KR101071184B1 - Drilling Method For Piling At Height Restricted Area - Google Patents

Drilling Method For Piling At Height Restricted Area Download PDF

Info

Publication number
KR101071184B1
KR101071184B1 KR1020090089161A KR20090089161A KR101071184B1 KR 101071184 B1 KR101071184 B1 KR 101071184B1 KR 1020090089161 A KR1020090089161 A KR 1020090089161A KR 20090089161 A KR20090089161 A KR 20090089161A KR 101071184 B1 KR101071184 B1 KR 101071184B1
Authority
KR
South Korea
Prior art keywords
pile
drilling
height
rod
hydraulic crawler
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
KR1020090089161A
Other languages
Korean (ko)
Other versions
KR20110031768A (en
Inventor
정승범
김승철
Original Assignee
삼성물산 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 삼성물산 주식회사 filed Critical 삼성물산 주식회사
Priority to KR1020090089161A priority Critical patent/KR101071184B1/en
Publication of KR20110031768A publication Critical patent/KR20110031768A/en
Application granted granted Critical
Publication of KR101071184B1 publication Critical patent/KR101071184B1/en
Assigned to 삼성물산주식회사 reassignment 삼성물산주식회사 권리의 전부이전등록 Assignors: 삼성물산 주식회사
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/28Placing of hollow pipes or mould pipes by means arranged inside the piles or pipes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/003Injection of material

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Agronomy & Crop Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • Earth Drilling (AREA)

Abstract

본 발명은 상부가 폐쇄되어 작업공간을 확보하기 어려운 높이 제한 공간의 파일시공을 위한 천공공사에서,The present invention is a perforated construction for pile construction of height-limited space difficult to secure the work space is closed the top,

(a) 천공위치를 선정하여 천공공사가 가능하도록 청소하고 정리하는 준비단계; (b) 소정의 작업공간을 확보할 수 있도록 유압크롤러드릴(400)의 기존의 붐(410) 및 로드(420) 등의 길이를 높이 제한 공간의 높이에 맞도록 짧게 제작하여, 상기 유압크롤러드릴(400)에 설치하는 유압크롤러드릴준비단계; (c) 원추형 굴착용 해머비트(100)를 상기 준비된 유압크롤러드릴(400)에 설치하는 해머비트부착단계; (d) 안정액 주입과 동시에 소정의 위치를 상기 원추형 굴착용 해머비트(100)가 부착된 유압크롤러드릴(400)을 이용하여 근입심도까지 로드를 연결하며 천공하는 천공단계; 및, (e) 상기 천공단계 후 상기 원추형 굴착용 해머비트(100) 및 로드(420)의 결합체를 인발하는 인발단계;로 구성되는 것을 특징으로 하는 높이 제한 공간에서 파일시공을 위한 천공공법을 제공한다.(a) preparatory step of selecting a drilling position to clean and organize the drilling work possible; (b) Shortening the length of the existing boom 410 and the rod 420, etc. of the hydraulic crawler drill 400 so as to secure a predetermined working space to match the height of the height restriction space, the hydraulic crawler drill Hydraulic crawler drill preparing step for installing; (c) a hammer bit attachment step of installing a conical drilling hammer bit 100 in the prepared hydraulic crawler drill 400; (d) drilling and drilling the rod by connecting the rod to the rooting depth using a hydraulic crawler drill 400 having the conical drilling hammer bit 100 attached thereto at the same time as the stabilizer injection; And (e) a drawing step of drawing out a combination of the conical drilling hammer bit 100 and the rod 420 after the drilling step; providing a drilling method for pile construction in a height-limited space, characterized in that consisting of. do.

또한, 추가로 (f) 상기 인발단계 후에, H-pile 등의 파일을 근입심도까지 연결하여 삽입하고 최종항타 및 그라우팅 등의 과정을 거쳐 파일을 설치하는 파일설치단계;를 더 추가하여 구성되는 것을 특징으로 하는 높이 제한 공간에서 파일시공을 위한 천공공법을 제공한다. In addition, (f) after the drawing step, the file installation step of inserting the file, such as H-pile up to the depth of insertion and install the file through the process of the final stroke and grouting; It provides a drilling method for pile construction in a height-limited space characterized in that.

높이 제한 공간, 천공, 파일 Height limited space, perforated, pile

Description

높이 제한 공간에서 파일시공을 위한 천공공법{Drilling Method For Piling At Height Restricted Area}Drilling Method For Piling At Height Restricted Area

본 발명은 파일공사의 중요한 부분을 차지하는 천공공사에서, 파일시공을 위한 천공공법에 관한 것으로, 고가도로 밑 등의 높이 제한 공간에서 기존 시설물을 철거하지 않고 간편하게 천공할 수 있는 높이 제한 공간에서 파일시공을 위한 천공공법에 관한 것이다.The present invention relates to a drilling method for pile construction in the drilling work occupying an important part of the pile construction, pile construction in a height limited space that can be easily drilled without removing the existing facilities in the height limited space, such as under the overpass Perforation method for.

근래에는 교통망 확충 등을 이유로 기존의 고가도로 또는 교량 등을 따라 동 일한 경로로 상기 고가도로 등의 바로 밑 지하에서 지하철공사가 많이 이루어지고 있다. Recently, due to the expansion of the transportation network, a lot of subway works have been performed in the same basement under the above-mentioned overpasses along the same overpass or bridge.

또한, 환경보호 및 자원보호의 관점에서 기존 건물을 철거하고 새로운 건물을 신축하는 것보다는 재건축 또는 리모델링을 장려하고 있다. 상기 재건축 또는 리모델링 등의 공사에서는 기존 건물의 기초 보강을 위하여 지하실 등의 기초보강공사가 많이 이루어진다. It also encourages reconstruction or remodeling, rather than dismantling existing buildings and building new ones in terms of environmental and resource protection. In the reconstruction or remodeling, such as a basement reinforcement for the basement reinforcement of the existing building is made a lot.

상기 지하철공사 및 기초보강공사 등에서는 지반보강을 위한 파일시공이 필수적이라고 할 수 있다. In the subway construction and foundation reinforcement construction, it can be said that pile construction for ground reinforcement is essential.

파일시공을 위한 종래의 공법으로 통상적으로 많이 사용되는 것은 (1) 대형굴삭기를 이용한 파일근입공법, (2) 오토파일러(auto piler)를 이용한 파일근입공법, (3) T4오거(auger)를 이용한 파일근입공법 등이 있다.Conventional methods for pile construction are commonly used for (1) pile root approach using large excavators, (2) pile root approach using auto pilers, and (3) T4 augers. Pile rooting method;

상기 (1) 대형굴삭기를 이용한 파일근입공법은 굴삭기의 암(arm)의 선단에 바이브로 해머(vibro hammer) 또는 유압장치를 장착하여 지상에서 파일을 항타하거나 압입하여 시공하는 공법이다. (1) The pile root approach method using a large excavator is a method of constructing by driving or pressing a pile from the ground by mounting a vibro hammer or a hydraulic device on the tip of the arm of the excavator.

상기 (2) 오토파일러(auto piler)를 이용한 파일근입공법은 오토파일러(auto piler)를 사용하여 유압을 사용하여 압입하여 시공하는 공법이다.(2) The pile rooting method using an auto piler is a method in which the pile is press-fitted using hydraulic pressure using an auto piler.

