WO2008100645A1 - Method of preparing sea bed for jack up rig deployment - Google Patents

Method of preparing sea bed for jack up rig deployment Download PDF

Info

Publication number
WO2008100645A1
WO2008100645A1 PCT/US2008/050023 US2008050023W WO2008100645A1 WO 2008100645 A1 WO2008100645 A1 WO 2008100645A1 US 2008050023 W US2008050023 W US 2008050023W WO 2008100645 A1 WO2008100645 A1 WO 2008100645A1
Authority
WO
WIPO (PCT)
Prior art keywords
filler material
slurry
conduit
hose
delivered
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Ceased
Application number
PCT/US2008/050023
Other languages
French (fr)
Inventor
Kevin B. Umehr
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Baker Hughes Holdings LLC
Original Assignee
Baker Hughes Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Baker Hughes Inc filed Critical Baker Hughes Inc
Publication of WO2008100645A1 publication Critical patent/WO2008100645A1/en
Anticipated expiration legal-status Critical
Ceased legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/10Placing gravel or light material under water inasmuch as not provided for elsewhere

Definitions

  • FIG. 1 is a schematic view showing the use of the method.
  • FIG. 2 is a section view through lines 2-2 of FIG. 1. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENT
  • FIG. 1 shows a vessel 10 that has sonar equipment schematically illustrated as 12 to allow it to find one or more can holes 14.
  • the vessel 10 has one or more storage tanks 16 for solid material such as beach sand 18 to be delivered as a slurry into the can hole 14.
  • the tank 16 delivers sand by screw conveyor 18 into mix tank 20.
  • the mix tank 20 has a motorized agitator 22 and a seawater feed line 24.
  • One or more slurry pumps 26 deliver the mixed slurry from tank 20 to reeled hose 28.
  • the lower end 30 of hose 28 is blanked off and the slurry 34 escapes radially through equally spaced ports 32 shown circumferentially distributed at 90 degrees in FIG. 2.
  • a positioning system 36 is integrated with the vessel steering system to hold the position of lower end 30 in as steady a position as possible while the slurry 34 is delivered into the can hole 14.
  • the sonar equipment gives feedback as to the sand profile development in the can hole. As the height of the pile increases the lower end 30 is raised up. When the can hole is sufficiently full, the hose 28 is pulled back into the vessel 10 and the jack up is brought into position and the legs extended with confidence that the jack up will be planted on a relatively level seabed 36.

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Drilling And Exploitation, And Mining Machines And Methods (AREA)
  • Underground Or Underwater Handling Of Building Materials (AREA)
  • Measurement Of Levels Of Liquids Or Fluent Solid Materials (AREA)

Abstract

A method of filling seabed holes involves vessels that locate the holes with sonar and one of which has onboard capabilities for storage of a solid and mixing it with liquid to create a pumpable slurry. The slurry is delivered through a coiled line that is fed out overboard and the end of the line is held in position by maintaining the vessel at the desired location during slurry pumping. The hose end can be held fixed or progressively raised during slurry delivery, depending on the starting depth. The hose further has an end feature that counteracts the tendency of the hose to whip from the force created by the pumped slurry exiting the end. The slurry encounters a plate at the hose end with lateral exits preferably equally spaced circumferentially to maintain the hose end in a steady position as the slurry is delivered.

