KR200337174Y1 - Mould assembly for constructing the tunnel type water conduit - Google Patents

Mould assembly for constructing the tunnel type water conduit Download PDF

Info

Publication number
KR200337174Y1
KR200337174Y1 KR20030027225U KR20030027225U KR200337174Y1 KR 200337174 Y1 KR200337174 Y1 KR 200337174Y1 KR 20030027225 U KR20030027225 U KR 20030027225U KR 20030027225 U KR20030027225 U KR 20030027225U KR 200337174 Y1 KR200337174 Y1 KR 200337174Y1
Authority
KR
Grant status
Grant
Patent type
Prior art keywords
support frame
fixed
mold
inner
construction
Prior art date
Application number
KR20030027225U
Other languages
Korean (ko)
Inventor
남준노
Original Assignee
남준노
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Grant date

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR OTHER BUILDING AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • E04G11/20Movable forms; Movable forms for moulding cylindrical, conical or hyperbolical structures; Templates serving as forms for positioning blocks or the like
    • E04G11/34Horizontally-travelling moulds for making walls blockwise or section-wise
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/102Removable shuttering; Bearing or supporting devices therefor

Abstract

본 고안은 대형의 터널형수로를 이음새없이 연속적을 시공하는데 적합한 거푸집조립체에 관한 것으로 내부거푸집과 외부거푸집을 타설되는 콘크리트의 큰 압력에 대응할 수 있도록 보다 견고하게 조립할 수 있도록 하고 수로 시공 후 내,외부거푸집을 다음 시공위치로 손쉽게 수평이동시켜 가면서 수로를 신속하게 연속적으로 시공할 수 있도록 해주기 위해서 내부거푸집(A)과, 이 내부거푸집(A)의 내부에서 수평이동할 수 있도록 되어 있는 2개이상의 내부거푸집용 지지프레임(B)과, 외부거푸집(C)과, 이 외부거푸집(C)의 외측에서 수평이동할 수 있도록 되어 있는 외부거푸집용 지지프레임(D)으로 이루어진 터널형수로의 연속시공용 거푸집조립체임. Within, outside the subject innovation is after the channel construction so that the more robust assembly to cope with a large pressure of the concrete which is poured the inner formwork and the outer formwork relates to a suitable mold assembly for the construction of continuous for a large tunnel Hung seamless, dice the following inner formwork (a) in order now to allow easy access to the installation position going to move horizontally for quick construction successively waterways, the inner formwork (a) 2 or more inner die which is to be moved horizontally in the interior of the the supporting frame (B) and the external mold (C), and a continuous to the outside mold tunnel formed by the outside outer mold support frame (D) for which is to be moved horizontally in the (C) Hung common die assembly cheim .

Description

터널형수로의 연속시공용 거푸집조립체{Mould assembly for constructing the tunnel type water conduit} When continuous common die assembly of the tunnel Hung {Mould assembly for constructing the tunnel type water conduit}

본 고안은 터널형수로의 연속시공용 거푸집조립체에 관한 것으로서, 특히 수로의 폭이 2m이상이고 높이가 2.4m이상인 대형의 터널형수로를 이음새없이 연속적으로 시공하는데 적합한 거푸집조립체에 관한 것이다. The subject innovation relates to a mold assembly suitable for installation in a row without a seam, and in particular the channel widths of 2m or more in the large tunnel Hung height is less than 2.4m relates to a continuous during common die assembly of the tunnel Hung.

종래에 대한민국 특허 제 0236423 호에 제시된 본 고안자에 의한 박스형수로의 연속시공방법 및 그 거푸집은 비교적 소형의 박스형수로를 시공하는데는 매우유용한 것이나 대형의 터널형수로에 적용할 경우 내,외부 거푸집의 크기와 중량이 커지는 까닭에 작업자가 손쉽게 조립, 해체하기가 매우 어려웠었을 뿐만 아니라 구조적으로도 타설되는 콘크리트의 큰 압력에 대하여 큰 저항력을 발휘할 수 없어서 안전하게 시공할 수 없었다. How a series of box-shaped channel according to the present inventor set out in the Republic of Korea Patent No. 0,236,423 call for the conventional construction and the dice would very useful in the construction of a relatively small box-shaped channel when applied to a large tunnel Hung in the size of the outer mold and easy access to the operator because the weight of a large assembly, as well as eoteul very difficult to dismantle structural one could be safe because you can exert a great resistance against the construction of the great pressure of concrete being poured.

본 고안은 내부거푸집과 외부거푸집을 타설되는 콘크리트의 큰 압력에 대응할 수 있도록 보다 견고하게 조립할 수 있고 수로시공 후 해체되는 내,외부 거푸집을 다음 시공위치로 손쉽게 수평이동시켜가면서 신속하게 연속적으로 시공할 수 있는 터널형수로의 연속시공용 거푸집조립체를 제공하는데 기술적 과제를 둔 것이다. The subject innovation is an internal die and can be more securely assembled to respond to large pressure in the concrete to be cast-in-place external die and the number going in, to the external mold and easy access level to the next installation position after construction dismantled quickly be installed by continuously be continuous to the tunnel Hung that will put the technical problem to provide a common die assembly.

