US2050001A - Method of laying tile floors - Google Patents

Method of laying tile floors Download PDF

Info

Publication number
US2050001A
US2050001A US62997A US6299736A US2050001A US 2050001 A US2050001 A US 2050001A US 62997 A US62997 A US 62997A US 6299736 A US6299736 A US 6299736A US 2050001 A US2050001 A US 2050001A
Authority
US
United States
Prior art keywords
channels
bodies
tiles
pouring
floor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
US62997A
Inventor
Edwin B Gates
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ATLAS MINERAL PRODUCTS Co
Original Assignee
ATLAS MINERAL PRODUCTS Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ATLAS MINERAL PRODUCTS Co filed Critical ATLAS MINERAL PRODUCTS Co
Priority to US62997A priority Critical patent/US2050001A/en
Application granted granted Critical
Publication of US2050001A publication Critical patent/US2050001A/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F15/00Flooring
    • E04F15/02Flooring or floor layers composed of a number of similar elements
    • E04F15/08Flooring or floor layers composed of a number of similar elements only of stone or stone-like material, e.g. ceramics, concrete; of glass or with a top layer of stone or stone-like material, e.g. ceramics, concrete or glass

Definitions

  • the present invention is a method of laying tile floors, having particular reference to what are familiarly termed acid proof and sanitary floors such as are required in food, dairy houses, chemical plants, sewers, floors around pickling tanks, etc
  • the present invention has particular reference to and is an improvement upon the method fully set forth in the patent to Edwin B. Gates, No. 1,985,159, dated December 18, 1934.
  • the joints are poured and venting of the entrapped air occurs immediately and evenly, thus enabling the fluent bonding material to readily pass into the various channelsand to quickly dispel the air entrapped therein and to leave a smooth joint surface free of all pin holes or bubbels which have heretofore been found objectionable and tedious to eliminate.
  • Fig. 1 is a plan view of a comparatively small section of a floor space and adjoining wall and showing an arrangement of tiles therein,
  • Fig. 2 is a similar View showing parts of the second and third steps of the improved process
  • Fig. 3 is a similar view showing a completion of the third step of the process and preparatory to pouring of the joints
  • Fig. 4 is a similar view showing the floor after the pouring process
  • Fig. 5 is an enlarged transverse sectional View taken through a portion of the floor and wall and illustrating the pouring process in operation
  • Fig. 6 is a similar view showing the appearance of the floor after the process is completed.
  • the bed or foundation upon which the floor is to be laid is smoothed and leveled off or graded to drain from wall to wall of the structure, and the bodies or tiles I are placed upon the bed in such relation that channels 8 are formed between the several tiles.
  • the distance between the tiles will be governed by the Width of channel required but care must be taken that channels of the proper width be provided between all of the several tiles so that all of said channels will be intercommunicating. It is preferred that those tiles next adjacent to the walls 9 of the building be spaced therefrom a substantial distance, this distance depending largely upon the total floor area of the building. The purpose of this space, when its use may be found d sirable, will be pointed out hereinafter.
  • the various channels 8 are covered to provide intercommunicating closed conduits, this being effected in the present instance by placing over the tiles a. sheet of open mesh fabric it.
  • This sheet is preferably of such character as to possess absorptive properties and to permit free venting of air or gases'trapped in the channels.
  • unbleached muslin, cheese cloth, loosely woven wool or open mesh canvas will be found effective, while perforated paper may suffice if the perforations are sufficiently close.
  • the marginal portions of the sheet are shaped around the extreme outer edges of the marginal tiles so as to protect such edges, whereupon the edges of the sheet or coverare bent down into the floor bed across the space between the marginal tiles and the walls.
  • the cover thus laid is Weighted down, this being most practically effected by covering the sheet material with either moist or dry sand indicated at H.
  • the tiling thus laid and covered is now ready for the pouring material, sumcient to at least fill all of the intercommunicating channels, which is poured into one of these channels.
  • the pouring material be introduced at intersecting channels substantially remote from the edge tiles of the floor.
  • a cup or funnel I2 is applied to intersecting channels by clearing away the sand and cover sheet immediately above the point of such intersection. Sand may then be packed around the funnel so as to hold the same properly in position, whereupon the hot fluent bonding material is introduced to the funnel.
  • This material immediately flows through the intersecting channels in all directions forcing out all air or gases that might.- tend to pocket therein through the open mesh of the covering H1.
  • the weighted covering limits the filling of the channel. If desired, additional venting may be effected by removing the sand and breaking the covering at a point such as is represented at I3 in Figure 2.
  • the cup When the channels have been filled, the cup is filled nearly to its top with the fluent bonding material, and the pressure thus produced maintains the various channels properly filled and compensates for contraction in the bonding material incident to its cooling. This insures an even filling of all joints up to and flush with the top surface of the various tiles.
  • the cup After cooling, the cup is removed and the sand and cover sheet taken away, after which the space l5 between the edge tiles and the wall 9 may be cleaned out and filled with a packing material as represented at l6.
  • This. material constitutes an expansion joint to compensate for creeping of the floor incident to varying temperatures.
  • tiles of square or rectangular formation there are shown tiles of square or rectangular formation, but it will be understood that the tiles may take other regular or irregular shapes, as desired, so long as the spaces or channels between the various tiles remain continuous or uninterrupted.
  • the method of laying a floor comprising the arrangement of separate bodies on a foundation to provide intercommunicating channels between them, covering said channels with a sheet of porous and absorptive material, and pouring into one of the channels a quantity of the channels.
  • the method of laying tiling or the like comprising arranging separate bodies upon a foundation with the bodies separated by intercommunicating channels, converting said channels into temporary intercommunicating conduits by superposing on the bodies a temporary sheet like cover of porous material so arranged as to extend across said channels, causing a fluent bonding material to flow through said conduits and to fill said channels to a uniform level and removing said cover after said level has been reached.
  • the method of laying tiling or the like comprising arranging separate bodies upon a foundation with the bodies separated by intercommunicating channels, converting said channels into temporary intercommunicating conduits by superposing on the bodies a temporary cover sheet of porous material so arranged as to extend across said channels, causing a fluent bonding material to flow through said conduits and to fill said channels to a uniform level by pouring a sufficient quantity thereof through one or more openings in said cover sheet, and removing said cover sheet after said spaces have been filled.
  • the method of laying tiling or the like comprising providing a foundation with enclosing walls, arranging separate bodies upon said foundation with the bodies spaced by intercommunicating channels, the marginal bodies being spaced from said walls, converting said channels into temporary intercommunicating conduits by superposing on the bodies a temporary cover of porous and/or absorptive material so arranged as to bridge the channels and closing the outer ends of said conduits by folding the marginal edges of said cover downwardly over the outer edges of the marginal bodies and across the spaces interposed between the last mentioned bodies and the walls adjacent thereto, causing a fluent bonding material to flow through said conduits and to fill said channels to a uniform level by pouring a suflicient quantity thereof through one or more openings in said cover, removing said cover after said channels have been filled, and filling the space between the marginal bodies and said walls to a level even with the top surfaces of said bodies.

