RU2242559C1 - Method for cyclic movement of solid reinforced concrete bridge span in longitudinal direction - Google Patents

Method for cyclic movement of solid reinforced concrete bridge span in longitudinal direction Download PDF

Info

Publication number
RU2242559C1
RU2242559C1 RU2004104737/03A RU2004104737A RU2242559C1 RU 2242559 C1 RU2242559 C1 RU 2242559C1 RU 2004104737/03 A RU2004104737/03 A RU 2004104737/03A RU 2004104737 A RU2004104737 A RU 2004104737A RU 2242559 C1 RU2242559 C1 RU 2242559C1
Authority
RU
Russia
Prior art keywords
sections
span
concreting
section
reinforcement
Prior art date
Application number
RU2004104737/03A
Other languages
Russian (ru)
Inventor
П.П. Куракин (RU)
П.П. Куракин
В.Н. Коротин (RU)
В.Н. Коротин
В.В. Чаленко (RU)
В.В. Чаленко
С.В. Дударев (RU)
С.В. Дударев
н А.С. Мелкон (RU)
А.С. Мелконян
Е.Н. Бирюков (RU)
Е.Н. Бирюков
С.В. Потапов (RU)
С.В. Потапов
Original Assignee
Открытое акционерное общество "Мостотрест"
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Открытое акционерное общество "Мостотрест" filed Critical Открытое акционерное общество "Мостотрест"
Priority to RU2004104737/03A priority Critical patent/RU2242559C1/en
Application granted granted Critical
Publication of RU2242559C1 publication Critical patent/RU2242559C1/en

Links

Images

Abstract

FIELD: building, particularly erection of preloaded reinforced concrete span structure having different span types and cross-sections.
SUBSTANCE: method is used for erecting span structure above existent buildings, structures, service lines, deep ravines and other barriers arranged along bridge axis. Bridge has side walls or ribs, upper or lower plates and straight reinforcement arranged in upper plate and located from inner surface of side walls or ribs. Method of bridge movement to piers involves concreting span structure sections in concrete form; reinforcing thereof and connecting the first one of formed sections to launching nose having length equal to 50%-60% of that of span structure section to be connected with it; moving above section by push jack and connecting next sections; arranging tightened through bundle of reinforcement in side walls thereof and in ribs after all span structure sections installation in design position; connecting reinforcement of all span structure sections. Form is made of two parts having sliding blocks, namely the first, lower, block supported by four hydraulic jacks and used for concreting lower plate, and the second block used for concreting side walls or ribs and upper plate. Section form is arranged behind push jacks along one concreting section. Launching nose is connected to front span structure section by means of single strands tightened by single-strand jacks. Movement is carried out with the speed of 7.5-12.5 m/h with push jack force not exceeding half of vertical force created by lifting jacks additionally used for span structure section movement. Length of through reinforcement bundle is not less than summary length of three span structure sections.
EFFECT: reduced time for bridge building and carrying out special supplementary works in spans.
3 dwg

Description

Предлагаемый способ относится к сооружению преднапряженного железобетонного пролетного строения различных пролетов и поперечных сечений. Особенно этот способ эффективен при необходимости сооружения пролетных строений над существующими зданиями, сооружениями, коммуникациями, глубокими оврагами и другими преградами, расположенными на оси моста.The proposed method relates to the construction of prestressed reinforced concrete spans of various spans and cross sections. This method is especially effective when it is necessary to construct spans over existing buildings, structures, communications, deep ravines and other obstacles located on the axis of the bridge.

Известные способы сооружения железобетонных пролетных строений различной длины методами навесного монтажа сборных железобетонных блоков, навесного бетонирования отдельными секциями, монтажа отдельных сборных балок с последующим объединением в неразрезность над опорами или вблизи опор, а также метод бетонирования пролетного строения на сплошных подмостях не могут быть применены при прохождении трассы моста над зданиями, сооружениями и другими препятствиями из-за ограниченности строительной высоты или невозможности расположить подмости и монтажное крановое оборудование на существующей застройке.Known methods for constructing reinforced concrete spans of various lengths by the methods of hinged installation of prefabricated reinforced concrete blocks, hinged concreting in separate sections, mounting individual prefabricated beams with subsequent integration into continuity above the supports or near the supports, as well as the method of concreting the span on solid scaffolds cannot be applied when passing bridge routes over buildings, structures and other obstacles due to the limited construction height or the inability to arrange Mosti and crane equipment installation on an existing building.