도 1은 본 고안에 의한 거푸집조립체의 한 실시예를 보인 정면도. 1 is a front view showing one embodiment of a die assembly of the present invention;

도 2는 도 1에서 보인 거푸집조립체의 부분 확대 종단면도. Figure 2 is a longitudinal cross-sectional close-up portion of the die assembly shown in Figure 1;

도 3은 도 1에서 보인 외부 거푸집 받침의 평면도. 3 is a plan view of the outer support die shown in Figure 1;

도 4는 도 1에서 보인 바닥시공 부재의 사시도. Figure 4 is a perspective view of the floor construction element 1 shown in Fig.

도 5는 도 1에서 보인 내부거푸집용 지지프레임의 측면도. Figure 5 is a side view of a support frame for the inner mold shown in Figure 1;

도 6은 도 1에서 보인 외부거푸집용 지지프레임의 측면도. Figure 6 is a side view of a support frame for the outer mold shown in Figure 1;

도 7은 본 고안에 의한 거푸집조립체의 다른 실시예를 보인 정면도. Figure 7 is a front view showing another embodiment of a die assembly of the present invention;

본 고안은 도 1내지 도 6에 예시한 바와 같이 내부거푸집(A)과, 이 내부거푸집(A)의 내측에서 수평이동할 수 있도록 되어 있는 2개이상의 내부거푸집용 지지프레임(B) 그리고 외부거푸집(C)과, 이 외부거푸집(C)의 외측에서 수평이동할 수 있도록 되어 있는 2개이상의 외부거푸집용 지지프레임(D)으로 이루어진 것이다. The subject innovation is the inner formwork (A), and the inner formwork (A) inside the at least two internal formwork supporting frame (B) and outer mold for, which is to be moved horizontally in the as illustrated in Figs. 1 to 6. Fig. ( C), and this will support frame made of a (D) is at least two for the outer mold so as to be movable in the horizontal in the outer side of the outer mold (C).

내부거푸집(A)은 강판으로 된 바닥 시공 부재(10)와, 이 바닥 시공 부재(10)의 양측 가장자리에 조립되는 각파이프와 같은 바닥 모서리 시공 부재(12),(12')와, 이 바닥 모서리 시공 부재(12),(12')위에 조립되는 천정을 포함하는 내측벽 시공부재(14),(14')로 이루어져 있다. And the inner formwork (A), and the bottom construction member 10, a steel plate, a bottom edge construction member 12, such as a square pipe is assembled on opposite side edges of the bottom construction member 10, 12 ', the bottom It consists of "the inner wall construction member (14, 14, including the ceiling that is assembled on top) edge of the construction element 12, 12 '.

상기 바닥 시공 부재(10)의 윗쪽에는 나중에 설명되는 내부거푸집용 지지프레임(B)이 놓여지는 안내레일(16)과, 안내레일(16')이 길이방향으로 평행하게 고정되어 있다. The upper side of the floor construction element 10 has an internal mold support frame (B) is parallel to the fixed guide rail 16 and the guide rail (16 ') the longitudinal axis is placed for that is explained later.

그리고 상기 바닥 시공 부재(10)의 아래쪽에는 스페이드(spade)(18),(18')가 조립되어 있어서 바닥 시공 부재(10)가 지면으로부터 시공할 수로의 바닥두께에 해당하는 높이에 떠있는 상태로 유지될 수 있도록 되어 있다. And floating on the height that has a spade (spade) (18), (18 ') the bottom construction member (10) in the assembly below the floor construction element (10) corresponds to the bottom thickness of the channel to be constructed from the ground It is to be maintained.

스페이드(18),(18')는 도 2와 도 4에 잘 표현된 바와 같이 앵글강(20)에 한쪽끝이 고정된 나사봉(22)과, 이 나사봉(22)의 다른쪽 끝부분이 나사결합되는 암나사관체(24)로 이루어져 있어서 안내레일(16),(16')과 바닥 시공 부재(10)에 형성된 구멍(26)을 통해서 조여지거나 풀어지는 볼트(28)로 조립되어 있다. The other end of the spade (18), (18 ') is the one end to the angle steel (20) as best represented in FIGS. 24 fixed screw rod 22, a screw rod (22) this is assembled in the female screw tube 24, guide rails 16, 16 'and bolt 28 to be tightened or released through the hole 26 formed in the bottom construction member (10) in made of screwed.

바닥 모서리 시공 부재(12),(12')의 내측에는 도 2에 잘 표현된 바와 같이 구멍(29)을 가진 앵글강(30)이 고정되어 있어서 상기 구멍(29)과 대응하는 바닥 시공 부재(10)의 암나사구멍(32)과 나사결합되는 볼트(34)로 조립, 해체할 수 있도록 되어 있다. In the bottom edge of the construction element 12, angle steel 30 with the hole 29 as best represented in Figure 2 an inner side (12 ') is fixed floor construction element that is in correspondence with the hole 29 ( a female screw hole 32 and the bolt 34 is screwed 10) assembly, are to be dismantled.

