US3831385A - Arctic offshore platform - Google Patents

Arctic offshore platform Download PDF

Info

Publication number
US3831385A
US3831385A US00266084A US26608472A US3831385A US 3831385 A US3831385 A US 3831385A US 00266084 A US00266084 A US 00266084A US 26608472 A US26608472 A US 26608472A US 3831385 A US3831385 A US 3831385A
Authority
US
United States
Prior art keywords
ice
water
wall
sheet
heat
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
US00266084A
Other languages
English (en)
Inventor
T Hudson
G Strickland
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chevron USA Inc
Original Assignee
Chevron Research and Technology Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chevron Research and Technology Co filed Critical Chevron Research and Technology Co
Priority to US00266084A priority Critical patent/US3831385A/en
Priority to CA171,931A priority patent/CA982832A/en
Priority to FI1931/73A priority patent/FI62697C/fi
Priority to GB2891073A priority patent/GB1417895A/en
Priority to NO2590/73A priority patent/NO148079C/no
Priority to DK350873A priority patent/DK143114C/da
Priority to US05/490,174 priority patent/US3972199A/en
Application granted granted Critical
Publication of US3831385A publication Critical patent/US3831385A/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B17/0017Means for protecting offshore constructions
    • E02B17/0021Means for protecting offshore constructions against ice-loads

