US20010033773A1 - Pipe weld alignment system - Google Patents
Pipe weld alignment system Download PDFInfo
- Publication number
- US20010033773A1 US20010033773A1 US09/846,014 US84601401A US2001033773A1 US 20010033773 A1 US20010033773 A1 US 20010033773A1 US 84601401 A US84601401 A US 84601401A US 2001033773 A1 US2001033773 A1 US 2001033773A1
- Authority
- US
- United States
- Prior art keywords
- pipe
- mast
- stationary table
- stinger
- erector
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L1/00—Laying or reclaiming pipes; Repairing or joining pipes on or under water
- F16L1/12—Laying or reclaiming pipes on or under water
- F16L1/20—Accessories therefor, e.g. floats, weights
- F16L1/225—Stingers
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING
- B63B35/00—Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for
- B63B35/03—Pipe-laying vessels
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L1/00—Laying or reclaiming pipes; Repairing or joining pipes on or under water
- F16L1/12—Laying or reclaiming pipes on or under water
- F16L1/16—Laying or reclaiming pipes on or under water on the bottom
- F16L1/18—Laying or reclaiming pipes on or under water on the bottom the pipes being S- or J-shaped and under tension during laying
- F16L1/19—Laying or reclaiming pipes on or under water on the bottom the pipes being S- or J-shaped and under tension during laying the pipes being J-shaped
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L1/00—Laying or reclaiming pipes; Repairing or joining pipes on or under water
- F16L1/12—Laying or reclaiming pipes on or under water
- F16L1/20—Accessories therefor, e.g. floats, weights
- F16L1/202—Accessories therefor, e.g. floats, weights fixed on or to vessels
- F16L1/207—Pipe handling apparatus
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L1/00—Laying or reclaiming pipes; Repairing or joining pipes on or under water
- F16L1/12—Laying or reclaiming pipes on or under water
- F16L1/20—Accessories therefor, e.g. floats, weights
- F16L1/235—Apparatus for controlling the pipe during laying
Definitions
- This invention relates generally to laying underwater pipe and, more particularly, to installing underwater pipelines on the seabed and/or connecting the same to floating terminals at the surface.
- Floating production facilities require risers to provide fluid conduits between subsea equipment and the surface facility (or platform).
- the floating structure responds dynamically to the forces of the environment to which it is exposed. This means that the conduit connecting the structure and subsea equipment must be connected in a manner that accommodates relative motions.
- the conduit requires top and bottom interfaces to establish functional connections.
- flexible pipe was considered as the only feasible means of providing flowline connections from equipment on the sea bed to a floating production vessel.
- flexible pipe is very expensive, much more so than standard steel pipe.
- the use of steel pipe in deep water risers was developed as an alternative means of achieving the sea bed connection. This presented the practical problem of how to deploy a steel pipe string vertically from a starting point on the ocean floor to a hand-off and terminus at a floating production system; thereby leading to the development and use of J-Lay towers for this purpose.
- the assembly and deployment of subsea steel pipelines from floating vessels usually employs a J-Lay tower, especially in deep water.
- the J-Lay tower provides a vertical, or nearly vertical, platform for welding lengths of pipe into a pipe string.
- the J-Lay tower tension feeds the pipe string from an anchor on the seabed.
- Prepared lengths of pipe, known as “pipe joints,” are fed one at a time into the J-Lay tower and welded together to form the pipe string.
- the angle at which the assembled pipe string leaves the vessel to enter the water is controlled by the angle and azimuth of the tower mast and “stinger,” which is an inverted structure pointing down into the water underneath the J-Lay tower, relative to the pipe string being deployed.
- J-Lay tower installations have employed vertical masts rigidly installed on pipe lay vessels. These installations utilized pipe tensioners integrated into the mast for control of the pipe string during deployment and hand-off operations.
- J-Lay towers have been manufactured with the ability to lower pipe straight down, or with an angle provided by a cone shaped stinger.
- Other towers have been installed at a fixed angle to allow a departure from the base at an approximation of the best average departure direction. Any angular departure of the pipeline from purely vertical in the first case or from the preset pipe angle in the second case would cause the pipeline to be bent around the stinger.
- most current stingers employ a static, fixed structure that imposes either cylindrical or conical shaped excursion boundaries on the emerging pipe string.
- Rigidly installed, vertical towers engender a number of problems caused by an inability to respond in real time to the dynamic forces encountered during pipe laying operations. For instance, welding and assembly operations are performed at the working floor on pipe with a substantial imposed moment. Other deficiencies include the fact that they do not allow: 1) control of the bending stress and tension within the pipe string as it is deployed in an arc to the sea bed; 2) the laying vessel to weather vane or rotate about the pipe and thereby prevent torsional wind-up of the pipe string; and 3) precise control of the pipe lay envelope. Further, current J-Lay tower designs omit any means for precise and accurate alignment of the pipe string and new pipe joints during the welding process. Current methods for deploying pipe also encounter problems not directly associated with the use of rigidly installed, vertical towers. None efficiently and/or automatically feed pipe joints into the tower or align the pipe joints with the tower center line to facilitate assembling the pipe string 12 .
- the present invention is directed to overcoming, or at least reducing the effects of, one or more of the problems set forth above.
- An apparatus for deploying pipe string comprises a mast; an articulated stationary table to which the mast is affixed; a stinger affixed to the stationary table to articulate with the mast; and a pipe erector operatively connected to the mast.
- FIG. 1 illustrates one embodiment of an apparatus for assembling and deploying pipe string underwater, the apparatus constructed and operated in accordance with the present invention
- FIGS. 2 - 5 illustrate an individual pipe joint and parts used to prepare the pipe joint to be incorporated into a pipe string as may be deployed by the embodiment of FIG. 1;
- FIG. 6 is a conceptualized perspective view of part of the tower system 10 of the embodiment in FIG. 1;
- FIG. 7 is a partial cross-sectional, side view of part of the tower system 10 of the embodiment in FIG. 1;
- FIG. 8 is a partial cross-sectional view of a part of the embodiment of FIG. 1;
- FIGS. 9 - 12 illustrate, in various views, the clamping system of the embodiment of FIG. 1;
- FIGS. 13 A- 13 B illustrate the swivel bearing of the embodiment in FIG. 1;
- FIG. 14 is a partial cross-sectional, side view of a screw jack as employed in the articulating joint of FIG. 1;
- FIG. 15 illustrates the stinger of the embodiment of FIG. 1
- FIGS. 16 A-C illustrate the erector system of the embodiment of FIG. 1;
- FIGS. 17 A-B illustrate the weld alignment and placement system in the embodiment of FIG. 1;
- FIGS. 18 - 20 illustrate a bootstrap mechanism as may be used in some alternative embodiments to erect the articulated tower in FIG. 1;
- FIG. 21 illustrates how the stinger of FIG. 1 controls the deployment of the pipe string
- FIGS. 22 - 25 illustrate how the invention may be employed in several pipe laying operations.
- FIG. 1 illustrates an apparatus 10 as may be used in various embodiments to deploy a pipe string 12 beneath the surface of a body of water 14 from a vessel 16 .
- the apparatus 10 is articulated as set forth in more detail below and may be used to deploy the pipe string 12 for a variety of purposes. Exemplary purposes include installing pipelines on the seabed (not shown) and deploying risers between a pipe string 12 (also not shown) on the seabed and the vessel 16 .
- the term “pipe string 12 ” refers to a plurality of pipe joints 17 , or pieces of pipe, affixed together and, thus, may generically be used to refer to pipelines and risers.
- the particular embodiment of the apparatus 10 illustrated in FIG. 1 is a tower system 10 and generally comprises an mast 15 , a stinger 20 , and a pipe erector 25 , all of which are articulated.
- a prepared pipe joint 17 is loaded onto a pipe erector 25 , which then loads it into the mast 15 .
- the pipe joint 17 is then affixed to the end of the pipe string 12 , whereupon it becomes a constituent part of the pipe string 12 .
- the pipe string 12 can then be further deployed through the stinger 20 and the mast 15 .
- the pipe joints 17 , apparatus 10 , and the method of using the apparatus 10 just now generally described are set forth in greater detail below.
- the pipe string 12 comprises a plurality of pipe joints 17 .
- Each pipe joint 17 comprises an individual pipe length 36 , shown in FIG. 2, which will be assembled (via welding) into the deployed pipe string 12 .
- Each pipe length 36 is prepared for assembly by machining weld prep surfaces 35 at each end of the pipe length 36 .
- a J-Lay collar 38 such as that shown in cross-section in FIG. 3, is welded to the upper end 40 of each pipe length 36 .
- the pipe joints 17 are then painted with a corrosion protection system in a manner commonly known in the art.
- a double collar 42 shown in FIGS. 4 - 5 , is then affixed to the pipe joint 17 around the J-lay collar 38 as shown in FIG. 8.
- the double collar 42 is a temporary split collar with multiple landing surfaces at differing diameters. It is used to secure the individual pipe joints 17 and the pipe string 12 at various stages in the assembly and deployment sequence as set forth below.
- the embodiment includes a mast 15 joined to a main skid frame 22 through an articulated joint 24 .
- the tower mast 15 includes a traveling table 26 , a pair of hydraulic cylinders 28 , and a stationary table 30 .
- the mast 15 and stationary table 30 also rest upon and are connected to a plurality of screwjacks 32 .
- the mast 15 is a three-part, welded, steel truss structure 18 mounted to the top surface 21 of the stationary table 30 . It supports two very large, hydraulic lifting cylinders 28 (with 500,000 lbs. lift capacity each), the traveling table 26 , the pipe clamping system 44 shown in FIGS. 10 - 12 , and the weld alignment system 46 shown in FIGS. 17 A- 17 B.
- the hydraulic cylinders 28 provide the vertical lift and tensioning capability on the pipe string 12 .
- Multiple wire ropes (not shown) tied to the base of the cylinders 28 at the stationary table 30 run over sheaves (also not shown) mounted at the top of the hydraulic cylinders 28 to the traveling table 26 .
- the mast 15 acts as the guide mechanism for vertical movement of the traveling table 26 . It also mounts the two centralizing units 48 discussed below that center the pipe joint 17 and straighten it prior to welding at the lower end as discussed further below.
