KR101683216B1 - Construction method of pier - Google Patents

Construction method of pier Download PDF

Info

Publication number
KR101683216B1
KR101683216B1 KR1020150109318A KR20150109318A KR101683216B1 KR 101683216 B1 KR101683216 B1 KR 101683216B1 KR 1020150109318 A KR1020150109318 A KR 1020150109318A KR 20150109318 A KR20150109318 A KR 20150109318A KR 101683216 B1 KR101683216 B1 KR 101683216B1
Authority
KR
South Korea
Prior art keywords
bracket
steel pipe
pipe column
deck plate
slab
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
KR1020150109318A
Other languages
Korean (ko)
Inventor
이창남
Original Assignee
(주)센벡스
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)센벡스 filed Critical (주)센벡스
Priority to KR1020150109318A priority Critical patent/KR101683216B1/en
Application granted granted Critical
Publication of KR101683216B1 publication Critical patent/KR101683216B1/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • E—FIXED CONSTRUCTIONS
    • E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02B—HYDRAULIC ENGINEERING
    • E02B3/00—Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04—Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/06—Moles; Piers; Quays; Quay walls; Groynes; Breakwaters ; Wave dissipating walls; Quay equipment
    • E—FIXED CONSTRUCTIONS
    • E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02B—HYDRAULIC ENGINEERING
    • E02B17/00—Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E—FIXED CONSTRUCTIONS
    • E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00—Independent underground or underwater structures; Retaining walls
    • E02D29/06—Constructions, or methods of constructing, in water
    • E—FIXED CONSTRUCTIONS
    • E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02B—HYDRAULIC ENGINEERING
    • E02B17/00—Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0039—Methods for placing the offshore structure
    • E—FIXED CONSTRUCTIONS
    • E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02B—HYDRAULIC ENGINEERING
    • E02B17/00—Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0056—Platforms with supporting legs
    • E—FIXED CONSTRUCTIONS
    • E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00—Production methods
    • E02D2250/0023—Cast, i.e. in situ or in a mold or other formwork

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

본 발명은 브래킷고정구를 이용하여 브래킷을 강관 기둥에 가고정하고 브래킷 상부에 거더와 데크플레이트를 설치하여 작업 공간으로 활용한 후 후속작업을 진행함으로써, 해상 작업 및 바지선 작업을 최소화할 수 있는 잔교 시공 방법에 대한 것이다.
본 발명의 잔교 시공 방법은 (a) 복수의 강관 기둥을 상단이 수면 위로 돌출되도록 수중 지반에 설치하는 단계; (b) 상하부가 개방된 원통형의 몸체부와 상기 몸체부 측면에 결합되는 거치부로 구성되는 브래킷을 각 강관 기둥 상부에 설치하는 단계; (c) 상단은 강관 기둥 상단에 걸침되고 하단은 상기 브래킷 일측에 고정되는 브래킷고정구를 설치하여 브래킷을 가고정하는 단계; (d) 상기 브래킷의 거치부 상부에 거더를 거치하고 거더 사이에 데크플레이트를 설치하는 단계; (e) 상기 브래킷의 몸체부와 강관 기둥 외주면을 용접으로 결합하여 고정하는 단계; (f) 상기 데크플레이트 상부에 콘크리트를 타설하고 양생하여 거푸집용 슬래브를 형성하는 단계; 및 (g) 상기 거푸집용 슬래브 상부에 철근을 배근하고 콘크리트를 타설하여 메인슬래브를 형성하는 단계; 를 포함하여 구성되는 것을 특징으로 한다.
The present invention relates to a bridging construction method capable of minimizing marine work and barge work by using a bracket fixture to fix a bracket to a steel pipe column and installing a girder and a deck plate at an upper part of the bracket, Lt; / RTI >
(A) installing a plurality of steel tube columns in an underwater sole such that an upper end thereof protrudes above the water surface; (b) installing a bracket comprising a cylindrical body portion with upper and lower openings and a mounting portion coupled to the side surface of the body portion on the upper portion of each steel pipe column; (c) installing a bracket fixture on the upper end of the steel tube column and a lower end fixed to one side of the bracket to fix the bracket; (d) installing a deck plate between the girders by mounting a girder on the upper portion of the bracket; (e) welding and fixing the body portion of the bracket to the outer circumferential surface of the steel pipe column; (f) pouring and curing concrete on the deck plate to form a mold slab; And (g) placing a reinforcing bar on the upper part of the slab for molding and pouring concrete to form a main slab; And a control unit.

Description

잔교 시공 방법{Construction method of pier}{Construction method of pier}

본 발명은 브래킷고정구를 이용하여 브래킷을 강관 기둥에 가고정하고 브래킷 상부에 거더와 데크플레이트를 설치하여 작업 공간으로 활용한 후 후속작업을 진행함으로써, 해상 작업 및 바지선 작업을 최소화할 수 있는 잔교 시공 방법에 대한 것이다.The present invention relates to a bridging construction method capable of minimizing marine work and barge work by using a bracket fixture to fix a bracket to a steel pipe column and installing a girder and a deck plate at an upper part of the bracket, Lt; / RTI >

잔교는 해안선이 접한 육지에서 선박의 접안 또는 이안이 용이하도록 직각 또는 일정한 각도로 돌출한 접안시설을 말하는 것으로, 말뚝을 강관 기둥으로 활용하고, 강관 기둥 상부에 콘크리트나 강판 등의 상부구조물이 설치된다.The pier is used as a steel pipe column and the upper structure such as concrete or steel plate is installed on the upper part of the steel pipe column. .

종래 잔교는 수심이 적당한 부분에 강관 기둥을 설치하고, 강관 기둥 주위에 빔을 격자형으로 상하 촘촘하게 적층 설치하여 브레이싱을 형성한 다음, 브레이싱 상부에 동바리와 거푸집을 순차적으로 설치하고 콘크리트 타설하여 강관 기둥 상부에 슬래브를 형성하는 순서로 시공한다. 이후 상부 슬래브 콘크리트 경화시 동바리, 거푸집 등의 가설재와 브레이싱은 제거된다.Conventional piers are constructed by placing steel pipe columns at appropriate water depths and forming a bracing by laminating beams vertically and densely around the steel pipe columns. Then, the steel pipes and piles are placed sequentially on the upper part of the bracing, And the slab is formed on the upper part. Then, when the upper slab concrete is cured, the construction material such as the hull, the formwork and the bracing are removed.

상기와 같은 종래의 잔교 시공 방법은 대부분의 작업이 해상에서 이루어지며 바지선이 필요하다.In the conventional bridging method, most work is performed at sea and a barge is required.

그러나 해상 작업은 기본적으로 지상 작업에 비하여 작업에 어려움이 많다. 그리고 바지선은 파고가 높은 경우 작업이 불가한 경우가 발생할 수 있는 등 날씨의 영향을 많이 받고 비용이 고가인 단점이 있다.However, the maritime work is basically more difficult than the ground work. And the barge line has a disadvantage that the work is impossible when the digging is high and the cost is high because it is affected by the weather.

특히, 조수간만의 차가 큰 서해안의 경우 간조(干潮) 시에는 해수면이 낮아 바지선 운영이 불가능하고, 만조(滿潮) 시에만 작업이 가능하여 강관 기둥을 하루 1~2개 정도 밖에 설치할 수 없으며, 지반 상태에 따라 설치되는 강관 기둥의 최종 높이의 편차가 커서 강관 기둥 상단 절단 작업이 필수적이다.Especially, in case of the west coast where the difference of tides is large, it is impossible to operate the barge due to low sea level at low tide and it is possible to work only at high tide, so that only one or two columns of steel pipe can be installed per day, It is necessary to cut the upper part of the steel column column because the final height of the steel column is different according to the ground condition.

