KR102794484B1 - Reinforcement Method of Piloti Type Building Using Light Concrete Panel - Google Patents

Reinforcement Method of Piloti Type Building Using Light Concrete Panel Download PDF

Info

Publication number
KR102794484B1
KR102794484B1 KR1020240002200A KR20240002200A KR102794484B1 KR 102794484 B1 KR102794484 B1 KR 102794484B1 KR 1020240002200 A KR1020240002200 A KR 1020240002200A KR 20240002200 A KR20240002200 A KR 20240002200A KR 102794484 B1 KR102794484 B1 KR 102794484B1
Authority
KR
South Korea
Prior art keywords
fastener
lightweight concrete
concrete panel
vertical plane
floor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
KR1020240002200A
Other languages
Korean (ko)
Inventor
박태원
엄태성
이상현
허무원
Original Assignee
단국대학교 산학협력단
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 단국대학교 산학협력단 filed Critical 단국대학교 산학협력단
Priority to KR1020240002200A priority Critical patent/KR102794484B1/en
Application granted granted Critical
Publication of KR102794484B1 publication Critical patent/KR102794484B1/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0218Increasing or restoring the load-bearing capacity of building construction elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/92Protection against other undesired influences or dangers
    • E04B1/98Protection against other undesired influences or dangers against vibrations or shocks; against mechanical destruction, e.g. by air-raids
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H9/00Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate
    • E04H9/02Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate withstanding earthquake or sinking of ground
    • E04H9/021Bearing, supporting or connecting constructions specially adapted for such buildings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Emergency Management (AREA)
  • Business, Economics & Management (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Mechanical Engineering (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

According to one embodiment of the present disclosure, provided is a method for reinforcing a piloti building, which comprises the steps of: (a) manufacturing a lightweight concrete panel in a factory; (b) transporting the lightweight concrete panel to a site; and (c) reinforcing the piloti building by arranging the lightweight concrete panel on the first floor of the piloti building.

Description

경량 콘크리트 패널을 이용한 필로티 건물의 보강 방법{Reinforcement Method of Piloti Type Building Using Light Concrete Panel}{Reinforcement Method of Piloti Type Building Using Light Concrete Panel}

본 개시는 필로티 건물을 보강하기 위한 방법에 관한 것으로, 구체적으로는 경량 콘크리트 패널을 이용하여 필로티 건물을 보강함으로써, 내진 성능을 향상시키는 방법에 관한 것이다.The present disclosure relates to a method for reinforcing a piloti building, and more particularly, to a method for improving seismic performance by reinforcing a piloti building using lightweight concrete panels.

이 부분에 기술된 내용은 단순히 본 개시에 대한 배경정보를 제공할 뿐 종래기술을 구성하는 것은 아니다.The material described in this section merely provides background information for the present disclosure and does not constitute prior art.

2009년 도시형 생활주택이 도입되면서 필로티 구조의 건축물에 대한 수요가 크게 증가하였다. 필로티 건물의 경우, 1층을 주차장용도로 사용가능하며, 이를 위하여 1층은 보와 기둥이 주를 이루는 골조 시스템을 채택한다. 또한,2 층 이상은 주거 용도로 사용되어, 벽체가 주를 이루는 전단벽 시스템으로 구성된다. With the introduction of urban housing in 2009, the demand for buildings with piloti structures has increased significantly. In the case of piloti buildings, the first floor can be used as a parking lot, and for this purpose, the first floor adopts a frame system mainly composed of beams and columns. In addition, the second floor and above are used for residential purposes, and are composed of a shear wall system mainly composed of walls.

한편, 현행 내진성능 평가요령에 따르면 필로티 건물은 수직비정형성 중 강성비정형에 해당하는 건축물로 1층이 연층이 되어 구조물 전체의 층변위가 1층에 집중되는 현상이 발생하는 경우가 많다. 이 경우 전체 구조물의 내진성능은 1층 기둥에 의해 좌우되므로 1층 기둥이 지진 발생 시 요구되는 층변위에도 전단력에 대한 저항능력을 상실하지 않는 것이 중요하며 구조물 전체의 안전에도 큰 영향을 미친다.Meanwhile, according to the current seismic performance evaluation guidelines, piloti buildings are buildings that fall under the category of rigid irregularity among vertical irregularities, and the first floor is often a soft floor, causing the entire structure's floor displacement to be concentrated on the first floor. In this case, the seismic performance of the entire structure is determined by the first-floor columns, so it is important that the first-floor columns do not lose their ability to resist shear force even when the required floor displacement occurs during an earthquake, and this also has a significant impact on the safety of the entire structure.

다만 최근 발생한 지진 등에서 피해를 입은 필로티 건물을 살펴보면, 1층 기둥이 전단파괴 되는 등 기둥의 전단저항능력이 부족한 것을 알 수 있다. 이처럼 필로티 건물의 수요는 크게 늘었지만, 건물의 안전에 직결되는 기둥의 내진성능이 부족한 경우가 많다. 또한, 시공이 완료된 기둥의 경우 마감재와 기타 부속 자재 등으로 인해 전단철근이 정상적으로 배근되었는지 확인하기 어려운 실정이다. 이러한 이유로 기둥의 내진성능향상을 위한 후 설치 보강공법에 대한 관심이 증가하고 있으며, 최근 들어 이에 관련된 연구도 많이 진행되고 있다.However, if you look at piloti buildings that have been damaged by recent earthquakes, you can see that the shear resistance of the columns is insufficient, as the columns on the first floor have been destroyed in shear. Although the demand for piloti buildings has greatly increased, there are many cases where the seismic performance of columns, which are directly related to the safety of the building, is insufficient. In addition, in the case of completed columns, it is difficult to confirm whether the shear reinforcement has been properly placed due to finishing materials and other auxiliary materials. For this reason, interest in post-installation reinforcement methods to improve the seismic performance of columns is increasing, and many studies on this have been conducted recently.

