KR101219995B1 - A temporary brace and a composite steel girder, a shift section steel girder used an building structure and thereof construction method - Google Patents

A temporary brace and a composite steel girder, a shift section steel girder used an building structure and thereof construction method Download PDF

Info

Publication number
KR101219995B1
KR101219995B1 KR1020120024832A KR20120024832A KR101219995B1 KR 101219995 B1 KR101219995 B1 KR 101219995B1 KR 1020120024832 A KR1020120024832 A KR 1020120024832A KR 20120024832 A KR20120024832 A KR 20120024832A KR 101219995 B1 KR101219995 B1 KR 101219995B1
Authority
KR
South Korea
Prior art keywords
steel
girder
girders
short side
steel girders
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
KR1020120024832A
Other languages
Korean (ko)
Inventor
박무용
Original Assignee
(주)한국건설공법
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)한국건설공법 filed Critical (주)한국건설공법
Priority to KR1020120024832A priority Critical patent/KR101219995B1/en
Application granted granted Critical
Publication of KR101219995B1 publication Critical patent/KR101219995B1/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/02Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
    • E04C3/04Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/02Bridges characterised by the cross-section of their bearing spanning structure of the I-girder type
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/30Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts being composed of two or more materials; Composite steel and concrete constructions
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/58Connections for building structures in general of bar-shaped building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/02Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
    • E04C3/29Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces built-up from parts of different material, i.e. composite structures
    • E04C3/293Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces built-up from parts of different material, i.e. composite structures the materials being steel and concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Chemical & Material Sciences (AREA)
  • Composite Materials (AREA)
  • Joining Of Building Structures In Genera (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

본 발명은 상기 종래기술의 문제점을 해결하기 위하여, 거더의 단변방향으로는 가설 브레이스와 강합성 거더를 설치하여 상기 강합성 거더를 3경간 연속스팬으로 거동하게 하여 휨모멘트를 대폭 감소시켰으며,
또한 거더의 장변방향으로는 강재 거더의 중앙부는 휨모멘트가 크고 양 단부는 휨모멘트가 작은 점을 감안하여 강재 거더의 양 단부와 중앙부에 사용되는 강재 거더의 크기에 차이를 두어 상기 강재 거더를 변단면으로 처리함으로써,
단변방향 강합성 거더에 작용하는 휨응력을 저감시키며, 장변방향 강재 거더는 휨응력에 따라 효율적으로 지지할 수 있는 건축구조물에 사용되는 가설 브레이스와 강합성 거더, 변단면 강재 거더 및 이들을 이용한 건축구조물 축조공법을 제공하는 것을 목적으로 한다.
상기 목적을 달성하기 위해 본 발명은 소정 간격으로 설치된 한 쌍의 강재 기둥(1)과 상기 강재 기둥(1) 사이에 결합되는 단변방향 강재 거더(2)에 있어서, 상기 단변방향 강재 거더(2)의 상면으로부터 소정 높이에 위치한 상기 강재 기둥(1) 플랜지에 결합된 지지플레이트(15)와 상기 단변방향 강재 거더(2)의 양 단부에서 거더의 중심방향으로 소정 거리에 위치한 상기 단변방향 강재 거더(2)의 상부 플랜지에 결합된 지지플레이트(15) 사이에는 각각 가설 브레이스(10)가 설치되고,
상기 강재 기둥(1)에 용접에 의해 접합되는 가셋 플레이트(5)는 상기 강재 거더(2)의 웨브와 보울트 접합되고, 상기 강재 거더(2) 양 단부의 소정 구간에는 각각 ∪자형 철판거푸집(13)이 설치되며, 상기 ∪자형 철판거푸집(13) 내부에는 현장타설 콘크리트(4)가 충전되고 그 상부에는 다수의 보강철근(7)이 설치되어 상기 강재 거더의 양 단부를 보강하는 것을 특징으로 한다.
또한 본 발명은 소정 간격으로 설치된 한 쌍의 강재 기둥(1)과 상기 강재 기둥(1) 사이에 결합되는 장변방향 강재 거더(16)에 있어서, 상기 장변방향 강재 거더(16)의 양 단부에서 중심방향으로 소정 거리에는 각각 춤이 작은 강재 거더(11)가 설치되고, 상기 장변방향 강재 거더(16)의 중앙부에는 춤이 큰 강재 거더(12)가 설치되되,
상기 춤이 큰 강재 거더(12)의 양 단부는 상기 춤이 작은 강재 거더(11)의 단부와 결합될 수 있도록 상부 플랜지와 웨브의 일부가 절개되도록 형성되고, 상기 춤이 큰 강재 거더(12)의 절개된 양 단부와 상기 춤이 작은 강재 거더(11)의 일단은 각각 용접에 의해 접합되는 것을 특징으로 한다.
또한 본 발명은 한 쌍의 강재 기둥(1)을 소정 간격으로 설치하는 단계; 상기 강재 기둥(1)에 단변방향으로 상기 가설 브레이스와 강합성 거더를 설치하고, 장변방향으로 상기 변단면 강재 거더를 설치하는 단계;상기 강재 기둥 주위에 사각형상의 개구부를 형성하고 슬래브를 타설하는 단계;
상기 강재 기둥 주위의 사각형상 개구부에 철근을 보강하고 콘크리트를 타설하여 상기 강재 기둥을 철근콘크리트로 보강하는 단계; 상기 가설 브레이스(10)를 절단하여 해체하는 단계;로 구성되는 것을 특징으로 한다.
The present invention, in order to solve the problems of the prior art, by installing a temporary brace and a composite girder in the short side direction of the girder to make the rigid girder behaves three consecutive spans, greatly reducing the bending moment,
In addition, the steel girders are changed in the longitudinal direction of the steel girders in consideration of the fact that the center of the steel girders has a large bending moment and both ends have a small bending moment. By treating it in section
It reduces the bending stress acting on the short lateral girder girders, and the long lateral steel girder is a temporary brace and composite girder, a sectional steel girder, and a building structure construction method using them. The purpose is to provide.
In order to achieve the above object, the present invention provides a short side steel girder (2) in a short side steel girder (2) coupled between a pair of steel poles (1) and the steel pole (1) installed at predetermined intervals. The short side steel girders positioned at a predetermined distance in the direction of the center of the girder at both ends of the support plate 15 and the short side steel girders 2 coupled to the flange of the steel column 1 located at a predetermined height from an upper surface of the Temporary braces 10 are installed between the support plates 15 coupled to the upper flanges of 2),
The gusset plate 5 joined to the steel pillar 1 by welding is bolted to the web of the steel girder 2, and each of the steel girder 2 has a U-shaped iron sheet formwork 13 at predetermined sections of both ends. ) Is installed, the cast iron formwork 13 is filled with the cast-in-place concrete (4) and a plurality of reinforcing bars (7) are installed on the upper portion to reinforce both ends of the steel girder. .
In addition, the present invention is a long side steel girders (16) coupled between the pair of steel pillars (1) and the steel pillars (1) provided at predetermined intervals, the center at both ends of the long side steel girders (16) The steel girders 11 with small dances are installed at predetermined distances in the direction, and the steel girders 12 with large dances are installed at the central portion of the long side steel girders 16.
Both ends of the large steel girders 12 of the dance are formed so that a portion of the upper flange and the web is cut so that the dancing can be combined with the ends of the small steel girders 11, the large steel girders 12 of the dance Both ends of the cut and one end of the dance steel girders 11 are characterized in that they are joined by welding, respectively.
In addition, the present invention comprises the steps of installing a pair of steel poles (1) at a predetermined interval; Installing the temporary brace and the composite girder in the short side direction on the steel pillar (1), and installing the side cross-section steel girder in the long side direction; forming a rectangular opening around the steel pillar and pouring slab ;
Reinforcing steel bars in the rectangular openings around the steel columns and placing concrete to reinforce the steel columns with reinforced concrete; Characterized in that consisting of; cutting the hypothesis brace 10 to dismantle.

