KR20180105100A - Vibration-free rapid excavation method using pilot tunnel in large-scale tunnel - Google Patents

Vibration-free rapid excavation method using pilot tunnel in large-scale tunnel Download PDF

Info

Publication number
KR20180105100A
KR20180105100A KR1020180105242A KR20180105242A KR20180105100A KR 20180105100 A KR20180105100 A KR 20180105100A KR 1020180105242 A KR1020180105242 A KR 1020180105242A KR 20180105242 A KR20180105242 A KR 20180105242A KR 20180105100 A KR20180105100 A KR 20180105100A
Authority
KR
South Korea
Prior art keywords
tunnel
main
pilot
excavation surface
blasting
Prior art date
Application number
KR1020180105242A
Other languages
Korean (ko)
Other versions
KR102211018B1 (en
Inventor
서동현
Original Assignee
서동현
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 서동현 filed Critical 서동현
Priority to KR1020180105242A priority Critical patent/KR102211018B1/en
Publication of KR20180105100A publication Critical patent/KR20180105100A/en
Application granted granted Critical
Publication of KR102211018B1 publication Critical patent/KR102211018B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/01Methods or apparatus for enlarging or restoring the cross-section of tunnels, e.g. by restoring the floor to its original level
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/006Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by making use of blasting methods

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Soil Sciences (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The present invention relates to a method of gradually blasting a pilot tunnel base ground between a pilot tunnel and a prearranged main tunnel excavation surface by excavating a pilot tunnel, boring an elongated hole from the prearranged main tunnel excavation surface to the tunnel base ground, inserting a pre-support into the elongated hole, grouting the ground to reinforce the ground, and charging an empty hole formed when the pre-support is inserted into the pilot tunnel base ground from the pilot tunnel and the prearranged main tunnel excavation surface and a radial hole additionally formed with explosive powder. The method of gradually blasting a pilot tunnel base ground comprises the steps of: excavating a pilot tunnel to be spaced apart from a prearranged main tunnel excavation surface in order to insert the pre-support into the tunnel and excavate the tunnel; inserting and grouting a pre-support material by forming an elongated hole in the tunnel base passing the main excavation surface of the prearranged main tunnel from the pilot tunnel; boring a plurality of main tunnel holes in the excavation surface of the prearranged main tunnel in a vertical direction; boring a radial charging hole in the base ground of the pilot tunnel in the vertical direction of the tunnel; connecting gunpowder and detonators by groups of sections, charging the charging hole with the connected gunpowder and detonators and connecting gunpowder and detonators to cross sections of empty holes formed when the pre-support is inserted and charging the empty hole with the connected gunpowder and detonators; gradually blasting the charging holes from a blind end of the tunnel in the vertical direction of the tunnel; removing pumice stones of the excavated surface formed by the blasting; and taking out generated muck and additionally supporting the excavated surface.

Description

대단면 터널에서 파일럿 터널을 이용한 미진동 급속 굴착 방법{Vibration-free rapid excavation method using pilot tunnel in large-scale tunnel}[0001] The present invention relates to a Vibration-free rapid excavation method using a pilot tunnel in a large-scale tunnel,

본 발명은 파일럿 터널을 굴착 또는 TBM 공법(머신)으로 파일럿 터널을 굴착하고, 예정 본 터널 주면 굴착면을 지나 터널 원지반까지 천공기로 장공을 천공하고 난 후, 장공에 선지보를 본 터널 굴착선까지 밀어 넣어 삽입한 후, 그라우팅 또는 가압 그라우팅하여 지반을 보강해 놓은 다음에 파일럿 터널 굴착면에서 본 터널 굴착면까지를 장약 발파하기 위한 미진동 급속 굴착 방법에 관한 것이다.In the present invention, the pilot tunnel is excavated or the pilot tunnel is excavated by the TBM method (machine), the slot is drilled through the excavation surface of the main tunnel to the tunnel base, and then the pre-beam is pushed to the tunnel excavation line The present invention relates to a micro-vibration rapid excavation method for blasting ground from a pilot tunnel excavation surface to a tunnel excavation surface after reinforcing the ground by grouting or pressure grouting.

종래에, 대단면 터널을 굴착하는 방법은 단면이 클수록 터널의 원지반이 연약하면 연약 할수록 이에 비례하여 분할 수를 증가시켜 굴착과 지보를 하였다. 굴착하는 방법은 인력으로 굴착, 굴삭기와 같은 기계로 굴착하거나 화약을 장약하여 발파하는 방법이 주로 적용되었다.Conventionally, in the method of excavating a large cross section tunnel, the larger the cross section is, the more the number of partitions is increased in accordance with the softness of the soft ground of the tunnel, and the excavation and support are performed. The excavation method was mainly excavated with manpower, excavated with a machine such as an excavator, or charged with gunpowder and blasting.

상기 인력 굴착 및 기계 굴착은 주로 토사와 암석이 섞여 있을 때 많이 사용되어 왔으며 굴착 중 원지반의 자립 시간이 짧아서 많은 보조 공법을 적용하여 보강한 후 굴착하게 되므로 터널 공기를 지연시키게 되고 보강비도 추가된다. 암반이 존재할 경우에는 화약을 사용한 발파 굴착을 하게 되며 소음 진동의 공해가 발생하여 진동 규제를 초과하지 않는 최소 장약량으로 발파를 하므로 공기와 공비가 과다해진다.The excavation and mechanical excavation are mainly used when the soil and the rock are mixed, and since the self-standing time of the excavation is short during the excavation, many assistive techniques are applied to reinforce the excavation and the tunnel air is delayed and the reinforcement ratio is added. In the presence of rock mass, blasting excavation using gunpowder is performed, and pollution of noise vibration occurs, so that it is blasted with the minimum load that does not exceed the vibration regulation, so that air and azeotropy become excessive.

상기 문제점을 해결하기 위해 쉴드 티비엠(Shild TBM)이나 그립형 티비엠(Grip type TBM)을 최근에는 적용하기도 하나 최소 4~7Km 이상 길이가 되지 않으면 경제성이 없고 도로 3차선 이상의 큰 터널에서는 기계적 구조의 한계로 적용하기 어려웠다.Shield TBM or Grip type TBM have recently been applied to solve the above problems. However, it is not economical if the length is not less than 4 ~ 7 Km, It was difficult to apply it to the limit of

본 발명은 상기와 같은 문제점을 해결하기 위한 것으로써, 종래의 공법으로 파일럿 터널을 굴착 또는 TBM 공법으로 파일럿 터널을 굴착한 후, 예정 본 터널 주면에 본 터널 굴착 주면공을 설치하고 파일럿 터널로부터 예정 본 터널 주면 굴착면까지의 파일럿 터널 횡단면에 방사상 모양으로 장약공을 형성하고 화약을 장약하여 터널의 종방향으로 순차적으로 발파함으로써 종래의 공법에서 보다 2~4배 이상 신속하게 굴진할 수 있고 대단면 터널에서 파일럿 터널 원지반을 미진동으로 굴착하기 위한 미진동 급속 굴착 방법을 제공하는 것을 목적으로 한다.SUMMARY OF THE INVENTION The present invention has been made to solve the above-mentioned problems, and it is an object of the present invention to provide a tunnel tunnel for excavating a pilot tunnel or excavating a pilot tunnel using a TBM method, It can be drilled 2 to 4 times faster than the conventional method by forming a charge hole in a radial shape on the cross section of the pilot tunnel to the excavation surface of the main tunnel in the tunnel and sequentially charging the gunpowder in the longitudinal direction of the tunnel, It is another object of the present invention to provide a micro-vibration rapid excavation method for excavating a pilot tunnel original in a tunnel in a microscopic manner.

본 발명의 상기 목적을 달성하기 위하여, 본 발명은 본 터널을 선지보하고 굴착하기 위하여 예정 본 터널의 주면 굴착면에서 이격하여 파일럿 터널을 굴착하는 단계와, 상기 파일럿 터널에서 상기 예정 본 터널의 주면 굴착면을 지나 터널 원지반 내에 장공을 천공하여 선지보재를 삽입하고 그라우팅하는 단계와, 상기 파일럿 터널 내에서 파일럿 터널의 원지반(9)에 터널의 종방향으로 방사상 장약공을 일정한 간격으로 장약공 선단이 예정 본 터널의 주면 굴착면에 인접하도록 천공 형성하는 단계와, 상기 장약공에 각 단면별로 그룹을 지어 화약과 뇌관을 결선하여 장약하고 상기 선지보재 설치시 생기는 빈공의 장약공에도 그 빈공이 속하는 단면에 화약과 뇌관을 결선하여 장약하는 단계와, 상기 장약공을 터널의 막장쪽에서부터 터널의 종방향으로 순차적으로 발파하는 단계와, 상기 발파에 의해 형성된 굴착면의 부석을 제거하고 면을 정형하는 단계와, 상기 발생된 버력을 밖으로 반출하고 굴착면을 추가 지보하는 단계로 이루어지는 것을 특징으로 한다.In order to accomplish the above object, according to the present invention, there is provided a tunnel tunneling method comprising the steps of: excavating a pilot tunnel at a distance from a main excavation surface of a main tunnel to excavate and tunnel the main tunnel; A step of drilling a long hole in the tunnel base through the excavation surface to insert and grouting the pre-support, and a step of inserting a radial loading hole in the longitudinal direction of the tunnel into the ground plate (9) of the pilot tunnel in the pilot tunnel at regular intervals The method of claim 1, further comprising the steps of: forming a perforation adjacent to the main excavation surface of the tunnel, and connecting the explosive and the primer by grouping each charge section into the charge hole, And charging the charge ball from the surface side of the tunnel to the longitudinal direction of the tunnel Primarily removing step and, pumice the excavated surface formed by the blasting of a blasting and is characterized in that the step of shaping the surface, out of the generated low-grade ore out and comprising a step of adding a gem excavated surface.

