KR101452381B1 - Construction method for underground structure - Google Patents

Construction method for underground structure Download PDF

Info

Publication number
KR101452381B1
KR101452381B1 KR1020130044483A KR20130044483A KR101452381B1 KR 101452381 B1 KR101452381 B1 KR 101452381B1 KR 1020130044483 A KR1020130044483 A KR 1020130044483A KR 20130044483 A KR20130044483 A KR 20130044483A KR 101452381 B1 KR101452381 B1 KR 101452381B1
Authority
KR
South Korea
Prior art keywords
slab
reinforcement
plate
underground
concrete
Prior art date
Application number
KR1020130044483A
Other languages
Korean (ko)
Inventor
윤동현
Original Assignee
윤동현
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 윤동현 filed Critical 윤동현
Priority to KR1020130044483A priority Critical patent/KR101452381B1/en
Application granted granted Critical
Publication of KR101452381B1 publication Critical patent/KR101452381B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0258Retaining or protecting walls characterised by constructional features
    • E02D29/0275Retaining or protecting walls characterised by constructional features cast in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/03Prefabricated parts, e.g. composite sheet piles
    • E02D5/04Prefabricated parts, e.g. composite sheet piles made of steel
    • E02D5/06Fitted piles or other elements specially adapted for closing gaps between two sheet piles or between two walls of sheet piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0007Production methods using a mold
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete

Abstract

The present invention relates to a method for constructing underground structure comprising: a step for boring to form a perforation hole (10) on the ground; a step for inserting a boring extension member (100) to extend by inserting the boring extension member (100) into the perforation hole (10); a step for installing the boring extension member (100); a step for supporting a soil blocking plate; a step for removing the boring extension member (100) to remove the boring extension member (100); a step for assembling a reinforcement assembly to form the reinforcement assembly (200); a step for inserting the reinforcement assembly; a step for removing a front soil blocking plate to remove the front soil blocking plate (110); a step for placing concrete wall; a step for removing a first-floor reinforcement plate forming exposed steel bar wall (220a); a step for installing a slab form coupling with the exposed steel bar wall (220a); and a step for placing slab concrete.