- the main skid frame 22 is a welded plate structure designed to support the entire tower system 10 via the stationary table 30 and all associated equipment. It provides the interface with the deck 34 of the vessel 16 and distributes the system loads over a large area of the deck 34 .
- the stationary table 30 is a welded steel plate structure with a 62.0′′ diameter hole 52 at its center for riser deployment.
- the stationary table 30 provides a common rigid interface for the mast 15 , stinger 20 , and erector 25 . It is supported by three screw jacks 54 and a gimbaled bearing 50 which are installed on the main skid frame 22 .
- a 62.0′′ bowl 58 is permanently installed in the riser hole 52 of the stationary table 30 .
- a 62.0′′ split bushing 60 is nested inside the bowl 58 .
- a 26.0′′ bushing 62 is, in turn, installed in the 62.0′′ bushing 60 .
- the 26.0′′ bushing 62 supports the pipe string 12 (via the temporary double collar 48 on the last pipe joint 17 in the pipe string 12 ) while the next pipe joint 17 is being welded in place.
- the traveling table 26 is a welded steel plate structure powered by the twin lifting cylinders 28 (shown in FIG. 2). It receives the top ends of the pipe joints 17 as they are lifted from the horizontal by the erector 25 .
- a split clamp 44 installed on the traveling table 26 secures the end of the pipe joint 17 (around a temporary double collar 42 ) and holds it in place while the pipe joint 17 is aligned by the mast 15 centralizing units 48 in preparation for welding at the lower end.
- the traveling table 26 supports the swivel bearing 65 , shown in FIGS. 13 A- 13 B, when in use, the swivel bearing 65 being inserted between the double collar 42 and the split clamp 44 .
- FIG. 13B is a split view drawing, presenting View A wherein the swivel bearing 65 is inserted into the traveling table 26 and View B wherein the traveling table 26 is shown without the swivel bearing 65 .
- the swivel bearing 65 is a mechanical bearing consisting of a turning body 66 and a non-turning body 68 with multiple, compression loaded, zylan coated, shear rings 70 interposed between them.
- the turning body 66 interfaces and supports the double collar 42 ; the non-turning body 68 interfaces with the split clamp 44 on the floor of the traveling table 26 .
- the shear rings 70 shear relative to one another in order to accommodate the differential motion between the turning body 66 and the non-turning body 68 .
- the swivel bearing 65 When needed, the swivel bearing 65 is inserted at the traveling table 26 as shown in FIG. 13B and carries the weight of the pipe string 12 during vessel 16 turning operations and heading adjustments.
- the bearing swivel 65 provides a rotating interface between the pipe string 12 and the mast 15 .
- the bearing swivel 65 also has numerous applications other than that disclosed above. For instance, the bearing swivel 65 might be used in many other applications requiring torsional isolation within a system without interrupting load path continuity and a high load capacity.
- the stationary table 30 and the main skid frame 22 define the articulated joint 24 employing a spherical bearing 72 and a plurality of screw jacks 54 .
- the interface between the stationary table 30 and the main skid frame 22 consists of the 62.0′′ spherical metal bearing 72 that is free to move up and down within a cylindrical bore 74 .
- the articulated joint 24 in this embodiment is a ball joint.
- the spherical bearing 72 encircles (and is welded to) the stinger base tube 76 , which is, in turn, bolted to the stationary table 30 .
- This articulated interface reacts all radial loads within the system.
- Three screw jacks 54 are arrayed at 120° intervals about the articulated joint 24 and tilt the mast 15 up to 15° off vertical on any azimuth. The screw jacks 54 react all vertical loads in the system.
- FIG. 14 illustrates a representative one of the screw jacks 54 .
- the screw jack 54 is a mechanical jack driven by a hydraulic motor 78 via a worm gear 80 .
- the nested inner and outer members 82 , 84 of the jack 54 have a common threaded interface. Rotation of the inner member 82 in either direction causes the outer member 84 to reciprocate along the common central axis 86 .
- the top of each jack 54 is capped with a secondary articulated joint 90 consisting of a spherical surface 88 and a lateral slide plate 92 arranged back-to-back within a common housing 94 .
- These secondary articulated joints 90 provide compensation for radial adjustments caused by tilting the mast 15 , and their position below the articulated joint 24 protects the jacks 54 from side loads.
- changes in deployment angle may be made during pipe laying operations responsive to changing conditions. This is accomplished by actuating the screw jacks 54 , which are controlled from the operator's panel on the stationary table 30 .
- the spherical ball joint 90 which is held captive radially by the cylindrical housing 93 , is free to pivot and to reciprocate responsive to the changing angular orientation of the stinger base tube 76 .
- the base tube 76 is rigidly affixed to the stationary table 30 and, hence, moves in response to angular change in the orientation of the stationary table 30 .
- the stinger 20 is a welded steel structure attached to the bottom of the stationary table 30 on the same central axis as the mast 15 . It is flanged and bolted together in two sections; the base tube 76 and the extension 96 .
- the stinger extension 96 houses a series of hydraulically driven rollers 98 . In the particular embodiment illustrated, there are rollers 98 at six different locations 100 , with four rollers 98 per location. The rollers 98 secure the pipe string 12 and assure that it does not violate the predetermined minimum bend radius during pipe lay operations.
- the bore 102 of the stinger 20 and the stationary table 30 above are large enough to allow passage of a flexible joint or other package (not shown) for deployment or retrieval.
- Cameras and lights 104 for monitoring the pipe string 12 are deployed at the bottom of the stinger 20 .
- the hydraulically driven rollers 98 of the stinger 20 are hinged at the outer diameter of the stinger frame, i.e., the stinger extension 96 . This feature allows the rollers 98 to be folded up out of the way, thereby allowing the passage of large diameter packages that are sometimes integrated into the pipe string 12 during deployment.
- the stinger 20 features two top roller stabilizer stations 140 that stabilize the pipe string 12 as it emerges from the underneath the weld floor, which in the particular embodiment illustrated is the stationary table 30 .
- the rollers 98 of the riser stabilizer stations 140 keep the top pipe joint 17 of the pipe string 12 aligned with the weld position to help prevent the introduction of bending moments at the weld site.
- the subsequent curvature of the pipe string 12 is controlled by the bottom four riser curvature stations 142 , which permit gradually wider excursions from the installation center line as described below.
- the stinger 20 is disclosed herein in conjunction with the mast 15 , this aspect of the present invention is not so limited.
- the stinger 20 may be used in virtually all subsea pipe laying activities to control critical bending stress in the pipe string 12 both as to the weld floor above and in the deployed pipe string 12 below.
- the stinger 20 may also be employed for a large range of pipe diameters without the need for reconfiguration or removal.
- the pipe erector 25 shown best in FIG. 16A, is fastened to the stationary table 30 by a hinge 27 at the base of the mast 15 as shown in FIG. 6 and is actuated by a cable 106 and hydraulic winch (not shown).
- the pipe erector 25 is shown in a horizontal position 108 , an intermediate position 110 , and a vertical position 112 . It receives the prepped pipe joints 17 one at a time as they are off-loaded from the pipe rack (not shown) by the jib crane 112 while the pipe erector 25 is in the horizontal position 108 .
- Bi-axial rollers (not shown) are incorporated into the erector 25 to allow orientation of the pipe ends and match marks as required. Hydraulically operated clamps 114 secure the pipe joint 17 to the pipe erector 25 as it lifts them through the intermediate position 110 to the vertical position 112 over the pipe string 12 for insertion into the pipe alignment system 46 prior to make-up with the pipe string 12 .
- the pipe alignment system 46 includes two centralizing units 48 , best shown in FIG. 17, mounted in the mast 15 of the mast 15 .
- Each centralizing unit 48 consists of four hydraulic cylinders 116 , each driving a pinned cam 118 with a flat face 120 .
- the flat face 120 on each cam 118 interfaces with the pipe joint 17 and applies the force of the corresponding cylinder thereto (multiplied by the eccentric geometry of the pinned cam 118 ).
- the centralizing units 48 are mounted in the mast 15 located at two different positions along the length of the pipe joint 17 .
- the hydraulic cylinders 116 are manually activated by an operator (standing at the stationary table 30 ) in order to visually align the weld preps 40 of the pipe joint 17 for welding.
- the lower centralizing unit 48 aligns the pipe joint 17 radially and the upper centralizing unit 48 , nominally located at the middle of the pipe joint 17 , is used to correct angular mismatch of the weld preparations 40 .
- the pipe erector system is therefore capable of automatically feeding pipe into the mast 15 .
- the erector 25 assures that the pipe joint 17 is aligned with the centerline of the mast 15 regardless of the angle of the mast 15 relative to the deck 34 of the vessel 16 . This is principally accomplished by centering the erector 25 on the mast 15 and hinging it at the base thereof. Since the mast 15 and the erector 25 are attached to the same surface, i.e., the stationary table 30 , correct angular alignment of the erector 25 is assured.
- the apparatus 10 comprises the mast 15 , the stinger 20 affixed to the stationary table 30 to articulate therewith, and the pipe erector 25 operatively connected to the stationary table 30 and the mast 15 .
- the mast 15 includes the main skid frame 22 ; a stationary table 30 , the stationary table 30 defining with the main skid frame 22 the articulated joint 24 ; the mast 15 rigidly affixed to and extending upwardly from the stationary table 30 ; and the traveling table 26 , which provides freedom of movement in at least one direction, that being along the central axis of the mast 15 .
- the articulated tower 10 provides freedom of movement in four degrees, including rotation about three primary axes and translation along a centerline of the mast 15 .
- the tower system 10 may be assembled at the site where the pipe string 12 is to be deployed.
- the main skid frame 22 , mast 15 components, stinger 20 components, and all other parts are shipped as separate pieces.
- they are reassembled and erected for operation.
- all components and support items are laid out on the deck 34 of the vessel 16 in the order of assembly and use.
- the main skid assembly including the main skid frame 22 , stationary table 30 , jacks 54 , and articulated joint 24 are landed in the position for laying the flowlines.
- the stinger 20 is keelhauled to a position below the main skid 22 and bolted to the bottom of the bearing swivel into 54 , which is rigidly attached to the bottom of the stationary table 30 as discussed above.
- the stationary table 30 is rotated to the full stop position to the rear to allow a stop shoulder (not shown) to be engaged in the articulated section against the frame.
