KR101200596B1 - Reinforcing Device for Double Floor and It's Installation Method - Google Patents
Reinforcing Device for Double Floor and It's Installation Method Download PDFInfo
- Publication number
- KR101200596B1 KR101200596B1 KR1020120060187A KR20120060187A KR101200596B1 KR 101200596 B1 KR101200596 B1 KR 101200596B1 KR 1020120060187 A KR1020120060187 A KR 1020120060187A KR 20120060187 A KR20120060187 A KR 20120060187A KR 101200596 B1 KR101200596 B1 KR 101200596B1
- Authority
- KR
- South Korea
- Prior art keywords
- clip
- double floor
- reinforcement
- bar
- support unit
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F15/00—Flooring
- E04F15/02—Flooring or floor layers composed of a number of similar elements
- E04F15/024—Sectional false floors, e.g. computer floors
- E04F15/02447—Supporting structures
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16B—DEVICES FOR FASTENING OR SECURING CONSTRUCTIONAL ELEMENTS OR MACHINE PARTS TOGETHER, e.g. NAILS, BOLTS, CIRCLIPS, CLAMPS, CLIPS OR WEDGES; JOINTS OR JOINTING
- F16B7/00—Connections of rods or tubes, e.g. of non-circular section, mutually, including resilient connections
- F16B7/18—Connections of rods or tubes, e.g. of non-circular section, mutually, including resilient connections using screw-thread elements
- F16B7/182—Connections of rods or tubes, e.g. of non-circular section, mutually, including resilient connections using screw-thread elements for coaxial connections of two rods or tubes
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- General Engineering & Computer Science (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Floor Finish (AREA)
Abstract
Description
본 발명은 이중 마루의 내진 보강장치 및 그 설치방법에 관한 것으로, 좀 더 상세하게는 전산장비나 측정장비 등을 지지하기 위해 이미 설치된 이중 마루의 상부패널의 전체를 해체하지 않고도 이중 마루의 상부패널을 지지하고 있는 지지구조물을 더욱 보강할 수 있도록 하는 이중 마루 내진 보강장치와 그 설치방법에 관한 것이다.
The present invention relates to a seismic reinforcing device for a double floor and its installation method, and more particularly, to the upper panel of the double floor without dismantling the entire upper panel of the double floor already installed to support the computing equipment or measuring equipment, etc. The present invention relates to a double floor seismic reinforcing device and a method of installing the same to further reinforce the supporting structure supporting the structure.
일반적으로 전산장비나 통신기기 또는 정밀 측정장비 등은 이중 마루의 상부에 설치되는데, 이러한 이중 마루의 내부에는 전원선, 통신선 등을 설치하거나 실내를 일정온도로 유지하기 위한 공조 덕트 등이 설치되며, 이를 위해 통상 실내 바닥에 일정 높이를 가지는 복수의 지지구조물을 일정 간격을 두고 설치한 다음, 이 지지구조물의 상부에는 상부패널을 설치함으로써 바닥과 상부패널 사이에 일정 높이의 공간이 형성되도록 하고 있다.In general, computer equipment, communication equipment, or precision measuring equipment is installed on the upper part of the double floor. Inside the double floor, a power line, a communication line, or an air conditioning duct is installed to maintain a constant temperature. To this end, a plurality of support structures having a predetermined height are usually installed on the indoor floor at regular intervals, and then an upper panel is installed on the upper portion of the support structure to form a space having a predetermined height between the floor and the upper panel.
그리고 이때 지지구조물의 상면에는 고무와 같은 재질로 이루어진 일정 두께의 완충패드를 설치하여 상부 또는 하부로부터 가해지는 충격이나 지진 등에 의한 외력을 어느 정도 흡수함으로써 이에 의해 지지되는 상부패널의 상부에 위치하는 전산장비 등을 보호할 수 있도록 하고 있다.At this time, the upper surface of the support structure by installing a buffer pad of a certain thickness made of a rubber-like material to absorb some of the external force caused by the impact or earthquake from the upper or lower part to be located in the upper part of the upper panel supported by this To protect the equipment.
그러나 종래의 이중 마루의 상부패널은 아무런 보강장치 없이 약 30cm 전후의 높이를 가지며 수직으로 설치되는 지지구조물에 의해서만 지지되어 있기 때문에 수평 방향으로의 흔들림이 발생되거나 외력이 가해지면 지지구조물이 쉽게 파단되거나 쓰러질 우려가 있고, 이 경우 상부패널을 지지하지 못하게 되며 그 결과 상부패널의 상부에 설치된 전산장비, 통신기기 등이 파손되거나 손상될 수 있다.
However, since the upper panel of the conventional double floor has a height of about 30 cm without any reinforcing device and is supported only by a vertically installed support structure, the support structure is easily broken when horizontal shaking or external force is applied. There is a risk of falling, and in this case, the upper panel cannot be supported, and as a result, computing equipment, communication equipment, etc. installed on the upper portion of the upper panel may be damaged or damaged.
최근 상기와 같은 종래의 이중 마루 지지구조물이 가지는 문제점 등을 해결하는 동시에 이중 마루를 더욱 견고하게 지지할 수 있도록 이중 마루 보강장치 등이 제안되고 있는데, 그 하나의 예로서 특허 제10-761955호에 개시된 내진 액세스플로어 지지구조를 들 수 있다.Recently, a double floor reinforcement device and the like have been proposed to solve the problems of the conventional double floor support structure as described above and to support the double floor more firmly. And the disclosed seismic access floor support structure.
