KR20180138389A - Aseismatic Reinforcement Double Steel Frame with Friction Slip Flange, and Aseismatic Reinforcement Method using thereof - Google Patents

Aseismatic Reinforcement Double Steel Frame with Friction Slip Flange, and Aseismatic Reinforcement Method using thereof Download PDF

Info

Publication number
KR20180138389A
KR20180138389A KR1020170078549A KR20170078549A KR20180138389A KR 20180138389 A KR20180138389 A KR 20180138389A KR 1020170078549 A KR1020170078549 A KR 1020170078549A KR 20170078549 A KR20170078549 A KR 20170078549A KR 20180138389 A KR20180138389 A KR 20180138389A
Authority
KR
South Korea
Prior art keywords
steel
concrete structure
reinforced concrete
steel frame
anchor
Prior art date
Application number
KR1020170078549A
Other languages
Korean (ko)
Other versions
KR102074251B1 (en
Inventor
박상태
Original Assignee
씨엠알기술연구원(주)
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 씨엠알기술연구원(주) filed Critical 씨엠알기술연구원(주)
Priority to KR1020170078549A priority Critical patent/KR102074251B1/en
Publication of KR20180138389A publication Critical patent/KR20180138389A/en
Application granted granted Critical
Publication of KR102074251B1 publication Critical patent/KR102074251B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H9/00Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate
    • E04H9/02Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate withstanding earthquake or sinking of ground
    • E04H9/021Bearing, supporting or connecting constructions specially adapted for such buildings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0218Increasing or restoring the load-bearing capacity of building construction elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H9/00Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate
    • E04H9/02Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate withstanding earthquake or sinking of ground
    • E04H9/027Preventive constructional measures against earthquake damage in existing buildings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Emergency Management (AREA)
  • Business, Economics & Management (AREA)
  • Environmental & Geological Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Electrochemistry (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Chemical & Material Sciences (AREA)
  • Working Measures On Existing Buildindgs (AREA)
  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

The present invention relates to a dual iron frame for earthquake-proof reinforcement with a friction flange mounted on a rebar concrete structure (50), and an earthquake-proof method, wherein the dual iron frame comprises: a flat plate-type anchor plate (100) attached along a base surface of a rebar concrete structure (50) to be reinforced; an anchor bolt (200); a steel member (300); and a plurality of connection members (400). When an earthquake occurs, the integrated behavior of a rebar concrete structure and the earthquake-proof reinforcement device can be secured.

Description

마찰플랜지가 구비된 내진보강용 이중 철골프레임 및 이를 이용한 내진공법{Aseismatic Reinforcement Double Steel Frame with Friction Slip Flange, and Aseismatic Reinforcement Method using thereof}BACKGROUND OF THE INVENTION 1. Field of the Invention [0001] The present invention relates to an anti-seismic reinforced steel frame having a friction flange and a seismic resistant method using the steel frame,

본 발명은 철골프레임을 사용하여 기존의 철근 콘크리트 구조물을 내진 보강할 경우 철근 콘크리트 구조물과 철골프레임의 일체 거동을 확보하여 지진에 효율적으로 대응할 수 있는 새로운 개념의 마찰플랜지가 구비된 내진보강용 이중 철골프레임 및 이를 이용한 내진공법에 관한 것이다.The present invention relates to a reinforced concrete double structure steel frame having a new concept of a friction flange capable of effectively responding to an earthquake by securing an integrated behavior of a reinforced concrete structure and a steel frame frame when an existing reinforced concrete structure is seismically reinforced using a steel frame Frame and an earthquake-proof method using the same.

2016년 9월 경주지진 이래 지진에 대비한 내진보강에 관심이 증대되면서 학교, 공공시설물 등 건축 구조물의 내진보강이 많이 이루어지고 있으며, 일반적으로 기존 철근 콘크리트 구조물의 내진보강은 토글 또는 브레이스가 구비된 마찰댐퍼, 점성댐퍼, 슬릿강재댐퍼 등의 제진보강공법과 철골브레이스, 철골프레임, CF기둥보강 등의 내진보강공법이 활발히 사용되고 있다. Since the earthquake in Gyeongju in September 2016, interest in earthquake-resistant seismic retrofitting has increased, and earthquake-proof reinforcement of buildings, such as schools and public facilities, has been increasing. Generally, seismic retrofitting of existing reinforced concrete structures is carried out with a toggle or brace Seismic reinforcement methods such as friction dampers, viscous dampers, and slit steel dampers have been actively used, as well as seismic retrofitting methods such as steel braces, steel frame and CF column reinforcement.

그러나 상기한 여러 종류의 내진보강공법들의 자체 성능은 다양한 실험 및 다수의 실적을 통하여 어느 정도 확보되었다고 할 수 있으나, 지진 발생시 내진보강장치와 보강대상 철근 콘크리트 구조물의 일체거동을 확보할 수 없다면 이러한 공법들은 무용지물이 될 수 밖에 없다.However, the self-performance of various types of seismic retrofitting techniques described above can be said to be secured to some extent through various experiments and a large number of achievements. However, if the seismic reinforcement device and the reinforcing concrete structure to be reinforced can not secure the integrated behavior, They are inevitable.

따라서 내진보강장치나 공법 자체의 개발과 함께 내진보강장치와 기존 철근 콘크리트 구조물의 일체 거동을 확보할 수 있는 접합구조에 대한 연구 개발의 중요성이 증대되고 있는데, 이와 관련된 선행기술을 살펴보면 다음과 같다.Therefore, the importance of R & D on seismic strengthening apparatuses and joint structures that can secure the integral behavior of existing reinforced concrete structures with the development of the seismic reinforcement apparatuses and the construction method itself is increasing, and the prior art related thereto will be described as follows.

도1(a)와 같이 내진보강용 H형강의 웨브를 보강대상 철근 콘크리트 구조물에 접합하여 내진보강할 경우 보강대상 콘크리트 구조물(1)에 다수의 수지앵커(2)를 1열 또는 2열로 장치하고, 내진보강용 H형강의 웨브(4)에 다수의 스터드볼트(3)를 1열 또는 2열로 용접결합하고, 거푸집을 설치한 후 콘크리트(5)를 타설하는 방법을 주로 사용하고 있는데, 이러한 접합방법은 지진 발생시 불규칙한 지진 에너지(횡하중)에 의하여 필연적으로 콘크리트에 균열이 발생되고, 균열이 발생됨과 동시에 H형강으로 지진하중의 전달이 어려워져 소기의 내진보강효과를 기대하기 어렵다는 문제점이 있다. As shown in FIG. 1 (a), when the web of the H-shaped steel for the reinforcement steel is joined to the reinforced concrete structure to be reinforced, a plurality of resin anchors 2 are installed in one or two rows in the reinforced concrete structure 1 A method in which a plurality of stud bolts 3 are welded to one another in a row or two in a web 4 of an H-shaped steel for an advanced steel and the concrete 5 is installed after the formwork is installed. In this method, cracks are generated in concrete due to irregular seismic energy (lateral load) at the time of earthquake, and it is difficult to transmit the seismic load to the H-shaped steel at the same time as cracks are generated and it is difficult to expect a desired seismic strengthening effect.

또한 도1(b)와 같이 내진보강용 H형강의 플랜지(7)를 보강대상 콘크리트 구조물(1)에 앵커(8) 및 에폭시수지(9)를 사용하여 접합하는 방식으로 내진보강할 경우 도1(c)에 도시된 것처럼 천공드릴(10)을 이용한 앵커구멍 천공작업을 수행해야만 하는데, 이러한 천공작업 과정에서 천공드릴(10)이 상부 플랜지(11)에 간섭되어 규정된 깊이의 수직 천공이 어렵고, 천공작업 과정에서 보강대상 콘크리트 구조물(1) 내부의 철근과 천공드릴이 맞닿을 경우 이를 회피할 수 있는 적절한 방안이 없어 내진보강장치의 견고한 설치가 어려운 문제점이 있다. 아울러 이러한 문제점을 개선하기 위하여 비교적 길이가 긴 천공드릴(13)을 사용하여 앵커구멍 천공작업시 상부플랜지(11)에도 구멍을 뚫는 경우도 있으나 이 방법 역시 천공작업 도중 철근 콘크리트 구조물 내부의 철근과 맞닿을 경우 이를 회피할 적절한 방법이 없을 뿐만 아니라 불필요한 천공 과정이 추가되고, 상부플랜지(11)의 천공에 따른 강도 저하의 결과를 초래하게 된다. 1 (b), when the flange 7 of the H-shaped steel for an advanced steel is joined to the reinforced concrete structure 1 by using the anchor 8 and the epoxy resin 9, it is necessary to perform an anchor hole drilling operation using the drilling hole 10 as shown in FIG. 3 (c). In such a drilling operation, the drilling hole 10 is interfered with the upper flange 11, , There is a problem that when the reinforcing bars and the drilling drill in the concrete structure 1 to be reinforced are in contact with each other during the drilling operation, there is no proper way to avoid this, and it is difficult to securely install the reinforcement. Further, in order to solve such a problem, a hole is drilled in the upper flange 11 during an anchor hole drilling operation using a relatively long drill hole 13, but this method is also applied to the reinforcing concrete structure inside the reinforced concrete structure There is not an appropriate way to avoid this, and an unnecessary drilling process is added, resulting in a decrease in strength due to the perforation of the upper flange 11.

