US8612275B1 - Spreading algorithm for work and time forecasting - Google Patents

Spreading algorithm for work and time forecasting Download PDF

Info

Publication number
US8612275B1
US8612275B1 US11/195,964 US19596405A US8612275B1 US 8612275 B1 US8612275 B1 US 8612275B1 US 19596405 A US19596405 A US 19596405A US 8612275 B1 US8612275 B1 US 8612275B1
Authority
US
United States
Prior art keywords
project
phase
percentage
expended
duration
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related, expires
Application number
US11/195,964
Inventor
James L. Crum
Michael W. Kanemoto
Mathew E. Perkins
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sprint Communications Co LP
Original Assignee
Sprint Communications Co LP
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sprint Communications Co LP filed Critical Sprint Communications Co LP
Priority to US11/195,964 priority Critical patent/US8612275B1/en
Assigned to SPRINT COMMUNICATIONS COMPANY L.P. reassignment SPRINT COMMUNICATIONS COMPANY L.P. ASSIGNMENT OF ASSIGNORS INTEREST (SEE DOCUMENT FOR DETAILS). Assignors: CRUM, JAMES L., KANEMOTO, MICHAEL W., PERKINS, MATHEW E.
Application granted granted Critical
Publication of US8612275B1 publication Critical patent/US8612275B1/en
Assigned to DEUTSCHE BANK TRUST COMPANY AMERICAS reassignment DEUTSCHE BANK TRUST COMPANY AMERICAS GRANT OF FIRST PRIORITY AND JUNIOR PRIORITY SECURITY INTEREST IN PATENT RIGHTS Assignors: SPRINT COMMUNICATIONS COMPANY L.P.
Assigned to SPRINT COMMUNICATIONS COMPANY L.P. reassignment SPRINT COMMUNICATIONS COMPANY L.P. TERMINATION AND RELEASE OF FIRST PRIORITY AND JUNIOR PRIORITY SECURITY INTEREST IN PATENT RIGHTS Assignors: DEUTSCHE BANK TRUST COMPANY AMERICAS
Expired - Fee Related legal-status Critical Current
Adjusted expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/109Time management, e.g. calendars, reminders, meetings or time accounting
    • G06Q10/1091Recording time for administrative or management purposes