- Mast support jigs (also not shown) are then attached to the top of the main skid 22 and the pieces of the mast 15 are assembled to the stationary table 30 on the jigs.
- the lower section 122 of the mast 15 will be in three pieces—two sides, a cylinder, and a center (or back) section.
- the middle section 124 of the mast 15 will include three similar pieces, without the cylinders.
- the top section 126 of the mast 15 will be installed as a single piece.
- a mast erector system, or bootstrap mechanism, 128 may be used.
- the assembly of a tower system, such as the mast 15 is frequently hampered by the lack of a crane tall enough to lift and move the tower on board the vessel.
- the boot strap mechanism 128 addresses this problem.
- the boot strap mechanism 128 includes a steel radius frame 130 with multiple chain guides 131 is, in this particular embodiment, temporarily installed on the stationary table 30 .
- a heavy duty link chain 132 shown in FIG. 20, running over the radius frame 130 is attached to the traveling table 26 and, via the radius frame 130 , to the stationary table 30 .
- the mast 15 is then erected using the boot strap mechanism 128 .
- Pressurization of the two main mast cylinders 28 actuates the traveling table 26 which, in turn, tensions the chains 132 and pulls the assembled mast 15 erect (the mast 15 rotates around the hinge line at the front legs).
- the back legs of the mast 15 and the base of the cylinders 28 are then bolted in place on the stationary table 30 .
- the jacks are then used to bring the mast 15 to the vertical position.
- the pipe erector 25 is installed on its hinge line (not shown) on the stationary table 30 in front of the mast 15 .
- the erector 25 is then connected to its actuation cable 106 and winch (not shown) and the hold back winch (also not shown). All peripheral facilities such as the pipe rack (not shown) and skids (not shown) containing the coating equipment and QC/QA equipment are positioned. All electrical, pneumatic and hydraulic hook-ups are completed and tested.
- prepped pipe joints 17 are arranged on the pipe rack (not shown) in the order of installation.
- a temporary double collar 42 is installed around the J-Lay collar 38 on each pipe joint 17 either prior to placement in the pipe erector 25 or while in the erector 25 , at the operator's discretion.
- the pipe joint 17 is placed in the cradle with a jib crane 112 using hydraulic tongs 113 , shown in FIGS. 16 B-C, designed to handle the pipe joints 17 .
- the pipe joints 17 are positioned by the jib crane 112 within the clamps 114 of the erector 25 and between the position markings (not shown) on the erector 25 .
- the erector 25 is activated and rotates upward towards the mast 15 to the vertical position 112 , at whatever angle the mast 15 is presently positioned.
- the upper end with the double collar 42 is gripped in the split clamp 44 on the traveling table 26 and the lower length is gripped by two the pipe centralizing units 48 .
- the split clamp 44 grips the upper landing surface 134 of the double collar 42 ; the lower landing surface 136 being reserved for use when the pipe joint 17 is lowered to the second position at the stationary table 30 .
- the erector clamps 114 are then released and the erector 25 is retracted back down to the horizontal position 108 beside the pipe rack.
- the hydraulic cylinders 118 of the centralizing units 48 are then manually activated by an operator standing at the stationary table 30 to align the pipe joint 17 weld preps for welding.
- the lower centralizing unit 48 aligns the pipe joint 17 radially and the upper centralizing unit 48 , at the middle of the pipe joint 17 , corrects any angular mismatch of the weld preparations.
- the pipe joint 17 is then welded onto the pipe string 12 and the weld inspected in accord with techniques well known in the art.
- the mast cylinders 28 lift the pipe string 12 slightly so that the double collar 42 on the lower pipe joint 17 (at the stationary table 30 ) can be removed. Once the double collar 42 is removed from the lower pipe joint 17 , the traveling table 26 is lowered and the double collar 42 on the top pipe joint 17 is seated at its bottom landing surface 136 in the nested bushings 60 , 62 and split bowl 58 installed in the riser hole 52 .
- FIGS. 22 - 24 illustrate several operations associated with a riser 145 . More particularly, FIG. 22 illustrates transfer of the riser 145 , FIG. 23 illustrates termination of the riser 145 , and FIG. 24 illustrates abandonment of the riser 145 .
- FIG. 22 after completing the riser 145 and a flexible joint 147 is integrated into the riser string, a fishplate 148 is attached to the top of the flexible joint 147 .
- An overhead crane 150 on the lay vessel 16 is then connected via cable and shackle (not shown) through the mast 15 to the fishplate 148 /flexible joint 147 termination.
- the weight of the riser 145 is then assumed by the crane 150 .
- FIG. 25 illustrates the set-up of the flexible joint 147 for these operations in greater detail.
- the crane 150 lowers the end of the riser 145 to a location below the stinger 20 where a line 152 from the receiving vessel 155 can be attached to the fishplate 148 .
- the riser 145 is lowered to a depth which will allow it to be safely traversed under the lay vessel 16 .
- the riser 145 is simultaneously reeled in by the recipient vessel 155 as shown in FIG. 23.
- the riser string is pulled upward to a point where the flexible joint 147 is above the receptacle (not shown) on the recipient vessel 155 .
- the flexible joint 147 is then lowered into the receptacle until it is fully seated.
- a pipe string 158 of smaller dimensions (composed of standard threaded drill pipe) will be attached to the riser 145 via a special swiveling head 160 welded to the end of the riser 145 .
- the pipe string 158 is deployed through the mast 15 as was the pipe string 12 in the manner described above.
- the drill pipe string 158 is played out so as to gradually lower the riser 145 to the seabed. Once the riser 145 is laid on the seabed, the pipe string 158 is disconnected and recovered.
- the riser 145 may subsequently be recovered, as well. Recovery of the riser 145 requires locating the end of the riser 145 via sonar and a remotely operated vehicle (“ROV”) mounted TV 162 , shown in FIG. 22 and reattaching the pipe string 158 . The pipe string 158 is then retrieved, pulling the end of the riser 145 up from the seabed into the mast 15 .
- ROV remotely operated vehicle
- the tower system 10 provides the capability to lay both a welded pipeline and a steel catenary riser (“SCR”) off the side of a vessel 16 of opportunity.
- the tower system 10 incorporates an articulating joint in the mast 15 system 10 itself, interposes a swiveling interface between the pipe string 12 and the mast 15 , and permits the mast 15 to articulate in response to varying current, wind, and tidal forces encountered during pipe laying operations.
- the mast 15 system 10 consequently permits rotation of the stationary table 30 and, hence, the mast 15 , stinger 20 , and erector 25 , about all three primary axes and is capable of (1) aligning itself both angularly and azimuthally with the pipe string 12 as it is deployed in order to attack the pipeline path, wind, and current at the most favorable conditions; (2) maintaining riser tension within a specified envelope: (3) permitting the laying vessel 16 to rotate about the pipe string 12 as weather and operational considerations dictate; and (4) allowing precise control of the riser lay envelope.
Abstract
Description
- This application is a continuation of
provisional application 60/083,964 filed May 1, 1998, incorporated herein by reference. - 1. Field of the Invention
- This invention relates generally to laying underwater pipe and, more particularly, to installing underwater pipelines on the seabed and/or connecting the same to floating terminals at the surface.
- 2. Description of the Related Art
- Floating production facilities require risers to provide fluid conduits between subsea equipment and the surface facility (or platform). The floating structure responds dynamically to the forces of the environment to which it is exposed. This means that the conduit connecting the structure and subsea equipment must be connected in a manner that accommodates relative motions. The conduit, of course, requires top and bottom interfaces to establish functional connections. At one time, flexible pipe was considered as the only feasible means of providing flowline connections from equipment on the sea bed to a floating production vessel. However, flexible pipe is very expensive, much more so than standard steel pipe. As a result, the use of steel pipe in deep water risers was developed as an alternative means of achieving the sea bed connection. This presented the practical problem of how to deploy a steel pipe string vertically from a starting point on the ocean floor to a hand-off and terminus at a floating production system; thereby leading to the development and use of J-Lay towers for this purpose.
- The assembly and deployment of subsea steel pipelines from floating vessels usually employs a J-Lay tower, especially in deep water. The J-Lay tower provides a vertical, or nearly vertical, platform for welding lengths of pipe into a pipe string. The J-Lay tower tension feeds the pipe string from an anchor on the seabed. Prepared lengths of pipe, known as “pipe joints,” are fed one at a time into the J-Lay tower and welded together to form the pipe string. The angle at which the assembled pipe string leaves the vessel to enter the water is controlled by the angle and azimuth of the tower mast and “stinger,” which is an inverted structure pointing down into the water underneath the J-Lay tower, relative to the pipe string being deployed.
- Previous J-Lay tower installations have employed vertical masts rigidly installed on pipe lay vessels. These installations utilized pipe tensioners integrated into the mast for control of the pipe string during deployment and hand-off operations. J-Lay towers have been manufactured with the ability to lower pipe straight down, or with an angle provided by a cone shaped stinger. Other towers have been installed at a fixed angle to allow a departure from the base at an approximation of the best average departure direction. Any angular departure of the pipeline from purely vertical in the first case or from the preset pipe angle in the second case would cause the pipeline to be bent around the stinger. Also, most current stingers employ a static, fixed structure that imposes either cylindrical or conical shaped excursion boundaries on the emerging pipe string.
- Rigidly installed, vertical towers engender a number of problems caused by an inability to respond in real time to the dynamic forces encountered during pipe laying operations. For instance, welding and assembly operations are performed at the working floor on pipe with a substantial imposed moment. Other deficiencies include the fact that they do not allow: 1) control of the bending stress and tension within the pipe string as it is deployed in an arc to the sea bed; 2) the laying vessel to weather vane or rotate about the pipe and thereby prevent torsional wind-up of the pipe string; and 3) precise control of the pipe lay envelope. Further, current J-Lay tower designs omit any means for precise and accurate alignment of the pipe string and new pipe joints during the welding process. Current methods for deploying pipe also encounter problems not directly associated with the use of rigidly installed, vertical towers. None efficiently and/or automatically feed pipe joints into the tower or align the pipe joints with the tower center line to facilitate assembling the
pipe string 12. - Current stinger designs have a problem in that the internal geometry of the stinger is usually fixed at the diameter of the pipe string being deployed. In order to allow the passage of large diameter packages integrated into the pipe string, the stinger must be dismantled or removed from around the hanging pipe string. Additionally, such stingers only act as guide conduits for the pipe and do not stabilize, i.e., control the alignment of, the pipe as it emerges from the weld floor.