따라서 내진보강용 철골프레임과 기존 철근 콘크리트 구조물의 일체 거동성을 확보할 수 있는 보다 효과적인 접합구조 및 내진공법의 개발이 시급히 요구되고 있는 실정이다.Therefore, it is urgently required to develop a more effective joint structure and seismic proofing method that can secure the unity mobility between the steel frame of the advanced steel frame and the existing reinforced concrete structure.

[선행기술문헌][Prior Art Literature]

등록특허 제10-1150392호Patent No. 10-1150392

등록특허 제10-1670633호Registration No. 10-1670633

상기한 문제점을 해결하기 위하여 창작된 본 발명의 목적은 다음과 같다.In order to solve the above-mentioned problems, the object of the present invention is as follows.

첫째, 지진 발생시 기존 철근 콘크리트 구조물과 철골프레임의 일체 거동을 확보할 수 있는 마찰플랜지가 구비된 내진보강용 이중 철골프레임 및 내진공법을 제공하는 것을 본 발명의 목적으로 한다. First, it is an object of the present invention to provide a double steel frame and an earthquake-proof method for an internal-progressive steel having a friction flange capable of securing an integrated behavior of an existing reinforced concrete structure and a steel frame at the time of an earthquake.

둘째, 마찰플랜지가 구비된 내진보강용 이중 철골프레임을 기존 철근 콘크리트 구조물과 견고하게 접합할 수 있는 접합구조 및 내진공법을 제공하는 것을 본 발명의 또 다른 목적으로 한다.It is another object of the present invention to provide a joining structure and an earthquake-proofing method capable of firmly joining a reinforced concrete double-steel frame equipped with a friction flange to an existing reinforced concrete structure.

셋째, 시공이 간편하고 철근 콘크리트 구조물의 바탕면 굴곡 편차를 흡수할 수 있는 마찰플랜지가 구비된 내진보강용 이중 철골프레임 및 내진공법을 제공하는 것을 본 발명의 또 다른 목적으로 한다.It is another object of the present invention to provide a double steel frame and an earthquake-proof method for an internal-strength steel having a frictional flange that is simple in construction and capable of absorbing a ground surface flexural deviation of a reinforced concrete structure.

넷째, 일체의 유지관리가 필요 없는 반영구적인 마찰플랜지가 구비된 내진보강용 이중 철골프레임 및 내진공법을 제공하는 것을 본 발명의 또 다른 목적으로 한다.Fourth, another object of the present invention is to provide a double steel frame and an earthquake-resistant method for an internal-strength steel with a semi-permanent friction flange that does not require any maintenance.

본 발명은 철근 콘크리트 구조물(50)에 장착되는 마찰플랜지가 구비된 내진보강용 이중 철골프레임에 관한 것으로서, 보강 대상이 되는 철근 콘크리트 구조물(50)의 바탕면을 따라 부착되는 평판 형태의 앵커플레이트(100); 상기 앵커플레이트(100)에 형성된 앵커볼트장착공(11)을 통과하여 철근 콘크리트 구조물(50)에 매립 장착되는 앵커볼트(200); 철근 콘크리트 구조물(50)에 장착되는 철골부재(300); 및, 일측 단부는 시공 현장에서 상기 앵커플레이트(100)의 외측면에 용접결합되고, 타측 단부는 상기 철골부재(300)를 따라 미리 설정된 거리마다 유동 가능하게 볼트로 가체결되는 다수의 연결부재(400);를 포함하여 구성되고, 상기 앵커플레이트(100)와 철근 콘크리트 구조물(50)의 바탕면 사이에는 상기 앵커볼트(200)가 매립 장착된 상태에서도 간격(gap)이 존재하여 빈 공간이 형성되고, 볼트로 가체결된 상기 연결부재(400)는 시공 현장에서 상기 앵커플레이트(100)에 용접결합된 후 볼트를 완전히 조임으로써 상기 철골부재(300)에 고정되고, 상기 철골부재(300)는 "H"형강으로 제작되어 철근 콘크리트 구조물(50)의 기둥이나 보를 따라 " ㅁ"자 형태의 뼈대를 이루는 구조가 되고, 수직 방향으로 배열되는 좌우 양측의 상기 철골부재(300) 각각은 2개가 나란히 배열되어 한 조를 이루는 이중 구조가 되고, 길게 늘어진 평판 형태의 부재로서 다수의 슬로트홀(33)이 길이 방향으로 구비되고, 이중 구조를 이루는 상기 철골부재(300) 사이에 압착되도록 볼트결합되는 마찰패드(310); 및, 이중 구조를 이루는 상기 철골부재(300)와 상기 마찰패드(310)의 슬로트홀(33)을 통과하도록 체결되어 상기 마찰패드(310)가 수직 방향으로 배열된 상기 철골부재(300) 사이에서 압착되도록 하는 압착볼트(340);를 더 포함하는 것을 특징으로 한다.The present invention relates to a reinforced concrete double-metal frame having a friction flange mounted on a reinforced concrete structure (50). The reinforced concrete frame (50) has a plate-like anchor plate 100); Anchor bolts 200 passing through the anchor bolt mounting holes 11 formed in the anchor plate 100 and being embedded in the reinforced concrete structure 50; A steel member 300 mounted on the reinforced concrete structure 50; And a plurality of connecting members (not shown) which are welded to the outer surface of the anchor plate 100 at one site and welded at a predetermined distance along the steel frame member 300 at the other end, And an anchor bolt (200) is embedded between the anchor plate (100) and the base surface of the reinforced concrete structure (50) The connecting member 400 fastened to the bolt is welded to the anchor plate 100 at the construction site and is fixed to the steel frame member 300 by completely tightening the bolt, H "shaped steel to form a" skeletal "skeleton along the columns or beams of the reinforced concrete structure 50, and two steel members 300 on both the left and right sides arranged in the vertical direction are arranged side by side Arrangement And a plurality of slit holes (33) are provided in the longitudinal direction, and the metal members (300) having a double structure are bolted to be press-bonded between the steel members (300) (310); And between the steel frame member 300 having the double structure and the steel frame members 300 fastened to pass through the slot holes 33 of the friction pad 310 and the friction pads 310 arranged in the vertical direction And a compression bolt (340) to be compressed.

아울러, 본 발명은 마찰플랜지가 구비된 내진보강용 이중 철골프레임을 이용한 내진공법에 관한 것으로서, 기존 마감재의 철거 작업 후 철근 콘크리트 구조물(50)의 보강 부위 바탕면의 페인트 및 이물질을 제거하여 바탕면을 정리하는 제1단계; 앵커플레이트(100)에 형성된 앵커볼트장착공(11)의 패턴에 따라 철근 콘크리트 구조물(50)의 바탕면에 앵커볼트 장착을 위한 구멍을 천공하는 제2단계; 제2단계에서 천공된 구멍에 앵커볼트(200)를 장착하여 앵커플레이트(100)를 철근 콘크리트 구조물(50)의 바탕면과 미리 설정된 거리만큼 간격이 존재하도록 부착하는 제3단계; 철골부재(300)에 고장력볼트로 가조립된 연결부재(400)를 밀거나 당기면서 앵커플레이트(100)의 외측면에 밀착한 후 용접결합하는 제4단계; 가체결된 고장력볼트를 완전히 조임으로써 연결부재(400)와 철골부재(300)를 최종 결합하는 제5단계; 거푸집을 설치한 후 모르타르 또는 콘크리트를 타설양생하여 철근 콘크리트 구조물(50)과 철골부재(300)를 일체로 결합하는 타설양생층(500)을 형성하는 제6단계; 및, 양생이 완료된 후 거푸집을 제거하고 마감공정을 수행하는 제7단계;를 포함하여 구성되는 것을 특징으로 한다.In addition, the present invention relates to a seismic proofing method using a reinforced concrete double-metal frame having a friction flange, wherein after removing the existing finishing material, paint and foreign matter on the reinforcing part of the reinforced concrete structure 50 are removed, A first step of arranging the first step; A second step of drilling a hole for mounting the anchor bolt on the base surface of the reinforced concrete structure 50 according to the pattern of the anchor bolt mounting hole 11 formed in the anchor plate 100; A third step of attaching the anchor bolts 200 to the perforated holes in the second step so that the anchor plates 100 are spaced apart from the base surface of the reinforced concrete structure 50 by a predetermined distance; A fourth step of pressing and joining the connecting member 400 assembled with the high-tension bolt to the steel member 300 while closely contacting the outer surface of the anchor plate 100 and welding the same; A final step of finally joining the connecting member 400 and the steel frame member 300 by tightly fastening the high tension bolt fastened together; A sixth step of placing mortar or concrete on concrete after the mold is installed and forming a cured concrete layer 500 for integrally joining the reinforced concrete structure 50 and the steel frame member 300; And a seventh step of removing the mold after completion of curing and performing a finishing process.

