WO2004106696A1 - A spool piece termination structure, a connection arrangement comprising such a termination structure and a pipeline termination - Google Patents
A spool piece termination structure, a connection arrangement comprising such a termination structure and a pipeline termination Download PDFInfo
- Publication number
- WO2004106696A1 WO2004106696A1 PCT/IB2004/001762 IB2004001762W WO2004106696A1 WO 2004106696 A1 WO2004106696 A1 WO 2004106696A1 IB 2004001762 W IB2004001762 W IB 2004001762W WO 2004106696 A1 WO2004106696 A1 WO 2004106696A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- pipeline
- alignment
- hub
- end section
- termination
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Ceased
Links
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L1/00—Laying or reclaiming pipes; Repairing or joining pipes on or under water
- F16L1/12—Laying or reclaiming pipes on or under water
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B43/00—Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
- E21B43/01—Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells specially adapted for obtaining from underwater installations
- E21B43/0107—Connecting of flow lines to offshore structures
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L1/00—Laying or reclaiming pipes; Repairing or joining pipes on or under water
- F16L1/26—Repairing or joining pipes on or under water
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y10—TECHNICAL SUBJECTS COVERED BY FORMER USPC
- Y10S—TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y10S285/00—Pipe joints or couplings
- Y10S285/92—Remotely controlled
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y10—TECHNICAL SUBJECTS COVERED BY FORMER USPC
- Y10T—TECHNICAL SUBJECTS COVERED BY FORMER US CLASSIFICATION
- Y10T29/00—Metal working
- Y10T29/53—Means to assemble or disassemble
- Y10T29/53313—Means to interrelatedly feed plural work parts from plural sources without manual intervention
- Y10T29/53348—Running-length work
- Y10T29/53357—Pipe section
Definitions
- a spool piece termination structure a connection arrangement comprising such a termination structure and a pipeline termination
- the present invention relates to spool piece termination structure according to the preamble of claim 1 and a connection arrangement for subsea connection of a pipeline to a spool piece com- prising such a termination structure.
- the invention also relates to a method according to the preamble of claim 20 for subsea connection of a pipeline to a spool piece.
- the invention also relates to a pipeline termination according to the preamble of claim 26.
- a spool piece is used for connecting a pipe- line termination to a pipe termination of a subsea installation, such as e.g. a subsea production or injection well.
- the spool piece is designed to span between the end points of the pipeline termination and said pipe termination in order to complete a connection between the pipeline and said pipe.
- the spool piece is provided with a spool piece hub which is to mate with a corresponding pipeline hub arranged at the pipeline termination.
- a pipeline connection arrangement and method for subsea connection of a pipeline to a spool piece is previously known from US 4 019 334 A.
- the spool piece hub is here attached to a foundation arranged on the seabed.
- the pipeline hub is secured to a trunnion assembly and is installed on the subsea foundation by being lowered together with the trunnion assembly downwards from a surface vessel guided by a guide cable.
- a remotely operated connecting tool is lowered downwards from the surface vessel and is operated to displace the spool piece hub into engagement with the pipeline hub, whereupon the connecting tool is operated to actuate a clamping device so as to clamp together the spool piece hub and the pipeline hub.
- the connecting tool is then retrieved to the surface vessel.
- the pipeline hub is here secured to a landing platform, which is to be lowered onto the seabed from a surface vessel.
- the spool piece hub is secured to a connecting tool, which is lowered downwards onto the landing platform so as to come to rest thereon, whereupon the connecting tool is operated to displace the spool piece hub into engagement with the pipeline hub.
- the pipeline hub is secured to the rather complex and bulky landing platform before being lowered into the sea from a surface vessel.
- the lay ramp and other equipment of the pipe-laying vessel have to be adapted and dimensioned for enabling manipulation and lay out of the landing platform. This will raise the costs for the pipe-laying vessel and reduce the number of vessels available for the pipe-laying operation, which could cause high costs for performing the pipe-laying operation.
- the object of the present invention is to make possible subsea connection of a pipeline to a spool piece, without requiring any complex and/or bulky equipment to be attached to the pipeline hub before it is descended into the sea from a surface vessel.
- this object is achieved by a spool piece termination structure having the features of claim 1 , a con- nection arrangement having the features of claim 6 and a method having the features of claim 20.
- the spool piece termination structure comprises a base frame, which is openly shaped downwards so as to allow the termination structure to receive a pipeline end section provided with a pipeline hub by lowering the termination structure downwards onto said pipeline end section.
- the actual connection of the pipeline hub to the spool piece hub may be performed by displacing the pipeline hub and the spool piece hub with the clamping device in relation to each other so as to bring the pipeline hub and the spool piece hub into contact with each other, whereupon the clamping device is activated so as to clamp together the pipeline hub and the spool piece hub.
- the initial connection between the pipeline hub and the spool piece termination structure is accomplished by lowering the termination structure downwards onto the pipeline hub.
- the entire pipeline may be laid on the seabed before the measures of connecting the pipeline to the spool piece are initiated.
- no landing platform or similar structure has to be secured to the pipeline end section when it is descended from the pipe-laying vessel, which will facilitate the pipe-laying operation and allow the pipeline to be laid out by means of a conventional pipe-laying vessel.
- the inventive solution will reduce the demands on the pipe-laying vessel with respect to its equipment as compared to the prior art solutions where a landing platform or the similar is secured to the pipeline before it leaves the pipe-laying vessel.
- the alignment structure is designed to receive at least a part of a rotationally symmetric flange of a pipeline end section.
