KR102077421B1 KR1020190048701A KR20190048701A KR102077421B1 KR 102077421 B1 KR102077421 B1 KR 102077421B1 KR 1020190048701 A KR1020190048701 A KR 1020190048701A KR 20190048701 A KR20190048701 A KR 20190048701A KR 102077421 B1 KR102077421 B1 KR 102077421B1
Authority
KR
South Korea
Prior art keywords
bolt
groove filling
groove
belt
strip
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
KR1020190048701A
Other languages
Korean (ko)
Inventor
윤용수
Original Assignee
(주)제이피이엔씨
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)제이피이엔씨 filed Critical (주)제이피이엔씨
Priority to KR1020190048701A priority Critical patent/KR102077421B1/en
Application granted granted Critical
Publication of KR102077421B1 publication Critical patent/KR102077421B1/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2200/00Geometrical or physical properties
    • E02D2200/16Shapes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

본 발명은 흙막이벽의 시공시 엄지말뚝과 띠장간에 발생된 홈을 띠장에 설치된 홈메우기 볼트로 쉽게 메울 수 있도록 하고, 홈메우기 볼트의 지지구조에 구면 결합이 적용되어 어스앵커의 설치각도에 대응하여 최적으로 앵커력이 발휘되도록 띠장이 설치될 수 있도록 한 홈메우기 볼트를 갖는 띠장 및 이의 시공 방법을 제공한다.
본 발명의 적절한 실시 형태에 따른 띠장은, 흙막이벽의 엄지말뚝에 경사되게 지지되어 엄지말뚝에 작용하는 토압을 어스앵커로 전달하는데 사용되는 띠장에 있어서, H형 단면에 의해 상부플랜지, 하부플랜지 및 복부를 갖고, 하부플랜지에 일정 간격마다 복열로 홈메우기 볼트 설치용 장공을 형성시킨 띠장 본체와; 일단이 띠장 본체에 홈메우기 볼트 설치용 장공을 통해 연결되어 띠장 본체와 엄지말뚝과의 사이에 벌어진 홈의 간격량에 대응하여 띠장 본체로부터 돌출 길이가 조정되도록 설치되는 복수개의 홈메우기 볼트와; 홈메우기 볼트의 타단에 연결되어 엄지말뚝에 정착되는 하나 이상의 홈메우기 볼트 고정판과; 홈메우기 볼트에 한 쌍씩 나사 결합되어 띠장 본체에 위치 조정된 홈메우기 볼트를 고정시키는 고정너트;가 포함되어 있는 것을 특징으로 한다.
The present invention makes it easy to fill the grooves generated between the thumb pile and the girdle during construction of the retaining wall with the grooved bolt installed in the girdle, and spherical coupling is applied to the support structure of the grooved filling bolt to correspond to the installation angle of the earth anchor. In order to provide an optimal anchoring force to provide a belt length and a construction method thereof having a groove filling bolt to be installed.
In accordance with a preferred embodiment of the present invention, the belt is inclined to the thumb pile of the retaining wall and is used to transmit earth pressure acting on the thumb pile to the earth anchor, wherein the upper flange, the lower flange and A belt main body having an abdomen and forming a slot for installing a grooved bolt in a double row at regular intervals on the lower flange; A plurality of groove filling bolts, one end of which is connected to the belt main body through a slot for installing a grooved bolt and installed to adjust a protruding length from the belt main body in response to a gap amount of a groove formed between the belt main body and the thumb pile; At least one groove filling bolt fixing plate connected to the other end of the groove filling bolt and fixed to the thumb pile; It is characterized in that it comprises a; fixing nut for fixing the groove filling bolt positionally adjusted to the strip body by screwing one pair to the groove filling bolt.

Description

홈메우기 볼트를 갖는 띠장 및 이의 시공 방법{Furring strip having groove filling bolt and construction method of the same}Furring strip having groove filling bolt and construction method of the same}

본 발명은 홈메우기 볼트를 갖는 띠장 및 이의 시공 방법에 관한 것으로, 특히 흙막이벽의 시공시 엄지말뚝과 띠장 간에 발생된 홈을 띠장에 설치된 홈메우기 볼트로 쉽게 메울 수 있도록 하고, 홈메우기 볼트의 지지구조에 구면 결합이 적용되어 어스앵커의 설치각도에 대응하여 최적으로 앵커력이 발휘되도록 띠장이 설치될 수 있도록 한 홈메우기 볼트를 갖는 띠장 및 이의 시공 방법에 관한 것이다.The present invention relates to a belt sheet having a grooved bolt and a construction method thereof, and in particular, to facilitate the filling of the grooves generated between the thumb pile and the strip during construction of the retaining wall with a grooved bolt installed in the belt, and supporting the grooved bolt A spherical coupling is applied to the structure, and the present invention relates to a belt having a groove-filled bolt and a construction method thereof so that the belt can be installed so that the anchoring force is optimally exhibited in response to the installation angle of the earth anchor.

흙막이벽은 토목 건축 현장에서 터파기 공사시 토사 등이 무너지는 것을 방지하기 위해 시공된다. 이때 흙막이벽이 무너지는 것을 방지하기 위해서는 통상 스트러트공법 또는 어스앵커 공법이 선택적으로 사용된다. 여기서 어스앵커 공법은 흙막이벽 배면에 앵커체를 형성하여 인장력에 의해 토압을 지지하는 공법으로 앵커는 인장재를 사용하여 힘을 흙 또는 암반속에 전달토록 한다. 이때 어스앵커의 두부를 정착시키기 위해 흙막이벽측 엄지말뚝에 띠장이 설치된다. 그런데 엄지말뚝은 시공 후 불규칙한 배열을 이루게 되는 경우, 엄지말뚝과 띠장과의 사이에서 불규칙한 유격(홈)발생으로, 이 홈을 메우기 위해 홈메우기 강재(앵글, 강판, H형 강재 등)가 설치된다. 이때 홈메우기 강재는 해당 위치의 엄지말뚝과 띠장간의 홈 간격이 다르므로 규격되기가 어렵고, 어스앵커의 설치방향에 따른 띠장의 기울어진 각도에 능동적 대응이 안되며, 용접 설치 작업이 어려운 문제가 있다.The retaining wall is constructed to prevent the earth and sand from collapsing during the excavation work at the civil construction site. At this time, the strut method or the earth anchor method is selectively used in order to prevent the soil wall from falling down. Here, the anchor anchor method is a method of supporting the earth pressure by the tensile force by forming the anchor body on the back of the earth wall, anchors to use the tension member to transmit the force into the soil or rock. At this time, a belt is installed in the thumb pile side of the earth wall to fix the head of the earth anchor. However, when the thumb pile is irregularly arranged after construction, irregular gaps (grooves) are generated between the thumb pile and the belt strip, and groove filling steels (angles, steel sheets, H-shaped steels, etc.) are installed to fill the grooves. . At this time, the grooved steel is difficult to be specified because the groove gap between the thumb pile and the strip of the corresponding position is different, it is difficult to actively correspond to the inclination angle of the strip according to the installation direction of the earth anchor, and the welding installation work is difficult. .

