WO2006084367A2 - Bracket and bridging member for metal stud wall - Google Patents
Bracket and bridging member for metal stud wall Download PDFInfo
- Publication number
- WO2006084367A2 WO2006084367A2 PCT/CA2006/000188 CA2006000188W WO2006084367A2 WO 2006084367 A2 WO2006084367 A2 WO 2006084367A2 CA 2006000188 W CA2006000188 W CA 2006000188W WO 2006084367 A2 WO2006084367 A2 WO 2006084367A2
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- bracket
- stud
- bridging member
- metal
- metal stud
- Prior art date
Links
- 239000002184 metal Substances 0.000 title claims abstract description 67
- 238000005192 partition Methods 0.000 claims abstract description 8
- 238000009434 installation Methods 0.000 description 6
- 238000005452 bending Methods 0.000 description 3
- 239000000463 material Substances 0.000 description 2
- 238000009429 electrical wiring Methods 0.000 description 1
- 230000002452 interceptive effect Effects 0.000 description 1
- 238000009428 plumbing Methods 0.000 description 1
- 238000007493 shaping process Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/74—Removable non-load-bearing partitions; Partitions with a free upper edge
- E04B2/76—Removable non-load-bearing partitions; Partitions with a free upper edge with framework or posts of metal
- E04B2/762—Cross connections
- E04B2/763—Cross connections with one continuous profile, the perpendicular one passing continuously through the first one
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/74—Removable non-load-bearing partitions; Partitions with a free upper edge
- E04B2/7407—Removable non-load-bearing partitions; Partitions with a free upper edge assembled using frames with infill panels or coverings only; made-up of panels and a support structure incorporating posts
- E04B2/7453—Removable non-load-bearing partitions; Partitions with a free upper edge assembled using frames with infill panels or coverings only; made-up of panels and a support structure incorporating posts with panels and support posts, extending from floor to ceiling
- E04B2/7457—Removable non-load-bearing partitions; Partitions with a free upper edge assembled using frames with infill panels or coverings only; made-up of panels and a support structure incorporating posts with panels and support posts, extending from floor to ceiling with wallboards attached to the outer faces of the posts, parallel to the partition
Definitions
- TITLE BRACKET AND BRIDGING MEMBER FOR METAL STUD WALL
- the present invention relates to a bracket for attaching bridging to the studs of a metal stud wall, in particular a bracket which is s-impie- and quick to install on either side of the web of the metal stud.
- the present invention also relates to bridging members for metal stud walls having openings therein at regular spaced intervals to aid in spacing of studs in the stud wall .
- Metal studs for use in constructing partition walls are becoming more prevalent .
- the metal studs have a generally C shaped cross section and are utilized in a manner similar to wooden studs for constructing partition walls . .
- the metal studs are typically arranged vertically and tied together at the top and bottom by U shaped channel members which act as top and bottom plates for the stud wall . Stud walls which are subjected to wind and or axial loads such as is found if the stud wall forms the exterior wall or is a load bearing wall, require lateral support to provide resistance to rotation and minor axis bending under wind and axial loads .
- the lateral support for the metal stud walls is generally provided by installing bridging members which tie the metal studs together at points intermediate the ends of the studs .
- These bridging members may be either metal strapping attached to the outside flanges of the studs or may be internal bridging members installed through openings provided in the web in the metal stud .
- the bridging members are physically tied to the metal stud.
- L shaped brackets are provided to transfer the support provided by the interior bridging members to the edges of the metal studs .
- the present invention provides in one aspect for a bracket for use in a metal stud wall having internal bridging members for tying the metal studs and bridging members together.
- the bracket comprises an L shaped bracket having a leg for overlying the bridging member j oined to an upright for overlying the metal stud.
- the outside corners of the leg and upright of the L shaped bracket are truncated so that the bracket may be inserted within the channel of a metal stud and rotated to the proper position for attaching to the bridging member and metal stud.
- a bridging member for a metal stud partition wall the bridging member being provided with openings at regular intervals along its length thereof to aid in spacing of the studs in the metal stud partition wall .
- an L shaped the bracket having a leg for overlaying the bridging member and an upright for overlaying the metal stud.
- the bracket has a downwardly extending tab at the junction of the leg and the upright sized to fit within the opening of the bridging member .
- Figure 1 is a perspective view of a typical metal stud wall
- Figure 2 is a perspective view of an embodiment of the bracket of the present invention.
- Figure 3 is a perspective view of the bracket of Figure 2 installed on the metal stud and bridging member in one orientation
- Figure 4 is a perspective view of the bracket of Figure 2 installed on the metal stud and bridging member in a second orientation where the studs may not be in the normal spacing of 12" , 16" or 24" on center;
- Figure 5 is a cross section view of the bracket of Figure 2 installed in the orientation according ' to figure 3;
- Figure 6 is a cross section view of the bracket of Figure 2 installed in the orientation in accordance with figure 4 ;
- Figure 7 is a perspective view illustrating the installation of the bracket of Figure 2 within the channel of the metal stud;
- Figure 8 is a side elevation view of the bracket of Figure 2 being installed within the channel of the metal stud;
- Figure 9 is a cross section view of the bracket of Figure 2 installed in the orientation in accordance with figure 8.