본 발명의 구성에 따른 기술적 효과는 다음과 같다.Technical effects of the configuration of the present invention are as follows.

첫째, 마찰플랜지가 구비된 내진보강용 이중 철골프레임을 기존 철근 콘크리트 구조물과 견고하게 접합하여 지진 발생시 기존 철근 콘크리트 구조물과 내진보강용 철골프레임의 일체 거동을 확보할 수 있다. First, the reinforced concrete double frame steel frame with friction flange is firmly joined with the existing reinforced concrete structure, so that the integrated behavior of the existing reinforced concrete structure and the steel frame for the advanced steel can be ensured when an earthquake occurs.

다시 말하면, 이중 구조의 수직 방향 철골부재(300)와 그 사이에 압착되는 마찰패드(310) 등으로 이루어진 마찰플랜지가 구비된 내진보강용 이중 철골프레임을 기존 철근 콘크리트 구조물의 기둥이나 보를 따라 설치한 후 고강도 무수축 모르타르나 콘크리트를 타설하여 일체화함으로써 지진 발생시에도 기존 철근 콘크리트 구조물과 일체 거동을 보장할 수 있다. In other words, a double steel frame for an advanced steel having a frictional flange composed of a double-structure vertical steel frame member 300 and a friction pad 310 pressed therebetween is installed along a column or a beam of a conventional reinforced concrete structure After the high strength non-shrinkage mortar or concrete is poured and integrated, it is possible to guarantee the integrated behavior with existing reinforced concrete structure even in case of earthquake.

둘째, 시공이 간편하고, 철근 콘크리트 구조물의 바탕면 굴곡 편차를 흡수할 수 있다.Second, it is easy to construct and can absorb the deviation of the ground plane of the reinforced concrete structure.

다시 말하면, 연결부재(400)를 철골부재(300)에 볼트로 가조립만 한 상태에서 연결부재(400)와 앵커플레이트(100)의 용접결합을 수행함으로써 철근 콘크리트 구조물(50)의 바탕면 굴곡 편차나, 앵커플레이트(100) 또는 철골부재(300)의 형상 편차를 흡수하면서 보다 편리하고 신속하게 용접작업을 수행할 수 있다. 왜냐하면, 앵커플레이트(100)와 철근 콘크리트 구조물(50) 사이의 간격과 함께 연결부재(400)도 철골부재(300)에 가조립 상태가 될 경우 앵커플레이트(100), 연결부재(400) 및 철골부재(300)들의 유동성이 충분히 확보되어 연결부재(400)의 웨브 단부가 앵커플레이트(100)의 외측면에 쉽게 밀착되어 용접이 신속하게 이루어질 수 있기 때문이다.In other words, the welded joint of the connecting member 400 and the anchor plate 100 is performed in a state in which the connecting member 400 is bolted to the steel member 300, It is possible to more conveniently and quickly perform the welding work while absorbing the shape variation of the anchor plate 100 or the steel member 300. When the anchor plate 100 and the reinforcing concrete structure 50 are spaced apart from each other and the connecting member 400 is also assembled to the steel frame member 300, the anchor plate 100, the connecting member 400, The fluidity of the anchor plate 300 is sufficiently secured and the web end of the connecting member 400 can be easily brought into close contact with the outer surface of the anchor plate 100,

셋째, 별도의 유지관리가 필요 없는 반영구적인 내진보강용 철골프레임 및 내진공법을 제공할 수 있다.Third, it is possible to provide a semi-permanent advanced steel frame frame and seismic proofing method that do not require separate maintenance.

다시 말하면, 마찰플랜지가 구비된 내진보강용 이중 철골프레임이 기존 철근 콘크리트 구조물(50)과 일체화되어 수명을 함께 함으로써 별도의 유지관리가 불필요하다.In other words, the double-steel frame having the anti-rebate steel frame provided with the friction flange is integrated with the existing reinforced concrete structure 50, so that the lifetime of the reinforced concrete frame 50 is not required.

넷째, 수직 방향으로 배열되는 이중 구조의 철골부재(300) 사이에 마찰패드(310)가 압착되는 구조를 갖춤으로써, 지진과 같은 외력이 작용하여 철골부재(300)의 변위가 발생하면 이에 따라 마찰패드(310)의 슬로트홀(33)이 허여하는 범위 내에서 마찰력이 수반된 유동이 반복적으로 발생하여 외력을 효율적으로 감쇠시킬 수 있다.Fourth, by providing a structure in which the friction pads 310 are pressed between the steel members 300 having a double structure arranged in the vertical direction, when an external force such as an earthquake acts to cause the displacement of the steel member 300, The flow accompanied by the frictional force is repeatedly generated within the range allowed by the slot hole 33 of the pad 310, so that the external force can be effectively damped.

도1은 종래 기술을 도시한다.
도2는 본 발명의 구체적 실시예로서 "T"형강의 연결부재(400)가 철골부재(300)의 플랜지에 결합되는 경우를 도시한다.
도3은 본 발명의 다른 구체적 실시예로서 "ㄷ"형강의 연결부재(400)가 철골부재(300)의 플랜지에 결합되는 경우를 도시한다.
도4a는 기존 철근 콘크리트 구조물(50)의 개구부 내측면을 따라 앵커플레이트(100)를 설치한 상태를 도시한다.
도4b는 앵커플레이트(100)에 연결부재(400)의 일측 단부를 용접결합한 후 가체결된 볼트를 완전히 조인 상태를 도시한다.
도4c는 모르타르나 콘크리트를 타설하여 양생이 완료된 상태를 도시한다.
도5는 수직 방향으로 배열되는 철골부재(300), 마찰패드(310) 및 압착볼트(340)의 결합구조를 도시한다.
도6은 마찰플랜지가 구비된 내진보강용 이중 철골프레임의 지진력 감쇠 개념도이다.
Figure 1 shows a prior art.
2 shows a case in which the connecting member 400 of the " T " shaped steel is coupled to the flange of the steel member 300 as a specific embodiment of the present invention.
3 shows another embodiment of the present invention in which the connecting member 400 of the " D " shape steel is coupled to the flange of the steel member 300.
FIG. 4A shows a state in which the anchor plate 100 is installed along the inner side surface of the opening of the existing reinforced concrete structure 50. FIG.
4B shows a state in which one end of the connecting member 400 is welded to the anchor plate 100, and then the bolt fastened to the anchor plate 100 is fully tightened.
FIG. 4C shows a state in which curing is completed by installing mortar or concrete.
5 shows a coupling structure of the steel member 300, the friction pad 310 and the compression bolt 340 arranged in the vertical direction.
FIG. 6 is a conceptual diagram of a seismic attenuation of a double-wall steel frame for an anti-seam steel provided with a friction flange.

이하에서는 본 발명의 구체적 실시예를 첨부도면을 참조하여 보다 상세히 설명한다.DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Reference will now be made in detail to the preferred embodiments of the present invention, examples of which are illustrated in the accompanying drawings.

본 발명은 철근 콘크리트 구조물(50)에 장착되는 마찰플랜지가 구비된 내진보강용 이중 철골프레임에 관한 것이다.The present invention relates to a double steel frame for an internal-progressive steel provided with a friction flange mounted on a reinforced concrete structure (50).