- the alignment structure may receive the pipeline end section flange irrespective of the roll angle of the pipeline end section and the associated pipeline hub. Consequently, the roll angle of the pipeline end section and the associated pipeline hub is of no importance during the installation of the pipeline on the seabed and during the subsequent operations for connecting the pipeline hub to the spool piece hub.
- the pipeline end section and the associated pipeline hub may be laid on the seabed with arbitrary roll angle, which will facilitate the pipe-laying operation.
- the termination structure and alignment structure are provided with corresponding alignment members which are designed to come into contact with each other when the alignment structure and clamping device are displaced towards each other so as to reduce the angle between the hub mating faces.
- the pipeline hub will automatically be sufficiently aligned with the spool piece hub to meet the closing capture range of the clamping device when they have been displaced towards each other.
- one of the alignment structure and termination structure is provided with at least one male-like alignment member, preferably in the form of a spear, which is designed to fit into a corresponding female-like alignment member, preferably in the form of a spear funnel, arranged on the other of said structures.
- This will provide a co-axial alignment so as to allow the mutual alignment shoulder/recess arrangement of the hubs perform the final alignment and load transfer.
- the respective male-like alignment member is preferably displaceably mounted in the associated structure so as to allow the alignment member to be retracted out of the corresponding female-like alignment member without having to displace the entire alignment structure in relation to the termination structure. This will facilitate the retrieval to the surface of the alignment structure after the completion of the connection between the pipeline hub and the spool piece hub.
- the invention also relates to a pipeline termination having the features of claim 26.
- the design of the pipeline termination with a flange located behind the pipeline hub will allow the pipeline termination to be manipulated sub-sea during the operations for connecting the pipeline hub to a corresponding spool piece hub, without requiring any complex and/or bulky equipment to be attached to the pipeline termination before it is descended into the sea from a surface vessel.
- said flange is rotationally symmetric.
- the roll angle of the pipeline termination is of no importance during the installation of the pipeline on the seabed and during the subsequent operations for connecting the pipeline hub to the spool piece hub.
- the pipeline termination may be laid on the seabed with arbitrary roll angle, which will facilitate the pipe-laying operation.
- Fig 1 is a perspective view of a spool piece termination structure according to a first embodiment of the invention
- Fig 2 is a perspective view of the rear section of an alignment structure intended for co-operation with the ter- mination structure of Fig 1 ,
- Fig 3 is a perspective view of the alignment structure of Fig 2, as seen from the opposite direction,
- Fig 4 is a vertical cross section through the centre of the alignment structure of Figs 2 and 3,
- Fig 5-7 are schematical illustrations of different stages in a method for subsea connection of a pipeline to a spool piece by means of the termination structure of Fig 1 and the alignment structure of Figs 2-4,
- Fig 8 is a perspective view of a spool piece termination structure according to a second embodiment of the in- vention.
- Figs 9-15 are schematical illustrations of different stages in a method for subsea connection of a pipeline to a spool piece by means of the termination structure of Fig 8.
- a spool piece termination structure 5 according to a first embodiment of the present invention is shown in Fig 1 .
- the termination structure 5 is intended for use in subsea connection of a pipeline 1 (see Figs 5-7) to a spool piece 2 and comprises a clamping device 3 for clamping together a pipeline hub 1 a (see Figs 5-7) secured to the end of the pipeline and a corresponding spool piece hub 2a secured to the end of the spool piece.
- the spool piece hub 2a and the associated spool piece 2 are to be mounted to the termination structure 5 before being lowered into the sea from a surface vessel.
- the spool piece hub and the spool piece are mounted to the termination structure before the performance of a connecting operation.
- the clamping device 3 is attached to a vertical base plate 6 forming part of the body of the termination structure.
- the termination structure 5 comprises a base frame 7, which is openly shaped downwards so as to allow the termination structure 5 to receive a pipeline end section 1 b (see Figs 5-7) pro- vided with a pipeline hub 1 a by lowering the termination structure 5 downwards onto said pipeline end section.
- the base frame 7 comprises two cantilever beams 8a, 8b extending from the plate 6 below and on either side of the clamping device 3.
- the cantilever beams are intended to extend essentially in parallel with a pipeline end section properly received in the termination structure.
- the clamping device 3 is preferably fixedly secured in relation to the base frame 7 so as to be displaceable together with the base frame 7 and the other parts of the termination structure 5.
- the termination structure 5 comprises a guiding device 9 for engaging the pipeline end section when received in the termination structure so as to secure that the pipeline end section and the associated pipeline hub are properly received and positioned in the termination structure.
- the guiding device consists of a yoke 9 having inverted U-shape with a downwardly directed opening for receiving a pipeline end section.
- the yoke 9 has its legs 9a, 9b secured to the outer ends of the cantilever beams 8a, 8b so as to bridge the gap between said beams.
- the pipeline end section is to enter the termination structure 5 via the open space between the cantilever beams 8a, 8b when the termination structure is lowered onto it.
- the bottom 9c of the yoke 9 is intended to come to bear against a pipeline end section received in the termination structure 5 so as to secure that the pipeline end section and the associated pipeline hub are positioned in front of the clamping device 3 in the space between the cantilever beams 8a, 8b and the yoke 9.
- the guiding device 9 is preferably provided with releasable locking means 10 for locking a pipeline end section in relation to the termination structure 5 when received therein.
- the locking means 10 are suitably designed to engage with a sleeve member 1 c (see Figs 5-7) arranged on the pipeline end section fixedly secured in relation to the pipeline hub 1 a so as to thereby lock the pipeline end section 1 b and the pipeline hub 1 a in relation to the termination structure 5 in a predetermined axial position.