그리고 상기 바닥 모서리 시공 부재(12),(12')의 윗쪽에는 구멍(36)을 가진 앵글강(38)이 고정되어 있어서 상기 구멍(36)과 대응하는 내측벽 시공부재(14) ,(14')의 하단부에 있는 암나사구멍(39)과 나사결합되는 볼트(40)로 조립,해체할 수 있도록 되어 있다. And the inner walls of the construction member (14, 14, which method is there fixed the angle steel (38) with a hole (36) above the said bottom corner of the construction element 12, 12 'corresponding to the hole 36 a female screw hole 39 and the bolt 40 is screwed in the lower end of the ') it is to be assembled, dismantled.

내부거푸집용 지지프레임(B)은 도 1, 도 2 및 도 5에 잘 표현된 바와 같이 아래쪽에는 크레들(craddle)(42),(42')이 고정되어 있어서 상기 바닥 시공 부재 (10)에 있는 안내레일(16),(16')을 따라서 수평이동할 수 있도록 되어 있다. Internal mold support frame (B) for the bottom as best represented in Fig. 1, 2 and 5, the cradle (craddle) (42), (42 ') is fixed in which the bottom construction member (10) Therefore, the guide rails 16, 16 'is to be able to move horizontally.

그리고 내부거푸집용 지지프레임(B)의 양외측과 윗쪽에는 여러개의 홈형강(44)이 고정되어 있고, 이 홈형강(44)과 상기 지지프레임(B)에는 구멍(46)이 형성되어 있으며, 이 구멍(46)의 한쪽에는 너트(48)가 고정되어 있어서 상기 너트(48)와 나사결합되는 볼트(50)를 조이거나 푸는 것에 의해서 상기 홈형강(44)에 끼워지는 H형강과 같은 밀대(52)를 내측벽시공부재(14),(14')쪽으로 밀착되게 근접시켜주거나 멀어지도록 하면서 내측벽시공부재(14),(14')를 지지해줄 수 있도록 되어 있다. And, the both outer sides and top of the inner mold support frame (B) for and are fixed a number of home-beams (44), has a hole 46 is formed in the support frame (B) and the home-beams 44, one end of the hole 46, the push rod, such as H-beams to be fitted to the groove shaped steel (44) by that nut 48 is in a fixed tighten the bolt 50 screwed with the nut (48) and unwinding ( 52) is the inner walls of the construction member (14), to give the support a), the inner wall construction member (14, 14 and away jugeona to tightly close-up) (14.

외부거푸집(C)은 상기 내부거푸집(A)의 외측에서 조립되는 외측벽 시공 부재 (54),(54')로 이루어져 있다. Outer mold (C) consists of the outer wall construction member 54, 54 'which is assembled on the outside of the inner formwork (A).

외부거푸집용 지지프레임(D)은 도 1, 도 2 및 도 6에 잘 표현된 바와 같이 상기 외측벽 시공부재(54),(54')를 지지해줄 수 있도록 2개의 수직막대(56),(56')의 상부가 수평막대(58)로 연결되어 있다. External mold support frame for (D) is 1, 2, and two vertical bars 56. As best represented in Figure 6 to give support to the outer wall construction member 54, 54 ', (56 there is an upper portion of ') is connected to the horizontal bar (58).

상기 수직막대(56),(56')의 하단부에는 크레들(60),(60')이 고정되어 있고, 상기 수평막대(58)의 아래쪽에도 크레들(62),(62')이 고정되어 있다. Said vertical rod (56), (56) the lower end of, the cradle (60), (60 'and is fixed), a cradle 62, 62' is fixed to the underside of the horizontal bar (58) .

그리고 상기 수직막대(56),(56')의 내측에는 여러개의 홈형강(64)이 고정되어 있고, 이 홈형강(64)과 상기 수직막대(56),(56')에는 구멍(66)이 형성되어 있으며, 이 구멍(66)의 한쪽에는 너트(68)가 고정되어 있어서 이 너트(68)와 나사결합되는 볼트(70)를 조이거나 푸는 것에 의해서 상기 홈형강(64)에 끼워지는 H형강과 같은 밀대(72)를 상기 외측벽 시공부재(54),(54')쪽으로 밀착되게 근접시켜주거나 멀어지도록 하면서 외측벽 시공 부재(54),(54')를 지지해줄 수 있도록 되어 있다. And, the hole 66 'inside has several groove-beams (64) and is fixed, the grooves beams 64 and the vertical bar (56), (56), the vertical bars 56, 56' and is formed, at one of the holes 66, the nut 68 is in a fixed fitted to the nut 68 and threaded into the groove section steel (64) by being pinched or relax the bolt (70) H 'while away jugeona by close-tightly towards the outer wall construction element (54), (54 a push rod 72, such as beams in the outer wall construction member 54, 54' is to give the support a).

상기 외부거푸집(C)과 외부거푸집용 지지프레임(D)은 도 1 ~ 도 3에 잘 표현된 바와 같이 한쌍의 받침틀(74),(74')위에 설치된다. The outer mold (C) and external formwork support frame (D) for are provided on the pair of support frame 74, 74 'as is also well represented in the 1 to 3.

