KR20250061777A - Construction method of the structure of the elevator machine room on the rooftop of an apartment building by recycling the gangform of typical floor - Google Patents
Construction method of the structure of the elevator machine room on the rooftop of an apartment building by recycling the gangform of typical floor Download PDFInfo
- Publication number
- KR20250061777A KR20250061777A KR1020230146136A KR20230146136A KR20250061777A KR 20250061777 A KR20250061777 A KR 20250061777A KR 1020230146136 A KR1020230146136 A KR 1020230146136A KR 20230146136 A KR20230146136 A KR 20230146136A KR 20250061777 A KR20250061777 A KR 20250061777A
- Authority
- KR
- South Korea
- Prior art keywords
- floor
- steel
- rooftop
- machine room
- wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/34—Extraordinary structures, e.g. with suspended or cantilever parts supported by masts or tower-like structures enclosing elevators or stairs; Features relating to the elastic stability
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B5/00—Floors; Floor construction with regard to insulation; Connections specially adapted therefor
- E04B5/16—Load-carrying floor structures wholly or partly cast or similarly formed in situ
- E04B5/32—Floor structures wholly cast in situ with or without form units or reinforcements
- E04B5/36—Floor structures wholly cast in situ with or without form units or reinforcements with form units as part of the floor
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G11/00—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
- E04G11/36—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G13/00—Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
- E04G13/06—Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for stairs, steps, cornices, balconies, or other parts corbelled out of the wall
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
본 발명은 엘리베이터 기계실 바닥 골조공사를 안전하고 신속하게 시공하는 방법에 관한 것으로, 옥탑 1층 기계실 바닥의 승강로 부분에 설치되는 큰 철골보(권상기 및 가이드 레일 양중 지지)를 설치하기 위하여, 철골기둥을 옥탑 1층 승강로 벽체의 내부, 벽체 인접, 벽체로 부터 일정거리 이격, 옥상바닥, 승강로 내부에 설치하는 방식 중의 하나, 상기 철골기둥에 철골보를 설치하는 단계, 상기 철골기둥 또는 철골보에 큰 철골보를 설치하는 단계, 기계실 바닥 데크 플레이트 설치 및 기계실 바닥 콘크리트를 타설하는 것에 관한 것이다.The present invention relates to a method for safely and quickly constructing an elevator machine room floor skeleton construction, and to a method for installing a large steel beam (supporting lifting of a traction machine and a guide rail) installed in a hoistway section of a first-floor machine room floor on a rooftop, including one of the following methods: installing a steel column inside a first-floor elevator hall wall on a rooftop, adjacent to the wall, spaced a certain distance from the wall, on a rooftop floor, or inside a hoistway; installing a steel beam on the steel column; installing a large steel beam on the steel column or the steel beam; installing a machine room floor deck plate, and pouring machine room floor concrete.
Description
본 발명은 엘리베이터 기계실 바닥 골조공사를 안전하고 신속하게 시공하는 방법에 관한 것으로, 옥탑 1층 기계실 바닥의 승강로 부분에 설치되는 큰 철골보(권상기 및 가이드 레일 양중 지지)를 설치하기 위하여, 철골기둥을 옥탑 1층 승강로 벽체의 내부, 벽체 인접, 벽체로 부터 일정거리 이격, 옥상바닥, 승강로 내부에 설치하는 방식 중의 하나, 상기 철골기둥에 철골보를 설치하는 단계, 상기 철골기둥 또는 철골보에 큰 철골보를 설치하는 단계, 기계실 바닥 데크 플레이트 설치 및 기계실 바닥 콘크리트를 타설하는 것에 관한 것이다.The present invention relates to a method for safely and quickly constructing an elevator machine room floor skeleton construction, and to a method for installing a large steel beam (supporting lifting of a traction machine and a guide rail) installed in a hoistway section of a first-floor machine room floor on a rooftop, including one of the following methods: installing a steel column inside a first-floor elevator hall wall on a rooftop, adjacent to the wall, spaced a certain distance from the wall, on a rooftop floor, or inside a hoistway; installing a steel beam on the steel column; installing a large steel beam on the steel column or the steel beam; installing a machine room floor deck plate, and pouring machine room floor concrete.
또한 외벽의 갱폼을 최상층 시공후 옥탑골조 공사에 재활용하는 것이다.Additionally, the gang form of the exterior wall is reused in the rooftop frame construction after the top floor is constructed.
엘리베이터 기계실 바닥을 조기에 설치하되, 권상기, 가이드레일 전체를 양중할 수 있는 구조가 필요하다.The elevator machine room floor should be installed early, but a structure capable of lifting the entire hoist and guide rail is required.
그러나 종래의 기술은 이에 대한 안전하게, 또는 신속하게 슬래브 공사를 진행하는 공사 방법이 마련되어 있지 않다. However, conventional technology does not provide a construction method that can safely or quickly perform slab construction.
또한 엘리베이터 설치 중 높은 하중을 갖는 권상기, 레일양중용 윈치, 가이드 레일 양중하중을 버틸 수 있는 구조가 명확하지 않은 실정이다.In addition, during elevator installation, it is unclear whether the structure can withstand the high load of the hoisting machine, rail lifting winch, and guide rail lifting load.
1) 기계실 바닥을 옥상 완료 후 수일내에 완료하는 방법1) How to complete the machine room floor within a few days after completing the rooftop
2) 권상기, 레일양중용 윈치, 전체 가이드 레일 양중하중(수 톤)을 버틸 수 있는 구조2) Structure capable of supporting the lifting load (several tons) of the entire guide rail, winch for lifting the hoisting machine
3) 엘리베이터 착수를 조속히 할 수 있도록 옥탑을 완성하여 전기팀에게 인도3) Complete the rooftop and hand it over to the electrical team so that the elevator can be started quickly.
[철골구조물 설치 어려움][Difficulty in installing steel structures]
다양한 벽체 두께와 배치 구조에 따라 승강로 벽체내부에 철골기둥과 철골보를 시공시, 하부 앙카 또는 베이스 플레이트 및 철골구조물 설치, 철근시공시 간섭이 발생하여 작업이 복잡하고 시간이 소요될 수 있다.When constructing steel columns and beams inside the elevator wall depending on the various wall thicknesses and layout structures, interference may occur during the installation of lower anchors or base plates and steel structures, and reinforcement bar construction, making the work complex and time-consuming.
[수톤의 하중을 견디는 기계실 바닥 구조][Machine room floor structure capable of supporting several tons of load]
권상기, 레일양중용 윈치, 전체 가이드 레일 양중시, 수 톤의 하중이 기계실 바닥에 걸린다.When lifting the hoist, the winch for lifting the rail, and the entire guide rail are lifted, a load of several tons is hung on the machine room floor.
그러나 종래의 슬래브만으로 불충분하고, 바닥 콘크리트 양생까지 기간이 소요된다.However, conventional slabs alone are insufficient, and it takes time for the floor concrete to cure.
[승강로 내부로의 높은 추락 위험][High risk of falling into the elevator shaft]
승강로 내부에 작업발판(RCS, ACS, PCS)을 사용하는 경우, 옥탑 1층 벽체 콘크리트 타설 후, 기계실 바닥 형성전에 작업발판을 해체해야 한다. When using a working platform (RCS, ACS, PCS) inside the elevator shaft, the working platform must be dismantled after pouring concrete for the first floor walls and before forming the machine room floor.
작업발판이 해체되면, 승강로는 옥탑부터 지하 바닥까지 허공의 사각형 굴똑 모양이 되며, 하부에 바닥구조가 없다.When the working platform is dismantled, the elevator shaft becomes a rectangular hollow space from the roof to the basement, with no floor structure below.
기계실 바닥을 시공하기 위해서는 하부에 동바리나 다른 방법을 사용해야 한다.To construct the machine room floor, you must use a slab or other method underneath.
이 경우, 승강로 내부로 기계실 바닥이 승강로 내부로 추락할 위험이 높다.In this case, there is a high risk that the machine room floor will fall into the elevator shaft.
[기계실 바닥 데크 플레이트 지지의 불안정][Instability of the machine room floor deck plate support]
기계실 바닥 데크 플레이트는 승강로 내부에 설치되어야 한다. 벽체 내부로 데크 플레이트가 들어가는 경우, 벽체 콘크리트가 절단되어 안전위험이 높으며, 감리가 승인하지 않는다.The machine room floor deck plate must be installed inside the hoistway. If the deck plate is inserted inside the wall, the wall concrete will be cut, which poses a high safety hazard and is not approved by the supervisor.
따라서 데크 플레이트를 승강로 내부에 정확히 일치되는 평면의 면적을 설치되어야 한다.Therefore, the deck plate must be installed with a flat surface area that exactly matches the inside of the elevator shaft.
그러나 데크 플레이트는 자력으로 설치가 되지 않으므로, 하부에 데크를 지지하는 구조가 있어야 한다.However, since the deck plate is not installed magnetically, there must be a structure to support the deck underneath.
그러나 종래에는 승강로 내부에 아무것도 없으므로 데크를 설치하기 곤란하며, 추락 위험이 있다.However, since there is nothing inside the elevator shaft, it is difficult to install a deck and there is a risk of falling.
[높은 하중 지지를 위한 기계실 바닥 콘크리트의 장기간 양생시간][Long-term curing time of machine room floor concrete for high load support]
기계실 바닥에는 권상기, 권상기 하부철골보, 공사용 와이어의 윈치, 승강로에 수직으로 설치되는 가이드 레일의 양중하중이 있다.On the machine room floor, there are lifting loads for the hoisting machine, the lower steel beam of the hoisting machine, the winch for the construction wire, and the guide rail installed vertically in the hoistway.
그러나 이러한 높은 하중을 기계실 바닥이 견디기 위해서는 바닥 콘크리트가 충분히 양생되어야 하며, 시간이 소요된다. 그에 따라 엘리베이터 설치 착수도 늦어지고, 엘리베이터 완성, 호이스트 철거, 호이스트 구간 마감공사가 직렬로 지연되어 전체 공사기간도 증가한다.However, in order for the machine room floor to withstand such a high load, the floor concrete must be sufficiently cured, which takes time. Accordingly, the elevator installation is also delayed, and the elevator completion, hoist removal, and hoist section finishing work are all serially delayed, which increases the overall construction period.
[기계실 천정 공사의 비효율성][Inefficiency of machine room ceiling construction]
기계실 천정 골조를 위한 천정 형틀 작업에서, 기계실 내부에 동바리를 설치하면 지붕 콘크리트가 양생될 때까지 동바리를 존치해야 하므로 엘리베이터 공사를 착수할 수 없고 전체 공사기간도 증가한다.In ceiling formwork work for the machine room ceiling skeleton, if a joist is installed inside the machine room, the joist must be maintained until the roof concrete is cured, so elevator construction cannot begin and the overall construction period also increases.
기계실 천정 형틀을 데크 플레이트로 시공시, 데크 플레이트를 지지하기 위한 받침 구조가 명확하지 않거나 양생기간 동안 존치해야 한다.When constructing the machine room ceiling formwork with deck plates, the support structure to support the deck plates must be clear or must be maintained during the curing period.
[코어벽체 내부에 철골기둥과 철골보를 설치시 비용증가][Increased cost when installing steel columns and beams inside the core wall]
옥탑 1층~기계실 벽체 내부에 철골기둥과 보를 설치하는 경우, 공사기간이 단축되지만, 철골공사 관련 공사비가 증가하는 단점이 있다. When installing steel columns and beams on the first floor of the rooftop or inside the walls of the machine room, the construction period is shortened, but there is a disadvantage in that the construction costs related to the steel structure construction increase.
[기계실 골조공사 기간의 증가][Increase in the machine room skeleton construction period]
기계실 바닥 및 벽체 천정의 골조공사 방법이 명확하지 않고, 콘크리트 양생기간이 필요한 방식으로 공사기간이 길고, 그에 따라 전체 공사기간이 증가한다.The method of skeletal construction of the machine room floor and wall ceiling is unclear, and the construction period is long because it requires a concrete curing period, which increases the overall construction period.
[철골구조물 설치 어려움][Difficulty in installing steel structures]
벽체두께가 좁은 부분은 철근과 형틀이 설치되는 벽체 부분이 피하여 인접한 넓은 부분에 시공하도록 한다.In areas where the wall thickness is narrow, construction should be done in the adjacent, wide area, avoiding the area where the rebar and formwork are installed.
[승강로 내부로의 높은 추락 위험][High risk of falling into the elevator shaft]
작업발판을 해체한 후, 기계실 바닥을 시공하기 위해, 철골보를 승강로 내부에 설치한다. After dismantling the working platform, steel beams are installed inside the elevator shaft to construct the machine room floor.
또한, 기계실 바닥 데크 플레이트를 받치는 받침대를 설치한다.Additionally, a pedestal is installed to support the machine room floor deck plate.
철골보와 받침대를 설치하기 위하여 벽체내부에 매립철물을 설치한다.Install embedded ironwork inside the wall to install steel beams and supports.
매립철물은 벽체 내부에 설치되고 벽체 콘크리트 타설 후 고정된다.Embedded hardware is installed inside the wall and fixed after the wall concrete is poured.
[기계실 바닥 데크 플레이트 지지의 불안정][Instability of the machine room floor deck plate support]
승강로 내부벽체를 따라 데크 플레이트 받침대를 설치한다.Install deck plate supports along the inner walls of the elevator shaft.
받침대는 코어벽체 내부에 매립된 철물에 의해 벽체 콘크리트 타설 후 설치된다.The pedestal is installed after the concrete wall is poured by means of ironwork embedded within the core wall.
또한 승강장 내부에 철골보를 설치하여 데크 플레이트를 지지하도록 한다.Additionally, steel beams are installed inside the platform to support the deck plate.
[높은 하중 지지를 위한 기계실 바닥 콘크리트의 장기간 양생시간][Long-term curing time of machine room floor concrete for high load support]
기계실 바닥의 권상기 등 높은 하중은 철골보를 통해 지지하도록 한다.High loads such as the lifting machine on the machine room floor are supported by steel beams.
철골보를 설치하여 기계실 바닥 콘크리트 양생 기간을 단축하도록 한다.Install steel beams to shorten the curing period of the concrete floor of the machine room.
[기계실 천정 공사의 비효율성][Inefficiency of machine room ceiling construction]
기계실 천정에 데크 플레이트를 설치하여 동바리를 설치하지 않도록 하고, 데크 플레이트가 안전하게 지지되도록 받침대를 설치한다.Install a deck plate on the ceiling of the machine room to avoid installing a sill, and install a support to safely support the deck plate.
받침대는 기계실 벽체상부에 매립된 매립철물에 연결하여 설치한다.The pedestal is installed by connecting it to the embedded hardware embedded in the upper part of the machine room wall.
[코어벽체 내부에 철골기둥과 철골보를 설치시 비용증가][Increased cost when installing steel columns and beams inside the core wall]
옥탑 1층~기계실 벽체 내부에 철골기둥과 보를 설치하지 않고, 벽체 상부에 매립철몰을 설치하여 받침대와 철골보를 설치하도록 한다.On the first floor of the rooftop, instead of installing steel columns and beams inside the walls of the machine room, install embedded steel bars on the upper part of the walls to install the supports and steel beams.
[기계실 골조공사 기간의 증가][Increase in the machine room skeleton construction period]
기계실 바닥 및 벽체 천정의 골조공사를 위한 형틀의 지지방법을 신속하고 간단하게 시공할 수 있도록 벽체내 매립철물과 받침대를 신속하고 용이하게 설치하도록 한다.To enable quick and easy installation of embedded hardware and supports within the wall, the formwork for the skeletal work of the machine room floor and wall ceiling can be constructed quickly and simply.
기계실 벽체와 천정은 한번에 콘크리트를 타설하도록 한다.The walls and ceiling of the machine room are to be concreted at once.
[철골구조물 설치 어려움][Difficulty in installing steel structures]
벽체두께가 좁은 부분을 피하여 인접한 넓은 부분에 철골구조물을 안전하고 정밀하고 신속하게 설치할 수 있다.It allows for safe, precise, and quick installation of steel structures in adjacent, wide areas, avoiding areas with narrow wall thickness.
[승강로 내부로의 높은 추락 위험][High risk of falling into the elevator shaft]
기계실 바닥 데크 플레이트를 안전하고, 신속, 용이하게 설치할 수 있다.Machine room floor deck plates can be installed safely, quickly and easily.
데크 플레이트는 벽체의 받침대에 지지되면서 철골보에도 2중으로 지지된다.The deck plate is supported on the wall pedestals and is also double supported on the steel beams.
따라서 추락위험이 없다.Therefore, there is no risk of falling.
[기계실 바닥 데크 플레이트 지지의 불안정][Instability of the machine room floor deck plate support]
받침대는 코어벽체 내부에 매립된 철물에 의해 벽체 콘크리트 타설 후 설치되므로 고정된다.The pedestal is fixed by being installed after the concrete wall is poured by ironwork embedded within the core wall.
승강장 내부의 철골보위에 데크 플레이트가 설치되므로 안정성이 높다.The deck plate is installed on the steel frame inside the platform, so it is highly stable.
[높은 하중 지지를 위한 기계실 바닥 콘크리트의 장기간 양생시간][Long-term curing time of machine room floor concrete for high load support]
기계실 바닥의 하중은 철골보를 통해 지지되므로 기계실 바닥 콘크리트 양생 기간이 단축된다.Since the load of the machine room floor is supported by the steel beam, the curing period of the machine room floor concrete is shortened.
[기계실 천정 공사의 비효율성][Inefficiency of machine room ceiling construction]
기계실 벽체의 받침대를 통해 기계실 천정에 데크 플레이트를 안전하고 신속하게 설치할 수 있고, 콘크리트 양생을 의한 동바리가 생략되어 공사기간이 단축된다.The deck plate can be installed safely and quickly on the ceiling of the machine room through the pedestal of the machine room wall, and the construction period is shortened as the support for concrete curing is omitted.
[코어벽체 내부에 철골기둥과 철골보를 설치시 비용증가][Increased cost when installing steel columns and beams inside the core wall]
옥탑 1층~기계실 벽체 내부에 철골기둥과 보를 설치하지 않으므로, 비용이 증가하지 않는다.Since steel columns and beams are not installed inside the walls of the 1st floor rooftop machine room, costs do not increase.
[기계실 골조공사 기간의 증가][Increase in the machine room skeleton construction period]
벽체내 매립철물과 받침대를 신속하고 용이하게 설치하여 3일 내지 4일만에 기계실 골조를 완성할 수 있다. 이에 따라 전체 공사기간이 단축된다.The machine room frame can be completed in just 3 to 4 days by quickly and easily installing embedded hardware and supports within the wall, thereby shortening the overall construction period.
도 1 내지 도 148은 본 발명에 따른 제 1 내지 제 4 실시예Figures 1 to 148 illustrate the first to fourth embodiments according to the present invention.
높은 하중을 담당하는 옥탑 기계실 바닥의 큰 철골보를 설치하기 위한 철골기둥은 다양한 위치에 시공될 수 있다.Steel columns for installing large steel beams on the rooftop machine room floor that support high loads can be constructed in various locations.
1) 승강로 벽체의 벽체내부에 철골기둥 설치1) Installation of steel columns inside the walls of the elevator shaft
2) 승강로 벽체로 부터 일정거리 이격거리에 철골기둥 설치2) Install steel columns at a certain distance from the elevator shaft wall.
3) 승강로 벽체라인에 붙여서 철골기둥 설치3) Install steel columns by attaching them to the elevator shaft wall line.
4) 승강로 사각형 허공의 내부 공간에 철골기둥 설치4) Installation of steel columns in the rectangular space inside the elevator shaft
5) 상기 1) 내지 4)방식의 혼용 또는 조합5) Mixing or combining the above methods 1) to 4)
다음은 철골기둥의 설치방법의 제 1 실시예이다.The following is a first embodiment of a method for installing a steel column.
제 1실시예는 승강로 벽체의 벽체내부에 철골기둥 설치를 일부 설치하고 일부는 벽체 외부에 설치하는 방식이다.In the first embodiment, some of the steel columns are installed inside the wall of the elevator shaft and some are installed outside the wall.
도 1은 1개층에 승강로 1가 2개 있는 일반적인 아파트의 평면도이다. 노란색 부분이 엘리베이터 승강로가 있는 부분이다.Figure 1 is a floor plan of a typical apartment with two elevator shafts per floor. The yellow area is where the elevator shaft is.
도 2는 상기 승강로 #1 (코어 1번)에 설치되는 본 발명에 따른 철골구조물의 설치예이다.FIG. 2 is an example of installation of a steel structure according to the present invention installed in the elevator #1 (core 1).
승강로에 2대의 엘리베이터가 있으며, 본 발명의 핵심인 높은 하중을 부담하는 큰 철골보가 각 엘리베이터마다 2개가 설치된다.There are two elevators in the hoistway, and two large steel beams that support high loads, which are the core of the present invention, are installed in each elevator.
큰 철골보를 지지하기 위하여 벽체 폭이 큰 일부 벽체에는 철골기둥과 철골보가 설치된다. 벽체 폭이 좁은 승강장 홀측(계단실과 승강로 사이부분)에는 벽체밖에 철골이 시공된다.In order to support large steel beams, steel columns and beams are installed on some walls with wide walls. On the platform side (the area between the stairwell and the elevator shaft) where the wall width is narrow, steel frames are installed outside the walls.
철골구조물은 옥탑1층과 옥탑2층 2개층에 걸쳐 시공된다. 1개층씩 따로 별도로 설치될 수 있다. 옥탑 1층만 설치될 수 있다.The steel structure is constructed over two floors, the first and second floors of the rooftop. Each floor can be installed separately. It can only be installed on the first floor of the rooftop.
