KR200354436Y1 - The structure for underground tunnel formation - Google Patents

The structure for underground tunnel formation Download PDF

Info

Publication number
KR200354436Y1
KR200354436Y1 KR20-2004-0003062U KR20040003062U KR200354436Y1 KR 200354436 Y1 KR200354436 Y1 KR 200354436Y1 KR 20040003062 U KR20040003062 U KR 20040003062U KR 200354436 Y1 KR200354436 Y1 KR 200354436Y1
Authority
KR
South Korea
Prior art keywords
steel pipe
tunnel
steel
stress
stress material
Prior art date
Application number
KR20-2004-0003062U
Other languages
Korean (ko)
Inventor
김정윤
Original Assignee
주식회사 한국엔티에스이앤씨
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 한국엔티에스이앤씨 filed Critical 주식회사 한국엔티에스이앤씨
Priority to KR20-2004-0003062U priority Critical patent/KR200354436Y1/en
Application granted granted Critical
Publication of KR200354436Y1 publication Critical patent/KR200354436Y1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • E21D11/383Waterproofing; Heat insulating; Soundproofing; Electric insulating by applying waterproof flexible sheets; Means for fixing the sheets to the tunnel or cavity wall
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • E21D11/385Sealing means positioned between adjacent lining members
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/005Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by forcing prefabricated elements through the ground, e.g. by pushing lining from an access pit

Abstract

본 고안은 터널굴착부의 토사를 미리 파내지 않고 먼저 지중에 터널형성용 구조물을 설치하여 사전에 충분히 응력에 견디도록 한다음 구조물 내측을 굴착하여 지하터널을 형성하도록 하는 본인의 선출원발명인 특허출원 제2002-36953호 및 실용신안등록 제274812호의 기술내용을 좀더 개량고안하여 튼튼하고 견고하며 방수까지도 완벽한 터널형성용 구조물 구조를 빠른시간내에 시공할 수 있도록 한 지하터널 형성용 구조물 설치방법 및 그 구조에 관한 것으로,The present invention does not excavate the earth and sand of the tunnel excavation part in advance, but first installs the tunnel-forming structure in the ground so that it can withstand the stress sufficiently in advance and then excavates the inside of the structure to form the underground tunnel. -36953 and Utility Model Registration No. 274812, further improving the technical contents of the underground tunnel formation structure and the method for the construction of a tunnel construction structure that can be completed in a short time to complete a robust, robust and even waterproof In that,

종래와 같이 강관과 강관사이에 설치가 불가하고 비경제적인 길이가 긴 소구경의 파이프를 압입하지 않고 선도관에 형성된 토류방지판투입구를 통해 목재로된 토류방지판을 설치하므로 시공이 간편하고 자재비가 저렴하며, 선도관에서 설치함으로 호박돌이나 그 밖의 장해물을 신속히 제거해가면서 진행할 수 있어서 설치가 용이하고 직선도가 우수하며,As it is impossible to install between steel pipes and steel pipes as in the past, it is easy to install and material cost is prevented by installing wooden earth prevention plate through the earth prevention plate inlet formed in the leading pipe without injecting the small diameter pipe which is uneconomical. It is inexpensive, and it is easy to install and has excellent straightness because it can be progressed while removing amber stones and other obstacles quickly by installing in the leading pipe.

상기 응력재삽입공에 강관연결파이프나 각종 빔(beam)으로된 응력재를 삽입한다음 강관내면에 덧대어지는 강판으로 강관과 응력재를 용접하여 강관들을 서로 연결함으로써 연결상태가 매우 견고함은 물론 상기 응력재의 양측단에 플랜지나 강봉을 일체로 돌출성형하여 응력재가 강관으로부터 이탈되지 않기 때문에 구조적으로 안전한 구조체를 형성할 수 있으며,After inserting a steel pipe connecting pipe or a stress material made of various beams into the stress reinsertion hole, the steel pipe and the stress material are welded to the inner surface of the steel pipe and the steel pipes are connected to each other to connect the steel pipes to each other. By integrally protruding a flange or steel bar at both ends of the stress material, the stress material does not escape from the steel pipe, thereby forming a structurally safe structure.

강관내면에 부식방지용 그라우트주입구를 응력재상측이나 응력재와 응력재 사이에 위치토록 형성하고 이를 통해 그라우트를 주입하여 주위를 고결시킴과 동시에 강관 및 응력재외면이 그라우트재로 감싸지도록 하여 강관의 외면 및 응력재외면의 부식을 방지하고 수명을 증가시킴은 물론 구조적으로도 더욱 튼튼한 구조체를 형성할 수 있으며,Corrosion prevention grout inlet is formed on the inner surface of steel pipe to be located between stress material or between stress material and stress material. And prevent corrosion of the outer surface of the stress material and increase the life, as well as to form a more robust structure,

터널부내부로 물이 침투하지 못하도록 다양한 방법으로 방수처리를 하여 방수가 완벽하며,Waterproofing is perfect by waterproofing in various ways to prevent water from penetrating into the tunnel.

터널굴착후 노출되는 철판 및 파이프등의 부식방지의 경제적 부담과 요철부위의 미적문제 및 장기간 유지보수비의 과다등을 완전히 해소함으로써,By completely eliminating the economic burden of corrosion protection of steel plates and pipes exposed after tunnel excavation, aesthetic problems of uneven parts and excessive maintenance cost, etc.

지하터널 구조물을 더욱 편리하고 신속하면서도 시공이 정확하고, 경제적으로 설치 할 수 있으며, 구조물의 설치시는 물론 설치후에도 그 구조물이 구조적으로 매우 견고하여 터널굴착 작업을 안정적으로 할 수 있도록 하는등 결과적으로 작업상 위험성을 완전배제하여 안심하고 터널을 형성할 수 있도록 하는 것은 물론 적은 인력과 장비 및 자재를 사용토록 하여 경제적이고 튼튼한 터널을 구축할 수 있는 것이다.As a result, the underground tunnel structure can be installed more conveniently and quickly, and the construction is accurate and economical.In addition, after the installation and after the installation, the structure is very structurally strong so that tunneling work can be stable. It is possible to construct tunnels with confidence by completely eliminating work risks, and to build an economical and robust tunnel using less manpower, equipment and materials.

Description

지하터널 형성용 구조물 설치구조{The structure for underground tunnel formation}Structure for underground tunnel formation {The structure for underground tunnel formation}

본 고안은 터널굴착부의 토사를 미리 파내지 않고 먼저 지중에 터널형성용 구조물을 설치하여 사전에 충분히 응력에 견디도록 한다음 구조물 내측을 굴착하여 지하터널을 형성하도록 하는 본인의 선출원발명인 특허출원 제2002-36953호 및 실용신안등록 제274812호의 기술내용을 좀 더 개량고안하여 튼튼하고 견고하며 방수까지도 완벽한 터널형성용 구조물 구조를 빠른시간내에 시공할 수 있도록 한 지하터널 형성용 구조물 설치방법 및 그 구조에 관한 것이다.The present invention does not excavate the earth and sand of the tunnel excavation part in advance, but first installs the tunnel-forming structure in the ground so that it can withstand the stress sufficiently in advance and then excavates the inside of the structure to form the underground tunnel. -36953 and Utility Model Registration No. 274812 to further improve the technical content of the underground tunnel formation structure installation method and the structure that can be constructed in a short time to build a strong, robust and waterproof even tunnel construction structure It is about.

일반적으로 터널을 형성하기 위해서는 반드시 터널외부로 부터 발생하는 응력에 견딜 수 있도록 터널구조물이 설치되는바, 이와같은 터널구조물을 설치하기 위한 종래의 터널구조물 설치방법의 일실시예를 설명하면 다음과 같다.In general, in order to form a tunnel, a tunnel structure is installed so as to withstand the stress generated from the outside of the tunnel. Hereinafter, an embodiment of a conventional tunnel structure installation method for installing such a tunnel structure will be described. .