그리고 상기 브레이싱은 상부 구조물 형성을 위한 작업자의 작업 통로로 이용되는데, 해상에서 용접에 의하여 브레이싱을 설치하는 작업이 용이하지 않고, 브레이싱 제거 작업은 설치가 완료된 슬래브 하부에서 진행하여야 하므로 매우 어렵고 고도의 위험성이 수반된다.The bracing is used as a work path of an operator for forming an upper structure. It is not easy to install a bracing by welding at sea, and the bracing work must be performed from the lower part of the slab where the installation is completed. .

그뿐만 아니라 상부 슬래브는 두께가 1m 내외로 매우 두꺼워 가설재가 많이 소요되는데, 이에 따라 가설재의 시공 및 해체 작업에 시간 및 비용이 많이 필요하고, 해상에서 작업이 이루어지는 특성상 공정이 복잡하고 비용이 만만치 않은 문제점이 있다.In addition, the upper slab has a thickness of about 1 m, which requires a lot of construction material. Therefore, it takes a lot of time and cost to construct and dismantle the construction material. Due to the nature of the work in the sea, the process is complicated and costly There is a problem.

이에 따라 PC 바닥판을 이용한 잔교식 구조물 및 잔교식 구조물의 시공방법에 대한 기술이 제안되었다(특허 제10-1213262호).As a result, a technique has been proposed for a construction method of a paved structure and a paved structure using a PC deck (Patent No. 10-1213262).

상기 등록기술은 가설재의 시공 및 해체 작업에 소요되는 시간을 단축할 수 있으나, PC 부재가 중량이고 사이즈에 한계가 있어 바지선 작업이 여전히 곤란한 문제점이 있다.The above registration technique can shorten the time required for construction and dismantling work of the construction material. However, there is a problem that it is difficult to work barges because the PC member is limited in weight and size.

상기와 같은 과제를 해결하기 위하여 본 발명은 해상 작업 및 바지선 작업을 최소화할 수 있는 잔교 시공 방법을 제공하고자 한다.In order to solve the above-mentioned problems, the present invention provides a bridging installation method capable of minimizing marine work and barge work.

본 발명은 가설 공사를 최소화할 수 있어 가설재의 해체 작업에 소요되는 노력을 경감할 수 있는 잔교 시공 방법을 제공하고자 한다.The present invention provides a method of constructing a bridging bridge that can reduce the effort required for the dismantling work of the installation material because the construction work can be minimized.

바람직한 실시예에 따른 본 발명은 (a) 복수의 강관 기둥을 상단이 수면 위로 돌출되도록 수중 지반에 설치하는 단계; (b) 상하부가 개방된 원통형의 몸체부, 상기 몸체부 측면에 결합되는 거치부 및 상기 몸체부의 측면에 결합되는 것으로 상부가 개방된 ㄷ자 형상이고, 하면 중앙에 결합공이 형성된 지지구로 구성되는 브래킷을 각 강관 기둥 상부에 설치하는 단계; (c) 하부에 홈부가 형성되어 강관 기둥의 상단에 걸리는 걸림구 및 상단이 상기 걸림구에 너트로 결합되는 전산볼트로 구성되는 브래킷고정구를 상기 걸림구는 강관 기둥 상단에 홈부가 걸침되는 한편, 상기 전산볼트의 하단은 지지구의 결합공에 삽입하여 지지구 하부에서 너트로 고정되도록 설치하여 브래킷을 가고정하고, 상기 전산볼트의 상단 또는 하단에 결합되는 너트를 조여 브래킷의 레벨을 조절하는 단계; (d) 상기 브래킷의 거치부 상부에 거더를 거치하고 거더 사이에 데크플레이트를 설치하는 단계; (e) 상기 브래킷의 몸체부와 강관 기둥 외주면을 용접으로 결합하여 고정하는 단계; (f) 상기 데크플레이트 상부에 데크플레이트를 작업 발판 삼아 콘크리트를 강관 기둥 상단이 일정 길이 돌출되도록 타설하고 양생하여 거푸집용 슬래브를 형성하는 단계; 및 (g) 상기 거푸집용 슬래브 상부에 철근을 배근하고 콘크리트를 타설하여 메인슬래브를 형성하는 단계; 를 포함하여 구성되는 것을 특징으로 하는 잔교 시공 방법을 제공한다.According to a preferred embodiment of the present invention, there is provided a method of manufacturing a steel pipe, comprising the steps of: (a) installing a plurality of steel tube columns in an underwater sole such that an upper end thereof protrudes above a water surface; (b) a bracket comprising a cylindrical body portion having upper and lower openings, a mounting portion coupled to a side surface of the body portion, and a U-shaped upper portion which is coupled to a side surface of the body portion and is open at an upper portion thereof, Installing each steel pipe on the column top; (c) a bracket fixture formed of a metal bolt formed with a groove portion at a lower portion and coupled to the upper end of the steel pipe column with a nut at the upper end of the steel pipe column, Adjusting the level of the bracket by inserting the lower end of the computerized bolt into the coupling hole of the support, fixing the bracket by the nut at the lower portion of the support, tightening the nut coupled to the upper or lower end of the bolt, (d) installing a deck plate between the girders by mounting a girder on the upper portion of the bracket; (e) welding and fixing the body portion of the bracket to the outer circumferential surface of the steel pipe column; (f) forming a slab for molding by pouring and curing the concrete so that the upper end of the steel pipe column protrudes by a predetermined length, using the deck plate as a work footing on the deck plate; And (g) placing a reinforcing bar on the upper part of the slab for molding and pouring concrete to form a main slab; The method of the present invention includes the steps of:

다른 바람직한 실시예에 따른 본 발명은 상기 (b) 단계에서, 상기 브래킷 설치 전에 강관 기둥 측면에 브래킷 하부를 지지하기 위한 스터드볼트가 용접 결합되는 것을 특징으로 하는 잔교 시공 방법을 제공한다.According to another preferred embodiment of the present invention, in the step (b), a stud bolt for supporting the lower portion of the bracket is welded to the side of the steel pipe column before the bracket is installed.

삭제delete

다른 바람직한 실시예에 따른 본 발명은 상기 몸체부의 측면에는 고정공이 관통 형성되고, 상기 고정공에는 몸체부를 관통하여 강관 기둥 외측에 밀착되는 고정볼트가 결합되는 것을 특징으로 하는 잔교 시공 방법을 제공한다.According to another preferred embodiment of the present invention, a fixing hole is formed in a side surface of the body part, and a fixing bolt which passes through the body part and is in close contact with the outside of the column of the steel pipe is coupled to the fixing hole.

다른 바람직한 실시예에 따른 본 발명은 상기 거더는 하부플랜지, 상기 하부플랜지 중앙 상부에 구비되는 웨브 및 상기 웨브 상부에 구비되는 것으로 상기 하부플랜지보다 폭이 좁은 상부플랜지로 구성되고, 상기 데크플레이트는 하부플랜지 상부에 거치되는 것을 특징으로 하는 잔교 시공 방법을 제공한다.According to another preferred embodiment of the present invention, the girder is composed of a lower flange, a web provided on the upper center of the lower flange, and an upper flange provided on the web and narrower than the lower flange, And is mounted on an upper portion of the flange.

다른 바람직한 실시예에 따른 본 발명은 상기 거더는 하부플랜지, 상기 하부플랜지 중앙 상부에 구비되는 웨브 및 상기 웨브 상단 양측면에 각각 결합되는 상부철근으로 구성되고, 상기 데크플레이트는 하부플랜지 상부에 거치되는 것을 특징으로 하는 잔교 시공 방법을 제공한다.According to another preferred embodiment of the present invention, the girder is composed of a lower flange, a web provided on the upper center of the lower flange, and an upper reinforcing bar coupled to both side surfaces of the web top, Thereby providing a pier construction method.

본 발명에 따르면 브래킷고정구를 이용하여 브래킷을 강관 기둥에 가고정하고 브래킷 상부에 거더와 데크플레이트를 설치하여 작업 발판으로 활용한 후 후속작업을 진행할 수 있다. 따라서 별도의 바지선이 필요 없이 지상 작업과 동일하게 후속 작업을 진행할 수 있다.According to the present invention, the bracket is fixed to the column of the steel pipe by using the bracket fixture, and the girder and the deck plate are installed at the upper part of the bracket, so that the work can be carried out after using it as a work footing. Therefore, it is possible to carry out the following work in the same way as the ground work without needing a separate barge.