Definitions

  • ABSTRACT A method and apparatus for reducing ice forces on a marine structure erected in a body of water which becomes frozen through natural weather conditions.
  • the structure has a wall of heat transmitting material forming its perimetrical surface in the zone where natural ice will freeze onto or impinge against the structure.
  • Enclosed chambers are built within the structure and in heat transmitting relationship with the outer wall and heat is applied to the chambers to heat and maintain the outer wall at a temperature above the melting point of the natural ice occurring in the water around it.
  • the marine structure is formed with a heated wall which slopes upwardly and inwardly in the area of ice contact to provide a ramplike surface upon which a sheet of ice will be forced with reduced friction as it moves against the structure.
  • a heated wall which slopes upwardly and inwardly in the area of ice contact to provide a ramplike surface upon which a sheet of ice will be forced with reduced friction as it moves against the structure.
  • This invention relates to a marine structure for installation in waters upon which thick sheets of ice are formed during the winter season.
  • the winter ice normally may reach thicknesses of 6 to 10 feet or more and rafting, pressure ridges, and other accumulations may cause the thickness of the ice in places to be several times the thickness of the original sheet.
  • the ice sheets are of vast area and although normally they may move relatively slowly with wind and water currents, the mass of ice in movement can cause very high forces on a stationary structure in its path.
  • Such ice may have a compressive strength in the range of about 650 to 1,000 pounds per square inch and a structure strong enough to withstand the crushing force of the ice would necessarily be very massive and correspondingly expensive to construct.
  • the amount of force imposed initially on the structure by the ice sheet will, of course, be dependent on the form, dimensions and characteristics of the structure and the dimensions and characteristics of the ice. But in all cases, as the problem is understood now, a much greater force will be imposed initially on the structure before the adhesive bond between it and the ice is broken than will be imposed after the bond is disrupted. Ordinarily it would be necessary under these conditions to build the structure strong enough to withstand the initial forces imposed on it by the ice sheet even though the forces imposed on it during the major portion of its useful life would not require a structure of such rugged construction.
  • a structure built strong enough to withstand the initial ice forces would be correspondingly more expensive to build and more difficult to install than one designed to take only the load of a relatively moving ice sheet.
  • the present invention is designed to alleviate this condition of initial high loading imposed on the offshore structure by a method and apparatus to be described hereinafter.
  • a method for preventing the natural ice from freezing on and adhering to the surfaces of the offshore structure exposed to the water in the zone of natural ice formation and appropriate apparatus is exemplified to accomplish this method.
  • This method comprises a system for applying heat to the inner surface of the outer wall or shell of the structure, particularly adjacent the water line where the natural ice will tend to freeze onto or impinge against the outer surface of the shell to cause the temperature of the outer surface of the shell in the area of ice contact to be maintained above the melting point of the ice.
  • the heating system is such that heat can be applied continuously to the shell of the platform while ice is present in the water around it, both to prevent adhesion of ice to the shell and to provide a film of water between the ice and the outer surface of the shell to assist the ice in slipping over and upon this surface when the ice contacts it, both of which features function to reduce the force imposed on the structure by the moving ice sheets.
  • an offshore drilling platform is constructed with a portion of its perimetrical outer wall or shell in the form ofa frustum of a cone sloping upwardly and inwardly of the platform at an angle of approximately 45 to the horizontal.
  • the conical surface extends from a location below the region of ice formation on the surface of the water to some distance above the level of the water surface and will function somewhat in the manner of a ramp upon which an edge ofa sheet of ice will be raised above its natural level on the surface of the water as the ice moves toward the platform.
  • the ice sheet will be flexed in the region of the platform causing the ice to fracture and break from the tensile forces resulting from the flexural Stress.
  • Water-tight compartments which in the preferred embodiment function as water tanks, are constructed within the platform adjacent the outer conical shell and the latter acts as a common exterior wall for both the platform structure and the water tanks.
  • the tanks are connected to pumps for circulating water through them and through heat exchangers, which latter are in communication with the exhaust gases from the engines which generate the power for operating the machinery and other apparatus on the platform.
  • the tanks are filled with water which is heated an amount to maintain the outer surface of the shell of the platform above the melting point of the natural ice which forms around or impinges upon it, thus preventing the ice from freezing onto and adhering to the outer surface of the platform.
  • the water tanks are of sufficient capacity to contain enough heated water to maintain the critical area of the shell of the platform at a temperature above the melting point of the natural ice throughout a period of at least 24 hours if no additional heat is added to the water during that time.
  • This will provide a safe period for making repairs if the source of heat for the water should fail during the critical period when the ice sheet may otherwise be in a condition to freeze onto the platform and start moving. It will be noted that if the source of heat for the water fails during the time when the ice sheet is in motion so that the intact ice sheet does not adhere to the shell, any additional load imposed on the platform by the ice will be considerably less than the force imposed on the platform by the thrust of an ice sheet which is frozen onto and adhering to the shell.
  • FIG. 1 is a schematic representation, partly in section and with some elements rearranged in position for clarity of disclosure, of an offshore drilling platform incorporating the features of this invention and illustrates the embodiment which employs heated water tanks to maintain the critical areas of the shell of the structure above the freezing temperature of the natural ice around it.
  • FIG. 2 is a schematic illustration in sectional plan view taken on the line 22 of FIG. 1.
  • FIG. 3 is a schematic representation in elevation and partly in section of another arrangement of apparatus incorporating the features of this invention and illustrates the use of heat transfer panels to heat the critical area of the perimetrical shell of an offshore structure above the melting point of the natural ice surrounding It.
  • FIG. 4 is a schematic illustration in plan view and partly in section taken along the line 4-4 of FIG. 3, with portions broken away to expose details of the assembly.
  • FIG. 1 represents an offshore drilling platform 10 installed in a body of water 12 in engagement with the underwater bottom 14 to which it is secured temporarily by piles 16.
  • the platform is designed particularly for installation in arctic waters upon which thick sheets of ice 18 will seasonably be formed.
  • the platform has a lower support portion 20 which extends into the water and forms a base which supports a deck portion 22 above the surface of the water.
  • the lower portion of the platform is exposed to the water and ice forces incident to its environment and is the portion of the platform of principal interest to the present invention.
