SA521430384B1 - طريقة ونظام بناء نفق تحت الأرض - Google Patents

طريقة ونظام بناء نفق تحت الأرض

Info

Publication number
SA521430384B1
SA521430384B1 SA521430384A SA521430384A SA521430384B1 SA 521430384 B1 SA521430384 B1 SA 521430384B1 SA 521430384 A SA521430384 A SA 521430384A SA 521430384 A SA521430384 A SA 521430384A SA 521430384 B1 SA521430384 B1 SA 521430384B1
Authority
SA
Saudi Arabia
Prior art keywords
drilling
bore
along
bores
tunnel
Prior art date
Application number
SA521430384A
Other languages
Arabic (ar)
English (en)
Inventor
جوردان ستيفن
Original Assignee
هايبر تانل اي بي ليمتد
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by هايبر تانل اي بي ليمتد filed Critical هايبر تانل اي بي ليمتد
Publication of SA521430384B1 publication Critical patent/SA521430384B1/ar

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/08Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining with additional boring or cutting means other than the conventional cutting edge of the shield
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/02Drilling rigs characterised by means for land transport with their own drive, e.g. skid mounting or wheel mounting
    • E21B7/025Rock drills, i.e. jumbo drills
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/005Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by forcing prefabricated elements through the ground, e.g. by pushing lining from an access pit
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/03Driving non-circular tunnels
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/0621Shield advancing devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/10Making by using boring or cutting machines

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Soil Sciences (AREA)
  • Physics & Mathematics (AREA)
  • Fluid Mechanics (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)
  • Sampling And Sample Adjustment (AREA)
  • Geophysics And Detection Of Objects (AREA)
  • Lining And Supports For Tunnels (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
  • Earth Drilling (AREA)
SA521430384A 2019-03-22 2021-09-22 طريقة ونظام بناء نفق تحت الأرض SA521430384B1 (ar)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
GB1903979.1A GB2582376B (en) 2019-03-22 2019-03-22 Method and system of constructing an underground tunnel
PCT/GB2020/050756 WO2020193960A1 (en) 2019-03-22 2020-03-20 Method and system of constructing an underground tunnel

Publications (1)

Publication Number Publication Date
SA521430384B1 true SA521430384B1 (ar) 2022-06-27

Family

ID=66381560

Family Applications (1)

Application Number Title Priority Date Filing Date
SA521430384A SA521430384B1 (ar) 2019-03-22 2021-09-22 طريقة ونظام بناء نفق تحت الأرض

Country Status (19)

Country Link
US (2) US11591908B2 (https=)
EP (2) EP4019737A1 (https=)
JP (2) JP2022524893A (https=)
CN (1) CN113692476A (https=)
AU (2) AU2020249771B2 (https=)
BR (1) BR112021018735A2 (https=)
CA (2) CA3133618C (https=)
DK (1) DK3942154T3 (https=)
EA (1) EA202192429A1 (https=)
ES (1) ES2927425T3 (https=)
GB (1) GB2582376B (https=)
MX (1) MX2021011532A (https=)
MY (1) MY209706A (https=)
PL (1) PL3942154T3 (https=)
PT (1) PT3942154T (https=)
SA (1) SA521430384B1 (https=)
SG (1) SG11202110350UA (https=)
WO (1) WO2020193960A1 (https=)
ZA (2) ZA202106987B (https=)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2582376B (en) * 2019-03-22 2021-06-09 Hypertunnel Ip Ltd Method and system of constructing an underground tunnel
CN111119913B (zh) * 2020-02-24 2024-05-17 中铁二院工程集团有限责任公司 一种隧道施工中tbm脱困处理方法及隧道施工结构
GB2592699B (en) * 2020-09-21 2022-03-16 Hypertunnel Ip Ltd Tunnelling shield
CN112267899A (zh) * 2020-10-12 2021-01-26 广东冠粤路桥有限公司 一种隧道出洞施工方法
WO2023082168A1 (zh) * 2021-11-12 2023-05-19 于宙 一种钻地机器人和免开挖地面的管道铺设方法
AU2022462279A1 (en) * 2022-06-10 2025-01-02 Epiroc Rock Drills Aktiebolag Control system, drill rig and method therein
GB2638709A (en) * 2024-02-28 2025-09-03 Hypertunnel Ip Ltd A pipe for lining a bore drilled by directional drilling apparatus and a method of conveying material underground