Description

지중 구조물 시공방법{CONSTRUCTION METHOD FOR UNDERGROUND STRUCTURE}{CONSTRUCTION METHOD FOR UNDERGROUND STRUCTURE}
본 발명은 토목 분야에 관한 것으로서, 상세하게는 지중 구조물의 시공방법에 관한 것이다.Field of the Invention [0002] The present invention relates to a civil engineering field, and more particularly, to a method of constructing an underground structure.
도심의 한복판 건설현장에서 지하의 흙더미는 퍼 올려져있고, 그 자리에 H-BEAM과 I-BEAM 등이 설치되어 있으며, 상부 쪽 1층 바닥 높이쯤에는 복공판이 깔려있는 것을 볼 수 있는데, 이는 지중 구조물의 시공을 하기 위해 설치해 놓은 임시 시설물이다. At the center of the city center, underground dirt is pumped up, H-BEAM and I-BEAM are installed on the floor, and a floorboard is laid on the floor above the first floor. It is a provisional facility that is installed to construct the structure.
또한 복공판이 깔려있는 도로를 시민들은 버스를 타고 지나간다든지 혹은 승용차를 몰고 지나간다든지 하는 경험도 가졌을 것인데, 이 역시 지하철로, 지하도로, 지하차고, 지하상가 등의 공사를 하기 위해 지하작업을 하는 동안, 시민들은 어쩔 수 없이 불편을 인내할 수밖에 없는 임시 시설물이다. In addition, citizens would have had the experience of passing through a bus or a passenger car, which is also underground, underground, underground garage, underground shopping mall, etc. , Citizens are temporary facilities that can not but be forced to endure discomfort.
즉, 지금까지 지하작업을 하기 위해서는 토류판 공법이나 CIP 공법으로 흙막이 공사를 하면서 지하 흙을 먼저 파내고, 흙막이의 보강작업으로 H-BEAM과 I-BEAM 등으로 가리짱을 만들면서, 상부 쪽에는 복공판을 덮는 작업을 필수적으로 해왔다. In other words, in order to carry out the underground work up to now, it is necessary to dig out underground soil while carrying out soil works by using earth plate method or CIP method, and to make girders with H-BEAM and I-BEAM by reinforcing earth retaining, Has been essential.
그리고 지하의 바닥과 벽체작업을 해오면서 상기 H-BEAM과 I-BEAM 등을 아래서부터 상부로 반대의 순서로 해체해 가는 작업을 하고, 마지막에 1층 바닥을 만들게 된다. In addition, I work on the floor and walls of the underground and work on disassembling the H-BEAM and I-BEAM from the bottom to the top in the opposite order, and finally I will make the first floor.
그러니까 지금까지는 상기 임시로 사용하기 위한 복공판과 그 아래에 있는 H-BEAM과 I-BEAM을 설치하고, 또 해체해야만 하는 작업이 필수적이었지만, 이는 소모성 작업으로 여기에 들어간 기간과 비용이 정작 지하층의 바닥과 벽체를 만들기 위한 기간과 비용보다 오히려 더 많이 필요했고, 특히 CIP공법에서 흙막이로 사용하기 위해 만들었던 기둥들도 벽체 정도에 버금가는 비용이 들지만, 벽체가 만들어지고 나면 벽체의 뒤에 서있을 뿐 아무 쓸모가 없는 등 문제를 안고 있다.So far, it has been necessary to install and temporarily dismantle the H-BEAM and I-BEAM below, but this is a consuming operation, and the period and the cost of the operation are actually lower And the cost of building the wall is much more than the cost and the cost. Especially, the pillars that were made for civil engineering works in CIP process cost just as much as the wall, but once the wall is built, it stands at the back of the wall and is useless There are problems such as lack of.
본 발명은 상기와 같은 문제점을 해결하기 위하여 도출된 것으로서, 시공이 간편하고, 시공의 시간 및 비용을 줄일 수 있도록 하는 지중 구조물 시공방법을 제시하는 것을 그 목적으로 한다.SUMMARY OF THE INVENTION It is an object of the present invention to provide a method of constructing an underground structure that is simple in construction and can reduce time and cost of construction.
상기 과제의 해결을 위하여, 본 발명은 지반에 천공 홀(10)을 형성하는 천공단계; 양측에 각각 전면 흙막이판(110) 및 후면 흙막이판(120)이 착탈가능하게 결합함과 아울러, 상기 전면 흙막이판(110) 및 후면 흙막이판(120)의 하단은 상호 일정거리를 유지하도록 형성된 천공 홀 확공부재(100)를 상기 천공 홀(10)에 삽입하여 확공하는 천공 홀 확공부재 삽입단계; 상기 천공단계 및 천공 홀 확공부재 삽입단계를 측방으로 반복하여, 다수의 상기 천공 홀 확공부재(100)가 열지어 설치되도록 하는 천공 홀 확공부재 설치단계; 상기 전면 흙막이판(110)의 상단은 전방으로 지지하고, 상기 후면 흙막이판(120)의 상단은 후방으로 지지하는 흙막이판 지지단계; 상기 전면 흙막이판(110) 및 후면 흙막이판(120)은 상기 천공 홀(10)에 삽입된 상태에서, 상기 천공 홀 확공부재(100)를 제거하는 천공 홀 확공부재 제거단계; 복수의 배근판(210)에 벽체 철근(220,230,240)을 조립하여 배근조립체(200)를 형성하는 배근조립체 조립단계; 상기 전면 흙막이판(110) 및 후면 흙막이판(120)의 사이에 상기 배근조립체(200)를 삽입하되, 상기 복수의 배근판(210)이 상하방향 적층구조로서 상기 전면 흙막이판(110)의 위치에 오도록 하는 배근조립체 삽입단계; 상기 전면 흙막이판(110)을 제거하는 전면 흙막이판 제거단계; 상기 후면 흙막이판(120)과 상기 배근판(210)의 사이 영역에 콘크리트를 타설하여 벽체(W)를 형성하는 벽체 콘크리트 타설단계; 상기 복수의 배근판(210) 중 1층 슬래브 설치위치의 배근판(210a1)을 제거하고, 상기 벽체 철근(220,230,240)의 일부를 노출시켜 노출된 벽체 철근(220a)을 형성하는 1층 배근판 제거단계; 상기 벽체(W)의 사이 영역의 지반 위에 1층 슬래브 거푸집(21)을 설치하고, 1층 슬래브 철근(310)을 배근하되, 상기 노출된 벽체 철근(220a)과 결합하는 슬래브 거푸집 설치단계; 상기 1층 슬래브 거푸집(21)에 콘크리트를 타설하여 1층 슬래브(S1)를 형성하는 슬래브 콘크리트 타설단계;를 포함하는 것을 특징으로 하는 지중 구조물 시공방법을 제시한다.In order to solve the above-described problems, the present invention provides a method of drilling a hole in a ground; The front and rear flooring panels 110 and 120 are detachably coupled to both sides of the front and rear flooring panels 110 and 120, Inserting a hole drilling material (100) into the hole (10) to insert the hole drilling material (100); A perforation hole lengthening step of repeating the perforating step and the perforation hole louver inserting step sideways so that a plurality of the perforation hole louver 100 are installed to be installed; Supporting the upper end of the front securing plate 110 forward and supporting the upper end of the rear securing plate 120 rearward; Removing the perforated hole lengthening material 100 from the front sheathing plate 110 and the rear sheeting plate 120 when the perforated hole louver 100 is inserted into the perforation hole 10; An assembling step of assembling the reinforcing assembly (200) by assembling the reinforcing bars (220, 230, 240) to the plurality of reinforcement plates (210); Wherein the plurality of reinforcement plates 210 are installed in a vertical stacked structure between the front and rear flooring plates 110 and 120 so that the position of the front flooring plate 110 In the step of inserting the assembly; Removing the front earth retaining plate (110); A concrete concrete casting step of casting concrete in an area between the rear retaining plate 120 and the reinforcement plate 210 to form a wall W; Removing a reinforcement plate 210a1 at one slab installation position of one of the plurality of reinforcement plates 210 and removing a first reinforcement plate 220a forming a exposed wall reinforcement 220a by exposing a part of the wall reinforcement 220, step; A slab form setting step of providing a one-layer slab formwork 21 on the ground in the area between the walls W and joining the exposed slab reinforcement 310 with the exposed wall reinforcing bar 220a; And a slab concrete pouring step of pouring concrete into the single-layer slab former 21 to form a single-ply slab S1.
상기 슬래브 콘크리트 타설단계 이후, 상기 1층 슬래브(S1)의 하부를 굴착하고, 상기 슬래브 거푸집을 제거하는 굴착단계; 상기 복수의 배근판(210) 중 지하 1층 슬래브 설치위치의 배근판(210a2)을 제거하고, 상기 벽체 철근(220,230,240)의 일부를 노출시켜 노출된 벽체 철근(220a)을 형성하는 지하 1층 배근판 제거단계; 상기 벽체(W)의 사이 영역의 지하지반 위에 지하 1층 슬래브 거푸집(22)을 설치하고, 지하 1층 슬래브 철근(320)을 배근하되, 상기 노출된 벽체 철근(220a)과 결합하는 지하 1층 슬래브 거푸집 설치단계; 상기 지하 1층 슬래브 거푸집(22)에 콘크리트를 타설하여 지하 1층 슬래브(SB1)를 형성하는 슬래브 콘크리트 타설단계;를 포함하는 것이 바람직하다.A drilling step of excavating a lower portion of the one-story slab S1 and removing the slab former after the slab concrete pouring step; A reinforcement plate 210a2 of a first underground slab installation position of the plurality of reinforcement plates 210 is removed and a part of the underground reinforcement 220a is exposed by exposing a part of the reinforcement bars 220, A plate removing step; A slab form 22 of a basement is installed on an underground floor of an area between the walls W and a slab reinforcement 320 of a basement is installed, A slab form setting step; And a slab concrete pouring step of pouring concrete into the underground one-storey slab form 22 to form a one-storey underground slab SB1.
