KR20250124265A - A method of structural construction using steel girder and deck plate at pit floor in apartment structural construction - Google Patents

A method of structural construction using steel girder and deck plate at pit floor in apartment structural construction

Info

Publication number
KR20250124265A
KR20250124265A KR1020240020053A KR20240020053A KR20250124265A KR 20250124265 A KR20250124265 A KR 20250124265A KR 1020240020053 A KR1020240020053 A KR 1020240020053A KR 20240020053 A KR20240020053 A KR 20240020053A KR 20250124265 A KR20250124265 A KR 20250124265A
Authority
KR
South Korea
Prior art keywords
wall
steel
installing
floor
apartment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
KR1020240020053A
Other languages
Korean (ko)
Inventor
양경옥
Original Assignee
양경옥
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 양경옥 filed Critical 양경옥
Priority to KR1020240020053A priority Critical patent/KR20250124265A/en
Publication of KR20250124265A publication Critical patent/KR20250124265A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/32Floor structures wholly cast in situ with or without form units or reinforcements
    • E04B5/36Floor structures wholly cast in situ with or without form units or reinforcements with form units as part of the floor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

본 발명은 아파트 건설공사에서 피난안전구역층인 피트층의 골조공사 기간을 단축하기 위한 것으로, 피트층 벽체를 재래식으로 시공한 후, 천정을 데크 플레이트로 시공하거나, 철골기둥과 철골보를 설치하고 상기 철골보에 데크 플레이트를 설치하여 시공하는 것에 관한 것이다.The present invention is intended to shorten the period of skeletal construction of a pit layer, which is a refuge safety zone layer, in an apartment construction project, and relates to construction by constructing a pit layer wall in a conventional manner and then constructing a ceiling with a deck plate, or by installing steel columns and steel beams and then installing a deck plate on the steel beams.

Description

아파트 피난구역(피트)층 공사방법 및 이를 위한 장치{A method of structural construction using steel girder and deck plate at pit floor in apartment structural construction} {A method of structural construction using steel girders and deck plates at pit floors in apartment structural construction}

본 발명은 아파트 건설공사에서 피난안전구역층인 피트층의 골조공사 기간을 단축하기 위한 것으로, 피트층 벽체를 재래식으로 시공한 후, 천정을 데크 플레이트로 시공하거나, 철골기둥과 철골보를 설치하고 상기 철골보에 데크 플레이트를 설치하여 시공하는 것에 관한 것이다.The present invention is intended to shorten the period of skeletal construction of a pit layer, which is a refuge safety zone layer, in an apartment construction project, and relates to construction by constructing a pit layer wall in a conventional manner and then constructing a ceiling with a deck plate, or by installing steel columns and steel beams and then installing a deck plate on the steel beams.

40층~49층 아파트에는 일반적으로 화재시 피난할 수 있는 피난안전구역이 22층 내지 26층 사이에 있다.In apartment buildings with 40 to 49 floors, the fire safety zone is usually between the 22nd and 26th floors.

피난안전구역은 화재시 주민들이 피난할 수 있는 공간, 펌프실, 제연휀룸(연기 배출), 피트(설배 배관으로 수직 통로) 등이 있으며, 사람이 거주하지 않는다.The refuge safety zone is a space where residents can evacuate in case of a fire, including a pump room, smoke exhaust fan room (for smoke discharge), and a pit (a vertical passageway with a flue pipe), and is not inhabited by people.

피난층은 일반적으로 층고가 4.8m 내지 5.5m 등으로 높다.The shelter floor is generally high, with a floor height of 4.8 m to 5.5 m.

이에 따라 아래의 기준층 2.85m의 세대에서는 알폼의 거푸집 형틀을 사용하지만 피난층에서는 알폼과 유로폼을 혼용해야 한다.Accordingly, in the 2.85m standard floor below, the formwork frame of Alform is used, but in the refuge floor, Alform and Euroform must be used together.

높은 위치의 천정슬래브를 시공하기 위해서는 시스템 비계(동바리, 서포트)를 설치해야 하고, 콘크리트 타설 후에는 내부로 들어가 서포트 해체, 천정 형틀해체, 벽체 형틀 해체를 해야 한다.In order to construct a high ceiling slab, a system scaffolding (support) must be installed, and after pouring the concrete, the support, ceiling formwork, and wall formwork must be dismantled by going inside.

이에따라 시공시, 시공 후 해체시 비용과 인력이 많이 소요되는 문제가 있다.Accordingly, there is a problem that a lot of cost and manpower is required during construction and dismantling after construction.

따라서 일반적이지 않은 피트층 한 개층에 많은 시간이 소요되어 전체공기간이 증가하는 문제를 해결하기 위한 새로운 공사방법이 필요한 실정이다.Therefore, a new construction method is needed to solve the problem of increasing the overall air space by taking a lot of time for one unusual pit layer.

본 발명은 상기와 같은 아파트 피난층 골조공사에서 재래식 공사로 인한 시간과 노력이 많이 소요되는 문제와 과제를 해결하기 위한 것이다.The present invention is intended to solve the problems and challenges of requiring a lot of time and effort due to conventional construction in the above-mentioned apartment evacuation floor frame construction.

[천청 슬래브 서포트 설치][Installation of the ceiling slab support]

천정 슬래브 형틀을 설치하기 위해 다수의 시스템 비계(조립하는 견고한 비계, 동바리, 서포트)를 설치해야 하는데, 시간과 인력이 많이 들어간다.Installing the ceiling slab formwork requires the installation of multiple system scaffolds (rigid scaffolds, joists, and supports) which is time-consuming and labor-intensive.

시스템 비계 설치시, 20명 내지 25명이 수일간 작업해야 한다.When installing a system scaffold, 20 to 25 people must work for several days.

[천청 슬래브 서포트 해체][Dismantling of the ceiling slab support]

천정 슬래브 타설 후 양생기간을 거친 후 높은 위치의 시스템 비계를 해체하여 반출하는데 시간과 노력이 많이 소요된다.After the ceiling slab has been poured and the curing period has passed, it takes a lot of time and effort to dismantle and remove the high-level system scaffolding.

피난층은 벽으로 둘러싸여 지고, 창문이 작으므로, 시스템 비계를 해체하여 1층으로 내리는데, 인력, 타워크레인, 호이스트 사용기간이 증가하여 상부 세대층 공사에 지장을 준다.The shelter floor is surrounded by walls and has small windows, so the system scaffolding is dismantled and lowered to the first floor, which increases the use of manpower, tower cranes, and hoists, hindering construction on the upper floors.

[재래식 슬래브 형틀 설치][Conventional slab formwork installation]

천정에 목재 및 합판으로 거푸집을 설치해야 하므로, 인력에 의한 자재운반 설치로 시간이 크게 소요된다.Since the formwork must be installed on the ceiling using wood and plywood, it takes a lot of time to transport and install the materials by hand.

