KR200241026Y1 - Tunnel Construction Structure for using Wave Profile Type Steel Plate - Google Patents

Tunnel Construction Structure for using Wave Profile Type Steel Plate Download PDF

Info

Publication number
KR200241026Y1
KR200241026Y1 KR2020010009429U KR20010009429U KR200241026Y1 KR 200241026 Y1 KR200241026 Y1 KR 200241026Y1 KR 2020010009429 U KR2020010009429 U KR 2020010009429U KR 20010009429 U KR20010009429 U KR 20010009429U KR 200241026 Y1 KR200241026 Y1 KR 200241026Y1
Authority
KR
South Korea
Prior art keywords
tunnel
construction
shotcrete
corrugated steel
steel sheet
Prior art date
Application number
KR2020010009429U
Other languages
Korean (ko)
Inventor
유근무
Original Assignee
유근무
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 유근무 filed Critical 유근무
Priority to KR2020010009429U priority Critical patent/KR200241026Y1/en
Application granted granted Critical
Publication of KR200241026Y1 publication Critical patent/KR200241026Y1/en

Links

Abstract

본 고안은 터널의 입출구나 계곡부 등의 토피가 얕은 지역에 구축되는 터널건설구조에 관한 것으로, 특히 터널건설 지점을 대규모로 굴착한 후 라이닝콘크리트를 구축하기 위한 거푸집과 거푸집을 지지시켜 주는 지지대를 설치하고 있는 종래의 공법에서 나타나는 제 문제점을 해결하기 위해, 터널 건설지점 양측에 토류벽을 설치하고 상부 반단면을 소규모로 개착하며, 파형강판을 상부 반단면 터널형상으로 조립 설치하고 파형강판 조립체의 내측면에 숏크리트를 쏘아 붙인 후, 나머지 하부 반단면을 마저 굴착하고 그 내측면에 숏크리트를 타설하여서, 굴진된 암반터널과 같은 조건을 만들어 한번 제작된 강재터널폼으로 일관성 있게 연속된 터널을 건설할 수 있게 하여 줌으로써, 라이닝콘크리트를 타설하기 위한 별도의 터널 폼 제작 및 설치 작업이 불필요하게 되므로 공사기간을 단축하고 공사비용을 절감할 수 있으며, 소규모의 굴토공사 만으로도 작업공간이 충분히 확보되므로 자연환경의 훼손 및 파괴를 최소화시킬 수 있고 빠른 기간 안에 자연상태로 복원될 수 있도록 한 파형강판을 이용한 터널건설구조를 제공한다.The present invention relates to a tunnel construction structure that is constructed in a shallow toffee area such as tunnel entry and exit, and particularly, a support for supporting formwork and formwork for constructing lining concrete after excavating a large-scale tunnel construction site. In order to solve the problems of the conventional construction method, the earth walls are installed on both sides of the tunnel construction site, and the upper half section is small-sized, and the corrugated steel sheet is assembled into the upper half section tunnel shape. By shooting shotcrete on the side, excavating the remaining lower half section and placing the shotcrete on the inner side, constructing the same condition as the excavated rock tunnel, and constructing the continuous tunnel with the steel tunnel form made once To create and install a separate tunnel form for placing lining concrete Since it is unnecessary, the construction period can be shortened and construction cost can be reduced, and the work space is secured only by the small pit excavation, so that the damage and destruction of the natural environment can be minimized, and the waveform can be restored to the natural state in a short time. Provide tunnel construction structure using steel plate.