상기 (3) T4오거(auger)를 이용한 파일근입공법은 오거(auger)를 이용하여 케이싱(casing)을 근입한 후 공벽을 유지하고, 상기 케이싱 내부를 천공하여 파일을 삽입하는 공법이다.(3) The pile rooting method using the T4 auger is a method of inserting a pile by holding a hollow wall after inserting a casing using an auger and drilling the inside of the casing.

그러나, 상술한 상기 지하철공사 및 기초보강공사 등과 같이 파일설치 작업을 하기위한 상부공간이 극히 제한된 경우, 상기 종래의 공법은 아래와 같은 이유로 적용하기 힘든 문제점이 있다.However, when the upper space for the pile installation work, such as the above-mentioned subway construction and foundation reinforcement construction is extremely limited, the conventional method is difficult to apply for the following reasons.

(1) 대형굴삭기를 이용한 파일근입공법은 5M 이상의 상부공간이 확보되어야 하며, 주로 N치 30이하의 무른 지반에만 사용할 수 있다. 또한, 파일을 압입하여 설치하므로 시방서상의 수직도(1/75~1/200)을 확보하기 어렵다는 단점이 있다. (1) The pile root access method using a large excavator should be secured with an upper space of 5M or more, and can be used only on soft ground with an N value of 30 or less. In addition, there is a disadvantage that it is difficult to secure the vertical degree (1/75 ~ 1/200) on the specification because the pile is press-installed.

(2) 오토파일러(auto piler)를 이용한 파일근입공법은 상기 대형굴삭기를 이용한 파일근입공법과 마찬가지로 5M 이상의 상부공간이 확보되어야 하며, 주로 N치 30이하의 무른 지반에만 사용할 수 있다. 또한, 파일을 압입하여 설치하므로 시방서상의 수직도(1/75~1/200)을 확보하기 어렵다는 단점이 있다. 그리고 워터제트(water jet)가 병행되어야 하므로 다량의 물과 워터제트장비가 필요하다. 또한, 상기 오토파일러(auto piler) 자체의 기동성이 확보되지 않아 타 장비를 사용하여 이동설치되어야 하는 단점이 있다. (2) The pile rooting method using an auto piler should be secured with an upper space of 5M or more like the pile rooting method using a large excavator, and can be mainly used only on a soft ground having an N value of 30 or less. In addition, there is a disadvantage that it is difficult to secure the vertical degree (1/75 ~ 1/200) on the specification because the pile is press-installed. In addition, a large amount of water and water jet equipment are required because the water jet must be parallel. In addition, the mobility of the auto piler (auto piler) itself is not secured there is a disadvantage that must be moved to install using other equipment.

(3) T4오거(auger)를 이용한 파일근입공법은 도 1에 도시된 종래의 굴착용 해머비트(10)를 사용하여 천공하는 공법으로 N치에 무관하게 대부분의 지질에 적용가능하고 굴착 수직도를 유지할 수 있다는 장점이 있으나, 8M 이상의 상부공간이 확보되어야 하고, 공벽유지를 위한 케이싱의 설치 후 상기 설치된 케이싱의 인발이 어려워 대심도 천공에 부적합하다는 단점이 있다. (3) The pile rooting method using the T4 auger is a method of drilling using the conventional drilling hammer bit 10 shown in FIG. 1 and is applicable to most lipids regardless of the N value. Although there is an advantage that can be maintained, the upper space of 8M or more must be secured, and after the installation of the casing for the maintenance of the wall wall is difficult to draw the installed casing has a disadvantage of being unsuitable for drilling the depth.

도 1은 T4오거(auger)를 이용한 파일근입공법에서 주로 사용되는 종래의 굴착용 해머비트(10)를 도시한 사시도이다.Figure 1 is a perspective view showing a conventional drilling hammer bit 10 mainly used in the pile rooting method using a T4 auger (auger).

종래의 굴착용 해머비트(10)는 도 1에 도시된 바와 같이, 전체적인 형상이 원주(圓柱, column)형을 이루고 있다.Conventional drilling hammer bit 10 as shown in Figure 1, the overall shape is a column (圓柱, column) form.

따라서, 지반을 천공하여 굴착할 때, 천공벽(1)과의 마찰이 많이 발생하고 지반을 파고 들어가는 천공능력이 미흡할 뿐 아니라 천공벽(1)의 다짐성능도 떨어지는 단점이 있다. 따라서 원하는 소정의 성능을 발휘하기 위해서는 천공시 대규모 및 대용량의 유압드릴이 필요하며, 진동과 소음이 허용범위를 초과하여 발생하므로 많은 민원을 야기한다. Therefore, when drilling and drilling the ground, a lot of friction with the drilling wall (1) occurs, not only the poor drilling ability to dig into the ground, but also has the disadvantage of poor compaction performance of the drilling wall (1). Therefore, in order to achieve the desired desired performance, a large-scale and large-capacity hydraulic drill is required at the time of drilling, and vibration and noise are generated beyond the allowable range, causing a lot of complaints.

상기한 종래의 고가도로 밑 또는 지하실 등의 높이 제한 공간에서 파일시공을 위한 천공공사에서, 종래의 유압크롤러드릴(400) 및 해머비트(10)를 개량하지 않고는 그대로 사용할 수 없다. In the above-mentioned conventional high-altitude boring for pile construction in a height-restricted space such as a basement or a basement, the conventional hydraulic crawler drill 400 and the hammer bit 10 cannot be used without improvement.

왜냐하면, 상기 유압크롤러드릴(400)의 기존의 붐(410)과 로드(420) 등의 길이가 필요 이상으로 길어서 천공을 위한 높이를 확보할 수가 없고, 상술한 종래의 굴착용 해머비트(10)를 사용하면 유압크롤러드릴의 규모와 용량이 필요 이상으로 너무 크게 요구되어 넓은 수평 및 수직 작업공간이 요구되기 때문이다.Because the length of the existing boom 410 and the rod 420, etc. of the hydraulic crawler drill 400 is longer than necessary to secure a height for drilling, the above-described conventional drilling hammer bit 10 This is because the size and capacity of the hydraulic crawler drill is so much larger than necessary that a large horizontal and vertical workspace is required.

따라서, 종래에는 고가도로 등의 밑에서 천공공사를 하기 위하여 상기 고가도로 등을 철거하거나 상기 고가도로 등을 우회하여 천공공사를 실시하였고, 종래의 기초보강공사를 하기 위해서는 건물의 외부에서 건물의 지하로 지반을 굴착하여 기초보강을 실시하였다. Therefore, in the related art, in order to perform the drilling work under the overpass, the overpass was demolished or the overpass was carried out to perform the perforation work. Basic reinforcement was performed.

그러나 이와 같은 종래의 공사방법은 기존의 시설물을 철거하는 등의 막대한 경제적 시간적 손실을 초래하였고, 넓은 작업공간을 요구하므로 인접도로 및 인접건물에 피해를 주는 등의 문제점이 있다. However, such a conventional construction method has caused enormous economic time loss such as dismantling existing facilities, and requires a wide working space, thus causing problems such as damage to adjacent roads and adjacent buildings.

본 발명은 상기한 바와 같은 종래의 제반 문제점을 해소하기 위해서 제시되는 것이다.SUMMARY OF THE INVENTION The present invention has been made in order to solve the above-mentioned problems of the related art.

