KR100973914B1 - Retaining nature-rock wall with plane rocks and building method thereof - Google Patents

Retaining nature-rock wall with plane rocks and building method thereof Download PDF

Info

Publication number
KR100973914B1
KR100973914B1 KR1020090117548A KR20090117548A KR100973914B1 KR 100973914 B1 KR100973914 B1 KR 100973914B1 KR 1020090117548 A KR1020090117548 A KR 1020090117548A KR 20090117548 A KR20090117548 A KR 20090117548A KR 100973914 B1 KR100973914 B1 KR 100973914B1
Authority
KR
South Korea
Prior art keywords
stone
stones
decorative
anchor
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
KR1020090117548A
Other languages
Korean (ko)
Inventor
이희종
Original Assignee
주식회사 한일환경디자인
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 한일환경디자인 filed Critical 주식회사 한일환경디자인
Priority to KR1020090117548A priority Critical patent/KR100973914B1/en
Application granted granted Critical
Publication of KR100973914B1 publication Critical patent/KR100973914B1/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0225Retaining or protecting walls comprising retention means in the backfill
    • E02D29/0233Retaining or protecting walls comprising retention means in the backfill the retention means being anchors
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/30Miscellaneous comprising anchoring details

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Revetment (AREA)

Abstract

본 발명은 평석을 구비한 뒷돌 고정식 산벽 구조물 및 그 시공방법에 관한 것으로, 더욱 상세하게는 지반에 비스듬히 각기 이격되도록 기립 배치된 복수 개의 제 1 장식석과; 상기 제 1 장식석들 사이에 각기 엇갈리게 개재된 복수 개의 제 1 지지석과; 상기 제 1 지지석들의 상부에 각기 제공된 복수 개의 평석과; 상기 평석들의 각 상부면에 상기 제 1 장식석과 각기 엇갈리게 기립 배치된 복수 개의 제 2 장식석과; 상기 제 2 장식석들 사이에 각기 엇갈리게 개재된 복수 개의 제 2 지지석과; 상기 장식석과 상기 지지석 후방에 배치된 복수 개의 뒷돌과; 상기 장식석 및 상기 지지석을 상기 뒷돌에 각기 연결시키는 복수 개의 앵커부재; 일측이 상기 장식석 배면에 삽설되고 타측이 철근콘크리트 기초의 배근부에 용접 취부되는 철근부재;를 포함하되, 상기 제 1 장식석의 하단부는 철근콘크리트 기초에 매몰되어 지지되고, 상기 제 1 지지석의 하단부는 철근콘크리트 기초에 매몰되어 지지되고, 상기 장식석, 상기 지지석, 상기 평석의 전면이 노출되고 상기 앵커부재를 매몰시키도록 토사가 뒷채움되는 것을 특징으로 하는 구조와 그 시공방법을 제공함으로써, 유연성 및 배수성이 양호하고 침하 전도에 강하고, 공사기간의 단축시켜 저단가 시공이 가능한 자연친화적 산벽을 구현 및 시공할 수 있는 특징이 있다.The present invention relates to a back stone fixed mountain wall structure having a flat stone and a construction method thereof, and more particularly, a plurality of first decorative stones that are standing up so as to be spaced apart at an angle to the ground; A plurality of first supporting stones interposed between the first decorative stones, respectively; A plurality of plystones respectively provided on top of the first supporting stones; A plurality of second decorative stones standing up alternately with the first decorative stones on each upper surface of the slate; A plurality of second supporting stones interposed between the second decorative stones, respectively; A plurality of back stones disposed behind the decorative stone and the support stone; A plurality of anchor members respectively connecting the decorative stone and the support stone to the back stone; One side is inserted into the back of the decorative stone and the other side is a reinforcing member is welded to the reinforcement portion of the reinforced concrete foundation; including, the lower end of the first decorative stone is supported by being buried in the reinforced concrete base, the lower end of the first supporting stone Is buried in the reinforced concrete foundation is supported, the front surface of the decorative stone, the support stone, the flat stone is exposed and the soil is backfilled to bury the anchor member, and by providing a construction method, flexibility And good drainage and strong settlement conduction, and can shorten the construction period, thereby realizing and constructing a natural-friendly mountain wall capable of low unit cost construction.

Description

평석을 구비한 뒷돌 고정식 산벽 구조물 및 그 시공방법 { Retaining nature-rock wall with plane rocks and building method thereof }Retaining nature-rock wall with plane rocks and building method

본 발명은 평석을 구비한 뒷돌 고정식 산벽 구조물 및 그 시공방법에 관한 것이다.The present invention relates to a back stone fixed mountain wall structure having a flat stone and a construction method thereof.

옹벽은 주택 부지, 노변 등에 형성된 경사지, 절토지 및 암반 등의 법면의 붕괴를 방지하기 위하여 설치되는 콘크리트 구조물이다. 통상적으로, 이러한 옹벽은 콘크리트로 구성된 블럭의 축조나 콘크리트 타설에 의해 형성된다.Retaining wall is a concrete structure that is installed to prevent the collapse of the slope, such as slopes, cut land and rock formed in the housing site, roadside. Typically, such retaining walls are formed by the construction of concrete blocks or by pouring concrete.

그러나, 이러한 콘크리트 구조물인 옹벽은 유연성이 적고, 배수 불량으로 침하 또는 전도될 위험이 높음은 물론, 공사기간이 길고 생태를 파괴하고 환경을 위해하고 나아가 해체시 폐기물 발생으로 인한 자연 훼손이 심각한 문제점을 있었다.However, such a retaining wall, which is a concrete structure, has a low flexibility, high risk of sinking or falling due to poor drainage, a long construction period, ecological damage, environmental damage, and further, natural damage caused by waste generation during dismantling. there was.

상기와 같은 문제점을 해결하고자 창출된 본 발명의 목적은, 주변 환경과 조화를 이룰 수 있는 친화경 구조로서 시공이 간편하고 경제적인 시공을 구현할 수 있는 평석을 구비한 뒷돌 고정식 산벽 구조물 및 그 시공방법를 제공함에 있다.An object of the present invention created to solve the above problems, as a friendly environment structure that can be harmonized with the surrounding environment is easy to install and economical construction with a back stone fixed mountain wall structure having a flat stone and its construction method In providing.

본 발명의 목적은, 자연석을 이용한 옹벽에 있어서, 지반에 비스듬히 각기 이격되도록 기립 배치된 복수 개의 제 1 장식석과; 상기 제 1 장식석들 사이에 각기 엇갈리게 개재된 복수 개의 제 1 지지석과; 상기 제 1 지지석들의 상부에 각기 제공된 복수 개의 평석과; 상기 평석들의 각 상부면에 상기 제 1 장식석과 각기 엇갈리게 기립 배치된 복수 개의 제 2 장식석과; 상기 제 2 장식석들 사이에 각기 엇갈리게 개재된 복수 개의 제 2 지지석과; 상기 장식석과 상기 지지석 후방에 배치된 복수 개의 뒷돌과; 상기 장식석 및 상기 지지석을 상기 뒷돌에 각기 연결시키는 복수 개의 앵커부재; 일측이 상기 장식석 배면에 삽설되고 타측이 철근콘크리트 기초의 배근부에 용접 취부되는 철근부재;를 포함하되, 상기 제 1 장식석의 하단부는 철근콘크리트 기초에 매몰되어 지지되고, 상기 제 1 지지석의 하단부는 철근콘크리트 기초에 매몰되어 지지되고, 상기 장식석, 상기 지지석, 상기 평석의 전면이 노출되고 상기 앵커부재를 매몰시키도록 토사가 뒷채움되는 것을 특징으로 하는 평석을 구비한 뒷돌 고정식 산벽 구조물에 의해 달성될 수 있다.An object of the present invention, in the retaining wall using a natural stone, a plurality of first decorative stones standing up so as to be spaced apart at an angle to the ground; A plurality of first supporting stones interposed between the first decorative stones, respectively; A plurality of plystones respectively provided on top of the first supporting stones; A plurality of second decorative stones standing up alternately with the first decorative stones on each upper surface of the slate; A plurality of second supporting stones interposed between the second decorative stones, respectively; A plurality of back stones disposed behind the decorative stone and the support stone; A plurality of anchor members respectively connecting the decorative stone and the support stone to the back stone; One side is inserted into the back of the decorative stone and the other side is a reinforcing member is welded to the reinforcement portion of the reinforced concrete foundation; including, the lower end of the first decorative stone is supported by being buried in the reinforced concrete base, the lower end of the first supporting stone Is buried in the reinforced concrete base is supported by, the front of the decorative stone, the support stone, the flat stone is exposed by the back stone fixed mountain wall structure, characterized in that the soil is backfilled to bury the anchor member Can be achieved.

또한, 본 발명의 다른 목적은, 자연석을 이용한 옹벽 시공방법에 있어서, 지반에 기립 배치되도록 복수 개의 제 1 장식석과 복수 개의 제 1 지지석을 각기 엇갈리게 배치하는 단계와; 상기 제 1 장식석들과 상기 제 1 지지석들 후방에 복수 개의 뒷돌을 배치하여 각기 앵커부재로 연결시키는 단계와; 상기 제 1 지지석들의 상부에 각기 복수 개의 평석을 배치하는 단계와; 상기 평석들의 각 상부면에 상기 제 1 장식석과 각기 엇갈리게 복수 개의 제 2 장식석을 배치하고, 복수 개의 상기 제 2 장식석과 복수 개의 제 2 지지석을 각기 엇갈리게 배치하는 단계와; 상기 제 2 장식석들과 상기 제 2 지지석들 후방에 복수 개의 뒷돌을 배치하여 각기 앵커부재로 연결시키는 단계; 철근부재의 일측이 상기 장식석 배면에 삽설되고 타측이 콘크리트 기초의 배근부에 용접 취부되는 단계;를 포함하는 평석을 구비한 뒷돌 고정식 산벽 시공방법에 의해 달성될 수 있다.In addition, another object of the present invention, in the retaining wall construction method using a natural stone, the step of arranging a plurality of first decorative stones and a plurality of first support stones, respectively, so as to stand up on the ground; Arranging a plurality of back stones behind the first decorative stones and the first supporting stones and connecting the anchor stones to the anchor members, respectively; Arranging a plurality of plystones on top of the first support stones, respectively; Arranging a plurality of second decorative stones alternately with the first decorative stone on each upper surface of the slate, and arranging the plurality of second decorative stones and the plurality of second supporting stones respectively; Arranging a plurality of back stones behind the second decorative stones and the second supporting stones and connecting the anchor stones to the anchor members, respectively; One side of the rebar member is inserted into the back of the decorative stone and the other side is welded to the reinforcement portion of the concrete foundation; it can be achieved by a back stone fixed mountain wall construction method comprising a flat stone.

이상의 구성을 갖는 본 발명은 유연성 및 배수성이 양호하고 침하 전도에 강하고, 공사기간의 단축시켜 저단가 시공이 가능한 자연친화적 산벽을 구현 및 시공할 수 있는 효과가 있다.The present invention having the above configuration is good in flexibility and drainage, strong in subsidence conduction, and can shorten the construction period, thereby realizing and constructing a natural-friendly mountain wall capable of low cost construction.

이하, 도면을 참조하여 본 발명의 구성을 상세히 설명하면 다음과 같으며, 동일한 구성요소에 대해서는 별도의 번호매김을 하지 않음을 미리 밝혀둔다.Hereinafter, the configuration of the present invention with reference to the drawings in detail as follows, it will be clear that the same components do not have a separate numbering in advance.

도 1은 본 발명의 제 1 실시예에 의한 평석을 구비한 뒷돌 고정식 산벽 구조물의 일부를 나타내는 사시도이고, 도 2는 도 1의 단면도이고, 도 3은 본 발명의 산벽 구조물의 최하층을 개략적으로 나타내는 평면도이고, 도 4는 본 발명의 산벽 구조물의 두 번째 층을 개략적으로 나타내는 평면도이고, 도 5는 본 발명의 산벽 구조물의 최상층을 개략적으로 나타내는 평면도이다1 is a perspective view showing a part of a back stone fixed mountain wall structure having a flat stone according to a first embodiment of the present invention, Figure 2 is a cross-sectional view of Figure 1, Figure 3 schematically shows the lowest layer of the mountain wall structure of the present invention 4 is a plan view schematically illustrating a second layer of the mountain wall structure of the present invention, and FIG. 5 is a plan view schematically showing a top layer of the mountain wall structure of the present invention.

