US828718A - Track construction for street and othe railways. - Google Patents

Track construction for street and othe railways. Download PDF

Info

Publication number
US828718A
US828718A US30470006A US1906304700A US828718A US 828718 A US828718 A US 828718A US 30470006 A US30470006 A US 30470006A US 1906304700 A US1906304700 A US 1906304700A US 828718 A US828718 A US 828718A
Authority
US
United States
Prior art keywords
cavities
bases
rails
rail
railways
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
US30470006A
Inventor
Reuben D Culver
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to US30470006A priority Critical patent/US828718A/en
Application granted granted Critical
Publication of US828718A publication Critical patent/US828718A/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B3/00Transverse or longitudinal sleepers; Other means resting directly on the ballastway for supporting rails
    • E01B3/28Transverse or longitudinal sleepers; Other means resting directly on the ballastway for supporting rails made from concrete or from natural or artificial stone
    • E01B3/38Longitudinal sleepers; Longitudinal sleepers integral or combined with tie-rods; Combined longitudinal and transverse sleepers; Layers of concrete supporting both rails

Definitions

  • My invention relates to an improved track construction for street and other railways; and it consists in the novel elements and combination of elements hereinafter described and claimed.
  • the ob'ect of my invention is to provide an improve track construction for street and other railways which is practically inclestructible through the action of the elements or through wear, except as to the rails.
  • the further object of my invention is to provide a railway-track construction which will be perfectly drained and not liable to get 7 out of alinement because of settling and which will yet be sufficiently elastic to prevent all injurious jar or vibration.
  • the further ob ect is to provide a railways; track construction wherein when the grade has been once established the same may be maintained perpetually at almost no cost;
  • the further object is to provide such 'a systern of'railway-track construction as will be specially adapted for use in constructin or reconstructing.
  • the further object is to provide a railwaytrack construction which will be practicable in reconstructing ordinary railway-tracks on thorou lily-settled grades.
  • the urther object is to provide a railwaytrack construction which will obviate the necessity of crossties and yet provide an independent base for each rail, whereby should one base settle such settling will not throw upwardly the opposite rail, as is the case when cross-ties are used.
  • Figure 1 is a transverse section of a street-railway construction made in accordance with my invention.
  • Fig. 2 is a sectional side elevation.
  • Fig. 3 is a plan view of one of the cement-concrete bases.
  • Fig. i is a detail view showing the construction of the lower end of a rail-anchor, and
  • Fig. 5 is a detail view of a modified construe-- 2 2 indicate parallel trenches under the lines of rails 3, and which trenches are er fectly drained by a i e or sewer whic is located oentrail a s ig t distance below each trench 2. Wit 'n the trenches are laidce -1nent-concrete bases 5. Said bases maybeoi any desired shape in cross-section to adapt them for the required service, and in some cases I prefer to make the bases with slo i'ng or buttressed sides, as shown by dotted lies in Fig'fljalthough in ordinary cases itivill be suflicient to have the side walls vertical.
  • I grater also to make the bottom wall of the ases thicker than the side walls, as it must act as a foundation for said side walls, as Well as for all other parts of the track construction.
  • the sections may be separated at'any other suitable point in the length of the bases.
  • Asuitable numb er of cavities 7 are formed in the upper part of the body of the cement-concrete composing the b ases 5.
  • Said cavities are preferably rectangular, but of coursemay be of any desired shape provided they are open at assess? They should be of uniform size.
  • 8. body 8 of sand, fine gravel, cinders, earth, burnt clay, or any other indestructible but slightly-resilient materiai, should be placed within said cavities, so as to partially fill the same, and then said body of slightiywesiiient material shouid be' thoroughly tarnped and brought to the desired grade.
  • Said blocks 10 may be made of burnt clay, cement-concrete, metal, stone, chemically-treated. wood, or any other suit able and practically-indestructible material.
  • the space between. the blocks 10 and the walls of the cavities is very slight and should be filled with sand, coal-tar, or other imervious but yielding material.
  • the upper faces of the said blocks 10 preferably have a central longitudinal depression 11, in which the bases 12 of the rails 3 are located.
  • Said rails may of course be of the usual forms in cross-section; but in the present instance I have shown the bases of the rails trussshaped in cross-section, or, in other words, the base is arched in cross-section, thus forming a yielding or spring base, and thereby affording additional resiliency to the rails for the pur ose of lessening the vibration or jar caused y locomotives or cars.
  • the rails 3 are preferably gaged or spaced apart by means of tie-rods 13, the ends of which are passed through holes in the webs of the rails and secured b r means of nuts 14.