필로티 건물의 내진성능 향상을 위한 대표적인 보강공법으로는 직접적인 기둥 보강, 섬유시트 부착, 철골 브레이스 보강 및 콘크리트 전단벽 보강 등이 있다. 직접적인 기둥 보강의 경우, 경제성이 낮고, 필로티 적용이 쉽지 않으며, 많은 작업자가 투입되어야 한다는 단점이 있다. 또한, 섬유시트 부착 방식은 현재 가장 널리 사용되는 공법이나, 필로티 건물에의 적용이 매우 어렵고, 경제성이 좋지 않다는 단점이 있다. 또한, 철골 브레이스 보강의 경우, 공기가 길고, 필로티 적용성이 좋지 아니하며, 다수 작업자가 필요하다. 마지막으로 콘크리트 전단벽 보강의 겨우, 공기가 길고, 필로티 적용이 어렵다는 단점이 있다. Representative reinforcement methods for improving the seismic performance of piloti buildings include direct column reinforcement, fiber sheet attachment, steel brace reinforcement, and concrete shear wall reinforcement. In the case of direct column reinforcement, there are disadvantages in that it is low in economic feasibility, it is not easy to apply to piloti, and many workers are required. In addition, the fiber sheet attachment method, although the most widely used method at present, is very difficult to apply to piloti buildings, and it has disadvantages in that it is not economical. In addition, in the case of steel brace reinforcement, the construction period is long, the piloti application is not good, and many workers are required. Finally, in the case of concrete shear wall reinforcement, there are disadvantages in that the construction period is long and the piloti application is difficult.

특히 상기한 보강방법 중, 철골 브레이스 설치 또는 콘크리트 전단벽 보강의 경우, 추가적인 시설물이 설치되어야 하는바, 필로티 건물에 적용될 경우 주차장영역 또는 출입 영역을 크게 침해하는 문제점이 있다.In particular, among the above-mentioned reinforcement methods, in the case of installing steel braces or reinforcing concrete shear walls, additional facilities must be installed, and when applied to piloti buildings, there is a problem of significantly encroaching on the parking lot area or entrance area.

이에, 본 개시는 필로티 건물에 특화된 건물 보강방법을 제공하는 데 목적이 있다.Accordingly, the present disclosure aims to provide a building reinforcement method specialized for piloti buildings.

또한, 본 개시는 공기가 짧으면서도, 시공 난이도가 낮은 건물 보강방법을 제공하는 데 목적이 있다.In addition, the present disclosure aims to provide a building reinforcement method that has a short construction period and low construction difficulty.

또한, 본 개시는 소수의 작업자가 투입되더라도 시공이 가능한 건물 보강방법을 제공하는 데 목적이 있다.In addition, the present disclosure aims to provide a building reinforcement method that can be constructed even with a small number of workers.

본 발명이 해결하고자 하는 과제들은 이상에서 언급한 과제들로 제한되지 않으며, 언급되지 않은 또 다른 과제들은 아래의 기재로부터 통상의 기술자에게 명확하게 이해될 수 있을 것이다.The problems to be solved by the present invention are not limited to the problems mentioned above, and other problems not mentioned will be clearly understood by those skilled in the art from the description below.

본 개시의 일 실시예에 의하면, 필로티 건물을 보강하기 위한 방법으로서, (A) 경량 콘크리트 패널이 공장에서 제조되는 단계; (B) 상기 경량 콘크리트 패널이 현장으로 운반되는 단계; 및 (C) 상기 경량 콘크리트 패널이 상기 필로티 건물의 1층에 배치됨으로써, 상기 필로티 건물이 보강되는 단계;를 포함하되, 상기 (C) 단계는 (c1) 1층의 상부면 및 1층의 하부 바닥면에 앵커홀이 천공되는 단계; (c2) 상기 상부면 및 상기 하부 바닥면 각각에 제1 체결구가 설치되는 단계; (c3) 상기 상부면 및 상기 하부 바닥면에 설치된 각각의 제1 체결구의 일면에 제2 체결구가 부착되는 단계; (c4) 상기 각각의 제2 체결구에 상기 경량 콘크리트 패널의 양단부가 삽입되는 단계; 및 (c5) 상기 각각의 제2 체결구에 제3 체결구가 설치되는 단계; (c6) 상기 각각의 제1 체결구 내부에 에폭시가 충진되고, 상기 제2 체결구와 상기 제3 체결구가 형성하는 공간 내에 무수축 몰타르가 시공되는 단계;를 포함하는 방법을 제공한다.According to one embodiment of the present disclosure, a method for reinforcing a piloti building comprises the steps of: (A) a lightweight concrete panel being manufactured in a factory; (B) the lightweight concrete panel being transported to a site; and (C) the lightweight concrete panel being placed on a first floor of the piloti building, thereby reinforcing the piloti building; wherein step (C) comprises: (c1) a step of drilling anchor holes in an upper surface of the first floor and a lower floor surface of the first floor; (c2) a step of installing a first fastener in each of the upper surface and the lower floor surface; (c3) a step of attaching a second fastener to one surface of each of the first fasteners installed in the upper surface and the lower floor surface; (c4) a step of inserting both ends of the lightweight concrete panel into each of the second fasteners; and (c5) a step of installing a third fastener in each of the second fasteners. (c6) A method is provided, including a step of filling epoxy inside each of the first fasteners and constructing non-shrinkage mortar inside a space formed by the second fastener and the third fastener.

또한, 바람직하게는, 본 개시의 일 실시예에 의한 상기 제1 체결구는 종단면의 형상이 'ㄷ'자이고, 상기 (c2) 단계에서, 개방된 일면이 상기 각각의 바닥면을 향하도록 설치된다.In addition, preferably, the first fastener according to one embodiment of the present disclosure has a cross-sectional shape of the letter 'ㄷ', and in the step (c2), it is installed such that the open side faces each of the bottom surfaces.

또한, 바람직하게는, 본 개시의 일 실시예에 의한 상기 제2 체결구는 종단면의 형상이 'ㄷ'자이며, 제1 수직면; 상기 제1 수직면과 마주보도록 형성되되 상기 제1 수직면의 길이보다 짧은 길이를 갖는 제2 수직면; 및 상기 제1 수직면과 상기 제2 수직면을 연결하는 수평면을 포함하고, 상기 수평면이 상기 제1 체결구에 부착되되, 상기 상부면에 설치된 제2 체결구의 제2 수직면이 향하는 방향과, 상기 하부 바닥면에 설치된 제2 체결구의 제2 수직면이 향하는 방향이 동일하다.In addition, preferably, the second fastener according to one embodiment of the present disclosure has a cross-sectional shape in the shape of the letter 'ㄷ' and includes: a first vertical plane; a second vertical plane formed to face the first vertical plane but having a length shorter than the length of the first vertical plane; and a horizontal plane connecting the first vertical plane and the second vertical plane, wherein the horizontal plane is attached to the first fastener, and a direction in which the second vertical plane of the second fastener installed on the upper surface faces and a direction in which the second vertical plane of the second fastener installed on the lower bottom surface faces are the same.

