TW202037421A - Forging-drawing forming method for aluminum alloy pipe fitting - Google Patents
Forging-drawing forming method for aluminum alloy pipe fitting Download PDFInfo
- Publication number
- TW202037421A TW202037421A TW108112355A TW108112355A TW202037421A TW 202037421 A TW202037421 A TW 202037421A TW 108112355 A TW108112355 A TW 108112355A TW 108112355 A TW108112355 A TW 108112355A TW 202037421 A TW202037421 A TW 202037421A
- Authority
- TW
- Taiwan
- Prior art keywords
- forging
- forming
- aluminum alloy
- blank material
- axis
- Prior art date
Links
Images
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B21—MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
- B21K—MAKING FORGED OR PRESSED METAL PRODUCTS, e.g. HORSE-SHOES, RIVETS, BOLTS OR WHEELS
- B21K1/00—Making machine elements
- B21K1/14—Making machine elements fittings
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B21—MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
- B21J—FORGING; HAMMERING; PRESSING METAL; RIVETING; FORGE FURNACES
- B21J13/00—Details of machines for forging, pressing, or hammering
- B21J13/02—Dies or mountings therefor
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B21—MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
- B21J—FORGING; HAMMERING; PRESSING METAL; RIVETING; FORGE FURNACES
- B21J3/00—Lubricating during forging or pressing
-
- C—CHEMISTRY; METALLURGY
- C21—METALLURGY OF IRON
- C21D—MODIFYING THE PHYSICAL STRUCTURE OF FERROUS METALS; GENERAL DEVICES FOR HEAT TREATMENT OF FERROUS OR NON-FERROUS METALS OR ALLOYS; MAKING METAL MALLEABLE, e.g. BY DECARBURISATION OR TEMPERING
- C21D9/00—Heat treatment, e.g. annealing, hardening, quenching or tempering, adapted for particular articles; Furnaces therefor
- C21D9/08—Heat treatment, e.g. annealing, hardening, quenching or tempering, adapted for particular articles; Furnaces therefor for tubular bodies or pipes
- C21D9/085—Cooling or quenching
-
- C—CHEMISTRY; METALLURGY
- C22—METALLURGY; FERROUS OR NON-FERROUS ALLOYS; TREATMENT OF ALLOYS OR NON-FERROUS METALS
- C22F—CHANGING THE PHYSICAL STRUCTURE OF NON-FERROUS METALS AND NON-FERROUS ALLOYS
- C22F1/00—Changing the physical structure of non-ferrous metals or alloys by heat treatment or by hot or cold working
- C22F1/04—Changing the physical structure of non-ferrous metals or alloys by heat treatment or by hot or cold working of aluminium or alloys based thereon
Landscapes
- Chemical & Material Sciences (AREA)
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Physics & Mathematics (AREA)
- Thermal Sciences (AREA)
- Crystallography & Structural Chemistry (AREA)
- Materials Engineering (AREA)
- Metallurgy (AREA)
- Organic Chemistry (AREA)
- Forging (AREA)
Abstract
Description
本發明是有關於一種鋁合金管件冷作成型方法,特別是指一種鋁合金管件鍛抽成型方法。The invention relates to a cold forming method for aluminum alloy pipe fittings, in particular to a forging and drawing forming method for aluminum alloy pipe fittings.
台灣公告編號第564857號專利案公開了一種自行車的豎管與前叉的套合結構,一把手穿設於該豎管的一端,該豎管的令一端又插固於一前叉管。Patent No. 564857 of Taiwan Publication No. 564857 discloses a fitting structure between a vertical tube and a front fork of a bicycle. A handle passes through one end of the vertical tube, and one end of the vertical tube is inserted into a front fork tube.
這種豎管因應造型需求以及考慮結構強度,一般是採用熱鍛方式製成。This kind of vertical pipe is generally made by hot forging in response to the modeling requirements and the structural strength.