Definitions

  • the present disclosure is directed to manpower forecasting, and more particularly, but not by way of limitation, to a spreading algorithm for work and time forecasting.
  • Development projects in enterprises may include several sub-divisions or tasks to be completed.
  • the work of completing tasks may be divided into several phases, and the several tasks making up a project may be expected to complete each of the phases at the same time.
  • Personnel for example task team leaders, may estimate the amount of resources needed during the development project so that adequate resources are available to make timely progress in each of the work phases.
  • Resources may include hours to be worked by appropriately skilled developers and/or costs including overhead costs, software tool leasing costs, training costs, and other expenditure costs.
  • a method of forecasting work hours per unit of time includes estimating a project hour budget.
  • the method includes determining a percentage of the project hour budget to be expended in each of a plurality of project phases based on average percentages of project hour budgets expended in each project phase in completed projects.
  • the method includes distributing the project hour budget across a plurality of units of time based on the percentage of the project hour budget to be expended in each project phase, on the project hour budget, and on a schedule of project milestones.
  • a system for distributing budget hours is also provided according to another embodiment.
  • the system includes a data store including a project hour budget, a schedule percentage of project hour budget to be expended in each of a plurality of project phases, and a schedule percentage of project duration to be expended in each of the plurality of project phases.
  • the system also includes an analysis tool that generates a distribution of project hours to each of a plurality of periods of duration based on the project hour budget. The distribution of project hours further based on the schedule percentage of project hour budget to be expended in each project phase and the schedule percentage of project duration to be expended in each project phase.
  • the analysis tool also generates a report containing the distribution of project hours to the periods of duration.
  • a method of forecasting comprises projecting resource expenditure over each of a plurality of units of time over the course of a project based on a resource budget.
  • the resource expenditure is further based on a definition of a duration of project phases as a percentage of a total project duration, a project start date, a project end date and an estimate of a percentage of resources to be expended during each project phase.
  • FIG. 1 is a block diagram of a resource spreading system according to an embodiment of the present disclosure.
  • FIGS. 2A , 2 B, and 2 C depict an exemplary project lifecycle, project schedule, and resource schedule according to an embodiment of the present disclosure.
  • FIG. 3 is a logic flow diagram of a process suitable for practicing embodiments of the present disclosure.
  • FIG. 4 illustrates an exemplary general purpose computer system suitable for implementing the several embodiments of the disclosure.
  • the number of personnel needed to staff a project or task development effort may vary from one phase to the next phase. Depending on the duration of phases, the staffing levels may vary from one project to the next. In large projects or in large organizations projecting needed staffing levels can be difficult and challenging. Errors in projecting or estimating needs may result in a sudden, unanticipated drop-off of staffing needs that may result in a layoff of surplus personnel.
  • a method and tool of spreading estimated resource consumption across the different phases of a project based on a defined resource consumption schedule for each phase of the task is described below.
  • the consumption schedule employed may be a generic consumption schedule based on averages calculated from actual charged hours and costs from completed projects. Alternatively, a custom consumption schedule may be provided for individual projects to accommodate special characteristics unique to the individual project.
  • FIG. 1 a block diagram of a system 100 for spreading resource estimates is depicted.
  • the system 100 comprises an analyzer component 102 , a spreading data store 104 , and an actuals data store 106 .
  • the actuals data store 106 stores historical data from completed projects.
  • the analyzer component 102 may be a computer program or application and is suitable to be executed on any general purpose computer system.
  • the spreading data store 104 and the actuals data store 106 may be implemented by using a general purpose computer system. General purpose computer systems are described in greater detail hereinafter.
  • the project lifecycle 114 may comprise a requirements analysis phase 115 , a design phase 116 , a development phase 117 , and a deployment phase 118 .
  • the main work of the project flows from the requirements analysis phase 115 , to the design phase 116 , to the development phase 117 , and to the deployment phase 118 , but some time may be spent in any given phase reworking some of the tasks associated with the previous phases.
  • the requirements analysis phase 115 is directed to identifying the functional behavior expected and or desired by the project consumer, for example a customer, and identifying appropriate engineering requirements of a system that can provide the desired functional behavior.
  • the design phase 116 is directed to crafting an architecture or a skeleton of a system that provides the functional behavior.
  • the results of the requirements phase 115 typically provides guidance to the design phase 116 or defines, at a high level, what is to be designed.
  • the design phase 116 may involve identifying a system of cooperating software and/or hardware components, defining the interfaces among these components, defining software tasks, and defining software classes within each software task.
  • the design phase 116 may involve determining a projected processing load of an application and planning how to distribute the processing load across multiple hosts or computers.
  • the design phase 116 may involve identifying a growth path for scaling up the design as the processing load increases over time, for example as corporate accounts increase in number.
  • the design phase 116 typically provides guidance to the development phase 117 or defines what is to be built.
  • the development phase 117 is directed to building a working system in accordance with the design and testing the system in accordance with the requirements. Because the development phase 117 is large, in some embodiments it may be further partitioned into additional phases, for example an implementation phase, a unit test phase, a system integration phase, and a system test phase.
  • the completed system provided by the development phase 117 provides the system that is deployed during the deployment phase 118 , for example installing a working system in the facility of a customer.
  • the deployment phase 118 may also include a warranty period during which the enterprise repairs problems in the system reported by users or the customer.
  • the spreading data store 104 contains project and task information that may be used by the analyzer 102 to determine an estimate or forecast of resource consumption per unit of time.
  • the spreading data store 104 contains a project schedule identifying the duration of each of the phases of the project.
  • the project schedule may include a start date and an end date of the project.
  • the duration of each phase may be defined as a percentage of the project duration.
  • an exemplary project schedule 122 is illustrated with the percentages of the project duration consumed by each phase. It has been observed that the duration of project phases tend to consume a constant percentage of total project duration or calendar time. This is contrary to expectation in that applying twice as many personnel resources to the task of requirements analysis, for example, may be expected to reduce the duration of the requirements analysis phase by half, but the expected reduction does not occur and in fact the duration may remain substantially unchanged. It may be that fixed time lags associated with interacting with other personnel, for example scheduling meetings, constrain progress.
  • the percentages may be based on, for example, data from completed projects which is maintained in the spreading data store 104 or actuals data store 106 .
  • the requirements analysis phase 115 is depicted as consuming 20% of the duration of the project
  • the design phase 116 is depicted as consuming 25% of the duration of the project
  • the development phase 117 is depicted as consuming 40% of the duration of the project
  • the deployment phase 118 is depicted as consuming 15% of the duration of the project.
  • the deployment phase 118 may consume a fixed time duration, for example thirty days.
  • the durations of the remaining project phases are defined as a percentage of project duration exclusive of the deployment phase 118 .
  • the spreading data store 104 also contains a generic task resource consumption schedule identifying the percentage of resources, for example budget hours, that are typically expended during each task phase. It has been observed that the magnitude of effort consumed in each phase of projects, as a percentage of total project effort, tends to be constant and independent from the scale of the project. For example, it may be that approximately twenty percent of project effort is consumed in requirements analysis whether the project is a 10,000 hour project or a 100,000 hour project.
  • the requirements analysis phase 115 is depicted as consuming 10% of project resources
  • the design phase 116 is depicted consuming 25% of project resources
  • the development phase 117 is depicted consuming 60% of project resources
  • the deployment phase 118 is depicted consuming 5% of project resources.
  • the generic task resource consumption schedule is based on a record of resource consumption from previously completed tasks. This information may be generated, for example, by the analyzer component 102 working on information stored in the actuals data store 106 .
  • the analyzer component 102 selects data of appropriate dates from the actuals data store 106 , for example data from the last six months of completed projects.
  • Data contained by the actuals data store 106 may be stored along with an appropriate indication of the time and date the data was stored, which may be referred to as a time-date stamp of the data.
  • the analyzer component 102 may select from available data in the actuals data store 106 based on the time-date stamp of the data. Older data, for example three year old data, may not be as applicable as more recent data because processes may have changed.
  • the spreading data store 104 may contain one or more custom task resource consumption schedules. Some tasks may not conform to the typical resource consumption schedule. For example, an architecture task may consume all of the resources allocated to the task during the requirements analysis and design phases. For example, a project to develop embedded software to execute on a processor adapted to a special environment and employing specialized interfaces may consume more resources in the development phase 117 due to additional system integration activities. Users of the system 100 may define these custom task resource consumption schedules using a spreadsheet program or other data entry mechanism, for example entering an arbitrary percentage for each of the project phases, the sum of the percentages adding up to 100%.
  • the generic task resource consumption schedule, the custom task resource consumption schedules, and the project schedule may be stored as spreadsheets in the spreading data store 104 .
  • the analyzer component 102 generates the resource schedule of resource expenditure per unit of time for one or more tasks.
  • the unit of time also referred to as periods of duration, may be weeks, months, or some other preferred unit of time.
  • the analyzer component 102 may store the estimated schedules of resource expenditure in the spreading data store 104 .
  • the analyzer component 102 may also generate a report 108 including the estimated schedule of resource expenditure for one or more tasks.
  • the analyzer 102 accesses the information stored in the spreading data store 104 and determines the estimated resource consumption per unit time of each phase as:
  • the exemplary project schedule 122 is employed.
  • the first project is scheduled to start on January 1, and complete on December 31, and has an estimated level of effort of 400,000 hours.
  • the requirements analysis phase 115 will consume 10.4 weeks
  • the design phase 116 will consume 13 weeks
  • the development phase will consume 20.8 weeks
  • the deployment phase 118 will consume 7.8 weeks.
  • these phases may be rounded so that the requirements analysis phase 115 will consume 10 weeks
  • the design phase 116 will consume 13 weeks
  • the development phase will consume 21 weeks
  • the deployment phase 118 will consume 8 weeks.
  • the exemplary resource schedule 126 is employed.
  • the requirements analysis phase 115 will consume 40,000 hours, the design phase 116 will consume 100,000 hours, the development phase will consume 240,000 hours, and the deployment phase 118 will consume 20,000 hours.
  • the requirements analysis phase 115 will consume about 4,000 hours per week from January 1 to about March 12, the design phase 116 will consume about 7,692 hours per week from about March 13 to about June 11, the development phase will consume about 11,429 hours per week from about June 12 to about November 5, and the deployment phase 118 will consume about 2,500 hours per week from about November 6 to December 31.
  • the exemplary project schedule 122 is employed and the exemplary resource schedule 126 is employed, but the development phase is sub-divided into a coding sub-phase that consumes 70% of both development time and level of effort, a unit testing sub-phase that consumes 10% of both development time and level of effort, and a system testing sub-phase that consumes 20% of both development time and level of effort.
  • the coding sub-phase will consume about 11,200 hours per week from about June 12 to about September 24, the unit test sub-phase will consume about 11,400 hours per week from about September 25 to about October 8, and the system test sub-phase will consume about 11,400 hours per week from about October 9 to about November 5.
  • the dates and weekly hour consumption rate for the other project phases remains unchanged.
  • the percentages for duration and resource consumption of the sub-task phases are identical, but in other embodiments different percentages may be employed.
  • the deployment phase 118 is a fixed 30 day interval.
  • the project schedule allocates 25% of the schedule to the requirements analysis phase 115 , 35% of the schedule to the design phase 116 , and 40% of the schedule to the development phase for a total of 100%.
  • the third project is scheduled to start on January 1 and to complete, through the end of the development phase 117 , by about November 30.
  • the third project has an estimated level of effort of 400,000 hours and uses the exemplary resource schedule 126 .
  • the requirements analysis phase 115 will consume about 40,000 hours over about 12 weeks at a rate of about 3,333 hours per week.
  • the design phase 116 will consume about 100,000 hours over about 17 weeks at a rate of about 5,882 hours per week.
  • the development phase 117 will consume about 240,000 hours over about 19 weeks at a rate of about 12,632 hours per week.
  • the Deployment phase 118 will consume about 20,000 hours over 30 days at a rate of about 5,000 hours per week.
  • a custom resource schedule 126 is employed.
  • the custom resource schedule 126 calls for using 60% of hour resources in the requirements analysis phase 115 and 40% of hour resources in the design phase 116 .
  • This custom resource schedule 126 may apply, for example, for an architecting project or an architecting portion of a project.
  • the fourth exemplary project is scheduled to start January 1, complete about June 11, and consume about 6,000 hours. Based on this information, the requirements analysis phase 115 will consume about 3,600 hours from January 1 to about March 12 at a rate of about 360 hours per week.
  • the design phase 116 will consume about 2,400 hours from about March 13 to about June 11 at a rate of about 171 hours per week.
  • a duration of the phases of the project are defined. This definition may take the form of a project start date, a project end date, and a definition of what percentage of project duration is consumed in each phase. This information may be stored in a spreadsheet.
  • the durations of the project phases may be used to determine project schedule milestone dates, for example an end of the requirements analysis phase 115 , an end of the design phase 116 , an end of the development phase 117 , and an end of the deployment phase 118 .
  • the process proceeds to block 132 where the average resource consumption per project phase is determined based on historical data, for example by analyzing the data contained by the actuals data store 106 .
  • the results may be expressed as percentages of total project duration in order to make the results more readily applicable to projects having different lengths. This may be referred to as a generic task resource consumption schedule.
  • the actuals used to determine the averages may be selected from a desirable time period to be representative of current processes.
  • the process proceeds to block 134 where if a custom task resource consumption schedule is desired the process proceeds to block 136 where the custom task resource consumption schedule is defined, as for example by entering data into a spreadsheet.
  • the process proceeds to block 138 where the total amount of resources budgeted for the task, for example a level-of-effort estimate, is defined.
  • the process proceeds to block 140 where the resources to be expended per unit of time for each phase of the subject task are determined and stored. The determination is based on the task resource consumption schedule that applies, either the generic task resource consumption schedule or the custom task resource consumption schedule. The determination is also based on the total amount of resources allocated for the task, and the durations of the project phases. The determination of resources to be expended per unit of time for each phase is stored in the spreading data store 104 for each task.
  • the process proceeds to block 142 where if more tasks remain to have their resource consumption per unit time determined, the process returns to block 134 .
  • the process exits.
  • a final report exhibiting the estimated resource expenditure per unit of time for each phase for all the tasks is generated before the process exits.
  • the unit of time also referred to as periods of duration, may be weeks, months, or some other preferred unit of time.
  • FIG. 4 illustrates a typical, general-purpose computer system suitable for implementing one or more embodiments disclosed herein.
  • the computer system 380 includes a processor 382 (which may be referred to as a central processor unit or CPU) that is in communication with memory devices including secondary storage 384 , read only memory (ROM) 386 , random access memory (RAM) 388 , input/output (I/O) 390 devices, and network connectivity devices 392 .
  • the processor may be implemented as one or more CPU chips.
  • the secondary storage 384 is typically comprised of one or more disk drives or tape drives and is used for non-volatile storage of data and as an over-flow data storage device if RAM 388 is not large enough to hold all working data. Secondary storage 384 may be used to store programs which are loaded into RAM 388 when such programs are selected for execution.
  • the ROM 386 is used to store instructions and perhaps data which are read during program execution. ROM 386 is a non-volatile memory device which typically has a small memory capacity relative to the larger memory capacity of secondary storage.
  • the RAM 388 is used to store volatile data and perhaps to store instructions. Access to both ROM 386 and RAM 388 is typically faster than to secondary storage 384 .
  • I/O 390 devices may include printers, video monitors, liquid crystal displays (LCDs), touch screen displays, keyboards, keypads, switches, dials, mice, track balls, voice recognizers, card readers, paper tape readers, or other well-known input devices.
  • the network connectivity devices 392 may take the form of modems, modem banks, ethernet cards, universal serial bus (USB) interface cards, serial interfaces, token ring cards, fiber distributed data interface (FDDI) cards, wireless local area network (WLAN) cards, radio transceiver cards such as code division multiple access (CDMA) and/or global system for mobile communications (GSM) radio transceiver cards, and other well-known network devices.
  • These network connectivity 392 devices may enable the processor 382 to communicate with an Internet or one or more intranets. With such a network connection, it is contemplated that the processor 382 might receive information from the network, or might output information to the network in the course of performing the above-described method steps. Such information, which is often represented as a sequence of instructions to be executed using processor 382 , may be received from and outputted to the network, for example, in the form of a computer data signal embodied in a carrier wave
  • Such information may be received from and outputted to the network, for example, in the form of a computer data baseband signal or signal embodied in a carrier wave.
  • the baseband signal or signal embodied in the carrier wave generated by the network connectivity 392 devices may propagate in or on the surface of electrical conductors, in coaxial cables, in waveguides, in optical media, for example optical fiber, or in the air or free space.
  • the information contained in the baseband signal or signal embedded in the carrier wave may be ordered according to different sequences, as may be desirable for either processing or generating the information or transmitting or receiving the information.
  • the baseband signal or signal embedded in the carrier wave, or other types of signals currently used or hereafter developed, referred to herein as the transmission medium may be generated according to several methods well known to one skilled in the art.
  • the processor 382 executes instructions, codes, computer programs, scripts which it accesses from hard disk, floppy disk, optical disk (these various disk based systems may all be considered secondary storage 384 ), ROM 386 , RAM 388 , or the network connectivity devices 392 .

