JPS63103112A - Steel jacket quaywall - Google Patents

Steel jacket quaywall

Info

Publication number
JPS63103112A
JPS63103112A JP24703986A JP24703986A JPS63103112A JP S63103112 A JPS63103112 A JP S63103112A JP 24703986 A JP24703986 A JP 24703986A JP 24703986 A JP24703986 A JP 24703986A JP S63103112 A JPS63103112 A JP S63103112A
Authority
JP
Japan
Prior art keywords
jacket
sheet pile
sheet
members
steel jacket
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP24703986A
Other languages
Japanese (ja)
Inventor
Senji Yamaguchi
山口 銑治
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Steel Corp
Original Assignee
Kawasaki Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kawasaki Steel Corp filed Critical Kawasaki Steel Corp
Priority to JP24703986A priority Critical patent/JPS63103112A/en
Publication of JPS63103112A publication Critical patent/JPS63103112A/en
Pending legal-status Critical Current

Links

Abstract

PURPOSE:To stabilize a quaywall at great water depth by a method in which auxiliary holding members are attached in parallel to the inside of a horizontal brace facing the water side of a steel jacket, and sheet piles are set between the vertical parallel members to fix them to the bottom ground under water. CONSTITUTION:Sheet pile-holding auxiliary members 16 are set in parallel on the inside of a brace on the water side of a steel jacket consisting of jacket legs 15a and horizontal braces 15b, and a sheet pile 17 is set between the members 16 and 15b. The assembled jacket is vertically lifted up on a predetermined place and settled on a given place of the seabed ground. Steel tubular piles are driven through the legs 15a to a given position into the ground and the sheet pile 17 is driven to a given setting position. The back side of the jacket 15 is embedded with soil and reinforced concrete is placed to the top of the jacket 15 as needed. The quaywall at great water depth can thus be stabilized.

Description

【発明の詳細な説明】 「産業上の利用分野」 この発明は、水底若しくは海底地盤上に設置された鋼製
ジャケットを矢板施工時の仮設材とすると共に施工後は
矢板安定用の永久構造材とした岸壁に関する。
[Detailed Description of the Invention] "Industrial Application Field" This invention uses a steel jacket installed on the bottom of the water or on the seabed ground as a temporary material during the construction of sheet piles, and after construction as a permanent structural material for stabilizing the sheet piles. Regarding the quay.

「従来の技術」 矢板で山止めしてなる岸壁は矢板を安全に支持できるよ
うに設計されるもので従来の矢板式岸壁としては第13
図axdに示されるものが存在する。
``Conventional technology'' The quay made of sheet piles is designed to safely support the sheet piles.
There are those shown in Figure axd.

すなわち i)通常の矢板式(a図)であって、前面に鉛直な矢板
1を打ち込み、背面を土砂2aで部分的に埋立てた後、
タイロッド3及び控え壁4を施工し、残りの埋立て2b
を完成するもの。
That is, i) It is a normal sheet pile type (Figure a), after driving a vertical sheet pile 1 in the front and partially filling in the back with earth and sand 2a,
Construct tie rods 3 and buttresses 4, and reclaim the remaining 2b
something that completes.

ii )自立矢板式(b図)で、前面に鉛直な鋼管矢板
5を打ち込み、背面を土砂6で埋立てたもの。
ii) A self-supporting sheet pile type (Figure b) with vertical steel pipe sheet piles 5 driven into the front and the back filled with earth and sand 6.

iii )斜め控え杭矢板式(0図)で、通常の矢板式
(a図)におけるタイロッド3の代りに斜杭7を矢板8
背面に打設し、矢板8頭部と斜坑7頭部を連結して組杭
とし、矢板8の水平変位を拘束するもの。
iii) In the diagonal pile sheet pile type (Fig. 0), the diagonal piles 7 are used instead of the tie rods 3 in the normal sheet pile type (Fig. a).
The pile is driven on the back side, and the 8 head of the sheet pile and the 7 head of the inclined shaft are connected to form a set of piles, and the horizontal displacement of the sheet pile 8 is restrained.

iv)二重矢板式(d図)で、矢板9.10を間隔をお
いて2列に打ち、2列の矢板頭部相互をタイロッド11
でつなぎ、この内部に土砂12などを充堪したもの。
iv) In the double sheet pile type (Fig. d), sheet piles 9 and 10 are set in two rows at intervals, and the two rows of sheet pile heads are tied together with tie rods 11.
The inside is filled with earth and sand 12.