도 1 내지 도 5를 참조하면, 본 발명에 의한 산벽 구조물은 지반에 비스듬히 각기 이격되도록 기립 배치된 복수 개의 제 1 장식석(11), 제 1 장식석들(11) 사이에 각기 엇갈리게 개재된 복수 개의 제 1 지지석(21)과, 제 1 지지석들(21)의 상부에 각기 제공된 복수 개의 평석(31)과, 평석들(31)의 각 상부면에 제 1 장식석(11)과 각기 엇갈리게 기립 배치된 복수 개의 제 2 장식석(13)과, 제 2 장식석들(13) 사이에 각기 엇갈리게 개재된 복수 개의 제 2 지지석(23)과, 장식석(11)(13)과 지지석(21)(23) 후방에 배치된 복수 개의 뒷돌(51)(53)과, 장식석(11)(13) 및 지지석(21)(23)을 뒷돌(51)(53)에 각기 연결시키는 복수 개의 앵커부재(61)(63)(65)를 포함한다.1 to 5, the mountain wall structure according to the present invention includes a plurality of first intersecting stones interposed between a plurality of first decorative stones 11 and first decorative stones 11 that are erected to be spaced apart from each other at an angle to the ground. First support stones 21, a plurality of plystones 31 respectively provided on top of the first support stones 21, and a first decorative stone 11 and each on each upper surface of the plystones 31, respectively. A plurality of second decorative stones 13 staggered and standing, a plurality of second supporting stones 23 alternately interposed between the second decorative stones 13, decorative stones 11, 13 and support A plurality of back stones 51 and 53 arranged behind the seats 21 and 23, and decorative stones 11 and 13 and support stones 21 and 23 are respectively connected to the back stones 51 and 53, respectively. It includes a plurality of anchor members 61, 63, 65 to.

제 1 장식석(11)은 지반에 일정한 각도로 비스듬히 이격되도록 복수 개가 배치되어 있다. 여기서, 제 1 장식석(11)의 하단부는 콘크리트 기초에 매몰되도록 하여 강력한 지지를 구현하고 있다. 그리고, 제 1 장식석(11)은 두께가 얇고 폭 길이보다는 높이 길이가 큰 석재를 사용하는 것이 보다 아름다운 조경을 구현할 수 있음은 물론, 본 발명의 산벽 구조의 특징인 수직 조경방법에 대응할 수 있다.A plurality of first decorative stones 11 are disposed so as to be spaced at an angle to the ground at an angle. Here, the lower end of the first decorative stone 11 is embedded in the concrete foundation to implement a strong support. In addition, the first decorative stone 11 may use a stone having a thin thickness and a large height length rather than a width length to implement more beautiful landscaping, and may correspond to a vertical landscaping method, which is a feature of the mountain wall structure of the present invention. .

제 1 지지석(21)은 제 1 장식석들(11) 사이에 엇갈리게 각기 배치되어 있어 전체적으로 제 1 장식석(11)과 제 1 지지석(21)은 지그재그로 배치되어 있다. 여기서, 제 1 지지석(21)은 양단부가 제 1 장식석들(11)의 측면에 밀착되어 지지함으로써 일종의 셀(shell) 구조를 형성함으로써 배수가 양호하고, 침하 전도에 강한 특징이 있다.The first supporting stones 21 are alternately arranged between the first decorative stones 11 so that the first decorative stones 11 and the first supporting stones 21 are arranged in a zigzag. Here, the first support stone 21 is formed in a kind of shell (shell structure) by supporting both ends in close contact with the side surfaces of the first decorative stones 11, the drainage is good, and has a strong characteristic to settle conduction.

그리고, 제 1 지지석(21)의 하단부는 콘크리트 기초에 매몰되어 있다.The lower end of the first supporting stone 21 is embedded in the concrete foundation.

평석(31)은 제 1 지지석들(21)의 상부에 각기 배치되어 있다. 여기서, 평석(31)은 제 1 장식석(11)이 기립되어 있는 것과는 달리 와립(臥立)되어 있으며, 상부면은 제 2 장식석(13)이 정립될 수 있도록 이에 대응된 형상을 갖는 것이 바람직하다.The flat stones 31 are respectively disposed on the upper portions of the first supporting stones 21. Here, the flat stone 31 is granulated unlike the first decorative stone 11 is standing, the upper surface has a shape corresponding to the second decorative stone 13 can be established. desirable.

그리고, 본 발명에 의한 평석(31)은 제 2 장식석(13)의 기초 역할을 수행함은 물론, 보다 자연스러운 심미감을 현출할 수 있는 특징이 있다.In addition, the flat stone 31 according to the present invention serves as a basic role of the second decorative stone 13, as well as a feature that can exhibit a more natural aesthetics.

제 2 장식석(13)은 평석들(31)의 각 상부면에 제 1 장식석(11)과 각기 엇갈리게 기립되도록 복수 개가 배치되어 있다. 여기서, 제 2 장식석(13)은 두께가 얇고 폭 길이보다는 높이 길이가 큰 석재를 사용하는 것이 보다 아름다운 조경을 구현할 수 있음은 물론, 본 발명의 산벽 구조의 특징인 수직 조경방법에 대응할 수 있다.A plurality of second decorative stones 13 are arranged on each upper surface of the flat stones 31 so as to stand up alternately with the first decorative stones 11. Here, the second decorative stone 13 can be used to implement a more beautiful landscaping, as well as a vertical landscaping method which is a feature of the mountain wall structure of the present invention using a stone having a thin thickness and a height length larger than the width length. .

제 2 지지석(23)은 제 2 장식석들(13) 사이에 엇갈리게 각기 배치되어 있어 전체적으로 제 2 장식석(13)과 제 2 지지석(23)은 지그재그로 배치되어 있다. 여기서, 제 2 지지석(23)은 양단부가 제 2 장식석들(13)의 측면에 밀착되어 지지함으로써 일종의 셀(shell) 구조를 형성함으로써 배수가 양호하고, 침하 전도에 강한 특징이 있다.The second supporting stones 23 are alternately arranged between the second decorative stones 13 so that the second decorative stones 13 and the second supporting stones 23 are arranged in a zigzag as a whole. Here, the second support stone 23 has a good drainage by forming a kind of shell structure by supporting both ends in close contact with the side surfaces of the second decorative stones (13), and has a strong characteristic against settlement conduction.

하부 뒷돌(51)은 제 1 장식석(11)과 제 1 지지석(21)의 후방에 배치되어 각기 대응된 앵커부재(63)에 의해 연결되어 있다. 그리고, 상부 뒷돌(53)은 제 2 장식석(13)과 제 2 지지석(23)의 후방에 배치되어 각기 대응된 앵커부재(65)에 의해 연결되어 있다.The lower back stone 51 is disposed behind the first decorative stone 11 and the first supporting stone 21 and connected by the corresponding anchor members 63, respectively. And, the upper back stone 53 is disposed behind the second decorative stone 13 and the second support stone 23 is connected by the corresponding anchor member 65, respectively.

또한, 상부 뒷돌(53)은 하부 뒷돌(51)의 수직 상방으로 일정 거리 이격되도록 위치되어 있다.In addition, the upper back stone 53 is positioned to be spaced apart a predetermined distance vertically upward of the lower back stone 51.

그리고, 토사는 장식석(11)(13), 지지석(21)(23), 평석(31)의 전면이 노출되도록 하고, 앵커부재(61)(63)를 매몰시키도록 뒷채움되어 있다. 여기서, 뒷채움되는 토사에는 일반적인 흙에 한정된 것으로 설명하고 있으나 이에 한정하지 않고 자갈이나 기타 잡석 등도 일부 포함될 수 있다.The earth and sand are backfilled to expose the entire surface of the decorative stones 11 and 13, the support stones 21 and 23, and the flat stone 31, and to bury the anchor members 61 and 63. Here, the backfilled soil is described as being limited to general soil, but is not limited thereto, and may include some gravel or other rubble.

상부 평석(33)은 제 2 장식석들(13)에 각기 엇갈리게 개재되도록 토사에 복수 개가 배치되어 있다. 여기서, 상부 평석(33)은 장식석(11)(13)이 기립되어 있는 것과는 달리 와립(臥立)되어 있으며, 상부면은 후술되는 상부 장식석(15)이 정립될 수 있도록 이에 대응된 형상을 갖는 것이 바람직하다.A plurality of upper flat stones 33 are arranged in the soil to be interposed between the second decorative stones 13, respectively. Here, the upper flat stone 33 is granulated unlike the decorative stone (11, 13) is standing, and the upper surface has a shape corresponding to this so that the upper decorative stone 15 to be described later can be established It is preferable to have.

그리고, 본 발명에 의한 상부 평석(33)은 상부 장식석(15)의 기초 역할을 수행함은 물론, 보다 자연스러운 심미감을 현출할 수 있는 특징이 있다.In addition, the upper flat stone 33 according to the present invention serves as a basis of the upper decorative stone 15, as well as has a feature that can exhibit a more natural aesthetics.

상부 장식석(15)은 상부 평석들(33)의 각 상부면에 제 2 장식석(13)과 각기 엇갈리게 복수 개가 기립 배치되어 있다. 여기서, 상부 장식석(15)은 두께가 얇고 폭 길이보다는 높이 길이가 큰 석재를 사용하는 것이 보다 아름다운 조경을 구현할 수 있음은 물론, 본 발명의 산벽 구조의 특징인 수직 조경방법에 대응할 수 있다.A plurality of upper feldspar 15 is standing on the upper surface of each of the upper flat stones 33 and the plurality of the standing feldspar alternately with each other. Here, the upper decorative stone 15 can be used to implement a more beautiful landscaping, as well as the vertical landscaping method of the mountain wall structure of the present invention using a stone having a thin thickness and a large height length rather than the width length.

상부 지지석(25)은 상부 장식석들(15) 사이에 엇갈리게 각기 배치되어 있어 전체적으로 상부 지지석(15)과 상부 지지석(25)은 지그재그로 배치되어 있다. 여기서, 상부 지지석(25)은 양단부가 상부 장식석들(15)의 측면에 밀착되어 지지함으로써 일종의 셀(shell) 구조를 형성함으로써 배수가 양호하고, 침하 전도에 강한 특징이 있다.The upper support seats 25 are alternately arranged between the upper decorative stones 15 so that the upper support seats 15 and the upper support seats 25 are arranged in a zigzag as a whole. Here, the upper support stone 25 is formed by a kind of shell (shell) structure by supporting both ends in close contact with the side of the upper decorative stones 15 has a good drainage, it is characterized by strong settlement conduction.

본 발명의 상부 장식석(15)과 상부 지지석(25)은 최상층에 해당되며 뒷돌에 의하여 연결되지 않는 구조를 갖는다. 또한, 토사는 상부 장식석(15), 상부 지지석(25)의 전면이 노출되도록 뒷채움되어 있다. 여기서, 뒷채움되는 토사에는 일반적인 흙에 한정된 것으로 설명하고 있으나 이에 한정하지 않고 자갈이나 기타 잡석 등도 일부 포함될 수 있다. The upper decorative stone 15 and the upper support stone 25 of the present invention corresponds to the uppermost layer and has a structure that is not connected by the back stone. In addition, the earth and sand are back-filled so that the front face of the upper decorative stone 15, the upper support stone 25 is exposed. Here, the backfilled soil is described as being limited to general soil, but is not limited thereto, and may include some gravel or other rubble.

도 6은 장식석과 뒷돌의 연결 구조를 개략적으로 나타내는 단면도이다. 여기서, 앵커부재의 도면부호는 도 2를 참조하기로 한다.6 is a cross-sectional view schematically showing a connection structure between the decorative stone and the back stone. Here, reference numerals of the anchor members will be referred to FIG. 2.

도 6을 참조하면, 본 발명에 의한 앵커부재(61)(63)는 제 1 장식석(11)의 배면과 하부 뒷돌(51)의 전면을 연결시키거나, 또는 제 1 장식석(11)의 배면과 콘크리트 기초(70)의 배근부(71)를 연결시키는 구성을 갖는다.Referring to FIG. 6, the anchor members 61 and 63 according to the present invention connect the rear surface of the first decorative stone 11 and the front surface of the lower back stone 51 or the first decorative stone 11 of the first decorative stone 11. It has the structure which connects the back side 71 of the concrete foundation 70 with the back surface.