본 발명의 다른 양태는, 상기 방사상 장약공을 천공 형성하는 단계와, 상기 방사상 장약공에 장약하는 단계 사이에, 상기 예정 본 터널의 주면 굴착면이 형성되고 진동이 감쇄되도록 상기 예정 본 터널의 주면 굴착면에 종방향으로 복수 개의 본 터널 주면공을 천공하는 단계를 더 구비하는 것을 특징으로 한다.In another aspect of the present invention, there is provided a method of manufacturing a radar device, comprising the steps of: forming the radial charge hole; forming a main excavation surface of the predetermined tunnel, Further comprising the step of drilling a plurality of main tunnel main surfaces in the longitudinal direction on the excavation surface.

본 발명의 또 다른 하나의 양태는, 파일럿 터널의 원지반을 순차적으로 발파하여도 폭력이 누적된 진동이 발생하지 않고, 미리 시공된 파일럿 터널에서 본 터널 원지반을 선지보에 의하여 완벽히 지보했을 경우에는 막장부터 종방향으로 무한하게 순차적으로 발파가 가능하여 급속 시공이 가능하며, 실제 시공에서는 안전과 공정상 일정한 1회 굴진장을 정하여 순차적 발파와 지보를 반복하여 터널을 시공하는 것을 특징으로 한다.According to another aspect of the present invention, in the case where the accumulated vibrations do not occur even when the ground plates of the pilot tunnel are successively blasted, and the tunnel base sheet viewed from the pilot tunnel that has been constructed in advance is completely supported by the pre- In the actual construction, the tunnel is constructed by repeatedly performing the sequential blasting and supporting operation by setting a predetermined one-time excavation length in terms of safety and the process in the actual construction.

상기와 같이 구성된 본 발명에 의한 발파 공법에 의하면, 파일럿 터널을 종래 공법으로 굴착하거나 TBM 공법으로 파일럿 터널을 굴착하고, 파일럿 터널 내에서 예정 본 터널 주면 굴착면을 지나 터널 원지반에 본 터널이 굴착 중 붕괴하지 않도록 완벽하게 본 터널 굴착 전에 선지보를 하면 파일럿 터널 굴착면과 본 터널 굴착면 사이를, 다시 말하면 파일럿 터널을 본 터널까지 확대 굴착할 때에 단면의 방사 방향으로 화약을 장약하여 종방향으로 순차적으로 발파하므로써 종래 공법 대비 1회 굴진장을 2배 내지 무한 굴진이 가능하여 신속한 시공성을 제공하고 발파 진동이 누적되지 않게 하는 효과가 있다.According to the blasting method of the present invention as described above, the pilot tunnel is excavated by the conventional method, the pilot tunnel is excavated by the TBM method, and the tunnel seen through the tunnel excavation surface in the pilot tunnel, If the pre-beaming is carried out before tunneling, it is possible to charge the gunpowder in the radial direction of the cross section between the pilot tunnel excavation surface and the tunnel excavation surface, in other words, when the pilot tunnel is extended to the tunnel, By blasting, it is possible to perform two times or more indefinite punching by one round of punching compared to the conventional method, thereby providing quick workability and preventing blasting vibrations from accumulating.

본 발명은 갱내 선지보 터널에서 대단면의 본 터널을 굴착하기 전에 선굴착된 파일럿 터널 굴착면이 추가적인 자유면 역할을 하여 종래 기술에서 중요한 요소인 심발공을 생략할 수 있고, 발파 진동을 감소시키고, 장약량이 감소되고, 최소의 장약으로 최대의 굴착 효과를 얻도록 하므로써 경제적인 시공을 할 수 있는 효과를 제공한다.In the present invention, the pilot tunnel excavation surface pre-excavated before excavating the major tunnel in the underground mine tunnel serves as an additional free surface, so that it is possible to omit the deep hole, which is an important factor in the prior art, , The amount of load is reduced, and the maximum excavation effect is obtained with minimum loading, thereby providing an economical construction.

본 터널 주면공을 미리 천공 설치 후 파일럿 터널 원지반을 확대 발파할 때에 주면공이 발파 진동을 반사하거나 감쇄시키는 효과가 있다.When the main tunnel of the tunnel is installed in advance and the pilot tunnel is enlarged and blasted, the main surface ball has an effect of reflecting or attenuating the blasting vibration.

대단면 본 터널의 원지반에 선지보 네일을 시공하면서 생성된 선지보 빈공을 이용하여 발파함으로써 장약공의 전체 천공 갯수를 감소시켜 경제적인 시공을 할 수 있는 효과가 있다.It is possible to economically construct the tunnel by reducing the total number of piercing holes by blasting by using the pre-spiral vail generated by constructing the spiral nail on the ground of the large-scale tunnel.

또한, 종래의 굴착 후 지보보다 먼저 지보 후에 굴착을 하므로서 원지반의 이완 영역 발생을 감소시켜 주는 효과가 있다.In addition, since the excavation is carried out before the conventional post-excavation support , It is effective to reduce the occurrence of the relaxation area of the paper sheet.

도 1은 본 발명에 따른 발파 방법 중 예정 본 터널의 굴착면에 주면공을 먼저 시공하고 파일럿 터널의 원지반에 장약공을 방사상으로 주면공에 근접하게 배치하여 방사상으로 설치된 장약공에만 장약하여 발파하는 발파 공법을 도시한 도면으로 주면공에 라인드릴링공법을 적용한것이다 .
도 2는 본 발명에 따른 발파 공법에서 1회 굴착 지보를 할 때, 굴착을 종방향으로 4회에 걸쳐 순차적으로 발파하는 순서를 도시한 도면이다.
도 3은 본 발명에 따른 장약공 상부의 원지반에 선지보재와 선지보재 시공시 형성된 빈공을 도시한 단면도이며 빈공에도 장약을 한 상태를 도시한다.
도 4는 본 발명에 따른 발파 공법의 상부와 하부 단면 영역 구분도이다.
도 5는 본 발명에 따른 발파 장약 방법 중 주면공에 격간 장약을 하는 선균열 발파 공법을 도시한 도면이며 주면공을 선 발파 후 방사상 장약공 발파를 순차적으로 함을 도시한 도면이다.
도 6은 본 발명에 따른 발파 방법으로 장약 방법 중 주면공의 천공 직경 보다 작은 직경의 정밀 화약을 장약하여 방사상 장약공부터 주면공으로 순차적으로 발파되는 스므스 블라스팅 발파 공법을 도시한 도면이다.
도 7은 본 발명의 또 다른 발파 방법으로 본 터널의 주면공에서 방사상 장약공의 선단까지 이격거리를 종방향으로 방사상 장약공 간격 이상으로 하여 장약공을 파일럿 터널의 내부를 자유면으로 순기폭 방법에 의해 주면공까지 순차적으로 장약하여 발파하는 것을 도시한 도면이다.
FIG. 1 is a view showing a method of blasting according to an embodiment of the present invention; FIG. 1 is a schematic view of a blasting method according to the present invention, in which a main surface is first installed on an excavation surface of a tunnel, The drawing shows the blasting method, and the line drilling method is applied to the main surface.
FIG. 2 is a view showing a procedure of sequentially blasting excavation four times in the longitudinal direction at the time of performing excavation once in the blasting method according to the present invention.
FIG. 3 is a cross-sectional view showing a veneer formed when the pre-support material and the pre-support material are formed on the paperboard of the upper part of the charge space according to the present invention.
4 is a sectional view of upper and lower sectional regions of the blasting method according to the present invention.
FIG. 5 is a view showing a pre-cracking blasting method that performs prestressing on a main surface of a blasting charge method according to the present invention, and shows a sequential blasting of a radial charge after a pre-blasting on a main surface.
FIG. 6 is a view showing a blasting method of blasting successively blasting from a radial charge hole to a main surface charge by charging a precise powder of a diameter smaller than the perforation diameter of the main surface of the charge method in the blasting method according to the present invention.
7 is a view showing another method of blasting according to the present invention, in which the distance from the main surface of the tunnel to the tip of the radial loading hole is set to be longer than the radial loading gap length in the longitudinal direction, To the main surface of the main body.

이하에서 첨부된 도면을 참조하여 본 발명을 상세히 설명한다.DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will now be described in detail with reference to the accompanying drawings.

중요 용어를 먼저 설명하면, "원지반"이란 터널을 시공하는 지반을 말하는 것으로, 더욱 상세하게는 본 터널의 외측 지반을 본 터널 원지반이라 하고, 파일럿 터널 외측 지반을 파일럿 터널 원지반이라 한다.First, the term "paper sheet" refers to a ground for constructing a tunnel. More specifically, the outer ground of the tunnel is referred to as a tunnel base, and the outer ground of the pilot tunnel is referred to as a pilot tunnel ground.

"파일럿 터널"이란 종래의 터널 시공 방법으로 형성하는 구조적으로 안전성을 쉽게 확보할 수 있는 본 터널 내부에 형성하는 본 터널의 단면보다 작은 단면의 터널로서, 첫째로, 파일럿 터널 굴착에 따른 변위가 본 터널에 구조적 영향을 미치지 않거나 변위의 발생 정도가 미소하도록, 선지보재를 설치하고자 하는 본 터널의 굴착 예정면과 파일럿 터널 굴착면이 이격을 갖도록 설치하는 터널이다.The term "pilot tunnel" means a tunnel having a smaller cross section than that of the main tunnel formed inside the main tunnel, which is structurally formed by a conventional tunnel construction method and can secure safety easily. Firstly, It is a tunnel installed so that the planned excavation surface of the main tunnel to install the pre-supports and the excavation surface of the pilot tunnel are spaced apart so as not to have a structural effect on the tunnel or to cause a small degree of displacement.

