KR20120097261A KR1020110016743A KR20110016743A KR20120097261A KR 20120097261 A KR20120097261 A KR 20120097261A KR 1020110016743 A KR1020110016743 A KR 1020110016743A KR 20110016743 A KR20110016743 A KR 20110016743A KR 20120097261 A KR20120097261 A KR 20120097261A
Authority
KR
South Korea
Prior art keywords
partition wall
upper plate
shear
filler
seismic load
Prior art date
Application number
KR1020110016743A
Other languages
Korean (ko)
Other versions
KR101187179B1 (en
Inventor
이승재
Original Assignee
한국기술교육대학교 산학협력단
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 한국기술교육대학교 산학협력단 filed Critical 한국기술교육대학교 산학협력단
Priority to KR1020110016743A priority Critical patent/KR101187179B1/en
Publication of KR20120097261A publication Critical patent/KR20120097261A/en
Application granted granted Critical
Publication of KR101187179B1 publication Critical patent/KR101187179B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0218Increasing or restoring the load-bearing capacity of building construction elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/92Protection against other undesired influences or dangers
    • E04B1/98Protection against other undesired influences or dangers against vibrations or shocks; against mechanical destruction, e.g. by air-raids
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/74Removable non-load-bearing partitions; Partitions with a free upper edge
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/01Reinforcing elements of metal, e.g. with non-structural coatings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H9/00Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate
    • E04H9/02Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate withstanding earthquake or sinking of ground
    • E04H9/021Bearing, supporting or connecting constructions specially adapted for such buildings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H9/00Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate
    • E04H9/02Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate withstanding earthquake or sinking of ground
    • E04H9/027Preventive constructional measures against earthquake damage in existing buildings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Business, Economics & Management (AREA)
  • Emergency Management (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Mechanical Engineering (AREA)
  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

PURPOSE: A construction method of a partition wall with an earthquake load absorbing function is provided to improve resistance to an earthquake load by installing a partition wall between a column and a beam when an existing structure is reinforced. CONSTITUTION: A construction method of a partition wall with an earthquake load absorbing function is as follows. An upper plate is fixed to the bottom surface of a beam where a partition wall is to be installed. Lower channels(13) are arranged on the bottom of the upper plate and are supported by timbering. The space between the upper plate and the lower channel is filled with filler(15). After the filler is hardened, the timbering is removed. Buffer plates(70) are installed on the facing surfaces of columns. Reinforcing bars are arranged in the space formed by the buffer plates and the lower channels in a latticed shape, and wall concrete is placed.

Description

지진하중 흡수 기능을 갖는 칸막이 벽체의 시공방법{Method for constructing partition wall having seismic control}Method for constructing partition wall having seismic control

본 발명은 기둥과 보가 강접된 라멘 골조 건물에 있어 기둥과 보 사이의 공간에 설치되어 단순히 실과 실을 분리하는 칸막이 벽체를 지진하중을 흡수, 저감시키는 기능을 갖도록 시공하는 방법에 관한 것이다.The present invention relates to a method of constructing a partition wall having a function of absorbing and reducing seismic loads in a ramen framed building in which a column and a beam are in close contact with each other and installed in a space between the column and the beam.

최근 국내외에서 발생한 일련의 큰 지진으로 인하여 지진의 피해에 대한 경각심과 내진설계의 필요성에 대한 인식이 확산되고 있다. 특히 박물관, 원자력발전소와 같은 중요한 구조물이나 고층빌딩, 경기장 및 교량과 같은 대형 구조물의 지진피해는 막대한 인명 및 재산 피해를 동반하므로 충분한 내진성능을 확보할 필요가 있다. 또한 주거용 건물의 리모델링이 광범위하게 추진됨에 따라 내진설계기준이 적용되기 이전에 시공된 건물의 내진보강방법에 대한 관심이 점차 증가하고 있다.Recently, due to a series of large earthquakes both at home and abroad, awareness of earthquake damage and the need for seismic design are spreading. In particular, earthquake damage of important structures such as museums and nuclear power plants or large structures such as high-rise buildings, stadiums, and bridges is accompanied by enormous human and property damages, so it is necessary to secure sufficient seismic performance. In addition, as the remodeling of residential buildings is widely pursued, interest in the seismic reinforcement method of buildings constructed before the seismic design standards are applied is gradually increasing.

리모델링시 건물은 안전성과 경제성에 입각하여 작용하는 하중의 특성에 따라 효과적인 대응을 해야 한다. 특히 국내 내진 기준은 지속으로 강화되고 있는 추세이며 1990년대 이전에 건축된 대다수의 건물이 강화된 현재의 내진 기준을 만족하지 못하고 있는 실정이다. 따라서 지진에 대한 내력 및 연성 확보를 위해 기존 구조물의 황력저항요소 설계에 세심한 주의가 필요하다.When remodeling, the building should respond effectively to the characteristics of the load acting on the basis of safety and economy. In particular, domestic earthquake resistance standards are continuously being strengthened, and most buildings built before the 1990s do not meet the current earthquake resistance standards. Therefore, it is necessary to pay close attention to the design of the resistive element of the existing structure to secure earthquake resistance and ductility.

전통적으로 건물을 지진력에 저항할 수 있도록 튼튼하게 설계하는 내진설계와 더불어 최근에는 건물을 지반에서 분리하여 건물의 진동 주기를 지진의 주요 주기(Predominant period)에서 멀어지게 함으로써 건물이 지진을 피해가도록 하는 면진(Seismic Isolation) 및 지진에 의한 입력에너지를 각종 제진장치를 이용하여 효율적으로 소산함으로써 건물의 피해를 최소화하는 제진(Seismic Control) 등 다양한 설계를 동원하여 지진에 의한 인명 및 재산 피해를 최소화할 수 있도록 강구하고 있다. In addition to the seismic design, which has traditionally designed the building to resist seismic forces, the building has recently been separated from the ground to keep the building's vibration period away from the predominant period. Seismic Isolation and Seismic Control minimize the damage of buildings by efficiently dissipating the input energy due to earthquakes using various vibration suppression devices. I'm trying to be.

