KR101628988B1 KR1020140030554A KR20140030554A KR101628988B1 KR 101628988 B1 KR101628988 B1 KR 101628988B1 KR 1020140030554 A KR1020140030554 A KR 1020140030554A KR 20140030554 A KR20140030554 A KR 20140030554A KR 101628988 B1 KR101628988 B1 KR 101628988B1
Authority
KR
South Korea
Prior art keywords
sheet
sheet pile
drilling
guide
auger
Prior art date
Application number
KR1020140030554A
Other languages
Korean (ko)
Other versions
KR20150107505A (en
Inventor
조상흠
Original Assignee
조상흠
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 조상흠 filed Critical 조상흠
Priority to KR1020140030554A priority Critical patent/KR101628988B1/en
Publication of KR20150107505A publication Critical patent/KR20150107505A/en
Application granted granted Critical
Publication of KR101628988B1 publication Critical patent/KR101628988B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/03Prefabricated parts, e.g. composite sheet piles
    • E02D5/04Prefabricated parts, e.g. composite sheet piles made of steel

Abstract

본 발명은 더블 천공로드가 구성된 오거를 이용한 시트파일 시공공법 및 그 시공공법에 사용되는 가이드플레이트에 관한 것으로서, 보다 상세하게는 전석층이나 암반층 지반과 같이 시트파일 항타작업이 곤란한 지층에서 시트파일의 양단부에 형성된 이음귀를 통해 인접하는 시트파일이 상호 연결상태를 유지하며 상기 시트파일을 설치하고자 하는 가상의 설치라인을 중심으로 교호적으로 배치할 수 있도록 지면에 교호적으로 천공홀을 형성하는 시트파일 시공공법 및 그 시공공법에 사용되는 가이드플레이트에 관한 것으로서, 시트파일의 양단부에 형성된 이음귀로 인접된 시트파일이 상호 연결되어 교호적으로 배치되는 시트파일의 센터위치에 맞게 상호 일정 각도를 이루며 오거에 연결 구성된 제 1천공로드와 제 2천공로드를 이용하여 상기 시트파일을 설치하려는 위치의 지면에 상기 제 1, 2천공로드의 끝부에 각각 구성되는 굴착해머를 이용하여 천공홀을 천공할 수 있도록 더블 천공로드가 구비된 오거를 이용한 시트파일 시공공법 및 그 시공공법에 포함되며 상기 제 1, 2천공로드를 이용하여 천공 완료 후, 시트파일 항타 시, 상기 시트파일이 항타되는 경로를 이탈하지 않도록 가이드하는 가이드플레이트를 제공함에 주안점을 두어, 시트파일을 설치하고자 하는 가상의 설치라인으로 상기 시트파일의 양단부에 형성된 이음귀로 인접된 시트파일이 상호 연결되어 교호적으로 배치되는 시트파일의 센터위치에 맞게 상호 일정 각도를 이루며 연결 구성된 제 1, 2천공로드를 이용하여 천공홀을 교호적으로 천공하고, 상기 천공홀에 시트파일을 항타할 수 있는 시트파일 시공공법을 제공하고, 상기 제 1, 2천공로드를 이용하여 교호적으로 천공할 수 있도록 상기 제 1, 2천공로드와 같이 교호적으로 가이드 홀이 형성된 가이드박스를 구비하여 시트파일을 설치하고자 하는 가상의 설치라인이 경로를 이탈하지 않으며, 시트파일 항타 시, 시트파일의 이음귀로 인접된 시트파일이 상호 연결되어 교호적으로 배치되는 시트파일과 같이 교호적으로 가이드 홈이 형성된 가이드플레이트를 구비하여 항타되는 시트파일이 경로를 이탈하지 않아 천공홀의 형성 및 시트파일의 항타를 용이하게 할 수 있고, 그로 인해 작업의 효율성과 작업시간을 단축시킬 수 있는 더블 천공로드가 구성된 오거를 이용한 시트파일 시공공법 및 그 시공공법에 사용되는 가이드플레이트에 관한 것이다.The present invention relates to a sheet pile construction method using an auger having a double piercing rod and a guide plate used in the pile construction method. More particularly, the present invention relates to a sheet pile construction method, Wherein the sheet piles are alternately connected to each other through the joint ears formed at both ends thereof and are alternately arranged around a virtual installation line on which the sheet pile is to be installed, The present invention relates to a guide plate for use in a pile construction method and a construction method thereof, wherein sheet files adjacent to each other by jointed ears formed at both ends of the sheet pile are mutually connected to each other, And a second piercing rod connected to the first piercing rod and the second piercing rod, A sheet pile construction method and a pile construction method using an auger provided with a double piercing rod so as to perforate a piercing hole using a piercing hammer formed at the end of the first and second piercing rods, And a guide plate guiding the sheet file so as not to deviate from the path where the sheet file is pushed when the sheet file is punched after completion of the punching using the first and second punch rods. The first and second perforated rods configured to be connected to each other at a predetermined angle in accordance with the center position of the sheet file arranged alternately and connected alternately to the adjacent sheet files formed at the opposite ends of the sheet file by virtual installation lines A sheet pile construction method for punching a perforation hole alternately and hitting a sheet pile in the perforation hole, A guide box having an alternating guide hole such as the first and second drilling rods so as to drill alternately by using the first and second drilling rods is provided so that a virtual installation line for installing the sheet file When a sheet file is hung, a sheet file to be hung by a guide plate having alternately formed guide grooves such as a sheet file alternately connected with adjoining sheet files by the joining ears of the sheet file, A sheet pile construction method using an auger which has a double piercing rod capable of facilitating the formation of a perforation hole and hitting a sheet file thereby reducing the efficiency of the operation and the working time and a guide used in the construction method Plate.

Description

더블 천공로드가 구성된 오거를 이용한 시트파일 시공공법 및 그 시공공법에 사용되는 가이드플레이트{Using auger drilling rod is composed of a double sheet pile construction method used in the construction process and its box and the guide plate guide}[0001] The present invention relates to a sheet pile construction method using an auger having a double piercing rod and a guide plate used in the pile construction method,

본 발명은 더블 천공로드가 구성된 오거를 이용한 시트파일 시공공법 및 그 시공공법에 사용되는 가이드플레이트에 관한 것으로서, 보다 상세하게는 전석층이나 암반층 지반과 같이 시트파일 항타작업이 곤란한 지층에서 시트파일의 양단부에 형성된 이음귀를 통해 인접하는 시트파일이 상호 연결상태를 유지하며 상기 시트파일을 설치하고자 하는 가상의 설치라인을 중심으로 교호적으로 배치할 수 있도록 지면에 교호적으로 천공홀을 형성하는 시트파일 시공공법 및 그 시공공법에 사용되는 가이드플레이트에 관한 것이다.The present invention relates to a sheet pile construction method using an auger having a double piercing rod and a guide plate used in the pile construction method. More particularly, the present invention relates to a sheet pile construction method, Wherein the sheet piles are alternately connected to each other through the joint ears formed at both ends thereof and are alternately arranged around a virtual installation line on which the sheet pile is to be installed, To a guide plate used in a file construction method and a construction method thereof.

근래에는 교통망 확충 등을 이유로 기존의 고가도로 또는 교량 등을 따라 동일한 경로로 상기 고가도로 등의 바로 밑 지하에서 지하철공사가 많이 이루어지고 있다.Recently, a lot of subways have been built under the above-mentioned overpasses on the same route along existing overpasses or bridges due to the expansion of transportation networks.

또한, 환경보호 및 자원보호의 관점에서 기존 건물을 철거하고 새로운 건물을 신축하는 것보다는 재건축 또는 리모델링을 장려하고 있다. 상기 재건축 또는 리모델링 등의 공사에서는 기존 건물의 기초 보강을 위하여 지하실 등의 기초보강공사가 많이 이루어진다.It also encourages reconstruction or remodeling rather than demolishing existing buildings and building new ones in terms of environmental protection and resource conservation. In the construction such as reconstruction or remodeling, a lot of foundation reinforcement work such as a basement is carried out to reinforce the foundation of an existing building.

상기 지하철공사 및 기초보강공사 등에서는 지반보강을 위한 파일시공이 필수적이라고 할 수 있다.In the above subway construction and basic reinforcement work, file construction for reinforcement of the ground is essential.