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Operations Research (AREA)
  • Economics (AREA)
  • Marketing (AREA)
  • Data Mining & Analysis (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Educational Administration (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

A method of forecasting work hours per unit of time is provided. The method comprises estimating a project hour budget, determining a percentage of the project hour budget to be expended in each of a plurality of project phases based on average percentages of project hour budgets expended in each project phase in completed projects, and distributing the project hour budget across a plurality of units of time based on the percentage of the project hour budget to be expended in each project phase, on the project hour budget, and on a schedule of project milestones.

Description

CROSS-REFERENCE TO RELATED APPLICATIONS
This application includes subject matter related to U.S. patent application Ser. No. 11/196,692, filed Aug. 3, 2005, entitled “Milestone Initial Scheduling,” by Michael W. Kanemoto, et al, which is hereby incorporated by reference for all purposes.
STATEMENT REGARDING FEDERALLY SPONSORED RESEARCH OR DEVELOPMENT
Not applicable.
REFERENCE TO A MICROFICHE APPENDIX
Not applicable.
FIELD OF THE INVENTION
The present disclosure is directed to manpower forecasting, and more particularly, but not by way of limitation, to a spreading algorithm for work and time forecasting.
BACKGROUND OF THE INVENTION
Development projects in enterprises may include several sub-divisions or tasks to be completed. The work of completing tasks may be divided into several phases, and the several tasks making up a project may be expected to complete each of the phases at the same time. Personnel, for example task team leaders, may estimate the amount of resources needed during the development project so that adequate resources are available to make timely progress in each of the work phases. Resources may include hours to be worked by appropriately skilled developers and/or costs including overhead costs, software tool leasing costs, training costs, and other expenditure costs.
SUMMARY OF THE INVENTION
According to one embodiment, a method of forecasting work hours per unit of time is provided. The method includes estimating a project hour budget. The method includes determining a percentage of the project hour budget to be expended in each of a plurality of project phases based on average percentages of project hour budgets expended in each project phase in completed projects. The method includes distributing the project hour budget across a plurality of units of time based on the percentage of the project hour budget to be expended in each project phase, on the project hour budget, and on a schedule of project milestones.
A system for distributing budget hours is also provided according to another embodiment. The system includes a data store including a project hour budget, a schedule percentage of project hour budget to be expended in each of a plurality of project phases, and a schedule percentage of project duration to be expended in each of the plurality of project phases. The system also includes an analysis tool that generates a distribution of project hours to each of a plurality of periods of duration based on the project hour budget. The distribution of project hours further based on the schedule percentage of project hour budget to be expended in each project phase and the schedule percentage of project duration to be expended in each project phase. The analysis tool also generates a report containing the distribution of project hours to the periods of duration.
According to still other embodiments, a method of forecasting is also provided. The method comprises projecting resource expenditure over each of a plurality of units of time over the course of a project based on a resource budget. The resource expenditure is further based on a definition of a duration of project phases as a percentage of a total project duration, a project start date, a project end date and an estimate of a percentage of resources to be expended during each project phase.
These and other features and advantages will be more clearly understood from the following detailed description taken in conjunction with the accompanying drawings and claims.
BRIEF DESCRIPTION OF THE DRAWINGS
For a more complete understanding of the present disclosure and the advantages thereof, reference is now made to the following brief description, taken in connection with the accompanying drawings and detailed description, wherein like reference numerals represent like parts.
FIG. 1 is a block diagram of a resource spreading system according to an embodiment of the present disclosure.
FIGS. 2A, 2B, and 2C depict an exemplary project lifecycle, project schedule, and resource schedule according to an embodiment of the present disclosure.
FIG. 3 is a logic flow diagram of a process suitable for practicing embodiments of the present disclosure.
FIG. 4 illustrates an exemplary general purpose computer system suitable for implementing the several embodiments of the disclosure.
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
It should be understood at the outset that although an exemplary implementation of one embodiment of the present disclosure is illustrated below, the present system may be implemented using any number of techniques, whether currently known or in existence. The present disclosure should in no way be limited to the exemplary implementations, drawings, and techniques illustrated below, including the exemplary design and implementation illustrated and described herein.
The number of personnel needed to staff a project or task development effort may vary from one phase to the next phase. Depending on the duration of phases, the staffing levels may vary from one project to the next. In large projects or in large organizations projecting needed staffing levels can be difficult and challenging. Errors in projecting or estimating needs may result in a sudden, unanticipated drop-off of staffing needs that may result in a layoff of surplus personnel. A method and tool of spreading estimated resource consumption across the different phases of a project based on a defined resource consumption schedule for each phase of the task is described below. The consumption schedule employed may be a generic consumption schedule based on averages calculated from actual charged hours and costs from completed projects. Alternatively, a custom consumption schedule may be provided for individual projects to accommodate special characteristics unique to the individual project. By using appropriate consumption schedules to estimate resource consumption in each of the phases of a task greater insight into and understanding of future needs may be obtained, thereby contributing to more reliable achievement of management goals. An insight of the disclosure is that the percentage of project duration expended in different project phases is independent of the percentage of project effort expended in the associated project phases.
Turning now to FIG. 1, a block diagram of a system 100 for spreading resource estimates is depicted. The system 100 comprises an analyzer component 102, a spreading data store 104, and an actuals data store 106. The actuals data store 106 stores historical data from completed projects. The analyzer component 102 may be a computer program or application and is suitable to be executed on any general purpose computer system. The spreading data store 104 and the actuals data store 106 may be implemented by using a general purpose computer system. General purpose computer systems are described in greater detail hereinafter.
Turning to FIG. 2A, an exemplary project lifecycle 114 is illustrated. In an embodiment, the project lifecycle 114 may comprise a requirements analysis phase 115, a design phase 116, a development phase 117, and a deployment phase 118. Generally, the main work of the project flows from the requirements analysis phase 115, to the design phase 116, to the development phase 117, and to the deployment phase 118, but some time may be spent in any given phase reworking some of the tasks associated with the previous phases. For example, during the development phase 117, unresolved design and requirements issues may be discovered causing some additional work to be done in both the requirements analysis phase 115 and the design phase 116. The requirements analysis phase 115 is directed to identifying the functional behavior expected and or desired by the project consumer, for example a customer, and identifying appropriate engineering requirements of a system that can provide the desired functional behavior.
The design phase 116 is directed to crafting an architecture or a skeleton of a system that provides the functional behavior. The results of the requirements phase 115 typically provides guidance to the design phase 116 or defines, at a high level, what is to be designed. The design phase 116, for example, may involve identifying a system of cooperating software and/or hardware components, defining the interfaces among these components, defining software tasks, and defining software classes within each software task. The design phase 116 may involve determining a projected processing load of an application and planning how to distribute the processing load across multiple hosts or computers. The design phase 116 may involve identifying a growth path for scaling up the design as the processing load increases over time, for example as corporate accounts increase in number. The design phase 116 typically provides guidance to the development phase 117 or defines what is to be built. The development phase 117 is directed to building a working system in accordance with the design and testing the system in accordance with the requirements. Because the development phase 117 is large, in some embodiments it may be further partitioned into additional phases, for example an implementation phase, a unit test phase, a system integration phase, and a system test phase. The completed system provided by the development phase 117 provides the system that is deployed during the deployment phase 118, for example installing a working system in the facility of a customer. The deployment phase 118 may also include a warranty period during which the enterprise repairs problems in the system reported by users or the customer.
The spreading data store 104 contains project and task information that may be used by the analyzer 102 to determine an estimate or forecast of resource consumption per unit of time. The spreading data store 104 contains a project schedule identifying the duration of each of the phases of the project. The project schedule may include a start date and an end date of the project. The duration of each phase may be defined as a percentage of the project duration.
Turning now to FIG. 2B, an exemplary project schedule 122 is illustrated with the percentages of the project duration consumed by each phase. It has been observed that the duration of project phases tend to consume a constant percentage of total project duration or calendar time. This is contrary to expectation in that applying twice as many personnel resources to the task of requirements analysis, for example, may be expected to reduce the duration of the requirements analysis phase by half, but the expected reduction does not occur and in fact the duration may remain substantially unchanged. It may be that fixed time lags associated with interacting with other personnel, for example scheduling meetings, constrain progress.
The percentages may be based on, for example, data from completed projects which is maintained in the spreading data store 104 or actuals data store 106. The requirements analysis phase 115 is depicted as consuming 20% of the duration of the project, the design phase 116 is depicted as consuming 25% of the duration of the project, the development phase 117 is depicted as consuming 40% of the duration of the project, and the deployment phase 118 is depicted as consuming 15% of the duration of the project. In an alternate embodiment, the deployment phase 118 may consume a fixed time duration, for example thirty days. In the fixed time duration deployment phase 118 embodiment, the durations of the remaining project phases are defined as a percentage of project duration exclusive of the deployment phase 118.
The spreading data store 104 also contains a generic task resource consumption schedule identifying the percentage of resources, for example budget hours, that are typically expended during each task phase. It has been observed that the magnitude of effort consumed in each phase of projects, as a percentage of total project effort, tends to be constant and independent from the scale of the project. For example, it may be that approximately twenty percent of project effort is consumed in requirements analysis whether the project is a 10,000 hour project or a 100,000 hour project.
Turning now to FIG. 2C, an exemplary resource schedule 126 is depicted. The requirements analysis phase 115 is depicted as consuming 10% of project resources, the design phase 116 is depicted consuming 25% of project resources, the development phase 117 is depicted consuming 60% of project resources, and the deployment phase 118 is depicted consuming 5% of project resources. The generic task resource consumption schedule is based on a record of resource consumption from previously completed tasks. This information may be generated, for example, by the analyzer component 102 working on information stored in the actuals data store 106.
In a preferred embodiment, the analyzer component 102 selects data of appropriate dates from the actuals data store 106, for example data from the last six months of completed projects. Data contained by the actuals data store 106, for example actual reporting data on hours worked on specific projects, may be stored along with an appropriate indication of the time and date the data was stored, which may be referred to as a time-date stamp of the data. The analyzer component 102 may select from available data in the actuals data store 106 based on the time-date stamp of the data. Older data, for example three year old data, may not be as applicable as more recent data because processes may have changed. It may be that data from special ranges of dates may be deemed extraordinary and/or not typical, for example data from the months of November, December, and/or January when an above average amount of vacation may be consumed by staff. The same generic task consumption schedule may be employed to spread resource estimates for all tasks for a given project.