본 발명은 이러한 제반 사정을 감안하여 창작된 것으로 아래와 같은 목적을 가진다. The present invention has been made in view of the above circumstances and has the following object.

본 발명은 단순히 실을 분리하는 기능을 넘어서 지진하중 흡수 기능을 가지도록 칸막이 벽체를 구성하고 이를 시공하는 방법을 제공하는 목적으로 한다. It is an object of the present invention to provide a method of constructing a partition wall and constructing it so as to have a seismic load absorbing function beyond a function of simply separating the yarns.

본 발명의 적절한 실시 형태에 따르면, 칸막이 벽체가 시공될 위치의 보의 하면과 슬래브의 상면에 각각 다수 개의 전단연결재가 설치된 상부판을 고정하는 단계; 상단 부분과 하단 부분을 갖고 상단 부분에는 일정 길이에 걸쳐 비닐관이 씌워지고 비닐관의 사이에 완충재가 설치된 전단연결부재를 상단 부분이 상부판을 향하도록 일정 간격으로 하부채널을 관통하도록 설치하고 하부채널을 전단연결재가 내부에 수용되도록 상부판의 하부와 상부에 각각 배치한 다음 전단변형부재의 상단을 상부판에 결합하는 단계; 하부채널 사이에 동바리를 설치하는 단계; 상부판과 하부채널으로 둘러싸인 공간에 충전재를 충전하는 단계; 충전재가 경화된 후 동바리를 제거하고 양쪽의 기둥이 마주보는 기둥 면에 각각 슬래브와 보 사이의 전체 높이에 걸쳐 완충판을 설치하는 단계; 및 완충판과 하부채널에 의해 둘러싸인 공간에 보강철근을 격자형태로 배근하고 거푸집을 짜댄 후 벽체 콘크리트를 타설하는 단계를 포함하는 것을 특징으로 하는 지진하중 흡수 기능을 갖는 칸막이 벽체의 시공방법이 제공된다.According to a preferred embodiment of the present invention, the method further comprises: fixing a top plate on which a plurality of shear connecting members are respectively installed on the bottom surface of the beam and the top surface of the slab at the position where the partition wall is to be constructed; The upper part and the lower part, and the upper part is covered with a vinyl tube over a certain length, and the shear connection member with a cushioning material installed between the vinyl tube is installed so as to penetrate the lower channel at regular intervals so that the upper part faces the upper plate. Arranging the lower and upper portions of the upper plate so that the shear connector is accommodated therein, and then coupling the upper end of the shear deformation member to the upper plate; Installing a grouping between the lower channels; Filling a filler into a space surrounded by an upper plate and a lower channel; Removing the copper bar after the filler is cured, and installing a buffer plate over the entire height between the slab and the beam on each side of the pillar facing each other; And reinforcing the reinforcing bars in a lattice form in the space surrounded by the buffer plate and the lower channel, squeezing the formwork, and placing the wall concrete, thereby providing a method of constructing a partition wall having a seismic load absorbing function.

상기 전단변형부재는 철근이 될 수 있고, 상기 충전재는 모르타르, 콘크리트 또는 섬유보강 콘크리트 중에서 어느 하나가 될 수 있으며, 상기 완충재는 고무 또는 고무 발포체가 될 수 있고, 완충판은 고무 또는 고무 발포체로 구성될 수 있다.The shear deformation member may be a reinforcing bar, the filler may be any one of mortar, concrete or fiber reinforced concrete, the cushioning material may be rubber or rubber foam, and the buffer plate may be made of rubber or rubber foam. Can be.

본 발명에 따르면 저비용으로 신축 또는 기존 건물의 보강시에 기둥과 보 사이의 공간에 설치되어 지진하중에 대한 건물의 저항능력을 효율적으로 향상시킬 수 있다.According to the present invention can be installed in the space between the column and the beam at the time of new construction or reinforcement of existing buildings at low cost can effectively improve the building's resistance to earthquake load.

본 명세서에서 첨부되는 다음의 도면들은 본 발명의 바람직한 실시 예를 예시하는 것이며, 발명의 상세한 설명과 함께 본 발명의 기술사상을 더욱 이해시키는 역할을 하는 것이므로, 본 발명은 첨부한 도면에 기재된 사항에만 한정되어서 해석되어서는 아니 된다.
도 1은 본 발명에 따른 라멘 골조에 설치되는 지진하중 흡수장치를 나타낸 분해사시도이고 도 2는 종단면도이며 도 3은 횡단면도이다.
도 4 내지 도 8은 본 발명에 따른 칸막이 벽체를 시공하는 방법을 순서대로 나타낸 정면도이다.
도 9는 지진하중 작용시 본 발명에 따른 지진하중 흡수장치가 지진하중을 흡수하는 원리를 보여주는 단면도이다.
The following drawings, which are attached in this specification, illustrate the preferred embodiments of the present invention, and together with the detailed description thereof, serve to further understand the technical spirit of the present invention. It should not be construed as limited.
1 is an exploded perspective view showing an earthquake load absorbing device installed in a ramen frame according to the present invention, Figure 2 is a longitudinal cross-sectional view and Figure 3 is a cross-sectional view.
4 to 8 are front views sequentially showing a method of constructing a partition wall according to the present invention.
9 is a cross-sectional view showing the principle that the seismic load absorber according to the present invention absorbs the seismic load when the seismic load is applied.

