KR20050095511A - Prestressed composite girder continuous bridge constructed by introducing prestressed concrete steel prestressed by a construction stage and compression stress to the upper structure through a partial down process, and constructing method thereof - Google Patents

Prestressed composite girder continuous bridge constructed by introducing prestressed concrete steel prestressed by a construction stage and compression stress to the upper structure through a partial down process, and constructing method thereof Download PDF

Info

Publication number
KR20050095511A
KR20050095511A KR1020040032061A KR20040032061A KR20050095511A KR 20050095511 A KR20050095511 A KR 20050095511A KR 1020040032061 A KR1020040032061 A KR 1020040032061A KR 20040032061 A KR20040032061 A KR 20040032061A KR 20050095511 A KR20050095511 A KR 20050095511A
Authority
KR
South Korea
Prior art keywords
girder
prestressed
prestress
composite girder
spans
Prior art date
Application number
KR1020040032061A
Other languages
Korean (ko)
Other versions
KR100563126B1 (en
Inventor
노윤근
박상현
Original Assignee
노윤근
박상현
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 노윤근, 박상현 filed Critical 노윤근
Publication of KR20050095511A publication Critical patent/KR20050095511A/en
Application granted granted Critical
Publication of KR100563126B1 publication Critical patent/KR100563126B1/en

Links

Classifications

    • GPHYSICS
    • G07CHECKING-DEVICES
    • G07FCOIN-FREED OR LIKE APPARATUS
    • G07F17/00Coin-freed apparatus for hiring articles; Coin-freed facilities or services
    • G07F17/32Coin-freed apparatus for hiring articles; Coin-freed facilities or services for games, toys, sports, or amusements
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q20/00Payment architectures, schemes or protocols
    • G06Q20/08Payment architectures
    • G06Q20/18Payment architectures involving self-service terminals [SST], vending machines, kiosks or multimedia terminals
    • GPHYSICS
    • G07CHECKING-DEVICES
    • G07FCOIN-FREED OR LIKE APPARATUS
    • G07F11/00Coin-freed apparatus for dispensing, or the like, discrete articles
    • G07F11/02Coin-freed apparatus for dispensing, or the like, discrete articles from non-movable magazines
    • G07F11/44Coin-freed apparatus for dispensing, or the like, discrete articles from non-movable magazines in which magazines the articles are stored in bulk

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Business, Economics & Management (AREA)
  • Accounting & Taxation (AREA)
  • Finance (AREA)
  • Strategic Management (AREA)
  • General Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Theoretical Computer Science (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

본 발명은 2경간이상의 다경간 교량에 적용하기 위한 것으로서, 내측 지점부에 연이어서 일정한 높이로 설치된 빔을 서로 연결한 다음 거더의 지점부 및 중앙부에 설치된 긴장장치에 의하여 긴장력이 도입되도록 시공단계별로 프리스트레스가 도입된 피에스씨 빔 및 강합성 거더를 포함한 프리스트레스 합성빔의 긴장효과와 부분적인 하강에 따른 상부 구조물에 압축응력을 도입하여 설치하는 프리스트레스 합성거더를 이용한 연속교 및 이의 설치방법에 관한 것으로서, 상기 프리스트레스 합성거더의 하강시 상대변위 측정을 할 수 있는 변위계를 부착하여 변형을 방지할 수 있도록 품질관리장치를 이용한 것이다.         The present invention is to be applied to a multi-span bridge over two spans, connecting the beams installed at a constant height in succession to the inner point, and then by the construction stage so that the tension force is introduced by the tension device installed in the point and the center of the girder The present invention relates to a continuous bridge using a prestressed composite girder and a method of installing the same, in which a prestressed composite beam including a PSC beam and a reinforced composite girder and a compressive stress is installed in an upper structure according to a partial drop. It is to use a quality control device to prevent deformation by attaching a displacement gauge that can measure the relative displacement when the prestressed composite girder descends.

다경간 교량중에서 5경간까지 또는 5경간 이상중 홀수의 경간을 갖는 교량의 첫 번째 내측 지점부 또는 6경간 이상의 교량 중에서 짝수의 경간인 경우에는 첫 번째 내측 지점부 및 중앙 지점부에 일정한 높이의 고임을 하여 인접하여 설치된 프리스트레스 합성거더를 연속화하고 슬래브를 타설한 다음 인접하여 설치된 상기 프리스트레스 합성거더의 양측단부 지점부에 설치된 정착구를 강연선으로 서로 연결한 지점부 긴장장치를 이용하여 압축력 도입으로 상부 구조물에 프리스트레스를 도입하고,         The first inner point of a bridge with an odd span of five to five spans or more than five spans, or an even span of six or more spans, and a fixed height at the first inner and central spots. The prestressed composite girders installed adjacent to each other, and the slab is poured, and then the prestressed devices are connected to each other by the tension lines connected to the anchorages connected to the two ends of the prestressed composite girders. To introduce

종래 업다운 및 다운 공법에서 적용하지 못했던 3경간 이상의 다경간 연속교에서도 양질의 내구성 향상과 원활한 시공을 도모할 수 있도록 종래기술과는 달리, 모든 교각에서 업다운 및 다운 공정을 행하는 것이 아니라, 5경간까지 또는 5경간이상중 홀수의 경간을 갖는 교량의 첫 번째 내측 지점부에서만 다운을 실시하거나, 6경간이상의 교량 중에서 짝수의 경간인 경우에는 첫 번째 내측 지점부 및 중앙 지점부에서 하강을 실시하는 다운 공정에 의해서 필요한 프리스트레스를 상부 구조물에 도입하는 부분 다운공정을 거친다음 상기 프리스트레스 합성보의 중앙부 하부에 설치된 정착구에 의하여 설치된 강연선에 긴장력을 도입하여 피에스씨 강재를 긴장함으로서 상부 구조물에 프리스트레스를 도입하는 것으로서, 상기 합성거더에 프리스트레스를 도입함에 있어서 피에스씨 강재와 부분적인 다운 공정에 의해서 시공단계별 압축력을 유발함을 주된 특징으로 하는 것이다.       Unlike the prior art, in order to improve the durability and smooth construction even in multi-span continuous bridges of 3 spans or more, which were not applied in the conventional up-down and down methods, up to 5 spans are not performed in all bridge piers. Alternatively, the down process may be performed only at the first inner point of a bridge having an odd span of five spans or more, or in the case of even spans of six or more spans of a bridge. The prestress is introduced into the upper structure by tensioning the PS steel by introducing tension to the strand installed by the anchorage installed in the lower portion of the center of the prestressed composite beam after the partial down process of introducing the necessary prestress to the upper structure. Prestress to the girder In the introduction, it is characterized by causing the compressive force for each construction stage by the PS steel and the partial down process.

또한, 상기 프리스트레스 합성거더를 하강할 때 상기 거더의 변위를 측정하기 위하여 변위계를 부착하여 하강시 상기 합성거더에 유해한 응력이 작용되는 것을 방지하는 품질관리장치인 변위계를 설치한 것에 특징이 있는 프리스트레스 합성거더 연속교 시공방법에 관한 것이다.        In addition, a prestressed composite is characterized in that a displacement gauge, which is a quality control device for preventing harmful stress from acting upon the synthetic girder, is installed by attaching a displacement meter to measure the displacement of the girder when the prestressed composite girder is lowered. Girder continuous bridge construction method

Description

시공단계별로 프리스트레스를 도입하는 피에스씨 강재와 부분적인 다운공정을 통해서 상부 구조물에 압축응력을 도입하여 설치되는 프리스트레스 합성거더 연속교 및 이의 시공방법 {Prestressed composite girder continuous bridge constructed by introducing prestressed concrete steel prestressed by a construction stage and compression stress to the upper structure through a partial down process, and constructing method thereof}  Prestressed composite girder continuous bridge constructed by introducing prestressed concrete steel prestressed by PS steels that introduce prestresses at each construction stage and installed by introducing compressive stress to the upper structure through a partial down process a construction stage and compression stress to the upper structure through a partial down process, and constructing method

본 발명은 다경간의 교량에서 5경간까지 또는 5경간이상중 홀수의 경간을 갖는 교량의 첫 번째 내측 지점부 또는 6경간이상의 교량 중에서 짝수의 경간인 경우에는 첫 번째 내측 지점부 및 중앙 지점부에 일정한 높이의 고임을 하여 설치하고, 인접하여 설치된 프리스트레스 합성거더를 서로 연결하고 바닥판을 타설하여 연속화하고, 인접하여 설치된 상기 프리스트레스 합성거더의 양측단부 지점부에 설치된 정착구를 강연선으로 서로 연결한 지점부 긴장장치를 이용하여 압축응력을 도입하여 프리스트레스를 합성거더에 도입하고, According to the present invention, the first inner point portion of a bridge having an odd span of five spans or more than five spans or an even span among bridges having six or more spans has a constant height in the first inner spot and central spots. Point tension device that is installed by the stiffness of the joint, adjacently installed prestressed composite girder connected to each other, the bottom plate is placed in a continuous manner, and anchors installed at both ends of the adjacent prestressed composite girder connected by a strand The prestress is introduced into the composite girder by introducing compressive stress using

종래 업다운 및 다운 공법에서 적용하지 못했던 3경간 이상의 다경간 연속교에서도 양질의 내구성 향상과 원활한 시공을 도모할 수 있도록 종래기술과는 달리, 모든 교각에서 업다운 및 다운 공정을 행하는 것이 아니라, 5경간까지 또는 5경간이상중 홀수의 경간을 갖는 교량의 첫 번째 내측 지점부에서만 다운을 실시하거나, 6경간이상의 교량 중에서 짝수의 경간인 경우에는 첫 번째 내측 지점부 및 중앙 지점부에서 하강을 실시하는 다운 공정에 의해서 필요한 프리스트레스를 상부 구조물에 도입하는 부분 다운공정을 거친, 다음 상기 프리스트레스 합성보의 중앙부 하부에 설치된 정착구에 의하여 설치된 강연선에 긴장력을 도입하여 피에스씨 강재를 긴장하여 후긴장 효과를 극대화하여 교량 상부 구조물에 프리스트레스를 도입하는 것으로서, 상기 합성거더에 프리스트레스를 도입함에 있어서 피에스씨 강재와 부분적인 다운 공정에 의해서 시공단계별 압축력을 유발하도록 한 것이다.     Unlike the prior art, in order to improve the durability and smooth construction even in multi-span continuous bridges of 3 spans or more, which were not applied in the conventional up-down and down methods, up to 5 spans are not performed in all bridge piers. Alternatively, the down process may be performed only at the first inner point of a bridge having an odd span of five spans or more, or in the case of even spans of six or more spans of a bridge. After the partial down process of introducing the necessary prestress to the upper structure, the tension force is introduced into the strand installed by the anchorage installed in the lower part of the center of the prestressed composite beam to tension the PS steel to maximize the post-tension effect to the bridge upper structure. By introducing prestress, In the introduction of prestress to the composite girder, it is to induce compressive force by construction stage by PS steel and partial down process.

상기 프리스트레스 합성거더를 하강할 때 상기 거더의 변위를 측정하기 위하여 변위계를 부착하여 하강시 상기 합성거더가 하강량의 차이로 인하여 변위(tilting)되어 상기 합성빔에 유해한 응력이 작용되는 것을 방지하는 프리스트레스 합성거더의 연속교 시공방법에 관한 것이다.     Prestress to prevent displacement of the composite girder due to the difference in the amount of fall when the pre-stressed composite girder is lowered by attaching a displacement meter to measure the displacement of the girder to prevent harmful stress on the composite beam The present invention relates to a continuous bridge construction method for composite girders.

본 발명의 목적은 당초에 고임량 만큼 만 하강하므로서 종래 거더 상승으로 인해 지점부에 발생하였던 거더에 유해한 응력의 발생을 방지하면서 상기 거더에 설치된 강연선을 긴장하여 거더에 긴장력이 도입되도록 하므로서 연속교의 공사의 공정을 줄여 시공성을 용이하게 하면서 공사비를 절감하도록 하면서, 상기 거더 하강시 거더에 발생할 수 있는 편측처짐을 검측할 수 있도록 하여 거더에 발생할 수 있는 유해한 응력의 발생을 방지하는 품질관리장치인 변위계를 설치하고, 상기 연속교가 노후되거나 또는 교량의 내하력의 보강이 필요할 경우에 상기 거더에 설치된 상기 긴장장치를 재긴장하여 교량의 내하력을 보강하도록 하는 후긴장 효과를 지닌 프리스트레스 합성거더 연속교 시공방법을 제공하는데 있다.     The purpose of the present invention is to lower the amount of the original girder initially, while preventing the generation of harmful stress on the girder that occurred in the point due to the conventional girder while tensioning the stranded wire installed in the girder so that the tension force is introduced into the girder construction of the continuous bridge It is possible to reduce construction cost by reducing the process of the process, and to measure the unilateral deflection that may occur on the girder when the girder is lowered, so as to prevent the generation of harmful stress that may occur on the girder, To provide a pre-stressed composite girder continuous bridge construction method having a post-tension effect to reinforce the load capacity of the bridge when the continuous bridge is aging or reinforcement of the load capacity of the bridge to re-tension the tension device installed on the girder It is.

상기에서 본 발명의 주요 구성의 특징을 요약하여 설명하면 다음과 같다.      The summary of the features of the main configuration of the present invention described above is as follows.