먼저 도1에 도시된 바와같이 지중에 소정간격으로 대구경의 강관(10)을 터널과 같은 형태로 압입하여 강관(10)내부 및 강관(10) 외면을 그라우팅한 후에 강관(10)내측 터널면을 일정깊이로 굴착한다음 여러개로된 지보공(1)을 다수개의 볼트로 연결하여서된 지보공(1)을 구조물 내측전체에 걸쳐 설치한다음 그내측으로 콘크리트(400)를 타설하여 가시설공사를 완료하는 방법을 수차례 반복하면서 지하터널 형성용 구조물을 설치하였던바, 이와같은 일실시예에 의한 종래의 방법은 물론 그 밖의 터널구조물 설치방법들은 거의 모두가 공통적으로 일정깊이로 미리 터널굴착을 한다음 가시설공사를 완료하고 지하터널 구조물을 설치하는 공법을 반복하는 방법들이어서,First, as shown in FIG. 1, a large diameter steel pipe 10 is press-fitted into a tunnel-like shape at a predetermined interval in the ground to grout the inside of the steel pipe 10 and the outer surface of the steel pipe 10, and then the inner tunnel surface of the steel pipe 10. Excavation to a certain depth and then install the support ball (1) by connecting a plurality of support ball (1) with a plurality of bolts throughout the inside of the structure and then poured the concrete (400) to the inside to complete the construction work Repeatedly repeated several times, the underground tunnel formation structure was installed, and the conventional method according to one embodiment as well as the other tunnel structure installation methods are almost all common tunnel drilling in advance to a certain depth in advance How to complete the process and repeat the process of installing underground tunnel structures,

첫째로는 먼저 터널굴착을 선행한 후 가시설공사를 진행하여야 하므로 매번 가시설공사를 하여야 하는 번거로움이 있었으며, 안전사고의 문제점을 안고 있었다.First of all, there was a hassle of having to construct a temporary facility every time because the construction of a temporary facility should be carried out before the tunnel excavation, and there was a problem of a safety accident.

둘째로는 가시설공사를 진행하기 위해서는 먼저 터널굴착후 여러개로된 지보공(1)을 다수개의 볼트로 연결하여서 설치하여야 하는데 이 또한 작업이 매우 까다롭고 힘들어 많은 인력이 소요되고 공정이 길어 비경제적이며, 가시설의 작업으로 시공상의 작업이 매우 더딘 문제점이 있었다.Secondly, in order to proceed with the temporary construction, first, after the tunnel excavation, several jibo (1) should be connected by installing a plurality of bolts, which is also very demanding and difficult, requiring a lot of manpower and a long process, which is uneconomical. There was a problem that the construction work was very slow due to the work of the temporary facility.

셋째로는 선행되는 굴착작업시 너무 깊이 굴착을 하면 지반이 약할 경우 굴착도중에는 물론이고 굴착후 가시설공사중에 지반 또는 암반등이 붕괴하거나 낙하할 염려가 매우 높아서 항상 안전사고의 발생위험이 많아 항상 적은 깊이로만 굴착을 선행하여야 하므로 작업이 연관성이 결여된 문제점이 있었다.Thirdly, if the excavation is too deep during the preceding excavation work, if the ground is weak, it is very likely that the ground or rock will collapse or fall during the excavation construction as well as during the temporary construction work. Since the excavation was to be preceded only by the operation, there was a problem that the work was not related.

결국, 상기와 같이 종래의 터널구조물설치공법에 의하면 미리 터널굴착작업을선행한 후 가시설공사를 설치하고 나면 기설치된 가시설물이 간섭을 줌으로 공기가 길며, 위험하고 터널구조물을 설치할때 최소단위로 반복되는 방법이어서 많은 인력과 장비 및 자재가 소요되어 작업이 비능률적이고 비 경제적이며, 터널구조물의 지구력의 취약점때문에 항상 터널붕괴 및 안전사고의 발생위험으로 부터 벗어날 수 가 없는등의 여러가지 문제점을 않고 있었다.As a result, according to the conventional tunnel structure installation method as described above, after installing the temporary construction work after the tunnel excavation work in advance, the installed temporary facilities interfere with the air, which is long, dangerous, and at the minimum unit when installing the tunnel structure. As it is a repetitive method, it requires a lot of manpower, equipment and materials, which makes the work inefficient and inexpensive, and because of the weakness of the endurance of the tunnel structure, it was not always able to escape from the risk of tunnel collapse and safety accidents. .

이에, 상기한 방법들에 의한 터널 굴착시의 결점을 배제하여 작업상 위험성이 없고, 작업을 일관되게 능률적으로 할 수 있도록 미리 땅을 굴착하지 않은 상태에서 일시에 연속적인 굴착 공사만을 할 수 있도록 지하터널 형성용 구조물 설치방법이 안출되었는데, 이는 첨부도면 도2에 도시된 바와같이, 1.5m~2m의 대구경 강관을 터널시공예정면을 따라 지중에 압입한 다음, 상기 강관(10)과 강관(10)사이에 소구경파이프(2)를 강관(10)과 나란히 수평으로 설치하고, 상기 양 강관(10)에 걸친 상부를 통상의 시멘트, 규산, 폴리우레탄과 같은 것으로 감싸거나 동결공법으로 감싸서 토사 붕괴 방지용 그라우팅부(50)를 형성한다음, 상기 강관(10)들 측면의 대향되는 일정길이의 곡면 부위를 절개하여 상호 개방된 절개부를 형성하고 절개된 절개부의 상,하 양끝을 철판(3)으로 용접연결한 후 강간지주(strut)(4)를 설치하여 지지토록 하여서, 상기 강관 내부 하측을 스티로폴로 채운 후에 나머지 공간에 콘크리트로 타설하는 방법으로 지하터널 형성용 구조물을 설치하도록 한 것이다.Therefore, there is no risk of work by excluding the defects in tunnel excavation by the above methods, and only underground excavation work can be done at a time without excavating the ground so that work can be performed efficiently and consistently. A method for installing a structure for forming a tunnel was devised. As shown in FIG. 2, a large diameter steel pipe of 1.5 m to 2 m was press-fitted into the ground along the tunnel construction plan, and then the steel pipe 10 and the steel pipe 10 were inserted. The small diameter pipe 2 is installed horizontally in parallel with the steel pipe 10, and the upper part of the both steel pipes 10 is wrapped with the same cement, silicic acid, and polyurethane, or wrapped with a freezing method to collapse the soil. After forming the preventive grouting portion 50, by cutting the curved portion of the predetermined length of the sides of the steel pipes 10 to form a mutually open incision and the upper and lower ends of the incision cut off the iron plate ( 3) After the welding connection to the rape (strut) (4) to be installed to support, by filling the lower side of the steel pipe with styropol to install the structure for underground tunnel formation by placing concrete in the remaining space. .

그러나, 이와같은 방법은 첫째로는 강관(10)과 강관(10)사이마다 길이가 긴 소구경파이프(2)를 전부 강제 압입하여 설치하여야 하므로, 길이가 길땐 파이프의 선도관 및 조정장치가 없어 방향성 및 직진도가 결여되어 설치가 곤란하고, 강관(10)과 강관(10) 사이 폭이 넓어지면 소구경파이프(2)으로 토사방지가 불가하여 자재비 및 시공비가 많이 소요되고, 돌이 있거나 토층이 상이할 시 방향이 틀어지는등 직진도가 불확실하며, 호박돌이나 그 이상의 암석이 산재해 있을시 시공이 매우 어려우며, 강관내부에 충진공법을 병행 안할시 부식되어 취약하게 되여, 지하수 및 토류유실을 방지하기가 어렵게 되며, 파이프 내부를 충진 할시 비 경제적이다.However, in such a method, first, all the small-diameter pipes (2) having long lengths must be forcedly installed between the steel pipes (10) and the steel pipes (10). Lack of directionality and straightness makes it difficult to install, and if the width between the steel pipe 10 and the steel pipe 10 becomes wider, small diameter pipes 2 are not possible to prevent earth and sand and material costs are required. If the direction is different, the straightness is uncertain, and when the amber or more rocks are scattered, the construction is very difficult, and when it is not combined with the filling method inside the steel pipe, it becomes vulnerable to corrosion and prevents groundwater and earth loss. Is difficult and uneconomical to fill the pipe interior.