본 발명의 배경이 되는 기술로는 한국 등록특허 등록번호 제10-1677811호로서, '흙막이 지보공의 어스앵커 단독 띠장 강재 구조물 및 그 시공방법'이 제안되어 있다. 이는 서로 마주하는 강재로 띠장을 구성한 후 이러한 띠장에 스티프너 대체 용도의 간격유지용 연결이음판과 지압판 및 앵커인장부 상하고정장치, 축지지부 상하고정장치, 그리고 축볼트가 결합된 홈메우기겸용 거치대, 스페이서를 조립하여 반복 사용이 가능한 흙막이 지보공의 제거식 어스앵커 띠장 구조물을 구성한 것으로, 이를 통해 앵글 브라켓과 홈메우기용 강재의 재사용이 가능하도록 하고, 앵글브라켓과 홈메우기를 간편하게 조립 시공할 수 있도록 한 것이다.As a background technology of the present invention, Korean Registered Patent Registration No. 10-1677811 has been proposed, "Anchor ground sole steel strip structure and its construction method of earth retaining support." This is made of steel facing each other, and then used to connect gap plates for stiffener replacement, pressure plate and anchor tension part fixing device, shaft support part fixing device, and shaft bolt combined grooving brackets. Removable earth anchor belt structure of earth retaining support that can be used repeatedly by assembling spacer, which enables reuse of angle bracket and groove filling steel, and makes it easy to assemble and install angle bracket and groove filling will be.

그러나 상기 배경기술은 띠장 2개가 배면을 마주하여 설치되어야 하고, 홈메우기 겸용 거치대에 홈 간격에 따른 스페이서를 추가적으로 달리 설치해야 하고, 축볼트와 고정장치를 통해 홈메우기 겸용 거치대를 띠장에 결합시키는 추가적인 설치작업등으로 홈메우기 작업이 복잡하고, 체결부품이 많아지는 문제가 있다.However, the background art is that the two bands should be installed facing the rear, additionally installed spacers according to the groove spacing to the grooved mounting bracket, additional coupling to combine the grooved mounting bracket to the belt through the shaft bolt and the fixing device Groove filling work is complicated by the installation work, there is a problem that a lot of fastening parts.

본 발명의 배경이 되는 다른 기술로는 한국 등록특허 등록번호 제10-1364227호로서, '흙막이 벽체와 띠장 간의 홈메우기용 자라라 잭'이 제안되어 있다. 이는 팽창 및 수축이 가능한 상부 개방형의 플라스틱 케이스 구조로 구비하여, 흙막이 벽체와 띠장 간의 협소한 이격공간에 삽입한 다음, 콘크리트를 채워줌으로써, 흙막이 벽체와 띠장 간의 이격공간을 단순하면서도 손쉽게 메워줄 수 있고, 또한 흙막이 벽체와 띠장 간의 이격공간이 큰 경우, 자바라 잭을 여러개 상호 연결하여 사용할 수 있도록 함으로써, 흙막이 벽체와 띠장 간의 서로 다른 이격공간을 모두 수용하여 메워질 수 있도록 한 것이다. 그러나 상기 배경기술은 자바라 잭 설치에 따른 별도의 콘크리트 충전 및 양생 시간이 필요한 문제가 있다.As another technology that is the background of the present invention, Korean Patent Registration No. 10-1364227 has been proposed, 'Zarara Jack for home filling between the wall and the strip.' It is equipped with an upper open plastic case structure that can be expanded and contracted and inserted into a narrow space between the wall and the strip, and then filled with concrete, thereby filling the space between the wall and the strip simply and easily. In addition, when the space between the earth wall and the strip is large, the bellows jack can be connected to each other by using a large number of spaces, so that the space between the earth wall and the strip can be accommodated to fill all the different space. However, the background art has a problem that requires a separate concrete filling and curing time according to the bellows jack installation.

한국 등록특허 등록번호 제10-1677811호Korea Patent Registration No. 10-1677811 한국 등록특허 등록번호 제10-1364227호Korea Patent Registration No. 10-1364227

본 발명은 흙막이벽의 시공시 엄지말뚝과 띠장간에 발생된 홈을 띠장에 설치된 홈메우기 볼트로 쉽게 메울 수 있도록 하고, 홈메우기 볼트의 지지구조에 구면 결합이 적용되어 어스앵커의 설치각도에 대응하여 최적으로 앵커력이 발휘되도록 띠장이 설치될 수 있도록 한 홈메우기 볼트를 갖는 띠장 및 이의 시공 방법을 제공함에 그 목적이 있다.The present invention makes it easy to fill the grooves generated between the thumb pile and the girdle during construction of the retaining wall with the grooved bolt installed in the girdle, and spherical coupling is applied to the support structure of the grooved filling bolt to correspond to the installation angle of the earth anchor. It is an object of the present invention to provide a belt strip having a groove filling bolt and a construction method thereof so that the belt strip can be installed to optimally exert the anchor force.

본 발명의 적절한 실시 형태에 따른 홈메우기 볼트를 갖는 띠장은, H형 단면에 의해 상부플랜지, 하부플랜지 및 복부를 갖고, 하부플랜지에 일정 간격마다 복열로 홈메우기 볼트 설치용 장공을 형성시킨 띠장 본체와; 일단이 띠장 본체에 홈메우기 볼트 설치용 장공을 통해 연결되어 띠장 본체와 엄지말뚝과의 사이에 벌어진 홈의 간격량에 대응하여 띠장 본체로부터 돌출 길이가 조정되도록 설치되는 복수개의 홈메우기 볼트와; 홈메우기 볼트의 타단에 연결되어 엄지말뚝에 정착되는 하나 이상의 홈메우기 볼트 고정판과; 홈메우기 볼트에 한 쌍씩 나사 결합되어 띠장 본체에 위치 조정된 홈메우기 볼트를 고정시키는 고정너트가 포함되고, 홈메우기 볼트는 띠장 본체의 상부플랜지에 접합된 볼트형 스티프너에 연결커플러의 나사 결합을 매개로 연결되어, 연결커플러의 회전 조작방향에 따라 홈메우기 볼트의 이동 조절이 이루어지도록 하되, 홈메우기 볼트 고정판에는 반구홈이 구비되고; 홈메우기 볼트는 육각단면을 갖는 볼트 몸체, 볼트 몸체의 일단에 형성되어 상기 반구홈에 구면 결합되는 힌지볼, 볼트 몸체의 타단에 길게 형성되어 고정너트가 체결되는 고정너트 체결나사부로 구성된 것을 특징으로 한다.The belt-length having the grooved bolt according to the preferred embodiment of the present invention includes a belt-shaped body having an upper flange, a lower flange, and an abdomen with an H-shaped cross section, and forming a hole for installing the grooved-bolt bolt in a double row at regular intervals on the lower flange; ; A plurality of groove filling bolts, one end of which is connected to the belt main body through a slot for installing a grooved bolt and installed to adjust a protruding length from the belt main body in response to a gap amount of a groove formed between the belt main body and the thumb pile; At least one groove filling bolt fixing plate connected to the other end of the groove filling bolt and fixed to the thumb pile; A fastening nut is fixed to the slotted body by a pair of screwed in the slotted bolt to fix the grooved bolt positioned on the stripe body, and the slotted bolt is connected to the bolted stiffener connected to the upper flange of the stripe body. Is connected to, so that the movement adjustment of the groove filling bolt is made according to the rotation operation direction of the coupling coupler, the groove filling bolt fixing plate is provided with a hemisphere groove; The groove filling bolt is formed of a bolt body having a hexagonal cross section, a hinge ball formed at one end of the bolt body and spherically coupled to the hemisphere groove, and formed at the other end of the bolt body so as to be fastened to a fixing nut fastening screw portion to which a fixing nut is fastened. do.

삭제delete

또한, 홈메우기 볼트 고정판에는 구면 결합되어 있는 볼 너트가 설치되어 있고; 홈메우기 볼트는 육각단면을 갖는 볼트 몸체와, 볼트 몸체의 일단에 형성되어 상기 볼 너트에 나사 결합되는 볼 너트 체결나사부, 볼트 몸체의 타단에 길게 형성되어 고정너트가 체결되는 고정너트 체결나사부로 구성된 것을 특징으로 한다.In addition, the grooved bolt fixing plate is provided with a ball nut that is spherically coupled; The groove filling bolt is composed of a bolt body having a hexagonal cross section, a ball nut fastening screw portion formed at one end of the bolt body and screwed to the ball nut, and a fixed nut fastening screw portion formed at the other end of the bolt body to fasten a fixing nut. It is characterized by.

