KR100650444B1 - Cantilever part construction method of bridge - Google Patents

Cantilever part construction method of bridge Download PDF

Info

Publication number
KR100650444B1
KR100650444B1 KR1020050059329A KR20050059329A KR100650444B1 KR 100650444 B1 KR100650444 B1 KR 100650444B1 KR 1020050059329 A KR1020050059329 A KR 1020050059329A KR 20050059329 A KR20050059329 A KR 20050059329A KR 100650444 B1 KR100650444 B1 KR 100650444B1
Authority
KR
South Korea
Prior art keywords
girder
support
panel
slab
hardware
Prior art date
Application number
KR1020050059329A
Other languages
Korean (ko)
Inventor
서승권
Original Assignee
주식회사 효성엘비데크
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 효성엘비데크 filed Critical 주식회사 효성엘비데크
Priority to KR1020050059329A priority Critical patent/KR100650444B1/en
Application granted granted Critical
Publication of KR100650444B1 publication Critical patent/KR100650444B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/10Cantilevered erection
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
    • E01D19/125Grating or flooring for bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/268Composite concrete-metal

Abstract

A construction method for a cantilever of a bridge is provided to make construction of a cantilever simply and easily and to reduce a period of construction by constructing an outer cantilever without installing a timbering or a form. A construction method for a cantilever of a bridge comprises the steps of: manufacturing a PC panel(14a) using the precasting method to be extended from an inner girder(12e), located on the inside of an outer girder(12d) where a cantilever is installed, to a cantilever(40) by arranging main reinforcement bars(36) and distribution bars to intersect each other and placing a skeleton such a truss angle, etc. and placing concrete; installing the manufactured PC panel to be projected from the inner girder to the outer girder and forming a concrete groove on the PC panel where shear reinforcement bars(32) are arranged on the outer girder; and constructing a slab(16a) by arranging reinforcement bars on the upper part of the girders and the PC panel and placing concrete in the concrete groove, and the curing together with upper concrete.

Description

교량의 캔틸레버부 시공방법 {Cantilever part construction method of bridge}Cantilever part construction method of bridge

도 1a와 도 1b는 교량에 설치되는 캔틸레버부의 예를 나타내는 도면,1A and 1B are views showing an example of a cantilever part installed in a bridge;

도 2는 본 발명의 제1실시예에 따른 캔틸레버부의 시공방법을 나타낸 정면도,2 is a front view showing a construction method of the cantilever unit according to the first embodiment of the present invention;

도 3은 도 2의 평면도,3 is a plan view of FIG.

도 4는 본 발명의 제2실시예에 따른 캔틸레버부의 시공방법을 나타낸 정면도,4 is a front view showing a construction method of the cantilever unit according to the second embodiment of the present invention;

도 5는 본 발명의 제3실시예에 따른 캔틸레버부의 시공방법을 나타낸 정면도,5 is a front view showing a construction method of the cantilever unit according to the third embodiment of the present invention;

도 6은 본 발명의 제4실시예에 따른 캔틸레버부의 시공방법을 나타낸 정면도,6 is a front view showing a construction method of the cantilever unit according to the fourth embodiment of the present invention;

도 7a와 도 7b는 본 발명의 제5실시예에 따른 캔틸레버부의 시공방법을 나타낸 정면도,7A and 7B are front views showing the construction method of the cantilever unit according to the fifth embodiment of the present invention;

도 8은 본 발명의 제6실시예에 따른 캔틸레버부의 시공방법을 나타낸 정면도,8 is a front view showing a construction method of the cantilever unit according to the sixth embodiment of the present invention;

도 9a와 도 9b는 도 8에 나타낸 지지철물에 지지대가 체결되는 상태도,9a and 9b is a state in which the support is fastened to the support hardware shown in FIG.

도 10은 본 발명의 제7실시예에 따른 캔틸레버부의 시공방법을 나타낸 정면도,10 is a front view showing a construction method of the cantilever unit according to the seventh embodiment of the present invention;

도 11은 도 10에서 거더에 PC 패널이 설치된 상태에서의 평면도이다.FIG. 11 is a plan view in a state where a PC panel is installed in the girder in FIG. 10.

<도면의 주요부분에 대한 부호의 설명><Description of the symbols for the main parts of the drawings>

10: 교각 12: 거더10: Pier 12: Girder

14: PC 패널 16: 슬래브14: PC panel 16: slab

40,42: 캔틸레버부 40, 42: cantilever section

본 발명은 교량의 캔틸레버부 시공방법에 관한 것으로서, 더욱 상세하게는 교량의 돌출부에 일단이 고정 지지되고 타단이 자유로운 보 형태를 이루는 캔틸레버부를 용이하게 시공하기 위한 방법에 관한 것이다.The present invention relates to a method for constructing a cantilever portion of a bridge, and more particularly, to a method for easily constructing a cantilever portion having a beam shape fixed at one end to a protruding portion of a bridge and having a free end at the other end.

일반적으로 아파트의 베란다나 교량의 슬래브 돌출부 등과 같은 구조물을 건축하기 위해서는 일단이 고정 지지되고 타단이 자유로운 보 형태의 캔틸레버(cantilever)를 시공해야 한다.In general, in order to construct a structure such as a veranda of an apartment or a slab protrusion of a bridge, a cantilever of a beam type having a fixed end and a free end is required.

교량 건설에 있어 거더(girder)와 거더 사이에 슬래브를 시공하거나 또는 외측 거더에 돌출부(외측 캔틸레버부)를 시공하기 위해서는 일단에 거푸집을 설치하고, 설치된 거푸집에 콘크리트를 타설 및 양생하는 과정을 거치게 된다.In the construction of bridges, in order to construct slabs between girders and girders or to project protrusions (outer cantilever sections) to outer girders, formwork is installed at one end and concrete is laid and cured at the installed formwork. .

도 1a에 도시된 바와 같이, 양 거더((12a,12b),(12b,12c)) 사이는 양 거더 상단에 프리캐스트 콘크리트 패널(Precast Concrete Panel, 이하 PC 패널(14))을 걸치듯 올려놓고 슬래브(16)를 시공하기 위해 콘크리트를 타설 및 양생하면 되어 시공이 수월하다.As shown in Figure 1a, between both girders (12a, 12b, (12b, 12c)) and put the precast concrete panel (PC panel 14) on top of both girders In order to construct the slab 16, it is easy to construct the concrete by pouring and curing.

그러나 외측 거더(12a,12c)의 일측방으로 돌출되는 돌출부(캔틸레버부(40))를 시공하기 위해서는 먼저 가로대, 세로대 및 지지대로 이루어지는 캔틸레버 브래킷(동바리)을 설치하고, 그 상부에 합판 등의 판재를 놓고 상기 캔틸레버 브래킷과 볼트 등으로 결합한 다음 각 모서리를 마무리하여 거푸집을 완성한 후 콘크리트를 타설하여 양생함으로써 시공을 완료한다.However, in order to construct the protrusion (cantilever portion 40) projecting to one side of the outer girders 12a and 12c, first, a cantilever bracket (cutter) made of a crossbar, a longitudinal rod, and a support bar is installed, and a plate such as plywood on the upper portion thereof. Lay the combination of the cantilever bracket and bolts, and then finish each corner to finish the formwork to finish the construction by pouring concrete.

