TW202611370A - Construction methods for building piles - Google Patents

Construction methods for building piles

Info

Publication number
TW202611370A
TW202611370A TW113133851A TW113133851A TW202611370A TW 202611370 A TW202611370 A TW 202611370A TW 113133851 A TW113133851 A TW 113133851A TW 113133851 A TW113133851 A TW 113133851A TW 202611370 A TW202611370 A TW 202611370A
Authority
TW
Taiwan
Prior art keywords
casing
auger
pile
motor
constructing
Prior art date
Application number
TW113133851A
Other languages
Chinese (zh)
Other versions
TWI888268B (en
Inventor
李坤得
李建佑
李裕萍
Original Assignee
磐鼎營造股份有限公司
Filing date
Publication date
Application filed by 磐鼎營造股份有限公司 filed Critical 磐鼎營造股份有限公司
Priority to TW113133851A priority Critical patent/TWI888268B/en
Priority claimed from TW113133851A external-priority patent/TWI888268B/en
Application granted granted Critical
Publication of TWI888268B publication Critical patent/TWI888268B/en
Publication of TW202611370A publication Critical patent/TW202611370A/en

Links

Abstract

一種營建立樁之施工方法,包含:(A)利用一鑽掘機之一導筒導引定位一套管,並將該套管之上端接合於該鑽掘機之一馬達;(B)利用該馬達帶動該套管及該鑽掘機之一螺旋鑽桿旋轉,使該套管及該螺旋鑽桿鑽掘一軟土基地至一預定深度,其中,該螺旋鑽桿掘取的軟土可經由該套管之一排放孔排出;(C)將該套管與該馬達分離;(D)利用該螺旋鑽桿內部管道,將水泥漿灌入該套管之內部空間,繼而拔出該螺旋鑽桿;(E)將一營建立樁插設於該水泥漿;(F)回填乾砂石於該水泥漿上;及(G)拔出該套管。A method for constructing a pile includes: (A) using a guide tube of a drilling machine to guide and position a casing, and connecting the upper end of the casing to a motor of the drilling machine; (B) using the motor to drive the casing and a auger of the drilling machine to rotate, causing the casing and the auger to drill into a soft soil base to a predetermined depth, wherein the auger... (C) The excavated soft soil can be discharged through one of the discharge holes of the casing; (D) the casing is separated from the motor; (D) cement grout is poured into the internal space of the casing through the internal conduit of the auger, and then the auger is pulled out; (E) a construction pile is inserted into the cement grout; (F) dry sand and gravel are backfilled on the cement grout; and (G) the casing is pulled out.

Description

營建立樁之施工方法Construction methods for building piles

本發明是有關於一種施工方法,特別是指一種營建立樁之施工方法。This invention relates to a construction method, and more particularly to a construction method for erecting piles.

參閱圖1,習知鑽掘機1是用於在一營建基地設置一營建立樁(例如:中間樁、構台樁、大口徑基樁等等)。該鑽掘機1主要包括一螺旋鑽桿11、一用於提供該螺旋鑽桿11所需之旋轉動力之馬達12,及一用於引導該螺旋鑽桿11之導筒13等元件。當該營建基地為硬土基地時,該螺旋鑽桿11可以順利安全地在該硬土基地鑽掘出插設該營建立樁所需的圓筒形鑽掘孔。然而,若該營建基地為軟弱土層基地,由於該軟弱土層基地土質鬆軟,故當該螺旋鑽桿11鑽掘完成而接著上拉時,軟土將可能會坍塌至該圓筒形鑽掘孔中而使得附近的車輛、機具及人員面臨極大危險。故,有必要尋求解決之道。Referring to Figure 1, the conventional drilling machine 1 is used to install a construction pile (e.g., intermediate pile, platform pile, large-diameter foundation pile, etc.) on a construction site. The drilling machine 1 mainly includes a auger 11, a motor 12 for providing the rotational power required by the auger 11, and a guide cylinder 13 for guiding the auger 11. When the construction site is a hard soil base, the auger 11 can smoothly and safely drill the cylindrical borehole required for inserting the construction pile in the hard soil base. However, if the construction site is located on a soft soil layer, the loose soil could cause it to collapse into the cylindrical borehole when the auger 11 completes drilling and is pulled upwards, posing a significant danger to nearby vehicles, machinery, and personnel. Therefore, it is necessary to find a solution.