또한, 바람직하게는, 본 개시의 일 실시예에 의한 상기 (c3) 단계는, (c31) 상기 제1 체결구와 제2 체결구를 동시에 관통하도록 상기 앵커홀에 후설치 앵커가 설치되는 단계를 포함한다.In addition, preferably, the step (c3) according to one embodiment of the present disclosure includes the step (c31) of installing a post-installation anchor in the anchor hole so as to simultaneously penetrate the first fastener and the second fastener.

또한, 바람직하게는, 본 개시의 일 실시예에 의한 상기 (c4) 단계에서, 상기 경량 콘크리트 패널은 상기 제2 수직면이 향하는 방향에서 삽입된다.Additionally, preferably, in step (c4) according to one embodiment of the present disclosure, the lightweight concrete panel is inserted in the direction in which the second vertical plane faces.

또한, 바람직하게는, 본 개시의 일 실시예에 의한 상기 제3 체결구는 '1'자 형상이고, 상기 (c5) 단계에서, 상기 제3 체결구는 상기 제2 수직면에 부착되어 설치되고, 상기 제3 체결구와 상기 제2 체결구 사이에 공간이 형성된다.In addition, preferably, the third fastener according to one embodiment of the present disclosure has an 'I' shape, and in the step (c5), the third fastener is installed by being attached to the second vertical surface, and a space is formed between the third fastener and the second fastener.

또한, 바람직하게는, 본 개시의 일 실시예에 의한 상기 (c5) 단계는, (c51) 상기 제3 체결구와 상기 제2 수직면을 동시에 관통하도록 체결볼트가 볼팅되는 단계; 및 (c52) 상기 제3 체결구, 상기 경량 콘크리트 패널 및 상기 제1 수직면을 동시에 관통하도록 관통볼트가 볼팅되는 단계;를 포함한다.In addition, preferably, the step (c5) according to one embodiment of the present disclosure includes: (c51) a step of bolting a fastening bolt so as to simultaneously penetrate the third fastening member and the second vertical plane; and (c52) a step of bolting a penetrating bolt so as to simultaneously penetrate the third fastening member, the lightweight concrete panel, and the first vertical plane.

또한, 바람직하게는, 본 개시의 일 실시예에 의한 상기 경량 콘크리트 패널의 두께는 120 mm이고, 상기 경량 콘크리트 패널의 너비는 0.5 m 내지 1 m이다.In addition, preferably, the thickness of the lightweight concrete panel according to one embodiment of the present disclosure is 120 mm, and the width of the lightweight concrete panel is 0.5 m to 1 m.

또한, 바람직하게는 본 개시의 일 실시예에 따른 방법에 의해 설치되는 보강 시스템을 제공한다.Additionally, a reinforcing system is preferably provided, which is installed by a method according to one embodiment of the present disclosure.

이상에서 설명한 바와 같이 본 개시의 일 실시예에 의하면, 기존 기둥 주위에 보강 시스템이 배치되기에, 보강 후 주차 공간이 침해되지 않아 필로티 건물에 대한 적용성이 우수하다는 효과가 있다.As described above, according to one embodiment of the present disclosure, since the reinforcing system is arranged around an existing pillar, there is an effect that the parking space is not encroached upon after the reinforcing, so that the applicability to piloti buildings is excellent.

또한, 필요한 공간에 분리하여 설치가 가는한바, 거주자가 드나드는 출입 영역을 충분히 확보할 수 있으면서, 동시에 필로티 건물의 내진 성능을 향상시킬 수 있다는 효과가 있다.In addition, since it can be installed separately in the necessary space, it has the effect of securing sufficient entrance and exit areas for residents while improving the seismic performance of piloti buildings.

또한, 기 축조된 필로티 건물에 콘크리트 패널을 접합하기 위한 별도의 면처리가 불필요한바, 공기가 단축되며 시공 난이도가 저감되는 효과가 있다.In addition, there is no need for separate surface treatment to bond concrete panels to the pre-fabricated piloti building, which shortens the construction period and reduces construction difficulty.

또한, 본 개시의 일 실시예에 따른 경량 콘크리트 패널은 두께가 150 mm 이내이며, 너비는 0.5 m 또는 1 m 인바, 작업자 한 명이 들거나 옮기기에 용이하다. 이로 인해, 시공 시 인건비가 저감되는 효과가 있다.In addition, the lightweight concrete panel according to one embodiment of the present disclosure has a thickness of 150 mm or less and a width of 0.5 m or 1 m, making it easy for one worker to lift or move it. This has the effect of reducing labor costs during construction.

도 1은 본 개시의 일 실시예에 따른 경량 콘크리트 패널이 적용된 필로티 건물을 나타낸 것이다.
도 2a 및 도 2b는 본 개시의 일 실시예에 따른 경량 콘크리트 패널을 시공하는 순서를 나타낸 것이다.
도 3은 본 개시의 일 실시예에 따른 경량 콘크리트 패널을 이용한 시공 방법의 순서도이다.
FIG. 1 illustrates a piloti building to which lightweight concrete panels are applied according to one embodiment of the present disclosure.
FIGS. 2A and 2B illustrate a sequence for constructing a lightweight concrete panel according to one embodiment of the present disclosure.
FIG. 3 is a flow chart of a construction method using a lightweight concrete panel according to one embodiment of the present disclosure.

이하, 본 개시의 일부 실시예들을 예시적인 도면을 통해 상세하게 설명한다. 각 도면의 구성 요소들에 참조 부호를 부가함에 있어서, 동일한 구성 요소들에 대해서는 비록 다른 도면상에 표시되더라도 가능한 한 동일한 부호를 가지도록 하고 있음에 유의해야 한다. 또한, 본 개시를 설명함에 있어, 관련된 공지 구성 또는 기능에 대한 구체적인 설명이 본 개시의 요지를 흐릴 수 있다고 판단되는 경우에는 그 상세한 설명은 생략한다.Hereinafter, some embodiments of the present disclosure will be described in detail with reference to exemplary drawings. When adding reference numerals to components of each drawing, it should be noted that the same components are given the same numerals as much as possible even if they are shown in different drawings. In addition, when describing the present disclosure, if it is determined that a specific description of a related known configuration or function may obscure the gist of the present disclosure, the detailed description thereof will be omitted.