받침틀(74),(74')은 일정한 간격으로 배열되는 여러개의 홈형강(76),(76')의 내측 웹(web)(78)에는 외부거푸집(C)의 하단부가 끼워지는 홈형강과 같은 레일 (80),(80')이 고정되어 있고, 상기 홈형강(76),(76')의 윗쪽에는 상기 외부거푸집용 지지프레임(D)의 하단부에 있는 크레들(60),(60')이 놓여지는 L형강과 같은 레일(82),(82')이 고정되어 있다. Support frame 74, 74 'has a number of groove-beams (76), (76 are arranged at regular intervals "Home beams has inner web (web) (78) of) the lower end of the outer mold (C) which is fitted with such as rails 80, 80 'a are fixed, the home-beams 76, 76', the cradle 60 is in the lower end of the support frame (D) for the outer mold top of, (60 ' ) are the rails 82, 82 ', such as L-beam is fixed is placed.

이와 같은 받침틀(74)과 받침틀(74')은 양단부에 암나사관(84),(84')이 고정된 철근으로 이루어진 간격유지막대(86)와, 상기 레일(80),(80')의 아래쪽에서 상기 홈형강(76),(76')의 웹들을 관통하여 상기 암나사관(84),(84')과 나사결합되는 볼트(88),(88')를 조이거나 푸는 것에 의해서 소정의 간격으로 조립되거나 분리된다. In the same support frame 74 and the support frame (74) is internally threaded tube (84), (84 in both end portions ") is held bar intervals consisting of a fixed reinforcement 86 and the rails 80, 80 ' at the bottom of the predetermined said groove-beams 76, 76 'the female screw tube to pass through the web 84, 84' and due to tighten or relax the bolt (88), (88 ') is screwed It is assembled or separated with an interval.

즉, 받침틀(74)과 받침틀(74')은 시공할 수로의 폭에 해당하는 간격이 유지되도록 간격유지막대(86)와 볼트(88),(88')로 조립되었다가 수로의 시공 후 볼트 (88),(88')를 푸는 것에 의해서 분리, 해체되고, 간격유지막대(86)는 콘크리트속에 묻혀진 상태로 남아 있게 된다. That is, the support frame 74 and support frame 74 'is the cavity-holding bar 86 and the bolt 88 to be retained, (88 a distance corresponding to the width of the channel to be constructed, assembled in) after construction of the channel bolt 88, the separation, dissolution and by solving the (88), the gap holding rod 86 remains in the state buried in the concrete.

본 고안에 있어서, 내측벽시공부재(14),(14')를 바닥 시공 부재(10) 위에서 수평이동되는 내부거푸집용 지지프레임(B)과 함께 수평이동시켜주기 좋도록 해주기 위해서는 도 1과 도 2에 예시한 바와 같이 내측벽시공부재(14),(14')의 내측에는 한쪽에 장공(90)을 가진 홈형강(92)을 고정하고, 이와 대응하는 내부거푸집용 지지프레임(B)에는 마주보는 구멍(94)을 형성하며, 이 구멍(94)의 한쪽에는 너트(96)를고정하여서, 이 너트(96)와 나사결합되고 상기 구멍(94)과 장공(92)을 관통하는 선단부에 밀대(98)가 회전할 수 있도록 끼워 맞춤된 볼트(100)로 상기 내측벽시공부재(14),(14')와, 내부거푸집용 지지프레임 (B)을 결합하여서 상기 볼트(100)를 조이거나 푸는 것에 의하여 내측벽시공부재(14),(14')를 내부거푸집용 지지프레임(B)에서 외측으로 밀어주거나 내측으로 당겨줄 수 In the present design, the inner wall construction members 14, 14 'to order now to good cycle by horizontal movement with the inner mold support frame (B) for being moved horizontally on the floor construction member 10, Fig. 1 and Fig. the inner wall construction member as illustrated in Figure 2 (14), (14 ') inside the fixed grooves beams 92 with a long hole 90 on one side, and this corresponds to the inner mold, the support frame (B) for which the facing and seeing a hole 94, hayeoseo fixed to one side the nut 96 of the hole 94, the nut 96 is engaged with the screw and the distal end portion extending through the hole 94 and the long hole 92, push rod 98 is with the bolt (100) fitted so as to rotate the inner walls of the installation member 14, 14 'and, hayeoseo coupling the support frame (B) internal mold tighten the bolt 100 or the inner wall member constructed by solving (14), (14 '), the number of lines jugeona pushed outwardly pulled from the inside the support frame (B) internal mold 있도록 함과 아울러서 수로의 시공 후 제거되거나 내부거푸집용 지지프레임(B)쪽으로 이동되는 바닥 모서리 시공 부재(12),(12')와 밀대(52)들에 의해서 수로의 천정과 내측벽으로부터 이탈되는 상기 내측벽시공부재(14),(14')를 상기 내부거푸집용 지지프레임(B)과 결합된 상태를 유지할 수 있도록 해주는 것이 좋다. So that also the removed after construction of ahulreoseo channel or inner mold support frame (B) the bottom edge of the construction element 12 is moved toward, 12 'and the channel overhead by the push rod (52) for and to be detached from the inner wall it is recommended that the inner walls of the installation member 14, 14 'to help keep the state coupled with the support frame (B) for the inner mold.

그리고 본 고안에 있어서, 수로의 바닥쪽으로 타설되는 콘크리트에 기포가 남아있지 않도록 하여 콘크리트가 치밀하게 타설, 양생될 수 있도록 해주기 위해서는 도 4에 예시한 바와 같이 바닥 시공 부재(10)에 공기배출구멍(102)을 형성해주는 것이 좋다. And according to the present invention, in order to in the concrete to be poured into the bottom of the channel so that no air bubbles remain now to concrete can be carefully pouring, curing air to the floor construction element 10 as illustrated in Figure 4, the discharge hole ( 102), it is recommended that the form.