因此,本發明的目的,即在提供一種營建立樁之施工方法。Therefore, the purpose of this invention is to provide a construction method for building piles.

於是,本發明營建立樁之施工方法,適用於以一鑽掘機在一軟土基地設置一營建立樁,該鑽掘機包括一螺旋鑽桿、一馬達,及一導筒。該營建立樁之施工方法包含以下步驟:(A)利用該鑽掘機之該導筒導引定位一包括數個鋸齒及至少一排放孔之套管,並將該套管之上端接合於該鑽掘機之該馬達;(B)利用該馬達帶動該套管及該螺旋鑽桿旋轉,使該套管及該螺旋鑽桿鑽掘該軟土基地至一預定深度,其中,該螺旋鑽桿掘取的軟土可經由該套管之該排放孔排出;(C)將該套管與該馬達分離;(D)利用該螺旋鑽桿內部管道,將水泥漿灌入該套管之內部空間,繼而拔出該螺旋鑽桿;(E)將該營建立樁插設於該水泥漿;(F)回填乾砂石於該水泥漿上;及(G)拔出該套管。Therefore, the construction method for erecting a pile according to the present invention is applicable to setting up a pile in a soft soil base using a drilling machine, the drilling machine including a auger, a motor, and a guide tube. The construction method for erecting a pile includes the following steps: (A) using the guide tube of the drilling machine to guide and position a casing including a plurality of saw teeth and at least one discharge hole, and connecting the upper end of the casing to the motor of the drilling machine; (B) using the motor to drive the casing and the auger to rotate, so that the casing and the auger drill to excavate the soft soil base to a predetermined depth, wherein (C) The soft soil excavated by the auger can be discharged through the discharge hole of the casing; (D) Separate the casing from the motor; (E) Use the internal pipe of the auger to pour cement grout into the internal space of the casing, and then pull out the auger; (F) Insert the construction pile into the cement grout; (G) Backfill dry sand and gravel on the cement grout; and (G) Pull out the casing.

本發明的另一目的,即在提供另一種營建立樁之施工方法,適用於以一鑽掘機在一軟土基地設置一營建立樁,該鑽掘機包括一螺旋鑽桿、一馬達,及一導筒。該營建立樁之施工方法包含以下步驟:(a) 在該螺旋鑽桿不與該馬達接合的情況下,利用該鑽掘機之該導筒導引定位一包括數個鋸齒之套管,並將該套管之上端接合於該鑽掘機之該馬達;(b)利用該馬達帶動該套管旋轉,使該套管鑽入該軟土基地至一預定深度;(c)將該套管與該馬達分離,並將該螺旋鑽桿與該馬達接合;(d)利用該馬達帶動該螺旋鑽桿旋轉,使該螺旋鑽桿鑽掘該軟土基地至該預定深度;(e)利用該螺旋鑽桿內部管道,將水泥漿灌入該套管之內部空間,繼而拔出該螺旋鑽桿;(f)將該營建立樁插設於該水泥漿;(g)回填乾砂石於該水泥漿上;及(h)拔出該套管。Another object of the present invention is to provide an alternative method for constructing a pile, applicable to the use of a drilling rig to construct a pile in a soft soil base. The drilling rig includes a auger, a motor, and a guide tube. The method for constructing the pile comprises the following steps: (a) with the auger not engaged with the motor, guiding and positioning a casing comprising a plurality of serrations using the guide tube of the drilling rig, and engaging the upper end of the casing with the motor of the drilling rig; (b) using the motor to rotate the casing, causing the casing to drill into the soft soil base to a predetermined depth; (c) separating the casing from the motor, and connecting the auger to the motor. (d) Using the motor to rotate the auger, causing the auger to drill into the soft soil base to the predetermined depth; (e) Using the internal pipe of the auger, injecting cement grout into the internal space of the casing, and then pulling out the auger; (f) Inserting the construction pile into the cement grout; (g) Backfilling the cement grout with dry sand and gravel; and (h) Pulling out the casing.

本發明的功效在於:透過該套管以及該鑽掘機之協同運作,可適用於在該軟土基地設置該營建立樁,其中,在該螺旋鑽桿鑽掘該軟土基地的過程中,藉由該套管之保護,可防止該套管周圍的軟土坍塌,對於施工時臨近鄰房車輛、機具及人員提供很高的安全性。The advantages of this invention are: through the coordinated operation of the casing and the drilling machine, it can be applied to the installation of the camp pile in the soft soil base. During the drilling process of the auger drill in the soft soil base, the casing can protect the soft soil around the casing from collapse, providing a high level of safety for nearby vehicles, equipment and personnel during construction.