본 개시에 따른 실시예의 구성요소를 설명하는 데 있어서, 제1, 제2, i), ii), a), b) 등의 부호를 사용할 수 있다. 이러한 부호는 그 구성요소를 다른 구성 요소와 구별하기 위한 것일 뿐, 그 부호에 의해 해당 구성요소의 본질 또는 차례나 순서 등이 한정되지 않는다. 명세서에서 어떤 부분이 어떤 구성요소를 '포함' 또는 '구비'한다고 할 때, 이는 명시적으로 반대되는 기재가 없는 한 다른 구성요소를 제외하는 것이 아니라 다른 구성요소를 더 포함할 수 있는 것을 의미한다.In describing components of embodiments according to the present disclosure, symbols such as first, second, i), ii), a), b), etc. may be used. These symbols are only for distinguishing the components from other components, and the nature or order or sequence of the components is not limited by the symbols. When a part in the specification is said to "include" or "provide" a component, this does not mean that other components are excluded, but rather that other components can be further included, unless explicitly stated otherwise.

본 개시에서, '시스템'은 마땅히 물건으로 이해되어야 한다.In this disclosure, 'system' should be properly understood as a thing.

본 개시에서, '1층'은 필로티 건물에서 기둥과 천정이 있으나 벽이 없는 공간 부분을 의미하는 것으로, 예컨대 기둥이 지면으로부터 2층의 바닥면(즉, 1층의 상부면)에 이어진 경우 발생하는 외부 공간은 물론, 기둥이 지면으로부터 3층의 바닥면에 이어져서 외부에서 볼 경우 두 개 층에 이어진 공간을 형성한다면 해당 공간 전체를 의미하는 것으로 이해되어야 한다. In this disclosure, the term "first floor" means a space portion in a piloti building that has columns and a ceiling but no walls. For example, if a column extends from the ground to the floor surface of the second floor (i.e., the upper surface of the first floor), it should be understood to mean not only the external space created, but also the entire space created if the column extends from the ground to the floor surface of the third floor, forming a space connecting two floors when viewed from the outside.

도 1은 본 개시의 일 실시예에 따른 경량 콘크리트 패널이 적용된 필로티 건물을 나타낸 것이다.FIG. 1 illustrates a piloti building to which lightweight concrete panels are applied according to one embodiment of the present disclosure.

도 1을 참조하면, 본 개시의 일 실시예에 따른 경량 콘크리트를 포함하는 보강 시스템(1)은 필로티 건물의 1층에 배치될 수 있다. 구체적으로, 1층의 상부면(즉, 2층 슬라브의 하부면)과, 1층의 하부 바닥면 사이에 배치되되, 기존 기둥(C)의 주위에 배치됨으로써, 필로티 건물의 내진 성능이 향상될 수 있다. 기존 기둥(C) 주위에 보강 시스템(1)이 배치되는바, 보강 후 주차 공간이 침해되지 않을 수 있다는 장점이 있다. Referring to FIG. 1, a reinforcing system (1) including lightweight concrete according to one embodiment of the present disclosure may be placed on the first floor of a piloti building. Specifically, it is placed between the upper surface of the first floor (i.e., the lower surface of the second-floor slab) and the lower floor surface of the first floor, and by being placed around an existing column (C), the seismic performance of the piloti building may be improved. Since the reinforcing system (1) is placed around an existing column (C), there is an advantage in that a parking space may not be infringed after reinforcement.

또한, 본 개시의 일 실시예에 따른 경량 콘크리트 패널(14)은 너비가 0.5 m 또는 1 m 단위로 제작되는바, 필요한 공간에 분리 설치가 가능하여, 거주자가 드나드는 공간을 충분히 확보할 수 있으면서도, 필로티 건물의 내진 성능을 향상시킬 수 있다는 장점이 있다.In addition, the lightweight concrete panel (14) according to one embodiment of the present disclosure is manufactured in units of 0.5 m or 1 m in width, and thus can be installed separately in a required space, thereby securing sufficient space for residents to enter and exit, and has the advantage of improving the seismic performance of a piloti building.

도 2a 및 도 2b는 본 개시의 일 실시예에 따른 경량 콘크리트 패널을 시공하는 순서를 나타낸 것이다. 도 3은 본 개시의 일 실시예에 따른 경량 콘크리트 패널을 이용한 시공 방법의 순서도이다.FIG. 2a and FIG. 2b illustrate a sequence of constructing a lightweight concrete panel according to one embodiment of the present disclosure. FIG. 3 is a sequence diagram of a construction method using a lightweight concrete panel according to one embodiment of the present disclosure.

도 2a 및 도 2b는 단면으로 시공 순서를 나타낸 것이므로, 각각의 바닥면(B1,B2)과 보강 시스템(1)은 너비를 갖는 것으로 이해되어야 한다. 또한, 도 2a 및 도 2b는 설명의 편의를 위하여, 일부 구성은 과소하게 또는 과대하게 도시되었음에 유의하여야 한다.Since Figs. 2a and 2b show the construction sequence in cross-section, it should be understood that each floor surface (B1, B2) and the reinforcing system (1) have a width. In addition, it should be noted that some components in Figs. 2a and 2b are shown under- or over-sized for convenience of explanation.

도 2 내지 도 3을 참조하여, 본 개시의 일 실시예에 따른 경량 콘크리트 패널을 포함하는 보강 시스템(1)의 시공 방법을 상세히 설명한다.Referring to FIGS. 2 and 3, a method for constructing a reinforcing system (1) including a lightweight concrete panel according to one embodiment of the present disclosure will be described in detail.

공장에서 경량 콘크리트 패널(14)이 제조된다(S300). Lightweight concrete panels (14) are manufactured in a factory (S300).

제조된 경량 콘크리트 패널(14)은 보강이 필요한 현장에 운반된다(S310). The manufactured lightweight concrete panel (14) is transported to the site where reinforcement is required (S310).

상부면(B1)과 하부 바닥면(B2) 각각에 앵커홀(10)이 천공된다(S320). An anchor hole (10) is drilled in each of the upper surface (B1) and the lower bottom surface (B2) (S320).

도 2a의 (a)는 상부면(B1)과 하부 바닥면(B2)의 단면을 나타낸 것이다. 도 2a의 (b)를 참조하면, 후설치 앵커(13)가 설치되어야 할 앵커홀(10)이 천공되어 있는 것을 확인할 수 있다. 이때, 각각의 앵커홀(10)은 서로 마주보도록 배치되는 것이 바람직하다. Figure 2a (a) shows a cross-section of the upper surface (B1) and the lower bottom surface (B2). Referring to Figure 2a (b), it can be confirmed that an anchor hole (10) in which a post-installation anchor (13) is to be installed is drilled. At this time, it is preferable that each anchor hole (10) be arranged to face each other.

