power unit 22 may be directed to loads 14-18 whenever utility power 20 is unavailable or insufficient to meet the power demands of facility 12.
- controller 48 may continuously monitor quality characteristics of the power (i.e., the current, frequency, and/or voltage) via sensor 50 to determine if a fault condition exists. Controller 48 may determine existence of the fault condition (Step 110) based on a comparison of the monitored quality characteristics to desired characteristics stored in memory. If it is determined that the monitored quality characteristics significantly deviate from the desired characteristics, controller 48 may determine that a fault condition exists. Control of power distribution system 10 may loop between steps 100 and 110 until existence of a fault condition is detected.
- quality characteristics of the power i.e., the current, frequency, and/or voltage
- controller 48 may selectively trip load interruption devices 28-32 in an attempt to isolate a cause of the fault condition. Specifically, controller 48 may trip a load interruption device 28-32 that has not recently been tripped and that is associated with the offboard load 14-18 that is least critical and has the lowest corresponding priority (Step 120). As described above, offboard load 14 may be most critical, followed by offboard load 16, with offboard load 18 being least critical and having the lowest corresponding priority. Thus, in the example of Fig. 1, if no other of load interruption devices 28-32 has recently been tripped in response to the existing fault condition, load interruption device 32 may be the first-tripped device.
- controller 48 may check to see if the fault condition is still detectable (Step: 130). That is, controller 48 may compare the electric power quality characteristics monitored by sensor 50 to the desired characteristics and determine if significant deviations still exist. If significant deviations no longer exist (Step 130:No), it can be concluded that the most recent tripping isolated the cause of the fault condition, and diagnosis of the fault condition can be initiated (Step 140) while the remainder of power distribution system 10 remains operational. Because the most recent tripping isolated the fault condition, diagnosis can be limited to just the corresponding offboard load and associated portions of transmission network 24.
- Step 130 determines if any load interruption device 28-32 has not yet been tripped (Step 150). If one or more of load interruption devices 28-32 have not yet been tripped, the most recently-tripped of load interruption devices 28-32 may be reset (Step 160) and control may return to step 120, where the load interruption devices 28- 32 not yet tripped and associated with the most critical offboard load 14-18 may be tripped. Control may continue to loop through steps 120-160 until all load interruption devices 28-32 have been tripped.
- controller 48 may trip generator load interruption device 40 (Step 170). In one example, controller 48 may delay a time period after tripping all of load interruption devices 28-32 and before tripping generator load interruption device 40, if desired. By tripping generator load interruption device 40 after all of load interruption devices 28-32 have already been tripped during previous attempts to isolate the cause of the fault condition, opportunities may be provided for continued use of critical loads not directly associated with or affected by existence of the fault condition.
Landscapes
- Engineering & Computer Science (AREA)
- Power Engineering (AREA)
- Business, Economics & Management (AREA)
- Emergency Management (AREA)
- Supply And Distribution Of Alternating Current (AREA)
- Stand-By Power Supply Arrangements (AREA)
Abstract
Description
Claims
Priority Applications (4)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| AU2011261646A AU2011261646B2 (en) | 2010-06-01 | 2011-05-26 | Power distribution system having priority load control |