둘째는, 파일럿 터널에서 확대 발파시 방사 방향의 장약공이 적절한 길이를 확보하여 발파 효율이 높도록 배치한다.Second, in the pilot tunnel, the explosion holes in the radial direction are secured so that the blasting efficiency is high.

세째는, 파일럿 터널의 크기는 그 내부에서 선지보를 위한 천공 작업과 기계화 시공을 위한 최소의 단면 크기로 현장의 상황 여건에 따라 설계하며 국부적인 연약 지반을 위한 선지보가 중요할 때에는 인력 굴착도 해야 할 때가 있을 수 있다. Third, the size of the pilot tunnel is designed according to the conditions of the site with the minimum cross-sectional size for drilling work and mechanization construction inside the tunnel, and excavation should be done when local prefecture for soft ground is important There can be times.

"본 터널"이란 최종 목적물 터널을 의미하는 것으로, 굴착과 지보를 완료한 후, 사용되는 터널을 말한다. 파일럿 터널을 터널 단면 내부에 설치하여 선지보를 하는 경우는 터널 단면이 도로 3차선 이상인 대단면 터널에서 경제성을 가진다. 이보다 작은 단면의 터널은 기계화 시공에 제약을 받기 때문에 공사비와 공기가 증가된다. 본 발명에서 본 터널이란 최종 목적물 터널을 말한다."Tunnel" means the tunnel of the final object, which is used after completion of excavation and support. In the case where the pilot tunnel is installed inside the section of the tunnel and the pre-beam is made, it is economical in a large-section tunnel having a tunnel cross section equal to or higher than the road three lanes. Tunnels with a smaller cross section are subject to mechanized construction, which increases construction costs and air. In the present invention, the tunnel refers to the final object tunnel.

본 터널의 원지반에 변위와 응력의 증가가 없거나 미소하게 발생할 때에 본 터널을 굴착하기 전에 미리 설치한 네일을 "선지보재"라 정의한다. 선지보재는 네일과 같은 선형형태의 지보재로서 미리 설치된 선지보재는 본 터널의 막장을 굴착할때 생기는 변위에 따라서 지보력을 발휘하게 된다Nails that have been installed before excavating the tunnel are defined as "pre-support" when there is no increase or slight increase in displacement and stress on the ground of the tunnel. The prefabricated prefabricated prefabricated prefabricated prefabricated prefabricated nylon is a linear type of prefabricated nail,

선지보재의 재료는 고강도이면서 연신율이 원지반의 붕괴시까지 연신율 보다 커야 하며 철근, 강관, 강연선,GRP(Glass Reinforced Plastic)와 같은 선재는 모두 사용이 가능하다. The material of the pre-support is high strength and elongation must be higher than the elongation rate until the collapse of the paperboard. All wire materials such as reinforcing steel, steel pipe, steel wire and GRP (Glass Reinforced Plastic) can be used.

선지보재는 드릴로 천공하고 삽입하여 그라우팅으로 고정한다. 그라우팅 재료는 레진 캡슐 또는 시간적 화학 변화가 적은 무기계 재료인 시멘트계를 사용하고 차수를 주 목적으로 할 때에는 마이크로 시멘트나 용액형을 지반 조건에 따라 사용할 수 있다.The pre-support is drilled with drill, inserted and secured by grouting. The grouting material may be a resin capsule or a cementitious material, which is an inorganic material with little change in temporal chemistry, and micro cement or a solution type can be used according to the ground conditions when the main purpose is the ordering.

선지보재의 천공 직경은 연약 지반에서는 주입재와 원지반의 전단 강도를 고려하여 주면장을 105mm~200mm까지 크게 하고 암반에서는 35mm~105mm로 작게 시공한다.The perforation diameter of the prefabricated materials is 105mm ~ 200mm in the soft ground, and 35mm ~ 105mm in the rocky ground considering the shear strength of the injection material and paper.

"판형 지보재"라 함은 터널 굴착면에 설치되는 판형의 부재가 굴착면과 부착된 형태를 통칭하는 것으로 강섬유 숏크리트 또는 숏크리트와 그 내부를 보강하는 와이어 매쉬, 트러스 철근 케이지(Reinforced Steel Cage)가 조합된 것과, 이외에도 프리 캐스트 조각판을 선지보재에 지압판으로 고정하고 굴착면과 프리 캐스트 조각판 사이를 몰탈 또는 시멘트 밀크로 그라우팅하는 것도 판형 지보재라 한다."Plate-type support" refers to a type of plate-like member installed on the tunnel excavation surface attached to the excavation surface. It is a combination of steel fiber shotcrete or shotcrete and wire mesh and reinforced steel cage In addition, it is also called plate-type support in which pre-casting plate is fixed to the pre-support by a support plate and grouting between the excavation surface and the pre-casting plate by mortar or cement milk.

실시의 일예로 선지보재를 판형 지보재와 연결하는 방법은 굴착면에 1차 숏크리트를 취부하고 숏크리트면 위에 돌출된 선지보재에 트러스 철근 케이지(Reinforced Steel Cage)를 끼워 지압판을 대고 조여 설치하고 2차 숏크리트를 취부한다.As an example of the method, a first shotcrete is attached to an excavation surface, and a reinforced steel cage is fitted to the first support material protruded on the shotcrete surface, .

철근 케이지(Reinforced Steel Cage)는 철근을 격자로 조립한 것을 구조적 필요에 따라서 한겹 또는 여러겹을 간격을 두고 중첩하여 설치하는 것을 말하고 숏크리트에 묻히게 된다.Reinforced Steel Cage is a steel reinforced steel cage which is installed in a lattice and overlapped with one layer or several layers according to structural needs, and is buried in shotcrete.

"종방향"이란 터널 굴착 진행 방향을 말한다."Longitudinal direction" refers to the tunnel excavation direction.

파일럿 터널의 "확대 굴착부"란, 본 터널 예정 굴착면과 파일럿 터널 굴착면 사이로 정의하고, 파일럿 터널 원지반이라고도 한다.The "enlarged excavation part" of the pilot tunnel is defined as the area between the intended tunnel excavation surface and the pilot tunnel excavation surface, and is also referred to as the pilot tunnel ground section.

"순차적으로 발파"라고 하는 것은 도 3에서 보는 바와 같이, 1차 발파부터 4차발파까지 차례로 진동이 중복되지 않도록 시간차를 주어 발파 하는 것으로, 1차 발파부터 4차발파의 뇌관 결선을 하나의 그룹으로 하여 각각 그룹 간 시간차를 두어서 점화하는 것을 말한다.As shown in FIG. 3, the "sequential blasting" refers to blasting by giving a time difference so that vibrations do not overlap in sequence from the first blasting to the fourth blasting, and the blasting of the first blasting to the fourth blasting is referred to as one group And the time difference between the groups is set so as to ignite.

도 1을 보면, 예정 본 터널의 주면 굴착면(1)에서 이격되어 본 터널보다 직경이 작은 파일럿 터널(2)이 굴착되어 있다. 이격 거리는 파일럿 터널의 굴착에 따른 이완 영역 거리보다 크거나 미소한 영향을 받는 거리가 될수록 선지보 효과가 발생한다.1, a pilot tunnel 2 having a diameter smaller than that of the main tunnel is excavated, which is spaced apart from the main excavation surface 1 of the main tunnel. The spacing distance is larger than the relaxation area distance due to the excavation of the pilot tunnel,

상기 파일럿 터널(2)은 종래의 굴착 방법으로 굴착 또는 TBM 공법(머신)으로 굴착할 수 있다. 상기 방법들 중 어느 하나의 방법으로 굴착된 파일럿 터널(2)에서 예정 본 터널의 주면 굴착면(1)을 지나 터널 원지반에 천공기로 장공을 천공하고, 상기 장공에 선지보재(4)(도 3 참조)를 밀어 넣고, 그라우팅 또는 가압 그라우팅하여 원지반을 그라우팅에 의한 지반 개량과 차수 효과를 갖게 하여 원지반과 일체화되게 한다. 상기 선지보재(4)는 예정 본 터널의 주면 굴착면(1)보다 약간 아래로 돌출되도록 삽입하게 되므로 파일럿 터널(2)에서 예정 본 터널의 주면 굴착면(1)까지의 사이에 장공은 빈공으로 남아 있게 된다. 상기 빈공은 추후 파일럿 터널의 원지반 발파시 화약을 장약하는 장약공으로 사용할 수 있으므로 전체 장약공의 천공 갯수를 줄여 시공할 수 있다. 추후에 파일럿 터널(2)에서 예정 본 터널의 주면 굴착면(1) 사이의 파일럿 터널의 원지반을 굴착한 후에는 상기 선지보재(4)는 판형 지보재와 일체화시킨다. The pilot tunnel 2 can be excavated with a conventional excavation method or excavated with a TBM method (machine). In the pilot tunnel 2 excavated by any one of the above methods, a long hole is drilled through a main excavation surface 1 of a tunnel to be tunnelled by a perforator in the tunnel base plate, and the pre-supports 4 ), Grouting or pressurized grouting, so that the ground surface is integrated with the paperboard by providing ground improvement and order effect by grouting. Since the pre-supports 4 are inserted so as to protrude slightly below the main surface excavation surface 1 of the planned tunnel, the long holes are formed between the pilot tunnel 2 and the main excavation surface 1 of the planned tunnel, Will remain. Since the vacant space can be used as a loading space to charge a gunpowder when the ground block of the pilot tunnel is later blasted, it is possible to reduce the number of holes in the entire loading space. After the excavation of the ground plate of the pilot tunnel between the pilot tunnel 2 and the main excavation surface 1 of the planned tunnel in the future, the pre-supports 4 are integrated with the plate-like support.