(1) 다경간 연속교중에서 5경간까지 또는 5경간 이상중 홀수의 경간을 갖는 교량의 경우는 첫 번째 내측 지점부 또는 6경간이상의 교량 중에서 짝수의 경간인 경우에는 첫 번째 내측 지점부 및 중앙 지점부 상에 고임 및 하강장치(60)의 상부로 일정한 높이의 고임량(31)이 형성되도록 한 다음 그 위에 프리스트레스 합성거더(20)를 설치하고,     (1) In the case of bridges with odd spans of up to 5 spans or more than 5 spans in multi-span continuous bridges, the first inner spot and center spots in case of even spans among bridges of 6 spans or more. The high loading amount 31 of a constant height is formed on the top of the holding device and the lowering device 60, and then the prestress compound girder 20 is installed thereon.

(2) 상기 빔(20) 양측면부의 상부 양측단부에 설치된 지점부 긴장장치(40)에 연결된 강연선(42)을 긴장하여 상기 거더(20)에 압축력을 도입하여 교량 상부 구조물에 프리스트레스를 도입하는 것이며,     (2) the prestress is introduced to the upper structure of the bridge by introducing a compressive force to the girder 20 by tensioning the strand 42 connected to the point tension device 40 installed at the upper both ends of the beam 20 at both sides. ,

(3) 상기 5경간까지 또는 5경간 이상중 홀수의 경간을 갖는 교량의 첫 번째 내측 지점부 또는 6경간이상의 교량 중에서 짝수의 경간인 경우에는 첫 번째 내측 지점부 및 중앙 지점부 상에 일정한 고임량(31)에 의하여 설치된 프리스트레스 합성거더(20)를 다운(Down)하고,     (3) If the first inner point of a bridge having an odd span of up to five spans or more than five spans, or an even span among six or more spans, a fixed high dose on the first inner spot and a central spot ( Down the prestressed composite girder 20 installed by 31),

(4) 상기 빔(20) 중앙부 하부에 설치된 중앙부 긴장장치(50)에 연결된 강연선(42)을 긴장하여 교량 상부 구조물에 프리스트레스를 도입하는 것이며,    (4) to tension the strand 42 connected to the central tension device 50 installed below the central portion of the beam 20 to introduce prestress into the bridge superstructure,

(5) 상기 내측 지점부(12)상에 일정한 고임량(31)으로 들어올려져 설치된 거더(20)를 하강할 때 고임 및 하강장치(60)에 설치된 변위계(70)에 설치된 수포(72)를 이용하여 상기 거더(20)가 수평을 유지하면서 하강하여 교좌장치(14)에 안착되도록 하는 품질관리장치를 부착하여 교량의 품질을 관리하는 것이다.      (5) When the girder 20 is lifted and mounted on the inner point portion 12 by a constant high dose 31, the blister 72 is installed on the displacement meter 70 installed on the lifter and lowering device 60. By using the girder 20 is attached to a quality control device to be lowered while maintaining the horizontal to be seated on the bridge device 14 to manage the quality of the bridge.

상기의 본 발명에 대응되는 종래의 기술로서는 일본토목학회에서 1989년 3월 20일에 발행한 강, 콘크리트 합성구조의 설계가이드라인에 소개된 중간지점 상승하강에 의한 프리스트레스 도입법이 소개되어 있으나 시공이 복잡하고 완공후 유지관리가 힘들다는 단점으로 인하여 현재에는 사용하지 않고 있는 공법으로서 그 상세한 시공방법은 도 1의 시공순서와 같다.     As a conventional technique corresponding to the present invention, the prestress introduction method by the mid-point rise and fall introduced in the design guideline of the composite structure of steel and concrete issued by the Japanese Society of Civil Engineers on March 20, 1989 is introduced. Due to the disadvantages of complicated and difficult maintenance after completion, the construction method is not used at present, the detailed construction method is the same as the construction sequence of FIG.

상기의 도면을 참고로 하여 그 시공순서를 설명하면 다음과 같다.     Referring to the drawings, the construction sequence is as follows.

도 1의 (a)는 종래에 정정 구조물인 단경간 피에스씨빔 제작을 나타내는 것이며,     Figure 1 (a) shows the manufacturing of short span PS beam which is conventionally a correction structure,

(b)는 상기 제작된 피에스씨빔(110)을 양측의 지점부(101)와 중앙 지점부(102)에 설치된 일정한 길이로 상향으로 올라간 가지점(111)인 유압잭에 상기 피에스씨빔(110)을 거치하여 중앙 지점부(102) 상에서는 상기 피에스씨빔(110)이 유압잭 위에서 일정한 고임량(112)으로 고임된 상태로 들어올려 설치된 것을 보여주는 것이며,      (b) is the PS beam (110) to the hydraulic jack that is the branch point 111 is raised to a predetermined length installed on the branch portion 101 and the central point portion 102 on both sides of the PS beam (110) On the center point 102 through the) shows that the PS beam (110) is lifted up in a fixed state at a constant high dose 112 on the hydraulic jack,

(c)는 상기 중앙 지점부(102)에 연이어서 일정하게 고임된 상태로 된 상기 피에스씨빔(110)의 연속부에 철근 및 강판을 설치하고 이를 용접하여 연결하고 콘크리트를 타설양생하여 연결부(115)를 형성하여 연속교(100)를 형성하는 과정을 보여주는 것이며,      (c) installs reinforcing bars and steel sheets in the continuous portion of the PS beam 110 in a constant state of succession to the central point portion 102 and welds them, connects them, and pours concrete to connect the connecting portion ( 115) to show the process of forming a continuous bridge (100),

(d)는 상기 중앙 지점부(102) 상으로 일정한 고임량(112)으로 들어올려지게 설치된 상기 피에스씨빔(110)을 다시 일정한 양(113)만큼 상승하는 것을 보여주는 것이며,      (d) shows that the PS beam 110, which is installed to be lifted at a constant high dose 112 onto the central point portion 102, is raised by a constant amount 113 again,

(e)는 상기의 (d) 단계에서 고임량(112)과 상승량(113)만큼 상향으로 들어 올려진 상기 피에스씨빔(110)의 상부에 바닥판(116)을 타설하고 빔과 빔을 연결하는 가로보를 설치한 다음 상기 들어올려진 상기 피에스씨빔을 다시 상기 고임량과 상승량만큼의 길이를 하강(114)하여 상기 중앙 지점부(102)에 설치된 교좌장치(103)에 안착시키는 것이며,      (e) pours the bottom plate 116 on top of the PS beam 110, which is lifted upward by the high dose 112 and the rise amount 113 in step (d) and connects the beam with the beam. After installing the cross beams to lower the 114 as much as the high dose and the rising amount of the raised PS beam again to the seating device 103 installed in the central point portion 102,

(f)는 상기의 (e) 단계를 거치 상기 연속설치된 상기 피에스씨빔(110)의 상부에 교량을 설치하도록 하여 피에스씨빔 연속교(100)를 설치하는 과정을 단계적으로 보여주는 것이다.      (f) shows step by step the process of installing the PSC beam continuous bridge 100 by installing a bridge on top of the continuous CS beam 110 through the step (e) above.

상기 일련의 과정을 거쳐 설치된 연속교(100)의 주요 구성부의 특징은,         Features of the main components of the continuous bridge 100 installed through a series of processes,

(1) 지점부 상에 일정한 고임량(112)에 의해 빔(110)을 고임설치한 후에         (1) After installing the beam 110 by a constant high dose 112 on the point portion

(2) 다시 상기 빔(110)에 일정한 크기의 상승량(113) 만큼 위로 상승시켰다가         (2) The beam 110 is raised upward by a certain amount of the rising amount 113.

(3) 다시 상기 고임량과 상승량만큼 위로 들어 올려진 빔을 다시 상기 중앙 지점부(102)의 교좌장치(103)에 일정한 하강량(114)만큼 내려놓는 것으로서        (3) again lowering the beam lifted up by the high and rising amounts by a certain amount of descending 114 to the intersection device 103 of the central point portion 102;

즉, 들어올려진 빔을 다시 들어올리고 이렇게 이중으로 들어 올려진 빔을 하강하여 지점부에 안착시키 과정을 거치면서 연속교가 설치되는 것이다.        That is, the continuous bridge is installed while lifting the raised beam again and descending the beam which is lifted in this way to be seated at the point.

또한, 상기 공법을 이용하여 출원한 기술로서는 1998년 10월 08일자로 출원하여 제10-0328320호로 특허 등록된 "지점 상승 및 하강을 이용한 피에스씨 빔의 연속화 공법"과 1998년 01월 22일자로 출원하여 제10-0283603호로 특허등록된 "지점 상승 및 하강을 이용한 피에스 씨 빔의 연속화 공법"과 1999년 01월 21일자로 출원하여 제 10-0341342호로 특허등록된 "가지점의 상승.하강을 이용한 피에스 씨 빔교의 시공 및 보수, 보강공법"등이 있으며, 이 또한 상기에서 언급한 공법과 마찬가지로 다음과 같은 문제점을 포함하고 있는 기술로서 그 문제점으로서는 중앙 지점부의 응력개선을 목적으로 빔을 상승할 때, 바닥판 타설전의 지점부 구조계에서는 부모멘트가 추가로 작용하게 되어 빔 상연(上椽)에는 유해한 인장응력이 추가로 발생하게 되므로 하강량을 상승량보다 더욱 크게 작용시켜 상기 빔의 상연에서 발생되는 유해한 응력을 제거하고자 하였으나, 실제 시공시에는 상승 및 하강량의 편차만큼을 조절하여야 하기에 상당한 크기의 상승 및 하강량을 필요로 하여 시공성이 복잡하고, 공사비가 증대되는 문제점과 지점부에서는 유해한 응력이 도입되는 등의 문제점이 제기되어 왔다.        In addition, as a technology filed using the above method, filed on October 08, 1998 and registered as a Patent No. 10-0328320, "Continuous Method of PS Beam Using Point Rise and Fall" and January 22, 1998 The application method is a patented "No. 10-0283603", "Pease C beam continuity method using the rising and falling point" and the application of the date of January 21, 1999, and registered as "10-0341342", the rising and falling of the branch Construction, repair, and reinforcement method of the PS beam beam bridge, which is used, and the same method as the above-mentioned method, which also includes the following problems. The problem is to raise the beam for the purpose of improving the stress at the central point. At this time, in the structure of the point part before the bottom plate is placed, the parent moment acts additionally, and harmful tensile stress is additionally generated at the upper edge of the beam. To remove the harmful stress generated at the upper edge of the beam by acting greatly, but in actual construction, as much as the amount of rise and fall must be controlled by the deviation of the rise and fall amount, the construction complexity is complicated, Problems such as increased construction costs and harmful stresses have been introduced at the branch.

참고적으로 상기 도 1에서 적용하고 있는 30m 경간의 연속교에서의 고임량(112)은 150mm이며, 상승량(113)은 200mm이고, 상기 고임량(112)과 상승량(113)을 합한 하강량(114)은 350mm이다.For reference, the high dose 112 in the continuous bridge spanning 30 m, which is applied in FIG. 1, is 150 mm, the amount of rise 113 is 200 mm, and the amount of descending sum of the high dose 112 and the amount of rise 113 ( 114) is 350 mm.

즉, 상기에서 설명한 연속교의 특징을 상기의 수치를 대입하여 설명하면,         That is, the characteristics of the continuous bridge described above will be described by substituting the above numerical values.

(1) 지점부 상에 일정한 고임량(150mm)에 의해 빔이 고임설치된 후에         (1) After the beam is fixedly installed by a constant high dose (150 mm) on the point portion

(2) 다시 상기 빔에 일정한 크기의 상승량(200mm) 만큼 위로 상승        (2) ascending up the beam by a certain amount (200 mm)

(150mm+200mm)시켰다가 (150mm + 200mm)

(3) 다시 상기 고임량과 상승량만큼 위로 들어 올려진(150mm+200mm) 빔을 다시 상기 중앙 지점부의 교좌장치에 하강량(350mm) 만큼 내려놓아 연속교를 설치        (3) Install the continuous bridge by lowering the beam (150mm + 200mm) that is lifted up by the high dose and the amount of lift up by the amount of descending (350mm) to the seating device of the central point.

하는 것이다.It is.

상기에서 본 발명과 종래기술의 기술적 차이점을 설명한 것을 발생되는 응력도를 이용하여 다시한번 요약하여 비교설명하면 다음과 같다.When explaining the technical difference between the present invention and the prior art in the above summarized once again by using a degree of stress generated as follows.

상기의 모멘트 비교표에서보는바와 같이 종래기술의 공법에서는 상향으로 200mm의 상승량 만큼 빔을 들어 올리는 업(UP)공정이 적용되어 모멘트가 발생되고 있으나, 본 발명에서는 업(UP) 공정이 없어 모멘트가 발생되지 않으며, 또한 종래기술에서는 후긴장 공정이 없어 모멘트가 발생되지 않으나, 본 발명에서는 후긴장 공정이 있어 모멘트가 발생되는 것을 볼 수가 있다.As shown in the above moment comparison table, in the prior art, a moment is generated by applying an up (UP) process of lifting a beam upward by 200 mm, but in the present invention, there is no up (UP) process and a moment is generated. In addition, in the prior art, there is no post-tension process and no moment is generated, but in the present invention, there is a post-tension process and it can be seen that the moment is generated.