  • the upper portion of the platform may contain several levels of decks and may be enclosed and heated to provide a reasonably comfortable working environment and protection for men and equipment from the winter weather during which the temperature may drop to the range of F. Without adequate heating facilities in the working areas the operation of the arctic drilling platform would become virtually impossible during a major portion of the year.
  • the drilling platform illustrated in FIG. 1 may be designed to drill 10 or more wells from the same platform site to a depth of approximately 16,000 feet and accordingly is made large enough to accommodate the machinery and equipment necessary for this purpose.
  • a platform of this capacity for installation in 40 feet of water may have a bottom diameter of approximately 180 feet and a diameter at the water line of approximately 120 feet.
  • the base portion may have a height of 85 feet and support above it decks and other appurtenant equipment including a drilling derrick reaching to an elevation of approximately 160 feet above the floor of the sea.
  • a drilling platform of the above-noted dimensions will weigh several thousand tons before it receives any of the machinery and equipment necessary for the drilling operation.
  • the weight of the platform will increase proportionately as it is designed to withstand greater natural forces and since the weight of the structure reflects its cost, the cost will increase proportionately as the weight increases.
  • the present invention is directed toward a procedure for reducing the forces imposed on the base portion by natural ice formations, thus permitting less structural material to be incorporated in it and correspondingly reducing its mass as well as reducing its cost.
  • the waste heat from the power generating source is used to heat the shell of the platform above the melting point of the natural ice surrounding it in the manner and for the purpose to be described in more detail hereinafter.
  • the power source selected is a turbine engine and three 1,100 hp gas turbines are used for the power necessary to operate the drilling platform.
  • more than 32,000,000 BTU/hr. waste heat from the turbines will be available for heating the shell of the support structure. This amount of heat is amply adequate to maintain a shell of the dimensions noted above continuously at a temperature above the melting point of the natural ice formed in the water in contact with it.
  • FIG. 1 represents a drilling platform which is towed to the drilling site in a completely assembled and equipped condition and which requires no additional construction at the site except for lowering it into engagement with the sea bottom and, when necessary, securing it with piles.
  • Ballast tanks 24 (FIGS. 1 and 2) are built into the base portion 20 as an integral part of it to ballast the platform when being towed and to enable it to be lowered through the water into contact with the sea bottom.
  • the ballast tanks are each provided with appropriate sea cocks 26 which can be manipulated remotely from aboard the platform by means not shown but which can be provided for within the skill of the art and each ballast tank has connected to it a respective blowdown pipe 28 which receives air under pressure from a compressor 30.
  • the sea cocks can be opened to admit water into the ballast tanks or, alternatively, pressurized air can be introduced into the tanks to expel water from the tanks through the sea cocks.
  • ballast tanks When the platform is under tow, enough water is admitted to the ballast tanks to give it a draft of about 8 to 10 feet and the ballast tanks have sufficient volume to provide adequate buoyant space above the ballast water to give the platform stability in its towing condition.
  • the ballast tanks may of course be trimmed as necessary to compensate for any uneven distribution of weight in the platform.
  • the drilling platform represented by FIG. 1 is constructed to be readily established with full operating capability at a selected drilling site and with the ability to be removed from one site and established at another in operating condition without delay. To assist this mobility it is desirable that the platform be constructed to be stabilized at an offshore location with a minimum of secondary construction operations, such as the driving of piles, being required to secure it in position against the forces it will be exposed to.
  • the platform is constructed with a plurality of leg members 31 which are mounted to be moved vertically relative to the body of the platform by corresponding jacking arrangements 33.
  • the legs have expanded foot portions 35 and contain internal guides 32 (FIG. 2) for the piles 16.
  • FIG. 2 When the platform assembly reaches a drilling site, and while it still is floating, the leg members are lowered into engagement with the sea bottom. While the jacks are engaged with their respective legs the sea cocks 26 are opened to admit additional water to the ballast tanks 24 increasing the weight of the platform enough to give it negative buoyancy.
  • the footings 35 are designed to control the penetration of the legs into the sea bottom as the weight of the platform increases.
  • the jacks 33 are now operated to lower the platform along the legs in a leveled controlled condition until the bottom 37 of the platform is seated on the sea floor.
  • the ballast tanks may now be flooded an additional amount, adding sufficient weight to the platform for it to resist being displaced by natural forces.
  • the piles 16 may be driven into the submerged earth to hold the platform securely in position against horizontal loads imposed on it. It is an object of this invention to provide means for reducing considerably the force which otherwise would be imposed on a stationary platform by an ice sheet moving against it, thus enabling a structure to be assembled which is more adaptable to the conditions of use described heretofore.
  • the piles 16 When the platform is to be moved to another location the piles 16, if such piles have been used, are cut below the footings 35 or otherwise detached from the platform.
  • the compressors 30 are operated to expel water from the ballast tanks until a condition of buoyancy of the assembly is reached which will permit it to be elevated off bottom along the legs 31 under controlled conditions. Preferable during this operation, sufficient water will be kept in the ballast tanks to give the platform some negative buoyancy and it will be lifted along the legs by the operation of and under control of the jacks 33.
  • the platform is raised to its floating position, the ballast is adjusted, and the assembly is towed to its new location where it is again set on bottom as described heretofore.
  • FIG. 1 represents the drilling platform installed at the drilling site and equipped for the drilling operation.
  • the derrick indicated at 39, is enclosed for protection from the weather and extends into the body of the structure to a deck 41 which contains a support 43 for the rotary table.
  • the derrick has a crown block 45 which can be shifted to be aligned vertically with each of the several positions 47, FIG. 2, on bottom plate 49 through which separate wells may be drilled.
  • the rotary table not shown, likewise is constructed to be moved into alignment selectively with each of the positions 47.
  • a casing 51 is set in the well bore and sealed with a watertight connection 53 to the plate 49. If the platform is to be moved to another location, the casing will be detached from the platform and a watertight cover will be secured over the corresponding opening.
  • gas turbines may be used as the primary source of power for the platform.
  • Two of the power generating gas turbines 34 and 36 are illustrated schematically in form and position in FIG. 1.
  • the exhaust from each turbine is led through a respective conduit 38 and 40 to heat exchangers as represented by the coils 42 and 44.