파일시공을 위한 종래의 공법으로 통상적으로 많이 사용되는 것은 대형굴삭기를 이용한 파일근입공법, 오토파일러를 이용한 파일근입공법, T4오거를 이용한 파일근입공법 등이 있다.As a conventional method for constructing a file, a commonly used method is a file insertion method using a large excavator, a file insertion method using an autofilter, and a file insertion method using a T4 auger.

상기 대형굴삭기를 이용한 파일근입공법은 굴삭기의 암의 선단에 바이브로해머 또는 유압장치를 장착하여 지상에서 파일을 항타하거나 압입하여 시공하는 공법이다.The method of inserting a file using the above-mentioned excavator is a method in which a vibro hammer or a hydraulic device is mounted on the tip of an arm of an excavator to pile or press the file on the ground.

상기 오토파일러를 이용한 파일근입공법은 오토파일러를 사용하여 유압을 사용하여 압입하여 시공하는 공겁ㅂ이다.The method of inserting a file using the autofiller is a method of press-fitting by using an autofilter using oil pressure.

사기 T4오거를 이용한 파일근입공법은 오거를 이용하여 케이싱을 근입한 후 공벽을 유지하고, 상기 케이싱 내부를 천공하여 파일을 삽입하는 공법이다.
The method of inserting a file using a scam T4 auger is a method of inserting a file by inserting a casing using auger and then maintaining a vacant wall and drilling the inside of the casing.

이에 따른 종래에는 등록번호 100937170호는 마이크로파일을 시공함에 있어서 지반의 직진 천공공법과, 등록번호 101071184호는 높이제한 공간에서 파일시공을 위한 천공공법 및 출원번호 1020120152451호는 가변형 천공직경을 갖는 천공기를 이용한 천공공법을 나타내고 있다.
In the past, the registration number 100937170 has been applied to the direct punching of the ground in the construction of microfiles, the registration number 101071184, the punching method for pile construction in the height-limited space, and the application No. 1020120152451 discloses a perforator having a variable punching diameter Is used.

그러나 상기한 천공공법을 사용함에 있어서는 천공홀에 항타되는 시트파일의 양단부에 형성된 이음귀로 인접된 시트파일이 상호 연결되어 교호적으로 배치될 때, 상기 시트파일의 센터위치에 맞게 천공홀을 천공할 수 없어 통상적으로 시트파일이 항타되는 길이방향으로 길게 천공된 천공홀에 따라 시트파일을 항타 시, 별도의 부가적인 작업이 필요하게 되는 문제점이 있었다.
However, when the above-mentioned perforating method is used, when perforated holes formed at both ends of the sheet pile to be hammered into the perforation holes are interlinked and alternately arranged, the perforation holes are drilled in accordance with the center position of the sheet pile There is a problem in that additional additional work is required when hitting the sheet pile according to a perforation hole which is long punched in the longitudinal direction in which the sheet pile is normally punched.

본 발명은 상기한 종래 기술의 문제점을 해결하기 위하여 안출해낸 것으로서 시트파일의 양단부에 형성된 이음귀로 인접된 시트파일이 상호 연결되어 교호적으로 배치되는 시트파일의 센터위치에 맞게 상호 일정 각도를 이루며 오거에 연결 구성된 제 1천공로드와 제 2천공로드를 이용하여 상기 시트파일을 설치하려는 위치의 지면에 상기 제 1, 2천공로드의 끝부에 각각 구성되는 굴착해머를 이용하여 천공홀을 천공할 수 있도록 더블 천공로드가 구비된 오거를 이용한 시트파일 시공공법 및 그 시공공법에 포함되며 상기 제 1, 2천공로드를 이용하여 천공 완료 후, 시트파일 항타 시, 상기 시트파일이 항타되는 경로를 이탈하지 않도록 가이드하는 가이드플레이트를 제공함에 주안점을 두고 그 기술적 과제로서 완성해낸 것이다.SUMMARY OF THE INVENTION The present invention has been made in order to solve the above-mentioned problems of the prior art, and it is an object of the present invention to provide a sheet- The drill hole can be drilled using the drilling hammer formed at the end portion of the first and second drilling rods, respectively, on the surface of the sheet to which the sheet pile is to be installed by using the first drilling rod and the second drilling rod, The sheet pile construction method using the auger provided with the double piercing rod and the pile construction method, and after the completion of punching using the first and second piercing rods, The present invention has been accomplished on the basis of providing a guiding guide plate.

상기한 과제를 달성하기 위한 본 발명에 따르면, 외주에 스크류가 형성되고, 일 측 끝부에 굴착해머가 연결 구성된 천공로드가 구동부재의 작동에 의해 상, 하로 작동하는 오거가 장착된 천공장치를 이용하여 시트파일을 설치하고자 하는 위치의 지면에 천공장치를 위치시키는 준비단계와, 상기 천공장치의 천공로드 및 굴착해머를 이용하여 시트파일을 설치하고자 하는 가상의 설치라인으로 천공하는 천공단계와, 상기 천공단계에서 천공홀을 천공한 후, 천공로드 및 굴착해머를 인발하는 인발단계 및 상기 천공된 천공홀에 시트파일 및 상기 시트파일의 양단부에 형성된 이음귀로 인접된 시트파일이 상호 연결되어 교호적으로 배치되도록 항타하는 항타단계의 시트파일 시공방법에 있어서, 상기 천공단계에서는 천공장치에 연결 구성된 오거와 연결되되 시트파일의 양단부에 형성된 이음귀로 인접된 시트파일이 상호 연결되어 교호적으로 배치되는 시트파일의 센터위치에 맞게 상호 일정 각도를 이루며 상기 오거에 연결 구성된 제 1천공로드와 제 2천공로드의 작동으로 상기 제 1, 2천공로드의 끝부에 구성되는 각각의 굴착해머를 이용하여 시트파일을 설치하려는 위치의 지면에 천공홀(h)을 천공하는 것을 특징으로 하는 더블 천공로드가 구비된 오거가 장착된 천공장치를 이용한 시트파일 시공방법을 제공함으로서 그 과제를 해결하고자 한다.According to an aspect of the present invention for achieving the above object, there is provided a drilling apparatus, comprising: a drilling apparatus having an auger equipped with an auger having a screw on an outer periphery thereof and a drill rod connected to a drill hammer at one end thereof, A drilling step of perforating the sheet pile into a virtual installation line for installing the sheet pile using the drilling rod and the drilling hammer of the punching apparatus; A piercing step of piercing the perforation hole in the perforating step, drawing the perforation rod and the excavating hammer, and the sheet pile in the perforated hole and the adjoining sheet pile formed at both ends of the sheet pile, A method of constructing a sheet pile of a hammering stage in which the hammers are arranged to be arranged, The first punched rod and the second punched rod which are connected to the auger at mutually different angles in accordance with the center position of the sheet files alternately connected to each other and connected to each other by the joint ears formed at both ends of the reed seat file, And a perforation hole (h) is formed in a surface of the sheet at a location where the sheet pile is to be installed by using the respective drilling hammers formed at the end portions of the first and second drilling rods. The present invention provides a sheet pile construction method using a perforated pile apparatus.

