KR20250164066A - Construction method and apparatus of the core wall structure on the ground floor using steel column and girder inside the core wall in 1st basement in top down construction - Google Patents
Construction method and apparatus of the core wall structure on the ground floor using steel column and girder inside the core wall in 1st basement in top down constructionInfo
- Publication number
- KR20250164066A KR20250164066A KR1020240063542A KR20240063542A KR20250164066A KR 20250164066 A KR20250164066 A KR 20250164066A KR 1020240063542 A KR1020240063542 A KR 1020240063542A KR 20240063542 A KR20240063542 A KR 20240063542A KR 20250164066 A KR20250164066 A KR 20250164066A
- Authority
- KR
- South Korea
- Prior art keywords
- floor
- basement
- core
- ground
- above ground
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
- E02D29/05—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
- E02D29/055—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench further excavation of the cross-section proceeding underneath an already installed part of the structure, e.g. the roof of a tunnel
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/06—Foundation trenches ditches or narrow shafts
- E02D17/08—Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/35—Extraordinary methods of construction, e.g. lift-slab, jack-block
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0026—Metals
- E02D2300/0029—Steel; Iron
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2600/00—Miscellaneous
- E02D2600/20—Miscellaneous comprising details of connection between elements
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Paleontology (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Life Sciences & Earth Sciences (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Environmental & Geological Engineering (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
본 발명은 역타공사(탑다운) 방법으로 시공하는 것에 있어서, 지상층 코어부분(지상1층 철근콘크리트 구조의 코어벽체)의 착수방법에 관한 것으로, 보다 상세하게는 지하 역타기둥(PRD) 시공 후, 지면(지상 1층 바닥)으로 부터 하향으로 4~5m를 터파기 한 후, 철골기둥을 역타기둥에 접합하여 세우고, 지상 1층 바닥철골보, 지상 1층바닥 하부 (-2.0~3.0m) 테두리보와 지상 1층 바닥 콘크리트를 타설 한 후, 지상으로 골조를 형성하면서, 지하1층 잔여터파기, 지하2층 1차 터파기(지하1층 바닥 하부 -2.0m) 터파기 후, 지하1층 바닥 골조 완성 후, 지하1층 코어벽체를 시공하는 공사방법에 관한 것이다.The present invention relates to a method for starting a ground floor core section (core wall of reinforced concrete structure of the first floor above ground) in a top-down construction method, and more specifically, to a construction method in which, after constructing an underground reverse excavation column (PRD), a excavation is made 4 to 5 m downward from the ground (the floor of the first floor above ground), a steel column is erected by connecting it to the reverse excavation column, and after pouring a floor steel beam of the first floor above ground, a frame beam of the lower part of the first floor above ground (-2.0 to 3.0 m), and floor concrete of the first floor above ground, a framework is formed above ground, and after excavating the remaining part of the first basement floor, excavating the first part of the second basement floor (-2.0 m below the floor of the first basement floor), and after completing the floor framework of the first basement floor, the first basement floor core wall is constructed.
Description
본 발명은 역타공사(탑다운) 방법의 공사에서, 지하가 철골철근콘크리트 구조(SRC)에 있어서, 지상1층 코어벽체에 철골기둥을 설치하는 방법으로 지상층 코어부분(지상1층 철근콘크리트 구조의 코어벽체)을 착수하는 공사방법에 관한 것이다.The present invention relates to a construction method for starting the ground floor core section (core wall of the first floor reinforced concrete structure) by installing steel columns in the core wall of the first floor above ground in an underground steel-reinforced concrete structure (SRC) in a top-down construction method.
지하 역타기둥(PRD) 시공 후, 지상1층 바닥으로 부터 하향으로 4~5m(현장에 따라 다름)를 터파기 한 후, 철골기둥을 역타기둥에 접합하여 세우고, 지상1층 바닥철골보, 지상1층바닥 하부(-3.0m~4.0m) 테두리보와 지상1층 바닥 콘크리트를 타설 한 후, 지상1층으로 골조를 상향 시공하면서, 지하1층 잔여터파기, 지하2층 1차 터파기(지하1층 바닥 하부 -2.0m) 터파기 후, 지하1층 바닥 골조 완성 후, 지하1층 코어벽체를 시공하는 공사방법에 관한 것이다.This relates to a construction method in which, after constructing a PRD (Prestressed Reinforced Demolition) column, a excavation is made 4 to 5 m (varies depending on the site) downward from the first floor above ground, a steel column is erected by connecting it to the PRD column, the first floor steel beam, the lower part of the first floor (-3.0 m to 4.0 m) of the first floor above ground, and the first floor concrete is poured, and then the frame is constructed upward to the first floor above ground, while the remaining excavation of the first basement floor, the first excavation of the second basement floor (-2.0 m below the first basement floor), and then the core wall of the first basement floor is constructed after the first basement floor frame is completed.
탑다운 공사는 통상적으로 흙막이, 지하 역타기둥(PRD, RCD), 지하1층 터파기, 1층 바닥(철골보, 데크, 철근, 콘크리트), 지하2층 터파기 후 지하1층 바닥, 이와 같은 방법으로 지하5층 또는 지하7층까지 바닥과 동기초(매트)를 시공한 후, 유턴하여 수직재인 코어벽체와 기둥을 지하7층부터 상향으로 시공하여 지하를 완성한다.Top-down construction usually involves earth retaining walls, underground reverse excavation columns (PRD, RCD), excavation of the first basement floor, the first floor floor (steel beam, deck, rebar, concrete), excavation of the second basement floor, and then the first basement floor. In this way, the floor and mat are constructed up to the fifth or seventh basement floor, and then a U-turn is made to construct vertical core walls and columns upwards from the seventh basement floor to complete the basement.
한편 지상층 공사는 통상적으로 지하1층 바닥을 시공한 후, 지하1층 코어벽체를 시공한 후, 지하1층 코어벽체, 지상2층 이상의 공사를 진행한다.Meanwhile, construction on the ground floor usually begins with the construction of the basement floor, followed by the construction of the basement core wall, and then construction of the basement core wall and the second floor above ground.