  • the rails are secured to t e blocks 10 by anchor-bolts 15, the up er ends of which pass through holes in the ase of the rail on both sides of the web and are thereat provided with nuts 16 or e uivalent securing means.
  • the lower ends oi said anchor-bolts 15 are provided with hooks or bends 17, which pass around short sections of pipe or steel rods, forming anchors such as 18, and said anchors may be embedded in the concrete, as shown in Fig. 5, or detachably mounted in anchorseats 19, formed in the concrete, as shown in Fig.
  • Said anchorbolts 15 are preferably located in transverse recesses 20, formed in the cement-concrete bases 5 at points about midway between contiguous cavities 7.
  • Said blocks 10 are preferably made hollow by means of longitudinal openings 21 in order to lighten the same.
  • drain 22 indicates a small drain-passage formed in the bottom of the cavities 7 and extending through the bottom wall of the concrete bases for the urpose of draining the said cavities, and the upper end of said drain 22 is preferably closed by means of a porous earthenware plug or something similar thereto, whereby the sand will be prevented from passing into said drain, and et any water may percolate through said p ug 23.
  • openings formed in the side walls of the bases 5 said openings being for the purpose of affordin means for inserting the sand or other suitab e material into the cavities should it be necessary to do so in order to effect the proper alinement of the rails after the track has been constructed.
  • These 0 enin s when not used for this purpose are cosed y a body of cement or any other suitable material, so as to prevent the sand, &c., contained in the cavities from working out of said openings or water from finding ingress into the cavities.
  • the bottoms of said cavities 7 are preferably inclined from opposite sides to the center to facilitate drainage.
  • I claim 1 In a railway-track construction, a concrete base extending longitudinally beneath each track-rail, and rail-cushions arranged at intervals in the tops of said bases; substantially as specified.
  • a concrete base extending longitudinally beneath each track-rail, there bein cavities formed at intervals in the to s of t e bases, and railcushions arranged in said cavities; substantially as specified.
  • a concrete base extending longitudinally beneath each track-rail, there being cavities formed at intervals in the top of each base, rail-cushions arran ed in said cavities, and track-rails supported y said cushions; substantially as specified.
  • a con crete base extending longitudinally beneath each track-rail there being cavities formed at intervals in the top of each base, rail-cushions arranged in said cavities, rails mounted on said cushions, and means whereby said rails are rigidly connected to the bases; substantially as specified.
  • An improved track construction for street and other railways comprising concrete bases, there being cavities formed in said bases at intervals of the length of same, a body of sand or other slightly-resilient material in'certain of said cavities, a cover or packing placed u on said bodv of resilient material, rail-bloc s placed Within said cavities upon said cover or packin rails mounted upon said rail-blocks, means or securing the bases of said rails in position u on said railblocks, and means for gaging t e rails; substantially as specified.
  • An improved track construction for street and other railways comprising concrete bases, there bein cavities formed in said bases at intervals 0 the length of same,
  • I a body of sand or other slightly-resilient material in certain of said cavities, a cover or packing placed upon said bodv of resilient material, rail-blocks placed Within said cavities upon said cover or packing, rails mounted u on said rail-blocks, means for securin the ases of said rails in position upon said rail-blocks, means for gagin the rails, and the upper faces of said rai -blocl(s having lon itudinal depressions in which said rails are located; substantially as specified.
  • An improved track construction for street and other railways comprising concrete bases, there being cavities formed in said bases at intervals of the Ian th of the same, a body of sand or other slightly-reed? ent materia in certain of said cavities, a cover or packin placed upon said body of re silient materia rail-blocks placed Within said cavities upon said cover or packing, rails mounted upon said rail-blocks, means for securing the bases of said rails in position upon said rail-blocks, means for gagin the rails, anchors mounted in said bases an bolts connecting the bases of the rails to the said anchors substantially as specified.
  • An improved track construction for tr t and other railways comprising con crete bases, there being cavities formed in said bases at intervals of the ion th of the same, a bod of sand or other slig tly-resilient mat-aria in certain of said cavities, a cover or packin placed upon said body of resilient inateria rail-blocks placed Within said cavities upon said cover or packin rails mounted upon said rail-blocls, means or securing the bases of said rails in position upon said rail-blockaineans for gaging the rails, anchors detachably mounted in said bases, and bolts connecting the bases of the rails to the said anchors; substantially as specified.
  • a pair of rail-bases formed of bodies of concrete extending parallel with each other and arranged longitudinally beneath the trackrails, cushions arranged at suitable intervals in the tops of said bases, and means whereby track-rails are anchored to the bases; substantially as specified.