상기 문헌에서 제안하고 있는 액세스플로어 지지구조는 도 1에 도시된 바와 같이 나사산이 형성된 수직지지대(200)와, 수직지지대(200)에 체결되어 상하로 이동 가능한 상부연결편(300)과, 수직지지대(200)에 체결되어 상하로 이동가능하며 상부연결편(300) 아래에 이격되도록 위치하는 하부연결편(400)과, 일단이 상부연결편(300)에 결합되고 타단이 인접하는 수직지지대(200)에 체결된 상부연결편(300)에 결합되는 수평보강지지대(500) 및 일단이 하부연결편(400)에 결합되고 타단이 수평보강지지대(500)에 결합되는 경사보강지지대(600)로 이루어지고, 따라서 이러한 이중 마루 지지구조는 반드시 이중 마루의 상부패널이 설치되기 전에 설치되어야 하며, 상부패널의 상부에 전산장비 등이 설치되고 난 다음에는 실질적으로 설치가 불가능하며, 따라서 기설치된 이중 마루를 보강하기 위한 구조물로서는 채택할 수 없다는 문제가 있다.
The access floor support structure proposed in the document is a
본 발명은 상기와 같은 종래의 이중 마루 보강구조가 가지는 문제점을 해결하기 위해 안출된 것으로, 기설치된 이중 마루의 상부패널 전체를 해체하지 않고도 이중 마루의 상부패널을 지지하고 있는 이중 마루 지지구조물을 더욱 보강할 수 있도록 하는 이중 마루 보강장치 및 그 설치방법을 제공하는 데에 그 목적이 있다.
The present invention was devised to solve the problems of the conventional double floor reinforcement structure as described above, and further provides a double floor support structure that supports the top panel of the double floor without dismantling the entire upper panel of the previously installed double floor. An object of the present invention is to provide a double floor reinforcement device and a method of installing the same.
상기와 같은 이중 마루 보강장치를 제공하고자 하는 본 발명의 목적은 이중 마루 보강장치를, 상기 지지유닛의 측면에서 결합될 수 있도록 일측이 개방된 C자형상을 가지는 클립과; 상기 클립이 양단에 각각 설치되며, 상기 이웃하는 한 쌍의 지지유닛을 연결하는 길이를 가지는 보강바로 구성하는 것에 의해 달성된다.An object of the present invention to provide a double floor reinforcement device as described above is a double floor reinforcement device, a clip having a C-shaped open on one side to be coupled from the side of the support unit; The clip is installed at both ends, and is achieved by configuring a reinforcing bar having a length for connecting the neighboring pair of support units.
이때 상기 보강바는 내부에 중공이 형성되고, 상기 클립은 상기 중공에 삽입된 후, 상기 보강바의 외부를 가압함으로써 상기 보강바에 결합되는 것으로 실시될 수 있다.In this case, the reinforcement bar may have a hollow formed therein, and the clip may be inserted into the hollow and then coupled to the reinforcement bar by pressing the outside of the reinforcement bar.
또한 상기 보강바는 양단에 각각 볼트 또는 너트가 형성되고, 상기 클립에는 상기 볼트 또는 너트에 결합되는 너트 또는 볼트가 형성되어 서로 스크루 결합되며, 결합길이가 조절되도록 구성되는 것으로 실시될 수 있다.In addition, the reinforcing bar may be formed at both ends of the bolt or nut, respectively, the clip is a nut or bolt is coupled to the bolt or nut is screwed to each other, the coupling length is configured to be adjusted.
이에 더하여 상기 보강바는 일단에 각각 스크루가 형성된 한 쌍의 연결부재와, 상기 한 쌍의 연결부재와 스크루 결합되어 상기 한 쌍의 연결부재의 길이를 조절하는 길이조절부재로 구성되는 것으로 실시될 수 있다.
In addition, the reinforcing bar may be implemented as a pair of connecting members each having a screw formed at one end, and a length adjusting member which is screwed with the pair of connecting members to adjust the length of the pair of connecting members. have.
그리고 이중 마루 보강장치 설치방법을 제공하고자 하는 본 발명의 목적은 이중 마루 보강장치 설치방법을, 기설치된 상부패널 중 상부에 전산장비, 통신장비 등이 설치되지 않고 통로로 이용되는 부분에 설치된 상부패널의 일부를 제거하는 상부패널 제거단계와; 상기 상부패널 제거단계에 의해 이중 마루를 이루는 상부패널의 일부가 제거되고 나면, 개방된 공간을 통해 지지유닛에 보강바를 설치하는 보강바 설치단계와; 상기 보강바 설치단계에 의해 설치된 상기 보강바의 길이를 조절하여 상기 지지유닛에 상기 보강바를 밀착시키는 보강바 간격조절단계 및; 상기 상부패널 제거단계에서 제거된 상부패널을 재설치하는 상부패널 재설치 단계로 구성하는 것에 의해 달성된다.And an object of the present invention to provide a method for installing a double floor reinforcement device is a method for installing a double floor reinforcement device, the top panel is installed in the portion that is used as a passage without the computer equipment, communication equipment, etc. installed on the top of the pre-installed top panel An upper panel removing step of removing a portion of the upper panel; Reinforcing bar installation step of installing a reinforcing bar on the support unit through the open space after a part of the upper panel forming the double floor is removed by the upper panel removing step; A reinforcing bar spacing step of adjusting the length of the reinforcing bar installed by the reinforcing bar installation step to closely contact the reinforcing bar to the support unit; It is achieved by configuring a top panel reinstallation step of reinstalling the top panel removed in the top panel removal step.
이때 상기 보강바 간격조절단계에서 사용되는 상기 보강바는 일단에 각각 스크루가 형성된 한 쌍의 연결부재와, 상기 한 쌍의 연결부재와 스크루 결합되어 상기 한 쌍의 연결부재의 길이를 조절하는 길이조절부재로 이루어지는 것으로 실시될 수 있다.
In this case, the reinforcing bar used in the reinforcing bar gap adjusting step is a pair of connecting members each having a screw formed at one end, the length of adjusting the length of the pair of connecting members by screwing the pair of connecting members It can be implemented with a member.
본 발명은 기설치된 이중 마루의 상부패널 전체를 해체하지 않고도 지지유닛을 보강하는 보강바를 간편하게 설치할 수 있기 때문에 종래에 비해 보강장치를 설치하는 데에 소요되는 시간과 비용이 대폭 절감된다.The present invention can significantly install the reinforcing bar to reinforce the support unit without dismantling the entire upper panel of the double floor is already installed significantly compared to the conventional time and cost required to install the reinforcement device.
