KR100420941B1 - Ladder laid a wall of construction and method of constructing thereof - Google Patents

Ladder laid a wall of construction and method of constructing thereof Download PDF

Info

Publication number
KR100420941B1
KR100420941B1 KR10-2001-0047439A KR20010047439A KR100420941B1 KR 100420941 B1 KR100420941 B1 KR 100420941B1 KR 20010047439 A KR20010047439 A KR 20010047439A KR 100420941 B1 KR100420941 B1 KR 100420941B1
Authority
KR
South Korea
Prior art keywords
buried
fixed
fixing
ladder
pipe
Prior art date
Application number
KR10-2001-0047439A
Other languages
Korean (ko)
Other versions
KR20030013110A (en
Inventor
조성호
Original Assignee
조성호
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 조성호 filed Critical 조성호
Priority to KR10-2001-0047439A priority Critical patent/KR100420941B1/en
Publication of KR20030013110A publication Critical patent/KR20030013110A/en
Application granted granted Critical
Publication of KR100420941B1 publication Critical patent/KR100420941B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E06DOORS, WINDOWS, SHUTTERS, OR ROLLER BLINDS IN GENERAL; LADDERS
    • E06CLADDERS
    • E06C9/00Ladders characterised by being permanently attached to fixed structures, e.g. fire escapes
    • E06C9/02Ladders characterised by being permanently attached to fixed structures, e.g. fire escapes rigidly mounted
    • E06C9/04Ladders characterised by being permanently attached to fixed structures, e.g. fire escapes rigidly mounted in the form of climbing irons or the like
    • EFIXED CONSTRUCTIONS
    • E06DOORS, WINDOWS, SHUTTERS, OR ROLLER BLINDS IN GENERAL; LADDERS
    • E06CLADDERS
    • E06C7/00Component parts, supporting parts, or accessories
    • E06C7/50Joints or other connecting parts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor
    • E02D29/122Steps or handrails for shafts

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Ladders (AREA)

Abstract

본 발명은 지중에 매설되는 맨홀과 같은 지중 콘크리트 구조물 또는 건물의 벽에 고정적으로 설치되는 매설사다리 및 이의 시공방법에 관한 것으로서, 콘크리트 구조물에 매립되는 매립고정대(31)에 손잡이발판(51)이 끼워져 고정되는 매설사다리에 있어서, 상기 매립고정대(31)는 연결 프레임(33)의 양단에 형성된 파이프 고정구멍(35)에 고정 파이프(41)의 일단이 각각 끼워진 상태에서 상기 연결프레임 (33)과 2개의 고정 파이프(41)가 용접되고, 상기 고정 파이프(41)내에 복수개의 그립링(43)이 각각 삽입 고정되고, 상기 고정 파이프(41)의 타단에 사각 패널(45)이 용접되는 것을 특징으로 한다.The present invention relates to a buried ladder that is fixedly installed on a wall of underground concrete structures or buildings, such as a manhole buried in the ground, and a construction method thereof, wherein the handle scaffold 51 is fitted to a buried fixed base 31 embedded in a concrete structure. In the buried ladder to be fixed, the buried fixing rod 31 is connected to the connecting frame 33 and 2 in a state in which one end of the fixing pipe 41 is fitted into the pipe fixing hole 35 formed at both ends of the connecting frame 33, respectively. Two fixed pipes (41) are welded, a plurality of grip rings (43) are inserted and fixed in the fixed pipes (41), and a square panel (45) is welded to the other end of the fixed pipes (41). do.

Description

매설사다리 및 이의 시공방법{Ladder laid a wall of construction and method of constructing thereof}Ladder laid a wall of construction and method of constructing

본 발명은 지중에 매설되는 맨홀과 같은 지중 콘크리트 구조물 또는 건물의 벽에 고정적으로 설치되는 매설사다리 및 이의 시공방법에 관한 것으로서, 보다 상세하게는 거푸집의 파손없이 설치할 수 있는 매설사다리 및 이의 시공방법에 관한 것이다.The present invention relates to a buried ladder and a construction method thereof is fixedly installed on the underground concrete structure or a wall of a building, such as a manhole buried in the ground, and more particularly in buried ladder and its construction method that can be installed without damage to the formwork It is about.