상부면(B1)과 하부 바닥면(B2) 각각에 제1 체결구(11)가 설치된다(S330).A first fastener (11) is installed on each of the upper surface (B1) and the lower bottom surface (B2) (S330).

도 2a의 (b)를 참조하면, 이때, 제1 체결구(11)는 종단면의 형상이 'ㄷ'자이며, 스틸(steel) 소재로 형성되는 것이 바람직하다. 이로 인해, 제1 체결구(11)가 각각의 바닥면(B1,B2)에 설치되었을 때, 바닥면(B1,B2)과 내부에 공간을 형성할 수 있다. 한편, 제1 체결구(11)는 용접 또는 접착제에 의해 각각의 바닥면(B1,B2)에 결합될 수 있다.Referring to (b) of Fig. 2a, at this time, the first fastener (11) has a cross-sectional shape of the letter 'ㄷ' and is preferably formed of steel. Accordingly, when the first fastener (11) is installed on each of the bottom surfaces (B1, B2), a space can be formed between the bottom surfaces (B1, B2) and the inside. Meanwhile, the first fastener (11) can be joined to each of the bottom surfaces (B1, B2) by welding or adhesive.

상부면(B1)과 하부 바닥면(B2)에 경량 콘크리트 패널(14)과 기 축조된 필로티 건물 사이의 접합을 위한 별도의 면처리가 필요가 없고, 제1 체결구(11)를 각각의 바닥면(B1,B2)에 부착만 하면 되기에, 공기가 단축되며, 시공 난이도가 저감된다는 장점이 있다.There is no need for separate surface treatment for the joint between the lightweight concrete panel (14) and the pre-constructed piloti building on the upper surface (B1) and the lower floor surface (B2), and only the first fastener (11) needs to be attached to each floor surface (B1, B2), so there is an advantage in that the construction period is shortened and the difficulty of construction is reduced.

상부에 설치된 제1 체결구(11)의 일면과, 하부에 설치된 제1 체결구(11)의 일면 상에 각각 제2 체결구(12)가 부착되고, 후설치 앵커(13)가 설치된다(S340).A second fastener (12) is attached to one side of the first fastener (11) installed at the top and one side of the first fastener (11) installed at the bottom, respectively, and a post-installation anchor (13) is installed (S340).

도 2a의 (c)를 참조하면, 제1 체결구(11)의 일면 상에 제2 체결구(12)가 부착된다. 이때, 제2 체결구(12)는 종단면의 형상이 'ㄷ'자이되, 서로 마주보는 두 면의 길이가 다르게 구성될 수 있다. 즉, 제2 체결구(12)는 제1 수직면(121), 제2 수직면(122) 및 제1 수직면(121)과 제2 수직면(122) 사이에서 양자를 연결하는 수평면(123)을 포함할 수 있다. 이때, 제1 수직면(121)은 제2 수직면(122)보다 길게 형성되고, 이로 인해, 제2 수직면(122)의 방향에서 경량 콘크리트 패널(14)이 손쉽게 삽입될 수 있다.Referring to (c) of Fig. 2a, a second fastener (12) is attached to one side of a first fastener (11). At this time, the second fastener (12) may have a 'ㄷ' shape in its cross-section, but the lengths of the two sides facing each other may be configured differently. That is, the second fastener (12) may include a first vertical plane (121), a second vertical plane (122), and a horizontal plane (123) connecting the first vertical plane (121) and the second vertical plane (122). At this time, the first vertical plane (121) is formed longer than the second vertical plane (122), and thus, the lightweight concrete panel (14) may be easily inserted in the direction of the second vertical plane (122).

이때, 상부에 설치된 제2 체결구(12)의 제2 수직면(122)이 향하는 방향과, 하부에 설치된 제2 체결구(12)의 제2 수직면(122)이 향하는 방향이 같아야 한다. 그래야만, 제2 수직면(122)들이 향하는 방향으로 경량 콘크리트 패널(14)이 삽입될 수 있기 때문이다.At this time, the direction in which the second vertical surface (122) of the second fastener (12) installed at the top faces must be the same as the direction in which the second vertical surface (122) of the second fastener (12) installed at the bottom faces. This is because only then can the lightweight concrete panel (14) be inserted in the direction in which the second vertical surfaces (122) face.

도 2a의 (d)를 참조하면, 제1 체결구(11)에 부착된 제2 체결구(12)를 통해, 후설치 앵커(13)가 삽입된다. 이때, 제1 체결구(11)와 제2 체결구(12)에는 미리 앵커 관통홀(미도시)이 형성된 채로 제조될 수도 있으나, 반드시 이에 한정되는 것은 아니다. 일 예시로, 현장에서 작업자가 제1 체결구(11)와 제2 체결구(12)의 위치를 적당히 정하고, 후설치 앵커(13)를 관통시키기 위한 관통홀(미도시)을 직접 타공할 수 있다.Referring to (d) of Fig. 2a, a post-installation anchor (13) is inserted through a second fastener (12) attached to a first fastener (11). At this time, the first fastener (11) and the second fastener (12) may be manufactured with anchor penetration holes (not shown) formed in advance, but this is not necessarily limited to this. As an example, a worker may appropriately determine the positions of the first fastener (11) and the second fastener (12) on site and directly drill a penetration hole (not shown) for passing the post-installation anchor (13).

한편, 제2 체결구(12)는 스틸(steel) 소재로 형성되는 것이 바람직하다. Meanwhile, it is preferable that the second fastener (12) be formed of steel.

상부에 설치된 제2 체결구(12)에 경량 콘크리트 패널(14)의 일단이 삽입되고, 하부에 설치된 제2 체결구(12)에 경량 콘크리트 패널(14)의 타단이 삽입됨으로써, 경량 콘크리트 패널(14)이 설치된다(S350).One end of a lightweight concrete panel (14) is inserted into the second fastener (12) installed at the top, and the other end of the lightweight concrete panel (14) is inserted into the second fastener (12) installed at the bottom, thereby installing the lightweight concrete panel (14) (S350).