둘째로는 상기 강관(10)들 측면의 대향되는 일정길이의 곡면 부위를 절개하여 상호 개방된 절개부를 형성할때 이미 상재 토압에 의해 붕괴의 우려가 있고 절개된 절개부의 상,하 양끝을 철판(3)으로 용접연결한 후 강간지주(strut)(4)를 설치하여야 하는데 이때 하부철판으로 토압이 전달되므로 보강판을 따로 설치하여 작업이 복잡하고, 별도의 철판자재가 필요하여 자재비가 과다하게 들어가 비 경제적이며, 외부응력에 견디는 힘이 약하여 사전 필요한 조치가 없을 시 구조적으로 불안전하였다.Secondly, when cutting the curved portion of a predetermined length of the side of the steel pipes (10) to form a mutually open incision, there is a fear of collapse by the earthquake pressure, and the upper and lower ends of the incision cut the iron plate ( 3) After the welding connection, the rape column (strut) (4) should be installed. At this time, the earth pressure is transferred to the lower steel plate, so the work is complicated by installing the reinforcement plate separately. It was uneconomical and weak in external stress, structurally unstable in the absence of necessary measures.

셋째로는 상기 강관(10) 내부 하측에 거푸집용으로 스티로폴(5)로 채우는 작업에 있어서, 자재비가 과다하게 들며, 시공물량이 적을 경우 스치로폴(5)의 구매가 어려워 강관(10)에 맞추어 스티로폴(5)을 가공하거나 주문생산하여야 하고, 강관(10)의 치수가 달라지면 치수에 맞는 스치로폴(5)을 재 구입하여야 하므로 불편하였다.Third, in the work of filling the styropole (5) for the formwork in the lower side of the steel pipe (10), the material cost is excessive, when the construction volume is small, it is difficult to purchase the styropol (5) to match the steel pipe (10) (5) must be processed or made to order, and if the dimensions of the steel pipe (10) is different, it was inconvenient because you have to repurchase Schiropol (5) according to the dimensions.

그리고, 공사완료후 스티로폴(5)의 폐기물은 환경에 오염을 주며 처리도 곤란하였다.After the completion of the construction, the waste of Styropol 5 polluted the environment and was difficult to dispose of.

넷째로는 강관(10)내부가 무근콘크리트로 되어 있어 외부응력에 약하고 구조적으로 해석이 어렵고 또한, 보강공법을 써야 하므로 추가비용이 많이 발생되어 비경제적이고 위험요소가 산재해 있었다.Fourth, the steel pipe 10 inside is made of plain concrete, which is weak in external stress, difficult to interpret structurally, and requires additional reinforcement methods.

이와같은 문제점을 감안하여 본인이 안출하여 등록된 실용신안등록 제274812호가 있는데 이는 터널굴착부의 토사를 미리 파내지 않고 먼저 지중에 터널형성용 구조물을 설치하여 사전에 충분히 응력에 견디도록 한다음 구조물 내측을 굴착하여 지하터널을 형성하도록 하는 지하터널 형성용 구조물 설치방법을 이용하되,In consideration of such a problem, there is a utility model registration No. 274812, which has been drafted and registered by the person. Using a method for installing underground tunnel formation structures to form underground tunnels by excavating

강관내에 거푸집이 설치하고 거푸집이 설치된 강관내에 먼저 철근배근을 한상태에서 콘크리트를 타설하여 구조물의 설치시는 물론 설치후에도 그 구조물이 구조적으로 매우 견고하여 터널굴착 작업을 안정적으로 할 수 있도록 한 본인의 개량된 축조방법을 제공하여 결국 작업상 위험성을 완전배제하여 안심하고 터널을 형성할 수 있도록 하는 것은 물론 적은 인력과 장비 및 자재를 재활용토록 하여 경제적이고 친환경적이며 튼튼한 터널을 구축할 수 있도록 하여 준 것이다.Self-improvement to install the formwork in the steel pipe and install concrete in the steel pipe with the formwork first, and to make the tunneling work stable because the structure is very solid structurally after installation. In addition, by providing the construction method, it is possible to form a tunnel with confidence by completely eliminating work risks, and to recycle economically, eco-friendly and durable tunnels with less manpower, equipment and materials.

본 고안은 상기와 같은 본인의 선출원발명인 특허출원 제2002-36953호 및 실용신안등록 제274812호와 같이 터널굴착부의 토사를 미리 파내지 않고 먼저 지중에 터널형성용 구조물을 설치하여 사전에 충분히 응력에 견디도록 한다음 구조물 내측을 굴착하여 지하터널을 형성하도록 하는 지하터널 형성용 구조물 설치방법을 이용하되,The present invention does not excavate the earth and sand of the tunnel excavation part in advance, such as Patent Application No. 2002-36953 and Utility Model Registration No. 274812, which are the original patent applications of the present invention. Using the installation method of the underground tunnel forming structure to endure and excavate the inside of the structure to form an underground tunnel,

본인의 선출원발명인 특허출원 제2002-36953호 및 실용신안등록 제274812호의 방법보다 지하터널 구조물을 더욱 편리하고 신속하면서도 시공이 정확하고, 구조물의 설치시는 물론 설치후에도 그 구조물이 구조적으로 매우 견고하여 터널굴착 작업을 안정적으로 할 수 있도록 하여 결국 작업상 위험성을 완전배제하여 안심하고 터널을 형성할 수 있도록 하는 것은 물론 적은 인력과 장비 및 자재를 이용하여 튼튼한 터널을 구축할 수 있도록 터널부 내측으로 돌출되는 강관의 내측면을 절단하지 않고 그대로 사용함은 물론,Underground tunnel structure is more convenient, faster and more accurate than the method of Patent Application No. 2002-36953 and Utility Model Registration No. 274812, which is the applicant's original invention. The tunnel excavation work can be stably performed, thus completely eliminating work risks to form a tunnel with confidence, and protruding inside the tunnel part to build a strong tunnel with less manpower, equipment, and materials. Of course, without cutting the inner surface of the steel pipe to be used,

상기 응력재삽입공에 강관연결파이프나 각종 빔(beam)으로된 응력재를 삽입한다음 강관내면에 덧대어지는 강판으로 강관과 응력재를 용접하여 강관들을 서로 연결함으로써 연결상태가 매우 견고함은 물론 상기 응력재의 양측단에 플랜지나 강봉을 일체로 돌출성형하여 응력재가 강관으로부터 이탈되지 않기 때문에 구조적으로 안전한 구조체를 형성할 수 있도록 하며,After inserting a steel pipe connecting pipe or a stress material made of various beams into the stress reinsertion hole, the steel pipe and the stress material are welded to the inner surface of the steel pipe and the steel pipes are connected to each other to connect the steel pipes to each other. By protruding integrally formed flanges or steel rods at both ends of the stress material, it is possible to form a structurally safe structure because the stress material does not escape from the steel pipe,

강관내면에 부식방지용 그라우트주입구를 응력재상측이나 응력재와 응력재 사이에 위치토록 형성하고 이를 통해 그라우트를 주입하여 주위를 고결시킴과 동시에 강관 및 응력재외면이 그라우트재로 감싸지도록 하여 강관의 외면 및 응력재외면의 부식을 방지하고 수명을 증가시킴은 물론 구조적으로도 더욱 튼튼한 구조체를 형성할 수 있도록 하며,Corrosion prevention grout inlet is formed on the inner surface of steel pipe to be located between stress material or between stress material and stress material. And prevent corrosion of the outer surface of the stress material and increase the life, as well as to form a more robust structure,

터널부내부로 물이 침투하지 못하도록 다양한 방법으로 방수처리를 하여 방수가 완벽하도록 하는등 튼튼하고 견고하며 방수까지도 완벽한 터널형성용 구조물 구조를 시공할 수 있는 특수한 방법의 지하터널 형성용 구조물 설치방법을 제공하여 빠른시간내에 지하터널 형성용 구조물 구조를 얻을 수 있도록 함에 그 목적을 둔 것이다.The installation method of the underground tunnel formation structure is a special way to construct a strong, solid, and perfect tunnel-forming structure, such as waterproofing to prevent water from penetrating into the tunnel. The purpose is to provide a structure for forming underground tunnels in a short time by providing.

도1은 종래 고안의 일실시예도.1 is an embodiment of a conventional design.

도2는 종래 고안의 다른 실시예도.Figure 2 is another embodiment of the prior art design.

도3는 본 고안의 실시예를 나타낸 공정도.Figure 3 is a process diagram showing an embodiment of the present invention.