또한 본 발명은 지지유닛 사이에 설치되는 보강바의 길이를 적절하게 조절함으로써 보강바를 지지유닛에 밀착시킬 수 있기 때문에 지지유닛이 더욱 견고하게 지지되어 지지유닛에 외력이 작용하더라도 지지유닛이 파손되거나 손상되지 않으며, 그 결과 상부패널의 상부에 설치된 기기를 보호할 수 있다.In addition, since the present invention can be in close contact with the support unit by appropriately adjusting the length of the reinforcement bar installed between the support unit, the support unit is more firmly supported, even if the support unit is damaged or damaged As a result, it is possible to protect the equipment installed on top of the top panel.
그리고 기설치된 이중 마루가 클립과 보강바에 의해 보강되므로 지진 등에 의해 이중 바닥에 진동이 크게 발생하더라도 지지유닛이 기립 설치된 상태가 그대로 유지될 수 있고, 이에 의해 지지유닛이 상부패널을 지지하는 상태를 보다 안정적으로 유지할 수 있으며, 그 결과 기설치된 이중 마루의 내진 보강효과를 기대할 수 있다.
And since the installed double floor is reinforced by the clip and the reinforcing bar, even if a large vibration occurs in the double floor due to an earthquake or the like, the support unit can be kept upright, and thus the support unit supports the upper panel. It can be stably maintained, and as a result, the seismic reinforcing effect of the installed double floor can be expected.
도 1은 종래의 이중 마루 지지구조물의 예를 보인 사시도,
도 2(a, b)는 본 발명에 따른 클립과 보강바의 실시예 1을 보인 사시도,
도 3은 도 2의 사용상태도,
도 4 및 도 5는 본 발명에 따른 클립과 보강바의 실시예를 보인 사시도 및 사용상태도,
도 6 및 7은 본 발명에 따른 클립과 보강바의 또 다른 실시예를 보인 사시도 및 사용상태도,
도 8 및 도 9는 본 발명에 따른 이중 마루 내진 보강장치 설치 예를 보인 사시도,
도 10은 본 발명에 따른 클립에 요홈과 요부를 형성한 예를 보인 사시도,
도 11은 본 발명에 따른 이중 마루 보강장치 설치방법을 순서대로 나타낸 흐름도이다.1 is a perspective view showing an example of a conventional double floor support structure,
Figure 2 (a, b) is a perspective view showing an embodiment 1 of the clip and the reinforcement bar according to the present invention,
FIG. 3 is a use state diagram of FIG. 2,
4 and 5 are a perspective view and a state of use showing an embodiment of the clip and reinforcement bar according to the present invention,
6 and 7 is a perspective view and a state of use showing another embodiment of the clip and reinforcement bar according to the present invention,
8 and 9 is a perspective view showing an installation example of the double floor seismic reinforcement device according to the invention,
10 is a perspective view showing an example in which a recess and a recess are formed in a clip according to the present invention;
11 is a flowchart showing a method for installing a double floor reinforcement device according to the present invention in order.
이하에서는 바람직한 실시예를 도시한 첨부 도면을 통해 본 발명의 구성과 작용을 더욱 상세히 설명한다.
Hereinafter, the structure and operation of the present invention will be described in more detail with reference to the accompanying drawings, which show preferred embodiments.
본 발명은 이중 마루를 보강하기 위한 보강장치와, 이러한 보강장치를 설치하는 방법에 관한 것으로, 본 발명에 따른 이중 마루 보강장치는 도 2 내지 도 9에 도시된 바와 같이 클립(10)과 보강바(20)로 이루어지는데, 본 발명에서는 이러한 클립(10)과 보강바(20)로 이루어진 보강장치는 여러 가지 형태를 가지므로 이하에서는 이들을 각각 하나의 실시예로 하여 설명한다.The present invention relates to a reinforcement device for reinforcing a double floor, and a method for installing such a reinforcement device. The double floor reinforcement device according to the present invention includes a
<실시예 1>≪ Example 1 >
실시예 1은, 도 2(a, b) 및 도 3에 도시된 바와 같이 "C"자형의 클립부(11)와 결합부(12)로 이루어진 한 쌍의 클립(10)과, 이들 클립(10)과 결합되는 보강바(20)로 이루어진 보강장치에 관한 것이다.Embodiment 1 is a pair of
클립(10)은 클립부(11)와 결합부(12)로 이루어지는데, 이때 클립부(11)는 후술하는 지지유닛(30)의 스크루축(32)에 측면에서도 쉽게 장탈착될 수 있도록 측면의 일부가 절개된 모양의 "C"자형으로 이루어지고, 이러한 클립부(11)의 일측에 형성되는 결합부(12)는 상기 클립부(11)가 보강바(20)와 쉽게 결합될 수 있도록 돌출된 형상을 가진다.The
그리고 한 쌍의 결합부(12)와 결합되는 보강바(20)는 이웃하는 지지유닛(30)을 서로 연결할 수 있는 길이를 가지며 중공의 원형 파이프로 이루어진다.The reinforcing
그리고 결합부(12)와 보강바(20)가 결합시킬 때에는 돌출된 형상의 결합부(12)를 보강바(20)의 중공에 삽입시킨 상태에서 별도의 공구(펜치 등)를 이용하여 보강바(20)의 외부를 가압(코킹)하여 결합시키며, 이를 위해 결합부(12)에는 보강바(20) 내면과의 마찰력을 증가시키도록 복수의 돌기(도면부호 없음)를 형성하는 것이 바람직하다.And when the
그리고 지지유닛(30) 사이의 거리와 보강바(20)의 길이에 있어서 약간의 차이가 있을 수 있고, 이 경우 결합부(12)의 보강바(20) 내측으로의 삽입 깊이를 조절하여 클립(10)과 보강바(20)를 결합시키게 되면 이러한 길이의 차이에 따른 문제는 해소될 수 있다.