삭제delete

본 발명에 따른 더블 천공로드가 구성된 오거를 이용한 시트파일 시공공법 및 그 시공공법에 사용되는 가이드플레이트에 의하면, 시트파일을 설치하고자 하는 가상의 설치라인으로 상기 시트파일의 양단부에 형성된 이음귀로 인접된 시트파일이 상호 연결되어 교호적으로 배치되는 시트파일의 센터위치에 맞게 상호 일정 각도를 이루며 연결 구성된 제 1, 2천공로드를 이용하여 천공홀을 교호적으로 천공하고, 상기 천공홀에 시트파일을 항타할 수 있는 시트파일 시공공법을 제공하고, 상기 제 1, 2천공로드를 이용하여 교호적으로 천공할 수 있도록 상기 제 1, 2천공로드와 같이 교호적으로 가이드 홀이 형성된 가이드박스를 구비하여 시트파일을 설치하고자 하는 가상의 설치라인이 경로를 이탈하지 않으며, 시트파일 항타 시, 시트파일의 이음귀로 인접된 시트파일이 상호 연결되어 교호적으로 배치되는 시트파일과 같이 교호적으로 가이드 홈이 형성된 가이드플레이트를 구비하여 항타되는 시트파일이 경로를 이탈하지 않아 천공홀의 형성 및 시트파일의 항타를 용이하게 할 수 있고, 그로 인해 작업의 효율성과 작업시간을 단축시킬 수 있는 등 효과가 큰 발명이라 하겠다.According to the sheet pile construction method using the auger constructed according to the present invention and the guide plate used in the pile construction method, it is possible to provide a virtual installation line to which the sheet pile is to be installed, The sheet piles are alternately connected to each other and the punch holes are alternately drilled using the first and second punch rods configured to be connected to each other at a predetermined angle in accordance with the center position of the sheet pile, There is provided a sheet pile construction method for pile driving and a guide box having alternately formed guide holes such as the first and second piercing rods so as to drill alternately by using the first and second piercing rods The virtual installation line where the sheet file is to be installed does not deviate from the path, and when the sheet file is moved, And a guide plate having guide grooves formed in an alternating manner such as a sheet file alternately connected to each other so that the sheet file to be moved does not deviate from the path so that the formation of the perforation hole and the hitting of the sheet file are facilitated And it can be said that it is an effective invention that can shorten the work efficiency and the working time.

도 1a는 종래기술의 시트파일 항타공법에 따른 시트파일 항타장치의 개략도
도 1b는 도 1a의 시트파일 항타장치에 의해 시공된 시트파일의 개략도
도 2a는 종래기술의 워터젯공법에 따른 시트파일 항타장치의 개략도
도 2b는 도 2a의 시트파일 항타장치에 의해 시공된 시트파일의 개략도
도 3a는 종래기술의 선천공에 의한 항타공법에 따른 천공장치의 개략도
도 3b는 종래기술의 선천공에 의한 항타공법에 의해 시공된 시트파일의 개략도
도 4는 본 발명에 적용되는 오거를 나타내는 정면도
도 5는 본 발명에 적용되는 오거를 나타내는 측면도
도 6은 본 발명인 오거에 클램프와 보조클램프가 장착된 상태를 나타내는 측면도
도 7은 본 발명인 오거에 의해 지면에 항타되는 시트파일을 나타내는 평면도
도 8은 본 발명인 오거에 의해 지면에 천공된 천공홀과 항타된 시트파일을 나타내는 평면도
도 9는 본 발명에 적용되는 가이드박스를 나타내는 사시도, 평면도, 다른 실시 예의 사시도
도 10은 본 발명에 적용되는 가이드플레이트를 나타내는 사시도
FIG. 1A is a schematic view of a sheet file hitching device according to a conventional sheet file hitching method;
1B is a schematic view of a sheet file constructed by the sheet file jamming device of FIG.
2A is a schematic view of a sheet file hitching device according to the prior art water jet method;
FIG. 2B is a schematic view of a sheet file constructed by the sheet file jamming device of FIG.
FIG. 3A is a schematic view of a punching apparatus according to the prior art punching method
FIG. 3B is a schematic view of a sheet pile constructed by a pile driving method according to the prior art
4 is a front view showing an auger applied to the present invention
5 is a side view showing augers applied to the present invention
6 is a side view showing a state where the auger clamp and the auxiliary clamp are mounted according to the present invention
Fig. 7 is a plan view showing a sheet pile hitting the ground by auger according to the present invention. Fig.
Fig. 8 is a plan view showing a perforated hole perforated on the ground by the auger according to the present invention and a padded sheet pile
9 is a perspective view, a plan view, and a perspective view of another embodiment of the guide box according to the present invention.
10 is a perspective view showing a guide plate according to the present invention.

본 발명인 더블 천공로드가 구성된 오거를 이용한 시트파일 시공공법 및 그 시공공법에 사용되는 가이드플레이트에 대해 설명하면,A sheet pile construction method using an auger constructed as a double piercing rod according to the present invention and a guide plate used in the construction method will be described.

우선, 외주에 스크류가 형성되고, 일 측 끝부에 굴착해머가 연결 구성된 천공로드가 구동부재의 작동에 의해 상, 하로 작동하는 오거가 장착된 천공장치를 이용하여 시트파일을 설치하고자 하는 위치의 지면에 천공장치를 위치시키는 준비단계와, 상기 천공장치의 천공로드 및 굴착해머를 이용하여 시트파일을 설치하고자 하는 가상의 설치라인으로 천공하는 천공단계와, 상기 천공단계에서 천공홀을 천공한 후, 천공로드 및 굴착해머를 인발하는 인발단계 및 상기 천공된 천공홀에 시트파일 및 상기 시트파일의 양단부에 형성된 이음귀로 인접된 시트파일이 상호 연결되어 교호적으로 배치되도록 항타하는 항타단계의 시트파일 시공방법에 있어서, 상기 천공단계에서는 천공장치(100)에 연결 구성된 오거(200)와 연결되되 시트파일(400)의 양단부에 형성된 이음귀(410)로 인접된 시트파일(400)이 상호 연결되어 교호적으로 배치되는 시트파일(400)의 센터위치에 맞게 상호 일정 각도를 이루며 상기 오거(200)에 연결 구성된 제 1천공로드(210)와 제 2천공로드(220)의 작동으로 상기 제 1, 2천공로드(210, 220)의 끝부에 구성되는 각각의 굴착해머(211, 221)를 이용하여 시트파일을 설치하려는 위치의 지면에 천공홀(h)을 천공한다.
First, a perforation rod in which a screw is formed on the outer periphery and an excavating hammer is connected to one end thereof is pierced by a punch equipped with an auger which operates up and down by the operation of a driving member, A drilling step of drilling the drill hole into a virtual installation line for installing the sheet pile using the drilling rod and the drilling hammer of the drilling machine; A drawing step of drawing a boring rod and an excavating hammer, and a sheet pile construction step in which the sheet pile and the sheet pile adjacent to the pile hole formed at both ends of the sheet pile are mutually connected and alternately arranged, The perforation device 100 is connected to the auger 200 connected to the perforator device 100, and is formed at both ends of the sheet pile 400 A first perforation rod 400 connected to the auger 200 and having a predetermined angle with respect to a center position of the sheet pile 400 to which the adjacent sheet piles 400 are mutually connected and alternately arranged, 210 and the second drilling rod 220 by means of the drilling hammers 211 and 221 formed at the ends of the first and second drilling rods 210 and 220, The perforation hole (h) is drilled.

상기 제 1천공로드(210) 및 제 2천공로드(220)의 외주를 감싸며 천공장치(100)와 연결되는 클램프(300)로 인해 천공 시, 천공하려는 위치에서 제 1, 2천공로드(210, 220)가 이탈하지 않도록 한다.
The first and second puncturing rods 210 and 210 are disposed at a position to be punctured due to the clamp 300 that surrounds the peripheries of the first and second puncturing rods 210 and 220, 220 do not come off.

상기 제 1천공로드(210)와 제 2천공로드(220)의 끝부에 길이가 각각 상이하게 형성된 각각의 굴착해머(211, 221) 외주를 감싸는 보조클램프(310)로 인해 천공 시, 길이가 긴 굴착해머가 우선하여 전석층 또는 암반층에 도달하게 되어 경로가 이탈되는 것을 길이가 짧은 굴착해머와 연결된 보조클램프(310)로 인해 경로가 이탈되는 것을 방지할 수 있다.
The auxiliary clamps 310 surround the outer peripheries of the drilling hammers 211 and 221 formed at the ends of the first drilling rod 210 and the second drilling rod 220, It is possible to prevent the path from being deviated due to the auxiliary clamp 310 connected to the excavating hammer having a short length because the excavating hammer first reaches the entire rock layer or the rock layer and the path is deviated.

상기 천공장치(100)와 연결된 오거(200)에는 회전플레이트(230)가 구비되어 오거(200)를 회전시켜 천공하려는 위치를 가변할 수 있다.
The auger 200 connected to the punching device 100 may be provided with a rotation plate 230 to rotate the auger 200 to vary the position to be punched.