  • ballast tanks 24 are substantially filled with a heat transfer liquid. Atmospheric space 48 is left at the top of the tanks to function as a surge chamber and to provide for expansion of the liquid. Otherwise the ballast tanks may be connected to auxiliary surge tanks, not shown, for this purpose.
  • the heat transfer fluid may be sea water to which an appropriate corrosion inhibitor has been added to protect the steel surfaces in contact with it.
  • an antifreeze component is added to the water to prevent it from freezing solid within the ballast tanks and to cause it to remain pumpable if the water is not heated during a period when the shell of the support structure is reduced below the freezing point.
  • the ballast tanks may be purged of any salt water they contain and filled with fresh water to which is added a corrosion inhibitor, an antifreeze component and an algicide to make up a compounded heat transfer fluid.
  • Antifreeze components available for this purpose would be, for example, soluble salts, such as sodium chloride and calcium chloride, an alcohol such as methanol, or a glycol such as ethylene glycol, or a glycerol, or any of several other antifreeze substances which are well known, any of which may be added to the water in the ballast tanks in a sufficient amount to prevent the water from freezing to a nonpumpable condition throughout a predetermined temperature range at a time when heat is not being applied to the water.
  • a corrosion inhibitor is selected to be compatible and effective with the chosen antifreeze component.
  • the heat exchangers 42 and 44 are connected by appropriate pumps, as 50 and 52, respectively, to a common manifold 54 from which respective conduits, as 56 and 58, communicate with the top portion of each individual tank 24 below the level 59 of the water contained in it.
  • the lower portion of each tank is in communication with a common manifold 60 through respective lower conduits, as 61 and 62.
  • the heat exchangers 42 and 44 are connected to manifold 60, as
  • valves placed in the upper and lower conduits such as, respectively, valve 65 in conduit 56 and valve 66 in conduit 61 provide a means for controlling the flow of heat transfer fluid through an individual tank independently of the flow through adjoining tanks and also provide a means for isolating an individual tank from the heat transfer fluid circulating system as may be necessary for repair or maintenance.
  • ballast tanks for a platform of the dimensions described heretofore are designed to hold in excess of a total of 20,000 barrels of water.
  • the heat transfer fluid circulating system is designed to circulate fluid through these tanks at the rate of approximately 800 gallons per minute when the platform is in normal operation and 32,000,000 BTU/hr. will be available from the power generating turbines to heat this fluid.
  • FIGS. 1 and 2 indicates, by way of example, six ballast tanks 24. However this is not a critical number and more or fewer tanks may be appropriate for particular platforms.
  • the tanks illustrated are separated by radially disposed watertight walls or bulkheads 67 and are closed on their radially inwardly sides by a cylindrical wall or bulkhead 68.
  • the radially outer wall of the tanks is the perimetrical wall or shell 70 of the lower portion 20 of the platform.
  • FIG. 1 also indicates the ballast tanks as extending from the watertight bottom 37 of the platform up to the bottom deck 74 of the upper portion 22 with the heat transfer fluid in the ballast tanks in direct heat transfer contact with the inner surface 76 of outer wall 70 throughout substantially all of this region.
  • tanks for the heat exchange fluid which, although of adequate capacity, are of less volume than those indicated in the drawings.
  • Such smaller tanks will be distributed around the inner surface 76 of the wall 70 and be constructed to expose the inner surface to contact with the heat exchange fluid throughout the area where natural ice could freeze to the shell, extending for a distance above and below the surface level of the ambient water, to maintain this zone of the shell above the melting temperature of the natural ice in contact with it.
  • a weighted dry ballast may be used which requires less space than water ballast and thus provides additional dry working area within the platform.
  • the cylindrical bulkhead 68 defines working space at the core of the platform and appropriate decks, as 41, 78 and 80 are provided to support men and machinery. Although this space will be heated to a comfortable working temperature which normally may be above the temperature of the fluid in the tanks 24, there is nevertheless provided a layer of insulation 84 placed against the radially inner surface 86 of bulkhead 68 to reduce heat loss from these tanks if the temperature of the core area 88 should be below that of the tanks.
  • a wear plate 90 is secured to the outer surface of the shell in the zone on the platform of ice contact to strengthen this area and to receive the impact and abrasive action of the ice sheet bearing against the support structure.
  • FIGS. 3 and 4 represent an alternative arrangement of apparatus embodying the present invention and indicate also a modified form of platform to which it is applied.
  • the same numerals as used previously will be used again where applicable in relation to FIGS. 3 and 4 to designate corresponding elements.
  • the lower support portion and the upper deck portion 22 may be constructed as separate units which will be assembled together at the offshore site.
  • the support portion has pile guides 32 built into it around its periphery as well as through its central section to receive a corresponding number of piles 16.
  • the support portion of the platform is towed to a chosen offshore location and sunk into contact with the sea bottom by increasing the ballast weight. Piles 16 are then inserted through the pile guides 32 and driven into the submerged earth. The support section is leveled and the piles are grouted to the pile guides to hold the platform securely in position against the horizontal and vertical loads imposed on it. Subsequently, the upper deck portion 22 is lightered to the location and assembled on the stabilized lower portion.
  • a watertight bulkhead 68 surrounds the central area 88 of the platform and defines the inner wall of compartments 100 and 102 which may be used as ballast tanks for trimming the platform under tow and for sinking it at the well site in the manner described heretofore.
  • panels of coils of tubing are fitted to the inner surface of the shell in heat transfer relationship and the panels are manifolded together to receive the heat transfer fluid from heat exchangers which are exposed to the exhaust gases of the power generating turbines for the platform in a manner similar to that described heretofore.
  • the water may be displaced from the individual compartments which are then loaded with sufficient dry weighting material to compensate for what ever residual buoyancy the assembled platform may have.
  • This procedure reduces the corrosion problem of the interior surfaces of the compartments caused by water contained in the tankage and also provides additional dry working or storage space within the confines of the platform.
  • the heating panels 104 are placed against the interior surface 76 of the shell 70 in heat transferring relationship throughout the area which will be in contact with the ice sheet 18 formed on the surface of the ambient water and preferably will extend for some distance above and below the thickness of the sheet to assure that this area of the shell will be elevated in temperature above the melting point of the surrounding ice.
  • a wear plate is secured to the outer surface of the shell in this area for the purpose described heretofore.
  • the panels of heating coils are covered on their inward surfaces with a layer of insulating material 106, such, for example, as a foamed urethane to confine the heat from the panels to the shell of the platform in this area.
  • the insulating material is in turn covered by a cover 107 secured in a watertight manner to the surface 76 to prevent water in the ballast tanks from contacting the heating panels and the insulation.
