KR100189788B1 - Method and system for the casting of anchors and mooring of platforms, and anchor casting unit for same - Google Patents

Method and system for the casting of anchors and mooring of platforms, and anchor casting unit for same Download PDF

Info

Publication number
KR100189788B1
KR100189788B1 KR1019910000536A KR910000536A KR100189788B1 KR 100189788 B1 KR100189788 B1 KR 100189788B1 KR 1019910000536 A KR1019910000536 A KR 1019910000536A KR 910000536 A KR910000536 A KR 910000536A KR 100189788 B1 KR100189788 B1 KR 100189788B1
Authority
KR
South Korea
Prior art keywords
chain
anchoring
wire rope
anchor
lowering
Prior art date
Application number
KR1019910000536A
Other languages
Korean (ko)
Other versions
KR910014585A (en
Inventor
후지따 도꾸메
Original Assignee
다 노브레가 알로이시오 펠릭스
페트롤레오 브라질레이로 에스.에이. - 페트로브라스
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 다 노브레가 알로이시오 펠릭스, 페트롤레오 브라질레이로 에스.에이. - 페트로브라스 filed Critical 다 노브레가 알로이시오 펠릭스
Publication of KR910014585A publication Critical patent/KR910014585A/en
Application granted granted Critical
Publication of KR100189788B1 publication Critical patent/KR100189788B1/en

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B21/00Tying-up; Shifting, towing, or pushing equipment; Anchoring
    • B63B21/04Fastening or guiding equipment for chains, ropes, hawsers, or the like
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B21/00Tying-up; Shifting, towing, or pushing equipment; Anchoring
    • B63B21/22Handling or lashing of anchors
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B21/00Tying-up; Shifting, towing, or pushing equipment; Anchoring
    • B63B21/50Anchoring arrangements or methods for special vessels, e.g. for floating drilling platforms or dredgers
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B21/00Tying-up; Shifting, towing, or pushing equipment; Anchoring
    • B63B21/22Handling or lashing of anchors
    • B63B2021/225Marker buoys for indicating position of an anchor, or for providing a line connection between the anchor and the water surface

Abstract

본 발명은 앵커하강크래프트를 사용하여 해상 시추 및 채유선 플랫포옴을 정박하기 위한 앵커캐스팅시스템에 관한 것이고, 앵커캐스팅시스템의 대략적인 구조는 앵커의 승강통로가 있는 데크, 체인조작용 캡스턴, 와이어로우프드럼, 데크의 밑에 설치되고 닻줄파이프에 의해 체인을 캡스턴까지 왕복이동시키는 체인적재용 로커 그리고 받침대 위에 설치되는 케이블감기용 드럼으로 이루어진다. 플랫포옴의 정박시, 각 플랫포옴체인을 이미 배치된 정박용줄에 고정한 뒤에는 정박용줄을 그의 처짐부분의 위치로 하강시킬때는 언제나 정박용줄의 미끄러짐 또는 이탈을 방지하는 하강장치와 정박용줄인양장치를 사용한다.The present invention relates to an anchor casting system for anchoring offshore drilling and oil tanker platforms using anchor lowering craft, and the general structure of the anchor casting system is a deck having a lifting passage of an anchor, a chain operating capstan, a wire rope drum. It consists of a chain loading rocker installed under the deck and reciprocating the chain to the capstan by an anchor pipe and a cable winding drum mounted on the pedestal. When anchoring the platform, after securing each platform chain to the anchoring line already placed, use the lowering device and the anchoring line lifting device to prevent the anchoring line from slipping or deviating when lowering the anchoring line to the position of its deflection.

Description

앵커 하강 크래프트와 앵커 하강방법 및 플랫포옴 정박방법Anchor descending craft, anchor lowering method and platform anchoring method

제1도는 본 발명에 의한 앵커하강크래프트의 데크의 대략적인 배치도.1 is a schematic layout view of the deck of the anchor lowering craft according to the present invention.

제2도는 크래프트 후미에 서 있는 플랫포옴의 측면도.2 is a side view of the platform standing at the rear of the craft.

제3도는 2종류의 다른 길이의 체인 또는 대기부이에 고정하기 위한 2개의 고리를 한 끝에 갖고 있는 와이어로우프가 중간부분에 설치된 정박용 줄을 나타내는 도면.3 is a view showing an anchoring line in which a wire rope having two ends at one end for fixing to two kinds of chains of different lengths or waiting sections is installed.

제4도는 정박용 와이어로우프를 위한 개선된 캡스턴드럼의 부분 정단면도.4 is a partial front sectional view of an improved capstan drum for an anchoring wire rope.

제5도는 작동중의 앵커하강크래프트 후면도.5 is an anchor descending craft rear view during operation.

제6a도 내지 제6h도, 제7도 및 제12도는 본 발명에 의한 앵커하강 단계들을 나타내는 도면.6a to 6h, 7 and 12 are views showing the anchor lowering step according to the present invention.

제13a도 내지 제13h도는 본발명에 의한 플랫포옴정박시스템의 단계들을 나타내는 도면.13A-13H illustrate the steps of a platform anchoring system according to the present invention.

제14a도 내지 제14b도는 플랫포옴정박시스템용으로 사용되는 개선된 하강장치의 정면도 및 측면도.14A-14B are front and side views of an improved lowering device for use in a platform anchoring system.

제15도는 플랫포옴정박시스템용으로 사용되는 개선된 정박용줄인양장치를 나타내는 도면.FIG. 15 shows an improved anchoring device for use with a platform anchoring system.

제16도는 제15도의 정박용 줄인양장치의 부분 단면도.FIG. 16 is a partial cross-sectional view of the anchoring device for berth 15. FIG.

제17도는 개선된 정박용 줄인양장치의 플랫포옴에의 설치방법을 나타내는 도면.FIG. 17 shows an improved method of installing the anchoring lifting device on a platform.

제18a도 내지 제18d도는 본 발명에 의한 개선된 정박용 줄인양장치의 작동법을 나타내는 도면.18a to 18d show the operation of the improved anchoring device for berthing according to the present invention.

* 도면의 주요부분에 대한 부호의 설명* Explanation of symbols for main parts of the drawings

1 : 앵커하강크래프트(anchor dropping craft) 2 : 앵커1: anchor dropping craft 2: anchor

4 : 캡스턴(capstan) 5 : 체인4 capstan 5 chain

6, 12 : 드럼 7 : 와이어로우프6, 12: drum 7: wire rope

10 : 로커(locker) 14, 32 : 부이(buoy)10: locker 14, 32: buoy

16 : 프레임 18 : 플랫포옴16: frame 18: platform

21, 22 : 고리 23 : 플랜지21, 22: ring 23: flange

24 : 홈 25 : 연장로우프24: groove 25: extended rope

26, 28, 39 : 삼중링크 27 : 블럭 도르래장치26, 28, 39: triple link 27: block pulley device

33 : 걸이로우프 38 : 판33: hanger rope 38: plate

41 : 하강장치 43 : 도르래크라운41: lowering device 43: pulley crown

49 : 정박용 줄인양장치49: anchoring device for anchoring

본 발명은 시추 및 채유를 위해 플랫포옴 위에 항상 유지되는 모든 물품을 적재하도록 특수설계된 해상 시추 및 채유선을 앵커캐스팅장치를 사용하여 정박하기 위한 앵커캐스팅시스템에 관한 것으로서, 상기 앵커 캐스팅장치는 앵커와 와이어 로우프를 미리 연속하여 캐스트할 수 있고 정박용 줄의 당김테스트를 실시할 수 있고 또 플랫포옴이 위치하면 플랫포옴 체인에 로우프를 고정할 수 있도록 설치된다.The present invention relates to an anchor casting system for anchoring an offshore drilling and oil vessel using an anchor casting device specially designed to load all articles that are always held on a platform for drilling and oiling, wherein the anchor casting device comprises anchors and wires. The rope can be cast continuously in advance, the anchoring test can be carried out, and when the platform is positioned, it is installed to secure the rope to the platform chain.

특히 수심이 깊은 곳에서 사용하고자 할 경우에 해상시추 및 채유선을 정박하는 통상의 방법은 체인과 굵은 와이어로우프를 함께 이용하는 것으로 플랫포옴에는 체인과 와이어로우프를 조작할 무거운 승강크레인과 이의 설치공간이 있어야 한다. 이 경우 보통은 최소한 8줄의 정박용 줄과 각 정박용 줄용으로 2개의 주권양기가 필요하다. 가장 많이 사용되고 있는 시스템의 몇가지 예가 프랑스 특허 제2208373호, 미국 특허 제3985093호, 제3967572호 및 제4722293호에 개시되어 있다.In particular, when deep water is to be used, the usual method of anchoring offshore drilling and oil ships is to use a chain and a thick wire rope together. The platform must have a heavy lifting crane and its installation space for manipulating the chain and wire rope. do. In this case, at least eight anchoring lines and two sowing machines for each anchoring line are required. Some examples of the most used systems are disclosed in French Patent No. 2208373, US Patent No. 3985093, No. 3767572 and No. 4762293.

가장 적합한 공지의 시스템으로는 전술한 것이 있으나 채유플랫포옴에 사용할 경우에는 중대한 결점을 갖는다.The most suitable known systems are those described above but have significant drawbacks when used in oil-plated platforms.

채유플랫포옴은 일단 정위치로 하강되고 나면 향후 10 내지 15년간은 그대로 둔다. 이는 그 설비를 늘 사용하는 것이 아니라 어쩌다 한번씩 사용하는 것을 의미하고 따라서 제작비용이 상당히 고가이다. 이러한 사실이외에도 화물선적용량의 저하, 데크공간의 손실, 다른 물품들 사이의 격실로 인한 손실 등이 있다.Once the oil platform is lowered into place, it is left for the next 10 to 15 years. This does not mean that the equipment is used all the time, but is used once in a while, so the manufacturing cost is quite expensive. In addition to this fact, there is a reduction in cargo loading capacity, loss of deck space, and losses due to compartments between other goods.

종래의 시스템에서, 체인, 와이어로우프 그리고 앵커는 플랫포옴의 데크위에 적재되고, 체인에 이미 고정된 앵커를 예인밧줄에 묶인 앵커체이서(anchor chaser)로 알려진 장치에 의해서 특수한 예인선내로 전달함으로써 하강시킨다. 이러한 전달뒤에 예인선을 플랫포옴에서 앵커가 하강할 소정의 위치로 이동시켜 체인을 잡아당기고, 플랫포옴상의 권양기는 해제된다.In conventional systems, chains, wire ropes and anchors are loaded on deck of the platform and lowered by transporting anchors already secured to the chain into special tugboats by means of an anchor chaser tied to a tow rope. After this transfer, the tugboat is moved from the platform to a predetermined position where the anchor will descend to pull the chain, and the winch on the platform is released.

