US20070193647A1 - High pressure gas container with an auxiliary valve and process for filling it - Google Patents

High pressure gas container with an auxiliary valve and process for filling it Download PDF

Info

Publication number
US20070193647A1
US20070193647A1 US11/657,688 US65768807A US2007193647A1 US 20070193647 A1 US20070193647 A1 US 20070193647A1 US 65768807 A US65768807 A US 65768807A US 2007193647 A1 US2007193647 A1 US 2007193647A1
Authority
US
United States
Prior art keywords
gas
valve
container
auxiliary valve
container body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Abandoned
Application number
US11/657,688
Inventor
Ulrich Klebe
Friedel Michel
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
LAir Liquide SA pour lEtude et lExploitation des Procedes Georges Claude
Original Assignee
LAir Liquide SA a Directoire et Conseil de Surveillance pour lEtude et lExploitation des Procedes Georges Claude
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by LAir Liquide SA a Directoire et Conseil de Surveillance pour lEtude et lExploitation des Procedes Georges Claude filed Critical LAir Liquide SA a Directoire et Conseil de Surveillance pour lEtude et lExploitation des Procedes Georges Claude
Assigned to L'AIR LIQUIDE, SOCIETE ANONYME A DIRECTOIRE ET CONSEIL DE SURVEILLANCE POUR L'ETUDE ET L'EXPLOITATION DES PROCEDES GERORGES CLAUDE reassignment L'AIR LIQUIDE, SOCIETE ANONYME A DIRECTOIRE ET CONSEIL DE SURVEILLANCE POUR L'ETUDE ET L'EXPLOITATION DES PROCEDES GERORGES CLAUDE ASSIGNMENT OF ASSIGNORS INTEREST (SEE DOCUMENT FOR DETAILS). Assignors: KLEBE, ULRICH, MICHEL, FRIEDEL
Publication of US20070193647A1 publication Critical patent/US20070193647A1/en
Abandoned legal-status Critical Current

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C5/00Methods or apparatus for filling containers with liquefied, solidified, or compressed gases under pressures
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2201/00Vessel construction, in particular geometry, arrangement or size
    • F17C2201/01Shape
    • F17C2201/0104Shape cylindrical
    • F17C2201/0109Shape cylindrical with exteriorly curved end-piece
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2201/00Vessel construction, in particular geometry, arrangement or size
    • F17C2201/05Size
    • F17C2201/058Size portable (<30 l)
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2205/00Vessel construction, in particular mounting arrangements, attachments or identifications means
    • F17C2205/03Fluid connections, filters, valves, closure means or other attachments
    • F17C2205/0302Fittings, valves, filters, or components in connection with the gas storage device
    • F17C2205/0311Closure means
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2205/00Vessel construction, in particular mounting arrangements, attachments or identifications means
    • F17C2205/03Fluid connections, filters, valves, closure means or other attachments
    • F17C2205/0302Fittings, valves, filters, or components in connection with the gas storage device
    • F17C2205/0323Valves
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2209/00Vessel construction, in particular methods of manufacturing
    • F17C2209/22Assembling processes
    • F17C2209/221Welding
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2221/00Handled fluid, in particular type of fluid
    • F17C2221/01Pure fluids
    • F17C2221/014Nitrogen
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2221/00Handled fluid, in particular type of fluid
    • F17C2221/01Pure fluids
    • F17C2221/016Noble gases (Ar, Kr, Xe)
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2221/00Handled fluid, in particular type of fluid
    • F17C2221/01Pure fluids
    • F17C2221/016Noble gases (Ar, Kr, Xe)
    • F17C2221/017Helium
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2223/00Handled fluid before transfer, i.e. state of fluid when stored in the vessel or before transfer from the vessel
    • F17C2223/01Handled fluid before transfer, i.e. state of fluid when stored in the vessel or before transfer from the vessel characterised by the phase
    • F17C2223/0107Single phase
    • F17C2223/0123Single phase gaseous, e.g. CNG, GNC
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2223/00Handled fluid before transfer, i.e. state of fluid when stored in the vessel or before transfer from the vessel
    • F17C2223/01Handled fluid before transfer, i.e. state of fluid when stored in the vessel or before transfer from the vessel characterised by the phase
    • F17C2223/0146Two-phase
    • F17C2223/0153Liquefied gas, e.g. LPG, GPL
    • F17C2223/0161Liquefied gas, e.g. LPG, GPL cryogenic, e.g. LNG, GNL, PLNG
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2223/00Handled fluid before transfer, i.e. state of fluid when stored in the vessel or before transfer from the vessel
    • F17C2223/03Handled fluid before transfer, i.e. state of fluid when stored in the vessel or before transfer from the vessel characterised by the pressure level
    • F17C2223/033Small pressure, e.g. for liquefied gas
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2223/00Handled fluid before transfer, i.e. state of fluid when stored in the vessel or before transfer from the vessel
    • F17C2223/03Handled fluid before transfer, i.e. state of fluid when stored in the vessel or before transfer from the vessel characterised by the pressure level
    • F17C2223/036Very high pressure (>80 bar)
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2227/00Transfer of fluids, i.e. method or means for transferring the fluid; Heat exchange with the fluid
    • F17C2227/04Methods for emptying or filling
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2250/00Accessories; Control means; Indicating, measuring or monitoring of parameters
    • F17C2250/06Controlling or regulating of parameters as output values
    • F17C2250/0605Parameters
    • F17C2250/0621Volume
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2250/00Accessories; Control means; Indicating, measuring or monitoring of parameters
    • F17C2250/06Controlling or regulating of parameters as output values
    • F17C2250/0605Parameters
    • F17C2250/0636Flow or movement of content
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2265/00Effects achieved by gas storage or gas handling
    • F17C2265/02Mixing fluids
    • F17C2265/025Mixing fluids different fluids
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2270/00Applications
    • F17C2270/01Applications for fluid transport or storage
    • F17C2270/0165Applications for fluid transport or storage on the road
    • F17C2270/0181Airbags
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2270/00Applications
    • F17C2270/01Applications for fluid transport or storage
    • F17C2270/0165Applications for fluid transport or storage on the road
    • F17C2270/0184Fuel cells
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2270/00Applications
    • F17C2270/05Applications for industrial use
    • F17C2270/059Mass bottling, e.g. merry belts
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2270/00Applications
    • F17C2270/07Applications for household use
    • F17C2270/0763Fuel cells
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
    • Y02E60/30Hydrogen technology
    • Y02E60/32Hydrogen storage