대한민국 실용신안등록출원 제 98-18922호(1998. 9. 29 출원)에 "사다리 설치용 결합구"가 소개되어 있고, 대한민국 실용신안등록출원 제 99-28126호(1999. 12. 14 출원)에 "탈부착이 가능한 벽체고정용 사다리"가 소개되어 있으며, 대한민국 특허출원 제 20-39146호(2000. 7. 8 출원)에 "매설사다리 및 그의 설치방법"이 소개되어 있다.Korean Utility Model Registration Application No. 98-18922 (filed Sep. 29, 1998) introduces "ladder installation coupler", and Korean Utility Model Registration Application No. 99-28126 (applied on Dec. 14, 1999) Removable wall fixing ladder "is introduced, and" buried ladder and its installation method "is introduced in Korean Patent Application No. 20-39146 (filed July 7, 2000).

위에 언급된 종래의 매설사다리(1)의 경우, 도 1에 도시된 바와같이, 매립고정대(3)의 단부에 형성된 너트체결부(5)가 구조물의 벽(11)에서 돌출되며, 상기 너트체결부(5)에 의해 손잡이발판(15)이 매립고정대(3)에 체결된다.In the case of the conventional buried ladder (1) mentioned above, as shown in Figure 1, the nut fastening portion 5 formed at the end of the buried anchor 3 is protruded from the wall 11 of the structure, the nut fastening The handle scaffold 15 is fastened to the buried fixture 3 by the portion 5.

그러나, 종래의 매설사다리(1)를 설치하기 위해서는 매립고정대(3)의 너트체결부(5)가 거푸집(13)에서 외부로 돌출되도록 거푸집(13)에 구멍을 뚫어야 하기 때문에 반복적으로 사용할 수 있는 거푸집를 1회 사용하고 폐기해야하는 문제점이 있다.However, in order to install the conventional buried ladder (1), because the nut fastening portion 5 of the buried fixing rod (3) must be punched in the formwork 13 so as to project outward from the formwork (13) can be used repeatedly There is a problem that the formwork must be used once and disposed of.

따라서, 본 발명의 목적은 설치가 간편하고, 거푸집에 구멍을 뚫지 않고도 시공할 수 있어 거푸집의 낭비를 막을 수 있는 매설사다리 및 이의 시공방법을 제공하는 것이다.Accordingly, it is an object of the present invention to provide a buried ladder and a construction method thereof, which can be installed easily and can be installed without drilling holes in the formwork, thereby preventing waste of formwork.

상기와 같은 목적을 달성하기 위한 본 발명은 콘크리트 구조물에 매립되는 매립고정대에 손잡이발판이 끼워져 고정되는 매설사다리에 있어서, 상기 매립고정대는 연결 프레임의 양단에 형성된 파이프 고정구멍에 고정 파이프의 일단이 각각 끼워진 상태에서 상기 연결프레임과 2개의 고정 파이프가 용접되고, 상기 고정 파이프내에 복수개의 그립링이 각각 삽입 고정되고, 상기 고정 파이프의 타단에 사각 패널이 용접되는 것을 특징으로 한다.In order to achieve the above object, the present invention is a buried ladder that is fixed to the buried scaffold embedded in the buried anchor to be embedded in the concrete structure, the buried anchor is one end of the fixed pipe in each of the pipe fixing holes formed at both ends of the connection frame The connecting frame and the two fixed pipes are welded in a fitted state, and a plurality of grip rings are inserted and fixed in the fixed pipes, respectively, and a square panel is welded to the other end of the fixed pipe.

상기 연결 프레임은 못이 체결되는 체결구멍이 형성되는 것을 특징으로 한다.The connecting frame is characterized in that the fastening hole is formed to fasten the nail.