| CN201180027288.6A CN102934326B (en) | 2010-06-01 | 2011-05-26 | Power distribution system with priority load control |
| DE112011101884.3T DE112011101884B4 (en) | 2010-06-01 | 2011-05-26 | Power distribution system with priority load control |
| GB1223237.7A GB2503532B (en) | 2010-06-01 | 2011-05-26 | Power distribution system having priority Load Control |
Applications Claiming Priority (4)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| US35032410P | 2010-06-01 | 2010-06-01 | |
| US61/350,324 | 2010-06-01 | ||
| US13/032,212 US8604630B2 (en) | 2010-06-01 | 2011-02-22 | Power distribution system having priority load control |
| US13/032,212 | 2011-02-22 |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| WO2011153063A2 true WO2011153063A2 (en) | 2011-12-08 |
| WO2011153063A3 WO2011153063A3 (en) | 2012-02-16 |
Family
ID=45021461
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| PCT/US2011/038113 Ceased WO2011153063A2 (en) | 2010-06-01 | 2011-05-26 | Power distribution system having priority load control |
Country Status (6)
| Country | Link |
|---|---|
| US (1) | US8604630B2 (en) |
| CN (1) | CN102934326B (en) |
| AU (1) | AU2011261646B2 (en) |
| DE (1) | DE112011101884B4 (en) |
| GB (1) | GB2503532B (en) |
| WO (1) | WO2011153063A2 (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103956825A (en) * | 2014-05-05 | 2014-07-30 | 国网上海市电力公司 | Configuration method for self-provided emergency power supplies |
Families Citing this family (19)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US20130120107A1 (en) * | 2011-11-14 | 2013-05-16 | Wei Song | Methods and systems for programming an electric machine |
| US9281716B2 (en) | 2011-12-20 | 2016-03-08 | Kohler Co. | Generator controller configured for preventing automatic transfer switch from supplying power to the selected load |
| US20130158726A1 (en) | 2011-12-20 | 2013-06-20 | Kohler Co. | System and method for using a network to control multiple power management systems |
| US9431942B2 (en) | 2012-07-02 | 2016-08-30 | Kohler Co. | Generator management system that selectively activates generators based on an operating parameter |
| US9778632B2 (en) | 2012-07-02 | 2017-10-03 | Kohler Co. | Generator management system and method that selectively activate at least one of a plurality of generators in a power generation system |
| US8963349B2 (en) | 2012-07-02 | 2015-02-24 | Kohler, Co. | Generator management system that selectively cuts off fuel to a generator to add a load to a bus |
| US9197098B2 (en) | 2012-07-02 | 2015-11-24 | Kohler Co. | Standby power system that predicts a need to supply power to a load to minimize start time of a generator |
| US9698625B2 (en) | 2012-07-02 | 2017-07-04 | Kohler Co. | Power generation system with anticipatory operation |
| US9368972B2 (en) | 2012-07-27 | 2016-06-14 | Kohler Co. | Generator management system that determines a time to activate and deactivate generators based on the load level |
| US8841787B1 (en) * | 2013-03-15 | 2014-09-23 | Caterpillar Inc. | Generator set adaptive droop control method |
| EP2879258B1 (en) * | 2013-11-28 | 2016-07-13 | Airbus Operations GmbH | Aircraft power management system and method for managing power supply in an aircraft |
| EP2879260B1 (en) | 2013-11-28 | 2017-04-05 | Airbus Operations GmbH | Aircraft power management system and method for managing power supply in an aircraft |
| CN103904739B (en) * | 2014-03-25 | 2017-02-01 | 华为技术有限公司 | Communication power supply circuit and manufacturing method |
| CN105182944A (en) * | 2015-09-30 | 2015-12-23 | 成都飞机工业(集团)有限责任公司 | Full digital solid-state power distribution management system and method for unmanned plane |
| GB2552982B (en) * | 2016-08-17 | 2019-12-11 | Ge Aviat Systems Ltd | Method and apparatus for arranging fuses in a printed circuit board |
| FR3055991B1 (en) * | 2016-09-14 | 2018-09-28 | Continental Automotive France | METHOD OF DETECTING FAILURES |
| US11176806B1 (en) * | 2019-12-06 | 2021-11-16 | Johnson Controls Fire Protection LP | Erratic short-circuit detection |