- the locking means 10 comprise two pivo- table locking arms 10a, 10b, which are pivotable into and out of engagement with said sleeve 1 c and which are arranged at the bottom part 9c of the yoke 9.
- the termination structure 5 illustrated in Fig 1 is intended to cooperate with an alignment structure 20 designed to be connect- able to a pipeline end section 1 b received in the termination structure 5 by being lowered downwards onto said pipeline end section so as to come to bear against it.
- the alignment structure 20 is designed to receive, when it is lowered downwards onto the pipeline end section 1 b, at least a part of a flange 1 d (see Figs 5 and 6) of the pipeline end section received in the termination structure 5.
- Said flange 1 d is fixedly secured in relation to the pipeline hub 1 a and is preferably rotationally symmetric.
- the alignment structure 20 is provided with a housing 21 of inverted U-shape with a downwardly directed opening for receiving said pipeline end section flange 1 d.
- the alignment structure 20 comprises an alignment device 22 for properly aligning said flange 1 d and thereby the pipeline hub 1 a in relation to the alignment structure when received therein.
- the alignment device comprises at least one force applying member 22a for forcing a received pipeline end section flange 1 d against an abutment 23 of the alignment structure.
- said abutment is formed by a wall 23 of the housing 21.
- the alignment device preferably comprises at least three force applying members 22a spaced apart in the circumferential direction of a received pipeline end section flange 1 d for forcing said flange against the abutment 23.
- the respective force applying member 22a comprises a push member, which is displaceably mounted in the alignment structure 20 and is displaceable by means of a hydraulic cylinder 24 arranged in the alignment structure.
- the alignment structure 20 and clamping device 3 are designed to be displaceable in relation to each other when the alignment structure has come to bear against a pipeline end section 1 b re- ceived in the termination structure 5 so as to allow the pipeline hub 1 a and the clamping device 3 to be mutually displaced into contact with each other. This will be more closely described below with reference to Figs 5-7.
- the termination structure 5 and alignment structure 20 are provided with corresponding align- ment members 15, 25 which are designed to come into contact with each other when the alignment structure 20 and clamping device 3 are displaced towards each other so as to properly align the pipeline hub 1 a in relation to the spool piece hub 2a.
- One of the alignment structure and termination structure is suitably provided with at least one male-like alignment member 25, preferably in the form of a spear, which is designed to fit into a corresponding female-like alignment member 15, preferably in the form of a spear funnel, arranged on the other of said structures.
- the respective male-like alignment member 25 is prefera- bly displaceably mounted in the associated structure 20 so as to allow the alignment member 25 to be retracted out of the corresponding female-like alignment member 15 without having to displace the entire alignment structure 20 in relation to the termination structure 5.
- the respective male-like alignment member 25 is preferably displaceable by means of a hydraulic cylinder arranged in the associated structure.
- the alignment structure is provided with two displaceably mounted alignment spears 25 arranged in the alignment structure 20 so as to be located below and on either side of the centre line of a pipeline end section 1 b onto which the alignment structure 20 has been lowered.
- the respective spear 25 is dis- placeable by means of a hydraulic cylinder 28 arranged in the alignment structure 20.
- the termination structure 5 is here provided with two spear funnels 15 for receiving a respective one of the alignment spears 25.
- the spear funnels 15 are located on either side of the centre line of a spool piece hub 2a mounted to the termination structure 5.
- the respective spear funnel 15 is here attached to the vertical base plate 6 of the termination structure.
- the respective alignment member 25 of the alignment structure 20 is preferably designed to abut against the corresponding alignment member 15 of the termination structure 5 when the clamping device 3 has been displaced into contact with the pipeline hub so as to align the hub mating faces prior to their mutual contact for final alignment.
- the alignment structure 20 is preferably also provided with at least two stop members 26, which are arranged in the alignment structure so as to be located above and on either side of the centre line of a pipeline end section onto which the alignment structure 20 has been lowered.
- the respective stop member 26 is designed to abut against a corresponding stop member 16 of the termination structure 5 when the clamping device 3 is displaced into contact with the pipeline hub 1 a so as to reduce the angle between the hub mating faces.
- the pipeline hub 1 a will automatically be sufficiently aligned with the spool piece hub 2a to meet the closing capture range of the clamping device.
- the alignment structure 20 and the termination structure 5 are each provided with two such stop members 26, 16 in addition to the corresponding function included in the alignment members 25, 15.
- the termination structure 5 and the alignment structure 20 are provided with means for receiving a remotely operated connecting tool provided with force applying means, preferably in the form of hydraulic cylinders, for displacing the alignment structure 20 and the clamping device 3 in relation to each other.
- the clamping device 3 is preferably designed to be displaced in relation to the alignment structure 20 by being displaced together with the other parts of the termination structure 5 in relation to the alignment structure.
- the alignment structure 20 and the termination structure 5 are each provided with slots 27, 17 for docketing of hydraulic cylinders of the connecting tool to said structures.
- the connecting tool may also be provided with torque applying device 32 preferably hydrauli- cally operated, for actuating the clamping device 3 so as to clamp together the pipeline hub 1 a and the spool piece hub 2a.
- the torque applying device may be installed separately.
- the alignment structure 20 could form part of the connect- ing tool or the connecting tool could, alternatively, be designed as a separate unit that is lowered downwards into engagement with the alignment structure 20 and the termination structure 5 after the positioning of the termination structure and the alignment structure onto a pipeline end section.
- the termination struc- ture 5 is provided with guiding means 18 designed to co-operate with corresponding guiding means on the connecting tool so as to guide the connecting tool into a correct position in relation to the termination structure when the connecting tool is lowered downwards into engagement with the termination structure.