타설된 콘크리트의 양생과정이 끝나면 시공과정과 역순으로 캔틸레버 브래킷에서 볼트 등을 제거하고, 합판을 떼어내는 거푸집 해체작업을 하게 된다.After curing process of pour concrete, bolts are removed from cantilever bracket in the reverse order of construction process, and formwork is dismantled to remove plywood.

그러나 이와 같은 캔틸레버 시공방법은 캔틸레버 브래킷의 설치 및 해체 작업의 번거롭고 불편하며 시공기간이 길어지는 문제점이 있다.However, such a cantilever construction method has a problem that the installation and dismantling work of the cantilever bracket is cumbersome and inconvenient, and the construction period is long.

또한, 도 1b에 도시한 바와 같이 교량의 폭이 넓어 교각(10)을 좌우로 인접되게 설치하는 경우에, 양 교각(10)에 각각 설치된 내측 거더(12c) 사이에 돌출부(캔틸레버부(42))를 시공하기 위해서 각각의 내측 거더(12c)에 상기한 방식으로 거푸집을 반복해서 설치 및 해체해야 하는 문제점이 있었다.In addition, as shown in FIG. 1B, when the width of the bridge is wide and the pier 10 is installed adjacently to the left and right, a protrusion (cantilever portion 42) is provided between the inner girders 12c provided in the pier 10, respectively. There was a problem in that the formwork was repeatedly installed and dismantled in each of the inner girders 12c in the above-described manner in order to construct).

상술한 문제점을 해결하기 위하여 안출된 본 발명은 동바리나 거푸집을 설치하지 않고 캔틸레버부를 시공할 수 있기 때문에 캔틸레버부의 시공이 간편하고 용이하며 시공기간을 줄일 수 있는 교량의 캔틸레버부 시공방법을 제공하는데 주목적 이 있다.The present invention devised to solve the above problems can be installed cantilever portion without installing a copper bar or formwork, the main purpose to provide a cantilever portion construction method of the bridge can be easy and easy construction of the cantilever portion can reduce the construction period There is this.

본 발명의 다른 목적은 양 교각이 좌우로 인접되게 설치되는 경우에 일측 거더에만 동바리와 지지철물을 설치하여 캔틸레버부를 시공할 수 있기 때문에 시공이 간편하고 용이하며 시공기간을 줄일 수 있을 뿐만 아니라 자재를 절감할 수 있는 교량의 캔틸레버부 시공방법을 제공하는데 있다.Another object of the present invention is to install the cantilever part by installing the copper bar and the support hardware only on one side girders when the two piers are installed adjacent to the left and right, the construction is easy and easy, and the construction period can be reduced as well as the material It is to provide a cantilever construction method of the bridge can be reduced.

상술한 목적을 달성하기 위한 본 발명의 실시예에 따른 교량의 캔틸레버부 시공방법은, 내측 거더에서 외측 거더의 돌출부까지 연장될 수 있도록 PC 패널을 프리캐스팅 방식에 의해 한판으로 제작하는 공정과, 상기 PC 패널을 내측 거더에서 외측 거더의 돌출부까지 돌출되도록 설치하는 공정 및 상기 내외측 거더의 상부와 PC 패널의 상부에 철근을 배근하고 콘크리트를 타설하여 슬래브를 시공하는 공정을 포함한다.Method for constructing the cantilever portion of a bridge according to an embodiment of the present invention for achieving the above object, the process of manufacturing a PC panel in a single plate by a precasting method so as to extend from the inner girder to the protrusion of the outer girder, and And installing the PC panel so as to protrude from the inner girder to the protrusion of the outer girder and installing the slab by placing reinforcing bars on the upper part of the inner and outer girder and the upper part of the PC panel.

이하 본 발명의 실시예에 대하여 첨부된 도면을 참고로 그 구성 및 작용을 설명하기로 한다.Hereinafter, the configuration and operation of the present invention will be described with reference to the accompanying drawings.

도 2는 본 발명의 제1실시예에 따른 캔틸레버부의 시공방법을 나타낸 정면도이고, 도 3은 도 2의 평면도이다.2 is a front view showing a construction method of the cantilever unit according to the first embodiment of the present invention, Figure 3 is a plan view of FIG.

도시된 바와 같이, 캔틸레버부(40)가 설치되는 외측 거더(12d)의 안쪽에 있는 내측 거더(12e)에서 캔틸레버부(40)까지 연장될 수 있도록 PC 패널(14a)을 프리캐스팅 방식에 의해 한판으로 제작한다.As shown, the PC panel 14a is plated by precasting so that the cantilever portion 40 can extend from the inner girder 12e inside the outer girder 12d on which the cantilever portion 40 is installed to the cantilever portion 40. Produced by

즉, 주철근(36)과 배력철근(미도시)을 교차되도록 배근하고 필요에 따라 그 상부에 트러스 앵글 등 골조(미도시)를 배치한 상태에서 콘크리트를 타설하고 양생한다.That is, the reinforcement so as to cross the main reinforcement 36 and the reinforcement reinforcement (not shown) and the concrete is poured and cured in the state in which a skeleton (not shown) such as a truss angle is disposed on the upper portion as necessary.

이때 상기 주철근(36)은 외측 캔틸레버부(40)까지 연장되도록 배근하여 상부 슬래브(16a)의 무게를 지탱할 수 있도록 한다.At this time, the main reinforcing bar 36 is to extend to the outer cantilever portion 40 to support the weight of the upper slab (16a).

이와 같이 프리캐스팅 방식에 의해 한판으로 제작된 PC 패널(14a)을 내측 거더(12e)에서 외측 거더(12d) 밖 돌출부까지 돌출되도록 설치하되, 상기 외측 거더(12d) 상부에 전단철근(32)이 배근된 부분의 PC 패널(14a)에는 콘크리트홈(34)을 형성한다.In this way, the PC panel 14a manufactured as a single plate by the precasting method is installed to protrude from the inner girder 12e to the protrusion outside the outer girder 12d, but the shear reinforcement 32 is disposed on the outer girder 12d. A concrete groove 34 is formed in the PC panel 14a of the recessed portion.

상기 거더(12e,12d)의 상부와 PC 패널(14a)의 상부에 철근을 배근하고 슬래브를 시공하기 위해 콘크리트를 타설하되, 콘크리트홈(34)에도 콘크리트를 함께 타설하여 상부 콘크리트와 함께 양생함으로써 슬래브(16a)를 시공한다.Reinforce the reinforcing bars in the upper part of the girder (12e, 12d) and the upper part of the PC panel 14a and cast concrete to construct the slab, but also cast concrete together in the concrete groove 34 to cure with the upper concrete slab Construct (16a).

이와 같이 PC 패널(14a)을 외측 캔틸레버부(40)까지 연장되도록 한판으로 미리 제작하여 슬래브(16a)를 시공함으로써 외측 캔틸레버부(40)의 시공시에 동바리와 거푸집을 설치하지 않아도 된다.In this way, the PC panel 14a is prefabricated in a single plate so as to extend to the outer cantilever portion 40, and the slab 16a is constructed so that it is not necessary to install the copper bar and formwork at the time of constructing the outer cantilever portion 40.