상기 슬래브 거푸집 설치단계 이전, 상기 벽체(W)의 사이 영역에 지중기둥(C)을 형성하는 지중기둥 형성단계;를 더 포함하고, 상기 슬래브 거푸집 설치단계는, 상기 1층 슬래브 철근(310)을 배근하되 상기 지중기둥(C)의 상부에 노출된 기둥 철근(330)과 결합하는 것이 바람직하다.And forming a ground column (C) in an area between the walls (W) before the step of installing the slab formwork, wherein the step of installing the slab former comprises: It is preferable to join the pillar reinforcement 330 exposed at the top of the underground column C.
상기 슬래브 거푸집 설치단계 이전, 상기 벽체(W)의 사이 영역에 보를 형성하는 보 형성단계;를 더 포함하고, 상기 슬래브 거푸집 설치단계는, 상기 1층 슬래브 철근(310)을 배근하되 상기 보의 상부에 노출된 보 철근과 결합하는 것이 바람직하다.And a beam forming step of forming a beam in an area between the walls W before the step of installing the slab formwork, wherein the step of installing the slab formwork is a step of placing the single-layer slab reinforced concrete structure 310, Is preferably combined with the exposed reinforcing bars.
상기 천공 홀 확공부재(100)는 H 빔(130); 타 천공 홀 확공부재(100a)의 H 빔(130a)과 결합하도록, 상기 H 빔(130)의 플랜지 및 웹의 내부 영역에 결합하는 "ㄷ"자형 결합부재(140);를 포함하는 것이 바람직하다.The perforation hole lumen 100 may include an H beam 130; Shaped engaging member 140 that engages with the flange of the H beam 130 and the inner region of the web so as to engage with the H beam 130a of the other perforated hole reaming member 100a Do.
상기 전면 흙막이판(110) 및 후면 흙막이판(120)의 상단은 상기 H 빔(130)의 웹을 관통하여 결합하는 흙막이판 결합구(131)에 의해 결합하고, 상기 전면 흙막이판(110) 및 후면 흙막이판(120)의 하단에는 이중머리 볼트 삽입홈(112,122)이 형성되며, 상기 전면 흙막이판(110) 및 후면 흙막이판(120)의 하단은 상호 일정거리를 유지하도록 상기 이중머리 볼트 삽입홈(112,122)에 삽입된 이중머리 볼트(160)에 의해 지지되는 것이 바람직하다.The upper ends of the front seat cladding plate 110 and the rear seat climbing plate 120 are coupled by a seat closure plate coupling hole 131 through which the web of the H beam 130 is coupled, The double bottom head bolt insertion grooves 112 and 122 are formed at a lower end of the rear earth retaining plate 120 and the lower ends of the front earth retaining plate 110 and the rear earth retaining plate 120 are fixed to the double head bolt insertion groove 112, Are preferably supported by the double head bolts (160) inserted into the first and second bolts (112, 122).
상기 H 빔(130)의 웹 하단에는 상기 이중머리 볼트(160)에 걸리도록 이중머리 볼트 걸림홈(132)이 형성된 것이 바람직하다.And a double head bolt receiving groove 132 is formed at the lower end of the web of the H beam 130 so as to be caught by the double head bolt 160.
상기 배근조립체(200)는 상기 배근판(210)에 연직방향으로 결합한 복수의 폭방향 철근(220); 상기 복수의 폭방향 철근(220)에 깊이방향으로 결합한 복수의 깊이방향 철근(230); 상기 복수의 폭방향 철근(220)에 길이방향으로 결합한 복수의 길이방향 철근(240);을 포함하는 것이 바람직하다.The reinforcing assembly 200 includes a plurality of transverse reinforcing bars 220 coupled to the reinforcing plate 210 in a vertical direction. A plurality of depth direction reinforcing bars 230 coupled to the plurality of width direction reinforcing bars 220 in the depth direction; And a plurality of longitudinal reinforcing bars 240 longitudinally coupled to the plurality of width reinforcing bars 220.
상기 폭방향 철근(220)은 상기 후면 흙막이판(120)과의 간격유지를 위하여, 단부가 상기 후면 흙막이판(120)에 접촉하도록 설치된 간격유지철근(221)을 포함하는 것이 바람직하다.The width direction reinforcement 220 may include a spacing reinforcing bar 221 provided at an end thereof to contact the rear securing plate 120 to maintain a gap with the rear securing plate 120.
상기 배근판(210)은 상하방향 적층구조로 설치되는 복수의 철판(210a,210b); 상기 복수의 철판(210a,210b)의 결합부위에 덧대기 이음을 위해 결합하는 덧대기 철판(211);을 포함하고, 상기 복수의 철판(210a,210b)은 상기 보 또는 상기 슬래브와의 결합부위를 선택적으로 제거할 수 있도록 설치하는 것이 바람직하다.The reinforcement plate 210 includes a plurality of iron plates 210a and 210b installed in a vertically stacked structure; And a plurality of steel plates (210a, 210b) joined to the joining portions of the plurality of steel plates (210a, 210b) It is preferable to install the apparatus in such a manner that it can be selectively removed.
상기 길이방향 철근(240)의 단부에는, 타 배근조립체(200a)의 길이방향 철근(240a)의 단부와 끼움결합하도록 절곡구조의 끼움결합부(250)가 형성된 것이 바람직하다.The end portion of the longitudinal reinforcing bar 240 may be formed with a fitting portion 250 having a bent structure to fit into the end portion of the longitudinal reinforcing bar 240a of the other reinforcing assembly 200a.
상기 끼움결합부(250)는 상기 길이방향 철근(240)의 일단에서 내측으로 절곡되어 형성된 내향 끼움결합부(251); 상기 길이방향 철근(240)의 타단에서 외측으로 절곡되어 형성된 외향 끼움결합부(252);를 포함하는 것이 바람직하다.The fitting portion 250 includes an inward fitting portion 251 bent inward from one end of the longitudinal reinforcing bar 240; And an outwardly engaging portion 252 formed outwardly from the other end of the longitudinal reinforcing bar 240.
상기 길이방향 철근(240)은 상호 대칭구조로 형성된 한 쌍의 길이방향 철근(240a,240b)을 포함하는 것이 바람직하다.The longitudinal reinforcing bars 240 may include a pair of longitudinal reinforcing bars 240a and 240b formed in an inter-symmetrical structure.
상기 복수의 길이방향 철근(240)의 끼움결합부(250)에는 깊이방향을 따라 슬라이딩판(253)이 결합한 것이 바람직하다.And a sliding plate 253 is coupled to the fitting part 250 of the plurality of longitudinal bars 240 along the depth direction.
본 발명은 시공이 간편하고, 시공의 시간 및 비용을 줄일 수 있으며, 특히 도로 밑을 굴착해야 할 경우에는 시민들의 불편을 최소화할 수 있어서, 시공성 및 구조적 안정성이 우수한 지중 구조물 시공방법을 제시한다.The present invention provides a method of constructing an underground structure having excellent workability and structural stability because it is easy to construct, can reduce the time and cost of construction, and can minimize the inconvenience of citizens when excavating under the road.
도 1 이하는 본 발명의 실시예를 도시한 것으로서,
도 1은 천공 홀 확공부재의 사시도.
도 2는 천공 홀 확공부재의 평면도.
도 3은 흙막이판의 부분사시도.
도 4는 H 빔의 측면도.
도 5는 이중머리 볼트의 사시도.
도 6은 천공 홀 확공부재의 단면도.
도 7은 천공 홀 확공부재의 부분사시도.
도 8은 천공 홀 확공부재 삽입단계의 공정도.
도 9,10은 천공 홀 확공부재 제거단계의 공정도.
도 11은 배근조립체의 사시도.
도 12는 배근조립체의 측면도.
도 13은 길이방향 철근의 평면도.
도 14는 배근조립체 삽입단계의 공정도.
도 15는 콘크리트 타설단계의 공정도.
도 16은 배근판 제거단계의 공정도.
도 17,18은 1층 슬래브 설치단계의 공정도.
도 19,20은 지하 1층 슬래브 설치단계의 공정도.
도 21,22는 지중기둥 형성단계의 공정도.
1 shows an embodiment of the present invention,
1 is a perspective view of a perforation hole expanding member.
2 is a plan view of the perforation hole expanding member.
Figure 3 is a partial perspective view of the cladding board.
4 is a side view of an H beam.
5 is a perspective view of a double head bolt.
6 is a sectional view of the perforation hole expanding member.
7 is a partial perspective view of the perforation hole expanding member.