아울러 데크플레이트와 거푸집용 슬래브를 작업대로 활용하면서 영구구조물로 사용할 수 있으므로, 가설재의 해체 작업이 불필요하다. 따라서 가설 공사를 최소화할 수 있고 이에 소요되는 공기 단축 및 공사비 절감이 가능하다.In addition, since the deck plate and the form slab can be used as a permanent structure while being used as a work platform, the dismantling work of the construction material is unnecessary. Therefore, it is possible to minimize the construction work and to shorten the construction time and the construction cost.

도 1은 본 발명 잔교 시공 방법의 (a) 단계를 도시하는 사시도.
도 2는 본 발명 잔교 시공 방법의 (b) 단계를 도시하는 사시도.
도 3은 강관 기둥과 브래킷의 결합 관계를 도시하는 사시도.
도 4는 본 발명 잔교 시공 방법의 (c) 단계를 도시하는 도면.
도 5는 본 발명 잔교 시공 방법의 (d) 단계를 도시하는 사시도.
도 6은 본 발명 잔교 시공 방법의 (e) 단계를 도시하는 사시도.
도 7은 본 발명 잔교 시공 방법의 (f) 단계를 도시하는 도면.
도 8은 본 발명 잔교 시공 방법의 (g) 단계를 도시하는 사시도.
도 9는 스터드볼트가 결합된 강관 기둥을 도시하는 사시도.
도 10은 브래킷고정구의 실시예를 도시하는 사시도.
도 11은 고정볼트에 의해 강관 기둥에 고정되는 브래킷을 도시하는 사시도.
도 12는 다양한 실시예에 따른 거더와 데크플레이트의 결합 관계를 도시하는 도면.
BRIEF DESCRIPTION OF THE DRAWINGS Fig. 1 is a perspective view showing a step (a) of a bridging method of the present invention. Fig.
Fig. 2 is a perspective view showing the step (b) of the bridging method of the present invention. Fig.
3 is a perspective view showing a connection relationship between a steel pipe column and a bracket;
4 is a view showing the step (c) of the method of constructing a bridge according to the present invention.
5 is a perspective view showing the step (d) of the method of constructing a bridging of the present invention.
6 is a perspective view showing step (e) of the method of constructing a bridging of the present invention.
7 is a view showing step (f) of the method of constructing a bridging of the present invention.
8 is a perspective view showing the step (g) of the method of constructing the bridges of the present invention.
9 is a perspective view showing a steel pipe column to which a stud bolt is coupled;
10 is a perspective view illustrating an embodiment of a bracket fastener;
11 is a perspective view showing a bracket fixed to a steel pipe column by a fixing bolt;
12 is a view showing a coupling relationship between a girder and a deck plate according to various embodiments;

이하, 첨부한 도면 및 바람직한 실시예에 따라 본 발명을 상세히 설명한다.Hereinafter, the present invention will be described in detail with reference to the accompanying drawings and preferred embodiments.

도 1 내지 도 8은 본 발명 잔교 시공 방법의 각 단계를 도시하는 도면이다. 1 to 8 are diagrams showing respective steps of a bridging method of the present invention.

본 발명의 잔교 시공 방법은 (a) 복수의 강관 기둥(1)을 상단이 수면 위로 돌출되도록 수중 지반에 설치하는 단계; (b) 상하부가 개방된 원통형의 몸체부(21), 상기 몸체부(21) 측면에 결합되는 거치부(22) 및 상기 몸체부(21)의 측면에 결합되는 것으로 상부가 개방된 ㄷ자 형상이고, 하면 중앙에 결합공(231)이 형성된 지지구(23)로 구성되는 브래킷(2)을 각 강관 기둥(1) 상부에 설치하는 단계; (c) 하부에 홈부가 형성되어 강관 기둥(1)의 상단에 걸리는 걸림구(31) 및 상단이 상기 걸림구(31)에 너트로 결합되는 전산볼트(32)로 구성되는 브래킷고정구(3)를 상기 걸림구(31)는 강관 기둥(1) 상단에 홈부가 걸침되는 한편, 상기 전산볼트(32)의 하단은 지지구(23)의 결합공(231)에 삽입하여 지지구(23) 하부에서 너트(33)로 고정되도록 설치하여 브래킷(2)을 가고정하고, 상기 전산볼트(32)의 상단 또는 하단에 결합되는 너트를 조여 브래킷(2)의 레벨을 조절하는 단계; (d) 상기 브래킷(2)의 거치부(22) 상부에 거더(5)를 거치하고 거더(5) 사이에 데크플레이트(6)를 설치하는 단계; (e) 상기 브래킷(2)의 몸체부(21)와 강관 기둥(1) 외주면을 용접(W)으로 결합하여 고정하는 단계; (f) 상기 데크플레이트(6) 상부에 데크플레이트(6)를 작업 발판 삼아 콘크리트(C1)를 강관 기둥(1) 상단이 일정 길이 돌출되도록 타설하고 양생하여 거푸집용 슬래브(7)를 형성하는 단계; 및 (g) 상기 거푸집용 슬래브(7) 상부에 철근(R)을 배근하고 콘크리트(C2)를 타설하여 메인슬래브(8)를 형성하는 단계; 를 포함하여 구성되는 것을 특징으로 한다.(A) installing a plurality of steel tube columns (1) in an underwater ground so that an upper end thereof protrudes above a water surface; (b) a cylindrical body 21 having upper and lower openings, a mounting portion 22 coupled to a side surface of the body portion 21, and a U- , And a bracket (2) composed of a support (23) having a coupling hole (231) formed at the center of the lower surface thereof on the upper part of each steel column (1); (c) a bracket fixture (3) formed of a bolt (32) formed with a groove portion at the bottom and having a stopper (31) hooked on the upper end of the steel pipe column (1) and an upper end connected to the stopper (31) The lower end of the bolt 32 is inserted into the coupling hole 231 of the support 23 and the lower end of the bolt 32 is inserted into the coupling hole 231 of the support 23, Adjusting the level of the bracket 2 by tightening the nut coupled to the upper or lower end of the bolt 32; (d) installing a deck plate (6) between the girders (5) by mounting a girder (5) above the mounting portion (22) of the bracket (2); (e) welding and fixing the body 21 of the bracket 2 to the outer peripheral surface of the steel pipe column 1 by welding W; (f) forming a concrete slab 7 by pouring and curing the concrete (C1) so that the upper end of the steel pipe column 1 protrudes by a predetermined length with the deck plate 6 as a working platform on the deck plate 6 ; (G) placing a reinforcing bar (R) on the mold slab (7) and casting concrete (C2) to form a main slab (8); And a control unit.

본 발명의 잔교 시공 방법은 해안선이 접한 육지에서 선박의 접안 또는 이안이 용이하도록 돌출된 접안시설인 잔교를 시공하는 방법에 대한 것이다.The method of constructing a bridge of the present invention relates to a method of constructing a bridge, which is a berthing facility protruded so that the berth of the ship or the berth can be easily projected on the land facing the coastline.

본 발명에서는 우선 (a) 복수의 강관 기둥(1)을 상단이 수면 위로 돌출되도록 수중 지반에 설치한다(도 1).In the present invention, (a) a plurality of steel tube columns 1 are installed in an underwater sole such that the upper end thereof protrudes above the water surface (FIG. 1).

그리고 (b) 상하부가 개방된 원통형의 몸체부(21), 상기 몸체부(21) 측면에 결합되는 거치부(22) 및 상기 몸체부(21)의 측면에 결합되는 것으로 상부가 개방된 ㄷ자 형상이고, 하면 중앙에 결합공(231)이 형성된 지지구(23)로 구성되는 브래킷(2)을 각 강관 기둥(1) 상부에 설치한다(도 2).(B) a cylindrical body portion 21 having upper and lower openings, a mounting portion 22 coupled to a side surface of the body portion 21, and a U- And a bracket 2 constituted by a support 23 formed with a coupling hole 231 at the center of the lower surface thereof is installed on the upper part of each steel column 1 (Fig. 2).