도 4는 본 발명의 제2실시예에 따른 캔틸레버부의 시공방법을 나타낸 정면도이다.4 is a front view showing a construction method of the cantilever unit according to the second embodiment of the present invention.

도시된 바와 같이, 거더(12f)의 상부에 암나사산이 형성된 너트(37)를 매립하고, 상기 거더(12f)에 매립된 너트(37)의 하부에 숫나사산이 형성된 지지대(33)를 나사 결합하여 거더(12f)에 지지대(33)를 입설한다.As shown, a nut 37 with a female thread formed in the upper part of the girder 12f is embedded, and a support 33 in which a male thread is formed in the lower part of the nut 37 embedded in the girder 12f is screwed into the girder. A support stand 33 is placed in 12f.

프리캐스팅 방식으로 제작된 PC 패널(14b)을 거더(12f)의 외측으로 수평되게 배치하되, 상기 거더(12f)에 고정되어 지지대(33)의 상부에 연결되는 와이어(35)를 PC 패널(14b)의 끝단부에 고정시켜 PC 패널(14b)이 움직이지 않도록 고정한다.The PC panel 14b manufactured by the precasting method is arranged horizontally to the outside of the girder 12f, and the wire 35 fixed to the girder 12f and connected to the upper part of the support 33 is connected to the PC panel 14b. ) To secure the PC panel 14b so as not to move.

상기 거더(12f)의 상부와 PC 패널(14b)의 상부에 철근을 배근하고, 콘크리트를 타설하여 양생함으로써 슬래브(16b)의 시공이 완료된다.Construction of the slab 16b is completed by reinforcing the reinforcing bars on the upper part of the girder 12f and the upper part of the PC panel 14b, and pouring and curing concrete.

다음 상기 지지대(33)를 거더(12f)에서 분리하고 거더(12f) 및 PC 패널(14b)에서 와이어(35)를 분리한다.The support 33 is then separated from the girder 12f and the wire 35 from the girder 12f and the PC panel 14b.

이와 같이 PC 패널(14b)을 지지대(33)를 이용하여 설치하고 그 상부에 슬래브(16b)를 시공함으로써 동바리와 거푸집을 설치하지 않아도 된다.In this way, the PC panel 14b is installed by using the support base 33, and the slab 16b is installed on the upper portion thereof, thereby eliminating the need for installing copper bars and formwork.

도 5는 본 발명의 제3실시예에 따른 캔틸레버부의 시공방법을 나타낸 정면도이다.5 is a front view showing a construction method of the cantilever unit according to the third embodiment of the present invention.

도시된 바와 같이, 좌우로 인접된 교각의 상부에 설치된 양 거더(12f,12g)에 양끝단부가 ㄱ자로 절곡된 수평지지보(38,호리빔)를 걸쳐 설치하고, 프리캐스팅 방식으로 제작된 PC 패널(14c)을 일측 거더(12f)의 상부와 수평 지지보(38)의 상부 일부에 설치한다.As shown, the two girders (12f, 12g) installed on the upper left and right adjacent piers are installed across the horizontal support beam 38 (horizontal beams) bent at the letter A, the PC produced in a precast method The panel 14c is installed in the upper part of the one side girder 12f and the upper part of the horizontal support beam 38. As shown in FIG.

상기 일측 거더(12f)의 상부와 PC 패널(14c)의 상부에 철근을 배근하고, 콘크리트를 타설하여 양생함으로써 교각의 일측 거더(12f) 또는 양측 거더(12f,12g)에 슬래브(16c)의 시공이 완료된다.Construction of the slab 16c on one side girder 12f or both side girders 12f, 12g of the piers by reinforcing the reinforcing bars in the upper part of the one side girder 12f and the upper part of the PC panel 14c, and casting and curing the concrete. Is complete.

다음 상기 수평지지보(38)를 양 거더(12f,12g)에서 해체한다.Next, the horizontal support 38 is dismantled from both girders 12f and 12g.

이와 같이 PC 패널(14c)을 수평지지보(38)를 이용하여 설치하고 그 상부에 슬래브(16c)를 시공함으로써 동바리와 거푸집을 설치하지 않아도 된다.In this way, the PC panel 14c is installed using the horizontal support 38, and the slab 16c is installed on the upper portion thereof, thereby eliminating the need for installing the copper bars and the formwork.

도 6은 본 발명의 제4실시예에 따른 캔틸레버부의 시공방법을 나타낸 정면도이다.6 is a front view showing a construction method of the cantilever unit according to the fourth embodiment of the present invention.

도 6과 후술하는 도 7은 본 발명의 상기한 제1,2,3실시예에 따라 일측(도면에서 보아 좌측) 거더에 PC 패널과 슬래브의 시공이 완료된 상태에서, 이를 이용해 타측(도면에서 보아 우측) 거더에 PC 패널과 슬래브를 시공하는 방법을 나타내는 도면이다.FIG. 6 and FIG. 7 to be described later show that the construction of the PC panel and the slab is completed on one side (left side as seen in the figure) girder according to the first, second and third embodiments of the present invention, and the other side (as seen in the figure) Right) It is a figure which shows the method of constructing a PC panel and a slab in a girder.

도 6에 도시한 바와 같이, 좌우로 인접된 교각의 상부에 설치된 양 거더(12h,12i) 중 일측 거더(12h)에 PC 패널(14d)과 슬래브(16d)의 시공이 완료된 상태에서, 상기 슬래브(16d)의 측면에 앵커 등의 고정부재(50)를 미리 설치하여 L자형 앵글(52)을 고정하고, 상기 L자형 앵글(52)의 받침과 타측 거더(12i)의 상부에 프리캐스팅 방식으로 제작된 PC 패널(14e)을 설치한다.As shown in FIG. 6, in the state where the construction of the PC panel 14d and the slab 16d is completed on one side girder 12h among the two girders 12h and 12i provided on the upper and the adjacent piers, the slab is completed. A fixing member 50, such as an anchor, is installed on the side of 16d in advance to fix the L-shaped angle 52, and the pre-casting method is provided on the base of the L-shaped angle 52 and the other side girder 12i. The manufactured PC panel 14e is installed.

상기 타측 거더(12i)의 상부와 PC 패널(14e)의 상부에 철근을 배근하고, 콘크리트를 타설하여 양생함으로써 교각의 타측 거더(12i)에 슬래브(16e)의 시공이 완료된다.Construction of the slab 16e on the other side girder 12i of the piers is completed by reinforcing the reinforcing bars in the upper portion of the other side girder 12i and the upper portion of the PC panel 14e, and pouring and curing concrete.

이와 같이 일측 거더(12h)에 설치된 캔틸레버부와 L자형 앵글(52)을 이용하여, 좌우로 인접된 교각에 설치된 타측 거더(12i)에 PC 패널(14e)과 슬래브(16e)를 시공함으로써 동바리와 거푸집을 설치하지 않아도 된다.In this way, by using the cantilever portion and the L-shaped angle 52 provided on one side girder 12h, the PC panel 14e and the slab 16e are installed on the other side girders 12i provided on the left and right adjacent piers. There is no need to install the formwork.

도 7a와 도 7b는 본 발명의 제5실시예에 따른 캔틸레버부의 시공방법을 나타낸 정면도이다.7A and 7B are front views illustrating a construction method of the cantilever unit according to the fifth embodiment of the present invention.