Из известных наиболее близким является способ возведения моста, эстакады, характеризующийся тем, что он включает возведение опор и, по крайней мере, одного неразрезного по длине пролетного строения из образующих, по крайней мере, одну в поперечном сечении ветвь железобетонных продольных балок, которые выполняют на стапеле из монолитного или сборно-монолитного железобетона путем бетонирования в съемной опалубке посекционно с армированием ненапрягаемой и напрягаемой арматурой с последующей производимой с использованием аванбека продольно-цикловой надвижкой секций до размещения каждой из них в проектном положении, при этом напрягаемую арматуру размещают в закрытых каналах в виде пучков, в том числе образованных из проволочных прядей (канатов), и/или стержней, и/или лент из высокопрочного материала, в том числе из металла, или металлопласта, или высокопрочных углеродосодержащих или полимерных нитей, причем часть каналов выполняют прямолинейными, а часть каналов -криволинейными или полигональными с конфигурацией и расположением преимущественно в вертикальном сечении выпуклостей и вогнутостей, соответствующими или пропорциональными эпюре изгибающих моментов, рабочую арматуру, расположенную в прямолинейных каналах, напрягают в пределах каждой секции перед ее надвижкой и перемещением со стапеля, а арматуру, расположенную в криволинейных или полигональных каналах, проталкивают или протягивают в каналах после надвижки всего пролетного строения или надвигаемой ветви его и напрягают после надвижки всех секций, образующих пролетное строение, или его надвигаемую часть, или его ветвь, при этом соотношение площадей поперечного сечения и/или несущих способностей арматуры, напрягаемой посекционно, и арматуры, напрягаемой после надвижки в проектное положение всей надвигаемой части или ветви пролетного строения, принимают по расчету. Стапель выполняют из основания, стоек, балочной клетки и опирающейся на домкраты опалубки с бетонными стенками, которые располагают по краям и оси бетонируемой секции пролетного строения, причем по верху стенок укладывают стальные листы, стыки которых сваривают, а верхнюю поверхность листов очищают, шлифуют и покрывают антифрикционной смазкой, преимущественно силиконовой, по верху стальных листов укладывают листы фанеры длиной, меньшей расстояния между опалубкой и дополнительной опорой вблизи нее, и шириной, превышающей ширину стальных листов. Перед бетонированием секции производят размещение каналообразователей в проектное положение на арматурных подкладках, которые располагают на расстоянии друг от друга вдоль каналообразователя, после чего устанавливают в проектное положение анкера, производят формирование пучков высокопрочных прядей в установленных каналообразователях с закреплением прядей в анкерных устройствах, производят соединение каналообразователей с анкерными устройствами с герметизацией всех стыков, в верхних и нижних точках перегиба арматуры на транзитных каналообразователях устанавливают дополнительные дренажные трубки, причем транзитные каналообразователи заполняют пластиковыми трубами для придания большей жесткости каналообразователю, обрезку высокопрочных прядей производят механическим способом, а после набора бетоном секции пролетного строения проектной прочности производят натяжение высокопрочных пучков, при этом инъектирование натянутой арматуры производят до или непосредственно после надвижки секции пролетного строения.The closest known method is the construction of a bridge, overpass, characterized in that it includes the construction of supports and at least one continuous along the span of forming at least one branch in the cross section of reinforced concrete longitudinal beams that perform on slipway of monolithic or precast-monolithic reinforced concrete by concreting in removable formwork section by section with reinforcement of non-tensile and tensile reinforcement with subsequent production using an advance backing nn-cyclic sliding of the sections until each of them is placed in the design position, while the tensioned reinforcement is placed in closed channels in the form of bundles, including those formed from wire strands (ropes), and / or rods, and / or tapes of high-strength material, including from metal, or metal, or high-strength carbon-containing or polymer filaments, with some of the channels being straight and part of the channels being curved or polygonal with a configuration and arrangement mainly in a vertical section in convexities and concavities corresponding to or proportional to the diagram of bending moments, the working reinforcement located in rectilinear channels is strained within each section before its sliding and moving from the slipway, and the reinforcement located in curvilinear or polygonal channels is pushed or stretched in the channels after sliding the span or the pushed branch of it and strain after the slide of all the sections forming the span, or its pushed part, or its branch, while the ratio the cross sections and / or the bearing capacity of the reinforcement, tensioned section by section, and reinforcement, tensioned after sliding into the design position of the entire overhanging part or branch of the superstructure, are taken as calculated. The slipway is made of base, racks, beam cage and formwork supported by jacks with concrete walls, which are placed along the edges and axis of the concrete section of the span, and steel sheets are laid on the top of the walls, the joints are welded, and the upper surface of the sheets is cleaned, ground and coated with antifriction grease, mainly silicone, plywood sheets are laid on top of steel sheets with a length shorter than the distance between the formwork and the additional support near it, and a width exceeding the width of the steel x sheets. Before concreting the sections, the channel formers are placed in the design position on reinforcing pads that are located at a distance from each other along the channel former, then they are installed in the design position of the anchor, bundles of high-strength strands are formed in the installed channel formers with the strands fixed in anchor devices, the channel formers are connected to anchor devices with sealing of all joints at the upper and lower points of the bend of the reinforcement to the transit additional drainage tubes are installed on the channel formers, and the transit channel formers are filled with plastic pipes to give the channel former more rigidity, high-strength strands are trimmed mechanically, and after concrete sections of the span structure are designed to be designed, high-strength beams are tensioned, while tensioned reinforcement is injected before or immediately after spans of the span section.

Натяжение пучков высокопрочных прядей производят путем назначения величины натяжения для каждой секции индивидуально в соответствии с воспринимаемой нагрузкой. При выполнении секции плитно-ребристой или коробчатой бетонирование секции пролетного строения на стапеле производят в два этапа, на первом из которых бетонируют одновременно два ребра или ребра и нижнее днище коробчатой балки. При выполнении секции пролетного строения плитной бетонирование секции производят в один этап, для чего на стапеле монтируют элементы опалубки секции. После бетонирования секции пролетного строения производят экзотермическое выдерживание бетона. Надвижку пролетного строения производят четырьмя домкратами, которые устанавливают впереди устоя с возможностью соединения посредством четырех арматурных стержней со стальными балочками, смонтированными в пролетном строении, причем для надвижки первой секции пролетного строения два из четырех стержней прикрепляют к аванбеку. Пролетное строение опирают на отдельно стоящие железобетонные стойки прямоугольного поперечного сечения (RU №2208084 С1, кл. Е 01 D 21/00, 2003).The tension of the beams of high-strength strands is produced by assigning the amount of tension for each section individually in accordance with the perceived load. When performing a section of plate-ribbed or box-shaped concreting, the sections of the superstructure on the slipway are made in two stages, on the first of which two ribs or ribs and the lower bottom of the box-beam are concreted simultaneously. When performing the section of the superstructure, the slab concreting of the section is carried out in one stage, for which the elements of the formwork of the section are mounted on the slipway. After concreting sections of the superstructure produce exothermic curing of concrete. The span slide is made by four jacks, which are installed in front of the abutment with the possibility of connection by means of four reinforcing bars with steel beams mounted in the span, and for sliding the first section of the span, two of the four rods are attached to the outback. The span is based on freestanding reinforced concrete racks of rectangular cross-section (RU No. 2208084 C1, class E 01 D 21/00, 2003).