Definitions

  • the invention concerns a high pressure gas container comprising a container body for storing gas and a process for filling a high pressure gas container having a container body for storing gas and at least one first valve for discharging the stored gas.
  • a filling gas is cooled before its introduction into the pressure container, wherein on completion of the filling process the pressure container is sealed in a pressure-tight manner. As the gas warms up the pressure in the pressure container rises rapidly.
  • a fuel gas is filled into a light weight tank made with a liner of chrome nickel steel inside of a fibre reinforced shell, wherein the fuel is introduced in deep cooled liquid form and is stored at a pressure above 300 bar.
  • a pressure vessel for example of an airbag system, is filled with a gas or a gas mixture at a temperature which is higher than the boiling point thereof, closing the cold vessel and a pressure is produced in the filled and closed vessel by heating it to ambient temperatures.
  • a pressure container is filled with a gas mixture, wherein a gas mixture is introduced in its gaseous state or in its liquefied state or at least one gas component of a gas mixture is introduced in its gaseous state or in its liquefied state in a cooled pressure gas container.
  • U.S. Pat. No. 1,414,359 discloses a process for filling compressed gas containers, wherein a given quantity of liquefied gas is placed in a vessel of low specific heat capacity that is suspended within the container, the container is closed, and the walls of the container are maintained at a temperature above 0° C. until the enclosed substance has been converted into gaseous form.
  • DE 101 19 115 discloses a pressure container particularly suited for filling with low boiling permanent gases or gas mixtures at low temperatures which is provided on its inner surface with a material having a low heat conducting coefficient.
  • EP 0 033 386 discloses a process for transporting and storing permanent gases, in particular hydrogen, under pressure in pressure containers, wherein the gases are cooled to low temperatures above their boiling point and are transported and stored in isolated pressure containers.
  • the gas generators which are filled with various gases at ambient temperatures, provide for considerable technical problems, both in terms of their production and their filling with pressures of up to 700 bar or above.
  • the heat of compression in particular during a rapid filling leads to undefined temperature conditions which usually considerably affect the metering precision with which the amount of gas is introduced into the gas containers.
  • To meet a high metering standard is important with respect to the subsequent inflation characteristics of the airbag.
  • Very expensive and complex piston or diaphragm compressors are required to generate the very high pressures. This entails high investment and high maintenance costs.
  • a correspondingly complex and expensive downstream gas supply is required for these pressures.
  • the density of the gas stored in a gas container is as high as possible, wherein the filling of the gas container should be reliable, reproducible, save and economical.
  • the amount of gas filled into the container should be precisely metered and the throughput of gas filling facility should be as high as possible.
  • the high pressure induced mechanical instabilities are less prominent, yet problems of thermal insulation, thermal tension and thermal expansion due to strong temperature gradients appear.
  • the positioning of the gas containers at the gas supply station is not easy as the thermal contraction respectively expansion makes fine control of the spatial positioning system difficult.
  • An object of the present invention is to provide for a high pressure container with a container body for storing gas and a process for filling a high pressure gas container having a container body for storing gas, that allow for efficient, reproducible, reliable and economical filling of pressure gas containers.
  • the high pressure gas container with a container body for storing gas and with at least one first valve for discharging the stored gas is characterized by further comprising an auxiliary valve for introducing the gas into the container body and for temporarily closing the container body until the container body is sealed permanently, wherein the first valve and the auxiliary valve are in fluid connection with the container body.
  • the first valve is used for discharging the stored gas, when the container body is sealed permanently.
  • the first valve may be at a membrane valve that is opened when the stored gas is needed, e.g. during an accident which makes the operation of the airbag system necessary.
  • the first valve may be a membrane valve that bursts when the stored gas is needed for inflating an airbag.
  • the first valve is gas tight on a permanent time basis, e.g. for over 15 years. Usually the first valve is closed by welding.
  • the auxiliary valve also helps to facilitate the supplying respectively introducing of gas into the container body. For instance after supplying a first gas or after introducing a second gas, the container body is temporarily closed. and transported to a closing unit which closes the container body permanently.
  • auxiliary valve may, if connected in a fluid series connection with the first valve at the gas container, be used for controlling the gas flow during an discharge operation.
  • the amount of gas per unit time that is used for inflating an airbag may be suitably and precisely controlled.
  • the auxiliary valve may help to avoid gas leakage during the transport of the gas container for the time after the completion of the filling step until the gas container is permanently sealed.
  • the high pressure gas container may withstand pressures above 300 bar, for example up to 1300 bar, in particular in between 500 bar to 800 bar.
  • the gas to be introduced into the container may be a pure gas or a mixture of gases and may be an inert gas such as an noble gas in applications such as airbag systems.
  • the gas may also be a fuel gas such as hydrogen in connection with fuel cell systems.
  • the gas container may be filled with a cryogenically solidified or a cryogenically liquefied gas and high pressure may be obtained by closing the gas container shortly after its filling and letting the gas container warm up to room temperature.
  • the first valve and the auxiliary valve may be connected to the container body in fluid series connection, wherein the auxiliary valve may be in the fluid series connection between the first valve and the container body.
  • the first valve and the auxiliary valve may be connected to the container body with separate fluid connection lines.
  • the first valve may be provided at the container body prior to its filling with gas. In this case the gas is to be introduced through the auxiliary valve into the container body.
  • the first valve may be non-reversibly openable.
  • the auxiliary valve may be reversibly openable and closable.
  • a sealing portion is provided at the auxiliary valve for permanently closing the auxiliary valve.
  • the sealing portion may be provided in the fluid connection between the auxiliary valve and the container body, or, the auxiliary valve may be provided in the fluid interconnection between the sealing portion and the container body.
  • the gas container may be sealed permanently with the sealing machine operating at ambient pressure and at ambient temperature.
  • the auxiliary valve may be one of the following valves: a ball cock, a ball valve, a bibcock, a butterfly valve, a gate valve, a globe valve, a check valve, a rotary valve, a piston valve etc.
  • the auxiliary valve may be designed to be comparatively inexpensive as its purpose is solely for temporarily closing the container body. Usually it suffices when the auxiliary valve is able to retain the content of the gas container sufficiently constant for several minutes as usually the gas container may be permanently sealed shortly after its filling.
  • the first valve may be a membrane valve.
  • the high pressure gas container may be particularly intended for use in connection with an airbag system.
  • the high pressure gas container may be used for a fuel cell.
  • the gas container stores a fuel gas such as hydrogen.
  • the process for filling a high pressure gas container having a container body for storing gas, at least one first valve for discharging the stored gas and an auxiliary valve, wherein the first valve and the auxiliary valve are in fluid connection with the container body, comprises the following steps: The gas is introduced into the container body through the auxiliary valve, the auxiliary valve is at least temporarily closed, the auxiliary valve is sealed permanently.
  • the auxiliary valve helps to reduce losses due to evaporation out of the gas container by temporarily closing the container body until it is permanently sealed.
  • the first valve may be provided at the container body prior to its filling with gas.
  • the gas container is filled through the auxiliary valve and the auxiliary valve is then permanently sealed.
  • the first valve may also be provided at the container body after its filling with gas.
  • the filled container body is filled through the auxiliary valve, then the auxiliary valve is temporarily closed and then the first valve is affixed to auxiliary valve opposite to the gas container such that a rising pressure in the gas container does neither influence the affixing of the first valve nor lead to gas losses.
  • the first valve may be provided at the gas container without the need of placing the gas container inside of a pressurized pressure vessel.
  • the auxiliary valve may be sealed by welding.
  • the auxiliary valve may be sealed by the first valve in particular when the first valve is in series fluid connection with the auxiliary valve and the container body.
  • the first valve is provided and is configured at the gas container.
  • FIG. 1 shows the two-step process according to the invention
  • FIG. 2 shows a high pressure gas container to be used according to the invention shown in cross section
  • FIG. 3 shows further high pressure gas container to be used according to the invention shown in cross section
  • FIG. 4 shows a detailed view of a supplying unit of a filling device according to the invention.
  • FIG. 5 shows a supplying unit of a further embodiment of the filling device according to the invention.
  • FIG. 1 shows schematically the two-step process for filling a high pressure gas container 1 with a first gas 2 and a second gas 3 using a supplying unit 7 for supplying the first gas 2 into the gas container 1 and an introducing unit 9 for introducing the second gas 3 into the gas container 1 .
  • the gas container 1 comprises a container body 26 for receiving the first gas 2 and the second gas 3 and is connected to an auxiliary valve 5 .
  • the gas container 1 is connected to a cooling bath 4 which comprises a third gas 6 which is liquefied in order to precool the gas container 1 down to 86° K.
  • the third gas 6 is liquid nitrogen which is kept under a slight pressure in the cooling bath 4 in order to provide for 86° K in the cooling bath 4 .
  • This precooling is performed using a precooling unit 24 which at least partially immerses the gas container 1 in the cooling bath 4 .
  • the gas container 1 is then transported with a transport mechanism 12 to a supplying unit 7 for supplying liquid argon as first gas 2 into the gas container 1 .
  • the auxiliary valve 5 is closed in order to diminish evaporation losses of the first gas 2 .
  • the cooling of the gas container 1 is stopped by disconnecting the gas container 1 from the cooling bath 2 by a stopping unit 8 and is transported to an introducing unit for introducing the second gas 3 in its gaseous state.
  • the second gas 3 such as helium is taken from a second container 22 and is evaporated by an evaporator 25 and is introduced through the auxiliary valve 5 .
  • the unit 10 for closing comprises a sealing device 11 which seals the gas container 1 by welding.
  • Both the introducing unit 9 and the unit 10 for closing may be of a conventional type meaning that they do not need to be adapted for cryogenical temperatures and do not need to be capable of coping with high pressures above 300 bar.
  • the second gas 3 is introduced at ambient temperature into the gas container 1 . After closing the gas container 1 the gas container 1 are allowed to warm up to ambient temperatures such that the pressure inside of the container body 26 rises to a well-defined pressure around 600 bar.
  • the first gas 2 may be supplied at a pressure ranging from 0.5 bar to 3 bar and the second gas 3 may be introduced at 15 bar.