그 목적은 본 발명은 파일공사의 중요한 부분을 차지하는 천공공사에서, 높이 제한 공간에서 파일시공을 위한 천공공법에 관한 것으로, 고가도로 밑 등의 높이 제한 공간에서 기존 시설물을 철거하지 않고 간편하게 천공할 수 있는 높이 제한 공간에서 파일시공을 위한 천공공법을 제공함에 있다.The object of the present invention relates to a drilling method for the construction of piles in a height-restricted space in the drilling work occupying an important part of the pile construction, can be easily drilled without removing the existing facilities in the height-restricted space, such as under the elevated road The present invention provides a drilling method for pile construction in a height-limited space.

상기한 기술적 과제를 해결하기 위해 본 발명은 상부가 폐쇄되어 작업공간을 확보하기 어려운 높이 제한 공간의 파일시공을 위한 천공공사에서,In order to solve the above technical problem, the present invention is closed in the drilling work for the construction of the pile height limit space difficult to secure the work space,

(a) 천공위치를 선정하여 천공공사가 가능하도록 청소하고 정리하는 준비단계; (b) 소정의 작업공간을 확보할 수 있도록 유압크롤러드릴(400)의 기존의 붐(410) 및 로드(420) 등의 길이를 높이 제한 공간의 높이에 맞도록 짧게 제작하여, 상기 유압크롤러드릴(400)에 설치하는 유압크롤러드릴준비단계; (c) 원추형 굴착용 해머비트(100)를 상기 준비된 유압크롤러드릴(400)에 설치하는 해머비트부착단계; (d) 안정액 주입과 동시에 소정의 위치를 상기 원추형 굴착용 해머비트(100)가 부착된 유압크롤러드릴(400)을 이용하여 근입심도까지 로드를 연결하며 천공하는 천공단계; 및, (e) 상기 천공단계 후 상기 원추형 굴착용 해머비트(100) 및 로드(420)의 결합체를 인발하는 인발단계;로 구성되는 것을 특징으로 하는 높이 제한 공간에서 파일시공을 위한 천공공법을 제공한다.(a) preparatory step of selecting a drilling position to clean and organize the drilling work possible; (b) Shortening the length of the existing boom 410 and the rod 420, etc. of the hydraulic crawler drill 400 so as to secure a predetermined working space to match the height of the height restriction space, the hydraulic crawler drill Hydraulic crawler drill preparing step for installing; (c) a hammer bit attachment step of installing a conical drilling hammer bit 100 in the prepared hydraulic crawler drill 400; (d) drilling and drilling the rod by connecting the rod to the rooting depth using a hydraulic crawler drill 400 having the conical drilling hammer bit 100 attached thereto at the same time as the stabilizer injection; And (e) a drawing step of drawing out a combination of the conical drilling hammer bit 100 and the rod 420 after the drilling step; providing a drilling method for pile construction in a height-limited space, characterized in that consisting of. do.

또한, 추가로 (f) 상기 인발단계 후에, H-pile 등의 파일을 근입심도까지 연결하여 삽입하고 최종항타 및 그라우팅 등의 과정을 거쳐 파일을 설치하는 파일설치단계;를 더 추가하여 구성되는 것을 특징으로 하는 높이 제한 공간에서 파일시공을 위한 천공공법을 제공한다. In addition, (f) after the drawing step, the file installation step of inserting the file, such as H-pile up to the depth of insertion and install the file through the process of the final stroke and grouting; It provides a drilling method for pile construction in a height-limited space characterized in that.

본 발명에 따르면 다음과 같은 효과가 기대된다.According to the present invention, the following effects are expected.

첫째, 진동과 소음이 적어 민원 발생가능성이 낮아지고, 교량 밑 또는 지하실 등의 높이 제한 공간에서 기존 시설물의 철거나 교통통제 없이도 상기 기존 시설물의 바로 밑에서 적용할 수 있는 높이 제한 공간에서 파일시공을 위한 천공공법을 제공한다. First, the possibility of civil complaints is lowered due to less vibration and noise, and the construction of piles in a height-restricted space that can be applied directly under the existing facilities without having to remove existing traffic or control traffic in height-restricted spaces such as under a bridge or basement Provide drilling methods.

둘째, 약 4M 가량의 상부공간만 확보되면 적용할 수 있고 천공장비의 자체이동이 가능하며, 공사비 및 공기를 줄일 수 있는 높이 제한 공간에서 파일시공을 위한 천공공법을 제공한다. Second, it can be applied if only about 4M of upper space is secured, and the self-moving of drilling equipment is possible, and it provides a drilling method for pile construction in height limited space that can reduce construction cost and air.

셋째, 원추형 굴착용 해머비트를 사용하여 지반을 천공하여 굴착할 때, 천공벽(1)과의 마찰이 적게 발생하고 지반을 파고 들어가는 성능이 우수하여 지층의 지질에 무관하게 적용할 수 있고 시방서상의 수직도를 확보할 수 있으며, 천공벽(1)의 다짐능력도 우수하여 별도의 케이싱 설치가 필요없는 높이 제한 공간에서 파일시공을 위한 천공공법을 제공한다.Third, when drilling and drilling the ground by using the conical drilling hammer bit, the friction with the perforated wall (1) is less generated and the ability to dig into the ground is excellent, so that it can be applied regardless of the geology of the strata. The vertical degree can be secured, and the compaction ability of the perforated wall 1 is also excellent, thus providing a perforation method for pile construction in a height-limited space that does not require a separate casing installation.

넷째, 종래의 유압크롤러드릴(400)의 붐(410)과 로드(420) 등의 길이를 줄이고 원추형 굴착용 해머비트(100)를 사용하여, 고가도로 또는 교량 밑 또는 지하실 등의 높이 제한 공간에서의 천공공사에서 사용할 수 있는 높이 제한 공간에서 파일시공을 위한 천공공법을 제공한다.Fourth, by reducing the length of the boom 410 and the rod 420 and the like of the conventional hydraulic crawler drill 400 and using the conical drilling hammer bit 100, in the height limit space, such as overpass or under the bridge or basement Provides a drilling method for pile construction in a height-limited space available for drilling.

본 발명은 파일공사의 중요한 부분을 차지하는 천공공사에서, 높이 제한 공간에서 파일시공을 위한 천공공법에 관한 것으로, 고가도로 밑 등의 높이 제한 공간에서 기존 시설물을 철거하지 않고 간편하게 천공할 수 있는 높이 제한 공간에서 파일시공을 위한 천공공법에 관한 것이다.The present invention relates to a drilling method for the construction of piles in a height-restricted space in the drilling work occupying an important part of the pile construction, height-restricted space that can be easily perforated without removing the existing facilities in the height-restricted space, such as under the elevated road Perforations for pile construction in

이하, 첨부한 도면 및 바람직한 실시예에 따라 본 발명을 상세히 설명한다.Hereinafter, the present invention will be described in detail with reference to the accompanying drawings and preferred embodiments.

도 4는 본 발명의 높이 제한 공간에서 파일시공을 위한 천공공법의 실시과정을 도시한 개념도이고, 도 5는 본 발명의 높이 제한 공간에서 파일시공을 위한 천공공법의 공정을 나타낸 순서도이다.4 is a conceptual diagram illustrating an implementation process of a drilling method for pile construction in a height limitation space of the present invention, Figure 5 is a flow chart showing a process of a drilling method for pile construction in a height limitation space of the present invention.