  • a heat transfer fluid of the type described heretofore flows from surge tanks, as 108 and 1 10 into a manifold 54 from which it is taken by pumps 50 and 52.
  • the pumps deliver the fluid to heat exchangers 42 and 44 which receive heat from the exhaust gases of the platform power generating engines 34 and 36 through ducts 38 and 40.
  • the fluid flows from the heat exchangers to a manifold 112 and from the manifold respective conduits 114 conduct the fluid to the heat transfer panels 104.
  • the fluid is pumped through the tubing 116 of the panels and thence flows through respective conduits 118 into a manifold 120 from which it is conducted by piping 122 to the respective surge tanks as 108 and 110.
  • Appropriate valving is placed in the system to provide for the control of the fluid circulation to any one of the panel sections or to any surge tank and to enable these portions of the apparatus to be taken out of the operating system for maintenance or repair.
  • respective valves 124 are placed in the conduits 114 from the manifold 112 to the corresponding sections of the heat transfer panels 104 and respective valves 126 are placed in 'the conduits 118 carrying the return fluid from the heat transfer panels to the manifold 120.
  • each section of the surge tankage can be isolated independently of the others by a respective valve 128 placed in the piping 122 which leads from the manifold 120 to the surge chamber and by a corresponding respective valve 65 in the conduits, as 56 and 58, from the individual surge chamber, as 108 and 110, to the manifold 54.
  • the shell of the platform in the zone thereon of ice formation can be heated above the melting point of the ice by diverting the exhaust gaseous fluids from the power generating engines through appropriate ducting into heat transferring contact with the inner surface of the shell to function as the heat transfer fluid. Also, it is within the concept of this invention to provide sufficient power generating means aboard the platform to generate power for panels of electrical heating elements arranged in a manner similar to that described with reference to the heat transfer panels illustrated in H68. 3 and 4.
  • auxiliary sources of power may be used directly to supply the heat necessary to prevent ice from adhering to it.
  • a steam boiler may be used which is designed primarily to supply the heat transfer fluid for the ballast tanks 24 or for the heating panels 104, or the heat may be supplied by a power source external to the platform, as by connecting panels 104 of electrical heating elements to a source of electrical power generated apart from the platform.
  • the inventive concept is directed to the method and appropriate apparatus for reducing the forces imposed by natural ice on an offshore platform.
  • the force imposed on such a platform by the movement of a sheet of ice 8 feet thick frozen on and adhering to its steel shell will be approximately 10,000,000 to 20,000,000 pounds total.
  • the force of the ice sheet upon the platform will be reduced in the order of five to ten times for a total force of approximately 2,000,000 pounds.
  • a method for reducing ice forces on a marine structure established in a fixed condition in a body of water which becomes frozen through ambient natural conditions comprising:
  • said heat transfer fluid is a liquid which is heated by heat generated from a source on said marine structure and is circulated through a heating means therefor and through said chamber by a circulating pump mounted on said marine structure.
  • said heat transfer fluid is a mixture comprising water, an antifreeze component and a component to inhibit corrosion of the walls of said interior of said chamber.
  • a method for preventing ice from adhering to a selected surface of a marine structure established in a fixed condition at a location in a body of water which becomes frozen through ambient natural conditions comprising forming an outer wall for said structure at a position which will be in contact with said water in a zone of natural freezing of said water,
  • said wall being formed of a material which transmits heat and having an interior surface exposed within said structure and an exterior surface in contact with said water, heating said interior surface of said wall by means of a source of heat generated on said structure,
  • said film of water providing a means for reducing the force imposed on said structure by said ice as said ice moves upon said structure in engagement with said wall.
  • a method for reducing the force imposed on a marine structure established in a relatively fixed location by the movement against it of a sheet of ice present in the water adjacent the said structure comprising constructing said structure with an outer surface which is sloped inwardly and upwardly of said structure in the area of potential contact with an ice sheet present in said water,
  • said heated surface to function as. a ramp to cause a portion of a sheet of ice which moves against said structure to be lifted and bent from its normal position on said water
  • said film of water providing a means for reducing the force imposed on said structure by said ice as said ice moves relative to and against said structure and in engagement with said surface
  • a marine structure constructed to be maintained in a fixed position in a body of water which becomes frozen through natural conditions, comprising a support portion of said structure,
  • said support portion extending into a body of water and supporting a work platform above the surface of said water
  • said wall constructed to be disposed at an angle inclined to said surface of said water to provide a ramp-like surface to receive a sheet of ice moving relative to and in contact with said structure
  • Means for reducing the effect of ice forces on a structure established and maintained in a fixed position in an open sea environment, which sea becomes frozen at the surface through natural conditions, comprising a marine structure positioned in an open sea environment in fixed relationship to the bottom of the sea,
  • a selected area of said wall being formed of a material which readily transmits heat
  • said selected area of wall extending upwardly from below the surface of said sea'to above said surface at least throughout a zone of natural freezing of said water
  • Means for reducing the effect of ice forces in accordance with claim 11 in which the said selected area of said perimetrical wall is sloped upwardly and inwardly of said structure at an angle of approximately 45 to the horizontal to provide a ramp-like surface to receive and elevate above its natural level on said sea a portion of a sheet of ice which moves against said structure, thereby to cause said sheet of ice to bend and break adjacent said wall.
  • An offshore drilling platform for use in a body of water which becomes frozen through natural conditions, comprising a supporting base portion constructed to be installed in a relatively fixed position in a body of water,
  • said base portion constructed with sufficient buoyant capacity to maintain said drilling platform in a floating condition to permit said platform to be towed through said water
  • ballast compartments means for admitting ballast into said ballast compartments to decrease said buoyant capacity an amount to cause said drilling platform to be lowered into contact with the underwater bottom
  • ballast compartments means for circulating a heat transfer fluid through said ballast compartments
  • An offshore drilling platform in accordance with claim 13 including a power generating engine on said platform,
  • An offshore work platform for use in a body of water upon which ice is formed through natural conditions, comprising,
  • said wall section formed converging upwardly and inwardly of said platform at least in the region of contact of said surface of said water with said wall section and constructed to receive and elevate above its natural level a portion of a sheet of ice which moves on said body of water into contact with said wall section,