  • the amount of gas supplied respectively introduced into the gas container 1 may be controlled volumetrically, gravimetrically or by an opening time of a metering valve.
  • the second gas may be metered according to the partial pressure that is eventually desired at room temperature. This metering may be performed outside of the cooling bath 4 for instance in the sealing device 11 .
  • FIG. 2 shows a gas container 1 in cross section to be used according to the invention.
  • the gas container 1 comprises the auxiliary valve 5 in a first connection line 28 to the container body 26 and a first valve 27 in a second connection line 29 to the container body 26 .
  • the first valve 27 is provided at the container body 26 before the beginning of the filling process.
  • the first valve 27 is a membrane valve and is adapted to be opened at the instance of operation of the gas container 1 for example during the operation of the airbag system (not shown).
  • the first valve 27 operates non-reversibly, i.e. opens only once.
  • the first valve 27 may be welded to the container body 26 respectively to the second connection line 29 .
  • the auxiliary valve 5 is for facilitating the supplying of the first gas 2 respectively the introducing of the second gas 3 into the container body 26 .
  • the auxiliary valve 5 is for temporarily closing the container body 26 such that evaporation losses are reduced.
  • the auxiliary valve 5 is closed.
  • the auxiliary valve 5 may also be closed in between the supplying and the introducing step.
  • FIG. 3 shows a further gas container 1 in cross section to be used according to the invention, wherein the first valve 27 and the auxiliary valve 5 are in a fluid series connection 30 .
  • the permanent closing of the container body 26 is realized by the first valve 27 which is closed after the filling of the container body 26 with a gas 2 , 3 or a mixture of gases 2 , 3 .
  • the auxiliary valve 5 is used for facilitating the supplying of the first gas and/or the introducing of the second gas 3 .
  • FIG. 4 shows schematically the supplying unit 7 comprising a gas supply station 13 with a flexible filling tube 14 which is to be connected to the container 1 .
  • a tube head 15 is provided which comprises a metering valve 17 .
  • the tube head 15 is positioned at the gas container 1 with a positioning device 16 . Due to the flexibility of the filling tube 14 a gas tight connection between the gas supply station 13 , respectively the supplying unit 7 , and the gas container 1 is established in a short time.
  • the filling tube 14 is thermally isolated and comprises a gas channel 18 for supplying the first gas 2 into the gas container 1 .
  • the gas channel 18 is isolated by means of an insulation vacuum.
  • the filling tube 14 is doubled walled.
  • a heat shield 19 is introduced, which is at least partially actively cooled.
  • the moveable tube head 15 allows for a fast connection which is important if a multiplicity of gas containers 1 need to be filled.
  • FIG. 5 shows a further embodiment of a supplying unit 7 of the device for filling gas containers 1 .
  • Liquid argon is stored as first gas 2 in a large supply tank 33 and is supplied through a supply tube 32 into a first container 21 which also serves as phase separator 20 .
  • the liquid argon from the phase separator 20 is precooled in a second precooling unit 35 for precooling the second gas 2 .
  • the liquid argon is cooled to 2° K below its boiling point in order to avoid any formation of gas bubbles within the liquid phase, which might affect the metering precision of the amount of gas supplied into the gas container 1 .
  • the second precooling unit 35 uses liquid nitrogen as third gas 6 from a third container 23 which is connected to the second precooling unit 35 with conduits 34 .
  • the precooled liquid argon is then supplied with the filling tube 14 to the gas container 1 .
  • the filling tube 14 comprises a moveable tube head 15 which may be positioned precisely at the gas container 1 .
  • the gas container 1 is transported through the cooling bath by a transport mechanism 12 .
  • the cooling bath 4 is closed with a cover 36 in order to establish a pressure in the cooling bath 4 with which the temperature in the cooling bath is precisely controlled.
  • An advantageous process for filling high pressure gas containers 1 comprises the steps: Supplying a liquefied or solidified first gas 2 from a gas supply station 13 through a thermally insulated filling tube 14 with a movable tube head 15 to the high pressure gas container 1 .
  • the gas container 1 may be cooled, in particular by a cooling bath 4 .
  • the filling tube 14 is in particular cooled at least partially along its length, in particular by the cooling bath 4 .
  • the filling tube 14 may be filled using a two step filling process, in which after the supplying step of the first gas 2 , a gaseous second gas 3 , in particular Helium, is introduced into the gas container 1 , wherein in particular during the supplying step of the first gas 2 , the gas container 1 is cooled, in particular by a cooling bath 4 , and before or during the introducing step of the second gas 3 the cooling of the gas container 1 is stopped, in particular the gas container 1 is taken out of the cooling bath 4 .
  • Advantageously high pressure gas containers 1 for air bag systems or for fuel cells are filled.
  • the first gas 2 and/or the second gas 3 may be a mixture of gases.
  • An advantageous process of batch filling of high pressure gas containers 1 with gas comprises the step cooling multiple gas containers 1 in parallel, which are filled sequentially using the process according to the invention.
  • An advantageous arrangement for filling high pressure gas containers 1 with gas comprises a gas supply station 13 and multiple high pressure gas containers 1 , wherein the gas supply station 13 comprises at least one thermally insulated filling tube 14 with a movable tube head 15 for gas filling of the gas containers 1 , wherein the arrangement may comprise a positioning device 16 for moving the tube head 15 to the individual gas containers 1 .
  • a metering valve 17 for controlling a gas flow through the filling tube 14 may be provided in the tube head 15 .
  • the gas supply station 13 may comprise a cooling bath 4 for cooling the gas containers 1 , wherein the filling tube 14 may be at least partially immersed in the cooling bath 4 and wherein the arrangement may further comprise a transport mechanism 12 for transporting the gas containers 1 through the cooling bath 4 .
  • the filling tube 14 may be at least doubled walled and may comprise an insulation vacuum for thermal insulation.
  • the filling tube 14 may be actively cooled by a cooling medium, in particular a liquefied third gas 6 and/or may comprise a gas channel 18 and a tubular heat shield 19 at least partially around the gas channel 18 , wherein the heat shield 19 is cooled by the cooling medium.
  • Tube head 15 may comprise an auxiliary valve 5 for temporarily closing the gas container 1 .
  • the gas filling tube 14 is in particular for filling a liquefied first gas 2 into the gas containers 1 .
  • the gas supply station 13 may comprise a first container 21 for a liquefied first gas 2 .
  • the gas supply station 13 may advantageously comprise an introducing unit 9 for introducing a gaseous second gas 3 into the gas container 1 .
  • the gas supply station 13 may comprise a second container 22 for a liquefied second gas 3 , wherein the gas supply station 13 may comprise an evaporator 25 for converting the liquefied second gas 3 into its gaseous state.
  • the gas supply station 13 may comprise a third container 23 for a liquefied third gas 6 as cooling medium.
  • An advantageous gas supply station 13 for filling high pressure gas containers 1 with gas is adapted and in particular destined for use in the arrangement according to the invention.
  • An advantageous process for filling a high pressure gas container 1 comprises the following steps: Supplying a liquefied or solidified first gas 2 into a gas container 1 while the gas container 1 is being cooled; stopping the cooling of the gas container 1 after the supplying step of the first gas; then introducing a gaseous second gas 3 into the gas container 1 ; closing the gas container 1 , wherein in particular the cooling of the gas container 1 may be performed in a cooling bath 4 , in particular a cooling bath 4 of liquid nitrogen, and the cooling is stopped by disconnecting the gas container 1 from the cooling bath 4 .
  • the first gas 2 and/or the second gas 3 may be a mixture of plural gases.
  • the first gas 2 and/or the second gas 3 may be an inert gas, in particular a noble gas.
  • the gas container 1 may be temporarily closed.
  • the gas container 1 is in particular temporarily closed using an auxiliary valve 5 .
  • the closing of the gas container 1 may be performed by welding.
  • the gas containers 1 are in particular for air bag systems or for fuel cells.
  • the supplying of the first gas 2 may be performed at a pressure in the range from 0.2 bar to 15 bar, in particular in the range from 0.5 bar to 4 bar.
  • the supplying of the second gas 3 may be performed at a pressure in the range from 2 bar to 100 bar, in particular, in the range from 5 bar to 50 bar, for example in the range from 10 bar to 20 bar.
  • the first gas 2 may be supplied in a liquid state into the gas container 1 and solidifies in the gas container 1 .
  • the first gas 2 may be supplied at a temperature lower than its boiling temperature, in particular at least 1° K, preferably at least 2° K, lower than its boiling temperature, and at a temperature higher than its freezing temperature, in particular at least 1° K, preferably at least 2° K, higher than its freezing temperature.
  • the gas container 1 may be connected to a sealing device 11 , in particular a welding apparatus 12 , and after the introducing step of the second gas 3 the gas container 1 may be sealed by the sealing device 11 , in particular by welding.
  • the cooling is in particular performed using a liquefied third gas 6 , in particular liquid nitrogen, wherein in particular the temperature of the third gas 6 may be controlled by controlling the pressure in the third gas 6 .
  • the gas container 1 may be cooled before the supplying step of the first gas 2 .
  • An advantageous device for filling high pressure gas containers 1 comprises: A supplying unit 7 for supplying a liquefied or solidified first gas 2 into a gas container 1 while the gas container 1 is being cooled; a stopping unit 8 for stopping the cooling of the gas container 1 ; an introducing unit 9 for introducing a gaseous second gas 3 into the gas container 1 after the supplying step of the first gas; a unit 10 for closing the gas container 1 , wherein in particular the device further comprises a cooling bath 4 for cooling the gas container 1 , wherein in particular the device further comprises a transport mechanism 12 for transporting the gas containers 1 through the cooling bath 4 .
  • the unit 10 for closing the gas container 1 may be a welding apparatus 12 .
  • the device is in particular for filling high pressure gas containers 1 for air bag systems or for fuel cells.
  • the device in particular further comprises a gas supply station 13 and at least one thermally insulated filling tube 14 with a tube head 15 that is in fluid connection with the gas supply station 13 , wherein the filling tube 14 is for supplying the first gas 2 to the gas containers 1 , wherein the device in particular further comprises a positioning device 16 for positioning the tube head 15 at the gas containers 1 .
  • the invention concerns a high pressure gas container 1 with a container body 26 for storing gas and at least one first valve 27 for discharging the stored gas, characterized by further comprising an auxiliary valve 5 for introducing the gas into the container body 26 and for temporarily closing the container body 26 until the container body 26 is sealed permanently, wherein the first valve 27 and the auxiliary valve 5 are in fluid connection with the container body 26 .
  • the invention also concerns a process for filling a high pressure gas container 1 having a container body 26 for storing gas, at least one first valve 27 for discharging the stored gas and an auxiliary valve 5 wherein the first valve 27 and the auxiliary valve 5 are in fluid connection with the container body 26 , comprising the following steps: The gas is introduced into the container body 26 through the auxiliary valve 5 , the auxiliary valve 5 is at least temporarily closed, the auxiliary valve 5 is sealed permanently.
  • the invention allows for reliable, economical, reproducible and precise filling of high pressure gas containers using a conventional sealing apparatus without the need of its adaptation to either high pressure or low temperature appliance.