- said guiding means of the termination structure 5 comprises two guide post receptacles 18 arranged in the termination structure 5 so as to be located on either side of the spool piece hub 2a.
- the respective guide post receptacle 18 is intended to receive a guide post, by means of which the con- necting tool is guided into engagement with the termination structure 5.
- Pipeline terminations 1 e are shown in Fig 5 and Fig 9.
- the respective pipeline termination 1 e is to be applied to the end section 1 b of a pipeline 1 so as to allow the pipeline 1 to be connected sub-sea to a spool piece 2.
- the pipeline termination 1 e comprises a pipeline hub 1 a de- signed for connection to a corresponding spool piece hub 2a.
- the pipeline termination 1 e further comprises a flange 1 d located behind the pipeline hub 1 a and designed to constitute a reaction shoulder for use in the alignment and displacement of the pipe- line termination 1 e and the associated pipeline hub 1 a in relation to said spool piece hub 2a, as described in closer detail below.
- Said flange 1 d is fixedly secured in relation to the pipeline hub 1 a and is preferably rotationally symmetric.
- the pipeline termination 1 e is designed for co-operation with a connection arrange- ment according to the present invention.
- connection arrangement comprising the above-described termination structure 5 and alignment structure 20 is schematically illustrated in Figs 5-7.
- the pipeline 1 pro- vided with a pipeline hub 1 a, a flange 1 d and alternatively a sleeve member 1 c at the end section 1 b is initially laid on the seabed.
- the pipeline end section 1 b is to be supported by a suitable support, such as a rock heap or a fabricated support structure, so as to make sure that the pipeline end section 1 b is ele- vated from the seabed.
- Subsea metrology is then carried out between the pipeline hub 1 a and the permanent subsea installation to which the pipeline is to be connected.
- a guide line 40 will in this option be connected to the sleeve member 1c of the pipeline.
- the termination structure 5 is attached to a lifting device 41 provided with a guide member 42.
- the guide member 42 of the lifting device 41 is connected to the guide line 40 and the lifting device 41 is together with the termi- nation structure 5 and the associated spool piece 2 lowered into the sea, e.g. from a surface vessel, and guided towards the pipeline end section 1 b, as illustrated in Fig 5.
- the termination structure 5 and the lifting device 41 are lowered downwards until the pipeline end section 1 b is received between the cantilever beams 8a, 8b and the guiding device 9 of the termination structure abuts against the sleeve member 1 c, as illustrated in Fig 6.
- the locking means 10 will align and lock the sleeve member 1 c, and thereby the pipeline end section, axially in relation to the termination structure 5 in a preliminary parking position.
- the lifting device 41 is then disconnected from the termination structure 5 and retrieved to the surface.
- the alignment structure 20 is then lowered downwards, e.g.
- the alignment device 22 is actuated so as to properly align the pipeline end section flange 1 d in relation to the alignment structure 20.
- the connect- ing tool may be lowered into contact with the alignment structure 20 and the termination structure 5 after the positioning of the alignment structure onto the pipeline end section.
- the connecting tool is actuated so as to displace the termination structure 5 and thereby the clamping device 3 towards the align- ment structure 20.
- the sleeve member 1 c has been released from the locking means 10 so as to allow the termination structure 5 to slide along the pipeline 1.
- the torque applying device is made to actuate the clamping device 3 so as to clamp together the pipeline hub 1 a and the spool piece hub 2a, whereupon the alignment spears 25 are withdrawn from the respective spear funnel 15 and the connecting tool and the alignment structure 20 are retrieved to the surface.
- FIG 8 An alternative embodiment of a spool piece termination structure 5 according to the invention is illustrated in Fig 8. Details of the termination structure 5 illustrated in Fig 8 and other details of the connection arrangement illustrated in Figs 9-15 are in Fig 8-15 indicated with the same reference signs as the corresponding details of the termination structure and connection arrangement illustrated in Figs 1 -7.
- the main difference between the termination structure 5 of Fig 8 and the termination structure of Fig 1 is that the termination structure of Fig 8 is provided with a lifting appliance 50 for lifting a pipeline end section 1 b (see Figs 9-1 1 ) received in the termina- tion structure 5 upwards in relation to the base frame 7 in order to align the pipeline hub 1 a with the clamping device 3 through an active and more controllable operation.
- the lifting appliance 50 could be a separately installed unit or included in the alignment structure 20 or the connecting tool 30. This will allow the pipeline end section 1 b and the associated pipeline hub 1 a to be positioned directly onto the seabed or onto a fabricated subsea foundation.
- a guiding device 51 for engaging the pipeline end section 1 b when received in the termination structure 5 so as to secure that the pipeline end section and the associated pipeline hub 1 a are properly received and positioned in the termination structure 5 is designed to engage with the pipeline end section flange 1 d.
- the guiding device 51 here comprises two pairs of guide plates 51 a, 51 b attached to the cantilever beams 8a, 8b.
- a slot 52 for receiving said flange 1 d is provided between the two guide plates 51 a, 51 b of the respective guide plate pair. Said slot has a tapered, downwardly directed opening.
- the cantilever beams 8a, 8b will here constitute landing means for allowing the termination structure to rest on the seabed or on a fabricated subsea foundation.
- the lifting appliance 50 is attached to a yoke 53 having inverted U-shape with a downwardly directed opening for receiving a pipeline end section.
- the yoke 53 has its legs 53a, 53b secured to the outer ends of the cantile- ver beams 8a, 8b so as to bridge the gap between said beams.