Description

1936. E. B. GATES 2,050,001
METHOD OF LAYING TILE FLOORS Filed Feb. 8, 1956 AL I, Q 1 I I I I):
Patented Aug. 4, 1936 UNITED STATES 2,050,0fll
PATENT OFFIQE METHOD OF LAYING TILE FLOORS Application February 8, 1936, Serial No. 62,997
6 Claims.
The present invention is a method of laying tile floors, having particular reference to what are familiarly termed acid proof and sanitary floors such as are required in food, dairy houses, chemical plants, sewers, floors around pickling tanks, etc
The present invention has particular reference to and is an improvement upon the method fully set forth in the patent to Edwin B. Gates, No. 1,985,159, dated December 18, 1934.
While the method described in my former patent is satisfactory in most respects, it has been found that in the practice of the method therein set forth porosity of the joints frequently occurs, detracting from the appearance of the fioor and affording opportunity for the accumulation of bacteria. It therefore was necessary in the practice of that method to treat the joints after the sand and cover were removed, so as to eliminate the pin holes causing the pores created by insufficient venting of trapped air during the joint pouring process.
By the use of the present improved method the joints are poured and venting of the entrapped air occurs immediately and evenly, thus enabling the fluent bonding material to readily pass into the various channelsand to quickly dispel the air entrapped therein and to leave a smooth joint surface free of all pin holes or bubbels which have heretofore been found objectionable and tedious to eliminate.
The improved method for obtaining these results is more fully hereinafter described, reference being had to the attached drawing, where- Fig. 1 is a plan view of a comparatively small section of a floor space and adjoining wall and showing an arrangement of tiles therein,
Fig. 2 is a similar View showing parts of the second and third steps of the improved process,
Fig. 3 is a similar view showing a completion of the third step of the process and preparatory to pouring of the joints,
Fig. 4 is a similar view showing the floor after the pouring process,
Fig. 5 is an enlarged transverse sectional View taken through a portion of the floor and wall and illustrating the pouring process in operation, and
Fig. 6 is a similar view showing the appearance of the floor after the process is completed.
In carrying out the process, the bed or foundation upon which the floor is to be laid is smoothed and leveled off or graded to drain from wall to wall of the structure, and the bodies or tiles I are placed upon the bed in such relation that channels 8 are formed between the several tiles. The distance between the tiles will be governed by the Width of channel required but care must be taken that channels of the proper width be provided between all of the several tiles so that all of said channels will be intercommunicating. It is preferred that those tiles next adjacent to the walls 9 of the building be spaced therefrom a substantial distance, this distance depending largely upon the total floor area of the building. The purpose of this space, when its use may be found d sirable, will be pointed out hereinafter.
With the tiles thus placed upon the bed, the various channels 8 are covered to provide intercommunicating closed conduits, this being effected in the present instance by placing over the tiles a. sheet of open mesh fabric it. This sheet is preferably of such character as to possess absorptive properties and to permit free venting of air or gases'trapped in the channels. For this purpose, unbleached muslin, cheese cloth, loosely woven wool or open mesh canvas will be found effective, while perforated paper may suffice if the perforations are sufficiently close. The marginal portions of the sheet are shaped around the extreme outer edges of the marginal tiles so as to protect such edges, whereupon the edges of the sheet or coverare bent down into the floor bed across the space between the marginal tiles and the walls. The cover thus laid is Weighted down, this being most practically effected by covering the sheet material with either moist or dry sand indicated at H. The tiling thus laid and covered is now ready for the pouring material, sumcient to at least fill all of the intercommunicating channels, which is poured into one of these channels. In accomplishing this result, it is preferred that the pouring material be introduced at intersecting channels substantially remote from the edge tiles of the floor. To facilitate the pouring operation, a cup or funnel I2 is applied to intersecting channels by clearing away the sand and cover sheet immediately above the point of such intersection. Sand may then be packed around the funnel so as to hold the same properly in position, whereupon the hot fluent bonding material is introduced to the funnel. This material immediately flows through the intersecting channels in all directions forcing out all air or gases that might.- tend to pocket therein through the open mesh of the covering H1. The weighted covering limits the filling of the channel. If desired, additional venting may be effected by removing the sand and breaking the covering at a point such as is represented at I3 in Figure 2.
When the channels have been filled, the cup is filled nearly to its top with the fluent bonding material, and the pressure thus produced maintains the various channels properly filled and compensates for contraction in the bonding material incident to its cooling. This insures an even filling of all joints up to and flush with the top surface of the various tiles.
