KR20130003993A - 철탑 보강구조 및 보강방법 - Google Patents
철탑 보강구조 및 보강방법 Download PDFInfo
- Publication number
- KR20130003993A KR20130003993A KR1020110065689A KR20110065689A KR20130003993A KR 20130003993 A KR20130003993 A KR 20130003993A KR 1020110065689 A KR1020110065689 A KR 1020110065689A KR 20110065689 A KR20110065689 A KR 20110065689A KR 20130003993 A KR20130003993 A KR 20130003993A
- Authority
- KR
- South Korea
- Prior art keywords
- tower
- old
- steel tower
- new
- reinforcing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/02—Structures made of specified materials
- E04H12/08—Structures made of specified materials of metal
- E04H12/10—Truss-like structures
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
- E04G23/02—Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
- E04G23/0218—Increasing or restoring the load-bearing capacity of building construction elements
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02B—BOARDS, SUBSTATIONS OR SWITCHING ARRANGEMENTS FOR THE SUPPLY OR DISTRIBUTION OF ELECTRIC POWER
- H02B1/00—Frameworks, boards, panels, desks, casings; Details of substations or switching arrangements
- H02B1/01—Frameworks
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Chemical & Material Sciences (AREA)
- Structural Engineering (AREA)
- Civil Engineering (AREA)
- Materials Engineering (AREA)
- Wood Science & Technology (AREA)
- Life Sciences & Earth Sciences (AREA)
- Power Engineering (AREA)
- Chemical Kinetics & Catalysis (AREA)
- Electrochemistry (AREA)
- Mechanical Engineering (AREA)
- Working Measures On Existing Buildindgs (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
Description
도 2 및 도 3은 본 발명의 철탑 보강구조에서 구철탑과 신철탑이 결합된 상태를 도시하는 도면,
도 4는 본 발명의 철탑 보강구조에서 필러플레이트를 통한 신철탑과 구철탑의 결합관계를 도시하는 도면,
도 5는 본 발명의 철탑 보강구조에서 보강빔과 구철탑 주주재 사이에 설치된 지압판을 도시하는 도면.
도 6은 본 발명의 철탑 보강방법을 도시하는 흐름도.
110 : 보강빔 120 : 신철탑
121 : 신철탑 주주재 130 : 교각
S10 : 보강빔설치단계 S20 : 교각설치단계
S30 : 신철탑설치단계
Claims (6)
- 구철탑의 기초부에 대각선 방향으로 교차 설치되는 철근 콘크리트 재질의 보강빔과;
상기 보강빔의 교점을 중심으로 하방에 설치되어 전체의 하중을 지면으로 전달하는 교각과;
상기 보강빔의 끝단과 상기 구철탑의 주주재를 연결하여 신철탑을 형성하는 신철탑 주주재;를 포함하는 것을 특징으로 하는 철탑 보강구조.
- 제 1항에 있어서,
상기 구철탑 주주재와 신철탑 주주재의 연결 지점에 상기 구철탑과 신철탑을 연결시키는 필러플레이트가 구비되는 것을 특징으로 하는 철탑 보강구조.
- 제 1항에 있어서,
상기 구철탑 주주재와 보강빔의 결합 부위에 지압판이 설치되는 것을 특징으로 하는 철탑 보강구조.
- 구철탑을 유지한 상태에서 상기 구철탑 기초부에 대각선 방향으로 철근 콘크리트 재질의 보강빔을 설치하는 보강빔설치단계와;
상기 보강빔의 교점을 중심으로 하방에 교각을 설치하는 교각설치단계와;
상기 보강빔을 기초로 하여 상기 구철탑 외측에 신철탑의 주주재를 설치하는 신철탑설치단계;를 구비하는 것을 특징으로 하는 철탑 보강방법.