소정의 길이의 체인이 풀려나간 뒤, 시스템이 연속형이 아닌 경우는 체인을 (플랫포옴상의) 강로우프에 묶고 작업을 진행하며, 이때 와이어로우프용의 캡스턴에 의해서 앵커는 유지되어야 하는 지점으로 하강하고 체이서는 철회한다. 이때문에 앵커의 중량을 이겨내고 와이어로우프와 체인의 처짐을 방지할 수 있는 매우 강력한 예인선이 필요하다.After the chain of predetermined length has been released, if the system is not continuous, the chain is tied to the steel rope (on the platform) and the work is lowered to the point where the anchor is to be maintained by the capstan for the wire rope. Chaser withdraws. This requires a very strong tug that can withstand the weight of the anchor and prevent the wire rope and chain from sagging.

종래 시스템의 큰 단점은 채유플랫포옴을 와이어로우프로 정박하기 때문에 페어리드(fairlead)를 관통하는 부분과 파도와 염분을 포함한 해풍의 피해를 가장 많이 받는 방파구역이 체인의 경우에 비해 마모, 피로 및 부식의 진행이 빨라서 유지비용이 많이 소요되고 빈번히 그것을 교체하여야 하는 점이다.A major drawback of the conventional system is that the oil platform is anchored with wire-lows, so that the parts that pass through the fairlead and the breakwater areas most affected by sea breezes, including waves and salts, wear, fatigue and corrosion compared to the chain. Because of the rapid progress of the process, maintenance costs are high and frequent replacement is required.

시추플랫포옴의 경우는 여러장소로 빈번히 옮겨야 하고 상기한 부분들의 위치지점이 수심에 따라 다르기때문에 상기 단점은 그다지 큰 문제점은 아니다.In the case of the drilling platform, the above-mentioned disadvantages are not so much of a problem because they must be frequently moved to various places and the location points of the above-described parts vary depending on the depth.

실제로 채유선을 정위치로 유지시키기 위한 이상적인 최소의 요건은 해저에서부터 윗쪽으로 앵커, 제1길이의 체인, 중간길이의 와이어로우프, 제2길이의 체인, 페어리드, 권양기 및 제2길이의 체인용 로커(locker) 등에 대한 작업으로 이루어진다. 이러한 시스템의 최대 장점은 종래의 시스템과 같이 플랫포옴을 와이어로오프 대신 체인으로 정박하여 부식 및 금속피로의 문제점이 해소되는 것이다.In practice, the ideal minimum requirement to keep oil lines in place is for anchors, chains of first length, wire ropes of medium length, chains of second length, fairleads, hoisters and chains of second length upwards from the sea floor. This is done by working with a locker. The biggest advantage of such a system is that the platform is anchored with a chain instead of wire-off like the conventional system, so that problems of corrosion and metal fatigue are eliminated.

그러나 앵커의 캐스팅과 관련한 문제점을 극복하기 위한 효과적인 수단내에 상기 시스템을 설치하는데는 종래의 방법으로는 할 수가 없다. 제안된 모든 대책은 비용이 대단히 많이 소요되고 복잡한 것으로 판명되었다.However, there is no conventional method for installing the system in an effective means to overcome the problems associated with the casting of anchors. All proposed measures proved to be very expensive and complex.

본 발명은 상기와 같은 문제점을 해소하려는 것이다.The present invention is intended to solve the above problems.

본 발명의 목적은, 플랫포옴 데크에서 하강될 앵커를 캐스트하는데 필요한 모든 기어장치를 적재할 수 있는 앵커캐스팅크래프트(anchor-casting craft)로서 모든 앵커, 체인 및 와이어로우프를 미리 데크 너머로 캐스트하고 정박용 줄의 당김테스트를 실시할 수 있고 그 뒤에 플랫포옴을 정위치로 위치시키면 와이어로우프를 채유 또는 시추 플랫포옴 체인에 고정시킬 수 있는 앵커캐스팅크래프트를 제공하는데 있다.An object of the present invention is an anchor-casting craft, which is capable of loading all the gears required to cast an anchor to be lowered from a platform deck, precast all anchors, chains and wire ropes over the deck and anchors the berth. It is possible to carry out a pull test and to place the platform in position afterwards to provide an anchor casting craft that can secure the wire rope to the oil or drilling platform chain.

본 발명에 의한 캐스팅크래프트의 대략적인 구조는 앵커승강통로가 구비된 데크, 체인조작용 캡스턴, 적당한 와이어로우프드럼, 데크의 밑에 설치되고 닻줄파이프에 의해 체인을 캡스턴과 로커사이에서 왕복이동시키는 체인적재용 로커 그리고 적당한 받침대위에 설치되는 와이어로우프적재용 드럼으로 이루어져 있다.Approximate structure of the casting craft according to the present invention is a deck equipped with an anchor lifting passage, a chain operation capstan, a suitable wire rope drum, a chain loading installed under the deck and reciprocating the chain between the capstan and the rocker by the anchor rope pipe It consists of a rocker and wire rope loading drum mounted on a suitable base.

본 발명의 다른 목적은 본 발명에 의한 캐스팅크래프트와 와이어 정박로우프 캡스턴용의 개선된 드럼을 가진 신속하고 효율적인 앵커하강시스템을 제공하는데 있다.Another object of the present invention is to provide a fast and efficient anchor lowering system having an improved drum for casting craft and wire anchoring rope capstan according to the present invention.

본 발명의 또 다른 목적은 플랫포옴체인을 이미 하강된 정박용 줄에 묶은 뒤에 처짐위치로 하강할때 언제나 미끄러짐 또는 이탈을 완전히 방지하는 개선된 하강장치와 개선된 정박용 줄 인양장치를 갖는 플랫포옴정박시스템을 제공하는데 있다.Another object of the present invention is a platform anchoring system having an improved lowering device and an improved anchoring line lifting device that completely prevents slipping or slipping when the platform chain is tied to an already lowered anchoring line and then lowered to a deflection position. To provide.

본 발명의 그 밖의 목적, 특징, 장점은 도면을 참조한 상세한 설명으로부터 용이하게 이해될 것이다.Other objects, features, and advantages of the present invention will be readily understood from the detailed description with reference to the drawings.

이하 본 발명에 대해서 상세하게 설명한다.Hereinafter, the present invention will be described in detail.

본 발명은 해상 시추 및 채유선 플랫포옴의 데크상에 항상 놓여있는 모든 기어장치를 지지하는 해상 시추 및 채유선의 정박에 사용하는 앵커하강크래프트로 구성되며, 상기 크래프트는 앵커, 체인 및 와이어로우프를 미리 상기 데크너머로 캐스트할 수 있고 정박용 줄의 당김테스트를 실시할 수 있고 또 그 뒤에 플랫포옴이 정위치로 위치하면 플랫포옴체인에 상기 와이어로우프를 고정할 수 있도록 설치된다.The present invention comprises an offshore drilling and anchoring craft used for anchoring of offshore drilling and oiler, which supports all gear devices which are always on the deck of the offshore drilling and oiler platform, wherein the craft pre-contains anchors, chains and wire ropes in advance. The cast can be cast over the deck, and a pulling test of the anchoring string can be performed, and when the platform is placed in the correct position, the wire rope is fixed to the platform chain.

제1도는 하강크래프트(1)의 데크(deck)에 대한 대략적인 배치도이고, 그 위에 승강통로(3) 내의 앵커(2), 체인(5)용 캡스턴(4) 및 모터(9)와 구동부(8)에 의해 작동하는 와이어로우프(7)용의 개량된 2개의 드럼(6)이 있다. 체인(5)은 크래프트의 데크 아래쪽에 설치된 로커(10)에 적재되고 닻줄파이프(11)를 따라 캡스턴(4)과 로커(10) 사이를 왕복한다. 상기 닻줄파이프는 동력으로 로커(10) 안으로 용이하게 복귀할 수 있다. 와이어 로우프(7)는 받침대(13)에 설치된 적재용 드럼(12) 상에 감겨있고, 드럼에는 캡스턴(4)의 드럼(6) 상에 감긴 로우프(7)를 하강시킬때는 풀고 반대로 정박시킬때는 당기거나 교환시킬 수 있는 동력구동식 브레이크와 페어리드(제1도에는 도시안됨) 등의장치가 있다.FIG. 1 is a schematic layout view of the deck of the descending craft 1, on which the anchor 2 in the lifting passage 3, the capstan 4 for the chain 5 and the motor 9 and the driving unit (1). There are two improved drums 6 for the wire rope 7 operated by 8). The chain 5 is loaded into the rocker 10 installed below the deck of the craft and reciprocates between the capstan 4 and the rocker 10 along the anchor line pipe 11. The anchor pipe can be easily returned into the rocker 10 with power. The wire rope 7 is wound on the loading drum 12 installed in the pedestal 13, and the drum is loosened when the rope 7 wound on the drum 6 of the capstan 4 is lowered. There are devices such as power-driven brakes and fairleads (not shown in Figure 1) that can be pulled or exchanged.

드럼(6)과 적재용드럼(12)의 용량은 대형이므로 로우프를 길게 풀 수 있고 서로 연결하면 더 길게 풀 수 있다.Since the capacity of the drum 6 and the loading drum 12 is large, the ropes can be loosened for a long time and connected to each other for longer.

주부이(chief buoy)(14)는 하우징(15)에 하강되며, 더 작고 더 가벼운 부이, 앵커 및 앵커웨이트를 크리브(crib) 또는 특수받침대내에 둘 수도 있다. 기어장치를 데크상에서 더 용이하게 이동시키기 위해서 가동 트랙이 설치된 크레인을 제공할 수 있다.The chief buoy 14 is lowered in the housing 15 and may place smaller and lighter buoys, anchors and anchorweights in a crib or special pedestal. Cranes with movable tracks can be provided to move the gear arrangement more easily on the deck.

제2도와 같이, 프레임(16)은 거어더(girder)를 그의 전장에 걸쳐 지지하고 이 거어더를 따라 필요한 모든 도르래와 도르래장치가 설치되어 있다.As shown in FIG. 2, the frame 16 supports the girder over its entire length and is provided with all the necessary pulleys and pulleys along the girder.