Предлагаемое техническое решение не требует специальных вспомогательных обустройств в пролетах, где находятся препятствия, и может быть осуществлено при ограниченной строительной высоте железобетонных пролетных строений, которая определяется расчетом.The proposed technical solution does not require special auxiliary arrangements in the spans where obstacles are located, and can be carried out with a limited construction height of reinforced concrete spans, which is determined by calculation.

Достигается это тем, что способ цикличной продольной надвижки на опоры неразрезного железобетонного пролетного строения моста с боковыми стенками или ребрами и верхней или нижней плитой и армированием в виде прямых пучков в верхней плите и с внутренней стороны боковых стенок или ребер включает бетонирование в опалубке секций пролетных строений, их армирование и соединение первой из изготовленных секций с аванбеком, длина которого составляет 50-65% длины соединяемой с ним секции пролетного строения с последующей надвижкой толкающим домкратом с наращиванием следующими секциями, при этом опалубку изготавливают предпочтительно из двух имеющих подушки скольжения частей: первую, нижнюю, опирают на четыре гидродомкрата и используют для бетонирования нижней плиты, и вторую используют для бетонирования боковых стенок или ребер и для бетонирования верхней плиты, причем опалубку секций размещают за толкающими домкратами на длине одной секции бетонирования, а аванбек присоединяют к передней секции пролетного строения посредством одиночных прядей, которые натягивают однопрядевыми домкратами, надвижку производят со скоростью 7,5-12,5 м/час развиваемым толкающими домкратами горизонтальным усилием, не превышающим половины величины вертикального усилия, создаваемого дополнительно используемыми при надвижке подъемными домкратами, а после размещения всех секций пролетного строения в проектном положении в их боковых стенках или ребрах размещают напрягаемые транзитные пучки арматуры, длина которых не менее длины трех секций пролетного строения, и производят объединение арматуры всех секций пролетного строения.This is achieved by the fact that the method of cyclic longitudinal sliding onto supports of continuous reinforced concrete span structure of a bridge with side walls or ribs and an upper or lower slab and reinforcing in the form of straight beams in the upper slab and on the inner side of the side walls or ribs includes concreting in the formwork of the sections of the spans , their reinforcement and connection of the first of the manufactured sections with an outback, the length of which is 50-65% of the length of the span section connected to it, followed by a slide to the pushing house an atom with building up in the following sections, while the formwork is preferably made of two parts with sliding pillows: the first, lower, rest on four hydraulic jacks and are used for concreting the bottom plate, and the second is used for concreting the side walls or ribs and for concreting the top plate, the formwork sections are placed behind the pushing jacks along the length of one section of concreting, and the avanbek is attached to the front section of the span by means of single strands that are pulled in a single strand jacks, the slide is produced at a speed of 7.5-12.5 m / h, the horizontal force developed by the pushing jacks does not exceed half the magnitude of the vertical force created by the lifting jacks additionally used when sliding, and after placing all sections of the span in the design position in their side walls or ribs are placed prestressing transit beams of reinforcement, the length of which is not less than the length of three sections of the span, and produce the union of the reinforcement of all sections of the span.

Изобретение поясняется чертежами, где:The invention is illustrated by drawings, where:

на фиг.1 представлена схема бетонирования первой секции и монтажа аванбека,figure 1 presents a diagram of the concreting of the first section and the installation of the outback,

на фиг.2 представлена схема надвижки пролетного строения с помощью аванбека и бетонирования второй секции,figure 2 presents a diagram of the slide superstructure using advanceback and concreting the second section,

на фиг.3 представлена схема надвижки пролетного строения с помощью аванбека и бетонирования третьей секции.figure 3 presents a diagram of the slide superstructure using advanceback and concreting the third section.

Вспомогательные обустройства при предлагаемом способе работ располагаются за пределами подмостовых габаритов:Auxiliary arrangements with the proposed method of work are located outside the bridge dimensions:

- стапель-полигон 1 с опалубкой для бетонирования секций 2 пролетных строений;- slipway polygon 1 with formwork for concreting sections of 2 spans;

- стальной аванбек 3, который временно прикрепляют к секции 2 железобетонного пролетного строения на период надвижки с целью сократить изгибающие моменты и поперечные силы в поперечном сечении пролетного строения при надвижке;- steel outback 3, which is temporarily attached to section 2 of the reinforced concrete span for a sliding period in order to reduce bending moments and transverse forces in the cross section of the span when sliding;

- толкающее устройство 4 для продольной надвижки секций 2 пролетного строения.- a pushing device 4 for the longitudinal slide of sections 2 of the superstructure.

Железобетонное пролетное строение в одних и тех же сечениях при продольной надвижке испытывает различные (в том числе знакопеременные) усилия. Поэтому обязательным элементом каждого этапа надвижки является установка или снятие (иногда и то и другое) временных высокопрочных пучков, а также установка транзитной арматуры преднапряжения после окончания надвижки на опоры. Для продольной надвижки используют устройство, (например, по патенту РФ №2163276), включающее группу домкратов, одни из которых приподнимают секцию пролетного строения, а другие ее толкают. В пролетном строении используют каналообразователи (например, по патенту №2178046).Reinforced concrete span in the same sections with longitudinal sliding experiences various (including alternating) forces. Therefore, a mandatory element of each stage of the slide is the installation or removal (sometimes both) of temporary high-strength beams, as well as the installation of transit prestressing reinforcement after the end of the slide on the supports. For a longitudinal slide, a device is used (for example, according to RF patent No. 2163276), including a group of jacks, some of which raise the span section, while others push it. In the span use channel formers (for example, according to patent No. 2178046).