- the lifting appliance 50 comprises a gripping device 54, preferably hydraulically actuated, for gripping a pipeline end section 1 b onto which the termination structure 5 has been lowered.
- the gripping device 54 is vertically moveable in relation to the base frame 7 of the termination structure 5, preferably by means of a hydraulic cylinder 55, so as to allow the gripping device 54 to be lowered into contact with a pipeline end section 1 b that is received in the termination structure while still laying on the seabed or on a subsea foundation and allow the gripping device 54 to be raised together with a gripped pipeline end section 1 b in relation to the base frame 7.
- the operation of a connection arrangement comprising a spool piece termination structure 5 according to Fig 8 is schematically illustrated in Figs 9-15.
- the pipeline 1 provided with a pipeline hub 1 a and a flange 1 d at the end section 1 b is initially laid on the seabed.
- the pipeline end section 1 b is laid directly on the seabed or on a fabricated subsea foundation, i.e. it does not have to be elevated from the seabed/foundation.
- Subsea metrology is then carried out between the pipeline hub 1 a and the permanent subsea installation to which the pipeline is to be con- nected.
- the results of the subsea metrology are used to complete the geometry of the spool piece 2, which is mounted to the spool piece termination structure 5.
- the termination structure 5 is together with the associated spool piece 2 lowered into the sea, e.g.
- the gripping device 54 is then lowered downwards in relation to the base frame 7 into engagement with the pipeline end section 1 b, as illustrated in Fig 10, whereupon the gripping device is made to grip the pipeline end section 1 b.
- the gripping device 54 is then raised upwards in relation to the base frame 7, while carrying the pipeline end section 1 b, so as to align the pipeline hub 1 a with the clamping device 3 and release the pipeline end section flange 1 d from the guiding device 51 , as illustrated in Fig 11.
- An alignment structure 20 of the above-indicated type is then lowered down- wards into engagement with the pipeline end section flange 1 d, as illustrated in Fig 12, whereupon an alignment device of the alignment structure, e.g. of the type described with reference to Fig 2-4, is actuated so as to properly align the pipeline end section flange 1 d in relation to the alignment structure 20.
- a con- necting tool 30 comprising a pair of stroking cylinders 31 a, 31 b is then lowered downwards into contact with the alignment structure 20 and the termination structure 5.
- the alignment structure 20 and the connecting tool 30 may both be guided into position by means of guide posts 60 inserted into the guide post receptacles 18 of the termination structure 5, as illustrated in Figs 13 and 14.
- the stroking cylinders 31 a, 31 b are connected to the alignment structure 20 and the termination structure 5 via docketing slots 27, 17 arranged in said structures.
- the stroking cylinders 31 a, 31 b are then actuated so as to displace the termination structure 5 and thereby the clamping device 3 towards the alignment structure 20, as illustrated in Fig 15.
- a torque applying device 32 is made to actuate the clamping device 3 so as to clamp together the pipeline hub 1 a and the spool piece hub 2a, whereupon a pressure test is performed to verify the sealing integrity.
- the alignment spears 25 are withdrawn from the respective spear funnel 15 and the con- necting tool 30 and the alignment structure 20 are retrieved to the surface together with the lifting appliance 50 if configured as a separate unit.
- the torque applying device 32 may be included in the connecting tool 30 or constitute a separate unit that is moveable into contact with the termination structure separately from the connecting tool 30.
- the connecting tool 30 is provided with guiding means 33 de- signed to engage with the guide posts 60 as the connecting tool is lowered downwards into contact with the termination structure 5.
- the alignment structure 20 illustrated in Figs 12-15 has a some- what modified design as compared to the alignment structure of Figs 2-4. However, it comprises the same type of alignment device 22, alignment members 25 and stop members 26 as the alignment structure of Figs 2-4.
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Geology (AREA)
- Life Sciences & Earth Sciences (AREA)
- Mechanical Engineering (AREA)
- Environmental & Geological Engineering (AREA)
- Fluid Mechanics (AREA)
- Physics & Mathematics (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Earth Drilling (AREA)
- Mutual Connection Of Rods And Tubes (AREA)
- Non-Disconnectible Joints And Screw-Threaded Joints (AREA)
- Quick-Acting Or Multi-Walled Pipe Joints (AREA)
Abstract
Description
Claims
Priority Applications (3)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| US10/558,272 US7402000B2 (en) | 2003-05-28 | 2004-05-28 | Spool piece termination structure, a connection arrangement comprising such a termination structure and a pipeline termination |
