KR100734019B1 - Bridge construction method using a bridge girder supporting bracket which four or two-direction supporter is installed - Google Patents

Bridge construction method using a bridge girder supporting bracket which four or two-direction supporter is installed Download PDF

Info

Publication number
KR100734019B1
KR100734019B1 KR1020060099896A KR20060099896A KR100734019B1 KR 100734019 B1 KR100734019 B1 KR 100734019B1 KR 1020060099896 A KR1020060099896 A KR 1020060099896A KR 20060099896 A KR20060099896 A KR 20060099896A KR 100734019 B1 KR100734019 B1 KR 100734019B1
Authority
KR
South Korea
Prior art keywords
bridge
installing
girder
seat
support
Prior art date
Application number
KR1020060099896A
Other languages
Korean (ko)
Inventor
노윤근
정상욱
Original Assignee
우경건설 주식회사
정상욱
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 우경건설 주식회사, 정상욱 filed Critical 우경건설 주식회사
Priority to KR1020060099896A priority Critical patent/KR100734019B1/en
Application granted granted Critical
Publication of KR100734019B1 publication Critical patent/KR100734019B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/04Bearings; Hinges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
    • E01D19/125Grating or flooring for bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/30Metal

Abstract

A bridge construction method using a bridge girder supporting bracket with a support installed in four or two directions is provided to simplify a working process and to perform installation and maintenance works conveniently by installing a bridge girder supporting bracket having a four or two direction support on bridge bearings, installing girders on the support and installing a bridge slab. The bridge construction method using a bridge girder supporting bracket with a support installed in four or two directions comprises the steps of installing abutments on two sides of a bridge(10), installing piers on the inside at regular intervals and installing bridge bearings(15) on the upper parts of the abutment and the pier, and the upper parts of the pier and the pier, installing a bridge girder supporting bracket(30) provided with a bridge bearing mount portion(33) on the bridge bearing, placing a support installed in the four or two directions of the bridge girder supporting bracket upward, connecting girders(13) on a pair of supports integrally and installing girders on the bridge girder supporting bracket, arranging reinforcing bars on the girders to install a bridge slab(12), placing concrete and installing a bridge upper structure, and then installing curbs(11) on two sides. The bridge girder supporting bracket is manufactured with square pyramid shaped steel or V-shaped steel and provided with the bridge bearing mounting portion formed to the center in the appointed size and the support formed in four directions of the bridge bearing mounting portion.

Description

4방향 또는 2방향으로 지지대가 설치된 교량거더지지브라켓을 이용한 교량시공방법.{Bridge construction method using a bridge girder supporting bracket which four or two-direction supporter is installed}Bridge construction method using a bridge girder supporting bracket which four or two-direction supporter is installed}

도 1은 종래의 교량상부지지대의 하부에 교좌장치를 설치하고 그 하부에 교각 및 교대를 설치하여 교량을 시공한 것을 보여주는 도면.1 is a view showing the construction of the bridge by installing a bridge device in the lower portion of the conventional bridge upper support and the bridge and the alternator installed in the lower portion thereof.

도 2는 본 발명의 교량거더지지브라켓을 이용하여 교량을 설치한 것을 보여주는 도면.2 is a view showing the bridge is installed using the bridge girder support bracket of the present invention.

도 3은 본 발명의 교량거더지지브라켓이 거더 하부와 교각 및 교대 사이에 설치된 것을 위에서 보여주는 도면.3 is a view showing from above that the bridge girder support bracket of the present invention is installed between the girder bottom and the pier and shift.

도 4는 본 발명의 교량거더지지브라켓의 거더 하부와 교각 및 교대사이에 설치된 것의 종단면을 보여주는 도면. Figure 4 is a view showing a longitudinal section of what is installed between the girder lower portion and the bridge and shift of the bridge girder support bracket of the present invention.

도 5는 본 발명의 네방향지지대의 교량거더지지브라켓을 전체적으로 보여주는 도면.5 is a view showing the bridge girder support bracket of the four-way support of the present invention as a whole.

도 6은 본 발명의 다른 실시예인 2방향지지대의 교량거더지지브라켓을 전체적으로 보여주는 도면.Figure 6 is a view showing the bridge girder support bracket as a whole of another embodiment of the present invention.

<도면의 주요 부분에 대한 부호의 설명><Explanation of symbols for the main parts of the drawings>

10 ;교량 11 연석           10 bridge 11 curbstone

12 ; 교량상판슬래브 13 ; 거더           12; Bridge slab 13; Girder

14 ; 가로보 15 ; 교좌장치           14; Crossbeam 15; Device

16 ; 교각 및 교대           16; Pier and shift

20 ; 교량상부지지대 21 ; 브레싱           20; Bridge upper support 21; Breathing

22 ; 수직재하부연결재 23 ; 수직재           22; Vertical load connector 23; vertical

30 ; 교량거더지지브라켓 31 ; 지지대           30; Bridge girder support bracket 31; support fixture

32 ; 4각통체 33 ; 교좌안착부           32; Square cylinder 33; Seat seat

34 ; 통공부    34; Through-hole

본 발명은 교각 및 교대 상에 설치된 교좌장치 위에 네방향 또는 2방향지지대를 갖는 교량거더지지브라켓을 설치하고, 그 위에 거더를 설치하면서 교량상판 슬래브를 설치하여 교량을 시공하는 방법에 관한 것이다.The present invention relates to a method for constructing a bridge by installing a bridge girder support bracket having four or two direction supports on a bridge device installed on a bridge and a bridge, and installing a bridge deck slab while installing a girder thereon.