도 3은 철골기둥의 위치를 나타낸 것이다. 벽체 폭이 200mm로 좁은 부분에는 철골기둥이 벽체밖에 위치하고 있다.Figure 3 shows the location of steel columns. In the narrow part of the wall where the width is 200 mm, the steel columns are located outside the wall.
도 4는 철골기둥, 철골보, 큰 철골보를 함께 표시한 평면도이다. 큰 철골보는 가로 또는 세로, 가로+세로로 설치될 수 있다.Figure 4 is a plan view showing steel columns, steel beams, and large steel beams together. Large steel beams can be installed horizontally, vertically, or horizontally and vertically.
도 5는 철골구조물 설치 단면도 1이며, 벽체내부에 일부, 벽체밖에 일부 철골기둥이 설치된다.Figure 5 is a cross-sectional drawing 1 of a steel structure installation, with some steel columns installed inside the wall and some outside the wall.
도 6은 철골구조물 설치 단면도 2이며, 큰 철골보가 기계실 바닥아래에 승강로 벽체에 올려져 설치된다. 큰 철골보는 철골과의 연결 및 벽체 콘크리트 타설 후 높은 하중을 부담하는 강한 구조를 신속하고 안전하게 갖추게 된다.Figure 6 is a cross-sectional drawing 2 of the steel structure installation, in which a large steel beam is installed on the elevator shaft wall under the machine room floor. After the large steel beam is connected to the steel frame and the concrete of the wall is poured, a strong structure capable of bearing a high load is quickly and safely constructed.
도 7은 벽체두께가 200mm로 좁은 경우, 벽체밖에 철골기둥을 설치하는 것이다.Figure 7 shows a case where a steel column is installed outside the wall when the wall thickness is as narrow as 200 mm.
도 8은 철골기둥은 2개층 높이로 설치하는 것이다. .Figure 8 shows that steel columns are installed two stories high.
도 9는 엘리베이터 홀 부분의 벽체밖에 설치되는 철골구조물이다. 철골기둥과 철골보는 150mm 두께이고, 벽체로 부터 150mm 이격된다. Fig. 9 is a steel structure installed outside the wall of the elevator hall section. The steel columns and beams are 150 mm thick and are spaced 150 mm from the wall.
도 10은 도 9의 벽체로 부터 150mm 이격된 사이에 벽체알폼(60mm)이 설치, 해체된다.Fig. 10 shows a wall foam (60 mm) installed and dismantled at a distance of 150 mm from the wall of Fig. 9.
도 11은 2개층 철골기둥에 기계실 바닥 철골보가설치된 것이다. 엘리베이터 권상기 하부에 큰 철골보가 각각 2개씩 설치된다. 벽체로 부터 이격된 150mm 부분의 데크 플레이트를 지지하기 위하여 철골앵글(ㄱ, ㄴ형강 등) 또는 데크 받침대가 철골기둥과 철골보에 설치될 수 있다.Fig. 11 shows a machine room floor steel beam installed on a two-story steel column. Two large steel beams are installed on each of the lower sections of the elevator traction machine. In order to support the deck plate at a distance of 150 mm from the wall, steel angles (such as L-shaped steel) or deck supports can be installed on the steel columns and steel beams.
도 12은 도 11의 철골보에 기계실 바닥 데크 플레이트가 설치된 것이다. 데크는 벽체라인까지 철골보로 부터 돌출되어 있다.Fig. 12 shows a machine room floor deck plate installed on the steel beam of Fig. 11. The deck protrudes from the steel beam to the wall line.
도 13은 기계실 바닥까지만을 나타낸 것이다. 철골구조물은 도 13과 같이 기계실 바닥까지만 시공되고, 상부는 별도의 철골구조물 또는 벽체내부의 가설구조물로 조합, 혼용으로 시공될 수 있다.Figure 13 shows only the floor of the machine room. The steel structure is constructed only up to the floor of the machine room as shown in Figure 13, and the upper part can be constructed by combining or using a separate steel structure or a temporary structure inside the wall.
도 14는 기계실 지붕의 철골보이다. Fig. 14 is a steel beam of the machine room roof.
도 15는 기계실 지붕의 데크 플레이트이다.Fig. 15 is a deck plate of the machine room roof.
도 16은 철골구조물 2개층 전체의 이미지이다.Figure 16 is an image of the entire two-story steel structure.
다음은 본 발명에 따른 철골구조물과 옥탑 골조의 시공과정을 나타낸 것이다.The following shows the construction process of the steel structure and roof frame according to the present invention.
도 17은 옥탑층 단면도이다. 기계실, 홀, 계단실로 구성된다.Figure 17 is a cross-sectional view of the rooftop floor. It consists of a machine room, a hall, and a stairwell.
도 18은 설치일정이며, 최상층 아파트 세대를 타설한다. 그러면 옥상바닥이 형성된다. 타설전에 미리 철골구조물을 설치할 수 있는 앙카를 매립한다.Figure 18 is the installation schedule. The top floor apartment is poured. Then, the rooftop floor is formed. Before pouring, anchors are buried so that the steel structure can be installed in advance.
도 19는 철골구조물을 옥상에서 조립하는 것이다. 철골구조물은 지상1층 또는 옥상에서 조립한다. 사전에 옥탑의 치수를 현장에서 직접 확인하고, 실제 치수에 맞게 철골 공장에서 제작하여 현장으로 운송한다. 15일 또는 1개월 정도 전에 미리 조립하여 테스트할 수 있다.Figure 19 is assembling the steel structure on the rooftop. The steel structure is assembled on the first floor above ground or on the rooftop. The dimensions of the rooftop are checked on site in advance, and the steel frame is manufactured in a factory according to the actual dimensions and transported to the site. It can be assembled and tested 15 days or 1 month in advance.
또한 철골구조물을 세울 베이스 플레이트를 만든다. Additionally, a base plate is created to erect the steel structure.
도 20은 옥상 또는 지상1층에서 조립한 또는 승강로 제자리에서 직접 하나하나 설치한 철골구조물 전체이다.Figure 20 is the entire steel structure assembled on the rooftop or the first floor above ground or installed one by one directly in place in the elevator shaft.
큰 철골보가 기계실 바닥하부에 위치하고, 그 위에 기계실 바닥 데크 플레이트가 설치된다. 기계실 지붕은 홀 부분에만 데크 플레이트를 미리 설치한다. 권상기 부분은 권상기를 양중하고 난후 데크를 시공하도록 한다. 물론 권상기부분의 데크 플레이트도 미리 설치할 수 있으며, 이때 권상기는 옆의 개방된 부분(계단실 측, 창문 등)으로 양중할 수 있다.A large steel beam is located under the floor of the machine room, and the machine room floor deck plate is installed on top of it. The deck plate is installed in advance only in the hall part of the machine room roof. For the traction machine part, the deck is constructed after the traction machine is lifted. Of course, the deck plate of the traction machine part can also be installed in advance, and at this time, the traction machine can be lifted to an open part on the side (staircase side, window, etc.).
도 21은 타워크레인으로 철골구조물 전체를 양중하여 설치하는 것이다. 타워크레인의 용량과 철골구조물의 무게에 따라, 한개 또는 2개이상으로 나누어 조립하고 설치할 수 있다. Figure 21 is a method of lifting and installing the entire steel structure using a tower crane. Depending on the capacity of the tower crane and the weight of the steel structure, it can be assembled and installed by dividing it into one or two or more parts.
예로 기둥은 2개층으로 한번에 조립하고 기계실 지붕의 철골보는 분리하여 설치할 수 있다.For example, columns can be assembled in two layers at once, and the steel beams of the machine room roof can be installed separately.
예로 승강로 부분과 홀측을 분리하여 조립, 설치할 수 있다.For example, the elevator shaft section and the hall side can be separated and assembled and installed.
큰 철골보는 홀 측으로 연장되어 나중에 세워질 홀 측 벽체를 관통하게 된다.The large steel beam extends towards the hall and penetrates the hall side wall that will be erected later.
철골구조물은 9개의 베이스 플레이트에 동시에 내려진다. 베이스 플레이트와 철골기둥은 용접 또는 볼트로 연결된다.The steel structure is lowered simultaneously onto nine base plates. The base plates and steel columns are connected by welding or bolts.
도 22는 도 21에서 철골구조물이 설치된 후, 옥탑 골조공사를 진행하는 것이다. 옥탑 1층의 벽체 철근, 감리단 검측, 벽체 알폼을 설치한다. 이때 계단실도 신속하는 진행하여 옥탑 1층 전체를 같이 콘크리트를 타설하는 것이 유리하다.Figure 22 shows the rooftop frame construction after the steel structure is installed in Figure 21. The rooftop 1st floor wall reinforcement, inspection of the inspection team, and wall foam are installed. At this time, it is advantageous to quickly proceed with the stairwell and pour concrete for the entire rooftop 1st floor at the same time.
벽체알폼은 철골기둥과 철골보, 큰 철골보를 이용(벽체알폼의 거치 또는 위치 확인)하여 신속하고 정확하게 설치할 수 있다. Wall foam can be installed quickly and accurately using steel columns, steel beams, and large steel beams (installation or location of wall foam).
도 23은 옥탑 1층 콘크리트를 타설하는 것이다. 승강장 내부에 큰 규모의 작업발판(RCS, PCS, ACS)이 없는 경우, 벽체와 천정을 한번에 콘크리트를 타설할 수 있다. 기계실과 계단실은 같은날 같이 타설하거나 계단실을 몇일 후 나중에 타설할 수 있다.Fig. 23 is the pouring of the concrete on the first floor of the rooftop. If there is no large-scale work platform (RCS, PCS, ACS) inside the platform, the walls and ceiling can be poured at the same time. The machine room and the stairway can be poured on the same day, or the stairway can be poured a few days later.
도 24는 옥탑 2층 공사 착수를 나타낸다. 옥탑1층의 알폼을 해체하여 옥탑2층으로 양중준비하고, 옥탑2층으로 외부 갱폼을 올린 후, 기계실 벽체 철근을 설치한다.Figure 24 shows the start of construction on the second floor of the rooftop. The alform on the first floor of the rooftop is dismantled to prepare for lifting to the second floor of the rooftop, and after the external gang form is raised to the second floor of the rooftop, the machine room wall reinforcement is installed.
도 25는 기계실 벽체 알폼을 설치하는 것이다. 철골기둥과 철골보에 거치, 지지하여 알폼을 정확하고 신속하게 설치할 수 있다.Figure 25 shows the installation of machine room wall foam. The foam can be installed accurately and quickly by being supported and installed on steel columns and steel beams.
도 26은 벽체 철근과 알폼이 완료되어 건축작업자들이 내려가면, 타워크레인으로 엘리베이터 자재를 기계실 상부로 양중하여 기계실 바닥으로 수직으로 내려 놓는다. 상부에 데크 플레이트가 아직 시공되지 않아, 신속하고 정확하게 무거운 권상기를 제자리에 설치할 수 있다. Figure 26 shows that after the wall reinforcement and the Alform are completed and the construction workers have come down, the elevator materials are lifted to the top of the machine room by the tower crane and are lowered vertically to the machine room floor. Since the deck plate has not yet been constructed on top, the heavy hoist can be installed in place quickly and accurately.
본 발명의 특징에 따라 철골구조물과 콘크리트에 지지되는 큰 철골보가 있어 기계실 바닥 양생시간을 거치지 않고도 무거운 권상기를 빠른 시간내(하루 ~이틀만)에 설치할 수 있다. According to a feature of the present invention, since there is a steel structure and a large steel beam supported on concrete, a heavy hoist can be installed in a short period of time (one to two days) without going through a machine room floor curing time.
도 27은 권상기 양중 후, 상부의 잔여 데크 플레이를 설치하는 것이다. 계단실 작업도 병행 진행한다.Fig. 27 is the installation of the remaining deck play on the upper part after the lifting of the hoist. The stairwell work is also carried out in parallel.
상부의 잔여 데크 플레이를 설치되면, 기계실이 막히게 되므로, 전기팀이 올라와 엘리베이터를 본격적으로 설치하기 시작한다. 형판을 설치하고, 피아노선을 지하까지 내린다.Once the remaining deck play on the upper deck is installed, the machine room will be blocked, so the electrical team comes up and starts installing the elevator in earnest. They install the molds and lower the piano wire to the basement.
도 28은 기계실 및 계단실의 지붕 철근을 시공하는 것이다.Fig. 28 is the construction of roof reinforcement bars for the machine room and stairwell.
도 29는 옥탑 2층 벽체와 지붕 콘크리트를 반나절만에 같이 타설하는 것이다. 이로써 골조공사가 완료되었다. 기계실 벽체/지붕과 계단실은 같이 하루만에 타설하거나 계단실이 늦어지는 경우 계단실은 나중에 별도로 타설 할 수 있다.Fig. 29 shows the roof concrete and the second floor walls of the rooftop being poured together in half a day. This completes the skeletal work. The mechanical room walls/roof and the stairwell can be poured together in one day, or if the stairwell is delayed, the stairwell can be poured separately later.
도 30은 엘리베이터 설치 중 또는 설치후 나중에 노출되는 철골기둥과 철골보의 일부를 해체할 수 있다. 또는 영구적으로 존치할 수 있다. Fig. 30 may dismantle a portion of the steel columns and beams that are exposed during or after the elevator installation, or may be retained permanently.
도 31은 철골구조물 일부를 해체후의 모습니다. 기계실 중앙의 기둥은 옥상 전체 슬래브를 지지해야 하므로 구조상 존치해야 할 수 있다. Fig. 31 shows the appearance after dismantling a portion of the steel structure. The central column of the machine room may need to be retained for structural reasons as it must support the entire rooftop slab.
도 32는 본 발명의 핵심기술인 큰 철골보의 설치에 따른 높은 하중을 신속하고 안전하게 받치는 구조개념을 나타낸 것이다.Figure 32 illustrates a structural concept for quickly and safely supporting a high load by installing a large steel beam, which is a core technology of the present invention.
기계실 바닥에 걸치는 하중의 수톤이다.This is the number of tons of load that is placed on the machine room floor.
1) 권상기 받침대 철골보 다수1) Multiple steel beams for the pedestal of the winding machine
2) 권상기 : 수톤2) Lifting weight: several tons
3) 가이드 레일 양중용 윈치 3) Winch for lifting guide rail
4) 가이드 레인 (지하부터 ~ 옥탑까지 한번에 엮어서 양중) : 수톤4) Guide lane (from basement to rooftop, lifting at once): several tons
본 발명의 특징에 따라 큰 철골보는According to the features of the present invention, a large steel beam
1) 철골기둥, 철골보와 연결1) Connection with steel columns and beams
2) 승강로 벽체에 매립되는 경우, 콘크리트에 묻히여 높은 하중 부담 가능하다.2) When embedded in the elevator shaft wall, it is buried in concrete and can support high loads.
다음은 본 발명에 따른 큰 철골보의 수직적 위치의 종류의 예시이다.The following are examples of types of vertical positions of large steel beams according to the present invention.
도 33은 큰 철골보가 기계실 바닥아래에 위치하여 기계실 바닥을 받치는 방식이다.Fig. 33 shows a method in which a large steel beam is positioned under the machine room floor to support the machine room floor.
도 34는 큰 철골보가 기계실 바닥 중간부분에 위치하여 기계실 바닥에 묻히는 방식이다.Figure 34 shows a method in which a large steel beam is located in the middle of the machine room floor and buried in the machine room floor.
도 35는 큰 철골보가 기계실 바닥하부와 일치되게 설치되는 방식이다. Figure 35 shows a method in which a large steel beam is installed flush with the lower part of the machine room floor.
도 34 내지 도 35에서는 데크 플레이트는 큰 철골보의 하부 철판부분에 거치하여 설치할 수 있다. 큰 철골보 사이에 철골앵글을 연결하고 그 위에 데크 플레이트를 설치할 수도 있다.In Figures 34 and 35, the deck plate can be installed by being placed on the lower steel plate portion of a large steel beam. A steel angle can also be connected between large steel beams and the deck plate can be installed on top of it.
다음은 본 발명에 따른 홀 및 기계실 부분에 비계를 설치하는 방식의 예시이다.The following is an example of a method for installing a ladder in a hall and machine room according to the present invention.
도 36에서 홀 측에는 철골기둥 대신 비계를 설치한 후 콘크리트를 타설하고 해체할 수 있다.In Fig. 36, instead of steel columns, scaffolding can be installed on the hole side, and then concrete can be poured and dismantled.
기계실 벽체 안쪽에 비계를 설치하여 철골보와 지붕 데크 플레이트를 거치할 수 있다.Scaffolding can be installed inside the machine room walls to support steel beams and roof deck plates.
철골구조물과 비계방식을 혼용, 조합하여 사용할 수 있다.Steel structures and scaffolding systems can be used interchangeably and in combination.
도 37은 본 발명에 따른 철골구조물 설치와 옥탑골조 설치 과정이다.Figure 37 shows the process of installing a steel structure and a roof frame according to the present invention.
[0단계][Step 0]
최상층 벽체 및 지붕 (옥상 바닥)콘크리트를 타설한다. 이때 미리 철골구조물 연결용 앙카를 매립한다.The top floor walls and roof (rooftop) are poured with concrete. At this time, anchors for connecting the steel structure are embedded in advance.
[1단계][Step 1]
철골기둥 하단레벨에 맞게 베이스 플레이트를 설치한다.Install the base plate to match the lower level of the steel column.
이때 옥상 또는 지상 1층에서는 철골구조물(철골기둥, 철골보, 큰 철골보, 데크 플레이트)을 조립/검사한다.At this time, steel structures (steel columns, steel beams, large steel beams, deck plates) are assembled/inspected on the rooftop or the first floor above ground.
계단실에서는 철근, 형틀이 시공된다.In the stairwell, rebar and formwork are installed.
외부 갱폼이 옥탑 1층 높이로 인상된다.The external gang form is raised to the height of the first floor of the rooftop.
[2단계][Step 2]
철골구조물을 타워 크레인으로 들어서, 베이스 플레이트위에 설치하고, 검사한다.The steel structure is lifted by a tower crane, installed on a base plate, and inspected.
계단실에서는 철근, 형틀이 시공된다.In the stairwell, rebar and formwork are installed.
[3단계][Step 3]
옥탑 1층 벽체철근, 데크 철근, 감리단 철근 검측, 벽체 알폼 설치로 진행된다.It will proceed with inspection of the rooftop first floor wall reinforcement, deck reinforcement, and supervisory team reinforcement, and installation of wall foam.
계단실에서는 철근, 형틀이 시공된다.In the stairwell, rebar and formwork are installed.
[4단계][Step 4]
옥탑 1층 벽체 및 천정(기계실 바닥)의 콘크리트를 반나절만에 같이 타설한다.The concrete for the walls and ceiling (machine room floor) of the first floor of the rooftop was poured together in half a day.
계단실도 같이 타설하거나 나중에 타설한다.The stairwell can be poured at the same time or later.
[5단계][Step 5]
옥탑 2층 벽체철근, 감리단 검측, 벽체 알폼을 설치한다. 이후 엘리베이터 장비를 기계실 바닥으로 양중한다.Install the rooftop 2nd floor wall reinforcement, inspect the inspection team, and install the wall foam. Then, lift the elevator equipment to the machine room floor.
계단실 2층에서는 비계설치, 철근설치가 진행된다.On the second floor of the stairwell, ladders and rebar are installed.
외벽 갱폼이 인상된다.The exterior gang form is impressive.
[6단계][Step 6]
옥탑 2층 천정(지붕)에 잔여 데크 플레이트 설치, 지붕 철근, 감리단 검측이 진행된다.Installation of remaining deck plates on the second floor ceiling (roof), roof reinforcement, and inspection of the guardrail are in progress.
계단실 2층에서는 철근, 형틀이 진행된다.On the second floor of the stairwell, rebar and formwork are being installed.
[7단계][Step 7]
기계실 바닥에서 엘리베이터 설치가 착수된다. 형판 설치, 피아노선을 내린다. Elevator installation begins on the machine room floor. Formwork is installed and piano wires are lowered.
계단실 2층에서는 철근, 형틀이 진행된다.On the second floor of the stairwell, rebar and formwork are being installed.
[8단계][Step 8]
옥탑 2층 기계실 벽체, 천정 콘크리트를 반나절만에 타설한다.The walls and ceiling concrete of the mechanical room on the second floor of the rooftop were poured in half a day.
계단실 2층도 같이 타설하거나, 나중에 타설한다.The second floor of the stairwell can be poured at the same time or later.
다음은 본 발명에 따른 철골구조물 설치와 옥탑골조 설치 소요일수이다..The following are the number of days required for installing the steel structure and the roof frame according to the present invention.