상기 그립링은 클로우가 일방향으로 형성되어 손잡이발판의 홈에 체결되므로서 손잡이발판을 끼워넣을 수 있지만 반대방향으로 손잡이발판을 뺄 수 없는 일방향으로 고정용인 것을 특징으로 한다.The grip ring is fastened to the groove of the handle scaffold is formed by the claw in one direction, but can be inserted into the handle scaffold, it is characterized in that for fixing in one direction can not remove the handle scaffold in the opposite direction.

본 발명에 따른 매설사다리의 시공방법은 거푸집의 내측면에 고정프레임의 정면이 밀착되도록 고정프레임의 체결구멍에 못을 박아 거푸집에 고정하는 단계와, 콘크리트를 타설하여 상기 콘크리트가 양생되면 거푸집을 제거하는 단계와, 노출된 고정 파이프의 중공구멍에 실리콘을 주입하는 단계와, 상기 손잡이발판을 매립고정대에 삽입 고정하는 단계로 구성되는 것을 특징으로 한다.Method of construction of buried ladder according to the present invention is to nail the fastening hole of the fixing frame to the surface of the fixed frame to the inner surface of the formwork to fasten the nail to the formwork, and cast the concrete to remove the formwork when the concrete is cured And a step of injecting silicon into the hollow hole of the exposed fixing pipe, and inserting and fixing the handle scaffold into the buried holder.

이하 첨부도면을 참조하여 본 발명의 바람직한 실시예를 설명하기로 한다.Hereinafter, exemplary embodiments of the present invention will be described with reference to the accompanying drawings.

도 1은 종래의 매설사다리가 구조물의 벽에 고정된 상태를 도시한 평단면도1 is a cross-sectional view showing a state in which a conventional buried ladder is fixed to the wall of the structure

도 2는 본 발명에 따른 매설사다리를 도시한 사시도Figure 2 is a perspective view of the buried ladder according to the present invention

도 3은 본 발명에 따른 매설사다리를 도시한 분해사시도Figure 3 is an exploded perspective view showing a buried ladder according to the present invention

도 4는 본 발명에 따른 매설사다리가 구조물의 벽에 장착된 상태를 도시한 단면도Figure 4 is a cross-sectional view showing a state in which the buried ladder according to the invention mounted on the wall of the structure

도 5는 그립링에 의해 매립고정대에 손잡이발판이 장착된 상태를 도시한 확대 상세도Figure 5 is an enlarged detailed view showing a state in which the handle scaffold is mounted on the buried holder by the grip ring

도 6a 내지 도 6c는 본 발명에 따른 매립사다리의 시공방법을 도시한 개략도6a to 6c is a schematic diagram showing a construction method of a buried ladder according to the present invention

도 7은 본 발명에 따른 매립고정대가 맨홀 등에 시공된 예를 도시한 개략도Figure 7 is a schematic diagram showing an example of the construction of the buried anchor according to the invention, such as a manhole

*도면의 주요부분에 대한 부호설명** Description of Signs of Main Parts of Drawings *

21 : 매설사다리 31 : 매립고정대21: buried ladder 31: landfill

33 : 연결 프레임 41 : 고정 파이프33: connection frame 41: fixed pipe

43 : 그립링 45 : 사각 패널43: grip ring 45: square panel

51 : 손잡이발판 71 : 거푸집51: footrest 71: formwork

도 2를 참조하면, 본 발명에 따른 매설사다리(21)는 콘크리트 구조물에 매립되는 매립고정대(31)에 손잡이발판(51)이 끼워져 고정된다.Referring to Figure 2, the buried ladder 21 according to the present invention is fixed to the handle scaffold 51 is fitted to the buried fixture 31 embedded in the concrete structure.