즉, 다시말하면 종래기술의 업(up)공정은 빔을 지점부에서 상향으로 다시 들어 올린다는 것을 의미하여 이로인하여 상기 빔에 유해한 응력이 작용되어 빔에 균열등이 발생될 수 있다는 것을 의미하는 반면에 본 발명에서는 상기의 종래기술에서 빔을 다시 들어올리는 공정인 업(up)공정이 없어 빔에 유해한 응력이 발생되지 않아 빔에 균열등이 발생될 소지를 원천적으로 배제한 다는 것을 의미하며, 상기의 후긴장공법은 본 발명에서는 빔의 중앙부 하부에 강연선을 정착구를 이용하여 설치하여 빔을 지점부에 설치하고 빔을 연속화 시킨 후에 상기 빔에 설치된 강연선에 긴장력을 도입하는 것으로서 별도로 프리스트레스를 빔에 도입하는 것으로서 빔에 내하력을 보강하는 의미인 반면에 종래기술에서는 후 긴장 공정이 없어 빔에 별도로 프리스트레스를 도입할 수 없다는 것을 의미한다. 또한, 상기의 후긴장에 사용된 정착구와 강연선은 나중에 교량의 노후화 및 내하력의 보강이 필요할 때 상기 강연선을 재긴장하여 빔에 긴장력을 도입하여 교량의 내구연한을 연장시키도록 하는 보수보강장치로서도 그 역할을 할 수 있도록 한 것이다.    In other words, the prior art up process means that the beam is lifted upward from the point part, which means that harmful stress may be applied to the beam and cracks may be generated in the beam. In the present invention, there is no up process, which is a process of lifting the beam again in the prior art, so that harmful stress does not occur in the beam, and thus, the possibility of causing cracks in the beam is basically excluded. In the post-tension method, in the present invention, a strand is installed at a lower portion of the center portion of the beam by using a fixing unit, the beam is installed at a point, and after the beam is continually introduced, the prestress is separately introduced into the beam by introducing a tension force to the strand installed on the beam. In the prior art, there is no post-tension process, so the beam is prestressed separately. It means that there can be introduced. In addition, the anchorage and the strand used in the post-tension as a reinforcing reinforcement device to re-tension the strand when the aging of the bridge and reinforcement of the load is required later to introduce tension to the beam to extend the durability of the bridge. It is to play a role.

상기의 모멘트 비교표에서 보는바와 같이 종래의 기술에서 업(up) 공정시 단면제원과 본 발명의 다운(down) 공정시의 단면제원이 서로 동일하다면, M7=M5-M3, M8=M6-M4인 관계가 형성되므로 후 긴장 효과 크기만큼, 즉, M9와 M10 만큼 본 발명의 기술에 의한 구조역학적 효과가 우수함을 알 수 있다.As shown in the above moment comparison table, if the cross-sectional specification in the up process and the cross-sectional specification in the down process of the present invention are the same in the prior art, M7 = M5-M3 and M8 = M6-M4. As the relationship is formed, it can be seen that the structural dynamic effect by the technique of the present invention is excellent by the magnitude of the post-tension effect, that is, M9 and M10.

시공성 면에서도 무거운 중량 구조물을 상승시키기 위해서는 상당한 힘과 세밀한 주의가 요구되는 시공이기에 종래기술에서는 채택하고 있는 업(UP) 공정을 본 발명에서는 배제하고 빔을 하강할 때 빔이 수평을 이룰 수 있도록 하는 다운(DOWN) 공정만을 실행한다면 간편한 시공성과 후긴장 효과를 응용한다면 경제적이고 품질이 확보된 내구성이 우수한 교량건설을 할 수 있다는 점을 상기 모멘트 비교표에서 확실하게 입증하고 있다.     In terms of workability, since the construction requires a great deal of power and attention to raise a heavy weight structure, the present invention excludes the UP process, which is adopted in the prior art, so that the beam can be leveled when the beam descends. The moment comparison table clearly demonstrates that if only the DOWN process is carried out, simple construction and post-tension effects can be applied and economical and secured bridges with excellent quality can be constructed.

또 다른 종래기술로서는 2002년 5월 8일자로 출원하여 등록번호 제20-0285993호로 등록된 "상승 공정이 생략된 다경간 연속 합성형 구조물"에 관한 것으로서, 본 고안의 교량에서 발생되는 모멘트를 보여주는 도 9와 같이 모멘트가 발생되며, 상기 고안은 주형을 거치하고 연결전에 외측지점 및 내측지점 위에 설계 하강량 만큼 거치고임을 하고, 바닥판 콘크리트를 타설한 상태에서 상기 거치고임을 제거하여 주형의 하부 플랜지와 내측 지점부의 바닥판 콘크리트에 압축력을 도입하는 거이다.    Another prior art relates to a "multi-span continuous composite structure without an ascending process," filed on May 8, 2002, registered under registration number 20-0285993, which shows a moment generated in a bridge of the present invention. Moment is generated as shown in Figure 9, the design is to mount the mold and before the connection and the amount of the design fall on the outer point and the inner point before the connection, and the bottom flange of the mold by removing the mounting gripping in the state of placing the bottom plate concrete The compressive force is introduced into the bottom plate concrete at the inner point.

상기 고안의 기술내용을 상세히 설명하면      When describing the technical content of the invention in detail

- 내측지점에는 바닥판 콘크리트에 압축력을 도입하기 위한 하강량에 상응하는 거치고임을 설치하면서 2개소의 외측지점중 어느 1개소의 외측지점부에 거치고임을 하고 상기 거치고임을 해제하여 바닥판 콘크리트에 압축력을 도입하거나,       -At the inner point, install the mounting platform corresponding to the descending amount to introduce the compressive force to the bottom plate concrete, and attach it to the outer point at any one of the two outer points, and release the mounting ring to apply the compressive force to the bottom plate concrete. Introducing,

- 내측 지점에 거치고임을 실시하면서 2개소의 외측지점 모두에 거치고임을 하고 상기 거치고임을 해제하여 바닥판 콘크리트에 압축력을 도입하는 것이다.       -It is to apply the compressive force to the bottom plate concrete by releasing the ridge and releasing the ridge in both of the two outer points while carrying out the ridge in the inner point.

상기의 기술내용은 결국 내측지점부와 외측의 지점부 2개소 전부 또는 1개소에 거치고임을 실시하여 상기 지점부상에는 최소한 1개의 경간사이에 있는 거더는 항상 전체가 고임된 상태이며 이를 하강하는 것으로서 최소한 1개의 거더 전체가 통째로 고임되었다가 하강하는 것입니다.      The above description is carried out at all or one of the two points of the inner branch and the outer branch, so that the girder between at least one span is always in the state of being totally held on the branch and is lowered. The whole of one girder is held down and descends.

도 9와 같이 상기의 종래기술을 적용한 5경간 연속교에서 첫 번째 내측교각의 부모멘트를 제어하기 위하여 모든 내측 지점부 교각에서 다운 공정을 하게되면, 도 9(b)와 같이 모든 지점부에서 다운한 경우 중앙부에 위치한 내측 교각에서는 부모멘트 Ma가 발생되어, 설계하중에서의 모멘트 분포도와 중첩으로 작용하여 유해한 품질상태를 나타내는 문제점과, 내측교각등이 추가로 설계되거나, 혹은 시공오차에 의해 추가로 지점침하등의 문제가 발생하게 되면 설계하중하에서 가장 큰 부모멘트를 받고 있는 첫 번째 내측 교각에서는 오히려 정모멘트(Mc)가 발생되는 모순점등에 의해서, 종래 기술은 5경간 이상의 교량에 대해서는 적용할 수 없다는 구조역학적인 문제점으로 인해, 국내 및 국외에서도 상기 기술을 5경간이상에 적용한 설계 및 시공사례가 없으며, 전 지점부에서 동일한 양의 다운 및 상승이 이루어지도록 하는 시공이 매우 어려운 단점이 있다.      In the five-span continuous bridge to which the prior art is applied as shown in FIG. 9, when the down process is performed at all inner point piers to control the parent moment of the first inner piers, as shown in FIG. In one case, a parent moment Ma is generated in the inner pier located in the center part, and it acts as a moment distribution and superimposition of the design load, indicating a harmful quality state, and an inner pier is additionally designed, or additionally due to construction errors. If a problem such as point settlement occurs, the contradiction point in which the positive moment (Mc) is generated in the first inner pier that receives the largest parent moment under the design load, the prior art cannot be applied to bridges longer than 5 spans. Due to the structural problems, there are no cases of design and construction that apply the above technology to more than 5 spans in Korea and abroad. And, there is a very difficult disadvantage that the construction to make the same amount of down and rise at all points.

본 발명은 상기의 문제점을 개선하기 위하여 제안된 기술로서, 기존의 피에스씨 콘크리트빔교 뿐만아니라, 프리스트레스가 도입되는 강교에서도 똑같은 원리가 적용되는 것이기에 프리스트레스 합성거더라 칭하며, 이러한 프리스트레스 합성거더를 내측 지점부 또는 내측지점부 및 중앙 지점부 상에 일정한 높이의 고임량 만큼 거치된 거더를 상기의 고임량 만큼 만 하강하므로서 거더에 유해한 응력의 발생을 방지하면서 상기 거더에 설치된 강연선을 긴징하여 거더에 압축력이 도입되도록 하여 연속교의 교량 설치공사의 공정을 줄여 시공성을 용이하게 하면서 공사비를 절감하고, 상기 거더의 하강시 하강에따른 거더의 편측처짐을 방지하기 위하여 변위계를 설치하여 교량시공시 거더에 유해한 응력이 발생되지 않도록 정밀한 시공을 할 수 있도록 품질관리장치인 변위계를 설치하고, 또한 상기 연속교가 노후되거나 또는 내하력의 보강이 필요할 경우에 상기 거더에 설치된 상기 긴장장치를 재긴장하여 교량의 내하력을 보강하도록 하는 후긴장 효과를 지닌 프리스트레스 합성거더의 연속교 시공방법을 제공하는데 있다.       The present invention is a technique proposed to improve the above problems, the same principle is applied to not only the conventional PS concrete beam bridge, but also pre-stressed steel bridge is called prestress composite girder, such pre-stress composite girder, the pre-stress composite girder Alternatively, by lowering the girder mounted by the high dose of a certain height on the inner point and the central point by only the high dose, the compressive force is introduced to the girder by lengthening the stranded wire installed in the girder while preventing the generation of harmful stress on the girder. To reduce construction costs by reducing the process of bridge installation work of continuous bridges, to reduce construction costs, and to prevent unilateral sagging of girders due to descent when the girders descend, harmful stresses are generated on the girders during bridge construction. So that you can precisely install Of prestressed composite girders with post-tensioning effect to reinforce the load-bearing capacity of the bridge by installing a displacement gauge as a quality control device and re-tensioning the tension device installed on the girder when the continuous bridge is deteriorated or the load capacity needs to be reinforced. It is to provide a continuous bridge construction method.

본 발명은 다경간의 교량에서 5경간까지 또는 5경간이상중 홀수의 경간을 갖는 교량의 첫 번째 내측 지점부 또는 6경간이상의 교량 중에서 짝수의 경간인 경우에는 첫 번째 내측 지점부 및 중앙 지점부에 일정한 높이의 고임을 하여 설치하고, 인접하여 설치된 프리스트레스 합성거더를 서로 연결하고 바닥판을 타설하여 연속화하고, 인접하여 설치된 상기 프리스트레스 합성거더의 양측단부 지점부에 설치된 정착구를 강연선으로 서로 연결한 지점부 긴장장치를 이용하여 압축응력을 도입하여 프리스트레스를 합성거더에 도입하고, 상기 5경간까지 또는 5경간 이상, 즉 6경간 부터의 교량중 홀수의 경간을 갖는 교량의 첫 번째 내측 지점부 또는 6경간이상의 교량 중에서 짝수의 경간인 경우에는 첫 번째 내측 지점부 및 중앙 지점부 상에 일정한 고임량(31)에 의하여 설치된 프리스트레스 합성거더(20)를 다운(Down)하고,According to the present invention, the first inner point portion of a bridge having an odd span of five spans or more than five spans or an even span among bridges having six or more spans has a constant height in the first inner spot and central spots. Point tension device that is installed by the stiffness of the joint, adjacently installed prestressed composite girder connected to each other, the bottom plate is placed in a continuous manner, and anchors installed at both ends of the adjacent prestressed composite girder connected by a strand The prestress is introduced into the composite girder by introducing the compressive stress, and the first inner point of the bridge having the odd span of the bridge up to 5 spans or more than 5 spans, i.e., from 6 spans or more spans For even spans, a constant high dose (3 Down the prestressed composite girder 20 installed by 1),

상기 빔(20) 중앙부 하부에 설치된 중앙부 긴장장치(50)에 연결된 강연선(42)을 긴장하여 후긴장 효과를 극대화하도록 교량 상부 구조물에 프리스트레스를 도입하는 것이다. The prestress is introduced into the upper structure of the bridge to maximize the post-tension effect by tensioning the strand 42 connected to the center tension device 50 installed below the center of the beam 20.

상기 내측 지점부(12) 또는 첫째 내측 지점부 및 중앙 지점부 상에 일정한 고임량(31)으로 들어올려져 설치된 거더(20)를 하강할 때 고임 및 하강장치(60)에 설치된 변위계(70)에 설치된 수포(72)를 이용하여 상기 거더(20)가 수평을 유지하면서 하강하여 교좌장치(14)에 안착되도록 하는 품질관리장치를 부착하여 교량의 품질을 관리하는 것에 특징이 있다.        When descending the girder 20 mounted on the inner point portion 12 or the first inner point portion and the central point portion with a constant high dose 31, the displacement meter 70 installed on the holding and lowering device 60. By using the installed blister 72 is characterized in that the girder 20 is attached to the quality control device to be lowered while maintaining the horizontal to be seated on the bridge device 14 to manage the quality of the bridge.