또 타설되는 콘크리트를 치밀하게 해주는 바이브레이터와 같은 장비를 싣고 편리하게 이동시켜 가면서 사용할 수 있도록 해주기 위해서는 도 7에 예시한 바와 같이 내부거푸집용 지지프레임(B)의 크레들(42)과 크레들(42')사이에 공간부(104)를 형성하고, 바닥 시공 부재(10)위에는 그 길이 방향으로 안내레일(106),(106')을 고정시켜서 이 안내레일(106),(106')을 따라서 회전하는 바퀴(108),(108')가 달린 이동대차 (110)를 설치해주는 것이 좋다. In order now to be carrying equipment such as a vibrator that enables dense to be cast-in-place concrete using going to conveniently move Figure 7 the cradle 42 and the cradle 42 'of the support frame (B) for the internal formwork, as illustrated in and between the forming space 104, in the longitudinal direction above the bottom construction member 10, the guide rail 106, "thereby fixing the guide rail (106), (106 106 'to rotate a) thus it is recommended that the installation of wheels 108, 108 'are moved with the balance (110).

도면중 미설명 부호 112는 내부거푸집(A)의 내측벽시공부재(14)(14')와, 외측벽시공부재(54),(54')를 시공할 수로의 벽두께에 해당하는 간격으로 유지시켜 주는 간격유지구이다. Figure reference numeral 112 of which is maintained at a spacing that corresponds to the inner walls of the installation member 14, 14 'and the outer wall construction element (54), (54' wall thickness of the channel to be constructed a) of the inner formwork (A) by a distance holder, which.

이와 같이 구성된 본 고안의 조립은 도 1 ~ 도 6에 예시한 바와 같이 다듬어진 지면(E)위에 받침틀(74)과 받침틀(74')을 올려놓고 간격유지막대(86)와 볼트 (88),(88')로 받침틀(74)과 받침틀(74')을 평행하게 조립하는 단계와, 하반부 철근(F 1 )을 배근하는 단계와, 위, 아래쪽에 각각 안내레일(16),(16')이 고정되고 스페이드(18),(18')가 조립되는 바닥시공부재(10)를 지면(E)위에 떠있도록 설치하고 이 바닥시공부재(10)의 양측 가장자리에 바닥 모서리 시공부재(12),(12')를 조립하며, 이 바닥모서리 시공부재(12),(12')위에 내측벽시공부재(14),(14')를 세워조립하고 이와 같이 조립되는 내부거푸집(A)속에 2개이상의 내부거푸집용 지지프레임 (B)을 소정의 간격으로 설치하는 단계와, 상반부 철근(F 2 )을 배근하는 단계와, 상기 받침틀(74), (74')의 내측에 있는 레일(80),(80')에 외측 Thus the invented assembly are Figs. 1 to 6 the trimmed binary ground (E) on the support frame 74 and the support frame (74 ') up place with bolts 88, the gap holding rod (86) a as illustrated in the configured, (88 ') to the support frame 74 and the support frame (74; and the lower half reinforcement (F 1); and the above, each guide rail 16 at the bottom of the reinforcement to the parallel assembled), (16') the fixed and the spade (18), (18 ') the bottom construction member 10, the ground (E) floating installation and a floor construction bottom edge to side edge of the member 10, the construction member 12, so that on being assembled, ', and assembling, the bottom edge of the construction member (12), (12, 12' in) on the inner wall construction member 14, the assembly stand (14 ') and the inner formwork (a) which is assembled in this way two comprising the steps of: installing for more internal mold support frame (B) with a predetermined space, the inner rail (80) in a method comprising reinforcement the upper reinforcement (F 2), the support frame 74, 74 ', the outer (80 ') 시공부재(54),(54')의 하단부를 끼워 넣고 받침틀(74),(74')의 윗쪽에 있는 레일(82),(82')위에 2개이상의 외부거푸집용 지지프레임(D)을 소정의 간격으로 설치하여 외부거푸집용 지지프레임(D)의 수평막대(58)에 있는 크레들(62),(62')에 상기 외측벽시공부재(54), (54')의 상단부를 끼워 넣어서 외부거푸집(C)을 조립하는 단계와, 상기 내부거푸집 (A)과 외부거푸집(C)사이에 콘크리트를 타설하기 전에 2개이상의 내부거푸집용 지지프레임(B)의 외측에 있는 홈형강(44)들에 밀대(52)를 끼워 넣고 볼트(50)를 조여주고, 2개이상의 외부거푸집용 지지프레임(D)의 내측에 있는 홈형강(64)들에밀대(72)를 끼워 넣고 볼트(70)를 조여서 상기 내측벽시공부재(14),(14')와, 외측벽시공부재(54),(54')가 타설되는 콘크리트의 압력에 크게 저항할 수 있도록 해주는 단계로 조립이 완료된다. The construction member 54 'sandwiched the lower end of the support frame (74), (74 54') rail 82, 82 'on the support frame for the outer mold of two or more (D) on the top of the put into the upper end of (the outer wall construction members 54, 54) on the cradle 62, 62 'in the horizontal bar 58 of the support frame (D) installed at a predetermined interval for external formwork external and assembling the mold (C), of the internal formwork (a) and external formwork (C) home-beams (44) outside the at least two internal formwork supporting frame (B) for prior to pouring concrete between to put into the plunger 72 to the home-beams 64 in the inner side of the support frame (D) put into the plunger (52) for giving tightening the bolt 50, the outer of two or more die bolts 70 a step in which the inner walls of the construction member 14, 14 'and the outer wall construction member 54, 54' can be increased so that the resistance to pressure of the concrete which is cast-in-place assembly is completed by tightening.