아래에서 본 발명은 첨부된 도면에 제시된 실시 예를 참조하여 상세하게 설명이 되지만 제시된 실시 예는 본 발명의 명확한 이해를 위한 예시적인 것으로 본 발명은 이에 제한되지 않는다. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will be described in detail below with reference to the embodiments shown in the accompanying drawings, but the present invention is not limited thereto.

본 발명에 따른 지진하중 흡수 기능을 갖는 칸막이 벽체의 시공방법을 설명하기에 앞서 먼저 칸막이 벽체에 지진하중 흡수 기능을 부여하는 지진하중 흡수장치에 대해 설명한다.Prior to describing the construction method of the partition wall having the seismic load absorbing function according to the present invention, a seismic load absorbing device for providing the seismic load absorbing function to the partition wall will be described.

도 1은 본 발명에 따른 라멘 골조에 설치되는 지진하중 흡수장치를 나타낸 분해사시도이고 도 2는 종단면도이며 도 3은 횡단면도이다.1 is an exploded perspective view showing an earthquake load absorbing device installed in a ramen frame according to the present invention, Figure 2 is a longitudinal cross-sectional view and Figure 3 is a cross-sectional view.

도 1 내지 도 3을 참조하면, 본 발명에 따른 지진하중 흡수장치는 상부판(11), 상부판(11)의 하면에 결합된 다수 개의 전단연결재(12), 전단연결재(12)를 내부에 수용하도록 상부판(11)의 하부에 배치된 하부채널(13), 한쪽 끝이 상부판(11)에 결합되고 다른 쪽 끝이 하부채널(13)을 관통하여 일정 길이가 하부채널(13)의 하부에 돌출되게 설치된 다수 개의 전단변형부재(14), 상부판(11)과 하부채널(13)에 의해 둘러싸인 공간에 채워지는 충전재(15), 충전재(15)에 매립되는 전단변형부재(14)가 충전재(15)와 부착되지 않도록 전단변형부재(14)를 감싸는 비닐관(16) 및 전단변형부재(14)와 비닐관(16) 사이에 채워지는 완충재(17)를 포함한다. 1 to 3, the seismic load absorbing apparatus according to the present invention includes a plurality of shear connecting members 12 and shear connecting members 12 coupled to an upper plate 11 and a lower surface of the upper plate 11. A lower channel 13 disposed below the upper plate 11 so as to receive, one end is coupled to the upper plate 11 and the other end penetrates the lower channel 13 so that a predetermined length of the lower channel 13 A plurality of shear deformation members 14 protruding from the lower portion, a filler 15 filled in the space surrounded by the upper plate 11 and the lower channel 13, a shear deformation member 14 embedded in the filler 15 It includes a vinyl tube 16 surrounding the shear deformation member 14 and the buffer 17 is filled between the shear deformation member 14 and the vinyl tube 16 so that the filler 15 is not attached to the filler 15.

상부판(11)은 일정한 두께와 폭을 가지는 판재 형상을 가지는 것으로 다양한 재료로 구성될 수 있으나 바람직하게는 철근과의 결합방법이 다양한 강재로 구성하는 것이 유리하다. 상부판(11)에는 길이방향을 따라 일정한 간격을 두고 전단변형부재(14)를 조립하기 위한 다수 개의 전단변형부재 조립공(111)이 형성될 수 있다. 상부판(11)은 지진하중 작용시 보와 일체로 거동할 수 있도록 이 기술분야에서 주지된 다양한 방법으로 보의 하면에 고정될 수 있고 하나의 예로서 앵커볼트에 의해 보의 하면과 슬래브 상면에 고정될 수 있다. The upper plate 11 may have a plate shape having a predetermined thickness and width, but may be formed of various materials. Preferably, the upper plate 11 may be formed of various steel materials. The upper plate 11 may be provided with a plurality of shear deformation member assembly holes 111 for assembling the shear deformation member 14 at regular intervals along the longitudinal direction. The upper plate 11 can be fixed to the lower surface of the beam by various methods well known in the art so that the upper plate 11 can be integrated with the beam when the earthquake load is applied. Can be fixed.

상부판(11)의 하면에는 상부판(11)에 수직하게 다수 개의 전단연결재(12)가 고정된다. 전단연결재(12)는 상부판(11)과 하부채널(13) 사이의 공간에 채워지는 충전재(15)와 상부판(11)이 일체로 거동할 수 있도록 이들 사이의 합성효과를 높이기 위한 것으로 스터드 볼트를 포함하여 이 기술분야에서 공지된 임의의 전단연결재가 사용될 수 있다. 전단연결재(12)는 상부판(11)에 형성된 전단변형부재 조립공(111)과 상부판(11)을 보에 고정하기 위한 앵커볼트와 간섭되지 않은 위치에 임의의 패턴으로 배치될 수 있다. A plurality of shear connecting members 12 are fixed to the lower surface of the upper plate 11 perpendicular to the upper plate 11. The shear connector 12 is to enhance the synthetic effect therebetween so that the filler 15 and the upper plate 11, which are filled in the space between the upper plate 11 and the lower channel 13, can be integrated. Any shear connector known in the art, including bolts, can be used. Shear connector 12 may be arranged in any pattern at a position that does not interfere with the shear deformation member assembly hole 111 formed in the upper plate 11 and the anchor bolt for fixing the upper plate 11 to the beam.

