JPS61196072A - Disassembling of iron tower - Google Patents
Disassembling of iron towerInfo
- Publication number
- JPS61196072A JPS61196072A JP3459885A JP3459885A JPS61196072A JP S61196072 A JPS61196072 A JP S61196072A JP 3459885 A JP3459885 A JP 3459885A JP 3459885 A JP3459885 A JP 3459885A JP S61196072 A JPS61196072 A JP S61196072A
- Authority
- JP
- Japan
- Prior art keywords
- tower
- steel
- dismantling
- gantry
- inner tower
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 title 2
- 229910052742 iron Inorganic materials 0.000 title 1
- 229910000831 Steel Inorganic materials 0.000 claims description 23
- 239000010959 steel Substances 0.000 claims description 23
- 238000000034 method Methods 0.000 claims description 6
- 230000005540 biological transmission Effects 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 description 2
- 238000009434 installation Methods 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
Landscapes
- Working Measures On Existing Buildindgs (AREA)
Abstract
(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.
Description
【発明の詳細な説明】
イ 発明の目的
■ 産業上の利用分野
この発明は煙突の鋼製外塔、送電鉄塔、電波塔等の鉄塔
の解体方法に関するものである。DETAILED DESCRIPTION OF THE INVENTION A. Purpose of the Invention ■ Industrial Application Field This invention relates to a method for dismantling steel towers such as chimney outer steel towers, power transmission towers, and radio towers.
■ 従来の技術
従来は鉄塔の最上部付近に据えつけた自己昇降式のクレ
ーンによるか、または第4図に示すように、煙突の煙道
等の内塔が鋼製(鉄骨造)の外塔により支えられている
形式の場合には同図のように、内塔1をリフト#fif
5により下降させながらその下端から順に切断・撤去す
るとともに、内塔の上部に設置したクレーン12勿よび
作業床13により、外塔2すなわち鉄塔をその上端から
順に切断・撤去するものであった(特開昭53−138
340)。■ Conventional technology Conventionally, a self-elevating crane installed near the top of a steel tower was used, or as shown in Figure 4, an outer tower where the inner tower for the flue of a chimney, etc. was made of steel (steel structure). In the case of a type supported by
5, the outer tower 2, that is, the steel tower, was cut and removed sequentially from the lower end while being lowered by the crane 12 installed at the top of the inner tower, and the working floor 13. Japanese Patent Publication No. 53-138
340).
■ 発明が解決しようとする悶厘点
従来の技術では、鉄塔を上方から解体するので、高所で
の作業となるので、墜落や落下の危険があった。■ Disadvantages that the invention aims to solve In the conventional technology, steel towers are dismantled from above, which means work is done at high places, and there is a risk of falling or falling.
口 発明の構成
■ nH点を解決するための手段
′!i1図に示すように鉄塔の周囲に構築した構台4b
に載置されたリア目■5により鉄塔を下降させながら、
鉄塔をその下端より順に切断、撤去する。口 Structure of the invention■ Means for solving the nH point'! The gantry 4b built around the steel tower as shown in Figure i1
While lowering the steel tower with the rear eye ■5 placed on the
The steel towers will be cut and removed starting from the bottom end.
また第2図に示すように、鋼製外塔2の内部に煙道等の
内塔1を立設している場合は、外場の横架材または内塔
用構台4aの上に載置したリフ)1m15により下降さ
せながら、その下端より順に切断、撤去した後、前記工
程を行う。In addition, as shown in Fig. 2, when the inner tower 1 such as a flue is installed inside the steel outer tower 2, it is placed on the horizontal frame member in the outside field or on the pedestal 4a for the inner tower. After lowering the rift by 1 m 15 and sequentially cutting and removing it from the lower end, the above process is carried out.
■ 作用
鉄塔の解体はすべて地上付近すなわち鉄塔の下端で行わ
れる。■ All demolition of steel towers is carried out near ground level, that is, at the bottom end of the tower.