Abstract

A high pressure gas container with a container body for storing gas and at least one first valve for discharging the stored gas, further includes an auxiliary valve for introducing the gas into the container body and for temporarily closing the container body until the container body is sealed permanently, wherein the first valve and the auxiliary valve are in fluid connection with the container body. A process for filling a high pressure gas container having a container body for storing gas, at least one first valve for discharging the stored gas and an auxiliary valve wherein the first valve and the auxiliary valve are in fluid connection with the container body, includes the following steps: The gas is introduced into the container body through the auxiliary valve, the auxiliary valve is at least temporarily closed, the auxiliary valve is sealed permanently.

Description

  • The invention concerns a high pressure gas container comprising a container body for storing gas and a process for filling a high pressure gas container having a container body for storing gas and at least one first valve for discharging the stored gas.
  • For cold filling pressure containers, according to DE 101 07 895 a filling gas is cooled before its introduction into the pressure container, wherein on completion of the filling process the pressure container is sealed in a pressure-tight manner. As the gas warms up the pressure in the pressure container rises rapidly.
  • According to DE 198 17 324 a fuel gas is filled into a light weight tank made with a liner of chrome nickel steel inside of a fibre reinforced shell, wherein the fuel is introduced in deep cooled liquid form and is stored at a pressure above 300 bar.
  • According to WO 2005/043033 a pressure vessel, for example of an airbag system, is filled with a gas or a gas mixture at a temperature which is higher than the boiling point thereof, closing the cold vessel and a pressure is produced in the filled and closed vessel by heating it to ambient temperatures.
  • According to WO 2005/059431 a pressure container is filled with a gas mixture, wherein a gas mixture is introduced in its gaseous state or in its liquefied state or at least one gas component of a gas mixture is introduced in its gaseous state or in its liquefied state in a cooled pressure gas container.
  • U.S. Pat. No. 1,414,359 discloses a process for filling compressed gas containers, wherein a given quantity of liquefied gas is placed in a vessel of low specific heat capacity that is suspended within the container, the container is closed, and the walls of the container are maintained at a temperature above 0° C. until the enclosed substance has been converted into gaseous form.
  • DE 101 19 115 discloses a pressure container particularly suited for filling with low boiling permanent gases or gas mixtures at low temperatures which is provided on its inner surface with a material having a low heat conducting coefficient.
  • EP 0 033 386 discloses a process for transporting and storing permanent gases, in particular hydrogen, under pressure in pressure containers, wherein the gases are cooled to low temperatures above their boiling point and are transported and stored in isolated pressure containers.
  • It is known, that airbags in vehicles are increasingly using new types of gas generators, which in the event of an accident inflate the airbag within a few milliseconds. High pressure gas storage systems are used as gas generators.
  • Three different types of gas generators are currently in use:
      • Chemical generators which generate gas by reaction of a chemical solid with ambient air;
      • Hybrid generators which use both a fuel solid and gas that is stored in a pressurized high pressure gas container;
      • Cold gas generators that store gas in pressurized gas containers at high pressures up to 700 bar at 15° C.
  • The gas generators, which are filled with various gases at ambient temperatures, provide for considerable technical problems, both in terms of their production and their filling with pressures of up to 700 bar or above. The heat of compression in particular during a rapid filling leads to undefined temperature conditions which usually considerably affect the metering precision with which the amount of gas is introduced into the gas containers. To meet a high metering standard is important with respect to the subsequent inflation characteristics of the airbag. Very expensive and complex piston or diaphragm compressors are required to generate the very high pressures. This entails high investment and high maintenance costs. In addition, a correspondingly complex and expensive downstream gas supply is required for these pressures.
  • The known cold filling techniques avoid the problem originating from the filling of high pressures, however, these techniques usually work at extremely low temperatures which makes multiple adaptations of conventional process steps, such as the sealing of the gas container, to the low temperature conditions necessary, which is not desirable with respect investment and maintenance costs.
  • It is desirable that the density of the gas stored in a gas container is as high as possible, wherein the filling of the gas container should be reliable, reproducible, save and economical. The amount of gas filled into the container should be precisely metered and the throughput of gas filling facility should be as high as possible.
  • With respect to high temperature gas filling processes, that use high pressures above 300 bar, the known solutions to tightly connect a gas filling device with the gas container are challenging. The high pressures put high demands on safety and rigid connections and thick walled pipes are required to cope with the high pressure conditions.
  • With respect to the low temperature gas filling, the high pressure induced mechanical instabilities are less prominent, yet problems of thermal insulation, thermal tension and thermal expansion due to strong temperature gradients appear. In particular, the positioning of the gas containers at the gas supply station is not easy as the thermal contraction respectively expansion makes fine control of the spatial positioning system difficult.
  • Filling processes at room temperature operate at pressures above 300 bar and closing the filled pressurized gas containers is a difficult task. Usually complex high pressure vessels are used. The gas containers are brought into the high pressure vessel and are filled and closed under a high pressure. Usually the container comprises a membrane which is welded to the container. The closing process is technically complex and economically inefficient as the pressure vessel needs to be pressurized and depressurized for each loading cycle.
  • Gas filling at cold temperatures does not entail the problem of the pressure induced mechanical instabilities but needs to be performed at very low temperatures of usually below 100° K. Due to the low temperature and temperature gradients thermal induced stress and thermal expansion respectively contraction requires complex adaptation of the closing mechanism. It should be noted that in particular for airbag systems precise control of the amount of gas to be filled and stored in the gas container is indispensable for a reliable functioning of the airbag system.
  • An object of the present invention is to provide for a high pressure container with a container body for storing gas and a process for filling a high pressure gas container having a container body for storing gas, that allow for efficient, reproducible, reliable and economical filling of pressure gas containers.
  • This and other problems are solved according to the invention by a high pressure gas container and the process for filling a high pressure gas container as defined in the claims below. Further advantageous embodiments and developments, which can be employed individually or in any suitable combination, are also provided.
  • According to the invention the high pressure gas container with a container body for storing gas and with at least one first valve for discharging the stored gas is characterized by further comprising an auxiliary valve for introducing the gas into the container body and for temporarily closing the container body until the container body is sealed permanently, wherein the first valve and the auxiliary valve are in fluid connection with the container body.
  • The first valve is used for discharging the stored gas, when the container body is sealed permanently. For example the first valve may be at a membrane valve that is opened when the stored gas is needed, e.g. during an accident which makes the operation of the airbag system necessary. In connection with airbag systems the first valve may be a membrane valve that bursts when the stored gas is needed for inflating an airbag.
  • The first valve is gas tight on a permanent time basis, e.g. for over 15 years. Usually the first valve is closed by welding.
  • The auxiliary valve also helps to facilitate the supplying respectively introducing of gas into the container body. For instance after supplying a first gas or after introducing a second gas, the container body is temporarily closed. and transported to a closing unit which closes the container body permanently.
  • Furthermore the auxiliary valve may, if connected in a fluid series connection with the first valve at the gas container, be used for controlling the gas flow during an discharge operation. For example during an accident the amount of gas per unit time that is used for inflating an airbag may be suitably and precisely controlled.
  • The auxiliary valve may help to avoid gas leakage during the transport of the gas container for the time after the completion of the filling step until the gas container is permanently sealed.
  • The high pressure gas container may withstand pressures above 300 bar, for example up to 1300 bar, in particular in between 500 bar to 800 bar.
  • The gas to be introduced into the container may be a pure gas or a mixture of gases and may be an inert gas such as an noble gas in applications such as airbag systems. The gas may also be a fuel gas such as hydrogen in connection with fuel cell systems. The gas container may be filled with a cryogenically solidified or a cryogenically liquefied gas and high pressure may be obtained by closing the gas container shortly after its filling and letting the gas container warm up to room temperature.
  • The first valve and the auxiliary valve may be connected to the container body in fluid series connection, wherein the auxiliary valve may be in the fluid series connection between the first valve and the container body.