Description

파형강판을 이용한 터널건설구조{Tunnel Construction Structure for using Wave Profile Type Steel Plate}Tunnel Construction Structure for using Wave Profile Type Steel Plate}

본 고안은 터널의 입출구나 계곡부 등의 토피가 얕은 지역에 구축되는 터널에 관한 것으로, 특히 터널건설지점 양측에 토류벽을 설치하고 소규모로 개착한 후 파형강판을 터널형상으로 조립 설치한 다음, 내부에 숏크리트를 쏘아 붙여 굴진된 암반터널과 같은 조건을 만들어 한번 제작된 강재터널폼으로 일관성 있게 연속된 터널을 건설할 수 있도록 함으로써, 라이닝콘크리트를 타설하기 위해 별도의 터널 폼 제작 및 설치 작업이 불필요하게 되므로 공사기간을 단축하면서 공사비용을 절감할 수 있으며, 소규모의 굴토공사 만으로도 작업공간이 충분히 확보되므로 자연환경의 훼손 및 파괴를 최소화시킬 수 있고, 빠른 기간 안에 자연상태로 복원될 수 있도록 한 파형강판을 이용한 터널건설구조에 관한 것이다.The present invention relates to a tunnel that is constructed in a shallow toffee area such as a tunnel entrance or valley. Especially, the earth walls are installed on both sides of the tunnel construction site, and after the small-scale installation, the corrugated steel sheet is assembled in a tunnel shape. The shotcrete is shot on to create the same conditions as the excavated rock tunnel, so that a continuous tunnel can be constructed with the steel tunnel form that has been manufactured once, so that separate tunnel form production and installation work are unnecessary to cast the lining concrete. Therefore, the construction cost can be reduced while shortening the construction period, and the work space is secured only by the small-scale excavation work, so that the damage and destruction of the natural environment can be minimized, and the corrugated steel sheet can be restored to the natural state in a short time. The tunnel construction structure using the present invention.

통상 터널을 굴착하기 위해서는 터널상부의 토피층이 어느 정도 두께이상 되어야 아치 작용에 의해 붕괴되지 않고 터널을 건설할 수 있다.In general, in order to excavate a tunnel, the toffee layer on the upper part of the tunnel must be thicker than a certain thickness so that the tunnel can be constructed without collapsing by the arching action.

그러나, 도1에서 도시된 바와 같이, 지형 조건상 터널의 입출구(A)나 계곡부 (B)의 토피가 얕은 구간에서 불가피하게 터널(T)을 건설하여야 하는 경우가 있다.However, as shown in FIG. 1, there is a case where the tunnel T is inevitably required to be constructed in a section in which the toffee of the entrance / exit A or the valley B of the tunnel is shallow.

이렇게 토피가 얕은 지역은 지반 자체가 견고하지 못하므로 아치 작용을 할 수 없다. 때문에 이러한 경우의 터널은 도2에서 도시된 바와 같이 개착식 터널 공법으로 터널을 건설할 수밖에 없었다.This shallow toffee area cannot be arched because the ground itself is not strong. Therefore, in this case, the tunnel had no choice but to construct the tunnel by the open tunnel method as shown in FIG.

종래 토피가 얕은 지역의 터널건설방법은 도2에서 도시된 바와 같이, 터널의 전단면 라이닝콘크리트(3)가 구축될 수 있는 충분한 크기로 지반(1)을 개착하되, 좌우측의 사면(2)이 붕괴되지 않게 안전한 기울기를 갖도록 큰 범위로 개착작업을 실시한 후, 라이닝콘크리트(3)를 형성하기 위한 거푸집 및 지지대 등을 설치하고, 이 거푸집상에 콘크리트를 타설하여 라이닝콘크리트(3)를 형성하고, 라이닝콘크리트(3)가 경화된 후에 지지대 및 거푸집을 해체한 후, 라이닝콘크리트(3)의 상부에 다시 토사(4)를 되메우기하는 방법으로 공사를 수행하여 왔다.Tunnel construction method of the conventional toffee shallow area, as shown in Figure 2, the ground (1) to the ground enough to build the front surface lining concrete (3) of the tunnel, the slope of the left and right sides (2) After the opening work is carried out to a large extent so as to have a safe slope not to collapse, a formwork and a support for forming the lining concrete 3 are installed, and concrete is laid on the formwork to form the lining concrete 3, After the lining concrete 3 has been cured, the support and the formwork are dismantled, and construction has been carried out by filling the soil 4 again on the upper part of the lining concrete 3.