상부판(11)의 하부에는 전단연결재(12)를 내부에 수용하도록 하부채널(13)이 설치된다. 하부채널(13)은 충전재(15)를 채우고 경화될 때까지 보호하는 일종의 거푸집으로써 이 분야에서 공지된 임의의 소재로 제작될 수 있다. 이 실시 예에서 하부채널(13)은 'U'자 형상의 단면을 가지는 것으로 예시되었으나 형성될 충전재(15)의 단면 형상에 대응하여 다양한 단면 형상으로 변경될 수 있다. 하부채널(13)에는 일정한 간격을 두고 전단변형부재(14)가 관통할 수 있는 전단변형부재 설치공(121)이 천공된다. 하부채널(13)은 상부판(11)과 결합되지 않고 분리되어 지진하중 작용시 전단변형부재(14)가 전단변형하면서 지진하중을 흡수할 수 있도록 유도한다. The lower channel 13 is installed in the lower portion of the upper plate 11 to accommodate the shear connector 12 therein. The lower channel 13 can be made of any material known in the art as a form of formwork that fills the filler 15 and protects it until hardened. In this embodiment, the lower channel 13 is illustrated as having a 'U'-shaped cross section, but may be changed into various cross-sectional shapes corresponding to the cross-sectional shape of the filler 15 to be formed. The lower channel 13 is drilled with a shear deformation member installation hole 121 through which the shear deformation member 14 can pass at regular intervals. The lower channel 13 is separated from the upper plate 11 without being combined to induce the shear deformation member 14 to absorb the seismic load while shearing the shear member.

전단변형부재(14)는 한쪽 끝이 상부판(11)에 결합되고 다른 쪽 끝이 하부채널(13)을 관통하여 일정 길이가 하부채널(13)의 하부에 돌출되게 설치된다. 전단변형부재(14)는 지진하중 작용시 전단변형하면서 지진하중을 흡수하게 된다. 즉, 이 분야에서 주지된 강재이력댐퍼과 유사하게 그 재료 자체가 가지고 있는 전단변형특성을 이용하여 지진하중을 흡수하게 된다. 이러한 이유에서 전단변형부재(14)로는 그 하중-변형 특성이 주지된 이형철근으로 구성하는 것이 바람직하다. 그러나 본 발명이 전단변형부재(14)로 이형철근을 사용하는 것에 한정되지는 않으며 하중-변형 특성이 해석 및 실험을 통해 명확히 파악될 수 있다면 전단변형부재(14)의 재료에는 제한이 없다. Shear deformation member 14 is installed so that one end is coupled to the upper plate 11 and the other end penetrates the lower channel 13 so that a predetermined length protrudes below the lower channel 13. The shear deformation member 14 absorbs the earthquake load while shearing the earthquake load during the action. That is, similar to the steel history damper known in this field, the seismic load is absorbed by using the shear deformation characteristic of the material itself. For this reason, the shear deformation member 14 is preferably composed of a deformed rebar whose load-strain characteristics are well known. However, the present invention is not limited to the use of the deformed steel bar as the shear deformation member 14, and the material of the shear deformation member 14 is not limited as long as the load-strain characteristics can be clearly understood through analysis and experiment.

하부채널(13)의 아래쪽으로 돌출된 전단변형부재(14)의 하단부는 벽체 속에 매립되게 된다. 전단변형부재(14)의 상단은 상부판(11)에 결합되는데, 간단한 방법으로는 상부판(11)에 전단변형부재 조립공(111)을 천공하고 전단변형부재(14)의 상단에 나사산을 가공하여 전단변형부재 조립공(111)에 나사결합하고 너트(112)를 체결하여 고정하는 방법이 사용될 수 있다. The lower end of the shear deformation member 14 protruding downward of the lower channel 13 is embedded in the wall. The upper end of the shear deformation member 14 is coupled to the top plate 11, in a simple manner, the shear deformation member assembly hole 111 is drilled on the upper plate 11 and the thread is processed on the upper end of the shear deformation member 14. By screwing the shear deformation member assembly hole 111 and fastening by fastening the nut 112 can be used.

상부판(11)과 하부채널(13)에 의해 둘러싸인 공간에는 충전재(15)가 채워진다. 충전재(15)는 전단연결재(12)를 통해 상부판(11)과 일체로 합성되고 전단변형부재(14)를 감싸 구속한다. 충전재(15)로는 모르타르 또는 주 구조부재인 보와 기둥의 강도보다 저강도의 콘크리트가 사용될 수 있다. 충전재(15)의 강도가 주 구조부재의 강도보다 크게 되면 지진하중 작용시 주 구조부재에 하중이 집중되어 본 발명에 따른 지진하중 흡수장치가 작동할 수 없다. The filler 15 is filled in the space surrounded by the upper plate 11 and the lower channel 13. The filler material 15 is synthesized integrally with the upper plate 11 through the shear connector 12 and is wrapped around the shear deformation member 14 to be restrained. As the filler material 15, concrete having a lower strength than that of the mortar or the beams and columns that are the main structural members may be used. If the strength of the filler material 15 is greater than the strength of the main structural member, the load is concentrated on the main structural member during the earthquake load, so that the seismic load absorber according to the present invention cannot operate.

충전재(15)에 매립되는 전단변형부재(14)가 충전재(15)와 부착되지 않도록 전단변형부재(14)를 비닐관(16)으로 감싸고 전단변형부재(14)와 비닐관(16) 사이에는 완충재(17)를 설치한다. 완충재(17)는 지진하중 작용시 충전재(15)를 통해 직접 전단변형부재(14)로 응력이 전달되지 않도록 하기 위한 것으로 고무 또는 고무 발포체 등 탄성변형능력을 가지는 이 분야에서 공지된 임의의 소재가 사용될 수 있다.The shear deformation member 14 is enclosed with the vinyl tube 16 so that the shear deformation member 14 embedded in the filler 15 is not attached to the filler 15, and a cushioning material (14) is provided between the shear deformation member 14 and the vinyl tube 16. 17) Install. The cushioning material 17 is for preventing stress from being directly transmitted to the shear deformation member 14 through the filler 15 when the earthquake load is applied, and any material known in the art having elastic deformation capacity such as rubber or rubber foam may be used. Can be used.