After cooling, the cup is removed and the sand and cover sheet taken away, after which the space l5 between the edge tiles and the wall 9 may be cleaned out and filled with a packing material as represented at l6. This. material constitutes an expansion joint to compensate for creeping of the floor incident to varying temperatures.
In many instances it will be found that all joints of a floor of given area may be poured at one operation, while floors of a larger area may require the use of several pouring cups in order that a proper distribution of the fluent bonding material may be made. If the pouring operations are carried out simultaneously, the fluent materials from the several cups will meet and bond with each other.
In the present instance there are shown tiles of square or rectangular formation, but it will be understood that the tiles may take other regular or irregular shapes, as desired, so long as the spaces or channels between the various tiles remain continuous or uninterrupted.
It has been found that by providing a covering of a porous and absorptive material the surface of the bond in the channels will set smooth and will be free of pin holes or other interstices or other depressions which have proven objectionable in methods herebefore employed. The method here employed obviates the necessity of after treatment of the joints, as the surface sets smooth and uninterrupted. As in my former method, it will be understood that the gravity method of pouring need not be adhered to, as other means may as effectively be used for introducing the fluent bonding material to one or more channel intersections of the tile layout. In the claims the term body is used to indicate the tile, and it will be understood that such term not only includes tiles of refractory material but also includes blocks, slabs or bricks of other characters.
Having thus described my invention, I claim:
1. The method of laying a floor comprising the arrangement of separate bodies on a foundation with regularly spaced intercommunicating channels between them, covering said channels with a porous sheet of material, and introducing a fluent bonding material to said channels.
2. The method of laying a floor comprising the arrangement of separate bodies on a foundation to provide intercommunicating channels between them, covering said channels with a sheet of porous and absorptive material, and pouring into one of the channels a quantity of the channels.
3. The method of laying tiling or the like comprising arranging separate bodies upon a foundation with the bodies separated by intercommunicating channels, converting said channels into temporary intercommunicating conduits by superposing on the bodies a temporary sheet like cover of porous material so arranged as to extend across said channels, causing a fluent bonding material to flow through said conduits and to fill said channels to a uniform level and removing said cover after said level has been reached.
4. The method of laying tiling or the like, comprising arranging separate bodies upon a foundation with the bodies separated by intercommunicating channels, converting said channels into temporary intercommunicating conduits by superposing on the bodies a temporary cover sheet of porous material so arranged as to extend across said channels, causing a fluent bonding material to flow through said conduits and to fill said channels to a uniform level by pouring a sufficient quantity thereof through one or more openings in said cover sheet, and removing said cover sheet after said spaces have been filled.
5. The method of laying tiling or the like, comprising arranging separate bodies upon a foundation with the bodies spaced by intercommunieating channels, converting said channels into temporary intercommunicating conduits by superposing on the bodies a temporary cover sheet of porous material so arranged as to extend across said channels, weighting said cover sheet so as to hold it in position, causing a fluent bonding material to flow through said conduits and to fill such channels to a uniform level by pouring a sufficient quantity in through one or more openings in said cover sheet, and removing the cover sheet and the weighting means after said channels have been filled.
6. The method of laying tiling or the like comprising providing a foundation with enclosing walls, arranging separate bodies upon said foundation with the bodies spaced by intercommunicating channels, the marginal bodies being spaced from said walls, converting said channels into temporary intercommunicating conduits by superposing on the bodies a temporary cover of porous and/or absorptive material so arranged as to bridge the channels and closing the outer ends of said conduits by folding the marginal edges of said cover downwardly over the outer edges of the marginal bodies and across the spaces interposed between the last mentioned bodies and the walls adjacent thereto, causing a fluent bonding material to flow through said conduits and to fill said channels to a uniform level by pouring a suflicient quantity thereof through one or more openings in said cover, removing said cover after said channels have been filled, and filling the space between the marginal bodies and said walls to a level even with the top surfaces of said bodies.
EDWIN B. GATES.
US62997A 1936-02-08 1936-02-08 Method of laying tile floors Expired - Lifetime US2050001A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US62997A US2050001A (en) 1936-02-08 1936-02-08 Method of laying tile floors