- Figure 1 illustrates a typical metal stud wall generally indicated by the number 10.
- Stud wall 10 is constructed of a series of parallel spaced apart metal studs 12 held in position by a bottom track 14 and a top track 16. ;
- Metal studs 12 are connected to the bottom track 14 and top track 16 by the use of suitable screws 18.
- Metal studs 12 are provided with first generally circular openings 20 which are used for running utility services such as electrical wiring or plumbing pipes there through .
- the metal studs 12 are also provided with second openings 22 which are used to hold suitable bridging members 24. Bridging members 24 are tied to the metal studs 12 by brackets 26 as will be described herein below.
- second openings 22 are provided at a regular spaced interval along the length of the stud 12.
- the spacing between the openings 22 is generally on the order of between about 2 and 4 feet .
- two such openings 22 are provided on each stud 12 equally spaced to provide a spacing of about two and one third feet between each of the openings 22.
- a 10 ft . stud 12 would generally be provided with two such openings 22 to provide a spacing of three and one-third feet between the openings 22.
- Longer studs 12 such as 12 to 16 ft . studs would be provided with three or four such openings 22 to allow the proper spacing for the bridging numbers 24 to provide the support for the metal stud wall 10.
- the shape of the openings 22 can vary depending upon the manufacturer of the metal studs 12.
- One common shape utilized is a rectangular opening with an arched top 28 such as is illustrated in the figures .
- Other shapes including rectangular openings with a peaked top and in some cases a peaked bottom are also known .
- the common feature is that the opening 22 should allow the bridging member 24 to pass through the opening 22 and be placed in the proper position at the bottom of the opening 22 to provide for the support for the stud wall 10.
- Figure 2 illustrates in closer detail the connection between the metal stud 12 and the bridging member 24 utilizing a preferred embodiment of a bracket 26 according to the present invention .
- Metal stud 12 is generally C shaped having flanges 30 connected along one edge by a web 32 and having inwardly projecting extensions 34 along the second edge .
- the opening 22 as described above is generally rectangular with a rounded over top portion 28.
- Bridging member 24 is generally U- shaped having a width approximately equal to the width of the opening 22. The bridging member 24 is installed in the openings 22 in the studs 12 by inserting the bridging member 24 vertically in the openings 22 and then rotating the bridging member 24 downwardly until it snaps into the proper position in the opening 22.
- Bracket 26 is L-shaped having a leg 36 adapted in one orientation to rest against the 'bridging member 24 and an upright 38 adapted to rest against the web 32 of the stud 12.
- the L-shaped bracket transfers the support of the bridging member 24 to the metal stud 12.
- the length of the L- shaped bracket 24 should be sufficient to span the majority of the web of the metal stud 12.
- bridging member 24 is provided with slots 40 along the length thereof at regular spaced intervals .
- the spacing between slots 40 in the bridging member 24 is preferably 4 inches to accommodate the various spacing for the studs in the stud wall .
- bracket 26 is provided with a downwardly extending member such as the tab 42 at the junction of the upright 38 and leg 36. The tab 42 is sized to fit within the opening 40 of the bridging member 24.
- the tab 42 is preferably formed by striking out the tab 42 from the metal forming the leg 36 and bending the tab 42 to lie in the place of the upright 38.
- the tab in order to provide a tight fit between the tab 42 and the opening 40 , the tab is provided with edges which are bent inwardly to provide a depth to the tab 42 greater than the thickness of the metal .
- the bridging member 24 is attached to the stud 12 as described above .
- the bracket 26 is attached to the bridging member 24 and stud 12 as follows .
- the bracket 26 is placed over the bridging member 24 such that the downwardly extending tab 42 is inserted into the opening 40 of the bridging member 24.
- the stud 12 is then positioned such that the web 32 of the stud lies against the upright 38 of the bracket 26. In this manner the spacing of the studs 12 in the stud wall 10 is standard and uniform.
- the bracket 26 is then attached to the bridging member 24 and the web 32 of the stud 12 by suitable fasteners such as screws 44.
- predrilled holes 46 are provided in the upright 38 and leg 36 of the bracket 26 as illustrated in the figures .
- Two holes 46 are provided near the outer edges of the bracket 26 that can be used to attach the bracket 26 to the web 32 of the stud 12.
- Two inner holes 46 are provided to allow the bracket 26 to be attached to the bridging member 24.
- Figure 4 illustrates an alternative arrangement for connecting the bridging member 26 to the stud 12 utilizing a bracket 26 of the present invention .
- This arrangement is used in situations where the bridging member 24 is not provided with the openings 40 or where, owing to the spacing of the studs 12 to frame a particular arrangement in the stud wall 10, the spacing of the stud 12 does not line up with the opening 40 of the bridging member 24.
- the bracket 26 is reversed such that what was the upright 38 is placed against the bridging member 24 and what was the leg 36 is placed against the web 32 of the stud 12.
- the downwardly extending tab 42 lies along the upper surface of the bridging member 24 within the opening 22 and does not interfere with the connection of the bracket to the bridging member 24 or the stud 12.