Description

건축구조물에 사용되는 가설 브레이스와 강합성 거더, 변단면 강재 거더 및 이들을 이용한 건축구조물 축조공법.{A temporary brace and a composite steel girder, a shift section steel girder used an building structure and thereof construction method}{A temporary brace and a composite steel girder, a shift section steel girder used an building structure and details construction method}

본 발명은 건축구조물 축조 시 상부하중에 의해 강재 거더에 작용하는 휨응력을 저감시키며, 효율적으로 지지할 수 있는 건축구조물에 사용되는 가설 브레이스와 강합성 거더, 변단면 강재 거더 및 이들을 이용한 건축구조물 축조공법에 관한 것이다.The present invention reduces the bending stress acting on the steel girders due to the upper load during construction of the building structure, the temporary brace and the composite girder, the cross-section steel girders used in the building structure that can support efficiently, the construction structure construction method using them It is about.

일반적으로 건축구조물 축조 시 지하구조물을 축조하는 경우 지상에서 지하 최하층으로 한층씩 지반을 굴착하면서 구조물을 시공하는 역타공법이 있으며, 상기 역타공법에 의해 강재와 철근콘크리트가 합성된 지하구조물을 축조하는 경우, 강합성 기둥과 결합되는 강합성 거더는 강재 거더에 프리캐스트 콘크리트가 합성된 PC(프리캐스트 콘크리트) 합성거더를 사용하고 있다.
In general, when constructing an underground structure when constructing a building structure, there is a reverse drilling method for constructing a structure by excavating the ground one by one from the ground to the lower ground level, and when constructing an underground structure in which steel and reinforced concrete are synthesized by the reverse drilling method. The composite girder, which is combined with the rigid composite column, uses a PC (precast concrete) composite girder in which precast concrete is synthesized in the steel girder.

종래기술인 도 1은 PC 합성거더를 사용한 지하구조물의 평면도이고, 도 2는 도 1의 단변방향 PC 합성거더의 휨모멘트도이며, 도 3은 도 1의 A-A' 단면도이고, 도 4는 도 3의 C-C' 단면도이며, 도 5는 도 1의 B-B' 단면도이고, 도 6은 도 5의 D-D' 단면도와 E-E' 단면도이다.
1 is a plan view of an underground structure using a PC composite girder, FIG. 2 is a bending moment diagram of the short side PC composite girder of FIG. 1, FIG. 3 is a sectional view taken along line AA ′ of FIG. 1, and FIG. 4 is of FIG. 3. CC 'is sectional drawing, FIG. 5 is BB' sectional drawing of FIG. 1, FIG. 6 is DD 'sectional drawing and EE' sectional drawing of FIG.

건축구조물 축조 시 지하구조물을 역타공법에 의해 축조하는 경우, 일실시예로 도 1, 3, 4에서 보는 바와 같이 거더의 단변방향으로 강재 기둥(1)에 용접에 의해 결합되는 가셋 플레이트(5, gusset plate)는 단변방향 강재 거더(2)와 결합되는데 상기 단변방향 강재거더(2)의 중앙부는 강재 거더이고,
When building the underground structure by the reverse punching method when building the building structure, as shown in Figure 1, 3, 4, the gusset plate 5, which is coupled by welding to the steel column (1) in the short side direction of the girder as an example gusset plate) is coupled to the short side steel girder (2), the central portion of the short side steel girder (2) is a steel girder,

양 단부는 상기 강재 거더(2)에 보강철근(7)과 현장타설 콘크리트(4)가 합성되어 공장에서 제작된 프리캐스트 콘크리트이며, 상기 강재 기둥(1)의 가셋 플레이트(5)는 상기 단변방향 강재 거더(2)의 웨브와 보울트 접합된다.
Both ends are precast concrete manufactured in the factory by reinforcing steel (7) and cast-in-place concrete (4) synthesized in the steel girder (2), and the gusset plate (5) of the steel column (1) is the short side direction The bolt is joined to the web of the steel girder 2.

또한 도 1, 5, 6에서 거더의 장변방향으로 강재 기둥(1)에 용접에 의해 결합되는 가셋 플레이트(5)는 PC 합성거더(3)와 결합되는데, 상기 PC 합성거더(3)의 양 단부는 강재 거더의 웨브에 스터드 볼트(8)가 결합되고 철근콘크리트로 합성되며,
1, 5, and 6, the gusset plate 5 coupled by welding to the steel column 1 in the long side direction of the girder is combined with the PC composite girder 3, both ends of the PC composite girder 3 The stud bolt (8) is coupled to the web of the steel girder and synthesized with reinforced concrete,

중앙부는 PC 강선(9)과 철근콘크리트가 합성되어 공장에서 제작된 프리캐스트 콘크리트이며, 상기 강재 기둥(1)의 가셋 플레이트(5)는 상기 PC 합성거더(3)의 단부인 강재 거더의 웨브와 보울트 접합된다.
The central part is a precast concrete produced in a factory by combining the PC steel wire 9 and the reinforced concrete, and the gusset plate 5 of the steel pillar 1 is formed of a web of steel girder, which is an end of the PC composite girder 3. Bolted joints.

지하구조물을 역타공법에 의해 축조함에 있어서, 거더의 단변방향으로 상기 강재 기둥(1)의 가셋 플레이트(5)에 상기 단변방향 합성거더를 접합하면, 상기 단변방향 합성거더는 도 2의 휨모멘트도와 같이 단일경간 연속스팬으로 거동하므로 휨모멘트가 크게 발생하여 단면이 증대되고 중량이며,
In constructing the underground structure by reverse drilling method, when the short side synthetic girder is bonded to the gusset plate 5 of the steel column 1 in the short side direction of the girder, the short side synthetic girder is the bending moment diagram of FIG. As it behaves as a single span continuous span, the bending moment is greatly generated, increasing the cross section and weight.

또한 거더의 장,단변방향에 사용되는 PC 합성거더는 공장에서 제작되어 현장까지 운반되어 설치되므로 제작비와 운반비가 증대되고, 중량의 프리캐스트 콘크리트로 인해 설치작업이 어려워져 시공성이 저하되는 문제점이 있게 된다.In addition, the PC composite girder used in the long and short direction of the girder is manufactured at the factory and transported to the site for installation, thus increasing the production cost and transportation cost, and it is difficult to install due to the heavy weight of precast concrete, resulting in a decrease in workability. do.