8 is a process chart of the step of inserting the perforation hole lengthening material.
FIGS. 9 and 10 are a process chart of the step of removing the perforation hole expanding material.
11 is a perspective view of an assembly.
12 is a side view of the assembly.
13 is a plan view of a longitudinal reinforcing bar;
Fig. 14 is a process chart of a step of inserting an assembly. Fig.
15 is a process chart of the concrete pouring step.
16 is a process chart of the step of removing the reinforcement plate.
17 and 18 are a process chart of a single-layer slab installing step.
19 and 20 are a process chart of a step of installing a slab underground.
21 and 22 are a process chart of the underground column forming step.
이하, 첨부도면을 참조하여 본 발명의 실시예에 관하여 상세히 설명한다.Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings.
도 1 이하에 도시된 바와 같이, 본 발명에 의한 지중 구조물 시공방법은 기본적으로, 다음과 같은 공정에 의해 구성된다.As shown in FIG. 1 and subsequent drawings, the method for constructing an underground structure according to the present invention is basically composed of the following steps.
지반에 천공 홀(10)을 형성한다.A perforation hole (10) is formed in the ground.
양측에 각각 전면 흙막이판(110) 및 후면 흙막이판(120)이 착탈가능하게 결합함과 아울러, 전면 흙막이판(110) 및 후면 흙막이판(120)의 하단은 상호 일정거리를 유지하도록 형성된 천공 홀 확공부재(100)를 천공 홀(10)에 삽입하여 확공한다(도 1,2).The front and rear flooring panels 110 and 120 are detachably coupled to both sides of the front and rear flooring panels 120 and 120, And the reaming member 100 is inserted into the perforation hole 10 (Figs. 1 and 2).
오거 등에 의해 원형 단면 구조로 형성된 천공 홀(10)을 천공 홀 확공부재(100), 전면 흙막이판(110) 및 후면 흙막이판(120)에 의해 사각형 단면 구조로 변형시킴과 아울러, 형성된 천공 홀이 추가 천공작업 시 무너지지 않도록 한다.A perforation hole 10 formed in a circular cross section by an auger or the like is deformed into a rectangular sectional structure by the perforation hole lengthening member 100, the front sheeting plate 110 and the rear sheeting plate 120, Do not fall during this additional drilling operation.
이러한 천공단계 및 천공 홀 확공부재 삽입단계를 측방으로 반복하여, 다수의 천공 홀 확공부재(100)가 열지어 설치되도록 한다(도 8).The perforation step and the perforation hole lengthening material inserting step are repeated in the lateral direction so that a plurality of perforated hole louver 100 is installed to be installed (FIG. 8).
전면 흙막이판(110)의 상단은 전방으로 지지하고, 후면 흙막이판(120)의 상단은 후방으로 지지한다(도 9,10).The upper end of the front earth retaining plate 110 is supported at the front side and the upper end of the rear earth retaining plate 120 is supported at the rear side (Figs. 9 and 10).
전면 흙막이판(110) 및 후면 흙막이판(120)의 하단은 상호 일정거리를 유지하도록 결합한 상태이므로, 이들의 상단을 로프(111,121) 및 말뚝(113,123) 등에 의해 외측으로 지지하여, 전면 흙막이판(110)과 후면 흙막이판(120) 사이에 벽체를 형성하기 위한 영역을 확보하는 것이다.The upper ends of the front and rear flooring plates 110 and 120 are coupled to each other so as to maintain a constant distance therebetween and thus the upper ends of the front and rear flooring plates 120 and 121 are supported outwardly by the ropes 111 and 121 and the piles 113 and 123, 110 and the rear retaining plate 120 to secure a region for forming a wall.
전면 흙막이판(110) 및 후면 흙막이판(120)은 천공 홀(10)에 삽입된 상태에서, 천공 홀 확공부재(100)를 제거한다(도 9,10).The front retaining plate 110 and the rear retaining plate 120 are inserted into the perforation hole 10 to remove the perforation hole lengthening member 100 (FIGS. 9 and 10).
복수의 배근판(210)에 벽체 철근(220,230,240)을 조립하여 배근조립체(200)를 형성한다(도 11 내지 13).The reinforcing bars 220, 230 and 240 are assembled to the plurality of reinforcement plates 210 to form the reinforcing assembly 200 (FIGS. 11 to 13).
전면 흙막이판(110) 및 후면 흙막이판(120)의 사이에 배근조립체(200)를 삽입하되, 복수의 배근판(210)이 상하방향 적층구조로서 전면 흙막이판(110)의 위치에 오도록 한다.A plurality of reinforcement plates 210 are placed in a vertical laminated structure at a position of the front earth retaining plate 110 between the front retaining plate 110 and the rear retaining plate 120.
이후, 전면 흙막이판(110)을 제거한다(도 14).Thereafter, the front sheeting board 110 is removed (Fig. 14).
전면 흙막이판(110)을 제거하는 대신, 철근이 조립된 배근판(210)이 전면 흙막이판(110)의 위치에 오도록 하여, 흙막이 및 철근의 설치 역할을 동시에 수행하도록 한 것이다.Instead of removing the front retaining plate 110, the reinforcement plate 210, in which the reinforcing bars are assembled, comes to the position of the front retaining plate 110, so that the retaining plate and the reinforcing bars are simultaneously installed.
후면 흙막이판(120)과 배근판(210)의 사이 영역에 콘크리트를 타설하여 벽체(W)를 형성한다(도 15).Concrete is placed in a region between the rear retaining plate 120 and the reinforcement plate 210 to form a wall W (FIG. 15).
복수의 배근판(210) 중 1층 슬래브 설치위치의 배근판(210a1)을 제거하고, 벽체 철근(220,230,240)의 일부를 노출시킨다(도 16).One of the plurality of reinforcement plates 210 is removed from the reinforcement plate 210a1 of the slab installation position to expose a part of the wall reinforcing bars 220, 230 and 240 (Fig. 16).
벽체 철근의 일부를 노출시키기 위하여, 스티로폼 등의 임시부재를 콘크리트에 매설하는 방식, 타설된 콘크리트의 일부를 쪼아내는 방식 등을 사용하면 된다.In order to expose a part of the wall reinforcement, a method of burying a temporary member such as styrofoam in concrete or a method of peeling a part of the poured concrete may be used.
배근판(210a1)이 덧대기 철판(211)에 의해 지지되는 경우, 덧대기 철판(211)을 먼저 제거한 후 배근판(210a1)을 제거한다.When the reinforcement plate 210a1 is supported by the overlapping iron plate 211, the overlapping iron plate 211 is first removed, and then the reinforcement plate 210a1 is removed.
벽체(W)의 사이 영역의 지반 위에 1층 슬래브 거푸집(21)을 설치하고, 1층 슬래브 철근(310)을 배근하되, 노출된 벽체 철근(220a)과 결합한다(도 17).A one-layer slab formwork 21 is installed on the ground in the area between the walls W to join the slab reinforcement 310 with the exposed wall reinforcement 220a (FIG. 17).
1층 슬래브 거푸집(21)에 콘크리트를 타설하여 1층 슬래브(S1)를 형성한다(도 18).Concrete is placed in the one-story slab form 21 to form a one-storey slab S1 (Fig. 18).
이는 종래와 같이 가시설 흙막이 벽체 및 본 벽체의 이중 시공을 하지 않고, 복공판 등의 가시설도 필요 없으며, 한 번의 지중 벽체 및 슬래브 시공 후 이를 본 구조물로 활용하여 다음 작업을 진행하도록 하는바, 시공이 간편하고, 시공의 시간 및 비용을 대폭 줄일 수 있다는 효과가 있다.This is because it is not necessary to double construction of the temporary earth retaining wall and the main wall as in the past, and there is no need for the construction of the base plate and the like, and once the underground wall and slab are constructed, And the time and cost of construction can be greatly reduced.
더하여 일반 건축물의 지하층을 만드는 외에, 도로 밑을 굴착해서 지하철로, 지하도로, 지하상가, 지하주차장을 만들 경우에도 본 지중 구조물 시공방법을 활용한다면, 지하 흙을 굴착하기 전에 도로를 먼저 만들어서 아스팔트를 깔아버리기 때문에, H-beam과 I-beam을 설치하고, 복공판을 깔 필요가 없는 등 시민들의 불편을 최소화 할 수 있어서, 위 효과를 더욱 크게 얻을 수 있다. In addition to making basement floors of general buildings, if subway underground roads, underground roads, underground shopping malls, and underground parking lots are made by using underground road construction method, it is necessary to make roads before making underground soil, Because it spreads, it is possible to minimize the inconvenience of citizens such as installing H-beam and I-beam, and not needing to install a laminator, so that the above effect can be obtained even more.