Над каждой опорой 5 устанавливают специальные скользуны, по которым скользит пролетное строение.Above each support 5, special side-bearings are installed, along which the span glides.

Метод цикличной продольной надвижки (ЦПН) заключается в бетонировании отдельных частей пролетного строения на месте, причем 1/3 или 1/2 длины пролета расположена в крытом стапеле-полигоне непосредственно за одним из устоев. Каждый бетонируемый участок “захватки” неразрезного пролетного строения преднапрягается перед надвижкой. Для надвижки используется специальное гидравлическое оборудование и опорные части с низким коэффициентом трения, по которым пролетное строение перемещается над промежуточными опорами. Технические преимущества данной конструкции с бетонированием на месте включают следующее:The method of cyclic longitudinal slide (CPN) consists in concreting individual parts of the span in place, with 1/3 or 1/2 of the length of the span located in a covered slipway polygon directly behind one of the foundations. Each concreted section of the “capture” of continuous span is prestressed before the slide. For sliding, special hydraulic equipment and supporting parts with a low coefficient of friction are used, along which the span moves over the intermediate supports. The technical advantages of this in situ concreting design include the following:

- на полигоне реализуются преимущества заводского изготовления благодаря повторяемости рабочих операций и независимости работ от погодных условий,- the advantages of factory manufacturing are realized at the landfill due to the repeatability of work operations and the independence of work from weather conditions,

- исключаются подмости, сборка и разборка которых связана с большими затратами времени, а также стеснением существующего движения,- excluded scaffolds, the assembly and disassembly of which is associated with a large investment of time, as well as the constraint of the existing movement,

- исключаются частые деформационные швы в пролетном строении.- excludes frequent expansion joints in the span.

При этом себестоимость работ зависит от затрат на материалы, оплату труда и стоимость опалубки. Сокращение стоимости указанных составляющих можно получить за счет:In this case, the cost of work depends on the cost of materials, wages and the cost of formwork. Reducing the cost of these components can be obtained by:

- повторения похожих рабочих операций,- repetition of similar work operations,

- повторного использования легко собираемых и разбираемых форм и конструкций,- reuse of easily assembled and disassembled forms and structures,

- предварительной заготовки обычной и преднапряженной арматуры,- pre-harvesting conventional and prestressed fittings,

- транспортирования материалов на короткие расстояния,- transportation of materials over short distances,

- хорошего контроля качества бетонных работ,- good quality control of concrete work,

- защищенности зоны работ от погодных условий, что гарантирует выполнение работ строго по графику,- protection of the work zone from weather conditions, which guarantees the performance of work strictly on schedule,

- возможности повторного использования подмостей и оборудования на других работах,- the possibility of reuse of scaffolds and equipment in other works,

- сокращения трудозатрат и обеспечения высочайшего контроля за работой благодаря сосредоточению большей части работ внутри крытого полигона.- reduction of labor costs and ensuring the highest control over work due to the concentration of most of the work inside the indoor landfill.

В целом, метод ЦПМ применим для сооружения мостов как на прямой, так и на кривой одного радиуса. Кривая может быть и в вертикальной плоскости. Построенные по этому методу мосты имеют длину от 100 до 1200 м. Однако минимальная длина моста должна быть около 300 м, чтобы амортизировать стоимость опалубки и оборудования и сделать этот метод конкурентоспособным. Необязательно, чтобы мост имел одинаковые пролеты. Если один или два пролета имеют большую длину, чем остальные, надвижка может быть выполнена с применением временных опор. Оптимальными пролетами считаются пролеты 40-50 м. Величина концевых пролетов должна быть в пределах 75% от величины средних пролетов. Величина центрального преднапряжения для надвижки очень важна, поэтому требуется тщательно подбирать поперечное сечение конструкции при проектировании. Правильное положение бетонируемых секций на полигоне и обеспечение точного высотного положения опалубки имеет главное значение для успешной надвижки. Опалубка обычно изготавливается из двух частей полной готовности: первая - для нижней плиты и вторая - для боковых стен или ребер и верхней плиты. Это разделение гарантирует рабочий недельный цикл изготовления одной секции пролетного строения и обеспечивает максимальную производительность, особенно для больших мостов. Может применяться и отдельная цельная опалубка с соответствующим сокращением затрат на устройство полигона, однако в этом случае рабочий цикл составит 8 дней, чтобы обеспечить уход за бетоном внутренней поверхности в течение 24 часов до бетонирования верхней плиты. Функцией центрального напряжения является обеспечение восприятия поперечным сечением пролетного строения всех положительных и отрицательных моментов при любом изменении положения его над опорами. Прямые пучки в верхней плите и с внутренней стороны боковых стенок имеют стыковые муфты-звездочки и размещаются в каждой из двух (из трех) секций и обеспечивают необходимое продольное преднапряжение. Установка пучков в относительно тонких верхней и нижней плитах требует специальной анкеровки. В некоторых случаях при относительно больших пролетах моста (более 50 м) сила центрального преднапряжения слишком велика для последней стадии строительства. Чтобы выйти из положения, устанавливают временные пучки, которые снимают после установки пролетного строения в окончательное положение. Транзитные пучки устанавливаются тогда, когда надвижка завершена и пролетное строение заняло проектное положение. Эти пучки, длина которых достигает 90-100 м в зависимости от пролетов моста, размещаются в боковых стенках пролетного строения с расположением анкеров с внутренней стороны коробчатого сечения по эстетическим соображениям.In general, the CPM method is applicable for the construction of bridges both on a straight line and on a curve of the same radius. The curve can also be in a vertical plane. Bridges constructed using this method have a length of 100 to 1200 m. However, the minimum bridge length should be about 300 m in order to absorb the cost of formwork and equipment and make this method competitive. It is not necessary that the bridge have the same spans. If one or two spans are longer than the others, the slide can be performed using temporary supports. The spans of 40-50 m are considered optimal spans. The value of end spans should be within 75% of the average spans. The magnitude of the central prestressing for the slide is very important, therefore, it is necessary to carefully select the cross section of the structure during design. The correct position of the concrete sections at the landfill and the provision of the exact height of the formwork are of prime importance for a successful slide. Formwork is usually made of two ready-made parts: the first for the bottom plate and the second for the side walls or ribs and the top plate. This separation guarantees a working weekly production cycle for one section of the superstructure and provides maximum performance, especially for large bridges. A separate integral formwork can be used with a corresponding reduction in the cost of the construction of the landfill, however, in this case, the work cycle will be 8 days to provide care for the concrete on the inner surface for 24 hours before concreting the top plate. The function of the central voltage is to ensure that the cross-section of the span perceives all positive and negative moments with any change in its position above the supports. Straight bundles in the upper plate and on the inner side of the side walls have sprocket butt couplings and are placed in each of two (of three) sections and provide the necessary longitudinal prestressing. The installation of beams in relatively thin upper and lower plates requires special anchoring. In some cases, with relatively large bridge spans (more than 50 m), the central prestressing force is too high for the last stage of construction. To get out of the situation, set temporary beams, which are removed after installation of the span in the final position. Transit beams are installed when the slide is completed and the span has taken its design position. These beams, the length of which reaches 90-100 m, depending on the spans of the bridge, are located in the side walls of the span with the location of the anchors on the inside of the box section for aesthetic reasons.