- Bracket 26 is preferably provided with truncated outer corners 50 of the upright 38 and leg 36. In the embodiment illustrated in the figures, these truncated corners 50 are accomplished by cutting the corners off at a 45 ° angle . However, other arrangements would be immediately apparent to those skilled in the art .
- the provision of the truncated corners 50 allows the bracket 26 to be inserted within the channel as illustrated in Figure 7 and rotated into the proper position as illustrated in Figure 8.
- bracket 26 is in the proper position then it is easily attached to the bridging member 24 and stud 12 in the manner as described above .
- the distance from the corner where the upright and the leg j oin and the outside corner on the opposite side of the bracket is significantly greater than the inner width of the stud and therefore the bracket cannot be rotated into position as the bracket of the present invention can .
- These prior art brackets were required to be installed by placing it at an open end of the stud and sliding them down the interior of the channel of the stud .
- the provision of the truncated corners allows a depth of the leg 36 and upright 38 of the bracket 26 to be greater than the distance between the web 32 and extensions 34 of the stud 12. This results in a larger load bearing surface in contact with the bridging member 24 , thereby increasing the load transferring ability of the bracket 26.
- Prior art brackets installed in the channel of the stud had to have a leg depth less than the width of the channel in order to fit within the channel .
- the present invention allows for much easier and quicker installation of metal stud partition walls in which studs are tied together by intermediate bridging members .
- the bridging members are provided with an opening at regularly spaced intervals , preferably 4" on center and the brackets which tie the bridging members and metal studs together are provided with tabs which insert into the openings of the bridging members and thereby properly locate the stud through the proper spacing . This allows the installer to quickly install the studs of the metal wall at the proper spacing and tie the studs together .
- the use of the pre-punched openings of the bridging members to which the tabs of the brackets are inserted also aids in centering the brackets on the bridging member and the stud. This results in a stronger transfer of load bearing capability from the bridging member to the stud.
- the ' bracket may be made wider, just slightly less than the width of the stud, which also results in better transfer of load bearing capability.
- the bracket is also centered in the affixed position by means of the tab being inserted into the slot, there is no possibility of portions of the bracket extending past the edge of the stud and interfering with the installation of the finish surface material . With manually centered brackets of the prior art, if the installer was not careful, the bracket could be installed off center and interfere with the subsequent installation of the surface finish material .
- the bracket for tying a bridging member to a metal stud is provided with truncated outside corners such that the bracket may be easily installed within the channel of the stud by placing it vertically within the channel and rotating it into the proper position to overly the bridging member and the web of the stud.
- This also makes installation of the metal stud wall quicker and easier as it is not necessary for the installer to slide the bracket down the channel of the stud from one end or the other .
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Joining Of Building Structures In Genera (AREA)
- Load-Bearing And Curtain Walls (AREA)
Abstract
A bracket for use in a metal stud wall having internal bridging members for tying the metal studs and bridging members together. The bracket comprises an L shaped bracket having a leg for overlying the bridging member joined to an upright for overlying the metal stud. The outside corners of the leg and upright of the L shaped bracket are truncated so that the bracket may be inserted within the channel of a metal stud and rotated to the proper position for attaching to the bridging member and metal stud. In an aspect of the invention, the bridging member being provided with openings at regular intervals along its length thereof to aid in spacing of the studs in the metal stud partition wall. The bracket is provided with a downwardly extending tab at the junction of the leg and the upright sized to fit within an opening of the bridging member.
Description
TITLE : BRACKET AND BRIDGING MEMBER FOR METAL STUD WALL
FIELD OF THE INVENTION
The present invention relates to a bracket for attaching bridging to the studs of a metal stud wall, in particular a bracket which is s-impie- and quick to install on either side of the web of the metal stud. The present invention also relates to bridging members for metal stud walls having openings therein at regular spaced intervals to aid in spacing of studs in the stud wall .
BACKGROUND OF THE INVENTION
Metal studs for use in constructing partition walls are becoming more prevalent . The metal studs have a generally C shaped cross section and are utilized in a manner similar to wooden studs for constructing partition walls . . The metal studs are typically arranged vertically and tied together at the top and bottom by U shaped channel members which act as top and bottom plates for the stud wall . Stud walls which are subjected to wind and or axial loads such as is found if the stud wall forms the exterior wall or is a load bearing wall, require lateral support to provide resistance to rotation and minor axis bending under wind and axial loads .
The lateral support for the metal stud walls is generally provided by installing bridging members which tie the metal studs together at points intermediate the ends of the studs . These bridging members may be either metal strapping attached to the outside flanges of the studs or may be internal bridging members installed through
openings provided in the web in the metal stud . In order to transfer the support provided by the internal bridging members to the metal studs, the bridging members are physically tied to the metal stud. In most installations, L shaped brackets are provided to transfer the support provided by the interior bridging members to the edges of the metal studs . These L shaped brackets are attached to the metal stud "and "the 'bridging-member ~ " with the leg of the bracket being fastened to the interior bridging member and the upright of the L shaped bracket being attached to the metal stud. Where the bracket is installed on the outside of the web of the stud, it is a simple matter for the installer to lay the bracket in place and attach it to the bridging member and to the stud. If for some reason however, the bracket must be installed on the interior of the stud within the C channel, the bracket must be inserted into the interior of the stud at the top or bottom and slid to the proper position . As this must be accomplished before the stud is attached to the top track, it can increase the erection time necessary for the wall especially if the installer has to disconnect the stud from one of the tracks in order to install the bracket . There thus remains a need for a simple to install bracket for bridging members and metal studs which can be easily installed on either side of the web of the stud.