이하, 본 발명의 구성 및 작용을 첨부한 도면에 의하여 상세히 설명하면 다음과 같다.       Hereinafter, described in detail by the accompanying drawings the configuration and operation of the present invention.

도 2 (a),(b),(c),(d),(e),(f)는 본 발명의 부분 다운(Down) 공정을 이용하여 단계적으로 연속교를 시공하는 방법을 보여주는 도면으로서,         2 (a), (b), (c), (d), (e), and (f) are views showing a method of constructing a continuous bridge step by step using a partial down process of the present invention. ,

(a)는 종래에 사용되고 있는 프리스트레스가 도입되는 피에스씨빔 혹은 강합성 거더교를 제작하는 것을 나타내는 것이며,        (a) shows the manufacture of the PS seam beam or the composite girder bridge into which the prestress used conventionally is introduced,

(b)는 상기 제작된 프리스트레스 합성거더(20)를 양측의 외측 지점부(11)와 내측 지점부(12)에 상기 거더를 거치하면서 상기 첫째 내측 지점부 또는 첫째 내측 지점부 및 중앙 지점부 상에 일정한 높이로 상향으로 올라간 고임 및 하강장치(60)인 유압잭 또는 스크류 잭 위에 상기 프리스트레스 합성거더(20)를 거치하여 내측 지점부(12) 상에서는 상기 프리스트레스 합성거더(20)가 유압잭 위에서 일정한 고임량(31)으로 고임된 상태로 들어올려 설치된 것을 보여주는 것이며,       (b) is the prestress composite girder 20 produced on the first inner point portion or the first inner point portion and the center point portion while mounting the girder on the outer point portion 11 and the inner point portion 12 on both sides; The prestressed composite girder 20 is mounted on the hydraulic jack or screw jack, which is the spooling and lowering device 60, which is raised upward at a predetermined height, and the prestressed composite girder 20 is fixed on the hydraulic jack. To show that it was installed in a state of being held as 31,

(c)는 상기 첫째 내측 지점부 또는 첫째 내측 지점부 및 중앙 지점부 상에 일정한 높이로 상향으로 고임된 상태로 된 상기 프리스트레스 합성거더(20)의 연속부에 철근 및 강판을 용접설치하고 연속부에 콘크리트로 충전양생하여 연결부(15)를 형성하여 연속교(100)를 형성하는 과정을 보여주는 것이며,        (c) is welded to the continuous portion of the pre-stressed composite girder 20 in a state of being held up to a constant height upward on the first inner point portion or the first inner point portion and the center point portion, the continuous portion It shows the process of forming a continuous bridge (100) by forming a connection portion 15 by curing with concrete in the

(d)는 상기 첫째 내측 지점부 또는 첫째 내측 지점부 및 중앙 지점부 상에 일정한 높이로 상향으로 일정한 고임량(31)으로 들어올려지게 설치된 상기 프리스트레스 합성거더(20)의 상부에 바닥판(13)을 타설하고 인접하여 설치된 상기 프리스트레스 합성거더의 양측단부 지점부에 설치된 정착구를 강연선으로 서로 연결한 지점부 긴장장치를 이용하여 압축응력을 도입하여 프리스트레스를 합성거더에 도입하는 것을 보여주며,         (d) is a bottom plate (13) on top of the prestressed composite girder (20), which is installed to be lifted at a constant high dose (31) upwards at a constant height on the first inner point portion or the first inner point portion and the central point portion. ) Shows the introduction of prestress into the composite girder by introducing compressive stress using the point tensioning device connected to each other with a strand of anchorages installed at both ends of the prestress composite girder installed adjacent to each other.

(e)는 상기의 (d) 단계에서 상기 첫째 내측 지점부 또는 첫째 내측 지점부 및 중앙 지점부 상에 연이어서 설치된 프리스트레스 합성거더(20)의 하부에 각각 설치된 상기 고임 및 하강장치인 유압잭 또는 스크류 잭에 변위계(70)를 서로 연결부착 설치하고 상기 고임된 상태의 프리스트레스 합성거더를 하강하면서 상기 변위계(70)에 설치된 수포(72)를 이용하여 상기 거더(20)가 수평을 이루면서 하강하도록 하여 편측변위가 발생하지 않도록 하면서 상기 지점부(12)에 설치된 교좌장치(14)에 안착시키는 것이며,       (e) is a hydraulic jack or screw which is the spooling and lowering device respectively installed in the lower portion of the prestressed composite girder 20 which is installed on the first inner point portion or the first inner point portion and the center point portion in succession in step (d). Displacement meter 70 is connected to each other in a jack, and the prestressed composite girder in the stagnant state is lowered while the girder 20 is horizontally lowered by using the blister 72 installed in the displacement meter 70. It is to be seated on the bridge device 14 installed in the point portion 12 so that no displacement occurs,

(f)는 상기 프리스트레스 합성거더(20)의 중앙부 하부에 설치된 강연선(42)을 각각 긴장하여 거더(20)에 후 긴장력을 도입하면서 상기 연속설치된 상기 프리스트레스 합성거더(20)의 상부에 도로포장(16)을 하고 상기 거더(20)의 주위에 설치된 정착장치(40, 50) 및 강연선(42)에 부식방지를 하여 프리스트레스 합성거더 연속교(10)를 설치하는 과정을 단계적으로 보여주는 것이다.       (f) the road pavement on the upper portion of the continuously installed prestressed composite girder 20 while tensioning each of the strands 42 installed in the lower portion of the central portion of the prestressed composite girder 20 to introduce post-tension to the girder 20. 16) shows a step-by-step process of installing the prestressed composite girder continuous bridge (10) by preventing corrosion to the fixing device (40, 50) and the strand (42) installed around the girder (20).

본 시공방법의 특징은The features of this construction method

(1)은 첫째 내측 지점부 또는 첫째 내측 지점부 및 중앙 지점부 상에 일정한 높이로 상향으로 올라간 고임 및 하강장치(60)인 유압잭 또는 스크류 잭 위에 상기 프리스트레스 합성거더(20)를 고임거치하고,     (1) sticks the prestressed composite girder 20 on a hydraulic jack or a screw jack, which is a raising and lowering device 60 which is raised upward at a constant height on the first inner point portion or the first inner point portion and the central point portion,

(2)는 상기 프리스트레스 합성거더의 양측단부 지점부에 설치된 정착구를 강연선으로 서로 연결한 지점부 긴장장치를 이용하여 압축응력을 도입하여 프리스트레스를 합성거더에 도입하고,      (2) introduces the prestress into the composite girder by introducing a compressive stress using a point tension device that is connected to each other by a strand of anchorages installed at both ends of the prestress composite girder;

(3)은 상기 첫째 내측 지점부 또는 첫째 내측 지점부 및 중앙 지점부 상에 연이어서 설치된 프리스트레스 합성거더(20)의 하부에 설치된 상기 고임 및 하강장치인 유압잭 또는 스크류 잭에 변위계(70)를 서로 연결부착 설치하고 상기 고임된 상태의 프리스트레스 합성거더를 하강하면서 상기 변위계(70)를 이용하여 수평을 이루면서 하강하도록 하고,(3) is a displacement meter 70 to the hydraulic jack or screw jack which is the stabilizing and lowering device installed in the lower portion of the prestressed composite girder 20 successively installed on the first inner point portion or the first inner point portion and the center point portion. Installed and attached to the lowered prestressed composite girder in the stagnant state while using the displacement meter 70 to fall horizontally,

(4)는 상기 프리스트레스 합성거더(20)의 중앙부 하부에 설치된 강연선(42)을 각각 긴장하여 거더(20)에 후 긴장력을 도입하는 것이다.     (4) is to tension the strand wire 42 installed in the lower portion of the center portion of the prestress compound girder 20 to introduce a post-tension force to the girder 20, respectively.

상기 일정한 고임량(31)으로 고임된 거더(20)를 다시 고임량 만큼 하강량(30)으로 하여 하강시키는 것은 상기 거더(20)에 유해한 응력인 균열등의 발생을 방지하기 위함이다.The lowering of the girder 20 held at the constant high dose 31 by the high dose lowers the amount 30 so as to prevent occurrence of cracks, which are harmful stresses in the girder 20.

상기의 고임량 만큼 거더를 하강하므로서 혹시 있을 수 있는 내하력의 부족에 대하여는 상기 거더(20) 양측면의 상부 양측단부와 중앙부 하부에 설치된 지점부 긴장장치(40) 및 중앙부 긴장장치(50)에 연결된 강연선(42)을 긴장하여 상기 거더(20)에 긴장력이 도입되도록 하여 내하력을 보강하도록 하기 위한 것이다.     Regarding the lack of load capacity that may be possible by lowering the girder as much as the high dose, the stranded wire connected to the upper part both ends of the girder 20 and the lower side tension device 40 and the central tension device 50 installed on the lower side of the center part. To tension the 42 to introduce a tension force to the girder 20 to reinforce the load capacity.

상기의 지점부 긴장장치(40) 및 중앙부 긴장장치(50)는 상기 연속교(10)가 노후되거나 또는 내하력의 보강이 필요할 경우에 상기 각각의 긴장장치(40,50)에 연결된 강연선(42)을 재긴장하여 교량의 내하력을 보강할 수 있는 보수보강을 위하여 설치한 것이기도 하다.      The point tension device 40 and the center tension device 50 is a strand wire 42 connected to each of the tension device (40, 50) when the continuous bridge (10) is aging or reinforcement of load capacity is required It is also installed to reinforce the bridge to reinforce the load capacity of the bridge.

상기 첫째 내측 지점부 또는 첫째 내측 지점부 및 중앙 지점부에 일정한 고임량(31)으로 고임된 거더(20)를 다시 고임량 만큼을 하강량(30)으로 하여 하강하는 경우, 일반적인 30m경간 연속교를 기준으로 설명하는 경우, 고임량(31)이 150mm가 되도록 들어올려 거치하고, 상기 고임량인 150mm를 다시 하강량(30)으로 하여 하강한 다음 상기 첫째 내측 지점부 또는 첫째 내측 지점부 및 중앙 지점부 상에 설치된 교좌장치(14)에 안착시켜 교량(10)을 설치하는 것이다.    In the case where the girder 20 stuck to the first inner point portion or the first inner point portion and the center point portion at a constant high dose 31 is lowered again by a high dose as a descending amount 30, a typical 30m span continuous bridge In the case of describing the reference, the high wage 31 is lifted and mounted so as to be 150 mm, and the high wage 150 mm is lowered again as the lower amount 30, and then the first inner point part or the first inner point part and the center are lowered. The bridge 10 is installed by seating on the bridge device 14 installed on the branch.

도 3은 도 2의 A단면을 상세히 보여주는 도면으로서, 상기 첫째 내측 지점부 또는 첫째 내측 지점부 및 중앙 지점부 상에 일정한 고임량(31)으로 들어올려져 연이어서 설치된 거더(20)를 하강할 때 상기 거더의 하부에 각각 설치된 고임 및 하강장치(60)인 유압잭 또는 스크류 잭에 복수개 이상의 변위 측정 수평프레임(71)을 상하로 설치한 것으로서, 상기 변위 측정 수평프레임(71)의 중앙부에 수포(72)가 형성되어 있다.3 is a view showing the cross-section A of FIG. 2 in detail, when lowering the girder 20 successively installed on the first inner point portion or the first inner point portion and the central point portion by being raised at a constant high dose 31. A plurality of displacement measuring horizontal frames 71 are installed vertically in a hydraulic jack or a screw jack, which are respectively a spool and a lowering device 60 installed at the lower part of the girder, and a blister 72 is formed at the center of the horizontal displacement measuring frame 71. ) Is formed.

상기의 거더(20)를 고임량(31) 만큼 하강할 때 순차적으로 상기 고임 및 하강량 장치(60)인 유압잭 또는 스크류 잭을 하강하면서 상기 거더(20)가 수평을 이루면서 하강하도록 하는데 이때 상기 고임 및 하강장치(60)에 편차등이 발생되어 상기 거더(20) 편차에 따른 변위등이 발생될 우려가 있으므로 이때 상기 변위계(70)인 상기 변위 측정 수평프레임(71)에 설치된 수포(72)가 중앙부에 위치하는 지를 지속적으로 관찰하면서 상기 거더(20)를 하강하도록 하여 상기 거더(20)의 편차에 따른 편차변위의 발생을 방지하기 위함이다.    When the girder 20 is lowered by the high dose 31, the girder 20 is lowered horizontally while descending the hydraulic jack or the screw jack, which are the high and low amount devices 60, in this case. And because there is a possibility that the deviation is generated in the lowering device 60, the displacement and the like according to the deviation of the girder 20, the blister 72 installed in the displacement measuring horizontal frame 71, which is the displacement meter 70 is This is to prevent the occurrence of the deviation displacement due to the deviation of the girder 20 by continuously descending the girder 20 while observing whether it is located in the center.