파일럿 터널의 원지반(9)을 굴착하기 위하여 장약공은 파일럿 터널에서 방사상으로 천공한다. 이러한 장약공은 터널의 시점부로부터 터널의 종점부를 향하여 터널의 종방향으로 연속하여 시공한다. 방사상 장약공의 발파는 1회 굴착과 지보를 하는 굴진장을 터널의 종방향으로 다수의 방사상 장약공을 순차적으로 연속 발파하게 되며, 굴착하기 전에 터널이 자립하도록 지보를 해 놓았기 때문에 연속하여 복수의 방사상 장약공을 발파 할 수 있는 것이다.In order to excavate the ground plate 9 of the pilot tunnel, the loading hole is drilled radially in the pilot tunnel. These charging holes are continuously constructed in the longitudinal direction of the tunnel from the viewpoint of the tunnel toward the end point of the tunnel. The blasting of the radial charge ball causes continuous excavation of the radial charge ball in the longitudinal direction of the tunnel by the excavation field which performs one excavation and support, and since the tunnel is self-sustained before excavation, Of the radial charge ball.

장공의 천공 직경은 연약 지반에서는 주입재와 원지반의 전단 강도를 고려하여 105mm~200mm 정도로 천공하고 암반에서는 원지반 35mm~105mm 정도로 천공한다. 선지보재(4)의 간격은 연약 지반이나 토사 암반 등의 지반 조건에 따라 수치해석을하여 간격을 달리하여 시공한다.The perforation diameter of the long hole is about 105mm ~ 200mm in consideration of the shear strength of the injection material and the paper in the soft ground, and is drilled in the rock about 35mm ~ 105mm. The spacing of the prefabricated materials (4) is numerically analyzed according to the ground conditions such as soft ground and sandstone rock, and construction is carried out at intervals.

도 1에서, 예정 본 터널의 주면 굴착면(1)에 본 터널 주면공(5)을 복수개 천공하게 된다. 상기 본 터널 주면공(5)은 터널의 길이 방향, 즉 종방향으로 천공한다. In FIG. 1, a plurality of main tunnel holes 5 are drilled on the main tunnel excavation surface 1 of the tunnel to be tuned. The main tunnel main surface hole 5 is perforated in the longitudinal direction, that is, the longitudinal direction of the tunnel.

본 터널 주면공(5)의 횡방향 간격은 목적에 따라 다르게 설치한다.The lateral spacing of the tunnel main surface 5 of the main tunnel is set differently according to the purpose.

첫째, 본 터널 굴착시 진동 감소를 목적으로 할 때에는 본 터널 주면에 라인 드릴링이 되도록 가능한 10cm이상의 큰 직경을 30cm 간격으로 조밀하게 설치하여 파일럿 터널 원지반이 발파시 진동 에너지가 감쇄되도록 하거나 파력이 반사되도록 한다. 주면공의 직경을 10cm로 하고, 이웃하는 주면공과의 간격을 30cm로 라인 드릴링을 하면, 본 터널 원지반으로 전달되는 진동은 파일럿 터널의 원지반의 발파 진동의 30% 정도가 감소된다.First, in order to reduce the vibration during excavation of the tunnel, it is necessary to dispose the large diameter of 10cm or more as much as 30cm as possible to enable line drilling on the main tunnel surface so that the vibration energy is reduced or the wave is reflected when the pilot tunnel ground is blasted. do. When the diameter of the main hole is 10cm and the distance between the adjacent main hole is 30cm, the vibration transmitted to the main tunnel is reduced by about 30% of the blasting vibration of the ground of the pilot tunnel.

둘째, 선균열 발파를 목적으로 할 때는 주면에 격간으로 장약을 하여 발파하므로서 선균열이 발생되도록 한 후, 파일럿 터널 원지반을 종방향으로 순차적으로 발파하며 이와 같은 발파는 본 터널 주면에 여굴이 최소화되도록 매끈한 발파 결과를 얻는다.Second, for the purpose of blast cracking, the blast furnace is buried in the main surface and blasted so that the cracks are generated. Then, the pilot tunnel is sequentially blasted in the longitudinal direction, and such blasting is performed so that the burrows on the main tunnel surface are minimized Obtain smooth blasting results.

세째, 스므스 블라스팅 장약을 할 때는 천공홀의 직경보다 작은 직경의 정밀화약을 사용하여 발파하게 되며 발파 순서는 파일럿 터널 원지반의 방사상 장약공을 먼저 순차적으로 발파한 후 본 터널 주면공(5)을 발파한다.Third, blasting is carried out using fine powder of diameter less than the diameter of the perforation hole, and the order of blasting is to sequentially blast the radial charge ball of the pilot tunnel and then blast the main tunnel hole (5) .

네째, 순기폭으로 발파를 할 때에는 방사상 장약공을 종방향 장약 간격보다 더 크게 본 터널 주면공에서 이격하여 방사상 장약공 선단을 배치하며 발파 순서는 방사상 장약공을 파일럿 터널 굴착면에서부터 본 터널 굴착면으로 순차적으로 발파한 후 본 터널 주면공(5)을 발파한다.Fourthly, when blasting with a net explosion, radial charge holes are spaced from the main tunnel hole, which is larger than the longitudinal charge gap, and radial charge holes are arranged. The order of blasting is the tunnel excavation face viewed from the pilot tunnel excavation face , And then blast the main tunnel hole (5).

일반적인 설계를 할때에 진동 감소를 위한 본 터널 주면공의 횡방향 간격은 첫번째의 라인 드릴링이 가장 좁게 설치되며 순기폭 발파는 간격이 가장 크게 된다. In general design, the lateral gap of the main tunnel for vibration reduction is set to be the narrowest in the first line drilling and the largest gap in the net explosive blasting.

상기 본 터널 주면공들의 간격은 터널 원지반의 암질 또는 토질의 종류에 따라 간격을 달리하여 설계한다.The spacing of the main tunnel holes is designed to be different according to the rock quality of the tunnel base or the type of soil.

가능한 진동제어의 크기는, 라인 드릴링이 가장 작게 설계가 가능하고 굴착면의 여굴을 고려하여 진동제어를 할때는 선균열 발파 또는 스므스 블라스팅 공법을 주면공에 적용 한다.The possible size of vibration control is that the line drilling can be designed to be the smallest, and when vibration control is performed considering the excavation surface, line blasting or smash blasting is applied to the ball.

본 터널의 주면공의 간격은 암질과 진동의 영향이 미치는 보안물건의 허용가능한 진동치에 맞도록 결정하여 설계하면 된다. The spacing of the main surface of the main tunnel may be determined by designing it according to the allowable vibration value of the security object affected by the rock quality and vibration.

설계방법은 해당지반의 발파진동 추정식과 기존의 주면공 간격에 따른 진동 차단률을 고려하여 장약량과 장약공 배치를 하면 된다The design method should be based on the blast vibration estimation formula of the relevant ground and the vibration blocking rate according to the interval of the main surface of the ground.

도 1에서는 본 터널 주면공(5)에 장약으로 하지 않기 때문에 본 터널 주면공(5)과 파일럿 터널의 원지반의 장약공의 장약면까지의 거리가 비교적 짧으며, 파일럿 터널의 원지반의 장약공의 장약이 발파될 때, 라인 드릴링된 주면공이 약대가 되어 굴착면이 되게 되며 라인 드릴링에 의해 발파 진동이 반사 되거나 감쇄된다.1, the distance to the loading surface of the main tunnel of the main tunnel of the tunnel is relatively short because the main tunnel hole 5 of the main tunnel of the tunnel is not charged, When the charge is blasted, the line-drilled main surface becomes the excavation surface, and the blasting vibration is reflected or attenuated by the line drilling.

도 2 및 도 3에 도시되어 있는 바와 같이, 장약공은 이전에 천공한 선지보 설치를 위한 장공의 빈공을 이용하는 장약공(6-3)과, 빈공 장약공 사이에 1개 이상의 방사상으로 장약공(6-1, 6-2, 6-4)을 천공한다. 상기와 같은 방사상 장약공(6-1, 6-2, 6-3, 6-4)은 터널의 길이 방향으로 반복하여 천공한다.As shown in FIGS. 2 and 3, the charge ball is provided with a charge hole 6-3 using a hole of a long hole for pre-drilling the previously inserted hole, and a charge hole 6-3, (6-1, 6-2, 6-4). The radial charging holes 6-1, 6-2, 6-3 and 6-4 are repeatedly perforated in the longitudinal direction of the tunnel.

터널의 굴착은 본 천공홀에 장약하여 지반과 지보 조건에 따라서 도 3에 도시되어 있는 바와 같이 순차적으로 3~4회 발파 후 굴착면 스케일링과 버력 처리 숏크리트 지보와 선지보재의 지압판 설치를 한다. 이와 같은 작업을 반복하여 터널을 굴착한다.Excavation of the tunnels takes place in this perforation hole, and excavation surface scaling, buckling treated shotcrete support and prefabrication of the prefabricated plates are installed 3 ~ 4 times in succession as shown in Fig. 3 depending on the ground and support conditions. These operations are repeated to excavate the tunnel.

도 2를 보면, 장약공을 1m 간격으로 설치하여 첫번째, 두번째, 세번째, 및 네번째 장약공(6-1, 6-2, 6-3, 6-4)을 시차를 두어 순차적으로 발파시 한번에 4m씩 굴진할 수 있다. 따라서, 종래 기술 대비 1회 굴진장을 4배씩 길게 할 수 있으므로 급속 시공이 가능하게 된다. 2, the charge ball is installed at an interval of 1 m, and the first, second, third, and fourth charge holes 6-1, 6-2, 6-3, and 6-4 are staggered sequentially, I can be pushed by each one. Accordingly, since the one-time bending length can be lengthened four times as compared with the conventional technology, rapid construction becomes possible.