도 3에 도시된 바와 같이, 상기 브래킷(2)은 몸체부(21)와 거치부(22)로 구성된다. As shown in Fig. 3, the bracket 2 is composed of a body portion 21 and a mounting portion 22.

상기 몸체부(21)는 강관 기둥(1)을 관통하여 강관 기둥(1) 상부 외측에 위치된다. 따라서 몸체부(21)의 내측 지름은 강관 기둥(1)을 관통할 수 있는 크기로 제작한다.The body 21 penetrates the steel pipe column 1 and is located outside the upper part of the steel pipe column 1. [ Therefore, the inner diameter of the body portion 21 is made to be large enough to penetrate the steel pipe column 1. [

상기 거치부(22)는 후술할 (d) 단계에서 거더(5)가 거치되는 부분으로 충분한 크기로 구성하며, 몸체부(21) 외측에 용접 결합할 수 있다.The mounting portion 22 may have a sufficient size as a portion where the girder 5 is mounted in a step (d) to be described later, and may be welded to the outside of the body portion 21.

상기 브래킷(2)에는 인접 측면이 몸체부(21)와 거치부(22) 일면에 각각 결합되는 지지플레이트를 복수 개 결합할 수 있다.A plurality of support plates may be coupled to the bracket 2 such that adjacent side surfaces of the bracket 2 are coupled to one side of the body portion 21 and the mounting portion 22, respectively.

이후, (c) 하부에 홈부가 형성되어 강관 기둥(1)의 상단에 걸리는 걸림구(31) 및 상단이 상기 걸림구(31)에 너트로 결합되는 전산볼트(32)로 구성되는 브래킷고정구(3)를 상기 걸림구(31)는 강관 기둥(1) 상단에 홈부가 걸침되는 한편, 상기 전산볼트(32)의 하단은 지지구(23)의 결합공(231)에 삽입하여 지지구(23) 하부에서 너트(33)로 고정되도록 설치하여 브래킷(2)을 가고정하고, 상기 전산볼트(32)의 상단 또는 하단에 결합되는 너트를 조여 브래킷(2)의 레벨을 조절한다(도 4).
그리고 (d) 상기 브래킷(2)의 거치부(22) 상부에 거더(5)를 거치하고 거더(5) 사이에 데크플레이트(6)를 설치한다(도 5의 (a) 내지 (b)).
(C) a bracket fixture (31) formed with a groove portion at the bottom and having a latching hole (31) which is caught on the upper end of the steel pipe column (1) and a bolt (32) 3 is inserted into the hole 231 of the support 23 and the lower end of the bolt 32 is inserted into the hole 231 of the support 23, And the level of the bracket 2 is adjusted by tightening a nut coupled to the upper or lower end of the bolt 32 (FIG. 4).
And (d) a deck plate 6 is installed between the girders 5 by placing the girder 5 above the mounting portion 22 of the bracket 2 (FIGS. 5 (a) to 5 (b) .

상기 브래킷고정구(3)를 이용하여 브래킷(2)을 강관 기둥(1)에 가고정한 다음에는 브래킷(2) 상부에 거더(5)와 데크플레이트(6)를 설치하여 작업 발판으로 활용할 수 있다.After the bracket 2 is fixed to the column 1 of the steel pipe by using the bracket fixture 3, a girder 5 and a deck plate 6 may be installed on the bracket 2 to serve as a footrest.

이에 따라 데크플레이트(6) 상부에서 지상 작업과 동일하게 후속 작업을 진행할 수 있으므로, 해상 작업 및 바지선 작업을 최소화할 수 있다.As a result, subsequent operations can be performed on the deck plate 6 in the same manner as the ground work, so that the marine work and the barge work can be minimized.

다음으로, (e) 상기 브래킷(2)의 몸체부(21)와 강관 기둥(1) 외주면을 용접(W)으로 결합하여 고정한다(도 6).Next, (e) the body 21 of the bracket 2 is joined to the outer circumferential surface of the steel pipe column 1 by welding (W) (FIG. 6).

상기 (e) 단계에서는 데크플레이트(6) 상부에서 브래킷(2)의 몸체부(21)를 강관 기둥(1)에 용접(W)하여 본 고정한다.In the step (e), the body 21 of the bracket 2 is welded (W) to the steel tube column 1 at the upper part of the deck plate 6 to fix it.

상기 (e) 단계의 용접 작업은 해상에서 작업이 매우 곤란하다. 따라서 본 발명에서는 용접에 의한 브래킷(2)과 강관 기둥(1)의 본 고정에 앞서, 브래킷고정구(3)로 브래킷(2)을 강관 기둥(1)에 가고정하여 거더(5) 및 데크플레이트(6)를 설치함으로써 작업 발판을 마련하고, 작업 발판 위에서 안정적으로 용접 작업을 수행할 수 있도록 하였다. The welding work in the step (e) is very difficult to work at sea. Therefore, in the present invention, before the bracket 2 and the steel pipe column 1 are fixed by welding, the bracket 2 is fixed to the steel pipe column 1 by the bracket fastener 3 so that the girder 5 and the deck plate 6), so that a stable operation can be performed on the work foot plate.

상기 브래킷고정구(3)는 슬래브 내에 영구 존치할 수도 있으나, 물량 절감 등을 위하여 (e) 단계의 용접에 의한 본 고정 후 제거하여 재사용하는 것이 바람직하다.The bracket fixture 3 may be permanently installed in the slab, but it is preferable to remove the bracket fixture 3 after welding by welding in step (e) for reuse.

상기 몸체부(21)의 용접(W)은 강관 기둥(1) 전 둘레에 걸쳐 실시할 수 있으며, 구조계산에 의해 일부 길이만 실시하는 것도 가능하다.Welding W of the body portion 21 can be performed over the entire circumference of the steel pipe column 1, and it is possible to carry out only a part of the length by calculation of the structure.

또한, 상기 강관 기둥(1)의 외주면과 브래킷(2)의 몸체부(21) 내주면 사이에 에폭시 등을 주입하거나 브래킷(2) 하부에서 실링 처리를 하여, 콘크리트가 해상으로 누출되어 바다를 오염시키거나 슬래브 하부에서 수분이 침투하여 구조물의 내구성을 저하시키지 않도록 구성할 수 있다.Epoxy or the like is injected between the outer circumferential surface of the steel pipe column 1 and the inner circumferential surface of the body portion 21 of the bracket 2 or a sealing treatment is performed at the lower portion of the bracket 2 to cause the concrete to leak into the sea, Or that moisture does not penetrate from the bottom of the slab to deteriorate the durability of the structure.

그리고 (f) 상기 데크플레이트(6) 상부에 데크플레이트(6)를 작업 발판 삼아 콘크리트(C1)를 강관 기둥(1) 상단이 일정 길이 돌출되도록 타설하고 양생하여 거푸집용 슬래브(7)를 형성하며(도 7), (g) 상기 거푸집용 슬래브(7) 상부에 철근(R)을 배근하고 콘크리트(C2)를 타설하여 메인슬래브(8)를 형성한다(도 8).(F) The deck plate 6 is placed on the deck plate 6 and the concrete C1 is poured and cured so that the upper end of the steel column 1 protrudes by a predetermined length, thereby forming a slab 7 for molding (FIG. 7). (G) The reinforcing bars R are placed on the slab 7 and the concrete C2 is laid on the slab 7 to form the main slab 8 (FIG. 8).