- 제 4항에 있어서,
상기 신철탑설치단계에서 상기 구철탑 주주재와 신철탑 주주재의 연결 지점에 필러플레이트를 삽입시켜 상기 구철탑과 신철탑을 연결하는 필러플레이트삽입단계가 추가되는 것을 특징으로 하는 철탑 보강방법.
- 제 4항에 있어서,
상기 보강빔설치단계에서 상기 구철탑 주주재와 보강빔의 결합 부위에 지압판을 설치하는 지압판설치단계가 추가되는 것을 특징으로 하는 철탑 보강방법.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| KR1020110065689A KR101319784B1 (ko) | 2011-07-01 | 2011-07-01 | 철탑 보강구조 및 보강방법 |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| KR1020110065689A KR101319784B1 (ko) | 2011-07-01 | 2011-07-01 | 철탑 보강구조 및 보강방법 |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| KR20130003993A true KR20130003993A (ko) | 2013-01-09 |
| KR101319784B1 KR101319784B1 (ko) | 2013-10-18 |
Family
ID=47836032
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| KR1020110065689A Active KR101319784B1 (ko) | 2011-07-01 | 2011-07-01 | 철탑 보강구조 및 보강방법 |
Country Status (1)
| Country | Link |
|---|---|
| KR (1) | KR101319784B1 (ko) |
Cited By (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR101474948B1 (ko) * | 2014-08-22 | 2014-12-22 | 주식회사 지에스웹 | 체험 시설물의 지지기둥 시공공법 |
| CN108798057A (zh) * | 2018-06-07 | 2018-11-13 | 广东省输变电工程有限公司 | 输电塔十字加固装置 |
| CN109667277A (zh) * | 2018-12-25 | 2019-04-23 | 中国能源建设集团广东省电力设计研究院有限公司 | 悬臂式连梁电缆终端场 |
| CN114969898A (zh) * | 2022-05-05 | 2022-08-30 | 贵州电网有限责任公司 | 一种500kV输电线路铁塔覆冰条件下加固措施方案选择方法 |
| KR20240028816A (ko) * | 2022-08-25 | 2024-03-05 | 한국전력공사 | 현장 맞춤형 송전철탑 상향공법 |
| ES2981816A1 (es) * | 2023-03-10 | 2024-10-10 | Ruiz Maximo Jesus Pozo | Refuerzo estructural completo para apoyos metalicos de media tension |
Families Citing this family (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR101621944B1 (ko) | 2014-07-22 | 2016-05-17 | 주식회사 남강엔지니어링 | 인크로징 철탑 각입 셋팅장치 |
| KR20200036389A (ko) | 2018-09-28 | 2020-04-07 | 한국전력공사 | 조합형 주주재 보강기구 |
| KR102005848B1 (ko) * | 2019-01-21 | 2019-10-08 | 진종신 | 내진기능을 갖춘 배전선로의 철탑구조 |
Family Cites Families (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2004036235A (ja) * | 2002-07-03 | 2004-02-05 | Eito Kogyo Kk | 鉄塔嵩上げ工法 |
| KR100662883B1 (ko) * | 2006-08-29 | 2006-12-28 | 대한전기감리(주) | 송전용 철탑의 보강 구조 |
| JP4957894B2 (ja) * | 2007-02-27 | 2012-06-20 | 東京電力株式会社 | 送電用鉄塔の補強方法 |
-
2011
- 2011-07-01 KR KR1020110065689A patent/KR101319784B1/ko active Active
Cited By (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR101474948B1 (ko) * | 2014-08-22 | 2014-12-22 | 주식회사 지에스웹 | 체험 시설물의 지지기둥 시공공법 |
| CN108798057A (zh) * | 2018-06-07 | 2018-11-13 | 广东省输变电工程有限公司 | 输电塔十字加固装置 |
| CN109667277A (zh) * | 2018-12-25 | 2019-04-23 | 中国能源建设集团广东省电力设计研究院有限公司 | 悬臂式连梁电缆终端场 |
| CN114969898A (zh) * | 2022-05-05 | 2022-08-30 | 贵州电网有限责任公司 | 一种500kV输电线路铁塔覆冰条件下加固措施方案选择方法 |
| KR20240028816A (ko) * | 2022-08-25 | 2024-03-05 | 한국전력공사 | 현장 맞춤형 송전철탑 상향공법 |