본 발명은 상기 종래기술의 문제점을 해결하기 위하여, 거더의 단변방향으로는 가설 브레이스와 강합성 거더를 설치하여 상기 강합성 거더를 3경간 연속스팬으로 거동하게 하여 휨모멘트를 대폭 감소시켰으며,
The present invention, in order to solve the problems of the prior art, by installing a temporary brace and a composite girder in the short side direction of the girder to make the rigid girder behaves three consecutive spans, greatly reducing the bending moment,

또한 거더의 장변방향으로는 강재 거더의 중앙부는 휨모멘트가 크고 양 단부는 휨모멘트가 작은 점을 감안하여 강재 거더의 양 단부와 중앙부에 사용되는 강재 거더의 크기에 차이를 두어 상기 강재 거더를 변단면으로 처리함으로써,
In addition, the steel girders are changed in the longitudinal direction of the steel girders in consideration of the fact that the center of the steel girders has a large bending moment and both ends have a small bending moment. By treating it in section

단변방향 강합성 거더에 작용하는 휨응력을 저감시키며, 장변방향 강재 거더는 휨응력에 따라 효율적으로 지지할 수 있는 건축구조물에 사용되는 가설 브레이스와 강합성 거더, 변단면 강재 거더 및 이들을 이용한 건축구조물 축조공법을 제공하는 것을 목적으로 한다.It reduces the bending stress acting on the short lateral girder girders, and the long lateral steel girder is a temporary brace and composite girder, a sectional steel girder, and a building structure construction method using them. The purpose is to provide.

상기와 같은 목적을 달성하기 위해 제공되는 본 발명은 소정 간격으로 설치된 한 쌍의 강재 기둥(1)과 상기 강재 기둥(1) 사이에 결합되는 단변방향 강재 거더(2)에 있어서, 상기 단변방향 강재 거더(2)의 상면으로부터 소정 높이에 위치한 상기 강재 기둥(1) 플랜지에 결합된 지지플레이트(15)와 상기 단변방향 강재 거더(2)의 양 단부에서 거더의 중심방향으로 소정 거리에 위치한 상기 단변방향 강재 거더(2)의 상부 플랜지에 결합된 지지플레이트(15) 사이에는 각각 가설 브레이스(10)가 설치되고,

상기 강재 기둥(1)에 용접에 의해 접합되는 가셋 플레이트(5)는 상기 강재 거더(2)의 웨브와 보울트 접합되고, 상기 강재 거더(2) 양 단부의 소정 구간에는 각각 ∪자형 철판거푸집(13)이 설치되며, 상기 ∪자형 철판거푸집(13) 내부에는 현장타설 콘크리트(4)가 충전되고 그 상부에는 다수의 보강철근(7)이 설치되어 상기 강재 거더의 양 단부를 보강하는 것을 특징으로 한다.
The present invention provided to achieve the above object is a short-sided steel girder (2) coupled between a pair of steel poles (1) and the steel poles (1) installed at predetermined intervals, the short-sided steel The short side positioned at a predetermined distance in the direction of the center of the girder at both ends of the support plate 15 coupled to the flange of the steel column 1 located at a predetermined height from the upper surface of the girder 2 and the short side steel girder 2 Temporary braces 10 are respectively installed between the support plates 15 coupled to the upper flanges of the directional steel girders 2,

The gusset plate 5 joined to the steel pillar 1 by welding is bolted to the web of the steel girder 2, and each of the steel girder 2 has a U-shaped iron sheet formwork 13 at predetermined sections of both ends. ) Is installed, the cast iron formwork 13 is filled with the cast-in-place concrete (4) and a plurality of reinforcing bars (7) are installed on the upper portion to reinforce both ends of the steel girder. .

삭제delete

또한 본 발명은 소정 간격으로 설치된 한 쌍의 강재 기둥(1)과 상기 강재 기둥(1) 사이에 결합되는 장변방향 강재 거더(16)에 있어서, 상기 장변방향 강재 거더(16)의 양 단부에서 중심방향으로 소정 거리에는 각각 춤이 작은 강재 거더(11)가 설치되고, 상기 장변방향 강재 거더(16)의 중앙부에는 춤이 큰 강재 거더(12)가 설치되되,

상기 춤이 큰 강재 거더(12)의 양 단부는 상기 춤이 작은 강재 거더(11)의 단부와 결합될 수 있도록 상부 플랜지와 웨브의 일부가 절개되도록 형성되고, 상기 춤이 큰 강재 거더(12)의 절개된 양 단부와 상기 춤이 작은 강재 거더(11)의 일단은 각각 용접에 의해 접합되는 것을 특징으로 한다.

또한 본 발명은 한 쌍의 강재 기둥(1)을 소정 간격으로 설치하는 단계; 상기 강재 기둥(1)에 단변방향으로 상기 가설 브레이스와 강합성 거더를 설치하고, 장변방향으로 상기 변단면 강재 거더를 설치하는 단계; 상기 강재 기둥 주위에 사각형상의 개구부를 형성하고 슬래브를 타설하는 단계;

상기 강재 기둥 주위의 사각형상 개구부에 철근을 보강하고 콘크리트를 타설하여 상기 강재 기둥을 철근콘크리트로 보강하는 단계; 상기 가설 브레이스(10)를 절단하여 해체하는 단계;로 구성되는 것을 것을 특징으로 한다.
In addition, the present invention is a long side steel girders (16) coupled between the pair of steel pillars (1) and the steel pillars (1) provided at predetermined intervals, the center at both ends of the long side steel girders (16) The steel girders 11 with small dances are installed at predetermined distances in the direction, and the steel girders 12 with large dances are installed at the central portion of the long side steel girders 16.

Both ends of the large steel girders 12 of the dance are formed so that a portion of the upper flange and the web is cut so that the dancing can be combined with the ends of the small steel girders 11, the large steel girders 12 of the dance Both ends of the cut and one end of the dance steel girders 11 are characterized in that they are joined by welding, respectively.

In addition, the present invention comprises the steps of installing a pair of steel poles (1) at a predetermined interval; Installing the temporary brace and the composite girder in the short side direction and installing the side sectional steel girder in the long side direction; Forming a rectangular opening around the steel column and placing slab;

Reinforcing steel bars in the rectangular openings around the steel columns and placing concrete to reinforce the steel columns with reinforced concrete; Characterized in that consisting of; cutting the hypothesis brace 10 to dismantle.

삭제delete

삭제delete

삭제delete

상기와 같은 본 발명의 건축구조물에 사용되는 단변방향 강재 거더는 건축구조물을 축조하는 과정에서는 강재 거더의 단변방향으로 가설 브레이스를 설치하여 강재 거더가 3경간 연속스팬으로 거동하게 되고,
In the short side direction steel girder used in the building structure of the present invention as described above, in the process of constructing the building structure, by installing a temporary brace in the short side direction of the steel girder, the steel girder behaves as a three span continuous span,

영구하중이 작용하는 경우에는 단변방향 강재 거더의 양 단부의 단면강성이 증대되도록 상기 강재 거더의 양 단부는 철판거푸집을 설치하고 그 내부를 철근콘크리트로 보강하여 강합성 기둥에 일체화되도록 결합됨으로써, 종래기술의 단변방향 강재 거더에 사용되는 강재량의 30 ~ 40%를 절감하며, 이로 인해 단변방향 강재 거더의 단면이 감축되고 경량화되는 효과가 있다.
When the permanent load is applied, both ends of the steel girder are joined to be integrated into the steel composite pillar by installing steel sheet formwork and reinforcing the inside with reinforced concrete so that the cross-section stiffness of both ends of the short side steel girder is increased. It saves 30 to 40% of the amount of steel used in the short-side steel girders of the technology, which reduces the cross-section of the short-side steel girders and reduces the weight.

또한 강재 거더의 장변방향으로는 휨응력에 따라 강재 거더의 양 단부와 중앙부의 크기에 차이를 두어 상기 강재 거더를 변단면으로 처리함으로써, 종래기술의 장변방향 강재 거더에 사용되는 강재량의 10 ~ 15%를 절감하며, 장변방향 강재 거더가 경량화되는 효과가 있다.
In addition, in the long side direction of the steel girder by treating the steel girder as a side cross-section with a difference in the size of both ends and the center portion of the steel girder according to the bending stress, 10 ~ 15 of the amount of steel used in the long side steel girder of the prior art It saves%, and the long side steel girders are effective in weight reduction.