參閱圖2至7,本發明營建立樁之施工方法之一第一實施例,適用於以一鑽掘機9在一軟土基地8設置一營建立樁7(例如H型鋼等)。其中,該鑽掘機9包括一螺旋鑽桿91、一馬達92,及一導筒93。在本第一實施例中,該營建立樁之施工方法包含以下步驟。首先,如圖2步驟S31所示,利用該導筒93導引定位一包括數個鋸齒21及至少一排放孔22之套管2,並且將該套管2之上端接合於該鑽掘機9之該馬達92,如圖3所示。其中,該套管2是藉由數個螺栓(圖未示)接合於該馬達92。在本第一實施例中,該套管2之材質為鋼材。該套管2之直徑為70公分至100公分,且長度為3公尺至15公尺。Referring to Figures 2 to 7, a first embodiment of the construction method for erecting a pile according to the present invention is applicable to setting up a pile 7 (e.g., an H-beam) on a soft soil base 8 using a drilling rig 9. The drilling rig 9 includes a auger 91, a motor 92, and a guide tube 93. In this first embodiment, the construction method for erecting the pile includes the following steps: First, as shown in step S31 of Figure 2, a sleeve 2 including several saw teeth 21 and at least one discharge hole 22 is guided and positioned using the guide tube 93, and the upper end of the sleeve 2 is connected to the motor 92 of the drilling rig 9, as shown in Figure 3. The sleeve 2 is connected to the motor 92 by several bolts (not shown). In this first embodiment, the sleeve 2 is made of steel. The diameter of the sleeve 2 is 70 cm to 100 cm, and the length is 3 m to 15 m.

接著,如步驟S32所示,利用該馬達92帶動該套管2及該螺旋鑽桿91旋轉,使該套管2及該螺旋鑽桿91鑽掘該軟土基地8至一預定深度。其中,該螺旋鑽桿91掘取的軟土可經由該套管2之排放孔22排出,如圖4、5所示。其中,當該套管2鑽入該軟土基地8至該預定深度時,仍保留長度約1.2公尺的該套管2位於地面81以上。Next, as shown in step S32, the motor 92 drives the casing 2 and the auger drill 91 to rotate, causing the casing 2 and the auger drill 91 to drill into the soft soil base 8 to a predetermined depth. The soft soil excavated by the auger drill 91 can be discharged through the discharge hole 22 of the casing 2, as shown in Figures 4 and 5. When the casing 2 has drilled into the soft soil base 8 to the predetermined depth, approximately 1.2 meters of the casing 2 remains above the ground surface 81.

接著,如步驟S33所示,將該套管2與該馬達92分離。Next, as shown in step S33, the sleeve 2 is separated from the motor 92.

接著,如步驟S34所示,利用該螺旋鑽桿91之內部管道910,將水泥漿6灌入該套管2之內部空間,如圖5所示。其中,該水泥漿6之強度為140公斤/平方公分至210公斤/平方公分。繼而,拔出該螺旋鑽桿91。Next, as shown in step S34, cement grout 6 is poured into the inner space of the sleeve 2 through the internal pipe 910 of the spiral drill rod 91, as shown in Figure 5. The strength of the cement grout 6 is between 140 kg/cm² and 210 kg/cm². Then, the spiral drill rod 91 is pulled out.

接著,如步驟S35所示,將該營建立樁7插設於該水泥漿6至所需的設計深度,如圖6所示。Next, as shown in step S35, the construction pile 7 is inserted into the cement grout 6 to the required design depth, as shown in Figure 6.

接著,如步驟S36所示,待經過約一、兩天該水泥漿6初步凝固之後,回填乾砂石5於該水泥漿6上,如圖7所示。最後,如步驟S37所示,將該套管2拔出,而完成本發明營建立樁之施工方法之第一實施例。Next, as shown in step S36, after the cement slurry 6 has initially solidified for about one or two days, dry sand and gravel 5 are backfilled on the cement slurry 6, as shown in Figure 7. Finally, as shown in step S37, the sleeve 2 is pulled out, thus completing the first embodiment of the construction method for erecting piles according to the present invention.