크래프트(19)의 후미에 설치된 플랫포옴(18)은 레일(20) 위에서 이동하며, 로우프와 체인을 고정하거나 분리할때 마다 동력을 받아 크래프트 후미에 따른 임의의 위치에서 그것들을 감을 수 있다. 플랫포옴에는 작동을 돕는 체인 및 와이어로우프용의 쐐기부가 형성될 수 있다.The platform 18 installed at the rear of the craft 19 moves on the rails 20 and can be powered at any time along the tail of the craft to receive power each time the rope and chain are secured or removed. The platform may be formed with wedges for chain and wire rope to aid operation.

제1도 및 제2도와 관련한 상기 설명은 본 발명의 크래프트의 일예로서, 이 크래프트는 그의 폭을 설계에서 채택할 수 있기 때문에 부양부의 데크상에 설치되어 작동을 더 용이하게 하지만 여타 종류의 크래프트를 채용할 수도 있다.The above description with respect to FIGS. 1 and 2 is an example of the craft of the present invention, which is installed on the deck of the buoyant to facilitate operation, although its width can be adopted in the design, but it is easier to operate other types of craft. It is also possible to employ.

이러한 대책의 주장점은 기존의 크래프트를 사용할 수 있고 약간의 변경도 가능한 동시에, 목적하는 시스템이 8개의 적재용 캡스턴과 8개의 와이어로우프 감기 캡스턴을 데크에 필요로 하지 않게 되는 점을 고려하면 권양기 및 여타 교정물의 비용을 포함하여 그러한 변경에 소요되는 비용이 각각의 반잠수식 채유선 플랫포옴의 건조시에 절약되는 비용보다 더 적다는 것이다.The assertion of these measures is that the existing craft can be used and minor modifications can be made, while the desired system does not require eight loading capstans and eight wire-rope winding capstans on the deck. The cost of such a change, including the cost of other calibrations, is less than the cost saved for drying each semi-submersible oiler platform.

여타 종류의 플랫포옴을 정박할 수 있는 이점이외에 다른 이점은 다음과 같다.In addition to the benefits of anchoring other types of platforms, other benefits include:

a) 연료보급을 위해 기지로 복귀하면서도 계속 작동할 수 있다.a) continue to operate while returning to base for refueling;

b) 하강된 정박용 줄에 대한 당김테스트를 실시할 수 있다.b) A pull test may be performed on the lowered berth.

c) 정박용 줄에 대한 검사 및/또는 교체가 가능하다.c) inspection and / or replacement of berths.

d) 피기백(piggyback)과 중간부이를 정박용 줄용으로 사용할 수 있다.d) Piggybacks and middle buoys may be used for berths.

e) 통상의 예인선을 사용할 수 있다.e) Usable tugs can be used.

f) 크래프트 자체를 화물조작 설비가 통상적으로 갖추어진 공장에 속하는 규정의 선창 등에 설치하여 운반 및 적재용으로 사용하므로 공급기지에서 필요로 하는 기어 및 장비의 조작이 필요없고 주문 제작된 품목들을 포함하기 때문에 일단의 조작에 대한 적절한 기술적 축적이 필요없다.f) The craft itself is used for transportation and loading by installing in a dock of a regulation belonging to a factory equipped with a cargo handling facility, so that it does not require the operation of gears and equipment required at the supply base and includes customized items. Therefore, there is no need for proper technical accumulation of a set of operations.

제3도에서, 앵커하강시스템을 다룰때 더 설명하겠지만 정박용줄의 중앙부분에 있는 와이어로우프의 양끝에는 2종류의 길이가 다른 체인 또는 대기부이에 고정하기 위한 고리(21, 22)가 형성되어 있다.In Fig. 3, as will be described further when dealing with the anchor lowering system, at both ends of the wire rope in the center of the anchoring row, loops 21 and 22 are formed for fixing to two kinds of chains or waiters of different lengths. .

와이어로우프(7)가 하강된 뒤 캡스턴드럼에 감길때까지 고리(22)는 나중에 고정될 것에 대비하여 크래프트의 후미에 있는 작업플랫포옴상에 놓여 있어야 한다. 그러나 고리의 치수뿐 아니라, 와이어가 드럼에 감길때 먼저 몇번 감긴 부분 위에 하강되는 고정부속품의 치수 역시 일정한 규격으로 되어있기 때문에 고리(22)의 상기와 같은 하강은 로우프의 연장부(예컨대 굵기가 가는 연장부)에 의해서 불가능하며, 이는 균일하지 못하게 감기는 원인이 되고 이로 인해 압착 및 꼬임에 의해 손상됨으로써 와이어로우프의 수명이 치명적인 수준에 이르게 된다.The ring 22 must rest on the working platform foam at the rear of the craft in preparation for later fixing until the wire rope 7 is lowered and wound around the capstan drum. However, not only the dimensions of the loop, but also the dimensions of the fixing accessories, which are lowered on the first few times when the wire is wound on the drum, are also of a certain standard, so that the above-described lowering of the ring 22 is not necessary for the extension of the rope (e.g. Extension), which causes uneven winding and can be damaged by crimping and twisting, resulting in a deadly life of the wire rope.

제4도와 같이, 정박용 와이어로우프의 캡스턴에는 홈(24)이 형성된 중간부의 플랜지(23)에 의해 두 부분(보조부분 (A)와 주부분 (B))으로 분할된 개선된 드럼이 설치되어 있고, 상기 홈(24)은 와이어로우프(7)를 보조부분 (A)와 주부분 (B) 사이에서 지지한다. 보조부분은 로우프를 덜 지지하며 주부분 (B)의 허브의 폭보다 더 좁은 허브를 갖고 있다. 이러한 허브의 직경차로 인해 주부분 (B)의 허브 직경과 같은 직경으로 될때까지 보조부분에 감기는 굵기가 가는 연장로우프 (25)를 적재할 수 있으므로 꼬일 위험성은 완전히 배제하게 된다.As shown in FIG. 4, the capstan of the anchoring wire rope is provided with an improved drum divided into two parts (auxiliary part (A) and main part (B)) by a flange 23 of an intermediate part in which a groove 24 is formed. The groove 24 supports the wire rope 7 between the auxiliary portion (A) and the main portion (B). The secondary part supports the rope less and has a hub that is narrower than the width of the hub of the main part (B). Due to the difference in diameter of the hub, it is possible to load the thinner extension rope 25 wound on the auxiliary part until it becomes the same diameter as the hub diameter of the main part (B), thereby completely eliminating the risk of twisting.

따라서, 주로우프(7)는 하강된 뒤 주부분 (B)에서 보조부분 (A)로 이동하고 거기서 주부분 (B)의 외측에 놓여 있는 삼중링크(26)와 여타 기존의 부속품에 의해 연장로우프(25)에 고정되며, 이로인해 고리(22)가 작업플랫포옴으로 전달된다. 이 모든 이유때문에 모든 적재용 드럼(12)의 형태는 동일하여야 한다.Thus, the main hoop 7 is lowered and then moved from the main part B to the auxiliary part A, where it is extended by a triple link 26 and other existing accessories which lie outside the main part B. It is fixed to (25), whereby the ring 22 is transferred to the working platform. For all these reasons the shape of all loading drums 12 should be identical.

미리 하강된 앵커하강시스템의 경우, 대기부이를 먼저 하강하여 정박하여야 하며 대기부이의 임무는 플랫포옴이 제자리에 이를때까지 수면에서 하강된 정박용 줄의 끝 또는 그 끝에 이르는 와이어의 끝을 파지하는 것이다.In the case of a preloaded anchor lowering system, the waiting buoy must be lowered and anchored first, and the job of the waiting buoy is to grasp the end of the lowered anchoring line or the end of the wire from the surface until the platform is in place. .

부이용 정박수단의 하강은 앵커의 경우에 대해서 후술하는 바와 동일하게 행해지며, 부이의 수량과 형태의 선택은 후술할 것이다.The lowering of the buoyant anchoring means is performed in the same manner as described later with respect to the case of the anchor, and the selection of the quantity and form of the buoy will be described later.

앵커는 후술하는 정박용 줄의 당김테스트를 할 수 있도록 중간지점에 대해 서로 대략 마주보게 쌍쌍이 하강된다.The anchors are lowered in pair pairs to face each other about the mid-point so that the anchoring test of the anchoring line will be described later.

본 발명에서 앵커를 하강시키는 방법이 제5도 및 제12도에 도시되어 있다. 제5도와 같이 앵커(2)를 가장 먼저 체인(5)의 끝에 고정되어 있는 앵커(2)의 승강통로 밖으로 이동시켜 블럭 도르래장치(27)에 의해서 체인용 캡스턴(4)의 앞으로 가져간다. 이때 앵커(2)의 중량은 체인(5)으로 이동하고 블럭 도르래장치(27)가 해제되어(제6a도) 데크를 넘어가 하강체인(5)을 출발시킨다(제6b도). 하강될 체인(5)의 길이는 특수한 삼중링크(28)(제6c도)가 작업 플랫포옴(18)(제5도)의 가장자리에 도달할 때에 기구는 물론 눈으로도 측정되고, 이때 와이어로 우프(7)의 고리(21)를 체인에 고정시킨다.The method of lowering the anchor in the present invention is shown in FIGS. 5 and 12. As shown in FIG. 5, the anchor 2 is first moved out of the hoistway of the anchor 2 fixed to the end of the chain 5 and brought to the front of the chain capstan 4 by the block pulley device 27. As shown in FIG. At this time, the weight of the anchor 2 moves to the chain 5 and the block pulley device 27 is released (FIG. 6a), goes beyond the deck, and starts the descending chain 5 (FIG. 6B). The length of the chain 5 to be lowered is measured not only by the instrument but also by the eye when the special triple link 28 (FIG. 6C) reaches the edge of the working platform 18 (FIG. 5), in which case the wire loop The hook 21 of (7) is fixed to the chain.