상기 천공단계에서 굴착해머(211, 221)와 천공홀(h)을 천공하려는 위치의 지면 사이에는 상기 제 1, 2천공로드(210, 220)가 관통할 수 있도록 가이드 홀(510)이 형성된 가이드박스(500)를 구비하여 상기 제 1, 2천공로드(210, 220)가 천공 시, 천공하려는 위치에서 경로가 이탈하지 않도록 천공한다.
In the drilling step, a guide hole 510 is formed between the digging hammer 211 and 221 and the ground surface at a position where the drilling hole h is to be inserted, through which the first and second drilling rods 210 and 220 can pass, Box 500 to puncture the first and second perforation rods 210 and 220 such that the first and second perforated rods 210 and 220 do not depart from the position where they are to be punctured.

상기 천공단계 후, 제 1, 2천공로드(210, 220)로 인해 형성된 지면의 천공홀(h)이 형성된 부분에는 상기 천공홀(h)에 항타되는 시트파일(400)이 관통할 수 있도록 가이드 홈(610)이 형성된 가이드플레이트(600)를 구비하여 상기 시트파일(400)이 항타 시, 항타하려는 위치에서 경로가 이탈하지 않도록 항타한다.
After the perforation step, a sheet pile 400 hinged to the perforation hole h is formed in a portion formed with the perforation hole h formed by the first and second perforated rods 210 and 220, And a guide plate 600 having grooves 610 formed therein so as to prevent the sheet file 400 from deviating from a position where the sheet file 400 is to be hammered.

상기 천공단계 후, 상기 천공홀(h)이 형성된 지면에 구비된 가이드박스(500)의 가이드 홀(510)이 형성된 부분에는 상기 천공홀(h)에 항타되는 시트파일(400)이 관통할 수 있도록 가이드 홈(610)이 형성된 가이드플레이트(600)를 구비하여 상기 시트파일(400)이 항타 시, 항타하려는 위치에서 경로가 이탈하지 않도록 항타한다.
After the perforation step, the sheet pile 400 hitting the perforation hole h can be passed through the guide hole 510 of the guide box 500 provided on the surface of the perforation hole h And a guide plate 600 having guide grooves 610 formed thereon so as to prevent the path from departing from the position where the seat file 400 is to be hammered.

상기한 천공공법에 포함되는 가이드박스(500)는 천공장치에 연결되는 오거에 순차적으로 연결 구성된 천공로드와 굴착해머를 이용하여 지면에 천공홀(h)을 천공하되, 상기 천공홀(h)을 천공하려는 위치의 지면에 위치하되 상기 굴착해머와 천공로드가 관통될 수 있도록 가이드 홀(510)이 형성되어 있다.The guide box 500 included in the perforating method may be constructed such that a perforation hole h is bored in the ground by using a perforating rod and an excavating hammer sequentially connected to an auger connected to a perforating device, And a guide hole 510 is formed in the ground surface of the position to be drilled so that the drilling hammer and the drilling rod can be penetrated.

상기 가이드박스(500)에 형성된 가이드 홀(510)은 시트파일(400)의 양단부에 형성된 이음귀(410)로 인접된 시트파일(400)이 상호 연결되어 교호적으로 배치 형성된다.
The guide holes 510 formed in the guide box 500 are formed by alternately connecting adjacent sheet piles 400 with joints 410 formed at both ends of the sheet pile 400.

상기한 천공공법에 포함되는 가이드플레이트(600)는 천공장치에 연결된 오거에 순차적으로 연결 구성된 천공로드와 굴착해머를 이용하여 지면에 천공홀(h)을 천공한 후, 상기 천공된 천공홀(h)에 시트파일(400)을 항타하되, 상기 시트파일(400)이 항타되는 위치의 지면에 위치되되, 시트파일(400)이 관통할 수 있도록 상기 시트파일(400)의 평단면의 형상보다 외측방향으로 일정 간격 이격되는 가이드 홈(610)이 형성되어 있다.The guide plate 600 included in the perforating method is formed by drilling a perforation hole h on the ground using a perforating rod and an excavating hammer sequentially connected to an auger connected to the perforating device, Of the flat surface of the sheet pile 400 so that the sheet pile 400 can pass through the sheet pile 400 while the sheet pile 400 is positioned on the ground surface where the sheet pile 400 is to be hammered, The guide grooves 610 are spaced apart from each other by a predetermined distance.

상기 가이드플레이트(600)에 형성된 가이드 홈(610)은 시트파일(400)의 양단부에 형성된 이음귀(410)로 인접된 시트파일(400)이 상호 연결되어 교호적으로 배치되는 시트파일(400)의 위치에 맞게 형성된다.
The guide groove 610 formed in the guide plate 600 is formed by connecting the sheet files 400 adjacent to each other with the joints 410 formed at both ends of the sheet file 400, As shown in FIG.

상기한 가이드 플레이트(600)는 천공홀(h)이 형성된 지면의 상부에 위치되는 가이드박스(500)의 상부에 위치되되, 상기 가이드 플레이트(600)의 가이드 홈(610)의 센터위치가 상기 가이드박스(500)에 형성된 가이드 홀(510)의 센터에 위치하여 사용할 수 있다.
The guide plate 600 is positioned above the guide box 500 positioned at the upper portion of the sheet of paper on which the perforation hole h is formed and the center position of the guide groove 610 of the guide plate 600 is aligned with the guide And may be located at the center of the guide hole 510 formed in the box 500.

상기한 본 발명인 더블 천공로드가 구성된 오거를 이용한 시트파일 시공공법 및 그 시공공법에 사용되는 가이드플레이트에 대해 도 4 내지 도 10을 참고로 보다 상세히 설명하면,4 to 10, a sheet pile construction method using an auger constructed as a double piercing rod according to the present invention and a guide plate used in the construction method will be described in more detail.

우선, 일반적으로 사용되는 시트파일 시공공법에 대해 설명하면,First, a sheet file construction method that is generally used will be described.

시트파일 시공공법은 외주에 스크류가 형성되고, 일 측 끝부에 굴착해머가 연결 구성된 천공로드가 구동부재의 작동에 의해 상, 하로 작동하는 오거가 장착된 천공장치를 이용하여 시트파일을 설치하려는 위치의 지면에 상기 천공로드와 연결된 굴착해머를 이용하여 천공홀을 형성한 후, 상기 천공홀에 시트파일을 항타하게 되는데,In the sheet file construction method, a perforation rod in which a screw is formed on the outer periphery and a drilling rod in which an excavating hammer is connected is connected to a position where a sheet file is to be installed by using a punch equipped with an auger, A drilling hole is formed on the surface of the drilling hole using an excavating hammer connected to the drilling rod,

이에 따른 시공공법은 외주에 스크류가 형성되고, 일 측 끝부에 굴착해머가 연결 구성된 천공로드가 구동부재의 작동에 의해 상, 하로 작동하는 오거가 장착된 천공장치를 이용하여 시트파일을 설치하고자 하는 위치의 지면에 천공장치를 위치시키는 준비단계와, 상기 천공장치의 천공로드 및 굴착해머를 이용하여 시트파일을 설치하고자 하는 가상의 설치라인으로 천공하는 천공단계와, 상기 천공단계에서 천공홀을 천공한 후, 천공로드 및 굴착해머를 인발하는 인발단계 및 상기 천공된 천공홀에 시트파일 및 상기 시트파일의 양단부에 형성된 이음귀로 인접된 시트파일이 상호 연결되어 교호적으로 배치되도록 항타하는 항타단계로 이루어진다.
In the construction method, a screw is formed on the outer periphery, and a perforation rod in which an excavating hammer is connected to one end is operated by the operation of the driving member, so as to install a sheet file using a punch equipped with an auger A drilling step of drilling the drill hole into a virtual installation line for installing the sheet pile using the drilling rod and the drilling hammer of the drilling machine; A drawing step of pulling out the boring rod and the excavating hammer, and a saddle stitching step in which the sheet pile and the adjoining sheet pile adjacent to each other at both ends of the sheet pile are interlinked and alternately arranged in the perforated hole .