[재래식 슬래브 형틀 해체][Dismantling of conventional slab formwork]

높은 위치의 천정 거푸집을 해체하는데 안전재해의 위험이 높다. 시간과 비용이 증가한다.Dismantling high-altitude ceiling formwork carries a high risk of safety hazards, increasing time and costs.

[전부 재래식 공사방법][All conventional construction methods]

형틀 작업이 전부 재래식으로 시간과 비용이 크게 증가한다.All the formwork is done conventionally, which greatly increases the time and cost.

[공사기간의 증가][Increase in construction period]

재래식 형틀 설치로 인하여 작업시간이 많이 소요된다. 일반적으로 피난층은 30일 내지 35일이 소요되고 있다.The installation of conventional formwork requires considerable time. Typically, shelter layers take 30 to 35 days to construct.

[마감공사의 중단][Suspension of finishing work]

중간의 피난층에서 약 한달간 공사가 중지되므로 하부에서 따라 올라오는 마감공사(창호, 조적, 미장, 방수, 인테리어)도 중단되어 작업의 연속성이 떨어지고 손실이 발생한다.Since construction is halted for about a month on the middle shelter, finishing work (windows, masonry, plastering, waterproofing, interior design) coming up from below is also halted, reducing the continuity of work and causing losses.

[천청 슬래브 서포트 설치][Installation of the ceiling slab support]

높은 위치의 천정 슬래브 형틀을 설치하기 위해 시스템 비계(동바리, 서포트)를 설치하지 않도록 한다. 이를 위해 무지주 공법을 고안한다. 데크 플레이트를 설치하는 공사방법을 고안한다.To install the ceiling slab formwork at high elevations, avoid installing system scaffolding (supports). To achieve this, a non-supporting method is developed. A construction method for installing deck plates is also developed.

[천청 슬래브 서포트 해체][Dismantling of the ceiling slab support]

서포트를 설치하지 않는 방법으로 하며, 무지주 공법을 사용하도록 한다.This is done by installing no support and using a non-supporting method.

[재래식 슬래브 형틀 설치][Conventional slab formwork installation]

데크 플레이트를 설치하도록 한다.Install the deck plate.

[철골기둥과 보의 설치][Installation of steel columns and beams]

데크 플레이트를 설치하기 위하여 철골기둥과 보를 일부 구간에 설치하도록 한다. 데크 플레이트는 상기 철골보에 거치하여 설치하도록 한다.To install the deck plate, steel columns and beams are installed in some sections. The deck plate is installed by being placed on the steel beams.

[앵글의 설치][Installation of angle]

철골기둥과 보를 설치하는 않는 경우, 벽체 상부에 ‘ㄱ’자 앵글을 설치한다. 데크 플레이트는 상기 앵글에 거치하여 설치하도록 한다.If steel columns and beams are not installed, an ‘L’-shaped angle is installed on the upper part of the wall. The deck plate is installed by resting on the angle.

또한 벽체상부에 엠베드 플레이트, 거셋 플레이트를 설치하여 철골보를 설치하도록 한다.Additionally, embed plates and gusset plates are installed on the upper part of the wall to install the steel beam.

[재래식 슬래브 형틀 해체][Dismantling of conventional slab formwork]

해체 작업이 생략되도록 데크 플레이트를 사용하도록 한다.Deck plates are used to eliminate dismantling work.

[공사기간의 증가][Increase in construction period]

철골기둥, 철골보, 앵글, 데크 플레이트의 철골조 구조와 재래식 철근, 형틀의 조합으로 작업을 단순화하여 공사기간을 15일 내지 17일로 단축하도록 한다.The steel frame structure of steel columns, steel beams, angles, and deck plates, combined with conventional rebar and formwork, simplifies the work and shortens the construction period to 15 to 17 days.

[마감공사의 중단][Suspension of finishing work]

마감공사의 중단이 최소호하도록 피난층 공사기간을 단축하도록 한다.The construction period for the shelter floor will be shortened to minimize disruption to finishing work.

본 발명에 따르면, 높은 피난층 벽체 상부에 데크 플레이트를 설치할 수 있는 받침보(철골보, 앵글)를 설치함에 따라 생략되는 작업은 아래와 같다.According to the present invention, the work that is omitted by installing a support beam (steel beam, angle) that can install a deck plate on the upper part of a high refuge floor wall is as follows.

1) 높은 층고의 시스템 비계 설치 작업이 생략된다.1) The installation of high-floor system scaffolding is omitted.

이에 따라 시스템 비계 자재 운반(다수의 트럭),Accordingly, transport of system scaffolding materials (multiple trucks),

타워크레인으로 자재 올림(양중),Lifting materials with a tower crane (lifting),

수십명의 비계설치 작업자들의 수일간의 설치작업Days of installation work by dozens of scaffolding installers

시스템 비계의 많은 하중을 위한 하부층의 동바리 보강Reinforcement of the lower floor of the scaffold for high loads of the system scaffold

이 생략된다.This is omitted.

2) 높은 층고의 시스템 비계 해체 작업이 생략된다.2) The work of dismantling high-floor system scaffolding is omitted.

이에 따라 수십명의 비계설치 작업자들의 수일간의 해체 작업This resulted in several days of dismantling work by dozens of scaffolding workers.

타워크레인 또는 호이스트로 시스템 비계 자재 내림,Lowering of system scaffolding materials using tower cranes or hoists;

시스템 비계 자재를 창고로 운반(다수의 트럭)Transporting system scaffolding materials to the warehouse (multiple trucks)

3) 피난층 작업기간의 단축3) Shortening the shelter layer work period

종래의 30일 내지 35일의 작업기간이 15일 내지 17일로 변경되어, 15일 내지 20일의 전체 공사기간이 단축된다.The previous 30 to 35-day work period was changed to 15 to 17 days, shortening the overall construction period by 15 to 20 days.

공사기간 단축은 현장관리자, 작업자, 현장관리비, 타워크레인, 호이스트 임대비용 감소, 조합 및 시행사의 프로젝트 파이낸싱 이자의 감소, 입주자의 빠른 입주 효과를 갖는다.Shortening the construction period has the effect of reducing the cost of site managers, workers, site management fees, tower cranes, and hoist rental fees, reducing project financing interest for the association and developer, and allowing residents to move in more quickly.

4) 연속적인 마감공사의 진행4) Progress of continuous finishing work

중간부분에서 공사기간이 최소화되므로, 마감공사가 진행되다가 중단되는 기간도 최소화되고 연속적인 층별 마감공사를 진행할 수 있다.Since the construction period is minimized in the middle section, the period during which finishing work is interrupted is also minimized, and finishing work can be carried out continuously on each floor.

도 1 내지 도 28는 본 발명에 따른 실시예 1이다.
도 29 내지 도 31은 본 발명에 따른 실시예 2이다.
Figures 1 to 28 are Example 1 according to the present invention.
Figures 29 to 31 are Example 2 according to the present invention.