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Earth Drilling (AREA)
  • Toys (AREA)
  • Treating Waste Gases (AREA)
  • Filling Or Discharging Of Gas Storage Vessels (AREA)
US00266084A 1972-06-26 1972-06-26 Arctic offshore platform Expired - Lifetime US3831385A (en)

Priority Applications (7)

Application Number Priority Date Filing Date Title
US00266084A US3831385A (en) 1972-06-26 1972-06-26 Arctic offshore platform
CA171,931A CA982832A (en) 1972-06-26 1973-05-22 Arctic offshore platform
FI1931/73A FI62697C (fi) 1972-06-26 1973-06-14 Foerfarande vid drift av en marinkonstruktion och en konstruktion foer utfoerande av foerfarandet
GB2891073A GB1417895A (en) 1972-06-26 1973-06-18 Offshore platform
NO2590/73A NO148079C (no) 1972-06-26 1973-06-22 Fremgangsmaate ved og anordning for aa nedsette virkningen av iskrefter paa en marin konstruksjon
DK350873A DK143114C (da) 1972-06-26 1973-06-25 Fremgangsmaade ved drift af en marinekonstruktion,som er anbragt stationaert paa bunden af et vandomraade,og marinekonstruktion til udoevelse af fremgangsmaaden
US05/490,174 US3972199A (en) 1972-06-26 1974-07-29 Low adhesional arctic offshore platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
US00266084A US3831385A (en) 1972-06-26 1972-06-26 Arctic offshore platform

Related Child Applications (1)

Application Number Title Priority Date Filing Date
US05/490,174 Continuation-In-Part US3972199A (en) 1972-06-26 1974-07-29 Low adhesional arctic offshore platform

Publications (1)

Publication Number Publication Date
US3831385A true US3831385A (en) 1974-08-27

Family

ID=23013110

Family Applications (1)

Application Number Title Priority Date Filing Date
US00266084A Expired - Lifetime US3831385A (en) 1972-06-26 1972-06-26 Arctic offshore platform

Country Status (6)

Country Link
US (1) US3831385A (sv)
CA (1) CA982832A (sv)
DK (1) DK143114C (sv)
FI (1) FI62697C (sv)
GB (1) GB1417895A (sv)
NO (1) NO148079C (sv)