잔교는 바닥 두께가 매우 두꺼워 데크플레이트(6)만으로 시공하중을 부담하는 것은 무리이므로, 데크플레이트(6) 상부에 1차로 콘크리트(C1)를 타설하여 거푸집용 슬래브(7)를 형성하고, 거푸집용 슬래브(7) 상부에 콘크리트(C2)를 타설하여 메인슬래브(8)를 형성하도록 한다.It is difficult to load the concrete load only with the deck plate 6 because the floor thickness is very thick. Therefore, the concrete slab 7 is formed by first casting the concrete C1 on the upper part of the deck plate 6, Concrete (C2) is placed on the slab (7) to form the main slab (8).

상기 데크플레이트(6)와 거푸집용 슬래브(7)에 의하여 지상 작업과 같이 작업이 가능하다.The deck plate (6) and the slab (7) for molding can be used to work like a ground work.

아울러 데크플레이트(6) 및 거푸집용 슬래브(7) 타설로 메인슬래브(8) 시공시 별도의 동바리 등 가설부재가 필요 없고, 동바리 제거 및 거푸집 탈형 등의 공정을 생략할 수 있는 등 가설 공사를 최소화할 수 있다.In addition, since the deck plate 6 and the form slab 7 are installed, the construction of the main slab 8 is not required, and it is possible to omit the steps such as removing the dirt and removing the formwork, can do.

또한, 대부분의 부재를 영구구조물로 사용하므로 가설재의 해체 작업 또한 불필요하다.In addition, since most of the members are used as permanent structures, disassembly work of the installation material is also unnecessary.

상기 (f) 단계 후 거푸집용 슬래브(7)가 경화되면 상부에서 브래킷(2)의 몸체부(21) 상부로 돌출된 강관 기둥(1) 부분을 절단하여 지반 상태에 따라 관입 깊이가 달라 상단의 높이가 각각 다른 강관 기둥(1)의 두부를 정리하는 단계를 실시할 수 있다.When the mold slab 7 is cured after the step (f), the part of the steel pipe column 1 protruded from the upper part to the upper part of the body part 21 of the bracket 2 is cut, A step of arranging the head portion of the steel pipe column 1 having different heights can be carried out.

상기 메인슬래브(8)는 상부 하중을 보 없이 직접 강관 기둥(1)에 전달하는 플랫 플레이트와 같은 구조이므로, 콘크리트(C2) 타설 전에 강관 기둥(1) 상단에 헤드(미도시)를 설치하여 상단을 막는 것이 바람직하다.Since the main slab 8 has the same structure as the flat plate that directly transmits the upper load to the steel pipe column 1 without receiving the upper load, a head (not shown) is installed at the upper end of the steel pipe column 1 before the concrete C2 is inserted, .

본 발명에서 상기 거푸집용 슬래브(7)는 거푸집의 역할을 하는 것이고, 거푸집용 슬래브(7) 상부의 메인슬래브(8)가 실제 상부 하중을 지지하여 강관 기둥(1)에 전달하게 된다.In the present invention, the mold slab 7 serves as a mold, and the main slab 8 on the mold slab 7 supports the actual upper load and transmits it to the column 1 of the steel pipe.

도면에는 미도시되었으나, 상기 브래킷(2)의 몸체부(21) 상단에는 메인슬래브(8)의 콘크리트 내에 매립되는 다월바를 결합시킬 수도 있다.Although not shown in the drawings, a dowel bar embedded in the concrete of the main slab 8 may be coupled to the upper end of the body portion 21 of the bracket 2.

상기 (b) 내지 (g) 단계는 해상의 바지선이 아니라 육상에서 육상 크레인에 의해 작업이 가능하다.The above steps (b) to (g) can be carried out by a land crane on land, rather than on an offshore barge.

즉, 강관 기둥(1)은 하중이 커서 크레인으로부터의 작업 반경을 크게 할 수 없으므로 해상의 바지선 상부에서 크레인으로 설치하고, 이후 강관 기둥(1)에 비해 상대적으로 설치 하중에 부담이 없는 브래킷(2), 거더(5) 및 데크플레이트(6)는 작업 범위가 넓은 육상 크레인을 이용하여 육상에서 작업할 수 있다That is, since the steel pipe column 1 has a large load and can not increase the working radius from the crane, it is installed as a crane at the upper part of the barge in the sea, and thereafter, the bracket 2 ), The girder (5) and the deck plate (6) can work onshore using a land crane with a wide working range

육상 크레인의 작업 범위 내에서 브래킷(2) 및 거더(5)와 데크플레이트(6)를 설치하고, 거푸집용 슬래브(7)와 메인슬래브(8)를 타설하여 잔교 일부를 먼저 설치한 후 기설치된 메인슬래브(8) 상에서 (b) 내지 (g) 단계를 순차적으로 반복하여 잔교를 시공한다.The brackets 2 and the girders 5 and the deck plate 6 are installed within the working range of the land cranes and a portion of the piers is installed first by placing the slabs 7 and the main slabs 8, Steps (b) to (g) are sequentially repeated on the main slab 8 to construct a pier.

이에 따라 강관 기둥(1) 설치 외의 다른 작업에서는 해상 작업을 생략하여 바지선 가동 여부와 상관없이 시공이 가능하므로 공기를 크게 단축할 수 있다.As a result, in the work other than the installation of the steel pipe column (1), the marine work can be omitted and the construction can be carried out irrespective of whether the barge is operated or not.

도 9는 스터드볼트가 결합된 강관 기둥을 도시하는 사시도이다.9 is a perspective view showing a steel pipe column to which a stud bolt is coupled.

상기 (b) 단계에서, 상기 브래킷(2) 설치 전에 강관 기둥(1) 측면에 브래킷(2) 하부를 지지하기 위한 스터드볼트(11)가 용접 결합될 수 있다. In step (b), a stud bolt 11 for supporting the lower portion of the bracket 2 may be welded to the side of the steel pipe column 1 before the bracket 2 is installed.

즉, 도 9에 도시된 바와 같이 강관 기둥(1) 측면에 스터드볼트(11)가 용접 결합되는 경우, 브래킷고정구(3)로 브래킷(2)을 가고정하는 (c) 단계 이전에 브래킷(2)의 레벨을 고정할 수 있다.That is, when the stud bolt 11 is welded to the side surface of the steel pipe column 1 as shown in Fig. 9, before the step (c) of brazing the bracket 2 with the bracket fastener 3, Can be fixed.

상기 스터드볼트(11)는 브래킷(2)의 설치 위치에 맞춰 각 강관 기둥(1) 측면에 레벨을 측정하여 마킹한 후 강관 기둥(1) 측면에 용접할 수 있다. The stud bolts 11 can be welded to the side surface of the steel tube column 1 after measuring the level on the side surface of each steel tube column 1 in accordance with the mounting position of the bracket 2,

상기 스터드볼트(11)는 강관 기둥(1) 측면에 복수 개 결합할 수 있으며, 스터드볼트(11) 설치 후 브래킷(2)을 스터드볼트(11) 상부에 거치한다.A plurality of the stud bolts 11 can be coupled to the side of the steel pipe column 1 and the bracket 2 is mounted on the stud bolt 11 after the stud bolts 11 are installed.

도 10은 브래킷고정구의 실시예를 도시하는 사시도이다.10 is a perspective view showing an embodiment of a bracket fixture.

도 10에 도시된 바와 같이, 상기 브래킷고정구(3)는 하부에 홈부가 형성되어 강관 기둥(1)의 상단에 걸리는 걸림구(31) 및 상단이 상기 걸림구(31) 너트로 결합되는 전산볼트(32)로 구성되고, 상기 브래킷(2)의 몸체부(21) 측면에는 상부가 개방된 ㄷ자 형상이고, 하면 중앙에 결합공(231)이 형성된 지지구(23)가 결합될 수 있다.10, the bracket fixture 3 is formed with a groove at a lower portion thereof and includes a latching hole 31 for fastening the upper end of the steel pipe column 1 and a bolt 31 for fastening the upper end to the bolt 31. [ And a support 23 formed with a coupling hole 231 at the center of the bottom can be coupled to the side surface of the body 21 of the bracket 2.