1층 슬래브(S1)를 형성한 이후의 공정은 다음과 같다.The process after forming the one-layer slab S1 is as follows.
1층 슬래브(S1)의 하부를 굴착하고, 슬래브 거푸집을 제거한 후, 복수의 배근판(210) 중 지하 1층 슬래브 설치위치의 배근판(210a2)을 제거하고, 벽체 철근(220,230,240)의 일부를 노출시킨다(도 16,19).The lower part of the slab S1 is excavated and the slab form is removed and then the reinforcement plate 210a2 at the slab installation position of the first one of the plurality of reinforcement plates 210 is removed and a part of the reinforcing bars 220, (Figs. 16 and 19).
배근판(210a2)이 덧대기 철판(211)에 의해 지지되는 경우, 덧대기 철판(211)을 먼저 제거한 후 배근판(210a1)을 제거한다.When the reinforcement plate 210a2 is supported by the overlapping iron plate 211, the overlapping iron plate 211 is first removed, and then the reinforcement plate 210a1 is removed.
벽체(W)의 사이 영역의 지하지반 위에 지하 1층 슬래브 거푸집(22)을 설치하고, 지하 1층 슬래브 철근(320)을 배근하되, 노출된 벽체 철근(220a)과 결합한다(도 19).A one-layer slab formwork 22 is installed on the underground of the area between the walls W and the slab reinforcement 320 of the underground one-storey is installed and coupled with the exposed wall reinforcement 220a (FIG. 19).
지하 1층 슬래브 거푸집(22)에 콘크리트를 타설하여 지하 1층 슬래브(SB1)를 형성한다(도 20).Concrete is placed in the slab form 22 of the first basement floor to form a basement one-story slab SB1 (FIG. 20).
이러한 공정의 반복에 의해 지중에 다층구조물을 안정적이고 간편하게 시공할 수 있다.By repeating this process, it is possible to stably and easily construct the multi-layer structure in the ground.
기둥이 필요한 경우에는, 슬래브 거푸집 설치단계 이전, 먼저 벽체(W)의 사이 영역에 지중기둥(C)을 형성하고, 1층 슬래브 철근(310)을 배근 시 지중기둥(C)의 상부에 노출된 기둥 철근(330)과 결합하는 방식으로 기둥과 슬래브를 일체화하면 된다(도 21,22).When a column is required, an underground column C is first formed in the area between the walls W before the slab form installation step, and when the one-story slab reinforcement 310 is placed at the top of the underground column C, The column and the slab may be integrated with each other by coupling with the pillar reinforcement 330 (Figs. 21 and 22).
보가 필요한 경우에는, 슬래브 거푸집 설치단계 이전, 벽체(W)의 사이 영역에 보를 형성하고, 1층 슬래브 철근(310)을 배근 시 보의 상부에 노출된 보 철근과 결합하는 방식으로 보와 슬래브를 일체화한다.If beams are required, a beam is formed in the area between the walls W before the slab form installation step, and the beam and the slab are combined in such a manner that the one-story slab reinforcement 310 is combined with the exposed beam at the top of the beam .
이하, 본 발명에 사용되는 각 부재의 구체적 구조에 관하여 상세히 설명한다.Hereinafter, the specific structure of each member used in the present invention will be described in detail.
천공 홀 확공부재(100)는 전면 흙막이판(110) 및 후면 흙막이판(120)이 H 빔(130)의 플랜지 양단에 각각에 착탈가능하게 결합하는 구조를 취한다(도 1,2).The perforated hole concentrator 100 has a structure in which the front sheer board 110 and the rear sheer board 120 are detachably coupled to both ends of the flange of the H beam 130 (FIGS.
이는 상부에서 볼 때 전체적으로 사각형 구조(날일자 형상)를 형성하게 되므로, 원형 단면의 천공 홀(10)을 사각형 단면의 천공 홀로 확공할 수 있도록 한다.This makes it possible to form the perforated hole 10 having a circular cross section into a perforated hole having a rectangular cross section, since the whole structure has a rectangular structure (blade-like shape) when viewed from above.
천공 홀(10)의 깊이가 깊은 경우에는, 타 천공 홀 확공부재(100a)와의 결합이 필요하며, 이 경우 타 천공 홀 확공부재(100a)의 H 빔(130a)과 결합하도록, H 빔(130)의 플랜지 및 웹의 내부 영역에 결합하는 "ㄷ"자형 결합부재(140)에 의해 복수의 H 빔(130,130a)이 상하방향을 따라 결합한 구조를 취한다(도 7).When the depth of the perforation hole 10 is deep, it is necessary to engage with the perforated hole louver 100a. In this case, the H-beam 130a of the perforated hole louver 100a is combined with the H- And a plurality of H beams 130 and 130a are coupled along the vertical direction by a " C "-shaped engaging member 140 which engages with the flange of the flange 130 and the inner region of the web (FIG.
"ㄷ"자형 결합부재(140)는 복수의 H 빔(130,130a)과 볼트-너트 결합, 용접결합 등의 방식에 의해 결합한다.The "e" shaped engaging member 140 is coupled to the plurality of H beams 130 and 130a by a method of bolt-nut coupling, welding coupling, or the like.
전면 흙막이판(110) 및 후면 흙막이판(120)의 상단은 H 빔(130)의 웹을 관통하여 결합하는 볼트-너트 구조 등에 의한 흙막이판 결합구(131)에 의해 착탈가능하게 결합한다(도 1,2).The upper ends of the front sheeting board 110 and the rear sheeting board 120 are detachably coupled to each other by a securing plate coupling hole 131 formed by a bolt-nut structure or the like that penetrates the web of the H beam 130 1,2).
상술한 바와 같이, 전면 흙막이판(110), 후면 흙막이판(120) 및 천공 홀 확공부재(100)는 그 하단의 간격이 상호 안정적으로 유지되어야 함과 아울러, 순차적으로 상측으로 제거될 수 있는 구조를 취하여야 한다.As described above, the spacing between the lower ends of the front securing plate 110, the rear securing plate 120, and the perforation hole lengthening member 100 must be maintained mutually stably, and at the same time, Structure.
이를 위하여, 전면 흙막이판(110) 및 후면 흙막이판(120)의 하단에는 이중머리 볼트 삽입홈(112,122)이 형성되고, 전면 흙막이판(110) 및 후면 흙막이판(120)의 하단은 상호 일정거리를 유지하도록 이중머리 볼트 삽입홈(112,122)에 삽입된 이중머리 볼트(160)에 의해 지지된다.For this, double-head bolt insertion grooves 112 and 122 are formed at the lower ends of the front securing plate 110 and the rear securing plate 120, and the lower ends of the front securing plate 110 and the rear securing plate 120 are spaced apart from each other by a predetermined distance And is supported by the double head bolts 160 inserted into the double head bolt insertion grooves 112,
H 빔(130)의 웹 하단에는 이중머리 볼트(160)에 걸리도록 이중머리 볼트 걸림홈(132)이 형성되므로, 이중머리 볼트(160)와 간섭이 방지된다(도 4,6).Since the double head bolt receiving groove 132 is formed at the lower end of the web of the H beam 130 so as to be caught by the double head bolt 160, interference with the double head bolt 160 is prevented (FIGS.
이러한 구조를 취하는 경우, 전면 흙막이판(110) 및 후면 흙막이판(120)의 하단은 이중머리 볼트(160)에 의해 상호 일정 간격을 유지하도록 지지되고, 제거 시에는 단지 흙막이판(110,120)을 상측으로 들어올리기만 하면 되므로, 간편한 작업이 가능하다.In this case, the bottom end of the front securing plate 110 and the rear securing plate 120 are supported by the double head bolts 160 so as to be spaced apart from each other by a predetermined distance, and only when the securing plates 110, So that it is possible to perform a simple operation.
배근조립체(200)는 기본적으로, 배근판(210)에 연직방향으로 결합한 복수의 폭방향 철근(220); 복수의 폭방향 철근(220)에 깊이방향으로 결합한 복수의 깊이방향 철근(230); 복수의 폭방향 철근(220)에 길이방향으로 결합한 복수의 길이방향 철근(240);을 포함하여 구성된다(도 11).The assembling assembly 200 basically comprises a plurality of transverse reinforcing bars 220 coupled to the backing plate 210 in the vertical direction; A plurality of depth direction reinforcing bars 230 coupled to the plurality of width direction reinforcing bars 220 in the depth direction; And a plurality of longitudinal reinforcing bars 240 longitudinally coupled to the plurality of width reinforcing bars 220 (FIG. 11).
이들 철근(220,230,240)은 추후 타설되는 콘크리트에 매설되어 벽체의 내부 배근을 형성하게 된다.These reinforcing bars 220, 230 and 240 are embedded in the concrete to be laid later to form an inner foundation of the wall.