SUMMARY OF THE INVENTION
The present invention provides in one aspect for a bracket for use in a metal stud wall having internal bridging members for tying the metal studs and bridging members together. The bracket comprises an L shaped bracket having a leg for overlying the bridging member
j oined to an upright for overlying the metal stud. The outside corners of the leg and upright of the L shaped bracket are truncated so that the bracket may be inserted within the channel of a metal stud and rotated to the proper position for attaching to the bridging member and metal stud.
In an aspect of the invention, there is provided a bridging member for a metal stud partition wall, the bridging member being provided with openings at regular intervals along its length thereof to aid in spacing of the studs in the metal stud partition wall .
In another aspect of the invention, an L shaped the bracket is provided having a leg for overlaying the bridging member and an upright for overlaying the metal stud. The bracket has a downwardly extending tab at the junction of the leg and the upright sized to fit within the opening of the bridging member .
BRIEF DESCRIPTION OF THE DRAWINGS
Preferred embodiments of the present invention are illustrated in the attached, drawings in which:
Figure 1 is a perspective view of a typical metal stud wall;
Figure 2 is a perspective view of an embodiment of the bracket of the present invention;
Figure 3 is a perspective view of the bracket of Figure 2 installed on the metal stud and bridging member in one orientation;
Figure 4 is a perspective view of the bracket of Figure 2 installed on the metal stud and bridging member in a second orientation where the studs may not be in the normal spacing of 12" , 16" or 24" on center;
Figure 5 is a cross section view of the bracket of Figure 2 installed in the orientation according 'to figure 3;
Figure 6 is a cross section view of the bracket of Figure 2 installed in the orientation in accordance with figure 4 ;
Figure 7 is a perspective view illustrating the installation of the bracket of Figure 2 within the channel of the metal stud;
Figure 8 is a side elevation view of the bracket of Figure 2 being installed within the channel of the metal stud; and
Figure 9 is a cross section view of the bracket of Figure 2 installed in the orientation in accordance with figure 8.
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
Figure 1 illustrates a typical metal stud wall generally indicated by the number 10. Stud wall 10 is constructed of a series of parallel spaced apart metal studs 12 held in position by a bottom track 14 and a top track 16. ; Metal studs 12 are connected to the bottom track 14 and top track 16 by the use of suitable screws 18. Metal studs 12 are provided with first generally circular openings 20 which are used for running utility services
such as electrical wiring or plumbing pipes there through . The metal studs 12 are also provided with second openings 22 which are used to hold suitable bridging members 24. Bridging members 24 are tied to the metal studs 12 by brackets 26 as will be described herein below. Typically, second openings 22 are provided at a regular spaced interval along the length of the stud 12. The spacing between the openings 22 is generally on the order of between about 2 and 4 feet . Thus for an eight- foot metal stud 12 two such openings 22 are provided on each stud 12 equally spaced to provide a spacing of about two and one third feet between each of the openings 22. Similarly a 10 ft . stud 12 would generally be provided with two such openings 22 to provide a spacing of three and one-third feet between the openings 22. Longer studs 12 such as 12 to 16 ft . studs would be provided with three or four such openings 22 to allow the proper spacing for the bridging numbers 24 to provide the support for the metal stud wall 10.
The shape of the openings 22 can vary depending upon the manufacturer of the metal studs 12. One common shape utilized is a rectangular opening with an arched top 28 such as is illustrated in the figures . Other shapes including rectangular openings with a peaked top and in some cases a peaked bottom are also known . Irrespective of the shaping of the opening 22 , the common feature is that the opening 22 should allow the bridging member 24 to pass through the opening 22 and be placed in the proper position at the bottom of the opening 22 to provide for the support for the stud wall 10.
Figure 2 illustrates in closer detail the connection between the metal stud 12 and the bridging member 24 utilizing a preferred embodiment of a bracket 26 according to the present invention . Metal stud 12 is generally C shaped having flanges 30 connected along one edge by a web 32 and having inwardly projecting
extensions 34 along the second edge . The opening 22 as described above is generally rectangular with a rounded over top portion 28. Bridging member 24 is generally U- shaped having a width approximately equal to the width of the opening 22. The bridging member 24 is installed in the openings 22 in the studs 12 by inserting the bridging member 24 vertically in the openings 22 and then rotating the bridging member 24 downwardly until it snaps into the proper position in the opening 22.