| GB0523956A GB2417534B (en) | 2003-05-28 | 2004-05-28 | A spool piece termination structure, a connection arrangement comprising such a termination structure and a pipeline termination |
| NO20055663A NO337860B1 (en) | 2003-05-28 | 2005-11-30 | Connection arrangement and method for subsea connection of a pipeline to a pipeline. |
Applications Claiming Priority (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| US47344803P | 2003-05-28 | 2003-05-28 | |
| US60/473,448 | 2003-05-28 |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| WO2004106696A1 true WO2004106696A1 (en) | 2004-12-09 |
Family
ID=33490604
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| PCT/IB2004/001762 Ceased WO2004106696A1 (en) | 2003-05-28 | 2004-05-28 | A spool piece termination structure, a connection arrangement comprising such a termination structure and a pipeline termination |
Country Status (4)
| Country | Link |
|---|---|
| US (1) | US7402000B2 (en) |
| GB (1) | GB2417534B (en) |
| NO (1) | NO337860B1 (en) |
| WO (1) | WO2004106696A1 (en) |
Cited By (11)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| GB2440336A (en) * | 2006-07-27 | 2008-01-30 | Verderg Connectors Ltd | A connection tool for connecting a pipeline to a subsea connection structure |
| WO2013070077A1 (en) * | 2011-11-08 | 2013-05-16 | Ihc Holland Ie B.V. | Method and device for coupling floating pipe sections |
| US8619134B2 (en) | 2009-03-11 | 2013-12-31 | Seatrepid International, Llc | Unmanned apparatus traversal and inspection system |
| EP2722479A1 (en) * | 2012-10-17 | 2014-04-23 | Vetco Gray Scandinavia AS | Subsea arrangement |
| NL2010715C2 (en) * | 2013-04-26 | 2014-10-29 | Ihc Holland Ie Bv | Coupling device for dredging pipes and method for coupling dredging pipes. |
| US9163485B2 (en) | 2010-12-15 | 2015-10-20 | Verderg Connectors Ltd | Connection apparatus and methods |
| WO2015197539A1 (en) * | 2014-06-23 | 2015-12-30 | Vetco Gray Scandinavia As | Pipeline termination arrangement |
| GB2536622A (en) * | 2015-03-16 | 2016-09-28 | Self Energising Coupling Co Ltd | Improved subsea tie back connector |
| CN108884958A (en) * | 2016-04-11 | 2018-11-23 | 川崎重工业株式会社 | Joint structure |
| WO2020142637A1 (en) | 2019-01-03 | 2020-07-09 | Subsea 7 (Us) Llc | Subsea connection of pipeline sections |
| GB2550814B (en) * | 2015-03-03 | 2021-04-14 | Aker Solutions As | Connection system for subsea pipelines |
Families Citing this family (31)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US7967070B2 (en) * | 2006-07-12 | 2011-06-28 | Deep Sea Technologies, Inc. | Diverless connector for bend restrictors and/or bend stiffeners |
| GB2442972B8 (en) * | 2006-07-27 | 2009-12-30 | Verderg Connectors Ltd | Connection tool |
| NO325935B1 (en) * | 2006-11-22 | 2008-08-18 | Aker Subsea As | The connecting device. |
| GB2447645B (en) * | 2007-03-16 | 2011-10-19 | Lewis Ltd | A subsea connector incorporating guide and latch means |
| US20090026765A1 (en) * | 2007-07-24 | 2009-01-29 | Oceaneering International, Inc. | Connector Jumper |
| NO329288B1 (en) * | 2007-12-21 | 2010-09-27 | Fmc Kongsberg Subsea As | Tool and method for connection of pipelines |
| US20100044052A1 (en) * | 2008-08-20 | 2010-02-25 | Schlumberger Technology Corporation | System and method for connecting and aligning a compliant guide |
| GB2469105B (en) * | 2009-04-02 | 2011-06-22 | Verderg Ltd | Apparatus and method for the connection of conduits |
| NO334143B1 (en) * | 2009-08-21 | 2013-12-16 | Aker Subsea As | Vertical connector for use on the seabed |
| NO330676B1 (en) * | 2009-09-16 | 2011-06-06 | Nemo Eng As | Load transfer underwater structure for permanent relief of forces in a rudder connection |
| NO331032B1 (en) * | 2009-10-07 | 2011-09-19 | Aker Subsea As | Horizontal switchgear tool |
| NO333113B1 (en) * | 2009-10-07 | 2013-03-04 | Aker Subsea As | Horizontal switchgear |
| GB2478548B (en) * | 2010-03-09 | 2015-11-25 | Acergy France SAS | Apparatus and method for installing a pipeline structure at sea |
| US8449221B1 (en) * | 2010-08-30 | 2013-05-28 | Trendsetter Engineering, Inc. | Method and apparatus for repairing a damaged section of a subsea pipeline |
| US9217314B2 (en) * | 2010-10-28 | 2015-12-22 | Gulfstream Services, Inc. | Method and apparatus for evacuating hydrocarbons from a distressed well |
| US8517634B1 (en) * | 2011-03-30 | 2013-08-27 | Chevron U.S.A. Inc. | Systems and methods for replacing, repositioning and repairing a section of subsea pipe located on a seabed |
| US20120263541A1 (en) * | 2011-04-15 | 2012-10-18 | Per Lillejordet | Subsea structure for pipe assemblies |
| US20130146301A1 (en) * | 2011-12-12 | 2013-06-13 | Trendsetter Engineering, Inc. | Subsea structure flowline connector assembly |
| US9163486B2 (en) * | 2011-12-12 | 2015-10-20 | Triton Connector Solutions Pte. Ltd. | Subsea structure flowline connector assembly |
| GB2516578B (en) * | 2012-06-06 | 2020-04-08 | Garry Ray Van Heerden | Pipe connection guide arrangement |
| CN102705581A (en) * | 2012-06-20 | 2012-10-03 | 中国石油大学(北京) | Device for lowering and mounting submarine pipeline and crossing pipeline |