以上a w d図の岸壁に於いて、岸壁上に加わる荷重
による矢板1天端の水側への傾倒は、a図にあっては、
タイロッド3及び控え壁4のバックアンカー効果により
阻止しており、b図にあっては、tA管矢板50大なる
自立剛性をもってバックアンカー材を不要として阻止し
ており、C図にあっては斜杭7がバンクアンカーとなっ
て阻止しており、d図にあってはタイロッド11及び矢
板10のバックアンカー効果により阻止している。
Above, on the quay shown in Figure a w d, the tilting of the top of the sheet pile 1 toward the water side due to the load applied to the quay is as follows in Figure a.
This is prevented by the back anchor effect of the tie rods 3 and buttresses 4, and in figure B, the tA pipe sheet pile 50 has great self-supporting rigidity, making the back anchor material unnecessary and prevented, and in figure C, it is prevented that the back anchor material is unnecessary. The piles 7 act as bank anchors to prevent this, and in Figure d, the tie rods 11 and the sheet piles 10 act as back anchors to prevent this.

「発明が解決しようとする問題点」 しかるに、叙上のものはいずれも岸壁完成後、矢板に発
生する応力及び変位の制約をうけて、a図のものでは水
深Ion程度以浅、b図のものでは5〜6m以浅、C図
のものでは6〜7m以浅、d図のものでは10m以浅0
海水域に限定される。
``Problems to be solved by the invention'' However, in all of the above cases, due to the constraints of stress and displacement that occur in the sheet piles after the quay is completed, the problem in figure a is shallower than the water depth of about Ion, and the figure in figure b is shallower than about Ion. In Figure C, it is shallower than 5 to 6 m, in Figure C, it is shallower than 6 to 7 m, and in Figure d, it is shallower than 10 m.
Restricted to seawater.

また、矢板の施工に先立って、ガイド等の仮施工をほど
こす必要があり、a図のものにあっては、タイロッド及
び控え壁が完成するまで埋立てができないので海上施工
期間が長い、矢板打ち込み後裏込め及び控え壁のない状
態では波浪に対して弱い等の難点があり、b図のものに
あっては安定性を確保せんとすると矢板断面がきわめて
大きくなる難点があり、実際には上載荷重、地震などに
よる矢板天端の変位が大きい、C図のものにあっては設
計法が確立されておらず不明な点が多いという難点があ
り、d図のものにあっては中詰土砂のない状態では波浪
に対して弱いという難点を夫々有している。
In addition, prior to the construction of the sheet piles, it is necessary to perform temporary construction such as guides, and the sheet piles shown in Figure a require a long offshore construction period because they cannot be reclaimed until the tie rods and buttresses are completed. Without backfilling or buttresses after driving, there are disadvantages such as being vulnerable to waves, and in the case of the type shown in Figure b, the cross section of the sheet pile becomes extremely large if stability is to be ensured. The problem is that the displacement of the top of the sheet pile due to overburden loads, earthquakes, etc. is large, and the design method for the one shown in Fig. C has not been established and there are many unknown points. Each of these has the disadvantage of being vulnerable to waves in the absence of earth and sand.