熱鍛就如其名,材料必須先經過加熱爐加熱至再結晶溫度以上,未達到變態點之溫度範圍內,再進行塑形的一種製程技術。這樣的製程技術,除了必須要有能承受高溫的熱鍛設備、取料設備外,熱鍛加工的模具耗損大,熱鍛作業的能源耗損多,整體而言會導致成本高。Hot forging is just like its name. The material must be heated in a heating furnace to a temperature above the recrystallization temperature and not reach the temperature range of the transformation point, and then a process technology for shaping. In addition to hot forging equipment and reclaiming equipment that can withstand high temperatures, such a process technology requires a large amount of die loss for hot forging processing and high energy consumption for hot forging operations, which leads to high costs as a whole.
因此,本發明之目的,即在提供一種利用冷作成型且可降低成本的鋁合金管件鍛抽成型方法。Therefore, the purpose of the present invention is to provide a method for forging and forming aluminum alloy pipes that utilizes cold forming and can reduce the cost.
於是,本發明鋁合金管件鍛抽成型方法,包含下列步驟:(A)製備一製備一呈中空柱狀的原材料,以及一鍛抽設備,該原材料採用鋁合金材質製成,該鍛抽設備包括一鍛抽模,以及一對應於該鍛抽模的鍛抽頭。(B) 該原材料進行加工並形成一胚材,該胚材沿一軸線延伸,並具有一相交於該軸線的第一端面、一沿該軸線相反於該第一端面的第二端面,以及一連接於該第一端面與該第二端面之間的外周面,該第一端面與該第二端面之間形成一原始長度,該外周面構成一原始外徑,該第一端面、該第二端面與該外周面的粗糙度控制在Ra0.4μm以下,該原始外徑以及該原始長度的尺寸公差在±0.01㎜以下。(C)該胚材進行均質退火:先將該胚材加熱至510℃~410℃,之後隨爐冷卻,以每小時爐內溫度下降10℃,冷卻至200℃~160℃時出爐。(D)檢測該胚材的洛氏硬度標尺HRF的硬度值為60±5度。(E)將該胚材浸漬於一潤滑液槽中,該潤滑液槽中盛放的潤滑液濃度TA40~50,工作溫度80℃~100℃,浸漬預定時間。(F)進行鍛抽作業:將已浸漬過潤滑液的胚材放置於該鍛抽設備的鍛抽模中,且操作該鍛抽頭相對於該鍛抽模趨近,該胚材受該鍛抽頭與該鍛抽模的鍛抽作用而形成一成品,該成品沿該軸線且呈中空管狀,並具有一相交於該軸線的第一側面、一沿該軸線相反於該第一側面的第二側面、一連接於該第一側面與該第二側面之間的外環面,以及一相反於該外環面且圍繞該軸線而可形成一內孔的內環面,該第一側面與該第二側面之間形成一大於該原始長度的延伸長度。Therefore, the aluminum alloy pipe forging and forming method of the present invention includes the following steps: (A) preparing a raw material in the shape of a hollow column, and a forging equipment, the raw material is made of aluminum alloy, and the forging equipment includes A forging die, and a forging tap corresponding to the forging die. (B) The raw material is processed to form a blank, which extends along an axis and has a first end surface intersecting the axis, a second end surface opposite to the first end surface along the axis, and a The outer peripheral surface connected between the first end surface and the second end surface, an original length is formed between the first end surface and the second end surface, the outer peripheral surface constitutes an original outer diameter, the first end surface, the second end surface The roughness of the end surface and the outer peripheral surface is controlled below Ra0.4μm, and the dimensional tolerance of the original outer diameter and the original length is below ±0.01mm. (C) Homogeneous annealing of the blank material: first heat the blank material to 510°C~410°C, and then cool it with the furnace. The furnace temperature drops by 10°C per hour, and it is discharged when it is cooled to 200°C~160°C. (D) The hardness value of the Rockwell hardness scale HRF of the blank material is 60±5 degrees. (E) The blank is immersed in a lubricating fluid tank, the lubricating fluid concentration in the lubricating fluid tank is TA40-50, the working temperature is 80-100°C, and the immersion time is predetermined. (F) Perform forging and drawing operations: place the blank material impregnated with lubricating fluid in the forging die of the forging and drawing equipment, and operate the forging tap to approach the forging die, and the blank material is subjected to the forging tap With the forging and drawing action of the forging die, a finished product is formed along the axis and in a hollow tube shape, and has a first side surface intersecting the axis and a second side surface opposite to the first side surface along the axis , An outer ring surface connected between the first side surface and the second side surface, and an inner ring surface opposite to the outer ring surface and surrounding the axis to form an inner hole, the first side surface and the first side surface An extension length greater than the original length is formed between the two sides.