도4는 본 고안을 실시하는데 사용되는 선도관과 파이프의 구성도.Figure 4 is a configuration diagram of the leading pipe and pipe used to practice the present invention.

도5a,도5b는 본 고안으로서 강관과 응력재를 강판으로 연결하는 상태예시도.Figure 5a, Figure 5b is an exemplary view of connecting the steel pipe and the stress material with a steel plate as the present design.

도6a,도6b는 본 고안으로서 방수용 철판으로 방수처리하고 숏크리트 또는 뿜칠채로 마감처리한 터널시공 상태도.Figure 6a, Figure 6b is a tunnel construction state of the waterproofing and steel plate for shotcrete or shot finish with the present invention.

도7a,도7b는 본 고안으로서 아스팔트펠트 또는 시트방수재층으로 방수처리하고 숏크리트 또는 뿜칠채로 마감처리한 터널시공 상태도.Figure 7a, Figure 7b is a tunnel construction state waterproofed with asphalt felt or sheet waterproofing layer and shotcrete or flushed with the present invention.

도8a,도8b는 본 고안으로서 방수용 철판으로 방수처리하고 거푸집내로 콘크리트를 양생하여 마감처리한 터널시공 상태도.Figure 8a, Figure 8b is a tunnel construction state of the present invention by the waterproofing steel plate waterproofing and curing the concrete into formwork.

도9a,도9b는 본 고안으로서 아스팔트펠트 또는 시트방수재층으로 방수처리하고 거푸집내로 콘크리트를 양생하여 마감처리한 터널시공 상태도.Figure 9a, Figure 9b is a tunnel construction state of waterproofing with asphalt felt or sheet waterproofing layer as the present design and curing by curing concrete into formwork.

도10a,도10b는 본 고안의 또다른 실시예로서,Figure 10a, 10b is another embodiment of the present invention,

도10a는 방수용 철판으로 방수처리하고 별도의 응력재를 댄다음 그 하측의 거푸집내로 콘크리트를 양생하여 마감처리한 터널시공 상태도.Fig. 10a is a tunnel construction state in which the waterproofing steel plate is waterproofed and a separate stress material is applied and the concrete is cured into the formwork at the lower side thereof.

도10b는 아스팔트펠트 또는 시트방수재층으로 방수처리하고 별도의 응력재를 댄다음 그 하측의 거푸집내로 콘크리트를 양생하여 마감처리한 터널시공 상태도.Figure 10b is a tunnel construction state of waterproofing with asphalt felt or sheet waterproofing material layer and curing the concrete into the formwork on the lower side after applying a separate stress material.

도11은 본 고안으로서 강관 및 응력재 외면의 부식을 방지하기 위해서 응력재사이에 형성한 그라우트주입구를 통해 그라우트재를 주입하는 상태를 나타낸 측면도.Figure 11 is a side view showing a state in which the grout material is injected through the grout inlet formed between the stress material in order to prevent corrosion of the steel pipe and the outer surface of the stress material as the present invention.

♣도면의 주요 부분에 대한 부호의 설명♣♣ Explanation of symbols for the main parts of the drawing

10:강관 12:응력재삽입공10: Steel pipe 12: Stress reinsertion hole

16:강관연결파이프 16a:플랜지16: Steel pipe connection pipe 16a: Flange

16b:강봉 17:빔16b: steel bar 17: beam

20:선도관 21:토류 방지판 투입구20: Lead pipe 21: Earth prevention plate inlet

30:압입 방향 조정장치 40:토류 방지판30: press-fit direction adjusting device 40: earth prevention plate

70:그라우팅부 100:강판70: grouting part 100: steel sheet

120:방수용 철판 121:아스팔트펠트 또는 시트방수재120: waterproofing iron plate 121: asphalt felt or sheet waterproofing material

200:그라우트주입구 210:빈공간200: grout inlet 210: empty space

300,750:강관연결용 응력재 400,700:콘크리트300,750: Stressor for steel pipe connection 400,700: Concrete

500:터널부 600,800:거푸집500: tunnel 600,800: formwork

상기와 같은 목적을 달성하기 위한 본 고안은 첨부도면 도3에 도시된 공정도에 따라 시공될 수 있는데 이하, 본 고안의 실시예를 첨부도면에 의거 상세히 설명하면 다음과 같다.The present invention for achieving the above object can be constructed in accordance with the process diagram shown in the accompanying drawings, Figure 3 below, the embodiment of the present invention will be described in detail based on the accompanying drawings.

본 고안의 실시예1은 도3에 따른 공정도와 도4 및 도5a 내지 도5b를 기초로 하여 도6a 내지 도7b에 도시된 바와같이 구성된다.Embodiment 1 of the present invention is constructed as shown in Figs. 6A to 7B on the basis of the process diagram according to Fig. 3 and Figs. 4 and 5A to 5B.

즉, 직경이 큰 소정갯수의 대구경 강관(10)을 터널공사 시공면에 시공면의 형태에 따라 원형이나 사각형을 이루도록 강제압입하되, 강관압입의 진행시 선도관(20)에 설치된 토류방지판 투입구(21)를 통해 강관(10)들 사이에 흙을 파낸다음 토류방지판 투입구(21)를 통해 토류방지판(40)을 순차적으로 투입하여 연결하고 그라우팅함으로서 그라우팅부(70)를 형성하고,That is, a large number of large diameter steel pipes 10 having a large diameter are forced into the tunnel construction surface to form a circle or a quadrangle depending on the shape of the construction surface. Digging soil between the steel pipes (10) through the (21) and then connecting and grouting the earth prevention plate 40 through the earth prevention plate inlet 21 to form a grouting portion 70,

상기 강관(10)들 측면을 절개하여 응력재삽입공(12)을 형성하고 이에 강관연결파이프(16)나 각종 빔(beam)(17)으로된 응력재(300)를 삽입한다음 강관(10)내면에 덧대어지는 강판(100)으로 강관(10)과 응력재(300)를 용접하여 강관(10)들을 서로 연결함과 동시에 상기 응력재(300)의 양측단에 플랜지(16a)나 강봉(16b)을 일체로 돌출성형하여 응력재(300)가 강관(10)으로부터 이탈하지 않도록 하며,The side surface of the steel pipes 10 are cut to form a stress reinsertion hole 12, and a stress material 300 made of a steel pipe connection pipe 16 or various beams 17 is inserted therein, and then the steel pipe 10 is inserted therein. The steel pipe 10 and the stress material 300 by welding the steel plate 100 to the inner surface to connect the steel pipes 10 and at the same time at both ends of the flange (16a) or steel bar ( 16b) integrally protruding to prevent the stress material 300 from escaping from the steel pipe 10,

상기 강관(10)내부 전체에 콘크리트(400)를 주입하여 양생시킨다음 강관(10)내측의 터널부(500)를 굴착한 후,After the concrete 400 is injected into the entire steel pipe 10 to cure, and then excavate the tunnel 500 inside the steel pipe 10,

상기 터널부(500)측으로 돌출된 일측 강관(10)과 타측 강관(10) 사이를 도6a내지 도6b와 같이 모두 방수용 철판(120)으로 연결하거나, 도7a 내지 도7b와 같이 전체에 아스팔트 펠트 또는 시트방수재층(121)을 형성하여 방수가 되도록 한다음,Between the one steel pipe 10 and the other steel pipe 10 protruding toward the tunnel 500, all connected to the waterproof steel plate 120 as shown in Figures 6a to 6b, or asphalt felt as a whole as shown in Figures 7a to 7b. Or to form a sheet waterproofing material layer 121 to be waterproof,

상기 터널부(500)하측에 터널바닥면을 형성하고 각각 강관(10) 및 방수용 철판(120)의 부식방지와 아스팔트펠트 또는 시트방수재층(121)의 보호 및 미관을 위해 강관(10) 및 방수용 철판(120)이나 아스팔트펠트 또는 시트방수재층(121)에 숏크리트 또는 뿜칠채(140)를 이용하여 터널벽면을 형성하여서 구성된다.The tunnel bottom surface is formed under the tunnel part 500, and the steel pipe 10 and waterproof for corrosion protection of the steel pipe 10 and waterproof steel plate 120, and protection and aesthetics of the asphalt felt or sheet waterproofing layer 121, respectively. It is configured by forming a tunnel wall surface using shotcrete or sprayed 140 on the iron plate 120 or asphalt felt or sheet waterproofing material layer 121.