Имеется два альтернативных метода цикличной продольной надвижки.There are two alternative methods of cyclic longitudinal slide.

А}. Тянущий методA}. Pulling method

В этом методе используются обычные домкраты для преднапряжения и прядевые пучки, которые позволяют тянуть пролетное строение посредством рамы, закрепленной за задний конец предпоследней секции.This method uses conventional prestressing jacks and strand bundles that allow the span to be pulled by a frame fixed to the rear end of the penultimate section.

Б}. Метод толканияB}. Push method

В этом методе используются синхронизированные домкраты, расположенные под пролетным строением, которые поднимают и затем толкают пролетное строение за счет трения между сталью домкрата и бетоном.This method uses synchronized jacks located under the span, which lift and then push the span due to friction between the steel of the jack and concrete.

Метод толкания имеет значительные преимущества над тянущим методом, наиболее существенным является возможность изменить направление движения в любое время, например дать задний ход. Это может быть необходимо, например, из-за чрезвычайно большого трения на опорах в момент трогания в холодную погоду, что вызывает большие деформации опор. Возможность немедленно менять направление движения в этом случае очень важна. Необходимо принять во внимание некоторые вопросы, связанные с местом расположения толкающих домкратов, а именно очень важно определить приемлемые размеры площади для установки толкающего оборудования: для анкеровки домкратов, используемых для передачи горизонтального усилия, а также место для установки тормозных башмаков, которые представляют собой стальные пластины, на которых покоится пролетное строение все время, исключая время надвижки. Опалубка обычно размещается за толкающими домкратами на длине одной секции бетонирования. Это увеличивает вертикальную реакцию на домкраты и уравновешивает момент от консоли.The pushing method has significant advantages over the pulling method, the most significant is the ability to change the direction of movement at any time, for example, back up. This may be necessary, for example, due to extremely large friction on the supports at the moment of starting in cold weather, which causes large deformations of the supports. The ability to immediately change direction in this case is very important. It is necessary to take into account some issues related to the location of the pushing jacks, namely, it is very important to determine the acceptable size of the area for installing the pushing equipment: for anchoring the jacks used to transmit horizontal force, as well as the place for installing the brake shoes, which are steel plates on which the superstructure rests all the time, excluding the sliding time. The formwork is usually placed behind the pushing jacks along the length of one concreting section. This increases the vertical response to the jacks and balances the moment from the console.

При проектировании опор важно максимально ограничить горизонтальную силу, которая воздействует на нижнюю часть опор. При этом происходят максимально допустимые отклонения опоры как результат воздействия максимального горизонтального усилия и допустимого трения. Система электронного контроля, смонтированная в верхней части опоры и связанная с домкратным оборудованием, точно контролирует отклонения опоры и позволяет избежать их максимального значения. Важным является правильное размещение опорных частей с учетом допусков на размещение плоских домкратов для подъемки пролетного строения и размещения постоянных опорных частей в проектном положении. Для больших горизонтальных усилий (которые возникают при включении в работу второго комплекта оборудования на опоре N1) объединение временных опор является возможным решением для восприятия этих сил.When designing the supports, it is important to limit the horizontal force that affects the lower part of the supports to the maximum. In this case, the maximum permissible deviations of the support occur as a result of the effect of the maximum horizontal force and permissible friction. An electronic control system mounted in the upper part of the support and connected with jacking equipment accurately controls the deviations of the support and avoids their maximum value. The important thing is the correct placement of the supporting parts, taking into account the tolerances for the placement of flat jacks for lifting the span and placing the permanent supporting parts in the design position. For large horizontal forces (which arise when the second set of equipment is turned on at support N1), the combination of temporary supports is a possible solution for the perception of these forces.