參閱圖8至14,本發明營建立樁之施工方法之第二實施例,包含以下步驟。首先,如圖8步驟S41所示,在該螺旋鑽桿91不與該馬達92接合的情況下,利用該導筒93導引定位該套管2,並且將該套管2之上端接合於該鑽掘機9之該馬達92,如圖9所示,繼而利用該馬達92帶動該套管2旋轉,使該套管2鑽入該軟土基地8至預定深度,如圖10所示。Referring to Figures 8 to 14, a second embodiment of the construction method for pile erection of the present invention includes the following steps. First, as shown in step S41 of Figure 8, without the auger 91 being engaged with the motor 92, the guide tube 93 is used to guide and position the casing 2, and the upper end of the casing 2 is engaged with the motor 92 of the drilling machine 9, as shown in Figure 9. Then, the motor 92 is used to drive the casing 2 to rotate, so that the casing 2 drills into the soft soil base 8 to a predetermined depth, as shown in Figure 10.

接著,如步驟S42所示,將該套管2與該馬達92分離,並且將該螺旋鑽桿91與該馬達92接合,如圖11所示。Next, as shown in step S42, the sleeve 2 is separated from the motor 92, and the spiral drill rod 91 is engaged with the motor 92, as shown in Figure 11.

接著,如步驟S43所示,利用該馬達92帶動該螺旋鑽桿91旋轉,使該螺旋鑽桿91鑽掘該軟土基地8至該預定深度。Next, as shown in step S43, the motor 92 drives the spiral drill 91 to rotate, so that the spiral drill 91 drills into the soft soil base 8 to the predetermined depth.

接著,如步驟S45所示,利用該螺旋鑽桿91之內部管道910,將水泥漿6灌入該套管2之內部空間,如圖12所示。其中,該水泥漿6之強度為140公斤/平方公分至210公斤/平方公分。繼而,拔出該螺旋鑽桿91。Next, as shown in step S45, cement grout 6 is poured into the internal space of the sleeve 2 through the internal pipe 910 of the spiral drill rod 91, as shown in Figure 12. The strength of the cement grout 6 is between 140 kg/cm² and 210 kg/cm². Then, the spiral drill rod 91 is pulled out.

接著,如步驟S46所示,將營建立樁7插設於該水泥漿6至所需的設計深度,如圖13所示。Next, as shown in step S46, the construction pile 7 is inserted into the cement grout 6 to the required design depth, as shown in Figure 13.

接著,如步驟S47所示,待經過約一、兩天該水泥漿6初步凝固之後,回填乾砂石5於該水泥漿6上,如圖14所示。最後,如步驟S48所示,將該套管2拔出,而完成本發明營建立樁之施工方法之第二實施例。Next, as shown in step S47, after the cement grout 6 has initially solidified for about one or two days, dry sand and gravel 5 are backfilled on the cement grout 6, as shown in Figure 14. Finally, as shown in step S48, the sleeve 2 is pulled out, thus completing the second embodiment of the construction method for erecting piles according to the present invention.

綜上所述,本發明之優點及功效在於,透過該套管2以及該鑽掘機9之協同運作,可適用於在該軟土基地8設置該營建立樁7,其中,在該螺旋鑽桿11鑽掘該軟土基地8的過程中,藉由該套管2之保護,可防止該套管2周圍的軟土坍塌,對於施工時臨近鄰房車輛、機具及人員提供很高的安全性;故確實能達成本發明的目的。In summary, the advantages and benefits of this invention are that, through the coordinated operation of the casing 2 and the drilling machine 9, it can be applied to the installation of the foundation pile 7 in the soft soil base 8. During the drilling process of the auger drill 11 in the soft soil base 8, the casing 2 can protect the soft soil around the casing 2 from collapse, providing a high level of safety for nearby vehicles, equipment and personnel during construction; thus, it can indeed achieve the purpose of this invention.

惟以上所述者,僅為本發明的實施例而已,當不能以此限定本發明實施的範圍,凡是依本發明申請專利範圍及專利說明書內容所作的簡單的等效變化與修飾,皆仍屬本發明專利涵蓋的範圍內。However, the above description is merely an example of the present invention and should not be used to limit the scope of the present invention. Any simple equivalent changes and modifications made in accordance with the scope of the patent application and the contents of the patent specification shall still fall within the scope of the present invention.