그러나 지상층 코어착수 이전이 선행작업이 길어서 시간이 많이 소요되어 지상층 착수가 늦어지고, 따라서 전체 공사기간(공기, 48개월 등)이 길다는 문제가 있다. 따라서 지상층 코어를 터파기 초기부터 시공할 수 있는 새로운 공사방법이 필요한 실정이다.However, the lengthy preparatory work required prior to the commencement of ground floor core construction delays ground floor construction, prolonging the overall construction period (up to 48 months, etc.). Therefore, a new construction method is needed that allows ground floor core construction from the initial excavation stage.
상기와 같은 기술적 과제를 해결하기 위하여, 본 발명에서는 지하1층 부분 터파기 후 지하 1층 코어벽체 중 상부부분에 철골구조물과 테두리보를 설치하여 지상층 공사를 위한 기초인 토대를 시공하여 지하1층 벽체 전체가 완성되지 않은 상태에서도, 지상1층 코어를 시공할 수 있도록 하는 공사방법 및 장치를 제공하고자 한다.In order to solve the above technical problem, the present invention provides a construction method and device that allows construction of the core of the above-ground floor even when the entire wall of the above-ground floor is not completed by installing a steel structure and a frame beam on the upper part of the core wall of the above-ground floor after excavating the portion of the above-ground floor, thereby constructing a foundation as a basis for construction of the above-ground floor.
상술한 기술적 과제를 해결하기 위해 본 발명은 탑다운 공사현장에서In order to solve the above-mentioned technical problem, the present invention is a top-down construction site
흙막이 설치 단계;Steps for installing the retaining wall;
동부분 지하말뚝(10) 근입 (지상1층바닥~최하층) 단계;Eastern part underground pile (10) insertion stage (1st floor above ground to lowest floor);
지하1층 1차 터파기 (지상1층 바닥 -3.0~5.0m) 단계;Basement 1st floor 1st excavation stage (1st floor above ground -3.0~5.0m)
지상1층 코어벽체 내부 철골기둥(20)설치 단계;Installation stage of steel columns (20) inside the core wall of the first floor above ground;
지상1층 바닥 철골보 설치 단계;Installation stage of the steel beam on the first floor above ground;
지상1층 바닥 -3.0 ~ -4.0m구간으로부터 지상1층 바닥 코어 및 바닥 콘크리트 타설(101) 단계;Step 101: pouring of floor core and floor concrete on the first floor from the section -3.0 to -4.0 m above ground;
지상1층 코어 1차 콘크리트 타설 (102) 단계;First floor core 1st concrete pouring stage (102);
지하1층 2차 잔여 터파기 및 지하말뚝(10)의 연결부재 설치(30) 단계;Stage 2 of excavation of the remaining excavation area on the first basement floor and installation of connecting members for underground piles (10) (30);
지상1층 코어 2차 및 지상2층 바닥 콘크리트 타설(103) 단계;Stage 1: Core 2 above ground floor and floor concrete pouring on the 2nd floor above ground (103);
지상2층 이상 코어 벽체 연속 시공 단계;Continuous construction stage of core walls above the second floor above ground;
지하2층 1차 터파기 후 지하1층 바닥 철골보 설치 단계;Stage of installing steel beams on the first basement floor after the first excavation of the second basement floor;
지하1층 바닥 콘크리트 타설 단계;Basement 1st floor concrete pouring stage;
지하1층 코어 하부벽체 타설 단계;Basement 1st floor core lower wall pouring stage;
지하3층 터파기 및 지하2층 바닥 골조 단계;Excavation of the 3rd basement floor and construction of the 2nd basement floor frame;
최하층까지 하향 터파기 및 각층 바닥/기초(반복) 단계;Downward excavation to the lowest level and each floor/foundation (repeat) step;
최하층 코어벽체 ~ 지하2층 코어벽체 상향 순타 골조 시공 단계;Construction stage of the uppermost core wall ~ the second basement floor core wall;
지하 코어벽체 골조공사 완료 단계; 및Completion stage of underground core wall skeleton construction; and
최상층(옥상)까지 층별 골조공사 반복 및 골조공사 완료 단계를 포함하여 구성된다.It consists of a stage where the skeleton construction is repeated on each floor up to the top floor (rooftop) and the skeleton construction is completed.
본 발명에 따르면 다음과 같은 효과를 기대할 수 있다.According to the present invention, the following effects can be expected.
탑다운 공사에서 지하1층 코어부분에 있어서 지상1층 바닥으로부터 하향으로 -3.0m 내지 -4.0m 구간에 철골구조물 및 테두리보를 형성하고, 이에 따라 지상1층 바닥부터 상향으로 골조공사를 연속적으로 시공할 수 있다.In top-down construction, a steel structure and a frame beam are formed in the section of -3.0m to -4.0m downward from the first floor above ground in the core section of the first basement floor, and thus the frame work can be continuously constructed upward from the first floor above ground.
지하1층 코어벽체 전체가 완성되지 않더라도(상부 부분만 완성되어도), 지상층 코어공사를 착수할 수 있다.Even if the entire basement core wall is not completed (only the upper part is completed), the ground floor core construction can begin.
지상1층 바닥으로 부터 하향으로 -3.0m 내지 -4.0m 구간을 터파기 한 후, 그 높이에서 지상1층 바닥 테두리보를 시공하고, 형틀을 해체할 수 있으므로, 지하1층의 6.0m~8.0m의 층고로 인한 높은 위치(지하1층 천정 높이) / 공간에서의 작업(비계설치, 철근, 형틀설치, 비계해체)이 삭제되어 작업생산성 및 작업의 안전성이 높아진다.After excavating a section of -3.0m to -4.0m downward from the first floor above ground, the first floor edge beam can be constructed at that height and the formwork can be dismantled. Therefore, work (installation of scaffolding, rebar, installation of formwork, dismantling of scaffolding) in a high location (ceiling height of the first basement floor) / space due to the 6.0m to 8.0m floor height of the first basement floor is eliminated, thereby increasing work productivity and work safety.
지하1층 코어벽체를 조기에 완성하므로써, 지상층 공사를 터파기 초기에 착수하므로써 전체공사기간을 단축할 수 있다.By completing the basement core wall early, the overall construction period can be shortened by starting the ground floor construction early in the excavation process.