또한, 홈메우기 볼트는 홈메우기 볼트 고정판에 경사지게 접합되어 있는 틸팅너트에 나사 결합으로 연결되는 것을 특징으로 한다.In addition, the groove filling bolt is characterized in that it is connected by screwing to the tilting nut that is inclined to the groove filling bolt fixing plate.

또한, 홈메우기 볼트는 띠장 본체의 상부플랜지에 접합된 볼트형 스티프너에 연결커플러의 나사 결합을 매개로 연결되어, 연결커플러의 회전 조작방향에 따라 홈메우기 볼트의 이동 조절이 이루어지도록 한 것을 특징으로 한다.In addition, the groove filling bolt is connected to the bolt type stiffener bonded to the upper flange of the belt body via the screw coupling of the coupling coupler, characterized in that the movement of the groove filling bolt is adjusted according to the rotation operation direction of the coupling coupler. do.

또한, 띠장 본체에 어스앵커가 설치되는 위치마다에 어스앵커의 설치위치 조정을 수용할 수 있도록 수평방향으로 길게 절단되어 형성된 어스앵커 인장재설치용 장공이 더 형성되고, 어스앵커 인장재설치용 장공의 둘레로 상,하부 플랜지에 접합되는 복수의 수평보강판이 설치되어 있는 것을 특징으로 한다.In addition, an earth anchor tension member installation hole is further formed in each of the positions where the earth anchor is installed in the strip body to accommodate the adjustment of the installation position of the earth anchor. It is characterized in that a plurality of horizontal reinforcing plate joined to the lower flange is installed.

또한, 어스앵커 인장재설치용 수평장공은 띠장 본체의 복부를 관통한 단일형으로 형성된 것을 특징으로 한다.In addition, the horizontal anchor hole for installing the anchor anchor is characterized in that it is formed in a single shape through the abdomen of the belt body.

또한, 어스앵커 인장재설치용 수평장공은 띠장 본체의 복부를 대칭형으로 하여 2열로 형성된 것을 특징으로 한다.In addition, the horizontal anchor hole for installing the earth anchor tension member is characterized in that formed in two rows by making the abdomen of the strip body main body symmetrical.

또한, 홈메우기 볼트 설치용 장공측에 상,하부 플랜지에 접합되는 복수의 수직보강판이 더 설치되어 있는 것을 특징으로 한다.In addition, a plurality of vertical reinforcing plates joined to the upper and lower flanges on the slotted side for installing the groove filling bolt is further characterized in that it is installed.

한편, 본 발명에 따른 홈메우기 볼트를 갖는 띠장의 시공 방법은, 띠장 본체에 홈메우기 볼트 고정판과 연결되어 있는 홈메우기 볼트를 고정너트로 가조립하여 놓는 단계와; 띠장 본체를 인양하여 엄지 말뚝에 설치된 띠장브라켓에 올려 지지시켜 놓는 단계와; 홈메우기 볼트의 위치를 조정하여 홈메우기 볼트 고정판을 엄지 말뚝에 밀착시켜 용접 접합시켜 놓는 단계와; 띠장과 엄지 말뚝간의 홈 간격에 따른 홈메우기 볼트의 위치를 조정하여 띠장 본체의 설치 자세를 조정한 후 고정너트를 조임하여 홈메우기 볼트를 띠장 본체에 확고하게 고정시켜 놓는 단계;를 포함하여 시공되는 것을 특징으로 한다.On the other hand, the construction method of the strip length having the groove filling bolt according to the present invention, the step of pre-assembling the groove filling bolt connected to the groove filling bolt fixing plate on the strip body; Lifting the belt main body to support and support it on a belt bracket installed on the thumb pile; Adjusting the position of the grooved bolts to bring the grooved bolt fixing plate into close contact with the thumb pile to weld the grooves; After adjusting the position of the groove filling bolt according to the groove spacing between the belt and the thumb pile to adjust the installation posture of the belt body, tightening the fixing nut to firmly fix the groove filling bolt to the belt body; It is characterized by.

또한, 홈메우기 볼트의 위치 조정은 띠장 본체측 볼트형 스티프너와 홈메우기 볼트를 나사 연결하는 연결커플러의 회전 조작을 통하여 이루어지는 것을 특징으로 한다.In addition, the position adjustment of the groove filling bolt is characterized in that made through the rotation operation of the coupling coupler for screwing the belt-shaped stiffener and the groove filling bolt.

본 발명의 홈메우기 볼트를 갖는 띠장 및 이의 시공 방법에 따르면, 띠장에 설치되는 홈메우기 볼트의 돌출 길이의 조절로 엄지말뚝과 띠장간에 발생된 홈 간격에 대응하여 홈 메우기를 용이하게 실시할 수 있다. 또한 홈메우기 볼트는 홈메우기 볼트 고정판을 통해 볼결합(구면결합)되어 있어 어느 방향으로든 경사 조절이 가능토록 띠장이 설치됨으로써 어스앵커의 설치각도에 대응하여 최적으로 앵커력이 발휘될 수 있다. 또한 홈메우기 볼트의 적용으로 종래와 같이 홈메우기 강재의 어려운 용접 작업이 없어지는 이점을 갖는다. 또한, 띠장에 일정간격마다 길게 형성된 어스앵커 인장재설치용 장공에 의해 어스앵커의 센터간 위치를 쉽게 조정할 수 있다.According to the belt strip having the grooved bolt of the present invention and a construction method thereof, groove filling can be easily performed corresponding to the groove spacing generated between the thumb pile and the strip length by adjusting the protruding length of the grooved bolts installed in the belt length. have. In addition, the groove filling bolt is ball-coupled (spherical coupling) through the groove filling bolt fixing plate is installed so that the inclination can be adjusted in any direction, the anchoring force can be optimally exhibited in response to the installation angle of the earth anchor. In addition, the application of the grooved bolt has the advantage that difficult welding work of the grooved steel as in the prior art is eliminated. In addition, the position between the centers of the earth anchors can be easily adjusted by means of the earth anchor tension member installation holes formed in the belt length at regular intervals.

본 명세서에서 첨부되는 다음의 도면들은 본 발명의 바람직한 실시 예를 예시하는 것이며, 발명의 상세한 설명과 함께 본 발명의 기술사상을 더욱 이해시키는 역할을 하는 것이므로, 본 발명은 첨부한 도면에 기재된 사항에만 한정되어서 해석되어서는 아니 된다.
도 1은 본 발명에 따른 홈메우기 볼트를 갖는 띠장의 설치상태도.
도 2는 도 1에 적용된 띠장이 설치된 상태에서의 정면도.
도 3은 도 2의 평면도.
도 4는 도 1에 적용된 띠장의 사시도.
도 5는 도 2의 측단면도.
도 6은 도 5에 도시된 홈메우기 볼트에 연결커플러가 추가적으로 설치된 상태도.
도 7은 도 2의 A-A선 단면도.
도 8은 본 발명에 적용되는 일 형태의 홈메우기 볼트와 홈메우기 볼트 고정판의 결합상태도.
도 9는 본 발명에 적용되는 다른 형태의 홈메우기 볼트와 홈메우기 볼트 고정판의 결합상태도.
도 10a 및 도 10b는 본 발명에 적용되는 띠장 본체측 어스애커가 설치되는 어스앵커 인장재설치용 장공의 다양한 배열 구성도.
도 11은 본 발명에 적용되는 홈메우기 볼트 고정판의 다른 실시 예의 사시도.
The following drawings attached in this specification are illustrative of the preferred embodiments of the present invention, and together with the detailed description of the invention serves to further understand the technical spirit of the present invention, the present invention is only to the matter described in the accompanying drawings It should not be construed as limited.
1 is an installation state of the strip having a groove filling bolt according to the present invention.
FIG. 2 is a front view in a state where the belt length applied to FIG. 1 is installed. FIG.
3 is a plan view of FIG.
Figure 4 is a perspective view of the strip length applied to Figure 1;
5 is a side cross-sectional view of FIG.
Figure 6 is a state in which the coupling coupler is additionally installed in the groove filling bolt shown in FIG.
7 is a cross-sectional view taken along the line AA of FIG. 2.
8 is a coupling state of the groove filling bolt and the groove filling bolt fixing plate of one embodiment applied to the present invention.
9 is a coupling state of the groove filling bolt and the groove filling bolt fixing plate of another form applied to the present invention.
Figure 10a and Figure 10b is a configuration diagram of a variety of arrangements for the anchor anchor tension member installation hole is installed on the strip body side earth anchor applied to the present invention.
Figure 11 is a perspective view of another embodiment of the grooved bolt fixing plate applied to the present invention.