폭방향 철근(220)은 벽체의 폭방향 배근을 형성하기 위한 것으로서, 후면 흙막이판(120)과의 간격유지를 위하여 타 폭방향 철근(220)에 비해 길이가 조금 더 긴 간격유지철근(221)을 포함하는 구성을 취하고, 이 간격유지철근(221)은 단부가 후면 흙막이판(120)에 접촉함으로써, 배근판(210)과 후면 흙막이판(120)의 간격을 유지한다.The widthwise reinforcing bars 220 are for forming a width directional reinforcement of the wall and are formed of spacing reinforcing bars 221 having a slightly longer length than the other widthwise reinforcing bars 220 in order to maintain a gap with the rear seating plate 120. [ And the spacing reinforcing bar 221 contacts the rear securing plate 120 so that the interval between the reinforcement plate 210 and the rear securing plate 120 is maintained.
이러한 폭방향 철근(220)은 배근판(210)에 고정된 구성을 취할 수도 있으나, 배근판(210)에 형성된 관통공을 통해 관통한 단부가 별도의 볼트 등의 결합구에 의해 착탈가능하게 고정된 구성을 취하는 것이 바람직하다.The width direction reinforcement 220 may have a structure fixed to the reinforcement plate 210. The end portion of the reinforcement 220 that passes through the through hole formed in the reinforcement plate 210 may be detachably fixed It is preferable to take the configuration as described above.
콘크리트의 타설 이후, 본 구조물의 설치를 위한 지반굴착과 함께 배근판(210)은 제거될 것인데, 이러한 배근판(210)의 제거작업을 용이하게 하기 위함이다.After the concrete is poured, the reinforcement plate 210 will be removed together with the ground excavation for installation of the present structure, in order to facilitate the removal operation of the reinforcement plate 210.
천공 홀(10)의 깊이가 깊은 경우, 배근판(210)은 복수의 철판(210a,210b); 복수의 철판(210a,210b)의 결합부위에 덧대기 이음을 위해 결합하는 덧대기 철판(211);을 포함하는 구성을 취하는 것이 바람직하다(도 12).When the depth of the perforation hole 10 is deep, the reinforcement plate 210 includes a plurality of steel plates 210a and 210b; And an embossed iron plate 211 for joining the joining portions of the plurality of iron plates 210a and 210b for superficial joining (FIG. 12).
지중에 설치될 본 구조물이 복수 층의 보, 슬래브를 포함하는 구성을 취하는 경우, 그 보와의 결합부위를 선택적으로 노출하도록, 보 결합부위 철판(210a)이 설치되는 것이 바람직하다(도 12).When the present structure to be installed in the earth has a structure including a plurality of beams and slabs, it is preferable that a beam-joining steel plate 210a is provided so as to selectively expose a joining portion with the beam (Fig. 12) .
즉, 지반의 일부 굴착 후, 덧대기 철판(211) 및 보 결합부위 철판(210a)만을 제거한 상태에서, 벽체 배근과 보 배근의 결합 및 보의 설치작업을 수행할 수 있도록 하기 때문이다.That is, after the excavation of a part of the ground, only the overlapped steel plate 211 and the steel plate 210a are removed, so that the joining of the wall reinforcement and the reinforcement rods and the installation work of the beams can be performed.
또한, 상술한 보의 설치작업 및 이에 따른 슬랩 설치작업은 해당 층까지의 굴착작업만을 진행한 상태의 지반 위에서 수행할 수 있으므로, 별도의 지지대 기타 가시설이 필요없다는 장점이 추가된다.In addition, the installation work of the beam and the slab installation work described above can be performed on the ground in a state where only the excavation works up to the corresponding layer are performed, so that there is added an advantage that there is no need for a separate support stand or the like.
이를 위해서는, 보 결합부위 철판(210a) 내측에 스티로폼 등의 설치에 의한 공동부를 형성하여 철근이 노출되도록 하는 것이 필요하다.To this end, it is necessary to form a cavity by installing styrofoam or the like inside the beam-joining portion steel plate 210a so that the reinforcing bars are exposed.
배근조립체(200)는 일정 폭을 갖도록 형성되어, 천공 홀(10)에 연속적으로 다수가 설치된다.The assembly assembly 200 is formed to have a constant width, and a plurality of consecutive holes are provided in the perforation hole 10.
이러한 다수의 배근조립체(200)가 상호 안정적으로 연결되도록 하기 위해서는, 길이방향 철근(240)의 단부에 타 배근조립체(200a)의 길이방향 철근(240a)의 단부와 끼움결합하도록 절곡구조의 끼움결합부(250)가 형성되는 것이 바람직하다(도 13,14).In order to stably connect the plurality of the body assemblies 200 with each other, the end portions of the longitudinal reinforcing bars 240 are fitted to the end portions of the longitudinal reinforcing bars 240a of the other reinforcing assembly 200a, It is preferable to form the portion 250 (Figs. 13 and 14).
끼움결합부(250)는 구체적으로, 길이방향 철근(240)의 일단에서 내측으로 절곡되어 형성된 내향 끼움결합부(251); 길이방향 철근(240)의 타단에서 외측으로 절곡되어 형성된 외향 끼움결합부(252);를 포함하는 구성을 취하는 것이 구조적 안정성 측면에서 바람직하다(도 13).Specifically, the fitting portion 250 includes an inwardly fitting portion 251 bent inwardly from one end of the longitudinal reinforcing bar 240; And an outwardly fitting portion 252 formed outwardly bent from the other end of the longitudinal reinforcing bar 240 in terms of structural stability (FIG. 13).
길이방향 철근(240)은 이러한 구조가 상호 대칭구조로 형성된 한 쌍의 길이방향 철근(240a,240b)에 의해 구성되는 것이 더욱 바람직하다(도 13).It is more preferable that the longitudinal reinforcing bar 240 is constituted by a pair of longitudinal reinforcing bars 240a and 240b whose structures are formed in mutually symmetrical structures (FIG. 13).
복수의 길이방향 철근(240)의 끼움결합부(250)에 깊이방향을 따라 슬라이딩판(253)이 결합하는 경우, 양 배근조립체(200,200a)의 더욱 안정적인 결합 및 편리한 시공을 기대할 수 있다(도 13,14).When the sliding plate 253 is coupled along the depth direction to the fitting portion 250 of the plurality of longitudinal bars 240, it is possible to expect a more stable connection and convenient construction of the two reinforcing bars 200 and 200a 13,14).
이상은 본 발명에 의해 구현될 수 있는 바람직한 실시예의 일부에 관하여 설명한 것에 불과하므로, 주지된 바와 같이 본 발명의 범위는 위의 실시예에 한정되어 해석되어서는 안 될 것이며, 위에서 설명된 본 발명의 기술적 사상과 그 근본을 함께 하는 기술적 사상은 모두 본 발명의 범위에 포함된다고 할 것이다.It will be apparent to those skilled in the art that various modifications and variations can be made in the present invention without departing from the spirit or scope of the invention as defined in the appended claims. It is to be understood that both the technical idea and the technical spirit of the invention are included in the scope of the present invention.
10 : 천공 홀 100 : 천공 홀 확공부재
110 : 전면 흙막이판 111 : 로프
112 : 이중머리 볼트 삽입홈 113 : 말뚝
120 : 후면 흙막이판 121 : 로프
122 : 이중머리 볼트 삽입홈 123 : 말뚝
130 : H 빔 131 : 흙막이판 결합구
132 : 이중머리 볼트 걸림홈 140 : "ㄷ"자형 결합부재
160 : 이중머리 볼트 200 : 배근조립체
210 : 배근판 211 : 덧대기 철판
220 : 폭방향 철근 221 : 간격유지철근
230 : 깊이방향 철근 240,240a,240b : 길이방향 철근
250 : 끼움결합부 251 : 내향 끼움결합부
252 : 외향 끼움결합부 253 : 슬라이딩판
W : 벽체 S1 : 1층 슬래브
SB1 : 지하 1층 슬래브 C : 지중기둥
10: Perforated hole 100: Perforated hole Expanded material
110: front sheeting board 111: rope
112: double head bolt insertion groove 113: pile
120: rear cladding board 121: rope
122: double head bolt insertion groove 123: pile
130: H beam 131: Earth retaining plate coupling member
132: double head bolt engagement groove 140: "C"
160: double head bolt 200: mounting assembly
210: a reinforcement plate 211: an embossed iron plate
220: widthwise reinforcing bar 221: spacing reinforcing bar
230: Depth direction reinforcing bars 240, 240a, 240b:
250: fitting part 251: inward fitting part
252: outward fitting portion 253: sliding plate
W: wall S1: one-story slab
SB1: B1 floor slab C: Underground pillar