本發明之功效在於:本發明利用連續步驟,可以利用冷鍛作業製得該成品,可以節省能源、減少模具耗損,並降低整體製造成本。The effect of the present invention is that the present invention utilizes continuous steps and can use cold forging operations to prepare the finished product, can save energy, reduce mold consumption, and reduce overall manufacturing costs.
本發明鋁合金管件鍛抽成型方法之一實施例,包含下列步驟:An embodiment of the method for forging and drawing an aluminum alloy pipe according to the present invention includes the following steps:
步驟一:參閱圖1與圖2,製備一呈中空柱狀的原材料1、一鍛抽設備2,以及一進階成型設備3(見圖4),該原材料1採用鋁合金材質製成(AL6066之鋁鎂矽鋁合金或AL7050之鋁鋅鎂鋁合金),該鍛抽設備2包括一鍛抽模10,以及一對應於該鍛抽模10的鍛抽頭20。該鍛抽模10具有一頂面11,以及一由該頂面11朝下延伸的第一模穴12,本實施例的第一模穴12呈上寬下窄的階級孔狀,該鍛抽頭20也呈上寬下窄的階級柱狀,該鍛抽頭20的階級部位及轉角處均製成圓弧導角。參圖4,該進階成型設備3包括一成型模30,以及一對應於該成型模30的成型頭40,該成型模30具有一第二模穴31,該成型頭40的階級部位及轉角處均製成圓弧導角。Step 1: Referring to Figure 1 and Figure 2, prepare a hollow cylindrical
步驟二:參閱圖1與圖2,該原材料1進行加工並形成一呈中空圓柱狀的胚材1’,該胚材1’沿一軸線L延伸,並具有一垂直相交於該軸線L的第一端面101、一沿該軸線L相反於該第一端面101的第二端面102、一連接於該第一端面101與該第二端面102之間的外周面103,以及一相反於該外周面103且圍繞該軸線L而可形成一中心孔104的內周面105,該第一端面101與該第二端面102之間形成一原始長度l,該外周面103構成一原始外徑D,該內周面105構成一原始內徑d,該第一端面101、該第二端面102、該內周面105與該外周面103的粗糙度控制在Ra0.4μm以下,該原始內徑d、該原始外徑D以及該原始長度l的尺寸公差在±0.01㎜以下。Step 2: Referring to Figures 1 and 2, the
步驟三:該胚材1’進行均質退火:先將該胚材1’加熱至510℃~410℃,之後隨爐冷卻,以每小時爐內溫度下降10℃,冷卻至200℃~160℃時出爐。Step 3: Homogeneous annealing of the blank material 1': first heat the blank material 1'to 510°C~410°C, and then cool down with the furnace, and then cool down to 200°C~160°C by 10°C per hour. Baked.