Description

PAI'BXTED AUG. 14, 1906. R. D. GHLVER.
APPLIOAIIOI FILED IAE. '1, 1908.
42 6 F161. 7' 7' ii 24 24 4 EEE F v Q A I 7 I R w m a: W Z .1 w E u A.- m u m. v H. Z e V- B r V J 4%.. i @Qv (NEWS 0 I'll "Gilli Plflll 00., VII-"IMO"; D-
TRACK GONSTRUGTION FOR STREET AND OTHER RAILWAYS.
ITNITED STATES PATENT OFFICE.
REUBEN D. CULVER, OF VVEEDERSBURG, INDIANA. TRACK CONSTRUCTION FOB: srass rfawo OTHER answers.
Specification of Trotters Patent.
Patented Aug. 14, 1906.
Application filed March '7, 1906. Serial No. SDiJIUO.
To a, whom it may concern:
Be it known that I, REUBEN D. Convene citizen of the United States, and a resident of Veedersburg, Fountain county, Indians, have invented certain new and useful Improvements in Track Construction for Street and other Railways, of which the following is a specification containing a full, clear, and exact description, reference being had to the accompanying drawings, forming a part hereof.
My invention relates to an improved track construction for street and other railways; and it consists in the novel elements and combination of elements hereinafter described and claimed.
The ob'ect of my invention is to provide an improve track construction for street and other railways which is practically inclestructible through the action of the elements or through wear, except as to the rails.
The further object of my invention is to provide a railway-track construction which will be perfectly drained and not liable to get 7 out of alinement because of settling and which will yet be sufficiently elastic to prevent all injurious jar or vibration.
The further ob ect is to provide a railways; track construction wherein when the grade has been once established the same may be maintained perpetually at almost no cost;
The further object is to provide such 'a systern of'railway-track construction as will be specially adapted for use in constructin or reconstructing. street-railways in pop one; cities and towns and in the building er sub way-tracks and tracks in railway yards and terminals.
The further object is to provide a railwaytrack construction which will be practicable in reconstructing ordinary railway-tracks on thorou lily-settled grades.
The urther object is to provide a railwaytrack construction which will obviate the necessity of crossties and yet provide an independent base for each rail, whereby should one base settle such settling will not throw upwardly the opposite rail, as is the case when cross-ties are used.
In the drawings, Figure 1 is a transverse section of a street-railway construction made in accordance with my invention. Fig. 2 is a sectional side elevation. Fig. 3 is a plan view of one of the cement-concrete bases. Fig. i is a detail view showing the construction of the lower end of a rail-anchor, and
Fig. 5 is a detail view of a modified construe-- 2 2 indicate parallel trenches under the lines of rails 3, and which trenches are er fectly drained by a i e or sewer whic is located oentrail a s ig t distance below each trench 2. Wit 'n the trenches are laidce -1nent-concrete bases 5. Said bases maybeoi any desired shape in cross-section to adapt them for the required service, and in some cases I prefer to make the bases with slo i'ng or buttressed sides, as shown by dotted lies in Fig'fljalthough in ordinary cases itivill be suflicient to have the side walls vertical. I grater also to make the bottom wall of the ases thicker than the side walls, as it must act as a foundation for said side walls, as Well as for all other parts of the track construction. I refer to make saidbases continuous from an to end of the line; but of course some may be made in sections of any desired length, the .iine 6 in Fig. 2 indicating the point of separation between adjacent sections when the bases are made in sections, or
the sections may be separated at'any other suitable point in the length of the bases.
Asuitable numb er of cavities 7 are formed in the upper part of the body of the cement-concrete composing the b ases 5. Said cavities are preferably rectangular, but of coursemay be of any desired shape provided they are open at assess? They should be of uniform size.
After the concrete has thoroughly set and formed its bond, 8. body 8, of sand, fine gravel, cinders, earth, burnt clay, or any other indestructible but slightly-resilient materiai, should be placed within said cavities, so as to partially fill the same, and then said body of slightiywesiiient material shouid be' thoroughly tarnped and brought to the desired grade. Placed upon the'body of resilient material .8, in orderto hold the same in osition, is, a cover or packing? which may be in the iorn'r of a creosoted plank or athin layerof'asohalt or coal-tar composition, or
un other material suitable for such purpose.
f he resilient material and its cover or 'packing'form what I term cushions, and superimposed upon said cushions are red- "supporting blocks or sleeper-blocks 10, of any desired thickness or shape, but preferably that shown in the drawings, the same being,
rectangular and loosely fitting within the ICC cavities 7. Said blocks 10 may be made of burnt clay, cement-concrete, metal, stone, chemically-treated. wood, or any other suit able and practically-indestructible material. The space between. the blocks 10 and the walls of the cavities is very slight and should be filled with sand, coal-tar, or other imervious but yielding material. The upper faces of the said blocks 10 preferably have a central longitudinal depression 11, in which the bases 12 of the rails 3 are located. Said rails may of course be of the usual forms in cross-section; but in the present instance I have shown the bases of the rails trussshaped in cross-section, or, in other words, the base is arched in cross-section, thus forming a yielding or spring base, and thereby affording additional resiliency to the rails for the pur ose of lessening the vibration or jar caused y locomotives or cars.
The rails 3 are preferably gaged or spaced apart by means of tie-rods 13, the ends of which are passed through holes in the webs of the rails and secured b r means of nuts 14. The rails are secured to t e blocks 10 by anchor-bolts 15, the up er ends of which pass through holes in the ase of the rail on both sides of the web and are thereat provided with nuts 16 or e uivalent securing means. The lower ends oi said anchor-bolts 15 are provided with hooks or bends 17, which pass around short sections of pipe or steel rods, forming anchors such as 18, and said anchors may be embedded in the concrete, as shown in Fig. 5, or detachably mounted in anchorseats 19, formed in the concrete, as shown in Fig. 2. Said anchorbolts 15 are preferably located in transverse recesses 20, formed in the cement-concrete bases 5 at points about midway between contiguous cavities 7. Said blocks 10 are preferably made hollow by means of longitudinal openings 21 in order to lighten the same.
22 indicates a small drain-passage formed in the bottom of the cavities 7 and extending through the bottom wall of the concrete bases for the urpose of draining the said cavities, and the upper end of said drain 22 is preferably closed by means of a porous earthenware plug or something similar thereto, whereby the sand will be prevented from passing into said drain, and et any water may percolate through said p ug 23.