상기 교량거더지지브라켓은 중앙부에 일정한 크기의 교좌안착부가 형성되고 상기 교좌안착부의 네방향 또는 2방향에 일정한 길이로서 중앙은 통공부가 형성된 4각통체의 강재로 설치된 지지대가 형성되도록 하되, 교좌안착부가 있는 내측으로 오므라든 형태를 갖는 것이다.The bridge girder support bracket has a seat seat having a predetermined size in the center and a fixed length in the four or two directions of the seat seat, and the center is formed of a support made of steel of a four-cylindrical body formed with a through hole. It has a shape that has been retracted inwardly.

상기 교량거더지지브라켓을 이용하여 교량을 설치하는 시공방법은 교량을 설치하기 위하여 양측 부에는 교대를 설치하고 내측으로는 일정한 간격으로 교각을 설치하면서 교좌장치를 각각 설치하고, 상기 설치된 교대와 교각, 교각과 교각의 상부에 설치된 교좌장치 위에 교좌안착부가 설치되도록 하면서 교량거더지지브라켓을 설치하되 상기 교량거더지지브라켓의 네방향 또는 2방향으로 형성된 지지대가 상향으로 거치되도록 한 다음, 거더를 한쌍의 지지대 위에 각각 설치하는 작업을 하면서 교량거더지지브라켓 위에 거더를 설치하고, 거더 위에 교량상판슬래브를 설치하기 위한 철근을 배근한 다음, 콘크리트를 타설양생하여 교량상부구조물을 설치한 다음 양측에 연석을 설치하는 과정을 거쳐 교량을 시공하는 것이다. The construction method for installing bridges using the bridge girder support brackets is to install bridges on both sides and install bridges at regular intervals to install bridges, respectively, and install the bridge devices. Install the bridge girder support bracket while the bridge seat is installed on the bridge device installed on the bridge and the upper part of the bridge, and the support formed in four or two directions of the bridge girder support bracket is mounted upward. The girder is installed on the bridge girder support brackets while the work is being installed on top of each other, the reinforcing bars for installing the bridge slab on the girder are reinforced, and the concrete is laid to install the upper structure of the bridge, and then the curb is installed on both sides. It is to construct bridge through process.

본 발명의 목적은 강재로 제작된 4각통체의 지지대를 네방향 또는 2방향으로 설치한 교량거더지지브라켓을 교각 및 교대에 설치하고 바로 거더를 설치하도록 하므로서 작업공정을 간단하게 하면서, 설치가 간편하고, 추후에 교량유지보수를 위하여 교좌장치를 교체하는 경우에도 교량거더지지브라켓의 교좌안착부만 하부에서 들어 올린다음 바로 교좌장치를 교체하도록 하는 것으로서 교량설치과정을 간편하게 함과 동시에 유지보수작업도 간편하게 수행할 수 있도록 하는 교량거더지지브라켓을 이용한 교량시공방법을 제공함에 있다. The object of the present invention is to install the girder support bracket, which is installed in four directions or two directions of the support of the four-piece cylindrical body made of steel, and to install the girder immediately and to install the girder, while simplifying the installation process, easy installation In the case of replacing the bridge device for the bridge maintenance in the future, the bridge seating part of the bridge girder bracket should be lifted from the lower side, and the bridge device will be replaced immediately. It is to provide a bridge construction method using a bridge girder support bracket that can be easily performed.

종래에는 교각 및 교대(16) 위에 교좌장치(15)를 설치하고, 교좌장치 위에 일정한 간격을 두고 종횡으로 수직재(23)를 설치하면서 상기 수직재(23)를 브레싱(21)으로 상호 연결하도록 하되 중앙에서는 브레싱(21)이 상호 교차되도록 하고, 수직재(23)의 하부에서는 수직재하부연결재(22)로 수직재(23)를 좌우로 상호연결한 교량상부지지대(20)를 설치하고, 상기 설치된 수직재(23) 위에 거더(13)를 거치하면서 거더(13)와 거더(13)는 가로보(14)로 상호 연결하도록 한 다음, 그 위에 철근 을 설치하고 콘크리트를 타설하여 교량상판슬래브(12)를 설치한 다음, 양측에 연석(11)을 설치하여 교량(10)을 시공하는 것으로서, 거더(13)와 교좌장치(15) 사이에 거더(13)를 포함한 교량상판슬래브(12)등과 작용하중을 지지하면서 교각 및 교대(16)에 전달하기 위한 교량상부지지대(20)를 설치하기 위하여, 거더(13)의 하부에 수직재(23)를 다수개 설치하고, 수직재(23)를 브레싱(21)으로 상호 연결하면서 수직재(23)의 하부도 수직재하부연결재(22)로 상호 연결하는 매우 복잡한 조립과정을 거쳐야만 교량상부지지대(20)의 설치가 가능하게되므로 그 작업과정이 매우 번거로우며 또한, 작업에 소요되는 인력 및 기간도 상당기간 소요되어 결국 교량설치공사비의 증가요인이 되는 문제점이 제기되어 왔다.Conventionally, the bridge device 15 is installed on the bridge piers and shifts 16, and vertical members 23 are vertically and horizontally installed at regular intervals on the bridge device so that the vertical members 23 are interconnected by the bracing 21, but the center is In the bracing 21 to cross each other, and in the lower portion of the vertical member 23 is installed the upper bridge support 20 is connected to the vertical member 23 to the left and right vertical member connecting member 22, the installed vertical member 23 After mounting the girder 13 above), the girder 13 and the girder 13 are interconnected by cross beams 14, and then installing reinforcing bars and pouring concrete to install bridge deck slabs 12. , The bridge 10 is installed by installing the curb 11 on both sides, and between the girder 13 and the bridge device 15 while supporting the working load with the bridge slab 12 including the girder 13, and the pier. And the upper bridge support 20 for delivering to the shift 16. To install, a plurality of vertical members 23 are installed in the lower part of the girder 13, and the lower members of the vertical member 23 are also interconnected with the vertical lower connector 22 while interconnecting the vertical members 23 with the bracing 21. Since the installation of the upper bridge support 20 is possible only through a very complicated assembly process, the work process is very cumbersome, and the manpower and time required for the work are also required for a long time, resulting in an increase in the cost of the bridge installation work. This has been raised.