도 1 내지 도 3은 본 발명에 따른 벽식구조의 탑다운 역타공법에서의 지상1층 철골부재를 이용한 지상1층 코어 및 외부벽체 시공방법의 흐름도이다.
도 4 내지 도 13은 본 발명에 따른 벽식구조의 탑다운 역타공법에서의 지상1층 철골부재를 이용한 지상1층 코어 및 외부벽체 시공방법의 실시예이다.Figures 1 to 3 are flow charts of a method for constructing a first-floor core and an external wall using a first-floor steel member in a top-down reverse-thrust method of a wall structure according to the present invention.
Figures 4 to 13 are examples of a method for constructing a first-floor core and an external wall using a first-floor steel member in a top-down reverse-thrust method of a wall structure according to the present invention.
이하, 본 발명에 따른 탑다운 역타공사에서의 지하1층 테두리보를 이용한 지상1층 코어벽체 시공방법의 흐름도이다.Below is a flow chart of a method for constructing a first-floor core wall using a first-floor basement frame beam in a top-down reverse excavation according to the present invention.
도 1 내지 도 3은 본 발명에 따른 탑다운 역타공법에서의 지하1층 테두리보를 이용한 지상1층 코어벽체 시공방법의 흐름도이다.Figures 1 to 3 are flow charts of a method for constructing a core wall on the first floor above ground using a basement floor edge beam in a top-down reverse-thrust method according to the present invention.
제1단계(S10)는 흙막이를 설치한다.Step 1 (S10) installs a retaining wall.
통상의 방법으로 공사부지 경계면으로 흙막이를 CIP, 슬러리월(지중연속벽)로 시공한다.In the usual way, the soil retaining wall is constructed along the boundary of the construction site using CIP and slurry wall (ground continuous wall).
제2단계(S20)는 동부분 지하말뚝(10)을 근입(지상1층바닥~최하층)한다.Step 2 (S20) involves driving underground piles (10) into the eastern part (from the first floor above ground to the lowest floor).
통상의 방법으로 동부분의 지하말뚝(10)을 PRD, RCD 공법으로 먼저 시공한다. 이어서 아파트 동 사이의 잔여부분의 지하말뚝(10)을 시공한다.In the conventional manner, the underground piles (10) of the eastern part are first constructed using PRD and RCD methods. Next, the underground piles (10) of the remaining parts between the apartment buildings are constructed.
제3단계(S30)는 지하1층 1차 터파기(지상1층 바닥 -3.0~4.0m)한다.Step 3 (S30) is the first excavation of the basement level (ground level -3.0~4.0m).
본 발명의 특징에 따라, 고층으로 올라가는 영역을 포함하는 동부분 (외주부(건물 외곽) 기둥, 코어벽체)에 있어서, 지상1층 바닥(지하말뚝(10)의 상단, 지면)으로 부터 하향으로 테두리보(101)(지상1층 바닥과 그 아래 3.0m 높이의 보)를 시공할 수 있는 높이인 -3.0m ~ 4.0m를 터파기 한다. 터파기 깊이는 현장마다 다를 수 있다.According to the features of the present invention, in the eastern part (outer perimeter (building exterior) column, core wall) including the area going up to the upper floor, a excavation is made from the first floor above ground (top of underground pile (10), ground) downward to a height of -3.0 m to 4.0 m at which a rim beam (101) (the first floor above ground and a beam 3.0 m high below it) can be constructed. The excavation depth may vary depending on the site.
지면 바로 아래는 퇴적층으로 암반이 아니고 토사이므로 포크레인으로 수일내내에 토사를 걷어 내면 되므로 터파기 기간이 짧다. 바닥이 나타나면 테두리보 하부에 버림콘크리트를 타설하는 경우, 테두리보 콘크리트 타설을 위한 테두리보 하부 동바리 설치를 용이하게 할 수 있다.The area immediately beneath the ground is composed of sedimentary soil, not bedrock. This allows for a quick excavation period, as the soil can be removed using a forklift within a few days. Once the bottom surface has been reached, pouring a slab of concrete beneath the perimeter beam facilitates the installation of a slab support for the perimeter beam concrete pour.
제4단계(S40)는 지상1층 바닥 철골보(1b) 설치한다.Step 4 (S40) installs the steel beam (1b) on the first floor above ground.
본 발명의 특징에 따라, 지상1층 바닥 철골보(1b)를 지하말뚝(10)에 연결하여 설치한다. 이에 따라, 동부분의 지상1층 바닥 철골보가 설치 완료된다.According to the features of the present invention, the first floor steel beam (1b) is installed by connecting it to the underground pile (10). Accordingly, the first floor steel beam of the eastern section is installed.
테두리보의 장치 구조는 다음과 같다.The structure of the border guard device is as follows.
지하 역타말뚝(10)에 테두리보(101)의 철골기둥(20)에 연결되고, 이어서 코어벽체 내부 철골보(1b)는 코어벽체를 따라 사각형으로 테두리보를 형성한다. 코어벽체의 두께에 따라 작은 치수의 코어벽체 내부 철골보(1b)가 설치되는 경우, 구조내력을 높이기 위하여 테두리보 상하부에 2단으로 철골보 설치, 또는 더욱 보강한 트러스 형태로 구성할 수 있다. 2단 설치시는 데두리보 상부(지상1층 바닥)에 1개, 지상1층 - 2.5~4.0m 레벨에 1개(1c)를 설치한다.The underground pile (10) is connected to the steel column (20) of the edge beam (101), and then the steel beam (1b) inside the core wall forms a square edge beam along the core wall. In case a small-sized steel beam (1b) inside the core wall is installed depending on the thickness of the core wall, in order to increase the structural strength, the steel beams can be installed in two stages above and below the edge beam, or configured in a further reinforced truss shape. In case of a two-stage installation, one is installed on the upper part of the edge beam (the floor of the first floor above ground), and one (1c) is installed on the first floor above ground - 2.5 to 4.0 m level.
테두리보 내부에 수직기둥 또는 경사재(1d)가 설치될 수도 있다.Vertical columns or inclined members (1d) may be installed inside the border beam.
코어내부의 칸막이 벽체에도 철골보가 설치될 수 있다.Steel beams can also be installed in the partition walls inside the core.