24 indicates openings formed in the side walls of the bases 5, said openings being for the purpose of affordin means for inserting the sand or other suitab e material into the cavities should it be necessary to do so in order to effect the proper alinement of the rails after the track has been constructed. These 0 enin s when not used for this purpose are cosed y a body of cement or any other suitable material, so as to prevent the sand, &c., contained in the cavities from working out of said openings or water from finding ingress into the cavities. By providing these openings the cushion material may be inserted into the cavities, if necessary, without dismantling the track. The bottoms of said cavities 7 are preferably inclined from opposite sides to the center to facilitate drainage.
By reason of the abovedescribed con struction it will be observed that the resilient mounting of the rails and the resilient bases of the rails themselves will have the effect of greatly lessening the wear and tear on both track and rolling-stock.
It will be further observed that there is an independent base for each rail, so that the possible settling of the base which supports one rail would have no effect upon the position of the opposite rail.
I have thus shown a construction of railway-tracks (steam or electric) which is absolutely indestructible through the action of the elements or through wear, except as to the rails. Being perfectly drained, the structure cannot subside or settle, yet is sufficiently elastic to properly prevent all jar or vibration. Its alinement and grade once established can be maintained perpetually at practically no cost. Such a system of construction will be found of special advantage in the constructing or reconstructing of street-railways in populous towns and cities, in the building of subway-tracks and tracks in railroad yards and terminals. It will be equally practicable in reconstructing ordinary railway-tracks on thoroughly-settled grades.
I claim 1. In a railway-track construction, a concrete base extending longitudinally beneath each track-rail, and rail-cushions arranged at intervals in the tops of said bases; substantially as specified.
2. In a railway-track construction, a concrete base extending longitudinally beneath each track-rail, there bein cavities formed at intervals in the to s of t e bases, and railcushions arranged in said cavities; substantially as specified.
3. In a railway-track construction, a concrete base extending longitudinally beneath each track-rail, there being cavities formed at intervals in the top of each base, rail-cushions arran ed in said cavities, and track-rails supported y said cushions; substantially as specified.
4. In a railway-track construction, a con crete base extending longitudinally beneath each track-rail there being cavities formed at intervals in the top of each base, rail-cushions arranged in said cavities, rails mounted on said cushions, and means whereby said rails are rigidly connected to the bases; substantially as specified.
5. In a railway-track construction, a concrete base extending longitudinally beneath each track-rail, there being cavities formed at intervals in the tops of each of the bases,
cushions located in the bottoms of the cavities, and rail-supporting blocks located in said cavities above the cushions; substantially as specified.
6. An improved track construction for street and other railways, comprising concrete bases, there being cavities formed in said bases at intervals of the length of same, a body of sand or other slightly-resilient material in'certain of said cavities, a cover or packing placed u on said bodv of resilient material, rail-bloc s placed Within said cavities upon said cover or packin rails mounted upon said rail-blocks, means or securing the bases of said rails in position u on said railblocks, and means for gaging t e rails; substantially as specified.
7. An improved track construction for street and other railways, comprising concrete bases, there bein cavities formed in said bases at intervals 0 the length of same,
I a body of sand or other slightly-resilient material in certain of said cavities, a cover or packing placed upon said bodv of resilient material, rail-blocks placed Within said cavities upon said cover or packing, rails mounted u on said rail-blocks, means for securin the ases of said rails in position upon said rail-blocks, means for gagin the rails, and the upper faces of said rai -blocl(s having lon itudinal depressions in which said rails are located; substantially as specified.
8. An improved track construction for street and other railways, comprising concrete bases, there being cavities formed in said bases at intervals of the Ian th of the same, a body of sand or other slightly-reed? ent materia in certain of said cavities, a cover or packin placed upon said body of re silient materia rail-blocks placed Within said cavities upon said cover or packing, rails mounted upon said rail-blocks, means for securing the bases of said rails in position upon said rail-blocks, means for gagin the rails, anchors mounted in said bases an bolts connecting the bases of the rails to the said anchors substantially as specified.
9. An improved track construction for tr t and other railways, comprising con crete bases, there being cavities formed in said bases at intervals of the ion th of the same, a bod of sand or other slig tly-resilient mat-aria in certain of said cavities, a cover or packin placed upon said body of resilient inateria rail-blocks placed Within said cavities upon said cover or packin rails mounted upon said rail-blocls, means or securing the bases of said rails in position upon said rail-blockaineans for gaging the rails, anchors detachably mounted in said bases, and bolts connecting the bases of the rails to the said anchors; substantially as specified.
10. In a track construction for street and other railways, the combination of independent cement-concrete bases having a series of cavities, cushioning devices mounted in said cavities, rails mounted upon said cushioning devices, the bottom of said cavities being inclined, a drain-passage in the bottom of said cavities and a porous plug at the upper end 3f Said drain-passagc substantially as speci- 1 1. In a railway-track construction, a pair of rail-bases formed of bodies of concrete extending parallel with each other and arranged longitudinally beneath the trackrails, and cushions arran ed at suitable intervals in the tops of said bases; substantially as specified '12. In a railway-track construction, a pair of rail-bases formed of bodies of concrete extending parallel with each other and arranged longitudinally beneath the trackrails, cushions arranged at suitable intervals in the tops of said bases, and means whereby track-rails are anchored to the bases; substantially as specified.
In testimony whereof I have signed my name to this specification in presence of two subscribing witnesses REUBEN D. OULVER. Witnesses ,M, P. SMITH,
EDWARD E. Lenses
US30470006A 1906-03-07 1906-03-07 Track construction for street and othe railways. Expired - Lifetime US828718A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US30470006A US828718A (en) 1906-03-07 1906-03-07 Track construction for street and othe railways.