이와 같은 종래의 터널건설공법은 토피가 얕은 지형조건을 갖는 터널의 입출구나 계곡부에 터널을 구축하기 위해서 라이닝콘크리트를 형성하기 위한 거푸집을 제작하여 설치하고, 거푸집을 견고히 지지시키기 위하여 많은 지지대를 설치함으로써, 거푸집의 설치 및 해체 작업에 많은 경제적 시간적 손실이 뒤따르는 문제점이 있었다.In the conventional tunnel construction method, a formwork for forming lining concrete is installed and installed in order to construct a tunnel at an entrance or a valley of a toffee having a shallow topographic condition, and many supports are installed to firmly support the formwork. Thereby, there was a problem that a lot of economic time is lost in the installation and dismantling work of the formwork.

또한, 굴착부의 안정과 작업공간의 확보등 안전을 고려하여 대규모의 절토공사를 수반하기 때문에 자연 환경의 훼손 및 파괴가 대단위로 발생하게 되며, 이에 따라 자연상태로의 복원이 어렵고 비경제적인 문제점이 있었다.In addition, due to large-scale cutting work in consideration of safety such as the stability of the excavation part and securing the working space, damage and destruction of the natural environment occurs in large units, and therefore, restoration to the natural state is difficult and economically problematic. .

이에 따라, 본 고안은 종래의 터널건설공법에서 나타나는 제 문제점을 해결하고자 안출한 것이다.Accordingly, the present invention has been made to solve the problems shown in the conventional tunnel construction method.

따라서, 본 고안의 목적은 라이닝콘크리트를 구축하기 위한 거푸집과 거푸집을 지지시켜 주는 지지대를 설치하지 않고 파형강판을 이용함으로써 공사기간을 단축하면서 공사비용을 절감하여 주며, 토류벽의 설치를 통해 소규모의 굴토공사 만으로도 작업공간을 충분히 확보함으로써 자연환경의 훼손 및 파괴를 최소화시키고, 빠른 기간 안에 자연상태로 복원될 수 있게 하여 주는 파형강판을 이용한 터널건설구조를 제공하는데 있다.Therefore, the purpose of the present invention is to reduce the construction cost by reducing the construction period by using corrugated steel sheet without installing the formwork for supporting the formwork and the formwork to build the lining concrete, and through the installation of small earth oysters It is to provide a tunnel construction structure using corrugated steel sheet that minimizes the damage and destruction of the natural environment by restoring sufficient working space with earthwork only and restores it to the natural state in a short time.

상기 목적을 달성하기 위해 본 고안은 터널 건설지점의 양측에 토류벽을 설치하고 소규모로 개착하며, 파형강판을 터널형상으로 조립 설치하고, 파형강판 조립체의 내부에 숏크리트를 쏘아 붙여 굴진된 암반터널과 같은 조건을 만들어 주고 한번 제작된 터널폼으로 일관성 있게 연속된 터널을 건설할 수 있도록 한 기술구성을 제공한다.In order to achieve the above object, the present invention installs the earth walls on both sides of the tunnel construction point and installs small-scale, and installs the corrugated steel sheet in the tunnel shape, and shot shotcrete inside the corrugated steel sheet assembly, such as the rock tunnel which is excavated. It creates a condition and provides a technical configuration to construct a continuous tunnel in a tunnel form made once.