  • The first valve and the auxiliary valve may be connected to the container body with separate fluid connection lines. The first valve may be provided at the container body prior to its filling with gas. In this case the gas is to be introduced through the auxiliary valve into the container body.
  • The first valve may be non-reversibly openable. The auxiliary valve may be reversibly openable and closable.
  • In order to close the gas container permanently a sealing portion is provided at the auxiliary valve for permanently closing the auxiliary valve. The sealing portion may be provided in the fluid connection between the auxiliary valve and the container body, or, the auxiliary valve may be provided in the fluid interconnection between the sealing portion and the container body.
  • By closing the auxiliary valve the gas container may be sealed permanently with the sealing machine operating at ambient pressure and at ambient temperature.
  • Complex pressure vessels or specific adaptations to extremely low temperatures are not required anymore. Advantageously conventional sealing techniques such as welding may be used for closing the gas container permanently.
  • The auxiliary valve may be one of the following valves: a ball cock, a ball valve, a bibcock, a butterfly valve, a gate valve, a globe valve, a check valve, a rotary valve, a piston valve etc.
  • The auxiliary valve may be designed to be comparatively inexpensive as its purpose is solely for temporarily closing the container body. Usually it suffices when the auxiliary valve is able to retain the content of the gas container sufficiently constant for several minutes as usually the gas container may be permanently sealed shortly after its filling.
  • The first valve may be a membrane valve. The high pressure gas container may be particularly intended for use in connection with an airbag system.
  • It should be noted that the high pressure gas container may be used for a fuel cell. In this case the gas container stores a fuel gas such as hydrogen.
  • According to the invention the process for filling a high pressure gas container having a container body for storing gas, at least one first valve for discharging the stored gas and an auxiliary valve, wherein the first valve and the auxiliary valve are in fluid connection with the container body, comprises the following steps: The gas is introduced into the container body through the auxiliary valve, the auxiliary valve is at least temporarily closed, the auxiliary valve is sealed permanently.
  • The auxiliary valve helps to reduce losses due to evaporation out of the gas container by temporarily closing the container body until it is permanently sealed.
  • The first valve may be provided at the container body prior to its filling with gas. In this case the gas container is filled through the auxiliary valve and the auxiliary valve is then permanently sealed.
  • The first valve may also be provided at the container body after its filling with gas. In this case the filled container body is filled through the auxiliary valve, then the auxiliary valve is temporarily closed and then the first valve is affixed to auxiliary valve opposite to the gas container such that a rising pressure in the gas container does neither influence the affixing of the first valve nor lead to gas losses.
  • Thus the first valve may be provided at the gas container without the need of placing the gas container inside of a pressurized pressure vessel.
  • The auxiliary valve may be sealed by welding. The auxiliary valve may be sealed by the first valve in particular when the first valve is in series fluid connection with the auxiliary valve and the container body.
  • Advantageously prior to filling the container body with gas, the first valve is provided and is configured at the gas container.
  • Further details and favourable aspects, which may be applied alone or may be combined in any suitable manner, will be explained with respect to the following drawings, which shall not restrict the scope of the present invention but shall schematically and exemplarily illustrate the invention.
  • FIG. 1 shows the two-step process according to the invention;
  • FIG. 2 shows a high pressure gas container to be used according to the invention shown in cross section;
  • FIG. 3 shows further high pressure gas container to be used according to the invention shown in cross section;
  • FIG. 4 shows a detailed view of a supplying unit of a filling device according to the invention; and
  • FIG. 5 shows a supplying unit of a further embodiment of the filling device according to the invention.
  • FIG. 1 shows schematically the two-step process for filling a high pressure gas container 1 with a first gas 2 and a second gas 3 using a supplying unit 7 for supplying the first gas 2 into the gas container 1 and an introducing unit 9 for introducing the second gas 3 into the gas container 1. The gas container 1 comprises a container body 26 for receiving the first gas 2 and the second gas 3 and is connected to an auxiliary valve 5. The gas container 1 is connected to a cooling bath 4 which comprises a third gas 6 which is liquefied in order to precool the gas container 1 down to 86° K. The third gas 6 is liquid nitrogen which is kept under a slight pressure in the cooling bath 4 in order to provide for 86° K in the cooling bath 4. This precooling is performed using a precooling unit 24 which at least partially immerses the gas container 1 in the cooling bath 4. The gas container 1 is then transported with a transport mechanism 12 to a supplying unit 7 for supplying liquid argon as first gas 2 into the gas container 1. Then the auxiliary valve 5 is closed in order to diminish evaporation losses of the first gas 2. Subsequently the cooling of the gas container 1 is stopped by disconnecting the gas container 1 from the cooling bath 2 by a stopping unit 8 and is transported to an introducing unit for introducing the second gas 3 in its gaseous state. The second gas 3 such as helium is taken from a second container 22 and is evaporated by an evaporator 25 and is introduced through the auxiliary valve 5. After completion of the introducing the auxiliary valve 5 is temporarily closed until the gas container 1 is permanently closed using a unit 10 for closing the gas container 1. The unit 10 for closing comprises a sealing device 11 which seals the gas container 1 by welding. Both the introducing unit 9 and the unit 10 for closing may be of a conventional type meaning that they do not need to be adapted for cryogenical temperatures and do not need to be capable of coping with high pressures above 300 bar. The second gas 3 is introduced at ambient temperature into the gas container 1. After closing the gas container 1 the gas container 1 are allowed to warm up to ambient temperatures such that the pressure inside of the container body 26 rises to a well-defined pressure around 600 bar. The first gas 2 may be supplied at a pressure ranging from 0.5 bar to 3 bar and the second gas 3 may be introduced at 15 bar. The amount of gas supplied respectively introduced into the gas container 1 may be controlled volumetrically, gravimetrically or by an opening time of a metering valve. The second gas may be metered according to the partial pressure that is eventually desired at room temperature. This metering may be performed outside of the cooling bath 4 for instance in the sealing device 11.
  • FIG. 2 shows a gas container 1 in cross section to be used according to the invention. The gas container 1 comprises the auxiliary valve 5 in a first connection line 28 to the container body 26 and a first valve 27 in a second connection line 29 to the container body 26. The first valve 27 is provided at the container body 26 before the beginning of the filling process. The first valve 27 is a membrane valve and is adapted to be opened at the instance of operation of the gas container 1 for example during the operation of the airbag system (not shown). The first valve 27 operates non-reversibly, i.e. opens only once. The first valve 27 may be welded to the container body 26 respectively to the second connection line 29. The auxiliary valve 5 is for facilitating the supplying of the first gas 2 respectively the introducing of the second gas 3 into the container body 26. The auxiliary valve 5 is for temporarily closing the container body 26 such that evaporation losses are reduced. After the supplying step of the first gas 2 respectively after the introducing step of the second gas 3, the auxiliary valve 5 is closed. The auxiliary valve 5 may also be closed in between the supplying and the introducing step. Once the container body 26 is completely filled with a gas 2, 3 or with a mixture of gases 2, 3 the first connection line 28 is closed using a sealing portion 31 by welding. The closing portion 31 makes sure that after the closing of the gas container 1, gas may not escape from the container body 26 through the first connection line 28. The sealing portion 31 allows for using inexpensive auxiliary valves 5 without limiting the advantages of temporarily closing the container body 26.
  • FIG. 3 shows a further gas container 1 in cross section to be used according to the invention, wherein the first valve 27 and the auxiliary valve 5 are in a fluid series connection 30. In this case the permanent closing of the container body 26 is realized by the first valve 27 which is closed after the filling of the container body 26 with a gas 2, 3 or a mixture of gases 2, 3. The auxiliary valve 5 is used for facilitating the supplying of the first gas and/or the introducing of the second gas 3.
  • FIG. 4 shows schematically the supplying unit 7 comprising a gas supply station 13 with a flexible filling tube 14 which is to be connected to the container 1. For connecting the filling tube 14 with the gas container 1, a tube head 15 is provided which comprises a metering valve 17. The tube head 15 is positioned at the gas container 1 with a positioning device 16. Due to the flexibility of the filling tube 14 a gas tight connection between the gas supply station 13, respectively the supplying unit 7, and the gas container 1 is established in a short time. The filling tube 14 is thermally isolated and comprises a gas channel 18 for supplying the first gas 2 into the gas container 1. The gas channel 18 is isolated by means of an insulation vacuum. For this purpose the filling tube 14 is doubled walled. For further reducing a heat transfer through radiation within the insulation vacuum a heat shield 19 is introduced, which is at least partially actively cooled. The moveable tube head 15 allows for a fast connection which is important if a multiplicity of gas containers 1 need to be filled.