도 7a에 도시된 바와 같이, 끝단부에 걸림고리(56a)가 형성된 연결 철물(56) 을 수직으로 절곡되게 설치하고, 콘크리트를 상기 연결 철물(56)을 따라 수직으로 절곡되게 타설하여 프리캐스팅 방식으로 PC 패널(14g)을 제작하되, 걸림고리(56a)가 PC 패널(14g) 본체의 상부로 돌출되도록 한다.As shown in FIG. 7A, the connection hardware 56 having the hook 56a formed at the end thereof is vertically bent, and the concrete is cast to be bent vertically along the connection hardware 56 to precast. Produce a PC panel (14g), so that the locking ring 56a protrudes to the upper portion of the PC panel (14g).

좌우로 인접된 교각의 상부에 설치된 양 거더(12j,12k) 중 일측 거더(12j)에 PC 패널(14f)과 슬래브(16f)의 시공이 완료된 상태에서, 상기 슬래브(16f)의 상면에 앵커 등의 고정부재(50)를 설치하여 고정홀(54a)과 연결 철물홀(54b)이 형성된 앵글(54)을 고정한다.Anchors, etc., on the upper surface of the slab 16f in a state in which the construction of the PC panel 14f and the slab 16f is completed on one side girders 12j among the two girders 12j and 12k provided on the upper sides of the adjacent piers. The fixing member 50 is installed to fix the angle 54 at which the fixing hole 54a and the connecting hardware hole 54b are formed.

타측 거더(12k)에 PC 패널(14g)을 걸친 상태에서 PC 패널(14g)에 돌출되게 형성된 걸림고리(56a))를 앵글(54)의 연결 철물홀(54b)에 끼워 PC 패널(14g)이 움직이지 않게 고정한다.The PC panel 14g is inserted into the connecting hardware hole 54b of the angle 54 by engaging the locking ring 56a formed to protrude from the PC panel 14g while the PC panel 14g is placed on the other girder 12k. Fix it so that it does not move.

상기 타측 거더(12k)의 상부와 PC 패널(14g)의 상부에 철근을 배근하고, 콘크리트를 타설하여 양생함으로써 교각의 타측 거더(12k)에 슬래브(16g)의 시공이 완료된다.Construction of the slab 16g on the other side girder 12k of the piers is completed by reinforcing the reinforcing bars in the upper portion of the other side girder 12k and the upper portion of the PC panel 14g, and pouring and curing concrete.

상기 상부로 돌출된 걸림고리(56a) 부분은 절단하거나 나중에 중분대용으로 사용한다.The upper part of the hook ring 56a protruding from the upper part is cut or used later for the middle squad.

이와 같이 일측 거더(12j)에 설치된 캔틸레버부와 앵글(54) 및 연결 철물(56)을 이용하여, 좌우로 인접된 교각에 설치된 타측 거더(12k)에 PC 패널(14g)과 슬래브(16g)를 시공함으로써 동바리와 거푸집을 설치하지 않아도 된다.In this way, the PC panel 14g and the slab 16g are mounted on the other side girders 12k provided on the left and right adjacent piers by using the cantilever portion, the angle 54, and the connecting hardware 56 provided on the one side girders 12j. Construction eliminates the need to install clubs and formwork.

도 7b는 도 7a의 PC 패널 제작공정에서, 콘크리트를 연결 철물을 따라 수직으로 절곡되게 타설하지 않고, 수평 부분의 연결 철물(56)에만 콘크리트를 타설하 여 PC 패널(14i)을 제작하는 것이 도 7a와 상이하며, 그 이외의 공정은 같으므로 여기서는 설명을 약한다.FIG. 7B shows that the PC panel 14i is manufactured by placing concrete only on the connecting hardware 56 in the horizontal portion, without placing concrete vertically bent along the connecting hardware in the PC panel manufacturing process of FIG. 7A. Since it is different from 7a and the other process is the same, description is abbreviate | omitted here.

도 8은 본 발명의 제6실시예에 따른 캔틸레버부의 시공방법을 나타낸 정면도이다.8 is a front view showing a construction method of the cantilever unit according to the sixth embodiment of the present invention.

본 발명의 실시예에 따른 캔틸레버부(42)의 시공방법은 도 8에 도시된 바와 같이, 먼저 대차를 이용하여 좌우로 인접된 교각의 상부에 설치된 양 거더(12n,12o) 중 일측(도면에서는 좌측) 거더(12n)에 동바리(22)의 일단을 설치하여 고정하고 상기 동바리(22)가 경사지게 외측상부를 향하도록 한 상태에서 동바리(22)의 타단에 좌측 거더(12n)와 이격시켜 지지철물(20)을 설치하여 고정한다.In the construction method of the cantilever portion 42 according to the embodiment of the present invention, as shown in FIG. 8, one side (in the drawing) of both girders 12n and 12o installed on the upper side of the piers adjacent to the left and right using a trolley first. Left) One end of the copper wheel 22 is installed and fixed to the girder 12n, and the support bar is spaced apart from the left girder 12n at the other end of the copper bar 22 in a state in which the copper bar 22 is inclined toward the outer upper part. Install and fix (20).

이때 상기 동바리(22)에는 길이를 조절할 수 있는 수단인 턴버클(turnbuckle,(23))을 구비하여 지지철물(20)의 수평이나 경사를 조절할 수 있도록 한다.At this time, the copper bar 22 is provided with a turnbuckle (23) which is a means for adjusting the length so that the horizontal or inclination of the support hardware 20 can be adjusted.

상기 동바리(22)에 의해 지지되는 지지철물(20)의 중앙 상부에 종방향으로 지지대(24)를 체결하여 지지철물(20) 상부에 지지대(24)를 입설한다.The support 24 is fastened to the upper portion of the support hardware 20 by fastening the support 24 in the longitudinal direction to the center of the support hardware 20 supported by the copper bar 22.

좌측 거더(12n)와 지지철물(20) 사이의 상부에 콘크리트 타설을 위한 PC 패널(14h)을 설치한다.A PC panel 14h for placing concrete is installed on the upper side between the left girder 12n and the supporting hardware 20.

상기 PC 패널(14h)은 주철근과 배력철근을 교차되도록 배근하고 콘크리트를 타설하고 양생하여 미리 제작한다.The PC panel 14h is prefabricated by reinforcing the main reinforcing bars and the reinforcing bars to cross, placing and curing concrete.

좌측 거더(12n) 상부와 PC 패널(14h) 상부에 철근을 배근한 후 콘크리트를 타설하여 양생함으로써 좌측 슬래브(16h)의 시공을 완료한다.After reinforcing the rebar in the upper part of the left girder 12n and the upper part of the PC panel 14h, the concrete is poured and cured to complete the construction of the left slab 16h.

이때 상기 지지대(24)를 좌측 슬래브(16h)에서 용이하게 떼어내기 위해 스티로폼과 같은 박리부재(28)를 댄 상태에서 콘크리트를 타설함이 바람직하다.At this time, in order to easily detach the support 24 from the left slab (16h) it is preferable to pour concrete in a state in which the peeling member 28, such as styrofoam.