그리고, 본 고안의 실시예2는 도3에 따른 공정도와 도4 및 도5a 내지 도5b를기초로 하여 도8a 내지 도9b에 도시된 바와같이 구성된다.In addition, Embodiment 2 of the present invention is constructed as shown in Figs. 8A to 9B based on the process diagram according to Fig. 3 and Figs. 4 and 5A to 5B.

즉, 직경이 큰 소정갯수의 대구경 강관(10)을 터널공사 시공면에 시공면의 형태에 따라 원형이나 사각형을 이루도록 강제압입하되, 강관압입의 진행시 선도관(20)에 설치된 토류방지판 투입구(21)를 통해 강관(10)들 사이에 흙을 파낸다음 토류방지판 투입구(21)를 통해 토류방지판(40)을 순차적으로 투입하여 연결하고 그라우팅함으로서 그라우팅부(70)를 형성하고,That is, a large number of large diameter steel pipes 10 having a large diameter are forced into the tunnel construction surface to form a circle or a quadrangle depending on the shape of the construction surface. Digging soil between the steel pipes (10) through the (21) and then connecting and grouting the earth prevention plate 40 through the earth prevention plate inlet 21 to form a grouting portion 70,

상기 강관(10)들 측면을 절개하여 응력재삽입공(12)을 형성하고 이에 강관연결파이프(16)나 각종 빔(beam)(17)으로된 응력재(300)를 삽입한다음 강관(10)내면에 덧대어지는 강판(100)으로 강관(10)과 응력재(300)를 용접하여 강관(10)들을 서로 연결함과 동시에 상기 응력재(300)의 양측단에 플랜지(16a)나 강봉(16b)을 일체로 돌출성형하여 응력재(300)가 강관(10)으로부터 이탈하지 않도록 하며,The side surface of the steel pipes 10 are cut to form a stress reinsertion hole 12, and a stress material 300 made of a steel pipe connection pipe 16 or various beams 17 is inserted therein, and then the steel pipe 10 is inserted therein. The steel pipe 10 and the stress material 300 by welding the steel plate 100 to the inner surface to connect the steel pipes 10 and at the same time at both ends of the flange (16a) or steel bar ( 16b) integrally protruding to prevent the stress material 300 from escaping from the steel pipe 10,

상기 강관(10)내부 전체에 콘크리트(400)를 주입하여 양생시킨다음 강관(10)내측의 터널부(500)를 굴착한 후,After the concrete 400 is injected into the entire steel pipe 10 to cure, and then excavate the tunnel 500 inside the steel pipe 10,

상기 터널부(500)측으로 돌출된 일측 강관(10)과 타측 강관(10) 사이를 도8a 내지 도8b와 같이 모두 방수용 철판(120)으로 연결하거나 도9a 내지 도9b와 같이 전체에 아스팔트 펠트 또는 시트방수재층(121)을 형성하여 방수가 되도록 한다음,Between the one steel pipe 10 and the other steel pipe 10 protruding toward the tunnel 500, all connected to the waterproof steel plate 120 as shown in Figure 8a to 8b, or asphalt felt or as a whole as shown in Figure 9a to 9b. After forming the sheet waterproofing material layer 121 to be waterproof,

상기 터널부(500)하측에 터널바닥면을 형성하고 각각 강관(10) 및 방수용 철판(120)의 부식방지와 아스팔트펠트 또는 시트방수재층(121)의 보호 및 미관을 위해 터널부(500)내측으로 거푸집(600)을 설치한다음 콘크리트(700)를 타설하여 터널벽면을 형성하여서 구성된다.A tunnel bottom surface is formed below the tunnel part 500 and the inside of the tunnel part 500 for corrosion protection of the steel pipe 10 and the waterproof steel plate 120, and protection and aesthetics of the asphalt felt or sheet waterproofing layer 121, respectively. After installing the formwork 600 by pouring concrete 700 is formed by forming a tunnel wall surface.

또한, 본 고안의 실시예3은 도3에 따른 공정도와 도4 및 도5a 내지 도5b를 기초로 하여 도10a 내지 도10b에 도시된 바와같이 구성된다.In addition, Embodiment 3 of the present invention is constructed as shown in Figs. 10A to 10B on the basis of the process diagram according to Fig. 3 and Figs. 4 and 5A to 5B.

즉, 직경이 큰 소정갯수의 대구경 강관(10)을 터널공사 시공면에 시공면의 형태에 따라 원형이나 사각형을 이루도록 강제압입하되, 강관압입의 진행시 선도관(20)에 설치된 토류방지판 투입구(21)를 통해 강관(10)들 사이에 흙을 파낸다음 토류방지판 투입구(21)를 통해 토류방지판(40)을 순차적으로 투입하여 연결하고 그라우팅함으로서 그라우팅부(70)를 형성하고,That is, a large number of large diameter steel pipes 10 having a large diameter are forced into the tunnel construction surface to form a circle or a quadrangle depending on the shape of the construction surface. Digging soil between the steel pipes (10) through the (21) and then connecting and grouting the earth prevention plate 40 through the earth prevention plate inlet 21 to form a grouting portion 70,

상기 강관(10)들 측면을 절개하여 응력재삽입공(12)을 형성하고 이에 강관연결파이프(16)나 각종 빔(beam)(17)으로된 응력재(300)를 삽입한다음 강관(10)내면에 덧대어지는 강판(100)으로 강관(10)과 응력재(300)를 용접하여 강관(10)들을 서로 연결함과 동시에 상기 응력재(300)의 양측단에 플랜지(12a)나 강봉(12b)을 일체로 돌출성형하여 응력재(300)가 강관(10)으로부터 이탈하지 않도록 하며,The side surface of the steel pipes 10 are cut to form a stress reinsertion hole 12, and a stress material 300 made of a steel pipe connection pipe 16 or various beams 17 is inserted therein, and then the steel pipe 10 is inserted therein. The steel pipe 10 and the stress member 300 by welding the steel plate 100 is attached to the inner surface to connect the steel pipe 10 with each other at the same time the flange 12a or the steel rod (12a) at both ends of the stress member 300 ( 12b) integrally protruding to prevent the stress material 300 from leaving the steel pipe 10,

상기 강관(10)내부 전체에 콘크리트(400)를 주입하여 양생시킨다음 강관(10)내측의 터널부(500)를 굴착한 후,After the concrete 400 is injected into the entire steel pipe 10 to cure, and then excavate the tunnel 500 inside the steel pipe 10,

상기 터널부(500)측으로 돌출된 일측 강관(10)과 타측 강관(10) 사이를 도10a와 같이 모두 방수용 철판(120)으로 연결하거나 도10b와 같이 전체에 아스팔트 펠트 또는 시트방수재층(121)을 형성하여 방수가 되도록 한다음,Between the one steel pipe 10 and the other steel pipe 10 protruding toward the tunnel portion 500 side as shown in Figure 10a all connected to the waterproof steel plate 120 or as shown in Figure 10b asphalt felt or sheet waterproofing layer 121 as a whole To make it waterproof.

상기 터널부(500)측으로 철근 및 H빔등으로된 별도의 응력재(750)를 설치하여 응력을 보강시킨후 그 하측으로 라이닝거푸집(800)을 설치한 후에 라이닝거푸집(800)내로 콘크리트(700)를 타설하고 양생시켜서 터널벽면과 바닥면을형성하여 구성된다.Reinforce the stress by installing a separate stress material 750 made of reinforcing bars and H beams to the tunnel portion 500 side, and then install the lining formwork 800 below the concrete 700 into the lining formwork 800. It is constructed by forming tunnel wall and floor by pouring and curing.