Once the bridging member 24 is installed within the opening 22, the brackets 26 for tying the bridging member 24 and metal stud 12 together may be installed. The bracket 26 provides for a secure connection between the metal stud 12 and bridging member 24. Bracket 26 transfers the support of the bridging member 24 across the web 32 of the stud 12 to provide for good support against rotation and axial bending of the metal stud 12. A preferred embodiment of the bracket 26 of the present invention is illustrated in figures 1 through 9. Bracket 26 is L-shaped having a leg 36 adapted in one orientation to rest against the 'bridging member 24 and an upright 38 adapted to rest against the web 32 of the stud 12. The L-shaped bracket transfers the support of the bridging member 24 to the metal stud 12. The length of the L- shaped bracket 24 should be sufficient to span the majority of the web of the metal stud 12.
In a first preferred embodiment illustrated in the figures , bridging member 24 is provided with slots 40 along the length thereof at regular spaced intervals . As the typical spacing of studs in a stud wall is 12, 16 or 24 inches on center, most preferably 16 inches on center, the spacing between slots 40 in the bridging member 24 is preferably 4 inches to accommodate the various spacing for the studs in the stud wall .
In the preferred embodiment illustrated in the figures , bracket 26 is provided with a downwardly extending member such as the tab 42 at the junction of the upright 38 and leg 36. The tab 42 is sized to fit within the opening 40 of the bridging member 24. The tab 42 is preferably formed by striking out the tab 42 from the metal forming the leg 36 and bending the tab 42 to lie in the place of the upright 38. In forming the opening 40 , it may be preferred to provide an opening of a width greater than the thickness of the metal of the bridging member 24 as the die for striking out the opening 40 will be sturdier and have a longer life . In these situations, in order to provide a tight fit between the tab 42 and the opening 40 , the tab is provided with edges which are bent inwardly to provide a depth to the tab 42 greater than the thickness of the metal .
As illustrated in Figures 2 and 3, the bridging member 24 is attached to the stud 12 as described above . The bracket 26 is attached to the bridging member 24 and stud 12 as follows . The bracket 26 is placed over the bridging member 24 such that the downwardly extending tab 42 is inserted into the opening 40 of the bridging member 24. The stud 12 is then positioned such that the web 32 of the stud lies against the upright 38 of the bracket 26. In this manner the spacing of the studs 12 in the stud wall 10 is standard and uniform. The bracket 26 is then attached to the bridging member 24 and the web 32 of the stud 12 by suitable fasteners such as screws 44. In order to make the attachment easier, predrilled holes 46 are provided in the upright 38 and leg 36 of the bracket 26 as illustrated in the figures . Preferably four such holes 46 provided in each of the upright 38 and leg 36. Two holes 46 are provided near the outer edges of the bracket 26 that can be used to attach the bracket 26 to the web 32 of the stud 12. Two inner holes 46 are provided to allow the bracket 26 to be attached to the bridging member 24.
Figure 4 illustrates an alternative arrangement for connecting the bridging member 26 to the stud 12 utilizing a bracket 26 of the present invention . This arrangement is used in situations where the bridging member 24 is not provided with the openings 40 or where, owing to the spacing of the studs 12 to frame a particular arrangement in the stud wall 10, the spacing of the stud 12 does not line up with the opening 40 of the bridging member 24. In this situation, the bracket 26 is reversed such that what was the upright 38 is placed against the bridging member 24 and what was the leg 36 is placed against the web 32 of the stud 12. The downwardly extending tab 42 lies along the upper surface of the bridging member 24 within the opening 22 and does not interfere with the connection of the bracket to the bridging member 24 or the stud 12.
There are situations where it may be required to install the bracket within the channel of the stud 12 rather than against the outer face of the web 32. With a preferred embodiment of the bracket 26 of the present invention this is easily accomplished as illustrated in Figures 7 to 9. Bracket 26 is preferably provided with truncated outer corners 50 of the upright 38 and leg 36. In the embodiment illustrated in the figures, these truncated corners 50 are accomplished by cutting the corners off at a 45 ° angle . However, other arrangements would be immediately apparent to those skilled in the art . The provision of the truncated corners 50 allows the bracket 26 to be inserted within the channel as illustrated in Figure 7 and rotated into the proper position as illustrated in Figure 8. This is accomplished as the distance between the corner 52 where the upright 38 and leg 36 join and the truncated corner 50 of the upright 38 or leg 36 on the opposite side is less than or equal to the inner width of the channel of the stud 12. Once the bracket 26 is in the proper position then it is easily
attached to the bridging member 24 and stud 12 in the manner as described above . In prior art arrangements , the distance from the corner where the upright and the leg j oin and the outside corner on the opposite side of the bracket is significantly greater than the inner width of the stud and therefore the bracket cannot be rotated into position as the bracket of the present invention can . These prior art brackets were required to be installed by placing it at an open end of the stud and sliding them down the interior of the channel of the stud .
As illustrated in Figure 9, the provision of the truncated corners allows a depth of the leg 36 and upright 38 of the bracket 26 to be greater than the distance between the web 32 and extensions 34 of the stud 12. This results in a larger load bearing surface in contact with the bridging member 24 , thereby increasing the load transferring ability of the bracket 26. Prior art brackets installed in the channel of the stud, had to have a leg depth less than the width of the channel in order to fit within the channel .