도1은 터널이 설치되는 구간의 지형조건을 나타내는 도면1 is a view showing the topographical conditions of the section in which the tunnel is installed

도2는 종래의 개착식 공법에 의해 건설된 터널의 단면도Figure 2 is a cross-sectional view of the tunnel constructed by the conventional open method

도3 내지 도8은 본 고안에 따른 파형강판을 이용한 터널건설구조의 시공예를 단계적으로 보여주는 도면3 to 8 are diagrams showing a construction example of the tunnel construction structure using a corrugated steel sheet according to the present invention step by step

< 도면의 주요부분에 대한 부호의 설명 ><Description of Symbols for Major Parts of Drawings>

1:지반 2:사면1: Ground 2: Slope

3:라이닝콘크리트 4:토사3: lining concrete 4: earth and sand

31:상부 반단면 굴착부 32:숏크리트부31: upper half cross-section excavation 32: shotcrete

33:하부 반단면 굴착부 34:내부 라이닝콘크리트33: lower half section excavation 34: inner lining concrete

35:브래킷 36:H강재35: Bracket 36: H steel

A:입출구 B:계곡부A: entrance and exit B: valley

p:파형강판 h:H파일p: waveform steel sheet h: H file

w:와이어메쉬w: wire mesh

이하, 본 고안의 기술구성을 첨부도면들에 도시되는 본 고안의 시공예들을 통하여 구체적으로 살펴보면 다음과 같다.Hereinafter, look at in detail through the construction examples of the present invention shown in the accompanying drawings the technical configuration of the present invention.

도3 내지 도8에는 터널건설 예정지점의 지반에 본 고안의 파형강판을 이용한 터널건설구조가 적용된 시공예를 단계적으로 보여주고 있다.3 to 8 show a construction example in which the tunnel construction structure using the corrugated steel sheet of the present invention is applied to the ground of the tunnel construction site.

이들 도면에 도시된 바와 같이 본 고안은, 터널을 건설하고자 하는 지점의 토사를 설계되어진 상부 반단면까지 굴착하고, 상부 반단면 굴착부(31)에 파형의 단면으로 형성되면서 호형상으로 굴곡되는 파형강판(p)들을 터널의 상부 반단면 형상으로 조립 설치하며, 파형강판 조립체의 내측에 숏크리트를 타설하고, 파형강판 조립체의 외부에 토사를 되메우기하고, 터널 건설지점의 나머지 하부 반단면을 마저 굴착하고, 하부 반단면 굴착부(33)에 숏크리트를 타설하며, 전체단면 숏크리트부(32)의 내측면에 내부 라이닝콘크리트(34) 공사를 시행하여서 구축되어진 것을 기술구성상의 기본적인 특징으로 한다.As shown in these drawings, the present invention excavates the earth and sand of the point where the tunnel is to be constructed up to the designed upper half cross section, and is formed in the upper half cross section excavation portion 31 in the form of a cross section of a wave shape that is curved in an arc shape. Assemble and install the steel sheets (p) into the upper half-section shape of the tunnel, place shotcrete inside the corrugated steel sheet assembly, backfill the soil to the outside of the corrugated steel sheet assembly, and excavate the remaining lower half section of the tunnel construction site. In addition, the shot concrete is poured into the lower half-section excavation portion 33, and the inner lining concrete 34 construction is performed on the inner surface of the entire cross-section shot concrete portion 32, which is a basic feature in technical construction.

상기와 같은 특징의 본 고안을 실시함에 있어서, 터널 건설지점에 상부 반단면을 굴착할 때 최소한의 규모만 굴착할 수 있도록 도3의 도시와 같이, 굴착되는 부분의 양측지점에 H파일(h)을 이용한 토류벽을 수직하게 설치하고 직각으로 하는 것이 바람직하다.In carrying out the present invention of the above characteristics, as shown in Figure 3 so as to excavate only the minimum size when excavating the upper half-section at the tunnel construction point, the H pile (h) at both sides of the excavated portion It is preferable to install the earth wall using the vertical and at right angles.

본 고안은 이와 같이 최소한의 상부 반단면 굴착부(31)만 확보하여도 터널공사를 진행하는데 아무런 문제가 없으며, 상기와 같이 토류벽을 형성하면서 토사층을 직각으로 개착하는 것은 토사의 굴착량 및 굴착부의 폭을 줄여서 자연 환경파괴를 최소화하고 빠른 원상복구가 이루어지도록 하기 위함이다.The present invention does not have any problem in proceeding the tunnel construction by securing only the minimum upper half-section excavation portion 31 as described above, and the excavation of the soil layer at a right angle while forming the earth wall as described above is the excavation amount and excavation portion of the soil. The purpose is to reduce the width to minimize the destruction of the natural environment and to achieve quick restoration.