먼저, 제 1 장식석(11)의 배면과 하부 뒷돌(51)의 전면을 연결시키는 앵커부재(63)는 제 1 장식석(11)의 배면에 삽설된 제 1 앵커(63a)과, 하부 뒷돌(51)의 전면에 삽설된 제 2 앵커(63b)와, 앵커들(63a)(63b)의 각 일단부와 각기 용접 취부된 한 쌍의 철근 부재(63c-1)(63c-2)와, 철근 부재(63c-1)(63c-2)의 각 타단부를 연결시키는 커플링(63d)으로 이루어져 있다.First, the anchor member 63 connecting the rear surface of the first decorative stone 11 and the front surface of the lower rear stone 51 includes a first anchor 63a inserted into the rear surface of the first decorative stone 11 and the lower rear stone. A second anchor 63b inserted into the front surface of the 51, a pair of reinforcing members 63c-1 and 63c-2 welded and attached to each one end of the anchors 63a and 63b, respectively; It consists of a coupling 63d which connects the other ends of the reinforcing member 63c-1 and 63c-2.

본 발명에 의한 실시예에서 커플링(63d)을 적용하는 이유는 연결 자유도가 낮아 철근 부재(63c-1)(63c-2) 만으로 바람직하는 연결이 곤란하고, 또한 강력한 결합력이 요구되는 경우가 실제 시공에 있어 빈번하기 때문이다. 또한, 커플링(63d)은 일정한 토크값을 정하여 획일화할 수 있어 작업자에 의한 용접 실수 등을 미연에 방지할 수 있는 특징이 있다.The reason why the coupling 63d is applied in the embodiment according to the present invention is that the connection freedom is low, and the preferable connection is difficult only with the reinforcing members 63c-1 and 63c-2, and a strong coupling force is actually required. This is because it is frequent in construction. In addition, the coupling 63d can be uniformized by setting a constant torque value, and has a feature of preventing welding mistakes and the like by the operator.

또한, 제 1 장식석(11)의 배면과 콘크리트 기초(70)의 배근부(71)를 연결시키는 앵커부재(61)는 철근 부재(61b-2)의 일단부가 콘크리트 기초(70)의 배근부(71)에 용접 취부되어 있는 것 외에는 위의 구조와 동일하기 때문에 이에 대한 상세한 설명은 생략하기로 한다.In addition, the anchor member 61 connecting the rear surface of the first decorative stone 11 and the reinforcement portion 71 of the concrete foundation 70 has one end of the reinforcing member 61b-2 being the reinforcement portion of the concrete foundation 70. Except for being welded to (71), it is the same as the above structure, so detailed description thereof will be omitted.

그리고, 철근 부재(61b-1)(61b-2)(63c-1)(63c-2)는 토사에 장기간 매몰되는 것으로 평균 부식속도가 0.02mm/year인 경우 100년의 내용 년수로 설계될 수 있도 록 부식방지용 에폭시 계열의 합성수지로 피복되는 것이 매우 바람직하다.The reinforcing members 61b-1, 61b-2, 63c-1 and 63c-2 are buried in the soil for a long time and can be designed for a service life of 100 years when the average corrosion rate is 0.02 mm / year. It is highly desirable to be coated with a corrosion-resistant epoxy resin.

본 발명에 의한 평석을 구비한 뒷돌 고정식 산벽 시공방법을 설명하면 다음과 같다.Referring to the method of constructing a back stone fixed mountain wall with a flat stone according to the present invention.

먼저, 지반에 기립 배치되도록 복수 개의 제 1 장식석(11)과 복수 개의 제 1 지지석(21)을 각기 엇갈리게 배치한다.First, the plurality of first decorative stones 11 and the plurality of first supporting stones 21 are alternately arranged so as to stand on the ground.

그런 다음, 제 1 장식석들(11)과 제 1 지지석들(21) 후방에 복수 개의 하부 뒷돌(51)을 배치한 후 각기 앵커부재(61)(63)로 연결시킨다. 여기서, 앵커부재(61) (63)는 전술된 바와 같이 제 1 장식석들(11)과 제 1 지지석들(21)을 연결시키거나 또는 제 1 장식석들(11)과 콘크리트 기초(70)의 배근부(71)를 연결 고정한다.Then, a plurality of lower back stones 51 are disposed behind the first decorative stones 11 and the first supporting stones 21 and then connected to the anchor members 61 and 63, respectively. Here, the anchor members 61 and 63 connect the first decorative stones 11 and the first supporting stones 21 as described above, or the first decorative stones 11 and the concrete foundation 70. Fix the back muscle part 71).

그리고, 제 1 지지석들(21)의 상부에 각기 복수 개의 평석(31)을 배치한다. 이때, 토사 뒷채움을 시행할 수도 있다.Then, a plurality of flat stones 31 are respectively disposed on the upper portions of the first supporting stones 21. At this time, the earth and sand may be filled.

계속해서, 평석들(31)의 각 상부면에 제 1 장식석(11)과 각기 엇갈리게 복수 개의 제 2 장식석(13)을 배치하고, 복수 개의 제 2 장식석(13)과 복수 개의 제 2 지지석(23)을 각기 엇갈리게 배치한다.Subsequently, a plurality of second decorative stones 13 and a plurality of second decorative stones 13 and a plurality of second are arranged alternately with the first decorative stone 11 on each upper surface of the flat stones 31. The support seats 23 are alternately arranged.

그리고, 제 2 장식석들(13)과 제 2 지지석들(23) 후방에 복수 개의 상부 뒷돌(53)을 배치한 후 각기 앵커부재(65)로 연결시킨다. 이때, 토사 뒷채움을 시행할 수도 있다.Then, the plurality of upper back stones 53 are disposed behind the second decorative stones 13 and the second support stones 23, and then connected to the anchor members 65, respectively. At this time, the earth and sand may be filled.

또한, 장식석(11)(13), 지지석(21)(23), 평석(31)의 전면이 노출되고 앵커부 재(61)(63)(65)를 매몰시키도록 토사로 뒷채움한다.Further, the front surfaces of the decorative stones 11, 13, the support stones 21, 23, and the flat stones 31 are exposed and backfilled with earth and sand to bury the anchor members 61, 63, 65.

이후, 최상층을 준비하는 경우에는, 제 2 장식석들(13)에 각기 엇갈리게 개재되도록 토사에 복수 개의 상부 평석(33)를 배치하고, 상부 평석들(33)의 각 상부면에 제 2 장식석들(13)과 각기 엇갈리게 복수 개의 상부 장식석(15)을 기립되게 배치한다. 그리고, 상부 장식석들(15)에 각기 엇갈리게 개재되도록 복수 개의 상부 지지석(25)를 배치한 다음, 토사로 뒷매움을 한다.Subsequently, in the case of preparing the uppermost layer, a plurality of upper slabs 33 are disposed in the earth and sand so as to interpose with the second slabs 13, and the second slabs on each upper surface of the upper slabs 33. A plurality of upper decorative stones 15 are placed upright and staggered with the fields 13. Then, the plurality of upper support stones 25 are arranged so as to interpose each other in the upper decorative stones 15, and then backfill with earth and sand.

마지막으로, 사이목을 배식하고 일정 시간이 경과하면 식재가 활착되어 아름답고 수려한 자연석으로 이루어진 산벽이 완성된다.Finally, after a certain time has elapsed after planting the samok, plantings are active and the mountain wall made of beautiful and beautiful natural stone is completed.

도 7은 본 발명의 제 1 실시예에 의한 평석을 구비한 뒷돌 고정식 산벽 구조물의 일부를 나타내는 사시도이고, 도 8은 도 7의 단면도이고, 도 9는 본 발명의 산벽 구조물의 최하층을 개략적으로 나타내는 평면도이고, 도 10은 본 발명의 산벽 구조물의 두 번째 층을 개략적으로 나타내는 평면도이고, 도 11은 본 발명의 산벽 구조물의 최상층을 개략적으로 나타내는 평면도이다FIG. 7 is a perspective view showing a part of a fixed stone wall structure having a backstone according to a first embodiment of the present invention, FIG. 8 is a cross-sectional view of FIG. 7, and FIG. 9 schematically shows a bottom layer of the mountain wall structure of the present invention. 10 is a plan view schematically showing a second layer of the mountain wall structure of the present invention, and FIG. 11 is a plan view schematically showing a top layer of the mountain wall structure of the present invention.

도 7 내지 도 11를 참조하면, 본 발명에 의한 산벽 구조물은 지반에 비스듬히 각기 이격되도록 기립 배치된 복수 개의 제 1 장식석(11), 제 1 장식석들(11) 사이에 각기 엇갈리게 개재된 복수 개의 제 1 지지석(21)과, 제 1 지지석들(21)의 상부에 각기 제공된 복수 개의 평석(31)과, 평석들(31)의 각 상부면에 제 1 장식석(11)과 각기 엇갈리게 기립 배치된 복수 개의 제 2 장식석(13)과, 제 2 장식석들(13) 사이에 각기 엇갈리게 개재된 복수 개의 제 2 지지석(23)과, 장식 석(11)(13)과 지지석(21)(23) 후방에 배치된 복수 개의 뒷돌(51)(53)과, 장식석(11)(13) 및 지지석(21)(23)을 뒷돌(51)(53)에 각기 연결시키는 복수 개의 앵커부재(61)(63)(65)를 포함한다.7 to 11, the mountain wall structure according to the present invention includes a plurality of first intersecting stones interposed between a plurality of first decorative stones 11 and first decorative stones 11 that are standing up so as to be spaced apart from each other at an angle to the ground. First support stones 21, a plurality of plystones 31 respectively provided on top of the first support stones 21, and a first decorative stone 11 and each on each upper surface of the plystones 31, respectively. A plurality of second decorative stones 13 staggered and standing, a plurality of second supporting stones 23 interposed between the second decorative stones 13, decorative stones 11, 13 and support A plurality of back stones 51 and 53 arranged behind the seats 21 and 23, and decorative stones 11 and 13 and support stones 21 and 23 are respectively connected to the back stones 51 and 53, respectively. It includes a plurality of anchor members 61, 63, 65 to.

제 1 장식석(11)은 지반에 일정한 각도로 비스듬히 이격되도록 복수 개가 배치되어 있다. 여기서, 제 1 장식석(11)의 하단부는 콘크리트 기초에 매몰되도록 하여 강력한 지지를 구현하고 있다. 그리고, 제 1 장식석(11)은 두께가 얇고 폭 길이보다는 높이 길이가 큰 석재를 사용하는 것이 보다 아름다운 조경을 구현할 수 있음은 물론, 본 발명의 산벽 구조의 특징인 수직 조경방법에 대응할 수 있다.A plurality of first decorative stones 11 are disposed so as to be spaced at an angle to the ground at an angle. Here, the lower end of the first decorative stone 11 is embedded in the concrete foundation to implement a strong support. In addition, the first decorative stone 11 may use a stone having a thin thickness and a large height length rather than a width length to implement more beautiful landscaping, and may correspond to a vertical landscaping method, which is a feature of the mountain wall structure of the present invention. .

제 1 지지석(21)은 제 1 장식석들(11) 사이에 엇갈리게 각기 배치되어 있어 전체적으로 제 1 장식석(11)과 제 1 지지석(21)은 지그재그로 배치되어 있다. 여기서, 제 1 지지석(21)은 양단부가 제 1 장식석들(11)의 측면에 밀착되어 지지함으로써 일종의 셀(shell) 구조를 형성함으로써 배수가 양호하고, 침하 전도에 강한 특징이 있다.The first supporting stones 21 are alternately arranged between the first decorative stones 11 so that the first decorative stones 11 and the first supporting stones 21 are arranged in a zigzag. Here, the first support stone 21 is formed in a kind of shell (shell structure) by supporting both ends in close contact with the side surfaces of the first decorative stones 11, the drainage is good, and has a strong characteristic to settle conduction.

그리고, 제 1 지지석(21)의 하단부는 콘크리트 기초에 매몰되어 있다.The lower end of the first supporting stone 21 is embedded in the concrete foundation.

평석(31)은 제 1 지지석들(21)의 상부에 각기 배치되어 있다. 여기서, 평석(31)은 제 1 장식석(11)이 기립되어 있는 것과는 달리 와립(臥立)되어 있으며, 상부면은 제 2 장식석(13)이 정립될 수 있도록 이에 대응된 형상을 갖는 것이 바람 직하다.The flat stones 31 are respectively disposed on the upper portions of the first supporting stones 21. Here, the flat stone 31 is granulated unlike the first decorative stone 11 is standing, the upper surface has a shape corresponding to the second decorative stone 13 can be established. desirable.