[0일차][Day 0]
골구조물 연결용 앙카 매립Anchor embedding for connecting bone structures
최상층 벽체 및 지붕 (옥상 바닥)콘크리트 타설Top floor walls and roof (rooftop) concrete casting
[1일차][Day 1]
철골기둥 하단의 베이스 플레이트 설치Installation of base plate at the bottom of steel column
철골구조물(철골기둥, 철골보, 큰 철골보, 데크 플레이트)을 조립/검사Assembling/inspecting steel structures (steel columns, steel beams, large steel beams, deck plates)
[2일차][Day 2]
철골구조물 베이스 플레이트위에 설치/검사 (오전)Installation/Inspection on Steel Structure Base Plate (AM)
옥탑 1층 벽체철근, 천정 데크 철근, 감리단 철근 검측 (오후)Rooftop 1st floor wall reinforcement, ceiling deck reinforcement, and supervisory reinforcement inspection (afternoon)
[3일차][Day 3]
옥탑 1층 벽체 알폼 설치 (오전)Rooftop 1st floor wall foam installation (morning)
계단실 철근, 형틀 시공Staircase rebar and formwork construction
옥탑 1층 벽체 및 천정(기계실 바닥)의 콘크리트 타설 (오후)Concrete pouring of the walls and ceiling of the first floor of the rooftop (machine room floor) (afternoon)
계단실 콘크리트 포함 또는 별도Staircase concrete included or separate
[4일차][Day 4]
옥탑 2층 벽체철근, 감리단 검측, 벽체 알폼 설치Rooftop 2nd floor wall reinforcement, inspection by supervisor, wall foam installation
외벽 갱폼 인상Exterior gang form impression
계단실 2층 비계설치, 철근설치Installation of stairs and reinforcing bars on the 2nd floor of the stairwell
[5일차][Day 5]
엘리베이터 장비 기계실 바닥으로 양중Lifting elevator equipment to machine room floor
옥탑 2층 천정(지붕) 잔여 데크 플레이트 설치, 지붕 철근, 감리단 검측Installation of remaining deck plates on the 2nd floor rooftop, roof reinforcement, and inspection by the supervisory team
계단실 2층 비계설치, 철근설치Installation of stairs and reinforcing bars on the 2nd floor of the stairwell
[6일차][Day 6]
기계실 바닥에서 엘리베이터 설치 착수. 형판 설치, 피아노선 시공 Start of elevator installation on the machine room floor. Installing formwork and piano wire.
계단실 2층 비계설치, 철근설치Installation of stairs and reinforcing bars on the 2nd floor of the stairwell
[7일차~또는 이후][Day 7~or thereafter]
옥탑 2층 기계실 벽체, 천정 콘크리트 타설Rooftop 2nd floor machine room wall and ceiling concrete pouring
계단실 2층 포함 타설Casting including the 2nd floor of the stairwell
다음은 철골기둥의 설치방법의 제 2 실시예이다.The following is a second embodiment of a method for installing a steel column.
제 2실시예는 승강로 벽체의 벽체내부에 철골기둥 설치를 일부 설치하고 일부는 벽체라인에 맞추어 설치하는 방식이다.The second embodiment is a method of installing steel columns partially inside the walls of the elevator shaft and partially along the wall line.
도 38은 1개층에 승강로 1가 2개 있는 일반적인 아파트의 평면도이다. 노란색 부분이 엘리베이터 승강로가 있는 부분이다.Figure 38 is a floor plan of a typical apartment with two elevator shafts per floor. The yellow area is where the elevator shaft is.
도 39는 상기 승강로 #1 (코어 1번)에 설치되는 본 발명에 따른 철골구조물의 설치예이다.Figure 39 is an example of installation of a steel structure according to the present invention installed in the elevator #1 (core 1).
승강로에 2대의 엘리베이터가 있으며, 본 발명의 핵심인 높은 하중을 부담하는 큰 철골보가 각 엘리베이터마다 2개가 설치된다.There are two elevators in the hoistway, and two large steel beams that support high loads, which are the core of the present invention, are installed in each elevator.
큰 철골보를 지지하기 위하여 벽체 폭이 큰 일부 벽체에는 철골기둥과 철골보가 설치된다. 벽체 폭이 좁은 승강장 홀측(계단실과 승강로 사이부분)에는 벽체라인에 맞추어 철골이 시공된다.In order to support large steel beams, steel columns and beams are installed on some walls with wide walls. On the platform hall side (the area between the stairwell and the elevator shaft) where the wall width is narrow, steel frames are constructed according to the wall line.
철골구조물은 옥탑1층과 옥탑2층 2개층에 걸쳐 시공된다. 1개층씩 따로 별도로 설치될 수 있다. 옥탑 1층만 설치될 수 있다.The steel structure is constructed over two floors, the first and second floors of the rooftop. Each floor can be installed separately. It can only be installed on the first floor of the rooftop.
도 40은 철골기둥의 위치를 나타낸 것이다. 벽체 폭이 200mm로 좁은 부분에는 철골기둥이 벽체라인과 동일하게 위치하고 있다.Figure 40 shows the location of steel columns. In the narrow part where the wall width is 200 mm, the steel columns are positioned at the same level as the wall line.
도 41은 철골기둥, 철골보, 큰 철골보를 함께 표시한 평면도이다. 큰 철골보는 가로 또는 세로, 가로+세로로 설치될 수 있다.Figure 41 is a plan view showing steel columns, steel beams, and large steel beams together. Large steel beams can be installed horizontally, vertically, or horizontal and vertically.
도 42는 철골구조물 설치 단면도 1이며, 벽체내부에 일부, 벽체라인에 일부 철골기둥이 설치된다.Figure 42 is a cross-sectional drawing 1 of a steel structure installation, in which some steel columns are installed inside the wall and some are installed on the wall line.
도 43은 철골구조물 설치 단면도 2이며, 큰 철골보가 기계실 바닥아래에 승강로 벽체에 올려져 설치된다. 큰 철골보는 철골과의 연결 및 벽체 콘크리트 타설 후 높은 하중을 부담하는 강한 구조를 신속하고 안전하게 갖추게 된다.Figure 43 is a cross-sectional drawing 2 of a steel structure installation, in which a large steel beam is installed on the elevator shaft wall under the machine room floor. The large steel beam quickly and safely forms a strong structure that can bear a high load after being connected to the steel frame and pouring concrete for the wall.
도 44는 벽체두께가 200mm로 좁은 경우, 벽체라인에 맞추어 철골기둥을 설치하는 것이다.Figure 44 shows how to install steel columns in line with the wall line when the wall thickness is as narrow as 200 mm.
도 45는 철골기둥은 2개층 높이로 설치하는 것이다. .Fig. 45 shows that steel columns are installed two stories high.
도 46은 엘리베이터 홀 부분의 벽체밖에 설치되는 철골구조물이다. 철골기둥과 철골보는 150mm 두께이고, 벽체에 붙여 있다. 철골기둥이 벽체 코너에 위치하므로 코너부분에 형틀이 필요없다.Fig. 46 is a steel structure installed outside the wall of the elevator hall area. The steel columns and beams are 150 mm thick and are attached to the wall. Since the steel columns are located at the corners of the wall, no formwork is required at the corners.
도 47은 도 46의 벽체라인에 맞추어 철골기둥과 보, 벽체알폼(60mm)이 설치, 해체된다. 벽체 알폼을 지지하기 위하여 알폼 거치 철판 조각이 군데 군데 철골기둥에 부착될 수 있다. 철골기둥과 만나는 코너분의 알폼설치가 용이하고 정확해진다. Fig. 47 shows the steel columns, beams, and wall foam (60 mm) being installed and dismantled in accordance with the wall line of Fig. 46. In order to support the wall foam, foam support steel plate pieces can be attached to the steel columns here and there. The installation of foam at corners where it meets the steel columns becomes easy and accurate.
도 48은 2개층 철골기둥에 기계실 바닥 철골보가설치된 것이다. 엘리베이터 권상기 하부에 큰 철골보가 각각 2개씩 설치된다. Fig. 48 shows a machine room floor steel beam installed on a two-story steel column. Two large steel beams are installed under each elevator traction machine.
도 49는 도 48의 철골보에 기계실 바닥 데크 플레이트가 설치된 것이다. 데크 플레이트는 벽체라인까지 철골보위에 설치된다.Fig. 49 shows a machine room floor deck plate installed on the steel beam of Fig. 48. The deck plate is installed on the steel beam up to the wall line.
데크 플레이트는 벽체에 붙여진 철골보위에 올라타 거치되므로 별도의 데크 플레이트 받침대가 필요없다.The deck plate is mounted on a steel frame attached to the wall, so a separate deck plate support is not required.
도 50은 기계실 바닥까지을 나타낸 것이다. 철골구조물은 기계실 바닥까지만 시공되고, 상부는 별도의 철골구조물 또는 벽체내부의 가설구조물로 조합, 혼용으로 시공될 수 있다.Figure 50 shows the machine room floor. The steel structure is constructed only up to the machine room floor, and the upper part can be constructed as a separate steel structure or a temporary structure inside the wall, combined or combined.
도 51은 기계실 지붕의 철골보이다. Fig. 51 is a steel beam of the machine room roof.
도 52는 기계실 지붕의 데크 플레이트이다.Fig. 52 is a deck plate of the machine room roof.
도 53은 철골구조물 2개층 전체의 이미지이다.Figure 53 is an image of the entire two-story steel structure.
다음은 본 발명에 따른 철골구조물과 옥탑 골조의 시공과정을 나타낸 것이다.The following shows the construction process of the steel structure and roof frame according to the present invention.
도 54는 옥탑층 단면도이다. 기계실, 홀, 계단실로 구성된다.Fig. 54 is a cross-sectional view of the rooftop. It consists of a machine room, a hall, and a stairwell.
도 55는 설치일정이며, 최상층 아파트 세대를 타설한다. 그러면 옥상바닥이 형성된다. 타설전에 미리 철골구조물을 설치할 수 있는 앙카를 벽체내부 및 벽체 라인에 인접하여 매립한다.Figure 55 is the installation schedule, and the top floor apartment is poured. Then, the rooftop floor is formed. Before pouring, anchors that can install the steel structure are buried inside the wall and adjacent to the wall line.
도 56은 철골구조물을 옥상에서 조립하는 것이다. 철골구조물은 지상1층 또는 옥상에서 조립한다. 사전에 옥탑의 치수를 현장에서 직접 확인하고, 실제 치수에 맞게 철골 공장에서 제작하여 현장으로 운송한다. 15일 또는 1개월 정도 전에 미리 조립하여 테스트할 수 있다.Fig. 56 is assembling a steel structure on a rooftop. The steel structure is assembled on the first floor above ground or on a rooftop. The dimensions of the rooftop are checked on site in advance, and the steel frame is manufactured in a factory according to the actual dimensions and transported to the site. It can be assembled and tested 15 days or 1 month in advance.
또한 철골구조물을 세울 베이스 플레이트를 만든다. Additionally, a base plate is created to erect the steel structure.
도 57은 옥상 또는 지상1층에서 조립한 또는 승강로 제자리에서 직접 하나하나 설치한 철골구조물 전체이다.Figure 57 is the entire steel structure assembled on the rooftop or the first floor above ground or installed one by one directly in place in the elevator shaft.
큰 철골보가 기계실 바닥하부에 위치하고, 그 위에 기계실 바닥 데크 플레이트가 설치된다. 기계실 지붕은 홀 부분에만 데크 플레이트를 미리 설치한다. 권상기 부분은 권상기를 양중하고 난후 데크 플레이트를 시공하도록 한다. 물론 권상기부분의 데크 플레이트도 미리 설치할 수 있으며, 이때 권상기는 옆의 개방된 부분(계단실 측, 창문 등)으로 양중할 수 있다.A large steel beam is located under the floor of the machine room, and the machine room floor deck plate is installed on top of it. The deck plate is installed in advance only in the hall part of the machine room roof. For the traction machine part, the deck plate is installed after the traction machine is lifted. Of course, the deck plate of the traction machine part can also be installed in advance, and at this time, the traction machine can be lifted to an open part on the side (staircase side, window, etc.).
도 58은 타워크레인으로 철골구조물 전체를 양중하여 설치하는 것이다. 타워크레인의 용량과 철골구조물의 무게에 따라, 한개 또는 2개이상으로 나누어 조립하고 설치할 수 있다. Fig. 58 is a method of lifting and installing an entire steel structure using a tower crane. Depending on the capacity of the tower crane and the weight of the steel structure, it can be assembled and installed by dividing it into one or two or more parts.
예로 기둥은 2개층으로 한번에 조립하고 기계실 지붕의 철골보는 분리하여 설치할 수 있다.For example, columns can be assembled in two layers at once, and the steel beams of the machine room roof can be installed separately.
예로 승강로 부분과 홀측을 분리하여 조립, 설치할 수 있다.For example, the elevator shaft section and the hall side can be separated and assembled and installed.
큰 철골보는 홀 측으로 연장되어 나중에 세워질 홀 측 벽체를 관통하게 된다.The large steel beam extends towards the hall and penetrates the hall side wall that will be erected later.
철골구조물은 9개의 베이스 플레이트에 동시에 내려진다. 베이스 플레이트와 철골기둥은 용접 또는 볼트로 연결된다.The steel structure is lowered simultaneously onto nine base plates. The base plates and steel columns are connected by welding or bolts.
도 59는 철골구조물이 설치된 후, 옥탑 골조공사를 진행하는 것이다. 옥탑 1층의 벽체 철근, 감리단 검측, 벽체 알폼을 설치한다. 이때 계단실도 신속하는 진행하여 옥탑 1층 전체를 같이 콘크리트를 타설하는 것이 유리하다.Fig. 59 shows the rooftop frame construction after the steel structure is installed. The rooftop 1st floor wall reinforcement, inspection of the inspection team, and wall foam are installed. At this time, it is advantageous to proceed quickly with the stairwell and pour concrete for the entire rooftop 1st floor at the same time.
벽체알폼은 철골기둥과 철골보, 큰 철골보를 이용(벽체알폼의 거치 또는 위치 확인)하여 신속하고 정확하게 설치할 수 있다. Wall foam can be installed quickly and accurately using steel columns, steel beams, and large steel beams (installation or location of wall foam).
도 60은 옥탑 1층 콘크리트를 타설하는 것이다. 승강장 내부에 큰 규모의 작업발판(RCS, PCS, ACS)이 없는 경우, 벽체와 천정을 한번에 콘크리트를 타설할 수 있다. 기계실과 계단실은 같은날 같이 타설하거나 계단실을 몇일 후 나중에 타설할 수 있다.Fig. 60 is the pouring of the concrete on the first floor of the rooftop. If there is no large-scale work platform (RCS, PCS, ACS) inside the platform, the walls and ceiling can be poured at the same time. The machine room and the stairway can be poured on the same day, or the stairway can be poured a few days later.
도 61은 옥탑 2층 공사 착수를 나타낸다. 옥탑1층의 알폼을 해체하여 옥탑2층으로 양중준비하고, 옥탑2층으로 외부 갱폼을 올린 후, 기계실 벽체 철근을 설치한다.Figure 61 shows the start of construction on the second floor of the rooftop. The alform on the first floor of the rooftop is dismantled to prepare for lifting to the second floor of the rooftop, and after the external gang form is raised to the second floor of the rooftop, the machine room wall reinforcement is installed.
도 62는 기계실 벽체 알폼을 설치하는 것이다. 철골기둥과 철골보에 거치, 지지하여 알폼을 정확하고 신속하게 설치할 수 있다.Fig. 62 is for installing machine room wall foam. The foam can be installed accurately and quickly by being mounted and supported on steel columns and steel beams.
도 63은 벽체 철근과 알폼이 완료되어 건축작업자들이 내려가면, 타워크레인으로 엘리베이터 자재를 기계실 상부로 양중하여 기계실 바닥으로 수직으로 내려 놓는다. 상부에 데크 플레이트가 아직 시공되지 않아, 신속하고 정확하게 무거운 권상기를 제자리에 설치할 수 있다. Figure 63 shows that after the wall reinforcement and the ALF are completed and the construction workers have come down, the elevator materials are lifted to the top of the machine room by the tower crane and are lowered vertically to the machine room floor. Since the deck plate has not yet been constructed on top, the heavy hoist can be installed in place quickly and accurately.
본 발명의 특징에 따라 철골구조물과 콘크리트에 지지되는 큰 철골보가 있어 기계실 바닥 양생시간을 거치지 않고도 무거운 권상기를 빠른 시간내(하루 ~이틀만)에 설치할 수 있다. According to a feature of the present invention, since there is a steel structure and a large steel beam supported on concrete, a heavy hoist can be installed in a short period of time (one to two days) without going through a machine room floor curing time.
도 64는 권상기 양중 후, 상부의 잔여 데크 플레이를 설치하는 것이다. 계단실 작업도 병행 진행한다.Fig. 64 is the installation of the remaining deck play on the upper part after the lifting of the hoist. The stairwell work is also carried out in parallel.
상부의 잔여 데크 플레이를 설치되면, 기계실이 막히게 되므로, 전기팀이 올라와 엘리베이터를 본격적으로 설치하기 시작한다. 형판을 설치하고, 피아노선을 지하까지 내린다.Once the remaining deck play on the upper deck is installed, the machine room will be blocked, so the electrical team comes up and starts installing the elevator in earnest. They install the molds and lower the piano wire to the basement.
도 65는 기계실 및 계단실의 지붕 철근을 시공하는 것이다.Fig. 65 is the construction of roof reinforcement bars for the machine room and stairwell.
도 66은 옥탑 2층 벽체와 지붕 콘크리트를 반나절만에 같이 타설하는 것이다. 이로써 골조공사가 완료되었다. 기계실 벽체/지붕과 계단실은 같이 하루만에 타설하거나 계단실이 늦어지는 경우 계단실은 나중에 별도로 타설 할 수 있다. Fig. 66 shows the roof concrete and the second floor walls of the rooftop being poured together in half a day. This completes the skeletal work. The mechanical room walls/roof and the stairwell can be poured together in one day, or if the stairwell is delayed, the stairwell can be poured separately at a later date.
도 67은 엘리베이터 설치 중 또는 설치후 나중에 노출되는 철골기둥과 철골보의 일부를 해체할 수 있다. 또는 영구적으로 존치할 수 있다. 벽체라인에 붙은 철골기둥은 용단(용접으로 자르기) 또는 미리 체결된 볼트와 철판을 해체한 후 해체한다.Fig. 67. Part of the steel columns and steel beams that are exposed during or after the elevator installation can be dismantled. Or, they can be left permanently. The steel columns attached to the wall line can be dismantled by cutting (welding) or by dismantling the bolts and steel plates that were previously fastened.
도 68은 철골구조물 일부를 해체후의 모습니다. 기계실 중앙의 기둥은 옥상 전체 슬래브를 지지해야 하므로 구조상 존치해야 할 수 있다. Fig. 68 shows the appearance after dismantling a portion of the steel structure. The central column of the machine room may need to be retained for structural reasons as it must support the entire rooftop slab.
도 69는 본 발명의 핵심기술인 큰 철골보의 설치에 따른 높은 하중을 신속하고 안전하게 받치는 구조개념을 나타낸 것이다.Figure 69 illustrates a structural concept for quickly and safely supporting a high load by installing a large steel beam, which is a core technology of the present invention.
기계실 바닥에 걸치는 하중의 수톤이다.This is the number of tons of load that is placed on the machine room floor.
1) 권상기 받침대 철골보 다수1) Multiple steel beams for the pedestal of the winding machine
2) 권상기 : 수톤2) Lifting weight: several tons
3) 가이드 레일 양중용 윈치 3) Winch for lifting guide rail
4) 가이드 레인 (지하부터 ~ 옥탑까지 한번에 엮어서 양중) : 수톤4) Guide lane (from basement to rooftop, lifting at once): several tons
본 발명의 특징에 따라 큰 철골보는According to the features of the present invention, a large steel beam
1) 철골기둥, 철골보와 연결1) Connection with steel columns and beams
2) 승강로 벽체에 매립되는 경우, 콘크리트에 묻히여 높은 하중 부담 가능하다.2) When embedded in the elevator shaft wall, it is buried in concrete and can support high loads.
다음은 본 발명에 따른 큰 철골보의 수직적 위치의 종류의 예시이다.The following are examples of types of vertical positions of large steel beams according to the present invention.
도 70은 큰 철골보가 기계실 바닥아래에 위치하여 기계실 바닥을 받치는 방식이다.Fig. 70 is a method in which a large steel beam is positioned under the machine room floor to support the machine room floor.
도 71는 큰 철골보가 기계실 바닥 중간부분에 위치하여 기계실 바닥에 묻히는 방식이다.Figure 71 is a method in which a large steel beam is located in the middle of the machine room floor and buried in the machine room floor.
도 72은 큰 철골보가 기계실 바닥하부와 일치되게 설치되는 방식이다. Fig. 72 shows a method in which a large steel beam is installed flush with the lower part of the machine room floor.
도 71 내지 도 72에서는 데크 플레이트는 큰 철골보의 하부 철판부분에 거치하여 설치할 수 있다. 큰 철골보 사이에 철골앵글을 연결하고 그 위에 데크 플레이트를 설치할 수도 있다.In Figures 71 and 72, the deck plate can be installed by being placed on the lower steel plate portion of a large steel beam. A steel angle can also be connected between large steel beams and the deck plate can be installed on top of it.
다음은 본 발명에 따른 홀 및 기계실 부분에 비계를 설치하는 방식의 예시이다.The following is an example of a method for installing a ladder in a hall and machine room according to the present invention.
도 73에서 홀 측에는 철골기둥 대신 비계를 설치한 후 콘크리트를 타설하고 해체할 수 있다.In Fig. 73, instead of steel columns, scaffolding can be installed on the hall side, and then concrete can be poured and dismantled.
기계실 벽체 안쪽에 비계를 설치하여 철골보와 지붕 데크 플레이트를 거치할 수 있다.Scaffolding can be installed inside the machine room walls to support steel beams and roof deck plates.
철골구조물과 비계방식을 혼용, 조합하여 사용할 수 있다.Steel structures and scaffolding systems can be used interchangeably and in combination.
도 74는 본 발명에 따른 철골구조물 설치와 옥탑골조 설치 과정이며 도 37의 설명과 같다.Fig. 74 is a process for installing a steel structure and a roof frame according to the present invention, and is the same as the description in Fig. 37.