이하에서는 첨부된 도면을 참조로 본 발명에 따른 피난층 데크 플레이트 받침보를 이용한 골조공사 시공방법을 나타낸다.Below, with reference to the attached drawings, a method for constructing a skeletal structure using a shelter deck plate support beam according to the present invention is shown.

아래는 본 발명에 따른 공사방법 실시예 1의 순서이다. 실시예 1은 데크 플레이트를 설치하기 위한 데크 플레이트 받침용 철골보를 벽체에 매립된 엠베드 플레이트에 설치하는 방식이다.Below is the sequence of Example 1 of the construction method according to the present invention. Example 1 is a method of installing a steel beam for supporting a deck plate for installing a deck plate on an embed plate embedded in a wall.

1) 피난층 바닥 콘크리트를 타설한다.1) Pour concrete on the refuge floor.

2) 피난층 벽체높이(4.8m~5.5m)의 약 절반인 1차 콘크리트를 타설하기 위하여, 벽체 철근, 벽체형틀을 설치한다.2) To pour the first concrete, which is approximately half the height of the refuge floor wall (4.8m to 5.5m), install the wall reinforcement and wall formwork.

피난층 외부의 갱폼의 높이가 세대 기준층 높이이므로, 피난층을 한번에 타설할 수 없고 2회에 나누어 콘크리트를 타설해야 한다.Since the height of the gang form outside the shelter layer is the height of the standard floor of the household, the shelter layer cannot be poured at once and the concrete must be poured in two parts.

3) 피난층 벽체의 1차 콘크리트를 타설한다.3) Pour the primary concrete of the refuge floor wall.

4) 높은 위치의 벽체 2차 철근을 설치하기 위하여, 벽체 주변으로 비계(철근, 형틀 작업용)를 설치한다.4) To install secondary reinforcement bars on high walls, scaffolding (for reinforcement bars and formwork) is installed around the wall.

5) 벽체2차 철근을 설치한다.5) Install the secondary wall reinforcement.

6) 이때 벽체에 철골보를 설치하기 위한 엠베드 플레이트(벽체와 철골보의 연결재중의 하나)를 설치한다. 엠베드 플레이트는 벽체 철근을 이용하여 철사줄로 묶는 방법, 철근에 용접하는 방법, 벽체 형틀에 부착, 연결하는 방법 등을 사용한다.6) At this time, an embed plate (one of the connecting materials between the wall and the steel beam) is installed to install the steel beam on the wall. The embed plate can be installed by tying it with wire using the wall steel, welding it to the steel, or attaching it to the wall formwork.

7) 벽체2차 형틀을 설치한다.7) Install the secondary wall formwork.

8) 피난층 벽체의 2차 콘크리트를 타설하여 피난층 벽체(높이 4.8m~5.5m)를 완성한다.8) Pour the secondary concrete on the refuge wall to complete the refuge wall (4.8m to 5.5m in height).

9) 데크 플레이트를 설치하기 위한 받침보(앵글, 철골보(H빔) 등)를 설치하기 위하여 벽체 상부의 벽체 형틀을 해체한다. 벽체 전체 형틀을 해체하여 천정이 닫히기 전(데크 플레이트 설치전)에 형틀을 1층으로 내리는 것이 유리하다. 천정이 닫히면, 타워크레인으로 들어서 내리기 어렵다.9) To install the supporting beams (angles, steel beams (H-beams), etc.) for the deck plate, the wall formwork at the top of the wall must be dismantled. It is advantageous to dismantle the entire wall formwork and lower it to the first floor before the ceiling is closed (before the deck plate is installed). Once the ceiling is closed, it is difficult to lift and lower it with a tower crane.

10) 벽체 상부에 상기 받침보를 설치한다. 일반형 데크 플레이트는 일반적으로 최대 4.5m길이를 설치할 수 있다. 데크의 길이가 4.5m를 넘어가면 데크 중앙부분이 아래로 처지기 때문이다. 벽간의 거리가 4.5m를 넘는 부분에는 중간에 철골보를 설치하여 데크 길이기 4.5m를 넘지않도록 분할한다. 만약 철골보의 길이가 길 경우에는 철골보의 부재 규격이 커져야 하므로, 중간에 철골기둥을 설치하여 철골보의 규격을 줄이도록 한다.10) Install the above-mentioned support beam on the upper part of the wall. The standard deck plate can generally be installed up to 4.5 m in length. This is because the central part of the deck will sag if the deck length exceeds 4.5 m. In the area where the distance between the walls exceeds 4.5 m, install a steel beam in the middle to divide the deck length so that it does not exceed 4.5 m. If the length of the steel beam is long, the size of the steel beam member must be increased, so install a steel column in the middle to reduce the size of the steel beam.

또한, 벽체 부분에는 앵글을 설치한다. 앵글은 다양한 모양이 사용될 수 있다. 사용될 수 있는 앵글의 종류는 ㄱ자(등변, 부등변) ㄷ자 I자 형태를 포함한다. 예로 외벽부분의 벽체 상부에 앵글이 설치된다. 앵글을 벽체상부에 부착하여 고정하는 방법은 벽체에 앵글을 대고 앵글측으로 부터 벽체내부로 앙카볼트를 삽입(때려 넣는)하는 방식, 벽체에 설치된 엠베드 플레이트에 거치 및 용접하는 방식, 벽체 내부에 매립앙카를 미리 설치한 후 콘크리트를 타설하고 앵글을 대고 볼트로 매립앙카에 고정하는 방식, 상부 앵글(벽체 내부의 기둥 또는 보에 부착된 앵글)에 앵글을 메다는 방식을 포함한다. 이때 벽체2차 콘크리트가 어느 정도 양생(굳어야)되는 시점에 받침보(앵글, 철골보 등)를 설치하여야 한다.Also, angles are installed on the wall section. Various shapes of angles can be used. The types of angles that can be used include L-shaped (equilateral, scalene), T-shaped, and I-shaped. For example, angles are installed on the upper part of the wall in the exterior wall section. The methods for attaching and fixing the angle to the upper part of the wall include placing the angle against the wall and inserting (driving) an anchor bolt into the wall from the angle side, placing and welding it to an embed plate installed on the wall, pouring concrete after installing a built-in anchor in advance inside the wall, placing the angle and fixing it to the built-in anchor with a bolt, and hanging the angle on the upper angle (an angle attached to a column or beam inside the wall). At this time, the supporting beam (angle, steel beam, etc.) must be installed when the secondary concrete of the wall has cured (hardened) to a certain extent.

11) 데크 플레이트(피난층 천정 형틀)를 받침보에 설치한다. 데크 플레이트의 하부 철판 또는 하부근을 앵글 또는 H형 철골보에 용접으로 고정한다. 데크 플레이트의 철근(상부 하부근)을 벽체 철근에 고정(용접 등)한다.11) Install the deck plate (shelter ceiling formwork) on the supporting beam. Weld the lower steel plate or lower reinforcement of the deck plate to the angle or H-shaped steel frame. Secure (weld, etc.) the reinforcing bars (upper and lower reinforcement bars) of the deck plate to the wall reinforcing bars.