  • FIG. 5 shows a further embodiment of a supplying unit 7 of the device for filling gas containers 1. Liquid argon is stored as first gas 2 in a large supply tank 33 and is supplied through a supply tube 32 into a first container 21 which also serves as phase separator 20. The liquid argon from the phase separator 20 is precooled in a second precooling unit 35 for precooling the second gas 2. The liquid argon is cooled to 2° K below its boiling point in order to avoid any formation of gas bubbles within the liquid phase, which might affect the metering precision of the amount of gas supplied into the gas container 1. The second precooling unit 35 uses liquid nitrogen as third gas 6 from a third container 23 which is connected to the second precooling unit 35 with conduits 34. The precooled liquid argon is then supplied with the filling tube 14 to the gas container 1. For this purpose the filling tube 14 comprises a moveable tube head 15 which may be positioned precisely at the gas container 1. The gas container 1 is transported through the cooling bath by a transport mechanism 12. The cooling bath 4 is closed with a cover 36 in order to establish a pressure in the cooling bath 4 with which the temperature in the cooling bath is precisely controlled.
  • In the following, further aspects, which are related to the present invention, are described. These individual aspects may be employed individually and separately or in any suitable combination with each other respectively one another:
  • An advantageous process for filling high pressure gas containers 1 comprises the steps: Supplying a liquefied or solidified first gas 2 from a gas supply station 13 through a thermally insulated filling tube 14 with a movable tube head 15 to the high pressure gas container 1. During the supplying step of the first gas 2, the gas container 1 may be cooled, in particular by a cooling bath 4. The filling tube 14 is in particular cooled at least partially along its length, in particular by the cooling bath 4. The filling tube 14 may be filled using a two step filling process, in which after the supplying step of the first gas 2, a gaseous second gas 3, in particular Helium, is introduced into the gas container 1, wherein in particular during the supplying step of the first gas 2, the gas container 1 is cooled, in particular by a cooling bath 4, and before or during the introducing step of the second gas 3 the cooling of the gas container 1 is stopped, in particular the gas container 1 is taken out of the cooling bath 4. Advantageously high pressure gas containers 1 for air bag systems or for fuel cells are filled. The first gas 2 and/or the second gas 3 may be a mixture of gases.
  • An advantageous process of batch filling of high pressure gas containers 1 with gas, comprises the step cooling multiple gas containers 1 in parallel, which are filled sequentially using the process according to the invention.
  • An advantageous arrangement for filling high pressure gas containers 1 with gas comprises a gas supply station 13 and multiple high pressure gas containers 1, wherein the gas supply station 13 comprises at least one thermally insulated filling tube 14 with a movable tube head 15 for gas filling of the gas containers 1, wherein the arrangement may comprise a positioning device 16 for moving the tube head 15 to the individual gas containers 1. Advantageously, a metering valve 17 for controlling a gas flow through the filling tube 14 may be provided in the tube head 15. The gas supply station 13 may comprise a cooling bath 4 for cooling the gas containers 1, wherein the filling tube 14 may be at least partially immersed in the cooling bath 4 and wherein the arrangement may further comprise a transport mechanism 12 for transporting the gas containers 1 through the cooling bath 4. In a useful embodiment, the filling tube 14 may be at least doubled walled and may comprise an insulation vacuum for thermal insulation. The filling tube 14 may be actively cooled by a cooling medium, in particular a liquefied third gas 6 and/or may comprise a gas channel 18 and a tubular heat shield 19 at least partially around the gas channel 18, wherein the heat shield 19 is cooled by the cooling medium. Tube head 15 may comprise an auxiliary valve 5 for temporarily closing the gas container 1. The gas filling tube 14 is in particular for filling a liquefied first gas 2 into the gas containers 1. The gas supply station 13 may comprise a first container 21 for a liquefied first gas 2. The gas supply station 13 may advantageously comprise an introducing unit 9 for introducing a gaseous second gas 3 into the gas container 1. The gas supply station 13 may comprise a second container 22 for a liquefied second gas 3, wherein the gas supply station 13 may comprise an evaporator 25 for converting the liquefied second gas 3 into its gaseous state. The gas supply station 13 may comprise a third container 23 for a liquefied third gas 6 as cooling medium.
  • An advantageous gas supply station 13 for filling high pressure gas containers 1 with gas is adapted and in particular destined for use in the arrangement according to the invention.
  • An advantageous process for filling a high pressure gas container 1, comprises the following steps: Supplying a liquefied or solidified first gas 2 into a gas container 1 while the gas container 1 is being cooled; stopping the cooling of the gas container 1 after the supplying step of the first gas; then introducing a gaseous second gas 3 into the gas container 1; closing the gas container 1, wherein in particular the cooling of the gas container 1 may be performed in a cooling bath 4, in particular a cooling bath 4 of liquid nitrogen, and the cooling is stopped by disconnecting the gas container 1 from the cooling bath 4. The first gas 2 and/or the second gas 3 may be a mixture of plural gases. The first gas 2 and/or the second gas 3 may be an inert gas, in particular a noble gas. After the supplying step of the first gas 2 and before the introducing step of the second gas 3 the gas container 1 may be temporarily closed. The gas container 1 is in particular temporarily closed using an auxiliary valve 5. The closing of the gas container 1 may be performed by welding. The gas containers 1 are in particular for air bag systems or for fuel cells. The supplying of the first gas 2 may be performed at a pressure in the range from 0.2 bar to 15 bar, in particular in the range from 0.5 bar to 4 bar. The supplying of the second gas 3 may be performed at a pressure in the range from 2 bar to 100 bar, in particular, in the range from 5 bar to 50 bar, for example in the range from 10 bar to 20 bar. The first gas 2 may be supplied in a liquid state into the gas container 1 and solidifies in the gas container 1. The first gas 2 may be supplied at a temperature lower than its boiling temperature, in particular at least 1° K, preferably at least 2° K, lower than its boiling temperature, and at a temperature higher than its freezing temperature, in particular at least 1° K, preferably at least 2° K, higher than its freezing temperature. After the supplying step of the first gas 2 and before the introducing step of the second gas 3, the gas container 1 may be connected to a sealing device 11, in particular a welding apparatus 12, and after the introducing step of the second gas 3 the gas container 1 may be sealed by the sealing device 11, in particular by welding. The cooling is in particular performed using a liquefied third gas 6, in particular liquid nitrogen, wherein in particular the temperature of the third gas 6 may be controlled by controlling the pressure in the third gas 6. The gas container 1 may be cooled before the supplying step of the first gas 2.
  • An advantageous device for filling high pressure gas containers 1, comprises: A supplying unit 7 for supplying a liquefied or solidified first gas 2 into a gas container 1 while the gas container 1 is being cooled; a stopping unit 8 for stopping the cooling of the gas container 1; an introducing unit 9 for introducing a gaseous second gas 3 into the gas container 1 after the supplying step of the first gas; a unit 10 for closing the gas container 1, wherein in particular the device further comprises a cooling bath 4 for cooling the gas container 1, wherein in particular the device further comprises a transport mechanism 12 for transporting the gas containers 1 through the cooling bath 4. The unit 10 for closing the gas container 1 may be a welding apparatus 12. The device is in particular for filling high pressure gas containers 1 for air bag systems or for fuel cells. The device in particular further comprises a gas supply station 13 and at least one thermally insulated filling tube 14 with a tube head 15 that is in fluid connection with the gas supply station 13, wherein the filling tube 14 is for supplying the first gas 2 to the gas containers 1, wherein the device in particular further comprises a positioning device 16 for positioning the tube head 15 at the gas containers 1.
  • The invention concerns a high pressure gas container 1 with a container body 26 for storing gas and at least one first valve 27 for discharging the stored gas, characterized by further comprising an auxiliary valve 5 for introducing the gas into the container body 26 and for temporarily closing the container body 26 until the container body 26 is sealed permanently, wherein the first valve 27 and the auxiliary valve 5 are in fluid connection with the container body 26. The invention also concerns a process for filling a high pressure gas container 1 having a container body 26 for storing gas, at least one first valve 27 for discharging the stored gas and an auxiliary valve 5 wherein the first valve 27 and the auxiliary valve 5 are in fluid connection with the container body 26, comprising the following steps: The gas is introduced into the container body 26 through the auxiliary valve 5, the auxiliary valve 5 is at least temporarily closed, the auxiliary valve 5 is sealed permanently. The invention allows for reliable, economical, reproducible and precise filling of high pressure gas containers using a conventional sealing apparatus without the need of its adaptation to either high pressure or low temperature appliance.
  • REFERENCE NUMERALS
    • 1 gas container
    • 2 first gas
    • 3 second gas
    • 4 cooling bath
    • 5 auxiliary valve
    • 6 third gas
    • 7 supplying unit
    • 8 stopping unit
    • 9 introducing unit
    • 10 unit for closing
    • 11 sealing device
    • 12 transport mechanism
    • 13 gas supply station
    • 14 filling tube
    • 15 tube head
    • 16 positioning device
    • 17 metering valve
    • 18 gas channel
    • 19 heat shield
    • 20 phase separator
    • 21 first container
    • 22 second container
    • 23 third container
    • 24 precooling unit
    • 25 evaporator
    • 26 container body
    • 27 first valve
    • 28 first connection line
    • 29 second connection line
    • 30 fluid series connection
    • 31 sealing portion
    • 32 supply tube
    • 33 supply tank
    • 34 conduits
    • 35 second precooling unit
    • 36 cover