The spreading data store 104 may contain one or more custom task resource consumption schedules. Some tasks may not conform to the typical resource consumption schedule. For example, an architecture task may consume all of the resources allocated to the task during the requirements analysis and design phases. For example, a project to develop embedded software to execute on a processor adapted to a special environment and employing specialized interfaces may consume more resources in the development phase 117 due to additional system integration activities. Users of the system 100 may define these custom task resource consumption schedules using a spreadsheet program or other data entry mechanism, for example entering an arbitrary percentage for each of the project phases, the sum of the percentages adding up to 100%. The generic task resource consumption schedule, the custom task resource consumption schedules, and the project schedule may be stored as spreadsheets in the spreading data store 104.
The analyzer component 102 generates the resource schedule of resource expenditure per unit of time for one or more tasks. The unit of time, also referred to as periods of duration, may be weeks, months, or some other preferred unit of time. The analyzer component 102 may store the estimated schedules of resource expenditure in the spreading data store 104. The analyzer component 102 may also generate a report 108 including the estimated schedule of resource expenditure for one or more tasks. In an embodiment to generate an estimated schedule or resource expenditure, the analyzer 102 accesses the information stored in the spreading data store 104 and determines the estimated resource consumption per unit time of each phase as:
estimate = { 100 ( P d ) ( φ d ) } { T φ % 100 } LOE = LOE × T φ % P d × φ d ( 1 )
where Pd is the total project duration in an appropriate time unit, φd is the duration of the subject project phase as a percentage of the total project duration, Tφ% is the percentage of task resources scheduled to be consumed during the subject project phase, and LOE is the total of resources allocated for the subject task. For the deploy-warranty phase, if a fixed time duration is assumed, the fixed duration time expressed in the appropriate units replaces the factor Pd×φd. In another embodiment, a different equation may be employed. In another embodiment, the equation may be elaborated to take account of different labor rates of different responsibilities and/or non-constant hour consumption schedules within a project phase.
Several exemplary projects are now discussed. In a first exemplary project, the exemplary project schedule 122 is employed. The first project is scheduled to start on January 1, and complete on December 31, and has an estimated level of effort of 400,000 hours. Based on this information, the requirements analysis phase 115 will consume 10.4 weeks, the design phase 116 will consume 13 weeks, the development phase will consume 20.8 weeks, and the deployment phase 118 will consume 7.8 weeks. Assuming the preferred time unit is the week, these phases may be rounded so that the requirements analysis phase 115 will consume 10 weeks, the design phase 116 will consume 13 weeks, the development phase will consume 21 weeks, and the deployment phase 118 will consume 8 weeks. In the first project, the exemplary resource schedule 126 is employed. Based on this information, the requirements analysis phase 115 will consume 40,000 hours, the design phase 116 will consume 100,000 hours, the development phase will consume 240,000 hours, and the deployment phase 118 will consume 20,000 hours. The requirements analysis phase 115 will consume about 4,000 hours per week from January 1 to about March 12, the design phase 116 will consume about 7,692 hours per week from about March 13 to about June 11, the development phase will consume about 11,429 hours per week from about June 12 to about November 5, and the deployment phase 118 will consume about 2,500 hours per week from about November 6 to December 31.
In a second exemplary project, the exemplary project schedule 122 is employed and the exemplary resource schedule 126 is employed, but the development phase is sub-divided into a coding sub-phase that consumes 70% of both development time and level of effort, a unit testing sub-phase that consumes 10% of both development time and level of effort, and a system testing sub-phase that consumes 20% of both development time and level of effort. Based on this information, the coding sub-phase will consume about 11,200 hours per week from about June 12 to about September 24, the unit test sub-phase will consume about 11,400 hours per week from about September 25 to about October 8, and the system test sub-phase will consume about 11,400 hours per week from about October 9 to about November 5. The dates and weekly hour consumption rate for the other project phases remains unchanged. In the second project, the percentages for duration and resource consumption of the sub-task phases are identical, but in other embodiments different percentages may be employed.
In a third exemplary project, the deployment phase 118 is a fixed 30 day interval. In the third project the project schedule allocates 25% of the schedule to the requirements analysis phase 115, 35% of the schedule to the design phase 116, and 40% of the schedule to the development phase for a total of 100%. The third project is scheduled to start on January 1 and to complete, through the end of the development phase 117, by about November 30. The third project has an estimated level of effort of 400,000 hours and uses the exemplary resource schedule 126. Based on this information, the requirements analysis phase 115 will consume about 40,000 hours over about 12 weeks at a rate of about 3,333 hours per week. The design phase 116 will consume about 100,000 hours over about 17 weeks at a rate of about 5,882 hours per week. The development phase 117 will consume about 240,000 hours over about 19 weeks at a rate of about 12,632 hours per week. The Deployment phase 118 will consume about 20,000 hours over 30 days at a rate of about 5,000 hours per week.
In a fourth exemplary project is similar to the first exemplary project, except that a custom resource schedule 126 is employed. The custom resource schedule 126 calls for using 60% of hour resources in the requirements analysis phase 115 and 40% of hour resources in the design phase 116. This custom resource schedule 126 may apply, for example, for an architecting project or an architecting portion of a project. The fourth exemplary project is scheduled to start January 1, complete about June 11, and consume about 6,000 hours. Based on this information, the requirements analysis phase 115 will consume about 3,600 hours from January 1 to about March 12 at a rate of about 360 hours per week. The design phase 116 will consume about 2,400 hours from about March 13 to about June 11 at a rate of about 171 hours per week.
Turning now to FIG. 3, a process of estimating the resource consumption per unit time for each phase of tasks associated with a project is depicted. In block 130 a duration of the phases of the project are defined. This definition may take the form of a project start date, a project end date, and a definition of what percentage of project duration is consumed in each phase. This information may be stored in a spreadsheet. In an embodiment, the durations of the project phases may be used to determine project schedule milestone dates, for example an end of the requirements analysis phase 115, an end of the design phase 116, an end of the development phase 117, and an end of the deployment phase 118.
The process proceeds to block 132 where the average resource consumption per project phase is determined based on historical data, for example by analyzing the data contained by the actuals data store 106. The results may be expressed as percentages of total project duration in order to make the results more readily applicable to projects having different lengths. This may be referred to as a generic task resource consumption schedule. The actuals used to determine the averages may be selected from a desirable time period to be representative of current processes.
The process proceeds to block 134 where if a custom task resource consumption schedule is desired the process proceeds to block 136 where the custom task resource consumption schedule is defined, as for example by entering data into a spreadsheet. The process proceeds to block 138 where the total amount of resources budgeted for the task, for example a level-of-effort estimate, is defined. The process proceeds to block 140 where the resources to be expended per unit of time for each phase of the subject task are determined and stored. The determination is based on the task resource consumption schedule that applies, either the generic task resource consumption schedule or the custom task resource consumption schedule. The determination is also based on the total amount of resources allocated for the task, and the durations of the project phases. The determination of resources to be expended per unit of time for each phase is stored in the spreading data store 104 for each task.
The process proceeds to block 142 where if more tasks remain to have their resource consumption per unit time determined, the process returns to block 134. When all tasks have had their resource consumption per unit time determined the process exits. In an embodiment, a final report exhibiting the estimated resource expenditure per unit of time for each phase for all the tasks is generated before the process exits. The unit of time, also referred to as periods of duration, may be weeks, months, or some other preferred unit of time.
The system described above may be implemented on any general-purpose computer with sufficient processing power, memory resources, and network throughput capability to handle the necessary workload placed upon it. FIG. 4 illustrates a typical, general-purpose computer system suitable for implementing one or more embodiments disclosed herein. The computer system 380 includes a processor 382 (which may be referred to as a central processor unit or CPU) that is in communication with memory devices including secondary storage 384, read only memory (ROM) 386, random access memory (RAM) 388, input/output (I/O) 390 devices, and network connectivity devices 392. The processor may be implemented as one or more CPU chips.
The secondary storage 384 is typically comprised of one or more disk drives or tape drives and is used for non-volatile storage of data and as an over-flow data storage device if RAM 388 is not large enough to hold all working data. Secondary storage 384 may be used to store programs which are loaded into RAM 388 when such programs are selected for execution. The ROM 386 is used to store instructions and perhaps data which are read during program execution. ROM 386 is a non-volatile memory device which typically has a small memory capacity relative to the larger memory capacity of secondary storage. The RAM 388 is used to store volatile data and perhaps to store instructions. Access to both ROM 386 and RAM 388 is typically faster than to secondary storage 384.
I/O 390 devices may include printers, video monitors, liquid crystal displays (LCDs), touch screen displays, keyboards, keypads, switches, dials, mice, track balls, voice recognizers, card readers, paper tape readers, or other well-known input devices. The network connectivity devices 392 may take the form of modems, modem banks, ethernet cards, universal serial bus (USB) interface cards, serial interfaces, token ring cards, fiber distributed data interface (FDDI) cards, wireless local area network (WLAN) cards, radio transceiver cards such as code division multiple access (CDMA) and/or global system for mobile communications (GSM) radio transceiver cards, and other well-known network devices. These network connectivity 392 devices may enable the processor 382 to communicate with an Internet or one or more intranets. With such a network connection, it is contemplated that the processor 382 might receive information from the network, or might output information to the network in the course of performing the above-described method steps. Such information, which is often represented as a sequence of instructions to be executed using processor 382, may be received from and outputted to the network, for example, in the form of a computer data signal embodied in a carrier wave
Such information, which may include data or instructions to be executed using processor 382 for example, may be received from and outputted to the network, for example, in the form of a computer data baseband signal or signal embodied in a carrier wave. The baseband signal or signal embodied in the carrier wave generated by the network connectivity 392 devices may propagate in or on the surface of electrical conductors, in coaxial cables, in waveguides, in optical media, for example optical fiber, or in the air or free space. The information contained in the baseband signal or signal embedded in the carrier wave may be ordered according to different sequences, as may be desirable for either processing or generating the information or transmitting or receiving the information. The baseband signal or signal embedded in the carrier wave, or other types of signals currently used or hereafter developed, referred to herein as the transmission medium, may be generated according to several methods well known to one skilled in the art.
The processor 382 executes instructions, codes, computer programs, scripts which it accesses from hard disk, floppy disk, optical disk (these various disk based systems may all be considered secondary storage 384), ROM 386, RAM 388, or the network connectivity devices 392.
While several embodiments have been provided in the present disclosure, it should be understood that the disclosed systems and methods may be embodied in many other specific forms without departing from the spirit or scope of the present disclosure. The present examples are to be considered as illustrative and not restrictive, and the intention is not to be limited to the details given herein, but may be modified within the scope of the appended claims along with their full scope of equivalents. For example, the various elements or components may be combined or integrated in another system or certain features may be omitted, or not implemented.
Also, techniques, systems, subsystems and methods described and illustrated in the various embodiments as discrete or separate may be combined or integrated with other systems, modules, techniques, or methods without departing from the scope of the present disclosure. Other items shown or discussed as directly coupled or communicating with each other may be coupled through some interface or device, such that the items may no longer be considered directly coupled to each other but may still be indirectly coupled and in communication, whether electrically, mechanically, or otherwise with one another. Other examples of changes, substitutions, and alterations are ascertainable by one skilled in the art and could be made without departing from the spirit and scope disclosed herein.