이 경우 상기 (c) 단계에서는 브래킷고정구(3)의 전산볼트(32)는 하단을 지지구(23)의 결합공(231)에 삽입하여 지지구(23) 하부에서 너트(33)로 고정하는 한편, 걸림구(31)를 강관 기둥(1)의 상단에 홈부가 걸치도록 브래킷고정구(3)를 설치한다.In this case, in the step (c), the lower end of the bolt 32 of the bracket fastener 3 is inserted into the coupling hole 231 of the support 23 and fixed by the nut 33 at the lower part of the support 23 On the other hand, the bracket fixing hole 3 is provided so that the groove portion is provided on the upper end of the steel pipe column 1.

상기 걸림구(31)는 ㄱ형상으로 형성되어 강관 기둥(1) 상단에 걸리나, 바람직하게는 도 10에 도시된 바와 같이 강관 기둥(1) 상단에 삽입되는 홈부가 형성되도록 구성하여 지지구(23)가 강관 기둥(1)으로부터 탈락되거나 수평 이동하지 않도록 구성할 수 있다.The stopper 31 is formed in a shape so as to be hooked on the upper end of the steel pipe column 1 and preferably a groove portion to be inserted into the upper end of the steel pipe column 1 as shown in FIG. Can be removed from the steel pipe column 1 or can not be horizontally moved.

상기 전산볼트(32)는 걸림구(31) 하부에 결합되는데, 걸림구(31) 일측에 관통공을 형성하고 관통공을 관통하여 걸림구(31) 상부로 돌출된 전산볼트(32) 상단 또는 지지구(23)의 결합공(231) 하부로 돌출된 전산볼트(32) 하단에서 너트를 조여 전산볼트(32)를 걸림구(31)에 결합할 수 있다.The bolt 32 is coupled to a lower portion of the latch 31. The bolt 32 has a through hole formed at one side of the latch 31 and penetrates through the through hole to form the upper end of the bolt 32 The bolts 32 can be fastened to the fastening holes 31 by tightening the nuts at the lower ends of the bolts 32 protruding below the fastening holes 231 of the support 23.

상기 지지구(23)는 다양한 형상이 가능하나, 도 10에서와 같이 ㄷ형상으로 구성할 수 있다. The support 23 may have a variety of shapes, but may have a C-shape as shown in FIG.

이 경우 ㄷ형상 지지구(23)의 웨브에 결합공(231)을 형성할 수 있다.In this case, a coupling hole 231 can be formed in the web of the c-shaped support 23.

각 강관 기둥(1)은 상단의 레벨이 서로 상이하므로 브래킷(2) 설치 시 브래킷(2)의 높이가 일정하지 않을 수 있다. 따라서 전산볼트(32)의 상단 또는 하단에 결합되는 너트를 조여 브래킷(2)의 레벨을 조절함으로써 각 브래킷(2)의 높이를 동일하게 맞출 수 있다.The height of the bracket 2 may not be constant at the time of installation of the bracket 2 because the level of the upper end of each steel tube column 1 is different from each other. Therefore, by adjusting the level of the bracket 2 by tightening the nut coupled to the upper or lower end of the bolt 32, the height of each bracket 2 can be matched to the same height.

도 11은 고정볼트에 의해 강관 기둥에 고정되는 브래킷을 도시하는 사시도이다.11 is a perspective view showing a bracket fixed to a steel pipe column by a fixing bolt.

도 11에서와 같이, 상기 몸체부(21)의 측면에는 고정공(24)이 관통 형성되고, 상기 고정공(24)에는 몸체부(21)를 관통하여 강관 기둥(1) 외측에 밀착되는 고정볼트(25)가 결합되도록 구성할 수 있다.11, a fixing hole 24 is formed through the side surface of the body portion 21, and the fixing hole 24 is fixed to the outside of the steel pipe column 1 through the body portion 21, So that the bolt 25 can be coupled.

상기 고정볼트(25)를 조여 강관 기둥(1) 측면에 브래킷(2)을 가고정할 수 있다. The bracket 2 can be fixed to the side surface of the steel tube column 1 by tightening the fixing bolt 25.

도 11에서 확인할 수 있는 바와 같이, 상기 고정공(24)의 내주면에 나사산을 형성하여 고정볼트(25)를 고정공(24)에 직접 체결할 수도 있고, 도면에는 도시되지 않았으나 고정공(24) 외주면에 너트를 용접하여 너트에 고정볼트(25)를 체결할 수도 있다.11, the fixing bolt 25 may be directly fastened to the fixing hole 24 by forming a screw thread on the inner circumferential surface of the fixing hole 24. Although not shown in the figure, The fixing bolt 25 may be fastened to the nut by welding a nut to the outer circumferential surface.

상기 고정볼트(25)는 앞서 도 9에서 설명한 스터드볼트(11)와 마찬가지로 브래킷(2)의 레벨을 고정한다.The fixing bolt 25 fixes the level of the bracket 2 in the same manner as the stud bolt 11 described previously with reference to FIG.

상기 고정볼트(25)는 스터드볼트(11)와 같이 사용할 수도 있고 스터드볼트(11) 없이 단독으로 사용하는 것도 가능하다.The fixing bolt 25 may be used as the stud bolt 11 or may be used alone without the stud bolt 11.

도 12는 다양한 실시예에 따른 거더와 데크플레이트의 결합 관계를 도시하는 도면이다.Fig. 12 is a view showing a coupling relationship between a girder and a deck plate according to various embodiments. Fig.

도 12의 (a)에 도시된 바와 같이, 상기 거더(5)는 하부플랜지(51), 상기 하부플랜지(51) 중앙 상부에 구비되는 웨브(52) 및 상기 웨브(52) 상부에 구비되는 것으로 상기 하부플랜지(51)보다 폭이 좁은 상부플랜지(53)로 구성되고, 상기 데크플레이트(6)는 하부플랜지(51) 상부에 거치되도록 구성할 수 있다. 12 (a), the girder 5 is provided on a lower flange 51, a web 52 provided on the upper center of the lower flange 51, and on the web 52 And an upper flange 53 having a smaller width than the lower flange 51. The deck plate 6 may be mounted on the lower flange 51. [

통상 데크플레이트(6)는 거더(5)의 상부플랜지(53) 상부에 거치함으로써 슬래브와 거더(5)가 T형 보를 이루도록 하여 단면 성능을 향상시키는데 이용한다.Typically, the deck plate 6 is mounted on the upper flange 53 of the girder 5 so that the slab and the girder 5 form a T-shaped beam to improve the cross-sectional performance.

그러나 본 발명에서 상기 데크플레이트(6)는 본 바닥구조물이 아니라 본 바닥구조물 형성을 위한 거푸집용 슬래브(7)를 형성하기 위한 것으로, 하중이 크지 않고 거더(5)에 전달되는 하중 또한 크지 않으므로, 데크플레이트(6)를 거더(5)의 하부플랜지(51)에 거치할 수 있다.However, in the present invention, the deck plate 6 is not a main floor structure but a slab 7 for forming a floor structure. The load is not large and a load transmitted to the girder 5 is not large, It is possible to mount the deck plate 6 on the lower flange 51 of the girder 5.

아울러 상부플랜지(53)의 폭을 하부플랜지(51)의 폭보다 좁게 구성하므로, 일반적인 H형강 빔과 달리 상부플랜지(53)와의 간섭 없이 데크플레이트(6)를 설치할 수 있다.The deck plate 6 can be installed without interfering with the upper flange 53 unlike a general H-shaped beam because the width of the upper flange 53 is narrower than the width of the lower flange 51.

상기 거더(5)는 상부플랜지(53)와 하부플랜지(51) 폭이 다른 규격 외 제품이므로, 빌트업 빔으로 형성 가능하다.Since the width of the upper flange 53 and the width of the lower flange 51 are different from each other, the girder 5 can be formed as a built-up beam.