이때 상기 변위 측정 수평프레임(71)이 복수개로 상기 고임 및 하강장치(60)의 측면에 부착되어 수평을 확인할 수 있도록 하는데 복수개로 확인을 하게되면은 한 개로 실시 하였을때보다 수평을 확인하는데 보다 정밀하게 확인을 할 수 있기 때문이다.At this time, the displacement measuring horizontal frame 71 is attached to the side of the pulley and the lowering device 60 in plural numbers to check the horizontality. Because it can be confirmed.

상기 변위 측정 수평프레임(71)의 중앙부에 설치된 수포(72)는 측량시 측량기가 수평을 이루고 있는지의 여부를 확인할 때 사용하는 것으로서 만약 측량기가 수평을 이루고 있을 경우에는 수포(72)가 중앙에 위치하게되므로 이를 확인한 후에 측량을 실시하게 되는 것이다. 이러한 현상을 연속교(10)의 시공에도 적용하도록 하는 것으로서 상기 고임 및 하강 장치(60)가 수평을 이루고 하강할때에는 상기 변위 측정 수평프레임(71)에 설치된 수포(72)가 중앙에 위치하게되므로 하강작업을 계속하게되는 것이다.        The blister 72 installed at the center of the displacement measuring horizontal frame 71 is used to check whether the instrument is horizontal when surveying. If the instrument is horizontal, the blister 72 is positioned at the center. The survey will be conducted after confirming this. This phenomenon is to be applied to the construction of the continuous bridge 10, when the lowering and lowering device 60 is horizontal and lowered, since the blister 72 installed in the displacement measuring horizontal frame 71 is positioned at the center. The descent work will continue.

도 4는 도 2의 A 단면에 설치된 변위계의 또 다른 실시예를 보여주는 도면으로서, 상기 첫째 내측 지점부 또는 첫째 내측지점부 및 중앙 지점부 상에 연이어서 설치된 상기 거더(20) 하부에 각각 고임 및 하강장치(60)를 설치하고 상기 고임 및 하강장치와의 사이에 상하로 복수개의 횡방향 스케일(82)을 결합부(87)에 의하여 연결설치하고, 상기 횡방향 스케일(82)과 접하게 복수개의 수직 스케일(81)을 상기 첫째 내측 지점부 또는 첫째 내측 지점 부 및 중앙 지점부 상에 수직으로 고정설치한 변위계(70)인 것이다.       Figure 4 is a view showing another embodiment of the displacement meter installed in the cross-section A of Figure 2, the first inner point portion or the first inner point portion and the central point portion on the girder 20 successively installed on the central point portion, respectively, A lowering device 60 is installed, and a plurality of horizontal scales 82 are connected to each other by the coupling portion 87 in the vertical direction between the stacking device and the lowering device, and the plurality of horizontal scales 82 are in contact with the horizontal scales 82. The vertical scale 81 is a displacement meter 70 fixedly installed on the first inner point portion or the first inner point portion and the center point portion.

도 5는 도 4의 변위계의 횡방향 및 수직 스케일의 설치방법을 보여주는 도면으로서, 상기 도 4에서 설명한 바와 같이 상기 첫째 내측 지점부 또는 첫째 내측 지점부 및 중앙 지점부 상에 설치된 고임 및 하강장치(60) 사이에 일정한 간격으로 복수개의 수직 스케일(81)을 설치하고 상기 수직으로 설치된 수직 스케일(81)과 상하로 일정한 간격을 두고 직교하도록 한 횡방향 스케일(82)을 설치하고 상기 횡방향 스케일(82)의 양측단부에 중앙부에 구멍(85)이 형성된 일정한 크기의 결합철편(86)을 형성하도록 한 변위계(70)이다.       5 is a view showing a horizontal and vertical scale installation method of the displacement meter of Figure 4, as described in Figure 4 above the first inner point portion or the first inner point portion and the centering portion installed on the lower point ( 60, a plurality of vertical scales 81 are installed at regular intervals, and a horizontal scale 82 is provided so as to be perpendicular to the vertically installed vertical scale 81 at regular intervals up and down. It is a displacement meter 70 which forms the coupling iron piece 86 of fixed size in which the hole 85 was formed in the center part in the both end parts of 82.

상기 횡방향 스케일(82)의 양측단부에 설치된 결합철편(86)을 후술하는 도 6의 고임 및 하강장치(60)의 상하부에 설치된 날개부(83)에 볼트너트 연결을 하던지 용접을 하여 연결설치하는 것이다.      The bolted connection or welding is performed by connecting bolts 86 to the upper and lower portions of the spooling and lowering device 60 of FIG. 6, which will be described later, with the coupling iron piece 86 provided at both ends of the lateral scale 82. It is.

상기 수직 및 횡방향 스케일(81,82)의 전체면에는 일정한 간격으로 눈금(84)이 형성되어 있어 상기 눈금을 이용하여 하강량을 일정하게하여 하강량이 서로 다르게되어 발생되는 빔의 편측변위를 방지하기 위함이다.      Scales 84 are formed on the entire surface of the vertical and lateral scales 81 and 82 at regular intervals to prevent the unilateral displacement of the beam caused by varying the falling amounts by using the graduations to be constant. To do this.

도 6은 본 발명의 고임 및 하강장치를 상세히 보여주는 도면으로서, 첫째 내측 지점부 또는 첫째 내측 지점부 및 중앙 지점부 상부에 설치되는 부분과 상부의 거더(20)의 하부에 밀착되어 설치되는 부분으로 구성되고, 상기 두 부분의 사이에 유압 또는 스크류에 의하여 상하로 움직이는 가동부가 형성된 것으로서, 상기 두 부분의 측면에 일정한 크기의 날개부(83)가 형성되되 상기 날개부(83)의 중앙에 구멍(84)을 형성하고, 상기 거더(20)의 하부면에 밀착되어 설치되는 부분에는 방충패드(73)가 설치되어 있어 상기 고임 및 하강장치(60)가 거더(20)에 밀착되어 하강시 거더(20)의 자중에 따른 충격등을 흡수할 수 있도록 설치한 것이다.Figure 6 is a view showing in detail the pooling and lowering device of the present invention, the first inner point portion or the first inner point portion and the portion installed in the upper portion of the upper portion and the central girder 20 in close contact with the portion installed It is configured, and the movable part is moved up and down by the hydraulic or screw between the two parts, the wing portion 83 of a predetermined size is formed on the side of the two portions, but the hole in the center of the wing portion 83 ( 84 is formed, and the portion that is installed in close contact with the lower surface of the girder 20 is provided with a insect repellent pad 73 so that the stiffening and lowering device 60 is in close contact with the girder 20 to lower the girder ( 20) It is installed to absorb the impact light due to its own weight.

도 7은 본 발명의 고임 및 하강장치를 내측 지점부 위에 설치한 것을 평면으로 보여주는 도면으로서, 첫째 내측 지점부 또는 첫째 내측 지점부 및 중앙 지점부 상부면에 도면에서 보는바와 같이 상기 고임 및 하강장치(60)를 네방향으로 설치하고 이들을 서로 변위계(70)로 연결하여 설치한 다음 상기 고임 및 하강장치(60)를 이용하여 상기 거더(20)를 하강하는 것이다.     7 is a plan view showing the installation and the lowering device of the present invention on the inner point portion in a plan view, as shown in the drawing on the upper surface of the first inner point portion or the first inner point portion and the central point portion as shown in the figure; Install the 60 in four directions and install them by connecting to each other with a displacement meter 70 and then to lower the girder 20 by using the pool and lowering device (60).

상기의 고임 및 하강장치(60)는 첫째 내측 지점부 또는 첫째 내측 지점부 및 중앙 지점부의 상부에 설치하도록 거더(20)의 하부에 밀착 설치하는 것으로서, 거더(20)가 설치되는 하부에 본 도에서와 같이 설치하게 된다.     Said hoisting and lowering device 60 is to be installed in close contact with the lower part of the girder 20 so that it may be installed in the upper part of a 1st inner point part or a 1st inner point part, and a center point part, and is shown in the lower part in which the girder 20 is installed. You will install it as in

상기 고임 및 하강장치(60)를 보여주는 도면이 스크류 잭을 예로 들어 설명하였으나 이외에도 유압잭 및 지렛대를 이용한 잭(도시생략)도 아울러 사용할 수 있음도 밝혀두는 바이며 또한 상기의 모든 종류의 고임 및 하강장치(60)에 적용한 본 발명에서 언급하고 있는 모든 종류의 변위계(70)를 적용 활용할 수 있음도 아울러 밝혀두는 바이다.     Although the drawing showing the pooling and lowering device 60 has been described using a screw jack as an example, it is also apparent that a jack using a hydraulic jack and a lever (not shown) can also be used as well as all types of pooling and lowering devices described above. It is also clear that all kinds of displacement meters 70 mentioned in the present invention applied to (60) can be applied and utilized.

상기 도4, 도 5에서 언급하고 있는 고임 및 하강장치(60)와 연결하는 방법은 상기 도 3에서 변위 측정 수평 프레임(71)을 상하로 일정한 간격을 두고 상기 고임 및 하강장치(60)와 연결하는 방법에서도 적용할 수 있다.     4 and 5, the method of connecting with the stool and lowering device 60 is connected to the stool and lowering device 60 at regular intervals up and down the displacement measuring horizontal frame 71 in FIG. It can also be applied to the method.

또한, 상기 변위계(70)는 기계적인 장치인 것인 반면에 컴퓨터를 이용하여 상기 고임 및 하강장치(60)에 센서를 설치하고 상기 센서를 컴퓨터에 연결하면서 상기 고임 및 하강장치(60)인 유압잭 또는 스크류 잭에 연결하여 컴퓨터에 이미 프로그램으로 저장시켜 놓은 하강 프로그램을 이용하여 상기 빔(20)의 하강량을 조절하면서 상기 거더(20)에 변위가 발생되지 않도록 수평을 이루도록 상기 컴퓨터의 프로그램과 유압잭의 유압량 또는 스크류 잭의 하강량을 조절하면서 하강하도록 하는 컴퓨터를 이용하는 방법을 사용할 수도 있음을 밝혀두는 바이다.    In addition, while the displacement meter 70 is a mechanical device, a hydraulic jack which is the clamping device and the lowering device 60 while installing a sensor on the pooling and lowering device 60 using a computer and connecting the sensor to the computer. Alternatively, the program and the hydraulic jack of the computer to be horizontal so that displacement is not generated in the girder 20 while adjusting the amount of falling of the beam 20 by using a falling program that is already stored as a program in the computer by connecting to a screw jack. It is to be noted that a computer-based method of lowering while adjusting the hydraulic pressure of the screw jack or the lowering amount of the screw jack may be used.

도 8(a)(b)(c)(d)(e)는 본 발명의 부분 다운 공정을 다경간에 적용하였을 때 발생되는 모멘트 분포를 보여주는 도면으로서, 본 도에서는 5경간 연속교를 예로 들어 설명하였으나 본 발명은 2경간이상의 모든 연속교에 적용할 수 있는 기술인 것이다. 8 (a) (b) (c) (d) (e) illustrate moment distributions generated when the partial down process of the present invention is applied to multiple spans. In this figure, a five span continuous bridge is described as an example. However, the present invention is a technique that can be applied to all continuous bridges of more than two spans.

도 10(a)(b)는 본 발명의 부분다운 공정의 또 다른 실시예인 중앙부 교각에서 행하고 강연선과 같은 PS 강재에 의한 단계별 긴장을 부분적으로 시행하여 발생된 모멘트를 보여주는 도면으로서, (a)는 중앙부 교각에서 다운 공정을 실시하여 모멘트가 발생된 것이며, (b)는 중앙부 교각에서 다운공정을 실시하고 단계별 긴장을 실시할 때 부분적으로 발생되는 부분 스트레싱의 위치를 보여주는 것이다.       Figure 10 (a) (b) is a view showing the moment generated by partially performing step tension by a PS steel, such as a strand, in a central pier which is another embodiment of the partial down process of the present invention, (a) is Moment is generated by performing the down process in the center piers, and (b) shows the location of the partial stresses that occur when the down process is performed in the middle piers and stepwise tension is applied.

도 11은 본 발명의 부분다운 공정의 또 다른 실시예인 내부교각에서의 다운 크기를 서로 다르게 하여 부등다운 시키므로서 발생된 모멘트를 보여주는 도면으로서, 내측교각과 외측교각의 다운크기를 서로 다르게 한 것이다.        FIG. 11 is a view illustrating a moment generated by varying down sizes in the inner piers, which is another embodiment of the partial down process of the present invention, to differently down, and different down sizes of the inner piers and the outer piers.

상기의 도 2에서 이미 설명한 본 발명의 연속교 설치단계를 본 도의 모멘트 분포도와 연계하여 설명하면 다음과 같다.      Referring to the step of installing the continuous bridge of the present invention already described in FIG. 2 in connection with the moment distribution diagram of the present invention is as follows.