앵커플레이트(100)는 도2에 도시된 바와 같이 평판 형태의 강판 부재로서 보강 대상이 되는 철근 콘크리트 구조물(50)의 바탕면(표면)을 따라 부착되는데, 주로 기둥이나 보를 따라 설치된다.As shown in FIG. 2, the anchor plate 100 is attached along the base surface (surface) of the reinforced concrete structure 50 to be reinforced as a plate-shaped steel plate member, and is installed mainly along the column or the beam.

아울러 앵커플레이트(100)는 도4a에 도시된 것처럼 다수의 조각으로 이루어져 개별적으로 앵커볼트(200)에 의하여 철근 콘크리트 구조물(50)의 바탕면에 부착되는 구조가 될 수도 있고, 첨부도면에 별도로 도시하지 않았으나 일측으로 길게 늘어진 1개의 강판 부재로 이루어질 수도 있다.In addition, the anchor plate 100 may be a structure having a plurality of pieces as shown in FIG. 4A and attached to the base surface of the reinforced concrete structure 50 individually by the anchor bolts 200, But may be formed of one steel plate member which is elongated to one side.

앵커볼트(200)는 앵커플레이트(100)에 형성된 앵커볼트장착공(11)을 통과하여 철근 콘크리트 구조물(50)에 매립 장착되면서 앵커플레이트(100)를 철근 콘크리트 구조물(50)의 표면에 부착시키는데, 앵커플레이트(100)와 철근 콘크리트 구조물(50)의 표면 사이에는 앵커볼트(200)가 매립 장착된 상태에서도 간격(gap)이 존재하여 빈 공간이 형성되고, 이러한 간격을 통하여 앵커플레이트(100)는 철근 콘크리트 구조물(50)의 표면에 부착된 상태에서도 유동 공간을 확보할 수 있게 된다. 아울러 이러한 간격을 통한 빈 공간에도 타설양생층(500)이 형성됨으로써 철골부재(300)와 철근 콘크리트 구조물(50)의 일체 거동을 확보하게 된다.The anchor bolts 200 pass through the anchor bolt mounting holes 11 formed in the anchor plate 100 and are embedded in the reinforced concrete structure 50 to attach the anchor plate 100 to the surface of the reinforced concrete structure 50 An anchor plate 100 and an anchor plate 100 are formed on the anchor plate 100. The anchor plate 100 has a gap formed between the anchor plate 100 and the surface of the reinforced concrete structure 50, It is possible to secure a fluidized space even in the state of being attached to the surface of the reinforced concrete structure 50. In addition, since the cured layer 500 is formed in the hollow space through the gap, the integrated behavior of the steel frame member 300 and the reinforced concrete structure 50 is secured.

철골부재(300)는 "H"형강과 같은 철골이 사용되는데, 웨브와 플랜지가 구비된 단면이라면 "H"형강이 아니라 "ㄷ"자 형태의 형강이나 "C"형강이 사용될 수도 있다.Steel members such as "H" shaped steel are used for the steel member 300, but "C" shaped steel or "C" shaped steel may be used instead of "H" shaped steel if the cross section provided with the web and flange is used.

이러한 철골부재(300)는 앵커플레이트(100)를 따라 장착되어 지진과 같은 외력이 작용할 경우 이를 전달받아 저항하는 주요 뼈대 역할을 하게 된다.The steel frame member 300 is mounted along the anchor plate 100 and acts as a main frame to receive and resist an external force such as an earthquake.

철골부재(300)는 도4b나 도4c에 도시된 것처럼 기존 철근 콘크리트 구조물(50)의 개구부 내측면을 따라 설치될 수 있는데, 철근 콘크리트 구조물(50)의 기둥이나 보를 따라 " ㅁ"자 형태의 뼈대를 이루는 구조가 될 수 있다.The steel member 300 may be installed along the inner side surface of the opening of the existing reinforced concrete structure 50 as shown in Figs. 4B and 4C. The reinforcing concrete structure 50 may be formed in a " It can be a structure that forms a skeleton.

여기서, 수직 방향으로 배열되는 좌우 양측의 철골부재(300) 각각은 2개가 나란히 배열되어 한 조를 이루는 이중 구조가 된다.Here, each of the right and left steel members 300 arranged in the vertical direction has a double structure in which two steel members 300 are arranged side by side.

도5에는 이러한 이중 구조가 보다 자세하게 도시되어 있는데, 마찰패드(310)가 수직 방향으로 배열되는 2개의 철골부재(300) 사이에 압착되도록 볼트결합되는 구조이다.This double structure is shown in more detail in Fig. 5, in which the friction pad 310 is bolted to be pressed between two steel members 300 arranged in the vertical direction.

마찰패드(310)는 길게 늘어진 평판 형태의 부재로서 다수의 슬로트홀(33)이 길이 방향으로 구비되는데, 금속(강판)으로 제작될 수도 있고 마찰력을 발생시키는 다양한 종류의 패드가 사용될 수도 있다.The friction pad 310 is a member in the form of an elongated flat plate, and is provided with a plurality of slot holes 33 in the longitudinal direction. The friction pad 310 may be made of metal (steel plate) or various kinds of pads that generate frictional force may be used.

압착볼트(340)는 이중 구조를 이루는 철골부재(300) 각각의 플랜지와 마찰패드(310)의 슬로트홀(33)을 통과하도록 체결되어 마찰패드(310)가 수직 방향으로 배열된 철골부재(300) 사이에서 압착되도록 한다.The compression bolts 340 are fastened to the metal members 300 of the double structure through the slit holes 33 of the friction pads 310 and the flanges of the steel members 300, ).

즉, 2개가 나란하게 수직 방향으로 배열되어 한 조를 이루는 철골부재(300)의 플랜지 사이에 마찰패드(310)가 압착볼트(340)로 결합되면서 압착되어 마찰플랜지 역할을 하면서 지진과 같은 외력을 감쇠시키게 된다.In other words, the friction pads 310 are joined together by the compression bolts 340 between the flanges of the steel members 300, which are arranged in the vertical direction in parallel with each other, so that they act as a friction flange while exerting an external force such as an earthquake .

이와 같이 마찰패드(310)가 이중 구조를 이루는 철골부재(300) 각각의 플랜지 사이에 압착되는 구조가 됨으로써 외력이 작용하여 철골부재(300)의 변위가 발생할 경우 마찰패드(310)가 철골부재(300) 각각의 플랜지 사이에서 상대적 이동을 반복하면서 마찰력으로 외력(지진 에너지)을 효율적으로 감쇠시키게 된다.When the friction pad 310 is compressed between the flanges of the steel members 300 having the dual structure, when the external force acts to cause the displacement of the steel member 300, 300), the external force (seismic energy) is efficiently damped by the frictional force while repeating the relative movement between the flanges.

다시 말하면, 도6에 도시된 것처럼 지진 하중(횡력)이 작용하여 철골부재(300)의 수평변위(D)가 발생하면, 이러한 수평변위(D)에 따라 마찰패드(310)에 구비된 슬로트홀(33)이 허용하는 범위(L) 내에서 마찰패드(310)가 철골부재(300)의 플랜지 및 결속지압판(320) 사이에서 상대적 이동을 반복하게 되고, 이러한 과정에서 발생하는 마찰력으로 지진 하중을 흡수하여 감쇠시키게 된다.6, when the horizontal displacement D of the steel frame member 300 is generated due to the action of the seismic load (lateral force) as shown in FIG. 6, The friction pad 310 repeats relative movement between the flange of the steel frame member 300 and the binding pressure plate 320 within a range L allowed by the load 33 and the seismic load Absorbed and attenuated.

마찰패드(310)의 상대적 이동에 따른 마찰력으로 감쇠시킬 수 없는 크기의 지진 하중(횡력)이 작용할 경우에는 최종적으로 슬로트홀(33) 부위가 파단되면서 지진 하중을 흡수하게 된다.When a seismic load (lateral force) of a magnitude that can not be attenuated by the friction force due to the relative movement of the friction pad 310 is applied, the portion of the slot hole 33 is finally broken and the seismic load is absorbed.

연결부재(400)는 철골부재(300)를 따라 미리 설정된 거리마다 볼트로 가체결되는데, 연결부재(400)의 일측 단부는 시공 현장에서 앵커플레이트(100)의 외측면에 용접결합되고, 연결부재(400)의 타측 단부는 용접결합한 후 볼트를 완전히 조임으로써 철골부재(300)에 최종적으로 고정된다.One end of the connecting member 400 is welded to the outer surface of the anchor plate 100 at the construction site, and the connecting member 400 is welded to the outer surface of the anchor plate 100, The other end of the steel member 400 is welded and finally fixed to the steel frame member 300 by fully tightening the bolt.