The present invention allows for much easier and quicker installation of metal stud partition walls in which studs are tied together by intermediate bridging members . In one aspect, the bridging members are provided with an opening at regularly spaced intervals , preferably 4" on center and the brackets which tie the bridging members and metal studs together are provided with tabs which insert into the openings of the bridging members and thereby properly locate the stud through the proper spacing . This allows the installer to quickly install the studs of the metal wall at the proper spacing and tie the studs together .
In addition, the use of the pre-punched openings of the bridging members to which the tabs of the brackets are
inserted also aids in centering the brackets on the bridging member and the stud. This results in a stronger transfer of load bearing capability from the bridging member to the stud. In addition, as the bracket is centered on the stud, the 'bracket may be made wider, just slightly less than the width of the stud, which also results in better transfer of load bearing capability. As the bracket is also centered in the affixed position by means of the tab being inserted into the slot, there is no possibility of portions of the bracket extending past the edge of the stud and interfering with the installation of the finish surface material . With manually centered brackets of the prior art, if the installer was not careful, the bracket could be installed off center and interfere with the subsequent installation of the surface finish material .
In the second aspect of the invention, the bracket for tying a bridging member to a metal stud is provided with truncated outside corners such that the bracket may be easily installed within the channel of the stud by placing it vertically within the channel and rotating it into the proper position to overly the bridging member and the web of the stud. This also makes installation of the metal stud wall quicker and easier as it is not necessary for the installer to slide the bracket down the channel of the stud from one end or the other .
Although various preferred embodiments of the present invention have been described herein in detail, it will be appreciated by those of skill in the art that variations may be made thereto without departing from the spirit of the invention or the scope of the appended claims .
Claims
1. A bracket for use in a metal stud wall having internal bridging members for tying the metal studs and bridging members together, the bracket comprises an L shaped bracket having a leg for overlying the bridging member j oined to an upright for overlying the metal stud, the outside corners of the leg and upright of the L shaped bracket being truncated so that the bracket may be inserted within the channel of a metal stud and rotated to the proper position for attaching to the bridging member and metal stud.
2. A bridging member for a metal stud partition wall, the bridging member being provided with openings at regular intervals along its length thereof to aid in spacing of the studs in the metal stud partition wall .
3. A bracket according to claim 1 wherein the bracket is provided with a downwardly extending tab at the junction of the leg and the upright sized to fit within the opening of the bridging member of claim 2.
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CA2,496,961 | 2005-02-11 | ||
CA2496961A CA2496961C (en) | 2005-02-11 | 2005-02-11 | Bracket and bridging member for metal stud wall |
Publications (2)
Publication Number | Publication Date |
---|---|
WO2006084367A2 true WO2006084367A2 (en) | 2006-08-17 |
WO2006084367A3 WO2006084367A3 (en) | 2006-09-28 |
Family
ID=36791477
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
PCT/CA2006/000188 WO2006084367A2 (en) | 2005-02-11 | 2006-02-13 | Bracket and bridging member for metal stud wall |
Country Status (3)
Country | Link |
---|---|
US (2) | US8011160B2 (en) |
CA (1) | CA2496961C (en) |
WO (1) | WO2006084367A2 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP2395168B1 (en) * | 2010-06-08 | 2015-05-06 | Mr. Leendert Weernink | Method for manufacturing a frame, assembly and upright |
Families Citing this family (49)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US9777479B2 (en) * | 2003-09-05 | 2017-10-03 | Bailey Metal Products Limited | Framing member having reinforced end |
CA2505306C (en) * | 2005-04-26 | 2014-06-17 | Bailey Metal Products Limited | Metal stud with bendable tab for bridging member support |
US7429023B2 (en) * | 2006-09-29 | 2008-09-30 | Morrow Michael L | Deck support |
NL1033867C2 (en) * | 2007-05-18 | 2008-11-20 | Bruinekool Yacht Support & Ind | Floor construction and method. |