- The present invention is directed to overcoming, or at least reducing the effects of, one or more of the problems set forth above.
- An apparatus for deploying pipe string is disclosed. The apparatus comprises a mast; an articulated stationary table to which the mast is affixed; a stinger affixed to the stationary table to articulate with the mast; and a pipe erector operatively connected to the mast.
- Other objects and advantages of the invention will become apparent upon reading the following detailed description and upon reference to the drawings in which:
- FIG. 1 illustrates one embodiment of an apparatus for assembling and deploying pipe string underwater, the apparatus constructed and operated in accordance with the present invention;
- FIGS.2-5 illustrate an individual pipe joint and parts used to prepare the pipe joint to be incorporated into a pipe string as may be deployed by the embodiment of FIG. 1;
- FIG. 6 is a conceptualized perspective view of part of the
tower system 10 of the embodiment in FIG. 1; - FIG. 7 is a partial cross-sectional, side view of part of the
tower system 10 of the embodiment in FIG. 1; - FIG. 8 is a partial cross-sectional view of a part of the embodiment of FIG. 1;
- FIGS.9-12 illustrate, in various views, the clamping system of the embodiment of FIG. 1;
- FIGS.13A-13B illustrate the swivel bearing of the embodiment in FIG. 1;
- FIG. 14 is a partial cross-sectional, side view of a screw jack as employed in the articulating joint of FIG. 1;
- FIG. 15 illustrates the stinger of the embodiment of FIG. 1;
- FIGS.16A-C illustrate the erector system of the embodiment of FIG. 1;
- FIGS.17A-B illustrate the weld alignment and placement system in the embodiment of FIG. 1;
- FIGS.18-20 illustrate a bootstrap mechanism as may be used in some alternative embodiments to erect the articulated tower in FIG. 1;
- FIG. 21 illustrates how the stinger of FIG. 1 controls the deployment of the pipe string; and
- FIGS.22-25 illustrate how the invention may be employed in several pipe laying operations.
- While the invention is susceptible to various modifications and alternative forms, specific embodiments thereof have been shown by way of example in the drawings and are herein described in detail. It should be understood, however, that the description herein of specific embodiments is not intended to limit the invention to the particular forms disclosed, but on the contrary, the intention is to cover all modifications, equivalents, and alternatives falling within the spirit and scope of the invention as defined by the appended claims.
- Illustrative embodiments of the invention are described below. In the interest of clarity, not all features of an actual implementation are described in this specification. It will of course be appreciated that in the development of any such actual embodiment, numerous implementation-specific decisions must be made to achieve the developers' specific goals, such as compliance with system-related and business-related constraints, which will vary from one implementation to another. Moreover, it will be appreciated that such a development effort, even if complex and time-consuming, would be a routine undertaking for those of ordinary skill in the art having the benefit of this disclosure.
- FIG. 1 illustrates an
apparatus 10 as may be used in various embodiments to deploy apipe string 12 beneath the surface of a body ofwater 14 from avessel 16. Note that, although this disclosure is frequently in terms of subsea operations, it is to be understood that the invention is not limited to oceanic or maritime applications. The invention may be employed with any large body of water including, but not limited to, oceans, seas, gulfs, and lakes. Theapparatus 10 is articulated as set forth in more detail below and may be used to deploy thepipe string 12 for a variety of purposes. Exemplary purposes include installing pipelines on the seabed (not shown) and deploying risers between a pipe string 12 (also not shown) on the seabed and thevessel 16. As those in the art will recognize, the term “pipe string 12” refers to a plurality of pipe joints 17, or pieces of pipe, affixed together and, thus, may generically be used to refer to pipelines and risers. - The particular embodiment of the
apparatus 10 illustrated in FIG. 1 is atower system 10 and generally comprises anmast 15, astinger 20, and apipe erector 25, all of which are articulated. Generally, a prepared pipe joint 17 is loaded onto apipe erector 25, which then loads it into themast 15. Once loaded, the pipe joint 17 is then affixed to the end of thepipe string 12, whereupon it becomes a constituent part of thepipe string 12. Thepipe string 12 can then be further deployed through thestinger 20 and themast 15. The pipe joints 17,apparatus 10, and the method of using theapparatus 10 just now generally described are set forth in greater detail below. - The
pipe string 12 comprises a plurality of pipe joints 17. Each pipe joint 17 comprises anindividual pipe length 36, shown in FIG. 2, which will be assembled (via welding) into the deployedpipe string 12. Eachpipe length 36 is prepared for assembly by machining weld prep surfaces 35 at each end of thepipe length 36. A J-Lay collar 38, such as that shown in cross-section in FIG. 3, is welded to theupper end 40 of eachpipe length 36. The pipe joints 17 are then painted with a corrosion protection system in a manner commonly known in the art. Adouble collar 42, shown in FIGS. 4-5, is then affixed to the pipe joint 17 around the J-lay collar 38 as shown in FIG. 8. Thedouble collar 42 is a temporary split collar with multiple landing surfaces at differing diameters. It is used to secure the individual pipe joints 17 and thepipe string 12 at various stages in the assembly and deployment sequence as set forth below. - Turning now to FIG. 6 and to FIG. 7, a part of one particular embodiment for the
mast 15 of FIG. 1 is shown. The embodiment includes amast 15 joined to amain skid frame 22 through an articulated joint 24. Thetower mast 15 includes a traveling table 26, a pair ofhydraulic cylinders 28, and a stationary table 30. Themast 15 and stationary table 30 also rest upon and are connected to a plurality ofscrewjacks 32. - The
mast 15 is a three-part, welded,steel truss structure 18 mounted to thetop surface 21 of the stationary table 30. It supports two very large, hydraulic lifting cylinders 28 (with 500,000 lbs. lift capacity each), the traveling table 26, thepipe clamping system 44 shown in FIGS. 10-12, and theweld alignment system 46 shown in FIGS. 17A-17B. Returning to FIG. 2 and to FIG. 3, thehydraulic cylinders 28 provide the vertical lift and tensioning capability on thepipe string 12. Multiple wire ropes (not shown) tied to the base of thecylinders 28 at the stationary table 30 run over sheaves (also not shown) mounted at the top of thehydraulic cylinders 28 to the traveling table 26. This arrangement effectively multiplies the cylinder stroke and doubles the vertical movement of the traveling table 26. Themast 15 acts as the guide mechanism for vertical movement of the traveling table 26. It also mounts the two centralizingunits 48 discussed below that center the pipe joint 17 and straighten it prior to welding at the lower end as discussed further below. - The
main skid frame 22 is a welded plate structure designed to support theentire tower system 10 via the stationary table 30 and all associated equipment. It provides the interface with thedeck 34 of thevessel 16 and distributes the system loads over a large area of thedeck 34. - Referring now to FIG. 7 and to FIG. 8, the stationary table30 is a welded steel plate structure with a 62.0″
diameter hole 52 at its center for riser deployment. The stationary table 30 provides a common rigid interface for themast 15,stinger 20, anderector 25. It is supported by threescrew jacks 54 and agimbaled bearing 50 which are installed on themain skid frame 22. A 62.0″bowl 58 is permanently installed in theriser hole 52 of the stationary table 30. A 62.0″ splitbushing 60 is nested inside thebowl 58. A 26.0″bushing 62 is, in turn, installed in the 62.0″bushing 60. The 26.0″bushing 62 supports the pipe string 12 (via the temporarydouble collar 48 on the last pipe joint 17 in the pipe string 12) while the next pipe joint 17 is being welded in place. - Turning now to FIGS.9-12, the traveling table 26 is a welded steel plate structure powered by the twin lifting cylinders 28 (shown in FIG. 2). It receives the top ends of the pipe joints 17 as they are lifted from the horizontal by the
erector 25. Asplit clamp 44 installed on the traveling table 26 secures the end of the pipe joint 17 (around a temporary double collar 42) and holds it in place while the pipe joint 17 is aligned by themast 15 centralizingunits 48 in preparation for welding at the lower end. The traveling table 26 supports the swivel bearing 65, shown in FIGS. 13A-13B, when in use, the swivel bearing 65 being inserted between thedouble collar 42 and thesplit clamp 44. Note that FIG. 13B is a split view drawing, presenting View A wherein the swivel bearing 65 is inserted into the traveling table 26 and View B wherein the traveling table 26 is shown without theswivel bearing 65. - Referring now to FIG. 13A, the swivel bearing65 is a mechanical bearing consisting of a turning
body 66 and anon-turning body 68 with multiple, compression loaded, zylan coated, shear rings 70 interposed between them. The turningbody 66 interfaces and supports thedouble collar 42; thenon-turning body 68 interfaces with thesplit clamp 44 on the floor of the traveling table 26. The shear rings 70 shear relative to one another in order to accommodate the differential motion between the turningbody 66 and thenon-turning body 68. - When needed, the swivel bearing65 is inserted at the traveling table 26 as shown in FIG. 13B and carries the weight of the