Полигон-стапель состоит из одной или двух площадок в зависимости от того, бетонируется ли захватка пролетного строения в одной опалубке или в двух. Полигон обслуживается кранами, имеет бетонный завод и площади для изготовления арматурных каркасов и выполнения работ по преднапряжению конструкции. С тыльной стороны опалубки имеется мощеная площадка, чтобы обезопасить пучки от возможного контакта с грунтом. Система роликов позволяет пучкам удобно размещаться в период надвижки пролетного строения. Обычно полигон удален от устоя на 15-20 метров. Между полигоном и устоем располагают временные опоры с расстоянием между ними 6-7 метров и со скользящими устройствами на них. По условиям многократного оборота опалубка выполняется из металла, древесина не используется. Нижняя часть опалубки опирается на четыре гидродомкрата. С боковых сторон (около 0,5 м), которые также выполняют роль зон скольжения, используются специальные направляющие, объединенные с неопрено-тефлоновыми опорными подушками, обеспечивающими низкий коэффициент трения.Открытие боковых частей опалубки, а также внутренней опалубки (в случае коробчатого сечения) также выполняется при помощи гидродомкратов.The slipway range consists of one or two sites, depending on whether the span grip is concreted in one formwork or in two. The landfill is serviced by cranes, has a concrete plant and areas for the manufacture of reinforcing cages and the performance of prestressing structures. On the back of the formwork there is a paved area to protect the beams from possible contact with the ground. The roller system allows the beams to fit comfortably during the span sliding process. Usually the landfill is 15-20 meters away from the abutment. Between the landfill and the abutment are temporary supports with a distance between them of 6-7 meters and with sliding devices on them. According to the conditions of multiple turnover, the formwork is made of metal, wood is not used. The lower part of the formwork rests on four hydraulic jacks. On the sides (about 0.5 m), which also play the role of sliding zones, special guides are used, combined with neoprene-Teflon support pillows that provide a low coefficient of friction. Opening the side parts of the formwork, as well as the inner formwork (in the case of a box section) also performed using hydraulic jacks.

Окончательное количество преднапряженных пучков в случае применения метода ЦПН на 40% больше в автодорожных мостах (в железнодорожных немного меньше) по сравнению с методом бетонирования пролетного строения на месте. Это происходит потому, что в дополнение к центральному преднапряжению необходимо еще производить напряжение конструкции транзитными пучками. Количество постоянных пучков может быть сокращено введением временных пучков, которые могут быть сняты и повторно использованы на строительстве. В любом случае повышение стоимости преднапряжения при методе ЦПН далеко перекрывается многими другими преимуществами и экономией. Для устройства преднапряжения используют пучки 100 тН мощности для автодорожных мостов, а для железнодорожных мостов 170 тН мощности. Пучки стыкуются через 2-3 захватки бетонирования с помощью муфт по патентам РФ №2094578, 2094577. Пучки в верхней плите сматывают на барабаны, чтобы не мешать работе при подготовке следующей “захватки”. Транзитные пучки располагают в стенках пролетного строения, их средняя мощность 200-300 тН. Эти пучки имеют длину 90-100 м, чтобы облегчить задачу свободного проталкивания их в каналы, и имеют натяжные анкеры на каждом конце. Натяжение этих пучков выполняется после окончательной установки пролетного строения в проектное положение. Однако пучки можно протащить заранее, если это окажется необходимым, но в этом случае каналы необходимо заполнить водным раствором актикоррозионного компаунда, который должен быть вымыт из канала перед инъектированием. The final number of prestressed beams in the case of applying the CPN method is 40% more in road bridges (in railways a little less) compared to the span concrete method in place. This is because, in addition to central prestressing, it is also necessary to produce structural stress in transit beams. The number of permanent beams can be reduced by introducing temporary beams that can be removed and reused in construction. In any case, the increase in the cost of prestressing with the CPN method is far overlapped by many other advantages and savings. For the prestressing device, beams of 100 tN of power are used for road bridges, and for railway bridges of 170 tN of power. The bundles are joined after 2-3 concreting hooks using couplings according to the patents of the Russian Federation No. 2094578, 2094577. The bundles in the top plate are wound onto drums so as not to interfere with the preparation of the next “grab”. Transit beams are located in the walls of the superstructure, their average power is 200-300 tN. These bundles have a length of 90-100 m to facilitate the task of freely pushing them into the channels, and have tension anchors at each end. The tension of these beams is performed after the final installation of the span in the design position. However, the beams can be pulled in advance if necessary, but in this case the channels must be filled with an aqueous solution of the anticorrosive compound, which must be washed out of the channel before injection.

Оборудование для надвижки состоит из, например, двух домкратов, один из которых поднимает пролетное строение, освобождая его от тормозных подушек, а другой обеспечивает толкание пролетного строения. Скорость надвижки около 10 м/час, поэтому забетонированный участок длиной 15-20 м может быть надвинут за 2 часа. Временные опорные части состоят из бетонной плиты с листом нержавеющей стали, прикрепленным к верхней поверхности для ограничения трения скольжения. После окончания надвижки эти опорные части заменяются постоянными, обычно - одна всесторонне-подвижная и одна линейно-подвижная. Разработаны стаканные опорные части, которые могут использоваться и как временные, и как постоянные. Эти опорные части состоят из стандартных стаканных опорных частей со специально удлиненными верхними плитами, которые имеют на своей поверхности нержавеющий лист, обеспечивающий скольжение во время надвижки. После окончания надвижки эти опорные части работают как постоянные предварительно будучи объединены с клиньями.Sliding equipment consists of, for example, two jacks, one of which raises the span, freeing it from the brake pads, and the other provides the push of the span. The speed of the slide is about 10 m / h, so a concreted area of 15-20 m in length can be pushed in 2 hours. Temporary support parts consist of a concrete slab with a stainless steel sheet attached to the upper surface to limit sliding friction. After the end of the slide, these supporting parts are replaced by constant ones, usually one comprehensively movable and one linearly movable. Glass support parts have been developed that can be used both temporary and permanent. These supporting parts consist of standard glass supporting parts with specially elongated top plates, which have on their surface a stainless sheet that provides sliding during sliding. After the end of the slide, these supporting parts work as permanent previously being combined with wedges.