이에 본 발명에서는 상기 천공단계에서 천공 시, 천공장치(100)에 연결 구성된 오거(200)와 연결되되 시트파일(400)의 양단부에 형성된 이음귀(410)로 인접된 시트파일(400)이 상호 연결되어 교호적으로 배치되는 시트파일(400)의 센터위치에 맞게 상호 일정 각도를 이루며 상기 오거(200)에 연결 구성된 제 1천공로드(210)와 제 2천공로드(220)의 작동으로 상기 제 1, 2천공로드(210, 220)의 끝부에 구성되는 각각의 굴착해머(211, 221)를 이용하여 시트파일을 설치하려는 위치의 지면에 천공홀(h)을 천공한다.In the present invention, the sheet pile 400 adjacent to the auger 200 connected to the punch device 100 when the punch is drilled in the punching step is connected to the joint ears 410 formed at both ends of the sheet pile 400, The first and second drilling rods 210 and 220 are connected to the auger 200 at predetermined angles in accordance with the center position of the sheet pile 400, The perforation holes h are formed in the surface of the sheet where the sheet pile is to be installed by using the respective drilling hammers 211 and 221 formed at the end portions of the first and second drilling rods 210 and 220.

이때, 사용되는 오거(200)에 연결 구성된 제 1, 2천공로드(210, 220)는 시트파일(400)을 항타하려는 위치에 천공홀(h)을 형성하게 되는데, 상기 천공홀(h)의 형성 시, 일반적으로는 시트파일(400)이 항타되는 천공홀(h)이 일직선상으로 형성되며, 본 발명의 핵심인 제 1, 2천공로드(210, 220)를 이용하면 시트파일(400)의 양단부에 형성된 이음귀(410)로 인접된 시트파일(400)이 상호 연결되어 교호적으로 배치될 때 상기 시트파일(400)의 센터위치에 맞게 제 1, 2천공로드(210, 220)가 상호 일정 각도를 이루며 천공홀(h)을 형성하게 된다.
At this time, the first and second drilling rods 210 and 220 connected to the auger 200 form a drilling hole h at a position where the sheet file 400 is to be hammered, The perforation hole h in which the sheet pile 400 is punched is formed in a straight line and the first and second punch rods 210 and 220, which are the core of the present invention, The first and second perforation rods 210 and 220 are aligned with the center position of the sheet pile 400 when the adjacent sheet piles 400 are mutually connected and alternately arranged by the joints 410 formed at both ends of the sheet pile 400. [ So that they form a perforation hole h at a predetermined angle.

상기에서 천공장치(100)를 이용하여 천공홀(h)을 천공 시, 상기 제 1천공로드(210) 및 제 2천공로드(220)의 외주를 감싸며 천공장치(100)와 연결되는 클램프(300)가 연결 구성되어 있어 천공하려는 위치에서 제 1, 2천공로드(210, 220)가 이탈하지 않도록 한다.When the perforation hole h is pierced by using the perforating device 100, the clamp 300 that surrounds the perforations of the first and second perforation rods 210 and 220 and is connected to the perforating device 100, So that the first and second drilling rods 210 and 220 are not separated from the drilling position.

상기한 클램프(300)는 제 1, 2천공로드(210, 220)의 외주를 감싸며, 일 측은 천공장치(100)와 연결되어 있다.The clamp 300 surrounds the peripheries of the first and second perforation rods 210 and 220 and is connected to the perforation device 100 at one side.

또한, 상기 클램프(300)의 경우, 제 1, 2천공로드(210, 220)의 길이에 따라 하나 이상 다수개를 상기 제 1, 2천공로드(210, 220)와 연결하여 천공 시, 이탈하지 않도록 할 수 있다.
In the case of the clamp 300, one or more of the first and second perforated rods 210 and 220 are connected to the first and second perforated rods 210 and 220 according to the length of the first and second perforated rods 210 and 220, .

상기에서 천공장치(100)를 이용하여 천공홀(h)을 천공 시, 상기 제 1천공로드(210)와 제 2천공로드(220)의 끝부에 길이가 각각 상이하게 형성된 각각의 굴착해머(211, 221) 외주를 감싸는 보조클램프(310)로 인해 길이가 긴 굴착해머가 우선하여 전석층 또는 암반층에 도달하게 되어 상기 전석층 또는 암반층으로 인해 경로가 이탈되는 것을 길이가 짧은 굴착해머와 연결된 보조클램프(310)로 인해 경로가 이탈되는 것을 방지할 수 있다.When the perforation holes h are drilled using the perforating device 100, the respective drilling hammers 211 having different lengths at the end portions of the first drilling rod 210 and the second drilling rod 220 The auxiliary clamp 310, which surrounds the outer circumference of the drill bit 221, causes the elongated drilling hammer to reach the osteoclast or rock layer first, It is possible to prevent the path from being deviated from the path 310.

이는 일반적으로 하나의 천공로드를 이용하여 천공 시, 상기 천공로드에 연결 구성된 굴착해머가 천공함에 있어 전석층 또는 암반층에 닿게 되면, 상기 전석층 또는 암반층으로 인해 경로가 이탈되는 상황이 빈번하게 일어나게 되었는데, 이를 방지하기 위한 것으로서, 제 1, 2천공로드(210, 220)의 일 측 끝부에 각각 연결 구성된 굴착해머(211, 221)의 일 측 외주를 감싸는 보조클램프(310)가 연결 구성되어 있다.In general, when the drilling hammer is connected to the drilling rod when the drilling is performed using one drilling rod, when the drilling hammer is contacted with the osteoclastic layer or the rock layer, the osteoclastic layer or the rock layer often causes a deviation from the path And an auxiliary clamp 310 that surrounds the outer periphery of one side of the excavating hammer 211 and 221 connected to one end of the first and second drilling rods 210 and 220 is connected.

상기 보조클램프(310)는 각각의 굴착해머(211, 221)의 외주를 감싸며 일정 간격 이격된 거리보다 좁아지거나 넓어지는 것을 방지하며, 상기 각각의 굴착해머(211, 221) 중 하나의 굴착해머가 전석층 또는 암반층과 닿게 되어 천공하려는 경로를 이탈하게 될 때, 상기 보조클램프(310)로 인해 경로의 이탈을 방지할 수 있도록 한 것이다.
The auxiliary clamp 310 surrounds the outer circumference of each of the excavating hammers 211 and 221 and prevents the excavating hammer 211 or 221 from becoming narrower or wider than a distance spaced by a predetermined distance, So that it is possible to prevent the path from departing due to the auxiliary clamp 310 when the path is torn away due to the contact with the entire rock layer or the rock layer.

상기 천공장치(100)와 연결된 오거(200)에는 회전플레이트(230)가 구비되어 오거(200)를 회전시켜 천공하려는 위치를 가변할 수 있다.The auger 200 connected to the punching device 100 may be provided with a rotation plate 230 to rotate the auger 200 to vary the position to be punched.

이는 천공장치(100)를 이용하여 천공함에 있어, 천공홀(h)을 형성해야 하는 방향이 기존의 천공하는 곳에서 멀지 않은 곳이라도 일반적으로는 천공장치(100)를 다시금 위치를 변동하여 천공하게 되어 재위치를 선정함에 따른 시간이 많이 발생되는 반면, 본 발명에서는 오거(200)의 회전플레이트(230)를 이용하여 상기 오저(200) 자체를 회전시킴으로 천공홀(h)을 천공하려는 위치로 위치시킬 수 있도록 하였다.
Even if the direction of forming the perforation hole h is not far from the existing perforation hole in the perforating device 100, generally, the perforator device 100 is repeatedly punched to vary the position However, in the present invention, by rotating the os 200 using the rotation plate 230 of the auger 200, it is possible to rotate the os 200 in a position to perforate the perforation hole h, .

상기 천공단계에서 굴착해머(211, 221)와 천공홀(h)을 천공하려는 위치의 지면 사이에는 상기 제 1, 2천공로드(210, 220)가 관통할 수 있도록 가이드 홀(510)이 형성된 가이드박스(500)를 구비하여 상기 제 1, 2천공로드(210, 220)가 천공 시, 천공하려는 위치에서 경로가 이탈하지 않도록 천공한다.In the drilling step, a guide hole 510 is formed between the digging hammer 211 and 221 and the ground surface at a position where the drilling hole h is to be inserted, through which the first and second drilling rods 210 and 220 can pass, Box 500 to puncture the first and second perforation rods 210 and 220 such that the first and second perforated rods 210 and 220 do not depart from the position where they are to be punctured.