도 3을 참조하면, 상기 매립고정대(31)는 연결 프레임(33)의 양단에 형성된 파이프 고정구멍(35)에 고정 파이프(41)의 일단이 각각 끼워진 상태에서 상기 연결프레임(33)과 2개의 고정 파이프(41)가 용접되고, 상기 고정 파이프(41)내에 복수개의 그립링(43)이 각각 삽입 고정되고, 상기 고정 파이프(41)의 타단에 사각 패널(45)이 용접된다.Referring to FIG. 3, the buried fixing rod 31 is connected to the connecting frame 33 and two in a state in which one end of the fixing pipe 41 is fitted into the pipe fixing hole 35 formed at both ends of the connecting frame 33, respectively. The fixed pipe 41 is welded, a plurality of grip rings 43 are inserted into and fixed in the fixed pipe 41, and a square panel 45 is welded to the other end of the fixed pipe 41.

상기 매립고정대(31)에 있어서, 상기 연결프레임(33)과 2개의 고정 파이프 (41)가 서로 용접되었을 때, 고정파이프(41)의 단부가 연결프레임(33)에서 돌출되지 않는다.In the buried fixture 31, when the connecting frame 33 and the two fixed pipes 41 are welded to each other, the end of the fixed pipe 41 does not protrude from the connecting frame 33.

상기 연결 프레임(33)은 못(도시하지 않음)이 체결되는 체결구멍(37)이 형성된다.The connection frame 33 is formed with a fastening hole 37 to which nails (not shown) are fastened.

도 4 및 도 5를 참조하면, 상기 그립링(43)은 클로우(claw)가 일방향으로 형성되어 손잡이발판(51)의 홈(53)에 체결되므로서 손잡이발판(51)을 화살표(61) 방향으로 끼워넣을 수 있지만 화살표(61) 반대방향으로 손잡이발판(51)을 뺄 수 없는 일방향으로 고정용이다.4 and 5, the grip ring 43 has a claw formed in one direction and is fastened to the groove 53 of the handle scaffold 51 to move the handle scaffold 51 in the direction of an arrow 61. Can be inserted into but is fixed in one direction can not pull the handle footrest 51 in the opposite direction of the arrow (61).

상기와 같이 구성된 매설사다리의 시공방법은 다음과 같다.The construction method of the buried ladder configured as described above is as follows.

도 6a에 도시된 바와같이, 거푸집(71)의 내측면에 고정프레임(33)의 정면이 밀착되도록 고정프레임(33)의 체결구멍(37)에 못(49)을 박아 거푸집(71)에 고정 (S101)한 후, 콘크리트(73)를 타설하여 상기 콘크리트가 양생되면 거푸집(71)을 제거한다(S102). 이것에 의해, 도 6b에 도시된 바와같이, 매립고정대(33)의 고정파이프(41)에 형성된 중공구멍(47)이 외부로 노출된다. 그 후 도 6c에 도시된 바와같이, 상기 노출된 중공구멍(47)에 실리콘(75)을 주입(S103)한 후, 도 4에 도시된 바와같이 손잡이발판(51)을 끼워 상기 손잡이발판(51)을 매립고정대(31)에 고정한다. 이것에 의해, 손잡이발판(51)에 형성된 홈(53)이 그립링(43)에 체결되어 상기 손잡이발판(51)이 매립고정대(33)에 고정되며, 실리콘(75)에 의해 손잡이발판(51)이 매립고정대(33)에서 흔들이지 않게된다.As shown in FIG. 6A, the nails 49 are fixed to the molds 71 by fastening the nails 49 to the fastening holes 37 of the fixing frame 33 so that the front surface of the fixing frame 33 is in close contact with the inner surface of the formwork 71. After (S101), the concrete 73 is poured to remove the formwork 71 when the concrete is cured (S102). Thereby, as shown in FIG. 6B, the hollow hole 47 formed in the fixing pipe 41 of the buried fixing table 33 is exposed to the outside. Thereafter, as illustrated in FIG. 6C, after the silicon 75 is injected into the exposed hollow hole 47 (S103), the handle scaffold 51 is fitted into the handle scaffold 51 as illustrated in FIG. 4. ) Is fixed to the landfill. As a result, the groove 53 formed in the handle scaffold 51 is fastened to the grip ring 43 so that the handle scaffold 51 is fixed to the buried stand 33, and the handle scaffold 51 is made of silicon 75. ) Is not shaken in the buried fixing (33).