Процесс превращения временных опорных частей в постоянные с использованием для этих целей плоских домкратов становится легкой операцией, если используются специальные опорные части. Боковые направляющие запроектированы так, чтобы их можно было установить в любой момент при надвижке. Эти направляющие соединены с опорами при помощи пучков.The process of turning temporary supporting parts into permanent ones using flat jacks for these purposes becomes an easy operation if special supporting parts are used. The lateral guides are designed so that they can be installed at any time when sliding. These guides are connected to the supports using beams.

Изготовление коробчатой балки с использованием двух комплектов опалубки ведется в следующей последовательности.The manufacture of a box beam using two sets of formwork is carried out in the following sequence.

ПонедельникMonday

Утро. Опускание днища и наружной опалубки. Натяжение высокопрочной арматуры и надвижка.Morning. Lowering the bottom and outer formwork. High tensile reinforcement tension and slide.

После обеда. Очистка и смазка опалубки. Подготовка пучков.After lunch. Cleaning and lubricating formwork. Beam preparation.

Вторник. Установка арматуры и каналообразователей в нижнюю плиту.Tuesday. Installation of fittings and channel formers in the bottom plate.

СредаWednesday

Продолжение работ по армированию нижней плиты. Установка арматуры верхней плиты и стенок. Бетонирование нижней плиты.Continuation of reinforcing the bottom plate. Installation of reinforcement for the top plate and walls. Concreting the bottom plate.

ЧетвергThursday

Продолжение установки арматуры верхней плиты и стенок, установка закладных частей и деталей для преднапряжения.Continuation of the installation of the reinforcement of the upper plate and walls, the installation of embedded parts and parts for prestressing.

ПятницаFriday

Бетонирование стенок и верхней плиты.Concreting of walls and top plate.

СубботаSaturday

ВоскресеньеSunday

Уход за бетоном. В случае низких температур применяется пропаривание.Curing. In case of low temperatures, steaming is used.

Преимущества метода цикличной надвижки состоят в том, что бригада из 14 человек изготавливает участок пролетного строения (15-20 м) за неделю.The advantages of the cyclic sliding method are that a team of 14 people makes a span section (15-20 m) per week.

Claims (1)

Способ цикличной продольной надвижки на опоры неразрезного железобетонного пролетного строения моста с боковыми стенками или ребрами и верхней или нижней плитой и армированием в виде прямых пучков в верхней плите и с внутренней стороны боковых стенок или ребер, характеризующийся тем, что он включает бетонирование в опалубке секций пролетных строений, их армирование и соединение первой из изготовленных секций с аванбеком, длина которого составляет 50-65% длины соединяемой с ним секции пролетного строения с последующей надвижкой толкающим домкратом с наращиванием следующими секциями, при этом опалубку изготавливают из двух имеющих подушки скольжения частей: первую, нижнюю, опирают на, предпочтительно четыре, гидродомкрата и используют для бетонирования нижней плиты, и вторую, которую используют для бетонирования боковых стенок или ребер и для бетонирования верхней плиты, причем опалубку секций размещают за толкающими домкратами на длине одной секции бетонирования, а аванбек присоединяют к передней секции пролетного строения посредством одиночных прядей, которые натягивают однопрядевыми домкратами, надвижку производят со скоростью 7,5 - 12,5 м/ч развиваемым толкающими домкратами горизонтальным усилием, не превышающим половины величины вертикального усилия, создаваемого дополнительно используемыми при надвижке подъемными домкратами, а после размещения всех секций пролетного строения в проектном положении в их боковых стенках или ребрах размещают напрягаемые транзитные пучки арматуры, длина которых не менее длины трех секций пролетного строения, и производят объединение арматуры всех секций пролетного строения.A method of cyclic longitudinal sliding onto supports of continuous reinforced concrete span structure of a bridge with side walls or ribs and an upper or lower plate and reinforcement in the form of straight beams in the upper plate and on the inner side of the side walls or ribs, characterized in that it includes concreting in the formwork of the span sections structures, their reinforcement and the connection of the first of the manufactured sections with an advance back, the length of which is 50-65% of the length of the span section connected to it, followed by pushing a jack with building-up in the following sections, while the formwork is made of two parts with sliding cushions: the first, lower, rely on, preferably four, hydraulic jacks and are used for concreting the bottom plate, and the second, which is used for concreting the side walls or ribs and for concreting the top slabs, and the formwork of the sections is placed behind the pushing jacks along the length of one section of concreting, and the avanbek is attached to the front section of the span using single strands that are tight They are called single-strand jacks, sliding is carried out at a speed of 7.5 - 12.5 m / h, the horizontal force developed by the pushing jacks, not exceeding half the magnitude of the vertical force created by the lifting jacks additionally used when sliding, and after placing all sections of the span in the design position in on their side walls or ribs are placed prestressing transit beams of reinforcement, the length of which is not less than the length of three sections of the span, and combine the reinforcement of all sections of the span th structure.
RU2004104737/03A 2004-02-19 2004-02-19 Method for cyclic movement of solid reinforced concrete bridge span in longitudinal direction RU2242559C1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
RU2004104737/03A RU2242559C1 (en) 2004-02-19 2004-02-19 Method for cyclic movement of solid reinforced concrete bridge span in longitudinal direction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
RU2004104737/03A RU2242559C1 (en) 2004-02-19 2004-02-19 Method for cyclic movement of solid reinforced concrete bridge span in longitudinal direction

Publications (1)

Publication Number Publication Date
RU2242559C1 true RU2242559C1 (en) 2004-12-20

Family

ID=34388796

Family Applications (1)

Application Number Title Priority Date Filing Date
RU2004104737/03A RU2242559C1 (en) 2004-02-19 2004-02-19 Method for cyclic movement of solid reinforced concrete bridge span in longitudinal direction

Country Status (1)