도 6 및 도 7은 각각 본 발명의 높이 제한 공간에서 파일시공을 위한 천공공법 중 천공단계 및 파일설치단계의 공정을 도시한 것이다. 6 and 7 illustrate the process of the drilling step and the pile installation step of the drilling method for the pile construction in the height limit space of the present invention, respectively.

본 발명의 높이 제한 공간에서 파일시공을 위한 천공공법은,The drilling method for pile construction in the height limit space of the present invention,

상부가 폐쇄되어 작업공간을 확보하기 어려운 높이 제한 공간의 파일시공을 위한 천공공사에서,In the drilling work for the pile construction of the height-restricted space where the upper part is closed and difficult to secure the working space,

(a) 천공위치를 선정하여 천공공사가 가능하도록 청소하고 정리하는 준비단계; (b) 소정의 작업공간을 확보할 수 있도록 유압크롤러드릴(400)의 기존의 붐(410) 및 로드(420) 등의 길이를 높이 제한 공간의 높이에 맞도록 짧게 제작하여, 상기 유압크롤러드릴(400)에 설치하는 유압크롤러드릴준비단계; (c) 원추형 굴착용 해머비트(100)를 상기 준비된 유압크롤러드릴(400)에 설치하는 해머비트부착단계; (d) 안정액 주입과 동시에 소정의 위치를 상기 원추형 굴착용 해머비트(100)가 부착된 유압크롤러드릴(400)을 이용하여 근입심도까지 로드를 연결하며 천공하는 천공단계; 및, (e) 상기 천공단계 후 상기 원추형 굴착용 해머비트(100) 및 로드(420)의 결합체를 인발하는 인발단계;로 구성되는 것을 특징으로 한다.(a) preparatory step of selecting a drilling position to clean and organize the drilling work possible; (b) Shortening the length of the existing boom 410 and the rod 420, etc. of the hydraulic crawler drill 400 so as to secure a predetermined working space to match the height of the height restriction space, the hydraulic crawler drill Hydraulic crawler drill preparing step for installing; (c) a hammer bit attachment step of installing a conical drilling hammer bit 100 in the prepared hydraulic crawler drill 400; (d) drilling and drilling the rod by connecting the rod to the rooting depth using a hydraulic crawler drill 400 having the conical drilling hammer bit 100 attached thereto at the same time as the stabilizer injection; And (e) a drawing step of drawing out a combination of the conical drilling hammer bit 100 and the rod 420 after the drilling step.

또한, (f) 상기 인발단계 후에, H-pile 등의 파일을 근입심도까지 연결하여 삽입하고 최종항타 및 그라우팅 등의 과정을 거쳐 파일을 설치하는 파일설치단계;를 더 추가하여 구성될 수도 있다.In addition, (f) after the drawing step, the file installation step of connecting the file, such as H-pile up to the depth of insertion and install the file through the process of the final stroke and grouting; may be further added. .

상기 (a) 준비단계는 천공위치를 선정하여 천공공사가 가능하도록 청소하고 정리하는 단계를 말한다. 즉, 고가도로 밑 등의 높이 제한 공간에서 천공을 하기위한 계측작업과 유압크롤러드릴(400) 등의 장비를 소정의 장소에 위치시키고 천공을 위한 전반적인 사전 준비과정을 말한다. 또한, 시공을 위한 높이를 확보하기 위하여 천공되는 지반 주변을 일정 깊이로 넓게 굴착하여 시공높이를 확보하고 장비 등을 위치시킬 수도 있다.The preparation step (a) refers to the step of cleaning and arranging to select a punching position to enable drilling. That is, the measurement operation for drilling in the height-restricted space, such as under the overpass and the hydraulic crawler drill 400 is placed in a predetermined place and refers to the overall preliminary preparation process for drilling. In addition, in order to secure the height for construction, the periphery of the periphery of the ground is excavated to a certain depth to secure the construction height and position the equipment.

상기 (b) 유압크롤러드릴준비단계는 소정의 작업공간을 수직으로 확보할 수 있도록 유압크롤러드릴(400)의 기존의 붐(410) 및 로드(420) 등의 길이를 높이 제한 공간의 높이에 맞도록 짧게 제작하여, 상기 유압크롤러드릴(400)에 설치하는 단계를 말한다. In the preparation of the hydraulic crawler drill, the length of the existing boom 410 and the rod 420 of the hydraulic crawler drill 400 is adjusted to the height of the limited space so as to secure a predetermined working space vertically. To make so short, it refers to the step of installing in the hydraulic crawler drill (400).

종래의 공사현장에서는 상기 유압크롤러드릴(400)의 기존의 붐(410) 및 로드(420) 등의 길이를 줄이려는 시도도 없이 기성제작 설치된 상기 붐(410) 및 로드(420) 등을 그대로 사용하였다. 따라서 기존 시설의 철거 등이 병행될 수 밖에 없었는데, 본 발명의 경우 기존 시설물의 층고에 맞추어 상기 붐(410) 및 로드(420) 등을 짧게 제작하여, 기존 시설물의 철거 등이 불필요하고 종래 유압크롤 러드릴(400)이 가진 천공능력이 그대로 유지되며 시방서상의 수직도가 확보되는 장점이 있다. In a conventional construction site, the ready-made boom 410 and the rod 420, etc., which are manufactured and manufactured without attempting to reduce the length of the existing boom 410 and the rod 420, etc. of the hydraulic crawler drill 400, are used as they are. It was. Therefore, the demolition of the existing facility was inevitably performed, but in the case of the present invention, the boom 410 and the rod 420 are made short in accordance with the height of the existing facility, so that the demolition of the existing facility is unnecessary and the conventional hydraulic crawl The drilling capability possessed by the ludrill 400 is maintained as it is, and there is an advantage of ensuring verticality in the specification.

상기 (c) 해머비트부착단계는 원추형 굴착용 해머비트(100)를 상기 준비된 유압크롤러드릴(400)에 설치하는 단계를 말한다. The (c) hammer bit attachment step refers to a step of installing a conical drilling hammer bit 100 to the prepared hydraulic crawler drill 400.

상기 원추형 굴착용 해머비트(100)는, 도 2에 도시된 바와 같이, 전체적으로 반경이 상부에서 하부로 줄어드는 원추 형상으로 표면에 돌기 모양의 다수 개의 본체볼팁(210)이 형성된 본체비트(200); 및, 상기 본체비트(200)의 하단부에 체결되며, 표면에 돌기 모양의 다수 개의 하부볼팁(310)이 형성된 하부비트(300);로 구성되는 것을 특징으로 한다. 또한, 상기 본체비트(200) 및 하부비트(300)의 표면에 각각 다수 개의 본체비트배출홈(220) 및 하부비트배출홈(320)이 더 추가되어 구성될 수 있으며, 상기 하부비트(300)의 하부비트배출홈(320)에 안정액배출구(330)가 더 추가되어 구성될 수도 있다. The conical drilling hammer bit 100, as shown in Figure 2, the main body bit 200 is formed with a plurality of body ball tips 210 of the projection shape on the surface in a conical shape of the radius is reduced from the top to the bottom as a whole; And a lower bit 300 which is fastened to a lower end of the main body bit 200 and has a plurality of lower ball tips 310 having a protrusion shape on a surface thereof. In addition, a plurality of body bit discharge grooves 220 and lower bit discharge grooves 320 may be further added to the surfaces of the body bits 200 and the lower bits 300, respectively, and the lower bits 300 may be added. The lower bit discharge groove 320 of the stabilizer discharge port 330 may be further added.

