KR101518471B1 - Mining method for stratigraphic ore in soft rock - Google Patents

Mining method for stratigraphic ore in soft rock Download PDF

Info

Publication number
KR101518471B1
KR101518471B1 KR1020140150283A KR20140150283A KR101518471B1 KR 101518471 B1 KR101518471 B1 KR 101518471B1 KR 1020140150283 A KR1020140150283 A KR 1020140150283A KR 20140150283 A KR20140150283 A KR 20140150283A KR 101518471 B1 KR101518471 B1 KR 101518471B1
Authority
KR
South Korea
Prior art keywords
tunnel
mining
ore
skeletal
mine
Prior art date
Application number
KR1020140150283A
Other languages
Korean (ko)
Inventor
권대륙
허준석
Original Assignee
권대륙
허준석
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 권대륙, 허준석 filed Critical 권대륙
Priority to KR1020140150283A priority Critical patent/KR101518471B1/en
Application granted granted Critical
Publication of KR101518471B1 publication Critical patent/KR101518471B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C41/00Methods of underground or surface mining; Layouts therefor
    • E21C41/16Methods of underground mining; Layouts therefor
    • E21C41/22Methods of underground mining; Layouts therefor for ores, e.g. mining placers
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D21/00Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels

Abstract

The present invention relates to a mining method to exploit underground mineral resources, where an ore body to be mined containing concentrated target mineral ingredients is in an uncompacted or in a clastic state, and is present in a stratigraphically horizontal or inclined form in a soft rock. The mining method comprises: (a) a step of digging a skeletal mine of a certain shape and size in a bedrock stratum located under a mineral layer containing the ore body, and has a certain degree of compactness or higher to be safe; (b) a step of digging a main cross mine in a low slope from the skeletal mine in a direction of the inclination angle of the ore body; (c) a step of digging a drift mine from the main cross mine towards a varve among the veins of ore in four mining blocks divided from the ore body; (d) a step of digging a plurality of production cross mines from the drift mine in the direction of the inclination angles between the veins of ore for mining in the four mining blocks; (e) a step of dividing the veins of ore on the left and right of the production cross mines into unit mining areas in equal size, mining the ore starting from a blind end moving towards the drift mine, and ending at the main cross mine; and (f) a step of transporting the mined ore to the ground through the skeletal mine using a transporting means.

Description

연약 암반층에 층서적으로 부존하는 광석의 채광방법 {MINING METHOD FOR STRATIGRAPHIC ORE IN SOFT ROCK}METHOD FOR STRATIGRAPHIC ORE IN SOFT ROCK METHOD FOR MINING METHOD FOR STRATIGRAPHIC ORE IN SOFT ROCK

본 발명은 미고결상태 또는 파쇄상태가 심한 지층에 수평 내지 완경사로 부존하는 다수 층의 광물 및 재채굴 구역의 광석을 채광하는 방법에 관한 것으로서, 보다 상세하게는, 미고결상태 또는 파쇄상태로 부존하는 연약 암반층의 채광대상광체 및 기채굴 구역에 잔존하는 유용 채광대상광체를 일정치 이상의 고결도가 있는 안정된 지층에서 채광대상광체에 접근하여 일정 규격의 블록으로 구분되는 광획을 대상으로 채광하는 연약 암반층에 층서적으로 부존하는 광석의 채광방법에 관한 것이다.
The present invention relates to a method for mining multiple ore and mined ore minerals present in horizontal or mild grains in a non-cemented or crushed strata, and more particularly, Which is located in a soft rock layer and which remains in the mining area of the soft rock layer, is moved from a stable layer having a high degree of certainty above a certain level to a mining target object, And to a mining method of ores that are present in the form of a layer book.

일반적으로 채광은, 넓은 의미로는 지각(地殼) 중에 존재하는 유용 광물을 채취하는 작업 전체를 가리킨다. 광상(鑛床)이라고 하는 형태로 한정된 구역에 집합되어 존재하는 유용광물을 채취하는 장소가 광산이며, 그 각각의 광상의 형태에 적합한 방법으로 경제적, 기술적, 안정적 및 합리적으로 유용광물을 채취하는 작업을 의미한다.In general, mining refers in its broadest sense to the whole work of mining beneficial minerals present in the earth's crust. It is the mine to collect the useful minerals collected in the area limited to the form of the deposit, and to collect minerals economically, technically, stably, and reasonably in a manner suited to the form of each deposit. .

종래기술에 따른 채광방법 중에 방사상 채광방법은, 지표면의 선택된 지점에서 선택된 광물층의 근접지까지 가능한 넓은 직경으로 이루어지는 수평갱, 사갱 또는 수갱을 굴착개설하되 그 저부에 작업장을 형성시키고, 깨끗한 공기를 갱내로 주입하여 광물층으로부터 적어도 하나 이상의 통기갱을 통하여 오염된 공기를 지표면 위까지 배출시키도록 수단을 장치하고, 작업장으로부터 선택된 방향으로 어느 선택된 거리까지 종래 방식으로 이동 가능한 천반지지장치를 병행 사용하여 광물층에 제1방사상 수갱을 채굴하고, 지지장치가 작업실로 부터 계속 이어지는 방사상 채굴거리마다에 위치되게 하되 그들의 이동부분이 제1방사상 수갱의 최초 벽을 향하여 직각으로 향하도록하며, 수갱이 연장됨에 따라 천반지지장치 아래에 가요성 간벽의 밀폐벽을 축조하고, 깨끗한 공기가 제1수갱 아래로 운반되어 작업채벽과 밀폐벽 사이에 외부로 흘러 밀폐벽의 단부를 뒤로 돌아 제2수갱을 경유하면 지표면 위까지 강제 송풍되게 하며, 어느 선택된 채광방법에 의하여 방사상 수갱을 넓히면서 제1벽의 적어도 일부분을 채굴하므로 계속 전진하여 제1방사상 수갱이 선택된 거리까지 채굴된 후, 제2벽을 형성하도록 선택된 채굴방법에 의하여 계속하여 방사상으로 채벽을 채굴하고, 광물질을 천반지지장치의 선을 따라 작업실 및 지표면까지 운반토록 하는 특징이 있다.
The radial mining method in the mining method according to the prior art excavates horizontal gangs, shafts or shafts having a wide diameter as far as possible from a selected point on the earth's surface to the vicinity of the selected mineral layer, forming a work area at the bottom thereof, Means for injecting air into the mine and discharging contaminated air from the mineral layer through the at least one ventilator to above the surface of the ground and using a tilt support device capable of being moved in a conventional manner to any selected distance in a selected direction from the work site Mining the first radial shafts in the mineral layer and causing the support to be positioned at every successive radial excavation distance from the work chamber so that their moving portions are directed at a right angle towards the initial wall of the first radial shafts, The enclosure wall of the flexible barrier below the top support Clean air is transported below the first shaft and flows out between the working wall and the closing wall to force the end of the closing wall back to the ground surface through the second shaft, Continuing advancing by continuing to advance at least a portion of the first wall while widening the radial shafts, the first radial shafts are mined to a selected distance and then continuously mined by the selected mining method to form the second wall, It is characterized by the fact that it can be transported to the work room and the ground along the line of the support device.

본 발명의 배경기술은 대한민국 공개특허공보 제10-1978-0000310호(1978년 02월 06일 공개, 발명의 명칭 : 방사상 채광방법)에 개시되어 있다.
Background Art [0002] The background art of the present invention is disclosed in Korean Patent Laid-Open Publication No. 10-1978-0000310 (published on Feb. 06, 1978, entitled "Radial mining method").

일반적인 방사상 채광방법은, 광물층에 직접 갱도를 굴착하면서 채광을 행하기 때문에 미고결상태 또는 파쇄상태 지층에 광물층이 형성되어 있는 경우에는 채광을 행하는 갱도가 붕락될 위험이 있어 안전사고를 예방하기 어렵고, 갱도의 붕락을 방지하기 위한 시설물 설치에 소요되는 시간 및 비용을 절감하기 어려운 문제점이 있다.In general, the radial mining method is to mining a tunnel directly to a mineral layer, so that when a mineral layer is formed in an unconsolidated or crushed state stratum, there is a danger that the tunnel undergoing mining may collapse, And it is difficult to reduce the time and cost required for installation of facilities for preventing the collapse of the tunnel.

따라서 이를 개선할 필요성이 요청된다.Therefore, there is a need for improvement.

본 발명은 미고결상태 또는 파쇄상태로 부존하는 연약 암반층의 채광대상광체(이하, 재채굴 구역의 광체를 포함한다.)를 일정치 이상의 고결도를 갖춘 안정된 지층에서 미고결상태 또는 파쇄상태의 채광대상광체에 접근하고 일정규격으로 구분한 광획을 대상으로 채광하는 취약 암반에 층서적으로 부존하는 광물을 경제적이고 안전하며 효율적인 방법으로 채광하는 채광방법을 제공하는데 그 목적이 있다.
The present invention relates to a method for producing a non-cemented or crushed mine (hereinafter referred to as " mine ") in a stable rock layer having a high degree of solidification above a certain level It is an object of the present invention to provide a method of mining minerals present in a bedrock in an economical, safe and efficient manner to a vulnerable rock bed which approaches a target minerals and minutely targets minerals classified to a certain standard.