아래에서는 이상과 같이 구성된 지진하중 흡수장치를 이용하여 칸막이 벽체를 시공하는 방법을 설명한다. The following describes a method of constructing a partition wall using the seismic load absorber configured as described above.

도 4 내지 도 8은 본 발명에 따른 칸막이 벽체를 시공하는 방법을 순서대로 나타낸 정면도이다.4 to 8 are front views sequentially showing a method of constructing a partition wall according to the present invention.

골조 시공이 완료된 후 또는 기존 건물에 칸막이 벽체에 의해 지진하중 저항시스템을 부가하는 경우 기존의 조적, 경량 콘크리트조 칸막이 벽체를 제거한 후 이웃하는 2개의 기둥(20,20) 사이의 슬래브(40) 상면과 보(30)의 하면에 각각 위에서 설명한 지진하중 흡수장치(10)를 설치한다. 슬래브 상면과 보의 하면에 지진하중 흡수장치를 설치하는 방법은 서로 동일하므로 아래에서는 주로 보(30)의 하면에 지진하중 흡수장치(10)를 설치하는 방법을 예로 들어 설명한다. When the seismic load resistance system is added by the partition wall to the existing building after the construction of the frame is completed, the upper surface of the slab 40 between two adjacent columns 20 and 20 after removing the existing masonry and lightweight concrete partition wall. The seismic load absorber 10 described above is installed on the lower surface of the beam 30, respectively. Since the method of installing the seismic load absorbing device on the upper surface of the slab and the lower surface of the beam is the same, the following description will mainly be given by the method of installing the seismic load absorbing device 10 on the lower surface of the beam 30 as an example.

먼저, 도 4에서와 같이 칸막이 벽체가 시공될 위치의 보(30)의 하면에 상부판(11)을 고정한다. 상부판(11)은 지진하중이 작용할 때 보(30)와 일체로 거동할 수 있도록 보(30)에 견고하게 고정시킬 수 있는 이 분야에서 주지된 다양한 방법으로 고정될 수 있다. 하나의 예로서 보의 하면에 앵커홀을 천공하고 앵커볼트를 삽입한 다음 무수축 모르타르를 앵커홀에 충전하여 앵커볼트를 고정하고 상부판(11)에 앵커볼트 삽입공을 천공한 다음 앵커볼트를 앵커볼트 삽입공로 관통시키고 너트를 체결하는 방법으로 고정될 수 있다. 전단연결재(12)는 상부판(11)이 고정된 후 현장에서 용접하여 설치할 수도 있으나 고정하기 전에 미리 설치하는 것이 바람직하다. First, as shown in FIG. 4, the upper plate 11 is fixed to the lower surface of the beam 30 at the position where the partition wall is to be constructed. Top plate 11 may be fixed in a variety of ways known in the art that can be firmly fixed to the beam 30 so that it can be integrated with the beam 30 when the earthquake load is applied. As an example, drill the anchor hole on the lower surface of the beam and insert the anchor bolt, and then fill the anchor hole with the non-shrink mortar to fix the anchor bolt, and drill the anchor bolt insertion hole in the upper plate 11, and then anchor bolt. It can be fixed by passing through the anchor bolt insertion hole and fastening the nut. Shear connector 12 may be installed in the field after the top plate 11 is fixed, but is preferably installed in advance before fixing.

다음으로, 도 5에서와 같이 하부채널(13)을 상부판(11)의 하부에 배치하고 동바리(60)로 지지한다. 동바리(60)을 설치하기 전에 슬래브(40)의 상면에 설치되는 상부판(11)의 상부에도 하부채널(13)을 설치해야 함은 물론이다. 이때, 하부채널(13)을 관통하여 일정 간격으로 전단변형부재(14)가 설치되어 있고 동바리(60)에 하부채널(13)을 지지하기 전에 전단변형부재(14)의 일단을 상부판(11)의 하면에 결합한다. 전단변형부재(14)를 상부판(11)에 고정하는 방법은 상부판(11)에 미리 천공된 전단변형부재 조립공(111)에 전단변형부재(14)의 상단을 나사결합하는 방법으로 고정될 수 있다. 충전재(15)와 전단변형부재(14)가 부착되지 않도록 하는 비닐관(16)이 설치되어 있고, 전단변형부재(14)와 비닐관(16) 사이에 완충재(17)가 미리 설치되어 있다. Next, as shown in FIG. 5, the lower channel 13 is disposed below the upper plate 11 and supported by the club 60. Before installing the copper bar 60, the lower channel 13 must also be installed on the upper part of the upper plate 11 installed on the upper surface of the slab 40, of course. At this time, the shear deformation member 14 is installed at regular intervals through the lower channel 13, and one end of the shear deformation member 14 is disposed on the top plate 11 before the lower channel 13 is supported on the club 60. ) To the bottom surface. The method of fixing the shear deformation member 14 to the upper plate 11 may be fixed by screwing the upper end of the shear deformation member 14 to the shear deformation member assembly hole 111 previously drilled into the upper plate 11. Can be. The vinyl tube 16 which prevents the filler 15 and the shear deformation member 14 from adhering is provided, and the shock absorbing material 17 is provided in advance between the shear deformation member 14 and the vinyl pipe 16.

다음으로, 도 6에서와 같이 상부판(11)과 하부채널(13) 사이의 공간에 충전재(15)를 충전한다. 충전재(15)는 강관에 콘크리트를 충전하는 것과 같이 이 분야에서 공지된 임의의 방법으로 상부판(11)과 하부채널(13) 사이의 공간에 밀실하게 충전될 수 있다. Next, as shown in FIG. 6, the filler 15 is filled in a space between the upper plate 11 and the lower channel 13. The filler material 15 may be tightly filled in the space between the upper plate 11 and the lower channel 13 by any method known in the art, such as filling concrete in the steel pipe.