상기 본체비트(200) 및 하부비트(300)는 종래의 굴착용 해머비트(10)에 주로 사용되는 통상적인 탄소강 등의 내구성이 우수한 재료로써 제작되며, 상기 본체비트(200)의 표면에 내마모성이 우수한 하이망간 계열의 코팅재를 사용할 수 있다. The main body bit 200 and the lower bit 300 is made of a material having excellent durability, such as conventional carbon steel mainly used in the conventional drilling hammer bit 10, the wear resistance on the surface of the main body bit 200 Excellent high manganese-based coating material can be used.

상기 (d) 천공단계는 안정액 주입과 동시에 소정의 위치를 상기 원추형 굴착용 해머비트(100)가 부착된 유압크롤러드릴(400)을 이용하여 근입심도까지 로드를 연결하며 천공하는 단계를 말한다. The drilling step (d) refers to the step of drilling and connecting the rod to the root depth using the hydraulic crawler drill 400 is attached to the predetermined position at the same time as the injection of the stabilizer.

도 3에 도시된 바와 같이, 본 발명의 높이 제한 공간에서 파일시공을 위한 천공공법에서 이용되는 원추형 굴착용 해머비트(100)의 천공시 작용을 살펴보면 다음과 같다. As shown in FIG. 3, the operation of the conical drilling hammer bit 100 used in the drilling method for pile construction in the height limitation space of the present invention is as follows.

종래의 원주형인 굴착용 해머비트(10)와 달리 전체적인 원추형으로 제작되므로, 원추형 굴착용 해머비트(100)를 사용하여 지반을 천공하여 굴착할 때 천공벽(1)과의 마찰이 적게 발생하며, 암석 등의 파쇄능력이 우수하고 지반을 파고 들어가는 성능이 우수하다. 또한, 이로 인하여 굴착 수직도 확보가 용이하다.Unlike the conventional cylindrical hammer bit (10) for drilling because it is manufactured in the overall conical shape, when using the conical drilling hammer bit 100 to drill the ground to excavate less friction with the perforated wall (1), Excellent crushing ability of rock and the like, and good performance of digging into the ground. In addition, it is easy to ensure the excavation verticality.

이와 더불어, 본 발명의 원추형 굴착용 해머비트(100)는 벤토나이트 등의 안정액이 천공벽(1)에 잘 침투하도록 도와주고, 상기 안정액과 섞인 파쇄된 흙이 천공벽(1)을 다져주도록 하는 역할을 하므로, 케이싱 없이도 종래의 굴착용 해머비트(10)를 사용하여 굴착한 천공벽(1)보다 붕괴가 잘 일어나지 않는다. In addition, the conical drilling hammer bit 100 of the present invention helps the stabilizer such as bentonite to penetrate the perforated wall 1 well, and the crushed soil mixed with the stabilizer to compact the perforated wall (1). Therefore, even without the casing, the collapse is less likely to occur than the drilled wall 1 excavated using the conventional drilling hammer bit 10.

도 6은 본 발명의 높이 제한 공간에서 파일시공을 위한 천공공법 중 천공단계의 공정을 도시한 것이다. Figure 6 shows the process of the drilling step of the drilling method for the pile construction in the height limitation space of the present invention.

도시된 바와 같이 상부 제한 공간에 맞추어 짧게 제작된 로드를 천공과 동시에 이어가며 굴착심도에 무관하게 원하는 깊이로 수직도를 유지하며 간편하게 천공할 수 있다.As shown in the drawing, a short rod made in accordance with the upper confined space may be continuously drilled at the same time while maintaining verticality at a desired depth regardless of the drilling depth.

상기 (e) 인발단계는 상기 천공단계 후 상기 원추형 굴착용 해머비트(100) 및 로드(420)의 결합체를 인발하는 단계이다. 상술한 바와 같이 공벽이 붕괴될 염려가 적으므로 빠른 시간에 간편하고 안전하게 상기 원추형 굴착용 해머비트(100) 및 로드(420)의 결합체를 인발할 수 있다.The (e) drawing step is a step of drawing a combination of the conical drilling hammer bit 100 and the rod 420 after the drilling step. As described above, since there is little fear of collapse of the vacant wall, a combination of the conical drilling hammer bit 100 and the rod 420 can be drawn easily and safely in a short time.

도 7은 본 발명의 높이 제한 공간에서 파일시공을 위한 천공공법 중 파일설치단계의 공정을 도시한 것이고, 도 8은 각종 파일의 이음부분에 대한 상세도이다.7 is a view illustrating a process of a pile installation step of a drilling method for pile construction in a height limited space of the present invention, Figure 8 is a detailed view of the joint portion of the various piles.

상기 (f) 파일설치단계는 상기 인발단계 후에, H-pile 등의 파일을 근입심도까지 연결하여 삽입하고 최종항타 및 그라우팅 등의 과정을 거쳐 파일을 설치하는 단계를 말한다. 이미 천공되어 공벽이 형성된 상태이고 상술한 바와 같이 천공벽(1)이 잘 다져져 케이싱이 없더라도 공벽붕괴가 발생할 위험이 적으므로 파일의 종류에 무관하게 시트파일(sheet file)이나 기성콘크리트파일 그리고 강관파일 등의 설치도 가능하며, 경우에 따라 현장타설 콘크리트파일의 시공도 얼마든지 가능하다.The file installation step (f) refers to a step of installing a file through a process such as final hitting and grouting by inserting a file such as an H-pile up to the depth of induction after the drawing step. As already mentioned above, the perforated wall is formed. As described above, the perforated wall 1 is well compacted so that there is little risk of decay of the wall even without a casing. It is also possible to install, etc. In some cases, it is possible to construct a concrete pile.

(1) H-pile의 이음은 통상적인 용접 등의 이음공법을 사용할 수도 있으나, 도 8a에 도시된 바와 같이, 상부파일 하단의 웨브(web)와 플랜지(flange)에 연결철판이 돌출되도록 연결철판을 용접하여 설치하고 상기 상부파일 하단의 연결철판이 하부파일 상단의 웨브와 플랜지에 끼워지도록 설치한 후 나머지 이음부를 용접한다.(1) The joint of the H-pile may use a jointing method such as a conventional welding, but as shown in FIG. 8A, the connecting iron plate is formed so that the connecting steel sheet protrudes from the web and the flange of the lower end of the upper pile. Install by welding and install so that the connecting steel plate of the lower end of the upper pile is fitted to the web and the flange of the upper end of the lower pile and welds the remaining joints.

(2) 강관파일의 이음은 통상적인 용접 등의 이음공법을 사용할 수도 있으나, 도 8b에 도시된 바와 같이, 상부파일 하단의 이음부에 다수 개의 연결용지그(jig)가 돌출되도록 용접하여 설치하고 상기 상부파일 하단의 연결용지그가 하부파일 상 단의 이음부에 끼워지도록 설치한 후 나머지 이음부를 용접한다.  (2) The joint of the steel pipe pile may use a jointing method such as conventional welding, but as shown in FIG. 8B, a plurality of connecting jigs are welded to the joint of the lower end of the upper pile to be welded and installed. The connecting jig at the bottom of the upper pile is installed to be fitted to the joint at the upper end of the lower pile and then welds the remaining joints.