pipe string 12 duringvessel 16 turning operations and heading adjustments. The bearingswivel 65 provides a rotating interface between thepipe string 12 and themast 15. The bearingswivel 65 also has numerous applications other than that disclosed above. For instance, the bearingswivel 65 might be used in many other applications requiring torsional isolation within a system without interrupting load path continuity and a high load capacity. - Referring once again to FIG. 7, the stationary table30 and the
main skid frame 22 define the articulated joint 24 employing a spherical bearing 72 and a plurality of screw jacks 54. The interface between the stationary table 30 and themain skid frame 22 consists of the 62.0″ spherical metal bearing 72 that is free to move up and down within a cylindrical bore 74. Thus, the articulated joint 24 in this embodiment is a ball joint. The spherical bearing 72 encircles (and is welded to) thestinger base tube 76, which is, in turn, bolted to the stationary table 30. This articulated interface reacts all radial loads within the system. Threescrew jacks 54 are arrayed at 120° intervals about the articulated joint 24 and tilt themast 15 up to 15° off vertical on any azimuth. The screw jacks 54 react all vertical loads in the system. - FIG. 14 illustrates a representative one of the screw jacks54. The
screw jack 54 is a mechanical jack driven by ahydraulic motor 78 via aworm gear 80. The nested inner andouter members jack 54 have a common threaded interface. Rotation of theinner member 82 in either direction causes theouter member 84 to reciprocate along the commoncentral axis 86. The top of eachjack 54 is capped with a secondary articulated joint 90 consisting of aspherical surface 88 and alateral slide plate 92 arranged back-to-back within acommon housing 94. These secondary articulatedjoints 90 provide compensation for radial adjustments caused by tilting themast 15, and their position below the articulated joint 24 protects thejacks 54 from side loads. - Thus, changes in deployment angle may be made during pipe laying operations responsive to changing conditions. This is accomplished by actuating the screw jacks54, which are controlled from the operator's panel on the stationary table 30. The spherical ball joint 90, which is held captive radially by the
cylindrical housing 93, is free to pivot and to reciprocate responsive to the changing angular orientation of thestinger base tube 76. Conversely, thebase tube 76, as discussed below, is rigidly affixed to the stationary table 30 and, hence, moves in response to angular change in the orientation of the stationary table 30. - The
stinger 20, as illustrated in FIG. 15, is a welded steel structure attached to the bottom of the stationary table 30 on the same central axis as themast 15. It is flanged and bolted together in two sections; thebase tube 76 and theextension 96. Thestinger extension 96 houses a series of hydraulically drivenrollers 98. In the particular embodiment illustrated, there arerollers 98 at sixdifferent locations 100, with fourrollers 98 per location. Therollers 98 secure thepipe string 12 and assure that it does not violate the predetermined minimum bend radius during pipe lay operations. Thebore 102 of thestinger 20 and the stationary table 30 above are large enough to allow passage of a flexible joint or other package (not shown) for deployment or retrieval. Cameras andlights 104 for monitoring thepipe string 12 are deployed at the bottom of thestinger 20. The hydraulically drivenrollers 98 of thestinger 20 are hinged at the outer diameter of the stinger frame, i.e., thestinger extension 96. This feature allows therollers 98 to be folded up out of the way, thereby allowing the passage of large diameter packages that are sometimes integrated into thepipe string 12 during deployment. - Also, the
stinger 20 features two toproller stabilizer stations 140 that stabilize thepipe string 12 as it emerges from the underneath the weld floor, which in the particular embodiment illustrated is the stationary table 30. Therollers 98 of theriser stabilizer stations 140 keep the top pipe joint 17 of thepipe string 12 aligned with the weld position to help prevent the introduction of bending moments at the weld site. The subsequent curvature of thepipe string 12 is controlled by the bottom fourriser curvature stations 142, which permit gradually wider excursions from the installation center line as described below. - Although the
stinger 20 is disclosed herein in conjunction with themast 15, this aspect of the present invention is not so limited. Thestinger 20 may be used in virtually all subsea pipe laying activities to control critical bending stress in thepipe string 12 both as to the weld floor above and in the deployedpipe string 12 below. Thestinger 20 may also be employed for a large range of pipe diameters without the need for reconfiguration or removal. - The
pipe erector 25, shown best in FIG. 16A, is fastened to the stationary table 30 by ahinge 27 at the base of themast 15 as shown in FIG. 6 and is actuated by acable 106 and hydraulic winch (not shown). Returning to FIG. 16A, thepipe erector 25 is shown in ahorizontal position 108, anintermediate position 110, and avertical position 112. It receives the preppedpipe joints 17 one at a time as they are off-loaded from the pipe rack (not shown) by thejib crane 112 while thepipe erector 25 is in thehorizontal position 108. Bi-axial rollers (not shown) are incorporated into theerector 25 to allow orientation of the pipe ends and match marks as required. Hydraulically operatedclamps 114 secure the pipe joint 17 to thepipe erector 25 as it lifts them through theintermediate position 110 to thevertical position 112 over thepipe string 12 for insertion into thepipe alignment system 46 prior to make-up with thepipe string 12. - The
pipe alignment system 46 includes two centralizingunits 48, best shown in FIG. 17, mounted in themast 15 of themast 15. Each centralizingunit 48 consists of fourhydraulic cylinders 116, each driving a pinnedcam 118 with aflat face 120. Theflat face 120 on eachcam 118 interfaces with the pipe joint 17 and applies the force of the corresponding cylinder thereto (multiplied by the eccentric geometry of the pinned cam 118). The centralizingunits 48 are mounted in themast 15 located at two different positions along the length of the pipe joint 17. Thehydraulic cylinders 116 are manually activated by an operator (standing at the stationary table 30) in order to visually align the weld preps 40 of the pipe joint 17 for welding. The lower centralizingunit 48 aligns the pipe joint 17 radially and the upper centralizingunit 48, nominally located at the middle of the pipe joint 17, is used to correct angular mismatch of theweld preparations 40. - The pipe erector system is therefore capable of automatically feeding pipe into the
mast 15. Theerector 25 assures that the pipe joint 17 is aligned with the centerline of themast 15 regardless of the angle of themast 15 relative to thedeck 34 of thevessel 16. This is principally accomplished by centering theerector 25 on themast 15 and hinging it at the base thereof. Since themast 15 and theerector 25 are attached to the same surface, i.e., the stationary table 30, correct angular alignment of theerector 25 is assured. - Thus, in the particular embodiment illustrated, the
apparatus 10 comprises themast 15, thestinger 20 affixed to the stationary table 30 to articulate therewith, and thepipe erector 25 operatively connected to the stationary table 30 and themast 15. Themast 15 includes themain skid frame 22; a stationary table 30, the stationary table 30 defining with themain skid frame 22 the articulated joint 24; themast 15 rigidly affixed to and extending upwardly from the stationary table 30; and the traveling table 26, which provides freedom of movement in at least one direction, that being along the central axis of themast 15. The articulatedtower 10 provides freedom of movement in four degrees, including rotation about three primary axes and translation along a centerline of themast 15. - The
tower system 10 may be assembled at the site where thepipe string 12 is to be deployed. Themain skid frame 22,mast 15 components,stinger 20 components, and all other parts are shipped as separate pieces. At the installation site on thevessel 16 of choice, they are reassembled and erected for operation. First, all components and support items (power skid, welding pallet, etc.) are laid out on thedeck 34 of thevessel 16 in the order of assembly and use. Next, the main skid assembly including themain skid frame 22, stationary table 30, jacks 54, and articulated joint 24 are landed in the position for laying the flowlines. Thestinger 20 is keelhauled to a position below themain skid 22 and bolted to the bottom of the bearing swivel into 54, which is rigidly attached to the bottom of the stationary table 30 as discussed above. The stationary table 30 is rotated to the full stop position to the rear to allow a stop shoulder (not shown) to be engaged in the articulated section against the frame. - Mast support jigs (also not shown) are then attached to the top of the
main skid 22 and the pieces of themast 15 are assembled to the stationary table 30 on the jigs. Returning to FIG. 1, thelower section 122 of themast 15 will be in three pieces—two sides, a cylinder, and a center (or back) section. Themiddle section 124 of themast 15 will include three similar pieces, without the cylinders. Thetop section 126 of themast 15 will be installed as a single piece. - In order to facilitate erection and take-down of the
mast 15, a mast erector system, or bootstrap mechanism, 128, best shown in FIGS. 18-20, may be used. The assembly of a tower system, such as themast 15, is frequently hampered by the lack of a crane tall enough to lift and move the tower on board the vessel. Theboot strap mechanism 128 addresses this problem. Theboot strap mechanism 128 includes asteel radius frame 130 with multiple chain guides 131 is, in this particular embodiment, temporarily installed on the stationary table 30. A heavyduty link chain 132, shown in FIG. 20, running over theradius frame 130 is attached to the traveling table 26 and, via theradius frame 130, to the stationary table 30. - The