와이어로우프(7)를 드럼(6)에 고정한 뒤, 초과된 길이의 체인[연장부(29)]이 체인(5)의 중량을 와이어로우프(7)로 이동시키기 위해 하강되고(제6d도), 상기 고정된 부분은 연장부(29)를 체인에서 이탈시키기 위해 플랫포옴(18)의 레벨까지 상승된다(이때 와이어로우프드럼과 함께 상승). 작동이 계속하여 현재 와이어로우프(7)는 하강되어 있고 이미 하강된 정박용 줄(체인 및 로우프)의 전장은 앵커(2)가 해저에 도달할때까지 조정된다(제6e도). 이때 하강크래프트(1)는 소정의 정박지점의 지지부 위에 놓여야 한다. 그리고나서 크래프트(1)는 플랫포옴의 예정위치쪽으로 이동하고(제6f도), 그 동안에 삼중링크(26)(제6g도-제6h도)가 대기부이에 고정될 플랫포옴(18)의 레벨로 있을때까지 체인(5)과 로우프(7)를 해저로 하강시켜 놓는다.After fixing the wire rope 7 to the drum 6, the chain of excess length (extension 29) is lowered to move the weight of the chain 5 to the wire rope 7 (Fig. 6D). The fixed portion is raised to the level of the platform 18 to lift the extension 29 out of the chain (which then rises with the wire rope drum). Operation continues and the current wire rope 7 is lowered and the overall length of the anchoring row (chain and rope) already lowered is adjusted until the anchor 2 reaches the seabed (Fig. 6e). At this time, the descending craft 1 should be placed on the support of the predetermined anchoring point. The craft 1 then moves towards the predetermined position of the platform (Fig. 6f), during which the triple link 26 (Figs. 6g-6h) is at the level of the platform 18 to be fixed to the atmosphere. Lower the chain (5) and rope (7) to the sea floor.

이러한 고정작용은 2종류의 방법으로 실시될 수 있다. 즉 첫번째로는 제7도와 같이, 로우프(7) 자체(고용량의 독립부이이며 하강루트에 미리 하강되는) 부이(31)에서 매달려 있는 로우프(30)에 직접 고정하는 것이고, 두번째로는 제8도와 같이 와이어로우프(7)를 해저에 내려놓고 연결부이의 일종인 부이(32)에 직경이 작고 가벼운 걸이로우프(33)로 고정하는 것이다.This fixing can be carried out in two ways. In other words, firstly, as shown in FIG. 7, the rope 7 itself (a high-capacity independent buoy and previously lowered in the lowering route) is directly fixed to the rope 30 suspended from the buoy 31. Like this, the wire rope 7 is placed on the seabed and fixed to the buoy 32, which is a kind of connection part, with a small and light hook rope 33.

두번째의 방법에서, 플랫포옴의 한쪽에 있는 앵커용의 모든 걸이로우프(33)는 부이(32)에 고정될 수 있으며(이러한 경우는 정박용 줄의 루트를 지나서 미리 놓일 수 있음), 또한 플랫포옴을 정위치로 가져갈때 표적으로서도 사용될 수 있다. 두 부이들 (32) 간의 고정[고정부분(34)]은 당김테스트에 영향을 주지 않도록 하강작업이 끝난 후에 실시되며, 플랫포옴을 정위치로 정박시킨 후에는 해제된다.In the second method, all hook ropes 33 for anchors on one side of the platform can be secured to buoys 32 (in this case they can be pre-set past the root of the anchoring row), and also the platform is fixed. It can also be used as a target when taken to a location. The fixing between the two buoys 32 (fixing part 34) is carried out after the lowering operation is completed so as not to affect the pulling test, and is released after the platform is anchored in place.

와이어로우프가 하강된 뒤에 크래프트는 제9도와 같이 대기부이에서 일정한 거리로 떨어져 있게 된다.After the wire rope is lowered, the craft is spaced a certain distance away from the atmosphere as shown in FIG.

부이(31)를 하강 크래프트(1) 근처로 가져가고, 보조캡스턴으로 로우프(35)를 밀어서 예인선으로 부이에 고정시킨다. 여기서 부이(31)는 일단 도달한 뒤에는 크래프트(1)에 정박되고 보조권양기는 해제된다. 그리고 나서 보조캡스턴 또는 블럭 도르래장치(37)(제10도)에 의해서 로우프(30)를 건 부이(31)의 연장부(37)(체인)의 삼중링크(26)를 작업 플랫포옴(18)의 레벨로 가져가고 체인의 연장부(29)를 고정하여 권양기(4) 에 의해서 로우프(30)를 건 부이의 판(38)을 플랫포옴(18)의 레벨로 가져가 로우프(7) 의 삼중링크(26)에 고정시킨다(제11도). 이 절차는 걸이로우프가 (해저에 놓인 주로우프와 함께) 부이에 대한 고정용으로 사용되는 경우이라면 동일하다.Bring the buoy 31 near the descending craft 1 and push the rope 35 with the auxiliary capstan to secure it to the buoy with a tugboat. Here, the buoy 31 is once anchored in the craft 1 and the auxiliary winch is released. Then, the triple link 26 of the extension portion 37 (chain) of the buoy 31 to which the rope 30 is hung by the auxiliary capstan or the block pulley device 37 (FIG. 10) of the working platform 18 Take the level and fix the extension 29 of the chain to take the plate 38 of the buoy, which has hung the rope 30 by the winch 4, to the level of the platform 18, thereby bringing the triple link of the rope 7 26) (FIG. 11). This procedure is the same if the hang rope is used to secure the buoy (with the main woofer placed on the seabed).

부이에의 고정이 완료된 후, 중량을 이동시키고 연장부들을 이탈시키는 절차가 로우프(7)를 부이(31)에 걸어매달고 걸이로우프의 연장부(37)를 부이에 고정시킬때까지 속행된다. 하강작업의 종료상태가 제12도에 도시되어 있다.After the fixing to the buoy is completed, the procedure of moving the weight and releasing the extensions is continued until the rope 7 is hung on the buoy 31 and the extension 37 of the hang rope is fixed to the buoy. The end state of the lowering operation is shown in FIG.

모든 쌍의 대향하는 정박용 줄이 하강된 뒤 정박용 줄을 서로에 대해 기설정된 힘으로 하강 크래프트 권양기로 당기면서 정박테스트를 실시하여야 한다. 이 정박테스트는 두번째 정박용 줄을 놓으면서 1쌍의 첫번째 정박용 줄을 대기부이 위로 직접 정박시킴으로써 실시된다. 두번째의 정박용 줄을 놓을 때 그 끝을 동일한 두께와 길이의 로우프(제2드럼)에 고정하여 전술한 바와 같이 작동을 속행하며, 이번의 다른 로우프는 첫번째의 정박용 줄의 대기부이용으로 놓이는 것이다. 첫번째의 정박용 줄은 도달한 후에는 권양기의 체인연장부에 고정되고 부이는 해제된다.After all pairs of berths have been lowered, the berth test is to be carried out while pulling the berths with the down-kraft hoist with a predetermined force against each other. The anchoring test is carried out by anchoring the first pair of berths directly over the waiting area while releasing the second berth. When the second anchoring line is laid, its end is fixed to a rope of the same thickness and length (second drum) to continue operation as described above. This other rope is used as a standby for the first anchoring line. will be. After the first berth is reached, it is fixed to the chain extension of the winch and the buoy is released.

한편 크래프트는 복귀하면서 로우프를 집어 올려 체인을 하강시킨 후에 앞서 고정된 지점으로 간다. 체인을 고정하고 로우프캡스턴을 두번째 정박용 줄위로 당기면서 첫번째 당김테스트를 하고, 그런 다음 제동을 가하여 드럼을 권양하고 두번째 정박용 줄을 첫번째 정박용 줄의 캡스턴으로 설정된 힘이 나올때 까지 당기며, 테스트를 하는데 필요한 시간동안 그 상태를 유지시킨다.Meanwhile, the craft returns, picks up the rope, lowers the chain, and goes to a fixed point. Secure the chain, pull the rope capstan over the second anchoring line, perform the first pull test, then brake to winch the drum, and pull the second anchoring line until the force set to the capstan of the first anchoring line is tested. Keep that state for as long as necessary.

당김테스트를 종료시키려면, 먼저 (당김력을 줄이기 위해) 체인을 이완시키고 나서 로우프를 이완시킴으로써 정박용 줄의 당김력을 완화시킨다. 그 다음 단계로 체인을 집어 올리는 동시에 와이어로우프를 (다시) 첫번째 정박용 줄의 끝에 까지 하강하고 나서 체인을 풀고 로우프를 부이에 직접 또는 걸이로우프로 묶는다. 그뒤 크래프트가 두번째 정박용 줄의 끝에 도달할때까지 보조로우프를 집어 그의 대기부이에 묶는다.To end the pull test, first relax the chain (to reduce the pull) and then relax the rope to relieve the pull of the berth. The next step is to pick up the chain and at the same time lower the wire rope (again) to the end of the first berth, then loosen the chain and tie the rope directly to the buoy or hook rope. Then pick up the secondary rope and tie it to his wait until Kraft reaches the end of the second berth.

제13a도 내지 제13h도에 플랫포옴 정박절차가 도시되어 있다. 먼저 하강 크래프트가 체인 캡스턴에 의해서 처리될 정박용 줄을 대기부이(제13a도)에서 집어 올리고 보조로우프를 그 정박용 줄(제13b도)에 고정시킨다. 크래프트는 플랫포옴으로 이동하면서 보조로우프를 하강시키고(제13c도) 플랫포옴 근방에서 하강 크래프트체인에 고정되는 체인의 제2부분의 끝을 잡고, 삼중링크(39)(제13d도)를 2개의 체인들이 만나는 곳으로 도입한다. 플랫포옴에 고정하는데 이용할 수 있는 정도의 길이로 체인이 하강한 뒤 그와 동시에 크래프트는 하강된 보조로우프를 집어올리기 시작하고, 그곳에서 로우프는 작업플랫포옴(18)에 있는 정박용 줄과 만나며, 이때 드럼은 고정된다(제13e도 및 제13f도).A platform anchoring procedure is shown in FIGS. 13A-13H. First, the descent craft picks up the anchoring row to be processed by the chain capstan from the waiting section (Fig. 13a) and fixes the auxiliary rope to the anchoring row (Fig. 13b). The craft moves down to the platform and lowers the secondary rope (Figure 13c), grabs the end of the second part of the chain that is secured to the descending craft chain near the platform, and the triple link 39 (Figure 13d) We introduce to place to meet. At the same time the chain descends to the length available to secure it to the platform, the craft then picks up the lower auxiliary rope, where the rope meets the anchoring line in the working platform (18), where the drum Is fixed (Figs. 13E and 13F).

체인의 길이가 아주 짧은 경우는 합류지점에 도달하도록 보조로우프를 더 많이 잡아 당기면 된다.If the chain is very short, you can pull more auxiliary ropes to reach the confluence.