다음으로, 도 7에서와 같이 충전재(15)가 충분히 경화된 후 동바리(60)를 제거하고 양쪽의 기둥(20)이 마주보는 기둥 면에 각각 슬래브(40)와 보(30) 사이의 전체 높이에 걸쳐 완충판(70)을 설치한다. 따라서 양쪽의 기둥(20)과 지진하중 흡수장치(10)의 양쪽 끝단 사이에는 각각 완충판(70)이 게재된다. 완충판(70)은 시공될 칸막이 벽체의 두께에 대응되는 폭을 가지고 두께는 지진하중 흡수장치(10)의 수평변위량에 의해 결정될 수 있다. 이 완충판(70)은 지진하중이 작용할 경우 기둥(20)과 지진하중 흡수장치(10)가 직접 부딪히는 것을 방지하는 완충기능과 함께 지진하중 흡수장치(10)의 수평변위를 흡수할 수 있는 재료가 사용된다. 이러한 기능을 수행하는 이 분야에서 공지된 다양한 재료가 사용될 수 있으며 예를 들어 고무 또는 고무 발포체가 사용될 수 있다. Next, after the filling material 15 is sufficiently cured as shown in FIG. 7, the copper strip 60 is removed, and the total height between the slab 40 and the beam 30 is respectively present on the pillar faces facing both pillars 20. The buffer plate 70 is installed. Accordingly, the buffer plate 70 is placed between both pillars 20 and both ends of the seismic load absorber 10. The buffer plate 70 has a width corresponding to the thickness of the partition wall to be constructed and the thickness may be determined by the horizontal displacement of the earthquake load absorbing device 10. The buffer plate 70 is a material capable of absorbing the horizontal displacement of the earthquake load absorber 10 together with a shock absorbing function that prevents the pillar 20 and the earthquake load absorber 10 from directly colliding when the earthquake load is applied. Used. Various materials known in the art which perform this function can be used, for example rubber or rubber foam can be used.

마지막으로, 도 8에서와 같이 완충판(70)과 지진하중 흡수장치(10)의 하부채널(13)에 의해 둘러싸인 공간에 보강철근을 격자형태로 배근하고 거푸집을 짜댄 후 벽체 콘크리트(80)를 타설하면 된다.Lastly, as shown in FIG. 8, the reinforcing bar is arranged in a lattice form in the space surrounded by the buffer plate 70 and the lower channel 13 of the earthquake load absorbing device 10, and the wall concrete 80 is poured thereafter. Just do it.

도 9는 지진하중 작용시 본 발명에 따른 지진하중 흡수장치가 지진하중을 흡수하는 원리를 보여주는 단면도이다. 9 is a cross-sectional view showing the principle that the seismic load absorber according to the present invention absorbs the seismic load when the seismic load is applied.

이상에서 상세하게 설명한 것처럼 본 발명에 따르면 칸막이 벽체의 상단과 하단에 각각 지진하중 흡수장치가 설치되고 이 지진하중 흡수장치(10)는 충전재(15)의 강도가 기둥(20)과 보(30)의 강도보다 낮으므로 지진하중은 지진하중 흡수장치(10)로 집중된다. 따라서 도 9에서와 같이 충전재(15)는 전단연결재(12)를 통해 상부판(11)에 일체로 합성되어 있고 상부판(11)은 앵커볼트를 통해 보(30)에 일체로 고정되어 있으며 하부채널(13)은 충전재(15)와 마찰력에 의해서만 부착되어 있으므로 지진하중에 의해 전단변형부재(14)가 전단변형을 일으키게 된다. 즉, 본 발명에 따른 지진하중 흡수장치는 금속의 소성변형에 의한 에너지 소산 특성을 이용하는 변위 의존형 에너지 소산장치와 유사하게 전단변형부재(14)의 전단변형으로 지진하중을 흡수함으로써 주 구조부재에 전달되는 지진하중을 저감시키게 된다. 따라서 지진하중에 의한 주 구조부재의 손상을 방지할 수 있으며 지진발생 후에는 지진하중 흡수장치만을 교체하면 되므로 유지관리가 용이하다. As described in detail above, according to the present invention, an earthquake load absorbing device is installed at the top and the bottom of the partition wall, respectively, and the earthquake load absorbing device 10 has the strength of the filler material 15 of the pillars 20 and the beams 30. Since the seismic load is lower than the seismic load is concentrated in the seismic load absorber (10). Therefore, as shown in FIG. 9, the filler 15 is integrally synthesized with the upper plate 11 through the shear connector 12, and the upper plate 11 is fixed integrally with the beam 30 through the anchor bolt and has a lower portion. Since the channel 13 is attached only to the filler 15 by the frictional force, the shear deformation member 14 causes shear deformation due to the earthquake load. That is, the seismic load absorbing device according to the present invention absorbs the seismic load by the shear deformation of the shear deformation member 14 and transmits the seismic load to the main structural member similarly to the displacement dependent energy dissipation device using the energy dissipation characteristics caused by the plastic deformation of the metal. It will reduce the seismic load. Therefore, it is possible to prevent damage to the main structural members due to the earthquake load, and after the earthquake, only the earthquake load absorbing device needs to be replaced, so maintenance is easy.

위에서 본 발명은 제시된 실시 예를 참조하여 상세하게 설명이 되었지만 이 분야에서 통상의 지식을 가진 자는 제시된 실시 예를 참조하여 본 발명의 기술적 사상을 벗어나지 않는 범위에서 다양한 변형 및 수정 발명을 만들 수 있을 것이다. 본 발명은 이와 같은 변형 및 수정 발명에 의하여 제한되지 않으며 다만 아래에 첨부된 청구범위에 의하여 제한된다. While the present invention has been particularly shown and described with reference to exemplary embodiments thereof, it will be understood by those skilled in the art that various changes and modifications may be made without departing from the spirit and scope of the invention . The invention is not limited by these variations and modifications, but is limited only by the claims appended hereto.