mast 15 is then erected using theboot strap mechanism 128. Pressurization of the twomain mast cylinders 28 actuates the traveling table 26 which, in turn, tensions thechains 132 and pulls the assembledmast 15 erect (themast 15 rotates around the hinge line at the front legs). The back legs of themast 15 and the base of thecylinders 28 are then bolted in place on the stationary table 30. The jacks are then used to bring themast 15 to the vertical position. - Next, the
pipe erector 25 is installed on its hinge line (not shown) on the stationary table 30 in front of themast 15. Theerector 25 is then connected to itsactuation cable 106 and winch (not shown) and the hold back winch (also not shown). All peripheral facilities such as the pipe rack (not shown) and skids (not shown) containing the coating equipment and QC/QA equipment are positioned. All electrical, pneumatic and hydraulic hook-ups are completed and tested. - Once assembly is complete, prepped
pipe joints 17 are arranged on the pipe rack (not shown) in the order of installation. A temporarydouble collar 42 is installed around the J-Lay collar 38 on each pipe joint 17 either prior to placement in thepipe erector 25 or while in theerector 25, at the operator's discretion. - Next, the pipe joint17 is placed in the cradle with a
jib crane 112 usinghydraulic tongs 113, shown in FIGS. 16B-C, designed to handle the pipe joints 17. The pipe joints 17 are positioned by thejib crane 112 within theclamps 114 of theerector 25 and between the position markings (not shown) on theerector 25. Once the pipe joint 17 is properly positioned and secured in theerector 25, theerector 25 is activated and rotates upward towards themast 15 to thevertical position 112, at whatever angle themast 15 is presently positioned. - As the top of the pipe joint17 arrives at the
vertical position 110, the upper end with thedouble collar 42 is gripped in thesplit clamp 44 on the traveling table 26 and the lower length is gripped by two thepipe centralizing units 48. The split clamp 44 grips theupper landing surface 134 of thedouble collar 42; thelower landing surface 136 being reserved for use when the pipe joint 17 is lowered to the second position at the stationary table 30. The erector clamps 114 are then released and theerector 25 is retracted back down to thehorizontal position 108 beside the pipe rack. - The
hydraulic cylinders 118 of the centralizingunits 48 are then manually activated by an operator standing at the stationary table 30 to align the pipe joint 17 weld preps for welding. The lower centralizingunit 48 aligns the pipe joint 17 radially and the upper centralizingunit 48, at the middle of the pipe joint 17, corrects any angular mismatch of the weld preparations. The pipe joint 17 is then welded onto thepipe string 12 and the weld inspected in accord with techniques well known in the art. - After welding and inspection, the
mast cylinders 28 lift thepipe string 12 slightly so that thedouble collar 42 on the lower pipe joint 17 (at the stationary table 30) can be removed. Once thedouble collar 42 is removed from the lower pipe joint 17, the traveling table 26 is lowered and thedouble collar 42 on the top pipe joint 17 is seated at itsbottom landing surface 136 in the nestedbushings bowl 58 installed in theriser hole 52. - As the
pipe string 12 descends below the stationary table 30, it passes throughbase tube 76 and theextension 96 of thestinger 20, theextension 96 being swivel mounted via theswivel bearing 65. Thestinger 20, as earlier mentioned, is equipped with sixstages 100 of hydraulically actuatedrollers 98. The top twosets 140 ofrollers 98 keep thepipe string 12 aligned with the centerline of the pipe joint 17 currently being installed. The subsequent curvature of the descendingpipe string 12 is controlled by the bottom foursets 142 ofrollers 98, which permit gradually wider excursions from the installation center line as shown in FIG. 21. - These steps may be repeated to lay a pipeline and establish a riser from the
pipe string 12. FIGS. 22-24 illustrate several operations associated with ariser 145. More particularly, FIG. 22 illustrates transfer of theriser 145, FIG. 23 illustrates termination of theriser 145, and FIG. 24 illustrates abandonment of theriser 145. - Turning now to FIG. 22, after completing the
riser 145 and a flexible joint 147 is integrated into the riser string, afishplate 148 is attached to the top of the flexible joint 147. Anoverhead crane 150 on thelay vessel 16 is then connected via cable and shackle (not shown) through themast 15 to thefishplate 148/flexible joint 147 termination. The weight of theriser 145 is then assumed by thecrane 150. FIG. 25 illustrates the set-up of the flexible joint 147 for these operations in greater detail. - Returning to FIG. 22, the
crane 150 lowers the end of theriser 145 to a location below thestinger 20 where aline 152 from the receivingvessel 155 can be attached to thefishplate 148. After attachment of the pull-inline 152 from the receivingvessel 155, theriser 145 is lowered to a depth which will allow it to be safely traversed under thelay vessel 16. While the line from thecrane 150 is played out, theriser 145 is simultaneously reeled in by therecipient vessel 155 as shown in FIG. 23. After clearing thelay vessel 16, the riser string is pulled upward to a point where the flexible joint 147 is above the receptacle (not shown) on therecipient vessel 155. The flexible joint 147 is then lowered into the receptacle until it is fully seated. - If the need for temporary riser abandonment occurs, then a
pipe string 158 of smaller dimensions (composed of standard threaded drill pipe) will be attached to theriser 145 via aspecial swiveling head 160 welded to the end of theriser 145. Thepipe string 158 is deployed through themast 15 as was thepipe string 12 in the manner described above. Thedrill pipe string 158 is played out so as to gradually lower theriser 145 to the seabed. Once theriser 145 is laid on the seabed, thepipe string 158 is disconnected and recovered. - The
riser 145 may subsequently be recovered, as well. Recovery of theriser 145 requires locating the end of theriser 145 via sonar and a remotely operated vehicle (“ROV”) mountedTV 162, shown in FIG. 22 and reattaching thepipe string 158. Thepipe string 158 is then retrieved, pulling the end of theriser 145 up from the seabed into themast 15. - Thus, in the particular embodiment illustrated, the
tower system 10 provides the capability to lay both a welded pipeline and a steel catenary riser (“SCR”) off the side of avessel 16 of opportunity. To this end, thetower system 10 incorporates an articulating joint in themast 15system 10 itself, interposes a swiveling interface between thepipe string 12 and themast 15, and permits themast 15 to articulate in response to varying current, wind, and tidal forces encountered during pipe laying operations. Themast 15system 10 consequently permits rotation of the stationary table 30 and, hence, themast 15,stinger 20, anderector 25, about all three primary axes and is capable of (1) aligning itself both angularly and azimuthally with thepipe string 12 as it is deployed in order to attack the pipeline path, wind, and current at the most favorable conditions; (2) maintaining riser tension within a specified envelope: (3) permitting the layingvessel 16 to rotate about thepipe string 12 as weather and operational considerations dictate; and (4) allowing precise control of the riser lay envelope. - The particular embodiments disclosed above are illustrative only, as the invention may be modified and practiced in different but equivalent manners apparent to those skilled in the art having the benefit of the teachings herein. Furthermore, no limitations are intended to the details of construction or design herein shown, other than as described in the claims below. It is therefore evident that the particular embodiments disclosed above may be altered or modified and all such variations are considered within the scope and spirit of the invention. Accordingly, the protection sought herein is as set forth in the claims below.
Claims (36)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US09/846,014 US6398457B2 (en) | 1998-05-01 | 2001-04-30 | Pipe weld alignment system and method of operation |
Applications Claiming Priority (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US8396498P | 1998-05-01 | 1998-05-01 | |
US09/301,751 US6273643B1 (en) | 1998-05-01 | 1999-04-29 | Apparatus for deploying an underwater pipe string |
US09/846,014 US6398457B2 (en) | 1998-05-01 | 2001-04-30 | Pipe weld alignment system and method of operation |
Related Parent Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US09/301,751 Division US6273643B1 (en) | 1998-05-01 | 1999-04-29 | Apparatus for deploying an underwater pipe string |
Publications (2)
Publication Number | Publication Date |
---|---|
US20010033773A1 true US20010033773A1 (en) | 2001-10-25 |
US6398457B2 US6398457B2 (en) | 2002-06-04 |
Family
ID=26769972
Family Applications (2)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US09/301,751 Expired - Lifetime US6273643B1 (en) | 1998-05-01 | 1999-04-29 | Apparatus for deploying an underwater pipe string |
US09/846,014 Expired - Lifetime US6398457B2 (en) | 1998-05-01 | 2001-04-30 | Pipe weld alignment system and method of operation |
Family Applications Before (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US09/301,751 Expired - Lifetime US6273643B1 (en) | 1998-05-01 | 1999-04-29 | Apparatus for deploying an underwater pipe string |
Country Status (1)
Country | Link |
---|---|
US (2) | US6273643B1 (en) |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20050284638A1 (en) * | 2004-06-28 | 2005-12-29 | Riggs David C | Method for inspection and repair of a flexible joint |