철골기둥(20)이 생략되는 경우, 철골보(1b), 하부철골보(1c)가 직접 지하 역타말뚝(10)에 연결설치될 수 있다.If the steel column (20) is omitted, the steel beam (1b) and the lower steel beam (1c) can be directly connected and installed to the underground reverse pile (10).
제5단계(S50)는 지하1층 테두리보에 콘크리트를 타설할 수 있도록 테두리보의 철근, 형틀을 설치한다.Step 5 (S50) involves installing the reinforcing bars and formwork of the perimeter beam so that concrete can be poured onto the perimeter beam on the first basement floor.
제6단계(S60)는 지상1층 바닥 콘크리트 타설을 위하여, 지상1층 바닥 데크플레이트, 데크 철근, 전기/설비 배관을 시공한다.Step 6 (S60) is to construct the first floor deck plate, deck reinforcement, and electrical/equipment piping for the first floor concrete pouring.
제7단계(S70)는 콘크리트 타설전 감리단의 검측(도면대로 시공하였는지)을 받는다.Step 7 (S70) is to receive inspection from the supervision team before pouring concrete (whether construction was done according to the drawings).
제8단계(S80)는 지하1층 1차 터파기 높이(지상1층 바닥 -3.0 ~ -4.0m구간) ~ 지상1층 바닥 코어(지상1층 바닥 테두리보) 및 지상1층 바닥 콘크리트 타설(101)한다.Step 8 (S80) is the first excavation height of the first basement floor (-3.0 to -4.0 m section from the first floor above ground) ~ the first floor floor core (first floor floor edge beam) and the first floor floor concrete pouring (101).
본 발명의 특징에 따라, 지상1층바닥으로 하향으로 -3.0 ~ -4.0m 높이(위치)에 테두리보에 있어서, 철골보와 철골기둥 주변으로 철근을 설치하고, 보 하부는 콘크리트가 아래로 흘러내리지 않도록 보 바닥 형틀 또는 와이어 메쉬로 마감한다. 이후 벽체 형틀을 설치한 후, 테두리보 콘크리트를 타설한다. 이어서 지상 1층 바닥 콘크리트를 타설한다.According to the features of the present invention, in the edge beam, at a height (location) of -3.0 to -4.0 m downward from the first floor above ground, reinforcing bars are installed around the steel beam and steel column, and the lower part of the beam is finished with a beam bottom formwork or wire mesh to prevent concrete from flowing down. After that, the wall formwork is installed, and then the edge beam concrete is poured. Subsequently, the first floor concrete is poured.
그러면 지상1층 바닥아래로 부터 T자 형태로 철골철근콘크리트(SRC)가 완성된다. 테두리보와 지상1층 바닥콘크리트는 분리타설 또는 동시 타설할 수 있다. 즉, 수직부재인 테두리보를 먼저 타설하고 수평재인 1층 슬래브를 나중에 타설할 수 있다. 또는 1층 슬래블 먼저 타설한 후, 나중에 지하1층 테두리보를 타설할 수 있다. 테두리보(오전)와 1층 슬래브(오후)를 같은 날 동시에 타설할 수 있다.Then, the steel-reinforced concrete (SRC) is completed in a T shape from below the ground floor. The perimeter beam and the ground floor concrete can be poured separately or simultaneously. That is, the vertical perimeter beam can be poured first, and the horizontal 1st floor slab can be poured later. Alternatively, the 1st floor slab can be poured first, and then the basement 1st floor perimeter beam can be poured later. The perimeter beam (morning) and the 1st floor slab (afternoon) can be poured simultaneously on the same day.
이 상태로 부터 지상1층 코어 벽체를 착수할 수 있는 토대가 마련된다.From this state, the foundation for starting the first floor core wall is prepared.
지하 1층 테두리보는 지상1층 바닥을 연결하여 수평지지력을 확보하면서, 지상1층 이상의 수직벽체의 하중을 지하말뚝(10)을 통해 지반으로 전달할 수 있는 구조를 갖게 된다.The basement 1st floor frame is structured to secure horizontal support by connecting the floor of the above-ground 1st floor, while transmitting the load of the vertical wall above the above-ground 1st floor to the ground through the underground pile (10).
동부분 외곽부분인 외주부에 기둥이 있는 경우, 지하1층 기둥 천정부근과 지상1층 바닥을 T자 형태로 콘크리트 타설하므로 수평력이 높아진다.In the case where there are columns in the outer perimeter of the eastern part, the horizontal force is increased by pouring concrete in a T shape around the ceiling of the columns on the first basement floor and the floor of the first floor above ground.
(종래에는 기둥부분의 슬라브를 타설하지 않고 1m × 1m 규모로 개구부(구멍)을 내고 지하로부터 기둥 피복이 올라올 때 마지막 단계에 타설하였다. 기둥상부 바닥을 콘크리트로 타설하면 지하1층 기둥 콘크리를 타설하기 어렵기 때문이다.)(In the past, instead of pouring the slab for the column section, an opening (hole) measuring 1m x 1m was made and the pouring was done at the last stage when the column covering was raised from the underground. This is because if the floor above the column is poured with concrete, it is difficult to pour the concrete for the column on the first basement floor.)
본 발명의 특징에 따른 이러한 구조적 특징에 따라, 테두리보의 두께와 보 내부 철골보의 크기와 수량은 구조계산(지하 기초 타설전, 지하 골조 완료 전, 지하1층 코어벽체 완료시 지상층 공사 높이와 수직, 수평하중)에 따라 결정되게 된다.According to these structural features according to the characteristics of the present invention, the thickness of the edge beam and the size and quantity of the steel beam inside the beam are determined according to the structural calculation (before pouring the underground foundation, before completion of the underground frame, and when the core wall of the first basement floor is completed, the height of the ground floor construction and the vertical and horizontal loads).
지하1층 코어벽체 완료시부터는 종래와 같이, 지하1층 코어벽체와 지하말뚝(10)이 상부하중을 담당하므로, 지하1층 코어벽체 완료시점에 지상층 높이(층수)를 반영하여 테두리보의 구조계산을 하여야 한다.From the completion of the basement 1st floor core wall, as before, the basement 1st floor core wall and underground pile (10) bear the upper load, so the structural calculation of the edge beam must be performed by reflecting the ground floor height (number of floors) at the time of completion of the basement 1st floor core wall.