Description

APPLICATION FOR PATENT
Title: Method of Preparing Sea Bed for Jack Up Rig Deployment
Inventor: Kevin B. Umbehr
FIELD OF THE INVENTION
[0001] The field of the invention is preparation of seabed for deployment of jack up rigs in locations previously occupied by another rig where the seabed surface has large depressions that can adversely affect the stability of another rig jacked into the location.
BACKGROUND OF THE INVENTION
[0002] When jack up rigs are deployed, their legs are powered down to the seabed for support. The loads on each leg are high and the base of each leg tends to sink into the seabed making a large depression, hi some cases, a depression can be over 40 feet deep and around a hundred feet across. The bottoms of the legs are generally flat with plates going up from the bottom and around the bottom of the leg. The impression or foot print on the seabed made by each leg is referred to as a "can hole" or a "spud can footprint" after the appearance of a leg lower end.
[0003] Many times a jack up is moved off location and, at a later time, another jack up needs to go back to that location to work on an existing well or another well that will be drilled in the same vicinity. The can holes that are in the vicinity present a stability risk to the subsequent jack up as the stability of the structure is endangered by these huge divots in the seabed that any given leg could enter either partially or totally.
[0004] Past efforts to level the seabed before the arrival of another jack up have been expensive and ineffective, hi one technique a barge laden with sand is brought to the vicinity of the can hole and the sand is simply bulldozed overboard. Currents divert much of the sand pushed off the barge so that it misses the can hole that needs filling, hi shallow depths, generally below 90 feet, an underwater dredge can be used. However, the Army Corps of Engineers has complete control over the use of such devices and their use is not cheap. Furthermore, environmental studies are generally required for dredging work and that has its own set of built in delays to get the required approvals.
[0005] The present invention provides an effective technique for depositing fill material where it is needed. It involves a vessel to bring the material to the site that has onboard facilities to mix solid and liquid into a pumpable slurry. The delivery system involves navigation equipment to position a slurry delivery line in the proper position during the delivery. Features are added to the delivery line exit to stabilize it against reaction from the slurry exit force. The line can be positioned in a single spot somewhat close to the center of the can hole and at about the level of the surrounding sea bed. Alternatively, the line can begin delivery of slurry within the can hole and be raised during delivery until the hole is suitably filled. These and other advantages of the present invention will be more readily appreciated by those skilled in the art from a review of the description of the preferred embodiment and the associated drawing while recognizing that the claims define the full scope of the invention.
SUMMARY OF THE INVENTION
[0006] A method of filling seabed holes involves vessels that locate the holes with sonar and one of which has onboard capabilities for storage of a solid and mixing it with liquid to create a pumpable slurry. The slurry is delivered through a coiled line that is fed out overboard and the end of the line is held in position by maintaining the vessel at the desired location during slurry pumping. The hose end can be held fixed or progressively raised during slurry delivery, depending on the starting depth. The hose further has an end feature that counteracts the tendency of the hose to whip from the force created by the pumped slurry exiting the end. The slurry encounters a plate at the hose end with lateral exits preferably equally spaced circumferentially to maintain the hose end in a steady position as the slurry is delivered.
BRIEF DESCRIPTION OF THE DRAWINGS
[0007] FIG. 1 is a schematic view showing the use of the method; and
[0008] FIG. 2 is a section view through lines 2-2 of FIG. 1. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENT
[0009] FIG. 1 shows a vessel 10 that has sonar equipment schematically illustrated as 12 to allow it to find one or more can holes 14. The vessel 10 has one or more storage tanks 16 for solid material such as beach sand 18 to be delivered as a slurry into the can hole 14. The tank 16 delivers sand by screw conveyor 18 into mix tank 20. The mix tank 20 has a motorized agitator 22 and a seawater feed line 24. One or more slurry pumps 26 deliver the mixed slurry from tank 20 to reeled hose 28. The lower end 30 of hose 28 is blanked off and the slurry 34 escapes radially through equally spaced ports 32 shown circumferentially distributed at 90 degrees in FIG. 2. A positioning system 36 is integrated with the vessel steering system to hold the position of lower end 30 in as steady a position as possible while the slurry 34 is delivered into the can hole 14.
[0010] Those skilled in the art will appreciate that the various can holes in a given location can in series be filled in the same manner. While beach sand is preferred as the solid material for ease of handling and lower wear and tear on the delivery equipment, other solids that can be made into a slurry and pumped can be used as alternates. The lower end is preferably suspended at the average depth 36 of the seabed that surrounds the can hole 14. One reason for this is to avoid a pile of sand that covers the end 30 which in combination with normal movement of the vessel 10 on the waterline 38 could rip the hose 28 or pull its associated reel overboard. However, some can holes are nearly 50 feet deep and over 100 feet in diameter, hi the larger can hole operations it is also possible to start the lower end 30 below the average seabed depth 36 so that it begins literally in the can hole 14. hi this version of the method, the sonar equipment gives feedback as to the sand profile development in the can hole. As the height of the pile increases the lower end 30 is raised up. When the can hole is sufficiently full, the hose 28 is pulled back into the vessel 10 and the jack up is brought into position and the legs extended with confidence that the jack up will be planted on a relatively level seabed 36.
[0011] While openings at 90 degrees are shown in FIG. 2, other spacing and clusters of openings can used instead of single spaced openings. The opening shape can be varied and should be large enough to avoid high back pressure and high velocities that can cause hole opening erosion. [0012] The above description is illustrative of the preferred embodiment and many modifications may be made by those skilled in the art without departing from the invention whose scope is to be determined from the literal and equivalent scope of the claims below.