제13g도에 도시된 단계에서, 체인과 와이어로우프의 삼중링크(39, 26)는 각각 거의 같은 레벨로 놓여 짧은 길이의 체인(40)에 의해서 본 분야에 공지된 블럭 도르래장치 또는 여타 수단에 의해 유지된 하강장치(41)와 함께 서로 고정되어서, 정박용 줄의 처짐부분의 레벨까지 내려갈때까지 고정된 정박용 줄의 하강을 돕는다 (제13h도). 이를 위해 일단 고정된 뒤에는 체인과 로우프의 중량이 하강장치(41)로 이동하고 삼중링크들(39, 26)은 크래프트 체인과 보조로우프에서 후퇴한다. 또 크래프트체인과 보조로우프는 하강장치(41)에 고정되고 하강장치는 그것을 지지하고 있는 수단에서 해제되며, 이때는 중량이 보조로우프로 이동한다.In the step shown in Fig. 13g, the triple links 39 and 26 of the chain and the wire rope are each placed at about the same level, and by means of a block pulley device or other means known in the art by the chain 40 of short length. It is fixed together with the retaining lowering device 41 to assist the lowering of the fixed anchoring string until the level of the deflection portion of the anchoring string is lowered (Fig. 13h). To this end, once secured, the weight of the chain and the rope moves to the lowering device 41 and the triple links 39 and 26 retreat from the craft chain and the auxiliary rope. In addition, the craft chain and the auxiliary rope are fixed to the lowering device 41 and the lowering device is released from the means supporting the lowering device.

정박용 줄은 도달하여 처질때까지 하강하고 하강장치(41)는 되돌아온다.The berth is reached and lowered until it sag and the lowering device 41 returns.

하강시에 있어서, 하강장치는 정박용 줄이 급작스럽게 당겨져 정박용 줄의 중량으로 인해 플랫포옴과 캡스턴에 심각한 손상을 줄 수 있는 정박용 줄의 미끄러짐 및/또는 이탈을 방지한다. 그러나, 이러한 기능은 파지된 정박용 줄의 미끄러짐을 방지할 수 있는 고정장치를 전혀 갖추고 있지 않은 기존의 체이서(chaser)로는 수행될 수 없다.On lowering, the lowering device prevents the berth from slipping and / or leaving the berth as it is pulled out abruptly, which can seriously damage the platform and capstan due to the weight of the berth. However, this function cannot be performed with an existing chaser that is not equipped with any fasteners that can prevent slippage of the gripping anchoring row.

제14a도 및 제14b도에는 제13g도에서 설명한 본 발명의 하강장치(41)의 세부가 작동을 위해 도시되어 있다. 하강장치는 지지기부(42)와 스핀들(44)에 의해 지지기부(42)에 끼워지는 도르래크라운(43)으로 이루어진다. 크라운(43) 옆쪽의 플랜지들에는 가용성로우프(46)(2개만 도시함) 용의 안내부 역할을 하는 슬롯(45)이 있고, 상기 로우프는 한 끝에서 스핀들(44)에 설치된 안내부(48)와 떨어져 있는 중간부의 공동돌출부 (47)에 고정되고, 다른 끝에서 체인의 링크들을 크라운(43)에 여러 각도로 묶을 수 있는 각각의 터버클(turbuckle)에 고정된다. 따라서 정박용 줄이 처짐부분의 지점으로 하강함에 따라 크라운(43)에 감겨진 체인은 크라운(43)에서 가장 먼저 이동해가는 처짐부분의 최상부쪽에서 흩어지려고 하는 경향이 있다. 가용성 로우프의 크기는, 체인이 유지되기는 하나 유지된 링크가 크라운에서 이동하기 시작할 때 정박용 줄의 중량을 이겨내지 못하도록 되어 있다. 따라서 최종의 가용성 로우프가 끊어졌을 때 정박용 줄은 실제로 처짐부분의 지점에 도달할 것이고 개선된 하강장치(41)의 미끄러짐은 플랫포옴 또는 캡스턴에 아무런 손상을 주지않게 된다.14A and 14B, details of the lowering device 41 of the present invention described in FIG. 13G are shown for operation. The lowering device is composed of a pulley crown 43 fitted to the support base 42 by the support base 42 and the spindle 44. On the flanges beside the crown 43 there is a slot 45 which serves as a guide for the fusible rope 46 (only two are shown), the rope having a guide 48 mounted to the spindle 44 at one end. ), And at the other end to the respective turbuckle, which can tie the links of the chain at various angles to the crown 43 at the other end. Therefore, as the anchoring line descends to the point of the deflection portion, the chain wound around the crown 43 tends to be scattered at the top of the deflection portion that moves first in the crown 43. The size of the fusible rope is such that the chain is maintained but not able to withstand the weight of the berth when the retained link begins to move in the crown. Thus, when the last fusible rope breaks, the berth will actually reach the point of deflection and the improved sliding of the lowering device 41 will not damage the platform or capstan.

정박용 줄의 일부를 정기적인 체크 또는 교체할때 마다 통상적인 절차에는 앵커의 변위가 필요하며, 이는 앵커체이서에 의해서 실행되고, 그후 플랫포옴으로 부터 정박용 줄을 필요한 길이대로 당기면 된다. 이렇게 하는데에는 실제로 나중에 정박용 줄을 재비치할 수 있을 정도로 상당히 강하게 잡아당겨야 하는 몇가지 단점이 있으며, 로우프를 교체하는 경우에는 더욱 그렇다.Whenever part of the anchoring line is regularly checked or replaced, the usual procedure requires displacement of the anchor, which is carried out by the anchor chaser, and then pulls the anchoring line to the required length from the platform. There are a few drawbacks to doing this, in fact that you have to pull it very strong enough to be able to reload the berth later, especially if you are replacing the rope.

본 발명에 따른 시스템에서와 같이 정박용 줄을 미리 하강시킨 경우, 정박용 줄을 플랫포옴체인의 제2부분이 와이어로우프(정박용 줄의 중간부분)와 연결되는 곳으로 올림으로써 더 간단하게 하강장치(1)로 동일한 작업을 할수 있으며, 이 경우에는 제15 도 및 제16도에 도시된 개선된 정박용 줄인양장치(49)가 사용된다. 정박용 줄을 그러한 지점에서 풀고 체인을 플랫포옴 위에 놓고 강하게 잡아당기면서 미리 하강된 부분은 하강크래프트로 집어 올린다. 플랫포옴체인(제2부분)을 포함하여 정박용 줄부분들은 체인을 하강 크래프트의 데크에 적재한 채로 연속적으로 교체될 수 있다.When the anchoring line is lowered in advance as in the system according to the present invention, the lowering device is more simply lowered by raising the anchoring line to a place where the second part of the platform chain is connected to the wire rope (middle part of the anchoring line). The same work can be done with (1), in which case the improved anchoring device 49 shown in FIGS. 15 and 16 is used. Loosen the berth at such a point, place the chain on the platform and pull it up strongly while picking up the pre-descent part with the descending craft. Anchoring strings, including the platform chain (second part), can be replaced continuously with the chain loaded on the deck of the descending craft.

정박용 줄인양장치(49)는 체이서의 상단절반부에 있는 체이서의 몸체(52)를 관통하는 스핀들(51)로 정위치로 유지된 도르래크라운(50), 체인위에서 슬라이드 운동하는 도립된 홈형태이고 보강된 부분에 있는 승강아이부(hoisting eye)(53), 안내부의 역할을 하는 벌어진 앞부분(54), 그리고 체인과 동시에 한 링크만이 통과하는 노즐모양의 뒷부분(55)으로 이루어진다.The anchoring lifting device 49 is a pulley crown 50 held in place by a spindle 51 penetrating through the body 52 of the chaser in the upper half of the chaser, and an inverted groove shape that slides on the chain. And it consists of a hoisting eye 53 (hoisting eye) 53 in the reinforcement part, a gaping front part 54 serving as a guide, and a nozzle-shaped rear part 55 through which only one link passes simultaneously with the chain.

제17도와 같이, 정박용 줄인양장치(49)는 플랫포옴의 부상레벨로 놓여있는 펜더(fender)(56) 밑에서 플랫포옴체인(제2부분)에 끼워져 걸이로우프(57)로 플랫포옴에 고정된다.As shown in FIG. 17, the anchoring device for anchoring 49 is fitted to the platform chain (second part) under the fender 56, which is placed at the floating level of the platform, and fixed to the platform by the hook rope 57. As shown in FIG.

인양장치를 사용하기 위해서, 걸이로우프(57)를 플랫포옴 근처에 놓여있는(크레인에 의해서) 하강 크래프트로 이동시켜 그 위에서 캡스턴의 주드럼의 와이어로우프에 고정하며, 그것과 함께 합류지점에 이를때까지 하강시킨다. 인양장치(49)가 하강함에 따라 하강 크래프트는 로우프를 인양장치(49) 위에서 수직 방향으로 하기 위해 정박용 줄의 루트를 따라 이동한다. 노즐모양의 뒷부분(55)이 첫번째 고정된 부분의 삼중링크 (39)(제18a도)에 도달하면 인양장치는 상승을 위해 정위치로 있게 된다. 크래프트는 그의 루트를 따라 계속 이동하여 인양장치(49)를 처짐부분의 가장 낮은 쪽으로 밀수 있는 위치에 도달하여야 하고(제18b도), 이때 정박용 줄을 상승시킬때 홈이 올라가 체인을 감고 도르래크라운(50) 안으로 끼운다(제18c도).To use the lifting device, the hanger rope 57 is moved to the descending craft (by crane) near the platform and secured thereon to the wire rope of the capstan's main drum until it reaches the confluence point. Lower As the lifting device 49 descends, the lowering craft moves along the root of the anchoring row to bring the rope vertically above the lifting device 49. When the nozzle-shaped rear part 55 reaches the triple link 39 (FIG. 18a) of the first fixed part, the lifting device is in the correct position for ascending. The craft must continue to move along its route to reach a position where it can push the lifting device 49 to the lowest point of the deflection (Fig. 18b), where the groove rises and winds up the chain as the berth is raised. (50) Insert into (Figure 18c).

삼중링크(39)는 수면에 도달하면 하강크래프트의 체인(또는 연장부)에 고정되며, 정박용 줄의 중량이 크래프트로 이동된다. 인양장치(49)는 그것을 유지하는 블럭 도르래장치 또는 여타수단에 직접 고정되고, 인양장치의 로우프는 풀리어 삼중링크(26) 에 묶이며, 체인부분(40)은 미리 놓여진 와이어로우프와 연결된다(제18c도). 그런 다음 체인부분(40)은 풀리어 크래프트에 놓여져, 전술한 절차의 역절차인 미리 놓여진 정박용 줄을 플랫포옴에 고정하기 위한 절차의 경우는 플랫포옴상의 체이서와 함께 체인의 끝으로 되돌아간다. 그런다음 크래프트가 놓여진 로우프를 잡으면서 플랫포옴 근처로 가서 회수될 미리 놓여진 로우프의 끝을 두번째 주드럼의 연장로우프와 묶어 이동시켜서(주드럼은 비워진다) 회수작업을 시작한다. 이후의 모든 작업은 플랫포옴에 고정된 정박용줄을 처짐부분의 레벨로 하강시키는 것을 포함하여 전술한 바와 같이 반복된다.When the triple link 39 reaches the water surface is fixed to the chain (or extension) of the descending craft, the weight of the anchoring line is moved to the craft. The lifting device 49 is directly fixed to the block pulley device or other means for holding it, the rope of the lifting device is tied to the pulley triple link 26, and the chain portion 40 is connected to the wire rope laid in advance ( 18c). The chain portion 40 is then placed on the pulley kraft, and in the case of the procedure for securing the pre-placed anchoring string to the platform, which is the reverse of the above procedure, returns to the end of the chain with the chaser on the platform. Then, while holding the rope on which the craft is placed, go to the platform and begin the recovery operation by moving the end of the pre-placed rope to be recovered with the extension rope of the second main drum (the drum is empty). All subsequent work is repeated as described above, including lowering the anchoring string secured to the platform to the level of the deflection.

본 발명을 바람직한 실시예에 대해서만 설명하였으나, 본 발명의 다수 변경예도 가능한 것이며 이러한 변경예도 본 발명에 속하는 것이다.Although the present invention has been described only with respect to preferred embodiments, many modifications of the invention are possible and such modifications also belong to the invention.

Claims (14)

데크상에 드럼(6) 및 부이(14)를 위한 공간(15)을 포함하는 앵커하강크래프트 (1)에 있어서, 플랫포옴을 정박하는데 필요한 모든 물품을 배에 적재할 수 있고, 상기 크래프트는 앵커용 승강통로가 있는 데크, 체인(5) 조작용 캡스턴(4), 닻줄파이프(11)에 의해 캡스턴(4)과 로커(10) 사이를 왕복이동하는 체인(5)을 적재하기 위해 데크의 밑에 설치된 로커(10) 및 와이어로우프(7)를 적재하기 위하여 받침대(13)에 장착된 드럼 (12)을 포함하며, 또한 모든 앵커(2), 체인(5) 및 와이어로우프(7)를 미리 연속적으로 하강하여 정박용 줄의 당김테스트를 실시한 뒤에 위치조정단계동안 와이어로우프를 채유 및 시추플랫포옴의 체인에 고정할 수 있는 것을 특징으로 하는 앵커하강크래프트.In the anchor lowering craft (1) comprising a space (15) for the drum (6) and the buoy (14) on the deck, all the goods necessary for anchoring the platform can be loaded onto the ship, the craft for anchors. Deck with lifting path, installed under the deck to load the chain 5 reciprocating between the capstan 4 and the rocker 10 by the capstan 4 for operating the chain 5 and the anchor pipe pipe 11 A drum 12 mounted to the pedestal 13 for loading the rocker 10 and the wire rope 7, and in advance all the anchors 2, the chain 5 and the wire rope 7 in advance. An anchor lowering craft characterized in that the wire rope can be fixed to a chain of oil and drilling platform during the positioning step after the lowering and pulling test of the anchoring line. 제1항에 있어서, 상기 와이어로우프(7)를 정박하기 위한 드럼(12)은 동력으로 작동되며, 작동의 하강단계에서 와이어로우프(7)를 캡스턴의 드럼(6)에 전달하고 또한 정박용 와이어로우프를 들어 올리거나 교체할때 역절차를 수행할 수 있도록 제동부 및 안내부가 설치되어 있는 것을 특징으로 하는 앵커하강크래프트.The drum 12 for anchoring the wire rope 7 is powered by power, which transfers the wire rope 7 to the drum 6 of the capstan and also the anchoring wire in the descending stage of operation. Anchor lowering craft, characterized in that the brake and the guide is installed to perform the reverse procedure when lifting or replacing the rope. 제1항 또는 제2항에 있어서, 상기 와이어로우프(7)를 정박하기 위한 캡스턴(4) 은 로우프가 한 부분에서 다른 부분으로 지나가는 홈(24)이 있는 플랜지(23)에 의해서 분리된 보조부분 (A)과 주부분 (B)으로 형성된 2개의 드럼(6)으로 이루어지고, 용량이 작은 보조부분 (A)은 주부분 (B) 보다 작은 직경의 허브를 가지며, 이 직경차는 보조부분 (A)의 허브가 주부분 (B)의 허브의 직경과 같아질 때까지 보조부분 (A)의 허브에 감겨지는 굵기가 가는 연장와이어로우프를 적재하도록 의도되는 것을 특징으로 하는 앵커하강크래프트.3. The secondary part according to claim 1 or 2, wherein the capstan (4) for anchoring the wire rope (7) is separated by a flange (23) with grooves (24) through which the rope passes from one part to another. The auxiliary portion (A), which is composed of two drums (6) formed of (A) and the main portion (B), has a hub having a diameter smaller than that of the main portion (B), and the diameter difference is the auxiliary portion (A). Anchor lowering craft, characterized in that it is intended to load a thin, elongated wire rope wound around the hub of the auxiliary part (A) until the hub of the main part (B) is equal to the diameter of the hub of the main part (B). 제3항에 있어서, 상기 주와이어르우프(7)는 주부분 (B)에 있는 드럼(6)의 허브의 표면의 반경방향 레벨과 동일한 반경방향 레벨로 상기 플랜지(23)의 홈(24)을 지나가는 것을 특징으로 하는 앵커하강크래프트.4. The groove 24 of the flange 23 according to claim 3, wherein the main wire loop 7 is at the same radial level as the radial level of the surface of the hub of the drum 6 in the main part B. Anchor descent craft, characterized in that passing by. 제3항에 있어서, 하강종료시 상기 주와이어로우프(7)는 주부분 (B)에서 보조부분 (A)으로 이동하여 작업플랫포옴(18)으로 상기 주와이어로우프를 운반할 상기 연장와이어로우프에 고정되는 것을 특징으로 하는 앵커하강크래프트.4. The main wire rope (7) according to claim 3, wherein at the end of the descent the main wire rope (7) is fixed to the extension wire rope to move from the main part (B) to the auxiliary part (A) and to carry the main wire rope to the work platform (18). Anchor descent craft, characterized in that. 작업플랫포옴(18), 하강될 앵커용 승강통로, 체인길이부, 와이어로우프(7) 용 드럼(6), 체인 캡스턴(4), 감겨진 와이어로우프(7)를 적재하는 드럼(12), 부이(14, 31, 32) 및 블럭 도르래장치(27)를 포함하고 상기 부이는 하강 정박용 줄(7)의 끝, 플랫포옴이 정위치에 도달할때까지 상기 정박용 줄(7)의 끝에 묶이는 걸이 와이어로우프(30)를 수면에서 집어 올리는 앵커하강크래프트(1)에 의해서 수행되는 앵커하강방법에 있어서,제1길이의 체인(5)의 끝에 이미 고정된 승강통로내의 앵커(2)를 블럭 도르래장치(27) 에 의해서 체인캡스턴(4) 앞의 위치로 이동시키는 단계, 앵커의 중량을 제1길이의 체인 (5)으로 이동시켜 블럭 도르래장치를 해제하고 나서 제1길이의 체인을 하강시키는 단계, 체인(5)에 고정되고 와이어로우프(7)의 고리(21)가 번갈아 고정될 제1삼중링크(28) 의 도달을 작업플랫포옴 레벨에서 검출함으로써 하강될 제1길이의 체인의 길이를 확인하는 단계, 상기 고정후 와이어로우프드럼(6)이 제동되면, 체인의 중량을 와이어로우프로 이동시킬 목적으로 다른 길이부(29)의 체인을 하강시키고, 다른 길이(29)의 체인을풀어놓기 위해 와이어로우프드럼(6)에 의해서 상기 작업 플랫포옴(18)의 레벨까지 고정부를 상승시키는 단계, 앵커(2)가 해저에 도달할 때까지 이미 하강된 줄(체인과 와이어로우프)의 전체 길이를 제어하면서 와이어로우프를 하강시키고, 이때 하강크래프트 (1)를 앵커(2)가 놓여 있게 될 지점 윗쪽에 위치시키는 단계, 하강크래프트(1)를 작업플랫포옴의 예정위치쪽으로 이동시키면서, 삼중링크(39)가 대기부이(31)에 고정될 작업플랫포옴(18)의 레벨에서 나타날때까지 체인과 와이어로우프를 해저로 낙하 또는 하강시키는 단계, 부이를 하강크래프트 근처로 가져가고, 예인선에 의해서 크래프트 상의 보조 드럼 (A)으로부터 와이어로우프를 잡아당겨 상기 부이(31)에 묶는 단계, 부이가 일단 도달한 후에는 하강크래프트에 고정하고 보조 드럼 (A)을 풀어 놓는 단계, 부이(31) 의 걸이 와이어로우프(30)의 고정판(38)을 이 판(38)에 고정되는 제2삼중링크(26)용 작업플랫포옴까지 가져가기 위하여 부이의 걸이 와이어로우프연장부(37) 및 체인의 삼중링크(39)를 작업플랫포옴(18)까지 가져가 연장부에 고정시키는 단계, 및 와이어로우프(7)가 부이에 의해서 부이에 고정된 걸이 와이어로우프 연장부(37)로 지지될 때까지 중량을 이동시키고 연장부를 풀어 놓는 단계로 이루어진 것을 특징으로 하는 앵커하강방법.Work platform 18, lifting path for anchor to be lowered, chain length part, drum 6 for wire rope 7, chain capstan 4, drum 12 for loading wound wire rope 7, buoy 14, 31, 32 and a block pulley device 27, the buoys being hung at the end of the lower anchoring row 7, at the end of the anchoring row 7 until the platform has reached the correct position. In the anchor lowering method performed by the anchor lowering craft (1) for picking up the wire rope (30) from the water surface, a block pulley device is provided for anchoring (2) in the lifting path already fixed at the end of the chain (5) of the first length. Moving the weight of the anchor to the chain 5 of the first length by releasing the block pulley device, and then lowering the chain of the first length by (27); Of the first triple link 28 fixed to the chain 5 and to which the hooks 21 of the wire rope 7 are alternately fixed. Confirming the length of the chain of the first length to be lowered by detecting the arrival at the working platform level, and when the wire rope drum 6 is braked after fixing, another length (for the purpose of moving the weight of the chain to the wire rope) Lowering the chain of 29) and raising the fixture by the wire rope drum 6 to the level of the working platform 18 to release the chain of another length 29, the anchor 2 being attached to the seabed. Lower the wire rope while controlling the overall length of the already lowered rope (chain and wire rope) until it is reached, placing the lower craft (1) above the point where the anchor (2) will be placed. While moving (1) toward the intended position of the work platform, drop the chain and wire rope down to the sea floor until the triple link 39 appears at the level of the work platform 18 to be secured to the atmosphere 31. Or lowering, bringing the buoy near the descending craft, pulling the wire rope from the auxiliary drum (A) on the craft by tug and binding it to the buoy 31, and once the buoy reaches, it is fixed to the descending craft. And releasing the auxiliary drum A, in order to take the fixing plate 38 of the hook wire rope 30 of the buoy 31 to the work platform for the second triple link 26 fixed to the plate 38. Take the hook wire rope extension portion 37 of the buoy and the triple link 39 of the chain to the working platform 18 to fix it to the extension, and the hanger wire of which the wire rope 7 is fixed to the buoy by the buoy. Anchor lowering method, characterized in that consisting of the step of moving the weight until the support is extended to the rope (37) and releasing the extension. 제6항에 있어서, 상기 삼중링크(39)의 대기부이로의 고정은 와이어로우프 자체로부터 부이의 걸이 와이어로우프(30) 상으로 직접 실시되는 것을 특징으로 하는 앵커하강방법.7. A method according to claim 6, characterized in that the fixing of the triple link (39) to the atmospheric buoy is carried out directly from the wire rope itself onto the hook wire rope (30) of the buoy. 제6항에 있어서, 상기 삼중링크(39)의 대기부이로의 고정은 와이어로우프를 해저에 충분히 하강시키고 굵기가 가는 걸이 와이어로우프(25)에 의한 공통부이에 와이어로우프를 정박시킴으로써 실시되는 것을 특징으로 하는 앵커하강방법.The method of claim 6, wherein the fixing of the triple link (39) to the atmospheric section is performed by lowering the wire rope sufficiently to the seabed and anchoring the wire rope to the common part by the hook wire rope (25). Anchor lowering method. 제8항에 있어서, 모든 걸이 와이어로우프(7)는 하강작업이 완료한 뒤에 두 부이 (14, 32) 사이에 정박하는 부이에 정박되고, 작업플랫포옴을 정위치에 정박한 뒤에 제거하는 것을 특징으로 하는 앵커하강방법.9. The hook wire rope (7) according to claim 8, characterized in that all the hook wire ropes (7) are anchored in buoys anchored between two buoys (14, 32) after the lowering operation is completed, and the work platform is anchored in place and then removed. Anchor lowering method. 제6항 내지 제9항중 어느 한 항에 있어서, 상기 앵커하강작업은 그 위치의 중간 지점(34)에 대하여 서로 대칭하여 쌍을 이루고 있는 앵커(2)에 의해 실시되는 것을 특징으로 하는 앵커하강방법.10. A method according to any one of claims 6 to 9, wherein the anchor lowering operation is performed by anchors (2) symmetrically paired with each other with respect to the intermediate point (34) of the position. . 앵커하강크래프트(1)에 의해서 실시되는 풀랫포옴 정박방법에 있어서, 상기 방법은 정박용 줄을 수용하고 있는 복수의 대기부이를 상기 앵커하강크래프트를 통하여 작업플랫포옴(18)의 미리 정해진 하강위치 근처에서 회수하고 상기 앵커하강크래프트 (1) 상의 체인캐스턴(4)을 사용하여 상기 부이로부터 그 정박용 줄을 제거하고, 그리고 상기 정박용 줄의 제1삼중링크(39)에 상기 앵커하강크래프트에 의해서 실시된 보조와이어로우프를 고정하는 단계, 앵커하강크래프트를 작업플랫포옴쪽으로 이동시키면서 보조와이어로우프를 하강시키고, 작업플랫포옴에 대향 끝이 연결된 제2길이의 체인(5) 의 자유단부를 작업플랫포옴 근처에서 집어 올리고, 제2삼중링크(26)에 의해서 상기 앵커하강크래프트의 제3길이의 체인에 제2길이의 체인을 연결하는 단계, 보조와어어로우프와 정박용 줄사이의 연결부에서 제1삼중링크(28)가 상기 앵커하강크래프트의 작업플랫포옴의 레벨로 상승할 때까지 앵커하강크래프트상의 드럼으로 보조와이어로우프를 잡아 당기고 나서 앵커하강크래프트상의 보조와이어로우프용 드럼을 정지시키는 단계,앵커하강크래프트상의 블럭 도르래장치에 의해서 유지된 하강장치(41)에 끼워 맞춤된 짧은 길이의 체인에 의해서 보조와이어로우프로 유지된 정박용 줄의 끝에서 제1삼중링크에 작업플랫포옴의 제2길이의 체인(5)과 앵커하강크래프트에 연결된 제3길이의 체인사이의 연결부에서 제2삼중링크(26)를 고정하고 정박용 줄의 중량을 상기 블럭 도르래장치(27)로 전달하는 단계, 및 작업플랫포옴의 제2길이의 체인에 연결된 제2삼중링크로부터 앵커하강크래프트의 제3길이의 체인을 풀고, 정박용 줄의 끝에서 제1삼중링크로부터 보조와이어로우프를 풀어 하강장치에 보조와이어로우프를 연결하고, 블럭 도르래장치로부터 하강장치(41)를 해제하고, 작업플랫포옴의 제2길이의 체인에 연결된 정박용 줄을 구비한 하강장치를 보조와이어로우프로 정박용 줄의 처짐부분의 레벨에 대응하는 해저깊이로 낮추고, 하강장치로부터 짧은 길이의 체인 및 정박용 줄의 해제후 하강장치를 회수하는 단계로 이루어지며, 상기 복수의 대기부이는 각각이 앵커(2), 상기 앵커에 한쪽 끝이 연결된 제1길이의 체인(5), 상기 제1길이의 체인의 대향 끝에 한쪽 끝이 연결된 와이어로우프(7) 및 상기 와이어로우프(7)의 대향 끝과 대기부이에 연결된 펜던트체인사이에 연결된 제1삼중링크(28)로 이루어지고, 상기 하강장치(41)는 지지기부(42)와 스핀들(44)에 의해 상기 지지기부내로 끼워지는 도르래크라운(43)으로 구성되며, 상기 크라운은 그의 양측부에 있는 플랜지에 슬롯(45)을 가지고, 상기 슬롯은 한쪽 끝이 스핀들에 설치된 중간부의 안내부(48)와 떨어져 있는 공동돌출부(47) 내에 고정되고 다른쪽 끝이 체인의 링크들을 상기 크라운에 여러 각도로 묶을 수 있는 각각의 터버클에 고정된 가용성 로우프(46)용 안내부 역할을 하는 것을 특징으로 하는 플랫포옴 정박방법.In the method of anchoring the full-latfoam anchoring carried out by the anchor lowering craft (1), the method includes placing a plurality of waiting portions containing the anchoring rope near the predetermined lowering position of the working platform (18) through the anchor lowering craft. Recover and remove the anchoring string from the buoy using the chain caster 4 on the anchor lowering craft 1, and by the anchor lowering craft on the first triple link 39 of the anchoring string. Securing the carried out auxiliary wire rope, moving the anchor lowering craft toward the work platform, and lowering the auxiliary wire rope, and picking up the free end of the chain 5 of the second length connected to the work platform in the vicinity of the work platform. Connecting the chain of the second length to the chain of the third length of the anchor lowering craft by the second triple link 26; At the connection between the jaw wire rope and the anchoring rope, the auxiliary triple rope 28 is pulled by the drum on the anchor down craft until the first triple link 28 ascends to the level of the working platform of the anchor down craft, and then on the anchor down craft. Stopping the drum for the auxiliary wire rope, the first at the end of the anchoring line held by the auxiliary wire rope by a short length chain fitted to the lowering device 41 held by the block pulley device on the anchor lowering craft; At the connection between the chain 5 of the second length of the working platform and the chain of the third length connected to the anchor descending craft on the triple link, the second triple link 26 is fixed and the weight of the anchoring string is determined by the block pulley device ( 27) and unwinding the chain of the third length of the anchoring craft from the second triple link connected to the chain of the second length of the working platform, At the end of the anchoring line, loosen the auxiliary wire rope from the first triple link, connect the auxiliary wire rope to the lowering device, release the lowering device 41 from the block pulley device, and anchor the connected wire to the chain of the second length of the working platform. Lowering the lowering device with the rope to the seabed depth corresponding to the level of the deflection of the anchoring line with the auxiliary wire row, and recovering the lowering device after the release of the short chain and anchoring line from the lowering device Each of the plurality of waiting parts includes an anchor 2, a chain 5 of a first length having one end connected to the anchor, a wire rope 7 having one end connected to an opposite end of the chain of the first length, and The first triple link 28 is connected between the opposite end of the wire rope (7) and the pendant chain connected to the standby portion, the lowering device 41 is supported by the support base 42 and the spindle 44 G Consisting of a pulley crown 43 fitted into the base, the crown having slots 45 on the flanges on both sides thereof, the slots having a cavity spaced apart from the guide 48 of the intermediate part installed at the spindle. A platform anchoring method characterized in that it serves as a guide for a fusible rope (46) secured in a projection (47) and the other end secured to each of the turbines that can tie the links of the chain at various angles to the crown. 제11항에 있어서, 임의의 정박용 줄에 대한 정기적인 검사 또는 교체를 위하여 앵커(2)는 하강크래프트(1)에 의해서 변위되며, 상기 정박용 줄은 플랫포옴의 체인의 제2부분을 와이어로우프(중간부분)에 고정시 정박용 줄인양장치(49)에 의해 상승되는 것을 특징으로 하는 플랫포옴 정박방법.12. The anchoring rope according to claim 11, wherein the anchoring (2) is displaced by the descending craft (1) for regular inspection or replacement of any anchoring rope, which anchors the second portion of the chain of platform. The platform anchoring method, characterized in that is lifted by the anchoring device (49) for anchoring when fixed to (middle part). 제12항에 있어서, 상기 정박용 줄인양장치(49)는 상하 뒤집힌 홈의 형태로 보강된 부분에서 몸체를 관통하는 스핀들에 의해 고정된 도르래 크라운(50), 체인을 안내하기 위해 더 벌어져 있는 앞부분(54), 그리고 체인의 삼중링크가 통과하지 못하게 하는 안내노즐과 정지부를 갖는 뒷부분(55)으로 구성된 것을 특징으로 하는 플랫포옴 정박방법.13. The pulley crown (50) according to claim 12, wherein the anchoring lifting device (49) is a pulley crown (50) secured by a spindle penetrating the body in a portion reinforced in the form of an upside-down inverted groove, a further opening portion for guiding the chain. (54), and a platform anchoring method comprising a rear portion (55) having a guide nozzle and a stop for preventing the triple link of the chain from passing. 제12항 또는 제13항에 있어서, 상기 정박용 줄인양장치(49)는 플랫포옴의 부양레벨로 놓이고 걸이로우프(57)에 의해 플랫포옴에 고정되는 펜더(56) 밑에서 플랫포옴체인의 제2부분에 놓여 있는 것을 특징으로 하는 플랫포옴 정박방법.14. The anchoring lifting device (49) according to claim 12 or 13, wherein the anchoring rope lifting device (49) is placed in the flotation level of the platform and is attached to the second portion of the platform chain under the fenders (56) secured to the platform by the hook rope (57). A platform anchoring method, characterized in that lying.
KR1019910000536A 1990-01-15 1991-01-15 Method and system for the casting of anchors and mooring of platforms, and anchor casting unit for same KR100189788B1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
BRP19000135 1990-01-15
BR909000135A BR9000135A (en) 1990-01-15 1990-01-15 ANCHOR LAUNCHING SYSTEM AND PLATFORM MOORING AND ANCHOR LAUNCHING UNIT

Publications (2)

Publication Number Publication Date
KR910014585A KR910014585A (en) 1991-08-31
KR100189788B1 true KR100189788B1 (en) 1999-06-01

Family

ID=4048731

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1019910000536A KR100189788B1 (en) 1990-01-15 1991-01-15 Method and system for the casting of anchors and mooring of platforms, and anchor casting unit for same

Country Status (11)

Country Link
US (1) US5522336A (en)
EP (3) EP0438258B1 (en)
JP (1) JP2562235B2 (en)
KR (1) KR100189788B1 (en)
BR (1) BR9000135A (en)
CA (1) CA2032609A1 (en)
DE (3) DE69128256D1 (en)
DK (2) DK0438258T3 (en)
ES (2) ES2105479T3 (en)
FI (1) FI101280B1 (en)
NO (2) NO307292B1 (en)

Families Citing this family (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2304319B (en) * 1995-08-15 1997-10-22 Gec Alsthom Ltd Method and apparatus for paying out, securing and hauling in a flexible elongate tensile member
US5779226A (en) * 1996-03-15 1998-07-14 Wudtke; Donald J. Anchoring system
US6019058A (en) * 1997-06-19 2000-02-01 Fmc Corporation Looped mooring line and method of installation
US6095075A (en) * 1998-10-09 2000-08-01 Leslea C. Gordon Retractable boat line
US6325010B1 (en) 2000-03-29 2001-12-04 Power Vent Technologies, Inc. Method of vessel propulsion with coordinated bow propulsion
EP1283158A1 (en) * 2001-08-06 2003-02-12 Single Buoy Moorings Inc. Anchor line installation method and connector for use in said method
CA2397926C (en) * 2002-09-11 2004-08-24 Leslea C. Gordon Retractable mooring line device
US7036601B2 (en) 2002-10-06 2006-05-02 Weatherford/Lamb, Inc. Apparatus and method for transporting, deploying, and retrieving arrays having nodes interconnected by sections of cable
NO324808B1 (en) 2005-03-22 2007-12-10 Advanced Prod & Loading As Mooring system
US7543800B2 (en) * 2006-08-01 2009-06-09 W.W. Patterson Company Single stack manual marine winch
NO337497B1 (en) * 2013-02-15 2016-04-25 Gva Consultants Ab Waste fluid discharge system and method
SE538099C2 (en) * 2013-04-12 2016-03-01 Bassoe Technology Ab A mooring system
CN103482514B (en) * 2013-09-27 2015-12-09 捷胜海洋装备股份有限公司 towing winch
CN103482515B (en) * 2013-09-27 2016-03-09 捷胜海洋装备股份有限公司 There is the towing winch of guide roller
CN103616173B (en) * 2013-11-27 2016-03-30 江苏科技大学 A kind of auxiliary pulling force car of tension tester
KR101598694B1 (en) * 2014-05-21 2016-02-29 대우조선해양 주식회사 Stern structure of ship having a mooring device and drill-ship having the same
CN110481708B (en) * 2019-09-26 2024-04-02 东营鑫奥船舶设备制造有限公司 Ship anchor bracket
CN112548523B (en) * 2020-11-27 2021-10-29 江苏科技大学 Manipulator anchor chain crosspiece positioning device and working method
CN112937760B (en) * 2021-01-29 2023-06-20 中海石油(中国)有限公司深圳分公司 Mooring large cable friction chain anti-drop device and method

Family Cites Families (23)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB471562A (en) * 1900-01-01
US3111926A (en) * 1961-12-07 1963-11-26 Shell Oil Co Apparatus for anchoring underwater vessels
GB1178067A (en) * 1967-08-24 1970-01-14 Atlas Mak Maschb G M B H A Hauling Drum of a Winch
FR2208373A5 (en) 1972-11-24 1974-06-21 Neptune Forages En Mer
NO132826C (en) * 1974-03-05 1976-01-14 Skipskonsulent As
US3967572A (en) 1974-08-13 1976-07-06 Santa Fe International Corporation Anchoring system and chain stopper therefor
US3931782A (en) * 1974-09-26 1976-01-13 Ocean Drilling & Exploration Company Mooring method for deployment and retrieving of mooring lines
US3985093A (en) 1975-04-30 1976-10-12 Armco Steel Corporation Chain-wire rope anchoring systems and anchoring systems and connectors therefor
US3995577A (en) * 1976-01-16 1976-12-07 Gentry Hermond G Marine device retrieving apparatus
US4020779A (en) * 1976-05-19 1977-05-03 Skagit Corporation Chain/wire rope connector assembly for anchor
US4348975A (en) * 1979-11-21 1982-09-14 Dove Peter G S Supply boat spooling system
DE3043755A1 (en) * 1980-11-20 1982-05-27 Blohm + Voss Ag, 2000 Hamburg PERMANENT ANCHORING OF FLOATING CONSTRUCTIONS
US4513681A (en) * 1981-09-29 1985-04-30 The Crosby Group, Inc. Wire rope to chain connector for anchoring systems
NL8105294A (en) * 1981-11-23 1983-06-16 Haak Rob Van Den METHOD FOR TENSIONING AN ANCHOR LINE, IN PARTICULAR FOR TESTING AN ANCHOR, AND AN APPARATUS FOR IMPLEMENTING THE METHOD INCLUDING, IN PARTICULAR, A CABLE OR CHAIN TENSIONER.
US4430023A (en) * 1981-12-17 1984-02-07 Exxon Production Research Co. Rope guiding device
US4476801A (en) * 1982-09-13 1984-10-16 John T. Hepburn Limited Mooring device
DE3248717A1 (en) * 1982-12-31 1984-07-05 Blohm + Voss Ag, 2000 Hamburg Method and device for lowering a star-shaped anchorage for floating structures in deep water
US4509448A (en) * 1983-10-13 1985-04-09 Sonat Offshore Drilling Inc. Quick disconnect/connect mooring method and apparatus for a turret moored drillship
CA1240308A (en) 1984-10-25 1988-08-09 Hepburn (John T.), Limited Integrated winch and windlass
NL8500719A (en) * 1985-03-13 1986-10-01 Haak Rob Van Den DEVICE FOR THE RELEASE AND LIGHTING OF ANCHORS.
CA1278224C (en) * 1985-05-10 1990-12-27 John T. Hepburn, Limited Anchoring system for floating structure
FR2594406A1 (en) * 1986-02-20 1987-08-21 Technip Geoproduction Device for rapid casting off and recovery of a mooring especially for an oil platform
US4878452A (en) * 1987-02-10 1989-11-07 Amca International Corporation Quick-release mooring apparatus for floating vessels

Also Published As

Publication number Publication date
NO307292B1 (en) 2000-03-13
DK0653349T3 (en) 1997-09-29
EP0612655B1 (en) 1997-11-19
DE69128256D1 (en) 1998-01-02
NO311881B1 (en) 2002-02-11
EP0612655A2 (en) 1994-08-31
ES2080245T3 (en) 1996-02-01
CA2032609A1 (en) 1991-07-16
DE69114868D1 (en) 1996-01-11
US5522336A (en) 1996-06-04
FI910170A0 (en) 1991-01-11
FI101280B (en) 1998-05-29
NO910152D0 (en) 1991-01-14
JP2562235B2 (en) 1996-12-11
KR910014585A (en) 1991-08-31
DE69126894D1 (en) 1997-08-21
JPH04212691A (en) 1992-08-04
EP0612655A3 (en) 1994-11-09
EP0653349B1 (en) 1997-07-16
BR9000135A (en) 1991-10-08
NO910152L (en) 1991-07-16
EP0438258A3 (en) 1991-11-27
DE69114868T2 (en) 1996-07-04
ES2105479T3 (en) 1997-10-16
EP0438258A2 (en) 1991-07-24
NO983400D0 (en) 1998-07-23
FI101280B1 (en) 1998-05-29
EP0438258B1 (en) 1995-11-29
DE69126894T2 (en) 1998-02-19
DK0438258T3 (en) 1996-02-26
EP0653349A1 (en) 1995-05-17
FI910170A (en) 1991-07-16
NO983400L (en) 1991-07-16

Similar Documents

Publication Publication Date Title
KR100189788B1 (en) Method and system for the casting of anchors and mooring of platforms, and anchor casting unit for same
US7044685B2 (en) Method of installation of a tension leg platform
EP2379404B1 (en) A method and apparatus for supporting a load
US10577056B2 (en) Mooring pulley tensioning system
US3842776A (en) Anchoring system
US3967572A (en) Anchoring system and chain stopper therefor
US4020779A (en) Chain/wire rope connector assembly for anchor
US20110278520A1 (en) Method and device for handling of rope
KR102050614B1 (en) Traction system for operating lines of a vessel
KR20110118805A (en) Method and device for hoisting an item by means of a crane
US6893190B2 (en) Method and structure for connecting a floating structure with rope anchor lines to the seabed
EP3251942B1 (en) Mooring pulley tensioning system
AU2001291717A1 (en) Method and structure for connecting a floating structure with rope anchor lines to the seabed
US4414911A (en) Berth for mooring supply ship to an offshore platform and for transferring personnel between them
KR20240022037A (en) Floating jig and method for installing support structure of offshore wind power generator using the same
SU500114A1 (en) Device for lowering and lifting heavy boats and other floating objects

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20011113

Year of fee payment: 6

LAPS Lapse due to unpaid annual fee