2:套管 21:鋸齒 22:排放孔 5:乾砂石 6:水泥漿 7:營建立樁 8:軟土基地 81:地面 9:鑽掘機 91:螺旋鑽桿 910:內部管道 92:馬達 93:導筒 S31~S37:步驟 S41~S48:步驟 2: Sleeve 21: Sawtooth 22: Drain Hole 5: Dry Sand and Gravel 6: Cement Slurry 7: Piling 8: Soft Soil Base 81: Ground 9: Drilling Machine 91: Spiral Drill Rod 910: Internal Pipeline 92: Motor 93: Guide Sleeve S31~S37: Steps S41~S48: Steps

本發明的其他的特徵及功效,將於參照圖式的實施方式中清楚地呈現,其中: 圖1是一示意圖,說明現有鑽掘機; 圖2是一流程圖,說明本發明營建立樁之施工方法之一第一實施例; 圖3是一局部剖視圖,說明該第一實施例之一定位套管步驟; 圖4是一局部剖視圖,說明該第一實施例之一鑽掘取土步驟; 圖5是一局部剖視圖,說明該第一實施例之一灌漿步驟; 圖6是一局部剖視圖,說明該第一實施例之一插設營建立樁步驟; 圖7是一剖視圖,說明該第一實施例之一回填砂石步驟; 圖8是一流程圖,說明本發明營建立樁之施工方法之一第二實施例; 圖9是一局部剖視圖,說明該第二實施例之一定位套管步驟; 圖10是一局部剖視圖,說明在該第二實施例中,將套管旋轉植入至一預定深度; 圖11是一局部剖視圖,說明在該第二實施例中,將該套管與一鑽掘機之一馬達分離,並且將該鑽掘機之一螺旋鑽桿與該馬達接合; 圖12是一局部剖視圖,說明該第二實施例之一灌漿步驟; 圖13是一局部剖視圖,說明該第二實施例之一插設營建立樁步驟;及 圖14是一剖視圖,說明該第二實施例之一回填砂石步驟。 Other features and benefits of this invention will be clearly shown in the embodiments with reference to the accompanying drawings, in which: Figure 1 is a schematic diagram illustrating a conventional drilling machine; Figure 2 is a flowchart illustrating a first embodiment of the pile erection method of this invention; Figure 3 is a partial sectional view illustrating the casing positioning step in the first embodiment; Figure 4 is a partial sectional view illustrating the soil excavation step in the first embodiment; Figure 5 is a partial sectional view illustrating the grouting step in the first embodiment; Figure 6 is a partial sectional view illustrating the pile insertion step in the first embodiment; Figure 7 is a sectional view illustrating the backfilling step in the first embodiment; Figure 8 is a flowchart illustrating a second embodiment of the pile erection method of this invention; Figure 9 is a partial cross-sectional view illustrating the casing positioning step in one of the second embodiments; Figure 10 is a partial cross-sectional view illustrating the casing being rotated and inserted to a predetermined depth in one of the second embodiments; Figure 11 is a partial cross-sectional view illustrating the separation of the casing from a motor of a drilling machine and the engagement of a auger rod of the drilling machine with the motor in one of the second embodiments; Figure 12 is a partial cross-sectional view illustrating the grouting step in one of the second embodiments; Figure 13 is a partial cross-sectional view illustrating the pile installation step in one of the second embodiments; and Figure 14 is a cross-sectional view illustrating the backfilling step in one of the second embodiments.

S31~S37:步驟 S31~S37: Steps

Claims (12)