다음은 철골기둥의 설치방법의 제 3 실시예이다.The following is a third embodiment of a method for installing a steel column.
제 3실시예는 승강로 벽체 외부에 철골기둥 설치하는 방식이다.The third embodiment is a method of installing steel columns on the outside of the elevator shaft wall.
도 75는 1개층에 승강로 1가 2개 있는 일반적인 아파트의 평면도이다. 노란색 부분이 엘리베이터 승강로가 있는 부분이다.Figure 75 is a floor plan of a typical apartment with two elevator shafts per floor. The yellow area is where the elevator shaft is.
도 76은 상기 승강로 #1 (코어 1번)에 설치되는 본 발명에 따른 철골구조물의 설치예이다.Fig. 76 is an example of installation of a steel structure according to the present invention installed in the elevator #1 (core 1).
승강로에 2대의 엘리베이터가 있으며, 본 발명의 핵심인 높은 하중을 부담하는 큰 철골보가 각 엘리베이터마다 2개가 설치된다.There are two elevators in the hoistway, and two large steel beams that support high loads, which are the core of the present invention, are installed in each elevator.
큰 철골보를 지지하기 위하여 옥상의 벽체외부에 철골기둥과 철골보가 설치된다. 벽체 폭이 좁은 승강장 홀측(계단실과 승강로 사이부분)에는 벽체밖에 철골이 시공된다.In order to support large steel beams, steel columns and beams are installed on the outside of the walls of the rooftop. On the platform hall side (the area between the stairwell and the elevator shaft) where the wall width is narrow, steel frames are installed outside the walls.
철골구조물은 옥탑1층과 옥탑2층 2개층에 걸쳐 시공된다. 1개층씩 따로 별도로 설치될 수 있다. 옥탑 1층만 설치될 수 있다.The steel structure is constructed over two floors, the first and second floors of the rooftop. Each floor can be installed separately. It can only be installed on the first floor of the rooftop.
도 77은 철골기둥, 철골보, 큰 철골보를 함께 표시한 평면도이다. 큰 철골보는 가로 또는 세로, 가로+세로로 설치될 수 있다.Figure 77 is a plan view showing steel columns, steel beams, and large steel beams together. Large steel beams can be installed horizontally, vertically, or horizontal+vertically.
도 78은 철골기둥만을 표시한 것이다. 철골기둥이 승강로 벽체 외부에 위치한다.Fig. 78 shows only the steel columns. The steel columns are located outside the elevator shaft walls.
도 79는 철골구조물 설치 단면도 1이며, 벽체 외부에 철골기둥이 설치된다.Figure 79 is a cross-sectional drawing 1 of a steel structure installation, in which steel columns are installed on the outside of the wall.
도 82은 철골구조물 설치 단면도 2이며, 큰 철골보가 기계실 바닥아래에 승강로 벽체에 올려져 설치된다. 큰 철골보는 철골과의 연결 및 벽체 콘크리트 타설 후 높은 하중을 부담하는 강한 구조를 신속하고 안전하게 갖추게 된다.Figure 82 is a cross-sectional drawing 2 of a steel structure installation, in which a large steel beam is installed on the elevator shaft wall under the machine room floor. The large steel beam quickly and safely forms a strong structure that can bear a high load after being connected to the steel frame and pouring concrete for the wall.
도 83은 벽체두께가 200mm로 좁은 경우, 벽체밖에 철골기둥을 설치하는 것이다.Fig. 83 shows a case where the wall thickness is as narrow as 200 mm, and a steel column is installed outside the wall.
도 84는 철골기둥은 2개층 높이로 설치하는 것이다. .Fig. 84 shows that steel columns are installed two stories high.
도 85는 엘리베이터 홀 부분의 벽체밖에 설치되는 철골구조물이다. 철골기둥과 철골보는 150mm 두께이고, 벽체로 부터 150mm 이격된다. Fig. 85 is a steel structure installed outside the wall of the elevator hall section. The steel columns and beams are 150 mm thick and are spaced 150 mm from the wall.
도 86은 벽체로 부터 150mm 이격된 사이에 벽체알폼(60mm)이 설치, 해체된다.In Fig. 86, a wall foam (60 mm) is installed and removed at a distance of 150 mm from the wall.
도 87은 2개층 철골기둥에 기계실 바닥 철골보가 설치된 것이다. 엘리베이터 권상기 하부에 큰 철골보가 각각 2개씩 설치된다. 벽체로 부터 이격된 150mm 부분의 데크 플레이트를 지지하기 위하여 철골앵글(ㄱ, ㄴ형강 등) 또는 데크 받침대가 철골기둥과 철골보에 설치될 수 있다.Fig. 87 shows a machine room floor steel beam installed on a two-story steel column. Two large steel beams are installed on each of the lower sections of the elevator traction machine. In order to support the deck plate at a distance of 150 mm from the wall, steel angles (such as L-shaped steel) or deck supports can be installed on the steel columns and steel beams.
도 88은 철골보에 기계실 바닥 데크 플레이트가 설치된 것이다. 데크는 벽체라인까지 철골보로 부터 돌출되어 있다.Fig. 88 shows a machine room floor deck plate installed on a steel beam. The deck protrudes from the steel beam to the wall line.
도 89는 기계실 바닥과 천정의 전체구조 이미지이다.Figure 89 is an overall structural image of the machine room floor and ceiling.
철골구조물은 기계실 바닥까지만 시공되고, 상부는 별도의 철골구조물 또는 벽체내부의 가설구조물로 조합, 혼용으로 시공될 수 있다.The steel structure is constructed only up to the floor of the machine room, and the upper part can be constructed as a separate steel structure or a temporary structure inside the wall, combined or used together.
다음은 본 발명에 따른 철골구조물과 옥탑 골조의 시공과정을 나타낸 것이다.The following shows the construction process of the steel structure and roof frame according to the present invention.
도 90은 옥탑층 단면도이다. 기계실, 홀, 계단실로 구성된다.Fig. 90 is a cross-sectional view of the rooftop. It consists of a machine room, a hall, and a stairwell.
도 91은 설치일정이며, 최상층 아파트 세대를 타설한다. 그러면 옥상바닥이 형성된다. 타설전에 미리 철골구조물을 설치할 수 있는 앙카를 매립한다. 앙카는 옥상바닥, 홀 바닥부분에서 설치되므로 정확하고 작업이 용이하다. 벽체 내부에 있을 경우, 철근과의 간섭이 발생하는 것에 비해 간단하다.Fig. 91 is the installation schedule, and the top floor apartment is poured. Then, the rooftop is formed. Before pouring, anchors are buried so that the steel structure can be installed in advance. Since the anchors are installed on the rooftop and the floor of the hall, they are accurate and easy to work with. It is simple compared to interference with the steel bars when they are inside the wall.
도 92는 철골구조물을 옥상에서 조립하는 것이다. 철골구조물은 지상1층 또는 옥상에서 조립한다. 사전에 옥탑의 치수를 현장에서 직접 확인하고, 실제 치수에 맞게 철골 공장에서 제작하여 현장으로 운송한다. 15일 또는 1개월 정도 전에 미리 조립하여 테스트할 수 있다.Fig. 92 is assembling a steel structure on a rooftop. The steel structure is assembled on the first floor above ground or on a rooftop. The dimensions of the rooftop are checked on site in advance, and the steel frame is manufactured in a steel factory according to the actual dimensions and transported to the site. It can be assembled and tested 15 days or 1 month in advance.
또한 철골구조물을 세울 베이스 플레이트를 만든다. Additionally, a base plate is created to erect the steel structure.
도 93은 옥상 또는 지상1층에서 조립한 또는 승강로 제자리에서 직접 하나하나 설치한 철골구조물 전체이다.Figure 93 is the entire steel structure assembled on the rooftop or the first floor above ground or installed one by one directly in place in the elevator shaft.
큰 철골보가 기계실 바닥하부에 위치하고, 그 위에 기계실 바닥 데크 플레이트가 설치된다. 기계실 지붕은 홀 부분에만 데크 플레이트를 미리 설치한다. 권상기 부분은 권상기를 양중하고 난후 데크를 시공하도록 한다. 물론 권상기부분의 데크 플레이트도 미리 설치할 수 있으며, 이때 권상기는 옆의 개방된 부분(계단실 측, 창문 등)으로 양중할 수 있다.A large steel beam is located under the floor of the machine room, and the machine room floor deck plate is installed on top of it. The deck plate is installed in advance only in the hall part of the machine room roof. For the traction machine part, the deck is constructed after the traction machine is lifted. Of course, the deck plate of the traction machine part can also be installed in advance, and at this time, the traction machine can be lifted to an open part on the side (staircase side, window, etc.).
도 94는 타워크레인으로 철골구조물 전체를 양중하여 설치하는 것이다. 타워크레인의 용량과 철골구조물의 무게에 따라, 한개 또는 2개이상으로 나누어 조립하고 설치할 수 있다. Fig. 94 is a method of lifting and installing an entire steel structure using a tower crane. Depending on the capacity of the tower crane and the weight of the steel structure, it can be assembled and installed by dividing it into one or more parts.
예로 기둥은 2개층으로 한번에 조립하고 기계실 지붕의 철골보는 분리하여 설치할 수 있다.For example, columns can be assembled in two layers at once, and the steel beams of the machine room roof can be installed separately.
예로 승강로 부분과 홀측을 분리하여 조립, 설치할 수 있다.For example, the elevator shaft section and the hall side can be separated and assembled and installed.
큰 철골보는 승강로 양측벽체를 관통하여 설치된다.Large steel beams are installed through the walls on both sides of the elevator shaft.
철골구조물은 9개의 베이스 플레이트에 동시에 내려진다. 베이스 플레이트와 철골기둥은 용접 또는 볼트로 연결된다.The steel structure is lowered simultaneously onto nine base plates. The base plates and steel columns are connected by welding or bolts.
도 95는 철골구조물이 설치된 후, 옥탑 1층 골조공사를 진행하는 것이다. 옥탑 1층의 벽체 철근, 감리단 검측, 벽체 알폼을 설치한다. 이때 계단실도 신속하는 진행하여 옥탑 1층 전체를 같이 콘크리트를 타설하는 것이 유리하다.Fig. 95 shows the rooftop 1st floor frame construction after the steel structure is installed. The rooftop 1st floor wall reinforcement, inspection of the inspection team, and wall foam are installed. At this time, it is advantageous to proceed quickly with the stairwell and pour concrete for the entire rooftop 1st floor at the same time.
벽체알폼은 철골기둥과 철골보, 큰 철골보를 이용(벽체알폼의 거치 또는 위치 확인)하여 신속하고 정확하게 설치할 수 있다. Wall foam can be installed quickly and accurately using steel columns, steel beams, and large steel beams (installation or location of wall foam).
도 96은 옥탑 1층 콘크리트를 타설하는 것이다. 승강장 내부에 큰 규모의 작업발판(RCS, PCS, ACS)이 없는 경우, 벽체와 천정을 한번에 콘크리트를 타설할 수 있다. 기계실과 계단실은 같은날 같이 타설하거나 계단실을 몇일 후 나중에 타설할 수 있다.Fig. 96 is the pouring of the first floor concrete of the rooftop. If there is no large-scale work platform (RCS, PCS, ACS) inside the platform, the walls and ceiling can be poured at the same time. The machine room and the stairway can be poured on the same day, or the stairway can be poured a few days later.
도 97은 옥탑 2층 공사 착수를 나타낸다. 옥탑1층의 알폼을 해체하여 옥탑2층으로 양중 준비한다.Fig. 97 shows the start of construction on the second floor of the rooftop. The foam on the first floor of the rooftop is dismantled and preparations are made for lifting to the second floor of the rooftop.
기계실 벽체 철근을 설치한다.Install machine room wall reinforcement bars.
도 98은 기계실 벽체 알폼을 설치하는 것이다. 철골기둥과 철골보에 거치, 지지하여 알폼을 정확하고 신속하게 설치할 수 있다.Fig. 98 is for installing machine room wall foam. The foam can be installed accurately and quickly by being mounted and supported on steel columns and steel beams.
도 99는 벽체 철근과 알폼이 완료되어 건축작업자들이 내려가면, 타워크레인으로 엘리베이터 자재를 기계실 상부로 양중하여 기계실 바닥으로 수직으로 내려 놓는다. 상부에 데크 플레이트가 아직 시공되지 않아, 신속하고 정확하게 무거운 권상기를 제자리에 설치할 수 있다. Figure 99 shows that after the wall reinforcement and the ALF are completed and the construction workers have come down, the elevator materials are lifted to the top of the machine room by the tower crane and lowered vertically to the machine room floor. Since the deck plate has not yet been constructed on top, the heavy hoist can be installed in place quickly and accurately.
본 발명의 특징에 따라 철골구조물과 콘크리트에 지지되는 큰 철골보가 있어서, 기계실 바닥 양생시간을 거치지 않고도 무거운 권상기를 빠른 시간내(하루 ~이틀만)에 설치할 수 있다. According to a feature of the present invention, since there is a steel structure and a large steel beam supported on concrete, a heavy hoist can be installed in a short period of time (in just one to two days) without going through the curing time of the machine room floor.
도 100은 권상기 양중 후, 상부의 잔여 데크 플레이를 설치하는 것이다. 계단실 작업도 병행 진행한다.Fig. 100 is to install the remaining deck play on the upper part after the lifting of the hoist. Staircase work is also carried out in parallel.
상부의 잔여 데크 플레이를 설치되면, 기계실이 막히게 되므로, 전기팀이 올라와 엘리베이터를 본격적으로 설치하기 시작한다. 형판을 설치하고, 피아노선을 지하까지 내린다.Once the remaining deck play on the upper deck is installed, the machine room will be blocked, so the electrical team comes up and starts installing the elevator in earnest. They install the molds and lower the piano wire to the basement.
도 101은 기계실 및 계단실의 지붕 철근을 시공하는 것이다.Fig. 101 is the construction of roof reinforcement of the machine room and stairwell.
도 102는 옥탑 2층 벽체와 지붕 콘크리트를 반나절만에 같이 타설하는 것이다. 이로써 골조공사가 완료되었다. 기계실 벽체/지붕과 계단실은 같이 하루만에 타설하거나 계단실이 늦어지는 경우 계단실은 나중에 별도로 타설 할 수 있다.Fig. 102 shows the roof concrete and the second floor walls of the rooftop being poured together in half a day. This completes the skeletal work. The mechanical room walls/roof and the stairwell can be poured together in one day, or if the stairwell is delayed, the stairwell can be poured separately at a later date.
도 103은 엘리베이터 설치 중 또는 설치후 나중에 노출되는 철골기둥과 철골보의 일부를 해체할 수 있다. 또는 영구적으로 존치할 수 있다. 옥상에 설치된 외부 철골기둥과 보는 용접으로 절단한다.Fig. 103 can dismantle some of the steel columns and beams that are exposed during or after the elevator installation, or can be left permanently. The external steel columns and beams installed on the roof are cut by welding.
도 104는 철골구조물 일부를 해체후의 모습니다. 기계실 중앙의 기둥은 옥상 전체 슬래브를 지지해야 하므로 구조상 존치해야 할 수 있다. Fig. 104 shows the appearance after dismantling a portion of the steel structure. The column in the center of the machine room may need to be retained for structural reasons as it must support the entire rooftop slab.
도 105는 본 발명의 핵심기술인 큰 철골보의 설치에 따른 높은 하중을 신속하고 안전하게 받치는 구조개념을 나타낸 것이다.Figure 105 illustrates a structural concept for quickly and safely supporting a high load by installing a large steel beam, which is a core technology of the present invention.
기계실 바닥에 걸치는 하중의 수톤이다.This is the number of tons of load that is placed on the machine room floor.
1) 권상기 받침대 철골보 다수1) Multiple steel beams for the pedestal of the winding machine
2) 권상기 : 수톤2) Lifting weight: several tons
3) 가이드 레일 양중용 윈치 3) Winch for lifting guide rail
4) 가이드 레인 (지하부터 ~ 옥탑까지 한번에 엮어서 양중) : 수톤4) Guide lane (from basement to rooftop, lifting at once): several tons
본 발명의 특징에 따라 큰 철골보는According to the features of the present invention, a large steel beam
1) 철골기둥, 철골보와 연결1) Connection with steel columns and beams
2) 승강로 벽체에 매립되는 경우, 콘크리트에 묻히여 높은 하중 부담 가능하다.2) When embedded in the elevator shaft wall, it is buried in concrete and can support high loads.
다음은 본 발명에 따른 큰 철골보의 수직적 위치의 종류의 예시이다.The following are examples of types of vertical positions of large steel beams according to the present invention.
도 106은 큰 철골보가 기계실 바닥아래에 위치하여 기계실 바닥을 받치는 방식이다.Fig. 106 is a method in which a large steel beam is positioned under the machine room floor to support the machine room floor.
도 107은 큰 철골보가 기계실 바닥 중간부분에 위치하여 기계실 바닥에 묻히는 방식이다.Fig. 107 is a method in which a large steel beam is located in the middle of the machine room floor and buried in the machine room floor.
도 108은 큰 철골보가 기계실 바닥하부와 일치되게 설치되는 방식이다. Fig. 108 is a method in which a large steel beam is installed flush with the lower part of the machine room floor.
도 107 내지 도 108에서는 데크 플레이트는 큰 철골보의 하부 철판부분에 거치하여 설치할 수 있다. 큰 철골보 사이에 철골앵글을 연결하고 그 위에 데크 플레이트를 설치할 수도 있다.In Figures 107 and 108, the deck plate can be installed by being placed on the lower steel plate portion of a large steel beam. A steel angle can also be connected between the large steel beams and the deck plate can be installed on top of it.
다음은 본 발명에 따른 홀 및 기계실 부분에 비계를 설치하는 방식의 예시이다.The following is an example of a method for installing a ladder in a hall and machine room according to the present invention.
도 109에서 옥상바닥층에는 철골기둥 대신 비계를 설치한 후 콘크리트를 타설하고 해체할 수 있다.In Fig. 109, instead of steel columns, scaffolding can be installed on the rooftop floor, and then concrete can be poured and dismantled.
도 110에서 옥상바닥층과 홀, 기계실 내부에 철골기둥 대신 비계를 설치하고 해체할 수 있다.In Fig. 110, scaffolding can be installed and dismantled instead of steel columns on the rooftop floor, inside the hall, and inside the machine room.
비계에 철골보와 큰 철골보를 설치할 수 있다.Steel beams and large steel beams can be installed on the ladder.
도 111은 본 발명에 따른 철골구조물 설치와 옥탑골조 설치 과정이며, 도 37의 설명과 유사하다.Figure 111 shows the process of installing a steel structure and a roof frame according to the present invention, and is similar to the description of Figure 37.
다음은 철골기둥의 설치방법의 제 4 실시예이다.The following is a fourth embodiment of a method for installing a steel column.
제 4실시예는 승강로 보이드 공간 내부에 철골기둥 설치하는 방식이다.The fourth embodiment is a method of installing steel columns inside the elevator shaft void space.
도 112는 1개층에 승강로 1가 2개 있는 일반적인 아파트의 평면도이다. 노란색 부분이 엘리베이터 승강로가 있는 부분이다.Figure 112 is a floor plan of a typical apartment with two elevator shafts per floor. The yellow area is where the elevator shaft is.
도 113은 상기 승강로 #1 (코어 1번)에 설치되는 본 발명에 따른 철골구조물의 설치예이다.Fig. 113 is an example of installation of a steel structure according to the present invention installed in the elevator #1 (core 1).
승강로에 2대의 엘리베이터가 있으며, 본 발명의 핵심인 높은 하중을 부담하는 큰 철골보가 각 엘리베이터마다 2개가 설치된다.There are two elevators in the hoistway, and two large steel beams that support high loads, which are the core of the present invention, are installed in each elevator.
큰 철골보를 지지하기 위하여 승강로 내부 보이드 공간에 철골기둥과 철골보가 설치된다. 벽체 폭이 좁은 승강장 홀측(계단실과 승강로 사이부분)에는 벽체밖에 철골이 분리 시공된다.In order to support large steel beams, steel columns and beams are installed in the void space inside the elevator shaft. In the elevator hall side (the area between the stairwell and the elevator shaft) where the wall width is narrow, the steel frame is installed separately outside the wall.
철골구조물은 옥탑1층과 옥탑2층 2개층에 걸쳐 시공된다. 1개층씩 따로 별도로 설치될 수 있다. 옥탑 1층만 설치될 수 있다.The steel structure is constructed over two floors, the first and second floors of the rooftop. Each floor can be installed separately. It can only be installed on the first floor of the rooftop.
도 114은 철골기둥, 철골보, 큰 철골보를 함께 표시한 평면도이다. 큰 철골보는 가로 또는 세로, 가로+세로로 설치될 수 있다.Figure 114 is a plan view showing steel columns, steel beams, and large steel beams together. Large steel beams can be installed horizontally, vertically, or horizontal+vertically.
도 115은 철골기둥만을 표시한 것이다. 철골기둥이 승강로 보이드 공간 내부에 벽체밖에 위치한다.Figure 115 shows only the steel columns. The steel columns are located outside the walls within the elevator shaft void space.
도 116은 철골구조물 설치 단면도 1이며, 승강로 내부에 철골기둥이 설치된다.Figure 116 is a cross-sectional drawing 1 of a steel structure installation, in which steel columns are installed inside the elevator shaft.