본 발명은 상기와 같은 문제점을 개선하기 위하여 제안된 것으로서, 사전에 제작된 교량거더지지브라켓을 교각 및 교대의 교좌장치 위에 설치하고, 그 위에 바로 거더를 거치하도록 하여 교량을 설치하는 교량의 상부구조물을 지지하면서 작용하중을 교좌장치로 적절히 전달하는 기능을 하는 교량거더지지브라켓을 번거롭지 않게 사전에 제작하되, 구조가 간단하면서 내부가 통공부가 형성된 강재의 4각통체로 지지대를 제작하여 구조적으로도 강한 지지기능을 발휘하도록 하는 교량거더지지브라켓을 이용한 교량시공방법인 것이다.The present invention has been proposed to improve the above problems, the bridge girder support bracket prepared in advance on the bridge and the bridge of the alternating device, the upper structure of the bridge to install the bridge to mount the girder directly thereon The bridge girder support bracket, which functions to properly transfer the working load to the bridge device, is produced without any hassle in advance. It is a bridge construction method using the bridge girder support bracket to exert the supporting function.

상기 교량거더지지브라켓(30)을 이용하여 교량(10)을 설치하는 시공방법은 교량(10)을 설치하기 위하여 양측부에는 교대를 설치하고 내측으로는 일정한 간격 으로 교각을 설치하면서 교좌장치(15)를 각각 설치하고, 상기 설치된 교대와 교각, 교각과 교각의 상부에 설치된 교좌장치(15) 위에 교좌안착부(33)가 설치되도록 하면서 교량거더지지브라켓(30)을 설치하되 상기 교량거더지지브라켓(30)의 네방향 또는 2방향으로 형성된 지지대(31)가 상향으로 거치되도록 한 다음, 거더(13)를 한쌍의 지지대(31) 위에 각각 일체연결설치하는 작업을 하면서 교량거더지지브라켓(30) 위에 거더(13)를 설치하고, 거더 위에 교량상판슬래브(12)를 설치하기 위한 철근을 배근한 다음, 콘크리트를 타설양생하여 교량상부구조물을 설치한 다음 양측에 연석(11)을 설치하여 교량(10)을 시공하는 것이다.The construction method for installing the bridge 10 by using the bridge girder support bracket 30 is installed on both sides to install the bridge 10, while installing the bridge at regular intervals inside the bridge device (15). ), Respectively, the bridge girder support bracket 30 is installed while the seat seating portion 33 is installed on the bridge device 15 installed in the upper portion of the bridge and the bridge, the bridge and the bridge, the bridge girder support bracket The support 31 formed in four or two directions of the 30 is mounted upwardly, and then the girder 13 is integrally installed and installed on the pair of supports 31, respectively. Install the girder 13 on the top, reinforce the reinforcing bar for installing the bridge slab 12 on the girder, and then cast concrete to install the bridge upper structure, and then install the curb 11 on both sides of the bridge ( 10) It is construction.

상기 교량거더지지브라켓(30)은 중앙에 일정한 크기의 교좌안착부(33)가 형성되고 상기 교좌안착부(33)의 네방향에 일정한 길이로서 중앙은 통공부(34)가 형성된 4각통체(32)의 지지대(31)가 형성되도록 하되 교좌안착부(33)가 있는 내측으로 오므라든 4각피라밋모서리형태를 갖는 강재로 제작한 것이거나,The bridge girder support bracket 30 is formed in the center of the seat seating portion 33 of a constant size and a constant length in the four directions of the seat seating portion 33 as the center of the quadrilateral body formed with a through hole 34 ( 32) is formed of a steel material having a four-sided pyramid corner shape, such that the support 31 is formed, but is retracted inward with the seat seat 33,

또는, 가운데가 일정한 크기의 교좌안착부(33)가 형성되고, 상기 교좌안착부(33)의 양측에 일정한 길이로서 중앙은 통공부(34)가 형성된 4각통체(32)의 지지대(31)가 형성되도록 하되 교좌안착부(33)가 있는 내측으로 오므라진 V자형태인 강재로 제작한 것이다.Alternatively, the support seat 31 of the quadrangular body 32 is formed in the center seating portion 33 having a constant size, a constant length on both sides of the seating portion 33, the center portion is formed with a through-hole 34 To be formed, but the seat seating portion 33 is made of steel that is V-shaped retracted inward.

종래에는 교좌장치 위에 거더를 지지하기 위하여 강재를 브레이싱으로 상호연결한 지지체를 제작하여 교각 위에 설치하므로서 교량설치시 지지체의 제작과 설치에 많은 시간과 인력이 소요되므로 설치가 매우 번거롭고, 또한 설치비용이 과다하게 소요되는 단점이 있는 것이다.Conventionally, in order to support a girder on a bridge device, a steel plate is interconnected by bracing and installed on a bridge, so that a lot of time and manpower is required to manufacture and install a support when installing a bridge. There is a drawback in overuse.