■ 実施例
m1図は煙突の鋼製外塔の解体を示す実施例であって、
まず外場の足元周囲に外塔用構台4bを設け、後記する
内塔の解体後、リフト装置5によりかんざし梁6を介し
て外場を昇降可能に支持し、その下方の外項構成部材を
切断・撤去した後、残りの外場を所定位置まで下降させ
、以後これを繰り返して解体する。なお、外場の転倒防
止のため、外項構成部材の節点において外方に突出する
片持梁11を取付け、その先端のローラー3を、構台4
bの垂直ガイドレール10に当接、転勤させる。この装
置は、送電鉄塔の嵩上げ工事(特開昭59−96390
)に使用するものをそのまま転用できる。■ Example m1 Figure is an example showing the dismantling of a steel outer tower of a chimney,
First, an outer tower gantry 4b is installed around the foot of the outer tower, and after dismantling the inner tower (to be described later), the outer tower is supported by a lift device 5 so as to be able to be raised and lowered via a crown beam 6, and the outer tower components below it are supported. After cutting and removing, the remaining outer area is lowered to the designated position, and this process is repeated to dismantle it. In order to prevent the outside field from falling over, a cantilever beam 11 that projects outward is installed at the node of the outside structure member, and the roller 3 at the tip is connected to the gantry 4.
It comes into contact with the vertical guide rail 10 of b and is transferred. This device is used for raising the height of power transmission towers (Japanese Patent Laid-Open No. 59-96390).
) can be used as is.
第2図は前記外場の解体に先だって行われる内塔の解体
作業を示す実施例であって、まず、鋼製の外場の各段の
内塔支持用の横架材(通常はステージとなっている。)
と内塔1との取付は部分が固定である場合には、その固
定部分を。Figure 2 is an example showing the dismantling work of the inner tower that is carried out prior to the demolition of the outer building. )
When attaching the inner tower 1 to the inner tower 1, if the part is fixed, use that fixed part.
ガス切断器等により一部切断・撤去し、その部分にロー
ラー、スライディング・パット等の摺動可能部材3を取
付ける。そして、内塔の足元付近に構台4aを構築し、
その上に載置したリフト装置5により、かんざし梁6を
介して内塔を昇降可能に吊る。この実施例でのリフト装
置はti2図に示すように構台4aの上紀立設したジヤ
ツキ5龜の上のクロスヘッド5cに上部ナツト5dによ
りロッド5bを係止し、さらにその下端に下部ナフト5
eによりかんざし梁6を係止したものであって、ロフト
5bを、その中間にねじ込まれたナツト5fにより固定
クロスへラド5c”に係止しまたはゆるめることによっ
て、ジヤツキのスFロークを盛り替えながらかんざし梁
を昇降させるものである(実公昭59−11557)。A portion is cut and removed using a gas cutter or the like, and a slidable member 3 such as a roller or a sliding pad is attached to that portion. Then, construct a gantry 4a near the foot of the inner tower,
The inner tower is lifted up and down via a hairpin beam 6 by a lift device 5 placed thereon. As shown in Figure ti2, the lift device in this embodiment has a rod 5b secured to a crosshead 5c on a jack 5 erected on the upper side of a gantry 4a by an upper nut 5d, and a lower napft 5 at its lower end.
By locking the loft 5b to the fixed cross and the rod 5c'' with the nut 5f screwed in the middle, or loosening the loft 5b, the stroke F of the jack can be changed. This is to raise and lower the hairpin beam (Utility Model Publication No. 59-11557).
かんざし梁の内塔への取付けは、内塔1の下部の適宜の
位置にかんざし梁の断面よりやや大きめの孔1aをあけ
、これにかんざし梁を貫通させて行う、なお、局部変形
を防ぐため、孔の直上の部分に補強リブ(ブラケット)
7を溶接する。To attach the hairpin beam to the inner tower, drill a hole 1a slightly larger than the cross section of the hairpin beam at an appropriate position at the bottom of the inner tower 1, and pass the hairpin beam through this hole.Please note that this is to prevent local deformation. , reinforcing rib (bracket) directly above the hole
Weld 7.