Claims (17)

What is claimed is:
1. A method of forecasting work hours per unit of time, comprising:
estimating a total project hour budget for a project comprising a plurality of project phases;
determining, with an analyzer stored as a set of computer readable instructions in a computer readable storage media and executable by a processor, a percentage of the total project hour budget to be expended in each of the plurality of project phases based on average percentages of project hour budgets expended in each project phase in completed projects; and
distributing, with the analyzer, the project hour budget across a plurality of units of time based on the percentage of the project hour budget to be expended in each project phase, on the project hour budget, and on a schedule of project milestones, wherein distributing, with the analyzer, the project hour budget across each project phase is based on:
estimate = { 100 ( P d ) ( φ d ) } { T φ % 100 } LOE = LOE × T φ % P d × φ d ( 1 )
where Pd is a total project duration, φd is a percentage of the total project duration expended in each project phase, Tφ% is the percentage of the project hour budget to be expended in each project phase, and LOE is the total project hour budget for the project.
2. The method of claim 1 wherein the schedule of project milestones is defined by a start date, an end date, and the percentage of the total project duration expended in each project phase.
3. The method of claim 2 wherein a warranty phase is defined as a fixed number of days.
4. The method of claim 1 wherein the project phases include one or more phases selected from the group consisting of a requirements analysis phase, a design phase, a development phase, an implementation phase, and a warranty phase.
5. The method of claim 1 wherein the percentage of project hour budget to be expended in each project phase is custom defined.
6. A system for distributing budget hours, comprising:
at least one processor;
a data store including:
a project hour budget;
one or more schedule percentage of project hour budget to be expended in each of a plurality of project phases; and
a schedule percentage of project duration to be expended in each of the plurality of project phases wherein the schedule percentage of project duration for a one of the plurality of project phases is independent of the schedule percentage of project hour budget for the one of the plurality of project phases; and
an analysis tool stored as a set of computer readable instructions in a computer readable storage media and executable by the least one processor, to generate a distribution of project hours to each of a plurality of periods of duration based on the project hour budget, the distribution of project hours further based on the schedule percentage of project hour budget to be expended in each project phase and the schedule percentage of project duration to be expended in each project phase, the analysis tool further operable to generate a report containing the distribution of project hours to the periods of duration, wherein the definitions of the percentage of project hour budget to be expended in each of a plurality of project phases and the definition of the percentage of project duration to be expended in each of the plurality of project phases are included in the report.
7. The system of claim 6 wherein one of the definitions of the percentage of project hour budget to be expended in each project phase: 1) is based at least in part on averages of hours spent or expended in project phases for completed projects; 2) is a custom definition; or 3) is based on at least in part on averages of hours expended in each of the plurality of project phases.
8. The system of claim 7 wherein a warranty phase is defined to have a duration of a fixed number of days.
9. A method of forecasting, comprising:
projecting, with an analyzer stored as a set of computer readable instructions in a computer readable storage media and executable by a processor, resource expenditure over each of a plurality of units of time over the course of a project based on a resource budget, the resource expenditure further based on a definition of a duration of project phases as a percentage of a total project duration, a project start date, a project end date and an estimate of a percentage of resources to be expended during each project phase wherein the definition of a duration of project phases is independent from the percentage of resources to be expended during each project phase, wherein projecting, with the analyzer, the resource expenditure across each project phase is based on:
estimate = { 100 ( P d ) ( φ d ) } { T φ % 100 } LOE = LOE × T φ % P d × φ d ( 1 )
where Pd is the total project duration, φd is the percentage of the total project duration expended in each project phase, Tφ% is the percentage of the resources to be expended in each project phase, and LOE is the resource budget.
10. The method of claim 9 wherein the estimate of a percentage of resources to be expended during each project phase is based at least in part on a determination of an average percentage of resources expended during project phases of projects completed over the previous about six months.
11. The method of claim 9 wherein the estimate of the percentage of resources to be expended during each project phase is customized for the specific task.
12. The method of claim 9 wherein the project phases are selected from the group consisting of a requirement analysis phase, a design phase, a development phase, a deploy-migration phase, and a deploy-warranty phase.
13. The method of claim 12 wherein the duration of the deploy-warranty phase is a fixed length of time.
14. The method of claim 9 wherein the units of time are one of weeks or months.
15. The method of claim 1, wherein the completed projects comprise a sub-set of all completed projects.
16. The method of claim 15, wherein the sub-set of all completed projects is selected based on a time-date stamp of all completed projects.
17. The system of claim 6, wherein the analysis tool generates the distribution of the project hour budget to each project phase based on:
estimate = { 100 ( P d ) ( φ d ) } { T φ % 100 } LOE = LOE × T φ % P d × φ d ( 1 )
where Pd is a total schedule project duration, φd is the schedule percentage of the total project duration expended in each project phase, Tφ% is the schedule percentage of the project hour budget to be expended in each project phase, and LOE is the project hour budget.
US11/195,964 2005-08-03 2005-08-03 Spreading algorithm for work and time forecasting Expired - Fee Related US8612275B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US11/195,964 US8612275B1 (en) 2005-08-03 2005-08-03 Spreading algorithm for work and time forecasting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
US11/195,964 US8612275B1 (en) 2005-08-03 2005-08-03 Spreading algorithm for work and time forecasting

Publications (1)

Publication Number Publication Date
US8612275B1 true US8612275B1 (en) 2013-12-17

Family

ID=49725848

Family Applications (1)

Application Number Title Priority Date Filing Date
US11/195,964 Expired - Fee Related US8612275B1 (en) 2005-08-03 2005-08-03 Spreading algorithm for work and time forecasting

Country Status (1)