一種營建立樁之施工方法,適用於以一鑽掘機在一軟土基地設置一營建立樁,該鑽掘機包括一螺旋鑽桿、一馬達,及一導筒,該營建立樁之施工方法包含以下步驟: (A)利用該鑽掘機之該導筒導引定位一包括數個鋸齒及至少一排放孔之套管,並將該套管之上端接合於該鑽掘機之該馬達; (B)利用該馬達帶動該套管及該螺旋鑽桿旋轉,使該套管及該螺旋鑽桿鑽掘該軟土基地至一預定深度,其中,該螺旋鑽桿掘取的軟土可經由該套管之該排放孔排出; (C)將該套管與該馬達分離; (D)利用該螺旋鑽桿內部管道,將水泥漿灌入該套管之內部空間,繼而拔出該螺旋鑽桿; (E)將該營建立樁插設於該水泥漿; (F)待該水泥漿初步凝固之後,回填乾砂石於該水泥漿上;及 (G)拔出該套管。 A method for constructing a pile, applicable to setting up a pile in a soft soil base using a drilling rig, the drilling rig including a auger, a motor, and a guide tube, the method comprising the following steps: (A) Using the guide tube of the drilling rig to guide and position a casing including a plurality of saw teeth and at least one discharge hole, and connecting the upper end of the casing to the motor of the drilling rig; (B) Using the motor to drive the casing and the auger to rotate, causing the casing and the auger to drill into the soft soil base to a predetermined depth, wherein the soft soil excavated by the auger can be discharged through the discharge hole of the casing; (C) Separating the casing from the motor; (D) Using the internal conduit of the auger drill rod, pour cement grout into the internal space of the casing, then pull out the auger drill rod; (E) Insert the erection pile into the cement grout; (F) After the cement grout has initially solidified, backfill it with dry sand and gravel; and (G) Pull out the casing. 如請求項1所述的營建立樁之施工方法,其中,在該步驟(A)中,該套管之材質為鋼材。The construction method for constructing piles as described in claim 1, wherein in step (A), the casing is made of steel. 如請求項1所述的營建立樁之施工方法,其中,在該步驟(A)中,該套管是藉由數個螺栓接合於該馬達。The construction method for constructing a pile as described in claim 1, wherein in step (A), the sleeve is connected to the motor by a number of bolts. 如請求項1所述的營建立樁之施工方法,其中,在該步驟(A)中,該套管之直徑為70公分至100公分,且長度為3公尺至15公尺。The construction method for constructing piles as described in claim 1, wherein in step (A), the diameter of the casing is 70 cm to 100 cm and the length is 3 m to 15 m. 如請求項1所述的營建立樁之施工方法,其中,在該步驟(B)中,當該套管鑽入該軟土基地至該預定深度時,仍保留長度約1.2公尺的該套管位於地面以上。The construction method for constructing piles as described in claim 1, wherein in step (B), when the casing is drilled into the soft soil base to the predetermined depth, the casing with a length of approximately 1.2 meters remains above the ground. 如請求項1所述的營建立樁之施工方法,其中,在該步驟(E)中,該營建立樁為H型鋼。The construction method for constructing a pile as described in claim 1, wherein in step (E), the pile is an H-beam. 一種營建立樁之施工方法,適用於以一鑽掘機在一軟土基地設置一營建立樁,其中,該鑽掘機包括一螺旋鑽桿、一馬達,及一導筒,該營建立樁之施工方法包含以下步驟: (a)在該螺旋鑽桿不與該馬達接合的情況下,利用該鑽掘機之該導筒導引定位一包括數個鋸齒之套管,並將該套管之上端接合於該鑽掘機之該馬達; (b)利用該馬達帶動該套管旋轉,使該套管鑽入該軟土基地至一預定深度; (c)將該套管與該馬達分離,並將該螺旋鑽桿與該馬達接合; (d)利用該馬達帶動該螺旋鑽桿旋轉,使該螺旋鑽桿鑽掘該軟土基地至該預定深度; (e)利用該螺旋鑽桿內部管道,將水泥漿灌入該套管之內部空間,繼而拔出該螺旋鑽桿; (f)將該營建立樁插設於該水泥漿; (g)待該水泥漿初步凝固之後,回填乾砂石於該水泥漿上;及 (h)拔出該套管。 A method for constructing a pile, applicable to setting up a pile in a soft soil base using a drilling rig, wherein the drilling rig includes a auger, a motor, and a guide tube, and the method comprises the following steps: (a) With the auger not engaged with the motor, guiding and positioning a casing comprising a plurality of serrations using the guide tube of the drilling rig, and engaging the upper end of the casing with the motor of the drilling rig; (b) Rotating the casing using the motor, causing the casing to drill into the soft soil base to a predetermined depth; (c) Separating the casing from the motor and engaging the auger with the motor; (d) Using the motor to rotate the auger, the auger drills into the soft soil base to the predetermined depth; (e) Using the internal conduit of the auger, cement grout is poured into the internal space of the casing, and then the auger is pulled out; (f) The erection pile is inserted into the cement grout; (g) After the cement grout has initially solidified, dry sand and gravel are backfilled on top of the cement grout; and (h) The casing is pulled out. 如請求項7所述的營建立樁之施工方法,其中,在該步驟(a)中,該套管之材質為鋼材。The construction method for constructing piles as described in claim 7, wherein in step (a), the casing is made of steel. 如請求項7所述的營建立樁之施工方法,其中,在該步驟(a)中,該套管是藉由數個螺栓接合於該馬達。The construction method for constructing a pile as described in claim 7, wherein in step (a), the sleeve is connected to the motor by a number of bolts. 如請求項7所述的營建立樁之施工方法,其中,在該步驟(a)中,該套管之直徑為70公分至100公分,且長度為3公尺至15公尺。The construction method for constructing a pile as described in claim 7, wherein in step (a), the diameter of the casing is 70 cm to 100 cm and the length is 3 m to 15 m. 如請求項7所述的營建立樁之施工方法,其中,在該步驟(b)中,當該套管鑽入該軟土基地至該預定深度時,仍保留長度約1.2公尺的該套管位於地面以上。The construction method for constructing a pile as described in claim 7, wherein in step (b), when the casing is drilled into the soft soil base to the predetermined depth, the casing with a length of approximately 1.2 meters remains above the ground. 如請求項7所述的營建立樁之施工方法,其中,在該步驟(f)中,該營建立樁為H型鋼。The construction method for constructing a pile as described in claim 7, wherein in step (f), the pile is an H-beam.
TW113133851A 2024-09-06 2024-09-06 Construction method of building piles TWI888268B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
TW113133851A TWI888268B (en) 2024-09-06 2024-09-06 Construction method of building piles