상기 좌측 슬래브(16h)가 시공된 지지대(24)에 고정용 L형강(26)을 설치하되, 좌측 슬래브(16h)의 상부에 압착한 상태에서 조임부재(27)로 지지대(24)에 고정시킨다.Fixing L-shaped steel 26 is installed on the support 24 on which the left slab 16h is constructed, and is fixed to the support 24 by the fastening member 27 in a state of being pressed onto the upper side of the left slab 16h. .

이에 의해 상기 지지철물(20)은 좌측 슬래브(16h)에 견고히 지지되어 동바리(22)를 해체해도 되므로 좌측 거더(12n)와 지지철물(20)에서 동바리(22)를 해체한다.As a result, the supporting hardware 20 is firmly supported by the left slab 16h so that the copper bar 22 may be dismantled, so that the copper bar 22 is dismantled from the left girders 12n and the supporting hardware 20.

다음 우측 슬래브(16i)를 시공하기 위해 우측 거더(12o)와 지지철물(20) 사이의 상부에 콘크리트 타설을 위한 PC 패널(14i)을 설치한다.Next, to install the right slab 16i, a PC panel 14i for placing concrete is installed on the upper part between the right girder 12o and the supporting hardware 20.

우측 거더(12o) 상부와 PC 패널(14i) 상부에 철근을 배근한 후 콘크리트를 타설함으로써 우측 슬래브(16i)의 시공을 완료한다.Construction of the right slab 16i is completed by reinforcing the reinforcing bars on the upper part of the right girder 12o and the upper part of the PC panel 14i.

이때 상기 지지대(24)를 우측 슬래브(16i)에서 용이하게 떼어내기 위해 스티로폼과 같은 박리부재(28)를 댄 상태에서 콘크리트를 타설함이 바람직하다.In this case, in order to easily detach the support 24 from the right slab 16i, it is preferable to cast concrete in a state where a peeling member 28 such as styrofoam is attached.

우측 슬래브(16i)의 시공이 완료되면 조임부재(27)를 풀어서 고정용 L형강(26)을 지지대(24)에서 분리한다.When the construction of the right slab 16i is completed, the fastening member 27 is released to separate the fixed L-shaped steel 26 from the support 24.

마지막으로 지지대(24)를 지지철물(20)에서 분리함과 동시에 PC 패널(14h,14i)에서 지지철물(20)을 분리시킨다.Finally, the support 24 is separated from the support 20, and the support 20 is separated from the PC panels 14h and 14i.

상기 지지철물(20)에 미리 줄을 연결하여 지지대(24)에서 떼어냄과 동시에 회수가 가능하도록 한다.A string is connected to the support hardware 20 in advance so that the support hardware 20 can be removed from the support 24 and recovered at the same time.

이와 같이 좌측 거더(12n)에 동바리(22)와 지지철물(20)을 설치하여 좌측 슬래브(16h)뿐만 아니라 우측 슬래브(16i)도 시공을 할 수 있어 시공이 용이하고 시공기간을 단축할 수 있다.Thus, by installing the copper bar 22 and the support hardware 20 in the left girders (12n), not only the left slab (16h) but also the right slab (16i) can be installed, the construction is easy and the construction period can be shortened. .

도 9a와 도 9b는 도 8에 나타낸 지지철물에 지지대가 체결되는 상태도이다.9A and 9B are state diagrams in which the support is fastened to the support hardware shown in FIG. 8.

도 6a에 도시된 바와 같이, 지지대(24a)의 하부에 교량의 진행방향으로(종방향으로) L자 절곡된 체결고리(25a)가 형성되고, 지지철물(20a)에도 종방향으로 L자 절곡된 체결홈(21a)이 형성된다.As shown in FIG. 6A, an L-curved fastening ring 25a is formed at the lower portion of the support 24a in the longitudinal direction of the bridge (in the longitudinal direction), and the L-shaped bending is also performed in the longitudinal direction in the supporting steel 20a. Fastening groove 21a is formed.

지지철물(20a)이 움직이지 않게 고정된 상태에서 지지철물(20a)의 상부에서 지지대(24a) 하부의 체결고리(25a)를 지지철물(20a)의 체결홈(21a)에 삽입한 후에 지지대(24a)를 교량의 진행방향으로 밀면 체결고리(25a)의 절곡된 부위가 지지철물(20a)에 걸려 이탈됨이 없이 체결된다.The support ring 20a is inserted into the fastening groove 21a of the support piece 20a at the upper part of the support piece 20a while the support piece 20a is fixed to the support piece 20a. When the 24a) is pushed in the direction of the bridge, the bent portion of the fastening ring 25a is fastened without being caught by the supporting hardware 20a.

반대로, 상기 지지대(24a)를 지지철물(20a)에서 분리하는 경우에는 지지대(24a)를 교량 진행의 반대방향으로 밀고 상부로 들어 올리면 지지철물(20a)에서 쉽게 분리된다.On the contrary, when the support 24a is separated from the support hardware 20a, the support 24a is easily removed from the support hardware 20a by pushing the support 24a in a direction opposite to the progress of the bridge and lifting the upper support 24a.

도 9b에 도시된 바와 같이, 지지대(24b)의 하부에 교량의 진행과 직각방향으로(횡방향으로) L자로 절곡된 체결고리(25b)가 형성되고, 지지철물(20b)에 횡방향으로 L자로 절곡된 체결홈(21b)이 형성된다.As shown in Fig. 9B, a fastening ring 25b bent in an L-shape at right angles (in the transverse direction) to the progress of the bridge is formed in the lower portion of the support 24b, and the support steel 20b is formed in the transverse direction L. The fastening groove 21b bent by a ruler is formed.

지지철물(20b)이 움직이지 않게 고정된 상태에서 지지철물(20b)의 상부에서 지지대(24b) 하부의 체결고리(25b)를 지지철물(20b)의 체결홈(21b)에 삽입한 후에 지지대(24b)를 교량의 진행방향으로 밀면 체결고리(25b)의 절곡된 부위가 지지철물 (20b)에 걸려 이탈됨이 없이 체결된다.The support ring 20b is inserted into the fastening groove 21b of the support hardware 20b at the top of the support hardware 20b in the state in which the support hardware 20b is fixed so as not to move. When 24b) is pushed in the direction of the bridge, the bent portion of the fastening ring 25b is fastened without being caught by the supporting hardware 20b.

반대로, 상기 지지대(24b)를 지지철물(20b)에서 분리하는 경우에는 지지대(24b)를 교량 진행의 반대방향으로 밀고 상부로 들어 올리면 지지철물(20b)에서 쉽게 분리된다.On the contrary, when the support 24b is separated from the support hardware 20b, the support 24b is easily removed from the support hardware 20b by pushing the support 24b in a direction opposite to the progress of the bridge and lifting the upper support 24b.

도 10은 본 발명의 제7실시예에 따른 캔틸레버부의 시공방법을 나타낸 정면도이고, 도 11은 도 10에서 거더에 PC 패널이 설치된 상태에서의 평면도이다.FIG. 10 is a front view illustrating a construction method of the cantilever unit according to the seventh embodiment of the present invention, and FIG. 11 is a plan view of a PC panel installed in the girder in FIG. 10.