즉, 연결부재(400)는 철골부재(300)에 볼트로 가체결된 상태로 시공 현장에 공급되고, 시공 현장에서 연결부재(400)와 앵커플레이트(100)를 먼저 용접결합한 후 볼트를 완전히 조임으로써 볼트결합이 완료된다.That is, the connecting member 400 is supplied to the construction site in a state where the bolt is fastened to the steel frame member 300. At the construction site, the connecting member 400 and the anchor plate 100 are first welded, The bolt connection is completed.

이러한 연결부재(400)는 도2에 도시된 바와 같이 "T"형강으로 제작되거나 도3에 도시된 것처럼 "ㄷ"형강으로 제작될 수 있는데, 경우에 따라서는 평판을 서로 용접하여 "T"형 단면이나 "ㄷ"형 단면 형태의 부재를 제작하여 사용할 수도 있다. 아울러, 연결부재(400)에는 타설되는 고강도 무수축 모르타르 또는 콘크리트가 통과하는 통과공(22)이 다수 구비된다.This connecting member 400 can be made of "T" shaped steel as shown in FIG. 2 or "C" shaped steel as shown in FIG. 3, where the plates are welded together to form a "T" Member having a cross-sectional shape or a " C " -shaped cross-sectional shape may be produced and used. In addition, the connection member 400 is provided with a plurality of through holes 22 through which high-strength non-shrinkage mortar or concrete is inserted.

연결부재(400)가 "T"형강으로 제작될 경우 연결부재(400) 웨브의 단면부가 앵커플레이트(100)의 외측면에 용접결합되고, 연결부재(400)의 플랜지 외측면이 철골부재(300)의 일측 플랜지 외측면에 맞닿도록 볼트결합된다.When the connecting member 400 is made of a T-shaped steel, the end surface of the web of the connecting member 400 is welded to the outer surface of the anchor plate 100, and the flange outer surface of the connecting member 400 is welded to the steel member 300 And is bolted to abut one side flange outer surface of the flange.

연결부재(400)가 "ㄷ"형강으로 제작될 경우 연결부재(400)의 양측 웨브 단면부가 각각 앵커플레이트(100)의 표면에 용접결합되고, 연결부재(400)의 플랜지 외측면이 철골부재(300)의 일측 플랜지 외측면에 맞닿도록 볼트결합된다.When the connecting member 400 is made of a " C " shape steel, both side end portions of the connecting member 400 are welded to the surface of the anchor plate 100, 300). ≪ / RTI >

연결부재(400)와 철골부재(300)를 결합하는 볼트는 도2 및 도3에 도시된 것처럼 전산볼트를 미리 철골부재(300)의 플랜지 표면에 용접결합한 후 용접결합된 볼트에 연결부재(400)를 끼우고 너트를 체결하는 방식이 선택될 수도 있고, 첨부도면에 별도로 도시하지 않았으나 철골부재(300)의 웨브나 플랜지를 관통하도록 머리부가 있는 일반볼트를 삽입하는 방식이 선택되거나, 머리부가 있는 일반볼트의 머리부를 철골부재(300)의 플랜지 표면에 용접결합하는 방식이 선택될 수도 있다.The bolts connecting the connecting member 400 and the steel member 300 are welded to the flange surface of the steel member 300 in advance as shown in FIGS. 2 and 3, A method of inserting a common bolt having a head portion through the web or flange of the steel member 300 may be selected or a method of inserting a bolt having a head portion may be selected, A method of welding the head portion of the ordinary bolt to the flange surface of the steel member 300 may be selected.

타설양생층(500)은 앵커플레이트(100)와 연결부재(400)가 차지하고 있는 철골부재(300)의 하부 영역의 공간을 채우도록 타설양생되는 고강도 무수축 모르타르나 콘크리트로 이루어지는데, 이러한 타설양생층(500)은 앵커볼트(200)와 함께 철근 콘크리트 구조물(50)과 철골부재(300)를 일체로 결합하는 역할을 하게 된다.The casting layer 500 is made of high-strength non-shrinkage mortar or concrete which is cured so as to fill the space of the lower region of the steel member 300 occupied by the anchor plate 100 and the connecting member 400. The layer 500 serves to integrally join the reinforced concrete structure 50 and the steel frame member 300 together with the anchor bolts 200.

아울러 타설양생층(500)은 도2 또는 도3에 도시된 것처럼 앵커플레이트(100)와 철근 콘크리트 구조물(50)의 표면 사이의 간격으로 형성된 빈 공간에도 형성된다.The installed curing layer 500 is also formed in an empty space formed between the anchor plate 100 and the surface of the reinforced concrete structure 50 as shown in FIG. 2 or FIG.

타설양생층(500)은 연결부재(400)에 형성된 다수의 통과공(22)을 통과하도록 타설되어 양생됨으로써 연결부재(400)와의 결합력을 증대시키게 된다.The curing layer 500 is inserted and cured to pass through the plurality of through holes 22 formed in the connecting member 400, thereby increasing the coupling force with the connecting member 400.

이러한 마찰플랜지가 구비된 내진보강용 이중 철골프레임는 도4(a~c)에 도시된 것처럼 기존 철골 콘크리트 구조물의 기둥과 보를 따라 설치되어 개구부를 보강하게 되는데, 이하에서는 마찰플랜지가 구비된 내진보강용 이중 철골프레임을 이용한 내진공법에 대하여 살펴본다.As shown in FIGS. 4 (a) to 4 (c), the double-steel steel frame having such a friction flange is installed along the columns and beams of existing steel-concrete structures to reinforce the openings. Hereinafter, A seismic proofing method using a double steel frame will be described.

<도4에 도시된 결합구조의 내진공법><Earthquake Resistance Method of Coupling Structure shown in FIG. 4>

(1) 제1단계(1) Step 1

기존 마감재의 철거 작업 후 철근 콘크리트 구조물(50)의 보강 부위 표면의 페인트 및 이물질을 제거하여 바탕면을 정리하는 과정이다. 이러한 과정은 면갈기 공정 등을 통하여 수행될 수 있다.And removing the paint and foreign matter on the reinforced portion of the reinforced concrete structure 50 after the removal of the existing finishing material. This process can be carried out through a surface grinding process or the like.

(2) 제2단계(2) Step 2

앵커플레이트(100)에 형성된 앵커볼트장착공(11)의 패턴에 따라 철근 콘크리트 구조물(50)의 표면에 앵커볼트 장착을 위한 구멍을 천공하는 과정이다.A hole for mounting an anchor bolt is formed on the surface of the reinforced concrete structure 50 according to the pattern of the anchor bolt mounting hole 11 formed in the anchor plate 100. [

앵커플레이트(100)는 도4a에 도시된 것처럼 다수의 조각으로 분리된 것이 사용될 수도 있고, 첨부도면에 별도로 도시하지 않았으나 일체형 강판이 사용될 수도 있다.The anchor plate 100 may be divided into a plurality of pieces as shown in FIG. 4A, or an integral steel plate may be used, although not separately shown in the accompanying drawings.

(3) 제3단계(도4a)(3) The third step (Fig. 4A)

제2단계에서 천공된 구멍에 앵커볼트(200)를 장착하여 앵커플레이트(100)를 철근 콘크리트 구조물(50)의 표면과 미리 설정된 거리만큼 간격이 존재하도록 부착하는 과정이다. The anchor bolts 200 are attached to the perforated holes in the second step so that the anchor plate 100 is adhered to the surface of the reinforced concrete structure 50 with a predetermined distance therebetween.

앵커볼트(200)는 다양한 종류와 규격의 제품이 사용될 수 있으며, 각 제품의 장착 메뉴얼에 따라 작업을 수행하게 되는데, 앵커볼트(200)의 장착이 완료된 상태에서 앵커플레이트(100)와 철근 콘크리트 구조물(50)의 바탕면 사이에는 개략 10 내지 20밀리미터 정도의 간격이 유지되도록 하여 앵커플레이트(100)의 유동 공간(거리)을 적절히 확보하도록 한다.The anchor bolts 200 can be manufactured in various types and sizes and work according to the mounting manual of each product. When the anchor bolts 200 are completely mounted, the anchor plate 100 and the reinforced concrete structure A distance of about 10 to 20 millimeters is maintained between the bottom surface of the anchor plate 50 and the flow space (distance) of the anchor plate 100 is appropriately secured.