아래에서 본 발명은 첨부된 도면에 제시된 실시 예를 참조하여 상세하게 설명이 되지만 제시된 실시 예는 본 발명의 명확한 이해를 위한 예시적인 것으로 본 발명은 이에 제한되지 않는다.In the following the present invention will be described in detail with reference to the embodiments shown in the accompanying drawings, but the embodiments presented are exemplary for a clear understanding of the present invention is not limited thereto.

본 발명에 따른 띠장(100)은 흙막이 벽의 엄지말뚝(12)에 경사되게 지지되어 엄지말뚝(12)에 작용하는 토압을 어스앵커(200)로 전달하는데 사용된다. 특히 띠장(100)은 흙막이 벽의 시공시 일정 간격마다 설치된 엄지말뚝(12)의 불균일한 정열 및 자세로 해당 엄지말뚝(12)과의 사이에 발생되는 홈의 간격 변화에 대응하여 이를 메울 수 있도록 구성한 것이다.The strip 100 according to the present invention is supported to be inclined to the thumb pile 12 of the retaining wall is used to transmit the earth pressure acting on the thumb pile 12 to the earth anchor 200. In particular, the strip 100 is a non-uniform alignment and posture of the thumb pile 12 installed at regular intervals during the construction of the wall wall so as to fill the gap in response to the gap change between the groove and the corresponding thumb pile 12 It is configured.

도 1 내지 도 6과 같이 띠장(100)은 H형 단면에 의해 상부플랜지(111), 하부플랜지(112) 및 복부(113)를 갖는 띠장 본체(110)를 구비한다. 띠장 본체(110)는 단위 길이를 가질 수 있으나 현장 여건에 따라 단위 길이를 절단하여 사용되거나 상,하부 플랜지(111,112)에 강판(도시안됨)을 볼트 접합을 통해 상호 연결되어 단위 길이 이상으로 길게 연결될 수 있다.1 to 6, the strip 100 has a strip main body 110 having an upper flange 111, a lower flange 112 and the abdomen 113 by the H-shaped cross section. The strip body 110 may have a unit length, but may be used by cutting the unit length according to the site conditions, or may be connected to the upper and lower flanges 111 and 112 by bolted joints to be connected longer than the unit length. Can be.

또한, 띠장 본체(110)는 하부플랜지(112)에 일정 간격마다 복열로 홈메우기 볼트 설치용 장공(112a)이 형성된다. 홈메우기 볼트 설치용 장공(112a)은 후술할 홈메우기 볼트(130 또는 130a)를 설치하기 위한 것이다. 홈메우기 볼트 설치용 장공(112a)은 길게 형성되어 있어 엄지말뚝(12)의 설치 위치에 대응하여 홈메우기 볼트(130 또는 130a)의 설치 위치를 조정할 수 있다.In addition, the strip main body 110 is formed in the lower flange 112 is a long hole 112a for installing the groove filling bolt in a double row at regular intervals. The slotting hole 112a for installing the grooved bolt is for installing the grooved bolt 130 or 130a to be described later. The slotting hole 112a for installing the filling groove bolt is formed to be long so that the mounting position of the filling groove bolt 130 or 130a may be adjusted in correspondence with the mounting position of the thumb pile 12.

띠장 본체(110)는 홈메우기 볼트 설치용 장공(112a)으로 인해 발생된 단면 손실을 복수의 수직보강판(115)을 통해 방지할 수 있다. 복수의 수직보강판(115)은 상,하부 플랜지(111,112)에 접합되어 복부(113)에 직각되게 설치된다.The strip body 110 may prevent the cross-sectional loss caused by the groove filling bolt installation long hole 112a through the plurality of vertical reinforcing plates 115. The plurality of vertical reinforcing plates 115 are joined to the upper and lower flanges 111 and 112 and installed at right angles to the abdomen 113.

띠장 본체(110)에 복수개의 홈메우기 볼트(130)가 설치된다. 홈메우기 볼트(130)는 일단이 띠장 본체(110)에 설치되어 띠장 본체(110)와 엄지말뚝(12)과의 사이에 벌어진 홈의 간격량에 대응하여 띠장 본체(110)로부터 돌출 길이가 조정되도록 설치된다. 본 실시 예에서 홈메우기 볼트(130)는 띠장 본체(110)의 하부플랜지(112)에 2열로 형성된 홈메우기 볼트 설치용 장공(112a)을 통해 설치된다. 이때 복수개의 홈메우기 볼트(130)는 동일한 길이를 가질 수 있지만, 통상 어스앵커(200)가 경사지게 설치되므로, 도 4 및 도 5와 같이 2열로 설치되는 경우 홈메우기 간격이 좁은 위치에 설치되는 것을 짧게 하고 상대적으로 홈메우기 간격이 넓은 위치에 설치되는 것을 길게 함이 바람직하다.A plurality of groove filling bolts 130 are installed in the belt-shaped body 110. The groove filling bolt 130 has one end installed in the belt main body 110 so that the length of the protrusion from the belt main body 110 is adjusted in response to the gap amount of the groove formed between the belt main body 110 and the thumb pile 12. It is installed as possible. In the present embodiment, the groove filling bolt 130 is installed through the groove filling bolt mounting hole 112a formed in two rows on the lower flange 112 of the strip body 110. In this case, the plurality of groove filling bolts 130 may have the same length, but since the earth anchors 200 are installed inclined in an inclined manner, when the groove filling bolts are installed in two rows as shown in FIGS. It is desirable to shorten and lengthen the installation in a location where the groove filling interval is wide.

도 8과 같이 일 형태의 홈메우기 볼트(130)는 육각단면을 갖는 볼트 몸체(131), 볼트 몸체(131)의 일단에 형성되어 후술할 홈메우기 볼트 고정판(120)에 형성된 반구홈(121)에 구면 결합되는 힌지볼(132), 볼트 몸체(131)의 타단에 길게 형성되어 고정너트(140)가 체결되는 고정너트 체결나사부(133)로 구성될 수 있다.As shown in FIG. 8, the groove filling bolt 130 has a hemispherical groove 121 formed at one end of the bolt body 131 having a hexagonal cross section and the bolt body 131 and formed at the groove filling bolt fixing plate 120 to be described later. The hinge ball 132 is spherically coupled to the other end of the bolt body 131 may be formed of a fixing nut fastening screw portion 133 to which the fixing nut 140 is fastened.