| IT202000001795A1 (en) * | 2020-01-30 | 2021-07-30 | Carel Ind Spa | ELECTRONIC CONTROLLER |
| GB2602499A (en) * | 2021-01-05 | 2022-07-06 | Eaton Intelligent Power Ltd | Circuit breaker system |
Family Cites Families (25)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US4321645A (en) | 1980-02-26 | 1982-03-23 | Sundstrand Corporation | Differential fault current protection of a multiprocessor controlled electric power generating system |
| US5170310A (en) * | 1990-11-29 | 1992-12-08 | Square D Company | Fail-resistant solid state interruption system |
| US5206776A (en) * | 1990-12-17 | 1993-04-27 | B. A. Bodenheimer And Co., Inc. | Protection system for ac generators |
| US5369356A (en) * | 1991-08-30 | 1994-11-29 | Siemens Energy & Automation, Inc. | Distributed current and voltage sampling function for an electric power monitoring unit |
| EP0970554B1 (en) * | 1997-03-26 | 2003-10-22 | Siemens Aktiengesellschaft | Process and arrangement for selective network monitoring for switchgear |
| US6008971A (en) * | 1998-03-23 | 1999-12-28 | Electric Boat Corporation | Fault protection arrangement for electric power distribution systems |
| JP2000209771A (en) * | 1999-01-08 | 2000-07-28 | Mitsubishi Electric Corp | Protection relay for distribution equipment |
| US6657837B1 (en) * | 1999-12-29 | 2003-12-02 | General Electric Company | Circuit breaker incorporating fault lockout protection |
| US20020080535A1 (en) * | 2000-12-22 | 2002-06-27 | Swindler David L. | Multiple ground fault trip function system and method for same |
| US6798627B2 (en) | 2002-02-05 | 2004-09-28 | Onan Corporation | Engine generator set systems and methods providing load power fault protection |
| US7747356B2 (en) | 2002-02-25 | 2010-06-29 | General Electric Company | Integrated protection, monitoring, and control system |
| US6972936B2 (en) * | 2002-03-29 | 2005-12-06 | Robert Allan Morris | Pre-emptive circuit breaker with arc fault and fault lockout short circuit protection |
| US20090290275A1 (en) | 2005-10-28 | 2009-11-26 | S & C Electric Co. | Fault Protection System and Method for an Electrical Power Distribution System |
| AU2007212381A1 (en) * | 2006-02-06 | 2007-08-16 | Optimal Innovations Inc. | Management of high-availability power infrastructures |
| GB0608773D0 (en) * | 2006-05-04 | 2006-06-14 | Rolls Royce Plc | An electrical generator protection system |
| US7933101B2 (en) | 2007-02-15 | 2011-04-26 | Aka Information Design | Generator power plant protection system and method |
| AU2008224840B2 (en) * | 2007-03-14 | 2013-10-03 | Zonit Structured Solutions, Llc | Smart NEMA outlets and associated networks |
| US7521822B2 (en) * | 2007-05-07 | 2009-04-21 | Cummins Power Generation Ip, Inc. | Protection techniques for a back-up electric power system |
| US7635967B2 (en) * | 2007-07-20 | 2009-12-22 | Eaton Corporation | Generator systems and methods using timing reference signal to control generator synchronization |
| US7566990B2 (en) * | 2007-07-20 | 2009-07-28 | Eaton Corporation | Power systems and methods using an induction generator in cooperation with an uninterruptible power supply |
| US8405944B2 (en) | 2007-10-09 | 2013-03-26 | Schweitzer Engineering Laboratories Inc | Distributed bus differential protection using time-stamped data |
| US7626798B2 (en) | 2008-01-24 | 2009-12-01 | Honeywell International Inc. | Electronic load control unit (ELCU) used as bus tie breaker in electrical power distribution systems |
| US20100019574A1 (en) * | 2008-07-24 | 2010-01-28 | John Baldassarre | Energy management system for auxiliary power source |
| GB0813916D0 (en) | 2008-07-31 | 2008-09-03 | Rolls Royce Plc | A Protection arrangement |
| US8478550B2 (en) * | 2010-07-23 | 2013-07-02 | Caterpillar Inc. | Generator set calibration controller |
-
2011
- 2011-02-22 US US13/032,212 patent/US8604630B2/en active Active
- 2011-05-26 CN CN201180027288.6A patent/CN102934326B/en active Active
- 2011-05-26 DE DE112011101884.3T patent/DE112011101884B4/en active Active