이는 천공홀(h)을 천공하려는 위치의 지면과 굴착해머(211, 221) 사이에 상기 가이드박스(500)를 위치시켜, 제 1, 2천공로드(210, 220)가 가이드 홀(510)을 관통한 후, 지면에 천공홀(h)을 천공함에 있어, 천공하려는 위치에서 상기 제 1, 2천공로드(210, 220)가 경로를 이탈하지 않도록 한 것이다.The guide box 500 is positioned between the digging holes 211 and 221 and the first and second drilling rods 210 and 220 are inserted into the guide hole 510 The first and second drilling rods 210 and 220 do not deviate from the path at the position to be drilled when drilling the drilling hole h on the ground.

이때, 가이드박스(500)에 형성된 가이드 홀(510)은 상부에서 하부로 길이방향으로 길게 가이드 홀(510)이 형성되되, 상기 가이드 홀(510)은 제 1, 2천공로드(210, 220)와 같이 시트파일(400)의 양단부에 형성된 이음귀(410)로 상호 연결되어 각각의 시트파일(400)이 교호적으로 배치될 때, 각각의 시트파일(400)의 센터위치가 각각의 가이드 홀(510)의 센터위치에 맞게 형성되고, 상호 교호적으로 배치되는 시트파일(400)로 인해 각각의 가이드 홀(510)도 상호 일정 각도를 이루며 교호적으로 형성되어야 한다.
The guide hole 510 formed in the guide box 500 has a guide hole 510 extending in the longitudinal direction from the top to the bottom. The guide hole 510 includes first and second apertures 210 and 220, When the respective seat files 400 are alternately arranged, the center positions of the seat files 400 are connected to the guide holes 410 formed at the opposite ends of the seat file 400, Each of the guide holes 510 is formed at an angle to each other and alternately formed by the sheet pile 400 arranged in a mutually alternating manner.

상기 천공단계 후, 제 1, 2천공로드(210, 220)로 인해 형성된 지면의 천공홀(h)이 형성된 부분에는 상기 천공홀(h)에 항타되는 시트파일(400)이 관통할 수 있도록 가이드 홈(610)이 형성된 가이드플레이트(600)를 구비하여 상기 시트파일(400)이 항타 시, 항타하려는 위치에서 경로가 이탈하지 않도록 항타한다.After the perforation step, a sheet pile 400 hinged to the perforation hole h is formed in a portion formed with the perforation hole h formed by the first and second perforated rods 210 and 220, And a guide plate 600 having grooves 610 formed therein so as to prevent the sheet file 400 from deviating from a position where the sheet file 400 is to be hammered.

상기 천공홀(h) 형성이 완료된 후, 상기 천공홀(h)에 시트파일(400)을 항타하게 되는데, 일반적으로는 별도의 항타장치를 이용하여 상기 시트파일(400)을 항타하거나 또는 상기 천공장치(100)에 연결된 오거(200)를 항타할 수 별도의 부재로 변경 장착하여 시트파일(400)을 항타하게 된다.After the formation of the perforation hole h is completed, the sheet pile 400 is stuck to the perforation hole h. Generally, the sheet pile 400 is driven using a separate plowing device, The auger 200 connected to the apparatus 100 is replaced with another member that can be hammered, and the sheet file 400 is driven.

이에 상기 가이드플레이트(600)를 천공홀(h)이 형성된 지면의 상부에 위치시켜, 상기 천공홀(h)에 항타되는 시트파일(400)이 항타 시, 경로를 이탈하지 않도록 한 것이다.Thus, the guide plate 600 is positioned above the hole formed with the hole h so that the sheet pile 400 hitting the hole h does not deviate from the path when hitting the hinge h.

이때, 가이드플레이트(600)에 형성된 가이드 홈(610)은 시트파일(400)의 평단면에서 외측방향으로 일정 간격 이격되어 형성된다.At this time, the guide grooves 610 formed in the guide plate 600 are spaced from the flat surface of the sheet pile 400 by a predetermined distance in the outward direction.

상기한 가이드 홈(610)은 시트파일(400)이 천공홀(h)에 항타 시, 시트파일(400)이 경로를 이탈하지 않으며 항타될 수 있도록 상기 시트파일(400)의 평단면의 형상과 동일하게 형성되되, 외측방향으로 일정 간격 넓게 이격되어 상기 시트파일(400)이 관통할 수 있도록 형성된다.The guide groove 610 may be formed in the shape of a flat section of the sheet pile 400 so that the sheet pile 400 can be removed without leaving the path when the sheet pile 400 hits the perforation hole h. And is formed such that the sheet pile 400 can be penetrated through the sheet pile 400 by being widely spaced apart from each other in the outward direction.

상기한 가이드 홈(610)은 천공홀(h)에 항타되는 시트파일(400)이 다수개일때, 상호 이음귀(410)로 연결되게 되는데, 상기 이음귀(410)로 연결 시, 각각의 시트파일(400)이 상호 교호적으로 배치되는 형상과 동일한 형상의 교호적으로 배치된 가이드 홈(610)이 형성될 수 있다.
The guide grooves 610 are connected to the mutual coupling ears 410 when the plurality of seat piles 400 to be pivoted in the punch hole h are connected to each other. Alternately arranged guide grooves 610 having the same shape as the shape in which the files 400 are arranged alternately can be formed.

또한, 상기한 가이드 플레이트(600)의 경우, 사용에 따라 천공홀(h)이 형성된 지면에 위치시켜 사용할 수도 있지만, 또는 상기 천공홀(h)의 상부에 가이드박스(500)를 위치시킨 후, 상기 가이드박스(500)의 상부에 가이드 플레이트(600)를 위치시켜 사용할 수도 있다.
The guide plate 600 may be placed on a surface of the hole formed with the hole h in accordance with the use of the guide plate 600. Alternatively, after the guide box 500 is positioned on the hole h, The guide plate 600 may be disposed on the upper portion of the guide box 500.

상기한 천공공법에 포함되는 가이드박스(500)는 천공장치에 연결되는 오거에 순차적으로 연결 구성된 천공로드와 굴착해머를 이용하여 지면에 천공홀(h)을 천공하되, 상기 천공홀(h)을 천공하려는 위치의 지면에 위치하되 상기 굴착해머와 천공로드가 관통될 수 있도록 가이드 홀(510)이 형성되어 있다.The guide box 500 included in the perforating method may be constructed such that a perforation hole h is bored in the ground by using a perforating rod and an excavating hammer sequentially connected to an auger connected to a perforating device, And a guide hole 510 is formed in the ground surface of the position to be drilled so that the drilling hammer and the drilling rod can be penetrated.

상기 가이드박스(500)에 형성된 가이드 홀(510)은 시트파일(400)의 양단부에 형성된 이음귀(410)로 인접된 시트파일(400)이 상호 연결되어 교호적으로 배치 형성되되, 이는 사용에 따라 다수개를 연속적으로 형성하여 사용할 수도 있다.
The guide holes 510 formed in the guide box 500 are formed by alternately connecting adjoining sheet piles 400 with the joints 410 formed at both ends of the sheet pile 400, It is also possible to use a plurality of continuous forming units.

또한, 상기한 천공공법에 포함되는 가이드플레이트(600)는 천공장치에 연결된 오거에 순차적으로 연결 구성된 천공로드와 굴착해머를 이용하여 지면에 천공홀(h)을 천공한 후, 상기 천공된 천공홀(h)에 시트파일(400)을 항타하되, 상기 시트파일(400)이 항타되는 위치의 지면에 위치되되, 시트파일(400)이 관통할 수 있도록 상기 시트파일(400)의 평단면의 형상보다 외측방향으로 일정 간격 이격되는 가이드 홈(610)이 형성되어 있다.In addition, the guide plate 600 included in the perforating method may be manufactured by drilling a perforation hole h on the ground using a perforating rod and an excavating hammer sequentially connected to auger connected to the perforating device, sectional shape of the sheet pile 400 so that the sheet pile 400 can be pierced while the sheet pile 400 hits the pile h of the sheet pile 400, Guide grooves 610 spaced apart from each other by a predetermined distance are formed.