Claims (14)

  1. 지반에 천공 홀(10)을 형성하는 천공단계;
    양측에 각각 전면 흙막이판(110) 및 후면 흙막이판(120)이 착탈가능하게 결합함과 아울러, 상기 전면 흙막이판(110) 및 후면 흙막이판(120)의 하단은 상호 일정거리를 유지하도록 형성된 천공 홀 확공부재(100)를 상기 천공 홀(10)에 삽입하여 확공하는 천공 홀 확공부재 삽입단계;
    상기 천공단계 및 천공 홀 확공부재 삽입단계를 측방으로 반복하여, 다수의 상기 천공 홀 확공부재(100)가 열지어 설치되도록 하는 천공 홀 확공부재 설치단계;
    상기 전면 흙막이판(110)의 상단은 전방으로 지지하고, 상기 후면 흙막이판(120)의 상단은 후방으로 지지하는 흙막이판 지지단계;
    상기 전면 흙막이판(110) 및 후면 흙막이판(120)은 상기 천공 홀(10)에 삽입된 상태에서, 상기 천공 홀 확공부재(100)를 제거하는 천공 홀 확공부재 제거단계;
    복수의 배근판(210)에 벽체 철근(220,230,240)을 조립하여 배근조립체(200)를 형성하는 배근조립체 조립단계;
    상기 전면 흙막이판(110) 및 후면 흙막이판(120)의 사이에 상기 배근조립체(200)를 삽입하되, 상기 복수의 배근판(210)이 상하방향 적층구조로서 상기 전면 흙막이판(110)의 위치에 오도록 하는 배근조립체 삽입단계;
    상기 전면 흙막이판(110)을 제거하는 전면 흙막이판 제거단계;
    상기 후면 흙막이판(120)과 상기 배근판(210)의 사이 영역에 콘크리트를 타설하여 벽체(W)를 형성하는 벽체 콘크리트 타설단계;
    상기 복수의 배근판(210) 중 1층 슬래브 설치위치의 배근판(210a1)을 제거하고, 상기 벽체 철근(220,230,240)의 일부를 노출시켜 노출된 벽체 철근(220a)을 형성하는 1층 배근판 제거단계;
    상기 벽체(W)의 사이 영역의 지반 위에 1층 슬래브 거푸집(21)을 설치하고, 1층 슬래브 철근(310)을 배근하되, 상기 노출된 벽체 철근(220a)과 결합하는 슬래브 거푸집 설치단계;
    상기 1층 슬래브 거푸집(21)에 콘크리트를 타설하여 1층 슬래브(S1)를 형성하는 슬래브 콘크리트 타설단계;를 포함하고,
    상기 천공 홀 확공부재(100)는
    H 빔(130);
    타 천공 홀 확공부재(100a)의 H 빔(130a)과 결합하도록, 상기 H 빔(130)의 플랜지 및 웹의 내부 영역에 결합하는 "ㄷ"자형 결합부재(140);를 포함하며,
    상기 전면 흙막이판(110) 및 후면 흙막이판(120)의 상단은 상기 H 빔(130)의 웹을 관통하여 결합하는 흙막이판 결합구(131)에 의해 결합하고,
    상기 전면 흙막이판(110) 및 후면 흙막이판(120)의 하단에는 이중머리 볼트 삽입홈(112,122)이 형성되며,
    상기 전면 흙막이판(110) 및 후면 흙막이판(120)의 하단은 상호 일정거리를 유지하도록 상기 이중머리 볼트 삽입홈(112,122)에 삽입된 이중머리 볼트(160)에 의해 지지되는 것을 특징으로 하는 지중 구조물 시공방법.
    Forming a perforation hole (10) in the ground;
    The front and rear flooring panels 110 and 120 are detachably coupled to both sides of the front and rear flooring panels 110 and 120, Inserting a hole drilling material (100) into the hole (10) to insert the hole drilling material (100);
    A perforation hole lengthening step of repeating the perforating step and the perforation hole louver inserting step sideways so that a plurality of the perforation hole louver 100 are installed to be installed;
    Supporting the upper end of the front securing plate 110 forward and supporting the upper end of the rear securing plate 120 rearward;
    Removing the perforated hole lengthening material 100 from the front sheathing plate 110 and the rear sheeting plate 120 when the perforated hole louver 100 is inserted into the perforation hole 10;
    An assembling step of assembling the reinforcing assembly (200) by assembling the reinforcing bars (220, 230, 240) to the plurality of reinforcement plates (210);
    Wherein the plurality of reinforcement plates 210 are installed in a vertical stacked structure between the front and rear flooring plates 110 and 120 so that the position of the front flooring plate 110 In the step of inserting the assembly;
    Removing the front earth retaining plate (110);
    A concrete concrete casting step of casting concrete in an area between the rear retaining plate 120 and the reinforcement plate 210 to form a wall W;
    Removing a reinforcement plate 210a1 at one slab installation position of one of the plurality of reinforcement plates 210 and removing a one-layer reinforcement plate 220a exposing a part of the wall reinforcements 220, 230, step;
    A slab form setting step of providing a one-layer slab formwork 21 on the ground in the area between the walls W and joining the exposed slab reinforcement 310 with the exposed wall reinforcing bar 220a;
    And a slab concrete casting step of casting concrete into the single-layer slab form (21) to form a single-layer slab (S1)
    The perforation hole lengthening member 100 includes
    H beam 130;
    Shaped engagement member 140 that engages with the flange of the H beam 130 and the inner region of the web to engage with the H beam 130a of the other perforation hole concentrator 100a,
    The upper ends of the front securing plate 110 and the rear securing plate 120 are coupled by a securing plate coupling hole 131 through which the web of the H beam 130 is coupled,
    Double head bolt insertion grooves 112 and 122 are formed at the lower ends of the front earth retaining plate 110 and the rear earth retaining plate 120,
    Wherein the lower ends of the front securing plate 110 and the rear securing plate 120 are supported by the double head bolts 160 inserted into the double head bolt insertion grooves 112 and 122 so as to maintain a constant distance therebetween. Construction method of structure.
  2. 제1항에 있어서,
    상기 슬래브 콘크리트 타설단계 이후,
    상기 1층 슬래브(S1)의 하부를 굴착하고, 상기 슬래브 거푸집을 제거하는 굴착단계;
    상기 복수의 배근판(210) 중 지하 1층 슬래브 설치위치의 배근판(210a2)을 제거하고, 상기 벽체 철근(220,230,240)의 일부를 노출시켜 노출된 벽체 철근(220a)을 형성하는 지하 1층 배근판 제거단계;
    상기 벽체(W)의 사이 영역의 지하지반 위에 지하 1층 슬래브 거푸집(22)을 설치하고, 지하 1층 슬래브 철근(320)을 배근하되, 상기 노출된 벽체 철근(220a)과 결합하는 지하 1층 슬래브 거푸집 설치단계;
    상기 지하 1층 슬래브 거푸집(22)에 콘크리트를 타설하여 지하 1층 슬래브(SB1)를 형성하는 슬래브 콘크리트 타설단계;를
    포함하는 것을 특징으로 하는 지중 구조물 시공방법.
    The method according to claim 1,
    After the slab concrete pouring step,
    Excavating a lower portion of the one-story slab (S1) and removing the slab form;
    A reinforcement plate 210a2 of a first underground slab installation position of the plurality of reinforcement plates 210 is removed and a part of the underground reinforcement 220a is exposed by exposing a part of the reinforcement bars 220, A plate removing step;
    A slab form 22 of a basement is installed on an underground floor of an area between the walls W and a slab reinforcement 320 of a basement is installed, A slab form setting step;
    A slab concrete pouring step of pouring concrete into the underground one-storey slab form 22 to form a one-storey underground slab SB1;
    Wherein the method comprises the steps of:
  3. 제1항에 있어서,
    상기 슬래브 거푸집 설치단계 이전, 상기 벽체(W)의 사이 영역에 지중기둥(C)을 형성하는 지중기둥 형성단계;를 더 포함하고,
    상기 슬래브 거푸집 설치단계는, 상기 1층 슬래브 철근(310)을 배근하되 상기 지중기둥(C)의 상부에 노출된 기둥 철근(330)과 결합하는 것을 특징으로 하는 지중 구조물 시공방법.
    The method according to claim 1,
    Further comprising the step of forming an underground column (C) in an area between the walls (W) before the step of installing the slab formwork,
    Wherein the step of installing the slab formers is performed by joining the single-layer slab reinforcement 310 with the pillar reinforcement 330 exposed at the upper portion of the underground column C.
  4. 제1항에 있어서,
    상기 슬래브 거푸집 설치단계 이전, 상기 벽체(W)의 사이 영역에 보를 형성하는 보 형성단계;를 더 포함하고,
    상기 슬래브 거푸집 설치단계는, 상기 1층 슬래브 철근(310)을 배근하되 상기 보의 상부에 노출된 보 철근과 결합하는 것을 특징으로 하는 지중 구조물 시공방법.
    The method according to claim 1,
    And forming a beam in an area between the walls (W) before the step of installing the slab form,
    Wherein the step of installing the slab formers is performed by joining the single-layer slab reinforcement 310 with the reinforcement exposed at the upper portion of the beam.
  5. 삭제delete
  6. 삭제delete
  7. 제1항에 있어서,
    상기 H 빔(130)의 웹 하단에는 상기 이중머리 볼트(160)에 걸리도록 이중머리 볼트 걸림홈(132)이 형성된 것을 특징으로 하는 지중 구조물 시공방법.
    The method according to claim 1,
    Wherein a double head bolt engagement groove (132) is formed at the lower end of the web of the H beam (130) so as to be engaged with the double head bolt (160).
  8. 제1항에 있어서,
    상기 배근조립체(200)는
    상기 배근판(210)에 연직방향으로 결합한 복수의 폭방향 철근(220);
    상기 복수의 폭방향 철근(220)에 깊이방향으로 결합한 복수의 깊이방향 철근(230);
    상기 복수의 폭방향 철근(220)에 길이방향으로 결합한 복수의 길이방향 철근(240);을
    포함하는 것을 특징으로 하는 지중 구조물 시공방법.
    The method according to claim 1,
    The assembly (200)
    A plurality of widthwise reinforcing bars 220 coupled to the backing plate 210 in a vertical direction;
    A plurality of depth direction reinforcing bars 230 coupled to the plurality of width direction reinforcing bars 220 in the depth direction;
    A plurality of longitudinal reinforcing bars 240 coupled longitudinally to the plurality of width reinforcing bars 220;
    Wherein the method comprises the steps of:
  9. 제8항에 있어서,
    상기 폭방향 철근(220)은
    상기 후면 흙막이판(120)과의 간격유지를 위하여, 단부가 상기 후면 흙막이판(120)에 접촉하도록 설치된 간격유지철근(221)을 포함하는 것을 특징으로 하는 지중 구조물 시공방법.
    9. The method of claim 8,
    The width direction reinforcement 220
    And a spacing reinforcing bar (221) provided at an end portion of the reinforcing bar to contact the rear securing plate (120) so as to maintain a gap with the rear securing plate (120).
  10. 제8항에 있어서,
    상기 배근판(210)은
    상하방향 적층구조로 설치되는 복수의 철판(210a,210b);
    상기 복수의 철판(210a,210b)의 결합부위에 덧대기 이음을 위해 결합하는 덧대기 철판(211);을 포함하고,
    상기 복수의 철판(210a,210b)은
    보 또는 상기 슬래브와의 결합부위를 선택적으로 제거할 수 있도록 설치하는 것을 특징으로 하는 지중 구조물 시공방법.
    9. The method of claim 8,
    The reinforcement plate 210
    A plurality of iron plates 210a and 210b provided in a vertically stacked structure;
    And an embossing iron plate (211) for joining to the joining portions of the plurality of iron plates (210a, 210b) for superficial joining,
    The plurality of iron plates (210a, 210b)
    Wherein the slab is installed so as to selectively remove a portion where the beam or the slab is joined to the ground.
  11. 제8항에 있어서,
    상기 길이방향 철근(240)의 단부에는,
    타 배근조립체(200a)의 길이방향 철근(240a)의 단부와 끼움결합하도록 절곡구조의 끼움결합부(250)가 형성된 것을 특징으로 하는 지중 구조물 시공방법.
    9. The method of claim 8,
    At the end of the longitudinal reinforcement 240,
    Wherein an engaging portion (250) of a bent structure is formed to fit into an end portion of the longitudinal reinforcing bar (240a) of the other reinforcing assembly (200a).
  12. 제11항에 있어서,
    상기 끼움결합부(250)는
    상기 길이방향 철근(240)의 일단에서 내측으로 절곡되어 형성된 내향 끼움결합부(251);
    상기 길이방향 철근(240)의 타단에서 외측으로 절곡되어 형성된 외향 끼움결합부(252);를
    포함하는 것을 특징으로 하는 지중 구조물 시공방법.
    12. The method of claim 11,
    The fitting portion 250
    An inwardly-fitting part 251 bent inward from one end of the longitudinal reinforcement 240;
    An outward fitting part 252 formed outwardly bent from the other end of the longitudinal reinforcing bar 240;
    Wherein the method comprises the steps of:
  13. 제12항에 있어서,
    상기 길이방향 철근(240)은
    상호 대칭구조로 형성된 한 쌍의 길이방향 철근(240a,240b)을 포함하는 것을 특징으로 하는 지중 구조물 시공방법.
    13. The method of claim 12,
    The longitudinal reinforcement 240 is
    And a pair of longitudinal reinforcing bars (240a, 240b) formed in an inter-symmetrical structure.
  14. 제11항에 있어서,
    상기 복수의 길이방향 철근(240)의 끼움결합부(250)에는 깊이방향을 따라 슬라이딩판(253)이 결합한 것을 특징으로 하는 지중 구조물 시공방법.
    12. The method of claim 11,
    Wherein a sliding plate (253) is coupled to the fitting part (250) of the plurality of longitudinal bars (240) along the depth direction.
KR1020130044483A 2013-04-22 2013-04-22 Construction method for underground structure KR101452381B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020130044483A KR101452381B1 (en) 2013-04-22 2013-04-22 Construction method for underground structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020130044483A KR101452381B1 (en) 2013-04-22 2013-04-22 Construction method for underground structure