Country Link
US (1) US8612275B1 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20110138352A1 (en) * 2005-10-17 2011-06-09 International Business Machines Corporation Method and System for Assessing Automation Package Readiness and Effort for Completion
US8682701B1 (en) 2006-04-13 2014-03-25 Sprint Communications Company L.P. Project pipeline management systems and methods having capital expenditure/expense flip targeting
US20140278694A1 (en) * 2013-03-15 2014-09-18 ConnectWise Inc. Systems and methods for business management using product data with product classes
US11321647B2 (en) 2013-03-15 2022-05-03 Connectwise, Llc Project scheduling and management system that uses product data with product classes
US11429913B2 (en) 2013-08-02 2022-08-30 Connectwise, Llc Systems and methods for converting sales opportunities to service tickets, sales orders, and projects

Citations (51)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5408663A (en) 1993-11-05 1995-04-18 Adrem Technologies, Inc. Resource allocation methods
US5619695A (en) 1994-02-03 1997-04-08 Lockheed Martin Corporation Method and apparatus for scheduling resources
US5907490A (en) 1997-06-10 1999-05-25 Electronic Data Systems Corporation System and method for project management and assessment
US5953707A (en) 1995-10-26 1999-09-14 Philips Electronics North America Corporation Decision support system for the management of an agile supply chain
US6032121A (en) 1997-05-15 2000-02-29 International Business Machines Corporation Method for proactive planning
US6216109B1 (en) 1994-10-11 2001-04-10 Peoplesoft, Inc. Iterative repair optimization with particular application to scheduling for integrated capacity and inventory planning
US20020165742A1 (en) 2000-03-31 2002-11-07 Mark Robins Feature centric release manager method and system
US20030018952A1 (en) 2001-07-13 2003-01-23 Roetzheim William H. System and method to estimate resource usage for a software development project
US6519763B1 (en) 1998-03-30 2003-02-11 Compuware Corporation Time management and task completion and prediction software
US20030083891A1 (en) 2001-10-25 2003-05-01 Lang Kenny W. Project Management tool
US20030083912A1 (en) 2001-10-25 2003-05-01 Covington Roy B. Optimal resource allocation business process and tools
US20030126141A1 (en) 2001-12-28 2003-07-03 Sprint Communications Company, L.P. System and method for managing and resourcing persons, skill sets and project requirements
US20040001103A1 (en) 2002-06-28 2004-01-01 Fliess Kevin V. Modeling business objects
US6678671B1 (en) 2000-11-02 2004-01-13 Klocwork Solutions Corporation System for linking a resource management system with an event of a project in a project management system and a method therefor
US6687677B1 (en) 1999-11-22 2004-02-03 International Business Machines Corporation System and method for deploying a procurement and accounts payable system
US6714915B1 (en) 1999-11-22 2004-03-30 International Business Machines Corporation System and method for project designing and developing a procurement and accounts payable system
US20040073467A1 (en) 2002-10-11 2004-04-15 Heyns Herman R. Software tools and method for business planning
US20040078254A1 (en) 2002-06-20 2004-04-22 Andy Piechl Methods and systems for human resource budgeting and control
US20040111306A1 (en) 2002-12-09 2004-06-10 Hitachi, Ltd. Project assessment system and method
US20040117046A1 (en) 2002-12-12 2004-06-17 Renzo Colle User interface for scheduling tasks
US20040162748A1 (en) 2003-02-14 2004-08-19 Vogel Eric S. Generating a resource allocation action plan
US20040162753A1 (en) 2003-02-14 2004-08-19 Vogel Eric S. Resource allocation management and planning
US20040162749A1 (en) 2003-02-14 2004-08-19 Vogel Eric S. Rationalizing a resource allocation
US20050114829A1 (en) 2003-10-30 2005-05-26 Microsoft Corporation Facilitating the process of designing and developing a project
US20050114830A1 (en) 2003-11-24 2005-05-26 Qwest Communications International Inc. System development planning tool
US20050120332A1 (en) 2003-12-02 2005-06-02 Hewlett-Packard Development Company, L.P. Method, system, and software for mapping and displaying process objects at different levels of abstraction
US20050137920A1 (en) 2003-12-22 2005-06-23 Itm Software Information technology enterprise manager and product portfolio manager application module
US20060010418A1 (en) 2003-11-04 2006-01-12 Realization Technologies, Inc. Facilitation of multi-project management using threoughput measurement
US6993533B1 (en) 2002-03-25 2006-01-31 Bif Technologies Corp. Relational database drill-down convention and reporting tool
US20060053043A1 (en) 2001-04-17 2006-03-09 4Sight Technologies, Inc. Enterprise project management system and method therefor
US20060129439A1 (en) 2004-09-07 2006-06-15 Mario Arlt System and method for improved project portfolio management
US7080024B2 (en) 2000-08-28 2006-07-18 Thompson Daniel J Method, system, and computer software program product for analyzing the efficiency of a complex process
US20060167732A1 (en) 2005-01-27 2006-07-27 International Business Machines Corporation Method and system for planning and managing multiple projects on demand with critical chain and replenishment
US7089193B2 (en) 2001-05-09 2006-08-08 Prochain Solutions, Inc. Multiple project scheduling system
US20060235732A1 (en) 2001-12-07 2006-10-19 Accenture Global Services Gmbh Accelerated process improvement framework
US7139720B1 (en) 2000-11-14 2006-11-21 Xerox Corporation Project planning system and method for accommodating AD HOC requests within a fixed core development cycle
US7139999B2 (en) 1999-08-31 2006-11-21 Accenture Llp Development architecture framework
US20070006161A1 (en) 2005-06-02 2007-01-04 Kuester Anthony E Methods and systems for evaluating the compliance of software to a quality benchmark
US20070073576A1 (en) 2005-09-29 2007-03-29 International Business Machines Corp. Resource capacity planning
US20070100685A1 (en) 2005-10-31 2007-05-03 Sbc Knowledge Ventures, L.P. Portfolio infrastructure management method and system
US20070112945A1 (en) 2005-11-12 2007-05-17 Lori Brown Supply and demand project management tool
US7222330B2 (en) * 1999-01-15 2007-05-22 Bicknell Barbara A Project planning system with content loaded project planning template generator and a plurality of content loaded project planning templates
US7222082B1 (en) 2000-06-28 2007-05-22 Kronos Technology Systems Limited Partnership Business volume and workforce requirements forecaster
US20070179871A1 (en) 2003-07-29 2007-08-02 Minor Earlena F System and Method for providing and utilizing cascading express asset capitalization integration rules
US20080110971A1 (en) 2004-04-20 2008-05-15 Mark Pover Service Provision Method and System Employing Threshold Range of Pricing and Leveling
US20080183549A1 (en) 2005-07-28 2008-07-31 Daniel Patrick Connors System and method for overcoming infeasibility determinations in using constraint satisfaction programming for scheduling human resources
US7613623B2 (en) 2002-09-17 2009-11-03 Hewlett-Packard Development Company, L.P. Enterprise management using an enterprise program office (EPO)
US7962358B1 (en) 2006-11-06 2011-06-14 Sprint Communications Company L.P. Integrated project and staffing management
US8001226B2 (en) 2005-06-29 2011-08-16 Fujitsu Limited Surplus determination system, management system, recording medium storing surplus determination program, and recording medium storing management program
US8280756B1 (en) 2005-08-03 2012-10-02 Sprint Communications Company L.P. Milestone initial scheduling
US8341591B1 (en) 2006-04-13 2012-12-25 Sprint Communications Company, L.P. Method and software tool for real-time optioning in a software development pipeline