따라서 홈메우기 볼트(130)는 체결나사부(133)가 띠장 본체(110)측 홈메우기 볼트 설치용 장공(112a)에 삽입된 후, 체결나사부(133)에 체결된 한 쌍의 고정너트(140)에 체결되어 띠장 본체(110)에 확고하게 고정 설치된다. 이때 한 쌍의 고정너트(140)의 체결 위치에 따라 홈메우기 볼트(130)의 설치 위치가 조정된다.Therefore, the grooved filling bolt 130 is fastened to the pair of fixing nuts 140 fastened to the fastening screw portion 133 after the fastening screw portion 133 is inserted into the slotted body mounting hole 112a for the slotted main body 110 side. It is fastened to the belt main body 110 is firmly installed. At this time, the installation position of the groove filling bolt 130 is adjusted according to the fastening position of the pair of fixing nuts 140.

홈메우기 볼트(130)는 타단에 엄지말뚝(12)에 정착되는 하나 이상의 홈메우기 볼트 고정판(120)에 연결된다. 홈메우기 볼트 고정판(120)에는 홈메우기 볼트(130)의 힌지볼(132)이 구면결합(볼결합)되는 반구홈(121)이 구비된다. 따라서 홈메우기 볼트(130)는 홈메우기 볼트 고정판(120)에서 반구홈(121)의 중심을 기준으로 자유로운 결합각도를 가질 수 있어 띠장(200)의 설치 각도를 어스앵커(200)에 대응하여 쉽게 변경할 수 있게 된다.The groove filling bolt 130 is connected to one or more groove filling bolt fixing plates 120 fixed to the thumb pile 12 at the other end. The groove filling bolt fixing plate 120 is provided with a hemisphere groove 121 in which the hinge ball 132 of the groove filling bolt 130 is spherically coupled (ball coupled). Therefore, the groove filling bolt 130 may have a free coupling angle with respect to the center of the hemisphere groove 121 in the groove filling bolt fixing plate 120, so that the installation angle of the strip 200 is easily corresponded to the earth anchor 200. You can change it.

여기서 홈메우기 볼트(130)의 힌지볼(132)이 반구홈(121)에서 이탈되지 않기 위해 도 8과 같이 홈메우기 볼트 고정판(120)에 홈메우기 볼트 이탈방지용 플레이트(127)가 더 설치될 수 있다.In order to prevent the hinge ball 132 of the groove filling bolt 130 from being separated from the hemisphere groove 121, the groove filling bolt fixing plate 120 may be further installed on the groove filling bolt fixing plate 120 as shown in FIG. 8. have.

한편, 도 6과 같이 홈메우기 볼트(130)는 띠장 본체(110)의 상부플랜지(111)에 접합된 볼트형 스티프너(150)에 연결커플러(152)의 나사 결합을 매개로 연결되어 구성될 수 있다. 따라서 연결커플러(152)의 회전 조작방향에 따라 나사 결합을 통해 홈메우기 볼트(130 또는 130a)의 이동 조절이 이루어지도록 할 수 있다. 물론 홈메우기 볼트(130 또는 130a)의 이동 조절 후에는 한 쌍의 고정너트(140)를 조여 띠장 본체(110)에 확고히 고정시킨다.On the other hand, as shown in Figure 6, the groove filling bolt 130 may be configured by connecting the screw coupling of the coupling coupler 152 to the bolt-shaped stiffener 150 bonded to the upper flange 111 of the strip body 110. have. Therefore, it is possible to adjust the movement of the groove filling bolt 130 or 130a through the screw coupling in accordance with the rotation operation direction of the connection coupler 152. Of course, after adjusting the movement of the groove filling bolt 130 or 130a by tightening a pair of fixing nuts 140 to be firmly fixed to the strip body (110).

이때 홈메우기 볼트(130 또는 130a)에 연결된 연결커플러(152)와 볼트형 스티프너(150)는 보강 기능과 함께 홈메우기 볼트(130 또는 130a)가 받는 지지력을 띠장 본체(110)에 분산시키는 역할도 수행한다.At this time, the coupling coupler 152 and the bolt-shaped stiffener 150 connected to the grooved bolt 130 or 130a also serve to distribute the bearing force received by the grooved bolt 130 or 130a to the strip body 110 together with the reinforcement function. To perform.

다른 한편, 도 4 및 도 7과 같이 띠장 본체(110)에 어스앵커(200)가 설치되는 위치마다 어스앵커(200)의 설치위치 조정을 수용할 수 있도록 수평방향으로 길게 절단되어 형성된 어스앵커 인장재설치용 장공(112b)이 더 형성될 수 있다. On the other hand, as shown in Figures 4 and 7, the earth anchor tension member formed by cutting long in the horizontal direction to accommodate the adjustment of the installation position of the earth anchor 200 for each position where the earth anchor 200 is installed in the strip body (110) An installation hole 112b may be further formed.

이때 어스앵커 인장재설치용 장공(112b)의 둘레로 상,하부 플랜지(111,112)에 접합되는 복수의 수평보강판(117)이 설치됨이 바람직하다. 따라서 어스앵커 인장재설치용 장공(112b)의 둘레가 복수의 수평보강판(117)으로 보강되어지고 띠장 본체(110)에서 발생된 단면 손실을 메울 수 있다.At this time, it is preferable that a plurality of horizontal reinforcing plates 117 joined to the upper and lower flanges 111 and 112 around the earth anchor tension member installation hole 112b. Therefore, the periphery of the earth anchor tension member installation hole (112b) is reinforced with a plurality of horizontal reinforcing plate 117 can fill the cross-sectional loss generated in the strip body (110).

여기서 도 4 및 도 10a와 같이 어스앵커 인장재설치용 장공(112b)은 띠장 본체(100)의 복부(113)를 관통한 단일형으로 형성될 수 있다. 또한, 도 10b와 같이 어스앵커 인장재설치용 장공(112b)은 띠장 본체(110)의 복부(113)를 대칭형으로 하여 2열로 형성될 수 있다.Here, as shown in FIGS. 4 and 10A, the earth anchor tension member installation hole 112b may be formed in a single shape through the abdomen 113 of the strip body 100. Also, as shown in FIG. 10B, the earth anchor tension member installation hole 112b may be formed in two rows by making the abdomen 113 of the strip body 110 symmetrical.

이와 같이 구성된 홈메우기 볼트를 갖는 띠장의 시공 방법에 대하여 설명한다.The construction method of the strip | belt length which has the grooved bolt comprised in this way is demonstrated.

먼저, 도 4와 같이 띠장 본체(110)에 홈메우기 볼트 고정판(120)과 연결되어 있는 홈메우기 볼트(130)를 고정너트(140)로 가조립하여 놓는다.First, as shown in FIG. 4, the groove filling bolt 130 connected to the groove filling bolt fixing plate 120 is temporarily assembled with the fixing nut 140.

그 다음, 도 5와 같이 띠장 본체(110)를 인양하여 엄지 말뚝(12)에 설치된 띠장브라켓(14)에 올려 지지시켜 놓는다.Next, as shown in FIG. 5, the strip main body 110 is lifted and supported on the strip bracket 14 installed on the thumb pile 12.

그 다음, 홈메우기 볼트(130)의 위치를 조정하여 홈메우기 볼트 고정판(120)을 엄지 말뚝(12)에 밀착되도록 용접 접합시켜 놓는다.Then, by adjusting the position of the grooved bolt 130 is welded to the grooved bolt fixing plate 120 to be in close contact with the thumb pile 12.

그 다음, 띠장(100)과 엄지 말뚝(12)간의 홈 간격에 따른 홈메우기 볼트(130)의 위치를 조정하여 띠장 본체(110)의 설치 자세를 조정한다. 이때 홈메우기 볼트(130)의 위치 조정에 따라 띠장 본체(110)의 기울어진 설치 자세가 조정되어 띠장 브라켓(15)에 지지되게 설치된다. Then, by adjusting the position of the groove filling bolt 130 according to the groove spacing between the strip 100 and the thumb pile 12 to adjust the installation posture of the strip main body 110. At this time, the inclined installation posture of the belt body 110 is adjusted according to the position adjustment of the groove filling bolt 130, and is installed to be supported by the belt bracket 15.