그러나, 본 고안을 실시함에 있어서는 반드시 토류벽을 설치하는 것은 아니며 현장상황에 따라 좌우측 사면이 붕괴되지 않게 일정한 기울기를 갖고 큰 범위로 형성하여도 무방하다.However, in carrying out the present invention, the earth wall is not necessarily provided and may be formed in a large range with a constant slope so that the left and right slopes do not collapse depending on the site situation.

상기와 같이 터널 상부 반단면을 굴착한 다음에는, 도4의 도시와 같이 상부 반단면 굴착부(31)의 바닥면 부근에서 굴착부의 내측으로 돌출되는 브래킷(35)들을 상기 토류벽의 H파일(h)들에 나란하게 고정·설치하고, 브래킷(35)위에 H강재(36)를 거치시켜 고정한 후, 그 H강재(36)의 상부에 파형강판(p)의 하단부를 지지시켜 가면서 터널의 상부 반단면 형상으로 조립 설치한다.After excavating the upper half end surface of the tunnel as described above, as shown in FIG. 4, the brackets 35 protruding into the excavation portion near the bottom surface of the upper half end excavation portion 31 are H piles (h) of the earth wall. ) Side by side, and fixed by mounting the H steel 36 on the bracket 35, and then supporting the lower end of the corrugated steel (p) on the top of the H steel 36, the upper half of the tunnel Assemble and install in cross-sectional shape.

이때, 파형강판(p)들의 조립은, 파형강판(p)들을 서로 지그재그 형식으로 배치하여 접합하는 것이 파형강판 조립체의 구조적 강도를 높이는데 유리하다.At this time, the assembly of the corrugated steel sheets (p), it is advantageous to arrange the corrugated steel sheets (p) in a zigzag form to each other to increase the structural strength of the corrugated steel sheet assembly.

상기와 같이 상부 반단면 파형강판 조립체를 완성한 다음에는, 도5의 도시와 같이 파형강판(p)의 내측면에 숏크리트를 타설한다.After completing the upper half-section corrugated steel sheet assembly as described above, shotcrete is poured on the inner surface of the corrugated steel sheet p as shown in FIG.

이때, 숏크리트가 잘 부착되도록 파형강판(p)의 내측면에 와이어메쉬(w)를 걸어서 배치한 다음 숏크리트를 타설한다.At this time, the wire mesh w is placed on the inner surface of the corrugated steel sheet p so that the shotcrete is attached well, and then the shotcrete is poured.

상부 반단면에 숏크리트부(32)를 시공한 다음에는, 도6의 도시와 같이 파형강판(p)의 외측 주변에 토사 되메우기를 실시한다.After the shotcrete portion 32 is constructed on the upper half end surface, the soil refilling is performed around the outer side of the corrugated steel sheet p as shown in FIG.

다음으로, 도7의 도시와 같이 터널 건설지점의 나머지 하부 반단면을 마저 굴착하고, 하부 반단면 굴착부(33)에 숏크리트를 타설하여 전체 단면에 대한 숏크리트부(32)를 완성한다.Next, as shown in FIG. 7, the remaining lower half end surface of the tunnel construction point is excavated evenly, and shotcrete is poured into the lower half end surface excavation portion 33 to complete the shotcrete portion 32 for the entire cross section.

여기서, 숏크리트부(32)는 상부 반단면에 설치된 파형강판 조립체에만 형성하여도 무방하나, 하부 반단면까지 연장하여서 형성하는 것이 구조적인 측면에서 유리하다.Here, the shotcrete portion 32 may be formed only on the corrugated steel sheet assembly installed on the upper half end surface, but it is advantageous in terms of the structure to extend to the lower half end surface.