And there may be a slight difference in the distance between the
<실시예 2><Example 2>
실시예 2는, 도 4와 도 5에 도시된 바와 같이 한 쌍의 연결부재(20A, 20B)와 길이조절부재(22)로 이루어진 보강바(20)와, 이 보강바(20)에 결합되는 클립(10)으로 이루어진 보강장치에 관한 것이다.Embodiment 2 is a
이웃하는 지지유닛(30)을 서로 연결하는 연결부재(20A, 20B)는 한 쌍으로 이루어지고, 이때 한 쌍의 연결부재(20A, 20B)의 일단에는 각각 스크루(21)가 형성된다.The connecting
그리고 이러한 한 쌍의 연결부재(20A, 20B) 사이에는 길이조절부재(22)가 설치되는데, 이를 위해 길이조절부재(22)의 양단에도 연결부재(20A, 20B)에 형성된 스크루와 결합될 수 있도록 스크루가 형성되며, 이에 의해 한 쌍의 연결부재(20A, 20B) 사이에 길이조절부재(22)가 결합되어 이웃하는 지지유닛(30)을 서로 연결할 수 있다. 그리고 필요에 따라 길이조절부재(22)를 조이거나 풀어 결합길이를 조절하게 되면 실시예 1에서와 같이 지지유닛(30) 사이의 거리와 보강바(20)의 길이의 차이 문제가 해소될 수 있다.The
그리고 길이조절부재(22)의 움직임이나 회전에 의해 조절된 결합길이가 임의로 변경되지 않도록 스크루(21)에는 길이조절부재(22)의 움직임을 제한하는 스토퍼(도시되지 않음)가 설치될 수 있다. 이때 스토퍼는 통상적으로 사용되고 있는 다양한 형태 중에서 당업자가 용이하게 실시할 수 있는 것 중 어느 하나가 선택되어 적용된다.
And the
<실시예 3><Example 3>
실시예 3은, 도 6과 도 7에 도시된 바와 같이 양단에 각각 볼트(21') 또는 너트가 형성된 봉재로 이루어진 보강바(20)와, 이 보강바(20)에 스크루 결합되도록 너트(12') 또는 볼트가 형성된 클립(10)으로 이루어진 보강장치에 관한 것이다.6 and 7, the reinforcing
즉, 실시예 3의 보강바(20)는 양단에 각각 볼트(21') 또는 너트가 형성된 봉재 형상으로 이루어지고, 이 보강바(20)에 결합되는 클립(10)에는 너트(12') 또는 볼트가 형성되며, 이러한 구성에 의해 클립(10)과 보강바(20)가 스크루 결합에 의해 연결된다.That is, the
이때 클립(10) 사이에 결합된 보강바(20)를 시계방향 또는 반시계 방향으로 회전시킴으로써 클립(10)과 보강바(20)의 결합 길이를 조절할 수 있고, 그 결과 실시예 1, 2에서와 같이 지지유닛(30) 사이의 거리와 보강바(20)의 길이에 있어서 있을 수 있는 길이의 차이 문제가 해소될 수 있다.In this case, by rotating the
이를 위해 클립(10)과 보강바(20)에 각각 형성되는 스크루는 보강바(20)가 어느 한 방향으로 회전될 때 양측의 클립(10)이 동시에 조여지거나 풀리도록 형성된다.
To this end, the
한편, 이중 마루에 이미 설치되어 상부패널을 지지하는 지지유닛(30, 종래의 지지구조물)은 다양한 형태를 가지는데, 본 발명에 따른 보강장치의 구조에 대한 이해를 돕기 위해 하나의 예를 들면, 이러한 지지유닛(30)은 통상 도 7에 도시된 바와 같이 바닥에 설치되는 베이스(31)와, 베이스(31)에 기립 설치되는 스크루축(32)과, 스크루축(32)의 상부에 스크루 결합되는 고정블록(33)과, 고정블록(33)의 상면에 설치되는 고무판(34)으로 이루어진다.
On the other hand, the
위에서는 서로 다른 구조의 보강장치를 실시예 1 내지 실시예 3으로 하여 각각 설명하였으나, 이와 달리 상대적으로 길이조절이 어려운 실시예 1과 길이조절이 용이한 실시예 2, 3을 조합하여 실시할 수도 있는데, 그 하나의 예로서 도 8에 도시된 바와 같이 실시예 1을 적용하여 좌우측의 지지유닛(30)에는 보강바(20)를 설치하고, 이들 사이에는 실시예 2의 연결바(20A, 20B)와 길이조절부재(22)를 설치하여 길이조절부재(22)를 회전시켜 스크루를 조이거나 풀면 지지유닛(30)의 측면에 인장력(또는 압축력)이 작용하여 그 양측에 설치된 보강바(20)가 지지유닛(30)에 밀착 고정되면서 보강바(20)가 지지유닛(30)을 측면에서 견고하게 지지하게 된다.Although the reinforcing devices having different structures are described as Examples 1 to 3, respectively, the combination of Embodiment 1, which is relatively difficult to adjust the length, and Embodiments 2 and 3, which are relatively easy to adjust the length, may be performed. As an example, as shown in FIG. 8, the
또 하나의 예로서 위에서 설명한 것과 달리 도 9에 도시된 바와 같이 지지유닛(30) 사이를 연결하는 보강바(20)를 모두 한 종류의 보강바(20)를 이용하여 간격을 조절하는 것으로 실시될 수도 있다.