- 2011-05-26 GB GB1223237.7A patent/GB2503532B/en not_active Expired - Fee Related
- 2011-05-26 AU AU2011261646A patent/AU2011261646B2/en active Active
- 2011-05-26 WO PCT/US2011/038113 patent/WO2011153063A2/en not_active Ceased
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103956825A (en) * | 2014-05-05 | 2014-07-30 | 国网上海市电力公司 | Configuration method for self-provided emergency power supplies |
Also Published As
| Publication number | Publication date |
|---|---|
| DE112011101884B4 (en) | 2016-12-29 |
| AU2011261646A1 (en) | 2012-12-13 |
| CN102934326B (en) | 2015-06-10 |
| US8604630B2 (en) | 2013-12-10 |
| AU2011261646A2 (en) | 2013-01-24 |
| WO2011153063A3 (en) | 2012-02-16 |
| US20110291411A1 (en) | 2011-12-01 |
| GB2503532A (en) | 2014-01-01 |
| GB201223237D0 (en) | 2013-02-06 |
| GB2503532B (en) | 2015-07-29 |
| CN102934326A (en) | 2013-02-13 |
| AU2011261646B2 (en) | 2015-02-19 |
| DE112011101884T5 (en) | 2013-03-21 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| AU2011261646B2 (en) | Power distribution system having priority load control | |
| US8519565B2 (en) | Generator set control system | |
| EP2200153B1 (en) | Genset power system having multiple modes of operation | |
| US8358036B2 (en) | Generator set control system | |
| AU2011270891B2 (en) | Control system having user-defined connection criteria | |
| CA2826437C (en) | Voltage control in a doubly-fed induction generator wind turbine system | |
| CN102239320B (en) | There is the electric power system of Instantaneous Control | |
| CN101519116B (en) | Marine power distribution and propulsion systems | |
| EP2690738B1 (en) | Generator management system that determines a time to activate and deactivate generators based on the load level | |
| US10107260B2 (en) | Wind turbine auxiliary circuit control | |
| JP5971716B2 (en) | Distribution board and distributed power supply system | |
| US20090152951A1 (en) | Electric system for providing uninterruptible power | |
| TW200847575A (en) | High efficiency alternative/renewable powered UPS system | |
| WO2015043602A1 (en) | Detecting faults in electricity grids | |
| US20120267896A1 (en) | Network Protection for Power Spot Networks | |
| NL2030568B1 (en) | Electrical device, computing device, vehicle, method and computer program | |
| US20260095048A1 (en) | Backup splice for islanding | |
| CN109842348A (en) | Solar energy pumping system and its operating method | |
| Гончарова et al. | MODERN MEANS OF PROTECTION OF THREE-PHASE ASYNCHRONOUS ELECTRIC MOTORS | |
| Wijayatilake | Application of Cost Effective Solutions for Improving Voltage Sag Immunity of an Automated Cement Manufacturing Plant | |
| Kuz’kin et al. | Control complex of group electric drive | |
| HK1093609B (en) | Electric network monitoring relay with switching output for automatic phase correction |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| WWE | Wipo information: entry into national phase |
Ref document number: 201180027288.6 Country of ref document: CN |
|
| 121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 11790229 Country of ref document: EP Kind code of ref document: A2 |
|
| WWE | Wipo information: entry into national phase |
Ref document number: 112011101884 Country of ref document: DE Ref document number: 1120111018843 Country of ref document: DE |
|
| WWE | Wipo information: entry into national phase |
Ref document number: 10578/DELNP/2012 Country of ref document: IN |
|
| ENP | Entry into the national phase |
Ref document number: 2011261646 Country of ref document: AU Date of ref document: 20110526 Kind code of ref document: A |
|
| ENP | Entry into the national phase |
Ref document number: 1223237 Country of ref document: GB Kind code of ref document: A Free format text: PCT FILING DATE = 20110526 |
|
| WWE | Wipo information: entry into national phase |
Ref document number: 1223237.7 Country of ref document: GB |
|
| 122 | Ep: pct application non-entry in european phase |
Ref document number: 11790229 Country of ref document: EP Kind code of ref document: A2 |