12) 데크 플레이트에 슬래브 철근을 설치한다.12) Install slab rebar on the deck plate.

13) 피난층 천정(슬래브) 콘크리트를 타설하여 피난층 골조를 완성한다.13) Complete the shelter frame by pouring concrete on the shelter ceiling (slab).

14) 피난층 천정의 데크 플레이트 하부 철판에는 나중에 단열재를 설치하도록 한다. 단열재는 플라스틱 못과 같은 것으로 하부 철판에 총(건)으로 쏴서 고정한다.14) Insulation will be installed later on the lower steel plate of the deck plate of the refuge floor ceiling. The insulation will be fixed to the lower steel plate by shooting plastic nails or similar objects with a gun.

상기 과정을 정리하면 아래와 같다.The above process can be summarized as follows.

아파트 피난구역(피트)층의 골조공사 방법으로서,As a method of skeletal construction of an apartment refuge area (pit) floor,

1) 벽체 철근을 설치하는 단계;1) Step of installing wall reinforcement;

2) 벽체 형틀을 설치하는 단계;2) Step of installing the wall formwork;

3) 벽체 콘크리트를 타설하는 단계;3) Step of pouring wall concrete;

4) 상기 벽체 상부에 철골보를 설치하는 단계;4) Step of installing a steel beam on the upper part of the above wall;

5) 상기 철골보에 데크 플레이트를 설치하는 단계;5) Step of installing a deck plate on the above steel beam;

6) 상기 데크 플레이트 상부에 슬래브 철근을 설치하는 단계;6) Step of installing slab reinforcement on the upper part of the deck plate;

7) 상기 데크 플레이트 상부에 슬래브 콘크리트를 타설하는 단계한다.7) Step of pouring slab concrete on top of the above deck plate.

상기 벽체상부에 데크 플레이트 설치를 위한 앵글 철골을 포함하는 철골부재를 설치한다.A steel member including an angle steel frame for installing a deck plate is installed on the upper part of the above wall.

상기 철골보의 길이에 따라 철골보의 중앙부분의 하부에 철골보 받침용 철골기둥을 설치한다.Depending on the length of the above steel beam, a steel column for supporting the steel beam is installed at the lower part of the central part of the steel beam.

상기 벽체상부에 철골보 설치를 위한 엠베드 플레이트, 거셋 플레이트를 포함하는 철골부재를 설치한다.Install steel members including an embed plate and a gusset plate for installing a steel beam on the upper part of the above wall.

상기 벽체 콘크리트는 2회에 나누어 타설한다.The above wall concrete is poured in two stages.

상기 철골보의 하부에 철골기둥을 설치한다.A steel column is installed at the bottom of the above steel beam.

상기 데크 플레이트 하부에 단열재를 부착하는 방식으로 시공한다.It is constructed by attaching insulation to the bottom of the above deck plate.

상기 장치를 정리하면 아래와 같다.The above devices are organized as follows.

아파트 피난구역(피트)층의 골조공사 장치으로서,As a skeletal construction device for the apartment refuge area (pit) floor,

벽체 골조;wall frame;

상기 벽체상부에 설치되는 철골보;Steel beam installed on the upper part of the above wall;

상기 철골보를 설치하기 위한 철골 연결부재;Steel connecting member for installing the above steel beam;

상기 철골보에 설치되는 데크 플레이트;A deck plate installed on the above steel beam;

상기 데크 플레이트에 설치되는 슬래브 철근;Slab reinforcement installed on the above deck plate;

상기 데크 플레이트에 타설되는 슬래브 콘크리트이다.It is a slab concrete poured on the above deck plate.

상기 벽체에 데크 플레이트 설치를 위한 앵글Angle for installing deck plate on the above wall

상기 철골보를 설치하기 위한 철골 연결부재로서의 엠베드 플레이트, 거셋 플레이트Embed plate and gusset plate as steel connecting members for installing the above steel beam

상기 철골보를 지지하며, 철골보 하부에 설치되는 철골기둥A steel column that supports the above steel beam and is installed under the steel beam.

이상으로 본 발명의 실시예를 나타내었다.The embodiments of the present invention have been described above.

앵글과 철골기둥, 철골보는 피난층의 설계에 따라 선택적으로 사용될 수 있다.Angles, steel columns and steel beams may be used selectively depending on the design of the shelter.

이하 실시예 1을 도면을 작성하여 설명한다.The following Example 1 is described using drawings.

도 1은 49층 아파트 단면도이며, 중간의 26층에 피난층이 있다. 피난층의 층고는 5.5m이다. 세대 기준층은 2.85m 높이다.Figure 1 is a cross-section of a 49-story apartment building, with an evacuation floor located on the 26th floor in the middle. The evacuation floor has a height of 5.5 meters. The standard floor of each unit is 2.85 meters high.

도 2는 26층 피난층의 평면도이다. 중앙에 코어(엘리베이터, 계단실, 설비배관 통로 등)가 있고 X자형으로 4개 세대(아파트)가 배치되어 있다. 검은 선은 벽체를 나타낸다. Figure 2 is a floor plan of the 26th floor evacuation floor. The core (elevator, stairwell, utility pipe passage, etc.) is located at the center, and four units (apartments) are arranged in an X shape. The black lines represent the walls.

도 3은 도 2의 검은 선인 벽체에 본 발명에 따른 데크 플레이트 받침용 철골보(붉은선)를 설계한 철골보 배치 평면도이다.Fig. 3 is a plan view of the arrangement of steel beams designed for supporting a deck plate according to the present invention (red line) on the wall, which is the black line in Fig. 2.

도 4는 11시 방향의 피난층의 철골보 설치 확대도이다. 11시 방향 최상부에 넓은 실(제연 휀룸, 화재시 연기 배출용 모터 설치)에는 철골보가 2개가 설치된다. 철골보의 간격은 2440mm(2.4m)이고 철골보의 길이는 실의 길이인 5295mm 정도이다. 이 간격은 데크 플레이트의 길이이기도 하다. 철골보는 벽체를 관통하지 않고 벽체에서 끊어질 수 있다. 중앙부분의 철골보의 길이는 5560mm인데, 더 길이가 길어질 경우에는 철골보의 규격(높이)이 커져야 하므로, 중간에 철골기둥을 설치하면, 철골보의 규격을 줄일 수 있게 된다. 철골기둥의 설치여부는 벽체간의 거리와 실의 크기에 따라 결정될 수 있다. 이때 철골보는 벽체에 매립된 엠베드 플레이트에 설치될 수 있다. 철골보를 직접 벽체 콘크리트에 연결할 수 없으므로, 벽체와 철골보는 연결하는 연결부재를 매립한다. 연결부재의 종류와 연결방식은 다양한다. 그 중 엠베드 플레이트가 일반적으로 사용되고 있다.Figure 4 is an enlarged view of the steel beam installation on the evacuation floor at the 11 o'clock direction. Two steel beams are installed in the wide room at the top (where the smoke exhaust fan and smoke exhaust motor are installed in case of fire) at the 11 o'clock direction. The spacing between the steel beams is 2440 mm (2.4 m), and the length of the steel beams is approximately 5295 mm, the length of the room. This spacing is also the length of the deck plate. The steel beams do not penetrate the wall but can be broken at the wall. The length of the steel beam in the center is 5560 mm. If the length were longer, the beam size (height) would have to be increased. Therefore, installing a steel column in the middle would allow the steel beam size to be reduced. The installation of steel columns can be determined by the distance between the walls and the size of the room. In this case, the steel beams can be installed on an embedded plate embedded in the wall. Since steel beams cannot be directly connected to the concrete wall, a connecting member is embedded to connect the wall and the steel beam. There are various types and methods of connecting members, but the most commonly used is the embed plate.