여기서, 상기 본 고안은 본 고안을 실현하기 위한 실시예1,2,3에서, 첨부도면 도11에 도시된 바와같이 상기 강관(10)내면에 부식방지용 그라우트주입구(200)를 형성하되, 강관(10)을 연결하는 응력재(300)상측이나 응력재(300)와 응력재(300) 사이에 위치토록 설치하여,Here, the present invention in the embodiments 1, 2, 3 for realizing the present invention, as shown in Figure 11 of the accompanying drawings to form a corrosion preventing grout inlet 200 on the inner surface of the steel pipe 10, 10) installed on the upper side of the stress member 300 or between the stress member 300 and the stress member 300 to connect,

강관(10)내에 콘크리트(400) 타설공정전에 그라우트주입구(200)를 통해 그라우트재를 주입하여 거드 및 횡빔용 응력재설치공정시 형성되는 응력재삽입공(12)을 통해 외부로 유실된 흙으로 인해 생기는 빈공간(210)을 그라우트재가 가득 채워지도록 하여 주위를 고결시킴과 동시에 강관(10) 및 응력재(200)외면이 그라우트재로 감싸지도록 하여 강관(10)의 외면 및 응력재(300)외면이 부식되지 않도록 방지토록 하는 부식방지용 갱외 그라우팅공정을 더 포함하여 이루어질 수 도 있는데,The grout material is injected through the grout inlet 200 before the concrete 400 is placed in the steel pipe 10, and due to the soil lost to the outside through the stress reinsertion hole 12 formed during the stress re-installation process for the girdle and the transverse beam. The resulting empty space 210 is filled with the grout material to solidify the surroundings, and at the same time, the outer surface of the steel pipe 10 and the stress material 200 are wrapped with the grout material so that the outer surface of the steel pipe 10 and the outer surface of the stress material 300 are filled. It may further comprise a corrosion preventing gang grouting process to prevent the corrosion from being,

이와같이 하면 빈공간(210)에 그라우트재가 가득 채워져 고결되므로 구조적으로도 매우 튼튼하게 되며, 강관(10)의 외면 및 응력재(300)외면이 부식되지 않기 때문에 수명이 연장되고 구조적으로도 더욱 안정된다.In this way, since the grout material is filled and solidified in the empty space 210, it is structurally very strong, and since the outer surface of the steel pipe 10 and the outer surface of the stress material 300 are not corroded, the service life is extended and structurally more stable. .

여기서, 상기 부식방지용 그라우트주입구(200)는, 응력재(300)상측에만 설치하여도 강관 및 응력재 외면을 충분히 감싸줄 수 있는 것은 물론 빈공간(210)을 채워줄 수 있으므로 응력재(300)와 응력재(300) 사이에 위치토록 설치하는 것은 생략하여도 무방하다.Here, the corrosion preventing grout injection hole 200, even if only installed on the upper side of the stress member 300 can sufficiently cover the outer surface of the steel pipe and the stress member, as well as can fill the empty space 210, the stress member 300 and the stress The location between the materials 300 may be omitted.

한편, 상기 거드 및 횡빔용 응력재설치공정에서 사용되는 응력재(300)들은,On the other hand, the stress material 300 used in the girdle and the horizontal beam stress re-installation process,

양측단에 플랜지(16a)나 강봉(16b)을 일체로 돌출형성하여 상기 강관(10)내에 콘크리트를 타설할시 응력재(300)가 플랜지(16a)나 강봉(16b)에 의해 강관으로부터 이탈되지 구성되는데, 여기서 상기 플랜지(16a)나 강봉(16b)이 돌출형성하는 방법의 일실시예를 응력재(300)를 강관연결파이프(16)로 형성한 경우로 가정하여 설명하면 먼저 소정의 길이로 절단되어진 강관연결파이프(16)의 좌,우 양측에 구멍을 뚫은 다음 여기에 강봉(16b)을 용접으로 결합하여 콘크리트 타설후 구조체와 일체되게 고정되도록 하거나, 강관연결파이프(16)의 좌,우 양측에 플랜지(16a)를 일체로 용접하여서 각각 플랜지(16a)나 강봉(16b)에 의해 강관연결파이프(16)가 강관(10)과 강관(10)으로 부터 움직이거나 빠지지 않도록 미연에 방지할 수 있는 것이다.When the concrete 16 is cast in the steel pipe 10 by integrally protruding the flange 16a or the steel bar 16b at both ends, the stress material 300 is not separated from the steel pipe by the flange 16a or the steel bar 16b. If the embodiment of the method in which the flange (16a) or the steel bar (16b) is formed to protrude, the assumption that the stress material 300 is formed of a steel pipe connecting pipe 16 will be described first to a predetermined length After drilling holes in both left and right sides of the cut steel pipe connecting pipe 16, and then joining the steel bar (16b) by welding to be fixed integrally with the structure after pouring the concrete, or left and right of the steel pipe connecting pipe (16) By welding the flange 16a integrally to both sides, the flange 16a or the steel bar 16b can be prevented in advance so that the steel pipe connecting pipe 16 does not move or come out of the steel pipe 10 and the steel pipe 10, respectively. It is.

이때, 상기 강봉(16b)은 십자형태로 결합되도록 구성하여 본 구조체와 고정되는 것이 가장 이상적이다.At this time, the steel bar (16b) is configured to be coupled to the cross shape is most ideally fixed with the present structure.

상기와 같은 본 고안은 터널굴착부의 토사를 미리 파내지 않고 먼저 지중에 터널형성용 구조물을 설치하여 사전에 충분히 응력에 견디도록 한다음 구조물 내측을 굴착하여 지하터널을 형성하도록 하는 본인의 선출원발명인 특허출원 제2002-36953호 및 실용신안등록 제274812호의 기술내용을 좀 더 개량하여 터널부 내측으로 돌출되는 강관의 내측면을 절단하지 않고 그대로 사용함으로써 튼튼하고 견고하며 방수가 완벽한 터널형성용 구조물 구조를 얻을 수 있는 특수한 방법을 개발하여,The present invention as described above is the first patent of the invention to install the tunnel-forming structure in the ground without having to excavate the earth and sand of the tunnel excavation portion in advance to sufficiently withstand the stress and then excavate the inner structure to form an underground tunnel By further improving the technical contents of the application No. 2002-36953 and Utility Model Registration No. 274812, the inner surface of the steel pipe protruding into the tunnel part is used as it is, without cutting the structure of the tunnel structure By developing special ways to achieve

종래와 같이 강관과 강관사이에 설치가 불가하고 비경제적인 길이가 긴 소구경의 파이프를 압입하지 않고 선도관에 형성된 토류방지판투입구를 통해 목재로된 토류방지판을 설치하므로 시공이 간편하고 자재비가 저렴하며, 선도관에서 설치함으로 호박돌이나 그 밖의 장해물을 신속히 제거해가면서 진행할 수 있어서 설치가 용이하고 직선도가 우수하며,As it is impossible to install between steel pipes and steel pipes as in the past, it is easy to install and material cost is prevented by installing wooden earth prevention plate through the earth prevention plate inlet formed in the leading pipe without injecting the small diameter pipe which is uneconomical. It is inexpensive, and it is easy to install and has excellent straightness because it can be progressed while removing amber stones and other obstacles quickly by installing in the leading pipe.

상기 응력재삽입공에 강관연결파이프나 각종 빔(beam)으로된 응력재를 삽입한다음 강관내면에 덧대어지는 강판으로 강관과 응력재를 용접하여 강관들을 서로 연결함으로써 연결상태가 매우 견고함은 물론 상기 응력재의 양측단에 플랜지나 강봉을 일체로 돌출성형하여 응력재가 강관으로부터 이탈되지 않기 때문에 구조적으로 안전한 구조체를 형성할 수 있으며,After inserting a steel pipe connecting pipe or a stress material made of various beams into the stress reinsertion hole, the steel pipe and the stress material are welded to the inner surface of the steel pipe and the steel pipes are connected to each other to connect the steel pipes to each other. By integrally protruding a flange or steel bar at both ends of the stress material, the stress material does not escape from the steel pipe, thereby forming a structurally safe structure.

터널부내부로 물이 침투하지 못하도록 다양한 방법으로 방수처리를 하여 방수가 완벽하며,Waterproofing is perfect by waterproofing in various ways to prevent water from penetrating into the tunnel.