步驟四:檢測均質退火後的該胚材1’,該胚材1’的洛氏硬度標尺HRF的硬度值必須達到60±5度。檢測該胚材1’時,是沿該軸線L等間距地對該胚材1’的外周面103進行多點檢測,以及沿該軸線L等間距地對該內周面105進行多點檢測。Step 4: Detect the blank material 1'after homogeneous annealing, the hardness value of the Rockwell hardness scale HRF of the blank material 1'must reach 60±5 degrees. When detecting the blank material 1', the outer
步驟五:將該胚材1’浸漬於一潤滑液槽(圖未示)中,該潤滑液槽中盛放的潤滑液濃度TA40~50,工作溫度80℃~100℃,浸漬預定時間,該潤滑液為氮化硼。Step 5: Immerse the blank material 1'in a lubricating fluid tank (not shown), the lubricating fluid concentration in the lubricating fluid tank is TA40~50, the working temperature is 80℃~100℃, and the immersion time is predetermined. The lubricating fluid is boron nitride.
步驟六:配合參圖3,進行鍛抽作業:將已浸漬過潤滑液的胚材1’放置於該鍛抽設備2的鍛抽模10的模穴12開口中,且操作該鍛抽頭20相對於該鍛抽模10趨近,該胚材1’受該鍛抽頭20與該鍛抽模10的鍛抽作用而形成一成品100,該成品100沿該軸線L且呈中空管狀,並具有一垂直相交於該軸線L的第一側面110、一沿該軸線L相反於該第一側面110的第二側面120、一連接於該第一側面110與該第二側面120之間的外環面130,以及一相反於該外環面130且圍繞該軸線L而可形成一內孔140的內環面150,該第一側面110與該第二側面120之間形成一大於該原始長度l的延伸長度l’,該內孔140平行於該軸線L的輪廓形狀對應於該鍛抽頭20的輪廓形狀。Step 6: With reference to Figure 3, perform the forging operation: Place the blank material 1'that has been immersed in the lubricating fluid in the opening of the
步驟七:如圖3及圖4所示,進階成型作業:將該成品100放置於該進階成型設備3的鍛抽模10的第二模穴31中,且操作該成型頭40相對於該成型模30趨近,該成品100受該成型頭40與該成型模30的成型作用而塑形成一造型成品100’。Step 7: As shown in Figures 3 and 4, the advanced forming operation: place the finished
因此,本發明利用上述步驟一至步驟七的連續步驟,可使該原材料1鍛抽形成該造型成品100’,且該造型成品100’ 可以避免金屬加熱出現的缺陷,獲得較高的精度和表面質量,並能提高工件的強度和硬度,冷鍛變形抗力大。亦即,利用該步驟二將該原材料1加工形成該胚材1’,則使該胚材1’的各個面的粗糙度控制在Ra0.4μm以下,該原始內徑d、該原始外徑D以及該原始長度l的尺寸公差在±0.01㎜以下,則使得鍛抽後的成品100不需在進行表面的精密加工,該鍛抽設備2與進階成型設備3也較不容易損耗,再利用步驟三之均質退火,可提高該胚材1’的可塑性,以利用後續的鍛抽作業,且使鍛抽後的成品100減少殘餘應力、提高組織和成分的均勻化。Therefore, the present invention utilizes the continuous steps from
所以,本發明鋁合金管件鍛抽成型方法,不需要設置高溫的熱鍛設備、取料設備,且利用步驟二的前置加工,除了可精進成品100的精密度外,更可減少模具的耗損、延長該鍛抽設備2與該進階成型設備3的使用壽命,可降低整體的能源耗損低,且可降低製造成本高。Therefore, the aluminum alloy pipe forging and forming method of the present invention does not require high-temperature hot forging equipment and reclaiming equipment, and the pre-processing of step two can not only improve the precision of the finished
值得一提的是,當該成品100已達到預期的使用目的時,可以省略步驟七的進階成型作業,也就是說,步驟七的進階成型作業是因應具有造型需求的造型成品100’才需要進行。It is worth mentioning that when the finished
另外,該步驟五的胚材1’浸漬於潤滑液槽中的時間,依胚材1’數量的不同而有所差異,當胚材1’數量為單支時,浸漬時間為4~5分鐘,當胚材1’數量為複數時,浸漬時間為25~35分鐘。In addition, the time for the blank material 1'to be immersed in the lubricating fluid tank in
再者,本發明步驟一所製備呈中空柱狀的原材料1,其製成的方式有下列A、B、C等三種(配合參圖5):Furthermore, the hollow columnar
A、取一圓柱材4,並對該圓柱材4進行車削加工,使該圓柱材4的尺寸及表面粗糙度達到預定精度,接著,以一預鍛抽設備(圖未示)進行預鍛抽作業,並製得一具有一呈單向開放的U形孔401’的雛胚4’,對該雛胚4’進行切削,且將該U形孔401’的盲端切除,即可製得呈中空柱狀的原材料1。A. Take a
B、取一中空柱材5,並對該中空柱材5進行車削加工,使該中空柱材5的尺寸及表面粗糙度達到預定精度,接著,以一預鍛抽設備(圖未示)進行預鍛抽作業,並製得一具有一階級孔501’的雛胚5’,對該雛胚5’進行切削,且將該階級孔501’的一小徑段及一大徑段的局部切除,即可製得呈中空柱狀的原材料1。B. Take a