도 5는 벽체의 두께와 데크 플레이트 설치 평면도를 나타낸 것이다. 코어부분의 벽체는 구조핵심이므로 600mm두께이다. 외벽은 300~400mm이고, 내부는 250mm(25cm)이다. 데크 플레이트의 폭은 약 600mm이다. 길이는 벽체와 철골보사이에 설치되며 2440mm 정도이다.Figure 5 illustrates the wall thickness and deck plate installation plan. The core wall, as the structural core, is 600 mm thick. The exterior wall is 300-400 mm thick, and the interior is 250 mm (25 cm). The deck plate is approximately 600 mm wide. Its length, installed between the wall and the steel beam, is approximately 2,440 mm.

도 6은 본 발명에 따른 철골보를 이용한 데크 플레이트 공사방법을 한장으로 요약한 것이다. 도 8 이하에서 각 단계를 설명한다.Figure 6 is a one-page summary of a deck plate construction method using a steel beam according to the present invention. Each step is described below in Figure 8.

도 7은 본 발명에 따른 철골보를 이용한 데크 플레이트 공사방법의 공정표이다. 콘크리트는 3회로 나누어 타설한다.Figure 7 is a process chart of a deck plate construction method using a steel beam according to the present invention. Concrete is poured in three stages.

피난층 벽체1차 타설 단계의 공사순서는 종래의 공법대로 시공한다.The construction sequence for the first stage of the shelter wall pouring is constructed according to the conventional construction method.

25층의 세대 콘크리트를 타설한 후, 외벽의 갱폼(형틀)을 인상하고, 갱폼의 창문부분의 개구부를 수정(피난층에는 창문이 적음)하고, 벽체철근을 타워크레인으로 26층 바닥으로 양중하고, 25층의 알폼(내부 형틀)을 해체한다.After pouring the concrete for the 25th floor, the gang form (form) of the exterior wall is raised, the openings of the window portion of the gang form are modified (there are fewer windows on the evacuation floor), the wall reinforcement is lifted to the 26th floor with a tower crane, and the 25th floor's alform (inner form) is dismantled.

벽체1차 부분의 벽체철근을 설치하면서, 전기설배 배관도 설치한다. 철근이 설치되면, 벽체1차 형틀(아래층의 알폼을 사용)을 설치한다. 그리고 벽체1차 콘크리트를 타설한다. 타설높이는 아래층의 알폼을 사용하므로 약 2.85m이다. 상기 과정은 종래 기술에 속한다.While installing the wall reinforcement for the first section of the wall, electrical piping is also installed. Once the reinforcement is installed, the first wall formwork (using the lower layer's Alform) is installed. Then, the first wall concrete is poured. The pouring height is approximately 2.85 m, using the lower layer's Alform. The above process is conventional.

다음으로 벽체 2차 부분에서는 외부 갱폼을 벽체1차 부분으로 인상하고, 높이가 5.5m이므로 내부의 작업자를 위하여 벽체에 인접하여 비계를 설치한다. 시스템 비계는 천정 공사를 위한 것이므로 상기 벽체에 인접한 비계와는 다르며, 본 발명에서는 시스템 비계는 사용하지 않고 삭제하였다. 비계를 설치하지 않는 경우에는, 렌탈장비(작업자가 내부에 타고, 위 아래로 오르 내리는 장비)를 이용하여 철근과 내부 형틀을 설치할 수 있다. 벽체 2차 철근이 설치되면, 본 발명에 따라 엠베드 플레이트 또는 거셋 플레이트를 설치한다. 철근에 엠베드 플레이트 또는 거셋 플레이트를 설치한다. 또는 엠베드 플레이트 철판 부분에 볼트를 붙착하고, 벽체 형틀에 구멍을 내고 너트로 고정하여 엠베드 플레이트를 설치할 수 있다. 거셋 플레이트는 벽체로 부터 튀어나오 철판 좌우에 형틀을 설치하거나, 형틀에 세로홈을 파서 철판이 튀어나오면서 형틀에 거치(설치)될 수 있도록 할 수 있다. 형틀 콘크리트 타설 후 너트 거셋 플레이트는 벽체로 부터 튀어나온 철판이고 다수의 볼트 구멍이 있어 철골보 단부의 볼트구멍에 철판(덧판, 서플라이스)를 대고 연결 설치하는 연결부재이다.Next, in the secondary wall section, the external gang form is raised to the primary wall section, and since the height is 5.5 m, a scaffolding is installed adjacent to the wall for the workers inside. The system scaffolding is for ceiling construction and is therefore different from the scaffolding adjacent to the wall. In the present invention, the system scaffolding is not used and is deleted. If the scaffolding is not installed, the rebar and internal formwork can be installed using rental equipment (equipment that workers ride inside and go up and down). Once the secondary wall rebar is installed, the embed plate or gusset plate is installed according to the present invention. The embed plate or gusset plate is installed on the rebar. Alternatively, the embed plate can be installed by attaching bolts to the steel plate section of the embed plate, making holes in the wall formwork, and securing them with nuts. The gusset plate can be installed by protruding from the wall and installing the formwork on the left and right of the steel plate, or by making vertical grooves in the formwork so that the steel plate can protrude and be placed (installed) on the formwork. After pouring the formwork concrete, the nut gusset plate is a steel plate protruding from the wall and has a number of bolt holes. It is a connecting member that is installed by placing the steel plate (plate, supply) against the bolt holes at the end of the steel beam.

벽체 2차 형틀을 설치하며, 벽체 1차의 알폼을 재사용하는 방식, 또는 재래식의 유로폼을 사용한다. 벽체 2차 콘크리트를 타설하여 벽체를 완성한다. 벽체는 슬래브 하단높이까지 타설한다.Install the secondary wall formwork, either by reusing the primary wall formwork or by using conventional Euroform. The secondary wall concrete is poured to complete the wall. The wall is poured to the bottom of the slab.