「問題点を解決するための手段」、「作用」本発明は叙
上の事情に鑑みなされたもので、その要旨とするところ
は、海中構造物構築基礎材として既に確立されているジ
ャケットレグと水平ブレース等のメンバーの立体架構よ
りなる鋼製ジャケットの水側に面する水平ブレースの内
側に挟持用補助メンバーを並列付加したうえ当該上下並
行メンバーの間隙間に矢板を差し渡し装着したものを水
底地盤に設置固定し、当該矢板背側に土砂を埋立てする
として矢板施工時にはジャケットがサポート兼打ち込み
ガイドの仮設材となって簡易迅速施工をもたらし、又、
埋立後は該水側に面する水平ブレースが矢板に対しての
復起し材となると共に、前記水平ブレースと直交してい
る岸壁奥方に延びる水平ブレース及びこれに取合うジャ
ケットレグが矢板鉛直全長に渡る多段バンクアンカーと
して役する永久構造材となって、大水深での施工を可能
とすると共に矢板の経済断面化を可能とし、さらには矢
板についてのバックアンカー付加後工程を不要とした点
にある。
``Means for Solving Problems'' and ``Operations'' The present invention was made in view of the above circumstances, and its gist is that it is a jacket leg that has already been established as a foundation material for constructing underwater structures. A steel jacket consisting of a three-dimensional structure of members such as horizontal braces has auxiliary clamping members added in parallel to the inside of the horizontal brace facing the water side, and sheet piles are inserted and installed in the gaps between the upper and lower parallel members. When the sheet pile is installed and fixed, and earth and sand is reclaimed on the back side of the sheet pile, the jacket serves as a temporary support and driving guide when constructing the sheet pile, resulting in simple and quick construction.
After reclamation, the horizontal brace facing the water side serves as a restoring material for the sheet pile, and the horizontal brace extending to the back of the quay and the jacket leg that connects to the horizontal brace perpendicular to the horizontal brace serve as the entire vertical length of the sheet pile. It is a permanent structural material that serves as a multi-stage bank anchor over a long period of time, making it possible to construct at great depths of water, making it possible to make sheet piles more economical, and further eliminating the need for the post-process of adding back anchors to sheet piles. be.

「実施例」 以下、これを施工手順図に基づいて詳細に説明する。"Example" This will be explained in detail below based on construction procedure diagrams.

すなわち、第1図に示すように岸壁建設予定位置の海底
地盤13を必要に応じてしゅんせつし、軟弱土を砂工4
で置換してその表面を平らに仕上げる。
In other words, as shown in Figure 1, the seabed ground 13 at the planned location of the wharf construction site is dredged as necessary, and the soft soil is removed by sandwork 4.
to make the surface flat.

なお海底地盤が良質で護岸の背面を土砂で埋立てた際に
辷り破壊又は不同沈下を起す恐れがない場合は、上記の
しゅんせつ及び砂14による置換は不要である。
Note that if the seabed ground is of good quality and there is no risk of sliding failure or uneven settlement when the back of the seawall is filled with earth and sand, the above-mentioned dredging and replacement with sand 14 are not necessary.

一方、陸上では第2図に示す如く海中構造物構築基礎材
として既に確立されているジャケットレグ15aと水平
ブレース15b等のメンバーの櫓状立体架構よりなる1
1製ジヤケツト15に於いて、水側に面する各レベルの
水平ブレースの内側に矢板挟持用の補助メンバー16、
・・・を並列付加設すると共に当該並行メンバー15b
、 16の間隙上下間に矢板パネル17を差し渡し装着
する。
On the other hand, on land, as shown in Figure 2, a tower-shaped three-dimensional structure consisting of members such as jacket legs 15a and horizontal braces 15b, which have already been established as foundation materials for constructing underwater structures, is used.
In the jacket 15 made by No. 1, there are auxiliary members 16 for holding sheet piles inside the horizontal braces at each level facing the water side.
... is added in parallel, and the parallel member 15b
A sheet pile panel 17 is installed across the upper and lower gaps of , 16.

矢板パネル17の一端はジャケット15の下端付近にと
どめ、他端はジャケット15の上端付近または打ち込み
化分それより上方に突き出してお(。
One end of the sheet pile panel 17 remains near the bottom end of the jacket 15, and the other end protrudes near the top end of the jacket 15 or above it.

メンバー15b、 16は矢板パネル17に対して打ち
込みガイドとなると共に対土庄、対波圧についての復起
しとして役する。
The members 15b and 16 serve as driving guides for the sheet pile panel 17, and also serve as restoring against soil pressure and wave pressure.

メンバー15b、16と矢板17aとの取合は第3図〜
第5図に詳示される。
The connection between members 15b, 16 and sheet pile 17a is shown in Figure 3~
This is shown in detail in FIG.