마지막으로, 도8의 도시와 같이 전체단면 숏크리트부(32)의 내측면에 내부라이닝콘크리트(34) 공사를 시행하고 마무리하여서 터널 구축을 완료한다.Finally, as shown in FIG. 8, the inner lining concrete 34 is constructed and finished on the inner surface of the entire cross-section shotcrete 32 to complete the tunnel construction.

본 고안은 상술한 바와 같이 파형강판을 이용해 상부 반단면 터널형상의 파형강판 조립체를 설치하고 나서, 상부 반단면 파형강판 조립체 및 하부 반단면의 내측면에 숏크리트부를 형성하여 암반 굴착후 타설되는 숏크리트 면과 동일한 현장조건을 제공하여 줌으로써, 터널 라이닝콘크리트를 한번 제작된 터널 폼으로 연속 시공할 수 있다.According to the present invention, after installing the corrugated steel sheet assembly having the upper half section tunnel shape using the corrugated steel sheet as described above, the shotcrete surface which is poured after rock excavation is formed by forming shotcrete on the inner half of the upper half section corrugated steel sheet assembly and the lower half section. By providing the same on-site conditions, the tunnel lining concrete can be continuously installed in the tunnel form once manufactured.

이상과 같이 구성되는 본 고안에 의하면 다음과 같은 효과가 있다.According to the present invention configured as described above has the following effects.

파형강판을 이용해 터널형상의 조립체를 형성하여 암반 터널과 동일한 조건을 만들어 줌으로써, 공사기간이 대폭적으로 단축됨은 물론이고, 공사의 품질이 향상되며, 시공성·경제성·안정성을 크게 도모하여 준다.By forming the tunnel-shaped assembly using corrugated steel sheet to create the same conditions as the rock tunnel, the construction period is greatly shortened, the construction quality is improved, and construction efficiency, economic feasibility, and stability are greatly improved.

라이닝콘트리트를 타설하기 위한 별도의 거푸집 및 지지대가 필요없게 되므로 공사비용이 크게 절약된다.The construction cost is greatly saved because there is no need for a separate formwork and support for placing lining concrete.

절토하는 면적이 종래 공법에 비해 크게 줄어들게 됨으로써, 자연환경의 훼손 및 파괴를 최소화할 수 있는 동시에 자연상태로 빨리 복원된다.Since the cut area is greatly reduced compared to the conventional method, it is possible to minimize the damage and destruction of the natural environment and at the same time quickly restore to the natural state.

이상에서 살펴본 바와 같이, 본 고안은 토피가 얕은 지역의 터널을 시공하는데 있어서, 시공기간을 단축시키고, 시공성·경제성 및 공사품질을 제고시키는 한편, 자연 훼손 및 파괴를 최소화할 수 있으며, 자연상태로 빨리 복원되게 하여 주는 매우 유용한 고안이다.As described above, the present invention can shorten the construction period, improve construction efficiency, economic feasibility and construction quality, and minimize natural damage and destruction in the construction of tunnels in shallow toffee, It is a very useful design that allows for quick restoration.

Claims (1)