C、取一圓柱材6,並對該圓柱材6進行第一次粗車削加工,接著,以一第一預鍛抽設備(圖未示)進行第一次預鍛抽作業,並製得一具有一呈單向開放的淺U形孔601’的粗胚6’,對該粗胚6’進行第二次細車削加工,使該雛胚6’的尺寸及表面粗糙度達到預定精度(尺寸校準),再以一第二預鍛抽設備(圖未示)進行第二次預鍛抽作業,並製得一具有一呈單向開放的深U形孔601”的雛胚6”,最後再對該雛胚6”進行切削,且將該深U形孔601”的盲端切除,即可製得呈中空柱狀的原材料1。C. Take a
綜上所述,本發明鋁合金管件鍛抽成型方法,整體製程簡單、設備容易,且可有效降低成本、節省能源及提高成品的品質,確實能達成本發明之目的。In summary, the aluminum alloy pipe forging and forming method of the present invention has simple overall manufacturing process and easy equipment, and can effectively reduce costs, save energy and improve the quality of finished products, and can indeed achieve the purpose of cost invention.
惟以上所述者,僅為本發明之實施例而已,當不能以此限定本發明實施之範圍,凡是依本發明申請專利範圍及專利說明書內容所作之簡單的等效變化與修飾,皆仍屬本發明專利涵蓋之範圍內。However, the above are only examples of the present invention. When the scope of implementation of the present invention cannot be limited by this, all simple equivalent changes and modifications made in accordance with the scope of the patent application of the present invention and the content of the patent specification still belong to This invention patent covers the scope.
1:原材料
2:鍛抽設備
10:鍛抽模
11:頂面
12:第一模穴
20:鍛抽頭
3:進階成型設備
30:成型模
31:第二模穴
40:成型頭
1’:胚材
L:軸線
101:第一端面
102:第二端面
103:外周面
104:中心孔
105:內周面
l:原始長度
D:原始外徑
d:原始內徑
100:成品
110:第一側面
120:第二側面
130:外環面
140:內孔
150:內環面
l’:延伸長度
100’造型成品
4:圓柱材
4’:雛胚
401’U形孔
5:中空柱材
5’:雛胚
501’階級孔
6:圓柱材
601’:淺U形孔深
601”:U形孔
6”:雛胚
1: raw materials
2: Forging equipment
10: Forging die
11: top surface
12: The first cavity
20: Forged tap
3: Advanced molding equipment
30: Forming mold
31: The second cavity
40: Forming head
1’: Embryo
L: axis
101: first end face
102: second end face
103: Outer peripheral surface
104: Center hole
105: inner circumference
l: original length
D: Original outer diameter
d: Original inner diameter
100: finished product
110: first side
120: second side
130: outer ring surface
140: inner hole
150: inner ring surface
l’:
本發明之其他的特徵及功效,將於參照圖式的實施方式中清楚地呈現,其中: 圖1是本發明鋁合金管件鍛抽成型方法一實施例的一製造流程方塊圖; 圖2是該實施例的一原材料與鍛抽設備的平面示意圖; 圖3是該實施例的一鍛抽成型示意圖; 圖4是該實施例之一進階成型設備的平面示意圖;及 圖5是該實施例之一原材料的製成方式。Other features and effects of the present invention will be clearly presented in the embodiments with reference to the drawings, in which: 1 is a block diagram of a manufacturing process of an embodiment of the forging and forming method of an aluminum alloy pipe according to the present invention; Figure 2 is a schematic plan view of a raw material and forging equipment of the embodiment; Figure 3 is a schematic diagram of forging and forming of the embodiment; Figure 4 is a schematic plan view of one of the advanced molding equipment of the embodiment; and Figure 5 shows the method of making one of the raw materials in this embodiment.