제9단계(S90)는 지상1층 코어의 1차 콘크리트 타설(102)한다.Step 9 (S90) is the first concrete pouring (102) of the core on the first floor above ground.
본 발명의 특징에 따라, 지상1층 바닥의 테두리보가 완성된 이후, 상향으로 지상층 공사를 시작한다. 일반적으로 로비인 지상1층의 층고가 높으므로 2회로 콘크리트를 분할 타설하며, 1차로 지상1층 코어벽체를 시공한다.According to the features of the present invention, after the perimeter beams of the first floor are completed, construction of the ground floor begins upward. Since the first floor, which is typically the lobby, has a high ceiling, concrete is poured in two stages, with the core wall of the first floor being constructed in the first stage.
이를 위해 1층 바닥에서 코어벽체 철근과 형틀을 설치한 후 1층 코어 1차 콘크리트를 타설한다.To do this, the core wall reinforcement and formwork are installed on the first floor, and then the first floor core primary concrete is poured.
제10단계(S100)는 지하1층 2차 잔여 터파기 및 지하말뚝(10)의 연결부재를 설치(30)한다.Step 10 (S100) involves excavating the second remaining excavation site on the first basement floor and installing the connecting member of the underground pile (10) (30).
본 발명의 특징에 따라, 지상1층 바닥 하부 테두리보 시공 이후에는 콘크리트 양생기간을 거친 다음 테두리 보의 형틀과 동바리를 해체한다. 이후 통상의 방법으로 하향으로 지하1층 2차 잔여 터파기를 해나간다.According to the features of the present invention, after the construction of the lower edge beam on the first floor above ground, the formwork and support of the edge beam are dismantled after a concrete curing period. Thereafter, the secondary remaining excavation of the first basement floor is carried out downwards using the conventional method.
터파기에 따라 지하1층 바닥까지 지하말뚝(10)이 노출되면, 지하말뚝(10)면의 흙을 청소한 후, 연결부재를 용접으로 설치(30)한다. 연결부재(30)는 통상 T-Bar로 불리우며, 한쪽면에는 다수의 스터드 볼트(31)가 부착되어 콘크리트와의 부착강도를 높인다.When the underground pile (10) is exposed to the ground of the first basement floor according to the excavation, the soil on the surface of the underground pile (10) is cleaned, and then a connecting member is installed by welding (30). The connecting member (30) is commonly called a T-Bar, and a number of stud bolts (31) are attached to one side to increase the bonding strength with the concrete.
제11단계(S110)는 지상1층 코어벽체 2차 및 지상2층 바닥 콘크리트 타설(103)한다.Step 11 (S110) involves pouring concrete for the second core wall of the first floor and the second floor (103).
본 발명의 특징에 따라, 지상1층 코어벽체 1차 콘크리트 타설 이후, 지하1층 잔여벽체와 지상2층 바닥 콘크리트를 T자 형태로 타설한다.According to the features of the present invention, after the first concrete pouring of the core wall of the first floor above ground, the remaining wall of the first basement floor and the floor concrete of the second floor above ground are poured in a T shape.
제12단계(S120)는 지상2층 이상 코어벽체를 연속 시공한다.Step 12 (S120) is to continuously construct core walls above the second floor.
이후 종래의 통상의 방법으로, 지상2층 바닥 이상의 골조를 시공한다.Afterwards, the frame of the second floor or higher is constructed using the conventional method.
제13단계(S130)는 지하2층 1차 터파기 및 지하1층 바닥 철골보 설치한다.Step 13 (S130) involves excavating the first basement level and installing the steel beam on the basement level.
한편, 지하에서는 지하2층 1차 터파기를 하며, 지하1층 바닥 철골보(301, 302) 설치를 위하여 지하1층 바닥으로부터 하향으로 -2.0m 정도 터파기를 한다. 지하2층 1차 터파기로써 -2.0m 정도만 우선 파는 이유는 지하2층 전체 터파기에는 시간이 많이 소요되고, 지하1층 바닥 철골보 설치를 위한 철골 작업자가 지면으로 부터 자신의 키 높이에서 지하말뚝에 브라켓 설치, 철골보 설치, 볼팅, 용접을 용이하고 안전하게 할 수 있도록 하기 위함이다. 지하2층 터파기가 완료되면 안쪽부터 철골보를 크레인으로 설치해 나온다. 종래에는 지하2층 바닥 높이에서 위쪽으로 철골을 설치하였으나, 본 발명에 따르면, 지하1층 -2.0m 높이에서 크레인으로 하향으로 지하1층 바닥 철골보를 설치한다.Meanwhile, in the basement, the first excavation of the second basement floor is performed, and the excavation is performed downwardly about -2.0m from the floor of the first basement floor in order to install the floor steel beams (301, 302) of the first basement floor. The reason why only -2.0m is first excavated for the first excavation of the second basement floor is because it takes a lot of time to excavate the entire second basement floor, and it is to enable the steel frame workers for installing the floor steel beams of the first basement floor to easily and safely install brackets on underground piles, install the steel beams, bolt, and weld from their own height from the ground. Once the excavation of the second basement floor is completed, the steel beams are installed from the inside by a crane. Conventionally, the steel frame was installed upwardly from the floor height of the second basement floor, but according to the present invention, the floor steel beams of the first basement floor are installed downwardly by a crane from a height of -2.0m of the first basement floor.
철골보 설치와 용접이 완료되면 지하2층 2차 터파기를 계속 진행한다.Once the steel beam installation and welding are completed, the second excavation of the second basement level will continue.
제14단계(S140)는 지하1층 바닥 콘크리트를 타설한다.Step 14 (S140) is to pour concrete for the basement floor.
지하1층 바닥철골보가 설치되면, 종래의 방법으로 데크 플레이트를 설치한 후, 철근, 전기,설비 배관 후 지하1층 바닥 콘크리트(104)를 타설한다.Once the basement 1st floor steel beam is installed, the deck plate is installed in the conventional manner, and then the basement 1st floor concrete (104) is poured after the steel bars, electrical and equipment piping are installed.