Cited By (22)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3952527A (en) * 1972-12-11 1976-04-27 Vinieratos Edward R Offshore platform for arctic environments
US3972199A (en) * 1972-06-26 1976-08-03 Chevron Research Company Low adhesional arctic offshore platform
US4029035A (en) * 1976-04-13 1977-06-14 German William H Ship's hull and method of bubbling hot gas therefrom
US4075964A (en) * 1975-08-29 1978-02-28 Global Marine, Inc. Ice melting system
US4102144A (en) * 1977-05-31 1978-07-25 Global Marine, Inc. Method and apparatus for protecting offshore structures against forces from moving ice sheets
US4114388A (en) * 1977-04-20 1978-09-19 Straub Erik K Pile protection device
US4127992A (en) * 1977-06-13 1978-12-05 Donald Bogosh Permanent pier piling
US4215952A (en) * 1978-03-15 1980-08-05 Chevron Research Company Offshore structure for use in waters containing large moving ice masses
US4239418A (en) * 1979-04-27 1980-12-16 Chevron Research Company Arctic multi-angle conical structure having a discontinuous outer surface
US4245929A (en) * 1979-04-27 1981-01-20 Chevron Research Company Arctic multi-angle conical structure
US4252471A (en) * 1978-11-01 1981-02-24 Straub Erik K Device for protecting piles
US4260292A (en) * 1979-10-25 1981-04-07 The Offshore Company Arctic offshore platform
US4325655A (en) * 1980-01-16 1982-04-20 Exxon Production Research Company Multiple slope structure
US4335980A (en) * 1980-04-28 1982-06-22 Chevron Research Company Hull heating system for an arctic offshore production structure
FR2559808A1 (fr) * 1984-02-16 1985-08-23 Fluor Doris Inc Plate-forme composite pour exploitations petrolieres en mers polaires
US4666341A (en) * 1983-07-22 1987-05-19 Santa Fe International Corporation Mobile sea barge and plateform
CN102619239A (zh) * 2012-04-18 2012-08-01 中国水电顾问集团中南勘测设计研究院 一种利用热液喷淋单元消减海洋工程结构物冰荷载的装置
CN102628280A (zh) * 2012-04-18 2012-08-08 中国水电顾问集团中南勘测设计研究院 一种利用热液循环单元消减海洋工程结构物冰荷载的装置
WO2019003096A1 (en) * 2017-06-27 2019-01-03 Jurong Shipyard Pte Ltd FLOATING LIFTING AND HANDLING STRUCTURE, TUBULAR, VERTICAL AND CONTINUOUS
CN112323714A (zh) * 2020-09-30 2021-02-05 中船第九设计研究院工程有限公司 一种倒t型坞门冬季临时防冰措施
US20220082270A1 (en) * 2018-09-13 2022-03-17 Lyle Eric Beutz Method and apparatus for winterizing system components
US20220340242A1 (en) * 2021-04-22 2022-10-27 Di Du Offshore Floating Island

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US993440A (en) * 1909-10-29 1911-05-30 Elouild Duplessis Ice-breaker.
US3632172A (en) * 1969-07-17 1972-01-04 Dresser Ind Method of and apparatus for weakening ice for assisting an icebreaker
US3749162A (en) * 1971-04-01 1973-07-31 Global Marine Inc Arctic oil and gas development
US3759046A (en) * 1972-03-23 1973-09-18 Global Marine Inc Movement of marine structures in saline ice

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US993440A (en) * 1909-10-29 1911-05-30 Elouild Duplessis Ice-breaker.
US3632172A (en) * 1969-07-17 1972-01-04 Dresser Ind Method of and apparatus for weakening ice for assisting an icebreaker
US3749162A (en) * 1971-04-01 1973-07-31 Global Marine Inc Arctic oil and gas development
US3759046A (en) * 1972-03-23 1973-09-18 Global Marine Inc Movement of marine structures in saline ice

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
The Oil and Gas Journal of Sept. 14, 1970 pages 60 61. *