본 발명은, 유효 광물성분이 농집된 채광대상광체가 미고결상태 또는 쇄설성상태이고 층서적으로 수평 또는 경사지게 연약 암반층에 부존하는 지하 광물자원을 개발하는 채광방법에 있어서, (a) 채광대상광체를 포함하는 광물층의 하부에 위치되고 일정치 이상의 고결도를 갖춰 안정성을 유지하는 암반 지층에 일정 형태와 규격을 갖는 골격갱도를 굴착하는 단계; (b) 상기 골격갱도로부터 상기 채광대상광체의 경사방향으로 완경사의 주크로스갱도를 굴착하는 단계; (c) 상기 주크로스갱도로부터 상기 채광대상광체를 4분할 채광블록으로 구분하여 맥중에 연층방향으로 연층갱도를 굴착하는 단계; 및 (d) 상기 연층갱도로부터 4분할된 각각의 구획에 채광을 위한 다수 개의 생산크로스갱도를 맥중 경사방향으로 굴착하는 단계; (e) 상기 생산크로스갱도의 좌우측 광맥을 일정한 규격으로 단위 채광구역을 구획하고 최종 막장에서부터 상기 연층갱도로 후퇴하면서 상기 주크로스갱도에서 채광이 마무리되도록 광석을 채굴하는 단계; 및 (f) 상기 채광작업에 의해 채굴된 광석을 상기 골격갱도를 통해 운반수단을 이용해 지상으로 이동하는 단계를 포함하는 것을 특징으로 한다.The present invention relates to a mining method for developing an underground mineral resource existing in a soft rock layer such that a mining object to be mined is an unconditioned or clinker-like state in which an effective mineral component is concentrated, Excavating a skeletal tunnel having a certain shape and size in a rock layer which is located at a lower portion of the mineral layer and which has stability higher than a predetermined value to maintain stability; (b) excavating the main cross tunnel of the mild slope from the skeletal tunnel in an oblique direction of the object body to be exposed; (c) dividing the object-to-be-mined object into four quad-mining blocks from the main cross tunnel to excavate the multi-layered tunnel in the direction of the middle layer; And (d) excavating a plurality of production cross tunnels for mining in each of the quadrants partitioned from the quaternary tunnel in the slope direction of the core; (e) mining the ore so as to finish the mining in the main crossing tunnel while dividing the unit mining area into the standard mining area of the production cross gutter to a predetermined size and retracting from the final screening area to the multi-layered mining area; And (f) moving the ore mined by the mining operation to the ground by using the conveying means through the skeleton tunnel.

또한, 본 발명의 상기 (a)의 단계에서, 상기 골격갱도는 아치형 또는 장방형으로 광석 운반차량이 통행 가능한 정도의 규격으로 굴착하고, 갱도 바닥면의 경사는 갱내부의 자연 배수가 가능하도록 1도 내지 2도의 경사로 굴착하는 것을 특징으로 한다.In addition, in the step (a) of the present invention, the skeletal tunnel is arched or rectangular, and the ore transporting vehicle is excavated to a size that allows passage of the ore, and the inclination of the tunnel bottom surface is adjusted to 1 degree And is excavated at an inclination of 2 degrees.

또한, 본 발명의 상기 (b) 단계의 주크로스갱도는, 상기 채광대상광체의 부존 부위에 따라 복수 개의 갱도로 개설할 수 있고, 주요 분기점에는 작업용 차량이나 장비의 회전이 가능한 반경의 공간부를 갖도록 굴착하는 것을 특징으로 한다.The main cross tunnel in the step (b) of the present invention can be formed by a plurality of tunnels according to an existing portion of the object to be mined, and has a space portion having a radius capable of rotating a work vehicle or equipment And excavation.

또한, 본 발명의 상기 (c) 단계의 주크로스갱도에서 분기되는 상기 연층갱도의 분기점에는 작업장비의 회전이 가능한 반경의 공간부를 형성하는 것을 특징으로 한다.Further, in the step (c) of the present invention, at the bifurcation point of the multi-layered tunnel that branches off from the main cross tunnel, a space portion having a radius capable of rotating the work equipment is formed.

또한, 본 발명의 각각의 갱도에는 그 주변의 암질, 반압 등에 대응하여 강재, 목재, 락볼트 또는 쇼크리트로 이루어지는 지보수단 중 선택된 어느 하나의 지보재를 시행하고, 상기 지보재 사이에는 목재, 강판, 와이어메쉬 중 선택된 어느 하나의 방법으로 절장을 실시하며, 상기 지보재의 저부에는 반팽에 대응하는 인버터를 설치하는 것을 특징으로 한다.In each of the tunnels of the present invention, any one support selected from among steel, wood, rock bolt, or shock support means corresponding to the surrounding rock quality, semi-pressure, etc., The inverter is installed at the bottom of the support, and the inverters corresponding to the inverter are installed on the bottom of the support.

또한, 본 발명의 상기 지보부재 중 상기 연층갱도 및 상기 생산크로스갱도에서는 광석 채굴 후 갱도의 천반이 자연 붕락되도록 원칙적으로 회수하는 것을 특징으로 한다.In addition, in the above-described stratum corneum and the produced cross gangway of the present invention, in principle, it is collected so that the ore of the tunnel after the ore mining is naturally collapsed.

또한, 본 발명의 상기 (e) 단계에서 작업장에는 채광작업 종료 까지는 천반부 침하나 붕락을 방지하기 위해 Forepoling이나 Mini pipe roof 등을 설치하는 것을 특징으로 한다.Also, in the step (e) of the present invention, the work site is provided with a fore-poling or a mini-pipe roof to prevent collapse until the completion of the mining operation.

또한, 본 발명의 상기 골격갱도에는 갱도 내의 통기를 위하여 지상과 관통되는 1개 이상의 통기갱도가 더 구비되는 것을 특징으로 한다.The skeletal tunnel of the present invention is further characterized in that at least one ventilation tunnel penetrating the ground is further provided for ventilation in the tunnel.

또한, 본 발명의 상기 골격갱도에는 갱내 지하수가 모여 저장되는 복수 의 저수조가 구비되는 것을 특징으로 한다.Further, the skeletal tunnel of the present invention is characterized in that a plurality of water storage tanks in which mine underground water is gathered and stored are provided.

또한, 본 발명의 상기 연층갱도와 상기 생산크로스갱도가 연결되는 곳에는 해당구역 광체를 전부 채광하기 전까지는 맥중 상기 연층갱도의 안정을 위해 적정 규모의 광맥을 필라로 잔치하는 것을 특징으로 한다.In addition, in the present invention, where the multi-level tunnel is connected to the production cross tunnel, the vein of an appropriate scale is feasted for the stabilization of the multi-level tunnel in the core until the entire zone minerals are mined.

또한, 본 발명의 상기 (e) 단계에서 최소 단위 채광구역은 1교대 근무시간 내에 채광이 완료될 수 있는 적정 규모로 구획하는 것을 특징으로 한다.In addition, the minimum unit lighting zone in the step (e) of the present invention is characterized by dividing it into an appropriate scale for completing mining within one shift working time.

또한, 본 발명의 광석을 운반하는 장비는 채광이 이루어지는 작업장까지 상기 골격갱도, 상기 주크로스갱도, 상기 연층갱도 및 상기 생산크로스갱도를 통해 이동하는 것을 특징으로 한다.The apparatus for transporting ores according to the present invention is characterized in that it moves through the skeletal tunnel, the main cross tunnel, the stratified tunnel and the produced cross tunnel to a work site where mining is performed.

또한, 본 발명의 상기 골격갱도 또는 상기 주크로스갱도는, 복수 개의 돌출부가 스크루 모양으로 연속되게 배치되는 파쇄부를 구비하는 굴착장비의 구동에 의해 굴진작업이 이루어지고, 상기 연층갱도 또는 상기 생산크로스갱도는, 유압진동리퍼 또는 원뿔형면삭기가 설치되는 굴삭장비에 의해 굴진되며, 상기 (e) 단계는, 상기 유압진동리퍼 또는 원뿔형면삭기가 설치되는 굴삭장비에 의해 채광대상광체를 채광하여 운반차량에 의해 상기 생산크로스갱도, 상기 연층갱도, 상기 주크로스갱도 및 상기 골격갱도를 따라 지상으로 이송되고, 상기 운반차량은, 동력을 제공하는 구동부와, 상기 구동부에 힌지부에 의해 회전 가능하게 연결되고 채광대상광체가 수납되는 수납부를 포함하는 것을 특징으로 한다.
Further, in the skeleton tunnel or the main cross tunnel of the present invention, a drilling operation is performed by driving an excavating equipment having a crushing portion in which a plurality of projecting portions are successively arranged in a screw shape, (10) is pushed by an excavating equipment in which a hydraulic vibration ripper or a conical type grounding machine is installed, and the step (e) is performed by mining the object to be mined by the excavating equipment in which the hydraulic vibration ripper or the conical grounding machine is installed, Wherein the transporting vehicle comprises: a driving unit for supplying power; a driving unit for driving the driving unit, the driving unit being rotatably connected to the driving unit by a hinge unit, And a housing portion for housing the housing.