제15단계(S150)는 지하1층 코어벽체 1차 콘크리트를 타설한다.Step 15 (S150) involves pouring the first concrete for the core wall of the first basement floor.
지하1층 바닥이 완성되면, 지하1층은 층고가 높으므로 2회로 분할하여, 종래의 방법으로 지하1층 코어벽체를 1차 높이로 콘크리트(105) 타설한다.When the basement floor is completed, the basement floor is divided into two stages because it has a high ceiling, and concrete (105) is poured into the basement floor core wall to the first height using the conventional method.
제16단계(S160)는 지하1층 코어벽체 2차(잔여분) 타설한다.Step 16 (S160) is to pour the second (remaining) core wall of the first basement floor.
지하1층 코어벽체를 1차 콘크리트 타설 후에는 비계설치, 철근, 형틀을 설치한 후 지하1층 잔여 벽체 콘크리트(106)를 타설한다. 테두리보 하부의 지하1층 코어벽체 콘크리트는 1차 또는 2차로 타설하며, 현장에 따라 달라진다.After the first concrete pouring of the basement 1st floor core wall, scaffolding, reinforcing bars, and formwork are installed, and then the remaining basement 1st floor wall concrete (106) is poured. The basement 1st floor core wall concrete below the edge beam is poured in one or two stages, and this varies depending on the site.
이로써 지하1층 코어벽체의 골조가 완료되었으며, 지상은 지상 3층 내지 지상 5층 정도에서 시공하고 있게 된다. 지상1층과 2층은 층고가 높고, 지상 3층은 통상적으로 아파트 또는 주상복합인 경우, 피트층 또는 전이층이다. 지상 4층 세대 기준층에서는 외부 형틀 폼(갱폼), 내부 벽체 및 슬라브 알폼 세팅에 많은 시간이 소요된다. 따라서 지하1층 코어벽체 완료시점과 지상 3층 내지 4층은 같은 시점에 있게 된다.With this, the skeleton of the basement core wall has been completed, and construction is currently underway on the 3rd to 5th floors above ground. The 1st and 2nd floors above ground have high ceilings, and the 3rd floor above ground is typically a pit or transition floor in apartments or mixed-use buildings. For the 4th floor above ground, a considerable amount of time is required for the external formwork (gang form), internal walls, and slab formwork setting. Therefore, the completion of the basement core wall and the 3rd to 4th floors will occur at the same time.
제17단계(S170)는 지하3층 터파기 및 지하2층 바닥 골조 시공한다.Step 17 (S170) involves excavating the 3rd basement floor and constructing the 2nd basement floor frame.
통상의 방법으로, 지하3층을 터파기 한 후 지하2층 바닥을 시공한다.In the usual way, the third basement floor is excavated and then the second basement floor is constructed.
제18단계(S180)는 최하층까지 하향 터파기 및 각층 바닥/기초(반복) 시공한다. 통상의 방법으로, 최하층(지하5층, 지하7층)까지 각 층 터파기 후 각 층 바닥을 역타 하향 시공해 나간다.Step 18 (S180) involves excavating down to the lowest level and constructing the floor/foundation (repeatedly) on each floor. Using the conventional method, excavation is performed on each floor down to the lowest level (5th and 7th basement levels), and then the floors are constructed downward using reverse excavation.
제19단계(S190)는 최하층 코어벽체 ~ 지하2층 코어벽체를 상향으로 순타방식으로 골조를 시공한다. 통상의 방법으로, 최하층 동기초 (매트) 시공 후에는 유턴하여 상향으로 지하수직부재를 시공해나간다. 지하1층 벽체까지는 이미 시공되어 있으므로 최하층부터 지하2층까지 시공해나간다.Step 19 (S190) involves constructing the skeleton from the lowest core wall to the second basement level using a sequential method. Following the construction of the lowest floor's slab (mat), a U-turn is made to construct the vertical underground members upward. Since the walls up to the first basement level have already been constructed, construction proceeds from the lowest level to the second basement level.
제20단계(S200)는 지하 코어벽체 골조공사 완료한다. 지하골조가 완료되면, 지상층은 층수 제한없이 옥상층까지 올릴 수 있다.Step 20 (S200) completes the underground core wall skeleton construction. Once the underground skeleton is complete, the ground floor can be extended to the rooftop without any floor restrictions.
제21단계(S210)는 최상층(옥상)까지 층별 골조공사 반복 및 골조공사 완료한다. 최상층(옥상층)까지 골조공사를 진행하여 골조공사를 완료하고, 통상적으로 골조공사 완료 후 약 10개월 내지 11월 동안 마감공사(인테리어)를 하고 공사를 준공하고 입주한다.Step 21 (S210) involves repeating the skeletal construction on each floor up to the rooftop and completing the skeletal construction. The skeletal construction is completed by completing the skeletal construction up to the rooftop. Typically, finishing work (interior decoration) takes approximately 10 to 11 months after the skeletal construction is completed, and construction is completed and occupancy begins.
도 4 내지 도 47은 본 발명에 따른 탑다운 역타공사에서의 지하1층 테두리보를 이용한 지상1층 코어벽체 시공방법의 실시예이다.Figures 4 to 47 are examples of a method for constructing a core wall on the first floor above ground using a basement floor edge beam in a top-down reverse excavation work according to the present invention.
도 4는 종래방법에 따라 지하말뚝(10)을 지중에 근입하여 시공한 예시이다.Figure 4 is an example of construction in which an underground pile (10) is driven into the ground according to a conventional method.
도 5는 지하 지반을 추가로 칼라로 표시한 것이다.Figure 5 shows the underground ground additionally colored.
도 6은 지하1층 1차 터파기(100) -3.0m를 칼라로 표시한 것이다.Figure 6 shows the first excavation (100) -3.0m on the first basement floor in color.
도 7은 본 발명의 특징에 따라, 지하1층 테두리보의 철골기둥(20)을 코어벽체 내부 위치에 설치한 것이다.Fig. 7 shows a steel column (20) of a basement first floor frame beam installed at an internal location of a core wall according to a feature of the present invention.
도 8은 도 7의 확대도이다.Figure 8 is an enlarged view of Figure 7.
도 9는 본 발명의 특징에 따라, 지하1층 테두리보에 콘크리트가 타설된 것이다.Fig. 9 shows concrete poured on the first basement floor edge beam according to a feature of the present invention.