강관내면에 부식방지용 그라우트주입구를 응력재상측과 응력재와 응력재 사이에 위치토록 설치하고 이를 통해 그라우트를 주입하여 응력재사이사이의 빈공간에 그라우트재가 가득 채워서 주위를 고결시킴과 동시에 강관 및 응력재외면이 그라우트재로 감싸지도록 하여 강관 및 응력재외면이 부식되지 않도록 함으로써, 사용수명이 증가됨은 물론 구조적으로도 더욱 튼튼한 구조체가 형성되며,Corrosion prevention grout inlet is installed on the inner surface of the steel pipe between the stress material and between the stress material and the stress material, and through this, grout is injected to fill the void space between the stress materials to solidify the surroundings and at the same time to fix the steel pipe and stress By enclosing the outer surface of the grout material to prevent corrosion of the steel pipe and the outer surface of the stress material, the service life is increased and structurally stronger structure is formed,

터널굴착후 노출되는 철판 및 파이프등의 부식방지의 경제적 부담과 요철부위의 미적문제 및 장기간 유지보수비의 과다등을 완전히 해소함으로써,By completely eliminating the economic burden of corrosion protection of steel plates and pipes exposed after tunnel excavation, aesthetic problems of uneven parts and excessive maintenance cost, etc.

지하터널 구조물을 더욱 편리하고 신속하면서도 시공이 정확하고, 경제적으로 설치 할 수 있으며, 구조물의 설치시는 물론 설치후에도 그 구조물이 구조적으로 매우 견고하여 터널굴착 작업을 안정적으로 할 수 있도록 하는등 결과적으로 작업상 위험성을 완전배제하여 안심하고 터널을 형성할 수 있도록 하는 것은 물론 적은 인력과 장비 및 자재를 사용토록 하여 경제적이고 튼튼한 터널을 구축할 수 있는 매우 획기적인 고안이다.As a result, the underground tunnel structure can be installed more conveniently and quickly, and the construction is accurate and economical.In addition, after the installation and after the installation, the structure is very structurally strong so that tunneling work can be stable. It is a very innovative design that can construct a tunnel that is economical and robust by using less manpower, equipment and materials, as well as allowing the tunnel to be safely formed by completely eliminating work risks.

Claims (4)

직경이 큰 소정갯수의 대구경 강관(10)을 터널공사 시공면에 시공면의 형태에 따라 원형이나 사각형을 이루도록 강제압입하되, 상기 강관(10)들 사이에 흙을 파낸다음 토류방지판(40)을 순차적으로 투입하여 연결하고 그라우팅함으로서 그라우팅부(70)를 형성하고,A large number of large diameter steel pipes 10 having a large diameter are forced into the tunnel construction surface to form a circle or a quadrangle depending on the shape of the construction surface, and the earth is prevented by digging soil between the steel pipes 10. By connecting and grouting sequentially to form a grouting portion 70, 상기 강관(10)들 측면을 절개하여 응력재삽입공(12)을 형성하고 이에 강관연결파이프(16)나 각종 빔(beam)(17)으로된 응력재(300)를 삽입한다음 강관(10)내면에 덧대어지는 강판(100)으로 강관(10)과 응력재(300)를 용접하여 강관(10)들을 서로 연결함과 동시에 상기 응력재(300)의 양측단에 플랜지(16a)나 강봉(16b)을 일체로 돌출성형하여 응력재(300)가 강관(10)으로부터 이탈하지 않도록 하며,The side surface of the steel pipes 10 are cut to form a stress reinsertion hole 12, and a stress material 300 made of a steel pipe connection pipe 16 or various beams 17 is inserted therein, and then the steel pipe 10 is inserted therein. The steel pipe 10 and the stress material 300 by welding the steel plate 100 to the inner surface to connect the steel pipes 10 and at the same time at both ends of the flange (16a) or steel bar ( 16b) integrally protruding to prevent the stress material 300 from escaping from the steel pipe 10, 상기 강관(10)내부 전체에 콘크리트(400)를 주입하여 양생시킨다음 강관(10)내측의 터널부(500)를 굴착한 후,After the concrete 400 is injected into the entire steel pipe 10 to cure, and then excavate the tunnel 500 inside the steel pipe 10, 상기 터널부(500)측으로 돌출된 일측 강관(10)과 타측 강관(10) 사이를 모두 방수용 철판(120)으로 연결하거나 전체에 아스팔트 펠트 또는 시트방수재층(121)을 형성하여 방수가 되도록 하며,Between the one steel pipe 10 and the other steel pipe 10 protruding toward the tunnel portion 500 side to the waterproof steel plate 120 or by forming an asphalt felt or sheet waterproofing layer 121 on the whole to be waterproof. 상기 터널부(500)하측에 터널바닥면을 형성하고 강관(10) 및 방수용 철판(120)의 부식방지와 아스팔트펠트 또는 시트방수재층(121)의 보호 및 미관을 위해 강관(10) 및 방수용 철판(120)이나 아스팔트펠트 또는 시트방수재층(121)에 숏크리트 또는 뿜칠채(140)를 이용하여 터널벽면을 구성하여서 이루어짐을 특징으로 하는 지하터널 형성용 구조물 구조.Form the tunnel bottom surface below the tunnel portion 500, the steel pipe (10) and the waterproof steel plate for the corrosion protection of the steel pipe (10) and waterproof steel plate 120 and the protection and aesthetics of the asphalt felt or sheet waterproofing layer (121). Underground tunnel formation structure, characterized in that made by forming a tunnel wall surface using shotcrete or sprayed 140 to the 120 or asphalt felt or sheet waterproofing material layer (121). 직경이 큰 소정갯수의 대구경 강관(10)을 터널공사 시공면에 시공면의 형태에 따라 원형이나 사각형을 이루도록 강제압입하되, 상기 강관(10)들 사이에 흙을 파낸다음 토류방지판(40)을 순차적으로 투입하여 연결하고 그라우팅함으로서 그라우팅부(70)를 형성하고,A large number of large diameter steel pipes 10 having a large diameter are forced into the tunnel construction surface to form a circle or a quadrangle depending on the shape of the construction surface, and the earth is prevented by digging soil between the steel pipes 10. By connecting and grouting sequentially to form a grouting portion 70, 상기 강관(10)들 측면을 절개하여 응력재삽입공(12)을 형성하고 이에 강관연결파이프(16)나 각종 빔(beam)(17)으로된 응력재(300)를 삽입한다음 강관(10)내면에 덧대어지는 강판(100)으로 강관(10)과 응력재(300)를 용접하여 강관(10)들을 서로 연결함과 동시에 상기 응력재(300)의 양측단에 플랜지(16a)나 강봉(16b)을 일체로 돌출성형하여 응력재(300)가 강관(10)으로부터 이탈하지 않도록 하며,The side surface of the steel pipes 10 are cut to form a stress reinsertion hole 12, and a stress material 300 made of a steel pipe connection pipe 16 or various beams 17 is inserted therein, and then the steel pipe 10 is inserted therein. The steel pipe 10 and the stress material 300 by welding the steel plate 100 to the inner surface to connect the steel pipes 10 and at the same time at both ends of the flange (16a) or steel bar ( 16b) integrally protruding to prevent the stress material 300 from escaping from the steel pipe 10, 상기 강관(10)내부 전체에 콘크리트(400)를 주입하여 양생시킨다음 강관(10)내측의 터널부(500)를 굴착한 후,After the concrete 400 is injected into the entire steel pipe 10 to cure, and then excavate the tunnel 500 inside the steel pipe 10, 상기 터널부(500)측으로 돌출된 일측 강관(10)과 타측 강관(10) 사이를 모두 방수용 철판(120)으로 연결하거나 전체에 아스팔트 펠트 또는 시트방수재층(121)을 형성하여 방수가 되도록 하며,Between the one steel pipe 10 and the other steel pipe 10 protruding toward the tunnel portion 500 side to the waterproof steel plate 120 or by forming an asphalt felt or sheet waterproofing layer 121 on the whole to be waterproof. 상기 터널부(500)하측에 터널바닥면을 형성하고 강관(10) 및 방수용 철판(120)의 부식방지와 아스팔트펠트 또는 시트방수재층(121)의 보호 및 미관을 위해 터널부(500)내측으로 거푸집(600)을 설치한다음 콘크리트(700)를 타설하여 터널벽면을 구성하여서 이루어짐을 특징으로 하는 지하터널 형성용 구조물 구조.A tunnel bottom surface is formed below the tunnel part 500 and the inside of the tunnel part 500 for corrosion protection of the steel pipe 10 and the waterproof steel plate 120 and protection and aesthetics of the asphalt felt or sheet waterproofing layer 121. After the formwork 600 is installed, the concrete tunnel structure is formed by placing the concrete 700 to form a tunnel wall surface. 직경이 큰 소정갯수의 대구경 강관(10)을 터널공사 시공면에 시공면의 형태에 따라 원형이나 사각형을 이루도록 강제압입하되, 상기 강관(10)들 사이에 흙을 파낸다음 토류방지판(40)을 순차적으로 투입하여 연결하고 그라우팅함으로서 그라우팅부(70)를 형성하고,A large number of large diameter steel pipes 10 having a large diameter are forced into the tunnel construction surface to form a circle or a quadrangle depending on the shape of the construction surface, and the earth is prevented by digging soil between the steel pipes 10. By connecting and grouting sequentially to form a grouting portion 70, 상기 강관(10)들 측면을 절개하여 응력재삽입공(12)을 형성하고 이에 강관연결파이프(16)나 각종 빔(beam)(17)으로된 응력재(300)를 삽입한다음 강관(10)내면에 덧대어지는 강판(100)으로 강관(10)과 응력재(300)를 용접하여 강관(10)들을 서로 연결함과 동시에 상기 응력재(300)의 양측단에 플랜지(12a)나 강봉(12b)을 일체로 돌출성형하여 응력재(300)가 강관(10)으로부터 이탈하지 않도록 하며,The side surface of the steel pipes 10 are cut to form a stress reinsertion hole 12, and a stress material 300 made of a steel pipe connection pipe 16 or various beams 17 is inserted therein, and then the steel pipe 10 is inserted therein. The steel pipe 10 and the stress member 300 by welding the steel plate 100 is attached to the inner surface to connect the steel pipe 10 with each other at the same time the flange 12a or the steel rod (12a) at both ends of the stress member 300 ( 12b) integrally protruding to prevent the stress material 300 from leaving the steel pipe 10, 상기 강관(10)내부 전체에 콘크리트(400)를 주입하여 양생시킨다음 강관(10)내측의 터널부(500)를 굴착한 후,After the concrete 400 is injected into the entire steel pipe 10 to cure, and then excavate the tunnel 500 inside the steel pipe 10, 상기 터널부(500)측으로 돌출된 일측 강관(10)과 타측 강관(10) 사이를 모두 방수용 철판(120)으로 연결하거나 전체에 아스팔트 펠트 또는 시트방수재층(121)을 형성하여 방수가 되도록 하며,Between the one steel pipe 10 and the other steel pipe 10 protruding toward the tunnel portion 500 side to the waterproof steel plate 120 or by forming an asphalt felt or sheet waterproofing layer 121 on the whole to be waterproof. 상기 터널부측으로 철근 및 H빔등으로된 별도의 응력재(750)를 설치하여 응력을 보강시킨후 그 하측으로 라이닝거푸집(800)을 설치하고 라이닝거푸집(800)내로 콘크리트(700)를 타설하고 양생시켜서 터널벽면과 바닥면을 구성함을 특징으로 하는 지하터널 형성용 구조물 구조.Reinforce the stress by installing a separate stress material (750) made of reinforcing bars and H beams to the tunnel side, and then install the lining formwork 800 below and cast concrete 700 into the lining formwork 800 and cure. Structure structure for underground tunnel formation, characterized in that by configuring the tunnel wall surface and the bottom surface. 제1항 내지 제3항중 어느 한 항에 있어서,The method according to any one of claims 1 to 3, 상기 강관(10)내면에 부식방지용 그라우트주입구(200)를 응력재(300)상측이나 응력재(300)와 응력재(300) 사이에 위치토록 설치하고,The corrosion prevention grout injection hole 200 is installed on the inner surface of the steel pipe 10 so as to be positioned above the stress material 300 or between the stress material 300 and the stress material 300, 강관(10)내에 콘크리트(400)를 타설하기전에 그라우트주입구(200)를 통해 그라우트재를 주입하여 거드 및 횡빔용 응력재(300)설치시 외부로 유실된 흙으로 인한 빈공간(210)을 그라우트재가 가득 채워지도록 하여 주위를 고결시킴과 동시에 강관(10) 및 응력재(200)외면이 그라우트재로 감싸지도록 하여 강관(10)의 외면 및 응력재(300)외면이 부식되지 않도록 구성됨을 포함함을 특징으로 하는 지하터널 형성용 구조물 구조.The grout material is injected through the grout inlet 200 before the concrete 400 is poured into the steel pipe 10 to grout the empty space 210 due to the soil lost to the outside when installing the stress material 300 for the girdle and the transverse beam. It is configured to ensure that the ash is filled to solidify the surrounding and at the same time the outer surface of the steel pipe 10 and the stress member 200 is wrapped with a grout material so that the outer surface of the steel pipe 10 and the outer surface of the stress member 300 is not corroded. Structure structure for underground tunnel formation, characterized in that.
KR20-2004-0003062U 2004-02-09 2004-02-09 The structure for underground tunnel formation KR200354436Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR20-2004-0003062U KR200354436Y1 (en) 2004-02-09 2004-02-09 The structure for underground tunnel formation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR20-2004-0003062U KR200354436Y1 (en) 2004-02-09 2004-02-09 The structure for underground tunnel formation