이와 같이 종전에 사용하던 브레이싱의 사용을 생략하면서, 구조적으로 강도가 우수하며 단위중량이 가벼운 4각통체를 이용하여 4방향 또는 2방향의 지지대가 형성되도록 교량거더지지브라켓을 제작하여 이를 교각의 교좌장치 위에 설치만 하고, 그 위에 거더와 지지대가 일체로 연결되도록 설치하면 교량설치가 간단히 완료되도록 하였다. In this way, the bridge girder bridge is made by forming a bridge girder support bracket to form a support in four directions or two directions by using a four-cylindrical cylinder with excellent structural strength and light weight while omitting the use of the conventional bracing. Only installation on the device, and the girder and the support on the unit to be connected integrally, the bridge installation was simply completed.

상기와 같이 기제작된 교량거더지지브라켓을 교각 위에 설치만 하면되며, 또한 내부가 빈 4각통체로 제작되어 총중량이 가벼워 설치가 용이하게 하므로서 교량설치기간이 단축되며 설치비용도 절감되도록 하는 것에 본 발명의 주안점이 있는 것이다. The bridge girder support bracket manufactured as described above only need to be installed on the pier, and also the inside is made of a hollow cylinder, so that the total weight is light, so that the installation is easy and the installation period of the bridge is shortened and the installation cost is also reduced. The main point is that.

이하, 본 발명의 구성 및 작용을 첨부된 도면에 의하여 상세히 설명하면 다음과 같다.Hereinafter, the configuration and operation of the present invention will be described in detail by the accompanying drawings.

도 2는 본 발명의 지지대가 설치된 교량거더지지브라켓을 이용하여 교량을 설치한 것을 보여주는 도면으로서, 교량(10)을 설치하기 위하여 양측부에는 교대를 설치하고 내측으로는 일정한 간격으로 교각을 설치하면서 교좌장치를 각각 설치하고, 상기 설치된 교대와 교각, 교각과 교각의 상부에 설치된 교좌장치(15) 위에 교좌안착부(33)가 설치되도록 하면서 교량거더지지브라켓(30)을 설치하되 상기 교량거더지지브라켓(30)의 네방향 또는 2방향으로 형성된 지지대(31)가 상향으로 거치되도록 한 다음, 거더(13)를 한쌍의 지지대(31) 위에 각각 일체연결설치하는 작업을 하면서 교량거더지지브라켓(30) 위에 거더(13)를 설치하고, 거더(13) 위에 교량상판슬래브(12)를 설치하기 위한 철근을 배근한 다음, 콘크리트를 타설양생하여 교 량상부구조물을 설치한 다음 양측에 연석을 설치하여 교량(10)을 시공한 것이다. 2 is a view showing the bridge is installed using the bridge girder support bracket is installed in the support of the present invention, in order to install the bridge 10, while installing the bridges on both sides and installing the piers at regular intervals inside Each bridge device is installed, and the bridge girder support brackets 30 are installed while the bridge seating portion 33 is installed on the bridge device 15 installed on the bridges and bridges, the bridges and bridges. The support 31 formed in four or two directions of the bracket 30 is mounted upward, and then the girder 13 is integrally installed and installed on the pair of supports 31, respectively. ) Install the girder 13 on the girder, reinforce the reinforcing bar for installing the bridge slab 12 on the girder 13, and then cast concrete to install the bridge upper structure. By installing a curb on one side it is constructed as a bridge (10).

상기 교량거더지지브라켓(30)은 중앙에 일정한 크기의 교좌안착부(33)가 형성되고 상기 교좌안착부(33)의 네방향에 일정한 길이로서 중앙은 통공부(34)가 형성된 4각통체(32)의 일정길이의 지지대(31)를 제작하되, 교좌안착부(33)가 있는 내측으로 오므라든 4각피라밋모서리형상을 갖는 강재로 제작한 것이거나,The bridge girder support bracket 30 is formed in the center of the seat seating portion 33 of a constant size and a constant length in the four directions of the seat seating portion 33 as the center of the quadrilateral body formed with a through hole 34 ( 32) to produce a support 31 of a predetermined length, but is made of a steel having a four-sided pyramid edge shape retracted inward with the seat seat 33,

또는, 가운데가 일정한 크기의 교좌안착부(33)가 형성되고, 상기 교좌안착부(33)의 양측에 일정한 길이로서 중앙은 통공부(34)가 형성된 4각통체(32)의 일정길이의 지지대(31)를 형성하되, 교좌안착부(33)가 있는 내측으로 오므라진 V자형태인 강재로 제작한 것이다.Or, the seat seat portion 33 of a certain size is formed in the center, the support seat of a certain length of the quadrangular body 32 formed with a through-hole 34 in the center as a constant length on both sides of the seat seat portion 33 31 is formed, but is made of a V-shaped steel material that is retracted inward to the seat seating portion (33).

상기 교량거더지지브라켓(30)은 교량의 상부구조물을 지지하면서 작용하중을 교좌장치(15)로 적절히 전달하는 기능을 하는 교량거더지지브라켓(30)을 사전에 제작하되, 구조가 간단하면서 내부가 통공부(34)가 형성된 4각통체(32)의 일정길이의 지지대(31)를 제작하여 구조적으로도 강한 지지기능을 발휘하도록 한 것이다. The bridge girder support bracket 30 supports the upper structure of the bridge while pre-fabricating the bridge girder support bracket 30, which functions to properly transfer the working load to the bridge device 15, but the structure is simple and internal. It is to produce a support 31 of a certain length of the quadrangular body 32, the through-hole 34 is formed to exhibit a structurally strong support function.