Claims (9)
Priority Applications (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
TW108112355A TWI679070B (en) | 2019-04-09 | 2019-04-09 | Forging and drawing method for aluminum alloy pipe fittings |
US16/733,459 US11638943B2 (en) | 2019-04-09 | 2020-01-03 | Method for manufacturing cold-forged, extruded aluminum alloy tube |
CN202010037760.5A CN111167993B (en) | 2019-04-09 | 2020-01-14 | Forging and drawing forming method for aluminum alloy pipe fitting |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
TW108112355A TWI679070B (en) | 2019-04-09 | 2019-04-09 | Forging and drawing method for aluminum alloy pipe fittings |
Publications (2)
Publication Number | Publication Date |
---|---|
TWI679070B TWI679070B (en) | 2019-12-11 |
TW202037421A true TW202037421A (en) | 2020-10-16 |
Family
ID=69582314
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
TW108112355A TWI679070B (en) | 2019-04-09 | 2019-04-09 | Forging and drawing method for aluminum alloy pipe fittings |
Country Status (2)
Country | Link |
---|---|
CN (1) | CN111167993B (en) |
TW (1) | TWI679070B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
TWI744154B (en) * | 2020-12-29 | 2021-10-21 | 金允成企業股份有限公司 | Aluminum alloy rod forging and forming method |
TWI802848B (en) * | 2021-02-19 | 2023-05-21 | 陳俊宏 | Forging method of standpipe |
Family Cites Families (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP3517522B2 (en) * | 1996-06-21 | 2004-04-12 | 日本パーカライジング株式会社 | Water-based lubricant for cold plastic working of metallic materials |
JPH10183160A (en) * | 1996-12-25 | 1998-07-14 | Sumitomo Metal Ind Ltd | Lubricant composition for high-temperature metal working and tube punching using the same |
IN192718B (en) * | 1998-06-09 | 2004-05-15 | Nihon Parkerizing | |
KR100621693B1 (en) * | 2000-08-07 | 2006-09-08 | 니혼 파커라이징 가부시키가이샤 | Aqueous lubricant for plastic working of metallic material and method of lubricant film processing |
TW588108B (en) * | 2000-08-07 | 2004-05-21 | Nihon Parkerizing | Aqueous lubricant for plastic working of metallic material and method for forming lubricant film |
JP2002307124A (en) * | 2001-04-12 | 2002-10-22 | Hiraguchi Seitan Kk | Cold forging method of aluminum metal parts |
CN1438080A (en) * | 2002-02-10 | 2003-08-27 | 利奇机械工业股份有限公司 | Method for producing aluminium by colol extrusion |
US7140226B2 (en) * | 2002-08-05 | 2006-11-28 | Giant Manufacturing Co., Ltd. | Methods for making a bicycle frame part having a disproportionally enlarged end section |
CN102430676A (en) * | 2010-09-29 | 2012-05-02 | 比亚迪股份有限公司 | Cold forging method for aluminum alloy structural member |
CN102688966B (en) * | 2011-03-24 | 2015-06-24 | 比亚迪股份有限公司 | Cold forging method and metal housing processing method |
CN102950445A (en) * | 2011-08-23 | 2013-03-06 | 宝山钢铁股份有限公司 | High-performance hexagonal cold-drawn steel of S2 tool steel and production method thereof |
CN104209361A (en) * | 2013-06-03 | 2014-12-17 | 宝钢特钢有限公司 | Preparation method of 30CrMnSiA hexagonal cold drawn material |
CN104561651B (en) * | 2013-10-11 | 2017-05-17 | 东港市东方高新金属材料有限公司 | Titanium alloy (Ti5563) rolled pipe and preparation method thereof |