그리고 상기 장,단변방향 강재 거더의 경량화로 인해 기둥과 기초의 자중이 감소됨으로써 건물 구조 시스템이 경량화되어 경제적이고, 종래기술의 프리캐스트 콘크리트 합성거더에 비해 단면이 감축되어 경량이며, 단변방향 강재 거더의 양 단부는 현장타설 콘크리트를 사용하므로 운반 및 설치작업이 용이한 효과가 있다.In addition, the weight of the columns and foundations is reduced due to the light weight of the long and short side steel girders, thereby reducing the weight of the building structure system and economical. Both ends of the cast-in-place concrete is easy to carry and install the effect is easy.

도 1은 종래기술인 PC 합성거더를 사용한 지하구조물의 평면도
도 2는 도 1의 단변방향 PC 합성거더의 휨모멘트도
도 3은 도 1의 A-A' 단면도
도 4는 도 3의 C-C' 단면도
도 5는 도 1의 B-B' 단면도
도 6은 도 5의 D-D' 단면도와 E-E' 단면도
도 7은 본 발명의 일실시예인 지하구조물의 평면도
도 8은 도 7의 단변방향 PC 합성거더의 휨모멘트도
도 9는 본 발명의 일실시예인 지하구조물의 사시도
도 10은 도 7의 F-F' 단면도
도 11은 도 10의 I-I' 단면도와 J-J' 단면도
도 12는 도 7의 G-G'단면도
도 13은 도 12의 K-K' 단면도와 L-L' 단면도
도 14(a), (b)는 도 12의 변단면 강재 거더의 접합상세 단면도
도 15는 본 발명의 다른 실시예인 지하구조물의 사시도
도 16은 도 15의 지하구조물에 슬래브가 시공된 상태의 사시도
1 is a plan view of an underground structure using a conventional PC composite girder
FIG. 2 is a bending moment diagram of the short side PC composite girder of FIG.
3 is a cross-sectional view taken along line AA ′ of FIG. 1.
4 is a cross-sectional view taken along line CC ′ of FIG. 3.
5 is a cross-sectional view taken along line BB ′ of FIG. 1.
6 is a cross-sectional view taken along line DD ′ and EE ′ of FIG. 5.
7 is a plan view of an underground structure that is an embodiment of the present invention
8 is a bending moment diagram of the short side PC composite girders of FIG.
9 is a perspective view of an underground structure which is an embodiment of the present invention
FIG. 10 is a cross-sectional view taken along line FF ′ of FIG. 7.
FIG. 11 is a sectional view taken along line II ′ and JJ ′ of FIG. 10.
12 is a cross-sectional view taken along the line G-G 'of FIG.
13 is a cross-sectional view taken along line KK 'and LL' of FIG.
Figure 14 (a), (b) is a bonded cross-sectional view of the cross-sectional steel girders of Figure 12
15 is a perspective view of an underground structure which is another embodiment of the present invention
16 is a perspective view of a state in which the slab construction in the underground structure of FIG.

본 발명이 속하는 기술분야에서 통상의 지식을 가진 자가 본 발명을 용이하게 실시할 수 있도록 본 발명의 바람직한 일실시예의 도면을 참조하여 설명하면 다음과 같다.
DETAILED DESCRIPTION OF EXEMPLARY EMBODIMENTS Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 7은 본 발명의 일실시예인 지하구조물의 평면도이고, 도 8은 도 7의 단변방향 PC 합성거더의 휨모멘트도로, 지하구조물 축조 시 소정 간격으로 설치된 한 쌍의 강재 기둥(1)에 결합되는 장,단변방향의 강재 거더에 있어서, 거더의 단변방향으로는 상기 한 쌍의 강재 기둥(1)의 플랜지와 강재 거더(2) 양 단부의 상부 플랜지 사이에 각각 가설 브레이스(13)를 설치함으로써,
7 is a plan view of an underground structure according to an embodiment of the present invention, and FIG. 8 is a bending moment of the short side PC composite girder of FIG. 7, which is coupled to a pair of steel columns 1 installed at predetermined intervals when constructing an underground structure. In the long and short side steel girders, in the short side direction of the girder, a temporary brace 13 is provided between the flanges of the pair of steel pillars 1 and the upper flanges of both ends of the steel girders 2, respectively.

상기 강재 거더(2)는 도 8의 휨모멘트도와 같이 3경간 연속스팬으로 거동하게 하여 그 춤(depth)이 저감되어 경량화되고, 이로 인해 종래기술의 단변방향 강재 거더에 사용되는 강재량의 30 ~ 40%가 절감되며, 이는 지상구조물에도 사용 가능하다.
The steel girder (2) is reduced to light weight by reducing the depth (depth) to behave as a three-span continuous span as shown in the bending moment diagram of Figure 8, 30 ~ of the amount of steel used in the short-side steel girders of the prior art 40% savings are available for ground structures.

또한 거더의 장변방향으로는 강재 거더의 휨응력에 따라 중앙부는 춤이 큰 강재 거더(12)를 사용하고 양 단부는 춤이 작은 강재 거더(11)를 사용하여 강재 거더를 변단면으로 형성함으로써, 종래기술의 장변방향 강재 거더에 사용되는 강재량의 10 ~ 15%가 절감되며, 이로 인해 장변방향 강재 거더는 경량화되고 이는 지상구조물에도 사용 가능하다.
In addition, in the long side direction of the girder, according to the bending stress of the steel girder, by using the steel girders 12 with a large dance and the steel girders 11 with small dances at both ends, the steel girders are formed in the cross section, Ten to fifteen percent of the steel used in the long side girder of the technology is saved, which makes the long side girder lighter and can be used for ground structures.

도 10은 도 7의 F-F' 단면도이고, 도 11은 도 10의 I-I' 단면도와 J-J' 단면도로, 소정 간격으로 설치된 한 쌍의 강재 기둥(1)과 상기 강재 기둥(1) 사이에 결합되는 단변방향 강재 거더(2)에 있어서,

상기 단변방향 강재 거더(2)의 상면으로부터 소정 높이에 위치한 상기 강재 기둥(1) 플랜지에 결합된 지지플레이트(15)와 상기 단변방향 강재 거더(2)의 양 단부에서 거더의 중심방향으로 소정 거리에 위치한 상기 단변방향 강재 거더(2)의 상부 플랜지에 결합된 지지플레이트(15) 사이에는 각각 가설 브레이스(10)가 설치되어 상기 단변방향 강재 거더(2)의 양 단부를 보강한다.
FIG. 10 is a cross-sectional view taken along line FF ′ of FIG. 7, and FIG. 11 is a cross-sectional view taken along line II ′ of FIG. 10 and JJ ′, and a short side coupled between the pair of steel columns 1 and the steel columns 1 provided at predetermined intervals. In the directional steel girders 2,

A predetermined distance in the direction of the center of the girder from both ends of the support plate 15 and the short side steel girder 2 coupled to the flange of the steel column (1) located at a predetermined height from the upper surface of the short side steel girder (2) Temporary braces 10 are installed between the support plates 15 coupled to the upper flanges of the short side steel girder 2 located at each to reinforce both ends of the short side steel girder 2.