도 10은 본 발명의 특징에 따라, 지하1층 테두리보의 장치 구성을 나타낸 것이다. 지하말뚝에 테두리보 기둥이 설치되고, 테두리보의 상부 철골보, 하부 철골보, 수직기둥 또는 경사재가 설치되어 철골구조물을 형성한다.Figure 10 illustrates the device configuration of a first-floor basement frame beam according to a feature of the present invention. Frame beam columns are installed on underground piles, and upper steel beams, lower steel beams, vertical columns, or inclined members of the frame beam are installed to form a steel structure.
도 11은 본 발명의 특징에 따라, 테두리보의 평면도이다. 지하 역타말뚝(10)에 테두리보(101)의 철골기둥(20)에 연결되고, 이어서 철골보(1b)가 설치된다. 하부에는 하부철골보(1c)와 경사재(수직기둥)(1d)가 설치된다. 철골기둥(20)이 생략되는 경우, 철골보(1b), 하부철골보(1c)가 직접 지하 역타말뚝(10)에 연결설치될 수 있다.Fig. 11 is a plan view of a perimeter beam according to a feature of the present invention. The perimeter beam (101) is connected to a steel column (20) of an underground reverse pile (10), and then a steel beam (1b) is installed. A lower steel beam (1c) and a sloped member (vertical column) (1d) are installed below. If the steel column (20) is omitted, the steel beam (1b) and the lower steel beam (1c) can be directly connected and installed to the underground reverse pile (10).
도 12 내지 도 13은 도 11의 상세도이다.Figures 12 and 13 are detailed views of Figure 11.
지하말뚝(10)은 종래방법에 따라 시공된 두꺼운 철골기둥이며, 가로 43cm, 세로 49cm, 두께 7cm이며, 지상1층 바닥부터 지하6~8층 최하층 기초까지 35m 정도 깊이로 근입되어 있고, 지상층의 하중을 지하로 전달하는 역할을 한다. 사각형의 코어벽체에 10cm 떨어진 위치에 5m 내지 6m간격으로 10개 이상이 시공되어 있다.The underground pile (10) is a thick steel column constructed according to a conventional method, measuring 43 cm in width, 49 cm in height, and 7 cm in thickness. It is installed to a depth of approximately 35 m from the floor of the first floor above ground to the foundation of the lowest floors of the sixth to eighth floors underground, and serves to transfer the load of the ground floor to the underground. More than 10 of them are constructed at intervals of 5 to 6 m at a distance of 10 cm from the square core wall.
테두리보 철골기둥(20)은 지하말뚝(10)에 연결재(철골 플레이트)를 통해 연결되어 있으며, 가로 20cm, 세로 20cm이다.The steel frame column (20) of the border is connected to the underground pile (10) through a connecting material (steel plate) and is 20 cm wide and 20 cm long.
코어벽체의 두께는 40cm이고, 철골기둥(20)과 철골보(1b)를 제외한 피복두께는 좌우 각각 10cm이며, 그 부분에 벽체 철근을 시공한다.The thickness of the core wall is 40 cm, and the covering thickness excluding the steel column (20) and steel beam (1b) is 10 cm on each side, and wall reinforcement is installed in that area.
지상1층 바닥 철골보(1b)는 두께는 20cm이고 높이는 구조계산에 따라 결정된다. 보와 콘크리트간의 접합력을 높이기 위하여 좌우에 스터드 볼트(31)가 부착된다(표시 생략).The steel beam (1b) on the first floor above ground has a thickness of 20 cm and its height is determined based on structural calculations. Stud bolts (31) are attached on both sides to increase the bonding strength between the beam and concrete (not shown).
지상1층 바닥 철골보(1b)는 지상1층 바닥높이에 1개, 테두리보 하부 레벨에 1개(1c)로 2단으로 하여 트러스 형태로 구성될 수 있다.The first floor steel beam (1b) can be configured in a truss shape in two stages, one at the height of the first floor and one at the lower level of the edge beam (1c).
경사재와 수직철골기둥(1d)이 추가로 설치될 수 있다.Additional inclined members and vertical steel columns (1d) may be installed.
테두리보(101)은 철골설치, 철근설치, 형틀설치(지하1층 터파기 레벨로부터 동바리 설치)후 콘크리트를 테두리보(코어 높이 2.5m, 코어벽체 두께 40cm)와 지상1층 바닥(30cm)을 콘크리트 분할타설 또는 동시타설로 T자 형태로 구성하면서 코어내부, 외부벽체, 외주부기둥과 함께 시공되어 강한 구조내력을 형성하는 효과를 갖는다.The edging beam (101) is constructed by installing steel frames, reinforcing bars, and formwork (installing a support beam from the excavation level of the first basement floor), and then pouring concrete into the edging beam (core height 2.5 m, core wall thickness 40 cm) and the first floor above ground (30 cm) in a T-shape by pouring concrete separately or simultaneously, and is constructed together with the core interior, exterior wall, and exterior perimeter columns, thereby forming a strong structural strength.
본 발명에 따른 탑다운 역타공사에서의 지하1층 철골구조물과 테두리보를 이용한 지상1층 코어벽체 착수방법은 지상1층 바닥 레벨의 테두리보를 철골구조로 보강 시공하여 지상층으로 진행하며, 지하1층에서도 역타구조를 시행할 수 있어, 탑다운 건설현장에 바로 이용할 수 있다.The method for starting a core wall on the first floor above ground using a steel structure and a frame beam on the first basement floor in a top-down reverse excavation work according to the present invention proceeds to the ground floor by reinforcing the frame beam on the first floor floor level with a steel structure, and since the reverse excavation structure can be implemented even on the first basement floor, it can be used directly in a top-down construction site.