여기서, 홈메우기 볼트(130)의 위치 조정은 도 6과 같이 띠장 본체(100)측 볼트형 스티프너(150)와 홈메우기 볼트(130)를 나사 연결하는 연결커플러(152)의 회전 조작을 통하여 이루어질 수 있다.Here, the adjustment of the position of the groove filling bolt 130 is made through the rotation operation of the coupling coupler 152 for screwing the bolt-shaped stiffener 150 and the groove filling bolt 130 as shown in FIG. Can be.

이후, 고정너트(140)를 조임하여 홈메우기 볼트(130)를 띠장 본체(110)에 확고하게 고정시켜 놓음으로써 띠장 본체(110)의 설치가 완료된다.Thereafter, the fixing nut 140 is tightened to firmly fix the groove filling bolt 130 to the strip main body 110, thereby completing the installation of the strip main body 110.

그 다음, 도 7과 같이 어스앵커(200)의 설치가 이루어진다. 이는 인장재(202)를 띠장(100)에 형성된 어스앵커 설치용 장공(112b)을 통해 삽입하여 흙막이 벽체에 형성시키는 천공홀 내부로 집어넣어 선단을 정착시킨 후 지압판(204)을 인장재(202)의 노출단에 끼워 띠장 본체(110)에 밀착시킨 후 인장하여 지압판(204)에 위치시킨 앵커헤드(206)에 정착시켜서 이루어진다.Then, the earth anchor 200 is installed as shown in FIG. This inserts the tension member 202 through the earth anchor installation hole 112b formed in the strip 100, inserts the tension member 202 into the perforation hole to be formed in the wall, and fixes the tip. Then, the pressure plate 204 is exposed to the tension member 202. It is made by being fixed to the anchor head 206 positioned on the acupressure plate 204 after being brought into close contact with the strip main body 110 at the end.

한편, 도 9와 같이 다른 실시 예로 홈메우기 볼트 고정판(120)에는 구면 결합되어 있는 볼 너트(125)가 설치되어 다른 형태의 홈메우기 볼트(130a)가 연결될 수 있다. 이때 변형된 홈메우기 볼트(130a)는 육각단면을 갖는 볼트 몸체(1301)와, 볼트 몸체(1301)의 일단에 형성되어 상기 볼 너트(125)에 나사 결합되는 볼 너트 체결나사부(1302), 볼트 몸체(1301)의 타단에 길게 형성되어 고정너트(140)가 체결되는 고정너트 체결나사부(1303)로 구성될 수 있다.On the other hand, as shown in Figure 9, the groove filling bolt fixing plate 120 is provided with a ball nut 125 that is spherically coupled to another groove filling bolt 130a can be connected. At this time, the deformed groove filling bolt (130a) is formed on one end of the bolt body (1301) having a hexagonal cross section, the bolt body 1301, the ball nut fastening screw portion (1302), which is screwed to the ball nut 125, bolt It is formed on the other end of the body 1301 and may be composed of a fixing nut fastening screw portion 1303 to which the fixing nut 140 is fastened.

여기서 도 11과 같이 홈메우기 볼트(130a)는 홈메우기 볼트 고정판(120)에 경사지게 접합되어 있는 틸팅너트(126)에 나사 결합으로 연결될 수도 있다.Here, as shown in FIG. 11, the groove filling bolt 130a may be connected to the tilting nut 126 that is inclinedly joined to the groove filling bolt fixing plate 120 by screwing.

지금까지 본 발명은 제시된 실시 예를 참조하여 상세하게 설명이 되었지만 이 분야에서 통상의 지식을 가진 자는 제시된 실시 예를 참조하여 본 발명의 기술적 사상을 벗어나지 않는 범위에서 다양한 변형 및 수정 발명을 만들 수 있을 것이다. 본 발명은 이와 같은 변형 및 수정 발명에 의하여 제한되지 않으며 다만 아래에 첨부된 청구범위에 의하여 제한된다. So far, the present invention has been described in detail with reference to the presented embodiments, but those skilled in the art may make various modifications and modifications without departing from the technical spirit of the present invention with reference to the presented embodiments. will be. The present invention is not limited by these modifications and variations, but only by the claims appended below.

100: 띠장
102: 어스앵커 인장재설치용 수평장공
110: 띠장 본체
112a: 홈메우기 볼트 설치용 장공
120: 홈메우기 볼트 고정판
130,130a: 홈메우기 볼트
140: 고정너트
150: 볼트형 스티프너
152: 연결커플러
100: Sash
102: horizontal anchor for earth anchor tension material installation
110: strip body
112a: Long hole for homefill bolt installation
120: grooved bolt fixing plate
130,130a: Homefill bolt
140: fixing nut
150: bolt type stiffener
152: coupler

Claims (11)