일반적으로 알려진바대로 구조적으로 강한 구조를 갖는 것은 4각으로서 내부가 빈, 통공부(34)를 이룬 강으로 제작된 상기의 4각통체(32)인 것으로서, 이러한 구조를 갖는 구조물을 본 발명의 교량상부구조물을 지지하는 교량거더지지브라켓(30)으로 활용하여 구조적으로 안정하면서 구조가 간단하여 제작원가를 저렴하게 하면서 공사비를 절감하는 장점도 활용하기 위함인 것이다.       As is generally known, a structurally strong structure is a quadrangular body 32, which is made of steel having a hollow part and a hollow part 34, and has a structure having such a structure. By using the bridge girder support bracket (30) to support the upper structure of the bridge is to take advantage of the advantages of reducing the construction cost while lowering the manufacturing cost due to the structurally stable and simple structure.

또한, 교량거더지지브라켓(30)을 간단한 구조로 사전에 제작하는 것은 교각 및 교대(16)에 상기 브라켓(30)을 설치하고 바로 거더(13)를 설치하도록 하므로서 작업공정을 간단하게 함과 동시에 설치도 간편하게 하면서, In addition, the bridge girder support bracket 30 is manufactured in advance in a simple structure by simplifying the work process by installing the bracket 30 on the pier and the shift 16 and immediately installing the girder 13. While making installation easier,

추후에 교량유지보수를 위하여 교좌장치(15)를 교체하는 경우에도 교량거더지지브라켓(30)의 교좌안착부(33) 하부에서 교좌장치(15)를 구속하고 있는 볼트와 너트를 해체한 다음 들어 올리고 바로 교좌장치(15)를 교체할 수 있도록 하여 유지보수작업도 간편하게 수행할 수 있도록 한 것이다.Even when the bridge device 15 is replaced for bridge maintenance in the future, the bolts and nuts that restrain the bridge device 15 from the bridge seating portion 33 of the bridge girder support bracket 30 are removed and then lifted. It is to be able to replace the lifting device 15 immediately to raise and to easily perform maintenance work.

상기의 기능을 발휘하기 위하여 교좌안착부(33), 즉 교좌장치(15)와 접하는 부분은 평평하게 하며, 바람직하게는 교좌장치(15)의 상부가 위치하는 부분은 오목하게 홈을 형성하여 설치시 홈내에 교좌장치(15)가 위치하도록 하여 간단히 교량거더지지브라켓(30)을 설치할 수 있도록 함과 동시에 외부의 진동에 의하여도 쉽게 교좌장치(15)로부터 교량거더지지브라켓(30)이 이탈되는 것도 방지할 수 있다. In order to exert the above functions, the seat seating portion 33, that is, the portion in contact with the seating device 15 is flat, and preferably, the portion in which the top of the seating device 15 is located is formed by forming a recess. The bridge girder support bracket 30 can be easily installed by allowing the bridge girder support bracket 30 to be located in the groove at the same time, and the bridge girder support bracket 30 can be easily detached from the bridge girder 15 by external vibration. It can also prevent.

상기 교량거더지지브라켓(30)의 지지대가 네방향으로 형성된 경우 도 3과 같이 지지대(31) 위에 거더(13)을 설치할 때 지지대가 거더(13)의 하부에서 교축방향 및 교축직각방향으로 각각 한쌍의 지지대가 거더를 지지하도록 하고, When the support of the bridge girder support bracket 30 is formed in four directions, when the girder 13 is installed on the support 31 as shown in FIG. 3, a pair of supports are arranged in the axial direction and the axial direction perpendicular to the lower side of the girder 13. To support the girders,

상기 교량거더지지브라켓(30)의 지지대가 2방향으로 형성된 경우 도 2 또는 도 4와 같이 지지대(31) 위에 거더(13)을 설치할 때 지지대가 거더(13)의 하부에서 교축방향으로 한쌍의 지지대가 거더를 지지하도록 하는 것이다. When the support of the bridge girder support bracket 30 is formed in two directions, when the girder 13 is installed on the support 31 as shown in FIG. 2 or 4, the support is a pair of supports in the axial direction from the lower side of the girder 13. To support the girders.

도 3과 4는 본 발명의 교량거더지지브라켓이 거더 하부와 교각 및 교대 사이에 설치된 것을 위에서와 종단면을 보여주는 도면으로서, 4방향 또는 2방향의 지지대(31)를 설치하고 그 위에 거더(13)를 설치할 때 한 방향으로 설치된 2개의 지지대(31) 위에 거더(13)를 일체연결설치하도록 하여 거더(13)와 지지대(31)가 일체가 되도록 부착하여 구조적으로 안정감을 갖도록 하기 위함인 것이다. 3 and 4 is a view showing the longitudinal cross-sectional view from above and that the bridge girder support bracket of the present invention is installed between the girder lower portion and the pier and the alternator, the support girders 13 are installed on the support 31 in four or two directions. When installing the girder 13 is integrally installed on the two support (31) installed in one direction so that the girder 13 and the support (31) to be integrally attached to have a structural stability.