Patent Citations (51)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5408663A (en) 1993-11-05 1995-04-18 Adrem Technologies, Inc. Resource allocation methods
US5619695A (en) 1994-02-03 1997-04-08 Lockheed Martin Corporation Method and apparatus for scheduling resources
US6216109B1 (en) 1994-10-11 2001-04-10 Peoplesoft, Inc. Iterative repair optimization with particular application to scheduling for integrated capacity and inventory planning
US5953707A (en) 1995-10-26 1999-09-14 Philips Electronics North America Corporation Decision support system for the management of an agile supply chain
US6032121A (en) 1997-05-15 2000-02-29 International Business Machines Corporation Method for proactive planning
US5907490A (en) 1997-06-10 1999-05-25 Electronic Data Systems Corporation System and method for project management and assessment
US6519763B1 (en) 1998-03-30 2003-02-11 Compuware Corporation Time management and task completion and prediction software
US7222330B2 (en) * 1999-01-15 2007-05-22 Bicknell Barbara A Project planning system with content loaded project planning template generator and a plurality of content loaded project planning templates
US7139999B2 (en) 1999-08-31 2006-11-21 Accenture Llp Development architecture framework
US6714915B1 (en) 1999-11-22 2004-03-30 International Business Machines Corporation System and method for project designing and developing a procurement and accounts payable system
US6687677B1 (en) 1999-11-22 2004-02-03 International Business Machines Corporation System and method for deploying a procurement and accounts payable system
US20020165742A1 (en) 2000-03-31 2002-11-07 Mark Robins Feature centric release manager method and system
US7222082B1 (en) 2000-06-28 2007-05-22 Kronos Technology Systems Limited Partnership Business volume and workforce requirements forecaster
US7080024B2 (en) 2000-08-28 2006-07-18 Thompson Daniel J Method, system, and computer software program product for analyzing the efficiency of a complex process
US6678671B1 (en) 2000-11-02 2004-01-13 Klocwork Solutions Corporation System for linking a resource management system with an event of a project in a project management system and a method therefor
US7139720B1 (en) 2000-11-14 2006-11-21 Xerox Corporation Project planning system and method for accommodating AD HOC requests within a fixed core development cycle
US20060053043A1 (en) 2001-04-17 2006-03-09 4Sight Technologies, Inc. Enterprise project management system and method therefor
US7089193B2 (en) 2001-05-09 2006-08-08 Prochain Solutions, Inc. Multiple project scheduling system
US20030018952A1 (en) 2001-07-13 2003-01-23 Roetzheim William H. System and method to estimate resource usage for a software development project
US20030083912A1 (en) 2001-10-25 2003-05-01 Covington Roy B. Optimal resource allocation business process and tools
US20030083891A1 (en) 2001-10-25 2003-05-01 Lang Kenny W. Project Management tool
US20060235732A1 (en) 2001-12-07 2006-10-19 Accenture Global Services Gmbh Accelerated process improvement framework
US20030126141A1 (en) 2001-12-28 2003-07-03 Sprint Communications Company, L.P. System and method for managing and resourcing persons, skill sets and project requirements
US6993533B1 (en) 2002-03-25 2006-01-31 Bif Technologies Corp. Relational database drill-down convention and reporting tool
US20040078254A1 (en) 2002-06-20 2004-04-22 Andy Piechl Methods and systems for human resource budgeting and control
US20040001103A1 (en) 2002-06-28 2004-01-01 Fliess Kevin V. Modeling business objects
US7613623B2 (en) 2002-09-17 2009-11-03 Hewlett-Packard Development Company, L.P. Enterprise management using an enterprise program office (EPO)
US20040073467A1 (en) 2002-10-11 2004-04-15 Heyns Herman R. Software tools and method for business planning
US20040111306A1 (en) 2002-12-09 2004-06-10 Hitachi, Ltd. Project assessment system and method
US20040117046A1 (en) 2002-12-12 2004-06-17 Renzo Colle User interface for scheduling tasks
US20040162753A1 (en) 2003-02-14 2004-08-19 Vogel Eric S. Resource allocation management and planning
US20040162749A1 (en) 2003-02-14 2004-08-19 Vogel Eric S. Rationalizing a resource allocation
US20040162748A1 (en) 2003-02-14 2004-08-19 Vogel Eric S. Generating a resource allocation action plan
US20070179871A1 (en) 2003-07-29 2007-08-02 Minor Earlena F System and Method for providing and utilizing cascading express asset capitalization integration rules
US20050114829A1 (en) 2003-10-30 2005-05-26 Microsoft Corporation Facilitating the process of designing and developing a project
US20060010418A1 (en) 2003-11-04 2006-01-12 Realization Technologies, Inc. Facilitation of multi-project management using threoughput measurement
US20050114830A1 (en) 2003-11-24 2005-05-26 Qwest Communications International Inc. System development planning tool
US20050120332A1 (en) 2003-12-02 2005-06-02 Hewlett-Packard Development Company, L.P. Method, system, and software for mapping and displaying process objects at different levels of abstraction
US20050137920A1 (en) 2003-12-22 2005-06-23 Itm Software Information technology enterprise manager and product portfolio manager application module
US20080110971A1 (en) 2004-04-20 2008-05-15 Mark Pover Service Provision Method and System Employing Threshold Range of Pricing and Leveling
US20060129439A1 (en) 2004-09-07 2006-06-15 Mario Arlt System and method for improved project portfolio management
US20060167732A1 (en) 2005-01-27 2006-07-27 International Business Machines Corporation Method and system for planning and managing multiple projects on demand with critical chain and replenishment
US20070006161A1 (en) 2005-06-02 2007-01-04 Kuester Anthony E Methods and systems for evaluating the compliance of software to a quality benchmark
US8001226B2 (en) 2005-06-29 2011-08-16 Fujitsu Limited Surplus determination system, management system, recording medium storing surplus determination program, and recording medium storing management program
US20080183549A1 (en) 2005-07-28 2008-07-31 Daniel Patrick Connors System and method for overcoming infeasibility determinations in using constraint satisfaction programming for scheduling human resources
US8280756B1 (en) 2005-08-03 2012-10-02 Sprint Communications Company L.P. Milestone initial scheduling
US20070073576A1 (en) 2005-09-29 2007-03-29 International Business Machines Corp. Resource capacity planning
US20070100685A1 (en) 2005-10-31 2007-05-03 Sbc Knowledge Ventures, L.P. Portfolio infrastructure management method and system
US20070112945A1 (en) 2005-11-12 2007-05-17 Lori Brown Supply and demand project management tool
US8341591B1 (en) 2006-04-13 2012-12-25 Sprint Communications Company, L.P. Method and software tool for real-time optioning in a software development pipeline
US7962358B1 (en) 2006-11-06 2011-06-14 Sprint Communications Company L.P. Integrated project and staffing management

Non-Patent Citations (64)