도 117은 철골구조물 설치 단면도 2이며, 큰 철골보가 기계실 바닥아래에 승강로 벽체에 올려져 설치된다. 큰 철골보는 철골과의 연결 및 벽체 콘크리트 타설 후 높은 하중을 부담하는 강한 구조를 신속하고 안전하게 갖추게 된다.Figure 117 is a cross-sectional drawing 2 of a steel structure installation, in which a large steel beam is installed on the elevator shaft wall under the machine room floor. The large steel beam quickly and safely forms a strong structure that can bear a high load after being connected to the steel frame and pouring concrete for the wall.
도 118은 벽체두께가 200mm로 좁은 경우, 벽체밖에 철골기둥을 설치하는 것이다. 옥탑 2층에서는 중간벽체라인의 철골기둥은 벽체가 없으므로 1개로 줄어든다. Fig. 118 shows a case where the wall thickness is as narrow as 200 mm, and steel columns are installed outside the wall. On the second floor of the rooftop, the number of steel columns in the middle wall line is reduced to one because there is no wall.
도 119는 철골기둥은 2개층 높이로 설치하는 것이다. .Fig. 119 shows that steel columns are installed two stories high.
도 120은 엘리베이터 홀 부분의 벽체밖에 설치되는 철골구조물이다. 철골기둥과 철골보는 150mm 두께이고, 벽체로 부터 150mm 이격된다. 또한 승강로 내부에 승강로 벽체로 부터 떨어진 부분에 철골구조물이 설치되어 큰 철골보를 지지한다.Fig. 120 is a steel structure installed outside the wall of the elevator hall. The steel columns and beams are 150 mm thick and are spaced 150 mm from the wall. In addition, a steel structure is installed inside the hoistway away from the hoistway wall to support a large steel beam.
도 121은 홀측 벽체로 부터 150mm 이격된 사이에 벽체알폼(60mm)이 설치, 해체된다. 승강로 내부도 승강로 벽체로 부터 150mm 이격된 사이에 벽체알폼(60mm)이 설치, 해체된다. In Fig. 121, a wall foam (60 mm) is installed and removed at a distance of 150 mm from the hall side wall. Inside the hoistway, a wall foam (60 mm) is also installed and removed at a distance of 150 mm from the hoistway wall.
도 122는 2개층 철골기둥에 기계실 바닥 철골보가 설치된 것이다. 엘리베이터 권상기 하부에 큰 철골보가 각각 2개씩 설치된다. 벽체로 부터 이격된 150mm 부분의 데크 플레이트를 지지하기 위하여 철골앵글(ㄱ, ㄴ형강 등) 또는 데크 받침대가 철골기둥과 철골보에 설치될 수 있다.Fig. 122 shows a machine room floor steel beam installed on a two-story steel column. Two large steel beams are installed on each of the lower sections of the elevator traction machine. In order to support the deck plate at a distance of 150 mm from the wall, steel angles (such as L-shaped steel) or deck supports can be installed on the steel columns and steel beams.
도 123은 철골보에 기계실 바닥 데크 플레이트가 설치된 것이다. 데크 플레이트는 승강로 부분과 홀 부분이 별도로 설치되구 중간은 하부는 벽체이다. Fig. 123 shows a machine room floor deck plate installed on a steel frame. The deck plate is installed separately in the elevator shaft area and the hall area, and the middle and lower areas are walls.
도 124는 기계실 바닥과 천정의 철골보 이미지이다.Figure 124 is an image of the steel beams on the floor and ceiling of the machine room.
철골구조물은 기계실 바닥까지만 시공되고, 상부는 별도의 철골구조물 또는 벽체내부의 가설구조물로 조합, 혼용으로 시공될 수 있다.The steel structure is constructed only up to the floor of the machine room, and the upper part can be constructed as a separate steel structure or a temporary structure inside the wall, combined or used together.
도 125는 기계실 바닥과 천정의 철골보, 데크 플레이트 전체 이미지이다.Figure 125 is an overall image of the steel beams and deck plates on the machine room floor and ceiling.
다음은 본 발명에 따른 철골구조물과 옥탑 골조의 시공과정을 나타낸 것이다.The following shows the construction process of the steel structure and roof frame according to the present invention.
도 126은 옥탑층 단면도이다. 기계실, 홀, 계단실로 구성된다.Fig. 126 is a cross-sectional view of the rooftop. It consists of a machine room, a hall, and a stairwell.
도 127은 설치일정이며, 최상층 아파트 세대를 타설한다. 그러면 옥상바닥이 형성된다. 타설전에 미리 철골구조물을 설치할 수 있는 앙카를 매립한다. 앙카는 옥상바닥, 홀 바닥부분에서 설치되므로 정확하고 작업이 용이하다. 벽체 내부에 있을 경우, 철근과의 간섭이 발생하는 것에 비해 간단하다.Fig. 127 is the installation schedule, and the top floor apartment is poured. Then, the rooftop is formed. Before pouring, anchors are buried so that the steel structure can be installed in advance. Since the anchors are installed on the rooftop and the floor of the hall, they are accurate and easy to work with. It is simple compared to interference with the steel bars when they are inside the wall.
도 128은 철골구조물을 옥상에서 조립하는 것이다. 철골구조물은 지상1층 또는 옥상에서 조립한다. 사전에 옥탑의 치수를 현장에서 직접 확인하고, 실제 치수에 맞게 철골 공장에서 제작하여 현장으로 운송한다. 15일 또는 1개월 정도 전에 미리 조립하여 테스트할 수 있다.Fig. 128 is assembling a steel structure on a rooftop. The steel structure is assembled on the first floor above ground or on a rooftop. The dimensions of the rooftop are checked on site in advance, and the steel frame is manufactured in a steel factory according to the actual dimensions and transported to the site. It can be assembled and tested 15 days or 1 month in advance.
또한 철골구조물을 세울 베이스 플레이트를 만든다. Additionally, a base plate is created to erect the steel structure.
도 129는 옥상 또는 지상1층에서 조립한 또는 승강로 제자리에서 직접 하나하나 설치한 철골구조물 전체이다.Figure 129 is the entire steel structure assembled on the rooftop or the first floor above ground or installed one by one directly in place in the elevator shaft.
큰 철골보가 기계실 바닥하부에 위치하고, 그 위에 기계실 바닥 데크 플레이트가 설치된다. 기계실 지붕은 홀 부분에만 데크 플레이트를 미리 설치한다. 권상기 부분은 권상기를 양중하고 난후 데크를 시공하도록 한다. 물론 권상기부분의 데크 플레이트도 미리 설치할 수 있으며, 이때 권상기는 옆의 개방된 부분(계단실 측, 창문 등)으로 양중할 수 있다.A large steel beam is located under the floor of the machine room, and the machine room floor deck plate is installed on top of it. The deck plate is installed in advance only in the hall part of the machine room roof. For the traction machine part, the deck is constructed after the traction machine is lifted. Of course, the deck plate of the traction machine part can also be installed in advance, and at this time, the traction machine can be lifted to an open part on the side (staircase side, window, etc.).
철골구조물은 승강로 부분과 홀 부분이 분리되어 있고, 상부의 기계실 부분은 하나로 연결되어 있다.The steel structure is divided into the elevator shaft and hall sections, and the upper machine room section is connected as one.
도 130은 타워크레인으로 철골구조물 중 옥탑 1층 부분만을 양중하여 설치하는 것이다. 타워크레인의 용량과 철골구조물의 무게에 따라, 한개 또는 2개이상으로 나누어 조립하고 설치할 수 있다. Fig. 130 is a method of installing only the first floor of a steel structure by lifting it with a tower crane. Depending on the capacity of the tower crane and the weight of the steel structure, it can be assembled and installed by dividing it into one or two or more parts.
예로 기둥은 2개층으로 한번에 조립하고 기계실 지붕의 철골보는 분리하여 설치할 수 있다.For example, columns can be assembled in two layers at once, and the steel beams of the machine room roof can be installed separately.
예로 승강로 부분과 홀측을 분리하여 조립, 설치할 수 있다.For example, the elevator shaft section and the hall side can be separated and assembled and installed.
큰 철골보는 승강로 양측벽체에 걸쳐 설치된다.Large steel beams are installed across the walls on both sides of the elevator shaft.
철골구조물은 12개의 베이스 플레이트에 동시에 내려진다. 베이스 플레이트와 철골기둥은 용접 또는 볼트로 연결된다.The steel structure is lowered simultaneously onto 12 base plates. The base plates and steel columns are connected by welding or bolts.
도 131은 옥탑 1층 철골구조물이 설치된 후, 옥탑 1층 골조공사를 진행하는 것이다. 옥탑 1층의 벽체 철근, 감리단 검측, 벽체 알폼을 설치한다. 이때 계단실도 신속하는 진행하여 옥탑 1층 전체를 같이 콘크리트를 타설하는 것이 유리하다.Fig. 131 shows the rooftop 1st floor steel structure being installed, and then the rooftop 1st floor frame construction is being carried out. The rooftop 1st floor wall reinforcement, inspection of the inspection team, and wall foam are being installed. At this time, it is advantageous to proceed quickly with the stairwell and pour concrete for the entire rooftop 1st floor at the same time.
벽체알폼은 철골기둥과 철골보, 큰 철골보를 이용(벽체알폼의 거치 또는 위치 확인)하여 신속하고 정확하게 설치할 수 있다. Wall foam can be installed quickly and accurately using steel columns, steel beams, and large steel beams (installation or location of wall foam).
도 132는 옥탑 1층 콘크리트를 타설하는 것이다. 승강장 내부에 큰 규모의 작업발판(RCS, PCS, ACS)이 없는 경우, 벽체와 천정을 한번에 콘크리트를 타설할 수 있다. 기계실과 계단실은 같은날 같이 타설하거나 계단실을 몇일 후 나중에 타설할 수 있다.Fig. 132 is the pouring of the first floor concrete of the rooftop. If there is no large-scale work platform (RCS, PCS, ACS) inside the platform, the walls and ceiling can be poured at the same time. The machine room and the stairway can be poured on the same day, or the stairway can be poured a few days later.
도 133은 옥탑 2층 철골구조물을 양중하여 추가로 설치하는 것이다. 옥탑 2층 철골구조물은 기계실 벽체 내부 안쪽에 위치한다.Fig. 133 is an additional installation of a steel structure on the second floor of a rooftop. The steel structure on the second floor of the rooftop is located inside the wall of the machine room.
도 134는 옥탑 2층 공사 착수를 나타낸다. 옥탑1층의 알폼을 해체하여 옥탑2층으로 양중 준비한다. 기계실 벽체 철근을 설치한다.Fig. 134 shows the start of construction on the second floor of the rooftop. The foam on the first floor of the rooftop is dismantled and prepared for lifting to the second floor of the rooftop. The machine room wall reinforcement is installed.
도 135는 기계실 벽체 알폼을 설치하는 것이다. 철골기둥과 철골보에 거치, 지지하여 알폼을 정확하고 신속하게 설치할 수 있다.Fig. 135 is for installing machine room wall foam. The foam can be installed accurately and quickly by being mounted and supported on steel columns and steel beams.
도 136은 벽체 철근과 알폼이 완료되어 건축작업자들이 내려가면, 타워크레인으로 엘리베이터 자재를 기계실 상부로 양중하여 기계실 바닥으로 수직으로 내려 놓는다. 상부에 데크 플레이트가 아직 시공되지 않아, 신속하고 정확하게 무거운 권상기를 제자리에 설치할 수 있다. Fig. 136 shows that when the wall reinforcement and the formwork are completed and the construction workers have come down, the elevator materials are lifted to the top of the machine room by the tower crane and are lowered vertically to the machine room floor. Since the deck plate has not yet been constructed on top, the heavy hoist can be installed in place quickly and accurately.
본 발명의 특징에 따라 철골구조물과 콘크리트에 지지되는 큰 철골보가 있어서, 기계실 바닥 양생시간을 거치지 않고도 무거운 권상기를 빠른 시간내(하루 ~이틀만)에 설치할 수 있다. According to a feature of the present invention, since there is a steel structure and a large steel beam supported on concrete, a heavy hoist can be installed in a short period of time (in just one to two days) without going through the curing time of the machine room floor.
도 137는 권상기 양중 후, 상부의 잔여 데크 플레이를 설치하는 것이다. 계단실 작업도 병행 진행한다.Fig. 137 is the installation of the remaining deck play on the upper part after the lifting of the hoist. The stairwell work is also carried out in parallel.
상부의 잔여 데크 플레이를 설치되면, 기계실이 막히게 되므로, 전기팀이 올라와 엘리베이터를 본격적으로 설치하기 시작한다. 형판을 설치하고, 피아노선을 지하까지 내린다.Once the remaining deck play on the upper deck is installed, the machine room will be blocked, so the electrical team comes up and starts installing the elevator in earnest. They install the molds and lower the piano wire to the basement.
도 138은 기계실 및 계단실의 지붕 철근을 시공하는 것이다.Fig. 138 is the construction of roof reinforcement of the machine room and stairwell.
도 139는 옥탑 2층 벽체와 지붕 콘크리트를 반나절만에 같이 타설하는 것이다. 이로써 골조공사가 완료되었다. 기계실 벽체/지붕과 계단실은 같이 하루만에 타설하거나 계단실이 늦어지는 경우 계단실은 나중에 별도로 타설 할 수 있다.Fig. 139 shows the roof concrete and the second floor walls of the rooftop being poured together in half a day. This completes the skeletal work. The mechanical room walls/roof and the stairwell can be poured together in one day, or if the stairwell is delayed, the stairwell can be poured separately at a later date.
도 140은 엘리베이터 설치 중 또는 설치후 나중에 노출되는 철골기둥과 철골보의 일부를 해체할 수 있다. 또는 영구적으로 존치할 수 있다. 승강로 내부의 철골기둥과 받침보는 해체해야 한다.Fig. 140 may dismantle some of the steel columns and beams that are exposed during or after the elevator installation, or may be left permanently. Steel columns and beams inside the hoistway must be dismantled.
도 141은 철골구조물 일부를 해체후의 모습니다. 기계실 중앙의 기둥은 옥상 전체 슬래브를 지지해야 하므로 구조상 존치해야 할 수 있다. Fig. 141 shows the appearance after dismantling a portion of the steel structure. The central column of the machine room may need to be retained for structural reasons as it must support the entire rooftop slab.
도 142는 본 발명의 핵심기술인 큰 철골보의 설치에 따른 높은 하중을 신속하고 안전하게 받치는 구조개념을 나타낸 것이다.Figure 142 illustrates a structural concept for quickly and safely supporting a high load by installing a large steel beam, which is a core technology of the present invention.
기계실 바닥에 걸치는 하중의 수톤이다.This is the number of tons of load that is placed on the machine room floor.
1) 권상기 받침대 철골보 다수1) Multiple steel beams for the pedestal of the winding machine
2) 권상기 : 수톤2) Lifting weight: several tons
3) 가이드 레일 양중용 윈치 3) Winch for lifting guide rail
4) 가이드 레인 (지하부터 ~ 옥탑까지 한번에 엮어서 양중) : 수톤4) Guide lane (from basement to rooftop, lifting at once): several tons
본 발명의 특징에 따라 큰 철골보는According to the features of the present invention, a large steel beam
1) 철골기둥, 철골보와 연결1) Connection with steel columns and beams
2) 승강로 벽체에 매립되는 경우, 콘크리트에 묻히여 높은 하중 부담 가능하다.2) When embedded in the elevator shaft wall, it is buried in concrete and can support high loads.
다음은 본 발명에 따른 큰 철골보의 수직적 위치의 종류의 예시이다.The following are examples of types of vertical positions of large steel beams according to the present invention.
도 143은 큰 철골보가 기계실 바닥아래에 위치하여 기계실 바닥을 받치는 방식이다.Fig. 143 is a method in which a large steel beam is positioned beneath the machine room floor to support the machine room floor.
도 144은 큰 철골보가 기계실 바닥 중간부분에 위치하여 기계실 바닥에 묻히는 방식이다.Figure 144 is a method in which a large steel beam is located in the middle of the machine room floor and buried in the machine room floor.
도 145은 큰 철골보가 기계실 바닥하부와 일치되게 설치되는 방식이다. Fig. 145 shows a method in which a large steel beam is installed flush with the lower floor of the machine room.
도 144 내지 도 145에서는 데크 플레이트는 큰 철골보의 하부 철판부분에 거치하여 설치할 수 있다. 큰 철골보 사이에 철골앵글을 연결하고 그 위에 데크 플레이트를 설치할 수도 있다.In Figures 144 to 145, the deck plate can be installed by being placed on the lower steel plate portion of a large steel beam. A steel angle can also be connected between large steel beams and the deck plate can be installed on top of it.
다음은 본 발명에 따른 홀 및 기계실 부분에 비계를 설치하는 방식의 예시이다.The following is an example of a method for installing a ladder in a hall and machine room according to the present invention.
도 146에서 홀 부분의 철골기둥 대신 비계를 설치한 후 콘크리트를 타설하고 해체할 수 있다.In Fig. 146, after installing scaffolding instead of steel columns in the hole section, concrete can be poured and then dismantled.
도 147에서 홀 부분과 기계실 내부에 철골기둥 대신 비계를 설치하고 해체할 수 있다.In Fig. 147, scaffolding can be installed and dismantled instead of steel columns in the hall area and inside the machine room.
도 148은 본 발명에 따른 철골구조물 설치와 옥탑골조 설치 과정이며, 도 37의 설명과 유사하다.Fig. 148 shows the process of installing a steel structure and a roof frame according to the present invention, and is similar to the description of Fig. 37.
본 명세서에서는 공동주택을 대상으로 실시예를 기술하였으나, 초고층 빌딩, 오피스텔, 오피스, 병원, 학교, 판매시설 등 건물의 엘리베이터는 동일하게 철근콘크리트 구조로 되어 있는 점으로부터 다른 유형의 건물에도 동일하게 적용된다.Although this specification describes examples targeting apartment complexes, the invention is equally applicable to other types of buildings, as elevators in buildings such as high-rise buildings, officetels, offices, hospitals, schools, and retail facilities are all made of reinforced concrete structures.
상기 도 1 내지 도 148에서, 철골기둥과 철골보의 구성방법은 조합, 혼용하여 사용할 수 있다. 아파트 옥탑의 구조가 다양하므로, 현지 사정에 맞추어 안전하고 유리한 방법을 조합하여 사용하도록 한다. 철골기둥의 위치나 철골보의 연결, 위치를 변형하여 시공하는 것은 본 발명의 사상의 범위내에 있는 것이다. 본 발명의 핵심사상은 수톤의 하중을 지탱하는 승강로 내부의 철골보를 신속 안전 정밀하게 시공하여 엘리베이터 공사의 조기 착수(최상층 타설 후 6일~7일만에) 및 가이드 레일 양중 기간을 단축하여 후속공사의 앞당김과 그에 따른 전체 공사기간을 단축하는 것이다.In the above drawings 1 to 148, the methods of constructing steel columns and steel beams can be combined or used interchangeably. Since the structure of the apartment rooftop is diverse, a safe and advantageous method is combined and used according to the local conditions. It is within the scope of the idea of the present invention to change the position of the steel columns or the connection or position of the steel beams for construction. The core idea of the present invention is to quickly, safely, and precisely construct the steel beams inside the hoistway supporting a load of several tons, thereby enabling early commencement of elevator construction (only 6 to 7 days after pouring the top floor) and shortening the guide rail lifting period, thereby advancing the follow-up construction and shortening the entire construction period accordingly.
다음은 철골기둥의 설치방법의 제 5 실시예이다.The following is a fifth embodiment of a method for installing a steel column.
제 5실시예는 철골기둥의 개수를 최소화하는 것이다. 권상기 하부에 큰 하중이 걸리는 점에 따라 권상기 하부에 2개의 철골기둥과 큰 철골보를 설치하는 방식이다. 승강로 코너부에는 설치하지 않는다. 그에 따라 철골기둥과 보가 축소됨에 따라 철골부재들을 고정하고 데크 플레이트를 안전하게 거치하기 위하여 T앵글 또는 L앵글 등을 큰 철골보 상부에 연결하여 고정한다. 상기 앵글은 기계실 바닥 콘크리트에 묻히는 것이 특징이다. 즉 앵글은 1) 큰 철골보의 고정, 2) 데크 플레이트의 고정, 3) 기계실 바닥 콘크리트에 묻힌다. 큰 철골보와 앵글은 엘리베이터 슬리브(형판 구멍)을 피해 설계 및 설치하도록 한다.The fifth embodiment is to minimize the number of steel columns. Since a large load is applied to the lower part of the traction machine, two steel columns and a large steel beam are installed under the traction machine. They are not installed at the corners of the hoistway. Accordingly, as the steel columns and beams are reduced, a T-angle or L-angle is connected and fixed to the upper part of the large steel beam in order to fix the steel members and safely place the deck plate. The angle is characterized by being buried in the concrete of the machine room floor. That is, the angle 1) fixes the large steel beam, 2) fixes the deck plate, and 3) is buried in the concrete of the machine room floor. The large steel beam and angle are designed and installed so as to avoid the elevator sleeve (pattern hole).
도 149는승강로의 벽체에 철골기둥이 설치되는데, 코너부분에 설치되는 것을 삭제하고, 권상기 받침 철골보 하부부분에 설치한다. 중앙부에 한개를 설치하여, 권상기 2대의 승강로에 총 5개의 철골기둥을 설치한다. 철골기둥은 옥탑 1층 벽체부분(내부, 외부, 인접)이며, 옥상바닥에서 기계실 바닥까지 이다.In Fig. 149, steel columns are installed on the walls of the elevator shaft. Those installed at the corners are deleted, and those installed at the lower part of the steel beam supporting the elevator shaft are installed. One is installed at the center, and a total of five steel columns are installed in the elevator shaft for two elevators. The steel columns are on the first floor of the rooftop (inside, outside, and adjacent), and from the rooftop floor to the machine room floor.