본 발명에 따른 연약 암반층에 층서적으로 부존하는 광석과 재채굴 방법은, 채광대상광체가 부존하는 광물층보다 하부에 위치하고 일정치 이상의 고결도를 갖춰 안정성을 유지하는 지층에 골격갱도를 굴착하고 광물층으로 주크로스갱도를 굴착하여 광물층에서 채광되는 채광대상광체를 생산크로스갱도 및 연층갱도를 통해 채광하므로 채광작업이 진행되는 동안에 갱도가 붕락되는 안전사고를 예방할 수 있고, 갱도의 붕락을 방지하는 별도의 지보시설 설치에 소요되는 시간 및 비용을 절감할 수 있는 이점이 있다.
The ore and the re-mining method that are present in the soft rock layer according to the present invention include a method of excavating a skeleton tunnel to a stratum which is located below a mineral layer having a mining object to be mined, It is possible to prevent the safety accident that the tunnel is collapsed during the mining operation by drilling the main cross tunnel to the mining layer through the production cross tunnel and the multi-layer tunnel to prevent the collapse of the tunnel. There is an advantage that the time and cost required to install a separate support facility can be reduced.

도 1은 본 발명의 일 실시예에 따른 연약 암반층(이하, 재채굴 구역을 포함한다.)에 층서적으로 부존하는 광석의 채광방법이 도시된 순서도이다.
도 2는 본 발명의 일 실시예에 따른 연약 암반층에 층서적으로 부존하는 광석의 채광방법을 구현하는 갱도구조가 도시된 구성도이다.
도 3은 본 발명의 일 실시예에 따른 연약 암반층에 층서적으로 부존하는 광석의 채광방법의 갱도가 도시된 구성도이다.
도 4는 본 발명의 일 실시예에 따른 연약 암반층에 층서적으로 부존하는 광석의 채광방법의 연층갱도 및 생산크로스갱도의 연결구조가 도시된 구성도이다.
도 5는 본 발명의 일 실시예에 따른 연약 암반층에 층서적으로 부존하는 광석의 채광방법의 주크로스갱도 및 연층갱도의 연결구조가 도시된 구성도이다.
도 6은 본 발명의 일 실시예에 따른 연약 암반층에 층서적으로 부존하는 광석의 채광방법의 지보재가 도시된 구성도이다.
도 7은 본 발명의 일 실시예에 따른 연약 암반층에 층서적으로 부존하는 광석의 채광방법의 골격갱도의 지보재가 도시된 구성도이다.
도 8은 본 발명의 일 실시예에 따른 연약 암반층에 층서적으로 부존하는 광석의 채광방법에 의해 개설된 갱도구조가 도시된 도면이다.
도 9는 본 발명의 일 실시예에 따른 연약 암반층에 층서적으로 부존하는 광석의 채광방법에 사용되는 운반차량이 도시된 도면이다.
도 10은 본 발명의 일 실시예에 따른 연약 암반층에 층서적으로 부존하는 광석의 채광방법의 채굴장비 및 채광장비가 도시된 도면이다.
도 11은 본 발명의 일 실시예에 따른 연약 암반층에 층서적으로 부존하는 광석의 채광방법의 채광블록이 도시된 도면이다.
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a flowchart showing a mining method of ores present in layers in a soft rock layer (hereinafter referred to as a submerged zone) according to an embodiment of the present invention. FIG.
FIG. 2 is a block diagram showing a tunnel structure for implementing a mining method of ores existing in a layered structure on a soft rock layer according to an embodiment of the present invention.
FIG. 3 is a view showing a tunnel of a mining method of ores existing in a layered form on a soft rock layer according to an embodiment of the present invention.
FIG. 4 is a view showing a connection structure between a soft tunnel and a produced cross tunnel of a mining method of ores present in a soft rock layer according to an embodiment of the present invention.
FIG. 5 is a view showing a connection structure of a main cross tunnel and a masonry tunnel of a mining method of ores present in a layered structure on a soft rock layer according to an embodiment of the present invention.
FIG. 6 is a block diagram showing a support of a mining method of ores in a layered form on a soft rock layer according to an embodiment of the present invention.
FIG. 7 is a block diagram showing a support of a skeletal tunnel of a mining method for ores present in a layered structure on a soft rock layer according to an embodiment of the present invention.
FIG. 8 is a view showing a tunnel structure formed by a mining method of an ore existing as a layer book on a soft rock layer according to an embodiment of the present invention.
FIG. 9 is a view showing a transportation vehicle used in a mining method of ores existing in layers on a soft rock layer according to an embodiment of the present invention.
FIG. 10 is a view showing mining equipment and mining equipment of a mining method of ores existing in a layered form on a soft rock layer according to an embodiment of the present invention.
FIG. 11 is a view showing a mining block of a mining method of an ore existing as a layer book on a soft rock layer according to an embodiment of the present invention. FIG.

이하, 첨부된 도면들을 참조하여 본 발명에 따른 연약 암반층에 층서적으로 부존하는 광석과 재채굴 방법의 일 실시예를 설명한다.DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, an embodiment of a method for ore and re-mining of a soft rock layer according to the present invention will be described with reference to the accompanying drawings.

이러한 과정에서 도면에 도시된 선들의 두께나 구성요소의 크기 등은 설명의 명료성과 편의상 과장되게 도시되어 있을 수 있다.In this process, the thicknesses of the lines and the sizes of the components shown in the drawings may be exaggerated for clarity and convenience of explanation.

또한, 후술되는 용어들은 본 발명에서의 기능을 고려하여 정의된 용어들로써, 이는 사용자, 운용자의 의도 또는 관례에 따라 달라질 수 있다.In addition, the terms described below are terms defined in consideration of the functions of the present invention, which may vary depending on the intention or custom of the user, the operator.

그러므로 이러한 용어들에 대한 정의는 본 명세서 전반에 걸친 내용을 토대로 내려져야 할 것이다.
Therefore, definitions of these terms should be made based on the contents throughout this specification.

도 1은 본 발명의 일 실시예에 따른 연약 암반층에 층서적으로 부존하는 광석의 채광방법이 도시된 순서도이고, 도 2는 본 발명의 일 실시예에 따른 연약 암반층에 층서적으로 부존하는 광석의 채광방법을 구현하는 갱도구조가 도시된 구성도이고, 도 3은 본 발명의 일 실시예에 따른 연약 암반층에 층서적으로 부존하는 광석의 채광방법의 갱도가 도시된 구성도이다.FIG. 1 is a flow chart illustrating a method of mining ore in a layered form on a soft rock layer according to an embodiment of the present invention. FIG. 2 is a flow chart illustrating a method of mining ore in a soft rock layer according to an embodiment of the present invention. FIG. 3 is a view showing a tunnel of a mining method of ores existing in a layered structure on a soft rock layer according to an embodiment of the present invention. FIG.

또한, 도 4는 본 발명의 일 실시예에 따른 연약 암반층에 층서적으로 부존하는 광석의 채광방법의 연층갱도 및 생산크로스갱도의 연결구조가 도시된 구성도이고, 도 5는 본 발명의 일 실시예에 따른 연약 암반층에 층서적으로 부존하는 광석의 채광방법의 주크로스갱도 및 연층갱도의 연결구조가 도시된 구성도이고, 도 6은 본 발명의 일 실시예에 따른 연약 암반층에 층서적으로 부존하는 광석의 채광방법의 지보재가 도시된 구성도이다.FIG. 4 is a schematic view showing a connection structure between a soft tunnel and a produced cross tunnel of a mining method of ores present in a soft rock layer according to an embodiment of the present invention, and FIG. 5 is a cross- FIG. 6 is a schematic view showing a connection structure of a main cross tunnel and a multi-layer tunnel in a mining method of an ore existing in a layered form on a soft rock layer according to an example, and FIG. 6 is a cross-sectional view of a soft rock layer according to an embodiment of the present invention. Fig. 2 is a schematic view showing the support of the mining method of the ore.

또한, 도 7은 본 발명의 일 실시예에 따른 연약 암반층에 층서적으로 부존하는 광석의 채광방법의 골격갱도의 지보재가 도시된 구성도이고, 도 8은 본 발명의 일 실시예에 따른 연약 암반층에 층서적으로 부존하는 광석의 채광방법에 의해 개설된 갱도구조가 도시된 도면이고, 도 9는 본 발명의 일 실시예에 따른 연약 암반층에 층서적으로 부존하는 광석의 채광방법에 사용되는 운반차량이 도시된 도면이다.FIG. 7 is a schematic view showing a supporting member of a skeletal tunnel of a mining method of ores existing in a layered structure on a soft rock layer according to an embodiment of the present invention, and FIG. 8 is a cross- FIG. 9 is a view showing a tunnel structure formed by a mining method of ores existing in the form of a layer book on a soft rock layer according to an embodiment of the present invention. Fig.

또한, 도 10은 본 발명의 일 실시예에 따른 연약 암반층에 층서적으로 부존하는 광석의 채광방법의 채굴장비 및 채광장비가 도시된 도면이고, 도 11은 본 발명의 일 실시예에 따른 연약 암반층에 층서적으로 부존하는 광석의 채광방법의 채광블록이 도시된 도면이다.10 is a view showing a mining equipment and a mining equipment of a mining method of ores existing in a layered form on a soft rock layer according to an embodiment of the present invention, and FIG. 11 is a cross- Fig. 2 is a view showing a mining block of a method of mining ore that is present in the form of a layer book.