삭제delete 흙막이벽의 엄지말뚝(12)에 경사되게 지지되어 엄지말뚝(12)에 작용하는 토압을 어스앵커(200)로 전달하는데 사용되는 띠장(100)에 있어서,
H형 단면에 의해 상부플랜지(111), 하부플랜지(112) 및 복부(113)를 갖고, 하부플랜지(112)에 일정 간격마다 복열로 홈메우기 볼트 설치용 장공(112a)을 형성시킨 띠장 본체(110)와;
일단이 띠장 본체(110)에 홈메우기 볼트 설치용 장공(112a)을 통해 연결되어 띠장 본체(110)와 엄지말뚝(12)과의 사이에 벌어진 홈의 간격량에 대응하여 띠장 본체(110)로부터 돌출 길이가 조정되도록 설치되는 복수개의 홈메우기 볼트(130 또는 130a)와;
홈메우기 볼트(130 또는 130a)의 타단에 연결되어 엄지말뚝(12)에 정착되는 하나 이상의 홈메우기 볼트 고정판(120)과;
홈메우기 볼트(130 또는 130a)에 한 쌍씩 나사 결합되어 띠장 본체(110)에 위치 조정된 홈메우기 볼트(130)를 고정시키는 고정너트(140);가 포함되고,
홈메우기 볼트(130)는 띠장 본체(110)의 상부플랜지(111)에 접합된 볼트형 스티프너(150)에 연결커플러(152)의 나사 결합을 매개로 연결되어, 연결커플러(152)의 회전 조작방향에 따라 홈메우기 볼트(130)의 이동 조절이 이루어지도록 하되, 홈메우기 볼트 고정판(120)에는 반구홈(121)이 구비되고;
홈메우기 볼트(130)는 육각단면을 갖는 볼트 몸체(131), 볼트 몸체(131)의 일단에 형성되어 상기 반구홈(121)에 구면 결합되는 힌지볼(132), 볼트 몸체(131)의 타단에 길게 형성되어 고정너트(140)가 체결되는 고정너트 체결나사부(133)로 구성된 것을 특징으로 하는 홈메우기 볼트를 갖는 띠장.
In the belt 100, which is inclined to the thumb pile 12 of the retaining wall and used to transmit the earth pressure acting on the thumb pile 12 to the earth anchor 200,
H-shaped cross-section main body 110 having an upper flange 111, a lower flange 112 and the abdomen 113, and formed in the lower flange 112 a slot for mounting the groove filling bolts 112a in a row at regular intervals. )Wow;
One end is connected to the belt-shaped body 110 through a slot for mounting a grooved bolt 112a and protrudes from the belt-shaped body 110 in response to the gap amount of the groove formed between the belt-shaped body 110 and the thumb pile 12. A plurality of grooved bolts 130 or 130a installed to adjust the length;
At least one groove filling bolt fixing plate 120 connected to the other end of the groove filling bolt 130 or 130a and fixed to the thumb pile 12;
A fixing nut 140 which is screwed to the groove filling bolt 130 or 130a by a pair to fix the groove filling bolt 130 positioned on the strip-shaped body 110 is included.
The groove filling bolt 130 is connected to the bolt type stiffener 150 bonded to the upper flange 111 of the strip body 110 via a screw coupling of the coupling coupler 152 to rotate the coupling coupler 152. To adjust the movement of the groove filling bolt 130 according to the direction, the groove filling bolt fixing plate 120 is provided with a hemisphere groove 121;
The groove filling bolt 130 is formed at one end of the bolt body 131 having a hexagonal cross section, the bolt body 131, and the other end of the hinge ball 132 and the bolt body 131 that are spherically coupled to the hemisphere groove 121. Longitudinally formed in the belt having a groove filling bolt, characterized in that consisting of a fixing nut fastening screw portion 133 is fastened to the fixing nut 140.
제 2항에 있어서,
홈메우기 볼트 고정판(120)에는 구면 결합되어 있는 볼 너트(125)가 설치되어 있고;
홈메우기 볼트(130a)는 육각단면을 갖는 볼트 몸체(1301)와, 볼트 몸체(1301)의 일단에 형성되어 상기 볼 너트(125)에 나사 결합되는 볼 너트 체결나사부(1302), 볼트 몸체(1301)의 타단에 길게 형성되어 고정너트(140)가 체결되는 고정너트 체결나사부(1303)로 구성된 것을 특징으로 하는 홈메우기 볼트를 갖는 띠장.
The method of claim 2,
The grooved bolt fixing plate 120 is provided with a ball nut 125 which is spherically coupled;
The groove filling bolt 130a has a bolt body 1301 having a hexagonal cross section, a ball nut fastening screw portion 1302 formed on one end of the bolt body 1301, and screwed to the ball nut 125, and a bolt body 1301. Longitudinally formed on the other end of the) long belt having a groove filling bolt, characterized in that consisting of a fixing nut fastening screw portion 1303 is fastened to the fixing nut 140.
제 2항에 있어서,
홈메우기 볼트(130a)는 홈메우기 볼트 고정판(120)에 경사지게 접합되어 있는 틸팅너트(126)에 나사 결합으로 연결되는 것을 특징으로 하는 홈메우기 볼트를 갖는 띠장.
The method of claim 2,
Grooving bolt (130a) is a belt having a groove filling bolt, characterized in that connected to the tilting nut 126, which is inclined to the groove filling bolt fixing plate 120 by screwing.
삭제delete 제 2항에 있어서,
띠장 본체(110)에 어스앵커(200)가 설치되는 위치마다에 어스앵커(200)의 설치위치 조정을 수용할 수 있도록 수평방향으로 길게 절단되어 형성된 어스앵커 인장재설치용 장공(112b)이 더 형성되고, 어스앵커 인장재설치용 장공(112b)의 둘레로 상,하부 플랜지(111,112)에 접합되는 복수의 수평보강판(117)이 설치되어 있는 것을 특징으로 하는 홈메우기 볼트를 갖는 띠장.
The method of claim 2,
An earth anchor tension member installation hole 112b is further formed to be horizontally cut in a horizontal direction so as to accommodate adjustment of the installation position of the earth anchor 200 at each position where the earth anchor 200 is installed in the strip body 110. And a plurality of horizontal reinforcing plates 117 joined to the upper and lower flanges 111 and 112 around the earth anchor tension member installation hole 112b.
제 6항에 있어서,
어스앵커 인장재설치용 장공(112b)은 띠장 본체(100)의 복부(113)를 관통한 단일형으로 형성된 것을 특징으로 하는 홈메우기 볼트를 갖는 띠장.
The method of claim 6,
Earth anchor tension member installation hole (112b) is a strip having a groove filling bolt, characterized in that formed in the unitary through the abdomen 113 of the strip body 100.
제 6항에 있어서,
어스앵커 인장재설치용 장공(112b)은 띠장 본체(110)의 복부(113)를 대칭형으로 하여 2열로 형성된 것을 특징으로 하는 홈메우기 볼트를 갖는 띠장.
The method of claim 6,
Earth anchor tension member installation hole (112b) is a strip having a groove filling bolt, characterized in that formed in two rows symmetrical the abdomen 113 of the strip body 110.
제 2항에 있어서,
홈메우기 볼트 설치용 장공(112a)측에 상,하부 플랜지(111,112)에 접합되는 복수의 수직보강판(115)이 더 설치되어 있는 것을 특징으로 하는 홈메우기 볼트를 갖는 띠장.
The method of claim 2,
A groove having bolts for groove filling bolts, characterized in that a plurality of vertical reinforcing plates (115) joined to the upper and lower flanges (111, 112) are further provided on the side of the slot (112a) for installing the groove filling bolts.
삭제delete 띠장 본체(110)에 홈메우기 볼트 고정판(120)과 연결되어 있는 홈메우기 볼트(130 또는 130a)를 고정너트(140)로 가조립하여 놓는 단계와;
띠장 본체(110)를 인양하여 엄지 말뚝(12)에 설치된 띠장브라켓(14)에 올려 지지시켜 놓는 단계와;
홈메우기 볼트(130 또는 130a)의 위치를 조정하여 홈메우기 볼트 고정판(120)을 엄지 말뚝(12)에 밀착시켜 용접 접합시켜 놓는 단계와;
띠장(100)과 엄지 말뚝(12)간의 홈 간격에 따른 홈메우기 볼트(130 또는 130a)의 위치를 조정하여 띠장 본체(110)의 설치 자세를 조정한 후 고정너트(140)를 조임하여 홈메우기 볼트(130 또는 130a)를 띠장 본체(110)에 확고하게 고정시켜 놓는 단계;를 포함하고,
홈메우기 볼트(130 또는 130a)의 위치 조정은 띠장 본체(100)측 볼트형 스티프너(150)와 홈메우기 볼트(130 또는 130a)를 나사 연결하는 연결커플러(152)의 회전 조작을 통하여 이루어지는 것을 특징으로 하는 홈메우기 볼트를 갖는 띠장의 시공 방법.
Pre-assembling the groove filling bolt 130 or 130a connected to the groove filling bolt fixing plate 120 to the strip body 110 using a fixing nut 140;
Lifting and supporting the belt-shaped body 110 on the belt-shaped bracket 14 installed on the thumb pile 12;
Adjusting the position of the grooved bolts 130 or 130a to bring the grooved bolt fixing plate 120 into close contact with the thumb pile 12 to weld the grooves;
After adjusting the installation posture of the belt-length main body 110 by adjusting the position of the groove-filling bolt 130 or 130a according to the groove gap between the belt-length 100 and the thumb pile 12, tightening the fixing nut 140 to tighten the groove And firmly fixing the bolt 130 or 130a to the belt-shaped body 110.
Position adjustment of the groove filling bolt (130 or 130a) is made through the rotation operation of the coupling coupler 152 for screwing the bolt-shaped stiffener 150 and the groove filling bolt (130 or 130a) side of the belt body 100 The construction method of the strip | belt length which has a groove filling bolt made into.
KR1020190048701A 2019-04-25 2019-04-25 Furring strip having groove filling bolt and construction method of the same Active KR102077421B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020190048701A KR102077421B1 (en) 2019-04-25 2019-04-25 Furring strip having groove filling bolt and construction method of the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020190048701A KR102077421B1 (en) 2019-04-25 2019-04-25 Furring strip having groove filling bolt and construction method of the same

Publications (1)