도 12의 (b)에 도시된 바와 같이, 상기 거더(5)는 하부플랜지(51), 상기 하부플랜지(51) 중앙 상부에 구비되는 웨브(52) 및 상기 웨브(52) 상단 양측면에 각각 결합되는 상부철근(54)으로 구성되고, 상기 데크플레이트(6)는 하부플랜지(51) 상부에 거치되도록 구성할 수 있다.12 (b), the girder 5 includes a lower flange 51, a web 52 provided at the upper center of the lower flange 51, And the deck plate 6 may be mounted on the lower flange 51. The upper reinforcing bar 54 may be formed of a metal plate.

상기 상부철근(54)은 T형강의 웨브(52) 상단 양측에 용접 결합되어 상부플랜지(53) 역할을 한다.The upper reinforcing bars 54 are welded to both sides of the upper end of the web 52 of the T-shaped steel to serve as upper flanges 53.

상기 거더(5)는 T형강 외에 빌트업 T빔에 상부철근(54)을 용접하여 사용할 수도 있다.The girder 5 may be used by welding an upper reinforcing bar 54 to a built-up T beam in addition to a T-shaped steel.

도 12의 (b)에 도시된 거더(5)의 실시예도 도 12의 (a)에서와 마찬가지로 상부플랜지(53)와의 간섭 없이 인접 거더(5) 사이에 데크플레이트(6)를 용이하게 설치할 수 있다.The embodiment of the girder 5 shown in Fig. 12 (b) can also easily mount the deck plate 6 between the adjacent girders 5 without interference with the upper flange 53 as in Fig. 12 (a) have.

1: 강관 기둥 11: 스터드볼트
2: 브래킷 21: 몸체부
22: 거치부 23: 지지구
231: 결합공 24: 고정공
25: 고정볼트 3: 브래킷고정구
31: 걸림구 32: 전산볼트
33: 너트 5: 거더
51: 하부플랜지 52: 웨브
53: 상부플랜지 54: 상부철근
6: 데크플레이트 7: 거푸집용 슬래브
8: 메인슬래브 C1, C2: 콘크리트
R: 철근 W: 용접
1: Steel pipe column 11: Stud bolt
2: bracket 21:
22: mounting part 23: supporting area
231: engaging hole 24: fixed hole
25: Fixing bolt 3: Bracket fixture
31: stopper 32: bolt
33: Nut 5: Girder
51: lower flange 52: web
53: upper flange 54:
6: Deck plate 7: Slab for molding
8: Main slab C1, C2: Concrete
R: Reinforcement W: Welding

Claims (6)

(a) 복수의 강관 기둥(1)을 상단이 수면 위로 돌출되도록 수중 지반에 설치하는 단계;
(b) 상하부가 개방된 원통형의 몸체부(21), 상기 몸체부(21) 측면에 결합되는 거치부(22) 및 상기 몸체부(21)의 측면에 결합되는 것으로 상부가 개방된 ㄷ자 형상이고, 하면 중앙에 결합공(231)이 형성된 지지구(23)로 구성되는 브래킷(2)을 각 강관 기둥(1) 상부에 설치하는 단계;
(c) 하부에 홈부가 형성되어 강관 기둥(1)의 상단에 걸리는 걸림구(31) 및 상단이 상기 걸림구(31)에 너트로 결합되는 전산볼트(32)로 구성되는 브래킷고정구(3)의 상기 걸림구(31)는 강관 기둥(1) 상단에 홈부가 걸침되는 한편, 상기 전산볼트(32)의 하단은 지지구(23)의 결합공(231)에 삽입하여 지지구(23) 하부에서 너트(33)로 고정되도록 설치하여 브래킷(2)을 가고정하고, 상기 전산볼트(32)의 상단 또는 하단에 결합되는 너트를 조여 브래킷(2)의 레벨을 조절하는 단계;
(d) 상기 브래킷(2)의 거치부(22) 상부에 거더(5)를 거치하고 거더(5) 사이에 데크플레이트(6)를 설치하는 단계;
(e) 상기 브래킷(2)의 몸체부(21)와 강관 기둥(1) 외주면을 용접(W)으로 결합하여 고정하는 단계;
(f) 상기 데크플레이트(6) 상부에 데크플레이트(6)를 작업 발판 삼아 콘크리트(C1)를 강관 기둥(1) 상단이 일정 길이 돌출되도록 타설하고 양생하여 거푸집용 슬래브(7)를 형성하는 단계; 및
(g) 상기 거푸집용 슬래브(7) 상부에 철근(R)을 배근하고 콘크리트(C2)를 타설하여 메인슬래브(8)를 형성하는 단계; 를 포함하여 구성되는 것을 특징으로 하는 잔교 시공 방법.
(a) installing a plurality of steel tube columns (1) in an underwater sole such that an upper end protrudes above the water surface;
(b) a cylindrical body 21 having upper and lower openings, a mounting portion 22 coupled to a side surface of the body portion 21, and a U- , And a bracket (2) composed of a support (23) having a coupling hole (231) formed at the center of the lower surface thereof on the upper part of each steel column (1);
(c) a bracket fixture (3) formed of a bolt (32) formed with a groove portion at the bottom and having a stopper (31) hooked on the upper end of the steel pipe column (1) and an upper end connected to the stopper (31) The lower end of the bolt 32 is inserted into the coupling hole 231 of the support 23 and the lower end of the bolt 32 is inserted into the coupling hole 231 of the support 23, Adjusting the level of the bracket 2 by tightening the nut coupled to the upper or lower end of the bolt 32;
(d) installing a deck plate (6) between the girders (5) by mounting a girder (5) above the mounting portion (22) of the bracket (2);
(e) welding and fixing the body 21 of the bracket 2 to the outer peripheral surface of the steel pipe column 1 by welding W;
(f) forming a concrete slab 7 by pouring and curing the concrete (C1) so that the upper end of the steel pipe column 1 protrudes by a predetermined length with the deck plate 6 as a working platform on the deck plate 6 ; And
(g) disposing a reinforcing bar (R) on the upper slab (7) and casting a concrete (C2) to form a main slab (8); Wherein the step of forming the bridging structure comprises:
제1항에서,
상기 (b) 단계에서, 상기 브래킷(2) 설치 전에 강관 기둥(1) 측면에 브래킷(2) 하부를 지지하기 위한 스터드볼트(11)가 용접 결합되는 것을 특징으로 하는 잔교 시공 방법.
The method of claim 1,
Wherein stud bolts (11) for welding the lower portion of the bracket (2) are welded to the side of the steel pipe column (1) before the installation of the bracket (2) in the step (b).
삭제delete 제1항에서,
상기 몸체부(21)의 측면에는 고정공(24)이 관통 형성되고, 상기 고정공(24)에는 몸체부(21)를 관통하여 강관 기둥(1) 외측에 밀착되는 고정볼트(25)가 결합되는 것을 특징으로 하는 잔교 시공 방법.
The method of claim 1,
A fixing hole 24 is formed in the side surface of the body portion 21 and a fixing bolt 25 penetrating the body portion 21 and coming into close contact with the outside of the steel pipe column 1 is coupled to the fixing hole 24 Wherein said step (c) comprises the steps of:
제1항에서,
상기 거더(5)는 하부플랜지(51), 상기 하부플랜지(51) 중앙 상부에 구비되는 웨브(52) 및 상기 웨브(52) 상부에 구비되는 것으로 상기 하부플랜지(51)보다 폭이 좁은 상부플랜지(53)로 구성되고, 상기 데크플레이트(6)는 하부플랜지(51) 상부에 거치되는 것을 특징으로 하는 잔교 시공 방법.
The method of claim 1,
The girder 5 includes a lower flange 51, a web 52 provided at the upper center of the lower flange 51, and an upper flange 51 having a width smaller than that of the lower flange 51, (53), and the deck plate (6) is mounted above the lower flange (51).
제1항에서,
상기 거더(5)는 하부플랜지(51), 상기 하부플랜지(51) 중앙 상부에 구비되는 웨브(52) 및 상기 웨브(52) 상단 양측면에 각각 결합되는 상부철근(54)으로 구성되고, 상기 데크플레이트(6)는 하부플랜지(51) 상부에 거치되는 것을 특징으로 하는 잔교 시공 방법.
The method of claim 1,
The girder 5 is composed of a lower flange 51, a web 52 provided at the upper center of the lower flange 51 and an upper reinforcing bar 54 respectively coupled to both upper surfaces of the web 52, Characterized in that the plate (6) is mounted above the lower flange (51).
KR1020150109318A 2015-08-03 2015-08-03 Construction method of pier Active KR101683216B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020150109318A KR101683216B1 (en) 2015-08-03 2015-08-03 Construction method of pier