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
TW113133851A TWI888268B (en) 2024-09-06 2024-09-06 Construction method of building piles

Publications (2)

Publication Number Publication Date
TWI888268B TWI888268B (en) 2025-06-21
TW202611370A true TW202611370A (en) 2026-03-16

Family

ID=97227764

Family Applications (1)

Application Number Title Priority Date Filing Date
TW113133851A TWI888268B (en) 2024-09-06 2024-09-06 Construction method of building piles

Country Status (1)

Country Link
TW (1) TWI888268B (en)

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103046557A (en) * 2012-12-04 2013-04-17 北京建材地质工程公司 Foundation pit water-sealing supporting method by using long spiral cement soil mixing structural steel pile
CN110144886A (en) * 2019-05-16 2019-08-20 深圳市工勘岩土集团有限公司 Deep soft stratum long spire is with pipe, churning driven pore-creating filling pile construction method

Similar Documents

Publication Publication Date Title
CN106013151A (en) Continuous pile wall construction method and construction device used for continuous pile wall construction method
CN109763827A (en) A shaft shield construction method and shaft shield machine
CN105569560A (en) Full casing type long auger drilled pile driver and construction method using the pile driver
JP2012112149A (en) Pile removal and backfill method and connection structure of backfill agent supply pipes
JP4974364B2 (en) Pile burying method
CN114108611B (en) A Construction Method of Large-diameter Concrete Steel Tube Variable-diameter Pile Foundation
KR101195235B1 (en) Underground structure construction method using composite pile
KR20050040044A (en) Ground boring method using double rock excavation
CN209958343U (en) Connecting joint for connecting reinforced concrete cast-in-place piles
KR100255423B1 (en) Method and apparatus of pipe for foundation construction
CN114622548A (en) Bored concrete pile pore-forming construction structure for complex stratum
CN205742191U (en) A kind of piling wall constructing device continuously
CN114622549A (en) Bored concrete pile hole-forming construction method for complex stratum
JP4074198B2 (en) How to remove existing piles
TW202611370A (en) Construction methods for building piles
CN112681296A (en) Full-casing construction method for rotary digging cast-in-place pile
CN115853024B (en) Anti-seepage wall structure and cofferdam anti-seepage construction method
TWI888268B (en) Construction method of building piles
JP3165997B2 (en) Casting method and equipment for sheet piles
JPH03257215A (en) Pile constructing method
CN111088796A (en) Resistance-reducing pile planting and long-distance pile feeding method for in-situ reinforcement of stratum
JP2006037491A (en) Expanded pile and construction method of the expanded pile
CN116464080B (en) Construction method for hole guiding of locking steel pipe pile cofferdam
CN214033683U (en) Pile forming structure of full casing cast-in-situ bored pile
JP3099041B2 (en) Pile construction method