슬래브 하부에 위치한 상기 강재 기둥(1)의 플랜지 측면에 용접접합된 가셋 플레이트(5)는 상기 강재 거더(2)의 웨브와 보울트 접합되고, 상기 강재 거더(2) 단부의 소정 구간에는 각각 ∪자형 철판거푸집(13)이 설치되며,
The gasset plate 5 welded to the flange side of the steel column 1 located under the slab is bolted to the web of the steel girder 2 and each has a U-shape in a predetermined section of the end of the steel girder 2. Iron plate formwork 13 is installed,

상기 ∪자형 철판거푸집(13) 내부에는 현장타설 콘크리트(4)가 충전되고 그 상부에 다수의 보강철근(7)이 설치되어 상기 단변방향 강재 거더(2)의 양 단부를 보강하고, 상기 단변방향 강재 거더(2)의 상면에는 스터드 볼트(8)를 설치하여 상기 강재 거더(2)와 슬래브를 일체화하며, 이는 지상구조물에도 사용 가능하다.
The U-shaped sheet metal formwork 13 is filled with in-place casting concrete 4 and a plurality of reinforcing bars 7 are installed thereon to reinforce both ends of the short side steel girders 2, and the short side direction. The upper surface of the steel girder 2 is provided with a stud bolt 8 to integrate the steel girder 2 and the slab, which can be used for ground structures.

도 12는 도 7의 G-G'단면도이고, 도 13은 도 12의 K-K' 단면도와 L-L' 단면도이며, 소정 간격으로 설치된 한 쌍의 강재 기둥(1)과 상기 강재 기둥(1) 사이에 결합되는 장변방향 강재 거더(16)에 있어서,상기 장변방향 강재 거더(16)의 양 단부에서 중심방향으로 소정 거리(지간의 1/4 ~ 1/5)에는 각각 춤이 작은 강재 거더(11)가 설치되고, 상기 장변방향 강재 거더(16)의 중앙부에는 춤이 큰 강재 거더(12)가 설치되되,
FIG. 12 is a cross-sectional view taken along line G-G 'of FIG. 7, and FIG. 13 is a cross-sectional view taken along line KK' and LL 'of FIG. 12, and is coupled between a pair of steel columns 1 and the steel columns 1 provided at predetermined intervals. In the long side steel girders 16, the steel girders 11 having small dances are respectively disposed at predetermined distances (1/4 to 1/5 of an interval) from both ends of the long side steel girders 16 toward the center. Is installed, in the central portion of the long side steel girders 16 is installed a large steel girders 12,

상기 춤이 큰 강재 거더(12)의 양 단부는 상기 춤이 작은 강재 거더(11)의 단부와 결합될 수 있도록 상부 플랜지와 웨브의 일부가 절개되도록 형성되고, 상기 춤이 큰 강재 거더(12)의 절개된 양 단부와 상기 춤이 작은 강재 거더(11)의 일단은 각각 용접에 의해 접합되며, 이는 지상구조물에도 사용 가능하다.
Both ends of the large steel girders 12 of the dance are formed so that a portion of the upper flange and the web is cut so that the dancing can be combined with the ends of the small steel girders 11, the large steel girders 12 of the dance Both ends of the cut and one end of the dance steel girders 11 are respectively joined by welding, which can be used for ground structures.

또한 상기 춤이 작은 강재 거더(11)의 일단은 단변방향 강재거더(2) 중앙부의 웨브에 설치된 가셋 플레이트(5)와 보울트로 힌지접합된다.
In addition, one end of the small steel girders 11 is hinge-bonded with the gusset plate 5 provided in the web of the central portion of the short side steel girders 2.

도 9는 본 발명의 일실시예인 지하구조물의 사시도로, 소정의 간격을 두고 설치된 강재 기둥 사이에 장,단변방향 강재 거더를 설치함에 있어서, 단변방향의 강재 거더(2)는 양 단부의 소정 구간에 ∪자형 철판거푸집(13)을 설치하고 그 내부에 현장타설 콘크리트를 충전하고 그 상부에는 다수의 보강철근(7)을 설치하며,

상기 강재 기둥(1) 플랜지에 결합된 지지플레이트(15)와 상기 단변방향 강재 거더(2)의 상부 플랜지에 결합된 지지플레이트(15) 사이에는 각각 가설 브레이스(10)를 설치하여 단변방향 강재 거더(2)의 양 단부를 보강한다.
9 is a perspective view of an underground structure according to an embodiment of the present invention. In installing long and short side steel girders between steel pillars installed at predetermined intervals, the steel girders 2 in the short side direction have predetermined sections at both ends. Install the U-shaped iron sheet formwork (13) on the inside and fill the cast-in-place concrete therein, and install a plurality of reinforcing bars (7) at the upper part thereof,

Temporary brace 10 is installed between the support plate 15 coupled to the steel pillar 1 flange and the support plate 15 coupled to the upper flange of the short side steel girder 2 to form a short side steel girder. Reinforce both ends of (2).

또한 장변방향에는 휨응력에 따라 강재 거더의 양 단부와 중앙부의 크기에 차이를 두어 상기 강재 거더를 변단면으로 처리하여 강재 거더의 양 단부는 춤이 작은 장변방향 강재 거더(11)를, 중앙부에는 춤이 큰 장변방향 강재 거더(12)를 설치하여 장변방향 강재 거더의 단면을 효율적으로 형성한다.
In addition, in the long side direction, the steel girders are treated as edges by varying the size of both ends and the center portion of the steel girders according to the bending stress, so that both ends of the steel girders have a long side steel girders 11 having a small dance, and a dance at the center portion. This long side steel girder 12 is provided to efficiently form the cross section of the long side steel girder.

도 14(a), (b)는 도 12의 변단면 강재 거더의 접합상세 단면도로, 도 14(a)에서 춤이 큰 강재 거더(12)의 양 단부는 상기 춤이 작은 강재 거더(11)의 단부와 결합될 수 있도록 상부 플랜지와 웨브의 일부가 절개되도록 형성되고, 상기 춤이 작은 강재 거더(11)의 단부는 상기 춤이 큰 강재 거더(12)의 절개된 양 단부와 용접접합된다.
14 (a) and 14 (b) are detailed cross-sectional views of the sectional steel girders of FIG. 12, and both ends of the steel girders 12 having large dances in FIG. 14 (a) are steel girders 11 having small dances. The upper flange and a portion of the web are formed to be cut so that they can be combined with the ends of the dance, and the end of the small steel girder 11 is welded with both cut ends of the large steel girder 12.

또한 도 14(b)에서 되어, 상기 춤이 큰 강재 거더(12)의 절개된 단부의 웨브 하단에는 소정 길이의 홈을 형성하고, 상기 홈에는 수평 스티프너(14)가 용접접합되며, 상기 수평 스티프너(14)의 단부와 상기 춤이 작은 강재 거더(11)의 하부 플랜지 단부는 용접 접합되고, 상기 춤이 작은 강재 거더(11)의 단부 웨브와 상기 춤이 큰 강재 거더(12)의 절개된 단부 웨브는 용접접합되어, 상기 수평 스티프너(14)는 상기 춤이 작은 강재 거더(11)의 하부 플랜지에 작용하는 인장력 또는 압축력을 지지한다.
In addition, in Fig. 14 (b), a groove of a predetermined length is formed at the bottom of the web of the cut end of the large steel girders 12, the horizontal stiffener 14 is welded to the groove, the horizontal stiffener The end of 14 and the lower flange end of the small steel girder 11 are welded together, the end web of the small steel girder 11 and the cut end of the large steel girder 12. The web is welded so that the horizontal stiffener 14 supports a tensile or compressive force acting on the lower flange of the small steel girder 11.