이때, 상기 장약공(6-1, 6-2, 6-3, 6-4)은 각 단면별로 그룹을 지어 화약과 뇌관을 결선하여 장약을 한다.At this time, the charge holes (6-1, 6-2, 6-3, 6-4) are grouped by each cross section, and the gunpowder and the primer are connected and charged.

도 3은 선지보재(4) 설치시 생기는 빈공에도 이 빈공이 속하는 단면에 함께 장약한다. 추후, 상기 장약공(6-1, 6-2, 6-3, 6-4)은 터널의 막장 쪽에서부터 종방향으로 순차적으로 발파하게 된다. 상기 장약공(6-1, 6-2, 6-3, 6-4)을 순차 발파한 각 발파장을 방사상 장약공의 종방향 간격(13)이라 하고 순차발파를 완료하고 지보를 하는 종방향 거리를 1회 굴진장이라 한다.Fig. 3 also shows the vents formed when the pre-supports 4 are installed together with the cross section to which these vias belong. Then, the charge holes 6-1, 6-2, 6-3, and 6-4 are sequentially blasted in the longitudinal direction from the tunnel side of the tunnel. Each of the charge waves successively blasted through the charge holes 6-1, 6-2, 6-3 and 6-4 is referred to as a longitudinal gap 13 of radial charge holes, The distance is called a bow.

상기와 같이, 파일럿 터널의 원지반을 순차적으로 발파하면, 폭력이 누적된 진동이 발생하지 않는다. 또한, 미리 시공된 파일럿 터널에서 본 터널 원지반을 선지보에 의하여 완벽히 지보했을 경우에는 막장부터 종방향으로 무한하게 순차적으로 발파가 가능하여 급속 시공이 가능하다. As described above, when the ground plates of the pilot tunnel are sequentially blasted, the accumulated vibration does not occur. In addition, when the tunnel base is completely supported by the pre- war beam, it can be blasted in an infinite sequence from the tunnel to the longitudinal direction, and rapid construction is possible.

도 4를 보면, 도 1에 도시된 발파 공법의 하부 단면 영역 구분도이다. 도 1 및 도 4의 하부 단면 영역(7, 8)은 도 4의 상부 단면 영역(9)을 상기 설명과 같이 순차 발파를 완료하고 도 4의 좌우측 하부 단면 영역(7, 8)에 단면 영역 천공홀(10)을 터널의 길이 방향으로 천공하고 화약을 장약한 후 발파한 후 버력을 밖으로 반출한다.FIG. 4 is a bottom cross-sectional view of the blasting process shown in FIG. 1. FIG. The lower section areas 7 and 8 of Figs. 1 and 4 complete the upper section area 9 of Fig. 4 by the sequential blasting as described above and the cross section area perforations 7 and 8 of the left and right lower section areas 7 and 8 of Fig. Holes 10 are punctured in the longitudinal direction of the tunnel, charged with gunpowder, blasted, and discharged outward.

도 5는 본 발명에 따른 발파 공법에 사용되는 장약 방법 중 선균열 발파 공법을 도시한 도면이다. 본 터널의 바로 아래의 주면을 따라 복수의 주면공을 터널의 종방향으로 천공하고 상기 주면공의 장약은 격간 장약을 한다. 선균열 발파 공법에서의 주면공간의 간격은 주면공과 주면공 사이가 크랙이 갈정도의 장약량이 되도록 설정한다. 파일럿 터널의 원지반에 방사상 장약을 할 때, 본 터널주면공으로부터 파일럿 터널의 원지반 내의 장약공의 선단은 지반의 연경도에 따라서 간격을 설계한다. 5 is a view showing a line cracking blasting method among the charging methods used in the blasting method according to the present invention. A plurality of main surfaces are drilled along the main surface immediately below the tunnel in the longitudinal direction of the tunnel, and the charge of the main surface is charged gradually. The spacing of the main surface spaces in the pre-cracking blasting method is set so that the amount of load between the main surface and the main surface is sufficient for the cracks to be generated. When radial loading is applied to the ground of the pilot tunnel, the tip of the charge hole in the ground of the pilot tunnel from the main tunnel hole is designed in accordance with the ground degree of the ground.

도 6은 본 발명에 따른 발파 공법에 사용되는 장약 방법 중 스므스 블라스팅 발파 공법을 도시한 도면이다. 스므스 블라스팅 발파 공법에서는 모든 주면공에 장약을 하는데, 이때, 주면공의 직경보다 작은 직경을 가진 정밀 화약을 장약하게 된다. 발파의 점화 순서는 파일럿 터널의 굴착면부터 본 터널 주면공으로 진행된다6 is a view showing a smash blasting blasting method among the charging methods used in the blasting method according to the present invention. In the smash blasting blasting method, all the surface balls are charged, and at this time, the fine powder having a diameter smaller than the diameter of the main surface balls is weakened. The ignition sequence of the blasting progresses from the excavation side of the pilot tunnel to the main tunnel side of the tunnel

발파에 의한 원지반(Natural ground)의 손상을 억제하여 여굴(餘掘)을 감소시킴과 동시 굴착면을 평활하게 완성하기 위하여 스므스 발파 공법을 이용한다. 균열이 적은 경암(硬岩)에 대하여 유리한 공법이나 균열이 많은 경암이나 연암에서는 효과가 적다.We use smash blasting technique to reduce the damage of natural ground by blasting and to reduce the excavation and smoothly finish the excavation surface simultaneously. This method is less effective for hard rocks with less cracks and more advantageous for hard rocks and soft rocks with many cracks.

도 7은 본 발명의 또 다른 발파 방법으로 주면공에서 방사상 장약공의 선단까지 이격거리를 종방향으로 방사상 장약공 간격 이상으로 하여 장약하고 파일럿 터널을 자유면으로 순기폭 방법으로 주면공까지 순차적으로 발파하는 것이다. 도면에서 보는 바와 같이, 파일럿 터널 굴착면쪽으로부터 본 터널 주면공 쪽으로 순차적으로 장약이 발파되는 것을 순기폭 공법이라 하고, 이와 반대로 발파되는 것을 역기폭 발파라 한다. 터널에서는 역기폭 공법은 원지반 손상과 진동이 과대하여 잘 사용하지 않는다. 순기폭 공법을 적용하게 되면, 파일럿 터널 쪽으로부터 본 터널쪽으로 순차적으로 장약이 발파되므로 파일럿 터널 내부가 자유면이 되게 되어 적은 장약으로 발파가 용이해지므로 순기폭 공법을 많이 적용한다. 7 is a view showing another method of blasting according to the present invention in which the distance from the main surface to the tip of the radial loading hole is set to be longer than the radial loading gap in the longitudinal direction and the pilot tunnel is moved to the free surface in a sequential manner It is to blast. As can be seen from the figure, the explosion of charges in succession from the excavation surface of the pilot tunnel toward the main tunnel side is called net explosion method, and conversely, the explosion is counterbalanced. In tunnel, weft width method does not use well due to excessive damage and vibration. Since the charge tunnel is blasted sequentially from the pilot tunnel side to the tunnel side, the inside of the pilot tunnel becomes free side and the blasting is facilitated with a small charge.

상기 본 터널 주면공(5)으로부터 파일럿 터널의 원지반의 장약공 선단까지의 거리는 종방향으로 방사상 장약공 간격 이상으로, 대략 1m~2.0m 정도의 거리로 장약을 하면 된다.The distance from the main tunnel main surface hole 5 to the tip of the loading ball on the ground surface of the pilot tunnel may be set at a distance of about 1 m to 2.0 m at a radial charge hole spacing or more in the longitudinal direction.

도 7에 도시된 순기폭 공법에서는 모든 주면공에 장약을 하기 때문에 본 터널 주면공과 파일럿 터널의 원지반의 장약공 선단까지의 거리가 비교적 길게 설계되며 발파시 파일럿 터널 굴착면에서 본 터널 주면공까지 순차적으로 발파되어 적은 장약량으로 효율적인 굴착이 된다. 순기폭의 발파 순서는 방사상의 장약공(6-1, 6-2, 6-3, 6-4)을 1차 발파 내지 4차 발파까지 연속으로 진행한 후 본 터널 주면공(5)의 순서로 발파한다.7, the distance from the main tunnel to the tip of the loading ball of the main tunnel of the main tunnel is designed to be relatively long, and the distance from the pilot tunnel excavation surface to the main tunnel of the tunnel So that efficient excavation can be carried out with a small amount of load. The order of explosion of the net explosion is that the radial charge holes (6-1, 6-2, 6-3, 6-4) are consecutively performed from the first blast to the fourth blast, .

위에서 살펴본 바와 같이, 본 발명에 따른 본 터널 주면공의 굴착면 형성 방법으로 라인 드릴링 공법, 선균열 공법, 스무스 블라스팅 공법, 순기폭 공법은 시공하려는 터널의 원지반의 암질과 보안 물건과의 거리에 따라 하나의 공법 또는 두 개 이상의 공법의 조합을 적절히 선택하여 시공하며, 풍화암과 같이 지반이 연약하여 발파없이 본터널의 굴착면을 쉽게 정형이 가능하면 주면공을 생략하고 방사상 천공과 장약을 하여 본 발명의 기술 사상으로 굴착 할 수 있다. As described above, according to the present invention, the line drilling method, line cracking method, smooth blasting method, and net explosion-proof method can be classified according to the distance between the rock material of the ground of the tunnel to be constructed and the security object If the excavation surface of the tunnel can be easily shaped without the blasting due to the weak ground such as weathered rock, the main surface is omitted and the radial perforation and charge are made, Can be excavated by the technical idea of.