KR20170061731A (en) * | 2015-11-26 | 2017-06-07 | 주식회사 세림티앤디 | Vehicle Brake Chamber Push Rod Frging Producing Method and Mold |
CN106269979A (en) * | 2016-08-26 | 2017-01-04 | 余姚市婉珍五金厂 | A kind of seamless pipe cold-extrusion technology |
CN109261743A (en) * | 2018-07-27 | 2019-01-25 | 柳州市横阳机械有限公司 | A kind of processing method of cold tube rolling |
-
2019
- 2019-04-09 TW TW108112355A patent/TWI679070B/en active
-
2020
- 2020-01-14 CN CN202010037760.5A patent/CN111167993B/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
TWI744154B (en) * | 2020-12-29 | 2021-10-21 | 金允成企業股份有限公司 | Aluminum alloy rod forging and forming method |
TWI802848B (en) * | 2021-02-19 | 2023-05-21 | 陳俊宏 | Forging method of standpipe |
Also Published As
Publication number | Publication date |
---|---|
CN111167993A (en) | 2020-05-19 |
CN111167993B (en) | 2022-09-09 |
TWI679070B (en) | 2019-12-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108580778B (en) | Forging method of thin-wall deep-cavity airplane hub die forging | |
US11638943B2 (en) | Method for manufacturing cold-forged, extruded aluminum alloy tube | |
CN107159830A (en) | Forging method | |
TW202037421A (en) | Forging-drawing forming method for aluminum alloy pipe fitting | |
CN103658478B (en) | The manufacture method of nuclear power evaporator transition cone forge piece | |
CN105252230A (en) | Machining process for inclined tee | |
CN105855321A (en) | Preparation method of multi-head internal thread seamless steel tube for high pressure boiler | |
CN104439032B (en) | valve body forging method | |
CN104368724A (en) | Forging forming process for large thick-wall end socket with bearing and nozzle | |
CN112191787A (en) | Processing method of titanium alloy die forging | |
US20120090375A1 (en) | Zoning closed-die extruding device and method | |
CN108237197B (en) | A kind of forging method improving the flaw detection of structural steel large-sized ring part | |
TWI744154B (en) | Aluminum alloy rod forging and forming method | |
US11872616B2 (en) | Method for manufacturing cold-forged, extruded aluminum alloy tube | |
TWI719750B (en) | Forging and forming method of aluminum alloy pipe fittings | |
CN104308056B (en) | The hot forging forming method of cylindrical forged piece | |
CN103286153A (en) | Manufacture method of ultra-large-diameter pipeline extruded nozzles | |
RU2527518C1 (en) | Ball valve semi-body with flange and method of its production | |
RU2502576C1 (en) | Method of making thin-wall large-sized shells by rotary drawing | |
CN110877091B (en) | Hot forging forming process method of steering knuckle arm | |
CN101712108A (en) | Method for manufacturing conical riser of direction column of motorcycle by adopting cold extrusion process | |
CN114192712B (en) | Die forging forming die and die forging forming method for large L-shaped hollow thin-wall pipeline | |
CN108760430A (en) | A kind of assay method of titanium alloy plate hot forming limit curve | |
CN108801801B (en) | A kind of measuring method of sheet alloy hot forming limit curve | |
RU2539799C2 (en) | Production of thin-wall pipes of higher precision from alloyed copper-based strain-hardened alloys |