(3) 기성콘크리트파일의 이음은 통상적인 장부식 이음 등의 이음공법을 사용할 수도 있으나, 도 8b에 도시된 바와 같이, 상부파일 하단 및 하부파일 상단의 이음부에 중앙에 요철이 형성되어 맞물릴 수 있도록 각각 숫연결철물 및 암연결철물을 콘크리트파일 제작시 매립하여 설치하고, 상기 상부파일 하단의 숫연결철물이 하부파일 상단의 암연결철물에 끼워지도록 설치할 수 있다. 또한, 상기 숫연결철물 및 암연결철물의 상호간에 맞물리는 요철에는 나사산을 형성하여 서로 돌려서 체결할 수도 있다.(3) The joints of the ready-made concrete pile may use a jointing method such as a conventional decorative joint, but as shown in FIG. 8B, irregularities are formed in the center of the joint of the lower end of the upper pile and the upper end of the lower pile. The male connecting hardware and the female connecting hardware may be installed to be embedded when the concrete pile is manufactured, and the male connecting hardware at the bottom of the upper pile may be installed to be fitted to the female connecting hardware at the top of the lower pile. In addition, it is also possible to fasten by turning each other by forming a screw thread in the concave-convex engagement between the male connecting iron and the female connecting hardware.

도 9는 본 발명의 높이 제한 공간에서 파일시공을 위한 천공공법 중 파일설치단계에서의 파일거치대에 대한 상세도이고, 도 10은 본 발명의 높이 제한 공간에서 파일시공을 위한 천공공법 중 파일설치단계에서의 파일거치대에 각종 파일을 거치한 실시예이다. 9 is a detailed view of the pile base in the pile installation step of the drilling method for the pile construction in the height-restricted space of the present invention, Figure 10 is a pile installation step of the drilling method for pile construction in the height-restricted space of the present invention It is an embodiment in which various files are mounted on a file holder in.

상기 파일거치대는 상기 파일설치단계에서의 설치중인 파일을 임시로 고정하기 위한 방법으로 사용되는 것으로, 천공된 구멍위에 설치되는 것으로, 중앙에 파일이 관통될 수 있는 홀이 형성되고 상기 홀의 양단에 구멍(도 9에는 ‘PILE 거치 HOLE’로 표기되어 있다.)이 형성된 두 개의 L형 앵글이 파일의 폭 간격으로 설치되는 파일거치상판 및 상기 L형 앵글의 구멍을 관통하여 설치되는 강봉 또는 볼트와 너트로 구성된다. 도시된 실시예 외에도 다양한 파일의 형태와 재질에 따라 상기 강봉 또는 볼트와 너트 외에도 통상적인 결속수단을 사용할 수 있다.The pile holder is used as a method for temporarily fixing the file being installed in the pile installation step, which is installed on a perforated hole, and has a hole through which a pile can be penetrated in the center and holes at both ends of the hole. 9 is formed with two L-shaped angles formed on the pile top plate and the steel rods or bolts and nuts installed through the holes of the L-angles. It consists of. In addition to the illustrated embodiment, it is possible to use conventional binding means in addition to the steel rods or bolts and nuts according to the shape and material of the various piles.

본 발명의 높이 제한 공간에서 파일시공을 위한 천공공법은 유압크롤러드릴(400)의 기존의 붐(410) 및 로드(420) 등의 길이를 줄이고 원추형 굴착용 해머비트(100)를 사용하므로, 진동과 소음이 적어 민원 발생가능성이 낮고, 교량 밑 또는 지하실 등의 높이 제한 공간에서 기존 시설물의 철거나 교통통제 없이도 상기 기존 시설물의 바로 밑에서 적용할 수 있으며, 약 4M 가량의 상부공간만 확보되면 적용할 수 있다. Drilling method for pile construction in the height-restricted space of the present invention because it reduces the length of the conventional boom 410 and the rod 420 of the hydraulic crawler drill 400, and uses a conical drilling hammer bit 100, vibration It is less likely to cause civil complaints due to less noise and noise, and it can be applied directly under the existing facilities without the traffic control or the removal of existing facilities in the height limit space such as under the bridge or basement. Can be.

또한, 유압크롤러드릴(400)을 이용하므로 천공장비의 자체이동이 가능하며, 공사비 및 공기를 줄일 수 있다. In addition, since the hydraulic crawler drill 400 is used, the drilling equipment itself can be moved, and construction cost and air can be reduced.

그리고 원추형 굴착용 해머비트(100)를 사용하여 지반을 천공하여 굴착할 때, 천공벽(1)과의 마찰이 적게 발생하고 지반을 파고 들어가는 성능이 우수하여 지층의 지질에 무관하게 적용할 수 있고 시방서상의 수직도를 확보할 수 있으며, 천공벽(1)의 다짐능력도 우수하여 별도의 케이싱 설치가 필요없다.And when using the conical drilling hammer bit 100 to drill the ground to excavate, less friction with the perforated wall (1) occurs and the ability to dig into the ground has excellent performance can be applied irrespective of the geology of the strata. The vertical degree on the specification can be secured, and the compaction ability of the perforated wall 1 is also excellent, and no separate casing is required.

본 발명은 상기에서 언급한 바와 같이 바람직한 실시예와 관련하여 설명되었으나, 본 발명의 요지를 벗어남이 없는 범위 내에서 다양한 수정 및 변형이 가능하며, 다양한 분야에서 사용 가능하다. While the present invention has been particularly shown and described with reference to exemplary embodiments thereof, it is to be understood that the invention is not limited to the disclosed embodiments, but, on the contrary, is intended to cover various modifications and equivalent arrangements included within the spirit and scope of the invention.

따라서 본 발명의 청구범위는 이건 발명의 진정한 범위 내에 속하는 수정 및 변형을 포함한다.Therefore, the claims of the present invention include modifications and variations that fall within the true scope of the invention.

도 1은 종래의 굴착용 해머비트(10)를 도시한 사시도이다.1 is a perspective view showing a conventional drilling hammer bit 10.

도 2는 본 발명의 높이 제한 공간에서 파일시공을 위한 천공공법에 이용되는 원추형 굴착용 해머비트(100)를 도시한 사시도이다.Figure 2 is a perspective view showing a conical drilling hammer bit 100 used in the drilling method for pile construction in the height-limited space of the present invention.

도 3은 본 발명의 높이 제한 공간에서 파일시공을 위한 천공공법의 실시과정에서 굴착면의 단면도이다.Figure 3 is a cross-sectional view of the excavation surface during the implementation of the drilling method for the pile construction in the height limit space of the present invention.

도 4는 본 발명의 높이 제한 공간에서 파일시공을 위한 천공공법의 실시과정을 도시한 개념도이다.4 is a conceptual diagram illustrating an implementation process of a drilling method for pile construction in a height limitation space of the present invention.

도 5는 본 발명의 높이 제한 공간에서 파일시공을 위한 천공공법의 공정을 나타낸 순서도이다.Figure 5 is a flow chart showing a process of the drilling method for pile construction in the height limit space of the present invention.

도 6은 본 발명의 높이 제한 공간에서 파일시공을 위한 천공공법 중 천공단계의 공정을 도시한 것이다. Figure 6 shows the process of the drilling step of the drilling method for the pile construction in the height limitation space of the present invention.

도 7은 본 발명의 높이 제한 공간에서 파일시공을 위한 천공공법 중 파일설치단계의 공정을 도시한 것이다. Figure 7 shows the process of the pile installation step of the drilling method for pile construction in the height limit space of the present invention.

도 8은 본 발명의 높이 제한 공간에서 파일시공을 위한 천공공법 중 파일설치단계에서의 각종 파일의 이음부분에 대한 상세도이다. 8 is a detailed view of the joint portion of the various piles in the pile installation step of the drilling method for pile construction in the height-limited space of the present invention.

도 9는 본 발명의 높이 제한 공간에서 파일시공을 위한 천공공법 중 파일설치단계에서의 파일거치대에 대한 상세도이다. 9 is a detailed view of the pile base in the pile installation step of the drilling method for pile construction in the height-limited space of the present invention.

도 10은 본 발명의 높이 제한 공간에서 파일시공을 위한 천공공법 중 파일설치단계에서의 파일거치대에 각종 파일을 거치한 실시예이다. 10 is an embodiment in which various files are mounted on pile piles in the pile installation step of the drilling method for pile construction in the height limit space of the present invention.

<도면의 주요 부분에 대한 부호의 설명><Explanation of symbols for the main parts of the drawings>

1: 천공벽1: perforated wall

10: 종래의 굴착용 해머비트10: Conventional Excavation Hammer Bits

100: 본 발명의 원추형 굴착용 해머비트100: conical drilling hammer bit of the present invention

200: 본체비트 200: body bit

210: 본체볼팁210: body ball tip

220: 본체비트배출홈 220: body bit discharge groove

300: 하부비트 300: lower bit

310: 하부볼팁310: lower ball tip

320: 하부비트배출홈 320: lower bit discharge groove

330: 안정액배출구330: stabilizer outlet

400: 유압크롤러드릴400: Hydraulic Crawler Drill

410: 붐410: boom

420: 로드420: load

Claims (7)

삭제delete 삭제delete 삭제delete 삭제delete 삭제delete 삭제delete 상부가 폐쇄되어 작업공간을 확보하기 어려운 높이 제한 공간의 파일시공을 위한 천공공사에서,In the drilling work for the pile construction of the height-restricted space where the upper part is closed and difficult to secure the working space, (a) 천공위치를 선정하여 천공공사가 가능하도록 청소하고 정리하는 준비단계;(a) preparatory step of selecting a drilling position to clean and organize the drilling work possible; (b) 소정의 작업공간을 확보할 수 있도록 유압크롤러드릴(400)의 기존의 붐(410) 및 로드(420) 등의 길이를 높이 제한 공간의 높이에 맞도록 짧게 제작하여, 상기 유압크롤러드릴(400)에 설치하는 유압크롤러드릴준비단계; (b) Shortening the length of the existing boom 410 and the rod 420, etc. of the hydraulic crawler drill 400 so as to secure a predetermined working space to match the height of the height restriction space, the hydraulic crawler drill Hydraulic crawler drill preparing step for installing; (c) 원추형 굴착용 해머비트(100)를 상기 준비된 유압크롤러드릴(400)에 설치하는 해머비트부착단계;(c) a hammer bit attachment step of installing a conical drilling hammer bit 100 in the prepared hydraulic crawler drill 400; (d) 안정액 주입과 동시에 소정의 위치를 상기 원추형 굴착용 해머비트(100)가 부착된 유압크롤러드릴(400)을 이용하여 근입심도까지 로드를 연결하며 천공하는 천공단계;(d) drilling and drilling the rod by connecting the rod to the rooting depth using a hydraulic crawler drill 400 having the conical drilling hammer bit 100 attached thereto at the same time as the stabilizer injection; (e) 상기 천공단계 후 상기 원추형 굴착용 해머비트(100) 및 로드(420)의 결합체를 인발하는 인발단계; 및,(e) a drawing step of drawing out a combination of the conical drilling hammer bit 100 and the rod 420 after the drilling step; And, (f) 상기 인발단계 후에, H-pile 등의 파일을 근입심도까지 연결하여 삽입하고 최종항타 및 그라우팅 등의 과정을 거쳐 파일을 설치하는 파일설치단계;를 포함하여 구성되는 것을 특징으로 하고,(f) after the drawing step, the file installation step of connecting and inserting the file, such as H-pile to the rooting depth and installing the file through a process such as the final stroke and grouting; 상기 (f) 파일설치단계에서의 파일연결 및 이음방법으로,In the (f) file installation step of the file connection and joint method, (1) H-pile의 경우 상부파일 하단의 웨브(web)와 플랜지(flange)에 연결철판이 돌출되도록 연결철판을 용접하여 설치하고 상기 상부파일 하단의 연결철판이 하부파일 상단의 웨브와 플랜지에 끼워지도록 설치한 후 나머지 이음부를 용접하며,(1) In the case of H-pile, the connecting steel plate is welded and installed so that the connecting steel plate protrudes from the web and the flange of the upper pile and the connecting steel plate of the upper pile is connected to the web and the flange of the upper pile of the lower pile. After installation so that the rest of the seam is welded, (2) 강관파일의 경우 상부파일 하단의 이음부에 다수 개의 연결용지그(jig)가 돌출되도록 용접하여 설치하고 상기 상부파일 하단의 연결용지그가 하부파일 상단의 이음부에 끼워지도록 설치한 후 나머지 이음부를 용접하고, (2) In the case of steel pipe piles, a plurality of connecting jigs are welded to the joints at the bottom of the upper pile to protrude, and the connecting jig at the bottom of the upper pile is fitted to the joints at the top of the lower pile. Weld seams, (3) 기성콘크리트파일의 경우 상부파일 하단 및 하부파일 상단의 이음부에 중앙에 요철이 형성되어 맞물릴 수 있도록 각각 숫연결철물 및 암연결철물을 형성하고 상기 상부파일 하단의 숫연결철물이 하부파일 상단의 암연결철물에 끼워지도록 설치하는 것을 특징으로 하며,(3) In the case of ready-made concrete piles, male and female connecting irons are respectively formed to form interdigital concavities and convexities at the bottom of the upper pile and the upper end of the lower pile. It is characterized in that the installation to be fitted to the female connecting hardware at the top of the pile, 상기 (f) 파일설치단계에서의 설치중인 파일을 임시로 고정하기 위한 방법으로,As a method for temporarily fixing the file being installed in the (f) file installation step, 천공된 구멍위에 설치되는 것으로, 중앙에 파일이 관통될 수 있는 홀이 형성되고 상기 홀의 양단에 구멍이 형성된 두 개의 L형 앵글이 파일의 폭 간격으로 설치되는 파일거치상판 및 상기 L형 앵글의 구멍을 관통하여 설치되는 강봉 또는 볼트와 너트로 구성되는 파일거치대를 이용하는 것을 특징으로 하는 높이 제한 공간에서 파일시공을 위한 천공공법.It is installed on the perforated hole, the pile is formed in the center through which the pile can be penetrated, and two L-angle angles formed with holes at both ends of the hole are installed on the pile top plate and the hole of the L-angle angle Drilling method for pile construction in a height-restricted space, characterized in that using a pile rod consisting of a steel rod or bolt and nut installed through the.
KR1020090089161A 2009-09-21 2009-09-21 Drilling Method For Piling At Height Restricted Area Expired - Fee Related KR101071184B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020090089161A KR101071184B1 (en) 2009-09-21 2009-09-21 Drilling Method For Piling At Height Restricted Area