すなわち、第3図に示す如く、 矢板17aとメンバー15b、 16とは溶接ビード1
8により仮止めされる。
That is, as shown in FIG.
It is temporarily fixed by 8.

尚、図中19は水側に面するジャケットレグ15の管軸
方向のほぼ全長に渡って打設される矢板並びにジャケッ
トレグ連結用の継手である。
In the figure, reference numeral 19 denotes a joint for connecting the sheet pile and the jacket leg, which is driven over almost the entire length in the tube axis direction of the jacket leg 15 facing the water side.

第4図は直線形の水平ブレース15bにU型の鋼矢板1
7aを用いた例を、又第5図は曲線形の水平ブレース1
5bに鋼管型の鋼矢板17aを用いた例を夫々示す。
Figure 4 shows a U-shaped steel sheet pile 1 on a straight horizontal brace 15b.
7a, and Figure 5 shows a curved horizontal brace 1.
5b shows an example using a steel pipe type steel sheet pile 17a.

第4図のU型鋼矢板を使用する場合は、矢板に働く土圧
などを分散させて復起しの水平ブレースに伝えるため、
金具20を矢板を挿入する前に水平ブレースに溶接又は
ボルトにて連結しておく。
When using the U-shaped steel sheet piles shown in Figure 4, in order to disperse the earth pressure acting on the sheet piles and transmit it to the horizontal braces for uprighting,
The metal fittings 20 are connected to the horizontal brace by welding or bolts before inserting the sheet piles.

なお金具20は水平ブレースに取付けた状態でその自由
端のエンドプレート20aとメンバー16との間に適当
なギャップを確保し、矢板の挿入及び打込みを容易にす
ると共に岸壁完成後には土庄など矢板に働く荷重を均等
に水平ブレースに伝達できるよう矢板のウェブとは密着
させる。
The fitting 20 secures an appropriate gap between the end plate 20a at the free end and the member 16 when attached to the horizontal brace, making it easy to insert and drive the sheet pile, and after the wharf is completed, it can be attached to the sheet pile such as a tonosho. It should be in close contact with the sheet pile web so that the applied load can be evenly transmitted to the horizontal brace.

第5図の場合は水側に面する水平ブレース15bが凹に
湾曲させられているが、これは、岸壁前面水深が大きい
とか埋立て出土の荷重が大きい場合など主働土圧が大き
くなって水平ブレースに極めて大きな断面が要求される
こととなるので、凹に湾曲して曲げモーメントを減少さ
せ、経済的な断面にできるようにしたものである。
In the case of Fig. 5, the horizontal brace 15b facing the water side is curved concavely, but this is due to the fact that the active earth pressure is large, such as when the water depth in front of the quay is large or the load from reclaimed excavation is large. Since the brace is required to have an extremely large cross section, it is curved concavely to reduce the bending moment and to make the cross section economical.

かかるジャケットの完成体を第6図に示す。The completed jacket is shown in FIG.

当該ジャケットに於いては、第7図に詳示する如く、 追加設の水平ブレース21の方向とジャケットレグ15
aに働く水平力の合力Rの作用方向とを合致させること
によってジャケットに働く水平力をジャケット全体に分
散させることが出来る。
In this jacket, as shown in detail in FIG. 7, the direction of the additional horizontal brace 21 and the jacket leg 15 are
By matching the direction of action of the resultant force R of the horizontal forces acting on a, the horizontal force acting on the jacket can be dispersed over the entire jacket.

図中Pは土圧を示す。P in the figure indicates earth pressure.

尚、1本発明にあっては叙上の如く矢板パネル17はジ
ャケット15によってサポートされるので、矢板の傾き
は岸壁に働く主働土圧が小さくなり、ジャケットを含め
た岸壁全体の建設費が最小になるように選定することが
できるが、鉛直に対して約30°以下の傾斜角であれば
、矢板打ち込み作業の−能率及び難易度は鉛直矢板の場
合と大差ない。
In addition, in the present invention, as described above, the sheet pile panels 17 are supported by the jacket 15, so the inclination of the sheet piles reduces the active earth pressure acting on the quay wall, and the construction cost of the entire quay wall including the jacket is minimized. However, if the angle of inclination is about 30° or less with respect to the vertical, the efficiency and difficulty of the sheet pile driving work are not much different from those for vertical sheet piles.