도 5는 본 발명의 네방향지지대의 교량거더지지브라켓을 전체적으로 보여주는 도면으로서, 중앙에 일정한 크기의 교좌안착부(33)가 형성되고 상기 교좌안착부(33)의 네방향에 일정한 길이로서 중앙은 통공부(34)가 형성된 4각통체(32)의 지지대(31)가 형성되도록 하되 교좌안착부(33)가 있는 내측으로 오므라든 4각피라밋모서리형상을 갖는 강재로 제작한 것이다. 5 is a view showing the bridge girder support bracket of the four-way support of the present invention as a whole, the seat seat portion 33 of a certain size is formed in the center and the center seat is a constant length in four directions of the seat seat portion 33. The support 31 of the four-cylindrical body 32 formed with the through-hole 34 is formed, but is made of steel having a four-cornered pyramid edge shape that is retracted inward with the seat seating portion 33.

상기 교량거더지지브라켓(30)을 간단한 구조로 사전에 제작하는 것은 교각 및 교대(16)에 상기 브라켓(30)을 설치하고 바로 거더(13)를 설치하도록 하므로서 작업공정을 간단하게 함과 동시에 설치도 간편하게 하면서, Producing the bridge girder support bracket 30 in a simple structure in advance allows the bracket 30 to be installed on the pier and the shift 16 and immediately installs the girder 13, thereby simplifying the work process and installing it. While making it easy

추후에 교량유지보수를 위하여 교좌장치(15)를 교체하는 경우에도 교량거더지지브라켓(30)의 교좌안착부(33) 하부에서 교좌장치(15)를 구속하고 있는 볼트와 너트를 해체한 다음 들어 올리고 바로 교좌장치(15)를 교체할 수 있도록 하여 유지보수작업도 간편하게 수행할 수 있도록 한 것이다.Even when the bridge device 15 is replaced for bridge maintenance in the future, the bolts and nuts that restrain the bridge device 15 from the bridge seating portion 33 of the bridge girder support bracket 30 are removed and then lifted. It is to be able to replace the lifting device 15 immediately to raise and to easily perform maintenance work.

상기의 기능을 발휘하기 위하여 교좌안착부(33), 즉 교좌장치(15)와 접하는 부분은 평평하게 하며, 바람직하게는 교좌장치(15)의 상부가 위치하는 부분은 오목하게 홈을 형성하여 설치시 홈내에 교좌장치(15)가 위치하도록 하여 간단히 교량거더지지브라켓(30)을 설치할 수 있도록 함과 동시에 외부의 진동에 의하여도 쉽게 교좌장치로부터 교량거더지지브라켓(30)이 이탈되는 것도 방지할 수 있다. In order to exert the above functions, the seat seating portion 33, that is, the portion in contact with the seating device 15 is flat, and preferably, the portion in which the top of the seating device 15 is located is formed by forming a recess. When the bridge device 15 is located in the groove, the bridge girder support bracket 30 can be easily installed, and the bridge girder support bracket 30 can be easily prevented from the bridge device even by external vibration. Can be.

도 6은 본 발명의 다른 실시예인 2방향지지대의 교량거더지지브라켓을 전체적으로 보여주는 도면으로서, 가운데가 일정한 크기의 교좌안착부(33)가 형성되고, 상기 교좌안착부(33)의 양측에 일정한 길이로서 중앙은 통공부(34)가 형성된 4각통체(32)의 지지대(31)가 형성되도록 하되 교좌안착부(33)가 있는 내측으로 오므라진 V자형태인 강재로 제작한 것이다.6 is a view showing the bridge girder support bracket of the two-way support as an embodiment of the present invention as a whole, the seat seating portion 33 of a certain size is formed in the middle, a constant length on both sides of the seat seating portion 33 As the center is to be made of a V-shaped steel material that is formed so that the support 31 of the four-cylindrical body 32 formed with the through hole 34, the inner side of the seat seat 33 is retracted.

상기 교량거더지지브라켓(30)을 간단한 구조로 사전에 제작하는 것은 교각 및 교대(16)에 상기 브라켓(30)을 설치하고 바로 거더(13)를 설치하도록 하므로서 작업공정을 간단하게 함과 동시에 설치도 간편하게 하면서, Producing the bridge girder support bracket 30 in a simple structure in advance allows the bracket 30 to be installed on the pier and the shift 16 and immediately installs the girder 13, thereby simplifying the work process and installing it. While making it easy

추후에 교량유지보수를 위하여 교좌장치(15)를 교체하는 경우에도 교량거더지지브라켓(30)의 교좌안착부(33) 하부에서 교좌장치(15)를 구속하고 있는 볼트와 너트를 해체한 다음 들어 올리고 바로 교좌장치(15)를 교체할 수 있도록 하여 유지보수작업도 간편하게 수행할 수 있도록 한 것이다.Even when the bridge device 15 is replaced for bridge maintenance in the future, the bolts and nuts that restrain the bridge device 15 from the bridge seating portion 33 of the bridge girder support bracket 30 are removed and then lifted. It is to be able to replace the lifting device 15 immediately to raise and to easily perform maintenance work.

상기의 기능을 발휘하기 위하여 교좌안착부(33), 즉 교좌장치(15)와 접하는 부분은 평평하게 하며, 바람직하게는 교좌장치(15)의 상부가 위치하는 부분은 오목하게 홈을 형성하여 설치시 홈내에 교좌장치(15)가 위치하도록 하여 간단히 교량거더지지브라켓(30)을 설치할 수 있도록 함과 동시에 외부의 진동에 의하여도 쉽게 교좌장치(15)로부터 교량거더지지브라켓(30)이 이탈되는 것도 방지할 수 있다.In order to exert the above functions, the seat seating portion 33, that is, the portion in contact with the seating device 15 is flat, and preferably, the portion in which the top of the seating device 15 is located is formed by forming a recess. The bridge girder support bracket 30 can be easily installed by allowing the bridge girder support bracket 30 to be located in the groove at the same time, and the bridge girder support bracket 30 can be easily detached from the bridge girder 15 by external vibration. It can also prevent.