10: 지진하중 흡수장치
11: 상부판
12: 전단연결재
13: 하부채널
14: 전단변형부재
15: 충전재
16: 비닐관
17: 완충재
20: 기둥
30: 보
40: 슬래브
60: 동바리
70: 완충판
80: 벽체 콘크리트
10: seismic load absorber
11: top panel
12: Shear connector
13: lower channel
14: shear deformation member
15: Filling material
16: vinyl tube
17: cushioning material
20: Column
30: Show
40: slab
60: Dongbari
70: buffer plate
80: wall concrete

Claims (5)

칸막이 벽체가 시공될 위치의 보의 하면과 슬래브의 상면에 각각 다수 개의 전단연결재가 설치된 상부판을 고정하는 단계;
상단 부분과 하단 부분을 갖고 상단 부분에는 일정 길이에 걸쳐 비닐관이 씌워지고 비닐관의 사이에 완충재가 설치된 전단연결부재를 상단 부분이 상부판을 향하도록 일정 간격으로 하부채널을 관통하도록 설치하고 하부채널을 전단연결재가 내부에 수용되도록 상부판의 하부와 상부에 각각 배치한 다음 전단변형부재의 상단을 상부판에 결합하는 단계;
하부채널 사이에 동바리를 설치하는 단계;
상부판과 하부채널으로 둘러싸인 공간에 충전재를 충전하는 단계;
충전재가 경화된 후 동바리를 제거하고 양쪽의 기둥이 마주보는 기둥 면에 각각 슬래브와 보 사이의 전체 높이에 걸쳐 완충판을 설치하는 단계; 및
완충판과 하부채널에 의해 둘러싸인 공간에 보강철근을 격자형태로 배근하고 거푸집을 짜댄 후 벽체 콘크리트를 타설하는 단계를 포함하는 것을 특징으로 하는 지진하중 흡수 기능을 갖는 칸막이 벽체의 시공방법.
Fixing a top plate on which a plurality of shear connectors are respectively installed on the bottom surface of the beam and the top surface of the slab where the partition wall is to be constructed;
The upper part and the lower part, and the upper part is covered with a vinyl tube over a certain length, and the shear connection member with a cushioning material installed between the vinyl tube is installed so as to penetrate the lower channel at regular intervals so that the upper part faces the upper plate. Arranging the lower and upper portions of the upper plate so that the shear connector is accommodated therein, and then coupling the upper end of the shear deformation member to the upper plate;
Installing a grouping between the lower channels;
Filling a filler into a space surrounded by an upper plate and a lower channel;
Removing the copper bar after the filler is cured, and installing a buffer plate over the entire height between the slab and the beam on each side of the pillar facing each other; And
A method of constructing a partition wall having a seismic load absorbing function, comprising: reinforcing reinforcing bars in a lattice form and weaving formwork in a space surrounded by a buffer plate and a lower channel.
청구항 1에 있어서,
전단변형부재는 철근인 것을 특징으로 하는 지진하중 흡수 기능을 갖는 칸막이 벽체의 시공방법.
The method according to claim 1,
A method of constructing a partition wall having a seismic load absorbing function, characterized in that the shear deformation member is reinforced.
청구항 1에 있어서,
충전재는 모르타르, 콘크리트 또는 섬유보강 콘크리트 중에서 어느 하나인 것을 특징으로 하는 지진하중 흡수 기능을 갖는 칸막이 벽체의 시공방법.
The method according to claim 1,
The filling material is a mortar, concrete or fiber reinforced concrete construction method of the partition wall having a seismic load absorption function, characterized in that any one.
청구항 1에 있어서,
완충재는 고무 또는 고무 발포체인 것을 특징으로 하는 지진하중 흡수 기능을 갖는 칸막이 벽체의 시공방법.
The method according to claim 1,
A cushioning material is a construction method of a partition wall having a seismic load absorbing function, characterized in that the rubber or rubber foam.
청구항 1에 있어서,
완충판은 고무 또는 고무 발포체로 구성되는 것을 특징으로 하는 지진하중 흡수 기능을 갖는 칸막이 벽체의 시공방법.
The method according to claim 1,
Method for constructing a partition wall having a seismic load absorbing function, characterized in that the buffer plate is composed of rubber or rubber foam.
KR1020110016743A 2011-02-24 2011-02-24 Method for constructing partition wall having seismic control KR101187179B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020110016743A KR101187179B1 (en) 2011-02-24 2011-02-24 Method for constructing partition wall having seismic control

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020110016743A KR101187179B1 (en) 2011-02-24 2011-02-24 Method for constructing partition wall having seismic control

Publications (2)

Publication Number Publication Date
KR20120097261A true KR20120097261A (en) 2012-09-03
KR101187179B1 KR101187179B1 (en) 2012-09-28

Family

ID=47108647

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020110016743A KR101187179B1 (en) 2011-02-24 2011-02-24 Method for constructing partition wall having seismic control

Country Status (1)