Country Link
RU (1) RU2242559C1 (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103510474A (en) * 2013-09-26 2014-01-15 中铁建设集团有限公司 Elastic bearing sliding device for incremental launching construction
CN103510470A (en) * 2012-06-29 2014-01-15 秦皇岛天业通联重工股份有限公司 Hydraulic span change device of bridge girder erection machine
CN103590337A (en) * 2012-08-17 2014-02-19 秦皇岛天业通联重工股份有限公司 Bridge girder erection machine system and transferring method thereof
CN105274942A (en) * 2015-11-23 2016-01-27 柳州欧维姆工程有限公司 Large-span continuous steel truss multi-point synchronous automatic cyclic alternating sliding shoe push system and construction method thereof
CN107988921A (en) * 2017-10-30 2018-05-04 四川公路桥梁建设集团有限公司 A kind of cross-line bridge single-point successively incremeantal launching method construction method of overcrossing railway, highway
CN113513630A (en) * 2021-04-30 2021-10-19 四川石油天然气建设工程有限责任公司 Pipeline crossing pushing system for narrow deep valley or wide river and process thereof
CN113668400A (en) * 2021-08-24 2021-11-19 中建八局第一建设有限公司 Heavy steel beam pushing equipment

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
ЗАХАРОВ Л.В. и др. Сборные неразрезные железобетонные пролетные строения мостов. - М.: Транспорт, 1983, с. 98-107. ФЕЛЬДМАН М.В. и др. Опыт продольной надвижки неразрезных железобетонных пролетных строений, Экспресс-информация. - М.: Оргтрансстрой, 1973, с. 23, рис. 10. *

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103510470A (en) * 2012-06-29 2014-01-15 秦皇岛天业通联重工股份有限公司 Hydraulic span change device of bridge girder erection machine
CN103510470B (en) * 2012-06-29 2016-08-24 秦皇岛天业通联重工科技有限公司 The hydraulic pressure of a kind of Bridge Erector becomes cross-device
CN103590337A (en) * 2012-08-17 2014-02-19 秦皇岛天业通联重工股份有限公司 Bridge girder erection machine system and transferring method thereof
CN103590337B (en) * 2012-08-17 2016-06-15 秦皇岛天业通联重工科技有限公司 A kind of bridge girder erection machine system and transfer method thereof
CN103510474A (en) * 2013-09-26 2014-01-15 中铁建设集团有限公司 Elastic bearing sliding device for incremental launching construction
CN105274942A (en) * 2015-11-23 2016-01-27 柳州欧维姆工程有限公司 Large-span continuous steel truss multi-point synchronous automatic cyclic alternating sliding shoe push system and construction method thereof
CN107988921A (en) * 2017-10-30 2018-05-04 四川公路桥梁建设集团有限公司 A kind of cross-line bridge single-point successively incremeantal launching method construction method of overcrossing railway, highway
CN107988921B (en) * 2017-10-30 2019-11-05 四川公路桥梁建设集团有限公司 A kind of cross-line bridge single-point successively incremeantal launching method construction method of overcrossing railway, highway
CN113513630A (en) * 2021-04-30 2021-10-19 四川石油天然气建设工程有限责任公司 Pipeline crossing pushing system for narrow deep valley or wide river and process thereof
CN113668400A (en) * 2021-08-24 2021-11-19 中建八局第一建设有限公司 Heavy steel beam pushing equipment
CN113668400B (en) * 2021-08-24 2022-12-20 中建八局第一建设有限公司 Heavy steel beam pushing equipment

Similar Documents

Publication Publication Date Title
RU2242559C1 (en) Method for cyclic movement of solid reinforced concrete bridge span in longitudinal direction
CN109676784A (en) A kind of assembled steel-concrete combined structure pedestal and pre-tensioning system T beam construction
JP5331924B1 (en) SPC bridge construction method
KR101101209B1 (en) Cantilever of slab for bridge using precast supporter and the method thereof
KR101693256B1 (en) Construction method of prefabricated psc bridge
KR101208231B1 (en) Method for constructing continuous supporting structure of corrugated steel web PSC beam
KR100522170B1 (en) Method of constructing simple and continuous composite bridges
KR101214602B1 (en) Incremental launching apparatus for constructing rail-type concrete slab of composite bridge using shearing connector rail, and method for the same
KR101198812B1 (en) composite rahmen bridge using a preflex girder
JP2009144410A (en) Pc bridge closure method
KR101347113B1 (en) Incremental launching apparatus for constructing shearing pocket-type concrete slab of composite bridge
JP5143666B2 (en) PC bridge erection method
KR200407182Y1 (en) Precasted concrete plate
KR20120019152A (en) Prestressed precast concrete composite beam and manufacture methode for there of and construction methode for there of
CN111364364A (en) Construction method for cast-in-place prestressed concrete continuous box girder
JP3737475B2 (en) Box girder bridge structure and construction method
KR100631029B1 (en) Precasted concrete plate assembly and the construction method using thereof
KR101067717B1 (en) Process for producing prestressed concrete girder and concrete girder structure
CN109930468A (en) Ultra-wide English truss formula edge of a wing assembled concrete box girder and its construction method
KR101178737B1 (en) Continuous structure of composite psc girder using prestress at section changing girder height of lower center as straight steel and construction method thereof
CN110761185A (en) Prestress assembly type track beam for station and construction method thereof
RU117452U1 (en) PLATE MOBILE MONOLITHIC SPAN STRUCTURE OF THE BRIDGE FROM COMBINED REINFORCED CONCRETE BEAMS
US20050093190A1 (en) Concrete structures and construction methods
US20030001070A1 (en) Manufactured reinforced concrete system
CN111395167B (en) Construction method of continuous rigid frame bridge

Legal Events

Date Code Title Description
HE4A Change of address of a patent owner
PD4A Correction of name of patent owner
PC43 Official registration of the transfer of the exclusive right without contract for inventions

Effective date: 20210630