(a)는 종래에 사용되고 있는 프리스트레스가 도입되는 피에스씨빔 혹은 강합성 거더교를 제작하여 상기 첫째 내측 지점부 또는 첫째 내측 지점부 및 중앙 지점부 상에 일정한 높이로 고임거치하고, 상기 프리스트레스 합성거더(20)의 연속부에 콘크리트를 타설양생하여 연결부(15)를 형성 및 바닥판을 타설하고 인접하여 설치된 상기 프리스트레스 합성거더의 양측단부 지점부에 설치된 정착구의 강연선을 긴장하여 상기 합성거더에 압축력을 도입하고, 상기 변위게에 의한 편측변위가 발생되지 않도록 하면서 상기 프리스트레스 합성거더(20)를 하강하여 교좌장치(14)에 안착시키고, 상기 프리스트레스 합성거더(20)의 중앙부 하부에 설치된 강연선(42)을 각각 긴장하여 거더(20)에 후 긴장력을 도입하여 설치한 프리스트레스 합성거더 연속교(10)를 보여주는 것이며,           (a) fabricates a PSC beam or a composite girder bridge into which prestresses used in the prior art are introduced, and are high-mounted on the first inner point portion or the first inner point portion and the center point portion, and the prestressed composite girder ( Placing concrete on the continuous part of 20) forms the connecting part 15, and casts the bottom plate, and tensions the strand of the anchorages installed at both end portions of the prestressed composite girder adjacent to each other and introduces a compressive force to the composite girder. The prestressed composite girder 20 is lowered and seated on the seating device 14 while preventing the unilateral displacement caused by the displacement cradle, and the stranded wire 42 provided below the central portion of the prestressed composite girder 20 is mounted. Showing the prestressed composite girder continuous bridge 10 installed by introducing the after-tension force to the girder 20 by each tension. Will be

(b)는 상기 순서에 의하여 설치된 연속교에 설계하중 모멘트 분포도를 보여주는 것이며,           (b) shows the design load moment distribution on the continuous bridge installed according to the above procedure,

(c)는 상기 거더에 도입된 프리스트레스 분포도를 보여주는 것이며,            (c) shows the prestress distribution diagram introduced into the girder,

(d)는 종래 기술과 다르게 첫 번째 내측 지점부 또는 첫 번째 내측 지점부 및 중앙 지점부 상에 만 거더에 고임을 실시하고 고임량 만큼만 다운(Down)시켜서(본도의 화살표가 다운(Down)공정을 의미함) 발생된 모멘트 분포도이다.           (d) differently from the prior art, by holding the girder on the first inner point or the first inner point and the center point and down only by the high dose (the arrow of the main figure is down). Moment distribution).

여기서 첫 번째 내측 지점부에만 설치된 거더의 고임을 하강하는 이유는 종래 모든 지점에 설치된 거더를 다운시키는 것과 비교해서 본 도의 모멘트도에서와 같이 그 성향이 전 교각을 다운했을때와 유사하나 첫 번째 내측교각에서는 그 크기가 2배이상 커서 효과적이며 ( Mb<<Md), 중앙부 내측교각이 추가로 침하되어도 부분다운 공정과 강연선과 같은 PS 강선을 긴장하므로서 중첩효과에 의해서, 지점부에서는 정모멘트가 중앙부에서는 부모멘트를 유발시켜 설계하중을 상쇄시킬 수 있는 매우 효과적인 공정임을 알 수 있다.           Here, the reason for lowering the girder of the girders installed only in the first inner point part is similar to when the entire piers are down as in the moment diagram of this figure, compared to bringing down the girders installed in all conventional points. It is more than twice as big in piers (Mb << Md), and even if the inner inner piers are subsided, the moment of tension is overlapped by the overlapping effect by tensioning the PS steel wires such as the partial down process and the strand. It can be seen that is a very effective process to offset the design load by inducing parental moment.

(e)는 상기 거더의 중앙부에 설치된 정착구에 연결된 강연선인 피에스 강재중 최초에 제작시 긴장되지 않은 강연선을 후긴장하여 상부 구조물에 프리스트레스를 추가로 도입하여 발생된 모멘트를 보여주는 것이다.         (e) shows the moment generated by additionally introducing prestress into the upper structure by stretching the unstrained strand in the first steel manufacture, which is a strand steel connected to the anchorage installed in the center of the girder.

따라서 본 발명의 기술을 이용하면 종래 기술에서 나타난 Ma, Mc와 같은 문제점을 부분다운 공정에 의한 Md와 단계별 강연선과 같은 PS 강재의 긴장을 통한 효과에 의해서 제거시킬 수 있는 장점이 있는 것이다. Therefore, the use of the technique of the present invention has the advantage that can be eliminated by the effects through the tension of the PS steel, such as Md and stepped strand by the step down process Ma, Mc such as shown in the prior art.

이상과 같이 피에스 강재인 강연선의 긴장과 부분적인 다운 공정에 의한 단계적으로 도입하는 프리스트레싱 공법을 적용한 결과는 종래의 기술에 비해서 간편한 시공성과 내구성 향상으로 경제적이며 우수한 연속교를 건설할 수 있다는 것을 보여주는 것이다. As described above, the result of applying the prestressing method introduced stepwise by the tension and partial down process of the steel strand of the PS steel shows that it is possible to construct an economical and excellent continuous bridge by simple construction and improved durability compared to the conventional technology.

본 발명은 프리스트레스 합성거더를 이용하여 2경간이상의 다경간 연속교를 시공하는 방법에 관한 것으로서, 첫째 내측 지점부 또는 첫째 내측 지점부 및 중앙 지점부 상에 일정한 높이의 고임량 만큼 거치된 빔을 상기의 고임량 만큼 만 하강하므로서 거더에 유해한 응력의 발생을 방지하면서 상기 거더에 설치된 강연선을 긴장하여 빔에 긴장력이 도입되도록 하여 연속교의 교량 설치공사의 공정을 줄여 시공성을 용이하게 하면서 공사비를 절감하고, 상기 거더의 하강시 하강에따른 빔의 편측처짐을 방지하기 위하여 변위계를 설치하여 교량시공시 빔에 유해한 응력이 발생되지 않도록 정밀한 시공을 할 수 있도록 품질관리장치인 변위계를 설치하며, 또한 상기 연속교가 노후되거나 또는 내하력의 보강이 필요할 경우에 상기의 빔에 설치된 상기 긴장장치를 재긴장하여 교량의 내하력을 보강하도록 하는 경제적이면서 교량 시공시 교량의 계획된 내구연한을 지킬 수 있도록 품질을 철저하게 관리하면서 교량의 노후 및 내하력의 보강이 요구될때에도 보수보강을 용이하게 할 수 있는 매우 효율적인 연속교의 시공방법인 것이다.The present invention relates to a method for constructing a multi-span continuous bridge of two spans or more using a prestressed composite girder, wherein the beam mounted on the first inner point portion or the first inner point portion and the center point portion by a high dose of a predetermined height is It reduces the construction cost by facilitating the construction process by reducing the process of bridge installation work of continuous bridges by tensioning the stranded wire installed in the girder while preventing the occurrence of harmful stress on the girder while reducing only the high dose of In order to prevent the lateral deflection of the beam due to the descending of the girder, by installing a displacement meter, a displacement gauge, which is a quality control device, is installed so that precise construction is performed so that no harmful stress is generated in the beam during bridge construction. The long installed in the beam in case of aging or when reinforcement of load capacity is needed It is an economical way to reinforce the device to reinforce the load capacity of the bridge, and it is easy to reinforce the reinforcement even when the retirement and load capacity of the bridge is required while maintaining the quality of the bridge to keep the bridge's planned durability. It is a very efficient method of constructing a continuous bridge.

도 1 (a),(b),(c),(d),(e),(f)는 종래의 기술인 가지점 상승 및 하강을 이용한 피에스씨빔 연속교 시공을 단계적으로 보여주는 도면.1 (a), (b), (c), (d), (e), (f) is a diagram showing a step-by-step CS bridge construction using a conventional branch point rise and fall.

도 2 (a),(b),(c),(d),(e),(f)는 본 발명의 부분 다운(Down) 공정을 이용하여 단계적으로 연속교를 시공하는 방법을 보여주는 도면.     Figure 2 (a), (b), (c), (d), (e), (f) is a view showing a method for constructing a continuous bridge in stages using the partial down process of the present invention.

도 3은 도 2의 A단면을 상세히 보여주는 도면.     3 is a view showing a section A of FIG. 2 in detail;

도 4는 도 2의 A 단면에 설치된 변위계의 또 다른 실시예를 보여주는 도면.     4 is a view showing yet another embodiment of a displacement meter installed in section A of FIG.

도 5는 도 4의 변위계의 횡방향 및 수직 스케일의 설치방법을 보여주는 도면.     5 is a view showing the installation method of the transverse and vertical scale of the displacement meter of FIG.

도 6은 본 발명의 고임 및 하강장치를 상세히 보여주는 도면.     Figure 6 is a view showing in detail the pooling and lowering device of the present invention.

도 7은 본 발명의 고임 및 하강장치를 내측 지점부 위에 설치한 것을 평면으로 보여주는 도면.     Figure 7 is a plan view showing the installation and the lowering device of the present invention on the inner point portion.

도 8(a)(b)(c)(d)(e)는 본 발명의 부분 다운 공정을 다경간에 적용하였을 때 발생되는 모멘트를 보여주는 도면.8 (a) (b) (c) (d) (e) show moments generated when the partial down process of the present invention is applied over multiple spans.

도 9(a)(b)(c)는 또 다른 종래기술인 다경간 연속교에서 발생되는 모멘트를 보여주는 모멘트 분포도. Figure 9 (a) (b) (c) is a moment distribution diagram showing the moment generated in another conventional multi-span continuous bridge.

도 10(a)(b)는 본 발명의 부분다운 공정의 또 다른 실시예인 중앙부교각에서 다은공정을 실시하고 강연선에 의한 단계별 긴장을 부분적으로 하여 발생된 모멘트를 보여주는 도면.     Figure 10 (a) (b) is a view showing the moment generated by performing the next step in the central pier is another embodiment of the partial down process of the present invention and partially tensioned step by the strand.

도 11은 본 발명의 부분다운 공정의 도 다른 실시예인 내부교각에서 다운크기를 서로 다르게 한 부등다운에 의하여 발생된 모멘트를 보여주는 도면.     FIG. 11 is a view showing a moment generated by uneven down with different down sizes in an inner piers, another embodiment of the partial down process of the present invention. FIG.

<도면의 주요부분에 대한 부호의 설명><Description of the symbols for the main parts of the drawings>

10 : 프리스트레스 합성거더 연속교 11 : 외측 지점부        10: prestressed composite girder continuous bridge 11: outer point

12 : 내측 지점부 13 : 바닥판        12: inner branch portion 13: bottom plate

14 : 교좌장치 15 : 연결부        14: teaching device 15: connection portion

16 : 아스콘 포장         16: ascon packaging

20 ; 프리스트레스 합성거더         20; Prestressed Composite Girder

30 ; 하강량 31 : 고임량         30; Lowering amount 31: High wage

40 : 지점부 긴장장치 41 : 정착구        40: branch tension device 41: anchorage

42 : 강연선        42: stranded wire

50 : 중앙부 긴장장치         50: central tension device

60 : 고임 및 하강장치         60: pulling and lowering device

70 : 변위계 71 : 변위측정 수평프레임        70: displacement meter 71: displacement measurement horizontal frame

72 : 수포 73 : 방충패드        72: blister 73: insect repellent pad

81 : 수직 스케일 82 : 횡방향 스케일        81: vertical scale 82: lateral scale

83 : 날개부 84 : 눈금        83: wing 84: scale

85 : 구멍 86 : 결합철편        85: hole 86: bonded iron piece

100 : 피에스씨빔 101 : 지점부        100: PS seabeam 101: Branch part

102 : 중앙 지점부 103 : 교좌장치        102: central point portion 103: the chair device

110 : 피에스씨빔 111 : 가지점        110: PS seabeam 111: branch

112 : 고임량 113 : 상승량        112: high wage 113: increase

114 : 하강량 115 : 연결부         114: descending amount 115: connecting portion

116 : 바닥판        116: bottom plate

Claims (17)