도 2a의 (e)를 참조하면, 상부에 설치된 제2 체결구(12)의 제2 수직면(122)이 형성된 부분을 통해, 경량 콘크리트 패널(14)의 일단이 삽입될 수 있다. 또한, 하부에 설치된 제2 체결구(12)의 제2 수직면(122)이 형성된 부분을 통해, 경량 콘크리트 패널(14)의 타단이 삽입될 수 있다. 이때, 일단이 삽입된 후 타단이 삽입되는 것으로 설명되었으나, 반드시 이에 한정되는 것은 아니며, 타단이 삽입된 후 일단이 삽입되는 순서로 설치되어도 무관하다.Referring to (e) of Fig. 2a, one end of a lightweight concrete panel (14) can be inserted through a portion where a second vertical surface (122) of a second fastener (12) installed at the top is formed. In addition, the other end of a lightweight concrete panel (14) can be inserted through a portion where a second vertical surface (122) of a second fastener (12) installed at the bottom is formed. At this time, it has been described that one end is inserted and then the other end is inserted, but it is not necessarily limited to this, and it does not matter if the installation is done in the order that one end is inserted and then the other end is inserted.

한편, 경량 콘크리트 패널(14)은 바람직하게는 그 두께가 150 mm 이내이며, 너비는 0.5 m 또는 1 m 인바, 작업자 한 명이 들거나 옮기기에 충분하다. 이로 인해, 거치 작업은 소수의 작업 인원이 투입되더라도 수행될 수 있어, 인건비가 저감되며 공기가 단축되는 장점이 있다.Meanwhile, the lightweight concrete panel (14) is preferably within 150 mm in thickness and 0.5 m or 1 m in width, which is sufficient for one worker to lift or move. As a result, the erection work can be performed even with a small number of workers, which has the advantage of reducing labor costs and shortening the construction period.

상부에 설치된 제2 체결구(12)와 하부에 설치된 제2 체결구(12) 각각에 제3 체결구(15)가 설치되고, 상부 및 하부에 설치된 제2 체결구(12)와 제3 체결구(15)를 관통하도록 체결볼트(16)가 볼팅된다(S360).A third fastener (15) is installed in each of the second fastener (12) installed at the top and the second fastener (12) installed at the bottom, and a fastening bolt (16) is bolted so as to penetrate the second fastener (12) and the third fastener (15) installed at the top and bottom (S360).

도 2b의 (f)를 참조하면, 상부에 설치된 제2 체결구(12)와 하부에 설치된 제2 체결구(12) 각각에 제3 체결구(15)가 설치된다. 제3 체결구(15)는 종단면이 일(1)자로 형성되며, 스틸(steel) 소재로 형성되는 것이 바람직하다. 바람직하게는, 제3 체결구(15)는 제2 체결구(12)의 제1 수직면(121)의 길이와 동일하도록 형성된다. 이때, 제2 체결구(12)와 제3 체결구(15)는 용접 또는 접착제에 의해 결합될 수 있다.Referring to (f) of Fig. 2b, a third fastener (15) is installed in each of the second fastener (12) installed at the top and the second fastener (12) installed at the bottom. The third fastener (15) has a cross-section formed in the shape of the letter “1” and is preferably formed of steel. Preferably, the third fastener (15) is formed to have the same length as the first vertical surface (121) of the second fastener (12). At this time, the second fastener (12) and the third fastener (15) can be joined by welding or adhesive.

제3 체결구(15)가 제2 체결구(12)에 설치되면, 제2 체결구(12)와 제3 체결구(15)가 내부에 수용공간을 형성하게 되며, 상기한 수용공간에는 경량 콘크리트 패널(14)의 단부가 안정적으로 거치될 수 있다. When the third fastener (15) is installed in the second fastener (12), the second fastener (12) and the third fastener (15) form an accommodation space inside, and an end of a lightweight concrete panel (14) can be stably placed in the aforementioned accommodation space.

도 2b의 (g)를 참조하면, 체결볼트(16)가 제3 체결구(15)와 제2 체결구(12)의 제2 수직면(122)을 동시에 관통하여 볼팅된다. 또한, 도 2b의 (h)를 참조하면, 관통볼트(17)가 제3 체결구(15), 경량 콘크리트 패널(14) 및 제1 수직면(121)을 동시에 관통하여 볼팅된다. 이로 인해, 제3 체결구(15)가 제2 체결구(12)와 안정적으로 결합되며, 경량 콘크리트 패널(14)을 안정적으로 고정할 수 있다.Referring to (g) of Fig. 2b, the fastening bolt (16) is bolted through the third fastening hole (15) and the second vertical plane (122) of the second fastening hole (12) simultaneously. In addition, referring to (h) of Fig. 2b, the through bolt (17) is bolted through the third fastening hole (15), the lightweight concrete panel (14), and the first vertical plane (121) simultaneously. As a result, the third fastening hole (15) is stably connected to the second fastening hole (12), and the lightweight concrete panel (14) can be stably fixed.

상부에 설치된 제1 체결구(11) 및 하부에 설치된 제1 체결구(11) 내에 에폭시(18)가 충진되고, 상부 및 하부에 설치된 제2 체결구(12)와 제3 체결구(15) 내의 공간에 무수축 몰타르가 시공된다(S370).Epoxy (18) is filled into the first fastener (11) installed at the top and the first fastener (11) installed at the bottom, and non-shrinkage mortar is applied into the space within the second fastener (12) and the third fastener (15) installed at the top and bottom (S370).

도 2b의 (i)를 참조하면, 상부 및 하부에 설치된 제1 체결구(11) 내부에 에폭시(18)가 충진된다. 이로 인해, 제1 체결구(11)는 각각의 바닥면(B1,B2)에 안정적으로 고정될 수 있다.Referring to (i) of Fig. 2b, epoxy (18) is filled inside the first fasteners (11) installed at the upper and lower portions. As a result, the first fasteners (11) can be stably fixed to each bottom surface (B1, B2).

또한, 상부 및 하부에 설치된 제2 체결구(12)와 제3 체결구(15)에 내의 공간에 무수축 몰타르가 시공된다. 이때, 제2 체결구(12)와 제3 체결구(15)는 일종의 거푸집 역할을 하면서도, 경량 콘크리트 패널(14)을 안정적으로 고정할 수 있는 역할을 동시에 수행할 수 있다. In addition, non-shrinkage mortar is applied to the space inside the second fastener (12) and third fastener (15) installed at the top and bottom. At this time, the second fastener (12) and third fastener (15) can simultaneously perform the role of a formwork while stably fixing the lightweight concrete panel (14).