도 1 내지 도 11을 참조하면, 본 발명의 일 실시 예에 따른 연약 암반층에 층서적으로 부존하는 광석과 재채굴 방법은, 유효 광물성분이 농집된 채광대상광체가 미고결상태 또는 쇄설성상태이고 층서적으로 수평 또는 경사지게 부존하는 지하 광물자원을 개발하는 채광방법에서, 채광대상광체를 포함하는 광물층의 하부에 위치되고 일정치 이상의 고결도를 갖춰 안정성을 유지하는 암반 지층에 일정 형태와 규격을 갖는 골격갱도(10)를 굴착하는 단계와, 골격갱도(10)로부터 채광대상광체의 경사방향으로 완경사의 주크로스갱도(30)를 굴착하는 단계와, 주크로스갱도(30)로부터 채광대상광체를 4분할 채광블록으로 구분하여 맥중에 연층방향으로 연층갱도(50)를 굴착하는 단계와, 연층갱도(50)로부터 4분할된 각각의 구획에 채광을 위한 다수 개의 생산크로스갱도(70)를 맥중 경사방향으로 굴착하는 단계와, 생산크로스갱도(70)의 좌우측 광맥을 일정한 규격으로 단위 채광구역을 구획하고 최종 막장에서부터 연층갱도(50)로 후퇴하면서 주크로스갱도(30)에서 채광이 마무리되도록 광석을 채굴하는 단계와, 채광작업에 의해 채굴된 광석을 골격갱도(10)를 통해 운반수단을 이용해 지상으로 이동하는 단계를 포함한다.Referring to FIGS. 1 to 11, the ore and re-mining method in the form of a layer on the soft rock layer according to an embodiment of the present invention is characterized in that the mining object to be mined, in which the effective mineral component is concentrated, In a mining method that develops horizontal or inclined underground mineral resources as a book, it has a certain shape and size in a rock layer which is located at the lower part of the mineral layer including the mining object and maintains stability with a high degree of certainty Excavating the skeleton tunnels (10), excavating the main cross tunnel (30) of mild slope from the skeletal tunnel (10) in an oblique direction of the object to be mined, A step of excavating the multi-layered tunnel 50 in the direction of the middle layer into a plurality of subdivided mining blocks; Drilling the tunnel 70 in a slanting direction in the core; dividing the unit light mining areas of the left and right veins of the production cross tunnel 70 into a predetermined size and retracting from the final screening site to the middle tunnel 50, Mining the ore so that the mining is finished, and moving the ore mined by the mining operation to the ground by using the conveying means through the skeletal tunnel 10.

채광대상광체를 포함하는 광물층의 고결도가 일정치 보다 낮은 경우에는 광물층을 직접 굴착하여 갱도를 형성하면서 채광을 행하는 기존의 채광법으로 채광작업을 행하면 광물층이 붕락되는 안전사고가 발생될 수 있기 때문에 본 실시예는 광물층 하부에 일정치 이상의 고결도를 갖춰 안정성이 유지되는 지층에 골격갱도(10)를 굴착하여 채광작업을 개시한다.If the degree of high integrity of the mineral layer containing the minerals subject to mining is lower than a certain value, if the mining operation is performed by the existing mining method in which minerals are directly excavated to form a tunnel, minerals may collapse The present embodiment initiates the mining operation by excavating the skeletal tunnel 10 to a stratum having a high degree of stability higher than a predetermined value and maintaining stability under the mineral layer.

골격갱도(10)를 굴착하는 단계(S10)의 골격갱도(10)는 아치형 또는 장방형으로 광석 운반차량이 통행 가능한 정도의 규격으로 굴착하고, 갱도 바닥면의 경사는 갱내부의 자연 배수가 가능하도록 1도 내지 2도의 경사로 굴착한다.The skeletal tunnel 10 in the step S10 of excavating the skeletal tunnel 10 is arched or rectangular and is excavated to the extent that the ore-carrying vehicle can pass, and the slope of the tunnel bottom surface is drilled 1 Or two degrees of inclination.

광물층 하부에 위치되고 층서상으로 가장 안정적인 지층에 지면으로부터 완만한 경사를 이루도록 갱도를 굴착하여 안정된 지층을 따라 골격갱도(10)를 굴착한다.The skeletal tunnel 10 is excavated along a stable stratum by excavating the tunnel to a gentle slope from the ground to the most stable strata located below the mineral layer.

여기서, 통기홀부 및 배수홀부는 갱도와 지표 사이에 시공되는 연통홀부(84)에 의해 이루어지며, 송풍기 또는 양수기 등이 설치되어 강제통풍 및 강제배수가 이루어지게 된다.Here, the vent hole portion and the drain hole portion are formed by a communication hole portion 84 that is formed between the tunnel and the ground, and a blower or a water pump is installed to perform forced ventilation and forced drainage.

골격갱도(10)는 무지보 상태 또는 최소의 지보부재(80)를 설치하고 부분적으로 단층 등 지질구조적인 취약부에 제한적인 쇼크리트를 타설하거나 실링작업을 실시하여 채광작업을 종료할 때까지 골격갱도(10)의 안정상태를 유지시킨다.The skeletal tunnel 10 is installed in an uninhabited state or with a minimum support member 80 and is installed in the skeletal tunnel 10 until the completion of the mining operation by placing a shocking or sealing operation restricted to a vulnerable part, (10).

주크로스갱도(30)를 굴착하는 단계의 주크로스갱도(30)는, 채광대상광체의 부존 부위에 따라 복수 개의 갱도로 개설할 수 있고, 주요 분기점에는 작업용 차량이나 장비의 회전이 가능한 반경의 공간부를 갖도록 굴착한다.The main cross tunnel 30 in the stage of excavating the main cross tunnel 30 can be formed by a plurality of tunnels in accordance with the existing portion of the mining object body. Excavate to have a part.

또한, 주크로스갱도(30)에서 분기되는 연층갱도(50)의 분기점에도 작업장비의 회전이 가능한 반경의 공간부를 형성한다.In addition, a space having a radius capable of rotating the work equipment is formed at a branch point of the multi-layer tunnel 50 branching from the main cross tunnel 30.

따라서 작업장비가 채광작업을 위해 갱도로 진입하거나 채광 후에 광석을 수납하여 갱도 외부로 이동될 때에 갱도와 갱도 사이의 연결부위가 작업장비와 간섭되는 것을 방지할 수 있게 된다.Therefore, when the work equipment enters the tunnel for mining or after the mining, the ore is received and moved outside the tunnel, the connection between the tunnel and the tunnel can be prevented from interfering with the work equipment.

주크로스갱도(30)를 굴착하는 단계(S30)는, 광물층 중에 채광대상광체가 구비되는 부위를 복수 개의 채광대상블록으로 설정하고, 골격갱도(10)로부터 각각의 채광대상블록까지 주크로스갱도(30)를 굴착하고, 주크로스갱도(30)의 내벽에는 필요할 경우 복수 개의 지보부재(80)를 설치하여 이루어질 수 있다.The step (S30) of excavating the main cross tunnel 30 is performed by setting a site where a mining object body is provided in the mineral layer as a plurality of object blocks to be mined, And a plurality of support members 80 may be provided on the inner wall of the main cross tunnel 30, if necessary.

채광대상블록은 골격갱도(10)에서 약50m 간격으로 선진천공을 상향 약8도 정도로 시공하여 채광대상광체의 주향 및 경사방향의 연속성과 광황을 확인하고, 이 결과에 근거하여 적정한 크기의 채광대상블록의 범위를 결정하게 된다.The block to be mined is constructed with an advanced perforation of approximately 8 degrees at an interval of about 50 m in the skeletal tunnel (10) to confirm continuity and lightness in the direction of inclination and inclination of the object to be mined. Based on this result, The range of the block is determined.

채광대상블록의 크기는 최대 약 120×100m로 하는데, 이는 각각의 채광대상블록 내부의 채광작업이 약30일 이내에 완료될 수 있는 크기로 결정하여야 하기 때문이다.The size of the block to be mined is at most about 120 x 100 m because the mining operation within each mining object block should be determined so as to be completed within about 30 days.

본 실시예의 주크로스갱도(30)는 골격갱도(10)로부터 약8도 이내의 상향 경사를 유지하도록 굴착되고, 비교적 소형의 굴삭장비에 의해 주크로스갱도(30)의 굴착이 이루어지게 된다.The main cross tunnel 30 of the present embodiment is excavated so as to maintain an upward inclination within about 8 degrees from the skeleton tunnel 10 and excavation of the main cross tunnel 30 is performed by a relatively small excavation equipment.

여기서, 골격갱도(10)의 굴착방향은 불가피한 경우를 제외하고는 광맥의 주향을 유지하며 굴착방향의 변경이 불가피한 경우에는 필수적으로 선진천공 시공결과를 적용하여 굴착하고, 회전반경이 비교적 크게 굴착한다.Here, the excavation direction of the skeleton tunnel 10 is maintained except for the case where the excavation direction of the skeleton tunnel 10 is inevitable, and when the excavation direction is inevitable to change, the excavation direction is necessarily applied by the advanced boring construction result, and the turning radius is relatively large .

골격갱도(10)의 굴착장비로는 갱도 규격에 적합한 굴착장비를 사용하는 것이 바람직하며, 파암의 적재부분인 Gathering Machine의 마모 손상을 개선한 굴착장치를 사용하는 것이 바람직하다.As the excavation equipment of the skeleton tunnel 10, it is preferable to use excavation equipment suited to the tunnel standard, and it is preferable to use the excavation equipment which improves the wear damage of the gathering machine, which is the loading part of the wave rock.