Claims

I claim:
1. A method of filling depressions in a seabed in preparation for deployment of a rig, comprising: positioning a vessel holding filler material in the vicinity of the depression; delivering the filler material to a location at least adjacent the depression through a conduit.
2. The method of claim 1 , comprising: using a flexible line as said conduit.
3. The method of claim 1, comprising: stabilizing said conduit at its lower end against whipping from the force of filler material exiting said lower end.
4. The method of claim 3, comprising: forcing the filler material to exit laterally from adjacent said lower end.
5. The method of claim 4, comprising: distributing said lateral exits symmetrically.
6. The method of claim 5 , comprising: preventing filler material from exiting straight out the end of said conduit.
7. The method of claim 2, comprising: locating said end of said conduit at a fixed depth with respect to said vessel while said filler material is delivered.
8. The method of claim 2, comprising: locating said end of said conduit at a variable depth with respect to said vessel while said filler material is delivered.
9. The method of claim 8, comprising: raising said end during delivery of said filler material.
10. The method of claim 9, comprising: selecting an initial position of said end within said depression.
11. The method of claim 1, comprising: using sonar to locate said depression.
12. The method of claim 1, comprising: using global positioning to maintain vessel position as said filler material is delivered.
13. The method of claim 1, comprising: using sand as said filler material.
14. The method of claim 13, comprising: slurrying said sand with seawater to deliver it to said conduit.
15. The method of claim 1, comprising: pumping said filler material down said conduit as a slurry.
16. The method of claim 7, comprising: using sand as said filler material.
17. The method of claim 8, comprising: using sand as said filler material.
PCT/US2008/050023 2007-02-15 2008-01-02 Method of preparing sea bed for jack up rig deployment Ceased WO2008100645A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
US11/675,449 2007-02-15
US11/675,449 US20080198685A1 (en) 2007-02-15 2007-02-15 Method of Preparing Sea Bed for Jack Up Rig Deployment

Publications (1)

Publication Number Publication Date
WO2008100645A1 true WO2008100645A1 (en) 2008-08-21

Family

ID=39420626

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/US2008/050023 Ceased WO2008100645A1 (en) 2007-02-15 2008-01-02 Method of preparing sea bed for jack up rig deployment

Country Status (2)

Country Link
US (1) US20080198685A1 (en)
WO (1) WO2008100645A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104537718A (en) * 2014-12-31 2015-04-22 河南理工大学 Large river valley depression filling preprocessing method based on grid DEM