슬래브 골조 단계에서는 본 발명에 따라 벽체를 따라 벽체 상부에 앵, 철골보(H형강)를 설치한다. 이때 철골보는 무게가 있으므로, 벽체 콘크리트가 어느 정도 양생(굳어서)이 되어 엠베드 플레이트가 고정되어야 한다. 양생시간은 콘크리트의 강도(24MPa, 30MPa 등)에 따라 다르며, 강도가 높으면 빨리 굳는다. 따라서 공기가 지연되어 부족할 경우에는, 벽체2차 콘크리트의 강도를 높게 레미콘을 제작하여 타설하는 것이 유리하다. 본 발명에 따른 앵글은 앵글과 벽체를 연결하는 볼트나 앙카, 엠베드 플레이트, 앵글 부재를 이용하여 설치한다. 철골보는 엠베드 플레이트 또는 벽체로 부터 튀어나온 거셋 플레이트에 연결 설치한다. 철골보 상부에는 슬래브 콘크리트와의 밀착을 위한 스터드 볼트가 설치될 수 있다.In the slab frame stage, according to the present invention, angles and steel beams (H-beams) are installed along the wall and on the upper part of the wall. At this time, since the steel beam is heavy, the wall concrete must be cured (hardened) to a certain extent so that the embed plate can be fixed. The curing time varies depending on the strength of the concrete (24 MPa, 30 MPa, etc.), and if the strength is high, it hardens quickly. Therefore, if the air is delayed and insufficient, it is advantageous to manufacture ready-mixed concrete with high strength for the secondary wall concrete and pour it. The angle according to the present invention is installed using bolts, anchors, embed plates, or angle members that connect the angle to the wall. The steel beam is installed by connecting it to the embed plate or the gusset plate protruding from the wall. Stud bolts may be installed on the upper part of the steel beam for close contact with the slab concrete.

만약 철골보의 길이가 길 경우에는 철골보의 높이나 폭이 커지게 되는데, 이 경우에는 철골보 중간지점에 본 발명에 따른 철골기둥을 하나 설치하면, 철골보의 기둥간의 길이가 반으로 줄어드므로, 작은 철골보를 사용하게 된다. 그러나 철골기둥은 나중에 실(방) 사용시 방해가 되는 경우, 해체해야 할 수도 있다.If the length of the steel beam is long, the height or width of the steel beam will increase. In this case, if a steel column according to the present invention is installed at the midpoint of the steel beam, the length between the steel beam columns will be reduced by half, allowing the use of a smaller steel beam. However, the steel column may need to be dismantled if it interferes with the use of the room later.

다음으로 본 발명에 따라 받침보 상부에 데크 플레이트를 설치한다. 데크 플레이트의 합부 철판은 철골보나 앵글에 올려지고, 용접으로 고정된다. 데크 플레이트에 부닥된 하부 하부철근은 벽체 철근등과 용접으로 추가로 고정될 수 있다.Next, according to the present invention, a deck plate is installed on top of the support beam. The deck plate's joint steel plate is placed on a steel beam or angle and secured by welding. The lower lower reinforcing bars attached to the deck plate can be additionally secured to wall reinforcing bars, etc., by welding.

이상과 같이 5일차에 벽체1차 타설, 11일차에 벽체 1차 타설, 17일차에 슬래브 콘크리트 타설로 완성된다. 상기 기간은 작업자수 및 공구분할에 따라 몇 일간 더 단축될 수 있다.As described above, the first wall was poured on the fifth day, the second wall was poured on the eleventh day, and the slab concrete was poured on the seventeenth day, completing the project. The above period can be shortened by several days depending on the number of workers and the division of labor.

이하 3차원 도면을 통해 본 발명에 따른 공사방법을 설명한다.The construction method according to the present invention is explained below through three-dimensional drawings.

도 8 내지 도 9는 벽체1차 콘크리트를 타설하여 벽체를 1차로 높인 것이다. 1차 높이는 아래층의 알폼을 사용하므로 2850mm정도로 한다.Figures 8 and 9 show the wall raised to the first level by pouring the first concrete wall. The first height is approximately 2850 mm because the lower layer's foam is used.

도 10은 벽체 2차의 일부 콘크리트를 타설한 이미지를 나타낸 것이다. 1차 벽체 상부에 2차 벽체가 올라가 있다, 2차 높이는 천정면의 높이에서 1차 높이를 감한 것으로 2390mm이다.Figure 10 shows an image of a portion of the concrete poured on the second wall. The second wall is placed on top of the first wall. The second wall height is 2390 mm, which is the height of the ceiling surface minus the first wall height.

도 11은 벽체 2차 상부에 엠베드 플레이트가 설치되는 것이며, 벽체내에 매립되고 철판은 벽체면에 노출된다.Fig. 11 shows an embed plate installed on the secondary upper part of a wall, embedded in the wall, and the steel plate exposed on the wall surface.

도 12 내지 도 13은 엠베드 플레이트 설치 후 벽체 2차 콘크리트가 타설된 것이다. 그리고 다음날부터 벽체 형틀을 해체한다. 피난층에는 사람이 거주하지 않고, 설비장비사 설치되므로 창문의 크기가 작고 갯수가 많지 않는 것을 나타내고 있다. 종래의 시스템 비계 설치시 해체 및 반출이 어려운 구조임을 나타내고 있다.Figures 12 and 13 show the secondary concrete pouring of the wall after the installation of the embed plate. The wall formwork is dismantled the following day. The evacuation floor is uninhabited and is installed by equipment manufacturers, so the windows are small and limited in number. This demonstrates the difficulty of dismantling and removing the scaffolding system used in conventional systems.

도 14는 벽체로 부터 돌출되는 거셋 플레이트를 나타낸 것이다. 거셋 플레이트의 일부는 벽체 내부에 매립되어 설치되는 방식, 엠베드 플레이트의 철판에 부착되는 방식이 있다.Figure 14 illustrates a gusset plate protruding from a wall. Some of the gusset plates are installed by being embedded within the wall, while others are attached to the steel plate of the embed plate.

도 15는 엠베드 플레이트의 노출된 철판 하부부분에 철골보 거치용 앵글이나 철판을 추가로 용접으로 설치한다. 1층의 철골보를 타워크레인으로 26층으로 양중한다.Figure 15 shows the installation of additional angles or steel plates for supporting steel beams by welding to the exposed lower part of the embed plate. The steel beams on the first floor are lifted to the 26th floor by a tower crane.

도 16은 철골보를 중간의 벽체에 설치하는 것이다. 이때 벽체에 매립된 엠베드 플레이트에 철골보를 설치한다.Figure 16 shows the installation of a steel beam on a middle wall. At this time, the steel beam is installed on an embed plate embedded in the wall.

도 17은 철골보 1개가 설치된 것을 나타낸 것이다. 철골보의 양측 단부(끝)는 각각 엠베드 플레이트 또는 튀어나온 거셋 플레이트에 설치된다. 엠베드 플레이트인 경우, 철골보는 철판에 용접으로 설치되고, 거셋 플레이트인 경우에는 볼트 또는 볼트와 용접으로 설치된다.Figure 17 illustrates the installation of a single steel beam. The ends of the steel beam are installed on either an embed plate or a protruding gusset plate, respectively. In the case of an embed plate, the steel beam is installed by welding to the steel plate, and in the case of a gusset plate, it is installed by bolting or welding with bolts.