본 실시예의 골격갱도(10) 및 주크로스갱도(30)의 굴착법은 자유단면 기계굴착공법으로 굴착되며, 이는 최소 3.8×2.8m부터 최대 4.5×3.0m까지 굴착단면 형상을 아치형이나 장방형으로 설계하고, 취약 암반에 봉착할 경우 굴착 막장면 안정 보조공법인 Forepoling 또는 Mini Pipe 타설하여 지지하고, 굴착단면을 자유롭게 굴착할 수 있는 굴착장비를 사용하여 굴착작업을 행한다.The excavation method of the skeletal tunnel 10 and the main cross tunnel 30 of this embodiment is excavated by a free cross-sectional mechanical excavation method, in which an excavated cross-sectional shape from an at least 3.8 × 2.8 m to a maximum 4.5 × 3.0 m is designed in an arcuate shape or a rectangular shape And when it is seated on a vulnerable rock, it supports the excavation front surface stabilization assistant corporation Forepoling or Mini Pipe, and performs the excavation work using the excavation equipment which can freely excavate the excavation section.

골격갱도(10)는 광물층과 이루는 고저차가 최소 약8m이상을 유지하도록 굴착하고, 골격갱도(10)의 경사각은 광물층을 따라 가급적 수평굴진하여 굴착 진행방향은 주향방향을 유지하며, 통기전용 골격갱도(10)의 굴착방향은 광물층의 경사방향으로 굴착하고 통기계통 확립을 위해 지상으로 관통되도록 시공한다.The skeletal tunnel 10 is excavated so that the height difference between the skeletal tunnel 10 and the mineral layer is maintained to be at least about 8 m or more. The inclination angle of the skeletal tunnel 10 is pushed horizontally along the mineral layer as much as possible, The excavation direction of the skeletal tunnel 10 is constructed such that it is excavated in the direction of inclination of the mineral layer and penetrates to the ground for establishing a ventilation system.

또한, 골격갱도(10)는 100m 간격을 유지하며 3개 이상의 골격갱도(10)를 동시에 굴착하여 골격갱도(10) 굴착에 소요되는 시간을 감소시킬 수 있게 한다.In addition, the skeletal tunnel 10 maintains an interval of 100 m and simultaneously excavates three or more skeletal tunnels 10 to reduce the time required for skeletal tunnel 10 excavation.

주크로스갱도(30)의 규격은 골격갱도(10)와 같이 최소 3.8×2.8m부터 최대 4.5×3.0m로 굴착하며, 경사각은 최대 8도 이내로 유지되도록 굴착한다.The size of the main cross tunnel 30 is excavated from a minimum of 3.8 x 2.8 m to a maximum of 4.5 x 3.0 m as in the skeletal tunnel 10, and the inclination angle is excluded so as to be within a maximum of 8 degrees.

주크로스갱도(30)의 형상은 응력집중에 효과적으로 대처할 수 있는 아치형으로 굴착하며, 필요 구간에의 지보부재(80)는 가급적 강재지보를 실시하고, 반팽현상을 방지하기 위해 리벳을 설치할 수도 있다.The shape of the main cross tunnel 30 is arch-shaped so as to effectively cope with the stress concentration. The support member 80 in the required section may be provided with a steel support as much as possible, and a rivet may be installed to prevent the reinforcement.

골격갱도(10)와 골격갱도(10) 사이에는 동일한 규격의 연락갱도를 연결하고, 연락갱도 설치 간격은 약 300m를 유지하며, 굴착 진행방향에 대한 선진천공으로 단층 및 불연속면 등 지질구조, 암질 및 암반상태를 확인하여 굴착방향을 결정한다.There is a connection tunnel of the same size between the skeletal tunnel (10) and the skeletal tunnel (10). The distance between the connection tunnel and the skeleton tunnel is about 300m. The advanced hole for the direction of the excavation leads to the geological structure such as fault and discontinuity, Determine the excavation direction by checking the rock condition.

채광대상블록의 크기는 최대 약120×100m이내로 하여 하나의 채광대상블록에서 이루어지는 채광작업이 약30일 이내에 종료될 수 있도록 하고, 1개의 골격갱도(10) 길이는 약1km 정도로 설계하는 것이 바람직하다.It is preferable that the mining target block is within a maximum size of about 120 x 100 m so that the mining operation in one mining object block can be completed within about 30 days and the length of one skeleton tunnel 10 is designed to be about 1 km .

연층갱도(50)를 굴착하는 단계(S50)는, 아치형의 갱도를 굴착하여 연층갱도(50)를 이루고, 연층갱도(50)의 내벽에는 복수 개의 지보부재(80)를 설치하며, 지보부재(80)의 천반에는 마감패널(82)을 설치하여 이루어진다.A step S50 of excavating the masonry tunnel 50 is performed by excavating an arcuate tunnel to form a masonry tunnel 50. A plurality of mover members 80 are installed on the inner wall of the masonry tunnel 50, 80) is provided with a finishing panel (82).

연층갱도(50)는 주크로스갱도(30)의 단부로부터 좌우로 굴착하고, 굴착규격은 약 3.8×2.8m로 결정하고, 맥중에 좌우 연층방향으로 수평굴진하며 길이는 약57m로 굴진하여 이루어지고, 필요 구간에 지보를 행하는 지보부재(80) 및 마감패널(82)을 설치한다.The masonry tunnel 50 is excavated to the left and right from the end of the main cross tunnel 30 and the drilling standard is determined to be about 3.8 x 2.8 m and is pushed horizontally in the direction of the right and left soft layers and pivoted to about 57 m in length , A support member (80) and a finishing panel (82) for supporting the required section are provided.

생산크로스갱도(70)를 굴착하는 단계(S40)는, 연층갱도(50)로부터 수직 또는 경사방향으로 아치형의 갱도를 굴착하여 생산크로스갱도(70)를 이루고, 생산크로스갱도(70)의 내벽에 복수 개의 지보부재(80)를 설치하며, 지보부재(80)의 천반에는 마감패널(82)을 설치하여 이루어진다.The step (S40) of excavating the production cross tunnel 70 is performed by excavating an arcuate tunnel in the vertical or inclined direction from the stratum tunnels 50 to form the production cross tunnel 70, A plurality of support members (80) are provided, and a finishing panel (82) is provided on the top of the support member (80).

생산크로스갱도(70)는 맥중 연층갱도(50) 상의 20m 간격으로 맥중 경사방향으로 굴착되어 이루어지고, 갱도 굴착단면의 규격은 약 3.8×2.8m로 결정하여 굴착한다.The production cross tunnel 70 is excavated in the incline direction in the direction of the incline 20m on the gritway 50 in the vein, and the specimen of the tunnel excavation section is determined to be about 3.8 x 2.8 m and excavated.

생산크로스갱도(70)의 길이는 약47m로 하고, 경사는 광맥을 따라 약3~5도 경사굴진하며 필요 구간에 지보를 행하도록 지보부재(80) 및 마감패널(82)을 설치한다.The length of the production cross tunnel 70 is about 47 m, and the inclination is inclined and pivoted about 3 to 5 degrees along the vein, and the support member 80 and the finishing panel 82 are installed to support the required section.

상기한 바와 같이 갱도에는 그 주변의 암질, 반압 등에 대응하여 강재, 목재, 락볼트 또는 쇼크리트로 이루어지는 지보수단 중 선택된 어느 하나의 지보재를 시행하고, 지보재 사이에는 목재, 강판, 와이어메쉬 중 선택된 어느 하나의 방법으로 쏠장이나 절장을 실시하며, 지보재의 저부에는 반팽에 대응하는 인버터를 설치한다.As described above, any one of the support members selected from among steel, wood, rock bolt, or shock support means corresponding to the surrounding rock quality, semi-pressure, and the like is installed in the tunnel, and any one selected from among wood, steel plate, And the inverter corresponding to the slag is installed at the bottom of the support material.

지보부재 중 연층갱도(50) 및 생산크로스갱도(70)에서는 광석 채굴 후 갱도의 천반이 자연 붕락되도록 원칙적으로 회수하므로 생산크로스갱도(70)는 채광작업이 종료되면 지보부재(80) 및 마감패널(82)을 원칙적으로 회수하여 자연 붕락을 유도하여 붕락된 상태로 방치한다.The production cross tunnel 70 is basically recovered so that the tunnel of the tunnel is naturally collapsed after the ore mining in the stratum grove 50 and the production cross tunnel 70 in the support member, (82) is recovered in principle to induce natural collapse and left in a collapsed state.

채광대상광체를 채광하는 단계(S50)는, 작업장에는 채광작업 종료시 까지는 천반부 침하나 붕락을 방지하기 위해 Forepoling이나 Mini pipe roof 등을 설치하여 생산크로스갱도(70)의 단부로부터 채광작업을 개시하고, 채굴이 완료되는 구역의 지보부재(80) 또는 마감패널(82)은 철거하며 연층갱도(50) 측으로 후퇴하면서 채광작업을 행한다.In step S50 of mining the mining target mining object, a mining operation is started from the end of the production cross mine 70 by installing a fore-poling or a mini pipe roof to prevent collapse, , The support member 80 or the finishing panel 82 in the area where the mining is completed is demolished and retracted to the side of the masonry tunnel 50 to perform the mining operation.

본 실시예는 광획 주방식 채광법을 행하여 생산크로스갱도(70)로부터 채광작업을 행하고, 생산크로스갱도(70)와 생산크로스갱도 사이에 형성되는 채광대상블록을 작업자의 1교대 근무시간 내에 채광작업이 완료될 수 있는 규격 15.0×13.8m~8.0×4.0m로 결정한다.In this embodiment, the mining operation is performed from the production cross tunnel 70 by performing the mining operation in the mining mode, and the mining target block formed between the production cross tunnel 70 and the production cross tunnel is mined within one working hour of the operator It is determined that the standard to be completed is 15.0 x 13.8 m to 8.0 x 4.0 m.