다경간 연속교의 지점부 상에 일정한 높이로 상향으로 올라간 고임 및 하강장치(60) 위에 상기 프리스트레스 합성거더(20)를 거치하고, 상기 내측 지점부(12)에 연이어서 일정하게 고임된 상태로 설치된 상기 프리스트레스 합성거더(20)를 철근 및 강판을 이용하여 연결하고 콘크리트를 타설양생하여 연결부(15)를 형성하고, 상기 연속된 프리스트레스 합성거더(20)의 상부에 바닥판(13)을 타설하면서 상기 거더(20)와 거더(20)를 서로 연결하는 가로보를 설치하여 시공된 연속교에 있어서,The prestressed composite girder 20 is mounted on the spool and the lowering device 60 that is upwardly raised to a certain height on the point portion of the multi-span continuous bridge, and is installed in a state in which it is fixedly connected to the inner point portion 12 in succession. The prestressed composite girder 20 is connected by using reinforcing bars and steel sheets, and concrete is poured to form a connecting portion 15, and the bottom plate 13 is placed on top of the continuous prestressed composite girder 20. In the continuous bridge constructed by installing a cross beam connecting the girder 20 and the girder 20 to each other, 상기 내측 지점부(12)상에 인접하여 설치된 상기 프리스트레스 합성거더(20)의 상부 양측단부 지점부에 설치된 정착구(41)를 강연선(42)으로 서로 연결한 지점부 긴장장치에 긴장력을 도입하고, 5경간까지 또는 5경간 이상, 즉 6경간 부터의 다경간 교량중 홀수의 경간을 갖는 교량의 첫 번째 내측 지점부 또는 6경간이상의 교량 중에서 짝수의 경간인 경우에는 첫 번째 내측 지점부 및 중앙 지점부 상에 설치된 상기 고임 및 하강장치(60)에 복수개 이상의 변위 측정 수평프레임(71)을 상하로 연결설치하고, 상기 변위 측정 수평프레임(71)의 중앙부에 수포(72)가 형성된 변위계를 설치하고, 상기 첫째 내측 지점부 또는 첫째 내측 지점부 및 중앙 지점부 상에 상기 변위계가 설치된 고임 및 하강장치에 의하여 일정한 고임량(31) 만큼 들어올려져 설치된 상기 거더를 상기 고임량 만큼만 하강량(30)으로 부분다운하여 교좌장치(14)에 안착시키고, 상기 프리스트레스 합성거더(20)의 중앙부 하부에 설치된 중앙부 긴장장치(50)에 연결된 강연선(42)을 각각 긴장하여 교량 상부 구조물에 프리스트레스를 도입하여 설치한 연속교인 것에 특징이 있는 시공단계별로 프리스트레스를 도입하는 피에스씨 강재와 부분적인 다운공정을 통해서 상부 구조물에 압축응력을 도입하여 설치되는 프리스트레스 합성거더 연속교.    Tension force is introduced into the point tension device which is connected to each other by the strand 42, the fixing unit 41 provided on the upper both side end points of the prestress compound girder 20 installed adjacent to the inner point portion 12, The first inner point and center point of the first inner point of a bridge with odd spans of up to five spans or more than five spans, ie from six spans, or of even spans of six or more spans. Connecting a plurality of displacement measuring horizontal frame (71) up and down in the spool and lowering device (60) installed on the top, and install a displacement meter formed with a blister 72 in the center of the displacement measuring horizontal frame (71), The girders are lifted up by a predetermined high wage amount 31 by the high and low tension devices provided with the displacement meter on the first inside point or the first inside point and the center point. Partly down to the amount of descending only 30 as the high dose to be seated on the seating device 14, the tension wire 42 connected to the central tension device 50 installed in the lower center of the prestress composite girder 20, respectively, Prestressed composite girder continuous bridge that is installed by introducing compressive stress to the upper structure through partial down process and PS steel that introduces prestress for each construction stage, which is characterized by being a continuous bridge installed by introducing prestress to the upper structure of the bridge. 제1항에 있어서,       The method of claim 1, 상기 부분다운을 중앙부 교각에서 실시하고, 강연선을 이용하여 단계별긴장를 부분적으로 실시하는 것에 특징이 있는 시공단계별로 프리스트레스를 도입하는 피에스씨 강재와 부분적인 다운공정을 통해서 상부 구조물에 압축응력을 도입하여 설치되는 프리스트레스 합성거더 연속교.       The partial down is carried out in the central piers, and the ps-steel is introduced to the pre-stress according to the construction stage, which is characterized by partial tensioning using the strand, and the compressive stress is introduced into the upper structure through the partial down process. Prestressed composite girder continuous bridge. 제 1항에 있어서,       The method of claim 1, 상기 부분다운시 내부교각에서의 다운크기를 서로다르게 한 부등다운인 것에 특징이 있는 시공단계별로 프리스트레스를 도입하는 피에스씨 강재와 부분적인 다운공정을 통해서 상부 구조물에 압축응력을 도입하여 설치되는 프리스트레스 합성거더 연속교.        Pre-stressed composite that is installed by introducing compressive stress to the upper structure through partial down process with PS steel that introduces prestress for each construction stage characterized by uneven down with different down sizes in inner piers during partial down Girder continuous bridge. 제 1항에 있어서,The method of claim 1, 상기 변위계는 내측 지점부(12)상에 설치된 고임 및 하강장치(60) 사이에 일정한 간격으로 수직으로 설치된 복수개의 수직 스케일(81)의 몸체에 일정한 간격으로 눈금이 형성되고, 상기 수직으로 설치된 수직 스케일(81)과 상하로 일정한 간격을 두고 직교하도록 한 횡방향 스케일(82)을 설치하고, 상기 횡방향 스케일(82)의 양측단부에 일정한 크기의 결합철편(86)을 형성하고 상기 결합철편(86)과 상기 고임 및 하강장치(60)에 설치된 날개부(83)와 서로 볼트너트 연결 또는 용접연결하도록 한 것에 특징이 있는 시공단계별로 프리스트레스를 도입하는 피에스씨 강재와 부분적인 다운공정을 통해서 상부 구조물에 압축응력을 도입하여 설치되는 프리스트레스 합성거더 연속교.      The displacement meter is formed on the body of a plurality of vertical scales 81 vertically installed at regular intervals between the spool and lowering device 60 installed on the inner point portion 12, the vertically installed vertically A horizontal scale 82 is provided so as to be perpendicular to the scale 81 at regular intervals up and down, and a coupling iron piece 86 having a constant size is formed at both ends of the horizontal scale 82, and the coupling iron piece ( 86) and the upper portion through the partial down process with the PS steel to introduce the pre-stress by the construction stage, characterized in that the bolt portion or the bolt portion connected to each other and the welding portion 83 installed in the spool and lowering device 60 Prestressed composite girder continuous bridge installed by introducing compressive stress into the structure. 제 4항에 있어서,       The method of claim 4, wherein 상기 수직 및 횡방향 스케일의 몸체에 수포가 형성되어 있으며, 전체면에는 일정한 간격으로 눈금(84)이 형성되어 있는 것에 특징이 있는 시공단계별로 프리스트레스를 도입하는 피에스씨 강재와 부분적인 다운공정을 통해서 상부 구조물에 압축응력을 도입하여 설치되는 프리스트레스 합성거더 연속교.        The blister is formed on the body of the vertical and horizontal scales, and the entire surface is subjected to the PS steel and the partial down process to introduce the prestress for each construction step, characterized in that the graduations 84 are formed at regular intervals. Prestressed composite girder continuous bridge installed by introducing compressive stress to the superstructure. 제 1항 또는 제 4항에 있어서,       The method according to claim 1 or 4, 상기 변위계는 상기 고임 및 하강장치(60)에 센서를 설치하고, 상기 센서를 컴퓨터에 연결하면서 상기 고임 및 하강장치에 연결하여 컴퓨터에 이미 프로그램으로 저장시켜 놓은 하강 프로그램을 이용하여 상기 거더의 하강량을 조절하면서 상기 거더에 변위가 발생되지 않도록 상기 컴퓨터의 프로그램을 이용하여 유압잭의 유압량 또는 스크류 잭의 하강량을 조절하면서 하강하도록 하는 것에 특징이 있는 시공단계별로 프리스트레스를 도입하는 피에스씨 강재와 부분적인 다운공정을 통해서 상부 구조물에 압축응력을 도입하여 설치되는 프리스트레스 합성거더 연속교.        The displacement meter installs a sensor in the pooling and lowering device 60, and connects the sensor to a computer, and connects the sensor to the pooling and lowering device, and lowers the amount of the girder by using a lowering program already stored in a computer. Part of the CS steel and the introduction of pre-stress for each construction stage characterized in that the lowering by adjusting the hydraulic amount of the hydraulic jack or the lowering amount of the screw jack by using the program of the computer so that the displacement does not occur in the girder while adjusting the Prestressed composite girder continuous bridge that is installed by introducing compressive stress to the upper structure through the normal down process. 프리스트레스가 도입되는 피에스씨 빔 혹은 강합성 거더로 이루어진 프리스트레스 합성거더를 서로 연결하여 다경간 연속교를 설치하는 시공방법에 있어서, In the construction method in which a multi-span continuous bridge is installed by connecting prestressed composite girders composed of PS beams or steel composite girders into which prestresses are introduced, (a) 정정 구조물인 종래의 프리스트레스 합성거더(20)를 제작하는 단계;         (a) manufacturing a conventional prestressed composite girder 20 which is a correction structure; (b) 상기 제작된 프리스트레스 합성거더(20)를 양측의 외측 지점부(11)와 내측 지점부(12)에 상기 거더를 거치하면서 5경간까지 또는 5경간 이상, 즉 6경간 부터의 교량중 홀수의 경간을 갖는 교량의 첫 번째 내측 지점부 또는 6경간이상의 교량 중에서 짝수의 경간인 경우에는 첫 번째 내측 지점부 및 중앙 지점부 상에 일정한 높이로 상향으로 올라간 고임 및 하강장치(60)인 유압잭 또는 스크류 잭 위에 상기 프리스트레스 합성거더(20)를 고임거치하는 단계;       (b) The number of the bridges from up to five spans or more than five spans, i.e., from six spans, while mounting the girder on the outer point portion 11 and the inner point portion 12 of the prepared prestressed composite girder 20 on both sides. In the case of even-numbered span among the first inner point part of the bridge having a span of 6 or more spans, the hydraulic jack which is a swelling and lowering device 60 which rises upward at a constant height on the first inner point part and the center point part or Placing the prestressed composite girder 20 on a screw jack; (c) 상기 첫째 내측 지점부 또는 첫째 내측 지점부 및 중앙 지점부 상에 일정한 높이로 상향으로 고임된 상태로 된 상기 프리스트레스 합성거더(20)의 연속부에 철근 및 강판을 용접설치하고 연속부에 콘크리트로 충전양생하여 연결부(15)를 형성하여 연속교(100)를 형성하는 단계;       (c) welding and installing reinforcing bars and steel sheets in the continuous portion of the prestressed composite girder 20 which is held on the first inner point portion or the first inner point portion and the central point portion at a constant height upward; Filling curing with concrete to form a connecting portion 15 to form a continuous bridge (100); (d) 상기 첫째 내측 지점부 또는 첫째 내측 지점부 및 중앙 지점부 상에 일정한 높이로 상향으로 일정한 고임량(31)으로 들어올려지게 설치된 상기 프리스트레스 합성거더(20)의 상부에 바닥판(13)을 타설하고 인접하여 설치된 상기 프리스트레스 합성거더의 양측단부 지점부에 설치된 정착구를 강연선으로 서로 연결한 지점부 긴장장치를 이용하여 압축응력을 도입하여 프리스트레스를 합성거더에 도입하는 단계;         (d) a bottom plate 13 on top of the prestressed composite girder 20 which is installed to be lifted at a constant height at a constant height upwards on the first inner point portion or the first inner point portion and the central point portion. Introducing a prestress into the composite girder by placing a compressive stress using a point tensioning device connected to each other with a strand by placing anchors installed at both end portions of the prestress composite girder adjacent to each other; (e) 상기의 (d) 단계에서 상기 첫째 내측 지점부 또는 첫째 내측 지점부 및 중앙 지점부 상에 연이어서 설치된 프리스트레스 합성거더(20)의 하부에 각각 설치된 상기 고임 및 하강장치인 유압잭 또는 스크류 잭에 변위계(70)를 서로 연결부착 설치하고 상기 고임된 상태의 프리스트레스 합성거더를 하강하면서 상기 변위계(70)에 설치된 수포(72)를 이용하여 상기 거더(20)가 수평을 이루면서 부분다운하도록 하여 편측변위가 발생하지 않도록 하면서 상기 지점부(12)에 설치된 교좌장치(14)에 안착시키는 단계; 및       (e) Hydraulic jacks or screw jacks, which are the spooling and lowering devices respectively installed in the lower portion of the prestressed composite girder 20 successively installed on the first inner point portion or the first inner point portion and the central point portion in step (d). One side of the girder 20 by horizontally installing the displacement gauges 70 to each other and using the blisters 72 installed on the displacement gauges 70 while lowering the prestressed composite girder in the stagnant state. Seating on a seating device (14) installed in the point portion (12) while preventing displacement; And (f) 상기 프리스트레스 합성거더(20)의 중앙부 하부에 설치된 강연선(42)을 각각 긴장하여 거더(20)에 후 긴장력을 도입하면서 상기 연속설치된 상기 프리스트레스 합성거더(20)의 상부에 도로포장(16)을 하고 상기 거더(20)의 주위에 설치된 정착장치(40, 50) 및 강연선(42)에 부식방지를 하여 프리스트레스 합성거더 연속교(10)를 설치하는 단계로 이루어진 것에 특징이 있는 시공단계별로 프리스트레스를 도입하는 피에스씨 강재와 부분적인 다운공정을 통해서 상부 구조물에 압축응력을 도입하여 설치되는 프리스트레스 합성거더 연속교 시공방법.        (f) pavement 16 on the upper part of the continuously installed prestressed girder 20 while tensioning each of the strands 42 provided on the lower portion of the center of the prestressed girder 20 to introduce post-tension to the girder 20. ) And the pre-stressed composite girder continuous bridge 10 is installed to prevent corrosion of the fixing devices 40 and 50 and the stranded wire 42 installed around the girder 20. Prestress composite girder continuous bridge construction method installed by introducing compressive stress to upper structure through partial down process with PS steel to introduce prestress. 제 7항에 있어서,       The method of claim 7, wherein 상기 변위계는 상기 첫째 내측 지점부 또는 첫째 내측 지점부 및 중앙 지점부 상에 설치된 상기 고임 및 하강장치(60)에 복수개 이상의 변위 측정 수평프레임(71)을 상하로 연결설치한 것으로서, 상기 변위 측정 수평프레임(71)의 중앙부에 수포(72)가 형성되어 있는 것에 특징이 있는 시공단계별로 프리스트레스를 도입하는 피에스씨 강재와 부분적인 다운공정을 통해서 상부 구조물에 압축응력을 도입하여 설치되는 프리스트레스 합성거더 연속교 시공방법.        The displacement meter is provided by connecting a plurality of displacement measuring horizontal frames 71 vertically to the spool and lowering device 60 provided on the first inner point portion or the first inner point portion and the center point portion, wherein the displacement measuring horizontal Continuous prestressed composite girders installed by introducing compressive stress to the upper structure through partial down process and PS steel which introduces prestress for each construction stage characterized by the formation of blister 72 in the center of frame 71 Construction method. 제 7항에 있어서,       The method of claim 7, wherein 상기 변위계는 내측 지점부(12)상에 설치된 고임 및 하강장치(60) 사이에 일정한 간격으로 복수개의 수직 스케일(81)을 수직으로 설치하고, 상기 수직으로 설치된 수직 스케일(81)과 상하로 일정한 간격을 두고 직교하도록 한 횡방향 스케일(82)을 설치하고, 상기 횡방향 스케일(82)의 양측단부에 일정한 크기의 결합철편(86)을 형성하고 상기 결합철편(86)과 상기 고임 및 하강장치(60)에 설치된 날개부(83)와 서로 볼트너트 연결 또는 용접연결하도록 한 변위계인 것에 특징이 있는 시공단계별로 프리스트레스를 도입하는 피에스씨 강재와 부분적인 다운공정을 통해서 상부 구조물에 압축응력을 도입하여 설치되는 프리스트레스 합성거더 연속교 시공방법.        The displacement meter vertically installs a plurality of vertical scales 81 at regular intervals between the spool and the lowering device 60 installed on the inner point portion 12, and is vertically fixed with the vertical scales 81 installed vertically. A horizontal scale 82 provided at right angles at intervals is provided, and coupling iron pieces 86 having a predetermined size are formed at both end portions of the horizontal scale 82, and the coupling iron pieces 86 and the holding and lowering devices are arranged. Compressive stress is introduced into the upper structure through the partial down process with the PS steel which introduces the prestress for each construction stage, which is characterized in that it is a displacement gauge which is connected to the bolt nut or welded to each other and the wing portion 83 installed at (60). Prestressed composite girder continuous bridge construction method installed. 제 9항에 있어서,       The method of claim 9, 상기 수직 및 횡방향 스케일의 전체면에는 일정한 간격으로 눈금(84)이 형성되어 있는 것에 특징이 있는 시공단계별로 프리스트레스를 도입하는 피에스씨 강재와 부분적인 다운공정을 통해서 상부 구조물에 압축응력을 도입하여 설치되는 프리스트레스 합성거더 연속교 시공방법.        Compression stress is introduced into the upper structure through the partial down process with the PS steel which introduces the prestress for each construction step, characterized in that the graduations 84 are formed at regular intervals on the entire surface of the vertical and lateral scales. Prestress composite girder continuous bridge construction method installed. 제 9항 또는 제 10항에 있어서,       The method according to claim 9 or 10, 상기 수직 및 횡방향 스케일의 몸체에 수포(72) 및 일정한 간격의 눈금(84)이 동시에 형성되어 있던지 또는 수포(72)만 설치되어 있는 것에 특징이 있는 시공단계별로 프리스트레스를 도입하는 피에스씨 강재와 부분적인 다운공정을 통해서 상부 구조물에 압축응력을 도입하여 설치되는 프리스트레스 합성거더 연속교 시공방법.        The CS steels for introducing prestresses for each construction step characterized in that both the blister 72 and the regular intervals 84 are formed on the body of the vertical and horizontal scales or only the blister 72 is provided. Prestress composite girder continuous bridge construction method is installed by introducing compressive stress to the upper structure through partial down process. 제 7항에 있어서,       The method of claim 7, wherein 상기 변위계는 상기 고임 및 하강장치(60)에 센서를 설치하고, 상기 센서를 컴퓨터에 연결하면서 상기 고임 및 하강장치에 연결하여 컴퓨터에 이미 프로그램으로 저장시켜 놓은 하강 프로그램을 이용하여 상기 거더의 하강량을 조절하면서 상기 거더에 변위가 발생되지 않도록 상기 컴퓨터의 프로그램을 이용하여 유압잭의 유압량 또는 스크류 잭의 하강량을 조절하면서 하강하도록 하는 것에 특징이 있는 시공단계별로 프리스트레스를 도입하는 피에스씨 강재와 부분적인 다운공정을 통해서 상부 구조물에 압축응력을 도입하여 설치되는 프리스트레스 합성거더 연속교 시공방법.        The displacement meter installs a sensor in the pooling and lowering device 60, and connects the sensor to a computer, and connects the sensor to the pooling and lowering device, and lowers the amount of the girder by using a lowering program already stored in a computer. Part of the CS steel and the introduction of pre-stress for each construction stage characterized in that the lowering by adjusting the hydraulic amount of the hydraulic jack or the lowering amount of the screw jack by using the program of the computer so that the displacement does not occur in the girder while adjusting the Prestressed composite girder continuous bridge construction method installed by introducing compressive stress to the upper structure through a typical down process. 제 7항에 있어서,       The method of claim 7, wherein 상기 고임 및 하강장치는 유압잭 또는 스크류 잭 또는 지렛대를 이용한 잭인 것에 특징이 있는 시공단계별로 프리스트레스를 도입하는 피에스씨 강재와 부분적인 다운공정을 통해서 상부 구조물에 압축응력을 도입하여 설치되는 프리스트레스 합성거더 연속교 시공방법.        The hoisting and lowering device is a prestressed composite girder continuous installed by introducing a compressive stress to the upper structure through a partial down process with the PS steel to introduce the prestress for each construction stage characterized by being a jack using a hydraulic jack or a screw jack or a lever. Construction method. 제 7항에 있어서,       The method of claim 7, wherein 상기 내측 지점부에 설치된 프리스트레스 합성거더의 하강량은 당초에 내측 지점부에 고임되어 설치된 고임량인 것에 특징이 있는 시공단계별로 프리스트레스를 도입하는 피에스씨 강재와 부분적인 다운공정을 통해서 상부 구조물에 압축응력을 도입하여 설치되는 프리스트레스 합성거더 연속교 시공방법.        The amount of descending of the prestressed composite girder installed in the inner point portion is initially compressed into the upper structure through partial down process with the PS steel to introduce the prestress for each construction stage, which is characterized in that it is a high-density installed in the inner point portion. Prestressed composite girder continuous bridge construction method installed by introducing stress. 제 7항에 있어서,       The method of claim 7, wherein 상기 고임 및 하강장치의 내측 지점부 상부에 설치되는 부분과 상부의 거더의 하부에 밀착되어 설치되는 부분의 측면에 일정한 크기의 날개부(83)가 형성되어 있고, 상기 빔의 하부면에 밀착되어 설치되는 부분에는 방충패드(73)가 설치되어 있는 것에 특징이 있는 시공단계별로 프리스트레스를 도입하는 피에스씨 강재와 부분적인 다운공정을 통해서 상부 구조물에 압축응력을 도입하여 설치되는 프리스트레스 합성거더 연속교 시공방법.        Wings 83 having a predetermined size are formed on the side of the portion that is installed in close contact with the lower portion of the upper girder and the lower portion of the girder and the lowering device, and is in close contact with the lower surface of the beam Prestressed composite girder continuous bridge construction is installed by introducing compressive stress to the upper structure through partial down process and PS steel which introduces prestress for each construction stage characterized by the fact that the insect repellent pad 73 is installed in the installed part. Way. 제 7항에 있어서,       The method of claim 7, wherein 상기 (b) 단계에서 내측 지점부 상에 고임 및 하강장치를 설치하는 것은 거더가 설치된 하부에 설치하되 네방향으로 각각 설치하고 이들을 서로 변위계(70)로 연결한 것에 특징이 있는 시공단계별로 프리스트레스를 도입하는 피에스씨 강재와 부분적인 다운공정을 통해서 상부 구조물에 압축응력을 도입하여 설치되는 프리스트레스 합성거더 연속교 시공방법.       In the step (b), the installation of the holding device and the lowering device on the inner point part is installed on the lower part where the girder is installed, each of which is installed in each of four directions and the prestress for each construction step characterized in that they are connected to each other by a displacement meter 70 Pre-stressed composite girder continuous bridge construction method installed by introducing compressive stress into the upper structure through the introduction of PS steel and partial down process. 제 7항에 있어서,       The method of claim 7, wherein 상기 부분다운은 중앙부 교각에서 실시하거나 또는 내부교각에서의 다운크기를 서로다르게 한 부등다운이며 상기의 부분다운을 실시한 후에 강연선을 이용하여 단계별로 긴장를 부분적으로 실시하는 것에 특징이 있는 시공단계별로 프리스트레스를 도입하는 피에스씨 강재와 부분적인 다운공정을 통해서 상부 구조물에 압축응력을 도입하여 설치되는 프리스트레스 합성거더 연속교 시공방법.       The partial down is an uneven down which is performed at the center piers or at different down piers in the inner piers, and the prestress is performed by the construction stages, which are characterized in that the tension is partially performed step by step using the strand after performing the above partial downs. Pre-stressed composite girder continuous bridge construction method installed by introducing compressive stress into the upper structure through the introduction of PS steel and partial down process.
KR1020040032061A 2004-03-26 2004-05-07 Prestressed composite girder continuous bridge constructed by introducing prestressed concrete steel prestressed by a construction stage and compression stress to the upper structure through a partial down process, and constructing method thereof KR100563126B1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
KR1020040020847 2004-03-26
KR1020040020847 2004-03-26