| EP2722480B1 (en) * | 2012-10-17 | 2016-04-20 | Vetco Gray Scandinavia AS | Connection appliance and connection arrangement comprising such a connection appliance |
| NO335672B1 (en) * | 2013-06-10 | 2015-01-19 | Vetco Gray Scandinavia As | Device, system and method for retrieving an installation end piece |
| GB2515506B (en) * | 2013-06-25 | 2015-11-25 | Acergy France SAS | Foundations for subsea pipeline accessories |
| NO337084B1 (en) * | 2013-12-19 | 2016-01-18 | Vetco Gray Scandinavia As | Connection system for underwater connection of an underwater control cable to an underwater device |
| CN104895503B (en) * | 2015-06-08 | 2017-01-18 | 哈尔滨工程大学 | Working platform fixed on outer surfaces of underwater pipelines |
| CA3118817C (en) * | 2017-04-03 | 2026-04-07 | Fmc Technologies, Inc. | Fracturing manifold alignment systems |
| US10753182B2 (en) * | 2017-08-16 | 2020-08-25 | Trendsetter Engineering, Inc. | Subsea connection system for connecting a hot stab of a flowline to a subsea structure |
| US11320081B1 (en) * | 2019-04-04 | 2022-05-03 | Foley Patents, Llc | Method and apparatus for disconnection of hoses and other conduits |
| NO349077B1 (en) * | 2019-07-02 | 2025-09-15 | Vetco Gray Scandinavia As | Umbilical termination assembly spreader bar |
| US12025254B2 (en) * | 2021-07-23 | 2024-07-02 | Carlisle Fluid Technologies, LLC | Anti-rotate hose clamp |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US4019334A (en) * | 1976-03-17 | 1977-04-26 | Exxon Production Research Company | Method and apparatus for making subsea pipe connections |
| US5433482A (en) * | 1993-08-16 | 1995-07-18 | Oceaneering International, Inc. | Weldless pipe repair apparatus and method |
| US5458440A (en) * | 1993-03-29 | 1995-10-17 | Shell Oil Company | Offshore pipeline system |
| EP0733843A1 (en) * | 1995-03-23 | 1996-09-25 | SNAMPROGETTI S.p.A. | Method for connecting underwater pipelines particularly suitable for great depths and big diameters |
| GB2323907A (en) * | 1997-04-03 | 1998-10-07 | Sonsub Int Ltd | Method and apparatus for connecting underwater conduits |
Family Cites Families (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US3204417A (en) * | 1963-10-28 | 1965-09-07 | Gunther And Shirley Company | Underwater pipe laying apparatus |
| US3267682A (en) * | 1964-12-21 | 1966-08-23 | Gunther And Shirley Company | Method of submarine pipe laying |
| US4028903A (en) * | 1975-11-12 | 1977-06-14 | Hydrotech International, Inc. | Method and apparatus for maneuvering pipe ends in a subsea location |
| US4076130A (en) * | 1976-02-27 | 1978-02-28 | Hydrotech International, Inc. | Apparatus for mounting a coupling member over a pipe end in a subsea location |
| US4218158A (en) * | 1977-10-14 | 1980-08-19 | Tesson Prosper A | Pipe handling method and apparatus |
| US4832530A (en) * | 1988-02-08 | 1989-05-23 | Andersen Scott F | Apparatus and method for joining pipe sections underwater |
| US5730551A (en) * | 1995-11-14 | 1998-03-24 | Fmc Corporation | Subsea connector system and method for coupling subsea conduits |
| US6142708A (en) * | 1999-05-19 | 2000-11-07 | Oil States Industries Inc. | Rotating porch for subsea branch and termination pipeline connections |
| NO20002065L (en) * | 2000-04-18 | 2001-10-19 | Kongsberg Offshore As | Method for connecting submarine pipelines and a tool for such connection |
| NO321806B1 (en) * | 2001-12-11 | 2006-07-03 | Aker Kvaerner Subsea As | Underwater tool for rudder retraction |
-
2004
- 2004-05-28 US US10/558,272 patent/US7402000B2/en not_active Expired - Lifetime
- 2004-05-28 WO PCT/IB2004/001762 patent/WO2004106696A1/en not_active Ceased
- 2004-05-28 GB GB0523956A patent/GB2417534B/en not_active Expired - Lifetime
-
2005
- 2005-11-30 NO NO20055663A patent/NO337860B1/en unknown
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US4019334A (en) * | 1976-03-17 | 1977-04-26 | Exxon Production Research Company | Method and apparatus for making subsea pipe connections |
| US5458440A (en) * | 1993-03-29 | 1995-10-17 | Shell Oil Company | Offshore pipeline system |
| US5433482A (en) * | 1993-08-16 | 1995-07-18 | Oceaneering International, Inc. | Weldless pipe repair apparatus and method |
| EP0733843A1 (en) * | 1995-03-23 | 1996-09-25 | SNAMPROGETTI S.p.A. | Method for connecting underwater pipelines particularly suitable for great depths and big diameters |
| GB2323907A (en) * | 1997-04-03 | 1998-10-07 | Sonsub Int Ltd | Method and apparatus for connecting underwater conduits |
Cited By (22)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| GB2440336B (en) * | 2006-07-27 | 2008-12-17 | Verderg Connectors Ltd | Connection tool with indexing system |
| US8267179B2 (en) | 2006-07-27 | 2012-09-18 | Verderg Connectors Limited | Connection tool with indexing system |
| GB2440336A (en) * | 2006-07-27 | 2008-01-30 | Verderg Connectors Ltd | A connection tool for connecting a pipeline to a subsea connection structure |
| US8619134B2 (en) | 2009-03-11 | 2013-12-31 | Seatrepid International, Llc | Unmanned apparatus traversal and inspection system |