채광작업은 생산크로스갱도(70)의 단부로부터 연층갱도(50) 측으로 후퇴하면서 채광작업을 실시하고, 단위 채광블록의 중앙에 위치하는 주크로스갱도(30)에서 최종 채광작업을 마무리한다.The mining operation is performed while retreating from the end of the production cross tunnel 70 to the side of the masonry tunnel 50 and finishing the final mining operation in the main cross tunnel 30 located at the center of the unit mining block.

최소 채광블록 작업장 내에서는 채굴작업의 안전성 확보를 위해 간이지보재를 활용하고 철수 시에 지보부재(80) 및 마감패널(82)을 회수하여 재활용한다.In the mining block workshop, the support material (80) and the finishing panel (82) are collected and recycled at the time of withdrawal in order to secure the safety of the mining work.

지보부재(80)는, H빔 또는 I빔을 아치형으로 굴곡시켜 이루어지며, 복수 개의 H빔 또는 I빔을 일정한 간격을 유지하도록 시공하여 이루어진다.The support member 80 is formed by bending an H beam or an I beam into an arcuate shape, and is constructed so as to maintain a plurality of H beams or I beams at a constant interval.

지보부재(80)는 H빔, I빔 또는 강관을 2개의 부재로 제작하여 현장까지 운반한 후에 간격이 1.0m로 유지되게 배치시키고, 상부 접합부 조립은 양쪽에 2개의 볼트로 고정하며 바닥면 반팽예방을 위해서는 인버트를 설치한다.The support member 80 is made of two members such as an H beam, an I beam, or a steel pipe. The support member 80 is disposed so as to maintain a distance of 1.0 m after being transported to the site. The upper joint assembly is fixed with two bolts on both sides, Install Invert for prevention.

지보부재(80)의 간격을 유지하기 위해 H빔 또는 I빔의 적정위치에 4개의 절장을 설치하고 이의 고정을 위해 보통철선으로 고정한다.In order to maintain the spacing of the support members 80, four trails are provided at appropriate positions of the H beam or the I beam and fixed with a wire usually for fixing the same.

지보부재(80)를 설치한 후에 마감패널(82)을 전체에 시공하고, 마감패널(82) 대신에 와이어메시를 시공할 수도 있다.After the support member 80 is installed, the finishing panel 82 may be entirely installed, and a wire mesh may be formed instead of the finishing panel 82.

마감패널(82)은, 한 쌍의 지보부재(80) 사이의 간격을 마감하도록 복수 개가 연속되게 배치되는 목재패널 또는 철재패널을 포함한다.The finishing panel 82 includes a wood panel or a steel panel in which a plurality of consecutively arranged wood panels or finishing panels 80 are arranged to close the gap between the pair of support members 80. [

상기한 바와 같은 지보부재(80) 및 마감패널(82)에 의한 강재지보법 외에 쇼크리트를 갱도 내벽에 타설하는 강재지보법이 적용될 수도 있으며, 이는 본 발명의 기술구성을 인지한 작업자가 용이하게 변경하여 실시할 수 있는 것이므로 구체적인 설명은 생략하기로 한다.A steel material holding method for placing a shock slit on the inner wall of a tunnel may be applied in addition to the steel material holding method using the sprinkler member 80 and the finishing panel 82 as described above. And the detailed description thereof will be omitted.

또한, 골격갱도(10)에는 갱도 내의 통기를 위하여 지상과 관통되는 1개 이상의 통기갱도가 더 구비되고, 갱내 지하수가 모여 저장되는 복수 의 저수조가 구비된다.Also, the skeletal tunnel 10 is provided with one or more ventilating passages penetrating the ground for ventilating in the tunnel, and a plurality of water storage tanks in which mineground groundwater is collected and stored.

따라서 골격갱도(10) 내부의 산소공급을 행하여 작업자의 호흡곤란을 방지할 수 있고, 갱도 내의 지하수가 저수조를 통해 배출될 수 있도록 한다.Therefore, oxygen supply to the inside of the skeleton tunnel 10 is performed to prevent dyspnea of the operator, and groundwater in the tunnel can be discharged through the water tank.

또한, 연층갱도(50)와 생산크로스갱도(70)가 연결되는 곳에는 해당구역 광체를 전부 채광하기 전까지는 맥중 연층갱도(50)의 안정을 위해 적정 규모의 광맥을 필라로 잔치한다.In addition, where the multi-level tunnel 50 and the production cross tunnel 70 are connected, a pillar of a suitable scale is feasted for stabilization of the multi-layered tunnels 50 until the zone optical body is fully mined.

따라서 채광대상광체를 채광하는 단계(S50)는, 연층갱도(50)의 단부에서 연장되는 생산크로스갱도(70)에서부터 채광작업을 시작하고, 주크로스갱도(30) 측으로 후퇴하면서 채광작업을 진행하며, 연층갱도(50)와 생산크로스갱도(70)의 연결부위에는 필라를 설치하고, 채광작업이 종료되는 생산크로스갱도(70)에서 지보부재(80)를 회수하면서 채광을 행하게 된다.Therefore, the step of mining the mining object (S50) starts mining work from the production cross mine 70 extending from the end of the masonry tunnel 50, retreats toward the main cross mine 30, A pillar is provided at a connection portion between the masonry tunnel 50 and the production cross tunnel 70 and mining is performed while recovering the support member 80 from the production cross tunnel 70 where the mining operation is completed.

또한, 채광대상광체를 채광하는 단계(S50)는, 채광작업을 종료하여 주크로스갱도(30)를 따라 후퇴할 때에 주크로스갱도(30)에 설치된 지보부재(80) 중 가능한 지보부재(80)를 회수하여 주크로스갱도(30)의 천반이 붕락되도록 유도한다.The step S50 of mining the mining object includes the steps of grasping the possible support member 80 among the support members 80 provided on the main cross tunnel 30 when the mining operation is finished and retreated along the main cross mine 30, Thereby guiding the top of the main cross tunnel 30 to collapse.

또한, 채광대상광체를 채광하는 단계(S50)는, 최소 단위 채광구역은 1교대 근무시간 내에 채광이 완료될 수 있는 적정 규모로 구획하여 채광이 이루어지교 교대 근무가 이루어지기 전에 작업장비가 생산크로스갱도(70)를 빠져나올 수 있도록 한다.In addition, the step of mining the mining object (S50) is performed such that the minimum unit mining area is divided into a proper scale for completion of mining within one shift working time, So that it can escape from the tunnel 70.

광석을 운반하는 장비는 채광이 이루어지는 작업장까지 골격갱도(10), 주크로스갱도(30), 연층갱도(50) 및 생산크로스갱도(70)를 통해 이동하고, 채광이 완료된 후에는 상기한 갱도의 역순으로 갱도 외부로 이동하게 된다.The ore transporting equipment moves through the skeletal tunnel 10, the main cross tunnel 30, the quaternary tunnel 50 and the production cross tunnel 70 to the worksite where the mining takes place, and after the mining is completed, And moves to the outside of the tunnel in the reverse order.

골격갱도(10) 또는 주크로스갱도(30)는, 복수 개의 돌출부(124)가 스크루 모양으로 연속되게 배치되는 파쇄부(122)를 구비하는 굴착장비(120)의 구동에 의해 굴착작업이 이루어지고, 연층갱도(50) 또는 생산크로스갱도(70)는, 유압진동리퍼(132) 또는 원뿔형면삭기가 설치되는 굴삭장치(130)에 의해 굴진되고, 채광대상광체를 채광하는 단계(S50)는, 유압진동리퍼(132) 또는 원뿔형면삭기가 설치되는 굴삭장치(130)에 의해 채광대상광체를 채광하여 운반차량(110)에 의해 생산크로스갱도(70), 연층갱도(50), 주크로스갱도(30) 및 골격갱도(10)를 따라 지상으로 이송되고, 운반차량(110)은, 동력을 제공하는 구동부(112)와, 구동부(112)에 힌지부(114)에 의해 회전 가능하게 연결되고 채광대상광체가 수납되는 수납부(116)를 포함한다.The skeletal tunnel 10 or the main cross tunnel 30 is excavated by driving the excavation equipment 120 having the crushing portion 122 in which a plurality of projections 124 are continuously arranged in a screw shape The sidewall tunnel 50 or the production cross tunnel 70 is pushed by the hydraulic vibration ripper 132 or the excavator 130 provided with the conical type grounding machine and the step S50 of mining the mining object is performed by the hydraulic pressure The excavating device 130 is provided with a vibration ripper 132 or a conical type grounding machine and the mining object is mined by the conveying vehicle 110 so that the production cross tunnel 70, the soft tunnel 50, the main cross tunnel 30, And the skeleton tunnel 10 and the conveying vehicle 110 includes a driving part 112 for providing power and a hinge part 114 rotatably connected to the driving part 112 by a hinge part 114, (Not shown).

굴착장비(120), 굴삭장비(130) 및 운송차량(110)은 골격갱도(10), 주크로스갱도(30), 연층갱도(50) 및 생산크로스갱도(70)의 유효단면적 내의 작업성 및 기동성을 고려하여 선정한다.The excavation equipment 120, the excavating equipment 130 and the transportation vehicle 110 are designed to operate within the effective cross-sectional area of the skeletal tunnel 10, the main cross tunnel 30, the quaternary tunnel 50 and the production cross tunnel 70, It is selected in consideration of maneuverability.