Publication Number Publication Date
KR102077421B1 true KR102077421B1 (en) 2020-02-13

Family

ID=69515267

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020190048701A Active KR102077421B1 (en) 2019-04-25 2019-04-25 Furring strip having groove filling bolt and construction method of the same

Country Status (1)

Country Link
KR (1) KR102077421B1 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113279393A (en) * 2021-07-15 2021-08-20 南通汉腾建筑科技有限公司 Prestressed profile steel support pile and installation method
KR102310228B1 (en) * 2021-01-11 2021-10-08 (주)제이피이엔씨 Furring strip support module for non welding groove filling and reuse
KR102322742B1 (en) * 2021-01-19 2021-11-08 (주)케이엘 Apparatus of supporting for wale with adjustable type for error
KR20220168135A (en) 2021-06-15 2022-12-22 주식회사 이에스지오 Method for filling gap between earth rtaining wall and wale
KR102746796B1 (en) * 2023-09-20 2024-12-24 이영범 Groove Filling Assembly for Side Pile Combined Wale

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100851062B1 (en) * 2007-05-29 2008-08-12 화엄토건(주) Jack stiffeners with magnetic material
KR20080111323A (en) * 2007-06-18 2008-12-23 주식회사 스마텍엔지니어링 Belt Gap
KR100898830B1 (en) * 2007-06-12 2009-05-22 정택동 Adjustable angle anchor bracket
KR20100117267A (en) * 2009-04-24 2010-11-03 안창운 Methode and structure for waling installation of soil guard
KR101364227B1 (en) 2013-10-11 2014-02-18 주식회사 에이씨이테크 Bellows jack for filling gap between earth retaining wall and wale
KR101618628B1 (en) * 2014-02-27 2016-05-09 박민서 A support of earth retaining wall and method for earth retaining wall using th same
KR101677811B1 (en) 2014-12-18 2016-11-18 주식회사 진림건설 Methode and structure for waling installation of soil guard

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100851062B1 (en) * 2007-05-29 2008-08-12 화엄토건(주) Jack stiffeners with magnetic material
KR100898830B1 (en) * 2007-06-12 2009-05-22 정택동 Adjustable angle anchor bracket
KR20080111323A (en) * 2007-06-18 2008-12-23 주식회사 스마텍엔지니어링 Belt Gap
KR20100117267A (en) * 2009-04-24 2010-11-03 안창운 Methode and structure for waling installation of soil guard
KR101364227B1 (en) 2013-10-11 2014-02-18 주식회사 에이씨이테크 Bellows jack for filling gap between earth retaining wall and wale
KR101618628B1 (en) * 2014-02-27 2016-05-09 박민서 A support of earth retaining wall and method for earth retaining wall using th same
KR101677811B1 (en) 2014-12-18 2016-11-18 주식회사 진림건설 Methode and structure for waling installation of soil guard

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102310228B1 (en) * 2021-01-11 2021-10-08 (주)제이피이엔씨 Furring strip support module for non welding groove filling and reuse
WO2022149692A1 (en) * 2021-01-11 2022-07-14 (주)제이피이엔씨 Wale support module for filling and reuse of non-welding groove
CN115516170A (en) * 2021-01-11 2022-12-23 株式会社Jp建设 Reusable beam support module for weldless caulking
CN115516170B (en) * 2021-01-11 2024-01-05 株式会社Jp建设 Beam support module for solderless caulking and reusable
JP7557081B2 (en) 2021-01-11 2024-09-26 ジェイピー イーアンドシー カンパニー リミテッド Wale-raised support modules for weldless backfilling and reuse.
KR102322742B1 (en) * 2021-01-19 2021-11-08 (주)케이엘 Apparatus of supporting for wale with adjustable type for error
KR20220168135A (en) 2021-06-15 2022-12-22 주식회사 이에스지오 Method for filling gap between earth rtaining wall and wale
CN113279393A (en) * 2021-07-15 2021-08-20 南通汉腾建筑科技有限公司 Prestressed profile steel support pile and installation method
CN113279393B (en) * 2021-07-15 2021-09-21 南通汉腾建筑科技有限公司 Prestressed profile steel support pile and installation method
KR102746796B1 (en) * 2023-09-20 2024-12-24 이영범 Groove Filling Assembly for Side Pile Combined Wale

Similar Documents

Publication Publication Date Title
KR102077421B1 (en) Furring strip having groove filling bolt and construction method of the same
US8800232B1 (en) Flange shear connection for precast concrete structures
KR100997128B1 (en) Screw Jack for Supporting Support
US5466095A (en) Underground support system and method of support
US20230399809A1 (en) Wale support module for filling and reuse of non-welding groove
JP4693299B2 (en) Column base connection structure
EP2278076A1 (en) Multi-purpose earth anchor bracket
KR101908356B1 (en) Aseismatic Reinforcement Double Steel Frame and Aseismatic Reinforcement Method using thereof
KR101845717B1 (en) Aseismatic Reinforcement Steel Frame with Hinge Type Friction Slip Brace and Aseismatic Reinforcement Method using thereof
JP6320500B1 (en) Bridge main girder, bridge with the main girder, and method of constructing the bridge
KR102704736B1 (en) Furring strip mounting method for enhanced safety and structure of the same
KR100916546B1 (en) Underground temporary facilities and their construction methods
KR20120131996A (en) Structure of temporary installation for land-side protection wall, and construction method thereof
JP6975680B2 (en) Steel method Frame method using frame members
JP2002146800A (en) Connection structure between superstructure and foundation pile and supporting hardware
KR20130038461A (en) Variable supporting device for sheathing work pile
KR200381589Y1 (en) A pile head reinforcement structure of precastconcrete pile
JP2021092029A (en) Existing tunnel reinforcement structure
KR102047897B1 (en) Constructing method of temporary earth retaining wall using strut connecting structure with reinforcement structure
KR102620398B1 (en) Coupling Jack for adjusting lenghth and support method of retaining wall using of the same
KR102275450B1 (en) Cover band of connection device for steel pipe strut and connection device for steel pipe strut having the same
KR102742756B1 (en) Construction method for connecting the support beam for temporary retaining
KR101656015B1 (en) Natural Panel type retaining wall
KR102248682B1 (en) Reusable supporting bracket for furring strip
JPH10331436A (en) Seismic retrofitting of columns and beams in existing structures

Legal Events

Date Code Title Description
PA0109 Patent application

Patent event code: PA01091R01D

Comment text: Patent Application

Patent event date: 20190425

PA0201 Request for examination
PA0302 Request for accelerated examination

Patent event date: 20190425

Patent event code: PA03022R01D

Comment text: Request for Accelerated Examination

PE0902 Notice of grounds for rejection

Comment text: Notification of reason for refusal

Patent event date: 20190828

Patent event code: PE09021S01D

E902 Notification of reason for refusal
PE0902 Notice of grounds for rejection

Comment text: Notification of reason for refusal

Patent event date: 20191218

Patent event code: PE09021S01D

E701 Decision to grant or registration of patent right
PE0701 Decision of registration

Patent event code: PE07011S01D

Comment text: Decision to Grant Registration

Patent event date: 20200204

GRNT Written decision to grant
PR0701 Registration of establishment

Comment text: Registration of Establishment

Patent event date: 20200207

Patent event code: PR07011E01D

PR1002 Payment of registration fee

Payment date: 20200207

End annual number: 3

Start annual number: 1

PG1601 Publication of registration
PR1001 Payment of annual fee

Payment date: 20230131

Start annual number: 4

End annual number: 4

PR1001 Payment of annual fee

Payment date: 20240131

Start annual number: 5

End annual number: 5

PR1001 Payment of annual fee

Payment date: 20250123

Start annual number: 6

End annual number: 6