이와 같이 조립되는 내부거푸집(A)과 외부거푸집(C)사이로 타설되는 콘크리트가 양생된 후 본 고안은 다음과 같은 순서로 해체된다. The subject innovation after the concrete is cured to be poured through this way the inner mold (A) and external formwork (C) to be assembled is dismantled in the following sequence.

내부거푸집용 지지프레임(B)에 조여져 있는 볼트(50)를 느슨하게 풀어서 홈형강(44)속에 끼워져 있는 밀대(52)를 빼내어 제거한다. Releasing the loose bolt 50 in fastened to the support frame (B) Internal mold to remove the stack of push rod 52 which is inserted into the groove section steel (44).

바닥모서리시공부재(12),(12')를 내측벽시공부재(14),(14')와, 바닥시공부재 (10)에 고정시켜 주고 있는 볼트(34),(40)을 풀어서 상기 바닥모서리시공부재(12) ,(12')를 먼저 제거하여 내측벽시공부재(14),(14')를 수로의 내측벽과 천정으로부터 떼어내고 바닥시공부재(10)의 안내레일(16),(16')을 따라서 수평이동하는 내부거푸집용 지지프레임(B)을 이용하여서 수로 밖으로 제거한다. Bottom edge construction member 12, 12 'the inner walls of the installation member 14, 14' and, by loosening the bolts 34, 40 which give to fixed to the bottom construction member 10, the bottom corner construction member 12, "to remove the first inner wall construction element (14), (14, 12 ') guide rails (16) of the detach from the inner side wall and the ceiling of the waterway floor construction member 10, (16 ') according to hayeoseo using a horizontal movement inside the mold support frame (B) for to be removed out of the channel.

그리고 바닥시공부재(10)와 스페이드(18),(18')를 고정시켜주고 있는 볼트(28)를 풀어주고 콘크리트속에 묻힌 상기 스페이드(18),(18')로 부터 바닥시공부재(10)를 분리시켜서 내부거푸집(A)을 해체한다. And floor construction member 10 and the spade (18), "to release the bolt 28, which give to secure the spade (18), (18, buried in concrete 18, from) the bottom construction member (10) the separation by deconstructs the inner formwork (a).

이어서 외부거푸집용 지지프레임(D)에 조여져 있는 볼트(70)를 느슨하게 풀어서 홈형강(64)속에 끼워져 있는 밀대(72)를 빼내어 제거하고, 받침틀(74),(74')의 안내레일(82),(82')을 따라서 수평이동하는 상기 외부거푸집용 지지프레임(D)과, 외부거푸집(C)을 해체하며, 받침틀(74),(74')의 외측에서 간격유지막대(86)와 조여져 있는 볼트(88),(88')를 풀어서 콘크리트에 묻힌 상기 간격유지막대(86)로부터 상기 받침틀(74),(74')을 제거하여 해체작업을 완료한다. Then the guide rail (82 of solving loosen the bolt 70 in fastened to the support frame (D) for the outer mold to remove the stack of push rod 72 which is inserted into the groove-beams 64, support frame 74, 74 ' ), (82 ') for Therefore, dismantle the horizontal movement of the outer mold support frame (D) for which, and the outer mold (C), support frame (74), (74') apart from the outer side holding rod 86 of the 'by solving the support frame (74), (74 from said gap holding rod (86) embedded in the concrete bolts 88, 88' tightened in removing) to complete the disassembly.

본 고안은 이와 같은 조립과 해체를 반복하면서 연속적으로 터널형수로를 시공하는 것이다. The subject innovation is to the construction of the tunnel Hung continuously while repeating such assembly and disassembly.

본 고안에 있어서, 내부거푸집(A)과 외부거푸집(C)자체는 통상의 조립식 거푸집이나 단일 거푸집으로 할 수 있고, 그 길이는 5m내외로 이루어져 있으며, 예시도면에서 수로의 단부용 거푸집의 표현은 생략되어 있다. According to the present invention, the inner mold (A) and external formwork (C) itself may be a conventional prefabricated mold or a single mold, its length is made up of 5m around, representation of a single-part-forming die of the number in the illustrative drawings are It is omitted.