EP1739279A1 (en) * | 2005-06-30 | 2007-01-03 | Single Buoy Moorings Inc. | Riser installation method from an offshore production unit |
US20090097924A1 (en) * | 2006-02-09 | 2009-04-16 | Heerema Marine Contractors Nederland B.V. | Crane Assisted Pipe Lay |
WO2009106789A1 (en) * | 2008-02-26 | 2009-09-03 | Pipeline Technique Limited | Method of forming a collar on a tubular component through depositing of weld metal and machining this deposit into a collar |
US20100021237A1 (en) * | 2005-06-29 | 2010-01-28 | Stewart Kenyon Willis | Pipe Laying Vessel and Methods of Operation Thereof |
US9382970B1 (en) | 2015-03-26 | 2016-07-05 | Chevron U.S.A. Inc. | Subsea remotely operated lifting shackle |
US9512938B2 (en) | 2008-12-23 | 2016-12-06 | Pipeline Technique Limited | Method of forming a collar on a tubular component through depositing of weld metal and machining this deposit into a collar |
GB2544547A (en) * | 2015-11-20 | 2017-05-24 | Acergy France SAS | Holding back Elongate elements during subsea operations |
US9874295B2 (en) | 2011-01-28 | 2018-01-23 | Saipem S.P.A. | Clamp assembly for pipe-laying vessel and method of laying a pipeline |
US10591088B2 (en) | 2011-01-28 | 2020-03-17 | Saipem S.P.A. | Pipe-laying vessel and method of laying a pipeline |
Families Citing this family (41)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6910848B1 (en) | 1998-05-01 | 2005-06-28 | Benton F. Baugh | Erector for J-Lay pipe laying system |
GB9904422D0 (en) * | 1998-07-22 | 1999-04-21 | Saipem Spa | Improvements in and relating to underwater pipe-laying |
US6561731B1 (en) * | 1999-03-15 | 2003-05-13 | Golden State Irrigation Services | Portable irrigation pipe installation and removal system |
CA2379124A1 (en) * | 1999-07-21 | 2001-02-01 | Teresio Signaroldi | Improvements in and relating to underwater pipe-laying |
EG23118A (en) * | 2000-06-05 | 2004-04-28 | Stolt Offshore Ltd | Pipe handling apparatus |
GB2373750A (en) * | 2001-03-27 | 2002-10-02 | Saipem Spa | Welding pipe-in-pipe pipelines |
US6592297B2 (en) * | 2001-04-25 | 2003-07-15 | Heerema Marine Contractors Nederland B.V. | Underwater pipe laying method and apparatus |
US6733208B2 (en) * | 2001-07-03 | 2004-05-11 | Torch Offshore, Inc. | Reel type pipeline laying ship and method |
US6966106B1 (en) | 2002-01-14 | 2005-11-22 | Itrec B.V. | Method and apparatus for transporting and running tubulars |
US6868902B1 (en) | 2002-01-14 | 2005-03-22 | Itrec B.V. | Multipurpose reeled tubing assembly |
US6776560B2 (en) | 2002-06-13 | 2004-08-17 | Mark Moszkowski | Flex J-Lay tower |
US6901998B1 (en) | 2003-03-17 | 2005-06-07 | Itrec B.V. | Method for using a multipurpose system |
US6932553B1 (en) | 2003-03-17 | 2005-08-23 | Itrec, B.V. | Multipurpose unit for drilling and well intervention |
GB0316375D0 (en) * | 2003-07-12 | 2003-08-13 | Stolt Offshore Sa | Method and associated apparatus for abandonment and recovery at sea |
US20050100413A1 (en) * | 2003-10-06 | 2005-05-12 | Baugh Benton F. | Roto-erector for J-Lay pipelaying system |
NO322872B1 (en) * | 2003-11-13 | 2006-12-18 | Aker Marine Contractors As | Vertical installation of an elongated process unit |
WO2005085692A1 (en) | 2004-03-10 | 2005-09-15 | Gusto Engineering B.V. | Light-weight versatile j-lay system |
WO2008041837A1 (en) * | 2006-10-04 | 2008-04-10 | Heerema Marine Contractors Nederland B.V. | Inner pipe fixation device |
GB0715999D0 (en) * | 2007-08-16 | 2007-09-26 | Acergy Uk Ltd | Method andapparatus for laying offshore pipeline from a vessel |
FR2922623B1 (en) * | 2007-10-23 | 2012-09-28 | Saipem Sa | DEVICE FOR RETENTION AND MAINTENANCE AND METHOD FOR CONNECTING AN UNDERWATER DRIVE TO A FLOATING SUPPORT. |
US8992124B2 (en) * | 2008-04-29 | 2015-03-31 | Itrec B.V. | Marine pipelaying system and method |
AU2008357518B2 (en) * | 2008-06-03 | 2013-10-10 | Heerema Marine Contractors Nederland S.E. | Pipeline guide assembly and method of laying a pipeline |
GB2460671B (en) * | 2008-06-04 | 2012-11-21 | Subsea 7 Ltd | Apparatus and method for use in laying pipe on the sea floor |
GB0811437D0 (en) | 2008-06-20 | 2008-07-30 | Saipem Spa | Pipe-laying vessel and method of laying a pipeline |
GB2462656B (en) * | 2008-08-15 | 2012-10-03 | Subsea 7 Ltd | Apparatus for use in laying pipe on the sea floor |
NL2002291C2 (en) * | 2008-12-05 | 2010-06-08 | Heerema Marine Contractors Nl | Improved pipeline support. |
NL2002351C2 (en) | 2008-12-19 | 2010-06-22 | Heerema Marine Contractors Nl | Vessel and method for laying a pipeline. |
NL2002348C2 (en) | 2008-12-19 | 2010-06-22 | Heerema Marine Contractors Nl | J-lay system with dual loading capability. |
NO330420B1 (en) * | 2009-03-16 | 2011-04-11 | Cecon Asa | Compilation and method of piping |
NL2003649C2 (en) * | 2009-10-16 | 2011-04-19 | Jansens & Dieperink Bv | DEVICE AND METHOD FOR POSITIONING SCALE PARTS. |
GB2476824B (en) | 2010-01-11 | 2013-12-18 | Subsea 7 Contracting Uk Ltd | Improvements relating to welding and other operations during J-lay pipelaying |
GB2477755A (en) * | 2010-02-11 | 2011-08-17 | Acergy Uk Ltd | Apparatus and method of laying a pipeline |
WO2012091560A2 (en) * | 2010-12-28 | 2012-07-05 | Itrec B.V. | Tubular installation system and method |
WO2012102607A1 (en) * | 2011-01-28 | 2012-08-02 | Heerema Marine Contractors Nederland B.V. | Stinger for a pipeline laying vessel |
GB2492402B (en) * | 2011-07-01 | 2013-10-09 | Technip France | Marine pipeline-installation tower and tensioning assembly |
WO2013082172A1 (en) * | 2011-11-28 | 2013-06-06 | T&T Engineering Services, Inc. | Tubular stand building and racking system |
CN102593760A (en) * | 2012-03-14 | 2012-07-18 | 中国海洋石油总公司 | Submarine cable drawing and guiding device |
GB2522345B (en) | 2013-02-06 | 2015-12-02 | Subsea 7 Ltd | Improvements relating to abandonment and recovery of pipelines |
CN105675195B (en) * | 2016-02-03 | 2018-04-24 | 中国海洋石油总公司 | Working ship operation real-time analyzer based on attitude of ship measurement |
CN106090430B (en) * | 2016-08-03 | 2018-01-12 | 上海振华重工(集团)股份有限公司 | Duct end installation system |
GB2576767B (en) * | 2018-08-31 | 2020-09-16 | Acergy France SAS | Abandonment and recovery of pipelines |
Family Cites Families (68)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US2048208A (en) | 1933-03-08 | 1936-07-21 | Nat Superior Co | Door type slip elevator |
US2450934A (en) * | 1946-05-25 | 1948-10-12 | Ingram X Calhoun | Well pipe handling apparatus |
US3331212A (en) | 1964-03-23 | 1967-07-18 | Shell Oil Co | Tension pipe laying method |
US3472034A (en) * | 1967-02-06 | 1969-10-14 | Brown & Root | Method and apparatus for controlling pipeline laying operations |
US3491541A (en) * | 1967-03-30 | 1970-01-27 | Houston Contracting Co | Submarine pipe laying apparatus and method |
FR1532570A (en) | 1967-05-31 | 1968-07-12 | Grands Travaux De Marseille Sa | Method and device for attenuating the effect of swell during the pure tension laying of subsea pipelines |
US3581506A (en) * | 1968-12-31 | 1971-06-01 | Pan American Petroleum Corp | Laying pipeline in deep water |
US3602175A (en) | 1969-07-02 | 1971-08-31 | North American Rockwell | Oil production vessel |
US3750769A (en) * | 1970-02-02 | 1973-08-07 | Dresser Ind | Drill pipe positioner for earth boring machine |
US3680322A (en) * | 1970-04-15 | 1972-08-01 | Brown & Root | Pipeline laying system utilizing an inclined ramp |
US3750451A (en) | 1970-04-15 | 1973-08-07 | Brown & Root | Internal tensioning system for laying pipeline |
US3921823A (en) * | 1970-12-15 | 1975-11-25 | Activite Atom Avance | Movement compensating apparatus for floating drilling |
US3737180A (en) | 1971-03-22 | 1973-06-05 | Kurier Corp | Pipe clamp |
US3747356A (en) * | 1972-04-07 | 1973-07-24 | Brown & Root | Method of arresting the propagation of a buckle in a pipeline |
US3775985A (en) | 1972-04-20 | 1973-12-04 | Mc Dermott J & Co Inc | Apparatus for laying submarine pipelines |
US3775987A (en) | 1972-07-11 | 1973-12-04 | Brown & Root | Method and apparatus for laying a submergible elongate structure |
US3860122A (en) * | 1972-12-07 | 1975-01-14 | Louis C Cernosek | Positioning apparatus |
DE2456141C3 (en) | 1974-11-27 | 1980-02-07 | Fa. Ludwig Freytag, 2900 Oldenburg | Process for laying pipelines in bodies of water with changing water depths and at different water levels in tidal areas and near the coast and a pipe-laying ship for carrying out the process |
FR2310515A1 (en) | 1975-05-06 | 1976-12-03 | Petroles Cie Francaise | ASSEMBLY AND LAYING PROCESS OF A SUBMARINE PIPE AND IMPLEMENTATION DEVICE |
US4109480A (en) * | 1975-06-20 | 1978-08-29 | The Sea Horse Corporation | Under water crane |
IT1055932B (en) * | 1976-01-29 | 1982-01-11 | Saipem Spa | APPARATUS PARTICULARLY SUITABLE FOR THE RECOVERY OF PIPES PLACED ON HIGH BOTTOMS AND A RECOVERY METHOD USING THE EQUIPMENT FROM A NAVEPOSATUBI |
US4202653A (en) | 1976-04-30 | 1980-05-13 | Western Gear Corporation | Pipe handling apparatus |
US4324194A (en) | 1976-12-10 | 1982-04-13 | Hydra-Rig, Inc. | Stabilized hoist rig for deep ocean mining vessel |
US4154037A (en) | 1977-03-18 | 1979-05-15 | Anderson Frohman C | Pole support assembly |
US4091629A (en) | 1977-04-11 | 1978-05-30 | Gunn Charles R | Marine pipeline installation system |
IT1089087B (en) | 1977-12-27 | 1985-06-10 | Saipem Spa | SEMI-SUBMERSIBLE PIPELINE SHIP EQUIPPED FOR LAYING PIPES ON DEEP SEA BOTTOMS AND RELATED METHOD OF USE |
US4340322A (en) * | 1978-05-05 | 1982-07-20 | Santa Fe International Corporation | Self propelled dynamically positioned reel pipe laying ship |
FR2458020A1 (en) | 1979-06-01 | 1980-12-26 | Gaz De France | DEVICE FOR LAYING A SUBSEA PIPE IN J |
US4274778A (en) * | 1979-06-05 | 1981-06-23 | Putnam Paul S | Mechanized stand handling apparatus for drilling rigs |
US4290495A (en) | 1979-06-18 | 1981-09-22 | Hydra-Rig, Inc. | Portable workover rig with extendable mast substructure, platform mounted drawworks and adjustable wellhead anchor |