(4) 제4단계(도4b)(4) In the fourth step (FIG. 4B)

철골부재(300)에 볼트로 가조립된 연결부재(400)를 밀거나 당기면서 연결부재(400)의 웨브의 단면부를 앵커플레이트(100)의 외측면에 밀착한 후 용접결합하는 과정이다.The end face of the web of the connecting member 400 is brought into close contact with the outer surface of the anchor plate 100 while pushing or pulling the connecting member 400 assembled with the bolts to the steel member 300.

즉, 연결부재(400)를 철골부재(300)에 볼트로 가조립만 한 상태에서 연결부재(400)와 앵커플레이트(100)의 용접결합을 수행함으로써 철근 콘크리트 구조물(50)의 바탕면 굴곡 편차나, 앵커플레이트(100) 또는 철골부재(300)의 형상 편차를 흡수하면서 보다 편리하고 신속하게 용접작업을 수행할 수 있다.That is to say, by performing the welding connection between the connecting member 400 and the anchor plate 100 in a state where the connecting member 400 is bolted to the steel member 300, The anchor plate 100, or the steel frame member 300 can be absorbed and the welding operation can be performed more conveniently and quickly.

다시 말하면, 앵커플레이트(100)와 철근 콘크리트 구조물(50) 사이의 간격과 함께 연결부재(400)도 철골부재(300)에 가조립 상태가 될 경우 앵커플레이트(100), 연결부재(400) 및 철골부재(300)들의 유동성이 충분히 확보되어 연결부재(400)의 웨브 단부가 앵커플레이트(100)의 외측면에 쉽게 밀착되어 용접이 신속하게 이루어질 수 있다.The anchor plate 100 and the reinforcing concrete structure 50 together with the connecting member 400 are also attached to the steel frame member 300. The anchor plate 100, The fluidity of the members 300 is sufficiently ensured so that the web end of the connecting member 400 can be easily brought into close contact with the outer surface of the anchor plate 100 and welding can be performed quickly.

(5) 제5단계(도4b)(5) In the fifth step (FIG. 4B)

앵커플레이트(100)와 연결부재(400)가 용접으로 결합된 후 가체결된 볼트를 완전히 조임으로써 연결부재(400)와 철골부재(300)를 최종 결합하는 과정인데, 이러한 과정을 통하여 앵커플레이트(100), 연결부재(400) 및 철골부재(300)이 완벽하게 일체거동을 할 수 있도록 결합되고, 앵커플레이트(100)는 앵커볼트(200)에 의하여 철근 콘크리트 구조물(50)에 장착된 상태가 된다.The anchor plate 100 and the connecting member 400 are welded together and then the bolts fastened to the anchor plate 100 are fully tightened to finally join the connecting member 400 and the steel frame member 300. Through this process, The anchor plate 100 is coupled to the reinforced concrete structure 50 by the anchor bolts 200 so that the anchor plate 100 and the connecting members 400 and 300 are completely integrated do.

(6) 제6단계(도4c)(6) In the sixth step (FIG. 4C)

거푸집을 설치한 후 고강도 무수축 모르타르 또는 콘크리트를 타설양생하여 철근 콘크리트 구조물(50)과 철골부재(300)를 일체로 결합하는 타설양생층(500)을 형성하는 과정이다.And then a high strength non-shrinking mortar or concrete is placed and cured to form a curing layer 500 for integrally joining the reinforcing steel structure 50 and the steel member 300 together.

이러한 과정을 통하여 기존 철근 콘크리트 구조물(50)과 철골부재(300)의 일체 거동이 확보된다.Through this process, the integrated behavior of the existing reinforced concrete structure 50 and the steel frame member 300 is secured.

거푸집을 설치하거나 고강도 무수축 모르타르 또는 콘크리트를 타설하여 양생하는 과정은 해당 분야의 일반적인 시공 방법에 따라 현장 여건 등을 감안하여 수행하게 되는데, 타설되는 고강도 무수축 모르타르 또는 콘크리트는 앵커플레이트(100)와 철근 콘크리트 구조물(50) 사이의 빈 공간에도 충분히 채워지도록 한다.The mortar or concrete with high strength and non-shrinkage mortar or concrete can be cured by taking into account the site conditions according to the general construction method of the relevant field. So that an empty space between the reinforced concrete structures 50 is sufficiently filled.

(7) 제7단계 (7) Step 7

양생이 완료된 후 거푸집을 제거하고 필요한 마감공정을 수행하는 과정이다.After curing is completed, the mold is removed and necessary finishing process is performed.

상기한 바와 같이 본 발명의 구체적 실시예를 첨부도면을 참조하여 설명하였으나 본 발명의 보호범위가 반드시 이러한 실시예에만 한정되는 것은 아니며 본 발명의 기술적 요지를 변경하지 않는 범위 내에서 다양한 설계변경, 공지기술의 부가나 삭제, 단순한 수치한정 등의 경우에도 본 발명의 보호범위에 속함을 분명히 한다.While the present invention has been particularly shown and described with reference to exemplary embodiments thereof, it is clearly understood that the same is by way of illustration and example only and is not to be taken by way of limitation, Addition or deletion of a technique, and limitation of a numerical value are included in the protection scope of the present invention.

50:철근 콘크리트 구조물
100:앵커플레이트
200:앵커볼트
300:철골부재
310:마찰패드
340:압착볼트
400:연결부재
500:타설양생층
11:앵커볼트장착공
22:통과공
33:슬로트홀
50: Reinforced Concrete Structures
100: anchor plate
200: Anchor bolt
300: steel member
310: Friction pad
340: Crimp Bolt
400: connecting member
500: Placed curing layer
11: Anchor bolt mounting ball
22: Through ball
33: Slot hole

Claims (7)