도 15는 본 발명의 다른 실시예인 지하구조물의 사시도이고, 도 16은 도 15의 지하구조물에 슬래브가 시공된 상태의 사시도로, 소정 간격으로 설치된 한 쌍의 강재 기둥(1)과 상기 강재 기둥(1) 사이에 결합되는 단변방향 강재 거더(2)에 있어서,
15 is a perspective view of an underground structure, which is another embodiment of the present invention, and FIG. 16 is a perspective view of a slab installed in the underground structure of FIG. 15, and a pair of steel pillars 1 and the steel pillars installed at predetermined intervals ( 1) In the short side steel girder (2) coupled between,

상기 단변방향 강재 거더(2)의 하면으로부터 소정 높이에 위치한 상기 강재 기둥(1) 플랜지에 결합된 지지플레이트(15)와 상기 단변방향 강재 거더(2)의 양 단부에서 거더의 중심방향으로 소정 거리에 위치한 상기 단변방향 강재 거더(2)의 하부 플랜지에 결합된 지지플레이트(15) 사이에는 각각 가설 브레이스(10)가 설치되어 상기 단변방향 강재 거더(2)의 양 단부를 보강하며, 이는 지상구조물에도 사용 가능하다.
A predetermined distance in the direction of the center of the girder from both ends of the support plate 15 and the short side steel girders (2) coupled to the flange of the steel column (1) located at a predetermined height from the lower surface of the short side steel girders (2) Temporary braces 10 are installed between the support plates 15 coupled to the lower flanges of the short side steel girder 2 located at each to reinforce both ends of the short side steel girder 2, which is a ground structure. Can also be used.

상기 단변방향 강재 거더에 상기 가설 브레이스와 강합성 거더을 사용하고, 장변방향 강재 거더에 상기 변단면 강재 거더를 사용하여 건축구조물을 축조하는 방법은 한 쌍의 강재 기둥을 소정 간격으로 설치하는 단계; 상기 강재 기둥에 장변방향으로 상기 변단면 강재 거더를 설치하고, 단변방향으로 상기 가설 브레이스와 강합성 거더를 설치하는 단계;
The method for constructing a building structure using the temporary brace and the composite girder for the short side steel girders and the cross sectional steel girder for the long side steel girders may include installing a pair of steel columns at predetermined intervals; Installing the side sectional steel girders in the longitudinal direction to the steel poles, and installing the temporary braces and the composite girder in the short sides;

상기 강재 기둥 주위에 사각형상의 개구부를 형성하여 슬래브를 타설하는 단계; 상기 강재 기둥 주위의 사각형상 개구부에 철근을 보강하고 콘크리트를 타설하여 상기 강재 기둥을 철근콘크리트로 보강하는 단계(미도시); 상기 가설 브레이스를 절단하여 해체하는 단계;로 시공되는 것을 특징으로 한다.Placing a slab by forming a rectangular opening around the steel pillar; Reinforcing the steel bars in the rectangular openings around the steel columns and placing concrete to reinforce the steel columns with reinforced concrete (not shown); Cutting the hypothesis brace to dismantle; characterized in that the construction as.

1 : 강재 기둥 2 : 단변방향 강재 거더
3 : PC 합성거더 4 : 현장타설 콘크리트
5 : 가셋 플레이트(gusset plate) 6 : 슬래브
7 : 보강철근 8 : 스터드 볼트(stud bolt)
9 : PC 강선 10 : 가설 브레이스
11 : 춤이 작은 강재 거더 12 : 춤이 큰 강재 거더
13 : ∪자형 철판 거푸집 14 : 수평 스티프너
15 : 지지플레이트 16 : 장변방향 강재 거더
Lx : 단변방향 지간 Ly : 장변방향 지간
M ; 휨모멘트
1: Steel column 2: Short-side steel girder
3: PC composite girder 4: Cast-in-place concrete
5: gusset plate 6: slab
7: rebar 8: stud bolt
9: PC steel wire 10: Hypothesis brace
11: Dancing Steel Girder Small 12: Dancing Steel Girder Small
13: U-shaped iron formwork 14: horizontal stiffener
15: support plate 16: long side steel girders
Lx: Short side span Ly: Long side span
M; Bending moment

Claims (7)