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112323805B (en) * 2020-09-15 2022-01-25 江苏在铭建设工程有限公司 Fixed catheter traction sensor and method of use
JP7582987B2 (en) * 2022-02-21 2024-11-13 東亜建設工業株式会社 GATT ship entry management system and entry management method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB488406A (en) * 1936-12-07 1938-07-06 Frits Rudolf Christiani Improvements in and relating to the depositing of sand and similar material under water
US4266889A (en) * 1979-11-23 1981-05-12 The United States Of America As Represented By The Secretary Of The Navy System for placing freshly mixed concrete on the seafloor
GB2098139A (en) * 1981-05-08 1982-11-17 Aannemers Comb Zinkwerke Vessel with depending pipe for dumping material
NL1014809C2 (en) * 2000-03-31 2001-10-19 Bos & Kalis Baggermaatsch Installation for hydraulic deposit of slurry at location beneath water level comprises slurry feed pipe, at end of which is speed reduction unit allowing slurry to discharge at reduced speed

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3791153A (en) * 1971-02-15 1974-02-12 Naoshi Kubo Method for placing hydraulic concrete

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB488406A (en) * 1936-12-07 1938-07-06 Frits Rudolf Christiani Improvements in and relating to the depositing of sand and similar material under water
US4266889A (en) * 1979-11-23 1981-05-12 The United States Of America As Represented By The Secretary Of The Navy System for placing freshly mixed concrete on the seafloor
GB2098139A (en) * 1981-05-08 1982-11-17 Aannemers Comb Zinkwerke Vessel with depending pipe for dumping material
NL1014809C2 (en) * 2000-03-31 2001-10-19 Bos & Kalis Baggermaatsch Installation for hydraulic deposit of slurry at location beneath water level comprises slurry feed pipe, at end of which is speed reduction unit allowing slurry to discharge at reduced speed

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104537718A (en) * 2014-12-31 2015-04-22 河南理工大学 Large river valley depression filling preprocessing method based on grid DEM
CN104537718B (en) * 2014-12-31 2017-06-16 河南理工大学 Large river basins depression filling preprocess method based on gridded DEM

Also Published As

Publication number Publication date
US20080198685A1 (en) 2008-08-21

Similar Documents

Publication Publication Date Title
KR101743424B1 (en) Methods and apparatus for the installation of columns/piles
US6368021B1 (en) Pile and method for installing same
US6309269B1 (en) Variable buoyancy buoy for mooring mobile offshore drilling units
US4086866A (en) Anchoring devices
JP6912490B2 (en) Submarine support units and methods for providing shallow water drilling terminals
CA2798391C (en) Subsea noise mitigation systems and methods
AU2009334509B2 (en) Rigless abandonment system
US9834907B1 (en) System and method of concurrently trenching, laying and burying underwater pipeline
US6203248B1 (en) Sliding-resistant bottom-founded offshore structures
US12234616B2 (en) Grouting method
US9617810B2 (en) Delivery method and system
JP5502538B2 (en) Pile construction method and pile construction device
EP2388189A1 (en) Spar hull centerwell arrangement
US20080198685A1 (en) Method of Preparing Sea Bed for Jack Up Rig Deployment
NO140995B (en) SLEEVE SYSTEMS FOR USE OF SLUDGE REMOVAL FROM A SEAFOUND AREA
US4069681A (en) Offshore structure for deltaic substrates
KR101672434B1 (en) Floating structure
WO2013053936A1 (en) Seabed anchoring system and method for such a system
EP1881113A2 (en) Suction arrangement for an anchorage in the seabed and method of operation
US4080796A (en) Bottom-supported vessel for performing subaqueous operations and method of placing a bottom-supported vessel in position for performing subaqueous operations
US8888407B2 (en) Method and a device for sealing and/or securing a borehole
US20150060137A1 (en) Tender Barge for Drillship Operating in Environmentally Sensitive Areas
WO2014202948A1 (en) Gravity base for a marine structure
OA11409A (en) Rov installed suction piles.
JP2000355960A (en) Intake method for deep ocean water

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 08713416

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 08713416

Country of ref document: EP

Kind code of ref document: A1