US10422136B2 (en) | 2017-02-13 | 2019-09-24 | Dennis LeBlang | Metal framing connections between members |
US20200018063A1 (en) * | 2008-09-08 | 2020-01-16 | Dennis LeBlang | Fire shield connector |
US20230093777A9 (en) * | 2009-06-22 | 2023-03-23 | Dennis LeBlang | Metal framing self-locking connectors |
US10364566B1 (en) | 2016-10-17 | 2019-07-30 | Dennis LeBlang | Self-locking metal framing connections using punched out tabs, ledges and notches |
US11060281B2 (en) | 2016-04-04 | 2021-07-13 | Dennis LeBlang | Spacer braces in tandem for walls, joists and trusses |
US20190309506A1 (en) * | 2018-11-22 | 2019-10-10 | Dennis LeBlang | Fire shield connector and plate |
US20190323226A1 (en) * | 2015-11-19 | 2019-10-24 | Dennis William LeBlang | Bulge notch connectors |
US20110107693A1 (en) * | 2009-10-06 | 2011-05-12 | Haskell Guy M | High efficiency building system with reduced costs and increased thermal performance |
JP5814003B2 (en) * | 2011-06-13 | 2015-11-17 | 積水ハウス株式会社 | Connecting bracket, frame provided with the same, and building using the same |
US9109361B2 (en) | 2011-10-26 | 2015-08-18 | Simpson Strong-Tie Company, Inc. | Bracing bridging member |
US8590255B2 (en) | 2011-10-26 | 2013-11-26 | Larry Randall Daudet | Bridging connector |
US9290928B2 (en) * | 2011-12-15 | 2016-03-22 | James Alan Klein | Header and sill connector clips and related wall assemblies |
US8882068B2 (en) * | 2012-02-26 | 2014-11-11 | Troy A. McGee | Boat transducer mounting apparatus |
US9849497B2 (en) | 2013-03-13 | 2017-12-26 | Simpson Strong-Tie Company Inc. | Teardrop and offset notch bridging connector |
US11008753B2 (en) | 2013-03-13 | 2021-05-18 | Simpson Strong-Tie Company, Inc. | Corrugated bridging member |
USD692746S1 (en) | 2013-03-13 | 2013-11-05 | Clarkwestern Dietrich Building Systems Llc | Bridging clip |
US9732520B2 (en) | 2013-03-17 | 2017-08-15 | Simpson Strong-Tie Company, Inc. | Inverted bridging connector |
US20150060381A1 (en) * | 2013-08-27 | 2015-03-05 | Robert M Consaul | Universal adjustable pallet rack load stop assembly |
US8863438B1 (en) | 2013-10-29 | 2014-10-21 | Floating Door, LLC | Apparatus and method of construction of an overhead door |
US9016024B1 (en) | 2013-11-27 | 2015-04-28 | Simpson Strong-Tie Company | Steel framing clip |
USD730545S1 (en) | 2013-12-30 | 2015-05-26 | Simpson Strong-Tie Company | Joist and rafter connector |
USD732708S1 (en) | 2013-12-30 | 2015-06-23 | Simpson Strong-Tie Company | Flared joist and rafter connector |
US9091056B2 (en) * | 2013-12-31 | 2015-07-28 | Simpson Strong-Tie Company, Inc. | Multipurpose concrete anchor clip |
US9527572B2 (en) | 2014-06-26 | 2016-12-27 | The Boeing Company | Elongated structures and related assemblies |
CA2903509C (en) * | 2014-09-04 | 2022-09-06 | Bailey Metal Products Limited | Bracket for bridging member for metal stud wall |
US10214902B1 (en) * | 2015-08-26 | 2019-02-26 | Flexability Concepts, Llc | Stud layout locker |
USD788950S1 (en) * | 2016-03-16 | 2017-06-06 | Werner Co. | Roof anchor |
ES2964801T3 (en) | 2016-10-05 | 2024-04-09 | Fortress Iron Lp | Platform Framing System |
USD821851S1 (en) | 2017-02-24 | 2018-07-03 | Clarkwestern Dietrich Building Systems Llc | Bridging clip |
USD822455S1 (en) | 2017-02-24 | 2018-07-10 | Clarkwestern Dietrich Building Systems Llc | Bridging clip with a rib |
USD823095S1 (en) | 2017-02-24 | 2018-07-17 | Clarkwestern Dietrich Building Systems Llc | Bridging clip with ribs |
USD798137S1 (en) * | 2017-03-09 | 2017-09-26 | Frank Locatell | Removable form tie |
WO2019012427A1 (en) * | 2017-07-11 | 2019-01-17 | Nova Building Ltd | Concrete building shoppable in small parts |
CN107338886A (en) * | 2017-08-31 | 2017-11-10 | 华侨大学 | A kind of anti-buckling combined shear wall construction of steel pipe profiled sheet concrete |
US10590647B2 (en) | 2018-03-16 | 2020-03-17 | Telling Industries, LLC | Cold rolled channel without clip |
US10309107B2 (en) * | 2018-03-16 | 2019-06-04 | Telling Industries, LLC | Cold rolled channel without clip |
US10563401B2 (en) | 2018-03-16 | 2020-02-18 | Telling Industries, LLC | Bridge clip |
US11028580B2 (en) | 2018-05-25 | 2021-06-08 | Fortress Iron, Lp | Deck frame with integral attachment tabs |
USD915868S1 (en) * | 2018-12-12 | 2021-04-13 | Nichietsu Inc. | Mounting plate for mold |
CN112523394A (en) * | 2019-09-18 | 2021-03-19 | 杭州欧尔装饰工程有限公司 | Light steel keel partition wall |
GB2593544A (en) * | 2020-03-27 | 2021-09-29 | Ash & Lacy Holdings Ltd | Manufacturing method |
USD915874S1 (en) | 2020-08-12 | 2021-04-13 | Frank Locatell | Removable form tie |
US11849845B2 (en) * | 2021-02-11 | 2023-12-26 | Menasha Corporation | Corner retention clip |
US11993928B2 (en) * | 2021-07-12 | 2024-05-28 | Falkbuilt Ltd. | Hybrid wall system |