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020090089161A KR101071184B1 (en) 2009-09-21 2009-09-21 Drilling Method For Piling At Height Restricted Area

Publications (2)

Publication Number Publication Date
KR20110031768A KR20110031768A (en) 2011-03-29
KR101071184B1 true KR101071184B1 (en) 2011-10-10

Family

ID=43936707

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020090089161A Expired - Fee Related KR101071184B1 (en) 2009-09-21 2009-09-21 Drilling Method For Piling At Height Restricted Area

Country Status (1)

Country Link
KR (1) KR101071184B1 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111608587B (en) * 2020-06-18 2025-01-07 深圳市工勘岩土集团有限公司 Construction system and method of hard rock drilling for interlocking piles in foundation pits in height-restricted areas
CN114541390A (en) * 2022-03-01 2022-05-27 上海广大基础工程有限公司 Cast-in-place pile construction method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11303563A (en) * 1998-04-24 1999-11-02 Kinki Ishiko Kk Machine for foundation construction work
KR100562465B1 (en) * 2004-06-04 2006-03-27 한우선 An agitation and hammer apparatus for boring and the using method thereof
US20060120810A1 (en) * 2006-02-14 2006-06-08 Cinquino John V Adjustable Pile Splicing Apparatus, System, Method,and Product-by-Process

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11303563A (en) * 1998-04-24 1999-11-02 Kinki Ishiko Kk Machine for foundation construction work
KR100562465B1 (en) * 2004-06-04 2006-03-27 한우선 An agitation and hammer apparatus for boring and the using method thereof
US20060120810A1 (en) * 2006-02-14 2006-06-08 Cinquino John V Adjustable Pile Splicing Apparatus, System, Method,and Product-by-Process

Also Published As

Publication number Publication date
KR20110031768A (en) 2011-03-29

Similar Documents

Publication Publication Date Title
CN110093928B (en) A kind of foundation pit supporting structure and earthwork excavation construction method
CN105780763B (en) Mesoporous vibrates the construction method of casing retaining wall long auger guncreting pile
CN111877344A (en) Old pipe pile breaking method
KR101144312B1 (en) Steel pipe pile equipped with base enlargement device and the construction method
KR101195235B1 (en) Underground structure construction method using composite pile
CN110397026A (en) A construction method and construction structure for pile foundations of bridges adjacent to existing lines
CN217870505U (en) Excavation supporting construction of tunnel top foundation ditch excavation
KR101381325B1 (en) The non-open cut tunnel construction method using the multistage small diameter steel pipe
CN117027027A (en) A rock-embedded and anchored lock-top steel pipe pile cofferdam construction method
KR20110031768A (en) Drilling method for pile construction in height confined space
JP4074198B2 (en) How to remove existing piles
KR20200013275A (en) A device that can be separated after entering a PHC pile using a steel pipe
CN115217124A (en) In-situ retaining structure for slope expanding excavation and construction method
KR102579002B1 (en) Method of demolition of underground exterior walls
CN114753381B (en) Method for removing underground barriers in non-excavation construction path range in limited space
CN210396738U (en) Air-leg rock drill bit
KR102073630B1 (en) Sacrificial Steel Pipe Cutting Method Using Sacrificial Steel Pipe for Field Drilled Shaft and Construction Method for Stiffness Increase on the Pile
KR102059051B1 (en) Method for excavating vertical shaft
KR20110087175A (en) Construction method that can be designed to improve the bearing capacity of PA piles
KR20100112725A (en) Construction method using by conection of the h pile and l,u-type sheet pile
JP3635167B2 (en) Steel pipe concrete well foundation installed on slope and its construction method
CN207244630U (en) Raked pile
CN222100898U (en) A method pile deep foundation pit support device
KR200373276Y1 (en) Steel pipe pile of support structure
TWI853491B (en) Anti-collapse continuous wall construction method for special geological layers

Legal Events

Date Code Title Description
A201 Request for examination
PA0109 Patent application

St.27 status event code: A-0-1-A10-A12-nap-PA0109

PA0201 Request for examination

St.27 status event code: A-1-2-D10-D11-exm-PA0201

P11-X000 Amendment of application requested

St.27 status event code: A-2-2-P10-P11-nap-X000

P13-X000 Application amended

St.27 status event code: A-2-2-P10-P13-nap-X000

R15-X000 Change to inventor requested

St.27 status event code: A-3-3-R10-R15-oth-X000

R16-X000 Change to inventor recorded

St.27 status event code: A-3-3-R10-R16-oth-X000

PG1501 Laying open of application

St.27 status event code: A-1-1-Q10-Q12-nap-PG1501

D13-X000 Search requested

St.27 status event code: A-1-2-D10-D13-srh-X000

D14-X000 Search report completed

St.27 status event code: A-1-2-D10-D14-srh-X000

E902 Notification of reason for refusal
PE0902 Notice of grounds for rejection

St.27 status event code: A-1-2-D10-D21-exm-PE0902

E13-X000 Pre-grant limitation requested

St.27 status event code: A-2-3-E10-E13-lim-X000

P11-X000 Amendment of application requested

St.27 status event code: A-2-2-P10-P11-nap-X000

P13-X000 Application amended

St.27 status event code: A-2-2-P10-P13-nap-X000

E701 Decision to grant or registration of patent right
PE0701 Decision of registration

St.27 status event code: A-1-2-D10-D22-exm-PE0701

GRNT Written decision to grant
PR0701 Registration of establishment

St.27 status event code: A-2-4-F10-F11-exm-PR0701

PR1002 Payment of registration fee

St.27 status event code: A-2-2-U10-U11-oth-PR1002

Fee payment year number: 1

PG1601 Publication of registration

St.27 status event code: A-4-4-Q10-Q13-nap-PG1601

FPAY Annual fee payment

Payment date: 20140904

Year of fee payment: 4

PR1001 Payment of annual fee

St.27 status event code: A-4-4-U10-U11-oth-PR1001

Fee payment year number: 4

PR1001 Payment of annual fee

St.27 status event code: A-4-4-U10-U11-oth-PR1001

Fee payment year number: 5

PN2301 Change of applicant

St.27 status event code: A-5-5-R10-R11-asn-PN2301

PN2301 Change of applicant

St.27 status event code: A-5-5-R10-R14-asn-PN2301

R18-X000 Changes to party contact information recorded

St.27 status event code: A-5-5-R10-R18-oth-X000

FPAY Annual fee payment

Payment date: 20160830

Year of fee payment: 6

PR1001 Payment of annual fee

St.27 status event code: A-4-4-U10-U11-oth-PR1001

Fee payment year number: 6

P22-X000 Classification modified

St.27 status event code: A-4-4-P10-P22-nap-X000

P22-X000 Classification modified

St.27 status event code: A-4-4-P10-P22-nap-X000

LAPS Lapse due to unpaid annual fee
PC1903 Unpaid annual fee

St.27 status event code: A-4-4-U10-U13-oth-PC1903

Not in force date: 20171001

Payment event data comment text: Termination Category : DEFAULT_OF_REGISTRATION_FEE

PC1903 Unpaid annual fee

St.27 status event code: N-4-6-H10-H13-oth-PC1903

Ip right cessation event data comment text: Termination Category : DEFAULT_OF_REGISTRATION_FEE

Not in force date: 20171001