본 발명은 강으로 제작된 4각통체의 지지대를 네방향 또는 2방향으로 설치한 교량거더지지브라켓을 교각 및 교대에 설치하고 바로 거더를 설치하도록 하므로서 작업공정을 간단하게 하면서, 설치가 간편하고, 추후에 교량유지보수를 위하여 교좌장치를 교체하는 경우에도 교량거더지지브라켓의 교좌안착부만 하부에서 들어 올 린다음 바로 교좌장치를 교체하도록 하는 것으로서 구조물의 구조가 간단하여 제작이 간편함과 동시에 교량설치과정이 간단하고, 추후에 실시되는 교량유지보수작업도 간편하게 수행할 수 있도록 하는 시공성 및 경제성이 향상된 교량거더지지브라켓을 이용한 교량시공방법인 것이다.The present invention is easy to install, while simplifying the work process by installing the girder support bracket made of steel in four directions or two directions of the bridge girder support bracket made of steel on the piers and shifts, Even in case of replacing the bridge device for bridge maintenance in the future, lift the bridge seat of the bridge girder support bracket from the lower part and replace the bridge device immediately. It is a bridge construction method using the bridge girder support bracket, which is easy to carry out the process, and can be easily performed in the future.

Claims (5)

교량을 설치하기 위하여 양측부에는 교대를 설치하고, 내측으로는 일정한 간격으로 교각을 설치하면서, 교좌장치를 각각 설치하고, 상기 설치된 교대와 교각, 교각과 교각의 상부에 설치된 교좌장치 위에 교좌안착부가 설치되도록 하면서 교량거더지지브라켓을 설치하되, 상기 교량거더지지브라켓의 네방향 또는 2방향으로 형성된 지지대가 상향으로 거치되도록 한 다음, 거더를 한쌍의 지지대 위에 각각 일체연결설치하는 작업을 하면서 교량거더지지브라켓 위에 거더를 설치하고, 거더 위에 교량상판슬래브를 설치하기 위한 철근을 배근한 다음, 콘크리트를 타설양생하여 교량샹부구조물을 설치한 다음 양측에 연석을 설치하여 교량을 시공하는 교량시공방법에 있어서,In order to install the bridges, both sides are provided with alternating parts, and inside of the bridges are installed at regular intervals, each of which installs a bridge device, and the seat seating portion is placed on the bridge device installed on the top of the bridges and bridges, the bridges and the bridges. The bridge girder support bracket is installed while being installed, but the support formed in four or two directions of the bridge girder support bracket is mounted upward, and then the girder is integrally connected and installed on a pair of supports, respectively. In the bridge construction method in which the girder is installed on the bracket, the reinforcing bar for installing the bridge slab is installed on the girder, the concrete is poured, the bridge shank structure is installed, and the curb is installed on both sides to install the bridge. 상기 교량거더지지브라켓은 중앙에 일정한 크기의 교좌안착부가 형성되고 상기 교좌안착부의 네방향에 일정한 길이의 지지대가 형성되되, 교좌안착부가 있는 내측으로 오므라든 4각파라밋모서리형성을 갖는 강재로 제작한 것에 특징이 있는 4방향 또는 2방향으로 지지대가 설치된 교량거더지지브라켓을 이용한 교량시공방법.          The bridge girder support bracket has a seat seat having a predetermined size in the center, and a support of a certain length is formed in four directions of the seat seat. Bridge construction method using the bridge girder support bracket is installed in four or two directions characterized by one. 삭제delete 제 1항에 있어서,The method of claim 1, 상기 교량거더지지브라켓은 가운데가 일정한 크기의 교좌안착부가 형성되고, 상기 교좌안착부의 양측에 일정한 길이의 지지대가 형성되되, 교좌안착부가 있는 내측으로 오므라진 V자형태인 강재로 제작한 것에 특징이 있는 4방향 또는 2방향으로 지지대가 설치된 교량거더지지브라켓을 이용한 교량시공방법. The bridge girder support bracket has a seat seat having a predetermined size in the center, and a support of a certain length is formed on both sides of the seat seat, and is made of steel having a V-shape inwardly with the seat seat. Bridge construction method using the bridge girder support bracket is installed in four or two directions. 제 1항 또는 제3항에 있어서,The method according to claim 1 or 3, 상기 지지대는 중앙은 통공부가 형성된 4각통체의 강재인 것에 특징이 있는 4방향 또는 2방향으로 지지대가 설치된 교량거더지지브라켓을 이용한 교량시공방법. The support is a bridge construction method using a bridge girder support bracket is installed in the four or two directions, characterized in that the center of the four-piece cylindrical steel formed through holes. 제 1항 또는 제3항에 있어서,The method according to claim 1 or 3, 상기 교좌안착부는 중앙이 일정한 크기의 오목홈이 형성되어 교좌장치의 상부가 홈내에 설치되도록 한 것에 특징이 있는 4방향 또는 2방향으로 지지대가 설치된 교량거더지지브라켓을 이용한 교량시공방법.The bridge seating portion is a bridge construction method using a bridge girder support bracket is installed in the four or two directions characterized in that the center is formed in a concave groove of a constant size so that the upper portion of the bridge device is installed in the groove.
KR1020060099896A 2006-10-13 2006-10-13 Bridge construction method using a bridge girder supporting bracket which four or two-direction supporter is installed KR100734019B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020060099896A KR100734019B1 (en) 2006-10-13 2006-10-13 Bridge construction method using a bridge girder supporting bracket which four or two-direction supporter is installed