도시된 바와 같이, 좌우로 인접된 교각의 상부에 설치된 양 거더(12p,12q)의 설치되는 PC 패널(14j,14k)을 프리캐스팅 방식으로 각각 제작하고, 각 PC 패널(14j,14k)에 볼트/너트 등의 체결부재(30)로 앵글(58)을 체결하여 PC 패널(14j,14k)을 서로 연결한다.As shown, the PC panels 14j and 14k of the two girders 12p and 12q installed on the upper and the adjacent side of the piers are manufactured by precasting, respectively, and bolted to each PC panel 14j and 14k. The angle 58 is fastened with the fastening member 30, such as a nut, to connect the PC panels 14j and 14k to each other.

상기 양 거더(12p,12q)의 상부에 앵글(58)로 서로 연결된 PC 패널(14j,14k)을 설치한다.PC panels 14j and 14k connected to each other by angles 58 are installed on the upper portions of both girders 12p and 12q.

양 거더(12p,12q)의 상부와 PC 패널(14j,14k) 상부에 철근을 배근하고, 콘크리트를 타설하여 양생함으로써 양측 거더(12p,12q)에 슬래브(16j,16k)의 시공이 완료된다.Construction of the slabs 16j and 16k is completed on both girders 12p and 12q by placing reinforcing bars on the upper portions of both girders 12p and 12q and the upper part of the PC panels 14j and 14k, and casting and curing the concrete.

마지막으로 PC 패널(14j,14k)을 서로 연결한 앵글(58)을 절단한다.Finally, the angle 58 connecting the PC panels 14j and 14k to each other is cut.

이와 같이 PC 패널(14j,14k)을 앵글(58)로 서로 연결하고 좌우로 인접된 교각에 설치된 양 거더(12p,12q)에 PC 패널(14j,14k)을 설치하여 슬래브(16j,16k)를 동시에 시공함으로써 동바리와 거푸집을 설치하지 않아도 되고, 시공기간을 단축할 수 있다.In this way, the PC panels 14j and 14k are connected to each other by an angle 58, and the PC panels 14j and 14k are installed in both girders 12p and 12q provided in adjacent piers on the left and right sides so that the slabs 16j and 14k are installed. By constructing at the same time, it is not necessary to install clubs and formwork, and the construction period can be shortened.

이상 도면과 상세한 설명에서 최적 실시예들이 개시되고, 이상에서 사용된 특정한 용어는 단지 본 발명을 설명하기 위한 목적에서 사용된 것일 뿐 의미 한정이나 특허청구범위에 기재된 본 발명의 범위를 제한하기 위하여 사용된 것이 아니다.Embodiments of the present invention are disclosed in the drawings and the detailed description, and the specific terms used above are used only for the purpose of describing the present invention, and are used to limit the scope of the present invention as defined in the meaning or claims. It is not.

그러므로 본 기술분야의 통상의 지식을 가진 자라면 이로부터 다양한 변형 및 균등한 타 실시예가 가능하고, 본 발명의 진정한 기술적 보호 범위는 특허청구범위의 기술적 사상에 의해 정해져야 할 것이다.Therefore, those skilled in the art can be various modifications and other equivalent embodiments from this, and the true technical protection scope of the present invention should be determined by the technical spirit of the claims.

이하에서 살펴본 바와 같이 본 발명에 의하면, 동바리나 거푸집을 설치하지 않고 외측 캔틸레버부를 시공할 수 있기 때문에 캔틸레버부의 시공이 간편하고 용이하며 시공기간을 줄일 수 있다.As described below, according to the present invention, since the outer cantilever portion can be constructed without installing the copper bar or the formwork, the construction of the cantilever portion is simple, easy, and the construction period can be reduced.

또한, 양 교각이 좌우로 인접되게 설치되는 경우에 일측 거더에서만 동바리와 지지철물을 설치하여 캔틸레버부를 시공할 수 있기 때문에 시공이 간편하고 용이하며 시공기간을 줄일 수 있을 뿐만 아니라 자재를 절감할 수 있다.In addition, when both piers are installed to the left and right adjacent to each other, the cantilever part can be installed by installing the copper bar and the supporting hardware only on one side girder, so the construction is simple and easy, and the construction period can be shortened, and the material can be saved. .

Claims (14)