| ES2981816A1 (es) * | 2023-03-10 | 2024-10-10 | Ruiz Maximo Jesus Pozo | Refuerzo estructural completo para apoyos metalicos de media tension |
Also Published As
| Publication number | Publication date |
|---|---|
| KR101319784B1 (ko) | 2013-10-18 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| KR101319784B1 (ko) | 철탑 보강구조 및 보강방법 | |
| US20110061321A1 (en) | Fatigue reistant foundation system | |
| CN203939288U (zh) | 防风网结构 | |
| CN201546227U (zh) | 用于支撑基坑围护桩墙和地下室结构外墙的钢支撑梁 | |
| CN103821676A (zh) | 风力发电机组的塔架基础 | |
| CN103912000A (zh) | 可重复使用的复合材料土钉墙支护面板及其施工方法 | |
| JP6834226B2 (ja) | 杭基礎および鉄塔建替工法 | |
| JP6027389B2 (ja) | 既設構造物の躯体を利用して構築された基礎構造 | |
| CN105587097A (zh) | 一种可调平地面架空结构 | |
| CN201288328Y (zh) | 梁板一体预制拼装式塔机固定基础 | |
| CN208633136U (zh) | 新型装配式螺旋锚复合基础 | |
| CN105421477A (zh) | 一种塔吊基础的施工方法 | |
| CN105696617A (zh) | 一种输电塔的斜置角锥支架装配式基础及其施工方法 | |
| CN218060773U (zh) | 一种钢结构柱脚抗剪键安装结构 | |
| KR100758546B1 (ko) | 고압전기 철탑 기초 전도방지 구조 | |
| CN205636751U (zh) | 面向多层地下建筑的装配式定型结构体系 | |
| CN206986917U (zh) | 锚栓风机基础 | |
| CN204112827U (zh) | 一种通讯塔 | |
| CN209779668U (zh) | 一种定日镜立柱和基础二合一桩基 | |
| CN110172989B (zh) | 高电压榫卯结构装配式主变基础 | |
| CN220301879U (zh) | 一种装配式箱变平台 | |
| CN202416344U (zh) | 柱钉支撑结构 | |
| CN208347285U (zh) | 一种建筑装修用高空施工支撑结构 | |
| CN201460373U (zh) | 拉线杆塔基础 | |
| CN208996550U (zh) | 地面钢制调压塔 |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A201 | Request for examination | ||
| PA0109 | Patent application |
St.27 status event code: A-0-1-A10-A12-nap-PA0109 |
|
| PA0201 | Request for examination |
St.27 status event code: A-1-2-D10-D11-exm-PA0201 |
|
| D13-X000 | Search requested |
St.27 status event code: A-1-2-D10-D13-srh-X000 |
|
| D14-X000 | Search report completed |
St.27 status event code: A-1-2-D10-D14-srh-X000 |
|
| E902 | Notification of reason for refusal | ||
| PE0902 | Notice of grounds for rejection |
St.27 status event code: A-1-2-D10-D21-exm-PE0902 |
|
| PG1501 | Laying open of application |
St.27 status event code: A-1-1-Q10-Q12-nap-PG1501 |
|
| P11-X000 | Amendment of application requested |
St.27 status event code: A-2-2-P10-P11-nap-X000 |
|
| P13-X000 | Application amended |
St.27 status event code: A-2-2-P10-P13-nap-X000 |
|
| E701 | Decision to grant or registration of patent right | ||
| PE0701 | Decision of registration |
St.27 status event code: A-1-2-D10-D22-exm-PE0701 |
|
| GRNT | Written decision to grant | ||
| PR0701 | Registration of establishment |
St.27 status event code: A-2-4-F10-F11-exm-PR0701 |
|
| PR1002 | Payment of registration fee |
St.27 status event code: A-2-2-U10-U11-oth-PR1002 Fee payment year number: 1 |
|
| PG1601 | Publication of registration |
St.27 status event code: A-4-4-Q10-Q13-nap-PG1601 |