상기 가이드플레이트(600)에 형성된 가이드 홈(610)은 시트파일(400)의 양단부에 형성된 이음귀(410)로 인접된 시트파일(400)이 상호 연결되어 교호적으로 배치되는 시트파일(400)의 위치에 맞게 형성되되, 이는 사용에 따라 다수개를 연속적으로 형성하여 사용할 수도 있다.
The guide groove 610 formed in the guide plate 600 is formed by connecting the sheet files 400 adjacent to each other with the joints 410 formed at both ends of the sheet file 400, And it may be formed by continuously forming a plurality of pieces depending on the use.

상기한 가이드 플레이트(600)는 천공홀(h)이 형성된 지면의 상부에 위치되는 가이드박스(500)의 상부에 위치되되, 상기 가이드 플레이트(600)의 가이드 홈(610)의 센터위치가 상기 가이드박스(500)에 형성된 가이드 홀(510)의 센터에 위치하여 사용할 수 있다.
The guide plate 600 is positioned above the guide box 500 positioned at the upper portion of the sheet of paper on which the perforation hole h is formed and the center position of the guide groove 610 of the guide plate 600 is aligned with the guide And may be located at the center of the guide hole 510 formed in the box 500.

상기와 같이 본 발명은 시트파일(400)을 설치하고자 하는 가상의 설치라인으로 상기 시트파일(400)의 양단부에 형성된 이음귀(410)로 인접된 시트파일(400)이 상호 연결되어 교호적으로 배치되는 시트파일(400)의 센터위치에 맞게 상호 일정 각도를 이루며 연결 구성된 제 1, 2천공로드(210, 220)를 이용하여 천공홀(h)을 교호적으로 천공하고, 상기 천공홀(h)에 시트파일(400)을 항타할 수 있는 시트파일 시공공법을 제공하고, 상기 제 1, 2천공로드(210, 220)를 이용하여 교호적으로 천공할 수 있도록 상기 제 1, 2천공로드(210, 220)와 같이 교호적으로 가이드 홀(510)이 형성된 가이드박스(500)를 구비하여 시트파일(400)을 설치하고자 하는 가상의 설치라인이 경로를 이탈하지 않으며, 시트파일(400) 항타 시, 시트파일(400)의 이음귀(410)로 인접된 시트파일(400)이 상호 연결되어 교호적으로 배치되는 시트파일(400)과 같이 교호적으로 가이드 홈(610)이 형성된 가이드플레이트(600)를 구비하여 항타되는 시트파일(400)이 경로를 이탈하지 않아 천공홀(h)의 형성 및 시트파일(400)의 항타를 용이하게 할 수 있고, 그로 인해 작업의 효율성과 작업시간을 단축시킬 수 있는 등 효과가 큰 발명이라 하겠다.
As described above, according to the present invention, adjacent sheet files 400 are connected to each other through a connecting ear 410 formed at both ends of the sheet file 400 with a virtual installation line for installing the sheet file 400, The perforation holes h are alternately punctured by using the first and second perforated rods 210 and 220 connected to each other at a predetermined angle in accordance with the center position of the sheet file 400 to be arranged, The sheet pile construction method according to claim 1, wherein the first and second piercing rods (210, 220) are pierced alternately by using the first and second piercing rods (210, 220) The virtual installation line for installing the sheet file 400 does not deviate from the path and the guide box 500 having the guide hole 510 alternately as shown in FIG. The sheet files 400 adjacent to the joint 410 of the sheet file 400 are interconnected The guide plate 600 having the guide grooves 610 formed alternately like the alternately arranged sheet files 400 is provided so that the sheet file 400 to be hammered does not deviate from the path, And the seat file 400 can be easily hammered, thereby making it possible to shorten the efficiency of the operation and the working time.

10, 20, 30, 100 : 천공장치 14, 24 : 진동해머
16, 26, 36 : 시트파일 27 : 강관
32 : 오거 33 : 케이싱 34 : 천공로드 35 : 굴착해머
200 : 오거 230 : 회전플레이트
210 : 제 1천공로드 211 : 굴착해머
220 : 제 2천공로드 221 : 굴착해머
300 : 클램프 310 : 보조클램프
400 : 시트파일 410 : 이음귀
500 : 가이드박스 510 : 가이드 홀
600 : 가이드플레이트 610 : 가이드 홈
h : 천공홀
10, 20, 30, 100: punch device 14, 24: vibration hammer
16, 26, 36: sheet file 27: steel pipe
32: auger 33: casing 34: drilling rod 35: drilling hammer
200: auger 230: rotating plate
210: first drilling rod 211: drilling hammer
220: second drilling rod 221: drilling hammer
300: Clamp 310: Secondary clamp
400: sheet file 410: jointed ear
500: guide box 510: guide hole
600: guide plate 610: guide groove
h: Perforation hole

Claims (12)

외주에 스크류가 형성되고, 일 측 끝부에 굴착해머가 연결 구성된 천공로드가 구동부재의 작동에 의해 상, 하로 작동하는 오거가 장착된 천공장치를 이용하여 시트파일을 설치하고자 하는 위치의 지면에 천공장치를 위치시키는 준비단계와, 상기 천공장치(100)에 연결 구성된 오거(200)와 연결되되 시트파일(400)의 양단부에 형성된 이음귀(410)로 인접된 시트파일(400)이 상호 연결되어 교호적으로 배치되는 시트파일(400)의 센터위치에 맞게 상호 일정 각도를 이루며 상기 오거(200)에 구성된 제 1천공로드(210)와 제 2천공로드(220)의 작동으로 상기 제 1, 2천공로드(210, 220)의 끝부에 구성되는 각각의 굴착해머(211, 221)를 이용하여 시트파일을 설치하고자 하는 가상의 설치라인으로 천공하는 천공단계와, 상기 천공단계에서 천공홀을 천공한 후, 천공로드 및 굴착해머를 인발하는 인발단계 및 상기 천공된 천공홀에 시트파일 및 상기 시트파일의 양단부에 형성된 이음귀로 인접된 시트파일이 상호 연결되어 교호적으로 배치되도록 항타하는 항타단계의 시트파일 시공방법에 있어서,
상기 천공장치(100)와 연결된 오거(200)에는 회전플레이트(230)가 구비되어 오거(200)를 회전시켜 천공하려는 위치를 가변할 수 있고,
상기 천공단계에서 굴착해머(211, 221)와 천공홀(h)을 천공하려는 위치의 지면 사이에는 상기 제 1, 2천공로드(210, 220)가 관통할 수 있도록 가이드 홀(510)이 형성된 가이드박스(500)를 구비하여 상기 제 1, 2천공로드(210, 220)가 천공 시, 천공하려는 위치에서 경로가 이탈하지 않도록 천공하며,
상기 천공단계 후, 제 1, 2천공로드(210, 220)로 인해 형성된 지면의 천공홀(h)이 형성된 부분에는 상기 천공홀(h)에 항타되는 시트파일(400)이 관통할 수 있도록 가이드 홈(610)이 형성된 가이드플레이트(600)를 구비하여 상기 시트파일(400)이 항타 시, 항타하려는 위치에서 경로가 이탈하지 않도록 항타하는 것을 특징으로 하는 더블 천공로드가 구비된 오거를 이용한 시트파일 시공방법.

A perforation rod having an outer periphery formed with a screw and a drilling rod having a drill hammer connected to one end thereof is pierced by a perforator equipped with an auger which is operated up and down by the operation of a driving member, And a sheet pile 400 connected to the auger 200 connected to the punch device 100 and adjacent to the pile ears 410 formed at both ends of the sheet pile 400 are connected to each other The first and second drilling rods 210 and 220 formed at the auger 200 are formed at angles mutually at an angle to the center position of the sheet files 400 arranged alternately. A perforating step of perforating the sheet pile into a virtual installation line for installing the sheet pile using each of the piercing hammers 211 and 221 formed at the end of the piercing rods 210 and 220; Afterwards, boring rod and excavated A sheet pile construction method of a piling stage in which a sheet pile in a perforated hole and sheet fingers adjacent to a sheet pile formed at both ends of the sheet pile are mutually connected and alternately arranged,
The auger 200 connected to the perforator 100 may be provided with a rotation plate 230 to vary the position of the auger 200 by rotating the auger 200,
In the drilling step, a guide hole 510 is formed between the digging hammer 211 and 221 and the ground surface at a position where the drilling hole h is to be inserted, through which the first and second drilling rods 210 and 220 can pass, Box 500 to puncture the first and second drilling rods 210 and 220 such that the first and second drilling rods 210 and 220 do not deviate from the position where the drilling is to be performed,
After the perforation step, a sheet pile 400 hinged to the perforation hole h is formed in a portion formed with the perforation hole h formed by the first and second perforated rods 210 and 220, And a guide plate (600) having a groove (610) formed therein to guide the sheet file (400) so that the path does not deviate from the position where the sheet file (400) Construction method.