내측 거더에서 외측 거더의 돌출부까지 연장될 수 있도록 PC 패널을 프리캐스팅 방식에 의해 한판으로 제작하는 공정과;Manufacturing a PC panel in a single plate by a precasting method so as to extend from the inner girder to the protrusion of the outer girder; 상기 PC 패널을 내측 거더에서 외측 거더의 돌출부까지 돌출되도록 설치하는 공정; 및Installing the PC panel to protrude from the inner girder to the protrusion of the outer girder; And 상기 내외측 거더의 상부와 PC 패널의 상부에 철근을 배근하고 콘크리트를 타설하여 슬래브를 시공하는 공정을 포함하는 교량의 캔틸레버부 시공방법.Method of constructing the cantilevered portion of the bridge including the step of laying the slab by reinforcing the reinforcing bar on the upper part of the inner and outer girder and the upper part of the PC panel. 제1항에 있어서,The method of claim 1, 상기 PC 패널을 제작하는 공정에서 횡방향으로 배근되는 주철근을 외측 거더의 돌출부까지 연장시켜 상부 슬래브의 하중을 지탱하는 것을 특징으로 하는 교량의 캔틸레버부 시공방법.The method of constructing the cantilever portion of a bridge, characterized in that in the process of manufacturing the PC panel to extend the cast iron reinforcement in the transverse direction to the protrusion of the outer girder to support the load of the upper slab. 제1항에 있어서,The method of claim 1, 상기 외측 거더 상부에 배근되는 전단철근이 있는 부분의 PC 패널에는 콘크리트홈을 형성하여 슬래브 시공을 위한 콘크리트 타설시 함께 타설하는 것을 특징으로 하는 교량의 캔틸레버부 시공방법.Method for constructing the cantilevered part of the bridge, characterized in that when forming a concrete groove in the PC panel of the part having a shear reinforcement on the outer girder to pour the concrete when placing the slab. 거더의 상부에 암나사산이 형성된 너트를 매립하고, 상기 너트에 하부에 숫 나사산이 형성된 지지대를 나사 결합하여 거더에 지지대를 입설하는 공정과;Embedding a nut having a female thread on an upper part of the girder, and screwing a support having a male thread on the lower part of the girder to install a support on the girder; 상기 거더의 외측으로 프리캐스팅 방식으로 제작된 PC 패널을 설치하되, 상기 거더에 고정되어 지지대의 상부에 연결되는 와이어를 PC 패널의 끝단부에 고정시켜 PC 패널을 움직이지 못하도록 고정시키는 공정과;Installing a PC panel manufactured by a precasting method to the outside of the girder, and fixing the wires fixed to the girder and connected to the upper part of the support to the end of the PC panel so as not to move the PC panel; 상기 거더의 상부와 PC 패널의 상부에 철근을 배근하고, 콘크리트를 타설하여 슬래브를 시공하는 공정; 및Reinforcing the reinforcing bar on the upper part of the girder and the upper part of the PC panel, and pouring the concrete to construct the slab; And 상기 지지대를 거더에서 분리하고 와이어를 PC 패널 및 슬래브에서 분리하는 공정을 포함하는 교량의 캔틸레버부 시공방법.The cantilever portion construction method comprising the step of separating the support from the girder and the wire from the PC panel and the slab. 좌우로 인접된 교각의 상부에 설치된 양 거더에 양끝단부가 ㄱ자로 절곡된 수평지지보를 걸쳐 설치하는 공정과;Installing both girders on horizontal girders, both ends of which are bent by the letter “a”, on both girders installed on the upper sides of adjacent piers; 일측 거더의 상부와 수평 지지보의 상부 일부에 프리캐스팅 방식으로 제작된 PC 패널을 설치하는 공정과;Installing a PC panel manufactured by a precasting method on an upper portion of one side girder and an upper portion of a horizontal support beam; 상기 일측 거더의 상부와 PC 패널의 상부에 철근을 배근하고, 콘크리트를 타설하여 일측 거더 또는 양측 거더에 슬래브를 시공하는 공정; 및Reinforcing the reinforcing bar on the upper part of the one side girder and the upper part of the PC panel, and placing the slab on one side girder or both side girders by pouring concrete; And 상기 수평지지보를 양 거더에서 해체하는 공정을 포함하는 교량의 캔틸레버부 시공방법.Method of constructing a cantilever portion of a bridge comprising the step of dismantling the horizontal support beams from both girders. 제1항, 제4항, 제5항 중 어느 하나의 방법으로 일측 거더에 캔틸레버부를 시공하는 공정과;Constructing a cantilever part on one side girder by any one of claims 1, 4, and 5; 상기 일측 거더에 시공된 슬래브의 측면에 앵커 등의 고정부재를 박아 L자형 앵글을 고정하는 공정과;Fixing an L-shaped angle by driving a fixing member such as an anchor on a side surface of the slab constructed on the one side girder; 상기 L자형 앵글의 받침과 타측 거더의 상부에 프리캐스팅 방식으로 제작된 PC 패널을 설치하는 공정; 및Installing a PC panel manufactured by a precasting method on the base of the L-shaped angle and on the other side of the girder; And 상기 타측 거더의 상부와 PC 패널의 상부에 철근을 배근하고, 콘크리트를 타설하여 타측 거더에 슬래브를 시공하는 공정을 포함하는 교량의 캔틸레버부 시공방법.Reinforcing the reinforcing bar on the upper part of the other girder and the upper part of the PC panel, and placing the concrete to install the slab on the other girder. 제1항, 제4항, 제5항 중 어느 하나의 방법으로 일측 거더에 캔틸레버부를 시공하는 공정과;Constructing a cantilever part on one side girder by any one of claims 1, 4, and 5; 끝단부에 걸림고리가 형성된 연결 철물을 수직으로 절곡되게 설치하고 콘크리트를 타설하여, 걸림고리가 노출되도록 프리캐스팅 방식으로 PC 패널을 제작하는 공정과;A step of manufacturing a PC panel by a precasting method to install the connection hardware in which the hook is formed at the end so as to be bent vertically and cast concrete to expose the hook; 상기 일측 거더에 시공된 슬래브의 상면에 앵커 등의 고정부재를 박아 고정홀과 연결 철물홀이 형성된 앵글을 고정하는 공정과;Fixing an angle formed with a fixing hole and a connecting hardware hole by driving a fixing member such as an anchor on an upper surface of the slab constructed on the one side girder; 타측 거더에 상기 PC 패널을 걸친 상태에서 PC 패널의 걸림고리를 앵글의 연결 철물홀에 끼워 PC 패널이 움직이지 않게 고정하는 공정; 및Fixing the PC panel so that the PC panel is not moved by inserting the hook of the PC panel into the connection hardware hole of the angle while the PC panel is placed on the other girder; And 상기 타측 거더의 상부와 PC 패널의 상부에 철근을 배근하고, 콘크리트를 타설하여 타측 거더에 슬래브를 시공하는 공정을 포함하는 교량의 캔틸레버부 시공방법.Reinforcing the reinforcing bar on the upper part of the other girder and the upper part of the PC panel, and placing the concrete to install the slab on the other girder. 제7항에 있어서,The method of claim 7, wherein 상기 PC 패널의 제작공정에서, 콘크리트를 연결 철물을 따라 수직으로 절곡되게 타설하는 것을 특징으로 하는 교량의 캔틸레버부 시공방법.In the manufacturing process of the PC panel, the cantilever portion construction method of the bridge, characterized in that the concrete is poured to be bent vertically along the connecting hardware. 대차를 이용하여 일측의 거더에 다수의 동바리가 외측상부를 향하도록 설치하고 동바리의 상부에 지지철물을 설치하는 공정과;Installing a plurality of clubs on one side of the girders to the upper side by using a trolley and installing a supporting hardware on the top of the clubs; 상기 지지철물의 중앙 상부에 종방향으로 지지대를 체결하여 지지철물 상부에 지지대를 입설하는 공정과;Fastening the support in the longitudinal direction to a central upper portion of the support hardware to place the support on the support hardware; 상기 일측 거더와 지지철물 사이의 상부에 프리캐스팅 방식으로 제작된 PC 패널을 설치하는 공정과;Installing a PC panel manufactured by a precasting method on an upper side between the one side girder and the supporting hardware; 상기 일측 거더 상부와 PC 패널 상부에 철근을 배근한 후 콘크리트를 타설하여 일측 슬래브를 시공하는 공정과;Constructing one side slab by placing concrete after placing reinforcing bars on the upper side of the girder and the upper part of the PC panel; 상기 일측 슬래브의 상부에 압착한 상태에서 고정용 L형강을 지지대에 고정시키는 공정과;Fixing the fixing L-shaped steel to a support in a state of being pressed onto the upper portion of the one side slab; 대차를 이용하여 상기 일측 거더와 지지철물에서 동바리를 해체하는 공정과;Dismantling the copper barley from the one side girder and the supporting hardware using a trolley; 상기 일측 거더와 대향되는 타측 거더와 지지철물 사이의 상부에 프리캐스팅 방식으로 제작된 PC 패널을 설치하는 공정과;Installing a PC panel fabricated by a precasting method on an upper side between the other side girder and the supporting hardware facing the one side girder; 상기 타측 거더 상부와 PC 패널 상부에 철근을 배근한 후 콘크리트를 타설하여 타측 슬래브를 시공하는 공정과;Reinforcing the reinforcing bar on the upper part of the other girder and the upper part of the PC panel, and then placing concrete to construct the other side slab; 상기 고정용 L형강을 지지대에서 분리하는 공정; 및Separating the fixed L-shaped steel from the support; And 상기 지지대를 지지철물에서 분리하고 지지철물을 회수하는 공정을 포함하는 교량의 캔틸레버부 시공방법.The cantilever portion construction method of the bridge comprising the step of separating the support from the support hardware and recovering the support hardware. 제9항에 있어서,The method of claim 9, 상기 동바리에, 동바리의 길이를 조절할 수 있는 턴버클을 구비하는 것을 특징으로 하는 교량의 캔틸레버부 시공방법.The cantilevered portion construction method of the bridge, characterized in that it comprises a turnbuckle capable of adjusting the length of the copper bar. 제9항에 있어서,The method of claim 9, 상기 콘크리트를 타설하여 슬래브를 시공하는 공정에서 지지대에 스티로폼을 댄 후 콘크리트를 타설하는 것을 특징으로 하는 교량의 캔틸레버부 시공방법.The method of constructing the cantilevered bridge of the bridge, characterized in that the concrete is poured after the styrofoam on the support in the process of installing the slab. 제9항에 있어서,The method of claim 9, 상기 지지대를 지지철물에 체결하는 공정에서, 지지대의 하부에 종방향으로 L자 절곡된 체결고리가 형성되고 상기 지지철물에 종방향으로 L자 절곡된 체결홈이 형성되어, 상기 지지철물의 상부에서 지지대 하부의 체결고리를 지지철물의 체결홈에 삽입한 후에 지지대를 종방향으로 밀어 지지대를 지지철물에 체결하는 것을 특징으로 하는 교량의 캔틸레버부 시공방법.In the process of fastening the support to the support hardware, L-shaped bent ring in the longitudinal direction is formed in the lower portion of the support and L-shaped bent in the longitudinal direction is formed in the support hardware, the upper portion of the support Method of constructing the cantilevered portion of the bridge, characterized in that the support ring is fastened to the support hardware by inserting the fastening ring of the support bottom into the fastening groove of the support hardware in the longitudinal direction. 제9항에 있어서,The method of claim 9, 상기 지지대를 지지철물에 체결하는 공정에서, 지지대의 하부에 횡방향으로 L자 절곡된 체결고리가 형성되고 상기 지지철물에 횡방향으로 L자 절곡된 체결홈이 형성되어, 상기 지지철물의 상부에서 지지대 하부의 체결고리를 지지철물의 체결홈에 삽입한 후에 지지대를 종방향으로 밀어 지지대를 지지철물에 체결하는 것을 특징으로 하는 교량의 캔틸레버부 시공방법.In the process of fastening the support to the support hardware, a fastening ring having an L-shape bent in the transverse direction is formed at the bottom of the support and a fastening groove having a L-shape bent in the transverse direction is formed in the support hardware, Method of constructing the cantilevered portion of the bridge, characterized in that the support ring is fastened to the support hardware by inserting the fastening ring of the support bottom into the fastening groove of the support hardware in the longitudinal direction. 프리캐스팅 방식으로 제작된 각 PC 패널에 볼트/너트 등의 체결부재로 앵글을 체결하여 PC 패널을 서로 연결하는 공정과;Connecting the PC panels to each other by fastening angles with fastening members such as bolts and nuts to each PC panel manufactured by the precasting method; 양 거더의 상부에 앵글로 서로 연결된 PC 패널을 설치하는 공정과;Installing PC panels connected to each other at an angle on top of both girders; 상기 양 거더의 상부와 PC 패널의 상부에 철근을 배근하고, 콘크리트를 타설하여 양 거더에 슬래브를 동시에 시공하는 공정 및;Reinforcing the reinforcing bar on the upper part of the girder and the upper part of the PC panel, and placing the slab on both girder at the same time by pouring concrete; 상기 PC 패널들을 서로 연결한 앵글을 절단하는 공정을 포함하는 교량의 캔틸레버부 시공방법.Method for constructing a cantilever portion of a bridge comprising a step of cutting an angle connecting the PC panels to each other.
KR1020050059329A 2005-07-01 2005-07-01 Cantilever part construction method of bridge KR100650444B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020050059329A KR100650444B1 (en) 2005-07-01 2005-07-01 Cantilever part construction method of bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020050059329A KR100650444B1 (en) 2005-07-01 2005-07-01 Cantilever part construction method of bridge