도 150은 승강로 벽체내부의 권상기 하부의 철골기둥과 철골보이다. 벽체는 최소 200mm이며, 300mm, 500mm정도이다. 철골보와 벽체끝 사이에는 철근이 설치된다.Fig. 150 shows the steel columns and beams at the bottom of the hoistway wall. The wall is at least 200 mm thick, and is approximately 300 mm or 500 mm thick. Reinforcing bars are installed between the steel beams and the ends of the wall.
도 151은 철골기둥이 설치된 상태를 나타낸다. 10개의 철골기둥이 승강로 벽체에 세워진다. 높이는 옥탑 1층 높이이며, 예로 2.8m이다. Figure 151 shows the state in which steel columns are installed. Ten steel columns are erected on the elevator shaft wall. The height is the height of the first floor of the rooftop, for example, 2.8 m.
도 152는 철골기둥이 홀측의 옥상바닥위에 세워진 상태이며, 홀측 벽체로 부터 밖으로 나와있는 예이다. 홀측 벽체(승강문 측)는 일반적으로 200mm~300mm이므로, 필요에 따라 벽체 밖에 세워질 수 있다. 영구 존치 또는 나중에 해체하도록 한다.Fig. 152 is an example of a steel column erected on the rooftop floor of the hall side, and extending out from the hall side wall. The hall side wall (door side) is generally 200mm to 300mm, so it can be erected outside the wall as needed. It can be permanently maintained or dismantled later.
도 153은 철골기둥간을 연결하는 철골보가 설치된 상태를 나타낸 것이다.Figure 153 shows the state in which steel beams connecting steel columns are installed.
도 154는 큰 철골보가 설치된 것이다. 큰 철골보는 권상기 하부에 설치되어 큰 하중을 부담하도록 한다.Fig. 154 shows a large steel beam installed. The large steel beam is installed at the bottom of the winding machine to support a large load.
도 155는 큰 철골보 상부에 T형강이 설치된 것이다. Fig. 155 shows a T-beam installed on top of a large steel beam.
본 발명에 따른 T형강은The T-shaped steel according to the present invention
1) 큰 철골보가 옆으로 이동하지 않도록 고정(용접 또는 볼팅)1) Fix (weld or bolt) the large steel beam so that it does not move sideways.
2) 기계실 바닥 데크 플레이트를 거치2) Install the machine room floor deck plate
3) T형강은 기계실 바닥 콘크리트에 묻히어 강한 구조물을 형성3) T-shaped steel is buried in the concrete of the machine room floor to form a strong structure.
4) 코어부 철골기둥 및 연결되는 철골보들의 삭제4) Deletion of core steel columns and connecting steel beams
하는 특징이 갖는다.It has the characteristics of doing so.
즉, T형강은 작고 비용이 저렴하지만 다기능을 갖고, 철골부재수를 줄인다.That is, T-beams are small and inexpensive, but they are multifunctional and reduce the number of steel members.
앵글은 T형강, ㄱ앵글, L앵글, ㄷ채널 등 다양한 형태를 포함한다. Angles include various shapes such as T-beams, L-angles, L-angles, and D-channels.
도 156은 기계실 바닥의 승강로 벽체를 나타낸 것이다.Figure 156 shows the elevator shaft wall on the machine room floor.
T형강은 T-beam steel
1) 큰 철골보 부분에만 설치1) Installed only on large steel beam sections
2) 승강로 벽체까지 연장 설치2) Extension installation to the elevator shaft wall
할 수 있다.You can do it.
1) 큰 철골보 부분에만 설치되는 경우, 데크 플레이트는 승강로 내부 벽체 알폼에 단부를 거치하도록 한다.1) When installed only on large steel beam sections, the deck plate shall be installed with its end resting on the inner wall foam of the elevator shaft.
도 157은 큰 철골보를 나타낸 것이다.Fig. 157 shows a large steel beam.
예로 큰 철골보는 높이 400mm, 폭 200mm와 같은 H형강이다.For example, a large steel beam is an H-beam with a height of 400 mm and a width of 200 mm.
큰 철골보는 폭 200mm이상인 경우에도 벽체에 속하지 않으므로 크기가 클 수록 유리하다.Large steel beams are not considered walls even if they are wider than 200 mm, so the larger the size, the more advantageous it is.
도 158은 T형강을 나타낸 것이다. 일반적인 데크 플레이트의 폭이 600mm(60cm)이므로 60cm간격으로 설치될 수 있다.Fig. 158 shows a T-beam. Since the width of a typical deck plate is 600 mm (60 cm), it can be installed at 60 cm intervals.
승강로 5m정도로 길이가 길 경우에는 2개로 나누어 설치하도록 한다.If the elevator shaft is long, such as about 5 m, it should be installed in two parts.
도 159는 T형강위에 기계실 바닥 데크 플레이트가 올려진 것이며 용접(데크 용접)하는 방법을 포함한다.Fig. 159 shows a machine room floor deck plate placed on a T-shaped steel plate and includes a method of welding (deck welding).
데크 상부의 철근이 설치될 수 있도록 높이가 낮은 T형강 또는 형강의 상부 올라온 부분을 일부씩 절단하여 가로 철근이 지나가도록 할 수 있다.The upper raised portion of the short T-beam or section can be cut to allow passage of transverse reinforcing bars to allow for installation of reinforcing bars on the upper deck.
도 160은 승강로 코어부분의 상태이다. 철골기둥에 큰 철골보가 연결되고, 그 위에 T형강이 설치되고, 그 위에 데크 플레이트, 그리고 철근 및 콘크리트, 권상기 순서로 시공된다.Figure 160 shows the status of the core section of the elevator shaft. A large steel beam is connected to a steel column, a T-shaped steel is installed on top of it, a deck plate is installed on top of it, and then steel and concrete, and a traction machine are constructed in that order.
도 161은 기계실 바닥 데크 플레이트가 설치된 것이다. 데크 플레이트는 T형강과 큰 철골보위에 올려지고 용접 등으로 고정된다.Fig. 161 shows the machine room floor deck plate installed. The deck plate is placed on T-shaped steel and large steel beams and fixed by welding, etc.
도 162는 승강로 벽체 부분에 L형강이 추가로 설치된 것이다. L형강은 데크 플레이트가 벽체 부분에서 지지되도록 하는 기능을 한다.Fig. 162 shows an L-shaped steel member additionally installed on the wall portion of the elevator shaft. The L-shaped steel member functions to support the deck plate on the wall portion.
이상과 같이, 승강로 코너부분과 측벽 부분에 철골기둥과 철골보를 설치하지 않고도, 중앙부분에만 철골구조물을 설치하여 구조적으로 안전한 방법으로 권상기 하중을 부담하는 철골구조물을 고안하였다. As described above, a steel structure was designed to support the load of a hoisting machine in a structurally safe manner by installing the steel structure only in the central portion without installing steel columns and beams in the corners and side walls of the elevator shaft.
여기서 큰 철골보 상부에 설치되는 형강 또는 앵글의 고안을 통해, 후속작업을 간단하고 신속하고 안전하게 할 수 있게 되었다.Here, the design of the profile or angle installed on top of the large steel beam made subsequent work simple, quick, and safe.
다음은 철골기둥의 설치방법의 제 6 실시예이다.The following is a sixth embodiment of a method for installing a steel column.
제 6실시예는 철골보의 형상을 가벼운 철골인 ㄱ형강, T형강, ㄷ형강, C채널로 구성하는 것이다.In the sixth embodiment, the shape of the steel beam is composed of light steel frames such as L-shaped steel, T-shaped steel, T-shaped steel, and C-channel.
일반적으로 H형강이 주로 사용되고 있으나, H형강은 재료비가 높고 설치비도 높다.Generally, H-beams are mainly used, but H-beams have high material costs and high installation costs.
2,000가구를 넘는 대형아파트 단지의 엘리베이터 옥탑은 동당 2개씩 배치되어 수십개가 된다.In large apartment complexes with over 2,000 households, there are dozens of elevators, with two per building.
이들 전체에 들어가는 철골과 철골종류에 따른 비용을 감안시, 데크 플레이트를 받치는 부분에 가벼운 철골을 사용하는 것이 유리하다. Considering the cost of the steel frame and the type of steel that goes into all of these, it is advantageous to use light steel for the part that supports the deck plate.
단, 가벼운 철골은 변형이 발생할 수 있으므로 수직 또는 수평 가새(경사재)로 보강할 필요가 있다.However, light steel frames may become deformed, so they need to be reinforced with vertical or horizontal braces (sloping members).
가벼운 철골은 신속하고 낮은 비용으로 옥탑 슬래브 골조를 시공하는 효과를 갖는다.Lightweight steel frames allow for the construction of rooftop slab framing at a fast and low cost.
도 163은 옥탑1층 기계실 바닥을 나타낸 것이다.Figure 163 shows the floor of the machine room on the first floor of the rooftop.
2대의 권상기가 위치하고 그 하부에는 큰 철골보가 설치된다.Two lifting machines are positioned, and a large steel beam is installed underneath them.
이를 위해 철골기둥이 승강로 벽체 내부 또는 외부에 설치된다.For this purpose, steel columns are installed inside or outside the elevator shaft walls.
기계실 바닥 테두리 철골보는 큰 철골보를 지지하가 위하여 큰 규격이 사용된다.The machine room floor frame steel beams are of large size to support large steel beams.
도 164는 옥탑2층의 기계실 벽체와 지붕이 추가된 것이다.Fig. 164 shows the mechanical room walls and roof on the second floor of the attic with the addition.
옥탑2층은 기계실 벽체와 지붕만 있는 것으로, 큰 하중이 없다.The second floor of the rooftop has only the machine room walls and roof, so there is no significant load.
따라서 기계실 지붕의 데크 플레이트와 철근, 콘크리트 하중만 견디도록 기계실 지붕 철골보를 구성하는 것이 경제적이다.Therefore, it is economical to construct the machine room roof steel frame to support only the deck plate, rebar, and concrete loads of the machine room roof.
이를 위해 기계실 지붕의 철골구조는 가벼운 철골인 ㄱ형강, T형강, ㄷ형강, C채널로 구성하도록 한다.To this end, the steel structure of the machine room roof is to be composed of light steel frames such as L-shaped steel, T-shaped steel, T-shaped steel, and C-channel.
도 165는 옥탑2층 기계실 벽체에 가새(경사재)가 추가된 것이다.Fig. 165 shows the addition of braces (slopes) to the wall of the machine room on the second floor of the rooftop.
경사재는 옥탑2층 지붕이 가벼운 철골인 ㄱ형강, T형강, ㄷ형강, C채널로 구성된 것을 보강하기 위해 설치된다.The sloping beams are installed to reinforce the roof of the second floor of the attic, which is made up of light steel frames such as L-shaped steel, T-shaped steel, T-shaped steel, and C-channel.
가새(경사재)도 가벼운 철골인 ㄱ형강, T형강, ㄷ형강, C채널로 구성된다.The braces (slope members) are also made of light steel frames such as L-shaped steel, T-shaped steel, T-shaped steel, and C-channel.
도 166은 옥탑2층 기계실 벽체 철골기둥과 지붕 철골구조를 나타낸 것이다.Figure 166 shows the steel columns of the wall of the machine room on the second floor of the roof and the steel structure of the roof.
도 167은 옥탑2층 기계실 벽체의 가새이며, 기둥의 중간, 보의 1/3지점에 가새가 연결되는 구조이다.Fig. 167 is a brace for the wall of the machine room on the second floor of the rooftop. It is a structure in which the brace is connected to the middle of the column and 1/3 of the way up the beam.
도 168은 옥탑2층 기계실 벽체의 가새이며, 기둥의 하부, 보의 중간지점에 가새가 연결되는 구조이다.Fig. 168 is a brace for the wall of the machine room on the second floor of the rooftop. It is a structure in which the brace is connected to the lower part of the column and the middle point of the beam.
도 169는 옥탑철골구조물을 지지하기 위하여, 옥상바닥에 앙카를 묻고, 옥탑2층 지붕에 철선, 와이어로 연결하여 고정한 것이다.Fig. 169 shows an example of anchors buried in the rooftop floor to support the rooftop steel structure, which are then fixed to the roof of the second floor of the rooftop using steel wires.
옥탑철골구조물에 콘크리트가 타설되기 전에는 바람에 의한 영향을 받을 수 있다. 이에 대응하기 위하여 와이어로 고정한다.Before the concrete is poured into the rooftop steel structure, it may be affected by wind. To cope with this, it is fixed with wire.
도 170은 기계실 지붕에 데크 플레이트가 설치되고, 와이어로 옥상바닥에 고정된 것을 나타낸 것이다.Fig. 170 shows a deck plate installed on the roof of a machine room and secured to the rooftop with wires.
도 171은 옥탑2층 기계실 지붕 철골구조의 상세를 나타낸 것이며, 가벼운 철골인 ㄱ형강이 사용된 것이다.Figure 171 shows the details of the steel structure of the roof of the machine room on the second floor of the attic. Light L-shaped steel was used for the steel structure.
ㄱ형강은 H철골기둥의 수직면에 볼트 또는 용접으로 연결된다.The L-shaped steel is connected to the vertical surface of the H-shaped steel column by bolts or welding.
도 172는도 171에서 지붕 철골보 ㄱ형강의 단면을 나타낸 것이다.Figure 172 shows a cross-section of the L-shaped steel roof steel beam in Figure 171.
지붕 철골보에는 기계실 지붕 데크 플레이트가 거치 설치된다.The machine room roof deck plate is installed on the roof steel beam.
도 173은 지붕 철골보 ㄱ형강만을 나타낸 것이다.Fig. 173 shows only the L-shaped steel of the roof steel frame.
도 174는 지붕 철골보를 T형강을 사용한 것이다.Fig. 174 shows a roof steel beam made of T-shaped steel.
ㄱ형강을 90돌 돌려 H철골기둥의 수직면에 볼트 또는 용접으로 연결된다.The L-shaped steel is turned 90 degrees and connected to the vertical surface of the H-shaped steel column by bolts or welding.
도 175는 지붕 철골보를 ㄷ형강을 사용한 것이다.Fig. 175 shows a roof steel beam made of T-shaped steel.
ㄷ형강의 H철골기둥의 수직면에 볼트 또는 용접으로 연결된다.It is connected to the vertical surface of the H-shaped steel column by bolts or welding.
이상과 같이 경량철골인 ㄱ형강, T형강, ㄷ형강, C채널 부재는 공사비가 저렴한 것을 목적으로 한다.As described above, the lightweight steel frame materials such as L-shaped steel, T-shaped steel, T-shaped steel, and C-channel are intended to have low construction costs.
다음은 옥탑의 외벽 거푸집 시공방법의 제 7 실시예이다.The following is the seventh embodiment of a method for constructing the outer wall formwork of a rooftop.
아파트 옥탑1층과 2층의 외벽중 일부는 지상1층부터 벽체형틀로서 갱폼을 사용한다.Some of the exterior walls of the first and second floors of the apartment use gang form as wall frames starting from the first floor above ground.
그러나 내부(엘리베이터 홀, 세대측 벽면)는 알폼을 사용한다.However, the interior (elevator hall, walls on the household side) uses Alform.
옥탑1층은 옥상바닥에서 알폼을 설치한다.On the first floor of the rooftop, Alform is installed on the rooftop floor.
옥탑2층은 바닥이 없고 층고가 2개층으로 높으므로 비계를 설치한 후, 그 작업대 위에서 알폼을 설치해야 한다.The second floor of the rooftop has no floor and the ceiling height is two stories high, so after installing the ladder, the foam must be installed on the workbench.
옥탑2층 벽면에 알폼을 설치하는 것이 따라서 시간이 많이 소요된다. 또 나중에 해체해야 한다.Therefore, it takes a lot of time to install the foam on the wall of the second floor of the rooftop. It also has to be dismantled later.
즉 알폼을 조각조각 높은 곳에 설치하는 작업은 안전위험도 높다.In other words, the work of installing Alfom piece by piece in high places carries a high safety risk.
따라서 외벽의 알폼 작업을 대체할 새로운 공사방법이 필요하다.Therefore, a new construction method is needed to replace the foam work on the exterior walls.
이에 본 발명에서는 알폼 대신 갱폼을 사용하기로 한다.Accordingly, in the present invention, gangform is used instead of alform.
그러나 옥탑2개층을 위하여 새로운 알폼을 공장 제작하여 현장으로 운송한 후, 옥탑에 설치하고 2개층 사용 후 폐기하는 것은 현실적이지 않다.However, it is not realistic to manufacture new foam for the two rooftop floors in a factory, transport it to the site, install it on the rooftop, and then discard it after use for the two floors.
알폼 작업에 비해 비용이 너무 많이 들어가기 때문이다.Because it costs too much compared to the foam work.
한편, 기준층(1층~49층 등)의 벽체에 알폼이 들어가는데, 세대에는 창문이 있어 갱폼(큰 철판)에 창문 구멍이 나 있고, 측벽은 창문이 없으므로 구멍이 없는 큰 철판의 갱폼이 사용되고 있다.Meanwhile, the walls of the standard floors (1st to 49th floors, etc.) are made of Alform. Since each unit has windows, there are window holes in the gangform (large iron plate), and since the side walls do not have windows, large iron plate gangform without holes is used.
이러한 점에 착안하여 본 발명에서는, 최상층(49층) 타설 후 측벽의 구멍이 없는 큰 철판의 갱폼을 옥탑의 외벽 거푸집으로 활용하도록 한다.Considering this point, in the present invention, a large steel plate gang form without holes in the side walls is used as the formwork for the outer wall of the rooftop after pouring the top floor (49th floor).
일반적으로 아파트 측벽은 2개 또는 그 이상이다. 따라서 4면의 옥탑 중 일부는 원래부터 갱폼이 붙어 있었고 옥상부분의 2개 내지 3개의 외벽에 측벽의 갱폼을 거푸집으로 사용한다. 엘리베이터 부분의 옥탑은 창문이 1개(기계실 환기용)만 있다.Generally, there are two or more side walls of an apartment. Therefore, some of the four-sided rooftops originally had gang forms attached, and the side walls' gang forms are used as formwork for two or three outer walls of the rooftop. The rooftop of the elevator section has only one window (for ventilation of the machine room).
옥탑 1층의 천정인 기계실 바닥에 기준층과 마찬가지로 갱폼 앙카볼트를 매립한 후, 타설 후 다음날 측벽에서 가져온 측벽 갱폼을 인상하도록 한다.After installing gangform anchor bolts on the ceiling of the first floor of the rooftop machine room, just like on the standard floor, the side wall gangform brought from the side wall is raised the next day after pouring.
따라서 옥탑의 4면이 갱폼으로 사용되어 신속하고 저렴하게 공사를 진행할 수 있다.Therefore, the four sides of the rooftop are used as gang forms, allowing construction to proceed quickly and inexpensively.
[측벽 갱폼의 규격][Side wall gang form specifications]
예로 아파트 평면에서 측벽1의 길이는 11.8m이다.For example, the length of side wall 1 in an apartment plan is 11.8 m.
측벽 갱폼은 2개로 제작하되 한개는 크게, 한개는 작게하며, 높이는 3,000mm이다.. 2개로 나누는 이유는 1개로 하면 너무 커서 타워크레인으로 들수 없기 때문이다.The side wall gang form is manufactured in two pieces, one large and one small, with a height of 3,000 mm. The reason for dividing it into two pieces is that if it were made in one piece, it would be too large to be lifted by a tower crane.
측벽2의 길이는 10.3m이다. 크기는 한개이고, 높이는 3,000mm이다. 측벽2의 갱폼은 한개로써 타워크레인으로 한번에 양중한다. 일반적으로 큰 갱폼의 무게는 3.5톤 내지 4톤이다.The length of side wall 2 is 10.3m. It is one size and 3,000mm high. The gang form of side wall 2 is one piece and is lifted at once by a tower crane. Generally, the weight of a large gang form is 3.5 to 4 tons.
아파트 층고는 일반적으로 2850mm이다.The apartment floor height is generally 2850mm.
측벽1 갱폼 1 = 길이 7,725mm (7.7m) , 높이 3,000mm (3.0m) (큰 것) Sidewall 1 Gangform 1 = Length 7,725mm (7.7m), Height 3,000mm (3.0m) (large)
측벽1 갱폼 2 = 길이 4,165mm (4.1m), 높이 3,000mm (3.0m) (작은 것) (2개로 구성)Sidewall 1 Gangform 2 = Length 4,165mm (4.1m), Height 3,000mm (3.0m) (small) (consists of 2 pieces)
측벽2 갱폼 = 길이 10,370mm (10.3m), 높이 3,000mm (3.0m)(1개로 구성)Sidewall 2 Gangform = Length 10,370mm (10.3m), Height 3,000mm (3.0m) (Consists of 1 piece)
측벽2 갱폼의 철판의 두께는 3.5mm이다.The thickness of the steel plate of the side wall 2 gangform is 3.5 mm.
[갱폼을 세로로 세워서 사용][Use the gang form vertically]
갱폼은 세로로 세워서 2개층으로 사용할 수 있다.Gangform can be used vertically in two layers.
측벽1 갱폼 1을 세로로 세우면 = 높이 7,725mm (7.7m) , 길이 3,000mm (3.0m) (큰 것)가 된다.If you erect sidewall 1 gangform 1 vertically = height 7,725mm (7.7m), length 3,000mm (3.0m) (large one).
높이 7,725mm는 옥탑 1층과 옥탑2층을 한번에 시공할 수 있다.The height of 7,725mm allows construction of the first and second floors of the rooftop at the same time.
갱폼을 옥탑2층으로 인상하지 않아도 되고, 옥상바닥에 안정하게 고정할 수 있다.There is no need to raise the gang form to the second floor of the rooftop, and it can be stably fixed to the rooftop floor.
옥탑 1층이 신속히 타설되므로, 옥탑2층의 노출되는 부분은 적어 바람에 의한 영향도 줄어든다.Since the first floor of the rooftop is quickly poured, the exposed area of the second floor of the rooftop is small, and the impact of the wind is also reduced.
만약, 바람이 강하게 부는 경우에는 갱폼을 옥상바닥에 눕히면 된다.If the wind is strong, you can lay the gang form down on the roof floor.
[측벽 갱폼의 수량][Quantity of side wall gang forms]
아파트 단지는 2동, 4동, 10개동 이상으로 구성된다. 각 동의 층수와 완료시점이 각기 다르다.Apartment complexes consist of 2, 4, or 10 or more buildings. Each building has a different number of floors and completion date.
따라서 측벽 갱폼의 사용이 완료되는 시점도 다르므로, 측벽 갱폼을 저층동에서 사용하고 고층동으로 이동사용하면 된다.Therefore, the timing of completion of use of the side wall gang form is different, so the side wall gang form can be used in low-rise buildings and then moved to high-rise buildings.
따라서 측벽 갱폼의 숫자는 부족하지 않을 수 있고, 옥탑에 즉각적으로 사용할 수 있다.Therefore, the number of side wall gang forms may not be insufficient and can be used immediately on the roof.
[갱폼 상부 안전난간대][Gangform upper safety railing]
갱폼 상부에는 안전난간대가 설치되어 있으므로, 이것을 그대로 사용할 수 있다. 그러면 옥탑시공시 별도로 안전난간대를 설치할 필요가 없다.Since a safety railing is installed on the top of the gangform, it can be used as is. Then, there is no need to install a separate safety railing when constructing the rooftop.
[옥탑의 층고가 갱폼 보다 높을 경우][If the rooftop floor height is higher than the gang form]
갱폼은 아파트 세대 높이인 2.85m보다 약간 높은 3.0m이다. The gang form is 3.0m high, slightly higher than the apartment unit height of 2.85m.
1) 옥탑 1층이 3.0m를 넘는경우에는, 갱폼 하부 또는 상부에 알폼을 추가로 설치한다. 1) If the first floor of the rooftop exceeds 3.0m, additional alform is installed on the bottom or top of the gangform.
2) 또는 벽체는 2회로 나누어 타설한다. 예로 옥탑1층이 4.5m인 경우, 벽체 1차 콘크리트 타설 후 갱폼을 상승시키고, 벽체 2차를 타설할 수 있다.2) Or, the wall is poured in two stages. For example, if the first floor of the rooftop is 4.5m, the gang form can be raised after the first concrete pouring of the wall, and the second concrete pouring of the wall can be done.
3) 또는 갱폼을 세로로 세워서 타설할 수 있다. 3) Or, the gangform can be placed vertically and poured.
4) 또는 갱폼2개를 2개층으로 쌓아서 시공한다. 측벽 갱폼의 수량이 부족할 경우에는, 창문이 있는 세대의 갱품에 창문 개구부를 다른 갱폼의 철판이나 합판으로 막아서 사용하도록 한다.4) Or, construct by stacking two gang forms in two layers. If the number of side wall gang forms is insufficient, use the iron plate or plywood of another gang form to block the window openings in the gang forms of the unit with windows.
[측벽 갱폼의 공사순서][Construction sequence of side wall gang form]
측벽갱폼을 재활용하는 옥탑공사의 공사순서는 다음과 같다.The construction sequence for the rooftop construction using the side wall gang form is as follows.
1) 최상층(예로 49층) 옥상의 옥탑 벽체라인에 측벽 갱폼지지용 철근 토막, 기타 앙카와 함께 일정거리에서 와이어로 지탱하기 위한 와이어 앙카(2개 거리, 다수) 를 매립한다.1) On the rooftop of the top floor (e.g. 49th floor), wire anchors (2 at a distance, multiple) are embedded to support the side wall gang form support rebar pieces and other anchors at a certain distance with wire.
철근 토막 또는 앙카는 승강로 벽체의 외부라인에 설치하고, 코어벽체 안쪽에도 설치할 수 있다.Rebar pieces or anchors can be installed on the outer line of the elevator shaft wall, and can also be installed on the inner side of the core wall.
측벽 갱폼은 단면상 옥상바닥의 좌우에 올라온 철근 토막, 앙카에 좌우가 고정되어 좌우로 움직이지 않도록 한다.The side wall gang form is made up of steel pieces on the left and right sides of the rooftop in cross-section, and is fixed to anchors on both sides to prevent it from moving left and right.
2) 최상층 콘크리트(벽체 및 옥상바닥)를 타설한다.2) Pour the top concrete (walls and rooftop floor).
3) 다음날 옥탑1층 승강로 벽체 내부 또는 벽체인접 또는 벽체외부에 철골기둥과 철골보로 구성된 기계실 바닥 무지주 공법용 철골구조물을 설치한다.3) The next day, a steel structure for the machine room floor without columns, consisting of steel columns and steel beams, is installed inside the wall of the first floor elevator shaft, adjacent to the wall, or outside the wall.
최상층 타설 다음날 측벽 갱폼을 상승하고, 파라펫(난간) 철근 및 합판 후 측벽을 포함한 일정부분의 파라셋 콘크리트를 타설한다.The day after the top floor is poured, the side wall gang forms are raised, and after the parapet (railing) reinforcement and plywood are laid, a certain portion of parapet concrete including the side walls is poured.
4) 그 다음날 측벽갱폼을 해체하여 옥상 바닥 또는 지상 1층으로 내린다. 갱폼하부의 작업발판(1개층 내지 2개층)을 해체한다.4) The next day, dismantle the side wall gang form and lower it to the rooftop or the first floor. Dismantle the working platform (one or two floors) under the gang form.
갱폼에 붙은 벽체의 모양을 내는 막대 철판을 제거(용접으로 붙인 것을 떼어냄)하여 갱폼 철판을 매끄럽게 한다. 또는 기존의 벽체 막대 철판을 그대로 사용한다.Remove the bar sheet metal that forms the shape of the wall attached to the gang form (by removing the welded one) and smooth the gang form sheet metal. Or, use the existing wall bar sheet metal as is.
갱폼이 옥탑 규모에 너무 큰 경우에는 일부를 절단한다.If the gang form is too large for the rooftop, cut off a portion of it.
5) 옥탑 1층 벽체 철근을 시공한다. 옥상바닥에 서서 측벽 갱폼 부분의 철근을 시공한다. 5) Install the reinforcement bars on the first floor of the rooftop. Stand on the rooftop floor and install the reinforcement bars on the side wall gang form.
6) 갱폼이 세워질 옥상바닥에 각재(사각 목재)를 설치한다. 그 위에 갱폼에 세워지도록 한다.6) Install lumber (square wood) on the rooftop where the gang form will be erected. Place the gang form on top of it.
7) 측벽 갱폼을 옥탑 1층 벽체 라인에 맞게 옥상바닥에 수직으로 세운다. 이때 옥상바닥에 미리 매립한 철근 토막 또는 앙카를 이용하여 측벽 갱폼이 외부쪽으로 이동하지 않도록 고정한다. 또한 지지막대를 이용하여 갱폼이 옥상측으로 쓰러지지 않도록 한다.7) Install the side wall gang form vertically on the rooftop floor in line with the rooftop 1st floor wall line. At this time, use the pre-embedded rebar pieces or anchors on the rooftop floor to secure the side wall gang form so that it does not move outward. Also, use the support bars to prevent the gang form from collapsing toward the rooftop.
8) 또한 갱품 상부 고리에 와이어를 이용하여 옥상바닥의 와이어 앙카1에 연결하고 고정한다.8) Also, connect and secure the wire to the wire anchor 1 on the rooftop using a wire on the upper ring of the gang product.
바람에 측벽 갱폼이 날리거나 이동하지 않도록 와이어로 고정한다.Secure the side wall gangforms with wire to prevent them from being blown away or moved by the wind.
여기서, 옥탑1층 측벽 갱폼이나 벽체철근 중 어는 것을 먼저 해도 상관없다. 갱폼을 세운후 안쪽에서 철근을 시공할 수도 있다. 같이 동시에 시공할 수도 있다. 철근을 완료한 후 갱폼을 설치할 수도 있다. Here, it doesn't matter which one of the side wall gang forms or the wall reinforcement is done first on the first floor of the rooftop. After the gang form is erected, the reinforcement can be installed from the inside. They can be installed at the same time. After the reinforcement is completed, the gang form can be installed.
감리단의 철근 검측이 용이하도록 철근 설치, 감리검측, 갱폼설치가 합리적이다.It is reasonable to install rebar, inspect, and install gang forms to facilitate the inspection of rebar by the supervisory team.
그러나 사정상 갱폼을 먼저 설치할 수도 있다.However, depending on circumstances, the gang form may be installed first.
9) 승강로 내부의 벽체철근과 알폼을 설치한다.9) Install wall reinforcement bars and foam inside the elevator shaft.
10) 기계실 바닥에 형틀(데크 플레이트 또는 알폼, 유로폼)을 설치한 후 바닥철근을 설치한다.10) After installing the formwork (deck plate or Alform, Euroform) on the machine room floor, install the floor reinforcement bars.
11) 기계실 바닥에 측벽 갱폼의 지지용 갱폼용 앙카 볼트를 매립한다.11) Embed anchor bolts for supporting gang forms on the machine room floor.
12) 옥탑1층 벽체 또는 천정까지 콘크리트를 타설한다. 12) Pour concrete up to the walls or ceiling of the first floor.
13) 옥탑1층이 완성되면, 옥탑2층 골조를 착수하며, 측벽 갱폼을 먼저 인상한다.13) Once the first floor of the rooftop is completed, the second floor frame is started, and the side wall gang forms are raised first.
또는 옥탑 2층 기계실 벽체 벽체철근을 먼저 시공한다.Or, construct the wall reinforcement of the machine room on the second floor of the rooftop first.
14) 또한 갱품 상부 고리에 와이어를 이용하여 옥상바닥의 와이어 앙카2(조금 먼거리에 위치)에 연결하고 고정한다.14) Also, use a wire to attach the upper hook of the gang product to the wire anchor 2 on the rooftop (located slightly farther away) and secure it.
바람에 측벽 갱폼이 날리거나 이동하지 않도록 와이어로 고정한다. 갱폼끼리 막대, 각 파이프로 연결하여 고정한다.Secure the side wall gangforms with wire to prevent them from being blown away or moved by the wind. Secure them by connecting the gangforms to each other with rods and each pipe.
타워크레인으로 3면의 갱폼을 인양줄로 매달아 놓는다. 바람에 의해 갱폼이 영향을 받을 수 있다.The three-sided gang form is suspended by ropes using a tower crane. The gang form may be affected by the wind.
갱폼상승 후 내부 알폼을 시공한 후, 콘크리트를 타설하도록 한다.After the gang form is raised, the internal alform is constructed and then concrete is poured.
옥상층 시점에는 대부분의 골조공사가 완료되어 타워크레인의 작업량이 많지 않으므로, 타워크레인이 옥탑 2층의 갱폼들을 콘크리트 타설시까지 몇시간 동안 인양줄로 안전상 연결상태로 있을 수 있다. By the time the rooftop is constructed, most of the skeletal work is complete and the tower crane has little to work with, so the tower crane can safely remain connected to the gang forms on the second floor of the rooftop with lifting ropes for several hours until the concrete is poured.
갱폼 상단에는 고정막대를 설치하여 갱폼간을 서로 연결하여 고정할 수 있다.A fixing bar can be installed on the top of the gangform to connect and fix the gangforms to each other.
15) 옥탑 2층 벽체 형틀, 천정(지붕) 형틀 및 철근을 일반적인 과정으로 설치한다.15) Install the rooftop 2nd floor wall formwork, ceiling (roof) formwork, and reinforcing bars using the general process.
16) 옥탑 2층 벽체 및 천정(지붕) 콘크리트를 타설하여 101동의 모든 골조공사를 완료한다.16) Complete all structural work of Building 101 by pouring concrete for the walls and ceiling (roof) of the 2nd floor of the rooftop.
17) 다음날 측벽 갱폼을 해체하여 지상1층로 내린 후 절단하여 트럭에 싣고 폐기물처리장으로 운송한다.17) The next day, the side wall gang form is dismantled, lowered to the first floor, cut, loaded onto a truck, and transported to a waste disposal site.
일반적으로 갱폼은 최상층 49층 측벽 타설 후 다음날 지상1층 내려 절단하고 폐기물처리장으로 운송되고 있으나, 본 발명에 따라 옥탑1층과 옥탑2의 옥상부분의 외벽 형트로서 사용된다. 이후 다른동에도 계속 사용될 수 있다. 또는 창고에 저장하여 다른 현장의 옥상공사에 사용될 수 있다.Normally, after the side walls of the 49th floor are poured, the gang form is lowered to the first floor above ground, cut, and transported to a waste disposal site the next day. However, according to the present invention, it is used as an exterior wall form for the rooftops of the first and second floors of the rooftop. It can be used continuously in other buildings thereafter. Or, it can be stored in a warehouse and used for rooftop construction at other sites.
원래부터 외벽에 붙어 있던 갱폼은 측벽 갱폼과 동일한 과정으로 진행한다.The gang form that was originally attached to the outer wall is installed through the same process as the side wall gang form.
즉 계단실 부분을 제외한 기계실 부분 선시공에서 ㄷ자 모양으로 갱폼이 동일하게 시공(앙카 매립, 상승, 고정, 해체)된다.In other words, in the pre-construction of the machine room section excluding the stairwell section, the gang form is constructed in the same way (anchor embedding, rising, fixing, and dismantling) in a T shape.
갱폼을 사용하면 외부에 비계를 설치하지 않아도 될 수 있다. 이 경우, 옥탑공사를 위해 비계자재의 반입, 설치, 해체와 함께 비계작업자(철근 형틀과는 다른 별도 공종의 작업자)가 생략되어 공사비가 감소한다.Using gang forms can eliminate the need for installing scaffolding outside. In this case, the cost of construction is reduced because the work of bringing in, installing, and dismantling scaffolding materials for rooftop construction, as well as scaffolding workers (workers of a different type from steel formwork) are omitted.
또한 다수 수량의 알폼작업(운반, 설치, 해체, 반출)이 생략되어 공사비가 감소한다.In addition, construction costs are reduced because a large number of foam operations (transportation, installation, dismantling, removal) are omitted.
한번에 타워크레인으로 측벽 갱폼 2개 내지 3개를 30분 내지 1시간에 설치할 수 있어, 신속하게 옥탑공사를 진행 전체 공사기간을 단축하는 효과를 갖는다.Two to three side wall gang forms can be installed at once with a tower crane in 30 minutes to 1 hour, which has the effect of quickly carrying out rooftop construction and shortening the overall construction period.
한편, 옥탑 2층 기계실 내부 벽체에 알폼 대신 측벽 갱폼을 사용할 수도 있다. 이때 지붕 콘크리트 타설 후에는 내부 갱폼을 빼내기 어려우므로 벽체를 타설한 후, 내부 갱폼을 반출하고 천정 슬래브 골조(천정 데크 플레이트, 지붕 철근, 지붕 콘크리트)를 후속으로 시공하도록 한다.Meanwhile, side wall gang forms can be used instead of alform for the inner walls of the 2nd floor machine room on the rooftop. In this case, since it is difficult to remove the inner gang forms after the roof concrete is poured, the inner gang forms are removed after the wall is poured and the ceiling slab frame (ceiling deck plate, roof reinforcement, roof concrete) is constructed subsequently.
[공사 기간][Construction period]
[최상층 타설 후 1일차][Day 1 after top layer pouring]
측벽갱폼 상승, 측벽부분 파라펫 철근 / 형틀 설치, 콘크리트 타설Side wall gang form rise, side wall parapet reinforcement/form installation, concrete pouring
옥탑 1층 ? 외벽갱폼 인상Rooftop 1st floor? Exterior wall gang form impression
승강로 벽체 내부 또는 외부에 철골구조물 설치(철골기둥, 철골보, 옥탑 1층 내지 2층)Installation of steel structures inside or outside the elevator shaft walls (steel columns, steel beams, 1st or 2nd floors of the rooftop)
[2일차][Day 2]
측벽갱폼 해체, 지상1층 또는 옥상바닥으로 이동 후 갱폼 수정(절단, 하부 작업발판 다리제거)Dismantle the side wall gang form, move to the first floor or rooftop, and then modify the gang form (cut, remove the lower working platform legs)
옥탑 1층 - 승강로 벽체철근 설치 Rooftop 1st floor - Installation of elevator shaft wall reinforcement
옥탑 1층 - 감리단 벽체 철근 검측Rooftop 1st floor - Inspection of the wall reinforcement of the guard room
옥탑 1층 - 승강로 내부측에 벽체형틀(알폼) 설치Rooftop 1st floor - Installation of wall formwork (Alform) on the inside of the elevator shaft
옥탑 1층 - 수정된 측벽갱폼을 옥탑1층 옥상부분 외벽에 설치Rooftop 1st floor - Install the modified side wall gang form on the exterior wall of the rooftop 1st floor
옥탑 1층 - 측벽갱폼과 외벽갱폼 막대로 연결고정, 측벽갱폼과 옥상바닥간에 와이어로 연결고정Rooftop 1st floor - side wall gang form and exterior wall gang form are connected and fixed with bars, side wall gang form and rooftop floor are connected and fixed with wires
옥탑 1층 - 기계실 바닥 데크 플레이트 설치, 전기 슬리브(형판구멍), 바닥 철근, 갱폼(외부, 측벽) 앙카 볼트 매립 Rooftop 1st floor - Machine room floor deck plate installation, electrical sleeve (plate hole), floor rebar, gang form (exterior, side wall) anchor bolt embedding
옥탑 1층 - 감리단 기계실 바닥 철근 검측Rooftop 1st floor - Inspection of the floor reinforcing bars in the machine room of the supervisory unit
[3일차][Day 3]
옥탑 1층 - 승강로 벽체 및 천정(기계실 바닥) 콘크리트 타설 (옥탑1층 골조완료) 및 양생Rooftop 1st floor - Concrete pouring for elevator shaft walls and ceiling (machine room floor) (Rooftop 1st floor frame completed) and curing
옥탑 1층 - 콘크리트 양생Rooftop 1st floor - Concrete curing
[4일차][Day 4]
옥탑 2층 - 외벽갱폼 인상(기계실 바닥에 매립된 앙카 볼트에 고정)Rooftop 2nd floor - Exterior wall gang form impression (attached to anchor bolts embedded in the machine room floor)
옥탑 2층 - 측벽갱폼 인상(기계실 바닥에 매립된 앙카 볼트에 고정)Rooftop 2nd floor - Side wall gang form impression (attached to anchor bolts embedded in the machine room floor)
옥탑 2층 - 측벽갱폼과 외벽갱폼 막대로 연결고정, 측벽갱폼과 옥상바닥간에 와이어로 연결고정Rooftop 2nd floor - side wall gang form and exterior wall gang form are connected and fixed with bars, and side wall gang form and rooftop floor are connected and fixed with wires.
옥탑 2층 - 기계실 벽체철근 설치 Rooftop 2nd floor - Machine room wall reinforcement installation
옥탑 2층 - 감리단 벽체 철근 검측Rooftop 2nd floor - Inspection of the guard room wall reinforcement
옥탑 2층 - 기계실 벽체형틀(알폼) 설치 Rooftop 2nd floor - Installation of machine room wall formwork (Alform)
옥탑 2층 - 기계실바닥에 엘리베이터 자재 양중(모터(권상기), 받침 철골, 배전반 등)Rooftop 2nd floor - Lifting elevator materials on the machine room floor (motor (traction machine), support steel frame, distribution board, etc.)
옥탑 2층 - 기계실 천정 철골보에 데크 플레이트 설치Rooftop 2nd floor - Installing deck plate on machine room ceiling steel beam
옥탑 2층 - 기계실 천정 데크 플레이트에 천정(지붕) 슬래브 철근설치Rooftop 2nd floor - Installation of ceiling (roof) slab rebar on the machine room ceiling deck plate
옥탑 2층 - 감리단 천정(지붕) 슬래브 철근검측Rooftop 2nd floor - Supervision room ceiling (roof) slab rebar inspection
[5일차][Day 5]
옥탑 2층 ? 기계실 벽체 및 지붕 콘크리트 타설Rooftop 2nd floor? Concrete pouring for machine room walls and roof
옥탑 2층 ? 엘리베이터 설치 착수(기계실 바닥에 형판, 피아노선 지하까지 내림)Rooftop 2nd floor? Elevator installation started (template on machine room floor, piano wire lowered to basement)
옥탑 2층 ? 기계실 부분 옥탑공사 완료, 계단실 부분 공사 진행Rooftop 2nd floor? Rooftop construction completed for the mechanical room, stairwell construction in progress
[6일차][Day 6]
옥탑 2층 ? 외벽 및 측벽 갱폼 해체 반출Rooftop 2nd floor? Dismantle and remove the outer wall and side wall gang form
[실시예 도면][Example Drawing]
다음은 측벽 갱폼을 옥탑에 재활용하는 실시예의 도면이다.Below is a drawing of an example of recycling side wall gangforms into a rooftop.