제 1항에 있어서,
상기 제 1천공로드(210) 및 제 2천공로드(220)의 외주를 감싸며 천공장치(100)와 연결되는 클램프(300)로 인해 천공 시, 천공하려는 위치에서 제 1, 2천공로드(210, 220)가 이탈하지 않도록 하는 것을 특징으로 하는 더블 천공로드가 구비된 오거를 이용한 시트파일 시공방법.
The method according to claim 1,
The first and second puncturing rods 210 and 210 are disposed at a position to be punctured due to the clamp 300 that surrounds the peripheries of the first and second puncturing rods 210 and 220, 220) are not separated from each other by using the auger provided with the double-perforated rod.
제 1항에 있어서,
상기 제 1천공로드(210)와 제 2천공로드(220)의 끝부에 길이가 각각 상이하게 형성된 각각의 굴착해머(211, 221) 외주를 감싸는 보조클램프(310)로 인해 천공 시, 길이가 긴 굴착해머가 우선하여 전석층 또는 암반층에 도달하게 되어 경로가 이탈되는 것을 길이가 짧은 굴착해머와 연결된 보조클램프(310)로 인해 경로가 이탈되는 것을 방지할 수 있는 것을 특징으로 하는 더블 천공로드가 구비된 오거를 이용한 시트파일 시공방법.
The method according to claim 1,
The auxiliary clamps 310 surround the outer peripheries of the drilling hammers 211 and 221 formed at the ends of the first drilling rod 210 and the second drilling rod 220, Wherein the drilling hammer is prevented from being deviated from the path due to the auxiliary clamp 310 connected to the drilling hammer having a short length so that the drilling hammer first reaches the entire rock layer or the rock layer and the path is deviated. A method of sheet file construction using auger.
삭제delete 삭제delete 삭제delete 삭제delete 삭제delete 삭제delete 천공장치에 연결된 오거에 순차적으로 연결 구성된 천공로드와 굴착해머를 이용하여 지면에 천공홀(h)을 천공한 후, 상기 천공된 천공홀(h)에 시트파일(400)을 항타하되,
상기 시트파일(400)이 항타되는 위치의 지면에 위치되되, 시트파일(400)이 관통할 수 있도록 상기 시트파일(400)의 평단면의 형상보다 외측방향으로 일정 간격 이격되는 가이드 홈(610)이 형성되고,
가이드플레이트(600)에 형성된 가이드 홈(610)은 시트파일(400)의 양단부에 형성된 이음귀(410)로 인접된 시트파일(400)이 상호 연결되어 교호적으로 배치되는 시트파일(400)의 위치에 맞게 형성되며,
상기 가이드 플레이트(600)는 천공홀(h)이 형성된 지면의 상부에 위치되는 가이드박스(500)의 상부에 위치되되, 상기 가이드 플레이트(600)의 가이드 홈(610)의 센터위치가 상기 가이드박스(500)에 형성된 가이드 홀(510)의 센터에 위치하여 사용할 수 있는 것을 특징으로 하는 가이드 플레이트.

A perforation hole h is formed in the ground using a perforating rod and an excavating hammer sequentially connected to auger connected to a perforating device and then the sheet pile 400 is stuck to the perforated hole h,
A guide groove 610 which is located at a position of a position where the sheet file 400 is hitting and spaced apart from the shape of the flat surface of the sheet file 400 by a predetermined distance so that the sheet file 400 can pass therethrough, Is formed,
The guide grooves 610 formed in the guide plate 600 are formed in the sheet pile 400 in such a manner that adjacent sheet piles 400 are connected to each other by interposing ears 410 formed at both ends of the sheet pile 400 Lt; / RTI >
The guide plate 600 is positioned above the guide box 500 positioned on the upper surface of the hole formed with the hole h and the center position of the guide groove 610 of the guide plate 600 is positioned on the guide box 500. [ (510) formed in the guide plate (500).

삭제delete 삭제delete
KR1020140030554A 2014-03-14 2014-03-14 Using auger drilling rod is composed of a double sheet pile construction method used in the construction process and its box and the guide plate guide KR101628988B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020140030554A KR101628988B1 (en) 2014-03-14 2014-03-14 Using auger drilling rod is composed of a double sheet pile construction method used in the construction process and its box and the guide plate guide

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020140030554A KR101628988B1 (en) 2014-03-14 2014-03-14 Using auger drilling rod is composed of a double sheet pile construction method used in the construction process and its box and the guide plate guide

Publications (2)

Publication Number Publication Date
KR20150107505A KR20150107505A (en) 2015-09-23
KR101628988B1 true KR101628988B1 (en) 2016-06-21

Family

ID=54246000

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020140030554A KR101628988B1 (en) 2014-03-14 2014-03-14 Using auger drilling rod is composed of a double sheet pile construction method used in the construction process and its box and the guide plate guide

Country Status (1)

Country Link
KR (1) KR101628988B1 (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101012916B1 (en) * 2007-05-09 2011-02-08 위성배 The Device of installing the column pile of sheet pile unit
JP2013019260A (en) * 2011-06-17 2013-01-31 Nagaigumi Co Ltd Drilling equipment and construction method for sheet pile

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101012916B1 (en) * 2007-05-09 2011-02-08 위성배 The Device of installing the column pile of sheet pile unit
JP2013019260A (en) * 2011-06-17 2013-01-31 Nagaigumi Co Ltd Drilling equipment and construction method for sheet pile

Also Published As

Publication number Publication date
KR20150107505A (en) 2015-09-23

Similar Documents

Publication Publication Date Title
KR20130094449A (en) Apparatus and method for continuous hole drilling
KR101694844B1 (en) Construction method of sheet pile using guide casing
KR101812265B1 (en) A Foundation Method Of Continuous and Cut Off wall By Overlap Casing
KR101243928B1 (en) Pile construction method using two excavating equipments and non welding type linked casing
JP6774132B1 (en) Construction method of steel pipe pile
KR100989853B1 (en) piling location fixing apparatus for cast in place concrete pile wall
KR101808960B1 (en) Sheet pile construction apparatus using multi-axled auger screw
KR101726229B1 (en) Vibration hammer of a boring machine and boring method using the same
KR102092514B1 (en) Ground drilling method for foundation reinforcement
KR101628988B1 (en) Using auger drilling rod is composed of a double sheet pile construction method used in the construction process and its box and the guide plate guide
KR20090131338A (en) Casing and sheet pile structuring method using thereof
KR101042272B1 (en) Boring casings pipe for micro-pile with connector
KR100529726B1 (en) Sheet Pile and Construction Method thereof
KR101615810B1 (en) Sheet Pile Construction Apparatus For Perforating and Pile Driver Work
KR20110111637A (en) Down hole and steel pressing apparatus for rock base and method using the same
KR101384840B1 (en) Apparatus for hole drilling using prd(percussion rotary drill) method
KR100937170B1 (en) Straight drilling method of ground for micro-pile construction
KR101548280B1 (en) Equipped with a double auger drilling rod and the drilling device is equipped with auger
KR101483181B1 (en) H beams for placing perforated part piercing can be done in the absence of H-type perforated and construction method for H-type perforated
JP6195376B2 (en) Ruler for placing steel pipe sheet pile, method for placing steel pipe sheet pile, and swivel excavator used for the method for placing steel pipe sheet pile
KR101313433B1 (en) Method for widening hole drilling using prd(percussion rotary drill) method
KR100395839B1 (en) Sheet Pile and Construction Method thereof
KR20140132640A (en) Auger drill with arm crushing means
JP2012197618A (en) Repair method for existing revetment
KR101257497B1 (en) Down hole bit and method for pressing sheet pile using the same

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
AMND Amendment
E601 Decision to refuse application
AMND Amendment
GRNT Written decision to grant
X701 Decision to grant (after re-examination)
FPAY Annual fee payment

Payment date: 20190902

Year of fee payment: 4

R401 Registration of restoration