도 18은 두번째 철골보가 설치된 것을 나타낸다.Figure 18 shows the second steel beam installed.

도 19는 세번째 철골보가 설치된 것을 나타낸다. 이와 같은 방식으로 철골보를 계속 설치한다.Figure 19 shows the third steel beam installed. Steel beams are installed continuously in this manner.

도 20은 앵글을 양중하는것을 나타낸 것이다. 앵글은 렌탈장비, 타워크레인, 비계를 이용하여 벽체 상부로 이동시킨다.Figure 20 illustrates the lifting of an angle. The angle is moved to the upper part of the wall using rental equipment, a tower crane, and a scaffold.

도 21 내지 도 23은 외부 벽체면을 따라 앵글을 벽체에 볼트 등으로 설치한다. 볼트 이외에도 앙카, 엠베드 플레이트 등 다양한 연결부재와 연결될 수 있다. 앵글의 종류(ㄱ자, ㄷ자 등, 등변/부등변)와 규격 (100mm*100mm, 1250mm*150mm 등)이 사용될 수 있다.Figures 21 to 23 show angles installed along the exterior wall surface with bolts, etc., to the wall. In addition to bolts, various connecting members such as anchors and embed plates can be connected. Angle types (L-shaped, T-shaped, etc., equilateral/unequal) and sizes (100mm*100mm, 1250mm*150mm, etc.) can be used.

도 24는 다른 방으로 이동하여 앵글을 추가로 설치하는 것을 나타낸 것이다.Figure 24 shows moving to another room to install additional angles.

도 25는 철골보와 앵글이 설치된 후의 단면의 이미지이다. 오른쪽 외부 벽체에는 앵글이 설치되고 벽체간의 중간부분에는 철골보가 설치된다.Figure 25 is an image of a cross-section after the steel beam and angles have been installed. Angles are installed on the right outer wall, and steel beams are installed in the middle section between the walls.

도 26은 앵글과 철골보 위에 데크 플레이트를 설치한 것이다. 일반적인 데크 플레리트의 폭은 600mm이다. 데크 플레이트 하부 철판은 벽체 내부로 들어가지 않고 앵글위에 설치된다. 데크에 부착된 상부 하부근은 벽체 내부로 들어가 철근에 용접등으로 추가로 연결될 수 있다. 철골보위에 데크 하부 철판이 걸쳐지고 용접으로 고정된다.Figure 26 shows a deck plate installed over angles and steel beams. The typical width of a deck plate is 600 mm. The lower steel plate of the deck plate is installed over the angles, not inside the wall. The upper lower steel bar attached to the deck extends into the wall and can be additionally connected to the steel bar by welding, etc. The lower steel plate of the deck is placed over the steel beam and secured by welding.

도 27은 다음으로 이동하여 철골보와 철골보사이에 데크를 설치한 것이다.Figure 27 shows the next step of installing a deck between steel beams.

도 28은 데크 플레이트가 설치된 단면이다. 데크는 앵글 또는 철골보 위에 설치된다.Figure 28 is a cross-section with the deck plate installed. The deck is installed on angle or steel beams.

이후 데크 플레이트에 철근, 전기설비 배관을 설치한 후 슬래브 콘크리트를 타설하여 피난층 골조를 완성한다.Afterwards, reinforcing bars and electrical equipment pipes are installed on the deck plate, and then slab concrete is poured to complete the shelter frame.

도 29 내지 도 31은 실시예2이며, 다른 아파트 현장에서 철골보가 설치되는 실시예를 타나낸다. 철골보, 철골기둥은 각 아파트 구조에 따라 다양하게 가로(도 30), 세로 형태(도 31)나 규격으로 설치될 수 있다.Figures 29 to 31 illustrate Example 2, which illustrates an example of installing steel beams at another apartment construction site. Steel beams and steel columns can be installed in various horizontal (Figure 30) and vertical (Figure 31) configurations or standards, depending on the structure of each apartment.

앞에서 설명되고, 도면에 도시된 본 발명의 실시예는, 본 발명의 기술적 사상을 한정하는 것으로 해석되어서는 안 된다. 본 발명의 보호범위는 청구범위에 기재된 사항에 의하여만 제한되고, 본 발명의 기술분야에서 통상의 지식을 가진 자는 본 발명의 기술적 사상을 다양한 형태로 개량 변경하는 것이 가능하다. 따라서 이러한 개량 및 변경은 통상의 지식을 가진 자에게 자명한 것인 한 본 발명의 보호범위에 속하게 될 것이다.The embodiments of the present invention described above and illustrated in the drawings should not be construed as limiting the technical concept of the present invention. The scope of protection of the present invention is limited only by the matters set forth in the claims, and those skilled in the art will be able to make various improvements and modifications to the technical concept of the present invention. Accordingly, such improvements and modifications, as long as they are obvious to those skilled in the art, will fall within the scope of protection of the present invention.

본 발명에 따른 철골구조물과 데크 플레이트를 이용한 층고가 높은 피난층의 공기단축 방법은 설계 및 공사방법을 수립하여 시행할 수 있으므로, 아파트 건설현장에 현장에 바로 적용이 가능하다.The method for shortening the air time of a high-rise evacuation floor using a steel structure and a deck plate according to the present invention can be implemented by establishing a design and construction method, and thus can be applied directly to an apartment construction site.

..

Claims (9)