Publications (1)

Publication Number Publication Date
KR101452381B1 true KR101452381B1 (en) 2014-10-22

Family

ID=51998145

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020130044483A KR101452381B1 (en) 2013-04-22 2013-04-22 Construction method for underground structure

Country Status (1)

Country Link
KR (1) KR101452381B1 (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090094971A (en) * 2008-03-04 2009-09-09 깨뱉시스템주식회사 Under ground top-down method
KR20100104481A (en) * 2009-03-18 2010-09-29 (주)네오크로스구조엔지니어링 Underground construction method of top-down with slurry walls
KR20110083449A (en) * 2010-01-13 2011-07-20 서울대학교산학협력단 Details and construction method of circular cft column to rc flat plate connections for top-down construction
KR101219445B1 (en) * 2011-08-11 2013-01-11 윤동현 Construction method for underground wall

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090094971A (en) * 2008-03-04 2009-09-09 깨뱉시스템주식회사 Under ground top-down method
KR20100104481A (en) * 2009-03-18 2010-09-29 (주)네오크로스구조엔지니어링 Underground construction method of top-down with slurry walls
KR20110083449A (en) * 2010-01-13 2011-07-20 서울대학교산학협력단 Details and construction method of circular cft column to rc flat plate connections for top-down construction
KR101219445B1 (en) * 2011-08-11 2013-01-11 윤동현 Construction method for underground wall

Similar Documents

Publication Publication Date Title
KR101691139B1 (en) Construction method using soil retaining wall
KR100531385B1 (en) Construction method of underground structure that enables continuous retaining wall using steel wale and diaphragm effect of concrete slab
US4005582A (en) Method of constructing underground concrete walls and reinforcement cage therefor
KR20080026014A (en) Establishment method of soil guard structure
KR101590032B1 (en) Column wall using pile and structure construction method therewith
KR100882831B1 (en) Reformed sheet plate and the method of installation of the same
KR101582173B1 (en) The structure assembly for building a tunnel and building method thereof
KR100951097B1 (en) Slab and subgrade external wall structure and method for constructing underground slab and subgrade external wall, bracket
KR100976847B1 (en) Precast concrete deck structure
KR101069705B1 (en) Method for installing waterproofing steel plate in construction of undergound tunnel
US20130047539A1 (en) Building Structure
JP2005120663A (en) Structure of earth retaining wall
KR100634726B1 (en) Form system for construction of underground slab and method for constructing underground slab and breast wall using the same
KR100633796B1 (en) Connecting structure of mid supporting beam for temporary soil sheathing work
KR100968048B1 (en) A retaining panel structure and construction method
KR101743758B1 (en) Downward construction method for vertical extension of building using base block
KR101274974B1 (en) Earth retaining wall and construction method thereof
KR100569703B1 (en) Structure of steel pipe applied to steel pipe roof construction method for building underground structure, and steel pipe roof structure therefor using the same, and steel roof construction method thereof
KR20090100867A (en) The method construction work and unit metal tubing constructing system for the road underground driveway
KR101344063B1 (en) The construction method of steel-concrete underpass
KR20050092881A (en) Steel pipe roof construction method for building underground structure, roof structure therefor, and structure of steel pipe therefor
KR101419863B1 (en) Pc panel needless of concrete forms using construction method of cast-in-place step retaining wall for slope reinforcement
KR101149895B1 (en) Reinforcement block for pillar of tunnel
KR20110131549A (en) Method for constructing nderground structure
KR20090114863A (en) Parallelly connected iron tube and construction method for underground structure using the same

Legal Events

Date Code Title Description
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20170927

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20180801

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20190821

Year of fee payment: 6