|
| PN2301 | Change of applicant |
St.27 status event code: A-5-5-R10-R13-asn-PN2301 St.27 status event code: A-5-5-R10-R11-asn-PN2301 |
|
| R18-X000 | Changes to party contact information recorded |
St.27 status event code: A-5-5-R10-R18-oth-X000 |
|
| FPAY | Annual fee payment |
Payment date: 20160726 Year of fee payment: 4 |
|
| PR1001 | Payment of annual fee |
St.27 status event code: A-4-4-U10-U11-oth-PR1001 Fee payment year number: 4 |
|
| P22-X000 | Classification modified |
St.27 status event code: A-4-4-P10-P22-nap-X000 |
|
| FPAY | Annual fee payment |
Payment date: 20170810 Year of fee payment: 5 |
|
| PR1001 | Payment of annual fee |
St.27 status event code: A-4-4-U10-U11-oth-PR1001 Fee payment year number: 5 |
|
| P22-X000 | Classification modified |
St.27 status event code: A-4-4-P10-P22-nap-X000 |
|
| FPAY | Annual fee payment |
Payment date: 20180726 Year of fee payment: 6 |
|
| PR1001 | Payment of annual fee |
St.27 status event code: A-4-4-U10-U11-oth-PR1001 Fee payment year number: 6 |
|
| FPAY | Annual fee payment |
Payment date: 20190723 Year of fee payment: 7 |
|
| PR1001 | Payment of annual fee |
St.27 status event code: A-4-4-U10-U11-oth-PR1001 Fee payment year number: 7 |
|
| R18-X000 | Changes to party contact information recorded |
St.27 status event code: A-5-5-R10-R18-oth-X000 |
|
| PR1001 | Payment of annual fee |
St.27 status event code: A-4-4-U10-U11-oth-PR1001 Fee payment year number: 8 |
|
| R18-X000 | Changes to party contact information recorded |
St.27 status event code: A-5-5-R10-R18-oth-X000 |
|
| PR1001 | Payment of annual fee |
St.27 status event code: A-4-4-U10-U11-oth-PR1001 Fee payment year number: 9 |
|
| R18-X000 | Changes to party contact information recorded |
St.27 status event code: A-5-5-R10-R18-oth-X000 |
|
| PN2301 | Change of applicant |
St.27 status event code: A-5-5-R10-R13-asn-PN2301 St.27 status event code: A-5-5-R10-R11-asn-PN2301 |
|
| PR1001 | Payment of annual fee |
St.27 status event code: A-4-4-U10-U11-oth-PR1001 Fee payment year number: 10 |
|
| PR1001 | Payment of annual fee |
St.27 status event code: A-4-4-U10-U11-oth-PR1001 Fee payment year number: 11 |
|
| PR1001 | Payment of annual fee |
St.27 status event code: A-4-4-U10-U11-oth-PR1001 Fee payment year number: 12 |
|
| P14-X000 | Amendment of ip right document requested |
St.27 status event code: A-5-5-P10-P14-nap-X000 |
|
| PR1001 | Payment of annual fee |
St.27 status event code: A-4-4-U10-U11-oth-PR1001 Fee payment year number: 13 |
|
| U11 | Full renewal or maintenance fee paid |
Free format text: ST27 STATUS EVENT CODE: A-4-4-U10-U11-OTH-PR1001 (AS PROVIDED BY THE NATIONAL OFFICE) Year of fee payment: 13 |