도 176은 101동의 평면도이다. 5개의 세대와 2개의 옥탑이 있다. 오른쪽의 측벽에 측벽1 갱폼1이 설치되어 있다. 상부의 측벽에 측벽2 갱폼이 설치되어 있다. 측벽에는 창문이 없으므로 갱폼의 철판은 구멍이 없는 원판이다.Fig. 176 is a floor plan of Building 101. There are five households and two rooftops. On the right side wall, Side Wall 1 Gangform 1 is installed. On the upper side wall, Side Wall 2 Gangform is installed. Since there are no windows on the side walls, the steel plates of the gangform are round plates without holes.
도 177은 측벽1 갱폼1의 입면도이다. 갱폼의 크기는 높이 3.0m, 가로 길이는 7.79m이다. 하부에는 갱폼다리가 있다.Fig. 177 is an elevation drawing of side wall 1 gangform 1. The size of the gangform is 3.0 m in height and 7.79 m in width. There is a gangform leg at the bottom.
도 178은 도 177의 측벽1 갱폼1의 하부 발판다리를 제거한 갱폼만을 나타낸 것이다. 하부에는 벽체에 고정하기 위한 앙카볼트 구멍이 있다. 상부에는 타워크레인으로 들어올리기 위한 인양고리가 다수 있다.Figure 178 shows only the gang form with the lower step leg of the side wall 1 gang form 1 of Figure 177 removed. There are anchor bolt holes at the bottom for fixing to the wall. There are several lifting hooks at the top for lifting with a tower crane.
갱폼 상부에는 안전난간대가 위로 설치되게 된다.A safety railing is installed on top of the gangform.
도 179는 측벽1 갱폼1의 평면도이다.Fig. 179 is a plan view of side wall 1 gangform 1.
도 180은 측벽2의 갱폼도면이다. 측벽2 갱폼은 한장이 벽체 전체를 시공하며, 길이는 10.5m이다. 높이는 3.0m이다.Figure 180 is a gangform drawing of side wall 2. The side wall 2 gangform is constructed in one sheet over the entire wall, and is 10.5 m long. The height is 3.0 m.
도 181은 측벽2의 입면도이다. 하부의 발판 다리가 제거된 것이다.Fig. 181 is an elevation view of side wall 2. The lower footrest legs have been removed.
도 182는 측벽2의 평면도이다.Fig. 182 is a plan view of side wall 2.
도 183은 측벽2의 단면도이다. 갱폼철판의 두께는 3.5mm정도이다.Fig. 183 is a cross-sectional view of side wall 2. The thickness of the gang form plate is approximately 3.5 mm.
도 176 내지 도 183의 갱폼은 일반적인 갱폼의 도면이며, 1층부터 최상층까지 사용되는 것이다. 본 발명에 따라 작성된 것이 아니다.The gang forms of Figs. 176 to 183 are drawings of general gang forms, and are used from the first floor to the top floor. They are not created according to the present invention.
도 184는 본 발명에 따른 옥탑1층 철골구조물을 설치한 것이다. 승강로 벽체에 철골기둥이 설치되고, 기계실 바닥레벨에 철골보가 설치되고 승강로 내부에 큰 철골보가 설치되어 권상기와 가이드 레일 양중하중을 부담하도록 한다.Fig. 184 shows the installation of a steel structure on the first floor of a rooftop according to the present invention. Steel columns are installed on the walls of the elevator shaft, steel beams are installed on the floor level of the machine room, and large steel beams are installed inside the elevator shaft to support the lifting load of the hoist and guide rail.
도 185는 측벽갱폼2를 설치한 것이다. 최상층 외벽의 갱폼을 해체 및 수정(길이를 절단)하고 옥상바닥에 세운다. 갱폼 상부의 고리에 타워크레인으로 들어서 설치한다. 하부는 옥상바닥에 설치된 철근토막, 각재 등에 의해 고정된다.Fig. 185 shows the installation of side wall gang form 2. The gang form of the top outer wall is dismantled and modified (cut to length) and installed on the rooftop. It is installed by lifting it into the ring on the top of the gang form with a tower crane. The lower part is fixed by rebar pieces, timber, etc. installed on the rooftop.
도 186은 측벽갱폼2를 칼라로 표시한 것이다.Figure 186 shows the side wall gang form 2 in color.
도 187은 철골구조물을 제외하고 측벽갱폼2만을 표시한 것이다.Fig. 187 shows only the side wall gang form 2, excluding the steel structure.
도 188은 측벽갱폼 1을 설치한 것이다. 측벽갱폼1과 2는 어는 것이나 먼저 설치될 수 있다. 교차부분은 잘라서 맞추거나 한쪽을 길게하고 그 면에 다른 갱폼을 갖다대어 90도 각도롤 형틀을 만들 수 있다.Fig. 188 shows the side wall gang form 1 installed. Either side wall gang form 1 or 2 can be installed first. The intersection can be cut and fitted, or one side can be lengthened and the other gang form can be placed on that side to create a 90 degree angle roll form.
도 189는 측벽갱폼1를 칼라로 표시한 것이다.Figure 189 shows the side wall gang form 1 in color.
도 190은 외벽갱폼이 올라온 것을 표시한 것이다. 외벽 갱폼은 가장 먼저 올라오게 되지만 여기서는 나중으로 표시하였다. 외벽갱폼은 추락의 위험이 있으므로 먼저 올라오고 이후에 벽체철근을 시공한다. 옥상부분은 추락위험이 없으므로 벽체철근 설치 후 측벽갱폼을 설치하도록 한다. 계단실 부분에도 갱폼을 설치할 수 있다. 그러나 계단실이 복잡하여 작업시간이 소요되므로, 별도로 뒤따라 오는 공정으로 하도록 한다. 계단실 부분은 알폼으로 시공할 수 있다.Fig. 190 shows the exterior wall gang form being raised. The exterior wall gang form is raised first, but it is shown here as being raised later. Since the exterior wall gang form is at risk of falling, it is raised first and the wall reinforcement is installed later. Since there is no risk of falling in the rooftop area, the side wall gang form is installed after the wall reinforcement is installed. Gang form can also be installed in the stairwell area. However, since the stairwell is complicated and requires work time, it is done as a separate process that follows. The stairwell area can be constructed with Alform.
도 191은 측벽 갱폼상부에 고리에 와이어를 매달고, 옥상바닥에 매립된 후크(고리)에 와이어를 연결한다. 와이어의 길이조절은 턴 버클(회전하면서 길이를 조절하는 연결재)을 사용한다. 와이어를 설치하는 이유는 옥상의 바람으로 인해 갱폼이 흔들리는 것을 방지하기 위한 것이다. 또한 각재나 파이프를 옥상바닥과 갱폼 사이에 경사지게 버팀목으로 고여 쓰러지지 않도록 한다.Figure 191 hangs wires on the hooks on the top of the side wall gangform, and connects the wires to the hooks (rings) embedded in the rooftop. The length of the wires is adjusted using turnbuckles (connectors that adjust the length by rotating). The purpose of installing the wires is to prevent the gangforms from shaking due to the wind on the rooftop. In addition, lumber or pipes are placed as supports at an angle between the rooftop and the gangforms to prevent them from collapsing.
도 192는 옥탑1층 콘크리트 타설후, 갱폼이 옥상2층으로 한개층 상승한 것이다. 갱폼하단부에는 아래 49층 이하에서 사용하던 앙카 볼트로 고정한다. 앙카볼트는 슬래브 내부에 앙카볼트 묻고 콘크리트 타설 후, 갱폼을 대고 볼트로 고정하는 것이다. 즉 못의 역할과 같으나 나중에 빼내서 갱폼이 위로 상승하도록 한다. 기계실 바닥에 앙카 볼트를 49층 아래층에서 했던 것과 마찬가지로 묻고 콘크리트 타설 후 다음날 갱폼을 위로 올려서 볼트로 고정한다. 이것은 기준층에서 했던 것과 동일하므로 안전하고 신속하다.Fig. 192 shows that after the concrete is poured on the first floor of the rooftop, the gang form rises one floor to the second floor of the rooftop. The lower part of the gang form is fixed with the anchor bolts used on the 49th floor and below. The anchor bolts are buried inside the slab, and after the concrete is poured, the gang form is placed against it and fixed with bolts. In other words, it is similar to a nail, but it is removed later to allow the gang form to rise up. The anchor bolts are buried in the floor of the machine room just as they were on the 49th floor and the next day after the concrete is poured, the gang form is raised and fixed with bolts. This is the same as what was done on the standard floor, so it is safe and quick.
도 193은 철골구조물과 옥탑2층의 갱폼을 같이 표시한 것이다.Figure 193 shows the steel structure and the gang form of the second floor of the rooftop together.
도 194는 옥탑2층의 갱폼을 칼라로 표시하고 갱폼을 고정하기 위한 막대(철골자재)를 갱폼간에 연결한 것이다.Fig. 194 shows the gang forms on the second floor of the rooftop in color and the bars (steel materials) for fixing the gang forms are connected between the gang forms.
도 195는 측벽갱폼을 세로로 세운 것이다. 세로로 세우는 이유는 옥탑 2개층을 한번에 시공하기 위한 것이다. 또는 옥탑1층의 높이가 3.0m인 갱폼보다 높은 경우이다. Fig. 195 shows the side wall gang form erected vertically. The reason for erecting it vertically is to construct two rooftop floors at once. Or, when the height of the rooftop floor is higher than the gang form, which is 3.0 m.
도 196은 갱폼 2개를 2단으로 쌓은 것이다. 연결부분은 추가 재료를 대고 용접으로 연결할 수 있다. 와이어로 고정하도록 한다. 2단으로 쌓은 이유는 옥탑 1층이 3.0m를 초과하여 한장으로 커버가 되지 않는 경우이다. 또는한번에 갱폼을 전부 세팅하기 위함이다.Fig. 196 is a two-tiered gang form. The connecting part can be connected by welding with additional material. It is fixed with wire. The reason for the two-tiered construction is when the first floor of the roof exceeds 3.0m and cannot be covered with one sheet. Or, to set all the gang forms at once.
종래에는 옥상부분에 쌍줄비계를 설치하고 알폼으로 시공 후 해체하여 정리하여 반출하였다.In the past, a double-row ladder was installed on the rooftop, constructed with foam, then dismantled, organized, and transported.
이는 많은 인력과 시간이 소요되는 방식이다.This is a method that requires a lot of manpower and time.
그러나 본 발명에 따르면, 타워크레인이라는 장비를 이용하여 한번에 외벽 거푸집을 설치 해체한다.However, according to the present invention, the outer wall formwork is installed and dismantled at once using equipment called a tower crane.
인력대신 기계실 사용하며, 비용과 시간을 단축하는 방법이다.This is a method of reducing costs and time by using a machine room instead of manpower.
도 197은 설치일정을 나타낸 것이다.Figure 197 shows the installation schedule.
앞서 설명한 설치일정의 내용을 표로 정리한 것이다.The contents of the installation schedule explained above are organized into a table.
[갱폼 옥탑에서 재활용 효과][Recycling effect on Gangform rooftop]
본 발명에 따르면According to the present invention
1) 철골구조물을 이용하여 슬래브 양생 기간을 없애고1) Eliminate the slab curing period by using a steel structure.
2) 측벽 갱폼을 재활용하여 옥상부분의 형틀작업시간을 단축하여2) By recycling the side wall gang form, the formwork time for the roof section is shortened.
3) 옥탑 기계실 부분의 골조를 5일만에 완성하고3) The frame of the rooftop machine room was completed in 5 days.
4) 5일차 오후에 엘리베이터 설치를 착수할 수 있도록 한다.4) Elevator installation can begin in the afternoon of the 5th day.
이는 종래의 재래색 공법이 2개층에 25일 내지 30일 소요되는 것에 비해 20일 내지 25일 단축된다.This is a reduction of 20 to 25 days compared to the conventional coloring method which takes 25 to 30 days for two layers.
또한 철골구조물의 큰 철골보를 이용하여 이른 시간에 수십개의 가이드레일을 지하부터 한줄로 엮어서 한번에 들어서 설치하므로 엘리베이터 설치기간도 단축된다.In addition, the elevator installation period is shortened by using the large steel beams of the steel structure to install dozens of guide rails in a single line from underground at an early hour.
종래에는 엘리베이터 설치기간은 49층 아파트의 경우 일반적으로 120일이 소요된다.Traditionally, it took 120 days to install an elevator in a 49-story apartment building.
그러나 '본 발명에 따르면However, according to the present invention
1) 옥탑골조에서 20일 내지 25일이 단축되고1) 20 to 25 days are shortened in the roof structure.
2) 가이드레일 전체를 엮어서 한번에 들어올리는 하중을 큰 철골보가 가능하게 하므로2) By linking the entire guide rail, a large steel beam can lift the load at once.
3) 전체 공사기간은 35일 내지 40일 이상 단축되고3) The total construction period is shortened by 35 to 40 days or more.
4) 갱폼을 재활용함에 따라 옥탑 공사비가 감소하고4) The cost of rooftop construction is reduced by recycling the gang form.
5) 그에 따라 입주자들은 미리 입주하고, 사업 대출 이자 및 시공사의 현장운영비가 절약되는 효과가 있다. 동일한 작업을 보다 짧은 시간에 하게 됨에 따라 생산성이 향상된다.5) Accordingly, residents can move in early, and the business loan interest and construction company's on-site operating costs are saved. Productivity is improved as the same work is done in a shorter period of time.
앞에서 설명되고, 도면에 도시된 본 발명의 실시예는, 본 발명의 기술적 사상을 한정하는 것으로 해석되어서는 안 된다. 본 발명의 보호범위는 청구범위에 기재된 사항에 의하여만 제한되고, 본 발명의 기술분야에서 통상의 지식을 가진 자는 본 발명의 기술적 사상을 다양한 형태로 개량 변경하는 것이 가능하다. 따라서 이러한 개량 및 변경은 통상의 지식을 가진 자에게 자명한 것인 한 본 발명의 보호범위에 속하게 될 것이다.The embodiments of the present invention described above and illustrated in the drawings should not be construed as limiting the technical idea of the present invention. The protection scope of the present invention is limited only by the matters described in the claims, and those with ordinary knowledge in the technical field of the present invention can improve and change the technical idea of the present invention in various forms. Accordingly, such improvements and changes will fall within the protection scope of the present invention as long as they are obvious to those with ordinary knowledge.
본 발명에 따른 옥탑 기계실의 철골구조물 및 시공방법은 설계도 작성, 부재제작을 통하여 공사현장에 바로 이용할 수 있다.The steel structure and construction method of the rooftop machine room according to the present invention can be used directly at a construction site through drawing up of design drawings and fabrication of components.
1 : 철골기둥
2 : 철골보
3 : 큰 철골보
4 : 데크 플레이트
5 : T형강1: Steel column
2: Steel beam
3: Large steel beam
4: Deck Plate
5: T-beam
Claims (1)
최상층 골조(옥상 바닥) 콘크리트를 타설하는 단계 ;
승강로 벽체 내부, 승강로 벽체에 인접, 승강로 벽체라인, 옥상바닥 또는 승강로 내부 보이드에 옥탑 1층 내지 옥탑 2층 철골기둥을 설치하는 단계;
상기 철골기둥에 철골보를 설치하는 단계 ;
상기 철골기둥 또는 철골보에 승강로 내부에 설치되는 철골보를 설치하여 철골구조물 설치를 완료하는 단계 ;
상기 옥탑1층 승강로 벽체에 철근을 시공하는 단계 ;
최상층 측벽 갱폼을 해체 및 수정하여 옥탑1층 옥상부분의 벽체외부 형틀로 설치하는 단계 ;
상기 철골보에 기계실 바닥에 형틀재, 철근을 설치한 후 승강로 벽체 및 기계실 바닥 콘크리트를 타설하는 단계 ;
상기 기계실 바닥 콘크리트 타설 후, 상기 옥상부분의 벽체외부 형틀을 옥탑2층(기계실 벽체)으로 상승하는 단계 ;
기계실 벽체 철근, 형틀재(벽체내부), 엘리베이터 장비를 기계실로 인양, 천정 형틀재 설치하는 단계 ;
상기 기계실 벽체 및 천정 콘크리트를 타설하는 단계 ; 및
엘리베이터 설치를 착수하는 단계
를 포함하는 것을 특징으로 하는 옥탑층의 엘리베이터 기계실 골조를 기준층의 갱폼을 재활용하여 시공하는 공사방법This is a construction method that constructs the elevator machine room frame on the rooftop of an apartment building by reusing the gang form of the standard floor.
Step of pouring concrete for the top floor structure (rooftop floor);
A step of installing a rooftop 1st floor or rooftop 2nd floor steel column inside the elevator shaft wall, adjacent to the elevator shaft wall, on the elevator shaft wall line, on the rooftop floor, or in the elevator shaft internal void;
A step of installing a steel beam on the above steel column;
A step of completing the installation of a steel structure by installing a steel beam installed inside an elevator shaft on the steel column or steel beam;
Step of constructing reinforcing bars on the wall of the elevator shaft on the first floor of the rooftop above;
Step of dismantling and modifying the top floor side wall gang form and installing it as the external wall formwork of the rooftop part of the first floor;
A step of installing formwork and reinforcing bars on the machine room floor in the above steel frame, and then pouring concrete for the elevator shaft walls and machine room floor;
After pouring concrete on the floor of the above-mentioned machine room, the step of raising the external formwork of the wall of the above-mentioned rooftop section to the 2nd floor of the rooftop (machine room wall);
Steps for lifting machine room wall reinforcement, formwork (inside the wall), elevator equipment to the machine room, and installing ceiling formwork;
Step of pouring concrete for the walls and ceiling of the machine room; and
Steps to start installing the elevator
A construction method for constructing an elevator machine room frame on a rooftop floor by recycling the gang form of the base floor, characterized by including
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| KR1020230146136A KR20250061777A (en) | 2023-10-28 | 2023-10-28 | Construction method of the structure of the elevator machine room on the rooftop of an apartment building by recycling the gangform of typical floor |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| KR1020230146136A KR20250061777A (en) | 2023-10-28 | 2023-10-28 | Construction method of the structure of the elevator machine room on the rooftop of an apartment building by recycling the gangform of typical floor |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| KR20250061777A true KR20250061777A (en) | 2025-05-08 |
Family
ID=95711230
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| KR1020230146136A Pending KR20250061777A (en) | 2023-10-28 | 2023-10-28 | Construction method of the structure of the elevator machine room on the rooftop of an apartment building by recycling the gangform of typical floor |
Country Status (1)
| Country | Link |
|---|---|
| KR (1) | KR20250061777A (en) |
-
2023
- 2023-10-28 KR KR1020230146136A patent/KR20250061777A/en active Pending
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN107090975B (en) | Formwork erecting construction method for ultrahigh large-span concrete cast-in-place beam bailey truss | |
| CN114232805B (en) | Construction method of ultrahigh-height large-span steel concrete beam hanging structure | |
| US10829927B2 (en) | Vertical slip form construction system with multi-function platform, and method of constructing a building therewith | |
| CN210659200U (en) | High-rise building elevator shaft operation platform | |
| CN115538792B (en) | Building construction method and building construction structure by using residential building machine | |
| KR20250036109A (en) | Structural Systems and Methods for Floor Structural Work in Elevator Machine Room of Apartment Housing | |
| CN115627912A (en) | Construction method of assembled externally-mounted flower basket type overhanging scaffold | |
| CN116657875B (en) | Cantilever steel structure construction platform with formwork system and construction method | |
| KR20250061777A (en) | Construction method of the structure of the elevator machine room on the rooftop of an apartment building by recycling the gangform of typical floor | |
| CN115288414A (en) | Construction method of hydraulic climbing operation frame for super high-rise core barrel special-shaped shaft | |
| KR20250061106A (en) | Construction Method and Apparatus for Elevator Mechanical Room Frames on the Roof Floor, such as Offices and Apartments, Using Steel Structures | |
| KR20250061779A (en) | Construction method of the structure of the elevator machine room on the rooftop of an apartment building by recycling the gangform of typical floor | |
| KR20210141194A (en) | Construction Method and Device of Wall and Floor Structure in Elevator's Machine Room in Apartment Building and Office Using Hanging Structural Method by Steel and Deck Plate in Top-down Structure | |
| KR20250058092A (en) | Construction Method and Apparatus for Elevator Mechanical Room Frames on the Roof Floor, such as Offices and Apartments, Using Steel Structures | |
| KR20250054214A (en) | Construction Method and Apparatus for Elevator Mechanical Room Frames on the Roof Floor, such as Offices and Apartments, Using Steel Structures | |
| JPH05133016A (en) | Peripheral supporting self-rising type building engineering method | |
| EP1801301B1 (en) | Method of adding extra floors on a building | |
| KR20250048506A (en) | Elevator machine room steel structure and construction method | |
| KR20250048507A (en) | Elevator machine room steel structure and construction method | |
| KR20250035530A (en) | Construction Method and Device of Floor Structure in Elevator's Machine Room in Apartment Building Using Hanging Structural Method | |
| KR102786962B1 (en) | Form auto climbing system having work cage, and concrete wall construction method using the same | |
| CN114809579B (en) | Erection method of elevating construction platform used for erecting formwork system around lighting shaft | |
| KR20250124265A (en) | A method of structural construction using steel girder and deck plate at pit floor in apartment structural construction | |
| KR200200364Y1 (en) | High building construction apparatus | |
| JP2761528B2 (en) | How to build structures |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PA0109 | Patent application |
Patent event code: PA01091R01D Comment text: Patent Application Patent event date: 20231028 |
|
| PG1501 | Laying open of application |