이상의 설명은 본 실시예의 기술 사상을 예시적으로 설명한 것에 불과한 것으로서, 본 실시예가 속하는 기술 분야에서 통상의 지식을 가진 자라면 본 실시예의 본질적인 특성에서 벗어나지 않는 범위에서 다양한 수정 및 변형이 가능할 것이다. 따라서, 본 실시예들은 본 실시예의 기술 사상을 한정하기 위한 것이 아니라 설명하기 위한 것이고, 이러한 실시예에 의하여 본 실시예의 기술 사상의 범위가 한정되는 것은 아니다. 본 실시예의 보호 범위는 아래의 청구범위에 의하여 해석되어야 하며, 그와 동등한 범위 내에 있는 모든 기술 사상은 본 실시예의 권리범위에 포함되는 것으로 해석되어야 할 것이다. The above description is merely an illustrative description of the technical idea of the present embodiment, and those with ordinary skill in the art to which the present embodiment belongs may make various modifications and variations without departing from the essential characteristics of the present embodiment. Therefore, the present embodiments are not intended to limit the technical idea of the present embodiment, but to explain it, and the scope of the technical idea of the present embodiment is not limited by these embodiments. The protection scope of the present embodiment should be interpreted by the following claims, and all technical ideas within a scope equivalent thereto should be interpreted as being included in the scope of the rights of the present embodiment.

1: 보강 시스템
10: 앵커홀
11: 제1 체결구
12: 제2 체결구
13: 후설치 앵커
14: 경량 콘크리트 패널
15: 제3 체결구
16: 체결볼트
17: 관통볼트
18: 에폭시
19: 무수축 모르타르
1: Reinforcement System
10: Anchor hole
11: 1st fastener
12: 2nd fastener
13: Post-installation anchor
14: Lightweight concrete panels
15: Third fastener
16: Fastening bolt
17: Through bolt
18: Epoxy
19: Non-shrinkage mortar

Claims (9)

필로티 건물을 보강하기 위한 방법으로서,
(A) 경량 콘크리트 패널이 공장에서 제조되는 단계;
(B) 상기 경량 콘크리트 패널이 현장으로 운반되는 단계; 및
(C) 상기 경량 콘크리트 패널이 상기 필로티 건물의 1층에 배치됨으로써, 상기 필로티 건물이 보강되는 단계;를 포함하되,
상기 (C) 단계는,
(c1) 1층의 상부면 및 1층의 하부 바닥면에 앵커홀이 천공되는 단계;
(c2) 상기 상부면 및 상기 하부 바닥면 각각에 제1 체결구가 설치되는 단계;
(c3) 상기 상부면 및 상기 하부 바닥면에 설치된 각각의 제1 체결구의 일면에 제2 체결구가 부착되는 단계;
(c4) 상기 각각의 제2 체결구에 상기 경량 콘크리트 패널의 양단부가 삽입되는 단계;
(c5) 상기 각각의 제2 체결구에 제3 체결구가 설치되는 단계; 및
(c6) 상기 각각의 제1 체결구 내부에 에폭시가 충진되고, 상기 제2 체결구와 상기 제3 체결구가 형성하는 공간 내에 무수축 몰타르가 시공되는 단계;를 포함하고,
상기 제2 체결구는 종단면의 형상이 'ㄷ'자이며,
제1 수직면;
상기 제1 수직면과 마주보도록 형성되되 상기 제1 수직면의 길이보다 짧은 길이를 갖는 제2 수직면; 및
상기 제1 수직면과 상기 제2 수직면을 연결하는 수평면을 포함하고,
상기 수평면이 상기 제1 체결구에 부착되되, 상기 상부면에 설치된 제2 체결구의 제2 수직면이 향하는 방향과, 상기 하부 바닥면에 설치된 제2 체결구의 제2 수직면이 향하는 방향이 동일한,
방법.
As a method for reinforcing a piloti building,
(A) A step in which lightweight concrete panels are manufactured in a factory;
(B) a step in which the lightweight concrete panel is transported to the site; and
(C) a step of reinforcing the piloti building by placing the lightweight concrete panel on the first floor of the piloti building; including,
Step (C) above,
(c1) A step of drilling anchor holes in the upper surface of the first floor and the lower floor surface of the first floor;
(c2) a step in which a first fastener is installed on each of the upper surface and the lower bottom surface;
(c3) a step in which a second fastener is attached to one side of each of the first fasteners installed on the upper surface and the lower bottom surface;
(c4) a step in which both ends of the lightweight concrete panel are inserted into each of the second fastening holes;
(c5) a step of installing a third fastener in each of the second fasteners; and
(c6) a step of filling epoxy inside each of the first fasteners and constructing non-shrinkage mortar inside the space formed by the second fastener and the third fastener;
The above second fastener has a cross-sectional shape in the shape of the letter ‘ㄷ’.
First vertical plane;
A second vertical plane formed to face the first vertical plane but having a length shorter than the length of the first vertical plane; and
Including a horizontal plane connecting the first vertical plane and the second vertical plane,
The above horizontal plane is attached to the above first fastener, and the direction in which the second vertical plane of the second fastener installed on the upper surface faces and the direction in which the second vertical plane of the second fastener installed on the lower bottom surface faces are the same.
method.
제1항에 있어서,
상기 제1 체결구는 종단면의 형상이 'ㄷ'자이고,
상기 (c2) 단계에서, 개방된 일면이 상기 각각의 바닥면을 향하도록 설치되는,
방법.
In the first paragraph,
The above first fastener has a cross-sectional shape in the shape of the letter ‘ㄷ’,
In the above step (c2), the open side is installed so that it faces each of the floor surfaces.
method.
삭제delete 제1항에 있어서,
상기 (c3) 단계는,
(c31) 상기 제1 체결구와 제2 체결구를 동시에 관통하도록 상기 앵커홀에 후설치 앵커가 설치되는 단계를 포함하는,
방법.
In the first paragraph,
The above step (c3) is,
(c31) Including a step of installing a post-installation anchor into the anchor hole so as to simultaneously penetrate the first fastening member and the second fastening member.
method.
제4항에 있어서,
상기 (c4) 단계에서,
상기 경량 콘크리트 패널은 상기 제2 수직면이 향하는 방향에서 삽입되는,
방법.
In paragraph 4,
In the above step (c4),
The above lightweight concrete panel is inserted in the direction in which the second vertical plane faces,
method.
제5항에 있어서,
상기 제3 체결구는 '1'자 형상이고,
상기 (c5) 단계에서, 상기 제3 체결구는 상기 제2 수직면에 부착되어 설치되고, 상기 제3 체결구와 상기 제2 체결구 사이에 공간이 형성되는,
방법.
In paragraph 5,
The above third fastener is shaped like the letter '1',
In the above step (c5), the third fastener is installed by being attached to the second vertical surface, and a space is formed between the third fastener and the second fastener.
method.
제6항에 있어서,
상기 (c5) 단계는,
(c51) 상기 제3 체결구와 상기 제2 수직면을 동시에 관통하도록 체결볼트가 볼팅되는 단계; 및
(c52) 상기 제3 체결구, 상기 경량 콘크리트 패널 및 상기 제1 수직면을 동시에 관통하도록 관통볼트가 볼팅되는 단계;를 포함하는,
방법.
In Article 6,
The above step (c5) is:
(c51) a step in which a fastening bolt is bolted to simultaneously penetrate the third fastening hole and the second vertical surface; and
(c52) a step of bolting a through bolt so as to simultaneously penetrate the third fastener, the lightweight concrete panel and the first vertical surface;
method.
제1항에 있어서,
상기 경량 콘크리트 패널의 두께는 120 mm이고,
상기 경량 콘크리트 패널의 너비는 0.5 m 내지 1 m인,
방법.
In the first paragraph,
The thickness of the above lightweight concrete panel is 120 mm,
The width of the above lightweight concrete panel is 0.5 m to 1 m,
method.
제1항 내지 제2항 및 제4항 내지 제8항 중 어느 한 항에 따른 방법에 의해 설치되는 보강 시스템.A reinforcing system installed by a method according to any one of claims 1 to 2 and claims 4 to 8.
KR1020240002200A 2024-01-05 2024-01-05 Reinforcement Method of Piloti Type Building Using Light Concrete Panel Active KR102794484B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020240002200A KR102794484B1 (en) 2024-01-05 2024-01-05 Reinforcement Method of Piloti Type Building Using Light Concrete Panel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020240002200A KR102794484B1 (en) 2024-01-05 2024-01-05 Reinforcement Method of Piloti Type Building Using Light Concrete Panel