철근 콘크리트 구조물(50)에 장착되는 마찰플랜지가 구비된 내진보강용 이중 철골프레임에 관한 것으로서,
보강 대상이 되는 철근 콘크리트 구조물(50)의 바탕면을 따라 부착되는 평판 형태의 앵커플레이트(100);
상기 앵커플레이트(100)에 형성된 앵커볼트장착공(11)을 통과하여 철근 콘크리트 구조물(50)에 매립 장착되는 앵커볼트(200);
철근 콘크리트 구조물(50)에 장착되는 철골부재(300); 및,
일측 단부는 시공 현장에서 상기 앵커플레이트(100)의 외측면에 용접결합되고, 타측 단부는 상기 철골부재(300)를 따라 미리 설정된 거리마다 유동 가능하게 볼트로 가체결되는 다수의 연결부재(400);
를 포함하여 구성되고,
상기 앵커플레이트(100)와 철근 콘크리트 구조물(50)의 바탕면 사이에는 상기 앵커볼트(200)가 매립 장착된 상태에서도 간격(gap)이 존재하여 빈 공간이 형성되고,
볼트로 가체결된 상기 연결부재(400)는 시공 현장에서 상기 앵커플레이트(100)에 용접결합된 후 볼트를 완전히 조임으로써 상기 철골부재(300)에 고정되고,
상기 철골부재(300)는,
"H"형강으로 제작되어 철근 콘크리트 구조물(50)의 기둥이나 보를 따라 " ㅁ"자 형태의 뼈대를 이루는 구조가 되고,
수직 방향으로 배열되는 좌우 양측의 상기 철골부재(300) 각각은 2개가 나란히 배열되어 한 조를 이루는 이중 구조가 되고,
길게 늘어진 평판 형태의 부재로서 다수의 슬로트홀(33)이 길이 방향으로 구비되고, 이중 구조를 이루는 상기 철골부재(300) 사이에 압착되도록 볼트결합되는 마찰패드(310); 및,
이중 구조를 이루는 상기 철골부재(300)와 상기 마찰패드(310)의 슬로트홀(33)을 통과하도록 체결되어 상기 마찰패드(310)가 수직 방향으로 배열된 상기 철골부재(300) 사이에서 압착되도록 하는 압착볼트(340);
를 더 포함하는 것을 특징으로 하는 마찰플랜지가 구비된 내진보강용 이중 철골프레임.
The present invention relates to a double steel frame for an internal-strength steel having a friction flange mounted on a reinforced concrete structure (50)
An anchor plate 100 in the form of a flat plate attached along the base surface of the reinforced concrete structure 50 to be reinforced;
Anchor bolts 200 passing through the anchor bolt mounting holes 11 formed in the anchor plate 100 and being embedded in the reinforced concrete structure 50;
A steel member 300 mounted on the reinforced concrete structure 50; And
And the other end of the connecting member 400 is welded to the outer surface of the anchor plate 100 at a construction site and the other end of the connection member 400 is fastened to the bolt so as to be movable at predetermined distances along the steel frame member 300. [ ;
And,
A gap is formed between the anchor plate 100 and the base surface of the reinforced concrete structure 50 even when the anchor bolts 200 are embedded,
The connecting member 400 fastened to the bolt is welded to the anchor plate 100 at the construction site and then fixed to the steel frame member 300 by completely tightening the bolt,
The steel frame member (300)
H " steel to form a " ㅁ " -shaped framework along the columns or beams of the reinforced concrete structure 50,
The two steel members 300 on both the right and left sides arranged in the vertical direction are arranged in parallel to each other to form a pair of double structures,
A friction pad 310 having a plurality of slit holes 33 formed in a longitudinally elongated flat plate shape and bolted to be pressed between the steel members 300 having a double structure; And
The steel frame member 300 having the dual structure and the friction pads 310 are coupled to the slit holes 33 of the friction pad 310 so that the friction pads 310 are pressed between the steel frame members 300 arranged in the vertical direction A compression bolt 340;
Further comprising a frictional flange, wherein the frictional flange further comprises:
제1항에서,
상기 연결부재(400)는,
"T"형강 또는 "ㄷ"형강으로 제작되며,
상기 연결부재(400)가 "T"형강으로 제작될 경우 상기 연결부재(400)의 웨브의 단면부가 상기 앵커플레이트(100)의 외측면에 용접결합되고, 상기 연결부재(400)의 플랜지 외측면이 상기 철골부재(300)의 일측 플랜지 외측면 또는 상기 철골부재(300)의 웨브 일측면에 맞닿도록 볼트결합되며,
상기 연결부재(400)가 "ㄷ"형강으로 제작될 경우 상기 연결부재(400)의 양측 웨브 단면부가 각각 상기 앵커플레이트(100)의 외측면에 용접결합되고, 상기 연결부재(400)의 플랜지 외측면이 상기 철골부재(300)의 일측 플랜지 외측면 또는 상기 철골부재(300)의 웨브 일측면에 맞닿도록 볼트결합되는 것을 특징으로 하는 마찰플랜지가 구비된 내진보강용 이중 철골프레임.
The method of claim 1,
The connecting member (400)
It is made of "T" or "C"
The cross section of the web of the connecting member 400 is welded to the outer surface of the anchor plate 100 and the flange outer surface 400 of the connecting member 400 is welded to the outer surface of the connecting plate 400. [ Is bolted to abut one side flange outer surface of the steel member (300) or one side surface of the web of the steel frame member (300)
When the connecting member 400 is made of a "C" shaped steel, both side end portions of the connecting member 400 are welded to the outer surface of the anchor plate 100, and the flange of the connecting member 400 And the side face is bolted to one side of the flange outer side of the steel frame member (300) or one side face of the web of the steel frame member (300).
제1항에서,
상기 연결부재(400)는,
"T"형강 또는 "ㄷ"형강으로 제작되는 하부연결부(410); 및,
"T"형강 또는 "ㄷ"형강으로 제작되는 상부연결부(420);
로 구성되며,
상기 하부연결부(410)의 웨브 단부는 상기 앵커플레이트(100)의 외측면에 용접결합되고, 상기 하부연결부(410)의 플랜지 외측면과 상기 상부연결부(420)의 플랜지 외측면이 서로 맞닿도록 볼트결합되고, 상기 상부연결부(420)의 웨브 단부가 각각 상기 철골부재(300) 웨브 일측면에 용접결합되는 것을 특징으로 하는 마찰플랜지가 구비된 내진보강용 이중 철골프레임.
The method of claim 1,
The connecting member (400)
A lower connection part 410 made of a " T " And
An upper connection part 420 made of a " T "
Lt; / RTI &gt;
The web end portion of the lower connection portion 410 is welded to the outer surface of the anchor plate 100 and the flange outer side surface of the lower connection portion 410 and the flange outer side surface of the upper connection portion 420 are in contact with each other. And a web end of the upper connection part (420) is respectively welded to one side of the web of the steel frame member (300).
제1항 내지 제3항 가운데 어느 한 항에서,
상기 앵커플레이트(100)는,
다수의 조각으로 이루어져 개별적으로 상기 앵커볼트(200)에 의하여 철근 콘크리트 구조물(50)의 표면에 부착되거나 일측으로 길게 늘어진 1개의 강판 부재인 것을 특징으로 하는 마찰플랜지가 구비된 내진보강용 이중 철골프레임.
4. The method according to any one of claims 1 to 3,
The anchor plate (100)
And a single steel plate member formed of a plurality of pieces and individually attached to the surface of the reinforced concrete structure (50) by the anchor bolts (200) or elongated in one side. .
제1항 내지 제3항 가운데 어느 한 항에서,
상기 앵커플레이트(100) 및 상기 연결부재(400)가 차지하고 있는 철골부재(300) 하부 영역의 공간을 채우도록 타설양생되어 철근 콘크리트 구조물(50)과 상기 철골부재(300)를 일체로 결합하는 타설양생층(500);
이 더 포함되는 것을 특징으로 하는 마찰플랜지가 구비된 내진보강용 이중 철골프레임.
4. The method according to any one of claims 1 to 3,
The anchor plate 100 and the connecting member 400 are cured so as to fill the space of the lower region of the steel member 300 and the reinforcing concrete structure 50 and the steel member 300 are integrally joined together Curing layer 500;
Wherein the reinforcing flange is provided with a plurality of projections.
제1항 또는 제2항에 기재된 마찰플랜지가 구비된 내진보강용 이중 철골프레임을 이용한 내진공법에 관한 것으로서,
기존 마감재의 철거 작업 후 철근 콘크리트 구조물(50)의 보강 부위 바탕면의 페인트 및 이물질을 제거하여 바탕면을 정리하는 제1단계;
앵커플레이트(100)에 형성된 앵커볼트장착공(11)의 패턴에 따라 철근 콘크리트 구조물(50)의 바탕면에 앵커볼트 장착을 위한 구멍을 천공하는 제2단계;
제2단계에서 천공된 구멍에 앵커볼트(200)를 장착하여 앵커플레이트(100)를 철근 콘크리트 구조물(50)의 바탕면과 미리 설정된 거리만큼 간격이 존재하도록 부착하는 제3단계;
철골부재(300)에 고장력볼트로 가조립된 연결부재(400)를 밀거나 당기면서 앵커플레이트(100)의 외측면에 밀착한 후 용접결합하는 제4단계;
가체결된 고장력볼트를 완전히 조임으로써 연결부재(400)와 철골부재(300)를 최종 결합하는 제5단계;
거푸집을 설치한 후 모르타르 또는 콘크리트를 타설양생하여 철근 콘크리트 구조물(50)과 철골부재(300)를 일체로 결합하는 타설양생층(500)을 형성하는 제6단계; 및,
양생이 완료된 후 거푸집을 제거하고 마감공정을 수행하는 제7단계;
를 포함하여 구성되는 것을 특징으로 하는 마찰플랜지가 구비된 내진보강용 이중 철골프레임을 이용한 내진공법.
A seismic isolation method using a double-steel steel frame for an internal-strength steel with a friction flange as set forth in claim 1 or 2,
A first step of removing the paint and foreign matter on the surface of the reinforcement portion of the reinforced concrete structure 50 after the existing finishing material is removed;
A second step of drilling a hole for mounting the anchor bolt on the base surface of the reinforced concrete structure 50 according to the pattern of the anchor bolt mounting hole 11 formed in the anchor plate 100;
A third step of attaching the anchor bolts 200 to the perforated holes in the second step so that the anchor plates 100 are spaced apart from the base surface of the reinforced concrete structure 50 by a predetermined distance;
A fourth step of pressing and joining the connecting member 400 assembled with the high-tension bolt to the steel member 300 while closely contacting the outer surface of the anchor plate 100 and welding the same;
A final step of finally joining the connecting member 400 and the steel frame member 300 by tightly fastening the high tension bolt fastened together;
A sixth step of placing mortar or concrete on concrete after the mold is installed and forming a cured concrete layer 500 for integrally joining the reinforced concrete structure 50 and the steel frame member 300; And
A seventh step of removing the formwork and performing a finishing process after curing is completed;
Wherein the reinforcing steel frame is provided with a friction flange.
제3항에 기재된 마찰플랜지가 구비된 내진보강용 이중 철골프레임을 이용한 내진공법에 관한 것으로서,
기존 마감재의 철거 작업 후 철근 콘크리트 구조물(50)의 보강 부위 바탕면의 페인트 및 이물질을 제거하여 바탕면을 정리하는 제1단계;
앵커플레이트(100)에 형성된 앵커볼트장착공(11)의 패턴에 따라 철근 콘크리트 구조물(50)의 바탕면에 앵커볼트 장착을 위한 구멍을 천공하는 제2단계;
제2단계에서 천공된 구멍에 앵커볼트(200)를 장착하여 앵커플레이트(100)를 철근 콘크리트 구조물(50)의 바탕면과 미리 설정된 거리만큼 간격이 존재하도록 부착하는 제3단계;
철골부재(300)에 용접결합된 상부연결부(420)에 볼트로 가조립된 하부연결부(410)를 밀거나 당기면서 앵커플레이트(100)의 외측면에 밀착한 후 용접결합하는 제4단계;
가체결된 볼트를 완전히 조임으로써 상부연결부(420)와 하부연결부(410)를 최종 결합하는 제5단계;
거푸집을 설치한 후 모르타르 또는 콘크리트를 타설양생하여 철근 콘크리트 구조물(50)과 철골부재(300)를 일체로 결합하는 타설양생층(500)을 형성하는 제6단계; 및,
양생이 완료된 후 거푸집을 제거하고 마감공정을 수행하는 제7단계;
를 포함하여 구성되는 것을 특징으로 하는 마찰플랜지가 구비된 내진보강용 이중 철골프레임을 이용한 내진공법.
The present invention relates to a seismic proofing method using a double steel frame for an internal-strength steel having a friction flange according to claim 3,
A first step of removing the paint and foreign matter on the surface of the reinforcement portion of the reinforced concrete structure 50 after the existing finishing material is removed;
A second step of drilling a hole for mounting the anchor bolt on the base surface of the reinforced concrete structure 50 according to the pattern of the anchor bolt mounting hole 11 formed in the anchor plate 100;
A third step of attaching the anchor bolts 200 to the perforated holes in the second step so that the anchor plates 100 are spaced apart from the base surface of the reinforced concrete structure 50 by a predetermined distance;
A fourth step of pressing and pulling the lower connection part 410 bolted to the upper connection part 420 welded to the steel member 300 and welding the upper connection part 410 closely to the outer surface of the anchor plate 100;
A final step of finally joining the upper connection part 420 and the lower connection part 410 by completely tightening the bolts fastened together;
A sixth step of placing mortar or concrete on concrete after the mold is installed and forming a cured concrete layer 500 for integrally joining the reinforced concrete structure 50 and the steel frame member 300; And
A seventh step of removing the formwork and performing a finishing process after curing is completed;
Wherein the reinforcing steel frame is provided with a friction flange.
KR1020170078549A 2017-06-21 2017-06-21 Aseismatic Reinforcement Double Steel Frame with Friction Slip Flange, and Aseismatic Reinforcement Method using thereof KR102074251B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020170078549A KR102074251B1 (en) 2017-06-21 2017-06-21 Aseismatic Reinforcement Double Steel Frame with Friction Slip Flange, and Aseismatic Reinforcement Method using thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020170078549A KR102074251B1 (en) 2017-06-21 2017-06-21 Aseismatic Reinforcement Double Steel Frame with Friction Slip Flange, and Aseismatic Reinforcement Method using thereof