| US9163485B2 (en) | 2010-12-15 | 2015-10-20 | Verderg Connectors Ltd | Connection apparatus and methods |
| WO2013070077A1 (en) * | 2011-11-08 | 2013-05-16 | Ihc Holland Ie B.V. | Method and device for coupling floating pipe sections |
| EP2722479A1 (en) * | 2012-10-17 | 2014-04-23 | Vetco Gray Scandinavia AS | Subsea arrangement |
| US9732575B2 (en) | 2012-10-17 | 2017-08-15 | Vetco Gray Scandinavia As | Subsea arrangement |
| NL2010715C2 (en) * | 2013-04-26 | 2014-10-29 | Ihc Holland Ie Bv | Coupling device for dredging pipes and method for coupling dredging pipes. |
| WO2014175735A1 (en) * | 2013-04-26 | 2014-10-30 | Ihc Holland Ie B.V. | Coupling device for dredging pipes and method for coupling dredging pipes |
| WO2015197539A1 (en) * | 2014-06-23 | 2015-12-30 | Vetco Gray Scandinavia As | Pipeline termination arrangement |
| US9835270B2 (en) | 2014-06-23 | 2017-12-05 | Vetco Gray Scandinavia As | Pipeline termination arrangement |
| GB2550814B (en) * | 2015-03-03 | 2021-04-14 | Aker Solutions As | Connection system for subsea pipelines |
| GB2536622A (en) * | 2015-03-16 | 2016-09-28 | Self Energising Coupling Co Ltd | Improved subsea tie back connector |
| EP3444516A4 (en) * | 2016-04-11 | 2019-11-13 | Kawasaki Jukogyo Kabushiki Kaisha | COUPLING STRUCTURE |
| CN108884958B (en) * | 2016-04-11 | 2021-01-05 | 川崎重工业株式会社 | Joint structure |
| CN108884958A (en) * | 2016-04-11 | 2018-11-23 | 川崎重工业株式会社 | Joint structure |
| US11248726B2 (en) | 2016-04-11 | 2022-02-15 | Kawasaki Jukogyo Kabushiki Kaisha | Joint structure |
| WO2020142637A1 (en) | 2019-01-03 | 2020-07-09 | Subsea 7 (Us) Llc | Subsea connection of pipeline sections |
| GB2580351A (en) * | 2019-01-03 | 2020-07-22 | Subsea 7 Us Llc | Subsea connection of pipeline sections |
| GB2580351B (en) * | 2019-01-03 | 2021-12-22 | Subsea 7 Us Llc | Subsea connection of pipeline sections |
| US12007044B2 (en) | 2019-01-03 | 2024-06-11 | Subsea 7 (Us) Llc | Subsea connection of pipeline sections |
Also Published As
| Publication number | Publication date |
|---|---|
| GB2417534B (en) | 2006-11-08 |
| GB0523956D0 (en) | 2006-01-04 |
| NO20055663D0 (en) | 2005-11-30 |
| US7402000B2 (en) | 2008-07-22 |
| GB2417534A (en) | 2006-03-01 |
| US20070009328A1 (en) | 2007-01-11 |
| NO337860B1 (en) | 2016-07-04 |
| NO20055663L (en) | 2005-12-20 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US7402000B2 (en) | Spool piece termination structure, a connection arrangement comprising such a termination structure and a pipeline termination | |
| US7503727B2 (en) | Pipeline termination skid, a connection arrangement comprising such a pipeline termination skid and a pipeline termination | |
| EP2722571B1 (en) | Pipeline termination skid | |
| EP1281017B1 (en) | A method for connection of underwater pipelines and a tool for such connection | |
| AU2008341224B2 (en) | Tool for connecting pipelines | |
| US8408842B2 (en) | Connection arrangement for subsea connection of fluid conduits | |
| JPS5944478B2 (en) | Method for connecting submarine pipes and equipment used therefor | |
| EP2176578A2 (en) | Pipeline connection apparatus and method | |
| WO2010112920A1 (en) | Apparatus and method for the connection of conduits | |
| EP4004334B1 (en) | Horizontal connector system and method | |
| EP2746530B1 (en) | Subsea arrangement | |
| AU2011343036B2 (en) | Connection apparatus and methods | |
| US11982385B2 (en) | Subsea connection device and assembly | |
| EP3008368B1 (en) | Arrangement, system and method for retrieving a laydown head | |
| HK1189924B (en) | Connection apparatus and methods |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| AK | Designated states |
Kind code of ref document: A1 Designated state(s): AE AG AL AM AT AU AZ BA BB BG BR BW BY BZ CA CH CN CO CR CU CZ DE DK DM DZ EC EE EG ES FI GB GD GE GH GM HR HU ID IL IN IS JP KE KG KP KR KZ LC LK LR LS LT LU LV MA MD MG MK MN MW MX MZ NA NI NO NZ OM PG PH PL PT RO RU SC SD SE SG SK SL SY TJ TM TN TR TT TZ UA UG US UZ VC VN YU ZA ZM ZW |
|
| AL | Designated countries for regional patents |
Kind code of ref document: A1 Designated state(s): BW GH GM KE LS MW MZ NA SD SL SZ TZ UG ZM ZW AM AZ BY KG KZ MD RU TJ TM AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HU IE IT LU MC NL PL PT RO SE SI SK TR BF BJ CF CG CI CM GA GN GQ GW ML MR NE SN TD TG |
|
| 121 | Ep: the epo has been informed by wipo that ep was designated in this application | ||
| WWE | Wipo information: entry into national phase |
Ref document number: 0523956.1 Country of ref document: GB Ref document number: 0523956 Country of ref document: GB |
|
| WWE | Wipo information: entry into national phase |
Ref document number: 2007009328 Country of ref document: US Ref document number: 10558272 Country of ref document: US |
|
| 122 | Ep: pct application non-entry in european phase | ||
| WWP | Wipo information: published in national office |
Ref document number: 10558272 Country of ref document: US |
|
| WWW | Wipo information: withdrawn in national office |
Ref document number: 0523956.1 Country of ref document: GB |