As another example, as described above, as illustrated in FIG. 9, all of the
또한 본 발명에 따른 클립부(11)의 상하면에는 각각 서로 이웃하는 방향의 클립(10)의 클립부(11)가 접촉되도록 설치될 수 있고, 이러한 경우에는 도 10에 도시된 바와 같이 클립부(11)의 상하면에 각각 서로 끼움 결합될 수 있도록 요홈(11A)과 요부(11B)가 교대로 형성될 수 있고, 상하측에 각각 접촉되는 클립부(11)가 요홈(11A)과 요부(11B)에 의해 서로 끼움 고정되도록 실시될 수 있다.In addition, the upper and lower surfaces of the
이러한 요홈(11A)과 요부(11B)에 의해 보강바(20)가 설치된 90°각도를 유지하는 강도가 보강되어 지지유닛(30)의 설치 각도가 틀어지지 않고 견고하게 유지된다.By the
이때 요홈(11A)과 요부(11B)의 형상은 당업자가 용이하게 실시하기 위해 다양한 형태로 실시될 수 있는데, 그 예로서 톱니형, 사각형, 반원형, 삼각형 중에서 선택되는 어느 하나의 형상으로 요홈(11A)과 요부(11B)가 각각 형성되고, 이러한 요홈(11A)과 요부(11B)는 클립부(11)의 상하면에 방사상으로 복수 개가 형성되거나 또는 보강바(20)가 설치되는 각도 즉, 90°간격으로 총 4개가 형성되는 것으로 실시될 수 있다.
At this time, the shape of the
이하에서는 상기와 같은 구조로 이루어진 이중 마루 보강장치를 이중 마루 바닥에 설치하는 방법을 작업순서에 따라 설명한다.Hereinafter, a method of installing the double floor reinforcement device having the above structure on the floor of the double floor will be described according to the work order.
본 발명에 따른 이중 마루 보강장치 설치방법은 도 11에 도시된 바와 같이 상부패널 제거단계(S100), 보강바 설치단계(S200), 보강바 간격조절단계(S300) 및 상부패널 재설치 단계(S400)로 이루어진다.
Double floor reinforcement installation method according to the invention is the upper panel removing step (S100), reinforcing bar installation step (S200), reinforcing bar spacing step (S300) and the top panel reinstallation step (S400) as shown in FIG. Is made of.
(1) 상부패널 제거단계(S100)(1) removing the upper panel (S100)
상부패널 제거단계(S100)는 기설치된 상부패널 중 그 상부에 전산장비, 통신장비 등이 설치되지 않고 통로로 이용되는 부분에 설치된 상부패널의 일부를 제거하는 단계로서, 이에 의해 작업자가 본 발명의 보강장치를 설치하기 위해 지지유닛(30)의 측면으로 접근할 수 있게 된다.The upper panel removing step (S100) is a step of removing a part of the upper panel installed in a portion used as a passage without any computing equipment, communication equipment, or the like installed on the upper part of the upper panel, whereby the operator of the present invention Access to the side of the
일반적으로 이중 마루가 설치되는 전산실이나 통신실은 상부패널이 격자형으로 배치되고, 이때 전산장비나 통신기기 등은 격자형으로 설치된 상부패널 상에 80cm 내지 1m 20cm의 폭을 가지고 설치되므로, 상부패널 제거단계(S100)를 통해 통로로 이용되는 부분에 설치된 상부패널만 제거하더라도 전산장비나 통신기기 등의 하부에 위치되어 이들을 지지하고 있는 지지유닛(30)까지의 거리는 60cm 이내이므로 작업자가 전산장비나 통신기기 하부에 위치하는 지지유닛(30)에 쉽게 접근할 수 있다.
In general, a computer room or a communication room in which a double floor is installed has an upper panel arranged in a lattice shape, and in this case, a computer equipment or communication device is installed with a width of 80 cm to 1 m and 20 cm on the upper panel installed in a lattice shape, thus removing the upper panel. Even if only the upper panel installed in the part used as a passage through the step (S100), the distance to the
(2) 보강바 설치단계(S200)(2) reinforcing bar installation step (S200)
이 단계는 상기 상부패널 제거단계(S100)에 의해 이중 마루를 이루는 상부패널의 일부가 제거되고 나면, 개방된 공간을 통해 지지유닛(30)의 측면으로 접근하여 지지유닛(30) 사이가 보강바(20)에 의해 사방으로 연결되도록 보강바(20)를 반복 설치하는 단계이다.In this step, after a part of the upper panel forming the double floor is removed by the upper panel removing step (S100), the
지지유닛(30)에 보강바(20)를 설치할 때에는 먼저 클립(10)과 보강바(20)를 결합한 다음, 이 클립(10)이 결합된 보강바(20)를 지지유닛(30)에 설치하게 되는데, 보강바(20)의 양단에는 개방부가 형성된 C자형의 클립(10)이 구비되어 있기 때문에 클립(10)의 개방부를 지지유닛(30)의 측면에 대고 가압하는 것만으로 클립(10)을 지지유닛(30)에 쉽게 결합시킬 수 있으며, 따라서 상부패널이 제거되지 않은 위치에 있는 지지유닛(30)에도 보강바(20)를 쉽게 설치할 수 있다.When installing the
이때 클립(10)이 지지유닛(30)에 결합된 상태에서 쉽게 빠지지 않도록 클립(10)을 지지유닛(30)에 고정하는 별도의 고정부재가 사용될 수도 있는데, 고정부재의 실시예로는 도 2(b)에 도시된 바와 같이 클립부(11)가 상하로 연장되는 길이를 가지는 것으로 실시되고, 이렇게 연장된 길이부분의 외부면에 탄성 밀착되도록 설치되어 클립부(11)를 지지유닛(30)에 밀착시키는 집게를 사용하는 방안이 있다.
In this case, a separate fixing member may be used to fix the
(3) 보강바 간격조절단계(S300)(3) reinforcing bar spacing step (S300)
보강바 간격조절단계(S300)는 상기 보강바 설치단계(S200)에 의해 상기 지지유닛(30)이 보강바(20)에 의해 연결되고 나면, 보강바(20) 간의 결합거리 또는 보강바(20)와 클립(10) 간의 결합거리를 조절하여 보강바(20)가 지지유닛(30)의 측면에 밀착되도록 하는 단계로서, 이에 의해 지지유닛(30)이 보강바(20)에 의해 견고하게 지지된다.Reinforcement bar spacing adjusting step (S300) is, after the
이때 보강바(20)는 위에서 설명한 실시예 1 내지 실시예 3에 따른 형태의 보강바(20)로 실시될 수 있는데, 예를 들면, 보강바(20)는 일단에 각각 스크루(21)가 형성된 한 쌍의 연결부재(20A, 20B)와, 한 쌍의 연결부재(20A, 20B))와 스크루 결합되어 한 쌍의 연결부재(20A, 20B)의 길이를 조절하는 길이조절부재(22)로 이루어지는 것으로 실시될 수 있다.
In this case, the
(4) 상부패널 재설치 단계(S400)(4) upper panel reinstallation step (S400)
이 단계는 상기 보강바 설치단계(S200)와 상기 보강바 간격조절단계(S300)에 의해 지지유닛(30) 사이에 보강바(20)의 설치작업과 길이조절 작업이 종료되고 나면, 상기 상부패널 제거단계(S100)에서 제거된 상부패널을 다시 설치하는 단계로서 이에 의해 본 발명의 보강장치의 설치가 완료된다.
This step is after the installation work of the reinforcing
위에서는 보강바 설치단계(S200)에서 보강바(20)를 지지유닛(30)에 모두 설치한 다음, 보강바 간격조절단계(S300)에서 보강바(20)의 설치간격을 한꺼번에 조절하는 것으로 설명하였으나, 이와 달리 1개의 보강바(20)를 설치한 다음, 이 보강바(20)의 설치간격을 조절하고, 다시 다른 보강바(20)를 설치한 다음, 이 보강바(20)의 설치간격을 조절하는 작업을 반복하는 것으로도 실시할 수 있다.
In the above reinforcement bar installation step (S200) and then install all the
이상 설명한 바와 같이 본 발명은 기설치된 이중 마루의 상부패널 전체를 해체하지 않고도 보강바를 간편하게 설치할 수 있으며, 이에 의해 이중 마루의 상부패널을 지지하고 있는 이중 마루 지지구조물을 더욱 견고하게 보강할 수 있다.
As described above, the present invention can easily install the reinforcing bar without dismantling the entire upper panel of the double floor, which is already installed, thereby reinforcing the double floor supporting structure that supports the upper panel of the double floor.
10: 클립 11: 클립부
11A: 요홈 11B: 요부
12: 결합부 12': 너트
20: 보강바 20A, 20B: 연결부재
21: 스크루 21': 볼트
22: 길이조절부재 30: 지지유닛
31: 베이스 32: 스크루축
33: 고정블록 34: 고무판10: Clip 11: Clip Section
11A:
12: coupling part 12 ': nut
20: reinforcing
21: screw 21 ': bolt
22: length adjusting member 30: support unit
31: base 32: screw shaft
33: fixed block 34: rubber plate
Claims (6)
상기 지지유닛(30)의 측면에서 결합될 수 있도록 일측이 개방된 C자 형상을 가지는 클립(10)과;
상기 클립(10)이 양단에 각각 설치되며, 상기 이웃하는 한 쌍의 지지유닛(30)을 연결하는 길이를 가지는 보강바(20)로 이루어지고,
상기 클립(10)은 클립부(11)와 결합부(12)로 이루어지며, 상기 클립부(11)의 상하면에는 각각 서로 이웃하여 설치되는 클립(10)의 클립부(11)가 서로 접촉 되도록 요홈(11A)과 요부(11B)가 교대로 형성된 것을 특징으로 하는 기 설치된 이중 마루 보강장치.
In the double floor consisting of a plurality of support units 30 are installed upright on the floor, and a plurality of upper panels installed on the support unit 30,
A clip (10) having a C-shape open at one side to be coupled at a side of the support unit (30);
The clip 10 is installed at both ends, respectively, made of a reinforcement bar 20 having a length connecting the neighboring pair of support units 30,
The clip 10 is composed of a clip portion 11 and the coupling portion 12, the upper and lower surfaces of the clip portion 11 so that the clip portion 11 of the clip 10 which is installed next to each other in contact with each other. Pre-installed double floor reinforcement, characterized in that the groove 11A and the recess 11B are formed alternately.
상기 보강바(20)는 내부에 중공이 형성되고,
상기 클립(10)은 상기 중공에 삽입된 후, 상기 보강바(20)의 외부를 가압함으로써 상기 보강바(20)에 결합되는 것을 특징으로 하는 기설치된 이중 마루 보강장치.
The method according to claim 1,
The reinforcement bar 20 has a hollow formed therein,
After the clip 10 is inserted into the hollow, pre-installed double floor reinforcement device, characterized in that coupled to the reinforcement bar 20 by pressing the outside of the reinforcement bar (20).
상기 보강바(20)는 양단에 각각 볼트 또는 너트가 형성되고, 상기 클립(10)에는 상기 볼트 또는 너트에 결합되는 너트 또는 볼트가 형성되어 서로 스크루 결합되며, 결합길이가 조절되도록 구성되는 것을 특징으로 하는 기설치된 이중 마루 보강장치.
The method according to claim 1,
The reinforcement bar 20 is a bolt or a nut is formed at both ends, respectively, the clip 10 is a nut or bolt is formed to be coupled to the bolt or nut is screwed to each other, characterized in that the coupling length is configured to be adjusted Prefabricated double floor reinforcement.
상기 보강바(20)는 일단에 각각 스크루(21)가 형성된 한 쌍의 연결부재(20A, 20B)와, 상기 한 쌍의 연결부재(20A, 20B)와 스크루 결합되어 상기 한 쌍의 연결부재(20A, 20B)의 길이를 조절하는 길이조절부재(22)로 이루어지는 것을 특징으로 하는 기설치된 이중 마루 보강장치.