叙上の如く組立されたジャケット15は第8図に示す如
く、台船22に′Mi載し、曳船23で据え付は予定場
所へ曳航する。
The jacket 15 assembled as described above is loaded onto a barge 22 as shown in FIG. 8, and towed by a tugboat 23 to a planned installation location.

次いで、第9図に示す如く、海上クレーン24を用いて
鋼製ジャケット15を鉛直に吊り上げ、海底地113又
は置換した砂14上の所定位置に沈設する。
Next, as shown in FIG. 9, the steel jacket 15 is lifted vertically using a marine crane 24 and is deposited at a predetermined position on the seabed 113 or replaced sand 14.

図は置換砂14上に沈設した例を示す。The figure shows an example where it is deposited on replacement sand 14.

さらに、ジャケットのレグ15aを通して鋼管杭25を
、その下端が支持層26の所定位置に達するまで杭打機
27で打ち込む。
Further, a steel pipe pile 25 is driven through the leg 15a of the jacket with a pile driver 27 until its lower end reaches a predetermined position on the support layer 26.

第10図に示す如く、レグ15aの内側面と鋼管杭25
の外側面で構成される環状部分28にセメントモルタル
を注入し、レグ15aと鋼管杭25を一体化する。尚、
この際、矢板の所要長さがレグの長さより大きいときは
前述の仮止めビード18をガスカットなどにより除去し
た後、ハンマーを用いて矢板を所定の根入れ位置まで打
込む。
As shown in FIG. 10, the inner surface of the leg 15a and the steel pipe pile 25
Cement mortar is injected into the annular portion 28 consisting of the outer surface of the leg 15a and the steel pipe pile 25 to be integrated. still,
At this time, if the required length of the sheet pile is greater than the length of the leg, the temporary bead 18 described above is removed by gas cutting or the like, and then the sheet pile is driven into a predetermined insertion position using a hammer.

既述の第5図の場合の矢板継手部の処理を第11図に示
す。
FIG. 11 shows the treatment of the sheet pile joint in the case of FIG. 5 described above.

図示の如く、レグ15aの継手19及び矢板17aの継
手29の内部の土砂をウォータージェットなどを用いて
排除し、止水剤たとえばセメントモルタル30を注入す
る。
As shown in the figure, earth and sand inside the joint 19 of the leg 15a and the joint 29 of the sheet pile 17a are removed using a water jet or the like, and a water stop agent such as cement mortar 30 is injected.

第12図に示す如く、ジャケット15の背面を土砂31
で埋め立て、ジャケットの天端に、必要に応じて鉄筋コ
ンクリート32を施工する。
As shown in FIG. 12, the back of the jacket 15 is covered with dirt 31.
Reinforced concrete 32 will be constructed at the top of the jacket as necessary.

ジャケット最上段の大気中に露出する水平ブレース及び
土庄分配用金物と、鋼矢板とを溶接等で連結する。
The horizontal brace and tonosho distribution hardware exposed to the atmosphere at the top of the jacket are connected to the steel sheet pile by welding or the like.

尚、土庄水圧等によるジャケットの水平変位及び発生応
力を一定値以下に押えるために必要な場合、ジャケット
の埋立土側に含まれる水平ブレースに水側と同様な処理
をして矢板を取り付けると、既述の第13図a、dと同
様の効果が期し得る。
In addition, if it is necessary to suppress the horizontal displacement and generated stress of the jacket due to Tonosho water pressure, etc. to below a certain value, if the horizontal brace included on the reclaimed soil side of the jacket is treated in the same way as the water side and sheet piles are attached, Effects similar to those shown in FIGS. 13a and 13d can be expected.

以下、同様な手順で、ジャケットを既に据え付けたジャ
ケットのレグ外側面と、矢板1枚分の幅だけ間隔をあけ
て据付け、隣接するジャケットレグ間の矢板をレグに取
付けた継手にかみ合わせて挿入し、ハンマーで所定位置
に打ち込み、必要に応じてジャケットの上部に天端コン
クリートを打設するとの工程を繰り返す。
Following the same procedure, install the jacket on the outer surface of the already installed jacket leg with a gap of the width of one sheet pile, and then insert the sheet pile between adjacent jacket legs by engaging them with the joints attached to the legs. , hammer into place, and repeat the process of pouring crown concrete on top of the jacket as necessary.

しかして、鉛直全長に渡る多段バックアンカーでサポー
トされた復起しを有する極めて安定した大水深に対応し
得る岸壁が完成する。
As a result, an extremely stable quay wall capable of coping with large water depths is completed, which is supported by multi-stage back anchors spanning the entire vertical length.

「発明の効果」 叙上本発明岸壁が奏し得る諸効果を列挙すると次記の如
くである。
"Effects of the Invention" The various effects that can be achieved by the quay of the present invention are listed below.

以下にのべる特長をもつ工法を考案することを目的とす
る。
The purpose is to devise a construction method with the following features.

i)−20m〜−30mの大水深の海域でも施工できる
i) Can be constructed even in deep sea areas of -20m to -30m.

ii )復起しを海底面付近から、ジャケット天端の間
で複数段設置できるので、矢板に慟(断面力が軽減する
結果、矢板を経済的な断面にすることができる。
ii) Since the righting can be installed in multiple stages from near the seabed surface to between the tops of the jackets, the cross-sectional force of the sheet piles is reduced, allowing the sheet piles to have an economical cross-section.

iii )あらかじめ矢板相互及び矢板の継手とジャケ
ットレグに取り付けた継手をかみ合わせて、復起しに挿
入しておくので、施工時の波浪に対して抵抗力が大きい
iii) Since the sheet piles and the joints of the sheet piles and the joints attached to the jacket legs are engaged with each other in advance and inserted into the restoring, there is great resistance to waves during construction.

iv)ジャケットに復起しが取り付けられ、それをガイ
ドとして矢板が挿入されているので、従来の矢板式岸壁
のように、矢板打ち込みに先だって、ガイド及びガイド
支持杭などの仮設工をほどこす必要がない。
iv) Since a backing is attached to the jacket and the sheet pile is inserted using it as a guide, it is necessary to construct temporary works such as guides and guide support piles before driving the sheet pile, as with conventional sheet pile quays. There is no.

■)従来の矢板式岸壁の場合、自立式を除いてタイロッ
ド及び控え工を必要とするので、矢板打ち込み、矢板背
面の埋たて後、タイロッド設置、控え工の建設作業を伴
うのに対し、これらの作業が不要である。
■) In the case of conventional sheet pile type quays, except for the free-standing type, tie rods and support works are required, which involves driving the sheet piles, burying the back of the sheet piles, installing tie rods, and constructing support works. These operations are unnecessary.

vi)上記iii )〜V)にのべた理由から、本工法
によれば海上工事期間が短いので静穏な日数の少ない海
域でも岸壁を建設することが可能である。
vi) For the reasons mentioned in iii) to V) above, according to this construction method, the offshore construction period is short, so it is possible to construct a quay even in sea areas where there are few calm days.

vi)外力を受けるジャケット構造物の設計法は確立さ
れており、信頼度の高い岸壁を建設することができる。
vi) The design method for jacket structures that receive external forces has been established, and it is possible to construct highly reliable quay walls.

viii)ジャケットの復起しの間隙に挿入した矢板の
継手は、相互にジャケットの下端まで確実にかみ合って
いるので、ジャケット据え付は後ハンマーで矢板を所定
の位置まで打ち込んでも矢板継手のかみ合いがはずれる
ことは、まずありえない。
viii) The joints of the sheet piles inserted into the gap between the jacket restings are securely engaged with each other up to the bottom edge of the jacket, so even when installing the jacket, the sheet pile joints will not engage even if the sheet piles are driven into the specified position with a rear hammer. It is almost impossible for it to come off.

したがって、廃棄物処理場のように背面埋立物からの有
害物質の漏えいを確実に防止する必要がある場合にも適
用できる。
Therefore, it can also be applied to cases where it is necessary to reliably prevent the leakage of harmful substances from backfills, such as in waste treatment plants.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は岸壁施工地盤の整備説明図、第2図は本発明で
使用する鋼製ジャケットの予備加工説明図、第3図〜第
5図は第2図中矢視A−A拡大断面図、第6図は本発明
が使用する一例の鋼製ジャケットの立姿勢図、第7図は
第6図のものの応力処理説明図、第8図は本発明に於け
る曳航説明図。 第9図は同じく沈設説明図、第10図、第11図は継ぎ
部の一体接続説明図、第12図は同じく埋め立て説明図
、第13図a % dは従来の岸壁の説明図である。 1・・・矢板、 2a・・・土砂、 2b・・・埋立て
、 3・・・タイロッド、 4・・・控え壁、 5・・
・鋼管矢板、6・・・土砂、 7・・・斜杭、 8・・
・矢板、 9・・・矢板、10・・・矢板、 11・・
・タイロッド、 12・・・土砂、 13・・・海底地
盤、 14・・・砂、 15・・・鋼製ジャケット、1
5a・・・ジャケットレグ、 15b・・・水平ブレー
ス、16・・・補助メンバー、 17・・・矢板パネル
、 17a・・・矢板、 18・・・溶接ビード、 1
9・・・継手、 20・・・金具、 20a・・・エン
ドプレート、 21・・・水平ブレース、 22・・・
台船、 23・・・曳船、 24・・・海上クレーン、
 25・・・鋼管杭、 26・・・支持層、 27・・
・杭打機、28・・・環状部分、 29・・・継手、 
30・・・セメントモルタル、 31・・・土砂、 3
2・・・鉄筋コンクリート。 ズ?フΔδ IQ ンチ511 ブ←4v 力4 ??           1つq ズ吐&e カ遡
Fig. 1 is an explanatory diagram of maintenance of the quay construction ground, Fig. 2 is an explanatory diagram of preliminary processing of the steel jacket used in the present invention, Figs. 3 to 5 are enlarged cross-sectional views taken along arrow A-A in Fig. 2, FIG. 6 is a vertical view of an example of a steel jacket used in the present invention, FIG. 7 is an explanatory diagram of stress treatment of the steel jacket of FIG. 6, and FIG. 8 is an explanatory diagram of towing in the present invention. FIG. 9 is an explanatory diagram of sinking, FIG. 10 and FIG. 11 are explanatory diagrams of integral connection of joint parts, FIG. 12 is an explanatory diagram of reclamation, and FIGS. 13a to 13 are explanatory diagrams of a conventional quay. 1... Sheet pile, 2a... Earth and sand, 2b... Landfill, 3... Tie rod, 4... Buttress, 5...
・Steel pipe sheet pile, 6... Earth and sand, 7... Oblique pile, 8...
・Sheet pile, 9...Sheet pile, 10...Sheet pile, 11...
・Tie rod, 12... Earth and sand, 13... Seabed ground, 14... Sand, 15... Steel jacket, 1
5a... Jacket leg, 15b... Horizontal brace, 16... Auxiliary member, 17... Sheet pile panel, 17a... Sheet pile, 18... Weld bead, 1
9...Joint, 20...Metal fitting, 20a...End plate, 21...Horizontal brace, 22...
barge, 23...tugboat, 24...maritime crane,
25... Steel pipe pile, 26... Support layer, 27...
・Pile driver, 28... Annular part, 29... Joint,
30...Cement mortar, 31...Earth and sand, 3
2...Reinforced concrete. Z? F Δδ IQ 511 Bu ← 4v Force 4 ? ? 1 q Zutsu & e Ka retro

Claims (3)

【特許請求の範囲】[Claims] (1)ジャケットレグと水平ブレース等のメンバーの立
体架構よりなる鋼製ジャケットの水側に面する水平フレ
ーズの内側に挟持用補助メンバーを並列付加したうえ当
該上下並行メンバーの間隙間に矢板を差し渡し装着した
ものを水底地盤に設置固定し、当該矢板背側に土砂を埋
立てしてなることを特徴とする鋼製ジャケット岸壁。
(1) A supporting member for clamping is added in parallel to the inside of the horizontal phrase facing the water side of a steel jacket consisting of a three-dimensional structure of members such as jacket legs and horizontal braces, and sheet piles are inserted in the gap between the above and below parallel members. A steel jacket quay characterized by being installed and fixed on the underwater ground and filled with earth and sand on the back side of the sheet pile.
(2)鋼製ジャケットの水側に面する水平ブレースを凹
に湾曲に構成してなる特許請求の範囲第1項に記載の鋼
製ジャケット岸壁。
(2) The steel jacket quay according to claim 1, wherein the horizontal brace facing the water side of the steel jacket is curved concavely.
(3)鋼製ジャケットの埋立土側にも矢板取付処理を施
してなる特許請求の範囲第1項に記載の鋼製ジャケット
岸壁。
(3) The steel jacket quay according to claim 1, wherein the steel jacket is also subjected to sheet pile attachment treatment on the reclaimed soil side.
JP24703986A 1986-10-17 1986-10-17 Steel jacket quaywall Pending JPS63103112A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP24703986A JPS63103112A (en) 1986-10-17 1986-10-17 Steel jacket quaywall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP24703986A JPS63103112A (en) 1986-10-17 1986-10-17 Steel jacket quaywall

Publications (1)

Publication Number Publication Date
JPS63103112A true JPS63103112A (en) 1988-05-07

Family

ID=17157504

Family Applications (1)

Application Number Title Priority Date Filing Date
JP24703986A Pending JPS63103112A (en) 1986-10-17 1986-10-17 Steel jacket quaywall

Country Status (1)

Country Link
JP (1) JPS63103112A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2020076285A (en) * 2018-11-02 2020-05-21 日本製鉄株式会社 Quay wall structure and construction method for quay wall structure

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5213857A (en) * 1975-07-11 1977-02-02 Hitachi Ltd Edge cutter
JPS5526244A (en) * 1978-08-14 1980-02-25 Toray Industries Fishing net

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5213857A (en) * 1975-07-11 1977-02-02 Hitachi Ltd Edge cutter
JPS5526244A (en) * 1978-08-14 1980-02-25 Toray Industries Fishing net

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2020076285A (en) * 2018-11-02 2020-05-21 日本製鉄株式会社 Quay wall structure and construction method for quay wall structure

Similar Documents

Publication Publication Date Title
US4440527A (en) Marine structure
US20060193701A1 (en) Earth retaining system such as a sheet pile wall with integral soil anchors
KR102011321B1 (en) Construction method of foundation using rectangular pipe and its foundation
JP5390044B1 (en) Underwater earth retaining method
JP3423394B2 (en) Underwater frame structure
CN108570996B (en) It builds a dam under the conditions of shallow water mud cofferdam method
JPH11323872A (en) Remodeling method of sheet pile type quay
JPH06146305A (en) Underwater foundation and installation method thereof
JPS63103112A (en) Steel jacket quaywall
JP2726611B2 (en) How to set up an open caisson
JP3871937B2 (en) Construction method for underwater frame structures
EP1004707B1 (en) Process for deepening and/or reinforcing, consolidating or renovating a quay wall constructed along a water basin
JPH04228714A (en) Water area construction using member to be driven into water bottom ground
JPH0426499Y2 (en)
JPS62236922A (en) Method of reinforcing sheet pile-wall structure
JPH1161775A (en) Method for repair and improvement of harbor and river civil engineering structure
JP2022146138A (en) Steel earth retaining material, earth retaining wall using the same, and method for constructing earth retaining wall
JP2002047665A (en) Installation method for jacket structure
JPS5844802B2 (en) Ganpekino hokiyoukohou
JPS5844803B2 (en) Kouyaitaheki no Kochikukohou
KR101961655B1 (en) Quay wall and construction method using driven pile and box type pre-cast concrete structure
JPH10102458A (en) Water area structure using underwater ground driving member
JP3069822B2 (en) Installation method of intake water discharge pipe
Vanderloos et al. Design and Construction of RO-RO Wharf at Webb Dock East, Melbourne
JPH03295929A (en) Open caisson sinking construction method