Claims (17)

1. High pressure gas container (1) with a container body (26) for storing gas and at least one first valve (27) for discharging the stored gas, characterized by
further comprising an auxiliary valve (5) for introducing the gas into the container body (26) and for temporarily closing the container body (26) until the container body (26) is sealed permanently, wherein the first valve (27) and the auxiliary valve (5) are in fluid connection with the container body (26).
2. Gas container (1) according to claim 1, characterized in that the first valve (27) and the auxiliary valve (5) are connected to the container body (26) with separate fluid connection lines (28, 29).
3. Gas container (1) according to claim 1, characterized in that the first valve (27) and the auxiliary valve (5) are connected to the container body (26) in a fluid series connection (30).
4. Gas container (1) according to claim 1, characterized in that the first valve (27) is non-reversibly openable.
5. Gas container (1) according to claim 1, characterized in that the auxiliary valve (5) is reversibly openable and closable.
6. Gas container (1) according to claim 1, characterized in that a sealing portion (31) is provided at the auxiliary valve (5) for permanently closing the auxiliary valve (5).
7. Gas container (1) according to claim 6, characterized in that the sealing portion (31) is provided in the fluid connection between the auxiliary valve (5) and the container body (26).
8. Gas container (1) according to claim 6, characterized in that the auxiliary valve (5) is provided in the fluid interconnection between the sealing portion (31) and the container body (26).
9. Gas container (1) according to claim 1, characterized in that the auxiliary valve (5) is one of the following valves: a ball cock, a ball valve, a bibcock, a butterfly valve, a gate valve, a globe valve, check valve, a rotary valve, a piston valve.
10. Gas container (1) according to claim 1, characterized in that the first valve (27) is a membrane valve.
11. Gas container (1) according to claim 1, characterized in that the high pressure gas container (1) is for an air bag system.
12. Gas container (1) according to claim 1, characterized in that the high pressure gas container (1) is for a fuel cell.
13. Process for filling a high pressure gas container (1) having a container body (26) for storing gas, at least one first valve (27) for discharging the stored gas and an auxiliary valve (5), wherein the first valve (27) and the auxiliary valve (5) are in fluid connection with the container body (26), comprising the following steps:
the gas is introduced into the container body (26) through the auxiliary valve (5),
the auxiliary valve (5) is at least temporarily closed,
the auxiliary valve (5) is sealed permanently.
14. Process according to claim 13, characterized in that the auxiliary valve (5) is sealed by welding.
15. Process according to claim 13, characterized in that the auxiliary valve (5) is sealed by the first valve (27).
16. Process according to claim 13, characterized in that prior to filling the container body (26) with gas, the first valve (27) is provided and is configured at the gas container (1).
17. Process according to claim 14, characterized in that the auxiliary valve (5) is sealed by the first valve (27).
US11/657,688 2006-01-27 2007-01-25 High pressure gas container with an auxiliary valve and process for filling it Abandoned US20070193647A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
EP06001696.1 2006-01-27
EP06001696A EP1813853B1 (en) 2006-01-27 2006-01-27 High pressure gas container with an auxiliary valve and process for filling it

Publications (1)

Publication Number Publication Date
US20070193647A1 true US20070193647A1 (en) 2007-08-23

Family

ID=37023143

Family Applications (1)

Application Number Title Priority Date Filing Date
US11/657,688 Abandoned US20070193647A1 (en) 2006-01-27 2007-01-25 High pressure gas container with an auxiliary valve and process for filling it

Country Status (5)

Country Link
US (1) US20070193647A1 (en)
EP (1) EP1813853B1 (en)
CN (1) CN101008467A (en)
AT (1) ATE431522T1 (en)
DE (1) DE602006006785D1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20110036163A1 (en) * 2005-08-11 2011-02-17 L'Air Liquide Societe Anonyme Pour L'Etude Et L'Exlotation Des Procedes Georges Claude Method for Filling a Pressurized Gas Tank
EP2466187A1 (en) * 2010-12-16 2012-06-20 Air Products And Chemicals, Inc. A gas storage container

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2896870B1 (en) * 2014-01-20 2021-03-17 Air Liquide Deutschland GmbH Method and device for automatic serial filling of pressure bottles with gas