GB2063333B (en) * | 1979-11-13 | 1983-09-21 | G P I Nii Nikelevokobaltovoi I | Apparatus for storing and moving a drill pipe to a position in alignment with the axis of a drill hole |
US4347029A (en) | 1979-12-28 | 1982-08-31 | Deepsea Ventures, Inc. | Pipe transfer system |
DE3112785C2 (en) * | 1981-03-31 | 1984-01-19 | Blohm + Voss Ag, 2000 Hamburg | Pipe-laying ship |
US4591294A (en) | 1982-03-31 | 1986-05-27 | Nis Engineering Limited | Welding and laying pipelines |
US4569168A (en) * | 1982-09-20 | 1986-02-11 | P J Repair Service, Inc. | Self-elevating substructure for a portable oil derrick |
US4547096A (en) | 1983-08-01 | 1985-10-15 | Mcdermott International, Inc. | Alignment of tubular piles for joinder |
US4704050A (en) * | 1983-10-05 | 1987-11-03 | Bechtel Power Corporation | J-configured offshore oil production riser |
US4561803A (en) | 1983-12-19 | 1985-12-31 | Mcdermott International, Inc. | Conductor guide system for offshore drilling platform |
US4652195A (en) * | 1984-01-26 | 1987-03-24 | Mcarthur James R | Casing stabbing and positioning apparatus |
US4917540A (en) | 1984-08-31 | 1990-04-17 | Santa Fe International Corporation | Pipeline laying system and vessel with pipeline straightening and tensioning device |
US4723874A (en) | 1984-08-31 | 1988-02-09 | Santa Fe International Corporation | Multi-reel operational lines laying vessel |
US4709766A (en) * | 1985-04-26 | 1987-12-01 | Varco International, Inc. | Well pipe handling machine |
US4759414A (en) * | 1986-04-25 | 1988-07-26 | W-N Apache Corporation | Modular drilling machine and components thereof |
US5145289A (en) * | 1986-06-19 | 1992-09-08 | Shell Oil Company | Reduced J-tube riser pull force |
US4717353A (en) | 1987-01-21 | 1988-01-05 | Mcdermott Incorporated | Docking head and plate |
US4784527A (en) | 1987-05-29 | 1988-11-15 | Conoco Inc. | Modular drilling template for drilling subsea wells |
US4832530A (en) * | 1988-02-08 | 1989-05-23 | Andersen Scott F | Apparatus and method for joining pipe sections underwater |
US5000416A (en) | 1990-01-26 | 1991-03-19 | The United States Of America As Represented By The Administrator Of The National Aeronautics And Space Administration | Alignment positioning mechanism |
US4992001A (en) | 1990-08-17 | 1991-02-12 | Mcdermott International, Inc. | Method of deepwater pipelay |
US5458441A (en) | 1991-04-23 | 1995-10-17 | Shell Oil Company | Pipe section for installation into a subsea pipeline |
GB9120429D0 (en) * | 1991-09-25 | 1991-11-06 | Stena Offshore Ltd | Reel pipelaying vessel |
GB9120432D0 (en) | 1991-09-25 | 1991-11-06 | Stena Offshore Ltd | Reel pipelaying vessel |
US5269630A (en) * | 1993-02-02 | 1993-12-14 | Power Lift Foundation Repair | Slab lifter |
US5458439A (en) * | 1993-04-29 | 1995-10-17 | Sonsub International Management Inc. | Pipe attachment and receiving assembly |
US5380130A (en) | 1993-09-20 | 1995-01-10 | Kerr-Mcgee Corp. | Preinstalled adjustable conductor guide |
US5421675A (en) | 1993-11-18 | 1995-06-06 | Mcdermott International, Inc. | Apparatus for near vertical laying of pipeline |
US5464307A (en) | 1993-12-29 | 1995-11-07 | Mcdermott International, Inc. | Apparatus for near vertical laying of pipeline |
US5347101A (en) | 1994-02-07 | 1994-09-13 | Mcdermott International, Inc. | Automatic tracking system for pipeline welding |
AU676431B2 (en) | 1994-03-16 | 1997-03-06 | Coflexip Stena Offshore Limited | Pipe laying vessel and method |
CA2140203C (en) * | 1995-01-13 | 1998-08-25 | Burns Stevenson And Associates Ltd. | Pipe alignment apparatus for use on wellhead derrick |
NL194836C (en) * | 1995-03-10 | 2003-04-03 | Allseas Group Sa | Device for laying a pipeline on a submerged soil. |
CA2158801C (en) | 1995-09-21 | 1998-07-14 | Grant Douglas Herbert | Pipeline weight and method of installing the same |
US5857715A (en) | 1997-09-04 | 1999-01-12 | J. Ray Mcdermott, S.A. | Pipeline branch arrangement |
US5919003A (en) * | 1998-02-13 | 1999-07-06 | Grand Isle Shipyard, Inc. | Marine pipeline recovery system and method of recovering marine pipeline |
GB2335724B (en) | 1998-03-27 | 2002-10-30 | Heerema Marine Contractors V O | Improvements in or related to methods of installing elongate underwater structures |
GB9806974D0 (en) | 1998-04-01 | 1998-06-03 | Coflexip Stena Offshore Ltd | Marine pipelay system |
US6213686B1 (en) * | 1998-05-01 | 2001-04-10 | Benton F. Baugh | Gimbal for J-Lay pipe laying system |
GB2339251B (en) | 1998-06-23 | 2003-06-18 | British Steel Plc | Laying of undersea pipes |
-
1999
- 1999-04-29 US US09/301,751 patent/US6273643B1/en not_active Expired - Lifetime
-
2001
- 2001-04-30 US US09/846,014 patent/US6398457B2/en not_active Expired - Lifetime
Cited By (22)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US7472755B2 (en) * | 2004-06-28 | 2009-01-06 | Riggs David C | Method for inspection and repair of a flexible joint |
US20050284638A1 (en) * | 2004-06-28 | 2005-12-29 | Riggs David C | Method for inspection and repair of a flexible joint |
US7909538B2 (en) * | 2005-06-29 | 2011-03-22 | Acergy Uk Limited | Pipe laying vessel and methods of operation thereof |
US20100021237A1 (en) * | 2005-06-29 | 2010-01-28 | Stewart Kenyon Willis | Pipe Laying Vessel and Methods of Operation Thereof |
EP1739279A1 (en) * | 2005-06-30 | 2007-01-03 | Single Buoy Moorings Inc. | Riser installation method from an offshore production unit |
WO2007004875A2 (en) * | 2005-06-30 | 2007-01-11 | Single Buoy Moorings Inc. | Riser installation method from an offshore production unit |
WO2007004875A3 (en) * | 2005-06-30 | 2007-03-15 | Single Buoy Moorings | Riser installation method from an offshore production unit |
US8142108B2 (en) | 2005-06-30 | 2012-03-27 | Single Buoy Moorings Inc. | Riser installation method from an offshore production unit |
US20100104373A1 (en) * | 2005-06-30 | 2010-04-29 | Single Buoy Moorings Inc. | Riser Installation Method from an Offshore Production Unit |
US20090097924A1 (en) * | 2006-02-09 | 2009-04-16 | Heerema Marine Contractors Nederland B.V. | Crane Assisted Pipe Lay |
US7722294B2 (en) * | 2006-02-09 | 2010-05-25 | Heerema Marine Contractors | Crane assisted pipe lay |
US20110127315A1 (en) * | 2008-02-26 | 2011-06-02 | Graham Hutt | Method of forming a collar on a tubular component through depositing of weld metal and machining this deposit into a collar |
WO2009106789A1 (en) * | 2008-02-26 | 2009-09-03 | Pipeline Technique Limited | Method of forming a collar on a tubular component through depositing of weld metal and machining this deposit into a collar |
US20140048585A1 (en) * | 2008-02-26 | 2014-02-20 | Pipeline Technique Limited | Method of forming a collar on a tubular component through depositing of weld metal and machining this deposit into a collar |
AU2008351912B2 (en) * | 2008-02-26 | 2015-03-12 | Pipeline Technique Limited | Method of forming a collar on a tubular component through depositing of weld metal and machining this deposit into a collar |
US9512938B2 (en) | 2008-12-23 | 2016-12-06 | Pipeline Technique Limited | Method of forming a collar on a tubular component through depositing of weld metal and machining this deposit into a collar |
US9874295B2 (en) | 2011-01-28 | 2018-01-23 | Saipem S.P.A. | Clamp assembly for pipe-laying vessel and method of laying a pipeline |
US10591088B2 (en) | 2011-01-28 | 2020-03-17 | Saipem S.P.A. | Pipe-laying vessel and method of laying a pipeline |
US9382970B1 (en) | 2015-03-26 | 2016-07-05 | Chevron U.S.A. Inc. | Subsea remotely operated lifting shackle |
GB2544547A (en) * | 2015-11-20 | 2017-05-24 | Acergy France SAS | Holding back Elongate elements during subsea operations |
GB2544547B (en) * | 2015-11-20 | 2019-06-12 | Acergy France SAS | Holding back Elongate elements during subsea operations |
US10527196B2 (en) | 2015-11-20 | 2020-01-07 | Acergy France SAS | Holding back elongate elements during subsea operations |
Also Published As
Publication number | Publication date |
---|---|
US6273643B1 (en) | 2001-08-14 |
US6398457B2 (en) | 2002-06-04 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US6273643B1 (en) | Apparatus for deploying an underwater pipe string | |
US8366352B2 (en) | System usable with a pipe laying vessel | |
EP2005050B1 (en) | Marine pipeline installation system and methods | |
US6213686B1 (en) | Gimbal for J-Lay pipe laying system | |
AU755992B2 (en) | Underwater pipe-laying vessels and methods | |
AU764086B2 (en) | Improvements in and relating to underwater pipe-laying | |
RU2606540C2 (en) | Pipe laying ship (versions) and method of pipeline laying (versions) | |
US6910848B1 (en) | Erector for J-Lay pipe laying system | |
US6293732B1 (en) | Travelling table for J-Lay pipelaying system | |
US6364573B1 (en) | Jack mechanism for J-Lay pipelaying system | |
US20010041095A1 (en) | Split double collar for deployment of pipe string | |
US11597478B2 (en) | Systems for handling one or more elongated members and methods for using same | |
US6334739B1 (en) | Stinger for J-Lay pipelaying system | |
AU2005276561B2 (en) | Apparatus and method for mooring a floating vessel | |
EP3844428B1 (en) | Abandonment and recovery of pipelines | |
NO179845B (en) | Tools Unit |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
AS | Assignment |
Owner name: OIL STATES INDUSTRIES, INC., TEXAS Free format text: MERGER/CHANGE OF NAME;ASSIGNOR:OIL STATES INDUSTRIES, INC.;REEL/FRAME:012641/0475 Effective date: 20011231 |
|
STCF | Information on status: patent grant |
Free format text: PATENTED CASE |
|
AS | Assignment |
Owner name: WELLS FARGO BANK OF TEXAS, TEXAS Free format text: SECURITY AGREEMENT;ASSIGNORS:OIL STATES INDUSTRIES, INC.;A-Z TERMINAL CORPORATION;CAPSTAR DRILLING, L.P.;AND OTHERS;REEL/FRAME:014709/0287 Effective date: 20031031 |
|
FPAY | Fee payment |
Year of fee payment: 4 |
|
FPAY | Fee payment |
Year of fee payment: 8 |
|
FPAY | Fee payment |
Year of fee payment: 12 |
|
AS | Assignment |
Owner name: OIL STATES INTERNATIONAL, INC., TEXAS Free format text: RELEASE BY SECURED PARTY;ASSIGNOR:WELLS FARBO BANK OF TEXAS, NATIONAL ASSOCIATION, AS AGENT;REEL/FRAME:055656/0969 Effective date: 20031030 |