골격갱도(10) 및 주크로스갱도(30)의 굴착장비(120)는, 소형의 굴착장비인 로드헤더를 사용하며, 운반차량(110)으로는 약 20톤의 적재량을 구비하는 Mine Truck 또는 연속운반시설을 사용하고, LM30SS를 선진시추기(140)를 사용하여 지반상태를 사전에 확인한다.The excavating equipment 120 of the skeletal tunnel 10 and the main cross tunnel 30 uses a load header which is a small excavating equipment and the conveying vehicle 110 is a mine truck having a load of about 20 tons, Use the transport facility and check the ground condition in advance using the advanced drilling rig (140) of the LM30SS.

연층갱도(50) 및 생산크로스갱도(70)의 굴착장비(120)는 진동 Ripper를 사용하고, 적재장비는 L.H.D(3.2m2)를 사용하고, 운반차량(110)은 Mine Truck(20톤)을 사용한다.The excavating equipment 120 of the masonry tunnel 50 and the production cross tunnel 70 use vibration rippers, the loading equipment uses LHD (3.2 m 2 ), the conveying vehicle 110 uses Mine Truck (20 tons) Lt; / RTI >

Mine Truck으로 이루어지는 운반차량(110)은 구동부(112)와 수납부(116)가 힌지부(114)에 의해 회전 가능하게 연결되므로 생산크로스갱도(70), 연층갱도(50), 주크로스갱도(30) 및 골격갱도(10)의 굴곡부위를 통과할 때에 갱도의 내벽과 운반차량(110)이 간섭되는 것을 방지할 수 있게 된다.The conveying vehicle 110 made of Mine Truck is constructed such that the driving section 112 and the receiving section 116 are rotatably connected by the hinge section 114 so that the production cross tunnel 70, the soft tunnel 50, 30 and the skeletal tunnel 10 from interfering with the inner wall of the tunnel and the transportation vehicle 110 when passing through the curved portion of the skeletal tunnel 10.

이로써, 채광대상광체가 부존하는 미고결상태 또는 파쇄상태 지층 보다 하부에 위치되고 일정치 이상의 고결도를 갖춰 안정성이 있는 지층을 통하여 채광대상광체를 채광하는 연약 암반층에 층서적으로 부존하는 광석의 채광방법을 제공할 수 있게 된다.
As a result, it is possible to provide a method of mining ore ores that are present in a layered form on a soft rock layer which is located below the crushed or ground state layer where the object to be mined is present and which has a high degree of solidity, Method.

본 발명은 도면에 도시되는 일 실시예를 참고로 하여 설명되었으나, 이는 예시적인 것에 불과하며, 당해 기술이 속하는 분야에서 통상의 지식을 가진 자라면 이로부터 다양한 변형 및 균등한 타 실시예가 가능하다는 점을 이해할 것이다.While the present invention has been particularly shown and described with reference to exemplary embodiments thereof, it is to be understood that the invention is not limited to the disclosed embodiments, but, on the contrary, is intended to cover various modifications and equivalent arrangements included within the spirit and scope of the appended claims. .

또한, 연약 암반층에 층서적으로 부존하는 광석의 채광방법을 예로 들어 설명하였으나, 이는 예시적인 것에 불과하며, 연약 암반층에 층서적으로 부존하는 광석의 채광방법이 아닌 다른 지층에 부존하는 광물의 채굴에도 본 발명의 채광방법이 사용될 수 있다.In addition, although the method of mining the ore existing in a layered form on the soft rock layer has been described as an example, this is merely an illustrative example, and the method of mining the minerals existing in the strata other than the mining method of the ore, The mining method of the present invention can be used.

따라서 본 발명의 진정한 기술적 보호범위는 아래의 특허청구범위에 의해서 정하여져야 할 것이다.
Accordingly, the true scope of the present invention should be determined by the following claims.

10 : 골격갱도 30 : 주크로스갱도
50 : 연층갱도 70 : 생산크로스갱도
80 : 지보부재 82 : 마감패널
84 : 연통홀부
10: Skeleton Tunnel 30: Main Cross Tunnel
50: Yeongcheon tunnel 70: Production cross tunnel
80: Support member 82: Finishing panel
84: communicating hole portion

Claims (13)