그리고, 본 발명에 의한 평석(31)은 제 2 장식석(13)의 기초 역할을 수행함은 물론, 보다 자연스러운 심미감을 현출할 수 있는 특징이 있다.In addition, the flat stone 31 according to the present invention serves as a basic role of the second decorative stone 13, as well as a feature that can exhibit a more natural aesthetics.

제 2 장식석(13)은 평석들(31)의 각 상부면에 제 1 장식석(11)과 각기 엇갈리게 기립되도록 복수 개가 배치되어 있다. 여기서, 제 2 장식석(13)은 두께가 얇고 폭 길이보다는 높이 길이가 큰 석재를 사용하는 것이 보다 아름다운 조경을 구현할 수 있음은 물론, 본 발명의 산벽 구조의 특징인 수직 조경방법에 대응할 수 있다.A plurality of second decorative stones 13 are arranged on each upper surface of the flat stones 31 so as to stand up alternately with the first decorative stones 11. Here, the second decorative stone 13 can be used to implement a more beautiful landscaping, as well as a vertical landscaping method which is a feature of the mountain wall structure of the present invention using a stone having a thin thickness and a height length larger than the width length. .

제 2 지지석(23)은 제 2 장식석들(13) 사이에 엇갈리게 각기 배치되어 있어 전체적으로 제 2 장식석(13)과 제 2 지지석(23)은 지그재그로 배치되어 있다. 여기서, 제 2 지지석(23)은 양단부가 제 2 장식석들(13)의 측면에 밀착되어 지지함으로써 일종의 셀(shell) 구조를 형성함으로써 배수가 양호하고, 침하 전도에 강한 특징이 있다.The second supporting stones 23 are alternately arranged between the second decorative stones 13 so that the second decorative stones 13 and the second supporting stones 23 are arranged in a zigzag as a whole. Here, the second support stone 23 has a good drainage by forming a kind of shell structure by supporting both ends in close contact with the side surfaces of the second decorative stones (13), and has a strong characteristic against settlement conduction.

하부 뒷돌(51)은 제 1 장식석(11)과 제 1 지지석(21)의 후방에 배치되어 각기 대응된 앵커부재(63)에 의해 연결되어 있다. 그리고, 상부 뒷돌(53)은 제 2 장식석(13)과 제 2 지지석(23)의 후방에 배치되어 각기 대응된 앵커부재(65)에 의해 연결되어 있다.The lower back stone 51 is disposed behind the first decorative stone 11 and the first supporting stone 21 and connected by the corresponding anchor members 63, respectively. And, the upper back stone 53 is disposed behind the second decorative stone 13 and the second support stone 23 is connected by the corresponding anchor member 65, respectively.

또한, 상부 뒷돌(53)은 하부 뒷돌(51)의 수직 상방으로 일정 거리 이격되도록 위치되어 있다.In addition, the upper back stone 53 is positioned to be spaced apart a predetermined distance vertically upward of the lower back stone 51.

그리고, 토사는 장식석(11)(13), 지지석(21)(23), 평석(31)의 전면이 노출되도록 하고, 앵커부재(61)(63)를 매몰시키도록 뒷채움되어 있다. 여기서, 뒷채움되는 토사에는 일반적인 흙에 한정된 것으로 설명하고 있으나 이에 한정하지 않고 자갈이나 기타 잡석 등도 일부 포함될 수 있다.The earth and sand are backfilled to expose the entire surface of the decorative stones 11 and 13, the support stones 21 and 23, and the flat stone 31, and to bury the anchor members 61 and 63. Here, the backfilled soil is described as being limited to general soil, but is not limited thereto, and may include some gravel or other rubble.

상부 장식석(15)은 하부에 배치된 제 2 장식석(13)과 각기 엇갈리게 복수 개가 기립 배치되다. 여기서, 상부 장식석(15)은 두께가 얇고 폭 길이보다는 높이 길이가 큰 석재를 사용하는 것이 보다 아름다운 조경을 구현할 수 있음은 물론, 본 발명의 산벽 구조의 특징인 수직 조경방법에 대응할 수 있다. 또한, 상부 장식석(15)은 토사 위에 배치된다.The upper decorative stone 15 is a plurality of standing up staggered with the second decorative stone 13 disposed in the lower each. Here, the upper decorative stone 15 can be used to implement a more beautiful landscaping, as well as the vertical landscaping method of the mountain wall structure of the present invention using a stone having a thin thickness and a large height length rather than the width length. In addition, the upper decorative stone 15 is disposed on the soil.

상부 지지석(25)은 상부 장식석들(15) 사이에 엇갈리게 각기 배치되어 있어 전체적으로 상부 지지석(15)과 상부 지지석(25)은 지그재그로 배치되어 있다. 여기서, 상부 지지석(25)은 양단부가 상부 장식석들(15)의 측면에 밀착되어 지지함으로써 일종의 셀(shell) 구조를 형성함으로써 배수가 양호하고, 침하 전도에 강한 특징이 있다.The upper support seats 25 are alternately arranged between the upper decorative stones 15 so that the upper support seats 15 and the upper support seats 25 are arranged in a zigzag as a whole. Here, the upper support stone 25 is formed by a kind of shell (shell) structure by supporting both ends in close contact with the side of the upper decorative stones 15 has a good drainage, it is characterized by strong settlement conduction.

본 발명의 상부 장식석(15)과 상부 지지석(25)은 최상층에 해당되며 뒷돌에 의하여 연결되지 않는 구조를 갖는다. 또한, 토사는 상부 장식석(15), 상부 지지석(25)의 전면이 노출되도록 뒷채움되어 있다. 여기서, 뒷채움되는 토사에는 일반적인 흙에 한정된 것으로 설명하고 있으나 이에 한정하지 않고 자갈이나 기타 잡석 등도 일부 포함될 수 있다. The upper decorative stone 15 and the upper support stone 25 of the present invention corresponds to the uppermost layer and has a structure that is not connected by the back stone. In addition, the earth and sand are back-filled so that the front face of the upper decorative stone 15, the upper support stone 25 is exposed. Here, the backfilled soil is described as being limited to general soil, but is not limited thereto, and may include some gravel or other rubble.

도 12는 장식석과 뒷돌의 연결 구조를 개략적으로 나타내는 단면도이다. 여기서, 앵커부재의 도면부호는 도 2를 참조하기로 한다.12 is a cross-sectional view schematically showing the connection structure between the decorative stone and the back stone. Here, reference numerals of the anchor members will be referred to FIG. 2.

도 12를 참조하면, 본 발명에 의한 앵커부재(61)(63)는 제 1 장식석(11)의 배면과 하부 뒷돌(51)의 전면을 연결시키거나, 또는 제 1 장식석(11)의 배면과 콘크리트 기초(70)의 배근부(71)를 연결시키는 구성을 갖는다.Referring to FIG. 12, the anchor members 61 and 63 according to the present invention connect the rear surface of the first decorative stone 11 and the front surface of the lower back stone 51 or the first decorative stone 11 of the first decorative stone 11. It has the structure which connects the back side 71 of the concrete foundation 70 with the back surface.

먼저, 제 1 장식석(11)의 배면과 하부 뒷돌(51)의 전면을 연결시키는 앵커부재(63)는 제 1 장식석(11)의 배면에 삽설된 제 1 앵커(63a)과, 하부 뒷돌(51)의 전면에 삽설된 제 2 앵커(63b)와, 앵커들(63a)(63b)의 각 일단부와 각기 용접 취부된 한 쌍의 철근 부재(63c-1)(63c-2)와, 철근 부재(63c-1)(63c-2)의 각 타단부를 연결시키는 커플링(63d)으로 이루어져 있다.First, the anchor member 63 connecting the rear surface of the first decorative stone 11 and the front surface of the lower rear stone 51 includes a first anchor 63a inserted into the rear surface of the first decorative stone 11 and the lower rear stone. A second anchor 63b inserted into the front surface of the 51, a pair of reinforcing members 63c-1 and 63c-2 welded and attached to each one end of the anchors 63a and 63b, respectively; It consists of a coupling 63d which connects the other ends of the reinforcing member 63c-1 and 63c-2.

본 발명에 의한 실시예에서 커플링(63d)을 적용하는 이유는 연결 자유도가 낮아 철근 부재(63c-1)(63c-2) 만으로 바람직하는 연결이 곤란하고, 또한 강력한 결합력이 요구되는 경우가 실제 시공에 있어 빈번하기 때문이다. 또한, 커플링(63d)은 일정한 토크값을 정하여 획일화할 수 있어 작업자에 의한 용접 실수 등 을 미연에 방지할 수 있는 특징이 있다.The reason why the coupling 63d is applied in the embodiment according to the present invention is that the connection freedom is low, and the preferable connection is difficult only with the reinforcing members 63c-1 and 63c-2, and a strong coupling force is actually required. This is because it is frequent in construction. In addition, the coupling (63d) can be uniformized by setting a constant torque value has a feature that can prevent the welding mistake by the operator in advance.

또한, 제 1 장식석(11)의 배면과 콘크리트 기초(70)의 배근부(71)를 연결시키는 앵커부재(61)는 철근 부재(61b-2)의 일단부가 콘크리트 기초(70)의 배근부(71)에 용접 취부되어 있는 것 외에는 위의 구조와 동일하기 때문에 이에 대한 상세한 설명은 생략하기로 한다.In addition, the anchor member 61 connecting the rear surface of the first decorative stone 11 and the reinforcement portion 71 of the concrete foundation 70 has one end of the reinforcing member 61b-2 being the reinforcement portion of the concrete foundation 70. Except for being welded to (71), it is the same as the above structure, so detailed description thereof will be omitted.

그리고, 철근 부재(61b-1)(61b-2)(63c-1)(63c-2)는 토사에 장기간 매몰되는 것으로 평균 부식속도가 0.02mm/year인 경우 100년의 내용 년수로 설계될 수 있도록 부식방지용 에폭시 계열의 합성수지로 피복되는 것이 매우 바람직하다.The reinforcing members 61b-1, 61b-2, 63c-1 and 63c-2 are buried in the soil for a long time and can be designed for a service life of 100 years when the average corrosion rate is 0.02 mm / year. It is highly desirable to be coated with a corrosion-resistant epoxy resin.

본 발명에 의한 평석을 구비한 뒷돌 고정식 산벽 시공방법을 설명하면 다음과 같다.Referring to the method of constructing a back stone fixed mountain wall with a flat stone according to the present invention.

먼저, 지반에 기립 배치되도록 복수 개의 제 1 장식석(11)과 복수 개의 제 1 지지석(21)을 각기 엇갈리게 배치한다.First, the plurality of first decorative stones 11 and the plurality of first supporting stones 21 are alternately arranged so as to stand on the ground.

그런 다음, 제 1 장식석들(11)과 제 1 지지석들(21) 후방에 복수 개의 하부 뒷돌(51)을 배치한 후 각기 앵커부재(61)(63)로 연결시킨다. 여기서, 앵커부재(61) (63)는 전술된 바와 같이 제 1 장식석들(11)과 제 1 지지석들(21)을 연결시키거나 또는 제 1 장식석들(11)과 콘크리트 기초(70)의 배근부(71)를 연결 고정한다.Then, a plurality of lower back stones 51 are disposed behind the first decorative stones 11 and the first supporting stones 21 and then connected to the anchor members 61 and 63, respectively. Here, the anchor members 61 and 63 connect the first decorative stones 11 and the first supporting stones 21 as described above, or the first decorative stones 11 and the concrete foundation 70. Fix the back muscle part 71).

그리고, 제 1 지지석들(21)의 상부에 각기 복수 개의 평석(31)을 배치한다. 이때, 토사 뒷채움을 시행할 수도 있다.Then, a plurality of flat stones 31 are respectively disposed on the upper portions of the first supporting stones 21. At this time, the earth and sand may be filled.

계속해서, 평석들(31)의 각 상부면에 제 1 장식석(11)과 각기 엇갈리게 복수 개의 제 2 장식석(13)을 배치하고, 복수 개의 제 2 장식석(13)과 복수 개의 제 2 지지석(23)을 각기 엇갈리게 배치한다.Subsequently, a plurality of second decorative stones 13 and a plurality of second decorative stones 13 and a plurality of second are arranged alternately with the first decorative stone 11 on each upper surface of the flat stones 31. The support seats 23 are alternately arranged.