소정 간격으로 설치된 한 쌍의 강재 기둥(1)과 상기 강재 기둥(1) 사이에 결합되는 단변방향 강재 거더(2)에 있어서,
상기 단변방향 강재 거더(2)의 상면으로부터 소정 높이에 위치한 상기 강재 기둥(1) 플랜지에 결합된 지지플레이트(15)와 상기 단변방향 강재 거더(2)의 양 단부에서 거더의 중심방향으로 소정 거리에 위치한 상기 단변방향 강재 거더(2)의 상부 플랜지에 결합된 지지플레이트(15) 사이에는 각각 가설 브레이스(10)가 설치되고,
상기 강재 기둥(1)에 용접에 의해 접합되는 가셋 플레이트(5)는 상기 강재 거더(2)의 웨브와 보울트 접합되고, 상기 강재 거더(2) 양 단부의 소정 구간에는 각각 ∪자형 철판거푸집(13)이 설치되며,
상기 ∪자형 철판거푸집(13) 내부에는 현장타설 콘크리트(4)가 충전되고 그 상부에는 다수의 보강철근(7)이 설치되어 상기 단변방향 강재 거더(2)의 양 단부를 보강하는 것을 특징으로 하는 건축구조물에 사용되는 가설 브레이스.
In the short side steel girders (2) coupled between the pair of steel poles (1) and the steel poles (1) provided at predetermined intervals,
A predetermined distance in the direction of the center of the girder from both ends of the support plate 15 and the short side steel girder 2 coupled to the flange of the steel column (1) located at a predetermined height from the upper surface of the short side steel girder (2) Temporary braces 10 are installed between the support plates 15 coupled to the upper flanges of the short-side steel girder 2 located at
The gusset plate 5 joined to the steel pillar 1 by welding is bolted to the web of the steel girder 2, and each of the steel girder 2 has a U-shaped iron sheet formwork 13 at predetermined sections of both ends. ) Will be installed,
The U-shaped sheet metal formwork 13 is filled with cast-in-place concrete (4) and a plurality of reinforcing bars (7) are installed on the upper portion to reinforce both ends of the short-side steel girders (2) Hypothesis braces used in building structures.
소정 간격으로 설치된 한 쌍의 강재 기둥(1)과 상기 강재 기둥(1) 사이에 결합되는 단변방향 강재 거더(2)에 있어서,
상기 단변방향 강재 거더(2)의 하면으로부터 소정 높이에 위치한 상기 강재 기둥(1) 플랜지에 결합된 지지플레이트(15)와 상기 단변방향 강재 거더(2)의 양 단부에서 거더의 중심방향으로 소정 거리에 위치한 상기 단변방향 강재 거더(2)의 하부 플랜지에 결합된 지지플레이트(15) 사이에는 각각 가설 브레이스(10)가 설치되고,
상기 강재 기둥(1)에 용접에 의해 접합되는 가셋 플레이트(5)는 상기 강재 거더(2)의 웨브와 보울트 접합되고, 상기 강재 거더(2) 양 단부의 소정 구간에는 각각 ∪자형 철판거푸집(13)이 설치되며,
상기 ∪자형 철판거푸집(13) 내부에는 현장타설 콘크리트(4)가 충전되고 그 상부에는 다수의 보강철근(7)이 설치되어 상기 단변방향 강재 거더(2)의 양 단부를 보강하는 것을 특징으로 하는 건축구조물에 사용되는 가설 브레이스.
In the short side steel girders (2) coupled between the pair of steel poles (1) and the steel poles (1) provided at predetermined intervals,
A predetermined distance in the direction of the center of the girder from both ends of the support plate 15 and the short side steel girders (2) coupled to the flange of the steel column (1) located at a predetermined height from the lower surface of the short side steel girders (2) Temporary braces 10 are respectively installed between the support plates 15 coupled to the lower flanges of the short-side steel girder 2 located at
The gusset plate 5 joined to the steel pillar 1 by welding is bolted to the web of the steel girder 2, and each of the steel girder 2 has a U-shaped iron sheet formwork 13 at predetermined sections of both ends. ) Will be installed,
The U-shaped sheet metal formwork 13 is filled with cast-in-place concrete (4) and a plurality of reinforcing bars (7) are installed on the upper portion to reinforce both ends of the short-side steel girders (2) Hypothesis braces used in building structures.
삭제delete 소정 간격으로 설치된 한 쌍의 강재 기둥(1)과 상기 강재 기둥(1) 사이에 결합되는 장변방향 강재 거더(16)에 있어서,
상기 장변방향 강재 거더(16)의 양 단부에서 중심방향으로 소정 거리에는 각각 춤이 작은 강재 거더(11)가 설치되고, 상기 장변방향 강재 거더(16)의 중앙부에는 춤이 큰 강재 거더(12)가 설치되되,
상기 춤이 큰 강재 거더(12)의 양 단부는 상기 춤이 작은 강재 거더(11)의 단부와 결합될 수 있도록 상부 플랜지와 웨브의 일부가 절개되도록 형성되고,
상기 춤이 큰 강재 거더(12)의 절개된 양 단부와 상기 춤이 작은 강재 거더(11)의 일단은 각각 용접에 의해 접합되는 것을 특징으로 하는 건축구조물에 사용되는 변단면 강재 거더.
In the long side steel girders 16 coupled between the pair of steel pillars 1 and the steel pillars 1 installed at predetermined intervals,
Steel girders 11 having small dances are installed at predetermined distances from both ends of the long side steel girders 16 in the center direction, and steel girders 12 having large dances are provided at a central portion of the long side steel girders 16. Is installed,
Both ends of the large steel girders 12 of the dance are formed so that a portion of the upper flange and the web are cut so that the dancing can be combined with the ends of the small steel girders 11,
Both ends of the cut steel girder (12) of the large dance girder and one end of the small steel girder (11) are each joined by welding, characterized in that the steel girder used in the building structure.
제4항에 있어서, 상기 춤이 큰 강재 거더(12)의 절개된 단부의 웨브 하단에는 소정 길이의 홈을 형성하고, 상기 홈에는 수평 스티프너(14)가 용접접합되며, 상기 수평 스티프너(14)의 단부와 상기 춤이 작은 강재 거더(11)의 하부 플랜지 단부는 용접 접합되고, 상기 춤이 작은 강재 거더(11)의 단부 웨브와 상기 춤이 큰 강재 거더(12)의 절개된 단부 웨브는 용접접합되는 것을 특징으로 하는 건축구조물에 사용되는 변단면 강재 거더.5. The groove according to claim 4, wherein a groove of a predetermined length is formed at the bottom of the web of the cut end of the large steel girder 12, and a horizontal stiffener 14 is welded to the groove, and the horizontal stiffener 14 is formed. The end of the lower flange end of the steel girders 11 and the dance is welded, the end web of the small steel girders 11 and the cut end web of the steel girders 12 of the dance is welded. Sectional steel girders used for building structures, characterized in that the joining. 한 쌍의 강재 기둥(1)을 소정 간격으로 설치하는 단계;
상기 강재 기둥(1)에는 단변방향으로 상기 청구항 1의 가설 브레이스와 강합성 거더를 설치하고, 장변방향으로 상기 청구항 4의 변단면 강재 거더를 설치하는 단계; 상기 강재 기둥 주위에는 사각형상의 개구부를 형성하고 슬래브를 타설하는 단계;
상기 강재 기둥 주위의 사각형상 개구부에는 철근을 보강하고 콘크리트를 타설하여 상기 강재 기둥을 철근콘크리트로 보강하는 단계;
상기 가설 브레이스(10)는 절단되어 해체되는 단계;로 구성되는 것을 특징으로 하는 건축구조물 축조공법.
Installing a pair of steel pillars 1 at predetermined intervals;
Installing the temporary brace and the composite girder of claim 1 in a short side direction and installing the cross-sectional steel girder of claim 4 in a long side direction; Forming a rectangular opening around the steel pillar and placing slab;
Reinforcing steel bars in the rectangular openings around the steel columns and placing concrete to reinforce the steel columns with reinforced concrete;
The temporary brace 10 is cut and dismantled; building structure construction method, characterized in that consisting of.
제6항에 있어서, 상기 청구항 1의 가설 브레이스와 강합성 거더는 상기 청구항 2의 가설 브레이스와 강합성 거더로 대치되어 구성되는 것을 특징으로 하는 건축구조물 축조공법.
The construction structure construction method according to claim 6, wherein the temporary brace and the rigid girder of claim 1 are configured to be replaced by the temporary brace and the rigid girder of claim 2.
KR1020120024832A 2012-03-12 2012-03-12 A temporary brace and a composite steel girder, a shift section steel girder used an building structure and thereof construction method Active KR101219995B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020120024832A KR101219995B1 (en) 2012-03-12 2012-03-12 A temporary brace and a composite steel girder, a shift section steel girder used an building structure and thereof construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020120024832A KR101219995B1 (en) 2012-03-12 2012-03-12 A temporary brace and a composite steel girder, a shift section steel girder used an building structure and thereof construction method

Publications (1)

Publication Number Publication Date
KR101219995B1 true KR101219995B1 (en) 2013-01-09

Family

ID=47841447

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020120024832A Active KR101219995B1 (en) 2012-03-12 2012-03-12 A temporary brace and a composite steel girder, a shift section steel girder used an building structure and thereof construction method

Country Status (1)

Country Link
KR (1) KR101219995B1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101474371B1 (en) * 2013-10-02 2014-12-24 (주)천마엔지니어링 Girder structure and construction method for structure without temporary structure using the same
CN114086792A (en) * 2021-12-03 2022-02-25 广州容柏生建筑工程设计咨询有限公司 Reinforced structure and method for increasing section through point position connection
CN114877239A (en) * 2022-05-17 2022-08-09 玉田县弘泰线材有限公司 High-strength special-shaped I-steel and processing method thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002004435A (en) * 2000-06-22 2002-01-09 Kajima Corp Braces and frames with braces
KR20040060276A (en) * 2002-12-30 2004-07-06 유각열 Beam support jack
JP2005299138A (en) 2004-04-08 2005-10-27 Shimizu Corp Reinforcement structure for ramen frames
KR100759041B1 (en) 2007-05-22 2007-09-17 주식회사 세진에스씨엠 Connection structure and connection method of pillars and cheolgolbo of building

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002004435A (en) * 2000-06-22 2002-01-09 Kajima Corp Braces and frames with braces
KR20040060276A (en) * 2002-12-30 2004-07-06 유각열 Beam support jack
JP2005299138A (en) 2004-04-08 2005-10-27 Shimizu Corp Reinforcement structure for ramen frames
KR100759041B1 (en) 2007-05-22 2007-09-17 주식회사 세진에스씨엠 Connection structure and connection method of pillars and cheolgolbo of building