Publications (2)

Publication Number Publication Date
KR20180138389A true KR20180138389A (en) 2018-12-31
KR102074251B1 KR102074251B1 (en) 2020-02-06

Family

ID=64959498

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020170078549A KR102074251B1 (en) 2017-06-21 2017-06-21 Aseismatic Reinforcement Double Steel Frame with Friction Slip Flange, and Aseismatic Reinforcement Method using thereof

Country Status (1)

Country Link
KR (1) KR102074251B1 (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04198537A (en) * 1990-11-29 1992-07-17 Misawa Homes Co Ltd Jointing construction for shape steel beam
KR20120004392A (en) * 2011-12-27 2012-01-12 디피알파트너 주식회사 Src joint structure and joint method
KR101214139B1 (en) * 2012-07-09 2012-12-20 홍정락 Steel reinforced concrete aseismatic structure and method using clamp
KR101357054B1 (en) * 2013-08-26 2014-02-03 (주)에스알텍 Dual frame type aseismatic structure and method
KR101368312B1 (en) * 2013-07-19 2014-02-27 비코비엔주식회사 Seismic retrofit structures by damper joint
KR101651849B1 (en) * 2015-11-17 2016-08-30 장극관 Seismic retrofitting technique of framed structure by elasto-plastic steel damper

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04198537A (en) * 1990-11-29 1992-07-17 Misawa Homes Co Ltd Jointing construction for shape steel beam
KR20120004392A (en) * 2011-12-27 2012-01-12 디피알파트너 주식회사 Src joint structure and joint method
KR101168876B1 (en) * 2011-12-27 2012-07-26 디피알파트너 주식회사 SRC Joint Structure and Joint Method
KR101214139B1 (en) * 2012-07-09 2012-12-20 홍정락 Steel reinforced concrete aseismatic structure and method using clamp
KR101368312B1 (en) * 2013-07-19 2014-02-27 비코비엔주식회사 Seismic retrofit structures by damper joint
KR101357054B1 (en) * 2013-08-26 2014-02-03 (주)에스알텍 Dual frame type aseismatic structure and method
KR101651849B1 (en) * 2015-11-17 2016-08-30 장극관 Seismic retrofitting technique of framed structure by elasto-plastic steel damper

Also Published As

Publication number Publication date
KR102074251B1 (en) 2020-02-06

Similar Documents

Publication Publication Date Title
KR101870309B1 (en) Aseismatic Reinforcement Steel Frame Structure and Aseismatic Reinforcement Method using thereof
KR101150392B1 (en) The joint structure and method of steel structure for earthquake-proof reinforcement
KR102012883B1 (en) Aseismatic Reinforcement Steel Frame with Friction Slip Brace and Aseismatic Reinforcement Method using thereof
JP2012077471A (en) Joint structure of precast members and concrete precast members
KR101845717B1 (en) Aseismatic Reinforcement Steel Frame with Hinge Type Friction Slip Brace and Aseismatic Reinforcement Method using thereof
KR101432087B1 (en) Composite rahman bridge using preflex beam and horizontal shear connectors and construction method thereof
KR101845078B1 (en) Aseismatic Reinforcement Steel Frame with Adjusting Connector and Aseismatic Reinforcement Method using thereof
KR101908356B1 (en) Aseismatic Reinforcement Double Steel Frame and Aseismatic Reinforcement Method using thereof
JP5503408B2 (en) Building construction method
KR102004854B1 (en) Aseismatic Reinforcement Steel Frame with Anchor Plate and Aseismatic Reinforcement Method using thereof
KR101521946B1 (en) Enlarged capital of steel framed reinforced concrete column
KR101176846B1 (en) Structure for reinforcing proof stress of girder
KR102000082B1 (en) Aseismatic Reinforcement Device with Toggle Type Friction Slip Brace, and Aseismatic Reinforcement Method using thereof
JP2750556B2 (en) Manufacturing method of prestressed concrete girder
KR20210005806A (en) Joining method of steel members using double anchor plate with wedge-shaped concave-convex section in the construction of steel structure or steel-reinforced concrete composite structure
KR20180138389A (en) Aseismatic Reinforcement Double Steel Frame with Friction Slip Flange, and Aseismatic Reinforcement Method using thereof
KR20120108328A (en) Deck panel using reinforced strand and construction method therefor
KR101814902B1 (en) Seismic Reinforcing Structure of Opening of Building And Reinforcing Method Using Segment Type Reinforcing Structure
KR20180138385A (en) Aseismatic Reinforcement Device with Friction Slip Flange, and Aseismatic Reinforcement Method using thereof
JP2002332645A (en) Foundation structure of rail for ground-traveling crane and laying method for foundation
KR101083062B1 (en) Hybrid reinforced concrete system
JP2004263507A (en) Building foundation construction method and building foundation structure
KR101038291B1 (en) Steel beam and hybrid beam of steel concrete for slim floor
JP2011089276A (en) Reinforcing structure and reinforcing method of bridge pier
JP6829631B2 (en) Construction method of column base, reinforcement method of existing column base

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right