10 : 지하역타말뚝
20 : 테두리보 철골기둥
30 : 연결부재 T-Bar
31 : 스터드 볼트
1b : 지상1층 바닥 철골보
1c : 테두리보 하부 철골보
1d : 테두리보 수직재 또는 경사재
301 : 지하1층 바닥 철골보
101 : 테두리보 콘크리트
102 : 지상1층 코어벽체 1차 콘크리트
104 : 지하1층 바닥 콘크리트
105 : 지하1층 코어벽체 1차 콘크리트
106 : 지하1층 잔여 벽체 콘크리트
107 : 지하2층 벽체 콘크리트10: Underground station piles
20: Steel frame column with edging
30: Connecting member T-Bar
31: Stud bolt
1b: Steel beam on the first floor above ground
1c: Lower steel beam of the border beam
1d: Border beam vertical or inclined member
301: Basement 1st floor steel beam
101: Concrete for the edge beam
102: 1st floor core wall 1st concrete
104: Concrete floor on the first basement level
105: Basement 1st floor core wall 1st concrete
106: Remaining concrete wall of basement 1st floor
107: Concrete wall on the second basement floor
Claims (1)
흙막이 설치 단계;
동부분 지하말뚝(10) 근입 (지상1층바닥~최하층) 단계;
지하1층 1차 터파기 (지상1층 바닥 -3.0~5.0m) 단계;
지상1층 코어벽체 내부 철골기둥(20)설치 단계;
지상1층 바닥 철골보(1c, 1b) 설치 단계;
상기 1차 터파기된 상부의 코어부분에 철근, 형틀을 설치하는 단계;
지상1층 바닥 -3.0 ~ -4.0m구간으로부터 지상1층 바닥 코어 및 바닥 콘크리트 타설(101) 단계;
지상1층 코어 1차 콘크리트 타설 (102) 단계;
지상1층 코어 2차 및 지상2층 바닥 콘크리트 타설(103) 단계; 및
지상2층 이상 코어 벽체 연속 시공 단계
를 포함하는 것을 특징으로 하는 지상층 코어공사 착수방법.
In the method of commencing ground floor core construction in top-down reverse excavation work,
Steps for installing the retaining wall;
Eastern part underground pile (10) insertion stage (1st floor above ground to lowest floor);
Basement 1st floor 1st excavation stage (1st floor above ground -3.0~5.0m)
Installation stage of steel columns (20) inside the core wall of the first floor above ground;
Installation stage of the steel beam on the first floor above ground (1c, 1b);
A step of installing reinforcing bars and formwork in the upper core portion of the first excavation;
Step 101: pouring of floor core and floor concrete on the first floor from the section -3.0 to -4.0 m above ground;
First floor core 1st concrete pouring stage (102);
Step 103 of pouring concrete for the second core of the first floor and the second floor above ground; and
Continuous construction stage of core walls above the second floor above ground
A method for commencing ground floor core construction, characterized by including:
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| KR1020240063542A KR20250164066A (en) | 2024-05-15 | 2024-05-15 | Construction method and apparatus of the core wall structure on the ground floor using steel column and girder inside the core wall in 1st basement in top down construction |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| KR1020240063542A KR20250164066A (en) | 2024-05-15 | 2024-05-15 | Construction method and apparatus of the core wall structure on the ground floor using steel column and girder inside the core wall in 1st basement in top down construction |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| KR20250164066A true KR20250164066A (en) | 2025-11-24 |
Family
ID=97877090
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| KR1020240063542A Pending KR20250164066A (en) | 2024-05-15 | 2024-05-15 | Construction method and apparatus of the core wall structure on the ground floor using steel column and girder inside the core wall in 1st basement in top down construction |
Country Status (1)
| Country | Link |
|---|---|
| KR (1) | KR20250164066A (en) |
-
2024
- 2024-05-15 KR KR1020240063542A patent/KR20250164066A/en active Pending
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| KR102588684B1 (en) | Method for constructing basement vertical member of top-down method constructed alternately | |
| CN106149868A (en) | Prefabricated buildings architectural structure system and assembly method thereof | |
| KR101267565B1 (en) | Construction method of under-ground core part structure in top-down construction procedure | |
| RU2220258C1 (en) | Process of erection of multilevel underground structure ( variants ) | |
| KR102396786B1 (en) | Underground expansion and top-down method of new building using reinforcement of existing underground outer wall | |
| RU2136818C1 (en) | Method for building of multistory underground structure with simultaneous excavation of basin | |
| CN115559351B (en) | Reverse construction method for multi-layer basement of all-steel structure | |
| KR100694493B1 (en) | Reverse casting method to use the temporary structure supported by brackets as a workbench | |
| KR20250164066A (en) | Construction method and apparatus of the core wall structure on the ground floor using steel column and girder inside the core wall in 1st basement in top down construction | |
| RU190322U1 (en) | Device for the construction of multi-storey underground structures | |
| CN210857277U (en) | Assembled underground structure | |
| KR100593203B1 (en) | Construction method of underground structure using deck support frame for side pressure support formation and deck support frame for side pressure support formation | |
| KR100679986B1 (en) | Installation structure of suspension type support girders for flat plate deck installation and reverse casting method using the same | |
| JP2022554045A (en) | Underground vertical member construction method of reversed construction that is alternately constructed every other floor | |
| JP2536249B2 (en) | Lift-down underground structure construction method | |
| JP6682173B1 (en) | How to build a building | |
| KR20240068954A (en) | Continuous construction method of the superstructure by adding spare piles to the lowest basement floor in the top-down construction project | |
| JPH08165662A (en) | Construction method of underground structure | |
| KR200369485Y1 (en) | a deck supportframe | |
| KR101026112B1 (en) | Construction method of underground structures using mega structure | |
| KR20240144025A (en) | Method of constructing underground vertical members using Top Down Construction Method of alternating construction one by one | |
| KR20240069939A (en) | Construction Method of Ground Floor Core Construction according to Start of Semi-Basement Core at 1st Basement Floor in Top-Down Construction | |
| KR20250048506A (en) | Elevator machine room steel structure and construction method | |
| JP2761528B2 (en) | How to build structures | |
| KR20250048507A (en) | Elevator machine room steel structure and construction method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PA0109 | Patent application |
St.27 status event code: A-0-1-A10-A12-nap-PA0109 |
|
| PG1501 | Laying open of application |
St.27 status event code: A-1-1-Q10-Q12-nap-PG1501 |
|
| Q12 | Application published |
Free format text: ST27 STATUS EVENT CODE: A-1-1-Q10-Q12-NAP-PG1501 (AS PROVIDED BY THE NATIONAL OFFICE) |