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101474371B1 (en) * 2013-10-02 2014-12-24 (주)천마엔지니어링 Girder structure and construction method for structure without temporary structure using the same
CN114086792A (en) * 2021-12-03 2022-02-25 广州容柏生建筑工程设计咨询有限公司 Reinforced structure and method for increasing section through point position connection
CN114877239A (en) * 2022-05-17 2022-08-09 玉田县弘泰线材有限公司 High-strength special-shaped I-steel and processing method thereof

Similar Documents

Publication Publication Date Title
KR100951097B1 (en) Slab and subgrade external wall structure and method for constructing underground slab and subgrade external wall, bracket
KR101379305B1 (en) Wall structure manufacturing method using precast front wall panel and precast back wall panel
KR100969586B1 (en) Rhamen bridge and construction method there of
KR20120096605A (en) Bracket support type downward construction system and method
KR101228012B1 (en) Precast concrete column connecting structure
CN112411355A (en) Steel-concrete composite bridge and construction method thereof
KR100938395B1 (en) Construction method of underground roadway using steel composite wall pile
KR101366903B1 (en) Girder having truss section and construction method of bridge and pedestrian overpass using it
KR101263370B1 (en) Precast end-block with girder connection member and bridge construction method using ths same
KR101735077B1 (en) Bridge deck using precast concrete panel
KR100856723B1 (en) Steel frame reverse casting system and method using cantilever type girder
KR20120136071A (en) Composite beam with partially filled concrete
KR101219995B1 (en) A temporary brace and a composite steel girder, a shift section steel girder used an building structure and thereof construction method
JP4585614B1 (en) Method for constructing synthetic steel slab bridge, ribbed steel slab, and synthetic steel slab bridge
KR20100108927A (en) The method of manufacturing for manufactured girder of composition style p.s.c form that have half section slab and the method of constructing for bridge by using the upper method
KR101264577B1 (en) Steel frame concrete beam and manufacturing method of the same
KR20080093261A (en) Steel composite bridge construction method
KR101940876B1 (en) Composite girder and construction method thereof
KR101329443B1 (en) Precast concrete frame and its construction method for buildings using precast concrete slab continued by post tensioning
KR102269141B1 (en) Deck plate wall installation method using underground pavement
KR200417438Y1 (en) Support bracket for beam and slab construction
KR101521946B1 (en) Enlarged capital of steel framed reinforced concrete column
JP6143068B2 (en) Underground structure of building
CN109137757A (en) A kind of anti-buckling structure of large span box girder with corrugated steel webs and construction method
KR101632911B1 (en) Bridge using end prestressed beam and the construction method therewith

Legal Events

Date Code Title Description
A201 Request for examination
PA0109 Patent application

St.27 status event code: A-0-1-A10-A12-nap-PA0109

PA0201 Request for examination

St.27 status event code: A-1-2-D10-D11-exm-PA0201

A302 Request for accelerated examination
PA0302 Request for accelerated examination

St.27 status event code: A-1-2-D10-D17-exm-PA0302

St.27 status event code: A-1-2-D10-D16-exm-PA0302

D13-X000 Search requested

St.27 status event code: A-1-2-D10-D13-srh-X000

D14-X000 Search report completed

St.27 status event code: A-1-2-D10-D14-srh-X000

P11-X000 Amendment of application requested

St.27 status event code: A-2-2-P10-P11-nap-X000

P13-X000 Application amended

St.27 status event code: A-2-2-P10-P13-nap-X000

P11-X000 Amendment of application requested

St.27 status event code: A-2-2-P10-P11-nap-X000

P13-X000 Application amended

St.27 status event code: A-2-2-P10-P13-nap-X000

E902 Notification of reason for refusal
PE0902 Notice of grounds for rejection

St.27 status event code: A-1-2-D10-D21-exm-PE0902

E13-X000 Pre-grant limitation requested

St.27 status event code: A-2-3-E10-E13-lim-X000

P11-X000 Amendment of application requested

St.27 status event code: A-2-2-P10-P11-nap-X000

P13-X000 Application amended

St.27 status event code: A-2-2-P10-P13-nap-X000

E701 Decision to grant or registration of patent right
PE0701 Decision of registration

St.27 status event code: A-1-2-D10-D22-exm-PE0701

GRNT Written decision to grant
PR0701 Registration of establishment

St.27 status event code: A-2-4-F10-F11-exm-PR0701

PR1002 Payment of registration fee

St.27 status event code: A-2-2-U10-U11-oth-PR1002

Fee payment year number: 1

PG1601 Publication of registration

St.27 status event code: A-4-4-Q10-Q13-nap-PG1601

FPAY Annual fee payment

Payment date: 20160125

Year of fee payment: 4

PR1001 Payment of annual fee

St.27 status event code: A-4-4-U10-U11-oth-PR1001

Fee payment year number: 4

P22-X000 Classification modified

St.27 status event code: A-4-4-P10-P22-nap-X000

FPAY Annual fee payment

Payment date: 20161223

Year of fee payment: 5

PR1001 Payment of annual fee

St.27 status event code: A-4-4-U10-U11-oth-PR1001

Fee payment year number: 5

FPAY Annual fee payment

Payment date: 20180102

Year of fee payment: 6

PR1001 Payment of annual fee

St.27 status event code: A-4-4-U10-U11-oth-PR1001

Fee payment year number: 6

FPAY Annual fee payment

Payment date: 20190102

Year of fee payment: 7

PR1001 Payment of annual fee

St.27 status event code: A-4-4-U10-U11-oth-PR1001

Fee payment year number: 7

FPAY Annual fee payment

Payment date: 20200302

Year of fee payment: 8

PR1001 Payment of annual fee

St.27 status event code: A-4-4-U10-U11-oth-PR1001

Fee payment year number: 8

PR1001 Payment of annual fee

St.27 status event code: A-4-4-U10-U11-oth-PR1001

Fee payment year number: 9

R18-X000 Changes to party contact information recorded

St.27 status event code: A-5-5-R10-R18-oth-X000

S20-X000 Security interest recorded

St.27 status event code: A-4-4-S10-S20-lic-X000

R18-X000 Changes to party contact information recorded

St.27 status event code: A-5-5-R10-R18-oth-X000

PN2301 Change of applicant

St.27 status event code: A-5-5-R10-R13-asn-PN2301

St.27 status event code: A-5-5-R10-R11-asn-PN2301

R18-X000 Changes to party contact information recorded

St.27 status event code: A-5-5-R10-R18-oth-X000

PR1001 Payment of annual fee

St.27 status event code: A-4-4-U10-U11-oth-PR1001

Fee payment year number: 10

PR1001 Payment of annual fee

St.27 status event code: A-4-4-U10-U11-oth-PR1001

Fee payment year number: 11

P14-X000 Amendment of ip right document requested

St.27 status event code: A-5-5-P10-P14-nap-X000

PR1001 Payment of annual fee

St.27 status event code: A-4-4-U10-U11-oth-PR1001

Fee payment year number: 12

PR1001 Payment of annual fee

St.27 status event code: A-4-4-U10-U11-oth-PR1001

Fee payment year number: 13

PR1001 Payment of annual fee

St.27 status event code: A-4-4-U10-U11-oth-PR1001

Fee payment year number: 14

U11 Full renewal or maintenance fee paid

Free format text: ST27 STATUS EVENT CODE: A-4-4-U10-U11-OTH-PR1001 (AS PROVIDED BY THE NATIONAL OFFICE)

Year of fee payment: 14