* Cited by examiner, † Cited by third party
Title
Advisory Action dated Dec. 23, 2010, U.S. Appl. No. 11/403,652 filed on Apr. 13, 2006.
Advisory Action dated Jan. 6, 2011, U.S. Appl. No. 11/491,203, filed Jul. 21, 2006.
Advisory Action dated Jul. 19, 2011, U.S. Appl. No. 11/403,773, filed Apr. 13, 2006.
Advisory Action dated Jun. 28, 2010, U.S. Appl. No. 11/196,692, filed Aug. 3, 2005, 3 pgs.
Advisory Action dated Nov. 24, 2010, U.S. Appl. No. 11/403,669, filed Apr. 13, 2006.
Alsup, Lance A., et al., Patent Application entitled, "Project Estimator", filed Jul. 21, 2006, U.S. Appl. No. 11/491,203.
Aoyama, Mikio, "Agile Software Process and Its Experience," Department of Information and Electronics Engineering, IEEE, Niigata Institute of Technology, 1998, pp. 3-12.
Armour, Phillip, "Ten Unmyths of Project Estimation," Communications of the ACM, Nov. 2002, vol. 45. No. 11, 4 pgs.
Bott, M.F., "Software as a Corporate Asset" IEE Proc-Softw. vol. 147, No. 2, Apr. 2, 2000, 6pgs.
C. Chapman and S. Ward, Constructively Simple Estimating: A Project Management Example, 2003, Palgrave Macmillan Journals and Operational research Society, vol. 54, No. 10, 1050-1058. *
C. Chapman and S. Ward, Constructively Simple Estimating: A Project Management Example, Oct. 2003, The Journal of the Operational research Society, vol. 54, No. 10, p. 1052. *
Cohen, Morris A., et al., "New Product Development: The Performance and Time-to-Market Tradeoff," Management Science, vol. 42, No. 2, Feb. 1996, 15 pgs.
Dean, Burton V., et al., "Multiproject Staff Scheduling with Variable Resource Constraints," IEEE Transactions on Engineering Management, vol. 39, No. 1, Feb. 1992, pp. 59-72.
Decision on Appeal dated Jan. 15, 2013, U.S. Appl. No. 11/403,701, filed Apr. 13, 2006.
DELTEK.com Webpages-Deltek Project Planner, Deltek, Mar. 2002, Retrieved from Arhcive.org May 18, 2010.
Deltek-Resource Planning and Project Budgeting Software for Professional Consultants: Wind 2, "Wind2 Resource Scheduling and Budgeting (RSB)," http://www.wind2.com/products/rsb.asp, Oct. 12, 2005, Wind2 Software Inc., 8 pgs.
Examiner's Answer dated Oct. 5, 2010, U.S. Appl. No. 11/403,701, filed Apr. 13, 2006.
Examiner's Answer dated Sep. 12, 2011, U.S. Appl. No. 11/491,203, filed Jul. 21, 2006.
Examiner's Answer dated Sep. 21, 2011, U.S. Appl. No. 11/491,203, filed Jul. 21, 2006.
Final Office Action dated Apr. 13, 2010, U.S. Appl. No. 11/196,692, filed Aug. 3, 2005, 47 pages.
Final Office Action dated Apr. 27, 2011, U.S. Appl. No. 11/403,773, filed Apr. 13, 2006.
Final Office Action dated Dec. 18, 2009, U.S. Appl. No. 11/403,701, filed Apr. 13, 2006, 16 pgs.
Final Office Action dated Feb. 9, 2011, U.S. Appl. No. 11/403,773, filed Apr. 13, 2006.
Final Office Action dated Nov. 17, 2011, U.S. Appl. No. 11/403,652, filed Apr. 13, 2006.
Final Office Action dated Oct. 27, 2010, U.S. Appl. No. 11/491,203, filed Jul. 21, 2006.
Final Office Action dated Oct. 4, 2011, U.S. Appl. No. 11/196,692, filed Aug. 3, 2005.
Final Office Action dated Sep. 14, 2010, U.S. Appl. No. 11/403,669, filed Apr. 13, 2006, 22 pgs.
Final Office Action dated Sep. 29, 2010, U.S. Appl. No. 11/403,652, filed Apr. 13, 2006.
Fox, Mark S., et al. "ISIS-a knowledge-based system for factory scheduling," Expert Systems, vol. 1, No. 1, Jul. 1984.
Heires, James T., et al., What I Did Last Summer: A Software Development Benchmarking Case Study, IEEE Software, Sep./Oct. 2001, pp. 33-39.
IBM-Introduction to Portfolio Management IBM, Rational Software, Sep. 2005.
IBM-Rational Portfolio Management-Product Data Sheet IBM, 2004.
Jandourek, Emil, "A Model for Platform Development," Hewlett-Packard Journal, Aug. 1996, pp. 1-18.
Kanemoto, Michael W., et al., Patent Application entitled, "Hardware/Software and Vendor Labor Integration in Pipeline Management," filed Apr. 13, 2006, U.S. Appl. No. 11/403,652, Specification (30 pgs.) and Drawings (6 sheets).
Kanemoto, Michael, W., et al., "Milestone Initial Scheduling," Filing Date-Aug. 3, 2005, U.S. Appl. No. 11/196,692, Specification (23 pgs.), Drawings (3 sheets).
Knauth, Margaret J., et al., Patent Application entitled, "A Method and Software Tool for Real-Time Optioning in a Software Development Pipeline," filed Apr. 13, 2006, U.S. Appl. No. 11/403,773, Specification (32 pgs.) and Drawings (9 sheets).
Knauth, Margaret J., et al., Patent Application entitled, "Predictive Growth Burn Rate in Development Pipeline," filed Apr. 13, 2006, U.S. Appl. No. 11/403,669, Specification (27 pgs.) and Drawings (3 sheets).
Knauth, Margaret J., et al., Patent Application entitled, "Project Pipeline Management Systems and Methods Having Capital Expenditure/Expense Flip Targeting," filed Apr. 13, 2006, U.S. Appl. No. 11/403,701, Specification (31 pgs.) and Drawings (6 sheets).
Lassila, Ora, et. al., "Toward the Development of Flexible Mixed-Initiative Scheduling Tools", Robotics Institute, Carnegie Mellow University, Mar. 15, 1994, 12 pgs.
Leffingwell, Dean, et al., "Tactical Management of Agile Development: Achieving Competitive Advantage," Rally Software Development Corporation, 2004.
Lipner, Steve, "The Trustworthy Computing Security Development Cycle," IEEE Security Conference, Dec. 2004, 12 pages.
Melik, Rudolf, et al., Professional Services Automation-Optimizing Project and Service Oriented Organizations, John Wiley & Sons, 2002.
Musselman, Kenneth, et al., "The Role of Simulation in Advanced Planning and Scheduling," IEEE Simulation Conference 2002, vol. 2, Dec. 2002, pp. 1825-1830.
Notice of Allowance dated Aug. 6, 2013, U.S. Appl. No. 11/403,652, filed Apr. 13, 2006.
Notice of Allowance dated Aug. 9, 2012, U.S. Appl. No. 11/403,773, filed Apr. 13, 2006.
Notice of Allowance dated Jun. 7, 2012, U.S. Appl. No. 11/196,692, filed Aug. 3, 2005.
Office Action dated Aug. 19, 2010, U.S. Appl. No. 11/403,773, filed Apr. 13, 2006, 31 pgs.
Office Action dated Jun. 8, 2010, U.S. Appl. No. 11/491,203, filed Jul. 21, 2006, 39 pgs.
Office Action dated Jun. 9, 2009, U.S. Appl. No. 11/403,701, filed Apr. 13, 2006, 16 pgs.
Office Action dated Mar. 29, 2010, U.S. Appl. No. 11/403,669, filed Apr. 13, 2006, 20 pgs.
Office Action dated Mar. 29, 2011, U.S. Appl. No. 11/196,692, filed Aug. 3, 2005.
Office Action dated Mar. 30, 2010, U.S. Appl. No. 11/403,652, filed Apr. 13, 2006, 26 pgs.
Office Action dated May 9, 2011, U.S. Appl. No. 11/403,652, filed Apr. 13, 2006.
Office Action dated May 9, 2012, U.S. Appl. No. 11/403,773, filed Apr. 13, 2006.
Office Action dated Sep. 16, 2009, U.S. Appl. No. 11/196,692, filed Aug. 3, 2005, 36 pages.
Pfahl, Dietmar, et al., "Integration of System Dynamics Modeling with Descriptive Process Modeling and Goal-Oriented Measurement," The Journal of Systems and Software vol. 46, 1999, pp. 135-150.
Pham, Hoang, et al., "Software Cost Model With Warranty and Risk Costs," IEEE Transactions on Computers, vol. 48, No. 1, Jan. 1999, pp. 71-75.
Powell, Anthony, et al. "Strategies for Lifecycle Concurrency and Iteration-A System Dynamics Approach," The Journal of Systems and Software, 1999, vol. 46, pp. 151-161.
Rautiainen, Kristian, et al., "4CC: A Framework for Managing Software Product Development," Helsinki University of Technology, Engineering Management Journal, vol. 14, No. 2, Jun. 2002, pp. 27-32.
Reaction Rate, 2007, The Free Dictionary, http://encyclopedia2.thefreedictionary.com/Rate+equation+(chemistry). *
Smith, Stephen F., et al., "Scheduling and Visualization," Final Technical Report AFRL-IF-RS-TR-2004-142, Jun. 2004, Carnegie Mellon University.
Smith-Daniels, Dwight E., et al., "Heuristic Scheduling of Capital Constrained Projects", Journal of Operations Management 14, 1996, 14 pgs.
Ulusoy, Gündüz, et al., "A framework for an interactive project scheduling system under limited resources," European Journal of Operational Research 90, 1996, 14 pgs.
Wolff, Mario, Project and Project Portfolio Management with SAP, 2002.

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20110138352A1 (en) * 2005-10-17 2011-06-09 International Business Machines Corporation Method and System for Assessing Automation Package Readiness and Effort for Completion
US8682701B1 (en) 2006-04-13 2014-03-25 Sprint Communications Company L.P. Project pipeline management systems and methods having capital expenditure/expense flip targeting
US20140278694A1 (en) * 2013-03-15 2014-09-18 ConnectWise Inc. Systems and methods for business management using product data with product classes
US10318901B2 (en) * 2013-03-15 2019-06-11 Connectwise, Llc Systems and methods for business management using product data with product classes
US10846636B2 (en) 2013-03-15 2020-11-24 Connectwise Llc Systems and methods for business management using product data with product classes
US11321647B2 (en) 2013-03-15 2022-05-03 Connectwise, Llc Project scheduling and management system that uses product data with product classes
US11551170B2 (en) 2013-03-15 2023-01-10 Connectwise, Llc Business management system that uses product data with product classes
US11429913B2 (en) 2013-08-02 2022-08-30 Connectwise, Llc Systems and methods for converting sales opportunities to service tickets, sales orders, and projects

Similar Documents

Publication Publication Date Title
US8589203B1 (en) Project pipeline risk management system and methods for updating project resource distributions based on risk exposure level changes
US7908167B1 (en) System and method for analysis of project variances
US8639553B1 (en) Predictive growth burn rate in development pipeline
US8280756B1 (en) Milestone initial scheduling
US7921405B2 (en) Facilitation of multi-project management using throughput measurement
Leach Critical chain project management improves project performance
US8306841B2 (en) Enterprise project management system and method therefor
US7774742B2 (en) Facilitation of multi-project management using task hierarchy
US8341591B1 (en) Method and software tool for real-time optioning in a software development pipeline
US8484060B2 (en) Project estimating system and method
Eder et al. Managing time in workflow systems
Ma et al. A computational experiment to explore better robustness measures for project scheduling under two types of uncertain environments
US20080300844A1 (en) Method and system for estimating performance of resource-based service delivery operation by simulating interactions of multiple events
US20120035972A1 (en) Optimizing Resources Allocation for Global Service Delivery
US8612275B1 (en) Spreading algorithm for work and time forecasting
US20140122161A1 (en) Workflow-based project management
Setzer et al. Change scheduling based on business impact analysis of change-related risk
Shariatmadari et al. A new resource buffer insertion approach for proactive resource investment problem
Oburu Effective project time management
Maciel Jr et al. Business-driven short-term management of a hybrid IT infrastructure
US8606614B1 (en) Hardware/software and vendor labor integration in pipeline management
Miranda Planning and executing time-bound projects
Erenguc et al. Integrating quality as a measure of performance in resource-constrained project scheduling problems
US8510229B1 (en) Project efficiency analysis
Doerner et al. Enriched workflow modelling and stochastic branch-and-bound

Legal Events

Date Code Title Description
AS Assignment

Owner name: SPRINT COMMUNICATIONS COMPANY L.P., KANSAS

Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNORS:CRUM, JAMES L.;KANEMOTO, MICHAEL W.;PERKINS, MATHEW E.;REEL/FRAME:016838/0953

Effective date: 20050715

AS Assignment

Owner name: DEUTSCHE BANK TRUST COMPANY AMERICAS, NEW YORK

Free format text: GRANT OF FIRST PRIORITY AND JUNIOR PRIORITY SECURITY INTEREST IN PATENT RIGHTS;ASSIGNOR:SPRINT COMMUNICATIONS COMPANY L.P.;REEL/FRAME:041895/0210

Effective date: 20170203

REMI Maintenance fee reminder mailed
LAPS Lapse for failure to pay maintenance fees

Free format text: PATENT EXPIRED FOR FAILURE TO PAY MAINTENANCE FEES (ORIGINAL EVENT CODE: EXP.)

STCH Information on status: patent discontinuation

Free format text: PATENT EXPIRED DUE TO NONPAYMENT OF MAINTENANCE FEES UNDER 37 CFR 1.362

FP Lapsed due to failure to pay maintenance fee

Effective date: 20171217

AS Assignment

Owner name: SPRINT COMMUNICATIONS COMPANY L.P., KANSAS

Free format text: TERMINATION AND RELEASE OF FIRST PRIORITY AND JUNIOR PRIORITY SECURITY INTEREST IN PATENT RIGHTS;ASSIGNOR:DEUTSCHE BANK TRUST COMPANY AMERICAS;REEL/FRAME:052969/0475

Effective date: 20200401