유효 광물성분이 농집된 채광대상광체가 미고결상태 또는 쇄설성상태이고 층서적으로 수평 또는 경사지게 연약 암반층에 부존하는 지하 광물자원을 개발하는 채광방법에 있어서,
(a) 채광대상광체를 포함하는 광물층의 하부에 위치되되 일정치 이상의 고결도를 갖춰 안정성을 유지하는 암반 지층에 일정 형태와 규격을 갖는 골격갱도를 굴착하는 단계;
(b) 상기 골격갱도로부터 상기 채광대상광체의 경사방향으로 완경사의 주크로스갱도를 굴착하는 단계;
(c) 상기 주크로스갱도로부터 상기 채광대상광체를 4분할 채광블록으로 구분하여 맥중에 연층방향으로 연층갱도를 굴착하는 단계; 및
(d) 상기 연층갱도로부터 4분할된 각각의 구획에 채광을 위한 다수 개의 생산크로스갱도를 맥중 경사방향으로 굴착하는 단계;
(e) 상기 생산크로스갱도의 좌우측 광맥을 일정한 규격으로 단위 채광구역을 구획하고 최종 막장에서부터 상기 연층갱도로 후퇴하면서 상기 주크로스갱도에서 채광이 마무리되도록 광석을 채굴하는 단계; 및
(f) 상기 채광작업에 의해 채굴된 광석을 상기 골격갱도를 통해 운반수단을 이용해 지상으로 이동하는 단계를 포함하는 것을 특징으로 하는 연약 암반층에 층서적으로 부존하는 광석의 채광방법.
A mining method for developing an underground mineral resource present in a soft rock layer in a state in which a mining object to be mined with an effective mineral component is unconsolidated or clinker and is horizontally or inclined with a layer book,
(a) excavating a skeleton tunnel having a certain shape and size in a rock layer which is positioned below a mineral layer including a mining object and which has high degree of solidification with a certain degree or more and maintains stability;
(b) excavating the main cross tunnel of the mild slope from the skeletal tunnel in an oblique direction of the object body to be exposed;
(c) dividing the object-to-be-mined object into four quad-mining blocks from the main cross tunnel to excavate the multi-layered tunnel in the direction of the middle layer; And
(d) excavating a plurality of production cross tunnels for mining in the slanting direction in the respective subdivisions of the quaternary tunnel;
(e) mining the ore so as to finish the mining in the main crossing tunnel while dividing the unit mining area into the standard mining area of the production cross gutter to a predetermined size and retracting from the final screening area to the multi-layered mining area; And
(f) moving the ore mined by the mining operation to the ground via the skeletal tunnel by using a conveying means.
제1항에 있어서,
상기 (a)의 단계에서, 상기 골격갱도는 아치형 또는 장방형으로 광석 운반차량이 통행 가능한 정도의 규격으로 굴착하고, 갱도 바닥면의 경사는 갱내부의 자연 배수가 가능하도록 1도 내지 2도의 경사로 굴착하는 것을 특징으로 하는 연약 암반층에 층서적으로 부존하는 광석의 채광방법.
The method according to claim 1,
In the step (a), the skeletal tunnel is excavated at a slope of 1 to 2 degrees such that the skeleton tunnel is arched or rectangular, and the slope of the tunnel bottom is excavated by natural drainage, Wherein the ore is present in the form of a layer on a soft rock layer.
제1항에 있어서,
상기 (b) 단계의 주크로스갱도는, 상기 채광대상광체의 부존 부위에 따라 복수 개의 갱도로 개설할 수 있고, 주요 분기점에는 작업용 차량이나 장비의 회전이 가능한 반경의 공간부를 갖도록 굴착하는 것을 특징으로 하는 연약 암반층에 층서적으로 부존하는 광석의 채광방법.
The method according to claim 1,
The main cross tunnel of the step (b) may be formed by a plurality of tunnels according to an existing portion of the object to be lighted, and excavated to have a space for a work vehicle or a radius capable of rotating equipment. A method of mining ores present in layers on a soft rock layer.
제1항에 있어서,
상기 (c) 단계의 주크로스갱도에서 분기되는 상기 연층갱도의 분기점에는 작업장비의 회전이 가능한 반경의 공간부를 형성하는 것을 특징으로 하는 연약 암반층에 층서적으로 부존하는 광석의 채광방법.
The method according to claim 1,
The method for mining ore as claimed in claim 1, wherein a space having a radius capable of rotating the working equipment is formed at a branch point of the multi-layered tunnel which branches off from the main cross tunnel in the step (c).
제1항에 있어서,
각각의 갱도에는 그 주변의 암질, 반압 등에 대응하여 강재, 목재, 락볼트 또는 쇼크리트로 이루어지는 지보수단 중 선택된 어느 하나의 지보재를 시행하고, 상기 지보재 사이에는 목재, 강판, 와이어메쉬 중 선택된 어느 하나의 방법으로 절장을 실시하며, 상기 지보재의 저부에는 반팽에 대응하는 인버터를 설치하는 것을 특징으로 하는 연약 암반층에 층서적으로 부존하는 광석의 채광방법.
The method according to claim 1,
Each of the tunnels is provided with one support selected from among steel, wood, rock bolt, or shock support corresponding to the surrounding rock quality, semi-pressure, etc., and any one selected from among wood, steel plate, and wire mesh , And an inverter corresponding to the slag is installed at the bottom of the support material. The method for mining ores of ores present in a layered form on a soft rock layer.
제5항에 있어서,
상기 지보재 중 상기 연층갱도 및 상기 생산크로스갱도에서는 광석 채굴 후 갱도의 천반이 자연 붕락되도록 원칙적으로 회수하는 것을 특징으로 하는 연약 암반층에 층서적으로 부존하는 광석의 채광방법.
6. The method of claim 5,
The method of mining ore as claimed in claim 1 or 2, wherein, in the manganese gangue and the production cross gangue, the manganese is recovered after mining of the ore in principle.
제1항에 있어서,
상기 (e) 단계에서 작업장에는 채광작업 종료시 까지는 천반부 침하나 붕락을 방지하기 위해 Forepoling이나 Mini pipe roof 등을 설치하는 것을 특징으로 하는 연약 암반층에 층서적으로 부존하는 광석의 채광방법.
The method according to claim 1,
The method of claim 1, wherein in the step (e), a fore-polling or a mini-pipe roof is installed to prevent collapse of the work site until the finishing work is completed.
제1항에 있어서,
상기 골격갱도에는 갱도 내의 통기를 위하여 지상과 관통되는 1개 이상의 통기갱도가 더 구비되는 것을 특징으로 하는 연약 암반층에 층서적으로 부존하는 광석의 채광방법.
The method according to claim 1,
Wherein the skeletal tunnel further comprises at least one ventilating tunnel penetrating the ground for venting in the tunnel.
제1항에 있어서,
상기 골격갱도에는 갱내 지하수가 모여 저장되는 복수 의 저수조가 구비되는 것을 특징으로 하는 연약 암반층에 층서적으로 부존하는 광석의 채광방법.
The method according to claim 1,
Wherein the skeletal tunnel is provided with a plurality of water storage tanks for collecting and storing mine underground water.
제7항에 있어서,
상기 연층갱도와 상기 생산크로스갱도가 연결되는 곳에는 해당구역 광체를 전부 채광하기 전까지는 맥중 상기 연층갱도의 안정을 위해 적정 규모의 광맥을 필라로 잔치하는 것을 특징으로 하는 연약 암반층에 층서적으로 부존하는 광석의 채광방법.
8. The method of claim 7,
Characterized in that, at a place where the above-mentioned multi-layered tunnels are connected to the above-mentioned production cross-tunnels, a suitable vein is floated on the pillars in order to stabilize the above-mentioned multi- The mining method of the ore.
제1항에 있어서,
상기 (e) 단계에서 단위 채광구역운 1교대 근무시간 내에 채광이 완료될 수 있는 적정 규모로 구획하는 것을 특징으로 하는 연약 암반층에 층서적으로 부존하는 광석의 채광방법.
The method according to claim 1,
The method for mining ore as claimed in claim 1, wherein in the step (e), the mining operation is divided into an appropriate scale so that mining can be completed within a unit working hour.
제1항에 있어서,
광석을 운반하는 장비는 채광이 이루어지는 작업장까지 상기 골격갱도, 상기 주크로스갱도, 상기 연층갱도 및 상기 생산크로스갱도를 통해 이동하는 것을 특징으로 하는 연약 암반층에 층서적으로 부존하는 광석의 채광방법.
The method according to claim 1,
Wherein the equipment for conveying the ore moves through the skeletal tunnel, the main cross tunnel, the quarry tunnel and the production cross tunnel to a work site where mining is performed.
제1항에 있어서,
상기 골격갱도 또는 상기 주크로스갱도는, 복수 개의 돌출부가 스크루 모양으로 연속되게 배치되는 파쇄부를 구비하는 굴착장비의 구동에 의해 굴진작업이 이루어지고,
상기 연층갱도 또는 상기 생산크로스갱도는, 유압진동리퍼 또는 원뿔형면삭기가 설치되는 굴삭장비에 의해 굴진되며,
상기 (e) 단계는, 상기 유압진동리퍼 또는 원뿔형면삭기가 설치되는 굴삭기에 의해 채광대상광체를 채광하여 운반차량에 의해 상기 생산크로스갱도, 상기 연층갱도, 상기 주크로스갱도 및 상기 골격갱도를 따라 지상으로 이송되고,
상기 운반차량은, 동력을 제공하는 구동부와, 상기 구동부에 힌지부에 의해 회전 가능하게 연결되고 채광대상광체가 수납되는 수납부를 포함하는 것을 특징으로 하는 연약 암반층에 층서적으로 부존하는 광석의 채광방법.
The method according to claim 1,
Wherein the skeleton tunnel or the main cross tunnel is pivoted by driving a drilling rig having a crushing portion in which a plurality of projections are continuously arranged in a screw shape,
The masonry tunnel or the production cross tunnel is pivoted by a digging equipment provided with a hydraulic vibration ripper or a conical grounding machine,
Wherein the step (e) comprises the steps of: mining the object to be mined by the excavator provided with the hydraulic vibration ripper or the conical type grounding machine, and moving the excavated object by the conveying vehicle along the production cross tunnel, Lt; / RTI >
Wherein the conveying vehicle includes a driving unit that provides power and a receiving unit that is rotatably connected to the driving unit by a hinge and accommodates a mining object to be mined. .
KR1020140150283A 2014-10-31 2014-10-31 Mining method for stratigraphic ore in soft rock KR101518471B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020140150283A KR101518471B1 (en) 2014-10-31 2014-10-31 Mining method for stratigraphic ore in soft rock

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020140150283A KR101518471B1 (en) 2014-10-31 2014-10-31 Mining method for stratigraphic ore in soft rock

Publications (1)

Publication Number Publication Date
KR101518471B1 true KR101518471B1 (en) 2015-05-15

Family

ID=53394134

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020140150283A KR101518471B1 (en) 2014-10-31 2014-10-31 Mining method for stratigraphic ore in soft rock

Country Status (1)

Country Link
KR (1) KR101518471B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116104538A (en) * 2023-03-16 2023-05-12 山东省地质矿产勘查开发局第五地质大队(山东省第五地质矿产勘查院) Goaf rapid stabilization method based on mining area stratum stability investigation

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR810002028B1 (en) * 1978-02-06 1981-12-15 H Roye Radial mining method
KR870003288A (en) * 1985-09-20 1987-04-16 야노스 나기, 로란드 데즈제리 Mining method of sudden mineral layer and its device
JPH06323089A (en) * 1992-10-02 1994-11-22 Friedrich W Paurat Tunnel excavating method and tunnel excavator for carrying out said method
KR20060040621A (en) * 2006-04-05 2006-05-10 (주)성풍건설 The construction method excavating underground plaza

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR810002028B1 (en) * 1978-02-06 1981-12-15 H Roye Radial mining method
KR870003288A (en) * 1985-09-20 1987-04-16 야노스 나기, 로란드 데즈제리 Mining method of sudden mineral layer and its device
JPH06323089A (en) * 1992-10-02 1994-11-22 Friedrich W Paurat Tunnel excavating method and tunnel excavator for carrying out said method
KR20060040621A (en) * 2006-04-05 2006-05-10 (주)성풍건설 The construction method excavating underground plaza

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116104538A (en) * 2023-03-16 2023-05-12 山东省地质矿产勘查开发局第五地质大队(山东省第五地质矿产勘查院) Goaf rapid stabilization method based on mining area stratum stability investigation
CN116104538B (en) * 2023-03-16 2023-10-10 山东省地质矿产勘查开发局第五地质大队(山东省第五地质矿产勘查院) Goaf rapid stabilization method based on mining area stratum stability investigation

Similar Documents

Publication Publication Date Title
US5782539A (en) Wall-to-wall surface mining process
CA2929663C (en) Mining method
US6857706B2 (en) Mining method for steeply dipping ore bodies
CN104790956B (en) It is remotely controlled roadway formula exploitation end and helps coal technique
CN103742149A (en) Method for re-mining residual floor coal in fully-mechanized top coal caving face
CN106150508B (en) A kind of tunnel drilling operation method in karst strata
RU2344291C2 (en) System of deposit development
CN112610218B (en) Thick coal seam fully-mechanized top-tunneling top-cutting pressure relief automatic roadway forming method
CN105888664A (en) Mining method for extremely-thick hard coal
CN108952725B (en) Low dilution mining method suitable for gentle dip thin ore body
US20130127231A1 (en) Hydraulic Mining System for Tabular Orebodies Utilising Directional Drilling
KR101518471B1 (en) Mining method for stratigraphic ore in soft rock
Bustillo Revuelta et al. Mineral resource extraction
RU2733759C1 (en) Open-underground method of development of stratified deposits of minerals
RU2295037C1 (en) Method for extracting thick inclined coal formation by column-chambers
Zou et al. Mechanical Underground Excavation in Rock
Markov et al. Application and improvement of technologies for underground mining of placer deposits in Yakutia
CN109403972A (en) Sublevel open stoping afterwards filling mining method
RU2425216C1 (en) Complex development method of bed series of anticline deposits
Webber et al. Review of mechanization within Lonmin
Matsui et al. Highwall stability due to punch mining at opencut coal mines
Sunuwar Challenges of shaft excavation in Nepal Himalaya: case study from hydropower projects
Team Burton highwall challenge
Wynne Case study management of outburst risk at Tahmoor colliery
Starcevich et al. Construction of the SR-99 recovery shaft.

Legal Events

Date Code Title Description
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20190329

Year of fee payment: 5