Publications (1)

Publication Number Publication Date
KR102794484B1 true KR102794484B1 (en) 2025-04-14

Family

ID=95478052

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020240002200A Active KR102794484B1 (en) 2024-01-05 2024-01-05 Reinforcement Method of Piloti Type Building Using Light Concrete Panel

Country Status (1)

Country Link
KR (1) KR102794484B1 (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11247463A (en) * 1998-02-27 1999-09-14 Shimizu Corp Seismic retrofit method for Pilotei type RC building
JP2009174148A (en) * 2008-01-22 2009-08-06 Univ Of Ryukyus Seismic reinforcement structure of concrete structure and seismic reinforcement method
KR20200001389U (en) * 2018-12-17 2020-06-25 박시환 Lighter precast concrete panel spacer

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11247463A (en) * 1998-02-27 1999-09-14 Shimizu Corp Seismic retrofit method for Pilotei type RC building
JP2009174148A (en) * 2008-01-22 2009-08-06 Univ Of Ryukyus Seismic reinforcement structure of concrete structure and seismic reinforcement method
KR20200001389U (en) * 2018-12-17 2020-06-25 박시환 Lighter precast concrete panel spacer

Similar Documents

Publication Publication Date Title
US11680401B2 (en) Precast wall panels and method of erecting a high-rise building using the panels
US8074414B2 (en) Precast wall panels and method of erecting a high-rise building using the panels
EP1005595B1 (en) Modular wall construction and method
US7231742B2 (en) Structural braced frame wall panel system
EP3088635B1 (en) Retrofitting structure for existing building
JP2009046966A (en) Seismic reinforcement method and reinforcement piece
JP4928091B2 (en) Seismic frame at the opening of a wooden building
KR20190101513A (en) Seismic retrofit structure of RC frame and construction method thereof
KR20010012535A (en) Building framework
JPH0960107A (en) Framed wall construction building incorporating a wooden ramen frame
CN104541006A (en) Seismic Strengthening Construction Method
KR102794484B1 (en) Reinforcement Method of Piloti Type Building Using Light Concrete Panel
JP5518017B2 (en) Seismic frame at the opening of a wooden building
KR102452802B1 (en) A construction method to use the seismic resistant precast concrete members
KR102794489B1 (en) Method for selection of the optimal reinforcement location for lightweight concrete panels in piloti buildings
KR102398605B1 (en) Construction method of seismic retrofit system using pc panel
KR102408922B1 (en) Seismic retrofit structure using PC panels
KR102862881B1 (en) Reinforcement Method of Piloti Type Building Using Composite Steel Plate Wall
KR20250112341A (en) Method for selection of the optimal reinforcement location for composite steel walls in piloti buildings
KR102638837B1 (en) Steel support for pre-construction of externally attached earthquake-reinforced superstructure and construction method using the same
JP7363523B2 (en) Beam end reinforcement structure
RU2597901C1 (en) Reconstructed building and method for low-rise building reconstruction
KR20220094841A (en) Middle connecting structure of steel pilar and construction method thereof
Calder GRAND BUILDINGS, TRAFALGAR SQUARE, LONDON WC2.
JPH11172808A (en) Vibration isolation wall panel, mounting structure thereof, and repairing method of vibration isolation wall

Legal Events

Date Code Title Description
PA0109 Patent application

St.27 status event code: A-0-1-A10-A12-nap-PA0109

PA0201 Request for examination

St.27 status event code: A-1-2-D10-D11-exm-PA0201

R18-X000 Changes to party contact information recorded

St.27 status event code: A-3-3-R10-R18-oth-X000

D13-X000 Search requested

St.27 status event code: A-1-2-D10-D13-srh-X000

PE0902 Notice of grounds for rejection

St.27 status event code: A-1-2-D10-D21-exm-PE0902

E13-X000 Pre-grant limitation requested

St.27 status event code: A-2-3-E10-E13-lim-X000

P11-X000 Amendment of application requested

St.27 status event code: A-2-2-P10-P11-nap-X000

E701 Decision to grant or registration of patent right
PE0701 Decision of registration

St.27 status event code: A-1-2-D10-D22-exm-PE0701

GRNT Written decision to grant
PR0701 Registration of establishment

St.27 status event code: A-2-4-F10-F11-exm-PR0701

PR1002 Payment of registration fee

St.27 status event code: A-2-2-U10-U11-oth-PR1002

Fee payment year number: 1

PG1601 Publication of registration

St.27 status event code: A-4-4-Q10-Q13-nap-PG1601

R18 Changes to party contact information recorded

Free format text: ST27 STATUS EVENT CODE: A-5-5-R10-R18-OTH-X000 (AS PROVIDED BY THE NATIONAL OFFICE)

R18-X000 Changes to party contact information recorded

St.27 status event code: A-5-5-R10-R18-oth-X000