본 발명의 가장 중요한 내용으로 도 2와 도 3에서 보는바와 같이, 파일럿 터널의 원지반을 순차적으로 발파하면, 폭력이 누적된 진동이 발생하지 않는다. 또한, 미리 시공된 파일럿 터널에서 본 터널 원지반을 선지보에 의하여 완벽히 지보 했을 경우에는 막장부터 종방향으로 무한하게 순차적으로 발파가 가능하여 급속 시공이 가능하다. 다만, 실제 시공에서는 안전과 공정상 일정한 1회 굴진장을 정하여 순차적 발파와 지보를 반복하여 터널을 시공한다.As shown in FIG. 2 and FIG. 3, when the ground plates of the pilot tunnel are sequentially blasted, the accumulated vibration does not occur. In addition, when the tunnel base is completely supported by the pre-war beam, it can be blasted in an infinite sequence from the tunnel to the longitudinal direction, and rapid construction is possible. However, in the actual construction, the tunnel is constructed by repeating the sequential blasting and supporting operation by setting a certain one round of the safety and the process.

본 명세서의 기술 사상은 선지보된 지반의 자립시간을 활용하여 1회 굴진장을 종래 공법보다 길게하여 시공하므로 굴착 준비, 환기, 숏크리트 취부 시간을 절감하고 일정한 굴진장으로 반복 시공이 가능하여 안전 사고도 줄일 수 있는 장점이 있다.The technical idea of this specification is to use the self-standing time of the ground to make the excavation length longer than the conventional method, so that it is possible to reduce excavation preparation, ventilation, shotcrete installation time and repeat construction with constant excavation length, There is an advantage that it can be reduced.

본 명세서의 실시 방법을 단계별로 나타내면 다음과 같다.Hereinafter, the method of the present invention will be described step by step.

본 터널을 선지보하고 굴착하기 위하여 예정 본 터널의 주면 굴착면(1)에서 이격하여 파일럿 터널(2)을 굴착하는 단계와,A step of excavating the pilot tunnel 2 from the main excavation surface 1 of the planned tunnel to excavate and tunnel the tunnel,

상기 파일럿 터널(2)에서 상기 예정 본 터널의 주면 굴착면(1)을 지나 터널 원지반 내에 장공을 천공하여 선지보재(4)를 삽입하고 그라우팅하는 단계와, Inserting and grouting the pre-support material (4) by drilling a long hole in the tunnel base plate through the main tunnel excavation surface (1) of the planned tunnel in the pilot tunnel (2)

상기 파일럿 터널(2)내에서 파일럿 터널의 원지반(9)에 터널의 종방향으로 방사상 장약공(6-1, 6-2, 6-3, 6-4)을 일정한 간격으로 장약공 선단이 예정 본 터널의 주면 굴착면(1)에 인접하도록 천공 형성하는 단계와,6-2, 6-3 and 6-4 in the longitudinal direction of the tunnels to the ground plate 9 of the pilot tunnel in the pilot tunnel 2 at regular intervals Forming a perforation adjacent to the main excavation surface (1) of the main tunnel,

상기 장약공(6-1, 6-2, 6-3, 6-4)에 각 단면별로 그룹을 지어 화약과 뇌관을 결선하여 장약하고 상기 선지보재(4) 설치시 생기는 빈공(12)의 장약공(6-3)에도 그 빈공(12)이 속하는 단면에 화약과 뇌관을 결선하여 장약하는 단계와,(6-1, 6-2, 6-3, 6-4) are grouped by each cross section to connect the gunpowder and the primer and charge the charge of the vents (12) generated in the installation of the pre- In the hole (6-3), a charge and a primer are connected and charged to a cross section to which the void 12 belongs,

상기 장약공(6-1, 6-2, 6-3, 6-4)을 터널의 막장쪽에서부터 터널의 종방향으로 순차적으로 발파하는 단계와,(6-1, 6-2, 6-3, 6-4) sequentially from the surface side of the tunnel to the longitudinal direction of the tunnel,

상기 발파에 의해 형성된 굴착면의 부석을 제거하고 면을 정형하는 단계와,Removing the pits of the excavation surface formed by the blasting and shaping the surface,

상기 발생된 버력을 밖으로 반출하고 굴착면을 추가 지보하는 단계로 이루어진다.Taking out the generated buckling force and further supporting the excavation surface.

본 발명의 다른 양태의 발명은, 상기 방사상 장약공(6-1, 6-2, 6-3, 6-4)을 천공 형성하는 단계와, 상기 방사상 장약공(6-1, 6-2, 6-3, 6-4)에 장약하는 단계 사이에, 상기 예정 본 터널의 주면 굴착면(1)이 형성되고 진동이 감쇄되도록 상기 예정 본 터널의 주면 굴착면(1)에 종방향으로 복수 개의 본 터널 주면공(5)을 천공하는 단계를 더 구비한다.The invention according to another aspect of the present invention is characterized in that it comprises the steps of forming the radial charging holes 6-1, 6-2, 6-3 and 6-4 by perforating the radial charging holes 6-1, 6-2, 6-3 and 6-4, a main excavation surface (1) of the predetermined tunnel is formed and a plurality of excavation surfaces Further comprising the step of drilling the tunnel main surface hole (5).

본 발명의 또 다른 하나의 양태는, 본 터널을 선지보하고 굴착하기 위하여 예정 본 터널의 주면 굴착면(1)에서 이격하여 파일럿 터널(2)을 굴착하는 단계와,According to another aspect of the present invention, there is provided a method of tunneling a tunnel, comprising the steps of: excavating a pilot tunnel (2) at a distance from a main surface excavation surface (1)

상기 파일럿 터널(2)에서 상기 예정 본 터널의 주면 굴착면(1)을 지나 터널 원지반 내에 장공을 천공하여 선지보재(4)를 삽입하고 그라우팅하는 단계와,Inserting and grouting the pre-support material (4) by drilling a long hole in the tunnel base plate through the main tunnel excavation surface (1) of the planned tunnel in the pilot tunnel (2)

상기 예정 본 터널의 주면 굴착면(1)에 복수 개의 본 터널 주면공(5)을 천공하는 단계와,Drilling a plurality of main tunnel main surfaces (5) on the main surface excavation surface (1) of the predetermined tunnel,

상기 파일럿 터널(2)내에서 종방향으로 본 터널 주면 굴착면(1)에서 장약공 선단이 장약공의 종방향 간격(13) 만큼 이격하여 방사상으로 장약공(6-1, 6-2, 6-3, 6-4)을 설치하는 단계와,6-2, 6 (6-1, 6-2, 6-3, 6-2, 6-3, 6-2, 6-3, 6-2, 6-3, 6-2, 6-4) radially in the longitudinal direction of the pilot tunnel 2, -3, 6-4)

상기 방사상 장약공(6-1, 6-2, 6-3, 6-4)에 각 단면별로 그룹을 지어 화약과 뇌관을 결선하여 장약하고 상기 선지보재(4) 설치시 생기는 빈공(12)에도 그 빈공(12)이 속하는 단면에 화약과 뇌관을 결선하여 장약하는 단계와,The radial charge holes 6-1, 6-2, 6-3 and 6-4 are grouped in each cross section to connect the gunpowder and the primer to charge the radial charge holes 6, and the vents 12 formed in the installation of the pre- Connecting the explosive and primer to the cross section to which the vents 12 belong,

상기 복수 개의 본 터널 주면공에 천공직경 보다 작은 직경의 정밀 화약을 장약하는 단계와,Charging a fine powder having a diameter smaller than a pore diameter in the plurality of main tunnel main surfaces;

상기 방사상 장약공(6-1, 6-2, 6-3, 6-4)을 터널의 막장쪽에서부터 터널의 종방향으로 순차적으로 발파하는 단계와,Sequentially blasting the radial charging holes 6-1, 6-2, 6-3, and 6-4 from the surface side of the tunnel in the longitudinal direction of the tunnel,

상기 본 터널 주면공을 발파하는 단계와, Blasting the main tunnel main hole;

상기 발파에 의해 형성된 굴착면의 부석을 제거하고 면을 정형하는 단계와,Removing the pits of the excavation surface formed by the blasting and shaping the surface,

상기 발생된 버력을 밖으로 반출하고 굴착면을 추가 지보하는 단계로 이루어진다.Taking out the generated buckling force and further supporting the excavation surface.