Related Child Applications (1)

Application Number Title Priority Date Filing Date
KR20-2004-0012693U Division KR200357814Y1 (en) 2004-05-07 2004-05-07 Prestressed composite girder continuous bridge constructed by introducing prestressed concrete steel prestressed by a construction stage and compression stress to the upper structure through a partial down process

Publications (2)

Publication Number Publication Date
KR20050095511A true KR20050095511A (en) 2005-09-29
KR100563126B1 KR100563126B1 (en) 2006-03-24

Family

ID=37276015

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020040032061A KR100563126B1 (en) 2004-03-26 2004-05-07 Prestressed composite girder continuous bridge constructed by introducing prestressed concrete steel prestressed by a construction stage and compression stress to the upper structure through a partial down process, and constructing method thereof

Country Status (1)

Country Link
KR (1) KR100563126B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100946739B1 (en) * 2007-08-28 2010-03-11 이엔이건설주식회사 Long-span bridge construction method using prestressed concrete girder

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100720997B1 (en) * 2006-07-18 2007-05-23 삼표이앤씨 주식회사 Continuous bridge construction method using concrete slab
KR100720996B1 (en) * 2006-07-18 2007-05-23 삼표이앤씨 주식회사 Continuous bridge construction method using precast slab
KR101383138B1 (en) * 2013-10-24 2014-04-09 박정환 Uniformly loading apparatus for manufacturing preflex composite beam

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100946739B1 (en) * 2007-08-28 2010-03-11 이엔이건설주식회사 Long-span bridge construction method using prestressed concrete girder

Also Published As

Publication number Publication date
KR100563126B1 (en) 2006-03-24

Similar Documents

Publication Publication Date Title
JPS6114287B2 (en)
KR100890455B1 (en) Loading apparatus using gravitational method and apparatus of manufacturing preflex composite girder using the loading apparatus
US5144710A (en) Composite, prestressed structural member and method of forming same
CN110700113B (en) Construction method of prestress applying device of non-prestressed beam bridge
CN112609595A (en) Construction method for closure section of beam-arch combined rigid frame bridge
CN113565010A (en) Gate-type pier cross beam construction method and formwork
KR101140433B1 (en) Method for fabricating prestressed steel composite girder
KR100563126B1 (en) Prestressed composite girder continuous bridge constructed by introducing prestressed concrete steel prestressed by a construction stage and compression stress to the upper structure through a partial down process, and constructing method thereof
US5553439A (en) Composite, prestressed structural members and methods of forming same
KR100840190B1 (en) I-beam segment connection method equipped with prestress steel synthetic concrete upper flange for continuous bridge
KR200357814Y1 (en) Prestressed composite girder continuous bridge constructed by introducing prestressed concrete steel prestressed by a construction stage and compression stress to the upper structure through a partial down process
KR200353950Y1 (en) Prestressed composite girder continuous bridge constructed by introducing prestressed concrete steel prestressed by a construction stage and compression stress to the upper structure through a partial down process
CN115162173A (en) Construction method of square steel-concrete combined type portal pier
KR20080095397A (en) Represtressed preflex composite girder and method of manufacturing the same
CN111218893B (en) Construction method for reinforcing existing line-crossing bridge by newly-added pier column bearing steel truss girder
KR101414811B1 (en) Method for strengthening girder using steel plate
NL2034933B1 (en) Construction method of lower cross beam of main tower of highway-railway dual-purpose and river-crossing A-type cable-stayed bridge
CN219653511U (en) Steel box girder cable-stayed bridge single-column inward-inclined steel tower embedded section fixing support
CN115323924B (en) Construction method of highway-railway dual-purpose river-crossing A-type cable-stayed bridge main tower
KR102707466B1 (en) Method for Manufacturing Deck-Integrated Composite Girder, Deck-Integrated Composite Girder Produced Thereby, and Method of Constructing Bridge Upper Structure
CN217352139U (en) Gate-type pier crossbeam construction die carrier
CN111335167B (en) Cross beam construction method using temporary prestress as temporary support
CN117988247A (en) 0# Block cast-in-situ bracket and pre-pressing method thereof
CN111395167B (en) Construction method of continuous rigid frame bridge
CN117488684A (en) Construction method of large-span cast-in-situ beam

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
LAPS Lapse due to unpaid annual fee