The method according to claim 1,
The reinforcing bar 20 is screw-coupled with a pair of connecting members 20A and 20B, each of which has a screw 21 formed at one end thereof, and the pair of connecting members 20A and 20B, respectively. Equipped with a double floor reinforcement device, characterized in that consisting of a length adjusting member 22 for adjusting the length of 20A, 20B).
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| KR1020120060187A KR101200596B1 (en) | 2012-06-05 | 2012-06-05 | Reinforcing Device for Double Floor and It's Installation Method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| KR1020120060187A KR101200596B1 (en) | 2012-06-05 | 2012-06-05 | Reinforcing Device for Double Floor and It's Installation Method |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| KR101200596B1 true KR101200596B1 (en) | 2012-11-12 |
Family
ID=47564538
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| KR1020120060187A Active KR101200596B1 (en) | 2012-06-05 | 2012-06-05 | Reinforcing Device for Double Floor and It's Installation Method |
Country Status (1)
| Country | Link |
|---|---|
| KR (1) | KR101200596B1 (en) |
Cited By (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR101427240B1 (en) | 2014-05-26 | 2014-08-13 | 주식회사 면진테크 | Reinforcing Device for Double Floor |
| KR101960276B1 (en) * | 2018-11-12 | 2019-03-20 | 최원보 | Floor Support Apparatus For Seismic Isolation Equipment Double Deck |
| KR101982672B1 (en) | 2018-10-11 | 2019-05-30 | (주)우드코리아 | Double floor panel with seismic function |
| KR102003969B1 (en) | 2019-04-19 | 2019-07-25 | 주식회사 에스앤와이시스템 | Access Floor having Aseismatic Capacity-Reinforcing Device Capable of Freely Controling Floor Height |
| KR20210091467A (en) | 2020-01-14 | 2021-07-22 | 윤석희 | Double floor panel with seismic function |
| KR102347587B1 (en) * | 2020-07-28 | 2022-01-06 | 주식회사 에스앤와이시스템 | Access Floor with Seismic Isolator with Activation Area and Deactivation Area |
| KR102358704B1 (en) | 2021-10-21 | 2022-02-08 | 주식회사 면진테크 | Double floor support seismic reinforcement |
| KR20220018217A (en) * | 2020-08-06 | 2022-02-15 | (주)엘엑스하우시스 | Aseismatic access floor having truss reinforcing structure |
| KR102884849B1 (en) * | 2025-03-17 | 2025-11-12 | 주식회사 에스앤와이시스템 | Access floor with seismic reinforcement bar |
Citations (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2000291241A (en) * | 1999-04-06 | 2000-10-17 | Ntt Power & Building Facilities Inc | Earthquake resistant fixing hardware |
| KR100778524B1 (en) * | 2006-05-24 | 2007-11-23 | 황기태 | Seismic Access Floor Support Structure with Horizontal Reinforcement Support and Access Floor Construction Method Using the Structure |
-
2012
- 2012-06-05 KR KR1020120060187A patent/KR101200596B1/en active Active
Patent Citations (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2000291241A (en) * | 1999-04-06 | 2000-10-17 | Ntt Power & Building Facilities Inc | Earthquake resistant fixing hardware |
| KR100778524B1 (en) * | 2006-05-24 | 2007-11-23 | 황기태 | Seismic Access Floor Support Structure with Horizontal Reinforcement Support and Access Floor Construction Method Using the Structure |
Cited By (11)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR101427240B1 (en) | 2014-05-26 | 2014-08-13 | 주식회사 면진테크 | Reinforcing Device for Double Floor |
| KR101982672B1 (en) | 2018-10-11 | 2019-05-30 | (주)우드코리아 | Double floor panel with seismic function |
| KR101960276B1 (en) * | 2018-11-12 | 2019-03-20 | 최원보 | Floor Support Apparatus For Seismic Isolation Equipment Double Deck |
| KR102003969B1 (en) | 2019-04-19 | 2019-07-25 | 주식회사 에스앤와이시스템 | Access Floor having Aseismatic Capacity-Reinforcing Device Capable of Freely Controling Floor Height |
| WO2020213967A1 (en) * | 2019-04-19 | 2020-10-22 | 주식회사 에스앤와이시스템 | Dual floor equipped with earthquake-proofing reinforcement device having freely adjustable floor height |
| KR20210091467A (en) | 2020-01-14 | 2021-07-22 | 윤석희 | Double floor panel with seismic function |
| KR102347587B1 (en) * | 2020-07-28 | 2022-01-06 | 주식회사 에스앤와이시스템 | Access Floor with Seismic Isolator with Activation Area and Deactivation Area |
| KR20220018217A (en) * | 2020-08-06 | 2022-02-15 | (주)엘엑스하우시스 | Aseismatic access floor having truss reinforcing structure |
| KR102450504B1 (en) * | 2020-08-06 | 2022-10-05 | (주)엘엑스하우시스 | Aseismatic access floor having truss reinforcing structure |
| KR102358704B1 (en) | 2021-10-21 | 2022-02-08 | 주식회사 면진테크 | Double floor support seismic reinforcement |
| KR102884849B1 (en) * | 2025-03-17 | 2025-11-12 | 주식회사 에스앤와이시스템 | Access floor with seismic reinforcement bar |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| KR101200596B1 (en) | Reinforcing Device for Double Floor and It's Installation Method | |
| AU2019100993A4 (en) | Height-Adjustable Jack and Vertical Modular Component Support using the same | |
| KR20120037686A (en) | Height adjusting structure of pipe | |
| WO2017178971A1 (en) | Supporting structure for basement formwork | |
| KR101805042B1 (en) | Supporting Assembly for Installation of Double Floor and Its Installation Method | |
| JP5746874B2 (en) | Ceiling structure and brace material and ceiling finishing plate fixing bracket | |
| JP2016014288A (en) | Aseismatic ceiling | |
| JP6207317B2 (en) | Ceiling structure | |
| KR101320700B1 (en) | The Supporting Structure Of Walls Corner | |
| JP5732950B2 (en) | Seismic structure of suspended ceiling | |
| KR101293433B1 (en) | Support unit for floor panels | |
| JP3911501B2 (en) | Floor construction method | |
| JP7693371B2 (en) | Ceiling base structure | |
| KR20240058596A (en) | Clamping washer for supporting stand, and supproting stand using the same | |
| US20240102293A1 (en) | An Apparatus for a Temporary Flooring or Temporary Structure | |
| JP5376580B2 (en) | Ceiling foundation structure | |
| JP4460377B2 (en) | Clean room joists and clean room joists using the same | |
| JP4709645B2 (en) | Building foundation bundles, under-floor structures of buildings and buildings | |
| KR102358704B1 (en) | Double floor support seismic reinforcement | |
| KR102875564B1 (en) | Ceiling fixture system for easy installation of medical equipment mobility | |
| JP7646150B2 (en) | Hanging hardware | |
| KR20120074096A (en) | Hanger with varialbe binding site and ceiling support system that is applied | |
| KR101063630B1 (en) | Ceiling finishing device and installation method using ceiling panel and frame member | |
| JP6782564B2 (en) | Ceiling finishing member mounting structure | |
| KR20200068270A (en) | Seismic reinforcement method of In-wall, out-of-wall and joint of Masonry building using steel bars |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A201 | Request for examination | ||
| A302 | Request for accelerated examination | ||
| P11-X000 | Amendment of application requested |
St.27 status event code: A-2-2-P10-P11-nap-X000 |
|
| P13-X000 | Application amended |
St.27 status event code: A-2-2-P10-P13-nap-X000 |
|
| PA0109 | Patent application |
St.27 status event code: A-0-1-A10-A12-nap-PA0109 |
|
| PA0201 | Request for examination |
St.27 status event code: A-1-2-D10-D11-exm-PA0201 |
|
| PA0302 | Request for accelerated examination |
St.27 status event code: A-1-2-D10-D17-exm-PA0302 St.27 status event code: A-1-2-D10-D16-exm-PA0302 |
|
| D13-X000 | Search requested |
St.27 status event code: A-1-2-D10-D13-srh-X000 |
|
| D14-X000 | Search report completed |
St.27 status event code: A-1-2-D10-D14-srh-X000 |
|
| E902 | Notification of reason for refusal | ||
| PE0902 | Notice of grounds for rejection |
St.27 status event code: A-1-2-D10-D21-exm-PE0902 |
|
| E13-X000 | Pre-grant limitation requested |
St.27 status event code: A-2-3-E10-E13-lim-X000 |
|
| P11-X000 | Amendment of application requested |
St.27 status event code: A-2-2-P10-P11-nap-X000 |
|
| P13-X000 | Application amended |
St.27 status event code: A-2-2-P10-P13-nap-X000 |
|
| E701 | Decision to grant or registration of patent right | ||
| GRNT | Written decision to grant | ||
| PE0701 | Decision of registration |
St.27 status event code: A-1-2-D10-D22-exm-PE0701 |
|
| PR0701 | Registration of establishment |
St.27 status event code: A-2-4-F10-F11-exm-PR0701 |
|
| PR1002 | Payment of registration fee |
St.27 status event code: A-2-2-U10-U11-oth-PR1002 Fee payment year number: 1 |
|
| PG1601 | Publication of registration |
St.27 status event code: A-4-4-Q10-Q13-nap-PG1601 |
|
| FPAY | Annual fee payment |
Payment date: 20150918 Year of fee payment: 4 |
|
| PR1001 | Payment of annual fee |
St.27 status event code: A-4-4-U10-U11-oth-PR1001 Fee payment year number: 4 |
|
| P22-X000 | Classification modified |
St.27 status event code: A-4-4-P10-P22-nap-X000 |
|
| PR1001 | Payment of annual fee |
St.27 status event code: A-4-4-U10-U11-oth-PR1001 Fee payment year number: 5 |
|
| FPAY | Annual fee payment |
Payment date: 20171102 Year of fee payment: 6 |
|
| PR1001 | Payment of annual fee |
St.27 status event code: A-4-4-U10-U11-oth-PR1001 Fee payment year number: 6 |
|
| P22-X000 | Classification modified |
St.27 status event code: A-4-4-P10-P22-nap-X000 |
|
| FPAY | Annual fee payment |
Payment date: 20181106 Year of fee payment: 7 |
|
| PR1001 | Payment of annual fee |
St.27 status event code: A-4-4-U10-U11-oth-PR1001 Fee payment year number: 7 |
|
| FPAY | Annual fee payment |
Payment date: 20191030 Year of fee payment: 8 |
|
| PR1001 | Payment of annual fee |
St.27 status event code: A-4-4-U10-U11-oth-PR1001 Fee payment year number: 8 |
|
| PR1001 | Payment of annual fee |
St.27 status event code: A-4-4-U10-U11-oth-PR1001 Fee payment year number: 9 |
|
| PR1001 | Payment of annual fee |
St.27 status event code: A-4-4-U10-U11-oth-PR1001 Fee payment year number: 10 |
|
| R18-X000 | Changes to party contact information recorded |
St.27 status event code: A-5-5-R10-R18-oth-X000 |
|
| PR1001 | Payment of annual fee |
St.27 status event code: A-4-4-U10-U11-oth-PR1001 Fee payment year number: 11 |
|
| PR1001 | Payment of annual fee |
St.27 status event code: A-4-4-U10-U11-oth-PR1001 Fee payment year number: 12 |
|
| PR1001 | Payment of annual fee |
St.27 status event code: A-4-4-U10-U11-oth-PR1001 Fee payment year number: 13 |
|
| PR1001 | Payment of annual fee |
St.27 status event code: A-4-4-U10-U11-oth-PR1001 Fee payment year number: 14 |
|
| U11 | Full renewal or maintenance fee paid |
Free format text: ST27 STATUS EVENT CODE: A-4-4-U10-U11-OTH-PR1001 (AS PROVIDED BY THE NATIONAL OFFICE) Year of fee payment: 14 |