Publications (1)

Publication Number Publication Date
KR100650444B1 true KR100650444B1 (en) 2006-11-29

Family

ID=37713770

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020050059329A KR100650444B1 (en) 2005-07-01 2005-07-01 Cantilever part construction method of bridge

Country Status (1)

Country Link
KR (1) KR100650444B1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102488897B1 (en) 2022-10-04 2023-01-18 (주)대우강건 horizontal beam apparatus
CN115748955A (en) * 2022-11-22 2023-03-07 中建八局第三建设有限公司 High-altitude cantilever plate stacking method construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102488897B1 (en) 2022-10-04 2023-01-18 (주)대우강건 horizontal beam apparatus
CN115748955A (en) * 2022-11-22 2023-03-07 中建八局第三建设有限公司 High-altitude cantilever plate stacking method construction method

Similar Documents

Publication Publication Date Title
KR101379305B1 (en) Wall structure manufacturing method using precast front wall panel and precast back wall panel
KR101178876B1 (en) Prestressed composit rahmen bridge construdtion method
KR100742206B1 (en) Steel-concrete composite rahmen bridge and construction method thereof
KR101840763B1 (en) Cantilever bridge with t-type fixinf support bracket construction method
KR100728106B1 (en) Cantilever construction structure of slab for bridge and the method thereof
KR100543969B1 (en) Composite rigid-frame bridge installing prestressed compound beam to the contral point of the slab of rigid-frame bridge and connecting the beam to the steel member installed in the upper of pole, and construction method thereof
KR101101204B1 (en) Cantilever of slab for steel box bridge using steel supporter and the method thereof
KR101395114B1 (en) Precast panel with corrugated steel web psc girder slab structure
KR200407092Y1 (en) Support Structure for PC Panel of Cantilever Part
KR100923564B1 (en) Precast concrete panel, construction method and structure of precast concrete panel using steel plate
KR101329443B1 (en) Precast concrete frame and its construction method for buildings using precast concrete slab continued by post tensioning
KR100894650B1 (en) Rahmen bridge with preflexion load and manufacturing method the same
KR20140111476A (en) Bridge construction method for forming continuous point part of pier using copping for connecting girder
KR200406615Y1 (en) T shape precast concrete panel
KR20140125754A (en) Bridge construction method for forming continuous point part of pier using copping for connecting girder
KR20010005431A (en) Steel concrete structure
KR100650444B1 (en) Cantilever part construction method of bridge
KR100522298B1 (en) Improved prestressed steel reinforced concrete beam and bridge construction method using the same beam
KR20090075484A (en) Preflex composite girder bridge coupled width composite girder and method thereof
KR100565384B1 (en) Structure of continuous PSC beam with connection member and steel cross beam and bridge construction method using the same
KR100634344B1 (en) Composite slab and the joint structure
KR101036177B1 (en) Method for constructing building using PRC integrating method
KR101482523B1 (en) Nodular Box Girder, and Nodular Box Girder Bridge and Constructing Method thereof
KR200343468Y1 (en) Composite rigid-frame bridge installing prestressed compound beam to the contral point of the slab of rigid-frame bridge and connecting the beam to the steel member installed in the upper of pole
KR100631030B1 (en) Precasted concrete plate and bridge slab construction method using that

Legal Events

Date Code Title Description
A201 Request for examination
N231 Notification of change of applicant
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20121120

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20131121

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20141120

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20160421

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20161121

Year of fee payment: 11

FPAY Annual fee payment

Payment date: 20171102

Year of fee payment: 12

FPAY Annual fee payment

Payment date: 20181029

Year of fee payment: 13

FPAY Annual fee payment

Payment date: 20191121

Year of fee payment: 14