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
US62997A US2050001A (en) 1936-02-08 1936-02-08 Method of laying tile floors

Publications (1)

Publication Number Publication Date
US2050001A true US2050001A (en) 1936-08-04

Family

ID=22046205

Family Applications (1)

Application Number Title Priority Date Filing Date
US62997A Expired - Lifetime US2050001A (en) 1936-02-08 1936-02-08 Method of laying tile floors

Country Status (1)

Country Link
US (1) US2050001A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2545046A (en) * 1945-09-11 1951-03-13 Wilbur E Rownd Paving block

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2545046A (en) * 1945-09-11 1951-03-13 Wilbur E Rownd Paving block

Similar Documents

Publication Publication Date Title
US4907385A (en) Drainage apparatus for concrete block walls
US5845456A (en) Basement waterproofing
US2147035A (en) Drainage system for basement walls
US1746816A (en) Building construction
US1931650A (en) Floor covering
US2021359A (en) Preformed sound-absorbing unit and method of making the same
US2050001A (en) Method of laying tile floors
US2130498A (en) Porous pipe
US1917062A (en) Concrete wall construction
US6564520B1 (en) Sheet-like masonry block drainage system
US2644790A (en) Apparatus for handling sludge
CN210031504U (en) Bridge floor drain pipe device for bridge
CN109457998A (en) A kind of pipeline sealing hole structure and its construction method
US1883496A (en) Combination floor and scale construction
EP0893219B1 (en) Apparatus for producing thin tiles of cement paste
US2125857A (en) Paving and expansion joint structure
CN106968398A (en) A kind of process that support column is poured below balcony
US1525797A (en) Process for molding wall sections
DE102008043640A1 (en) Floor construction with thermal insulation and sound insulation
CN209384695U (en) A kind of pipeline sealing hole structure
US4690368A (en) Apparatus for hollow concrete wall construction
US1572076A (en) Filtering apparatus
CN112962875A (en) Combined method for water-proof integration and accumulated water drainage of concrete roof structure
US2165437A (en) Floor and method of making the same
CN109322373A (en) Segmented combined floor drain double-layer drainage moisture discharge device and construction method