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020150109318A KR101683216B1 (en) 2015-08-03 2015-08-03 Construction method of pier

Publications (1)

Publication Number Publication Date
KR101683216B1 true KR101683216B1 (en) 2016-12-20

Family

ID=57734109

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020150109318A Active KR101683216B1 (en) 2015-08-03 2015-08-03 Construction method of pier

Country Status (1)

Country Link
KR (1) KR101683216B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101901091B1 (en) * 2018-01-18 2018-09-20 배동지 Steel plate inserting PHC Pile and retaining wall construction method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05339919A (en) * 1992-06-12 1993-12-21 Yoshinobu Miyashita Construction of landing pier
JPH10183779A (en) * 1996-12-20 1998-07-14 Sumitomo Forestry Co Ltd Connecting member for pillar connection
KR200381589Y1 (en) * 2005-01-17 2005-04-14 노춘복 A pile head reinforcement structure of precastconcrete pile
KR20070111000A (en) * 2006-05-16 2007-11-21 (주)스틸엔콘크리트 Prefabricated slab bridge with H-girder installed on the connecting support member inserted on the lattice pile pillar and construction method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05339919A (en) * 1992-06-12 1993-12-21 Yoshinobu Miyashita Construction of landing pier
JPH10183779A (en) * 1996-12-20 1998-07-14 Sumitomo Forestry Co Ltd Connecting member for pillar connection
KR200381589Y1 (en) * 2005-01-17 2005-04-14 노춘복 A pile head reinforcement structure of precastconcrete pile
KR20070111000A (en) * 2006-05-16 2007-11-21 (주)스틸엔콘크리트 Prefabricated slab bridge with H-girder installed on the connecting support member inserted on the lattice pile pillar and construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101901091B1 (en) * 2018-01-18 2018-09-20 배동지 Steel plate inserting PHC Pile and retaining wall construction method

Similar Documents

Publication Publication Date Title
KR102166504B1 (en) Landing pier structure and its construction method
JP4793634B2 (en) Temporary deadline construction method
CN108442232B (en) Prefabricated steel bridge structure and its construction method
JP2004183324A (en) Repair structure and repair method of existing pile pier
KR101297127B1 (en) Landing pier structure construction method
CN110485258B (en) Full-assembly type steel structure approach bridge and construction method thereof
KR20080103678A (en) Steel composite girders manufacturing method and bridge construction method using steel composite girders
JP6314547B2 (en) Repair structure and repair method for pile-type structures
JP2001288725A (en) Pile type foundation structure and construction method
JP2011117166A (en) Reinforcing material for preventing corrosion of existing steel-pipe column
JP2013108316A (en) Water cutoff wall body for cutoff and cutoff method using the same
JP2005264514A (en) Foundation slab structure of sea berth structure and its construction method
KR102308731B1 (en) Combined Structure of Column and Coping and Girders
KR200201561Y1 (en) Head reinforcement structure of steel pipe pile
JP6909959B2 (en) How to build pile support structure
JP2571751B2 (en) Pier
JP4437064B2 (en) Construction method and formwork structure of concrete floor slab for composite floor slab bridge
KR101581320B1 (en) Precast coping structure for bridge using precast deck
JP3928226B2 (en) Temporary deadline structure
JPH08120638A (en) Joint structure of pile and beam and construction method of structure using it
JPH08100464A (en) Connection structure and construction method of structure using it
KR100583007B1 (en) Prefab pier wharf
KR100927519B1 (en) Superstructure of Residual Bridge Using Composite Panel of Hollow Section and Construction Method
JP6870905B2 (en) Artificial ground and its construction method
JPH0953223A (en) Support pile mounting structure for jackets for construction of floating structures

Legal Events

Date Code Title Description
PA0109 Patent application

St.27 status event code: A-0-1-A10-A12-nap-PA0109

PA0201 Request for examination

St.27 status event code: A-1-2-D10-D11-exm-PA0201

D13-X000 Search requested

St.27 status event code: A-1-2-D10-D13-srh-X000

D14-X000 Search report completed

St.27 status event code: A-1-2-D10-D14-srh-X000

PE0902 Notice of grounds for rejection

St.27 status event code: A-1-2-D10-D21-exm-PE0902

E13-X000 Pre-grant limitation requested

St.27 status event code: A-2-3-E10-E13-lim-X000

P11-X000 Amendment of application requested

St.27 status event code: A-2-2-P10-P11-nap-X000

P13-X000 Application amended

St.27 status event code: A-2-2-P10-P13-nap-X000

E701 Decision to grant or registration of patent right
PE0701 Decision of registration

St.27 status event code: A-1-2-D10-D22-exm-PE0701

GRNT Written decision to grant
PR0701 Registration of establishment

St.27 status event code: A-2-4-F10-F11-exm-PR0701

PR1002 Payment of registration fee

St.27 status event code: A-2-2-U10-U11-oth-PR1002

Fee payment year number: 1

PG1601 Publication of registration

St.27 status event code: A-4-4-Q10-Q13-nap-PG1601

P22-X000 Classification modified

St.27 status event code: A-4-4-P10-P22-nap-X000

PR1001 Payment of annual fee

St.27 status event code: A-4-4-U10-U11-oth-PR1001

Fee payment year number: 4

L13-X000 Limitation or reissue of ip right requested

St.27 status event code: A-2-3-L10-L13-lim-X000

PR1001 Payment of annual fee

St.27 status event code: A-4-4-U10-U11-oth-PR1001

Fee payment year number: 5

PR1001 Payment of annual fee

St.27 status event code: A-4-4-U10-U11-oth-PR1001

Fee payment year number: 6

PR1001 Payment of annual fee

St.27 status event code: A-4-4-U10-U11-oth-PR1001

Fee payment year number: 7

PR1001 Payment of annual fee

St.27 status event code: A-4-4-U10-U11-oth-PR1001

Fee payment year number: 8

PR1001 Payment of annual fee

St.27 status event code: A-4-4-U10-U11-oth-PR1001

Fee payment year number: 9

L13 Limitation or reissue of ip right requested

Free format text: ST27 STATUS EVENT CODE: A-2-3-L10-L13-LIM-X000 (AS PROVIDED BY THE NATIONAL OFFICE)

L13-X000 Limitation or reissue of ip right requested

St.27 status event code: A-2-3-L10-L13-lim-X000

PN2301 Change of applicant

St.27 status event code: A-5-5-R10-R13-asn-PN2301

St.27 status event code: A-5-5-R10-R11-asn-PN2301

R11 Change to the name of applicant or owner or transfer of ownership requested

Free format text: ST27 STATUS EVENT CODE: A-5-5-R10-R11-ASN-PN2301 (AS PROVIDED BY THE NATIONAL OFFICE)

R13 Change to the name of applicant or owner recorded

Free format text: ST27 STATUS EVENT CODE: A-5-5-R10-R13-ASN-PN2301 (AS PROVIDED BY THE NATIONAL OFFICE)

PR1001 Payment of annual fee

St.27 status event code: A-4-4-U10-U11-oth-PR1001

Fee payment year number: 10

U11 Full renewal or maintenance fee paid

Free format text: ST27 STATUS EVENT CODE: A-4-4-U10-U11-OTH-PR1001 (AS PROVIDED BY THE NATIONAL OFFICE)

Year of fee payment: 10