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
KR10-2004-0007747A Division KR100521345B1 (en) 2004-02-06 2004-02-06 Construction establishment method and the structure for underground tunnel formation

Publications (1)

Publication Number Publication Date
KR200354436Y1 true KR200354436Y1 (en) 2004-06-25

Family

ID=49347476

Family Applications (1)

Application Number Title Priority Date Filing Date
KR20-2004-0003062U KR200354436Y1 (en) 2004-02-09 2004-02-09 The structure for underground tunnel formation

Country Status (1)

Country Link
KR (1) KR200354436Y1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100895881B1 (en) 2007-07-18 2009-05-04 주식회사 엔티에스이앤씨 Underground tunnel formation infrastructure establishment method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100895881B1 (en) 2007-07-18 2009-05-04 주식회사 엔티에스이앤씨 Underground tunnel formation infrastructure establishment method

Similar Documents

Publication Publication Date Title
KR100713787B1 (en) The underground structure assembly and the underground structure building method which it uses
KR101388521B1 (en) Construction method of underground structure under the pier with supporting piles
CN109838240B (en) River-crossing tunnel arch cover covering and digging construction method
KR100442712B1 (en) Construction establishment method and the structure for underground tunnel formation
JP6186267B2 (en) How to build an underground tunnel
KR20070075506A (en) Construction method of underground structure using concrete filled pipe roof and concrete wall
KR101536209B1 (en) Steel Pipe Multi Step Grouting device Open and cut and NATM complex excavation tunnel construction method
KR100914158B1 (en) Process of blocking water penetration and blocking earth collapsing by using impermeable wall without strut
KR101283672B1 (en) Non open cut method using the lifting device
KR100521345B1 (en) Construction establishment method and the structure for underground tunnel formation
KR100784201B1 (en) Method for construction of tunnel
KR100562121B1 (en) Shield tunneling construction method and tunnel structure
KR100992597B1 (en) The support material for a tunnel and tunnel support
KR100546998B1 (en) Construction method of temporary apparatus of thnnel for direct digging
KR100553979B1 (en) Construction establishment method and the structure for underground tunnel formation
KR100505301B1 (en) The structure for underground tunnel formation
KR102113291B1 (en) Soil retaining wall using phc pile and construction method thererof
KR100551685B1 (en) Construction establishment method and the structure for underground tunnel formation
KR200354436Y1 (en) The structure for underground tunnel formation
KR101283663B1 (en) Method for digging two arch type tunnel
KR20030065963A (en) A method of constrution method for tunnel of structure pipe
KR200351426Y1 (en) The structure for underground tunnel formation
KR101234270B1 (en) Method for non excavated excavating construction using steel pipe and steel pipe with hole
KR100753140B1 (en) Steel pipe roof assembly and the construction method for tunnel using thereof
KR200274812Y1 (en) the structure for underground tunnel formation

Legal Events

Date Code Title Description
U107 Dual application of utility model
REGI Registration of establishment
T201 Request for technology evaluation of utility model
T701 Written decision to grant on technology evaluation
G701 Publication of correction
EXTG Extinguishment