リフトH!により下降させた内塔は、−亘地上の基盤8
に預け、かんざし梁を抜き取り、上方に新たに設けた孔
1a” (図示せず)に盛り替え、再びリフ)It置に
より吊り、その下側の内塔の部分を切断・撤去する。こ
れを繰り返し、内塔・をすべで解体し、リフト装置や内
塔用構台も撤去する。Lift H! The inner tower, which was lowered by
Then, remove the ornamental beam, replace it in the hole 1a'' (not shown) newly made above, hang it again using a rift, and cut and remove the lower part of the inner tower. The inner tower was repeatedly dismantled in its entirety, and the lift equipment and inner tower pedestal were also removed.
また、内塔の解体の際は、必らずしも構台4aを要さず
、例えば特公昭5El−33550(ただし、構築方法
に関するものである。)に示すように外場(この場合は
鉄M−’7クリート製である。)の横架材(ステージ)
を使用しても差支えない。In addition, when dismantling the inner tower, the gantry 4a is not necessarily required, and the outer tower (in this case, the steel M-'7 cleat.) horizontal member (stage)
There is no problem in using .
ハ 発明の効果
実質的上解体けもとより、解体に先だつ機械や装置の設
置作業等すべて鉄塔の下部で行なわれるので、墜落や落
下事故による災害の恐れが少ない、また、周辺の建築や
機械設備等への養生を軽微にすることができる。C. Effects of the invention Since virtually all the installation work of machinery and equipment prior to demolition is carried out at the bottom of the steel tower, there is less risk of disasters due to falls or falling accidents, and surrounding buildings and mechanical equipment etc. It is possible to reduce the amount of care required.
鉄塔が内塔を有する場合、外場の解体に先だってこれを
ガイドとして、単に(同時には外場を解体せず)内塔を
吊り降ろしながら下方から解体すれば、やはり同様の効
果を得ることはい −うまでもない。If the steel tower has an inner tower, it is possible to obtain the same effect by simply lowering the inner tower and dismantling it from below using this as a guide (without dismantling the outer tower at the same time) before demolishing the outer tower. -That's no good.
′Ii1図および第2図は本発明の実施例を示す、縦断
面図であって、第1図は外塔の解体、tjE2図はこれ
に先だって行われる内項の解体の伏態をそれぞれ示す、
第3図は、第2図のリフト装置の部分の詳細図である。
第4図は従来の解体方法の一例を示す縦断面図である。Figures 1 and 2 are vertical sectional views showing an embodiment of the present invention, with Figure 1 showing the dismantling of the outer tower, and Figure 2 showing the dismantling of the inner tower that will be carried out prior to this. ,
FIG. 3 is a detailed view of the lift device portion of FIG. 2; FIG. 4 is a longitudinal sectional view showing an example of a conventional disassembly method.
Claims (3)
に載置されたリフト装置(5)により鉄塔を下降させな
がら、鉄塔をその下端より順に切断、撤去することを特
徴とする鉄塔の解体方法。(1) A gantry (4b) is constructed around the steel tower (2), and while the tower is lowered by a lift device (5) mounted on this, the steel tower is sequentially cut and removed from its lower end. How to dismantle a steel tower.
を、外塔の横架材または内塔用構台(4a)に載置した
リフト装置(5)により下降させながら、その下端より
順に切断、撤去した後、外塔の周囲に構築した構台(4
b)に載置されたリフト装置(5)により外塔を下降さ
せながら、外塔をその下端より順に切断、撤去すること
を特徴とする鋼製外塔を有する塔体の解体方法。(2) Inner tower (1) installed inside the steel outer tower (2)
are lowered by the lift device (5) placed on the horizontal members of the outer tower or the gantry (4a) for the inner tower, and cut and removed in order from the lower end, and then the gantry (4) built around the outer tower
b) A method for dismantling a tower body having a steel outer tower, characterized in that the outer tower is sequentially cut and removed from its lower end while lowering the outer tower using a lift device (5) mounted on the outer tower.