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5343904A (en) * 1991-09-09 1994-09-06 Charles Kaeser Aerosol can pressurizing device and aerosol can therefor
US5388620A (en) * 1992-09-28 1995-02-14 L'oreal Packaging container of the aerosol type which can be recharged with compressed gas
US5394908A (en) * 1993-12-13 1995-03-07 Trw Vehicle Safety Systems Inc. Apparatus and method for filling a container
US5462099A (en) * 1994-01-28 1995-10-31 S. C. Johnson & Son, Inc. System and method for pressurizing dispensing containers
US5588472A (en) * 1995-06-14 1996-12-31 Morton International, Inc. Method for combined gas fill and proof test of pressure vessels
US5820102A (en) * 1996-10-15 1998-10-13 Superior Valve Company Pressurized fluid storge and transfer system including a sonic nozzle
US6527009B2 (en) * 1997-11-14 2003-03-04 Air Products And Chemicals, Inc. Gas control device and method of supplying gas
US6883564B2 (en) * 2003-07-22 2005-04-26 Thomas M. Risch Pressurizing system for a dispensing container
US20050269351A1 (en) * 2004-05-20 2005-12-08 Nippon Tansan Gas Co., Ltd. Method and mechanism to seal a vessel for a highly pressurized combustion-supportable or flammable gas
US7013916B1 (en) * 1997-11-14 2006-03-21 Air Products And Chemicals, Inc. Sub-atmospheric gas delivery method and apparatus
US7108281B2 (en) * 2003-08-22 2006-09-19 Trw Vehicle Safety Systems Inc. Stored gas inflator with fill valve assembly
US7150299B2 (en) * 2003-09-12 2006-12-19 Air Products And Chemicals, Inc. Assembly and method for containing, receiving and storing fluids and for dispensing gas from a fluid control and gas delivery assembly having an integrated fluid flow restrictor

Family Cites Families (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US1414359A (en) 1921-01-03 1922-05-02 Heylandt Paul Process for filling high-pressure vessels with liquefiable gases
DE3003355A1 (en) 1980-01-31 1981-08-06 Messer Griesheim Gmbh, 6000 Frankfurt METHOD FOR TRANSPORTING AND STORING PERMANENT GASES
IT1256560B (en) * 1992-12-18 1995-12-07 UNDER-VALVE INTERCEPTING DEVICE FOR FLOW GAS CYLINDER
DE19518036C1 (en) * 1995-05-17 1996-12-05 Daimler Benz Ag Device for refueling gas bottles of a gas-powered bus
DE19817324A1 (en) 1998-04-18 1999-10-21 Messer Griesheim Gmbh Method for storing of cooled liquefied fuel gases, e.g. methane, hydrogen, etc.
DE10107895B4 (en) 2001-02-20 2007-07-05 Air Liquide Deutschland Gmbh Method and device for filling pressure vessels with low-boiling permanent gases or gas mixtures
DE10119115A1 (en) 2001-04-19 2002-10-31 Messer Griesheim Gmbh pressure vessel
AU2002342367A1 (en) * 2002-02-14 2003-09-04 Isi Airbag Gmbh Cold gas generator
WO2005043033A1 (en) 2003-10-17 2005-05-12 L'AIR LIQUIDE Société Anonyme à Directoire et Conseil de Surveillance pour l'Etude et l'Exploitation Method for filling a pressure vessel with gas
JP4643589B2 (en) 2003-12-19 2011-03-02 レール・リキード−ソシエテ・アノニム・プール・レテュード・エ・レクスプロワタシオン・デ・プロセデ・ジョルジュ・クロード Method for filling a compressed gas container with gas
EP1559949A1 (en) * 2004-01-28 2005-08-03 Gaveco AB A method and a system for refuelling of gas driven vehicles and a vehicle gas container
US7461860B2 (en) * 2004-05-21 2008-12-09 Delphi Technologies, Inc. Apparatus and method for providing combustible gas inflator

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5343904A (en) * 1991-09-09 1994-09-06 Charles Kaeser Aerosol can pressurizing device and aerosol can therefor
US5388620A (en) * 1992-09-28 1995-02-14 L'oreal Packaging container of the aerosol type which can be recharged with compressed gas
US5394908A (en) * 1993-12-13 1995-03-07 Trw Vehicle Safety Systems Inc. Apparatus and method for filling a container
US5462099A (en) * 1994-01-28 1995-10-31 S. C. Johnson & Son, Inc. System and method for pressurizing dispensing containers
US5588472A (en) * 1995-06-14 1996-12-31 Morton International, Inc. Method for combined gas fill and proof test of pressure vessels
US5820102A (en) * 1996-10-15 1998-10-13 Superior Valve Company Pressurized fluid storge and transfer system including a sonic nozzle
US6527009B2 (en) * 1997-11-14 2003-03-04 Air Products And Chemicals, Inc. Gas control device and method of supplying gas
US7013916B1 (en) * 1997-11-14 2006-03-21 Air Products And Chemicals, Inc. Sub-atmospheric gas delivery method and apparatus
US6883564B2 (en) * 2003-07-22 2005-04-26 Thomas M. Risch Pressurizing system for a dispensing container
US7108281B2 (en) * 2003-08-22 2006-09-19 Trw Vehicle Safety Systems Inc. Stored gas inflator with fill valve assembly
US7150299B2 (en) * 2003-09-12 2006-12-19 Air Products And Chemicals, Inc. Assembly and method for containing, receiving and storing fluids and for dispensing gas from a fluid control and gas delivery assembly having an integrated fluid flow restrictor
US20050269351A1 (en) * 2004-05-20 2005-12-08 Nippon Tansan Gas Co., Ltd. Method and mechanism to seal a vessel for a highly pressurized combustion-supportable or flammable gas

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20110036163A1 (en) * 2005-08-11 2011-02-17 L'Air Liquide Societe Anonyme Pour L'Etude Et L'Exlotation Des Procedes Georges Claude Method for Filling a Pressurized Gas Tank
EP2466187A1 (en) * 2010-12-16 2012-06-20 Air Products And Chemicals, Inc. A gas storage container
WO2012080169A1 (en) * 2010-12-16 2012-06-21 Air Products And Chemicals, Inc. A gas storage container

Also Published As

Publication number Publication date
DE602006006785D1 (en) 2009-06-25
CN101008467A (en) 2007-08-01
ATE431522T1 (en) 2009-05-15
EP1813853A1 (en) 2007-08-01
EP1813853B1 (en) 2009-05-13

Similar Documents

Publication Publication Date Title
US20080202629A1 (en) Two-Step-Process for Filling Gas Containers for Airbag Systems and Gas Filling Device for a Two-Step-Filling Process
US8671997B2 (en) Device and method for filling a container with a gas under pressure
EP0933583B1 (en) Cryogenic fluid cylinder filling system
US6810924B2 (en) Compressed gas stream introduction method and filling station
CN101180495A (en) Two-step-process for filling gas containers for airbag systems and gas filling device for a two-step-filling process
US20070186991A1 (en) Process and arrangement for filling high pressure gas containers using a filling tube
US7490635B2 (en) Method for filling a pressure vessel with gas
ES2263765T3 (en) PROCEDURE AND DEVICE FOR THE FILLING OF PRESSURE CONTAINERS WITH PERMANENT GASES OR MIXTURES OF PERMANENT GASES OF LOW EFFICIENCY POINT.
US20070181211A1 (en) Process and arrangement for filling a high pressure gas container with liquefied gas under hydrostatic pressure
EP1759144B1 (en) Filling of pressure vessels with cryogenically solidified gas
KR20210142135A (en) Apparatus and method for storing and supplying fluid fuel
EP1813853B1 (en) High pressure gas container with an auxiliary valve and process for filling it
US7611566B2 (en) Direct gas recirculation heater for optimal desorption of gases in cryogenic gas storage containers
KR100662189B1 (en) Refrigerant gas recycling apparatus for cryogenic cooling device
WO2006103987A1 (en) Method for supplying hydrogen gas and car for transporting liquefied hydrogen
US20080178612A1 (en) Method for Supplying Hydrogen Gas and Liquefied Hydrogen Delivery Vehicle
US20060037678A1 (en) Gas quenching installation and the corresponding quenching method
CN210037461U (en) Inflation and deflation circulation test system of high-pressure hydrogen storage cylinder
CN115899542A (en) Hydrogen system that puts that low temperature high pressure is stored up
RU2222749C2 (en) Gas storage vessel
AU2022334657A1 (en) Method and conveying device
Pregassame et al. Evaluation of cold filling processes for 70MPa storage systems in vehicles
Swanger LH2 Storage and Handling Demonstrations Using Active Refrigeration
CN117227077A (en) Liquid carbon dioxide filling system and filling method
US20190077657A1 (en) Gas-Loading and Packaging Method and Apparatus

Legal Events

Date Code Title Description
AS Assignment

Owner name: L'AIR LIQUIDE, SOCIETE ANONYME A DIRECTOIRE ET CON

Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNORS:KLEBE, ULRICH;MICHEL, FRIEDEL;REEL/FRAME:019259/0154

Effective date: 20070308

STCB Information on status: application discontinuation

Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION