KR20200124579A - Method of manufacturing support beam for retaining wall and support beam for retaining wall using the same - Google Patents

Method of manufacturing support beam for retaining wall and support beam for retaining wall using the same Download PDF

Info

Publication number
KR20200124579A
KR20200124579A KR1020190048095A KR20190048095A KR20200124579A KR 20200124579 A KR20200124579 A KR 20200124579A KR 1020190048095 A KR1020190048095 A KR 1020190048095A KR 20190048095 A KR20190048095 A KR 20190048095A KR 20200124579 A KR20200124579 A KR 20200124579A
Authority
KR
South Korea
Prior art keywords
support beam
retaining wall
support
manufacturing
tensioning means
Prior art date
Application number
KR1020190048095A
Other languages
Korean (ko)
Other versions
KR102324327B1 (en
Inventor
오세연
Original Assignee
오세연
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 오세연 filed Critical 오세연
Priority to KR1020190048095A priority Critical patent/KR102324327B1/en
Publication of KR20200124579A publication Critical patent/KR20200124579A/en
Application granted granted Critical
Publication of KR102324327B1 publication Critical patent/KR102324327B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/003Injection of material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0046Production methods using prestressing techniques
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/10Miscellaneous comprising sensor means
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The present invention relates to a method for manufacturing a support beam for an earth retaining wall and a support beam for an earth retaining wall using the same, wherein the method for manufacturing a support beam for an earth retaining wall can introduce prestress in an opposite direction of a direction to which earth pressure is applied, manufacture two support beams at the same time to lower a manufacturing cost, and form at least two bending moment portions since earth pressure is relatively greatly applied in case of the support beam in a range of 10 to 20 m used in deep excavation and the earth pressure cannot be applied by the single bending moment.

Description

흙막이 벽체용 지지빔의 제조방법 및 이를 이용한 흙막이 벽체용 지지빔{METHOD OF MANUFACTURING SUPPORT BEAM FOR RETAINING WALL AND SUPPORT BEAM FOR RETAINING WALL USING THE SAME}Manufacturing method of support beam for retaining wall and support beam for retaining wall using the same {METHOD OF MANUFACTURING SUPPORT BEAM FOR RETAINING WALL AND SUPPORT BEAM FOR RETAINING WALL USING THE SAME}

본 발명은 흙막이 벽체용 지지빔의 제조방법 및 이를 이용한 흙막이 벽체용 지지빔에 관한 것으로, 보다 상세하게는 토압이 작용하는 방향과 반대방향으로 프리스트레스를 도입될 수 있도록 하되, 2의 지지빔을 동시에 제작하여 제조단가를 낮출 수 있는 것은 물론, 깊은 굴착에 사용되는 10m ~ 20m 범위의 지지빔의 경우에는 토압이 상대적으로 크게 작용하는 바, 단일의 휨 모멘트 영역으로는 이를 적용할 수 없어 적어도 2개 이상의 휨 모멘트 영역을 형성한 흙막이 벽체용 지지빔의 제조방법 및 이를 이용한 흙막이 벽체용 지지빔에 관한 것이다.The present invention relates to a method of manufacturing a support beam for a retaining wall and a support beam for a retaining wall using the same, and more particularly, to allow the prestress to be introduced in a direction opposite to the direction in which earth pressure acts, but the support beams of two are simultaneously Not only can the manufacturing cost be lowered by manufacturing, but in the case of a support beam in the range of 10m to 20m used for deep excavation, the earth pressure is relatively large, and it cannot be applied in a single bending moment region, so at least two The present invention relates to a method of manufacturing a support beam for a retaining wall having the above bending moment region, and a support beam for a retaining wall using the same.

종래 건축물, 개착터널, 지하철, 전력구, 통신구, 하수관거 등과 같이 지반을 소정의 깊이 및 길이방향으로 연장하여 굴착하고, 그 굴착지반 내부 공간에 구조물을 설치하는 경우에 있어, 굴착된 지반면은 항상 토압에 의하여 붕괴되려고 한다.In the case of excavation by extending the ground in a predetermined depth and length direction such as a conventional building, open tunnel, subway, power outlet, communication port, sewage pipe, etc., and installing a structure in the space inside the excavated ground, the excavated ground surface is always It is about to collapse by earth pressure.

따라서 통상은 지지빔(H빔)을 먼저 지중에 매설시킨 후, 지반을 굴착하면서 지지빔 사이에 토류판을 끼워 설치하는 방식이다.Therefore, in general, a support beam (H-beam) is first buried in the ground, and then an earth plate is inserted between the support beams while excavating the ground.

이 때 토류판이 설치된 지지빔에는 수평빔 형태의 띠장을 설치하게 되는데, 이는 지지빔을 서로 수평방향으로 연결시켜줌으로서 지지빔과 띠장이 격자형태의 구조체로서 작용하는 주동토압에 보다 효과적으로 저항할 수 있도록 하기 위함이다.At this time, a horizontal beam-shaped strip is installed on the support beam on which the earth plate is installed, which connects the support beams in a horizontal direction so that the support beam and the strip can more effectively resist the main earth pressure acting as a grid-shaped structure. It is to do.

근래에는 시공을 간편하게 하기 위해 지지빔에 별도의 띠장과 버팀보 없이 지지빔 자체에 프리스트레스를 도입한 "프리스트레스가 도입된 엄지말뚝과 이를 이용한 자립식 가설 흙막이 시공방법(대한민국 등록특허 제1609805호): 이하 인용발명이라 한다."이 제시된 바 있다.In recent years, in order to simplify the construction, a pre-stress is introduced into the support beam itself without separate strips and support beams, and a "thumb pile with pre-stress introduced and a self-supporting temporary soil barrier construction method using the same (Republic of Korea Patent Registration No. 1609805): It is referred to as a cited invention."

상술된 인용발명은 프리스트레스를 도입하기 위해 엄지말뚝의 측면에 강봉으로 이루어지는 인장재를 설치하여 구성하였다.The above cited invention was constructed by installing a tension member made of a steel bar on the side of the thumb pile to introduce prestress.

하지만 이러한 인용발명은 제작이 어려워 생산성이 떨어지고, 가격이 매우 고가로 시공비가 많이 소요되는 문제점이 있었다.However, such a cited invention has a problem in that it is difficult to manufacture, resulting in a decrease in productivity, a very high price, and a large construction cost.

대한민국 등록특허 제1609805호Korean Patent Registration No. 1609805

본 발명은 상기와 같은 문제점을 감안하여 안출된 것으로, 본 발명의 제 1목적은, 프리스트레스가 도입된 2개의 지지빔을 동시에 제작할 수 있고, 구조가 간단하여 현장에서 제작이 용이한 흙막이 벽체용 지지빔의 제조방법 및 이를 이용한 흙막이 벽체용 지지빔을 제공하는데 있다.The present invention has been conceived in consideration of the above problems, and the first object of the present invention is to simultaneously manufacture two support beams with prestress introduced, and support for a retaining wall that is easy to manufacture in the field due to its simple structure. It is to provide a method of manufacturing a beam and a support beam for an earthen wall using the same.

본 발명의 제 2목적은, 콘크리트를 이용하여 소성변형을 최소화할 수 있고, 이에 따라 곡선구간을 최소화하여 수평 상태를 이룰 수 있어 토류판의 설치를 용이하게 하며, 더불어 충전된 콘크리트에 의해 프리스트레스를 최대한 확보하여 별도의 버팀보 없이 자립 설치할 수 있도록 한 흙막이 벽체용 지지빔의 제조방법 및 이를 이용한 흙막이 벽체용 지지빔을 제공하는데 있다.The second object of the present invention is to minimize plastic deformation by using concrete, thereby minimizing the curved section to achieve a horizontal state, thereby facilitating the installation of the earth plate, and maximizing prestress by the filled concrete. It is to provide a method of manufacturing a support beam for a retaining wall that can be secured and installed independently without a separate support beam, and a support beam for a retaining wall using the same.

본 발명의 제 3목적은, 깊은 굴착에 사용되는 10m ~ 20m 범위의 지지빔의 경우에는 토압이 상대적으로 크게 작용하는 바, 단일의 휨 모멘트 영역으로는 이를 적용할 수 없어 적어도 2개 이상의 휨 모멘트 영역을 형성한 흙막이 벽체용 지지빔의 제조방법 및 이를 이용한 흙막이 벽체용 지지빔A third object of the present invention is that in the case of a support beam in the range of 10m to 20m used for deep excavation, the earth pressure is relatively large, and it cannot be applied to a single bending moment region, so at least two bending moments Method of manufacturing support beam for retaining wall with area and support beam for retaining wall using the same

상기한 바와 같은 목적을 달성하기 위한 특징에 따르면, 제 1발명은 흙막이 벽체의 토류패널을 지지하기 위해 지중에 고정되는 흙막이 벽체용 지지빔의 제조방법에 관한 것으로, 이를 위해 내부가 중공인 한쌍의 지지빔을 준비하는 단계;(S10)와, 지중에 삽입되는 각 지지빔의 하부영역을 단일 고정지그에 일정간격을 두고 삽입하여 직립 고정하는 단계;(S20)와, 상기 각 지지빔에 휨 모멘트가 발생되도록 상기 각 지지빔의 사이로 인장수단을 장착시켜 인장력을 동시에 가하는 단계;(S30)와, 휨 모멘트가 발생된 상기 각 지지빔의 내부로 고강도 콘크리트를 주입하는 단계;(S40)와, 상기 고강도 콘크리트를 양생시켜 상기 각 지지빔의 내부에서 충전된 콘크리트에 압축된 잔류 프리스트레스를 도입하는 단계;(S50) 및 상기 각 지지빔을 인장수단과, 고정지그에서 해체한 후 프리스트레스가 도입된 흙막이 벽체용 지지빔을 완성하는 단계;(S60)를 포함하여 구성되되, 상기 흙막이 벽체용 지지빔은 토압이 작용하는 방향과 반대방향으로 휨 모멘트가 발생되게 설치되는 것을 특징으로 한다.According to the features for achieving the above object, the first invention relates to a method of manufacturing a support beam for a retaining wall fixed to the ground to support the earth panel of the retaining wall, and for this purpose, a pair of Preparing a support beam; (S10) and inserting a lower region of each support beam inserted into the ground at a predetermined interval into a single fixing jig and fixing it upright; (S20), and a bending moment at each of the support beams A step of simultaneously applying a tensile force by attaching a tensioning means between the support beams so that a bending moment is generated; (S30) and injecting high-strength concrete into the inside of each of the support beams in which a bending moment is generated; Curing high-strength concrete to introduce the compressed residual prestress into the concrete filled in each of the support beams; (S50) and the retaining wall to which the prestress is introduced after dismantling each of the support beams from a tensioning means and a fixing jig Completing the support beam for; (S60) is configured to include, wherein the support beam for the retaining wall is installed to generate a bending moment in a direction opposite to the direction in which the earth pressure acts.

제 2발명은, 제 1발명에서, 상기 S30단계의 인장수단은 인장잭 또는 강선을 이용한 인장기 중 선택되는 어느 하나이고, 상기 인장수단은 소성변형을 방지하기 위해 극한 휨 모멘트 이하로 인장력을 가하는 것을 특징으로 한다.In the second invention, in the first invention, the tensioning means of the step S30 is any one selected from a tensioning jack or a tensioner using a steel wire, and the tensioning means applies a tensile force below an extreme bending moment to prevent plastic deformation. It features.

제 3발명은, 제 1발명에서, 상기 S30단계는 각 지지빔에 휨 모멘트가 적용되는 부위를 등분시킨 다음, 등분된 지점을 펜으로 마킹하는 단계;(S31)와, 상기 마킹된 부위에 복수의 인장수단을 장착하는 단계;(S32)와, 상기 각 인장수단을 인장력을 가하되, 상기 각 인장수단 중 토류압력이 큰 지점에 장착된 인장수단은 지지빔의 극한 휨 모멘트 이하로 인장력를 가하고, 상대적으로 토류압력이 약한 지점에 장착된 인장수단은 상대적으로 작은 인장력을 가하는 단계;(S33)를 더 포함하는 것을 특징으로 한다.In the third invention, in the first invention, the step S30 is a step of dividing a portion to which a bending moment is applied to each support beam, and then marking the divided point with a pen; (S31) and a plurality of the marked portions Mounting the tensioning means of; (S32), and applying a tensile force to each of the tensioning means, wherein the tensioning means mounted at a point where the earth pressure of each of the tensioning means is large applies a tensile force below the ultimate bending moment of the support beam, The tensioning means mounted at the point where the earth pressure is relatively weak applies a relatively small tensioning force; (S33) is characterized in that it further comprises.

제 4발명은, 제 1발명에서, 상기 S30단계는 각 지지빔을 길이방향으로 등분시켜 마킹하는 단계;(S31)와, 상기 마킹된 부위에 복수의 인장수단과 버팀목 또는 고정지그를 상호 간 교번되게 장착하는 단계;(S32)와, 상기 각 인장수단을 인장력을 가하여 상기 각 지지빔에 적어도 2개 이상의 휨 모멘트를 구간을 형성시키는 단계;(S33)를 더 포함하는 것을 특징으로 한다.In the fourth invention, in the first invention, the step S30 is a step of dividing each support beam in a longitudinal direction and marking; (S31), a plurality of tensioning means and a support neck or a fixing jig are alternately alternating with each other at the marked portion. (S32) and applying a tensile force to each of the tensioning means to form a section with at least two bending moments on each of the support beams; (S33).

제 5발명은, 제 1발명 또는 제 3발명에서, 상기 S60단계 이후, 흙막이 벽체용 지지빔의 상부에 커플러를 이용하여 별도의 연장빔을 더 연결하는 단계;(S70)를 더 포함하는 것을 특징으로 한다.In the fifth invention, in the first invention or the third invention, after the step S60, further connecting a separate extension beam using a coupler to the upper part of the support beam for the retaining wall; (S70) is further included. To do.

제 6발명은, 제 1발명에서, 상기 S20단계는 상기 고정지그의 하부에는 각 지지빔의 하단부에 결합되는 보조지그 또는 반력수단을 더 설치하는 단계;(S21)를 더 포함하는 것을 특징으로 한다.In the sixth invention, in the first invention, the step S20 further comprises a step of further installing an auxiliary jig or reaction force means coupled to a lower end of each support beam at a lower portion of the fixing jig; (S21) .

상기한 바와 같은 목적을 달성하기 위한 특징에 따르면, 제 7발명은, 흙막이 벽체용 지지빔의 제조방법을 이용한 흙막이 벽체용 지지빔에 관한 것으로, 제 1발명 내지 제 6발명 중 어느 하나의 흙막이 벽체용 지지빔의 제조방법을 이용한 것을 특징으로 한다.According to the features for achieving the above object, the seventh invention relates to a support beam for a retaining wall using a method of manufacturing a support beam for a retaining wall, and the retaining wall of any one of the first to sixth inventions It is characterized by using a method of manufacturing a support beam for.

본 발명에 따른 흙막이 벽체용 지지빔의 제조방법 및 이를 이용한 흙막이 벽체용 지지빔에 따르면, 프리스트레스가 도입된 2개의 지지빔을 동시에 제작할 수 있고, 제조가 간단하여 현장에서 제작이 용이한 효과가 있다.According to the method of manufacturing a support beam for a retaining wall according to the present invention and a support beam for a retaining wall using the same, two support beams into which prestress is introduced can be simultaneously manufactured, and since the manufacturing is simple, there is an effect that it is easy to manufacture in the field. .

또한 적어도 2개 이상의 휨 모멘트 영역을 형성한 흙막이 벽체용 지지빔을 통해 깊은 굴착에 사용되는 10m ~ 20m 범위의 지지빔도에 적용가능한 효과가 있다.In addition, there is an effect applicable to support beams in the range of 10m to 20m used for deep excavation through the support beam for the earthen wall, which has at least two bending moment regions formed.

또한 충전되는 콘크리트가 프리스트레스를 갖게 됨으로 지지빔의 소성변형을 최소화할 수 있고, 이에 따라 곡선구간을 최소화하여 수평 상태를 이룰 수 있어 토류판의 설치가 용이한 효과가 있다.In addition, since the filled concrete has prestress, it is possible to minimize the plastic deformation of the support beam, and accordingly, it is possible to achieve a horizontal state by minimizing the curved section, so that the installation of the earth plate is easy.

또한 충전된 콘크리트에 의해 프리스트레스를 최대한 확보하여 별도의 버팀보 없이 자립 설치할 수 있는 효과가 있다.In addition, there is an effect that the prestress can be secured as much as possible by the filled concrete and can be installed independently without a separate support.

또한 프리스트레스를 도입하기 위해 지지빔의 측면에 강선을 장착한 구조보다 제작비가 저렴한 효과가 있다.In addition, in order to introduce pre-stress, there is an effect that the manufacturing cost is cheaper than the structure in which the steel wire is mounted on the side of the support beam.

도 1은 본 발명의 제 1실시예에 따른 흙막이 벽체용 지지빔의 제조방법을 나타내는 순서도,
도 2는 도 1의 S30단계를 나타내는 세부순서도,
도 3은 도 1의 S30단계를 나타내는 구성도,
도 4는 도 1의 S60단계를 나타내는 흙막이 벽체용 지지빔을 나타내는 사시도,
도 5는 도 1의 S70단계를 나타내는 흙막이 벽체용 지지빔을 나타내는 구성도,
도 6은 본 발명의 제 2실시예에 따른 흙막이 벽체용 지지빔의 제조방법을 나타내는 순서도,
도 7은 도 6의 S30단계를 나타내는 세부순서도,
도 8은 도 6의 S30단계를 나타내는 구성도이다.
1 is a flow chart showing a method of manufacturing a support beam for a retaining wall according to a first embodiment of the present invention;
2 is a detailed flowchart showing step S30 of FIG. 1;
3 is a configuration diagram showing step S30 of FIG. 1;
Figure 4 is a perspective view showing a support beam for the retaining wall showing step S60 of Figure 1,
5 is a configuration diagram showing a support beam for a retaining wall representing step S70 of FIG. 1,
6 is a flow chart showing a method of manufacturing a support beam for a retaining wall according to a second embodiment of the present invention;
7 is a detailed flow chart showing step S30 of FIG. 6;
FIG. 8 is a configuration diagram illustrating step S30 of FIG. 6.

이하의 본 발명의 목적들, 다른 목적들, 특징들 및 이점들은 첨부된 도면과 관련된 이하의 바람직한 실시예들을 통해서 쉽게 이해될 것이다. 그러나 본 발명은 여기서 설명되는 실시예들에 한정되지 않고 다른 형태로 구체화될 수도 있다.The following objects, other objects, features, and advantages of the present invention will be easily understood through the following preferred embodiments related to the accompanying drawings. However, the present invention is not limited to the embodiments described herein and may be embodied in other forms.

오히려, 여기서 소개되는 실시예들은 개시된 내용이 철저하고 완전해질 수 있도록 그리고 당업자에게 본 발명의 사상이 충분히 전달될 수 있도록 하기 위해 제공되는 것이다.Rather, the embodiments introduced herein are provided so that the disclosed content may be thorough and complete, and the spirit of the present invention may be sufficiently conveyed to those skilled in the art.

여기에 설명되고 예시되는 실시예들은 그것의 상보적인 실시예들도 포함한다.The embodiments described and illustrated herein also include complementary embodiments thereof.

본 명세서에서, 단수형은 문구에서 특별히 언급하지 않는 한 복수형도 포함한다. 명세서에서 사용되는 '포함한다(comprise)' 및/또는 '포함하는(comprising)'은 언급된 구성요소는 하나 이상의 다른 구성요소의 존재 또는 추가를 배제하지 않는다.In this specification, the singular form also includes the plural form unless specifically stated in the phrase. As used in the specification, "comprise" and/or "comprising" does not exclude the presence or addition of one or more other components.

이하, 도면을 참조하여 본 발명을 상세히 설명하도록 한다. 아래의 특정 실시예들을 기술하는데 있어서, 여러가지의 특정적인 내용들은 발명을 더 구체적으로 설명하고 이해를 돕기 위해 작성되었다. 하지만 본 발명을 이해할 수 있을 정도로 이 분야의 지식을 갖고 있는 독자는 이러한 여러 가지의 특정적인 내용들이 없어도 사용될수 있다는 것을 인지할 수 있다. 어떤 경우에는, 발명을 기술하는 데 있어서 흔히 알려졌으면서 발명과 크게 관련 없는 부분들은 본 발명을 설명하는 데 있어 혼돈을 막기 위해 기술하지 않음을 미리 언급해 둔다.Hereinafter, the present invention will be described in detail with reference to the drawings. In describing the specific embodiments below, various specific contents have been prepared to more specifically describe the invention and to aid understanding. However, readers who have knowledge in this field enough to understand the present invention can recognize that it can be used without these various specific contents. In some instances, it should be noted in advance that parts that are commonly known in describing the invention and are not significantly related to the invention are not described in order to avoid confusion in describing the invention.

도 1은 본 발명의 제 1실시예에 따른 흙막이 벽체용 지지빔의 제조방법을 나타내는 순서도이고, 도 2는 도 1의 S30단계를 나타내는 세부순서도이고, 도 3은 도 1의 S30단계를 나타내는 구성도이고, 도 4는 도 1의 S60단계를 나타내는 흙막이 벽체용 지지빔을 나타내는 사시도이고, 도 5는 도 1의 S70단계를 나타내는 흙막이 벽체용 지지빔을 나타내는 구성도이다.1 is a flow chart showing a method of manufacturing a support beam for a retaining wall according to a first embodiment of the present invention, FIG. 2 is a detailed flowchart showing step S30 of FIG. 1, and FIG. 3 is a configuration showing step S30 of FIG. FIG. 4 is a perspective view showing a support beam for a retaining wall representing step S60 of FIG. 1, and FIG. 5 is a configuration diagram showing a support beam for a retaining wall representing step S70 of FIG. 1.

도 1 내지 도 5에 도시된 바와 같이, 본 발명의 제 1실시예는 토압이 작용하는 방향과 반대방향으로 프리스트레스를 도입될 수 있도록 하되, 2의 지지빔을 동시에 제작하여 제조단가를 낮출 수 있도록 한 흙막이 벽체용 지지빔의 제조방법에 관한 것이다.As shown in Figs. 1 to 5, the first embodiment of the present invention allows prestress to be introduced in a direction opposite to the direction in which earth pressure acts, but to reduce the manufacturing cost by simultaneously manufacturing two support beams. It relates to a method of manufacturing a support beam for a retaining wall.

먼저 S10단계에서는 내부가 중공인 한쌍의 지지빔(10)을 준비한다.First, in step S10, a pair of support beams 10 having a hollow inside are prepared.

이 때 상기 지지빔(10)은 사각의 단면 또는 원형 단면으로 구성할 수 있으며, 이이외에 삼각, 오각 등 다각형의 형태로 제조될 수 있다.In this case, the support beam 10 may have a rectangular cross section or a circular cross section, and may be manufactured in a polygonal shape such as a triangle or a pentagon.

이러한 지지빔(10)은 지중에 삽입되는 고정단에 원뿔 형태의 삽입부(11)를 형성할 수 있다.The support beam 10 may form a cone-shaped insertion portion 11 at a fixed end inserted into the ground.

그리고 삽입부(11)의 둘레에는 콘크리트를 주입할때 공기를 배출하기 위한 다수의 통공(12)을 형성할 수 있다.In addition, a plurality of through holes 12 for discharging air when concrete is injected may be formed around the insert 11.

또한 상기 지지빔(10)은 인장력과 강성을 보강하기 위해 내부 4방면에는 중심방향으로 돌출된 스플라인 형태의 리브(미도시)를 형성하거나 철근(미도시)을 배근할 수 있다.In addition, the support beam 10 may form a spline-shaped rib (not shown) protruding in the center direction or reinforced reinforcing bars (not shown) on the four inner sides to reinforce tensile force and rigidity.

S20단계에서는 지중에 삽입되는 각 지지빔(10)의 하부영역을 단일 고정지그(40)에 일정간격을 두고 삽입하여 직립 고정한다.In step S20, the lower region of each support beam 10 inserted into the ground is inserted into a single fixing jig 40 at regular intervals and fixed upright.

여기서 상기 고정지그(40) 이외에 다양한 수단을 대체하여 사용할 수 있으며, 다만 해체가 용이한 수단이 요구된다.Here, a variety of means other than the fixing jig 40 can be used instead, but a means for easy disassembly is required.

상기에서 고정지그(40)에는 2개의 지지빔을 가이드할 수 있는 삽입구가 형성되는데 상기 삽입구는 지지빔(10)과의 유격이 확보될 수 있는 크기가 요구된다.In the above, the fixing jig 40 is provided with an insertion hole capable of guiding the two support beams, and the insertion hole is required to have a size capable of securing a clearance with the support beam 10.

이는 상기 고정지그(40)의 하부에는 각 지지빔(10)의 하단부에 결합되는 보조지그(41) 또는 반력수단을 더 설치하여(S21) 고정지그(40)를 중심으로 상기 각 지지빔(10)의 하단부에는 발생된 반력이 발생되도록 하고, 이로 인해 고정지그(40)의 하부 영역에서 역방향으로 휨 모멘트가 발생될 수 있도록 하기 위함이다.This is achieved by further installing an auxiliary jig 41 or a reaction force unit coupled to the lower end of each support beam 10 at the lower part of the fixing jig 40 (S21), and the support beam 10 This is to allow the generated reaction force to be generated at the lower end of the ), thereby generating a bending moment in the reverse direction in the lower region of the fixing jig 40.

따라서 지중에 삽입되는 각 지지빔(10) 역시 프리스트레스가 도입될 수 있다.Therefore, each support beam 10 inserted into the ground may also be prestressed.

상기에서 반력수단을 사용할 경우에는 후술되는 인장수단과 동일한 하중잭 또는 스트레스와이어를 이용한 인장기를 사용할 수 있다.In the case of using the reaction force in the above, a tensioner using the same load jack or stress wire as the tensioning means described later may be used.

S30단계는 상기 각 지지빔(10)에 휨 모멘트가 발생되도록 상기 각 지지빔(10)의 사이로 인장수단(30)을 장착시켜 인장력을 동시에 가할 수 있다.In step S30, a tensile force may be simultaneously applied by mounting a tensioning means 30 between the support beams 10 so that a bending moment is generated in each of the support beams 10.

이 때 상기 각 지지빔(10)은 상호 간 동일 높이를 갖게 수평 레벨을 맞추는 것이 선행되어야 한다.At this time, it should be preceded that each of the support beams 10 is aligned with the horizontal level to have the same height with each other.

그리고 인장수단(30)은 인장잭 또는 스트레스와이어를 이용한 인장기 중 선택되는 어느 하나이고, 상기 인장수단(30)은 소성변형을 방지하기 위해 극한 휨 모멘트 이하로 인장력을 가하여 상기 각 지지빔(10)에 프리스트레스를 최대한 확보되도록 할 수 있다.And the tensioning means 30 is any one selected from a tensioner using a tension jack or a stress wire, and the tensioning means 30 applies a tensile force below an extreme bending moment to prevent plastic deformation, so that each of the support beams 10 ) Can be secured as much as possible.

한편 상기 S30단계는 지지빔(10)의 강성 또는 지지빔(10)의 길이에 따라 휨 모멘트를 분산시키기 위해 적어도 2개 이상의 인장수단(30)을 설치할 수 있다.Meanwhile, in step S30, at least two or more tensioning means 30 may be installed in order to disperse the bending moment according to the rigidity of the support beam 10 or the length of the support beam 10.

이를 위해 먼저 각 지지빔(10)은 휨 모멘트가 적용되는 부위를 등분시킨 다음, 등분된 지점을 펜으로 마킹한다.(S31)For this, first, each support beam 10 divides a portion to which the bending moment is applied, and then marks the divided point with a pen (S31).

그리고 상기 마킹된 부위에 인장수단(30)을 장착하고(S32), 이 후에 상기 각 인장수단(30)을 통해 지지빔(10)에 인장력을 가할 수 있다.In addition, the tensioning means 30 may be mounted on the marked portion (S32), and thereafter, a tensile force may be applied to the support beam 10 through the respective tensioning means 30.

상기 각 인장수단(30) 중 토류압력이 큰 지점에 장착된 인장수단(30)은 지지빔(10)의 극한 휨 모멘트 이하로 인장력를 가하고, 상대적으로 토류압력이 약한 지점에 장착된 인장수단(30)은 상대적으로 작은 인장력을 가하는 것이 바람직하다.(S33)The tensioning means 30 mounted at the point where the earth pressure is high among the respective tensioning means 30 applies a tensile force below the ultimate bending moment of the support beam 10, and the tensioning means 30 mounted at a point where the earth pressure is relatively weak. ) Is desirable to apply a relatively small tensile force (S33)

이 때 상기 인장수단(30)에는 로드셀(31)을 연결하여 규격화된 휨 모멘트를 부여할 수 있다.In this case, a normalized bending moment may be provided by connecting the load cell 31 to the tensioning means 30.

S40단계에서는 휨 모멘트가 발생된 상기 각 지지빔(10)의 내부로 고강도 콘크리트(14)를 주입한다.In step S40, high-strength concrete 14 is injected into the inside of each of the support beams 10 in which a bending moment is generated.

상기 고강도 콘크리트(14)는 금속재질의 지지빔(10)의 가지고 있는 인장력과 더불어 인장수단(30)의 인장력을 해체한다 하더라도 도입된 프리스트레스를 보존하기 위한 것이다.The high-strength concrete 14 is for preserving the introduced prestress even if the tensile force of the tensioning means 30 is dismantled together with the tensile force of the support beam 10 made of a metal material.

여기서 상기 각 지지빔(10)은 직립 설치되기 때문에 개방된 상부를 통해 콘크리트를 공급하며 자중에 의해 콘크리트(14)가 지지빔(10)의 하부까지 타설된다.Here, since each of the support beams 10 is installed upright, concrete is supplied through the open upper portion, and the concrete 14 is poured to the lower portion of the support beam 10 by its own weight.

S50단계에서는 상기 고강도 콘크리트(14)를 양생시켜 상기 각 지지빔(10)의 내부에서 충전된 콘크리트(14)에 압축된 잔류 프리스트레스를 도입시킨다.In step S50, the high-strength concrete 14 is cured to introduce the compressed residual prestress into the concrete 14 filled in each of the support beams 10.

여기서 인장수단(30)의 인장력을 제거하면 지지빔(10)의 탄성변형(원래 상태로 복귀하는 힘)에 의해 콘크리트(14)가 압축되고, 압축된 콘크리트(14)는 잔류 프리스트레스가 가지고 있는 상태로 지지빔(10)의 내부에 충전된다.Here, when the tensile force of the tensioning means 30 is removed, the concrete 14 is compressed by the elastic deformation of the support beam 10 (the force to return to its original state), and the compressed concrete 14 is the state that the residual prestress has. The furnace is filled in the support beam 10.

보다 상세하게는 인장력을 제거하면 상기 지지빔(10)은 탄성변형에 의해 50% ~ 60% 정도 원래 형태로 복원되고, 50% 정도의 인장력은 콘크리트(14)에 잔류 프리스트레스 형태로 보존된다.In more detail, when the tensile force is removed, the support beam 10 is restored to its original shape by about 50% to 60% by elastic deformation, and about 50% of the tensile force is preserved in the concrete 14 in the form of residual prestress.

이에 따라 상기 프리스트레스가 도입된 지지빔(10)은 거의 곡선 구간을 최소화하여 수평상태를 이루게 되며, 이에 따라 토류판의 설치를 용이하게 해준다.Accordingly, the support beam 10 into which the pre-stress is introduced is in a horizontal state by substantially minimizing a curved section, thereby facilitating installation of the earth plate.

S60단계에서는 상기 각 지지빔(10)은 인장수단(30)과, 고정지그(40) 및 보조지그(41)와 해체시켜 프리스트레스가 도입된 흙막이 벽체용 지지빔(100)을 완성한다.In step S60, each of the support beams 10 is disassembled from the tensioning means 30, the fixing jig 40, and the auxiliary jig 41 to complete the support beam 100 for the prestressed wall.

이렇게 제조된 흙막이 벽체용 지지빔(10)은 토압이 작용하는 방향과 반대방향으로 설치된다. The support beam 10 for the earthing wall manufactured in this way is installed in a direction opposite to the direction in which the earth pressure acts.

한편 본 발명의 흙막이 벽체용 지지빔(100)의 길이가 10m ~ 20m의 범위로 요구될 경우, 상기 S50단계 이후, 흙막이 벽체용 지지빔(100)의 상부에 커플러(15)를 이용하여 별도의 연장빔(20)을 더 연결하는 단계(S60)를 더 포함할 수 있다.On the other hand, if the length of the support beam 100 for a retaining wall of the present invention is required in the range of 10 m to 20 m, after the step S50, a separate coupler 15 is used on the upper part of the support beam 100 for a retaining wall. A step (S60) of further connecting the extension beams 20 may be further included.

이러한 연장빔(20)은 토압이 크게 받지 않을 경우, 일반 지지빔(10)을 사용할 수 있고, 선택적으로 전술된 단계를 거쳐 제조된 지지빔을 사용할 수 있다. When the extension beam 20 is not subjected to a large earth pressure, a general support beam 10 may be used, and a support beam manufactured through the above-described steps may be optionally used.

상술된 흙막이 벽체용 지지빔의 제조방법을 이용한 흙막이 벽체용 지지빔(10)은 토압이 작용하는 방향과 반대방향으로 설치된다.The support beam 10 for the earth retaining wall using the method of manufacturing the support beam for the earth retaining wall described above is installed in a direction opposite to the direction in which the earth pressure acts.

본 발명의 흙막이 벽체용 지지빔의 제조방법 및 이를 이용한 흙막이 벽체용 지지빔은 다음과 같은 차별적인 특징을 갖는다.The method of manufacturing a support beam for a retaining wall of the present invention and a support beam for a retaining wall using the same have the following distinctive features.

첫째: 종래의 프리스트레스를 도입하기 위해 지지빔의 측면에 강선을 장착한 구조보다 제작비가 저렴한 특징이 있다.First: In order to introduce the conventional prestress, it has a feature of lower manufacturing cost than a structure in which a steel wire is mounted on the side of the support beam.

둘째: 제조방법이 간단하여 현장 제작이 가능한 특징이 있다.Second: It is characterized by a simple manufacturing method that enables on-site manufacturing.

셋째: 충전된 콘크리트에 의해 프리스트레스를 최대한 확보하여 별도의 버팀보나 띠장 없이 자립 설치할 수 있는 특징이 있다.Third: It has the characteristic that it can be installed independently without a separate support or belt by securing the prestress as much as possible by the filled concrete.

넷째: 2개의 프리스트레스 충전 지지빔을 동시 제작하여 가격은 물론 생산성을 향상시킬 수 있는 특징이 있다.Fourth: It has the characteristic that it can improve productivity as well as price by simultaneously manufacturing two prestressed filling support beams.

다섯째: 흙막이 벽체용 지지빔은 곡선 구간 없이 수평 상태를 최대한 유지하여 토류판의 설치를 용이하게 할 수 있는 특징이 있다.Fifth: The support beam for the earthen wall has a feature that can facilitate installation of the earth plate by maintaining the horizontal state as much as possible without a curved section.

도 6은 본 발명의 제 2실시예에 따른 흙막이 벽체용 지지빔의 제조방법을 나타내는 순서도이고, 도 7은, 도 6의 S30단계를 나타내는 세부순서도이고, 도 8은 도 6의 S30단계를 나타내는 구성도이다.6 is a flow chart showing a method of manufacturing a support beam for a retaining wall according to a second embodiment of the present invention, FIG. 7 is a detailed flowchart showing step S30 of FIG. 6, and FIG. 8 is a diagram showing step S30 of FIG. It is a configuration diagram.

도 6 내지 도 8에 도시된 바와 같이, 제 2실시예는 제 1실시예를 포함하며, 다만 깊은 굴착에 사용되는 10m ~ 20m 범위의 지지빔의 경우에는 토압이 상대적으로 크게 작용하는 바, 단일의 휨 모멘트 영역으로는 이를 적용할 수 없어 적어도 2개 이상의 휨 모멘트 영역을 형성한 흙막이 벽체용 지지빔(100)의 제조방법에 관한 것이다.As shown in Figs. 6 to 8, the second embodiment includes the first embodiment, but in the case of the support beam in the range of 10m to 20m used for deep excavation, the earth pressure acts relatively large. Since it cannot be applied to the bending moment region of, it relates to a method of manufacturing a support beam 100 for a retaining wall in which at least two bending moment regions are formed.

이를 위해 S30단계는 각 지지빔(10)을 길이방향으로 등분시켜 마킹하는 단계;(S31)와, 상기 마킹된 부위에 복수의 인장수단(30)과 버팀목(50) 또는 고정지그를 상호 간 교번되게 장착하는 단계;(S32)와, 상기 각 인장수단(30)을 인장력을 가하여 상기 각 지지빔(10)에 적어도 2개 이상의 휨 모멘트를 구간을 형성시키는 단계;(S33)를 더 포함하여 구성된다.To this end, step S30 is a step of dividing each support beam 10 into equal parts in the longitudinal direction and marking; (S31), a plurality of tensioning means 30 and a support 50 or a fixing jig are alternately alternating with each other at the marked portion. (S32), and applying a tensile force to each of the tensioning means (30) to form a section with at least two bending moments to each of the support beams (10); (S33) do.

상기 S32단계에서는 휨 모멘트 구간 사이의 지점에 표기된 마킹에는 반력이 발생되도록 버팀목(50)을 또는 고정지그 또는 반력수단을 장착하여 고정할 수 있다.In the step S32, the support 50 may be mounted or a fixing jig or reaction force means may be mounted to fix the markings marked at points between the bending moment sections so that reaction force is generated.

그리고 휨 모멘트 지점 영역에 표기된 마킹에는 인장수단(30)을 각각 설치하게 된다.Further, the tensioning means 30 are respectively installed on the markings marked in the bending moment point area.

그리고 S33단계에서는 상기 각 인장수단(30)에 인장력을 가하여 각각의 지지빔(10)에 적어도 2개 이상의 휨 모멘트가 발생되도록 하여 다단으로 프리스트레스를 최대한 확보되도록 할 수 있다.Further, in step S33, a tensile force is applied to each of the tensioning means 30 so that at least two or more bending moments are generated in each of the support beams 10, so that prestress can be secured as much as possible in multiple stages.

제 2실시예는 제 1실시예와는 달리 하나의 지지빔(10)에 다단으로 프리스트레스를 도입하여 별도의 연장빔을 연결할 필요가 없어 제조가 간단한 특징이 있다.The second embodiment, unlike the first embodiment, has a feature of being simple to manufacture because it does not require a separate extension beam to be connected by introducing pre-stress to one support beam 10 in multiple stages.

이상에서와 같이, 본 발명의 흙막이 벽체용 지지빔의 제조방법 및 이를 이용한 흙막이 벽체용 지지빔은 띠장으로 사용할 수 있음은 물론이다.As described above, it goes without saying that the method of manufacturing a support beam for a retaining wall of the present invention and a support beam for a retaining wall using the same can be used as a strip.

본 명세서에 기재된 실시예와 도면에 도시된 구성은 본 발명의 가장 바람직한 일 실시예에 불과할 뿐이고 본 발명의 기술적 사상을 모두 대변하는 것은 아니므로, 본 출원시점에 있어서 이들을 대체할 수 있는 다양한 균등물과 변형 예들이 있을 수 있음을 이해하여야 한다.Since the embodiments described in this specification and the configurations shown in the drawings are only the most preferred embodiments of the present invention and do not represent all the technical spirit of the present invention, various equivalents that can replace them at the time of application And it should be understood that there may be variations.

10: 지지빔 11: 삽입부 12: 통공
14: 콘크리트 15: 커플러
20: 연장빔
30: 인장수단 31: 로드셀
40: 고정지그 41: 보조지그
50: 버팀보
100: 흙막이 벽체용 지지빔
10: support beam 11: insertion part 12: through hole
14: concrete 15: coupler
20: extended beam
30: tensioning means 31: load cell
40: fixed jig 41: auxiliary jig
50: support
100: support beam for earthing wall

Claims (7)

흙막이 벽체의 토류패널을 지지하기 위해 지중에 고정되는 흙막이 벽체용 지지빔의 제조방법에 있어서,
내부가 중공인 한쌍의 지지빔(10)을 준비하는 단계;(S10)
지중에 삽입되는 각 지지빔(10)의 하부영역을 단일 고정지그(40)에 일정간격을 두고 삽입하여 직립 고정하는 단계;(S20)
상기 각 지지빔(10)에 휨 모멘트가 발생되도록 상기 각 지지빔(10)의 사이로 인장수단(30)을 장착시켜 인장력을 동시에 가하는 단계;(S30)
휨 모멘트가 발생된 상기 각 지지빔의 내부로 고강도 콘크리트를 주입하는 단계;(S40)
상기 고강도 콘크리트(14)를 양생시켜 상기 각 지지빔(10)의 내부에서 충전된 콘크리트(14)에 압축된 잔류 프리스트레스를 도입하는 단계;(S50) 및
상기 각 지지빔(10)을 인장수단(30)과, 고정지그(40)에서 해체한 후 프리스트레스가 도입된 흙막이 벽체용 지지빔(100)을 완성하는 단계;(S60)를 포함하여 구성되되,
상기 흙막이 벽체용 지지빔은 토압이 작용하는 방향과 반대방향으로 휨 모멘트가 발생되게 설치되는 것을 특징으로 하는 흙막이 벽체용 지지빔의 제조방법.
In the method of manufacturing a support beam for a retaining wall that is fixed in the ground to support the earth panel of the retaining wall,
Preparing a pair of support beams 10 with a hollow inside; (S10)
Inserting a lower region of each support beam 10 inserted into the ground at a predetermined interval into a single fixing jig 40 and fixing it upright; (S20)
A step of simultaneously applying a tensile force by attaching a tensioning means 30 between each of the support beams 10 so that a bending moment is generated in each of the support beams 10; (S30)
Injecting high-strength concrete into the inside of each of the support beams in which a bending moment is generated; (S40)
Curing the high-strength concrete 14 to introduce the compressed residual prestress into the concrete 14 filled in each of the support beams 10; (S50) and
Completing the support beam 100 for the pre-stressed prestressing wall after disassembling each of the support beams 10 from the tensioning means 30 and the fixing jig 40; (S60), including,
The method of manufacturing a support beam for a retaining wall, characterized in that the support beam for the retaining wall is installed to generate a bending moment in a direction opposite to the direction in which the earth pressure acts.
제 1항에 있어서,
상기 S30단계의 인장수단(30)은 인장잭 또는 강선을 이용한 인장기 중 선택되는 어느 하나이고,
상기 인장수단(30)은 소성변형을 방지하기 위해 극한 휨 모멘트 이하로 인장력을 가하는 것을 특징으로 하는 흙막이 벽체용 지지빔의 제조방법.
The method of claim 1,
The tensioning means 30 of the step S30 is any one selected from a tensioning jack or a tensioner using a steel wire,
The tensioning means (30) is a method of manufacturing a support beam for a retaining wall, characterized in that applying a tensile force below an extreme bending moment to prevent plastic deformation.
제 1항에 있어서,
상기 S30단계는 각 지지빔(10)에 휨 모멘트가 적용되는 부위를 등분시킨 다음, 등분된 지점을 펜으로 마킹하는 단계;(S31)와,
상기 마킹된 부위에 복수의 인장수단을 장착하는 단계;(S32)와,
상기 각 인장수단을 인장력을 가하되, 상기 각 인장수단(30) 중 토류압력이 큰 지점에 장착된 인장수단(30)은 지지빔(10)의 극한 휨 모멘트 이하로 인장력를 가하고, 상대적으로 토류압력이 약한 지점에 장착된 인장수단(30)은 상대적으로 작은 인장력을 가하는 단계;(S33)를 더 포함하는 것을 특징으로 하는 흙막이 벽체용 지지빔의 제조방법.
The method of claim 1,
The step S30 is a step of dividing a portion to which a bending moment is applied to each support beam 10, and then marking the divided point with a pen; (S31) and,
Mounting a plurality of tensioning means on the marked portion; (S32) and,
The tensioning force is applied to each of the tensioning means, but the tensioning means 30 mounted at a point where the earth pressure is high among the tensioning means 30 applies a tensile force less than the ultimate bending moment of the support beam 10, and a relatively earth pressure The tensioning means 30 mounted at the weak point is a step of applying a relatively small tensile force; (S33) a method of manufacturing a support beam for a retaining wall, characterized in that it further comprises.
제 1항에 있어서,
상기 S30단계는 각 지지빔(10)을 길이방향으로 등분시켜 마킹하는 단계;(S31)와, 상기 마킹된 부위에 복수의 인장수단(30)과 버팀목(50) 또는 고정지그를 상호 간 교번되게 장착하는 단계;(S32)와, 상기 각 인장수단(30)을 인장력을 가하여 상기 각 지지빔(10)에 적어도 2개 이상의 휨 모멘트를 구간을 형성시키는 단계;(S33)를 더 포함하는 것을 특징으로 하는 흙막이 벽체용 지지빔의 제조방법.
The method of claim 1,
The step S30 is a step of dividing each support beam 10 in the longitudinal direction and marking; (S31), a plurality of tensioning means 30 and a support 50 or a fixing jig are alternately alternated with each other at the marked portion Mounting; (S32), and applying a tensile force to each of the tensioning means (30) to form a section of at least two or more bending moments to each of the support beams (10); (S33) characterized by further comprising Method of manufacturing a support beam for a wall covering the earth.
제 1항 또는 제 3항에 있어서,
상기 S60단계 이후, 흙막이 벽체용 지지빔의 상부에 커플러(15)를 이용하여 별도의 연장빔(20)을 더 연결하는 단계;(S70)를 더 포함하는 것을 특징으로 하는 흙막이 벽체용 지지빔의 제조방법.
The method of claim 1 or 3,
After the step S60, further connecting a separate extension beam 20 using a coupler 15 to the upper part of the support beam for the retaining wall; (S70) of the support beam for the retaining wall, characterized in that it further comprises Manufacturing method.
제 1항에 있어서,
상기 S20단계는 상기 고정지그(40)의 하부에는 각 지지빔(10)의 하단부에 결합되는 보조지그(41) 또는 반력수단을 더 설치하는 단계;(S21)를 더 포함하는 것을 특징으로 하는 흙막이 벽체용 지지빔의 제조방법.
The method of claim 1,
The step S20 is a step of further installing an auxiliary jig 41 or a reaction force unit coupled to the lower end of each support beam 10 at a lower portion of the fixing jig 40; (S21) Method of manufacturing support beam for wall.
제 1항 내지 제 6항 중 어느 하나의 흙막이 벽체용 지지빔의 제조방법을 이용한 흙막이 벽체용 지지빔.A support beam for a retaining wall using the method of manufacturing a support beam for a retaining wall according to any one of claims 1 to 6.
KR1020190048095A 2019-04-24 2019-04-24 Method of manufacturing support beam for retaining wall and support beam for retaining wall using the same KR102324327B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020190048095A KR102324327B1 (en) 2019-04-24 2019-04-24 Method of manufacturing support beam for retaining wall and support beam for retaining wall using the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020190048095A KR102324327B1 (en) 2019-04-24 2019-04-24 Method of manufacturing support beam for retaining wall and support beam for retaining wall using the same