이와같이 시공방법에 의해 매설사다리(21)는 예컨대 도 7에 도시된 것과 같은 맨홀 등과 같은 지하 구조물 또는 지상 구조물의 벽 등에 설치될 수 있다.In this manner, the buried ladder 21 may be installed in a wall of an underground structure or a ground structure such as a manhole as illustrated in FIG. 7.

위에서 설명한 바와같이 본 발명에 따른 매설사다리 및 이의 시공방법은 설치가 간편하고, 거푸집에 구멍을 뚫지 않고도 시공할 수 있어 거푸집의 낭비를 막을 수 있는 효과가 있다.As described above, the buried ladder according to the present invention and the construction method thereof are easy to install and can be installed without drilling holes in the formwork, thereby preventing the waste of formwork.

Claims (4)

삭제delete 콘크리트 구조물에 매립되는 매립고정대(31)에 손잡이발판(51)이 끼워져 고정되고 상기 매립고정대(31)는 연결 프레임(33)의 양단에 형성된 파이프 고정구멍 (35)에 고정 파이프(41)의 일단이 각각 끼워진 상태에서 상기 연결프레임(33)과 2개의 고정 파이프(41)가 용접되고, 상기 고정 파이프(41)내에 복수개의 그립링(43)이 각각 삽입 고정되고, 상기 고정 파이프(41)의 타단에 사각 패널(45)이 용접되는 매설사다리에 있어서,The handle scaffold 51 is inserted into and fixed to the embedding holder 31 embedded in the concrete structure, and the embedding holder 31 has one end of the fixed pipe 41 in the pipe fixing hole 35 formed at both ends of the connecting frame 33. The connecting frame 33 and the two fixing pipes 41 are welded in the fitted state, and a plurality of grip rings 43 are inserted into and fixed in the fixing pipe 41, respectively. In the buried ladder, in which the square panel 45 is welded to the other end, 상기 연결 프레임(33)은 못이 체결되는 체결구멍(37)이 형성되는 것을 특징으로 하는 매설사다리.The connecting frame 33 is a buried ladder, characterized in that the fastening hole 37 is formed to fasten the nail. 삭제delete 거푸집(71)의 내측면에 고정프레임(33)의 정면이 밀착되도록 고정프레임(33)의 체결구멍(37)에 못(49)을 박아 거푸집(71)에 고정하는 단계(S101)와, 콘크리트 (73)를 타설하여 상기 콘크리트가 양생되면 거푸집(71)을 제거하는 단계(S102)와, 노출된 고정 파이프(41)의 중공구멍(47)에 실리콘(75)을 주입하는 단계(S103)와, 상기 손잡이발판(51)을 매립고정대(31)에 삽입 고정하는 단계로 구성되는 것을 특징으로 하는 매설사다리의 시공방법.Step (S101) and nailing the nail (49) in the fastening hole (37) of the fixing frame 33 so that the front of the fixing frame 33 is in close contact with the inner side of the formwork (71), concrete Pouring the 73 and removing the formwork 71 when the concrete is cured; and injecting the silicon 75 into the hollow hole 47 of the exposed fixed pipe 41 (S103); Construction method of the buried ladder, characterized in that consisting of the step of fixing the handle scaffold (51) to the buried fixing stand (31).
KR10-2001-0047439A 2001-08-07 2001-08-07 Ladder laid a wall of construction and method of constructing thereof KR100420941B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR10-2001-0047439A KR100420941B1 (en) 2001-08-07 2001-08-07 Ladder laid a wall of construction and method of constructing thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR10-2001-0047439A KR100420941B1 (en) 2001-08-07 2001-08-07 Ladder laid a wall of construction and method of constructing thereof

Related Child Applications (1)

Application Number Title Priority Date Filing Date
KR2020010023926U Division KR200251971Y1 (en) 2001-08-07 2001-08-07 Ladder laid a wall of construction

Publications (2)

Publication Number Publication Date
KR20030013110A KR20030013110A (en) 2003-02-14
KR100420941B1 true KR100420941B1 (en) 2004-03-04

Family

ID=27718176

Family Applications (1)

Application Number Title Priority Date Filing Date
KR10-2001-0047439A KR100420941B1 (en) 2001-08-07 2001-08-07 Ladder laid a wall of construction and method of constructing thereof

Country Status (1)

Country Link
KR (1) KR100420941B1 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100440172B1 (en) * 2002-03-21 2004-07-14 변무원 Ladder
KR100581659B1 (en) * 2006-01-26 2006-05-22 주식회사 종합건축사사무소금성 Skirting board with combined solidly with a wall

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04124394A (en) * 1990-09-14 1992-04-24 Takuma Nagamatsu Divided type footholding hardware
JPH07247777A (en) * 1994-03-11 1995-09-26 Nobuo Unno Accommodation ladder trap
KR19990033876U (en) * 1998-01-05 1999-08-16 강창수 Construction sideways installation frame
KR200178047Y1 (en) * 1999-11-09 2000-04-15 주식회사에이콘 A jointing structure for pipe
KR200184655Y1 (en) * 1999-12-10 2000-06-01 박덕수 Assembly type concrete ladder

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04124394A (en) * 1990-09-14 1992-04-24 Takuma Nagamatsu Divided type footholding hardware
JPH07247777A (en) * 1994-03-11 1995-09-26 Nobuo Unno Accommodation ladder trap
KR19990033876U (en) * 1998-01-05 1999-08-16 강창수 Construction sideways installation frame
KR200178047Y1 (en) * 1999-11-09 2000-04-15 주식회사에이콘 A jointing structure for pipe
KR200184655Y1 (en) * 1999-12-10 2000-06-01 박덕수 Assembly type concrete ladder

Also Published As

Publication number Publication date
KR20030013110A (en) 2003-02-14

Similar Documents

Publication Publication Date Title
KR100420941B1 (en) Ladder laid a wall of construction and method of constructing thereof
KR200251971Y1 (en) Ladder laid a wall of construction
JP3892099B2 (en) Sleeve formwork
KR200283437Y1 (en) Fixing implement of insulation for a floor
KR200346948Y1 (en) Drainpipe fixing sleeve
KR200241684Y1 (en) Cover-con
KR200246507Y1 (en) Land reclamation type anchor for concrete structure
KR200263919Y1 (en) Base for fixing support of road facilities
KR200354116Y1 (en) The assembly ladder
KR200226684Y1 (en) panel of subway open cut structure water proofing method
KR100389535B1 (en) subway open cut structure water proofing method and panel thereby
KR100600697B1 (en) The assembly ladder
KR0129827Y1 (en) Sleeve pipe for structure piping
JP3015499U (en) Concrete pole and connecting structure of concrete pole and steel pipe
WO1994029538A1 (en) Improvements in concrete floor construction
KR200379649Y1 (en) Link fixed on the wall for Rope
KR200379650Y1 (en) Link fixed on the wall for Rope
JP2001003374A (en) Execution method of underground concrete wall using embedded form
KR200376992Y1 (en) The insert for construction work
KR200251684Y1 (en) A sleeve with joint device for architecture
KR200193191Y1 (en) Fixtures for construction angle
KR19990035241U (en) The insert installed the supporting part of an iron
KR200237781Y1 (en) Sleeve joint device for construction
KR200297984Y1 (en) Dowel bar support device for expansion joints for concrete slab
KR200210583Y1 (en) wall constructing structure for field-toilet

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20070216

Year of fee payment: 4

LAPS Lapse due to unpaid annual fee