터널을 건설하고자 하는 지점의 토사를 설계되어진 상부 반단면까지 굴착하고, 상부 반단면 굴착부(31)에 파형의 단면으로 형성되면서 호형상으로 굴곡되는 파형강판(p)들을 터널의 상부 반단면 형상으로 조립 설치하며, 파형강판 조립체의 내측에 숏크리트를 타설하고, 파형강판 조립체의 외부에 토사를 되메우기하고, 터널 건설지점의 나머지 하부 반단면을 마저 굴착하고, 하부 반단면 굴착부(33)에 숏크리트를 타설하며, 전체단면 숏크리트부(32)의 내측면에 내부 라이닝콘크리트(34) 공사를 시행하여서 구축되어진 것을 특징으로 하는 파형강판을 이용한 터널건설구조.The earth and sand of the point where the tunnel is to be constructed is excavated to the designed upper half section, and the corrugated steel sheets (p) which are curved in an arc shape while being formed in the cross section of the waveform in the upper half section excavation portion 31 are in the upper half section shape of the tunnel. And install shotcrete inside the corrugated steel sheet assembly, backfill the earth and sand to the outside of the corrugated steel sheet assembly, excavate the remaining lower half end surface of the tunnel construction point, and shotcrete the lower half end excavation portion 33 The tunnel construction structure using a corrugated steel sheet, characterized in that it is constructed by performing the internal lining concrete 34 construction on the inner surface of the shotcrete section (32).
KR2020010009429U 2001-04-04 2001-04-04 Tunnel Construction Structure for using Wave Profile Type Steel Plate KR200241026Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR2020010009429U KR200241026Y1 (en) 2001-04-04 2001-04-04 Tunnel Construction Structure for using Wave Profile Type Steel Plate

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR2020010009429U KR200241026Y1 (en) 2001-04-04 2001-04-04 Tunnel Construction Structure for using Wave Profile Type Steel Plate

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
KR2020000031436U Division KR200231108Y1 (en) 2000-11-10 2000-11-10 Tunnel Construction Structure for using Wave Profile Type Steel Plate

Publications (1)

Publication Number Publication Date
KR200241026Y1 true KR200241026Y1 (en) 2001-10-10

Family

ID=73098866

Family Applications (1)

Application Number Title Priority Date Filing Date
KR2020010009429U KR200241026Y1 (en) 2001-04-04 2001-04-04 Tunnel Construction Structure for using Wave Profile Type Steel Plate

Country Status (1)

Country Link
KR (1) KR200241026Y1 (en)

Similar Documents

Publication Publication Date Title
KR100722665B1 (en) Steel guide wall for construction of underground diaphragm wall and construction method of underground diaphragm wall using the same
KR20080005109A (en) Structure for supporting retaining wall of earth with arch material and method constructing the arch structure
KR100656194B1 (en) Open cut and cover method applying tunnel cut method
KR20190102737A (en) Semi open cut type tunnel construction method at low overburden
JP6543176B2 (en) Building method
JP2002115260A (en) Extension method for basement
JP5843413B1 (en) Lowering method of existing tunnel
KR100890697B1 (en) Excavation-tunnel type Construction method of open tunnel-part
KR100289256B1 (en) Tunnel construction method in shallow toffee area
CN107044135A (en) A kind of tunnel portal excavates the construction method built
KR100898969B1 (en) Tunnel Boring Method Using Sheet Pile and Tunnel Structure therof
JP3516391B2 (en) Ground excavation method
KR200241026Y1 (en) Tunnel Construction Structure for using Wave Profile Type Steel Plate
JP2007046343A (en) Liquefaction preventive construction method of ground just under existing building
KR200241025Y1 (en) Tunnel Construction Structure for using Wave Profile Type Steel Plate
KR100442690B1 (en) Tunnel Construction Method for using Wave Profile Type Steel Plate
KR200231108Y1 (en) Tunnel Construction Structure for using Wave Profile Type Steel Plate
KR100941437B1 (en) 2 arch tunnel construction method for upper girder void proofing and efficient construction
KR102289576B1 (en) Top-down type underground structure construction method using earth support plate
JP2005002671A (en) Underpinning method and viaduct
KR100397958B1 (en) The structure timbering of cut with separating wale and the construction method thereof
KR101091081B1 (en) Excavation method and construction of dual tunnel
JP6543177B2 (en) Building method
JP6130139B2 (en) Caisson structure having pressure-resistant plate and construction method thereof
KR100515971B1 (en) Soil retaining method using H-pile having large section

Legal Events

Date Code Title Description
U106 Divisional application of utility model
REGI Registration of establishment
FPAY Annual fee payment

Payment date: 20020416

Year of fee payment: 3

LAPS Lapse due to unpaid annual fee