아파트 피난구역(피트)층의 골조공사 방법으로서,
1) 벽체 철근을 설치하는 단계;
2) 벽체 형틀을 설치하는 단계;
3) 벽체 콘크리트를 타설하는 단계;
4) 상기 벽체 상부에 철골보를 설치하는 단계;
5) 상기 철골보에 데크 플레이트를 설치하는 단계;
6) 상기 데크 플레이트 상부에 슬래브 철근을 설치하는 단계;
7) 상기 데크 플레이트 상부에 슬래브 콘크리트를 타설하는 단계
를 포함하여 시공되는 것을 특징으로 하는 아파트 피난구역(피트)층의 골조공사 방법
As a method of skeletal construction of an apartment refuge area (pit) floor,
1) Step of installing wall reinforcement;
2) Step of installing the wall formwork;
3) Step of pouring wall concrete;
4) Step of installing a steel beam on the upper part of the above wall;
5) Step of installing a deck plate on the above steel beam;
6) Step of installing slab reinforcement on the upper part of the deck plate;
7) Step of pouring slab concrete on top of the above deck plate
A method for constructing a skeleton of an apartment shelter (pit) floor, characterized by including
청구항 1에 있어서,
상기 벽체상부에 데크 플레이트 설치를 위한 앵글 철골을 포함하는 철골부재를 설치하는 것을 더 포함하는 것을 특징으로 아파트 피난구역(피트)층의 골조공사 방법
In claim 1,
A method for constructing a skeleton of an apartment refuge area (pit) floor, characterized in that it further includes installing a steel member including an angle steel frame for installing a deck plate on the upper part of the wall.
청구항 1에 있어서,
상기 벽체상부에 철골보 설치를 위한 엠베드 플레이트 또는 거셋 플레이트를 포함하는 철골부재를 설치하는 것을 더 포함하는 것을 특징으로 아파트 피난구역(피트)층의 골조공사 방법
In claim 1,
A method for constructing a skeleton of an apartment refuge area (pit) floor, characterized in that it further includes installing a steel member including an embed plate or a gusset plate for installing a steel beam on the upper part of the wall.
청구항 1에 있어서,
상기 벽체 콘크리트는 2회에 나누어 타설하는 것을 포함하는 것을 특징으로 아파트 피난구역(피트)층의 골조공사 방법
In claim 1,
The above wall concrete is characterized by being poured in two stages, and is a method for constructing a skeleton of an apartment refuge area (pit) floor.
청구항 1에 있어서,
상기 철골보의 하부에 철골기둥을 설치하는 것을 포함하는 것을 특징으로 아파트 피난구역(피트)층의 골조공사 방법
In claim 1,
A method for constructing a skeleton of an apartment refuge area (pit) floor, characterized by including installing a steel column at the bottom of the above steel beam.
아파트 피난구역(피트)층의 골조공사 장치으로서,
벽체 골조;
상기 벽체상부에 설치되는 철골보;
상기 철골보를 설치하기 위한 철골 연결부재;
상기 철골보에 설치되는 데크 플레이트;
상기 데크 플레이트에 설치되는 슬래브 철근; 및
상기 데크 플레이트에 타설되는 슬래브 콘크리트
로 포함하여 구성되는 것을 특징으로 하는 아파트 피난구역(피트)층의 골조공사 장치
As a skeletal construction device for the apartment refuge area (pit) floor,
wall frame;
Steel beam installed on the upper part of the above wall;
Steel connecting member for installing the above steel beam;
A deck plate installed on the above steel beam;
Slab reinforcement installed on the above deck plate; and
Slab concrete poured on the above deck plate
The skeletal construction device of the apartment refuge area (pit) floor characterized by including
청구항 7에 있어서,
상기 벽체에 데크 플레이트 설치를 위한 앵글 철골을 포함하는 철골부재가 더 포함되어 설치되는 것을 특징으로 아파트 피난구역(피트)층의 골조공사 장치
In claim 7,
A skeletal construction device for an apartment refuge area (pit) floor characterized in that a steel member including an angle steel frame for installing a deck plate on the above wall is further installed.
청구항 7에 있어서,
상기 철골보를 설치하기 위한 철골 연결부재는 엠베드 플레이트 또는 거셋 플레이트를 포함하는 것을 특징으로 아파트 피난구역(피트)층의 골조공사 장치
In claim 7,
The steel connecting member for installing the above steel beam is characterized by including an embed plate or a gusset plate, and is a skeletal construction device for the apartment refuge area (pit) floor.
청구항 7에 있어서,
상기 철골보를 지지하며, 철골보 하부에 설치되는 철골기둥을 포함하는 것을 특징으로 아파트 피난구역(피트)층의 골조공사 장치
In claim 7,
A skeletal construction device for an apartment refuge area (pit) floor, characterized by supporting the above steel beam and including a steel column installed under the steel beam.
KR1020240020053A 2024-02-10 2024-02-10 A method of structural construction using steel girder and deck plate at pit floor in apartment structural construction Pending KR20250124265A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020240020053A KR20250124265A (en) 2024-02-10 2024-02-10 A method of structural construction using steel girder and deck plate at pit floor in apartment structural construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020240020053A KR20250124265A (en) 2024-02-10 2024-02-10 A method of structural construction using steel girder and deck plate at pit floor in apartment structural construction

Publications (1)

Publication Number Publication Date
KR20250124265A true KR20250124265A (en) 2025-08-19

Family

ID=96915148

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020240020053A Pending KR20250124265A (en) 2024-02-10 2024-02-10 A method of structural construction using steel girder and deck plate at pit floor in apartment structural construction

Country Status (1)

Country Link
KR (1) KR20250124265A (en)

Similar Documents

Publication Publication Date Title
AU2020200977B2 (en) Methods, systems and components for multi-storey building construction
CN110512719B (en) Construction method of large-span interval corridor high-altitude formwork steel platform for high-rise residence
CN112942574A (en) Prefabricated reinforced concrete full-fabricated roof cornice and construction method thereof
CN109653517B (en) Multidirectional unloading system and construction method for assembling steel corridor by using same
KR20250036109A (en) Structural Systems and Methods for Floor Structural Work in Elevator Machine Room of Apartment Housing
KR20250124265A (en) A method of structural construction using steel girder and deck plate at pit floor in apartment structural construction
CN115182482B (en) Construction method of prefabricated hollow wall body without outer frame matching
CN112359860B (en) Construction method for non-support type open caisson capping
JP7369090B2 (en) shaft wall unit
AU2013101346A4 (en) Methods, systems and components for multi-storey building construction
RU2338843C1 (en) Method of multistorey building carcassing
CN112681705A (en) Steel wire rope net platform for construction and installation method thereof
KR20250048506A (en) Elevator machine room steel structure and construction method
KR20250048507A (en) Elevator machine room steel structure and construction method
KR20210141194A (en) Construction Method and Device of Wall and Floor Structure in Elevator's Machine Room in Apartment Building and Office Using Hanging Structural Method by Steel and Deck Plate in Top-down Structure
AU2013101347B4 (en) Methods, systems and components for multi-storey building construction
AU2013101345B4 (en) Methods, systems and components for multi-storey building construction
KR20250044543A (en) Penthouse structure construction method
KR20250035530A (en) Construction Method and Device of Floor Structure in Elevator's Machine Room in Apartment Building Using Hanging Structural Method
RU2308587C1 (en) Method for timber floor structure reconstruction
KR20250061106A (en) Construction Method and Apparatus for Elevator Mechanical Room Frames on the Roof Floor, such as Offices and Apartments, Using Steel Structures
KR20250061777A (en) Construction method of the structure of the elevator machine room on the rooftop of an apartment building by recycling the gangform of typical floor
KR20250081648A (en) A method of structural construction using steel and deck plate at pit floor in apartment structural construction
KR20250058092A (en) Construction Method and Apparatus for Elevator Mechanical Room Frames on the Roof Floor, such as Offices and Apartments, Using Steel Structures
KR20250139710A (en) A method of structural construction using steel girder and deck plate at pit floor in apartment structural construction

Legal Events

Date Code Title Description
PA0109 Patent application

St.27 status event code: A-0-1-A10-A12-nap-PA0109

PG1501 Laying open of application

St.27 status event code: A-1-1-Q10-Q12-nap-PG1501

Q12 Application published

Free format text: ST27 STATUS EVENT CODE: A-1-1-Q10-Q12-NAP-PG1501 (AS PROVIDED BY THE NATIONAL OFFICE)