본 고안은 내부거푸집(A)과 외부거푸집(C)을 각각 내부거푸집(A)의 바닥시공부재(10)위에서 수평이동되는 내부거푸집용 지지프레임(B)과, 받침틀(74), (74')위에서 수평이동되는 외부거푸집용 지지프레임(D)으로 보다견고하게 조립할 수 있고, 해체작업을 신속하고 쉽게 하면서 터널형 수로를 단시간에 연속적으로 시공할 수 있는 장점이 있다. The subject innovation is the inner formwork (A) and external formwork (C) of each inner formwork (A) inside the mold support frame (B) for the horizontal movement on the bottom construction member (10) of the, support frame (74), (74 ' ) can be more firmly assembled with the outer mold supporting frame (D) for being moved on a horizontal, there is an advantage that, while the disassembly work quickly and easily be constructed as a continuous tunnel-shaped channel in a short time.

Claims (5)

  1. 안내레일(16),(16')이 윗쪽에 길이방향으로 고정되어 있고 스페이드(18), (18')가 아래쪽에 조립되어 지면으로부터 떠있는 상태로 유지되는 바닥시공부재 (10)와 이 바닥시공부재(10)의 양측가장자리에 조립되는 각파이프와 같은 바닥모서리시공부재(12),(12')와 이 바닥모서리시공부재(12),(12')위에 조립되는 내측벽시공부재(14),(14')를 포함하는 내부거푸집(A)과, 바닥시공부재(10)의 안내레일(16), (16')과 대응하는 크레들(42),(42')이 하부에 고정되어 있어서 내부거푸집(A)속에서 수평이동할 수 있도록 되어 있는 2개이상의 내부거푸집용 지지프레임(B)과, 외측벽시공부재(54),(54')를 포함하는 외부거푸집(C)과, 여러개의 홈형강(76),(76')의 내측과 윗쪽에 각각 외측벽시공부재(54),(54')의 하단부가 지지되는 레일(80), (80')과, 레일(82),(82')이 길이방향으로 고정되어 있고 양단 Guide rails 16, 16 'are fixed in the longitudinal direction on the upper and the spade (18), (18') the bottom construction member (10) is maintained in the state of being assembled to the lower left from the surface and the bottom the bottom edge, such as a square pipe is assembled on each side edge of the construction element 10 construction member 12, the inner wall construction element (14 to be assembled over 12 'and the bottom edge of the construction element 12, 12' ), (14 ') inside the mold (a) and the guide of the bottom construction member (10) rails (16 and 16 comprising the "cradle (42 corresponding to a)), (42') is fixed to the lower in the inner mold (a) it is to be able to move horizontally more than one support for the inner die frame in (B) and the outer wall construction member 54, 54 'outer mold (C) containing, and several Home-beams 76, "respectively, the outer wall construction element (54), (54 inside and above the rail (80) which lower end is supported on), (80 '), a rail 82, 76', (82 ') it is fixed in the longitudinal direction and at both ends 부에 암나사관(84), (84')이 고정된 간격유지 막대(86)와 볼트(88),(88')에 의해서 일정한 간격이 유지되도록 조립되는 받침틀(74),(74')과, 받침틀(74),(74')의 레일(82),(82')과 대응하는 크레들(60),(60')이 고정된 수직막대(56),(56')와 외측벽시공부재(54),(54')의 상단부가 지지되는 크레들(62),(62')이 고정된 수평막대(58)로 이루어져 있어서 받침틀(74).(74')위에서 수평이동할 수 있도록 되어 있는 2개이상의 외부거푸집용 지지프레임(D)으로 이루어진 것을 특징으로 하는 터널형수로의 연속시공용 거푸집 조립체. Portion in internally threaded tube 84, 84 'are fixed gap holding rod (86) and bolt (88), (88, support frame 74 is assembled so as to maintain a constant spacing by a), (74') and , support frame (74), (74 ') rails (82), (82') of the corresponding cradle, to 60, 60 'vertical rods 56 is fixed, 56' and the outer wall construction member ( 54), (54 2, which is so made up ") the upper end a cradle which is supported (62), (62 ') of the horizontal bar 58 is fixed in the number of horizontal moving on the support frame 74 (74') one more common die assembly during run of the tunnel Hung, characterized in that the outer die made of the support frame (D) for.
  2. 제 1항에 있어서, 내부거푸집용 지지프레임(B)의 양외측과 윗쪽에는 밀대(52)가 끼워지는 홈형강(44)이 고정되어 있고, 밀대(52)가 내부거푸집용 지지프레임(B)의 한쪽에 고정된 너트(48)와 결합되는 볼트(50)에 의해서 이동할 수 있도록 되어 있으며, 외부거푸집용 지지프레임(D)의 수직막대(56),(56')내측에는 밀대(72)가 끼워지는 홈형강(64)이 고정되어 있고, 밀대(72)가 수직막대(56),(56')의 한쪽에 고정된 너트(68)와 결합되는 볼트(70)에 의해서 이동할 수 있도록 되어 있는 것을 특징으로 하는 터널형수로의 연속시공용 거푸집 조립체. The method of claim 1, wherein both outer sides and top of the support frame (B) Internal mold had a push rod (52) is a screw hole beams 44 is fitted, push rod 52, the support frame (B) Internal mold and a is to be moved by the bolt 50 is engaged with a nut 48 fixed to the one side, the inner side vertical bars 56, 56 'of the outer formwork support frame (D) for a, the plunger 72 and a groove section steel (64) is fitted is fixed, the plunger 72 is a vertical bar 56, which is to be moved by the bolt 70 to be engaged with a nut 68 fixed to one side of (56) common mold assembly during run of the tunnel, characterized in that Hung.
  3. 제 1항에 있어서, 내부거푸집용 지지프레임(B)에 고정된 너트(96)와 결합되어 있으며, 내측벽시공부재(14),(14')의 내측이 고정된 홈형강(92)의 장공(90)을 관통하는 볼트(100)의 선단부에는 밀대(98)가 회전할 수 있도록 끼워 맞춤되어 있어서 장공(90)을 통해서 위, 아래로 움직이는 내측벽과 천정시공부재(14),(14')를 볼트(100)로 밀어주거나 당겨줄 수 있도록 되어 있는 것을 특징으로 하는 터널형수로의 연속시공용 거푸집 조립체. According to claim 1, which is combined with a nut 96 fixed to the support frame (B) for an internal die, inner walls of the long hole of the installation member 14, 14 'a groove section steel 92 inside the fixing of the leading end of the bolt 100 that passes through the 90, the plunger 98 is in the fitting so as to rotate the above, the inner wall and ceiling installation member 14 moves down through the slot (90, 14 ' ) a common die assembly during run of the tunnel Hung, characterized in that which is to boost jugeona pull bolt (100).
  4. 제 1항에 있어서, 바닥시공부재(10)에 공기배출구멍(102)이 형성되어 있는 것을 특징으로 하는 터널형수로의 연속시공요 거푸집 조립체. The method of claim 1, wherein the continuous assembly of the formwork construction requires a tunnel Hung such a manner that the air discharge hole 102 formed in the bottom construction member (10).
  5. 제 1항에 있어서, 내부거푸집용 지지프레임(B)의 크레들(42)과 크레들(42')사이에는 공간부(104)가 형성되어 있고, 바닥시공부재(10)위에는 안내레일(106),(106')이 길이방향으로 고정되어 있으며, 이 안내레일(106),(106')위에는 바퀴(108),(108')가 달린 이동대차(110)가 설치되어 있는 것을 특징으로 하는 터널형수로의 연속시공용 거푸집 조립체. The method of claim 1, wherein the cradle 42 and the cradle 42 'between is formed on the space part 104, the bottom construction member 10, the guide rails 106 on top of the inner mold support frame (B) for, 106 'a is fixed in the longitudinal direction, the guide rails 106, 106' above the wheels 108, 108 'is attached moves balance tunnel Hung, characterized in that (110) is installed, when continuous common die assembly to.
KR20030027225U 2003-08-25 2003-08-25 Mould assembly for constructing the tunnel type water conduit KR200337174Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR20030027225U KR200337174Y1 (en) 2003-08-25 2003-08-25 Mould assembly for constructing the tunnel type water conduit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR20030027225U KR200337174Y1 (en) 2003-08-25 2003-08-25 Mould assembly for constructing the tunnel type water conduit