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
US30470006A US828718A (en) 1906-03-07 1906-03-07 Track construction for street and othe railways.

Publications (1)

Publication Number Publication Date
US828718A true US828718A (en) 1906-08-14

Family

ID=2897194

Family Applications (1)

Application Number Title Priority Date Filing Date
US30470006A Expired - Lifetime US828718A (en) 1906-03-07 1906-03-07 Track construction for street and othe railways.

Country Status (1)

Country Link
US (1) US828718A (en)

Similar Documents

Publication Publication Date Title
US828718A (en) Track construction for street and othe railways.
US1218141A (en) Railway-tie.
US964190A (en) Railway road-bed.
US676129A (en) Apparatus for surfacing railroad-tracks.
US841367A (en) Railway road-bed.
US621657A (en) Road-bed for railways
US588080A (en) Railway-track structure
US1066085A (en) Rail-support.
US987041A (en) Railway road-bed and track construction.
US1046575A (en) Reinforced-concrete railroad-tie.
US759852A (en) Concrete railway-tie.
US1307565A (en) Samuel a
US512343A (en) Method of laying railway-rails in paved streets
US1094635A (en) Railroad-tie.
US847783A (en) Railway-tie.
US777861A (en) Road or pavement.
US758612A (en) Concrete railway-tie.
US645181A (en) Railway construction.
US1381441A (en) Railroad-tie
US1013736A (en) Railway road-bed, track, and rail construction.
US679867A (en) Railroad-bed.
US128120A (en) Improvement in railway tracks
US694276A (en) Railroad construction.
US625675A (en) hevner
US758613A (en) Concrete railway-tie.