記載の鋼製外塔を有する塔体の解体方法。(3) The method for dismantling a tower body having a steel outer tower according to claim 2, wherein the inner tower is a steel flue.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP3459885A JPS61196072A (en) | 1985-02-25 | 1985-02-25 | Disassembling of iron tower |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP3459885A JPS61196072A (en) | 1985-02-25 | 1985-02-25 | Disassembling of iron tower |
Publications (1)
Publication Number | Publication Date |
---|---|
JPS61196072A true JPS61196072A (en) | 1986-08-30 |
Family
ID=12418778
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP3459885A Pending JPS61196072A (en) | 1985-02-25 | 1985-02-25 | Disassembling of iron tower |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS61196072A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2010001649A (en) * | 2008-06-20 | 2010-01-07 | Tomoe Corp | Demolition method of steel pipe single pole steel tower for power transmission |
JP2010235265A (en) * | 2009-03-31 | 2010-10-21 | Tlc:Kk | Derrick for assembling/disassembling iron tower |
JP2017533378A (en) * | 2014-10-07 | 2017-11-09 | リフトラ・アイピイ・エイピイエス | Spindle fixing device |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5369437A (en) * | 1976-12-03 | 1978-06-20 | Kawasaki Steel Corp | Method of dismantling steel tower |
JPS53136340A (en) * | 1977-04-30 | 1978-11-28 | Kawasaki Steel Corp | Method for dismantling steel-tower-supported long cylindrical structure |
-
1985
- 1985-02-25 JP JP3459885A patent/JPS61196072A/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5369437A (en) * | 1976-12-03 | 1978-06-20 | Kawasaki Steel Corp | Method of dismantling steel tower |
JPS53136340A (en) * | 1977-04-30 | 1978-11-28 | Kawasaki Steel Corp | Method for dismantling steel-tower-supported long cylindrical structure |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2010001649A (en) * | 2008-06-20 | 2010-01-07 | Tomoe Corp | Demolition method of steel pipe single pole steel tower for power transmission |
JP2010235265A (en) * | 2009-03-31 | 2010-10-21 | Tlc:Kk | Derrick for assembling/disassembling iron tower |
JP2017533378A (en) * | 2014-10-07 | 2017-11-09 | リフトラ・アイピイ・エイピイエス | Spindle fixing device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106948603A (en) | Wall plate member switching mechanism and its method for turning | |
JPS61196072A (en) | Disassembling of iron tower | |
CN111155754B (en) | Automatic elevator shaft jacking platform and using method thereof | |
US4238115A (en) | Jacking device | |
CN1314534A (en) | Integrated raising method for self-supporting house roof and its equipment | |
CN211776076U (en) | Steel construction retractable cat ladder of going to people for elevator well | |
JPH01190883A (en) | Lift up or down method | |
CN210500860U (en) | Secondary structure constructional column top bar planting assistor | |
JP3230104B2 (en) | Tower crane | |
JPS5858509B2 (en) | Construction method for rooftop towers in high-rise buildings | |
JPH0431412Y2 (en) | ||
CN219952606U (en) | Safety platform for beam slab prefabricated field | |
JP2546729Y2 (en) | Jig for tower crane climbing | |
JP2871468B2 (en) | How to build a building | |
JP3000061B2 (en) | Crane dismantling method | |
CN214195456U (en) | Construction foot rest for highway bridge | |
CN210944621U (en) | Jacking safety protection device of tower crane | |
JPH06101348A (en) | Method for constructing tower | |
CN214605199U (en) | Auxiliary device for punching high beam plate | |
CN207314779U (en) | A kind of temporary supporting platform of high-rise building equipment | |
JPS5846993B2 (en) | Method of constructing a steel tower using a lifting crane | |
CN206957180U (en) | A kind of movable operating platform for inner climbing crane tower installation, dismounting | |
JPH0130473Y2 (en) | ||
CN2476611Y (en) | Self-supporting roof lift-up device | |
JPS6294659A (en) | Chimney disassembling construction method |