Publications (1)

Publication Number Publication Date
KR200337174Y1 true KR200337174Y1 (en) 2004-01-07

Family

ID=49341752

Family Applications (1)

Application Number Title Priority Date Filing Date
KR20030027225U KR200337174Y1 (en) 2003-08-25 2003-08-25 Mould assembly for constructing the tunnel type water conduit

Country Status (1)

Country Link
KR (1) KR200337174Y1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2460306B (en) * 2008-05-29 2013-02-13 Intrasonics Sarl Data embedding system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2460306B (en) * 2008-05-29 2013-02-13 Intrasonics Sarl Data embedding system

Similar Documents

Publication Publication Date Title
US1701113A (en) Method of and apparatus for pouring concrete walls and floors of steel and concrete frame buildings
US4052031A (en) Adjustable concrete form apparatus
US4397441A (en) Wall form and method of assembly thereof
US4372906A (en) Method and apparatus for pre-casting steel reinforced concrete box-like modules
US3255990A (en) Mold for unitary building structure
US3490729A (en) Form assembly for molding monolithic concrete building
US4846437A (en) Bracket for supporting concrete formwork
US6270057B1 (en) Reuseable multi-story building construction guardrail system
US4272050A (en) Method and apparatus for pre-casting steel reinforced concrete box-like modules
US6023902A (en) Frame structure and method of construction by using the same
US3182374A (en) Method of and apparatus for molding concrete buildings monolithically
KR100993880B1 (en) Deck plate with raised bottom materal
US3170217A (en) Concrete slab form fill-in panel structure and supporting bracket therefor
US4495131A (en) Method for pre-casting steel reinforced concrete box-like modules
US4127254A (en) Concrete building construction forms
US4679762A (en) Form set-up
US3748806A (en) Concrete wall form
US3822336A (en) Method for forming a masonry wall panel
US20060137269A1 (en) Concrete panel construction system and method of making panels
JP2010007365A (en) Form timbering apparatus and form apparatus
US4003542A (en) Form pans for constructing ribbed slab structures
US2396174A (en) Form for the construction of concrete walls, beams, and the like
US4106743A (en) Adjustable bulkhead for concrete wall forms
US20050016114A1 (en) Masonry block anchor bolt assembly
US3826460A (en) Monolithic structure forming means with metal tubular bracing

Legal Events

Date Code Title Description
REGI Registration of establishment
FPAY Annual fee payment

Payment date: 20041228

Year of fee payment: 3

LAPS Lapse due to unpaid annual fee