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020060099896A KR100734019B1 (en) 2006-10-13 2006-10-13 Bridge construction method using a bridge girder supporting bracket which four or two-direction supporter is installed

Publications (1)

Publication Number Publication Date
KR100734019B1 true KR100734019B1 (en) 2007-06-29

Family

ID=38373821

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020060099896A KR100734019B1 (en) 2006-10-13 2006-10-13 Bridge construction method using a bridge girder supporting bracket which four or two-direction supporter is installed

Country Status (1)

Country Link
KR (1) KR100734019B1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100949584B1 (en) 2007-11-27 2010-03-25 주식회사 코아이엔씨 Pre-cast concrete elments and construction method using thereof for upper portion of bridge
CN102493331A (en) * 2011-12-19 2012-06-13 上海市城市建设设计研究总院 Structure capable of realizing large-span V-shaped pier continuous rigid frame bridge and construction process thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200333780Y1 (en) 2003-08-14 2003-11-17 노윤근 large number bracket in which supporter was installed is used and it is a bridge, multiplex point installed so that support might be carried out support bracket
KR20050018195A (en) * 2003-08-14 2005-02-23 노윤근 large number bracket in which supporter was installed is used and it is a bridge, multiplex point installed so that support might be carried out support bracket and its installation method
KR100555253B1 (en) 2005-03-02 2006-03-03 노윤근 The bridge construction method of having used composition double girder and this which connected and manufactured i beam by the upper and lower sides
KR100555249B1 (en) 2005-03-29 2006-03-03 노윤근 Bridge constructing method using even-sectioned i-type rolled steel beam having increased section intensity and i-type rolled steel beam manufactured with uneven steel plate

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200333780Y1 (en) 2003-08-14 2003-11-17 노윤근 large number bracket in which supporter was installed is used and it is a bridge, multiplex point installed so that support might be carried out support bracket
KR20050018195A (en) * 2003-08-14 2005-02-23 노윤근 large number bracket in which supporter was installed is used and it is a bridge, multiplex point installed so that support might be carried out support bracket and its installation method
KR100555253B1 (en) 2005-03-02 2006-03-03 노윤근 The bridge construction method of having used composition double girder and this which connected and manufactured i beam by the upper and lower sides
KR100555249B1 (en) 2005-03-29 2006-03-03 노윤근 Bridge constructing method using even-sectioned i-type rolled steel beam having increased section intensity and i-type rolled steel beam manufactured with uneven steel plate

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100949584B1 (en) 2007-11-27 2010-03-25 주식회사 코아이엔씨 Pre-cast concrete elments and construction method using thereof for upper portion of bridge
CN102493331A (en) * 2011-12-19 2012-06-13 上海市城市建设设计研究总院 Structure capable of realizing large-span V-shaped pier continuous rigid frame bridge and construction process thereof

Similar Documents

Publication Publication Date Title
KR100742206B1 (en) Steel-concrete composite rahmen bridge and construction method thereof
KR101178876B1 (en) Prestressed composit rahmen bridge construdtion method
KR100889273B1 (en) Construction method for rhamen bridge
KR100891924B1 (en) Variable section u-type girder for temporary bridge
KR20090001261A (en) Prestressed concrete girder bridge having connecting structure using steel bar, and constructing method thereof
KR100974305B1 (en) Continuous beam bridge construction method using girder for multi-span
KR100728106B1 (en) Cantilever construction structure of slab for bridge and the method thereof
KR100734019B1 (en) Bridge construction method using a bridge girder supporting bracket which four or two-direction supporter is installed
KR100923564B1 (en) Precast concrete panel, construction method and structure of precast concrete panel using steel plate
KR101198376B1 (en) Fcm pier table construction method using girder
KR100946716B1 (en) Long Span PSC Girder Type Rahmen Bridge and its Construction Method Using Moment Re-distribution
KR100522298B1 (en) Improved prestressed steel reinforced concrete beam and bridge construction method using the same beam
KR20040004819A (en) Method for changing steel bridge of supporting rail into concreat bridge
KR101043710B1 (en) Through bridge construction method by side beam and slab by box structure without lateral prestressing
KR101232329B1 (en) Integral bridge and construction method using arched and concrete-filled tube
KR20050018358A (en) Structure of continuous PSC beam with connection member and steel cross beam and bridge construction method using the same
KR100909004B1 (en) Hybrid composite girder continuous bridge and constructing method therefor
KR200397213Y1 (en) Mounting structure of Steel Cross-beam in Multi-girder concrete bridge and its construction method
KR100791991B1 (en) Temporary bridge consruction method using composite slab girder
KR101121725B1 (en) Construction method for psc girder and slab with precast deck and bridge construction method using the same
KR20080103721A (en) Supporter for bridge slab mold
KR101127427B1 (en) Rahmen bridge and construction method thereof
RU2331727C1 (en) Road, airfield slab
KR20080109983A (en) Bridge construction method using girder unit integrated slab
RU2453657C2 (en) Design of foundation for structure or building and method of its manufacturing

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20130614

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20140617

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20150615

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20160617

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20170517

Year of fee payment: 11

FPAY Annual fee payment

Payment date: 20180529

Year of fee payment: 12

FPAY Annual fee payment

Payment date: 20190508

Year of fee payment: 13