USD996963S1 (en) | 2021-11-18 | 2023-08-29 | Super Stud Building Products, Inc. | Clip |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3322447A (en) * | 1964-04-07 | 1967-05-30 | Angeles Metal Trim Co | Stiffening-bar mounting for metal wall studs |
US5784850A (en) * | 1994-11-10 | 1998-07-28 | Elderson; William L. | Stud wall system and method using spacer member |
CA2304264A1 (en) * | 2000-03-31 | 2001-09-30 | Bailey Metal Products Limited | Bracket for bridging member for metal stud wall |
CA2463747A1 (en) * | 2001-10-16 | 2003-05-15 | Flexability Concepts Llc | Deflection clip |
US6701689B2 (en) * | 2001-12-07 | 2004-03-09 | The Steel Network, Inc. | Stud spacer |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5642597A (en) * | 1996-06-21 | 1997-07-01 | Hendrickson; Gary J. | Drywall mounting bracket |
US5904023A (en) * | 1998-01-16 | 1999-05-18 | The Steel Network, Inc. | Steel stud stabilizing clip |
US6536179B2 (en) * | 2001-02-16 | 2003-03-25 | John M. Little | Blocking anchor for attachment of a bridge between adjacent floor joists |
US6609344B2 (en) * | 2001-11-21 | 2003-08-26 | Eluterio Saldana | Connectors, tracks and system for smooth-faced metal framing |
-
2005
- 2005-02-11 CA CA2496961A patent/CA2496961C/en active Active
-
2006
- 2006-02-13 WO PCT/CA2006/000188 patent/WO2006084367A2/en not_active Application Discontinuation
- 2006-02-13 US US11/352,335 patent/US8011160B2/en active Active
-
2011
- 2011-08-15 US US13/210,050 patent/US8356453B2/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3322447A (en) * | 1964-04-07 | 1967-05-30 | Angeles Metal Trim Co | Stiffening-bar mounting for metal wall studs |
US5784850A (en) * | 1994-11-10 | 1998-07-28 | Elderson; William L. | Stud wall system and method using spacer member |
CA2304264A1 (en) * | 2000-03-31 | 2001-09-30 | Bailey Metal Products Limited | Bracket for bridging member for metal stud wall |
CA2463747A1 (en) * | 2001-10-16 | 2003-05-15 | Flexability Concepts Llc | Deflection clip |
US6701689B2 (en) * | 2001-12-07 | 2004-03-09 | The Steel Network, Inc. | Stud spacer |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP2395168B1 (en) * | 2010-06-08 | 2015-05-06 | Mr. Leendert Weernink | Method for manufacturing a frame, assembly and upright |
Also Published As
Publication number | Publication date |
---|---|
CA2496961C (en) | 2012-11-27 |
US20070199274A1 (en) | 2007-08-30 |
US8356453B2 (en) | 2013-01-22 |
CA2496961A1 (en) | 2006-08-11 |
US20110296786A1 (en) | 2011-12-08 |
US8011160B2 (en) | 2011-09-06 |
WO2006084367A3 (en) | 2006-09-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CA2496961C (en) | Bracket and bridging member for metal stud wall | |
US6739562B2 (en) | Bracket for bridging member for metal stud wall | |
CA2505306C (en) | Metal stud with bendable tab for bridging member support | |
US9523196B2 (en) | Bracket for bridging member for metal stud wall | |
US6694695B2 (en) | Wall stud spacer system with spacer retainers | |
US10508446B2 (en) | Bridge clip | |
US7752821B2 (en) | Suspended ceiling system | |
CA2384534C (en) | Snap-fit panel connection apparatus | |
US20040172912A1 (en) | Spacer bar retainers and methods for retaining spacer bars in metal wall studs | |
EP1054116A1 (en) | Surface mounted grid system | |
US20140167405A1 (en) | Insert for HVAC Systems | |
JPH10501037A (en) | Method for interconnecting wallboards and novel wall elements | |
US20060070319A1 (en) | Devices and systems for preventing the propagation of fire along cables and methods of preventing same | |
US4257205A (en) | Attachment system for suspended drywall ceiling panels | |
US4574549A (en) | Adjustable roof insulation system | |
US6289617B1 (en) | Address plate for stepped wall structures | |
US9627871B2 (en) | Fire classified floor box assembly | |
KR100635929B1 (en) | Pipe supporter combined with v-band in dry air duct system | |
US20050034407A1 (en) | Support frame for duct | |
KR200303213Y1 (en) | Connecting and fixing device for the form and coverlet comprising cable tray or duct | |
US20120211115A1 (en) | Pipe enclosure apparatus | |
KR100913706B1 (en) | Hanger with rocker of tube | |
AU2017202856A1 (en) | External gutter system | |
EP1092813A2 (en) | Metallic grating to cover the channel for picking up and conveying water | |
KR950007029Y1 (en) | Hose clips |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
DPE1 | Request for preliminary examination filed after expiration of 19th month from priority date (pct application filed from 20040101) | ||
NENP | Non-entry into the national phase |
Ref country code: DE |
|
122 | Ep: pct application non-entry in european phase |
Ref document number: 06705144 Country of ref document: EP Kind code of ref document: A2 |
|
WWW | Wipo information: withdrawn in national office |
Ref document number: 6705144 Country of ref document: EP |