Country Link
KR (1) KR101187179B1 (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101378700B1 (en) * 2012-10-09 2014-03-28 한국기술교육대학교 산학협력단 Unit modular seismic absorbing apparatus for rahmen structures
CN104100004A (en) * 2013-04-07 2014-10-15 同济大学 Steel and concrete combined connecting piece with changeable dual column caps
KR101528972B1 (en) * 2013-02-22 2015-06-15 한국교통대학교산학협력단 Wall for seismic retrofit and construction methods of the wall
CN108643351A (en) * 2018-05-21 2018-10-12 同济大学 A kind of anchor bracing members ruggedized construction suitable for concrete beam and column node
CN109184254A (en) * 2018-10-23 2019-01-11 贵州中建建筑科研设计院有限公司 A kind of construction method and structure increasing partition wall newly on existing building floor
CN112878539A (en) * 2021-03-22 2021-06-01 沈阳建筑大学 High-energy-consumption damping wall
CN113719179A (en) * 2021-08-13 2021-11-30 北京建筑大学 Detachable cold-formed steel and lightweight filler shear wall and manufacturing method thereof
CN114577005A (en) * 2022-03-09 2022-06-03 四川科达节能技术有限公司 Steel rolling heating furnace brickwork
CN114658125A (en) * 2022-03-24 2022-06-24 澳创国际工程设计(深圳)有限公司 Shock insulation support for recycling temporary building and use method thereof
CN115928893A (en) * 2023-02-06 2023-04-07 上海核工程研究设计院股份有限公司 Modular connecting structure and method for penetration piece and concrete wall of nuclear power plant

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4016522B2 (en) 1999-02-15 2007-12-05 鹿島建設株式会社 Reinforcement structure of existing structure
JP2002285708A (en) 2001-03-27 2002-10-03 Taisei Corp Frame reinforcing structure
JP4277212B2 (en) 2004-08-30 2009-06-10 清水建設株式会社 Seismic reinforcement structure
JP4969152B2 (en) 2006-05-23 2012-07-04 太平洋セメント株式会社 Reinforcement structure and reinforcement method for concrete building

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101378700B1 (en) * 2012-10-09 2014-03-28 한국기술교육대학교 산학협력단 Unit modular seismic absorbing apparatus for rahmen structures
KR101528972B1 (en) * 2013-02-22 2015-06-15 한국교통대학교산학협력단 Wall for seismic retrofit and construction methods of the wall
CN104100004A (en) * 2013-04-07 2014-10-15 同济大学 Steel and concrete combined connecting piece with changeable dual column caps
CN108643351A (en) * 2018-05-21 2018-10-12 同济大学 A kind of anchor bracing members ruggedized construction suitable for concrete beam and column node
CN109184254A (en) * 2018-10-23 2019-01-11 贵州中建建筑科研设计院有限公司 A kind of construction method and structure increasing partition wall newly on existing building floor
CN112878539A (en) * 2021-03-22 2021-06-01 沈阳建筑大学 High-energy-consumption damping wall
CN113719179A (en) * 2021-08-13 2021-11-30 北京建筑大学 Detachable cold-formed steel and lightweight filler shear wall and manufacturing method thereof
CN114577005A (en) * 2022-03-09 2022-06-03 四川科达节能技术有限公司 Steel rolling heating furnace brickwork
CN114658125A (en) * 2022-03-24 2022-06-24 澳创国际工程设计(深圳)有限公司 Shock insulation support for recycling temporary building and use method thereof
CN114658125B (en) * 2022-03-24 2023-09-05 澳创国际工程设计(深圳)有限公司 Shock insulation support for temporary building cyclic utilization and use method thereof
CN115928893A (en) * 2023-02-06 2023-04-07 上海核工程研究设计院股份有限公司 Modular connecting structure and method for penetration piece and concrete wall of nuclear power plant
CN115928893B (en) * 2023-02-06 2024-01-12 上海核工程研究设计院股份有限公司 Modularized connecting structure and method for nuclear power plant penetrating piece and concrete wall

Also Published As

Publication number Publication date
KR101187179B1 (en) 2012-09-28

Similar Documents

Publication Publication Date Title
KR101187179B1 (en) Method for constructing partition wall having seismic control
KR101236575B1 (en) Method for constructing partition wall using seismic control device
KR101165320B1 (en) Earthquake-proof construction method for opening parts of building
KR101214139B1 (en) Steel reinforced concrete aseismatic structure and method using clamp
KR101185974B1 (en) Reinforcing apparatus for panel-zone of beam and column member using bracing member and structure reinforcing method therewith
KR101377327B1 (en) Method for reinforcing seismic capability of existing moment frames buildings of reinforced concrete by section enlargement
KR100927737B1 (en) Seismic strengthening composite system and seismic strengthening structure of building structure
JP4647714B1 (en) Buildings using walled columns with seismic prestressing
KR101112577B1 (en) Double Steel Frame Earthquake-Proof Device
KR101397800B1 (en) Method for reinforcing seismic capability of existing moment frames buildings of reinforced concrete by section enlargement
KR101705318B1 (en) Window and door open type vibration control system between columns for building
JP2008045393A (en) Composite energy absorbing structure and method for forming composite structure of building including one or plural floor slabs
KR101372087B1 (en) Strengthen method for steel frame structure using seismic control device
KR101565543B1 (en) A Joint Structures Between Steel Frame and Iron Concrete and A Joint Method
KR101456411B1 (en) Reinforcement Assembly For Coupling Beam Linked With Coupled Shear Wall
KR101478654B1 (en) Seismic Retrofit Technology using Diagrid Frames
KR101378700B1 (en) Unit modular seismic absorbing apparatus for rahmen structures
KR102083066B1 (en) Frame-type Damping Device and Reinforcing Method Using The Same
KR101242978B1 (en) Method for constructing partition wall using seismic control device
KR101403125B1 (en) Seismic control device and strengthen method for steel frame structure using thereof
KR101209363B1 (en) Concrete block for seismic reinforcement of H-shaped column and seismic reinforcing method using the same
JP5868603B2 (en) Seismic reinforcement method for existing buildings
KR101242972B1 (en) Method for constructing partition wall using seismic control device
KR101397886B1 (en) Method for reinforcing seismic capability of existing moment frames buildings of reinforced concrete by section enlargement
JP2006132150A (en) Seismic response control column and its construction method

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20150819

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20160627

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20170925

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20180823

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20190822

Year of fee payment: 8