Family Cites Families (40)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US528367A (en) * 1894-10-30 Robert l
FR1363959A (fr) * 1963-04-05 1964-06-19 Perfectionnements au creusement des puits et des galeries dans les sables et terrainsaquifères
US3943722A (en) * 1970-12-31 1976-03-16 Union Carbide Canada Limited Ground freezing method
US4017121A (en) * 1974-11-25 1977-04-12 Allied Chemical Corporation Longwall mining of trona with prefracturing to prevent slabbing
JPS5236834U (https=) * 1975-09-09 1977-03-15
JPS5236834A (en) 1975-09-18 1977-03-22 Nippon Kokan Kk <Nkk> Quake resisting wall made of steel
JPS5918895A (ja) * 1982-07-24 1984-01-31 古河鉱業株式会社 トンネルの掘進方法およびトンネル掘進機
JPS62273392A (ja) * 1986-05-19 1987-11-27 鹿島建設株式会社 液圧チユ−ブによるトンネル掘削工法
JPS63194098A (ja) * 1987-02-06 1988-08-11 鉄建建設株式会社 シ−ルドトンネルの覆工方法
JP2593356B2 (ja) * 1990-03-16 1997-03-26 清水建設株式会社 トンネル構築工法
JP2932197B2 (ja) * 1990-03-28 1999-08-09 株式会社間組 大断面ないし超大断面トンネルの掘削工法
WO1991016524A1 (fr) * 1990-04-25 1991-10-31 Kabushiki Kaisha Komatsu Seisakusho Procede de creusement d'un tunnel
JPH06102957B2 (ja) * 1990-08-24 1994-12-14 鉄建建設株式会社 シールドトンネルの地中接合方法
JP2920851B2 (ja) * 1991-04-02 1999-07-19 清水建設株式会社 コンクリート壁面の補修方法
JPH0742483A (ja) * 1993-07-28 1995-02-10 Tekken Constr Co Ltd 「全面開放型シールド掘進機」
CA2102760C (en) * 1993-11-09 1996-12-03 David M. Brown Underground horizontal pipe installation method and apparatus
JP3567939B2 (ja) * 1994-05-09 2004-09-22 鉄建建設株式会社 トンネルの築造方法
JP2874561B2 (ja) * 1994-07-22 1999-03-24 株式会社大林組 導坑による先行脚部補強型フォアパイリング工法
JPH11280093A (ja) * 1998-03-27 1999-10-12 Hazama Gumi Ltd 地下岩盤タンクの水封構造
US6520718B1 (en) * 1998-11-27 2003-02-18 Shigeki Nagatomo, Et Al. Sardine-bone construction method for large-section tunnel
JP2001254595A (ja) * 2000-03-10 2001-09-21 Maeda Corp トンネル掘削装置
JP3391444B2 (ja) * 2000-10-30 2003-03-31 株式会社アグルー・ジャパン トンネルライニング方法
JP4480907B2 (ja) * 2001-02-15 2010-06-16 島田 巌乃 トンネルの掘削工法
JP4253801B2 (ja) * 2004-09-30 2009-04-15 清水建設株式会社 トンネル構築工法
JP4425299B2 (ja) 2007-08-02 2010-03-03 大豊建設株式会社 地盤改良方法およびシールド
CN101403314B (zh) * 2008-11-18 2011-03-23 河南理工大学 煤矿井下钻孔水力压裂增透抽采瓦斯工艺
JP5642130B2 (ja) * 2012-02-23 2014-12-17 日本シビックコンサルタント株式会社 トンネルボーリングマシン
US10094172B2 (en) * 2012-08-23 2018-10-09 Ramax, Llc Drill with remotely controlled operating modes and system and method for providing the same
JP5807096B2 (ja) * 2014-07-08 2015-11-10 鹿島建設株式会社 地下構造物および地下構造物の断面構造
CN104863602B (zh) * 2015-04-09 2018-08-10 重庆大学 一种土质盾构隧道施工病害超前预报方法
CN105756700B (zh) * 2016-03-11 2019-01-22 中铁十八局集团有限公司 超大断面隧道穿煤系地层段的施工方法及封孔结构
CN105822316B (zh) * 2016-03-18 2019-06-18 张清林 一体式坑隧道掘进机
JP2017172280A (ja) * 2016-03-25 2017-09-28 清水建設株式会社 本体覆工壁およびその施工方法
CN106089174B (zh) * 2016-06-30 2019-05-14 太原理工大学 水压致裂化学膨胀剂充填快速掘进巷道的方法
CN106050243B (zh) * 2016-07-28 2019-01-22 中冶建工集团有限公司 超浅埋小间距大断面的多隧道并行施工方法
CA3036222A1 (en) * 2016-09-09 2018-03-15 Schlumberger Canada Limited Drilling and stimulating of subterranean formation
KR101922175B1 (ko) * 2017-03-06 2018-11-27 주식회사 장평건설 다중 와이어쏘를 이용한 암벽 절삭장치 및 절삭방법과 이를 이용한 굴착공법
KR101910351B1 (ko) * 2017-10-26 2018-10-23 주식회사 건석이엔지 천공 절단식 암벽 굴착 공법과 이를 위한 천공기구
CN107905834A (zh) * 2017-12-20 2018-04-13 中原工学院 一种低渗高突煤层体系化瓦斯开采方法
GB2582376B (en) * 2019-03-22 2021-06-09 Hypertunnel Ip Ltd Method and system of constructing an underground tunnel

Also Published As

Publication number Publication date
US20220003115A1 (en) 2022-01-06
BR112021018735A2 (pt) 2021-12-21
EA202192429A1 (ru) 2021-12-13
ES2927425T3 (es) 2022-11-04
GB201903979D0 (en) 2019-05-08
EP4019737A1 (en) 2022-06-29
ZA202400177B (en) 2024-05-30
CA3133618A1 (en) 2020-10-01
CA3149384C (en) 2023-11-14
CN113692476A (zh) 2021-11-23
JP2022524893A (ja) 2022-05-10
PL3942154T3 (pl) 2022-11-07
AU2023201956B2 (en) 2024-07-11
CA3133618C (en) 2022-04-05
MY209706A (en) 2025-07-30
WO2020193960A1 (en) 2020-10-01
US12378884B2 (en) 2025-08-05
MX2021011532A (es) 2021-10-22
AU2023201956A1 (en) 2023-05-18
AU2020249771A1 (en) 2021-10-14
EP3942154B1 (en) 2022-08-17
CA3149384A1 (en) 2020-10-01
DK3942154T3 (da) 2022-10-03
GB2582376B (en) 2021-06-09
GB2582376A (en) 2020-09-23
AU2020249771B2 (en) 2023-04-27
EP3942154A1 (en) 2022-01-26
JP2023113780A (ja) 2023-08-16
ZA202106987B (en) 2024-04-24
US11591908B2 (en) 2023-02-28
PT3942154T (pt) 2022-10-17
SG11202110350UA (en) 2021-10-28
US20230175395A1 (en) 2023-06-08

Similar Documents

Publication Publication Date Title
SA521430384B1 (ar) طريقة ونظام بناء نفق تحت الأرض
Bertuzzi Sydney sandstone and shale parameters for tunnel design
CN102296963B (zh) 特长深埋公路隧道的施工工法
AU2017405410A1 (en) Networked preferential gas migration passage construction and gas diversion drainage method
Gong et al. TBM tunneling in marble rock masses with high in situ stress and large groundwater inflow: a case study in China
CL2022003273A1 (es) Metodo de excavacion de cuevas para extraer un mineral de un yacimiento, y una infraestructura de mineria, sistema de monitoreo, maquinaria, sistema de control y medio de datos para el mismo
EA201391266A1 (ru) Способ и система для определения параметров формации
Do Ngoc et al. Prediction of surface settlement due to twin tunnel construction in soft ground of Hanoi metro line 03
AU2016393203A8 (en) Seismic well ties using blocking schemes
Diering Tunnels under pressure in an ulta-deep Witwatersrand gold mine
SE1750208A1 (en) Method and system for generating a drilling pattern
CN110939454A (zh) 一种隧道千米以上超前地质预报方法
Chilala et al. Initial effects of improved drill and blast practices on stope stability at Acacia’s Bulyanhulu Mine
CN102003191B (zh) 一种矿山帷幕注浆效果判定方法
Chinyowa et al. A review of pillar design for platinum mining to enhance stability: a Zimbabwean case study
Leeman The measurement of stress in rock: Part III: the results of some rock stress investigations
Shen et al. Interpretation of Interwell Chemical Tracer Tests in Layered Heterogeneous Reservoirs with Crossflow
Newman et al. Using tunnel boring data to augment the geological model
GB2573973A (en) System and method for providing a continuous wellbore survey
Thorpe Design and construction of a sprayed-concrete-lined quarry tunnel in the UK
Azhari et al. Greenfield settlement of kvmrt ssp line 2 in kuala lumpur limestone formation
Wang et al. Critical distance between copper mining roadway and a vertical water-blocked body
Vander Veer Report on the Lone Pine properties in the Cripple Creek district, Teller Co., Colo.
Giles The Chabrières Tunnel, Alpes-de-Haute-Provence, France
Trinh et al. Construction and Monitoring System for the Follobanen Tunnels Under Existing Ekeberg Tunnels in Oslo, Norway