Publications (2)

Publication Number Publication Date
KR20200124579A true KR20200124579A (en) 2020-11-03
KR102324327B1 KR102324327B1 (en) 2021-11-09

Family

ID=73197986

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020190048095A KR102324327B1 (en) 2019-04-24 2019-04-24 Method of manufacturing support beam for retaining wall and support beam for retaining wall using the same

Country Status (1)

Country Link
KR (1) KR102324327B1 (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020010390A (en) * 2000-07-29 2002-02-04 김회준 Prestressed composition pile and the manufacturing process
KR20040011113A (en) * 2002-07-29 2004-02-05 김정민 A method of construction for temporary retaining wall
US20070092341A1 (en) * 2005-10-21 2007-04-26 John Schmertmann Method and apparatus for increasing the force needed to move a pile axially
KR100768031B1 (en) * 2006-06-29 2007-10-19 (주)스틸엔콘크리트 Complex pile commected integral steel pile to prestressed concrete composite pile and method for working using it
KR101452185B1 (en) * 2013-07-29 2014-10-22 이동선 Concrete Composite Steel Pile and Its Manufacturing Apparatus and Method
KR101609805B1 (en) 2015-08-25 2016-04-06 오용환 Freestanding temporary retaining and its construction method with prestressed piles introduced

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020010390A (en) * 2000-07-29 2002-02-04 김회준 Prestressed composition pile and the manufacturing process
KR20040011113A (en) * 2002-07-29 2004-02-05 김정민 A method of construction for temporary retaining wall
US20070092341A1 (en) * 2005-10-21 2007-04-26 John Schmertmann Method and apparatus for increasing the force needed to move a pile axially
KR100768031B1 (en) * 2006-06-29 2007-10-19 (주)스틸엔콘크리트 Complex pile commected integral steel pile to prestressed concrete composite pile and method for working using it
KR101452185B1 (en) * 2013-07-29 2014-10-22 이동선 Concrete Composite Steel Pile and Its Manufacturing Apparatus and Method
KR101609805B1 (en) 2015-08-25 2016-04-06 오용환 Freestanding temporary retaining and its construction method with prestressed piles introduced

Also Published As

Publication number Publication date
KR102324327B1 (en) 2021-11-09

Similar Documents

Publication Publication Date Title
KR102312008B1 (en) Two Rows type Self reliance retaining wall construction method Using the Prestressed pile
KR20090037419A (en) Method for constructing precast coping by using multi-step tensioning
KR20130006420A (en) Method of constructing underground structure to be newly built
KR20200032316A (en) Method for Forming Top-down-typed Underground Strucutre using Trus-typed Support
KR100973601B1 (en) Braket for supporting wale beam of soil retaining wall and excavation method using the same
KR100916546B1 (en) Underground temporary structure and constructing method thereof
KR101169732B1 (en) Earth anchor and retaining wall using it
KR102478561B1 (en) Connector with insertion groove for wale and strut of earth retaining wall
KR20110060291A (en) Made of iron soil retaining plate and its support structure for form and retaining-wall vertical reinforcement
KR102079981B1 (en) Soil retaining plate and soil retaining plate assembly having the same
JP2000352296A (en) Method o constructing passage just under underground structure
KR102324327B1 (en) Method of manufacturing support beam for retaining wall and support beam for retaining wall using the same
KR100862387B1 (en) Tensional kit for top-down constructing of acupressure lasting anchor and top-down constructing method of acupressure lasting anchor using this
JP6192972B2 (en) Calvert
KR200247053Y1 (en) wale for construction method for defending earth using prestress
JPH1018424A (en) Root wrapping reinforcing structure of column base of steel post or the like
KR102482690B1 (en) Bridge foundation construction method using formwork integrated PC panels
KR20040031451A (en) Prestressed scaffolding method
JP4997207B2 (en) Construction method for underground structures
KR20180131042A (en) Pile and method for constucting same
KR102340926B1 (en) Method of manufacturing prestress charge support beam for retaining wall and prestress charge support beam using the same
KR200308716Y1 (en) Prestressed scaffolding method
JP6218130B2 (en) Seismic reinforcement structure and method for reinforced concrete
KR102542077B1 (en) Temporary Earth Retaining Construction Belt and Construction Method for Temporary Earth Retaining Construction Using It
JP2014173305A (en) Arc form and structure of retaining wall

Legal Events

Date Code Title Description
E902 Notification of reason for refusal
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant