JPS62252885A - Molten-metal vessel flow-in execution method - Google Patents

Molten-metal vessel flow-in execution method

Info

Publication number
JPS62252885A
JPS62252885A JP9627186A JP9627186A JPS62252885A JP S62252885 A JPS62252885 A JP S62252885A JP 9627186 A JP9627186 A JP 9627186A JP 9627186 A JP9627186 A JP 9627186A JP S62252885 A JPS62252885 A JP S62252885A
Authority
JP
Japan
Prior art keywords
pouring
molten metal
poured
metal container
gutter
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP9627186A
Other languages
Japanese (ja)
Other versions
JPH0718656B2 (en
Inventor
箱田 昌弘
野田 宣善
村田 義住
後藤 育蔵
高浦 錦蔵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Refractories Corp
Original Assignee
Kawasaki Refractories Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kawasaki Refractories Co Ltd filed Critical Kawasaki Refractories Co Ltd
Priority to JP61096271A priority Critical patent/JPH0718656B2/en
Publication of JPS62252885A publication Critical patent/JPS62252885A/en
Publication of JPH0718656B2 publication Critical patent/JPH0718656B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Furnace Housings, Linings, Walls, And Ceilings (AREA)
  • Blast Furnaces (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 産業上の利用分野 本発明は、高炉の鋳床樋等の溶融金属容器流し込み施工
方法に関する。
DETAILED DESCRIPTION OF THE INVENTION Field of the Invention The present invention relates to a method for pouring into a molten metal container such as a cast bed trough of a blast furnace.

従来の技術 近年、高炉の鋳床樋等の補修は、従来の耐火レンガ等の
内張り施工にかわって、不定形耐火物の流し込み施工に
なってきている。そのため、鋳床樋の側部にミキサー、
混線装置等を設置し、所要の不定形耐火材料を混線調製
し、鋳床樋に流し込む作業が多くなってきている。
BACKGROUND OF THE INVENTION In recent years, the repair of cast floor gutters and the like of blast furnaces has begun to be carried out by pouring monolithic refractories, instead of the conventional lining with firebrick or the like. Therefore, a mixer is installed on the side of the cast bed gutter.
The work of installing a cross-conductor, etc., cross-conducts the required monolithic refractory material, and pours it into the cast bed gutter is becoming more common.

発明が解決しようとする問題 しかし、小型や中型の高炉等にあっては、炉前の鋳床部
が狭く、ミキサーや混練装置の搬入や搬出が容易でなく
、またこれらの装置の容量や台数にも限度があって、流
し込み材料を短時間に多量連続状に鋳床樋に流し込むこ
とができず、はぼ0.25〜0゜5r+?毎混線調製し
て逐次流し込まねばならず、長時間かかっているもので
あった。そのため、高炉等の溶融金属を取扱う鋳床樋等
では、高熱による流し込み材料の硬化が早くて材料の流
動性がよくなく、打ち継ぎ層や亀裂、空洞等が発生して
気孔の多い施工体となり、残銑事故や樋寿命の低下の原
因となっているものであった。さらには、混練作業によ
る粉塵や流し込み材料による水蒸気、粉煙等が発生して
、作業環境がよくなく、長時間にわたる高熱作業の負荷
は作業者にとって厳しいものであった。
Problems to be Solved by the Invention However, in small and medium-sized blast furnaces, etc., the casting bed in front of the furnace is narrow, making it difficult to carry mixers and kneading devices in and out, and the capacity and number of these devices are limited. However, there are limits to pouring material into the gutter in a continuous manner in a large amount in a short period of time, and it is difficult to continuously pour a large amount of pouring material into the gutter. Each crosstalk had to be prepared and poured one after another, which took a long time. For this reason, in cast floor troughs and other facilities that handle molten metal in blast furnaces, etc., the poured material hardens quickly due to high heat, resulting in poor fluidity of the material, resulting in a construction with many pores and cracks, cracks, and cavities. This was the cause of pig iron residue accidents and reduced gutter life. Furthermore, dust from the kneading work, water vapor, powder smoke, etc. from the poured materials were generated, resulting in an unfavorable working environment, and the burden of long hours of high-temperature work was harsh on the workers.

問題点を解決するための手段 本発明は上記のような点に鑑みたもので、高炉の鋳床樋
等の溶融金属容器の補修現場とは別の場所で不定形耐火
性の流し込み材料を混線調製し、この混練m製した流し
込み材料を数トン位の大容量のバケットに装填して上記
溶融金属容器の補修現場へ搬送し、補修準備した溶融金
属容器に上記大容量のバケットに装填した流し込み材料
を熱硬化が生じないようにほぼ連続状態で流し込んで装
填して、流し込み材料をほぼ連続状態で短時間に多量流
し込め、流し込み材料の熱硬化を遅らせることができて
打ち継ぎ層や空洞等の発生を防止でき、施工体の残銑事
故の防止がはかれるとともに樋寿命を延しでき、さらに
長時間にわたる高熱作業の負荷を軽減できて作業環境の
改善等がはかれる溶融金属容器流し込み施工方法を提供
するにある。
Means for Solving the Problems The present invention was developed in view of the above-mentioned problems, and it is a method of mixing monolithic refractory pouring material at a location other than the repair site of a molten metal container such as a blast furnace casting bed gutter. The prepared and kneaded pouring material is loaded into a large-capacity bucket of approximately several tons and transported to the repair site of the molten metal container, and the molten metal container prepared for repair is poured into the large-capacity bucket. By pouring and loading the material in a nearly continuous state to prevent heat curing, a large amount of the poured material can be poured in a near continuous state in a short period of time, and the heat hardening of the poured material can be delayed, making it possible to create pouring layers, cavities, etc. We have developed a molten metal container pouring construction method that can prevent the occurrence of residual pig iron accidents on construction objects, extend the life of the gutter, reduce the burden of long-term high-temperature work, and improve the working environment. It is on offer.

実施例 以下、本発明を実施例にもとずい°ζ説明する。Example Hereinafter, the present invention will be explained based on examples.

第1図、第2図は本発明の一実施例で、高炉鋳床樋に実
施したものである。鋳床1は、第1図のように高炉2の
下方部に設けられて、第2図のようにレンガのような耐
火物で囲んti永久張りである外張耐火壁3の内側にア
ルミナ−炭化珪素−炭素系の不定形耐火性材料等を混練
調製した流し込み材料4を装填し、て内張耐火壁5を内
設した溶融金属容器である鋳床hM6を形成し、高炉2
から出銑される溶銑を貯積し、適宜にトピードカー7に
流出自在とし”ζいる。
FIGS. 1 and 2 show an embodiment of the present invention, which is applied to a blast furnace casting bed trough. The cast bed 1 is installed in the lower part of the blast furnace 2 as shown in FIG. A cast bed hM6, which is a molten metal container having a lining fireproof wall 5 therein, is loaded with a pouring material 4 prepared by kneading and preparing a silicon carbide-carbon based amorphous refractory material, etc.
The hot metal tapped from the torpedo car 7 is stored and can flow freely to the torpedo car 7 as needed.

この溶融金属容器である鋳床樋6の上部には、第1図の
ようにジブクレーン8、天井走行うレーン9を配設して
いて、外部からトラックのような搬送装置10で搬送さ
れる2〜5トン位の流し込み材料4を装填した大容量の
バケット11を吊設搬送自在として、第2図のように鋳
床樋6に流し込み材料4を順次はぼ連続的に流し込むよ
うにしている。上記流し込み材料4は、第1図のように
鋳床lとは別場所の鋳床lからやや離れた混練工場12
で混練調製している。その混練工場12には、図のよう
に1〜2Mといった従来の数倍の大容量のミキサー13
を複数台設置し、上記した不定形耐火性の粉末材料を大
容量のミキサー13で短時間で混線調製し、天井クレー
ン等の搬送機14を介して上記バケット11に順次装填
して搬送袋ff1F10を介して補修工程に合わせて鋳
床1部へ搬送し、鋳床樋6に流し込んで補修できるよう
にしているものである。また、上記した大容量のバケッ
ト11は、第2図のように外周部に脚部15を設けて鋳
床1の中枠固定部16に架設した中枠浮上り防止用押え
架台17等に設置自在としているとともに、上部に吊り
下げ部18を設けて吊設自在とし、さらに内部にはIM
送送中流し込み材料4が偏析したり、沈降したりして分
離するのを防止するための網板のような偏析分離防止板
19を中央部や側部の適宜の位置に内装しているもので
ある。20は、バケット排出弁で、21は排出口、22
は樋中枠である。
As shown in FIG. 1, a jib crane 8 and an overhead running lane 9 are installed above the cast bed gutter 6, which is the molten metal container. A large-capacity bucket 11 loaded with about 5 tons of pouring material 4 is suspended and conveyed freely, and the pouring material 4 is sequentially and almost continuously poured into the casting bed gutter 6 as shown in FIG. 2. The above-mentioned poured material 4 is poured into a mixing factory 12, which is located at a different location from the casting bed 1 and a little away from the casting bed 1, as shown in Fig. 1.
Kneaded and prepared. The kneading factory 12 has a mixer 13 with a capacity of 1 to 2M, which is several times larger than the conventional one, as shown in the figure.
A plurality of units are installed, and the above-mentioned amorphous refractory powder material is mixed in a short time with a large-capacity mixer 13, and is sequentially loaded into the above-mentioned bucket 11 via a conveyor 14 such as an overhead crane to form a conveyor bag ff1F10. The cast iron is conveyed to one part of the cast bed in accordance with the repair process, and poured into the cast floor gutter 6 for repair. In addition, the above-mentioned large-capacity bucket 11 is installed on a holding frame 17 for preventing floating of the middle frame, which is provided with legs 15 on the outer periphery and installed on the middle frame fixing part 16 of the cast bed 1, as shown in FIG. In addition, a hanging part 18 is provided on the upper part to allow the hanging part to be freely hung, and an IM is installed inside.
Segregation prevention plates 19, such as mesh plates, are installed at appropriate positions in the center and sides to prevent the poured material 4 from segregation, sedimentation, and separation during transport. It is. 20 is a bucket discharge valve, 21 is a discharge port, 22
is the middle frame.

作用 しかして、高炉2の鋳床樋6の内張耐火壁5を補修する
にあっては、工程表にしたがって損耗した内張耐火壁5
を解体して解体屑を排出し、第2図のように鋳床樋6の
上部の中枠固定部16に架設した中枠浮上り防止用押え
架台17に樋中枠22を配設して流し込みの準備をする
。一方、上記準備作業と併行して、第1図のように施工
現場と別の混練工場12で所定の耐火性材料を大型のミ
キサー13でそれぞれ混練して所定量の流し込み材料4
を調製し、所要の複数の大容量のバケット11にそれぞ
れ装填して、1−ラックの搬送装置10で作業計画に合
わせて鋳床1部へ搬入するものである。
When repairing the inner refractory wall 5 of the cast bed gutter 6 of the blast furnace 2, the worn inner refractory wall 5 should be repaired according to the process chart.
The gutter inner frame 22 is disassembled and the dismantled waste is discharged, and the gutter inner frame 22 is placed on the holding frame 17 for preventing floating of the inner frame installed on the inner frame fixing part 16 at the upper part of the cast floor gutter 6, as shown in FIG. Prepare for pouring. On the other hand, in parallel with the above preparatory work, as shown in FIG.
is prepared, loaded into a plurality of required large-capacity buckets 11, and transported to one part of the casting bed using a one-rack transport device 10 in accordance with the work plan.

このようにして、従来のように高熱の鋳床部で内張耐火
壁の解体や中枠設置等の作業を行う一方、流し込み材料
を別場所で併行して混練調製するため、従来のような鋳
床部で粉塵が発生ずるのを防止でき、施工現場の作業環
境をよくできるとともに、混練工)JX テ4! 特に
スペースに制限が少なくて所要のスペースを確保できる
ため、大型のミキサーを複数台設置できて、短時間に所
要の多量の流し込み材料の混絃調製が行えるものである
。そして、大容量のバケットに装填して、鋳床樋の準備
作業の工程に合わせて流し込み準備体勢を整えられて、
施工工事の短縮化がはかれるものである。
In this way, while work such as dismantling the inner fireproof wall and installing the inner frame is carried out in the high-temperature casting bed as in the past, the pouring material is mixed and prepared in a separate location at the same time. It prevents dust from being generated in the casting bed, improves the working environment at the construction site, and improves the working environment at the construction site. In particular, since there are few restrictions on space and the required space can be secured, a plurality of large mixers can be installed and a large amount of pouring material can be mixed in a short period of time. Then, it is loaded into a large-capacity bucket and ready for pouring according to the process of preparing the casting bed gutter.
This will help shorten the construction work.

なお、バケットには偏析分離防止板を配設しているため
、流し込み材料を装填して搬送しても、材料が偏析した
り、沈降したりして分離するのが防止でき、施工現場で
の混練調製と同様の品質を保持できるものである。
In addition, the bucket is equipped with a segregation prevention plate, so even if poured material is loaded and transported, it will prevent the material from segregating or settling and separating, making it easier to use at the construction site. It is possible to maintain the same quality as in kneading preparation.

そして、第2図のように流し込みの準備が終わった鋳床
樋6の流し込み部に天井クレーン9やジブクレーン8を
介して搬入待機したバケット11を搬送して設置し、バ
ケットI&l出弁20を開いて排出口21を開口すれば
、流し込み材料4は図のように樋中枠22でかこまれた
外張爾火璧3の内側に流入し、内張耐火壁5を形成して
いくものである。■のバケット11の流し込み材料4の
流入が終了すれば、同様にして搬入待機したバケット1
1を順次搬送して所要量装填し、所定の温度下で乾燥養
生して補修するものである。
Then, as shown in FIG. 2, the bucket 11 that is waiting to be carried in is transported and installed via the overhead crane 9 or jib crane 8 to the pouring part of the cast bed gutter 6 that has been prepared for pouring, and the bucket I&L outlet valve 20 is opened. When the discharge port 21 is opened, the pouring material 4 flows into the inside of the outer firewall 3 surrounded by the gutter frame 22 as shown in the figure, forming the inner fireproof wall 5. . Once the pouring material 4 has finished flowing into the bucket 11 of (2), the bucket 1 that was waiting to be carried in the same way
1 is sequentially transported, loaded in a required amount, and dried and cured at a predetermined temperature for repair.

このように、2〜5トンといった大容量のバケットを使
用して流し込み材料を流入するため、数回のバケットに
よる流し込みで、短時間に多量の材料を流入して装填で
きるとともにほぼ連fa状態で流入できて、流し込み材
料が熱硬化するのを遅らせ、流し込み材料を流動性よく
均−状に内部に装填できるものである。したがって、流
入した流し込み材料との間に打ち継ぎ層が生じたり、亀
裂や空洞等が発生ずるのを防止でき、気孔の少ない充填
密度の高い施工体を形成できるものである。
In this way, large capacity buckets of 2 to 5 tons are used to pour in the pouring material, so it is possible to pour in and load a large amount of material in a short time by pouring with the bucket several times, and it is almost continuous. It is possible to flow the pouring material, delay thermosetting of the pouring material, and uniformly charge the pouring material inside with good fluidity. Therefore, it is possible to prevent a pouring layer from forming between the pouring material and the generation of cracks, cavities, etc., and to form a construction body with a high packing density and few pores.

上記した施工方法の一例について、従来の施工のものと
比較してみると、次表の通りである。
An example of the construction method described above is compared with conventional construction methods as shown in the following table.

第1表は、本発明による施工と従来の施工についての施
工状況に関するものであり、第2表は、同上の110℃
、24時間乾燥後の施工体の比重と気孔率に関するもで
ある。
Table 1 shows the construction status of construction according to the present invention and conventional construction, and Table 2 shows the construction status of the construction according to the present invention and the conventional construction.
, concerning the specific gravity and porosity of the constructed body after drying for 24 hours.

本発明にあっては、第1表に示すように流し込み材料の
流し込み時間が実に従来の3分の1に短縮でき、中枠セ
ットから流し込み完了までも従来のほぼ2分の1に短縮
でき、鋳床樋の耐久性も25%も大第1表   8鉦口
l舎と(刺毛結果 第2表  bり看り…組直の比較 幅に延長できたものである。
In the present invention, as shown in Table 1, the time for pouring the pouring material can be reduced to one-third of the conventional method, and the time from setting the inner frame to completing the pouring can be reduced to approximately one-half of the conventional method. The durability of the cast floor gutter was also increased by 25% compared to Table 1, Table 2.

また、第2表のように施工体の気孔率も、5〜6%低減
でき、充填密度の向上がはかれたものである。
Furthermore, as shown in Table 2, the porosity of the constructed body was also reduced by 5 to 6%, and the filling density was improved.

上記実施例では、施工現場から離れて混練工場を設けた
が、隔壁等の粉塵防止壁を設は隣接して適宜のスペース
の場所に設置するようにしてもよく、また搬送装置とし
てはトラックに限らずに台車等で連結するようにするこ
ともでき、さらには本発明の流し込み対象としては、高
炉鋳床樋に限ることなく、連続鋳造設備のタンディシュ
や取鍋等についても同様に通用できるものである。
In the above embodiment, the kneading factory was set up away from the construction site, but a dust prevention wall such as a partition wall may be installed adjacently in an appropriate space. Furthermore, the pouring object of the present invention is not limited to blast furnace cast bed troughs, but can also be applied to tundishes, ladles, etc. of continuous casting equipment. It is.

発明の効果 以上のように本発明にあっては、高炉の鋳床樋等の溶融
全屈容器に流し込み材料を熱硬化が生じないようにほぼ
連続状態で短時間に多量流し込めて、流し込み時間の短
縮化がはかれるとともに、熱硬化を遅らせることができ
て材料の流動性を改善でき、打ち継ぎ層や亀裂、空洞等
が発生するのを防止でき、施工体の比重を高められて残
銑事故の防止や樋寿命の延長化がはかれるものである。
Effects of the Invention As described above, in the present invention, a large amount of material can be poured in a short period of time in an almost continuous state to prevent thermosetting by pouring the material into a molten fully bent container such as a cast bed gutter of a blast furnace, and the pouring time can be reduced. In addition to reducing heat hardening, it is possible to improve the fluidity of the material, prevent the occurrence of pouring layers, cracks, cavities, etc., and increase the specific gravity of the construction body, reducing the risk of residual iron accidents. It is possible to prevent this and extend the life of the gutter.

また、施工現場以外で流し込み材料を混練調製できるた
め、ミキサーの容量や台数を高められ、流し込み施工現
場での粉塵の発生の防止がはかれ゛C施工現場の作業環
境の改善がはかれるとともに、施工現場の準備作業に併
行して材料の混線調製を迅速に行え、また高熱発生の場
所での作業時間の短縮化がはかれて作業者の高熱作業の
負荷の軽減ができるととも高炉等の設備の生産性の向上
がはかれるなど優れた効果を奏するものである。
In addition, since pouring materials can be mixed and prepared outside of the construction site, the capacity and number of mixers can be increased, and the generation of dust at the pouring construction site can be prevented. It is possible to quickly mix and prepare materials in parallel with on-site preparation work, reduce work time in areas where high heat is generated, and reduce the burden of high-heat work on workers. It has excellent effects such as improved productivity.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明の一実施例の概略説明用図、第2図は同
上の流し込み状態の側断面図である。 1・・・鋳床、2・・・高炉、4・・・流し込み材料、
10・・・1般送装置、11・・・バケット、19・・
・偏析分離防止板。 出願人     川崎炉材株式会社 代理人 弁理士  森 本 邦 章 ’JS  +  7: :: 2 :、1
FIG. 1 is a schematic explanatory diagram of one embodiment of the present invention, and FIG. 2 is a side sectional view of the same in the pouring state. 1... Casthouse, 2... Blast furnace, 4... Pouring material,
10...1 general feeder, 11...bucket, 19...
- Segregation prevention plate. Applicant Kawasaki Rozai Co., Ltd. Agent Patent Attorney Kuniaki Morimoto'JS + 7: :: 2:, 1

Claims (2)

【特許請求の範囲】[Claims] (1)高炉の鋳床樋等の溶融金属容器の補修現場とは別
の場所で不定形耐火性の流し込み材料を混線調製し、こ
の混練調製した流し込み材料を数トン位の大容量のバケ
ットに装填して上記溶融金属容器の補修現場へ搬送し、
補修準備した溶融金属容器に上記大容量のバケットに装
填した流し込み材料を熱硬化が生じないようにほぼ連続
状態で流し込んで装填することを特徴とする溶融金属容
器流し込み施工方法。
(1) Amorphous refractory pouring material is mixed and mixed at a location other than the repair site for molten metal containers such as blast furnace casthouse gutters, and the mixed and prepared pouring material is poured into a large-capacity bucket of several tons. Loaded and transported to the repair site of the molten metal container,
A molten metal container pouring construction method characterized in that the pouring material loaded in the large-capacity bucket is poured into the molten metal container prepared for repair in a substantially continuous state so as not to cause thermal hardening.
(2)大容量のバケットが、流し込み材料の搬送中に偏
析したり、沈降したりして分離するのを防止するために
綱板等の材料分離防止板を備えたものである特許請求の
範囲第1項記載の溶融金属容器流し込み施工方法。
(2) The scope of the claim is that the large-capacity bucket is equipped with a material separation prevention plate such as a steel plate in order to prevent the poured material from separating due to segregation or sedimentation during transportation. The molten metal container pouring construction method according to item 1.
JP61096271A 1986-04-25 1986-04-25 Molten metal container pouring construction method Expired - Lifetime JPH0718656B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP61096271A JPH0718656B2 (en) 1986-04-25 1986-04-25 Molten metal container pouring construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP61096271A JPH0718656B2 (en) 1986-04-25 1986-04-25 Molten metal container pouring construction method

Publications (2)

Publication Number Publication Date
JPS62252885A true JPS62252885A (en) 1987-11-04
JPH0718656B2 JPH0718656B2 (en) 1995-03-06

Family

ID=14160483

Family Applications (1)

Application Number Title Priority Date Filing Date
JP61096271A Expired - Lifetime JPH0718656B2 (en) 1986-04-25 1986-04-25 Molten metal container pouring construction method

Country Status (1)

Country Link
JP (1) JPH0718656B2 (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5573460A (en) * 1978-11-27 1980-06-03 Nippon Kokan Kk <Nkk> Applying method of ladle lining
JPS5761152A (en) * 1980-09-30 1982-04-13 Matsushita Electric Works Ltd Outer wall material for horizontal application and connecting construction
JPS60161095U (en) * 1984-04-04 1985-10-25 播磨耐火煉瓦株式会社 Storage tank that prevents particle size segregation
JPS60171892U (en) * 1984-04-24 1985-11-14 播磨耐火煉瓦株式会社 Hopper that prevents particle size segregation

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5573460A (en) * 1978-11-27 1980-06-03 Nippon Kokan Kk <Nkk> Applying method of ladle lining
JPS5761152A (en) * 1980-09-30 1982-04-13 Matsushita Electric Works Ltd Outer wall material for horizontal application and connecting construction
JPS60161095U (en) * 1984-04-04 1985-10-25 播磨耐火煉瓦株式会社 Storage tank that prevents particle size segregation
JPS60171892U (en) * 1984-04-24 1985-11-14 播磨耐火煉瓦株式会社 Hopper that prevents particle size segregation

Also Published As

Publication number Publication date
JPH0718656B2 (en) 1995-03-06

Similar Documents

Publication Publication Date Title
JPH0592254A (en) Method for production and repair of container for molten metal
CN107570660B (en) Release agent and preparation method thereof
US3897256A (en) Refractory lining mixture for hot metallurgical vessels
JPS62252885A (en) Molten-metal vessel flow-in execution method
CN110451999A (en) A kind of aluminum-spinel refractory casting material and preparation method thereof
CN107096913B (en) Hot-metal bottle dry slag cut off device and preparation method
US3259672A (en) Method of forming and maintaining refractory bottoms of open hearth furnaces for the manufacture of steel
CN101637941B (en) Integral casting technology of hot metal ladle and moulding bed device
US4468780A (en) Method of lining a steel-making furnace
JPH0631435A (en) Ladle
CA2190701C (en) Method of casting castable refractories of vessel for molten metal
CN104014777A (en) Special casting lining ladle for silicon iron alloy and lining castable
US1058158A (en) Treatment of slag.
JP7115434B2 (en) Melting method of cold iron source in hot metal transport vessel
JPS6028959Y2 (en) Pouring refractory material supply device
JPH09174230A (en) Method for lining bed part of ladle
JP3670061B2 (en) Ginger and its forming method
US806621A (en) Copper-refining furnace.
JP2695038B2 (en) Method for pouring molten metal container
JPH02166207A (en) Vessel for molten metal of iron tapping trough and the like
RU2179908C1 (en) Method for protecting ladle car from growing over at melting irons with increased content of titanomagnetites
CN110449568A (en) A kind of compound packet bottom construction technology of ladle
JPS5926979A (en) Basic indefinite form refractories for molten metal vessel
SU1310429A1 (en) Device for discharging conversion pig iron
JP3022822U (en) Ladle for casting