본 발명의 또 다른 하나의 양태는, 본 터널을 선지보하고 굴착하기 위하여 예정 본 터널의 주면 굴착면(1)에서 이격하여 파일럿 터널(2)을 배치하여 굴착하는 단계와,In another aspect of the present invention, there is provided a method for constructing a tunnel, comprising the steps of: disposing and drilling a pilot tunnel (2) apart from a main surface excavation surface (1)

상기 파일럿 터널(2)에서 상기 예정 본 터널의 주면 굴착면(1)을 지나 터널 원지반 내에 장공을 천공하여 선지보재(4)를 삽입하고 그라우팅하는 단계와,Inserting and grouting the pre-support material (4) by drilling a long hole in the tunnel base plate through the main tunnel excavation surface (1) of the planned tunnel in the pilot tunnel (2)

상기 파일럿 터널(2)내에서 파일럿 터널의 원지반(9)에 본 터널 주면공(5)으로부터 방사상 장약공(6-1, 6-2, 6-3, 6-4) 선단이 방사상 장약공의 종방향 간격(13) 이상이 되도록 천공 형성하는 단계와,The ends of the radial charge holes 6-1, 6-2, 6-3, and 6-4 from the tunnel main surface 5 seen from the ground plate 9 of the pilot tunnel in the pilot tunnel 2, Forming a perforation to be equal to or greater than the longitudinal spacing 13,

상기 예정 본 터널의 주면 굴착면(1)이 형성되도록 상기 예정 본 터널의 주면 굴착면(1)에 주면을 따라 복수 개의 본 터널 주면공(5)을 천공하는 단계와, Drilling a plurality of main tunnel main surfaces 5 along a main surface on the main surface excavation surface 1 of the predetermined tunnel so that the main excavation surface 1 of the predetermined tunnel is formed,

상기 장약공(6-1, 6-2, 6-3, 6-4)에 각 단면별로 그룹을 지어 화약과 뇌관을 결선하여 장약하고 상기 선지보재(4) 설치시 생기는 빈공(12)의 장약공(6-3)에도 그 빈공(12)이 속하는 단면에 화약과 뇌관을 결선하여 장약하는 단계와,(6-1, 6-2, 6-3, 6-4) are grouped by each cross section to connect the gunpowder and the primer and charge the charge of the vents (12) generated in the installation of the pre- In the hole (6-3), a charge and a primer are connected and charged to a cross section to which the void 12 belongs,

상기 복수 개의 본 터널 주면공(5)을 모두 장약하는 단계와,Loading all of the plurality of main tunnel main surfaces 5,

상기 장약공(6-1, 6-2, 6-3, 6-4)을 터널의 막장쪽에서부터 터널의 종방향으로 순차적으로 발파하는 단계와,(6-1, 6-2, 6-3, 6-4) sequentially from the surface side of the tunnel to the longitudinal direction of the tunnel,

상기 복수 개의 본 터널 주면공(5)을 발파하는 단계와,Blasting the plurality of main tunnel main surfaces (5)

상기 발파에 의해 형성된 굴착면의 부석을 제거하고 면을 정형하는 단계와,Removing the pits of the excavation surface formed by the blasting and shaping the surface,

상기 발생된 버력을 밖으로 반출하고 굴착면을 추가 지보하는 단계로 이루어진다.Taking out the generated buckling force and further supporting the excavation surface.

1 : 예정 본 터널의 주면 굴착면 2 : 파일럿 터널
3 : 원지반 4 : 선지보재
5 : 본 터널 주면공 6 : 6-1~6-4 : 방사상 장약공
7 : 좌측 하부 단면 영역 8 : 우측 하부 단면 영역
9 : 파일럿 터널의 원지반(파일럿터널확대 굴착부) 10 : 단면 영역 천공홀
12 : 빈공(선지보 삽입후 생기는 빈공) 13 : 방사상 장약공의 종방향 간격
1: excavation surface of main tunnel in planned tunnel 2: pilot tunnel
3: Origami paper 4: Prefabricated material
5: Main tunnel 6: 6-1 ~ 6-4: Radial charge
7: lower left section area 8: right lower section area
9: ground plate of pilot tunnel (pilot tunnel enlarging excavation part) 10: cross-sectional area drilling hole
12: Vacuum (void created after insertion of the beam) 13: Longitudinal distance of the radial load

Claims (4)

본 터널을 선지보하고 굴착하기 위하여 예정 본 터널의 주면 굴착면(1)에서 이격하여 파일럿 터널(2)을 굴착하는 단계와,
상기 파일럿 터널(2)에서 상기 예정 본 터널의 주면 굴착면(1)을 지나 터널 원지반 내에 장공을 천공하여 선지보재(4)를 삽입하고 그라우팅하는 단계와,
상기 파일럿 터널(2)내에서 파일럿 터널의 원지반(9)에 터널의 종방향으로 방사상 장약공(6-1, 6-2, 6-3, 6-4)을 일정한 간격으로 장약공 선단이 예정 본 터널의 주면 굴착면(1)에 인접하도록 천공 형성하는 단계와,
상기 장약공(6-1, 6-2, 6-3, 6-4)에 각 단면별로 그룹을 지어 화약과 뇌관을 결선하여 장약하고 상기 선지보재(4) 설치시 생기는 빈공(12)의 장약공(6-3)에도 그 빈공(12)이 속하는 단면에 화약과 뇌관을 결선하여 장약하는 단계와,
상기 장약공(6-1, 6-2, 6-3, 6-4)을 터널의 막장쪽에서부터 터널의 종방향으로 순차적으로 발파하는 단계와,
상기 발파에 의해 형성된 굴착면의 부석을 제거하고 면을 정형하는 단계와,
상기 발생된 버력을 밖으로 반출하고 굴착면을 추가 지보하는 단계로 이루어지는 파일럿 터널을 이용한 미진동 급속 굴착 방법.
A step of excavating the pilot tunnel 2 from the main excavation surface 1 of the planned tunnel to excavate and tunnel the tunnel,
Inserting and grouting the pre-support material (4) by drilling a long hole in the tunnel base plate through the main tunnel excavation surface (1) of the planned tunnel in the pilot tunnel (2)
6-2, 6-3 and 6-4 in the longitudinal direction of the tunnels to the ground plate 9 of the pilot tunnel in the pilot tunnel 2 at regular intervals Forming a perforation adjacent to the main excavation surface (1) of the main tunnel,
(6-1, 6-2, 6-3, 6-4) are grouped by each cross section to connect the gunpowder and the primer and charge the charge of the vents (12) generated in the installation of the pre- In the hole (6-3), a charge and a primer are connected and charged to a cross section to which the void 12 belongs,
(6-1, 6-2, 6-3, 6-4) sequentially from the surface side of the tunnel to the longitudinal direction of the tunnel,
Removing the pits of the excavation surface formed by the blasting and shaping the surface,
And a step of taking out the generated buckling force and further supporting the excavation surface.
청구항 1에 있어서,
상기 방사상 장약공(6-1, 6-2, 6-3, 6-4)을 천공 형성하는 단계와, 상기 방사상 장약공(6-1, 6-2, 6-3, 6-4)에 장약하는 단계 사이에, 상기 예정 본 터널의 주면 굴착면(1)이 형성되고 진동이 감쇄되도록 상기 예정 본 터널의 주면 굴착면(1)에 종방향으로 복수 개의 본 터널 주면공(5)을 천공하는 단계를 더 구비하는 파일럿 터널을 이용한 미진동 급속 굴착 방법.
The method according to claim 1,
(6-1, 6-2, 6-3, 6-4) by drilling the radial charging holes (6-1, 6-2, 6-3, 6-4) A plurality of main tunnel boring holes 5 are formed in the longitudinal direction on the main tunnel excavation surface 1 of the predetermined tunnel so that the main tunnel excavation surface 1 of the tunnel is formed and the vibration is attenuated, Further comprising the steps of:
본 터널을 선지보하고 굴착하기 위하여 예정 본 터널의 주면 굴착면(1)에서 이격하여 파일럿 터널(2)을 굴착하는 단계와,
상기 파일럿 터널(2)에서 상기 예정 본 터널의 주면 굴착면(1)을 지나 터널 원지반 내에 장공을 천공하여 선지보재(4)를 삽입하고 그라우팅하는 단계와,
상기 예정 본 터널의 주면 굴착면(1)에 복수 개의 본 터널 주면공(5)을 천공하는 단계와,
상기 파일럿 터널(2)내에서 종방향으로 본 터널 주면 굴착면(1)에서 장약공 선단이 장약공의 종방향 간격(13) 만큼 이격하여 방사상으로 장약공(6-1, 6-2, 6-3, 6-4)을 설치하는 단계와,
상기 방사상 장약공(6-1, 6-2, 6-3, 6-4)에 각 단면별로 그룹을 지어 화약과 뇌관을 결선하여 장약하고 상기 선지보재(4) 설치시 생기는 빈공(12)에도 그 빈공(12)이 속하는 단면에 화약과 뇌관을 결선하여 장약하는 단계와,
상기 복수 개의 본 터널 주면공에 천공직경 보다 작은 직경의 정밀 화약을 장약하는 단계와,
상기 방사상 장약공(6-1, 6-2, 6-3, 6-4)을 터널의 막장쪽에서부터 터널의 종방향으로 순차적으로 발파하는 단계와,
상기 본 터널 주면공을 발파하는 단계와,
상기 발파에 의해 형성된 굴착면의 부석을 제거하고 면을 정형하는 단계와,
상기 발생된 버력을 밖으로 반출하고 굴착면을 추가 지보하는 단계로 이루어지는 파일럿 터널을 이용한 미진동 급속 굴착 방법.
A step of excavating the pilot tunnel 2 from the main excavation surface 1 of the planned tunnel to excavate and tunnel the tunnel,
Inserting and grouting the pre-support material (4) by drilling a long hole in the tunnel base plate through the main tunnel excavation surface (1) of the planned tunnel in the pilot tunnel (2)
Drilling a plurality of main tunnel main surfaces (5) on the main surface excavation surface (1) of the predetermined tunnel,
6-2, 6 (6-1, 6-2, 6-3, 6-2, 6-3, 6-2, 6-3, 6-2, 6-3, 6-2, 6-4) radially in the longitudinal direction of the pilot tunnel 2, -3, 6-4)
The radial charge holes 6-1, 6-2, 6-3 and 6-4 are grouped in each cross section to connect the gunpowder and the primer to charge the radial charge holes 6, and the vents 12 formed in the installation of the pre- Connecting the explosive and primer to the cross section to which the vents 12 belong,
Charging a fine powder having a diameter smaller than a pore diameter in the plurality of main tunnel main surfaces;
Sequentially blasting the radial charging holes 6-1, 6-2, 6-3, and 6-4 from the surface side of the tunnel in the longitudinal direction of the tunnel,
Blasting the main tunnel main hole;
Removing the pits of the excavation surface formed by the blasting and shaping the surface,
And a step of taking out the generated buckling force and further supporting the excavation surface.
본 터널을 선지보하고 굴착하기 위하여 예정 본 터널의 주면 굴착면(1)에서 이격하여 파일럿 터널(2)을 배치하여 굴착하는 단계와,
상기 파일럿 터널(2)에서 상기 예정 본 터널의 주면 굴착면(1)을 지나 터널 원지반 내에 장공을 천공하여 선지보재(4)를 삽입하고 그라우팅하는 단계와,
상기 파일럿 터널(2)내에서 파일럿 터널의 원지반(9)에 본 터널 주면공(5)으로부터 방사상 장약공(6-1, 6-2, 6-3, 6-4) 선단이 방사상 장약공의 종방향 간격(13) 이상이 되도록 천공 형성하는 단계와,
상기 예정 본 터널의 주면 굴착면(1)이 형성되도록 상기 예정 본 터널의 주면 굴착면(1)에 주면을 따라 복수 개의 본 터널 주면공(5)을 천공하는 단계와,
상기 장약공(6-1, 6-2, 6-3, 6-4)에 각 단면별로 그룹을 지어 화약과 뇌관을 결선하여 장약하고 상기 선지보재(4) 설치시 생기는 빈공(12)의 장약공(6-3)에도 그 빈공(12)이 속하는 단면에 화약과 뇌관을 결선하여 장약하는 단계와,
상기 복수 개의 본 터널 주면공(5)을 모두 장약하는 단계와,
상기 장약공(6-1, 6-2, 6-3, 6-4)을 터널의 막장쪽에서부터 터널의 종방향으로 순차적으로 발파하는 단계와,
상기 복수 개의 본 터널 주면공(5)을 발파하는 단계와,
상기 발파에 의해 형성된 굴착면의 부석을 제거하고 면을 정형하는 단계와,
상기 발생된 버력을 밖으로 반출하고 굴착면을 추가 지보하는 단계로 이루어지는 파일럿 터널을 이용한 미진동 급속 굴착 방법.