그리고, 제 2 장식석들(13)과 제 2 지지석들(23) 후방에 복수 개의 상부 뒷돌(53)을 배치한 후 각기 앵커부재(65)로 연결시킨다. 이때, 토사 뒷채움을 시행할 수도 있다.Then, the plurality of upper back stones 53 are disposed behind the second decorative stones 13 and the second support stones 23, and then connected to the anchor members 65, respectively. At this time, the earth and sand may be filled.

또한, 장식석(11)(13), 지지석(21)(23), 평석(31)의 전면이 노출되고 앵커부재(61)(63)(65)를 매몰시키도록 토사로 뒷채움한다.In addition, the front surfaces of the decorative stones 11, 13, the support stones 21, 23, and the flat stone 31 are exposed and backfilled with earth and sand to bury the anchor members 61, 63, 65.

이후, 최상층을 준비하는 경우에는, 하부에 배치된 제 2 장식석들(13)에 각기 엇갈리게 복수 개의 상부 장식석(15)을 기립되게 배치한 후 토사로 뒷매움을 한다. 여기서, 상부 장식석(15)은 토사 위에 배치된다.Subsequently, in the case of preparing the uppermost layer, the plurality of upper feldspars 15 are erected in a standing manner to the second feldspars 13 arranged at the bottom, and then backfilled with soil. Here, the upper decorative stone 15 is disposed on the soil.

마지막으로, 사이목을 배식하고 일정 시간이 경과하면 식재가 활착되어 아름답고 수려한 자연석으로 이루어진 산벽이 완성된다.Finally, after a certain time has elapsed after planting the samok, plantings are active and the mountain wall made of beautiful and beautiful natural stone is completed.

도 13은 본 발명의 제 3 실시예에 의한 평석을 구비한 뒷돌 고정식 산벽 구조물의 일부를 나타내는 사시도이고, 도 14는 도 13의 단면도이고, 도 15는 본 발명의 산벽 구조물의 최하층을 개략적으로 나타내는 평면도이고, 도 16은 본 발명의 산벽 구조물의 두 번째 층을 개략적으로 나타내는 평면도이고, 도 17은 본 발명의 산벽 구조물의 최상층을 개략적으로 나타내는 평면도이다FIG. 13 is a perspective view illustrating a part of a fixed stone wall structure having a backstone according to a third embodiment of the present invention, FIG. 14 is a cross-sectional view of FIG. 13, and FIG. 15 schematically illustrates a bottom layer of the mountain wall structure of the present invention. 16 is a plan view schematically illustrating a second layer of the mountain wall structure of the present invention, and FIG. 17 is a plan view schematically showing a top layer of the mountain wall structure of the present invention.

도 13 내지 도 17를 참조하면, 본 발명에 의한 산벽 구조물은 지반에 비스듬히 각기 이격되도록 기립 배치된 복수 개의 제 1 장식석(11), 제 1 장식석들(11) 사이에 각기 엇갈리게 개재된 복수 개의 지지석(21)과, 지지석들(21)의 상부에 각기 제공된 복수 개의 평석(31)과, 평석들(31)의 각 상부면에 제 1 장식석(11)과 각기 엇갈리게 기립 배치된 복수 개의 제 2 장식석(13)과, 제 2 장식석들(13) 사이에 각기 엇갈리게 개재된 복수 개의 제 2 지지석(23)과, 장식석(11)(13)과 지지석(21)(23) 후방에 배치된 복수 개의 뒷돌(51)(53)과, 장식석(11)(13) 및 지지석(21)(23)을 뒷돌(51)(53)에 각기 연결시키는 복수 개의 앵커부재(61)(63)(65)를 포함한다.Referring to FIGS. 13 to 17, the mountain wall structure according to the present invention includes a plurality of first intersecting stones interposed between a plurality of first decorative stones 11 and first decorative stones 11 that are erected to be spaced apart from each other at an angle to the ground. Two support stones 21, a plurality of flat stones 31 respectively provided on the tops of the support stones 21, and standing upside-down alternately with the first decorative stones 11 on each upper surface of the flat stones 31 The plurality of second decorative stones 13 and the plurality of second supporting stones 23 interposed between the second decorative stones 13, the decorative stones 11, 13 and the supporting stones 21, respectively. (23) A plurality of anchors for connecting the plurality of backing stones (51) and (53) arranged at the rear, and the decorative stones (11) (13) and the supporting stones (21) (23) to the backing stones (51) (53), respectively. Members 61, 63, 65;

제 1 장식석(11)은 지반에 일정한 각도로 비스듬히 이격되도록 복수 개가 배치되어 있다. 여기서, 제 1 장식석(11)의 하단부는 콘크리트 기초에 매몰되도록 하여 강력한 지지를 구현하고 있다. 그리고, 제 1 장식석(11)은 두께가 얇고 폭 길이보다는 높이 길이가 큰 석재를 사용하는 것이 보다 아름다운 조경을 구현할 수 있음은 물론, 본 발명의 산벽 구조의 특징인 수직 조경방법에 대응할 수 있다.A plurality of first decorative stones 11 are disposed so as to be spaced at an angle to the ground at an angle. Here, the lower end of the first decorative stone 11 is embedded in the concrete foundation to implement a strong support. In addition, the first decorative stone 11 may use a stone having a thin thickness and a large height length rather than a width length to implement more beautiful landscaping, and may correspond to a vertical landscaping method, which is a feature of the mountain wall structure of the present invention. .

지지석(21)은 제 1 장식석들(11) 사이에 엇갈리게 각기 배치되어 있어 전체적으로 제 1 장식석(11)과 지지석(21)은 지그재그로 배치되어 있다. 여기서, 지지석(21)은 양단부가 제 1 장식석들(11)의 측면에 밀착되어 지지함으로써 일종의 셀(shell) 구조를 형성함으로써 배수가 양호하고, 침하 전도에 강한 특징이 있다.The supporting stones 21 are alternately arranged between the first decorative stones 11 so that the first decorative stones 11 and the supporting stones 21 are arranged in a zigzag. Here, the support stone 21 has a good drainage by forming a kind of shell structure by supporting both ends in close contact with the side surfaces of the first decorative stones (11), and has a strong characteristic for settlement conduction.

그리고, 지지석(21)의 하단부는 콘크리트 기초에 매몰되어 있다.The lower end of the supporting stone 21 is embedded in the concrete foundation.

평석(31)은 지지석들(21)의 상부에 각기 배치되어 있다. 여기서, 평석(31)은 제 1 장식석(11)이 기립되어 있는 것과는 달리 와립(臥立)되어 있으며, 상부면은 제 2 장식석(13)이 정립될 수 있도록 이에 대응된 형상을 갖는 것이 바람직하다.Pyeongseok 31 is disposed on top of the supporting stones 21, respectively. Here, the flat stone 31 is granulated unlike the first decorative stone 11 is standing, the upper surface has a shape corresponding to the second decorative stone 13 can be established. desirable.

그리고, 본 발명에 의한 평석(31)은 제 2 장식석(13)의 기초 역할을 수행함은 물론, 보다 자연스러운 심미감을 현출할 수 있는 특징이 있다.In addition, the flat stone 31 according to the present invention serves as a basic role of the second decorative stone 13, as well as a feature that can exhibit a more natural aesthetics.

제 2 장식석(13)은 평석들(31)의 각 상부면에 제 1 장식석(11)과 각기 엇갈리게 기립되도록 복수 개가 배치되어 있다. 여기서, 제 2 장식석(13)은 두께가 얇고 폭 길이보다는 높이 길이가 큰 석재를 사용하는 것이 보다 아름다운 조경을 구현할 수 있음은 물론, 본 발명의 산벽 구조의 특징인 수직 조경방법에 대응할 수 있다.A plurality of second decorative stones 13 are arranged on each upper surface of the flat stones 31 so as to stand up alternately with the first decorative stones 11. Here, the second decorative stone 13 can be used to implement a more beautiful landscaping, as well as a vertical landscaping method which is a feature of the mountain wall structure of the present invention using a stone having a thin thickness and a height length larger than the width length. .

제 2 지지석(23)은 제 2 장식석들(13) 사이에 엇갈리게 각기 배치되어 있어 전체적으로 제 2 장식석(13)과 제 2 지지석(23)은 지그재그로 배치되어 있다. 여기서, 제 2 지지석(23)은 양단부가 제 2 장식석들(13)의 측면에 밀착되어 지지함으로써 일종의 셀(shell) 구조를 형성함으로써 배수가 양호하고, 침하 전도에 강한 특징이 있다.The second supporting stones 23 are alternately arranged between the second decorative stones 13 so that the second decorative stones 13 and the second supporting stones 23 are arranged in a zigzag as a whole. Here, the second support stone 23 has a good drainage by forming a kind of shell structure by supporting both ends in close contact with the side surfaces of the second decorative stones (13), and has a strong characteristic against settlement conduction.

하부 뒷돌(51)은 제 1 장식석(11)과 지지석(21)의 후방에 배치되어 각기 대응된 앵커부재(63)에 의해 연결되어 있다. 그리고, 상부 뒷돌(53)은 제 2 장식석(13)과 제 2 지지석(23)의 후방에 배치되어 각기 대응된 앵커부재(65)에 의해 연결되어 있다.The lower back stone 51 is disposed at the rear of the first decorative stone 11 and the support stone 21 and is connected by corresponding anchor members 63, respectively. And, the upper back stone 53 is disposed behind the second decorative stone 13 and the second support stone 23 is connected by the corresponding anchor member 65, respectively.

또한, 상부 뒷돌(53)은 하부 뒷돌(51)의 수직 상방으로 일정 거리 이격되도록 위치되어 있다.In addition, the upper back stone 53 is positioned to be spaced apart a predetermined distance vertically upward of the lower back stone 51.

그리고, 토사는 장식석(11)(13), 지지석(21)(23), 평석(31)의 전면이 노출되도록 하고, 앵커부재(61)(63)를 매몰시키도록 뒷채움되어 있다. 여기서, 뒷채움되는 토사에는 일반적인 흙에 한정된 것으로 설명하고 있으나 이에 한정하지 않고 자갈이나 기타 잡석 등도 일부 포함될 수 있다.The earth and sand are backfilled to expose the entire surface of the decorative stones 11 and 13, the support stones 21 and 23, and the flat stone 31, and to bury the anchor members 61 and 63. Here, the backfilled soil is described as being limited to general soil, but is not limited thereto, and may include some gravel or other rubble.

상부 장식석(15)은 하부에 배치된 제 2 장식석(13)과 각기 엇갈리게 복수 개가 기립 배치되다. 여기서, 상부 장식석(15)은 두께가 얇고 폭 길이보다는 높이 길이가 큰 석재를 사용하는 것이 보다 아름다운 조경을 구현할 수 있음은 물론, 본 발명의 산벽 구조의 특징인 수직 조경방법에 대응할 수 있다. 또한, 상부 장식석(15)은 토사 위에 배치된다.The upper decorative stone 15 is a plurality of standing up staggered with the second decorative stone 13 disposed in the lower each. Here, the upper decorative stone 15 can be used to implement a more beautiful landscaping, as well as the vertical landscaping method of the mountain wall structure of the present invention using a stone having a thin thickness and a large height length rather than the width length. In addition, the upper decorative stone 15 is disposed on the soil.

상부 지지석(25)은 상부 장식석들(15) 사이에 엇갈리게 각기 배치되어 있어 전체적으로 상부 지지석(15)과 상부 지지석(25)은 지그재그로 배치되어 있다. 여기서, 상부 지지석(25)은 양단부가 상부 장식석들(15)의 측면에 밀착되어 지지함으로써 일종의 셀(shell) 구조를 형성함으로써 배수가 양호하고, 침하 전도에 강한 특징이 있다.The upper support seats 25 are alternately arranged between the upper decorative stones 15 so that the upper support seats 15 and the upper support seats 25 are arranged in a zigzag as a whole. Here, the upper support stone 25 is formed by a kind of shell (shell) structure by supporting both ends in close contact with the side of the upper decorative stones 15 has a good drainage, it is characterized by strong settlement conduction.

본 발명의 상부 장식석(15)과 상부 지지석(25)은 최상층에 해당되며 뒷돌에 의하여 연결되지 않는 구조를 갖는다. 또한, 토사는 상부 장식석(15), 상부 지지석(25)의 전면이 노출되도록 뒷채움되어 있다. 여기서, 뒷채움되는 토사에는 일반적인 흙에 한정된 것으로 설명하고 있으나 이에 한정하지 않고 자갈이나 기타 잡석 등도 일부 포함될 수 있다. The upper decorative stone 15 and the upper support stone 25 of the present invention corresponds to the uppermost layer and has a structure that is not connected by the back stone. In addition, the earth and sand are back-filled so that the front face of the upper decorative stone 15, the upper support stone 25 is exposed. Here, the backfilled soil is described as being limited to general soil, but is not limited thereto, and may include some gravel or other rubble.

도 18은 장식석과 뒷돌의 연결 구조를 개략적으로 나타내는 단면도이다. 여기서, 앵커부재의 도면부호는 도 2를 참조하기로 한다.18 is a cross-sectional view schematically showing a connection structure between a decorative stone and a back stone. Here, reference numerals of the anchor members will be referred to FIG. 2.

도 18을 참조하면, 본 발명에 의한 앵커부재(61)(63)는 제 1 장식석(11)의 배면과 하부 뒷돌(51)의 전면을 연결시키거나, 또는 제 1 장식석(11)의 배면과 콘크리트 기초(70)의 배근부(71)를 연결시키는 구성을 갖는다.Referring to FIG. 18, the anchor members 61 and 63 according to the present invention connect the rear surface of the first decorative stone 11 and the front surface of the lower back stone 51 or the first decorative stone 11 of the first decorative stone 11. It has the structure which connects the back side 71 of the concrete foundation 70 with the back surface.

먼저, 제 1 장식석(11)의 배면과 하부 뒷돌(51)의 전면을 연결시키는 앵커부재(63)는 제 1 장식석(11)의 배면에 삽설된 제 1 앵커(63a)과, 하부 뒷돌(51)의 전면에 삽설된 제 2 앵커(63b)와, 앵커들(63a)(63b)의 각 일단부와 각기 용접 취부된 한 쌍의 철근 부재(63c-1)(63c-2)와, 철근 부재(63c-1)(63c-2)의 각 타단부를 연결 시키는 커플링(63d)으로 이루어져 있다.First, the anchor member 63 connecting the rear surface of the first decorative stone 11 and the front surface of the lower rear stone 51 includes a first anchor 63a inserted into the rear surface of the first decorative stone 11 and the lower rear stone. A second anchor 63b inserted into the front surface of the 51, a pair of reinforcing members 63c-1 and 63c-2 welded and attached to each one end of the anchors 63a and 63b, respectively; It consists of a coupling 63d for connecting the other ends of the reinforcing member 63c-1 and 63c-2.

본 발명에 의한 실시예에서 커플링(63d)을 적용하는 이유는 연결 자유도가 낮아 철근 부재(63c-1)(63c-2) 만으로 바람직하는 연결이 곤란하고, 또한 강력한 결합력이 요구되는 경우가 실제 시공에 있어 빈번하기 때문이다. 또한, 커플링(63d)은 일정한 토크값을 정하여 획일화할 수 있어 작업자에 의한 용접 실수 등을 미연에 방지할 수 있는 특징이 있다.The reason why the coupling 63d is applied in the embodiment according to the present invention is that the connection freedom is low, and the preferable connection is difficult only with the reinforcing members 63c-1 and 63c-2, and a strong coupling force is actually required. This is because it is frequent in construction. In addition, the coupling 63d can be uniformized by setting a constant torque value, and has a feature of preventing welding mistakes and the like by the operator.

또한, 제 1 장식석(11)의 배면과 콘크리트 기초(70)의 배근부(71)를 연결시키는 앵커부재(61)는 철근 부재(61b-2)의 일단부가 콘크리트 기초(70)의 배근부(71)에 용접 취부되어 있는 것 외에는 위의 구조와 동일하기 때문에 이에 대한 상세한 설명은 생략하기로 한다.In addition, the anchor member 61 connecting the rear surface of the first decorative stone 11 and the reinforcement portion 71 of the concrete foundation 70 has one end of the reinforcing member 61b-2 being the reinforcement portion of the concrete foundation 70. Except for being welded to (71), it is the same as the above structure, so detailed description thereof will be omitted.

그리고, 철근 부재(61b-1)(61b-2)(63c-1)(63c-2)는 토사에 장기간 매몰되는 것으로 평균 부식속도가 0.02mm/year인 경우 100년의 내용 년수로 설계될 수 있도록 부식방지용 에폭시 계열의 합성수지로 피복되는 것이 매우 바람직하다.The reinforcing members 61b-1, 61b-2, 63c-1 and 63c-2 are buried in the soil for a long time and can be designed for a service life of 100 years when the average corrosion rate is 0.02 mm / year. It is highly desirable to be coated with a corrosion-resistant epoxy resin.

본 발명에 의한 평석을 구비한 뒷돌 고정식 산벽 시공방법을 설명하면 다음과 같다.Referring to the method of constructing a back stone fixed mountain wall with a flat stone according to the present invention.

먼저, 지반에 기립 배치되도록 복수 개의 제 1 장식석(11)과 복수 개의 지지석(21)을 각기 엇갈리게 배치한다.First, a plurality of first decorative stones 11 and a plurality of support stones 21 are alternately arranged so as to stand on the ground.

그런 다음, 제 1 장식석들(11)과 지지석들(21) 후방에 복수 개의 하부 뒷 돌(51)을 배치한 후 각기 앵커부재(61)(63)로 연결시킨다. 여기서, 앵커부재(61) (63)는 전술된 바와 같이 제 1 장식석들(11)과 지지석들(21)을 연결시키거나 또는 제 1 장식석들(11)과 콘크리트 기초(70)의 배근부(71)를 연결 고정한다.Then, a plurality of lower rear stones 51 are disposed behind the first decorative stones 11 and the supporting stones 21 and then connected to the anchor members 61 and 63, respectively. Here, the anchor members 61 and 63 connect the first decorative stones 11 and the supporting stones 21 as described above, or the first decorative stones 11 and the concrete foundation 70. Connect and fix the back muscles 71.

그리고, 지지석들(21)의 상부에 각기 복수 개의 평석(31)을 배치한다. 이때, 토사 뒷채움을 시행할 수도 있다.Then, a plurality of pyeongseok 31 is arranged on top of the supporting stones 21, respectively. At this time, the earth and sand may be filled.

계속해서, 평석들(31)의 각 상부면에 제 1 장식석(11)과 각기 엇갈리게 복수 개의 제 2 장식석(13)을 배치하고, 복수 개의 제 2 장식석(13)과 복수 개의 제 2 지지석(23)을 각기 엇갈리게 배치한다.Subsequently, a plurality of second decorative stones 13 and a plurality of second decorative stones 13 and a plurality of second are arranged alternately with the first decorative stone 11 on each upper surface of the flat stones 31. The support seats 23 are alternately arranged.

그리고, 제 2 장식석들(13)과 제 2 지지석들(23) 후방에 복수 개의 상부 뒷돌(53)을 배치한 후 각기 앵커부재(65)로 연결시킨다. 이때, 토사 뒷채움을 시행할 수도 있다.Then, the plurality of upper back stones 53 are disposed behind the second decorative stones 13 and the second support stones 23, and then connected to the anchor members 65, respectively. At this time, the earth and sand may be filled.

또한, 장식석(11)(13), 지지석(21)(23), 평석(31)의 전면이 노출되고 앵커부재(61)(63)(65)를 매몰시키도록 토사로 뒷채움한다.In addition, the front surfaces of the decorative stones 11, 13, the support stones 21, 23, and the flat stone 31 are exposed and backfilled with earth and sand to bury the anchor members 61, 63, 65.

이후, 최상층을 준비하는 경우에는, 하부에 배치된 제 2 장식석들(13)에 각기 엇갈리게 복수 개의 상부 장식석(15)을 기립되게 배치한 후 토사로 뒷매움을 한다. 여기서, 상부 장식석(15)은 토사 위에 배치된다.Subsequently, in the case of preparing the uppermost layer, the plurality of upper feldspars 15 are erected in a standing manner to the second feldspars 13 arranged at the bottom, and then backfilled with earth and sand. Here, the upper decorative stone 15 is disposed on the soil.

마지막으로, 사이목을 배식하고 일정 시간이 경과하면 식재가 활착되어 아름답고 수려한 자연석으로 이루어진 산벽이 완성된다.Finally, after a certain time has elapsed after planting the samok, plantings are active and the mountain wall made of beautiful and beautiful natural stone is completed.

이상에서 설명된 본 고안은 전술된 실시예(들)에 한정되어 설명되었지만 이에 한정되지 않고 본 고안이 속하는 기술 분야의 통상의 지식을 가진 자가 용이하게 실시할 수 있을 정도의 변형 실시는 본 고안의 기술적 사상에 속하는 것임은 자명하다.The present invention described above is limited to the above-described embodiment (s), but not limited to this embodiment of the present invention is a modification that can be easily implemented by those skilled in the art to which the present invention belongs. It is obvious that it belongs to the technical idea.

도 1은 본 발명의 제 1 실시예에 의한 평석을 구비한 뒷돌 고정식 산벽 구조물의 일부를 나타내는 사시도이다.1 is a perspective view showing a part of a back stone fixed mountain wall structure having a flat stone according to a first embodiment of the present invention.

도 2는 도 1의 단면도이다.2 is a cross-sectional view of FIG. 1.

도 3은 본 발명의 산벽 구조물의 최하층을 개략적으로 나타내는 평면도이다.3 is a plan view schematically showing the lowest layer of the mountain wall structure of the present invention.

도 4는 본 발명의 산벽 구조물의 두 번째 층을 개략적으로 나타내는 평면도이다.4 is a plan view schematically showing a second layer of the mountain structure of the present invention.

도 5는 본 발명의 산벽 구조물의 최상층을 개략적으로 나타내는 평면도이다.Figure 5 is a plan view schematically showing the top layer of the mountain wall structure of the present invention.

도 6은 장식석과 뒷돌의 연결 구조를 개략적으로 나타내는 단면도이다.6 is a cross-sectional view schematically showing a connection structure between the decorative stone and the back stone.

도 7은 본 발명의 제 2 실시예에 의한 평석을 구비한 뒷돌 고정식 산벽 구조물의 일부를 나타내는 사시도이다.Figure 7 is a perspective view showing a part of the back stone fixed mountain wall structure having a flat stone according to a second embodiment of the present invention.

도 8은 도 7의 단면도이다.8 is a cross-sectional view of FIG. 7.

도 9는 본 발명의 산벽 구조물의 최하층을 개략적으로 나타내는 평면도이다.9 is a plan view schematically showing the lowest layer of the mountain wall structure of the present invention.

도 10은 본 발명의 산벽 구조물의 두 번째 층을 개략적으로 나타내는 평면도이다.10 is a plan view schematically showing a second layer of the mountain structure of the present invention.

도 11은 본 발명의 산벽 구조물의 최상층을 개략적으로 나타내는 평면도이다.11 is a plan view schematically showing the top layer of the mountain wall structure of the present invention.

도 12는 장식석과 뒷돌의 연결 구조를 개략적으로 나타내는 단면도이다.12 is a cross-sectional view schematically showing the connection structure between the decorative stone and the back stone.

도 13은 본 발명의 제 3 실시예에 의한 평석을 구비한 뒷돌 고정식 산벽 구조물의 일부를 나타내는 사시도이다.FIG. 13 is a perspective view showing a part of a back stone fixed mountain wall structure having pavement according to a third embodiment of the present invention. FIG.

도 14는 도 13의 단면도이다.14 is a cross-sectional view of FIG. 13.

도 15는 본 발명의 산벽 구조물의 최하층을 개략적으로 나타내는 평면도이다.15 is a plan view schematically showing the lowest layer of the mountain wall structure of the present invention.

도 16은 본 발명의 산벽 구조물의 두 번째 층을 개략적으로 나타내는 평면도이다.16 is a plan view schematically illustrating a second layer of the mountain structure of the present invention.

도 17은 본 발명의 산벽 구조물의 최상층을 개략적으로 나타내는 평면도이다.17 is a plan view schematically showing the top layer of the mountain structure of the present invention.

도 18은 장식석과 뒷돌의 연결 구조를 개략적으로 나타내는 단면도이다.18 is a cross-sectional view schematically showing a connection structure between a decorative stone and a back stone.

<< 도면의 주요 부분에 대한 부호의 설명 >><< Explanation of symbols for main part of drawing >>

11, 13, 15 : 장식석 21, 23, 25 : 지지석11, 13, 15: decorative stone 21, 23, 25: support stone

31, 33 : 평석31, 33: Pyeongseok

61, 63, 65 : 앵커부재61, 63, 65: anchor member

70 : 콘크리트 기초70: concrete foundation

Claims (21)

삭제delete 삭제delete 삭제delete 자연석을 이용한 옹벽에 있어서,In the retaining wall using natural stone, 지반에 비스듬히 각기 이격되도록 기립 배치된 복수 개의 제 1 장식석과;A plurality of first decorative stones standing up so as to be spaced apart at an angle to the ground; 상기 제 1 장식석들 사이에 각기 엇갈리게 개재된 복수 개의 제 1 지지석과;A plurality of first supporting stones interposed between the first decorative stones, respectively; 상기 제 1 지지석들의 상부에 각기 제공된 복수 개의 평석과;A plurality of plystones respectively provided on top of the first supporting stones; 상기 평석들의 각 상부면에 상기 제 1 장식석과 각기 엇갈리게 기립 배치된 복수 개의 제 2 장식석과;A plurality of second decorative stones standing up alternately with the first decorative stones on each upper surface of the slate; 상기 제 2 장식석들 사이에 각기 엇갈리게 개재된 복수 개의 제 2 지지석과;A plurality of second supporting stones interposed between the second decorative stones, respectively; 상기 장식석과 상기 지지석 후방에 배치된 복수 개의 뒷돌과;A plurality of back stones disposed behind the decorative stone and the support stone; 상기 장식석 및 상기 지지석을 상기 뒷돌에 각기 연결시키는 복수 개의 앵커부재; 및 A plurality of anchor members respectively connecting the decorative stone and the support stone to the back stone; And 일측이 상기 장식석 배면에 삽설되고 타측이 철근콘크리트 기초의 배근부에 용접 취부되는 철근부재;를 포함하되,It includes; one side is inserted into the back of the decorative stone and the other side is a rebar member welded to the reinforcement portion of the reinforced concrete base; 상기 제 1 장식석의 하단부는 철근콘크리트 기초에 매몰되어 지지되고, 상기 제 1 지지석의 하단부는 철근콘크리트 기초에 매몰되어 지지되고,The lower end of the first decorative stone is buried and supported on the reinforced concrete base, The lower end of the first support stone is buried and supported on the reinforced concrete foundation, 상기 장식석, 상기 지지석, 상기 평석의 전면이 노출되고 상기 앵커부재를 매몰시키도록 토사가 뒷채움되는 것을 특징으로 하는 평석을 구비한 뒷돌 고정식 산벽 구조물.The decorative stone wall structure with a back stone, characterized in that the decorative stone, the support stone, the front surface of the flat stone is exposed and the soil is back-filled to bury the anchor member. 제 4 항에 있어서,The method of claim 4, wherein 상기 제 2 장식석들에 각기 엇갈리게 개재되도록 상기 토사에 배치된 복수 개의 상부 평석과,A plurality of upper plystones disposed in the earth and sand so as to be alternately intersected with the second decorative stones, 상기 상부 평석들의 각 상부면에 상기 제 2 장식석과 각기 엇갈리게 기립 배치된 복수 개의 상부 장식석과,A plurality of upper decorative stones standing upright and staggered with the second decorative stone on each upper surface of the upper flat stones, 상기 상부 장식석들 사이에 각기 엇갈리게 개재된 복수 개의 상부 지지석을 더 포함하는 것을 특징으로 하는 평석을 구비한 뒷돌 고정식 산벽 구조물.The back stone fixed mountain wall structure having a flat stone, characterized in that it further comprises a plurality of upper support stones interposed between the upper decorative stones. 제 4 항에 있어서,The method of claim 4, wherein 상기 앵커부재는,The anchor member, 상기 장식석 및 상기 지지석에 삽설된 제 1 앵커와,A first anchor inserted in the decorative stone and the support stone; 상기 뒷돌에 삽설된 제 2 앵커와,A second anchor inserted in the back stone; 상기 제 1 앵커와 상기 제 2 앵커의 각 일단부가 취부되어 있되 표면에 합성수지가 피복된 한 쌍의 철근 부재와,A pair of reinforcing member having one end of each of the first anchor and the second anchor mounted thereon, the synthetic resin being coated on a surface thereof; 상기 한 쌍의 철근 부재의 타단부를 연결시키는 커플링을 포함하는 것을 특징으로 하는 평석을 구비한 뒷돌 고정식 산벽 구조물.And a coupling for connecting the other end of the pair of reinforcing bar members. 삭제delete 청구항 4 내지 청구항 6 중 어느 하나의 항의 구조물을 이용하여 천연석 옹벽을 시공하되,To construct a natural stone retaining wall using the structure of any one of claims 4 to 6, 지반에 기립 배치되도록 복수 개의 제 1 장식석과 복수 개의 제 1 지지석을 각기 엇갈리게 배치하는 단계와;Staggering each of the plurality of first decorative stones and the plurality of first supporting stones so as to stand on the ground; 상기 제 1 장식석들과 상기 제 1 지지석들 후방에 복수 개의 뒷돌을 배치하여 각기 앵커부재로 연결시키는 단계와;Arranging a plurality of back stones behind the first decorative stones and the first supporting stones and connecting the anchor stones to the anchor members, respectively; 상기 제 1 지지석들의 상부에 각기 복수 개의 평석을 배치하는 단계와;Arranging a plurality of plystones on top of the first support stones, respectively; 상기 평석들의 각 상부면에 상기 제 1 장식석과 각기 엇갈리게 복수 개의 제 2 장식석을 배치하고, 복수 개의 상기 제 2 장식석과 복수 개의 제 2 지지석을 각기 엇갈리게 배치하는 단계와;Arranging a plurality of second decorative stones alternately with the first decorative stone on each upper surface of the slate, and arranging the plurality of second decorative stones and the plurality of second supporting stones respectively; 상기 제 2 장식석들과 상기 제 2 지지석들 후방에 복수 개의 뒷돌을 배치하여 각기 앵커부재로 연결시키는 단계와;Arranging a plurality of back stones behind the second decorative stones and the second supporting stones and connecting the anchor stones to the anchor members, respectively; 철근부재의 일측이 상기 장식석 배면에 삽설되고 타측이 콘크리트 기초의 배근부에 용접 취부되는 단계; 및One side of the rebar member is inserted into the rear surface of the decorative stone and the other side is welded to the reinforcement portion of the concrete foundation; And 상기 장식석, 상기 지지석, 상기 평석의 전면이 노출되고 상기 앵커부재를 매몰시키도록 토사로 뒷채움하는 단계;를 더 포함하는 것을 특징으로 하는 평석을 구비한 뒷돌 고정식 산벽 시공방법.And backfilling with earth and sand to expose the front surface of the decorative stone, the support stone, and the flat stone, and to bury the anchor member. 삭제delete 삭제delete 삭제delete 삭제delete 자연석을 이용한 옹벽에 있어서,In the retaining wall using natural stone, 지반에 비스듬히 각기 이격되도록 기립 배치된 복수 개의 제 1 장식석과;A plurality of first decorative stones standing up so as to be spaced apart at an angle to the ground; 상기 제 1 장식석들 사이에 각기 엇갈리게 개재된 복수 개의 제 1 지지석과;A plurality of first supporting stones interposed between the first decorative stones, respectively; 상기 제 1 지지석들의 상부에 각기 제공된 복수 개의 평석과;A plurality of plystones respectively provided on top of the first supporting stones; 상기 평석들의 각 상부면에 상기 제 1 장식석과 각기 엇갈리게 기립 배치된 복수 개의 제 2 장식석과;A plurality of second decorative stones standing up alternately with the first decorative stones on each upper surface of the slate; 상기 제 2 장식석들 사이에 각기 엇갈리게 개재된 복수 개의 제 2 지지석과;A plurality of second supporting stones interposed between the second decorative stones, respectively; 상기 장식석과 상기 지지석 후방에 배치된 복수 개의 뒷돌과;A plurality of back stones disposed behind the decorative stone and the support stone; 상기 장식석 및 상기 지지석을 상기 뒷돌에 각기 연결시키는 복수 개의 앵커부재; A plurality of anchor members respectively connecting the decorative stone and the support stone to the back stone; 하부에 배치된 상기 제 2 장식석과 각기 엇갈리게 기립 배치된 복수 개의 상부 장식석과;A plurality of upper sprigs standing upright and staggered with the second sprig arranged at the bottom; 상기 상부 장식석들 사이에 각기 엇갈리게 개재된 복수 개의 상부 지지석을 포함하는 것을 특징으로 하는 평석; Pyeongseok characterized in that it comprises a plurality of upper support stones interposed between the upper decorative stones respectively; 일측이 상기 장식석 배면에 삽설되고 타측이 철근콘크리트 기초의 배근부에 용접 취부되는 철근부재;를 포함하되,It includes; one side is inserted into the back of the decorative stone and the other side is a rebar member welded to the reinforcement portion of the reinforced concrete base; 상기 제 1 장식석의 하단부는 철근콘크리트 기초에 매몰되어 지지되고, 상기 제 1 지지석의 하단부는 철근콘크리트 기초에 매몰되어 지지되고,The lower end of the first decorative stone is buried and supported on the reinforced concrete base, The lower end of the first support stone is buried and supported on the reinforced concrete foundation, 상기 장식석, 상기 지지석, 상기 평석의 전면이 노출되고 상기 앵커부재를 매몰시키도록 토사가 뒷채움되는 것을 특징으로 하는 평석을 구비한 뒷돌 고정식 산벽 구조물.The decorative stone wall structure with a back stone, characterized in that the decorative stone, the support stone, the front surface of the flat stone is exposed and the soil is back-filled to bury the anchor member. 제 13 항에 있어서,The method of claim 13, 상기 앵커부재는,The anchor member, 상기 장식석 및 상기 지지석에 삽설된 제 1 앵커와,A first anchor inserted in the decorative stone and the support stone; 상기 뒷돌에 삽설된 제 2 앵커와,A second anchor inserted in the back stone; 상기 제 1 앵커와 상기 제 2 앵커의 각 일단부가 취부되어 있되 표면에 합성수지가 피복된 한 쌍의 철근 부재와,A pair of reinforcing member having one end of each of the first anchor and the second anchor mounted thereon, the synthetic resin being coated on a surface thereof; 상기 한 쌍의 철근 부재의 타단부를 연결시키는 커플링을 포함하는 것을 특징으로 하는 평석을 구비한 뒷돌 고정식 산벽 구조물.And a coupling for connecting the other end of the pair of reinforcing bar members. 청구항 13 또는 청구항 14의 구조물을 이용하여 천연석 옹벽을 시공하되,Construct a natural stone retaining wall using the structure of claim 13, 지반에 기립 배치되도록 복수 개의 제 1 장식석과 복수 개의 제 1 지지석을 각기 엇갈리게 배치하는 단계와;Staggering each of the plurality of first decorative stones and the plurality of first supporting stones so as to stand on the ground; 상기 제 1 장식석들과 상기 제 1 지지석들 후방에 복수 개의 뒷돌을 배치하여 각기 앵커부재로 연결시키는 단계와;Arranging a plurality of back stones behind the first decorative stones and the first supporting stones and connecting the anchor stones to the anchor members, respectively; 상기 제 1 지지석들의 상부에 각기 복수 개의 평석을 배치하는 단계와;Arranging a plurality of plystones on top of the first support stones, respectively; 상기 평석들의 각 상부면에 상기 제 1 장식석과 각기 엇갈리게 복수 개의 제 2 장식석을 배치하고, 복수 개의 상기 제 2 장식석과 복수 개의 제 2 지지석을 각기 엇갈리게 배치하는 단계와;Arranging a plurality of second decorative stones alternately with the first decorative stone on each upper surface of the slate, and arranging the plurality of second decorative stones and the plurality of second supporting stones respectively; 상기 제 2 장식석들과 상기 제 2 지지석들 후방에 복수 개의 뒷돌을 배치하여 각기 앵커부재로 연결시키는 단계와;Arranging a plurality of back stones behind the second decorative stones and the second supporting stones and connecting the anchor stones to the anchor members, respectively; 하부에 배치된 상기 제 2 장식석들에 각기 엇갈리게 개재되도록 복수 개의 상부 장식석을 기립되게 배치하고, 상기 상부 장식석들에 각기 엇갈리게 개재되도록 복수 개의 상부 지지석을 배치하는 단계와;Arranging a plurality of upper garnishes so as to intersect the second garnishes disposed below and alternately interposing the upper garnishes; 철근부재의 일측이 상기 장식석 배면에 삽설되고 타측이 콘크리트 기초의 배근부에 용접 취부되는 단계; 및One side of the rebar member is inserted into the rear surface of the decorative stone and the other side is welded to the reinforcement portion of the concrete foundation; And 상기 장식석, 상기 지지석, 상기 평석의 전면이 노출되고 상기 앵커부재를 매몰시키도록 토사로 뒷채움하는 단계를 포함하는 것을 특징으로 하는 평석을 구비한 뒷돌 고정식 산벽 시공방법.And backfilling the soil with the sediment to expose the front surface of the decorative stone, the support stone, and the flat stone and to bury the anchor member. 삭제delete 삭제delete 삭제delete 자연석을 이용한 옹벽에 있어서,In the retaining wall using natural stone, 지반에 비스듬히 각기 이격되도록 기립 배치된 복수 개의 제 1 장식석과;A plurality of first decorative stones standing up so as to be spaced apart at an angle to the ground; 상기 제 1 장식석들 사이에 각기 엇갈리게 개재된 복수 개의 지지석과;A plurality of support stones interposed alternately between the first decorative stones; 상기 지지석들의 상부에 각기 제공된 복수 개의 평석과;A plurality of plystones respectively provided on top of the support stones; 상기 평석들의 각 상부면에 상기 제 1 장식석과 각기 엇갈리게 기립 배치된 복수 개의 제 2 장식석과;A plurality of second decorative stones standing up alternately with the first decorative stones on each upper surface of the slate; 상기 장식석과 상기 지지석 후방에 배치된 복수 개의 뒷돌과;A plurality of back stones disposed behind the decorative stone and the support stone; 상기 장식석 및 상기 지지석을 상기 뒷돌에 각기 연결시키는 복수 개의 앵커부재와;A plurality of anchor members respectively connecting the decorative stone and the support stone to the back stone; 일측이 상기 장식석 배면에 삽설되고 타측이 철근콘크리트 기초의 배근부에 용접 취부되는 철근부재;를 포함하되,It includes; one side is inserted into the back of the decorative stone and the other side is a rebar member welded to the reinforcement portion of the reinforced concrete base; 상기 제 1 장식석의 하단부는 철근콘크리트 기초에 매몰되어 지지되고, 상기 제 1 지지석의 하단부는 철근콘크리트 기초에 매몰되어 지지되고,The lower end of the first decorative stone is buried and supported on the reinforced concrete base, The lower end of the first support stone is buried and supported on the reinforced concrete foundation, 상기 장식석, 상기 지지석, 상기 평석의 전면이 노출되고 상기 앵커부재를 매몰시키도록 토사가 뒷채움되는 것을 특징으로 하는 평석을 구비한 뒷돌 고정식 산벽 구조물.The decorative stone wall structure with a back stone, characterized in that the decorative stone, the support stone, the front surface of the flat stone is exposed and the soil is back-filled to bury the anchor member. 제 19 항에 있어서,The method of claim 19, 상기 앵커부재는,The anchor member, 상기 장식석 및 상기 지지석에 삽설된 제 1 앵커와,A first anchor inserted in the decorative stone and the support stone; 상기 뒷돌에 삽설된 제 2 앵커와,A second anchor inserted in the back stone; 상기 제 1 앵커와 상기 제 2 앵커의 각 일단부가 취부되어 있되 표면에 합성수지가 피복된 한 쌍의 철근 부재와,A pair of reinforcing member having one end of each of the first anchor and the second anchor mounted thereon, the synthetic resin being coated on a surface thereof; 상기 한 쌍의 철근 부재의 타단부를 연결시키는 커플링을 포함하는 것을 특징으로 하는 평석을 구비한 뒷돌 고정식 산벽 구조물.And a coupling for connecting the other end of the pair of reinforcing bar members. 청구항 19 또는 청구항 20의 구조물을 이용하여 천연석 옹벽을 시공하되,Construct a natural stone retaining wall using the structure of claim 19 or 20, 지반에 기립 배치되도록 복수 개의 제 1 장식석과 복수 개의 지지석을 각기 엇갈리게 배치하는 단계와;Staggering the plurality of first decorative stones and the plurality of supporting stones, respectively, so as to stand on the ground; 상기 제 1 장식석들과 상기 지지석들 후방에 복수 개의 뒷돌을 배치하여 각기 앵커부재로 연결시키는 단계와;Arranging a plurality of back stones behind the first decorative stones and the supporting stones, and connecting the plurality of back stones to the anchor members, respectively; 하부에 배치된 상기 제 1 장식석과 각기 엇갈리게 복수 개의 제 2 장식석을 배치하는 단계와;Arranging a plurality of second swags alternately with the first swags disposed below; 상기 제 2 장식석들 후방에 복수 개의 뒷돌을 배치하여 각기 앵커부재로 연결시키는 단계와;Arranging a plurality of back stones behind the second decorative stones and connecting the anchor stones to the anchor members; 하부에 배치된 상기 제 2 장식석들에 각기 엇갈리게 개재되도록 복수 개의 상부 장식석을 기립되게 배치하는 단계와;Standing up the plurality of upper feldspars so as to interpose with the second feldspars disposed below each other; 철근부재의 일측이 상기 장식석 배면에 삽설되고 타측이 콘크리트 기초의 배근부에 용접 취부되는 단계; 및One side of the rebar member is inserted into the rear surface of the decorative stone and the other side is welded to the reinforcement portion of the concrete foundation; And 상기 장식석, 상기 지지석, 상기 평석의 전면이 노출되고 상기 앵커부재를 매몰시키도록 토사로 뒷채움하는 단계를 포함하는 것을 특징으로 하는 평석을 구비한 뒷돌 고정식 산벽 시공방법.And backfilling the soil with the sediment to expose the front surface of the decorative stone, the support stone, and the flat stone and to bury the anchor member.
KR1020090117548A 2009-12-01 2009-12-01 Retaining nature-rock wall with plane rocks and building method thereof Active KR100973914B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020090117548A KR100973914B1 (en) 2009-12-01 2009-12-01 Retaining nature-rock wall with plane rocks and building method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020090117548A KR100973914B1 (en) 2009-12-01 2009-12-01 Retaining nature-rock wall with plane rocks and building method thereof

Publications (1)

Publication Number Publication Date
KR100973914B1 true KR100973914B1 (en) 2010-08-03

Family

ID=42759275

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020090117548A Active KR100973914B1 (en) 2009-12-01 2009-12-01 Retaining nature-rock wall with plane rocks and building method thereof

Country Status (1)

Country Link
KR (1) KR100973914B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101370623B1 (en) 2013-12-16 2014-03-07 안슬바마로 Retaining wall having natural rock for replacing a concrete retaining wall being damageable by using calcium chloride and construction method thereof

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08184065A (en) * 1994-12-28 1996-07-16 Fukuhou:Kk Method for constructing masonry retaining wall
KR100657773B1 (en) * 2006-02-21 2006-12-14 주식회사 에코밸리 Environmental friendly retaining wall structure and construction method

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08184065A (en) * 1994-12-28 1996-07-16 Fukuhou:Kk Method for constructing masonry retaining wall
KR100657773B1 (en) * 2006-02-21 2006-12-14 주식회사 에코밸리 Environmental friendly retaining wall structure and construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101370623B1 (en) 2013-12-16 2014-03-07 안슬바마로 Retaining wall having natural rock for replacing a concrete retaining wall being damageable by using calcium chloride and construction method thereof

Similar Documents

Publication Publication Date Title
JP2017155574A (en) Construction method of retaining wall
KR101031583B1 (en) Natural Stone Retaining Wall Structure Using Blasting Stone and Concrete Resistance Block and Its Construction Method
KR102220613B1 (en) Freestanding retaining wall construction method
KR102263958B1 (en) the Method of Construction of Prefabricated Block for Retaining Wall Bulwark
KR101401730B1 (en) Reinforcing method of bearing power for soft ground and reinforcing apparatus used in the same method
CN210104786U (en) Road shoulder retaining component capable of greening
KR100296018B1 (en) Revetment structure using natural stones and method for constructing revetment structure using the same
KR101334749B1 (en) Vegetation block in tiers for retaining wall and method for construction of retaining wall using the same
CN203174626U (en) Geogrid reinforced wall
KR100973914B1 (en) Retaining nature-rock wall with plane rocks and building method thereof
CN110965577B (en) Construction method of chain lock type ecological block retaining wall
KR102116085B1 (en) A Eco-friendly retain wall structure
CN219118228U (en) Assembly type soil retaining greening water permeable member
KR100400170B1 (en) Revetment structure using natural stones
CN211773858U (en) Landscape gabion retaining wall
KR101716895B1 (en) Precasted retaining-wall segment structure and precasted retaining-wall structure
KR100742335B1 (en) Landscaping using natural stone cut and its construction method
KR200413303Y1 (en) Mountain wall structure using steel beam
KR102285192B1 (en) A Eco-friendly retain wall structure
CN214005732U (en) Reinforced retaining wall for local backfilling of foundation pit
CN211498943U (en) Building block for chain lock type ecological retaining wall
KR102371637B1 (en) Retaining wall block construction method with improved cohesion
KR100601126B1 (en) Anchor Structure of Shelf Greening Retaining Wall
KR200345934Y1 (en) Anchoring structure of afforestation Retaining-Wall
KR102371639B1 (en) Retaining wall block with improved cohesion

Legal Events

Date Code Title Description
A201 Request for examination
PA0109 Patent application

Patent event code: PA01091R01D

Comment text: Patent Application

Patent event date: 20091201

PA0201 Request for examination
A302 Request for accelerated examination
PA0302 Request for accelerated examination

Patent event date: 20091203

Patent event code: PA03022R01D

Comment text: Request for Accelerated Examination

Patent event date: 20091201

Patent event code: PA03021R01I

Comment text: Patent Application

E902 Notification of reason for refusal
PE0902 Notice of grounds for rejection

Comment text: Notification of reason for refusal

Patent event date: 20100217

Patent event code: PE09021S01D

E701 Decision to grant or registration of patent right
PE0701 Decision of registration

Patent event code: PE07011S01D

Comment text: Decision to Grant Registration

Patent event date: 20100709

GRNT Written decision to grant
PR0701 Registration of establishment

Comment text: Registration of Establishment

Patent event date: 20100728

Patent event code: PR07011E01D

PR1002 Payment of registration fee

Payment date: 20100728

End annual number: 3

Start annual number: 1

PG1601 Publication of registration
FPAY Annual fee payment

Payment date: 20130729

Year of fee payment: 4

PR1001 Payment of annual fee

Payment date: 20130729

Start annual number: 4

End annual number: 4

FPAY Annual fee payment

Payment date: 20140725

Year of fee payment: 5

PR1001 Payment of annual fee

Payment date: 20140725

Start annual number: 5

End annual number: 5

FPAY Annual fee payment

Payment date: 20150601

Year of fee payment: 6

PR1001 Payment of annual fee

Payment date: 20150601

Start annual number: 6

End annual number: 6

FPAY Annual fee payment

Payment date: 20160728

Year of fee payment: 7

PR1001 Payment of annual fee

Payment date: 20160728

Start annual number: 7

End annual number: 7

FPAY Annual fee payment

Payment date: 20170613

Year of fee payment: 8

PR1001 Payment of annual fee

Payment date: 20170613

Start annual number: 8

End annual number: 8

FPAY Annual fee payment

Payment date: 20180816

Year of fee payment: 9

PR1001 Payment of annual fee

Payment date: 20180816

Start annual number: 9

End annual number: 9

FPAY Annual fee payment

Payment date: 20190507

Year of fee payment: 10

PR1001 Payment of annual fee

Payment date: 20190507

Start annual number: 10

End annual number: 10

PR1001 Payment of annual fee

Payment date: 20200527

Start annual number: 11

End annual number: 11

PR1001 Payment of annual fee

Payment date: 20210601

Start annual number: 12

End annual number: 12

PR1001 Payment of annual fee

Payment date: 20220630

Start annual number: 13

End annual number: 13

PR1001 Payment of annual fee

Payment date: 20230601

Start annual number: 14

End annual number: 14