Cited By (31)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3972199A (en) * 1972-06-26 1976-08-03 Chevron Research Company Low adhesional arctic offshore platform
US3952527A (en) * 1972-12-11 1976-04-27 Vinieratos Edward R Offshore platform for arctic environments
US4117794A (en) * 1975-08-29 1978-10-03 Global Marine, Inc. Ice melting system and method
US4075964A (en) * 1975-08-29 1978-02-28 Global Marine, Inc. Ice melting system
US4029035A (en) * 1976-04-13 1977-06-14 German William H Ship's hull and method of bubbling hot gas therefrom
US4114388A (en) * 1977-04-20 1978-09-19 Straub Erik K Pile protection device
US4102144A (en) * 1977-05-31 1978-07-25 Global Marine, Inc. Method and apparatus for protecting offshore structures against forces from moving ice sheets
US4127992A (en) * 1977-06-13 1978-12-05 Donald Bogosh Permanent pier piling
US4215952A (en) * 1978-03-15 1980-08-05 Chevron Research Company Offshore structure for use in waters containing large moving ice masses
US4252471A (en) * 1978-11-01 1981-02-24 Straub Erik K Device for protecting piles
US4239418A (en) * 1979-04-27 1980-12-16 Chevron Research Company Arctic multi-angle conical structure having a discontinuous outer surface
US4245929A (en) * 1979-04-27 1981-01-20 Chevron Research Company Arctic multi-angle conical structure
US4260292A (en) * 1979-10-25 1981-04-07 The Offshore Company Arctic offshore platform
US4325655A (en) * 1980-01-16 1982-04-20 Exxon Production Research Company Multiple slope structure
US4335980A (en) * 1980-04-28 1982-06-22 Chevron Research Company Hull heating system for an arctic offshore production structure
DK152187B (da) * 1980-04-28 1988-02-08 Chevron Res Fremgangsmaade til reduktion af iskraefterne mod en offshore produktionskonstruktion samt en saadan konstruktion.
US4666341A (en) * 1983-07-22 1987-05-19 Santa Fe International Corporation Mobile sea barge and plateform
FR2559808A1 (fr) * 1984-02-16 1985-08-23 Fluor Doris Inc Plate-forme composite pour exploitations petrolieres en mers polaires
US4618286A (en) * 1984-02-16 1986-10-21 Fluor-Doris Incorporated Composite platform for petroleum workings in polar seas
CN102619239A (zh) * 2012-04-18 2012-08-01 中国水电顾问集团中南勘测设计研究院 一种利用热液喷淋单元消减海洋工程结构物冰荷载的装置
CN102628280A (zh) * 2012-04-18 2012-08-08 中国水电顾问集团中南勘测设计研究院 一种利用热液循环单元消减海洋工程结构物冰荷载的装置
CN110997473A (zh) * 2017-06-27 2020-04-10 裕廊船厂有限公司 连续竖向管件装卸及提升浮力结构
US10450038B2 (en) 2017-06-27 2019-10-22 Jurong Shipyard Pte Ltd Continuous vertical tubular handling and hoisting buoyant structure
WO2019003096A1 (en) * 2017-06-27 2019-01-03 Jurong Shipyard Pte Ltd FLOATING LIFTING AND HANDLING STRUCTURE, TUBULAR, VERTICAL AND CONTINUOUS
RU2757576C2 (ru) * 2017-06-27 2021-10-19 Джуронг Шипъярд Пте Лтд Плавучая вертикальная непрерывная структура для погрузки, разгрузки, подъема и спуска труб
CN110997473B (zh) * 2017-06-27 2022-03-22 裕廊船厂有限公司 连续竖向管件装卸及提升浮力结构
US20220082270A1 (en) * 2018-09-13 2022-03-17 Lyle Eric Beutz Method and apparatus for winterizing system components
US11692719B2 (en) * 2018-09-13 2023-07-04 Navsell Llc Method and apparatus for winterizing system components
CN112323714A (zh) * 2020-09-30 2021-02-05 中船第九设计研究院工程有限公司 一种倒t型坞门冬季临时防冰措施
US20220340242A1 (en) * 2021-04-22 2022-10-27 Di Du Offshore Floating Island
US11661157B2 (en) * 2021-04-22 2023-05-30 Di Du Offshore floating island

Also Published As

Publication number Publication date
FI62697C (fi) 1983-02-10
NO148079C (no) 1983-08-03
FI62697B (fi) 1982-10-29
DK143114B (da) 1981-03-30
CA982832A (en) 1976-02-03
GB1417895A (en) 1975-12-17
DK143114C (da) 1981-11-02
NO148079B (no) 1983-04-25

Similar Documents

Publication Publication Date Title
US3972199A (en) Low adhesional arctic offshore platform
US3831385A (en) Arctic offshore platform
US4335980A (en) Hull heating system for an arctic offshore production structure
US3749162A (en) Arctic oil and gas development
US4188157A (en) Marine structure
CA1185104A (en) Two-section arctic drilling structure
US3366173A (en) Subsea production system
US8684630B2 (en) Underwater reinforced concrete silo for oil drilling and production applications
US6347910B1 (en) Submarine power storage system
CN107075824B (zh) 用于离岸活动的海床终端
US3738114A (en) Method and apparatus for forming ice island for drilling or the like
GB2212452A (en) A method and apparatus for locally breaking a sheet of ice in a cold sea
US4486125A (en) Modular arctic structures system
US4504172A (en) Caisson shield for arctic offshore production platform
US4456072A (en) Ice island structure and drilling method
US4325656A (en) Apparatus and method for forming off-shore ice island structure
US4755082A (en) Removable bottom founded structure
US3740956A (en) Portable retaining structure
US3396544A (en) Storage tank fixed on the ocean bottom and method of installation
CA1054809A (en) Low adhesional arctic offshore platform
US4397586A (en) Offshore arctic structure
EP0009986A1 (en) Support structure for use in water
EP0221986A1 (en) Offshore structures
RU2779235C1 (ru) Морской производственный комплекс по добыче, подготовке и переработке сырьевого газа c целью производства сжиженного природного газа, широкой фракции легких углеводородов и стабильного газового конденсата на основании гравитационного типа (ОГТ)
Tarasov et al. PROTECTION OF OFFSHORE HYDROTECHNICAL STRUCTURES FROM ICE FORCES USING SOFT PNEUMATIC INFLATABLE CAPSULES IN DEVICES FOR ICE CRUSHABLE