Placing and drilling the pilot tunnel 2 away from the main surface excavation surface 1 of the planned tunnel to excavate and tunnel the tunnel,
Inserting and grouting the pre-support material (4) by drilling a long hole in the tunnel base plate through the main tunnel excavation surface (1) of the planned tunnel in the pilot tunnel (2)
The ends of the radial charge holes 6-1, 6-2, 6-3, and 6-4 from the tunnel main surface 5 seen from the ground plate 9 of the pilot tunnel in the pilot tunnel 2, Forming a perforation to be equal to or greater than the longitudinal spacing 13,
Drilling a plurality of main tunnel main surfaces 5 along a main surface on the main surface excavation surface 1 of the predetermined tunnel so that the main excavation surface 1 of the predetermined tunnel is formed,
(6-1, 6-2, 6-3, 6-4) are grouped by each cross section to connect the gunpowder and the primer and charge the charge of the vents (12) generated in the installation of the pre- In the hole (6-3), a charge and a primer are connected and charged to a cross section to which the void 12 belongs,
Loading all of the plurality of main tunnel main surfaces 5,
(6-1, 6-2, 6-3, 6-4) sequentially from the surface side of the tunnel to the longitudinal direction of the tunnel,
Blasting the plurality of main tunnel main surfaces (5)
Removing the pits of the excavation surface formed by the blasting and shaping the surface,
And a step of taking out the generated buckling force and further supporting the excavation surface.

KR1020180105242A 2018-09-04 2018-09-04 Vibration-free rapid excavation method using pilot tunnel in large-scale tunnel KR102211018B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020180105242A KR102211018B1 (en) 2018-09-04 2018-09-04 Vibration-free rapid excavation method using pilot tunnel in large-scale tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020180105242A KR102211018B1 (en) 2018-09-04 2018-09-04 Vibration-free rapid excavation method using pilot tunnel in large-scale tunnel

Publications (2)

Publication Number Publication Date
KR20180105100A true KR20180105100A (en) 2018-09-27
KR102211018B1 KR102211018B1 (en) 2021-02-01

Family

ID=63719316

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020180105242A KR102211018B1 (en) 2018-09-04 2018-09-04 Vibration-free rapid excavation method using pilot tunnel in large-scale tunnel

Country Status (1)

Country Link
KR (1) KR102211018B1 (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110145315A (en) * 2019-05-13 2019-08-20 中铁十六局集团第四工程有限公司 A kind of driving method weakening city shallow tunnel concussion of blasting
CN110219655A (en) * 2019-07-12 2019-09-10 华侨大学 The monitoring method of country rock accumulated damage in a kind of Tunnel Blasting driving
CN111852515A (en) * 2020-08-31 2020-10-30 中铁十六局集团有限公司 Tunnel stratum pre-reinforcement comprehensive grouting method
CN112127899A (en) * 2020-09-28 2020-12-25 中电建十一局工程有限公司 Conglomerate stratum tunnel arch ring consolidation grouting method
CN112964143A (en) * 2021-03-24 2021-06-15 山东科技大学 Three-time blasting method for hollow hole straight-hole cut
KR102273122B1 (en) * 2020-10-30 2021-07-05 강릉건설 주식회사 New Austrian Tunneling Method tunnel reinforcement method using pilot tunnel

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08270374A (en) * 1995-03-31 1996-10-15 Hazama Gumi Ltd Blasting type tunnel construction method
JP2003506605A (en) * 1999-08-06 2003-02-18 エルティーエム・コーポレイション Three-dimensional multi-stage tunnel excavation method and apparatus
KR20170061061A (en) * 2016-09-28 2017-06-02 서민규 Tunnel construction method by using pre-support and post-support, and suitable device therefor

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08270374A (en) * 1995-03-31 1996-10-15 Hazama Gumi Ltd Blasting type tunnel construction method
JP2003506605A (en) * 1999-08-06 2003-02-18 エルティーエム・コーポレイション Three-dimensional multi-stage tunnel excavation method and apparatus
KR20170061061A (en) * 2016-09-28 2017-06-02 서민규 Tunnel construction method by using pre-support and post-support, and suitable device therefor

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110145315A (en) * 2019-05-13 2019-08-20 中铁十六局集团第四工程有限公司 A kind of driving method weakening city shallow tunnel concussion of blasting
CN110219655A (en) * 2019-07-12 2019-09-10 华侨大学 The monitoring method of country rock accumulated damage in a kind of Tunnel Blasting driving
CN111852515A (en) * 2020-08-31 2020-10-30 中铁十六局集团有限公司 Tunnel stratum pre-reinforcement comprehensive grouting method
CN112127899A (en) * 2020-09-28 2020-12-25 中电建十一局工程有限公司 Conglomerate stratum tunnel arch ring consolidation grouting method
CN112127899B (en) * 2020-09-28 2022-08-23 中电建十一局工程有限公司 Method for consolidation grouting of conglomerate stratum tunnel arch ring
KR102273122B1 (en) * 2020-10-30 2021-07-05 강릉건설 주식회사 New Austrian Tunneling Method tunnel reinforcement method using pilot tunnel
CN112964143A (en) * 2021-03-24 2021-06-15 山东科技大学 Three-time blasting method for hollow hole straight-hole cut
CN112964143B (en) * 2021-03-24 2021-09-21 山东科技大学 Three-time blasting method for hollow hole straight-hole cut

Also Published As

Publication number Publication date
KR102211018B1 (en) 2021-02-01

Similar Documents

Publication Publication Date Title
KR20180105100A (en) Vibration-free rapid excavation method using pilot tunnel in large-scale tunnel
CN108661643B (en) It a kind of coal working face end adopts return channel and cuts top release shield lane method
CN108286920A (en) A kind of implementation of Tunnel Blasting and excavation
KR101247702B1 (en) Multi-Step Tunnel Constructing Method Using Pilot Tunnel
KR101827341B1 (en) Rock Excavation Method in Tunnel
AU2016305485B2 (en) A method and an apparatus for creating a void, low-density fill or combination of void and low-density fill for underground mining comprising at least one module of formwork to be positioned in an open stope of an underground mine prior to carrying out a backfilling operation.
KR101148331B1 (en) Excavation method for pre-nailed tunneling
AU2019255175B2 (en) Blasting technique
CN111442701B (en) Refined blasting construction method for narrow deep foundation pit under complex geological condition
CN112964144B (en) Soft rock railway tunnel blasting construction method in stress environment
CN108915694B (en) Construction method for tunnel lower-layer step full-section protective-layer-free extrusion blasting and road repairing and access protection
KR102131823B1 (en) Method of excavation
CN111997616A (en) Method for continuously recycling residual top-bottom column by adopting large section
CN111238329A (en) Method for performing geometric forming blasting on semi-coal rock roadway by adopting instantaneous bursting device
CN112880501B (en) Flight-limited hole drilling and blasting method for controlling tunnel blasting flyrock
CN102213574A (en) Short-term slope blasting molding method
CN102519323A (en) Pre-splitting blasting method for joint-cutting pipe
CN109322683A (en) Underground Large chamber medium-length hole controls blasting construction method
CN109405688A (en) Close on the blasting construction method in existing operation tunnel
KR101974183B1 (en) Construction methods of approaching dual tunnel
KR20190011887A (en) Method for digging huge tunnel using tnnnel boring mechine
CN106089216A (en) Rock tunnel breaks rock construction method
KR0146411B1 (en) Rock blasting method
US20200088030A1 (en) Underground shaft development method
KR101815480B1 (en) Method for excavating vertical shaft

Legal Events

Date Code Title Description
A201 Request for examination
G15R Request for early opening
E902 Notification of reason for refusal
E90F Notification of reason for final refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant